Findings Of Fact Respondent HRS published ITB 590:2306 for existing rental space in the central area of Brooksville, Florida. The bid solicitation specified a bid opening time and date of 2:00 p.m. July 17, 1991. Petitioner and Intervenor timely submitted sealed bids. They were the only two bidders. Neither they nor anyone else timely filed any protest of the bid specifications, and therefore the specifications are not subject to attack in this proceeding. Petitioner received a notice of intent to award the bid for lease 590:2306 to Intervenor by letter from Respondent dated August 27, 1991 and timely filed its notice of intent to protest and formal bid protest. Petitioner accordingly has standing to bring this proceeding. Intervenor is the intended awardee and as such has standing to intervene. Petitioner submitted the property located at 7348 Broad Street, Brooksville, Florida, and showed in his bid submittal form that his proposed property contained 22,500 net square feet, with future expansion of 2,100 square feet available. When Petitioner submitted his bid, it included a floor plan, site plan, and a PUR 7068 form. A PUR 7068 form is a "Public Entity Crime Certification Statement," a sworn statement under Section 287.133(a) F.S. The ITB included two separate requirements for bidders to establish that they have control over the property that they submit to HRS. HRS' purposes in requiring bidders to demonstrate control are to prevent bids based on total speculation, to establish a reasonable expectation that the bidder can meet his obligations if awarded the bid, and to establish a reasonable expectation that the property can be occupied on time. Item 1 on page 3 provides as follows: Control of property - This pertains to both the structure(s) and proposed parking areas. To submit a responsive bid, a prospective lessor must meet one of the following qualifications: a.) Be the owner of record of the facility and parking areas (submit copy of deed). b.) Be the lessee of space being proposed and present with bid, a copy of lease with documen- tation of authorization to sublease the facility and parking areas through the base lease term and all renewal option periods. c.) Submit documentation of an option to purchase the facility and/or parking areas. d.) Submit documentation of an option to lease the facility with authorization to in turn, sublease. Any lease must encompass the entire time period of the basic lease and any renewal option periods as required the state. e.) Submit form PUR. 7068 Sworn Statement of Public Entity Crimes (Attachment H). Page 12 provides, in part, as follows: In order for a bid proposal to be accepted the items 1 through 6 must be included in the bid proposal. Items 7 through 11 must be included, if applicable. [Items 11 and 13 state:] 11. Documentation showing bidder as controller of property. 13. Public Enemy [sic] Crime Certification Statement A pre-bid conference attended by Petitioner made clear that evidence of control and the PUR 7068 form were two different items. Petitioner testified that he attached the PUR 7068 form as his sole basis for evidencing control of the building and parking spaces he submitted for lease, and acknowledged that, in fact, the form did not provide any information with regard to his control of the buildings or parking spaces offered for lease. Petitioner's assertion that his name on some of his site plans, etc. constitutes evidence of control is not persuasive. Such assertion is not in line with the ITB requirements or even common sense. Petitioner Proctor owned the buildings he offered HRS in his bid submittal. Petitioner offered multiple buildings separated by parking areas and driveways. The property offered by Petitioner was to have built an awning- covered walkway between buildings but the walkway would have to be placed through the driveway area of the property. The expansion area for Petitioner's property designated in its bid submittal was composed of approximately 10 gated warehouse units which would be converted to office space. Petitioner had leased a portion of the same premises to HRS for 15 years, and HRS was still leasing that portion at the time of the bid opening. At the time of the bid opening, another portion of the property Petitioner proposed to be leased to HRS was also already rented to other tenants, including a lease to the Florida Department of Labor which was not scheduled to expire until December 31, 1991, one day prior to HRS' proposed first day of occupancy under the ITB. The space leased to the Department of Labor would require some renovation for HRS' use, at least to connect it on the interior with the rest of the building. The remainder of the second, adjacent, building to be rented under Petitioner's bid would require more extensive renovation to create office spaces to meet HRS' needs. In addition to the Department of Labor, Petitioner was also renting space in the second building to a beauty salon, a book store, an office supply store, a clothing store, and a barber at the time of bid submittal and opening and at the time of the formal hearing. These latter tenants were on month-to-month leases. In order to ensure that there would be time for necessary renovations before January 1, 1992 and further to ensure that the property would be available for occupancy on January 1, 1992, the ITB required in the following unequivocal language that all bidders file tenant acknowledgments of the bid/proposed lease with their bid submittal: Existing Tenants: If the offered space or any portion thereof (including parking areas) is at present occupied or will be covered by an active lease(s) at the stated availability date, written documentation by the tenant indicating acknowledgment of the bid and ability to vacate premises by the proposed date must be included with the bid submittal. [Emphasis added] Petitioner submitted no tenant acknowledgments from any of his tenants with his bid to HRS. Even though Petitioner failed to submit evidence of control in the form of a deed and further failed to submit the required acknowledgments from tenants occupying the premises on the bid date, HRS did not immediately disqualify Petitioner's bid as nonresponsive. Instead, HRS evaluated Petitioner's bid simultaneously with Intervenor TCC's bid. HRS relied on old leases in its files and actual knowledge that monthly rent was paid to Petitioner for its own currently leased space, and HRS ignored the absence of tenant acknowledgments with Petitioner's bid. HRS followed this course of action despite the requirement of the ITB on page 7, item 1 under EVALUATION OF BIDS which unequivocally provides: Bids received are first evaluated to determine technical responsiveness. This includes submittal on bid submittal forms, inclusion of required information, data, attachments, signatures and notarization, etc. Non responsive [sic] bids will be withdrawn from further consideration. The portion of the ITB designated, Documents Required To Be Submitted With Bid Submittal For Existing Buildings on page 12, item 4. required bidders to submit "Scale Floor Plans showing present configurations with dimensions." Page 3 of 22, Item 9.(b) further required that, as a part of the bid submittal, bidders were to provide "A scaled (1/16" or 1/8" or 1/4" = 1'0") floor plan showing present configuration with measurements." Contrary to the ITB requirement, Petitioner submitted a floor plan scaled at 1/20" = 1', which also failed to reflect the present configurations with all measurements. Petitioner's scaled floor plan submitted with his bid was prepared prior to the present addition to one building and contained a hand- drawn configuration without accurate measurements for the northwest corner of one building. The term of the lease as shown on the ITB and Bid Submittal Form was 9 and one-half years with an option to renew for 2-5 year renewal periods. At the time of the bid opening on July 17, 1991, the bid submitted by Petitioner failed to have any proposed rental rates shown for "Renewal Options: Option II years 1 through 5." HRS permitted Petitioner to correct or supplement its bid after the bid opening (same date and place) to cover this material omission. Page 6, item 4 of the ITB provided for the property owner or other bidding entity to sign the bid submission. The pertinent part states: 4. Each bid submitted shall be signed by the owner(s) corporate officers, or legal representative(s). The corporate, trade, or partnership title must be either stamped or typewritten beside the actual signature(s). If the Bid Submittal is signed by an Agent, written evidence from the owner of record of his/her authority must accompany the proposal. ALL BID SUBMITTAL SIGNATURES MUST BE WITNESSED BY TWO PERSONS. [Emphasis appears in ITB] Petitioner Proctor signed his bid submittal in proper person. TCC's bid submittal was signed by Sharon K. Lane, "Executive Director," of TCC Number 3 Ltd. Inc., Intervenor herein. At all times material, TCC Number 3 Ltd. Inc. has been a Florida corporation. At the time of the bid opening, Ms. Lane was TCC's sole shareholder and "all officers." At the time of formal hearing, Ms. Lane remained the sole shareholder, but others had assumed some of the corporate offices. Her status at the time of the bid submittal was sufficient for her to bid on behalf of the TCC corporation and to execute the PUR 7068 form on that corporation's behalf. Intervenor TCC submitted the required PUR 7068 form, but TCC submitted as sole evidence of control an undated, unrecorded "Contract for Sale and Purchase" by and between Hernando Plaza Ltd. as Seller and Intervenor TCC as Buyer, for the property which Intervenor was offering for lease to HRS. The best date assignable to this document is April 29, 1991. It was executed on behalf of Hernando Plaza Ltd. by Edward M. Strawgate and Harold Brown representing themselves as general partners of the limited partnership. TCC's obligation to proceed to closing under the foregoing contract was contingent upon TCC's securing an anchor tenant. However, the contract requires TCC to take steps to secure an anchor tenant. By its terms, TCC may purchase the property with or without an anchor tenant, but the contract requires TCC, in seeking an anchor tenant, to set time limits for the lease arrangement with the proposed anchor tenant which do not necessarily accord with the timing of HRS' bid process. HRS accepted TCC's contract to purchase from Hernando Plaza Ltd., as evidence of TCC's control of the premises offered by TCC for lease, believing it to constitute an option to purchase and the necessary evidence of control as required by the ITB. (See, Finding of Fact 6, supra.) At the time of the bid opening, HRS had no reliable information as to what entity actually owned the property offered by TCC, and TCC had not disclosed to HRS that its contract to purchase the property was with a legal entity other than the record title owner of the property, which record title owner was and is the Victor and Lillian Brown Foundation (Brown Foundation). See, infra. Up to that date, at least, Hernando Plaza Ltd. had represented itself to TCC as the owner of the property. The ITB did not require that an abstract of title be submitted with the bid, and HRS normally does not require an abstract from successful bidders, although the ITB contains provisions for future disclosure from successful bidders. (See, ITB item 5 under Requirements for Bidders to Submit Bids.) Absent some reason to "go behind" facial evidence of control, HRS attempts to protect itself by requiring successful bidders to put up an irrevocable letter of credit for one-half of one percent of the proposed lease rental obligation over the basic lease term as a penalty in the event a successful bidder cannot perform. (See, ITB page 4, item 10.) Hernando Plaza Ltd.'s certificate from the Florida Secretary of State expired December 31, 1981. That fact was advertised and the certificate cancelled July 16, 1982. At that time, Edward M. Strawgate was listed as a general partner and Harold Brown was listed as a limited partner of Hernando Plaza Ltd. Hernando Plaza Ltd. had been administratively dissolved for failure to file its annual report. Subsequent to the time that Intervenor submitted its bid proposal, but prior to formal hearing, Hernando Plaza Ltd. was reinstated by the Florida Secretary of State. Once reinstated, the limited partnership's ability to act related back and validated its prior actions. At all times material, the record title of the property offered by Intervenor TCC for lease to HRS was owned by "Harold Brown, Lillian Brown and Muriel Kahr as Trustees of the Victor and Lillian Brown Foundation." This title is derived from a recorded June 30, 1967 warranty deed from Hernando Plaza Ltd., which deed was admitted in evidence at formal hearing. The warranty deed was not attached to TCC's bid submittal. Neither TCC, the corporation, nor Sharon K. Lane, individually, held any authority as agent to submit a bid to HRS on behalf of the record title owner, the Brown Foundation. There is also in evidence a recorded December 18, 1985 Amendment to Lease between the Brown Foundation and City National Bank. That Amendment to Lease also was not attached to TCC's bid submittal to evidence control of the premises TCC was offering to lease to HRS. That Amendment to Lease also recites that Hernando Plaza Ltd. leased back the subject property from the Brown Foundation by a lease dated June 30, 1967. The June 30, 1967 lease was not recorded, was not part of TCC's bid submittal, and is not in evidence. The December 18, 1985 Amendment to Lease goes on to recite that Hernando Plaza Ltd. has assigned its lessee interest under the June 30, 1967 lease to City National Bank by a March 14, 1978 assignment. There is also in evidence a recorded March 14, 1978 "Assignment of Lessee's Interest in Lease from Hernando Plaza Ltd. to City National Bank." This assignment was not part of TCC's bid submittal. The December 18, 1985 Amendment to Lease goes on to further recite that the Brown Foundation has "agreed to give and grant to [Hernando Plaza Ltd.] an option to purchase the property." The remainder of the December 18, 1985 Amendment to Lease details the terms or conditions of the option to purchase granted by the Brown Foundation to Hernando Plaza. For instance, in order to exercise that option to purchase the subject property from the Brown Foundation, Hernando Plaza Ltd., among other requirements, would have to demonstrate that all the terms of the unrecorded June 30, 1967 lease are "in good standing." One may reasonably infer that "in good standing" would at a bare minimum mean that the rents under the lease are paid current at the time the option is exercised, but what the other terms of the lease might be are subject to pure conjecture. TCC's bid submittal did not include documentation that the June 30, 1967 lease was "in good standing." There is also in evidence a recorded June 7, 1989 Trustee's Deed (quitclaim deed of the trustee's interest) from City National Bank's successor bank/trustee to Hernando Plaza Ltd. The Trustee's Deed also was not attached to TCC's bid submittal. On the date of bid submittal/opening neither TCC, the corporation, nor Sharon K. Lane, individually, held any authority as agent to submit a bid on behalf of Hernando Plaza Ltd. or City National Bank's successor. At formal hearing, TCC submitted an October 24, 1991 written hearsay statement by Harold Brown as Trustee of the Brown Foundation to the effect that Hernando Plaza Ltd.'s December 18, 1985 option to purchase the property from the Brown Foundation was "in full force and effect" and that the June 30, 1967 lease back from the Brown Foundation to Hernando Plaza Ltd. was "in full force and effect and that the lessee is in good standing thereunder." Assuming these items may be considered in this proceeding pursuant to Section 120.58 (1) F.S. as supplementing or explaining direct evidence, they still do not clarify in any way what all the terms of the unrecorded 1967 lease are or that those terms will remain in good standing on the date in the future that Hernando Plaza Ltd. elects to exercise its option, if it elects to exercise its option to purchase the property from the Brown Foundation so that Hernando Plaza Ltd. may, in turn, convey the property to TCC, pursuant to Hernando Plaza Ltd. and TCC's April 29, 1991 contract for sale and purchase. Oddly enough, there is further explanatory hearsay that on October 24, 1991, Harold Brown was a trustee of the Brown Foundation and that he also was the sole limited partner of Hernando Plaza Ltd., although TCC's contract with Hernando Plaza for sale and purchase previously indicated Harold Brown was one of two general partners. Hernando Plaza Ltd.'s option to purchase the property from the Brown Foundation must be exercised by Hernando Plaza Ltd. before Hernando Plaza Ltd. can honor its contract to purchase/sell to TCC. Since there is no record evidence that the June 30, 1967 lease from the Brown Foundation as lessor to Hernando Plaza Ltd. as lessee will be in good standing on whatever future date Hernando Plaza Ltd. attempts to exercise its option with the Brown Foundation, one may only speculate both as to when and if TCC will be able to purchase the property from Hernando Plaza Ltd. TCC has only an option to become owner of the subject property at some unspecified date conditioned upon Hernando Plaza Ltd.'s first successfully exercising its option from the Brown Foundation and further conditioned upon all the terms of TCC's contract with Hernando Plaza Ltd. Apparently, TCC's only recourse to enforce its contract with Hernando Plaza Ltd. is a Circuit Court action for specific performance. TCC also submitted a site plan and floor plan with its bid submittal. The ITB required that offices on outside walls must provide windows. TCC's plans did not reflect windows in two sides of the building, but given HRS' retaining the right to partially design and locate its own halls and offices during the building's renovation, TCC's failure to show windows in the two outside walls is not, in and of itself, a material, disqualifying deviation from the ITB so as to unilaterally render TCC's bid nonresponsive. HRS staff member Donald J. Cerlanek prepared a bid synopsis of each bid. This involved completing a form from the HRS leasing manual which illustrates the characteristics of each of the bids. The bid requirements included evaluation criteria and a maximum amount of points which could be awarded for each criteria item. Five HRS bid evaluation committee members executed no conflict of interest forms. These were: Thomas C. Little Jr., David Thomley, Sylvia Smoot, Harvey Whitesides, and Mary Hawks. All committee members were given copies of the bid synopsis form to use in evaluating the properties submitted by Petitioner and Intervenor. Some of the committee members did not obtain or review the actual bid submissions of each of the bidders, but all of them had access to the bid submissions and read the bid synopsis forms for both Petitioner's and Intervenor's bid submittals. The bid evaluation committee members, except for Mary Hawks, made site visits to the properties submitted by Petitioner and Intervenor. Ms. Hawks essentially acted only as a facilitator or conduit for the evaluations of the other four evaluators as set out infra. The four site evaluators took notes regarding each location. The four site evaluators each assigned numerical weights to each item of evaluation criteria except for the rent and renewal rent portions of the evaluation criteria. Although on their site visits some committee members visiting TCC's site may have seen a color version of an artist's rendering of what TCC's project could look like after renovation was complete, a black and white version of the same artist's rendering was attached to TCC's bid submittal to which all committee members had access, and it is found that this situation in and of itself presented no false or misleading information nor constituted any prejudice to a fair bid process/evaluation. Likewise, although some evaluators discussed expansion prospects with TCC's and/or Proctor's on-site representatives, the evidence is credible and persuasive that each evaluator who visited the sites assessed the projects' respective expansion prospects substantially upon what they saw on each site and had experienced in Proctor's existing facility. The points awarded and reasons for the recommendations of each evaluator who visited the sites were reasonably based on specific needs of HRS. These specific needs of HRS were reasonably articulated by the two evaluators who made on-site inspections and who also testified at formal hearing and were reasonably set out in writing in the written notes of the two other evaluators who did not testify. Thomas C. Little, Jr., testified that he found the Intervenor's property superior as a result of the security problems at Petitioner's locations, the closer proximity of the courthouse, hospital, and health department to Intervenor's property and the superiority of a single building offered by Intervenor versus multiple buildings offered by Petitioner. Additionally, he found the esthetics of Petitioner's buildings lacking and expansion offered by Petitioner limited and was concerned that HRS would outgrow the space due to the fact that their service area is one of the most rapidly growing in Florida. His contemporaneous notes were to the same effect. Sylvia Smoot, also a member of the evaluation committee, testified that she found Intervenor's facility superior based on its proximity to the courthouse, hospitals, and other key locations, and its flexibility of design and concentration of space in one building. She further found Petitioner's location lacking as a result of the three separate buildings, its limited expansion room, and the necessity for redirecting clients between buildings, and the difficulty for elderly and handicapped clients accessing Petitioner's building. Her contemporaneous notes were to the same effect. Evaluators Whitesides and Thomley made substantially similar contemporaneous notes justifying their scoring of the two bidders. Three of the four site evaluators met as a group following the site visits and discussed the properties submitted by Petitioner and Intervenor. All four of the site evaluators made recommendations to accept the property for lease proposed by Intervenor, but they did not all confer and jointly develop a single recommendation to the facilities manager. The points assigned by each of the four site evaluators for the properties proposed by Petitioner and Intervenor were as follows: Evaluation Committee TCC Number Member's Names Proctor's Points 3's Points Thomley 75 98 Little 78 93 Whitesides 74 95 Smoot 80 91 307 377 The rent portion of the evaluation criteria was ascertained by applying present value methodology as set forth in the HRS leasing manual to the annual rents offered by the bidders. The discount factor was 8.32 percent. The present value of Proctor's bid was $1,934,038 and the present value of TCC's bid was $2,028,316. The leasing manual is considered advisory only. It advises present values be made, a determination of the difference in amounts be calculated and a comparison of the difference be made to determine a percentage. Thereafter, the percentage is applied to the maximum amount of points allocated for rent in the evaluation criteria. The lowest present value receives the maximum number of points allocated, and, thus, Proctor was awarded 35 points. TCC received 33 points, based upon the fact that its present value of rent was close to the present value submitted by Proctor. No penalty is imposed to a bidder whose rental amounts is higher than the lowest bidder. No benefit is conferred upon the lowest cost bidder over the next lowest bidder. Mary Hawks, Manager for Administrative Services, Department of Health and Rehabilitative Services, received each of the individual evaluation recommendations from Thomley, Little, Whitesides and Smoot. As a result of travel restrictions placed on the HRS, the four site evaluators and Ms. Hawks, who was also a fifth committee member, did not meet as a group following the site visits although three of the four site evaluators did meet collectively following the site visits. (See Finding of Fact 43-44, supra.) The committee members could have met by telephone conference call but Mary Hawks found it unnecessary to do so because there was such a clear evaluation in favor of Intervenor based on the total composite evaluation scores of 377 for Intervenor and only 307 for Petitioner, out of a total of 400 points. She assigned no points herself but approved their recommendations and forwarded a single recommendation in favor of TCC for ultimate approval by HRS management. Mary Hawks had spoken to the evaluation committee members subsequent to the evaluation and no member had expressed any reservation regarding his/her evaluation or a need to meet to discuss anything additional regarding the bid evaluation. The HRS Intent to Award to TCC subsequently issued. The evaluation process and formula for rent evaluation are not among the more commonly used methods but were reasonable and rational and fairly applied to the bids in this case. No conflict of interest in the evaluation committee members was demonstrated by Petitioner in these proceedings.
Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Health and Rehabilitative Services enter a Final Order finding that: The bid of TCC Number 3 Ltd. is nonresponsive; The bid of Derick Proctor is nonresponsive; Declining to award the bid for Lease No. 590:2306 to either bidder. RECOMMENDED this 20th day of December, 1991, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of December, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 91-5963BID The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Proctor's 74 PFOF: The following PFOF are accepted, except to the extent they are unnecessary, subordinate, or cumulative to the facts as found in the recommended order (RO). Unnecessary, subordinate, or cumulative material has not been utilized: 1-3, sentence 1 of PFOF 4, 5-6, 9, 11-12, sentence 1 of PFOF 13, sentence 1 of PFOF 16, 17-26, sentence 1 of PFOF 29, 30-33, 35-36, sentences 1 and 4 of PFOF 38, 39-41, 44-54, 56-57, 60-61, 63. The following PFOF are rejected because they are not FOF as framed but constitute a proposed conclusion of law (PCOL) or are rejected because they constitute mere legal argument: sentences 2 and 3 of PFOF 4, sentence 2 of PFOF 16, 34, 43. The following PFOF are rejected because, as framed, they constitute mere recitation of isolated, unreconciled testimony or other record evidence or are not supported by the greater weight of the credible record evidence as a whole. However, the subject matter is covered in the RO as proven and supported by the competent, substantial evidence in the record: 10, sentence 2 of PFOF 13, 14- 15, sentence 2 of PFOF 29, sentences 2 and 3 of PFOF 38, 55, 58. PFOF 7-8 are accepted as modified because parts are unnecessary, subordinate, or cumulative to the facts as found and other parts are mere recitations of unreconciled portions of the record and legal argument. The following PFOF are accepted in part but not utilized because parts are unnecessary, subordinate, or cumulative to the facts as found, and other parts are rejected as immaterial to the dispositive issues herein, although correctly quoted from the record: 68-73. The following PFOF are rejected as immaterial or not dispositive: 27-28, 37, 42, 59, 62, 65, 67, 74. The following PFOF are covered in preliminary material: 64, 66. HRS 21 PFOF: The following PFOF are accepted except to the extent they are unnecessary, subordinate, or cumulative to the facts as found in the RO. Material unnecessary, subordinate, or cumulative has not been utilized: 1-4, 6-8, 11-12, 16-19. The following PFOF are rejected because they are not FOF as framed but constitute PCOL or are rejected because they constitute mere legal argument: 5, 9-10, 14-15, 21. The following PFOF are rejected because, as framed, they constitute mere recitation of isolated, unreconciled testimony or other record evidence or are not supported by the greater weight of the credible record evidence as a whole. However, the subject matter is covered in the RO as proven and supported by the competent, substantial evidence in the record: 20. PFOF 13 is accepted as modified to correctly reflect the credible record evidence as a whole. TCC Number 3 75 PFOF: The following PFOF are accepted except to the extent they are unnecessary, subordinate, or cumulative to the facts as found in the RO. Material unnecessary, subordinate, or cumulative has not been utilized: 1-31, 34-38, 42- 45, 47-48, 56, 58-60, 64-69, 71-75. The following PFOF are rejected because they are not FOF as framed but constitute PCOL or are rejected because they constitute mere legal argument: 32. The following PFOF are rejected because, as framed, they constitute mere recitation of isolated, unreconciled testimony or other record evidence or are not supported by the greater weight of the credible record evidence as a whole. However, the subject matter is covered in the RO as proven and supported by the competent, substantial evidence in the record: 33, 40-41, 53-55, 57, 61-63, 70. The following PFOF are rejected as immaterial or as not dispositive: 39, 46, 49, 51-52. PFOF 50 is not a sentence, but the subject matter is covered in the RO as understood. COPIES FURNISHED: Thomas V. Infantino, Esquire Infantino & Berman Post Office Drawer 30 Winter Park, FL 32790 Ralph McMurphy, Esquire HRS District 3 Legal Office 1000 Northeast 16th Avenue Gainesville, FL 32609 B. Gray Gibbs, Esquire Sam Power, Clerk Bette B. Lehmberg, Esquire Department of Health and Suite 800 Rehabilitative Services One 4th Street North 1323 Winewood Boulevard St. Petersburg, FL 33701 Tallahassee, FL 32399-0700
The Issue The ultimate issue for determination is whether the School Board's proposed award of a construction contract to Federal Construction Company is fraudulent, arbitrary, illegal or dishonest. See Department of Transportation v. Groves- Watkins Constructors, 530 So.2d 912 (Fla. 1988). Also at issue is whether Gulf, as fifth lowest bidder, has standing to bring this action and, if so, whether it is entitled to award of the contract. STIPULATED FACTS In their Prehearing statement, filed on December 13, 1988, the parties have stipulated to the following facts: The SCHOOL BOARD placed [sic] for bids pursuant to bid documents on elementary school project known as "Elementary School "E". At a Pre-Bid Meeting on September 27 the bidders were told that the subcontractor's list must list one and only one subcontractor per item and include all subcontractors with no open blanks. If the general contractor was going to list himself as doing that particular piece of work he must so indicate. Bids were submitted to the SCHOOL BOARD on October 13, 1988, by six general contractors with the lowest bid being submitted by FEDERAL followed by PHILLIPS, INDUS, BARTON-MALOW and GULF. Required to be attached to each bid was a Bid Bond, Unit Price List, and List of Subcontractors. The List of Subcontractors Form required the bidder to list the names of subcontractors and suppliers who would perform the phases of the work indicated with the assumption that any work item (trade) not included would be performed by the Bidder's own forces. The lowest bidder, FEDERAL, left some of the items of work blank or had a horizontal line drawn beside them. FEDERAL's bid bond did not contain a penal sum and the Power of Attorney did not contain an original signature, but had a typed in date October 13, 1988 next to the copy of the signature. No Power of Attorney was filed in the Public Records of Sarasota County PHILLIPS' bid listed no subcontractors for any work items. INDUS' bid materially deviated in that it did not agree to complete the work in the time specified, left some work items blank on the subcontractor's list and listed itself as doing work items not normally done by a general contractor. BARTON-MALOW'S bid listed a steel supplier who did not bid the project to BARTON-MALOW and the bid bond was not on the specified form. GULF's bid was in conformance with the bid documents. On October 20, 1988, the SCHOOL BOARD Construction Staff recommended to the SCHOOL BOARD that the FEDERAL bid be accepted and that the contract be awarded to FEDERAL.
Findings Of Fact The bid specifications and related items for construction of Sarasota County School Board's Elementary School "E" and bus depot are dated July 1, 1988. (Joint Exhibit #1.) The Invitation for Sealed Bids was advertised on September 4, 11 and 18, 1988. Among the requirements included in the instructions to the invitation for sealed bids is the direction that each bid must be accompanied by a bid bond, written on the form satisfactory to the Board, or a cashier's check in the amount of five percent of the total base bid as a guarantee that, if successful, the bidder would enter into a written contract with the Board. (Joint Exhibit #1, P.C-1.300.) The instruction also includes the requirement that if a bid bond is submitted it must be "...written on the form bound within these bidding documents...". (Joint Exhibit #1, P.C-1.600.) Among other specifics related to the bond are the requirements that the dollar amount of the bond, or "5 percent of the bid", be typed or printed in the space provided, and that the surety's agent's power of attorney either be recorded in Sarasota County or include an original signature. (Joint Exhibit #1, P.C- 1.610.) Two addenda were issued to the July 1, 1988 bid specifications. Addendum No. 1 is dated September 30, 1988, and includes a revised bid form and list of subcontractors form. The material change in the list of subcontractors form was to delete language at the end of the form allowing changes or substitutions with written consent of the architect and owner prior to signing the agreement, and substituting this language: "The contractor shall not remove or replace subcontractors listed above except upon good cause shown and written approval by Owner". (Joint Exhibit #1, P.C-2.430.) Both the revised and former subcontractor list provide "Any work item (trade) not included will be assumed by the Owner as being performed by the Bidder's own forces". (Joint Exhibit #1, p.C-2.400.) A mandatory pre-bid conference was held on September 27, 1988. In order to have a valid bid proposal, all bidding contractors had to attend the conference. Gulf, Federal and the other bidders had representatives at the conference. Charles Collins, the School Board project manager, also attended and reviewed the specifications. He reminded the conference participants that the subcontractors list must be included with the bid and that one and only one subcontractor could be listed for each item. He also told the participants that if the contractor was going to do a particular item, he had to so indicate. He said that any deviation would result in the bid being rejected. (Transcript pp.316,319.) The bids were submitted and opened on October 13 1988. Six bids were received, with the following totals for both the school and bus depot: Federal $7,243,000.00 Phillips $7,322,155.00 Indus $7,390,000.00 Barton-Malow $7,398,000.00 Gulf $7,448,000.00 Carlson (amount not included in the record -- the highest bidder) (Joint Exhibits #2,3,4,5 and 6) The immediate reaction of Charles Collins and other School Board staff was that the lowest bid, Federal, was a very sloppy bid. There were problems, in fact, with the four lowest of the six bids. (Transcript pp.215 and 324.) Federal's bid bond was on the proper form, but the penal sum space was left blank. In addition, the power of attorney signature was not an original, but was rather part of the printed form. There was no power of attorney for its surety, American Home Assurance Company, on record in Sarasota County. The list of subcontractors form required by the School Board is divided into two columns. The first column lists the work item and in some cases, includes subcategories, such as "supplier", "installer", "manufacturer", "dealer/contractor", and similar designations. For some work items more than one, and as many as three, separate subcategories are included, indicating the need to fill in more than one blank for that work item. The heading over the second column is titled "Subcontractor or Material Supplier". The bidder is supposed to write in the space in this column the subcontractor or supplier for each of the work items and subcategories listed in the first column. Federal's list of subcontractors had either blank spaces or a line drawn in the second column for approximately twenty-two work items or subcategories under the work items. In several cases a single name was listed only once next to the work item, even though there were several subcategories under that item. For example, under the work item, "Pre-Engineered Metal Roof System", are three subcategories: "Manufacturer", "Dealer/Contractor (Supplier)" and "Erector". Federal has handwritten one name next to the "Dealer/Contractor (Supplier)" subcategory: "Hammer & Howell". (Joint Exhibit #3.) Dr. Melvin Pettit is the School Board's director of facilities and is responsible for the bidding process and construction of new schools. He is Charles Collins' supervisor. After the bid opening, Dr. Pettit and his other staff met with the bidders individually to make sure they understood the bid. Gulf's bid was very complete and there was not that much to interpret. (Transcript p.217.) Federal's bid was not complete and needed considerable explanation. Dr. Pettit took notes of the explanations on his copy of Federal's bid form. (Joint Exhibit #10.) Federal drew a line next to the work item "site concrete work" because it intended to do than work itself. Although it listed "United" only once for the two subcategories under "Sanitary Sewer Lift Station", it intended that United be both the supplier and installer. Under the work item, "Termite control", Federal drew a line because it did not have a bid or a subcontractor to list. "Underground Fuel Tanks (Bus Depot) and Accessories" with two subcategories, "Supplier" and "Installer", were left blank. Federal intended that J. H. Pump Services do the work, as they were also doing the fuel dispensing equipment, a separate work item on another page of the form. No supplier nor installer was listed under "Concrete Work" because the Federal representative could not remember the supplier's name when the bid was prepared. Federal had quotations for the "Chalkboard and tackboard" work item, but did not list a supplier. They also had quotations for the specialty signs but did not list a supplier for that work item. No subcontractor was listed under the work item, "Waste Handling Equipment"; Federal intended to use the same subcontractor for that and a separate item, "Food Service Equipment". For the separate items, "Dark Room Equipment" and "Library Equipment", no supplier was listed. Federal explained that it had quotes but did not list them because of the rush of bidding. No subcontractor nor supplier was listed for the separate items, "Intercommunications System" or "Public Address System". Federal explained that it intended to use the same subcontractor as that indicated for the electrical work because these items were included in the electrician's bid. For those items including separate subcategories, where only one name is listed, Federal intended in most cases to use the same firm for all subcategories. However, for the roof system example cited in paragraph #9, above, Federal assumed that Hammer and Howell would supply and erect a roof manufactured by Butler. In other words, Hammer and Howell would not also be the manufacturer of the system. The bid specifications list approved manufacturers, and Hammer and Howell is not one of them, nor were they certified as an approved manufacturer one week prior to the bid date, as required in the specifications. Bid opening day in a general contractor's office is a frantic time. Depending on the size of the job and its competitive nature, literally hundreds of phone calls are made. In this case there were over fifty line items that had to be filled in with names on the subcontractors list. Although quotations from subcontractors and suppliers are obtained in the weeks prior to opening, last minute confirmations are obtained in an effort to get the best and most accurate estimates. Preparation of the subcontractor list is time-consuming and critical to competition among bidders. If the bidder is allowed to leave an item blank, he may continue to "shop around" after the bid opening, if he is awarded the bid, to improve his profit margin. The owner, on the other hand, is deprived of the opportunity to consider the subcontractors or suppliers when the bids are evaluated. The bid opening was at 2:00 p.m. Federal, like many other contractors, dispatched an employee to the bid opening with a blank bid. While the staff were at the contractor's office compiling estimates, the representative at the opening was on the phone taking down last minute information. Rick Furr, Vice-President of Federal for eight years, did not give specific instructions to his representative regarding leaving blanks or drawing a line. In some cases, the blanks or lines were intended to mean that Federal was going to do the work itself; in most cases, however, Federal intended that someone else would do the work. After hearing Federal's explanation of its bid, Dr. Pettit and his staff discussed it and came to the conclusion that even though there were a "goodly number of irregularities", that it was "poorly done" and "sloppy" (transcript, p.219), in their opinion Federal did not gain significant material advantage, so they recommended the award go to Federal, as lowest bidder. Dr. Pettit explained at hearing that because of the language on the subcontractor list form, that ". . . any work item not included would be assumed by the owner as being performed by the Bidder's own forces", the School Board intended to require Federal to use their own forces for those work items which they left blank. By "their own forces", he means the work would be done by Federal employees on Federal's payroll, for whom workers' compensation is paid. (Transcript, pp.228-9.) This stated intention is so conflicting with Federal's intention and capabilities as to be utterly disingenuous. Although Federal can do its own site concrete work, just as most contractors do, it is not licensed to do termite control. It does not have a batch plant to supply concrete. It cannot manufacture a metal roof system, chalkboards and tackboards, specialty signs, darkroom equipment, an intercommunications system, or a public address system. Even if it could, it is not one of the approved manufacturers listed in the bid specifications for most of these items list. It is apparent, therefore, that Federal will either be unable to perform under the contract or that changes must be made to its subcontractors list. The approximate combined value of the work items left blank, or partially blank, by Federal is $1 million. Federal gained a competitive advantage by failing to complete all the blanks on the subcontractors list form. It gained precious minutes of time to concentrate on other aspects of the bid preparation; it is not bound to a given supplier, manufacturer or installer and can continue to bid shop. Phillips' bid, the second lowest, was non-responsive as it failed to list any subcontractors. It left blank the entire four-page attachment to the bid. (Joint Exhibit #4.) Indus' bid materially deviated from the specifications, as stipulated by the parties. (See stipulated Facts, above, and Joint Exhibit #5.) Barton-Malow's subcontractors list included Aetna Steel as the steel fabricator/supplier, but Aetna Steel verified in writing that they did not bid the structural steel on this job. Barton-Malow also used its surety's bid bond form, rather than the form required in the specification. The form provided by Barton-Malow lacked several provisions found on the required form, including the payments of expenses and attorney's fees in the event of a suit on the bond. (Joint Exhibits #1 and 6; Transcript, pp.89-90) Barton-Malow did fill in all of the blanks on the subcontractors list in accordance with the instructions at the pre-bid conference. In its bid specifications and accompanying documents and instructions, the School Board reserves the right to reject any and all bids received and to waive any and all irregularities in regard thereto. (Joint Exhibit #1, p.C- 1.310.) Since the only recommendation the School Board was given is to award the contract to Federal, the lowest bidder, it has not taken any action on the remaining bids.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the School Board of Sarasota County award the contract to Gulf Constructors, Inc., as the lowest responsive bidder. DONE and ENTERED this 1st day of March, 1989, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of March, 1989. APPENDIX The following constitute my rulings on the findings of fact submitted by the parties: Petitioner's Proposed Findings Addressed in Background. Adopted in paragraphs 2. and 7. Adopted in paragraph 2. Adopted in paragraph 7. Adopted in paragraph 4. Rejected as irrelevant. Adopted in paragraphs 12. and 17. 8.-10. Rejected as unnecessary. 11.-13. Adopted in paragraph 3. 14.-19. Adopted in substance in paragraph 11. 20. Adopted in summary in paragraph 16. 21.-30. Adopted in substance in paragraph 16. 31.-36. Adopted in substance in paragraph 17. 37.-41. Addressed in conclusions of law. Rejected as cumulative. Adopted in paragraph 18. Adopted in paragraph 19. Adopted in paragraph 20. 46.-58. Rejected as cumulative and unnecessary 59.-61. Adopted in paragraph 12. 62.-90. Rejected as cumulative, unnecessary or a restatement of testimony, rather than a finding of fact. 91.-96. Although credible, Mr. Cannon's opinion on the enforceability of the bond is not competent. This is basically a legal opinion. 97.-149. Rejected as cumulative, unnecessary, or a restatement of testimony, rather than a finding of fact. Respondent's Proposed Findings Addressed in Background. Adopted in paragraph 3. Adopted in paragraph 21. 4.&5. Adopted in paragraph 3. 6.&7. Rejected as statement of testimony, not a finding of fact. 8.&9. Rejected as immaterial. 10.&11. Adopted in paragraph 4. 12.&l3. Rejected as immaterial. 14.-16. Rejected as contrary to weight of evidence. 17. Adopted `in paragraph 11. 18.-45. Rejected as unnecessary or subordinate to the findings in paragraph 11. Adopted as a legal conclusion. 47.-52. Rejected as unnecessary. Adopted in paragraph 14. Rejected as unnecessary; this is addressed in the conclusions of law. 55.-59. Rejected as contrary to the weight of evidence. Rejected as unnecessary. Rejected as contrary to the weight of evidence. COPIES FURNISHED: DARYL J. BROWN, ESQUIRE MICHAEL S. TAAFFE, ESQUIRE ABEL, BAND, BROWN, RUSSELL & COLLIER 1777 MAIN STREET POST OFFICE BOX 49948 SARASOTA FLORIDA 34230-6948 JOHN V. CANNON, III, ESQUIRE ELVIN W. PHILLIPS, ESQUIRE WILLIAMS, PARKER, HARRISON & DIETZ 1550 RINGLING BOULEVARD POST OFFICE BOX 3258 SARASOTA, FLORIDA 34230 HONORABLE BETTY CASTOR COMMISSIONER OF EDUCATION THE CAPITOL TALLAHASSEE, FL 32399 DR. CHARLES W. FOWLER SUPERINTENDENT SCHOOL BOARD OF SARASOTA COUNTY 2418 HATTON STREET SARASOTA, FL 33577
The Issue Whether the apparent low bid on contract No. SB 95C-66W should be disqualified on the grounds that the bidder does not meet the experience specifications contained in the Invitation to Bid.
Findings Of Fact On August 16, 1994, the School Board issued Invitation to Bid (ITB) No. SB 95C-66W, which was described as being a "term contract to provide and/or install rubberized coatings for sports surfaces." Among the bidders who responded to the ITB were the Petitioner, Papico Construction, Inc., and AAA Tennis Courts, Inc. On August 31, 1994, bids were tabulated and the School Board posted its intent to award the bid to Papico. Thereafter, the bid process was delayed as a result of a protest filed by another bidder. On December 12, 1994, Petitioner filed the formal bid protest that resulted in this proceeding. The School Board does not challenge the timeliness of Petitioner's protest. Among the special conditions of the ITB is the following pertaining the qualifications of the bidder: E. QUALIFICATIONS: The bidder shall have maintained continual work experience in coatings for running tracks for a period of three years prior to the bid date. Bidder must submit written documentation with bid or within three days upon request, substantiating experience requirement. The bidder shall have a place of business for contact by the owner during normal working days. Petitioner framed its challenge to the bid process by the following portion of its formal bid protest: . . . To award this project to Papico or AAA Tennis Courts is not only directly in contradiction to the 3 years of continuous work experience section of the specifications (Special Conditions - E), but also deprives the school system of our experience. . . . Papico timely submitted to the School Board written documentation that substantiated that it met the experience requirement contained in Special Condition - E. The evidence presented at the formal hearing established that Papico is an experienced contractor for recreational surfaces and has been involved in coatings for running tracks since 1989. Between 1989 and the time of the formal hearing, Papico had been involved as either the contractor or as a subcontractor for the surfacing or resurfacing of running tracks at Indiantown Middle School, Parkland High School, Hidden Oaks Middle School, J.D. Parker Elementary School, Florida Atlantic University, Martin County High School, South Plantation High School, and Deland High School. At the formal hearing, Petitioner asserted that Papico also did not meet the experience criteria contained in Special Condition - M. That provision is as follows: M. QUALIFICATIONS: The contractor will submit a list of five all-weather running tracks the firm has resurfaced during the past three years. The list shall contain: owner name, location, phone number, number of tracks, and year constructed or resurfaced. (The district reserves the right to contract these owners as references.) Notwithstanding the fact that this issue was not properly preserved by Petitioner, the evidence established that Papico provided this list to the School Board, thereby complying with Special Condition - M.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Palm Beach County enter a final order that adopts the findings of fact and conclusions of law contained herein, dismisses the bid protest filed by Recreational Surfaces, Inc., and awards the subject contract to Papico Construction, Inc. DONE AND ENTERED this 9th day of February, 1995, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of February, 1995. COPIES FURNISHED: James Petrucelli Recreational Surfaces, Inc. 2123 Oregon Street Orlando, Florida 32803 Robert A. Rosillo, Esquire Palm Beach County School Board 3318 Forest Hill Boulevard, Suite C-302 West Palm Beach, Florida 33406-5813 Dr. Monica Uhlhorn, Superintendent Palm Beach County School Board 3340 Forest Hill Boulevard West Palm Beach, Florida 33406-5869
The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.
Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.
Findings Of Fact Respondent issued an invitation to bid on March 13, 1992. Bid number SB 92-244I involved the disassembly and removal of an existing walk-in freezer and the furnishing and installation of a new walk-in freezer at Coral Sunset Elementary School. The invitations to bid provided in paragraph Y of the Special Conditions: Failure to file a specification protest within the time prescribed in Florida Statutes 120.53 3.(b) shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. (sic) Bid specifications were included in the invitations to bid issued on March 13, 1992. Twenty-three bids were solicited. There were five responses. One of the responses was submitted by Choice Restaurant Equipment, Inc. ("Choice"). Choice is a vendor for equipment manufactured by Petitioner, Nor-Lake, Inc. ("Nor-Lake"). Nor-Lake is an out-of-state corporation with manufacturer's representatives in numerous states including Florida. 4, Petitioner, CHD Marketing Group ("CHD"), is the manufacturer's representative for Nor-Lake in Florida. CHD represents no other manufacturer of the product included in the bid response. Choice is a sales agent for CHD and other manufacturer's representatives in Florida. Choice sells the products of a variety of manufacturers but is the exclusive sales agent for CHD pursuant to a verbal agency agreement. Choice timely submitted a bid for bid number SB 92-244I on April 8, 1992, prior to the bid deadline of 2:00 p.m. on the same day. The successful bidder submitted its bid by Federal Express at 4:51 p.m on April 8, 1992. Respondent's Department of Purchasing and Stores (the "Department") had stated on March 13, 1992, when the invitations to bid were issued, that bid responses must be received by the Department no later than 2:00 p.m. on April 8, 1992, at the Department's address at 3980 RCA Boulevard/Suite 8044, Palm Beach Gardens, Florida, 33410-4276. Prior to April 8, 1992, the Department relocated to a new facility at 3326 Forest Hill Boulevard, West Palm Beach, Florida. The new address was posted at the old location and Department representatives were present at the old address to accept walk-in bids. Federal Express first attempted to deliver the successful bid at the Department's old address at 10:30 a.m. on April 8, 1992. Federal Express delivered the successful bid to the Department's new address at 4:51 p.m. At 2:00 p.m. on the same day, The Department announced that all bids were in and opened the bids that had been delivered. The successful bid and one other bid were delivered on April 8, 1992, after the public opening conducted at 2:00 p.m. on the same day. Bids were tabulated on April 9, 1992. Bid tabulations were posted on April 13, 1992, and the successful bid was announced. The successful bid was for $8,174.00. Three bids were lower than the successful bid. Choice's bid was for $7,742.56. The other two lower bids were for $8,020.00 and $6,620.00. All three lower bids were rejected as non- responsive. Choice's bid was rejected because it did not meet bid specifications for 22 gauge steel, thermostatically controlled door heaters, and reinforced steel door panels. CHD filed a Notice of Protest on April 14, 1992, and a Formal Written Protest on April 24, 1992. CHD's protest alleges that: Choice's bid was lower than that of the successful bidder; the successful bid was not timely made; the bids were not opened publicly in violation of bidding procedure requirements; and the bid specifications were arbitrary and capricious, favored one bidder, and that Choice's bid was responsive. Neither a notice of protest nor a formal written protest was submitted by Choice or Nor-Lake. Neither Choice nor Nor-Lake attended the informal protest conference conducted on April 30, 1992. On May 7, 1992, Respondent's Office of General Counsel issued its written notice of proposed agency action. The written notice recommended that the bid be awarded to the successful bidder and that CHD's protest be dismissed for lack of standing. CHD requested a formal hearing on May 14, 1992, and the matter was referred to the Division of Administrative Hearings for assignment of a hearing officer on May 15, 1992. The bid submitted by Choice was prepared by CHD but signed by the president of Choice. Neither Nor-Lake nor CHD signed a bid or were otherwise bidders of record for bid number SB 92-244I. Neither Choice, CHD, nor Nor-Lake, filed a notice of protest concerning the bid specifications within 72 hours after Choice received the notice of the project plans and specifications on March 13, 1992. The sole basis upon which CHD claims it is substantially affected is the adverse economic impact caused to it by the proposed agency action. The proposed agency action will result in lost sales from this and future transactions. CHD will lose commissions from this and future transactions. The dealer relationship between CHD and Choice will be damaged because Choice will not want to sell a freezer that is not acceptable to Respondent. The marketing strategy developed between CHD and Nor-Lake will be damaged because it is conditioned upon the award of public contracts.
The Issue Whether Respondent's action to reject all bids submitted in response to ITB 13-803-205, relating to the removal and replacement of the public address system at Countryside High School, is illegal, arbitrary, dishonest, or fraudulent, as alleged in the Amended Petition.
Findings Of Fact On March 4, 2013, the ITB was issued by Respondent for work related to the removal and replacement of the public address system at Countryside High School in Clearwater, Florida. According to the Special Conditions portions of the ITB, the "scope" of the project is to "[p]rovide labor and materials to remove and replace the auditorium sound system as per plans and specifications by Keane Acoustics, Inc." The ITB was assigned bid number 13-803-205 by Respondent. Bids for the contract were to be submitted to Respondent by 3:00 p.m., April 11, 2013. Bids for the project were timely received from two companies. The first company, Becker Communications, Inc., d/b/a BCI Integrated Solutions (BCI), submitted a bid in the amount of $118,143.27. Petitioner submitted a bid in the amount of $108,000.00. There is a section of the ITB titled "special conditions." The special conditions provide in part that "[t]his is an ALL or NONE bid [and] [t]he entire contract shall be awarded to the lowest responsive and responsible bidder meeting the specifications." On April 22, 2013, Respondent posted a notice advising of its intent to award the contract to BCI. Although Petitioner submitted the lowest bid, Respondent determined that Petitioner's bid was non-responsive because the bid failed to include "proof of 5 years [of] experience with this type of work" as required by the special conditions of the ITB. Petitioner interpreted this provision as requiring five years of experience as a certain type of general contractor, which Petitioner had, whereas Respondent intended for the ITB to convey that five years of experience related to the removal and installation of audio equipment was the desired type of experience. Petitioner's failure to respond to the ITB in the manner contemplated by Respondent was a technical, nonmaterial irregularity.1/ Numbered paragraph six of the General Terms & Conditions of the ITB provides in part that Respondent "expressly reserves the right to reject any bid proposal if it determines that the . . . experience of the bidder, compared to work proposed, justifies such rejection." On April 24, 2013, Petitioner provided to Respondent a notice advising of its intent to protest the award of the contract to BCI. On May 3, 2013, Petitioner filed its formal protest challenging Respondent's intended action of awarding the contract to BCI. Petitioner's formal protest enumerated several grounds. Of particular concern to Respondent were Petitioner's assertions that the ITB was "inconsistent with Florida law since bidders [were] not required to submit a List of Subcontractors by the time of opening bid"2/ and that provisions of the ITB were ambiguous with respect to the type of experience required to qualify for bidding.3/ Prior to receiving Petitioner's protest, Respondent was unaware of the fact that its bid specifications governing the disclosure of subcontractors did not comply with Florida law. Upon consideration of Petitioner's grounds for protest, Respondent determined that the ITB, as alleged by Petitioner, failed to comply with section 255.0515, Florida Statutes (2012),4/ and that there was ambiguity in the language regarding the experience requirements for bidders.5/ Respondent refers to the problems with the ITB as "procedural errors." These procedural errors will be referred to herein as "irregularities" as this term is more in keeping with the nomenclature of this area of jurisprudence. Given the ITB's irregularities, Respondent decided to reject all bids. In explaining Respondent's rationale for rejecting all bids, Michael Hewett, Respondent's Director of Maintenance,6/ testified that "the [irregularities] were such that [they] potentially could give an unfair advantage to one bidder over another." As for the issue related to the requirements of section 255.0515, Mr. Hewett explained that neither of the two bidders submitted a listing of subcontractors. It would have been competitively disadvantageous to BCI if Petitioner were able to successfully argue that BCI should be disqualified for failing to provide a listing of subcontractors when Petitioner also failed to provide such listing. During the same approximate time that the ITB in the present case was issued, Respondent issued an ITB for nearly identical work to be performed at one of its other facilities (Palm Harbor). In all material respects, the Palm Harbor ITB was identical to the one at issue herein. Unlike the present case, BCI was the sole bidder for the Palm Harbor project and this distinguishing fact reasonably explains why Respondent did not reject BCI's bid for the Palm Harbor Project even though the ITB therein was plagued with the same irregularities found in the present case.7/
Recommendation Upon consideration of the above findings of fact and conclusions of law, it is RECOMMENDED: That the Pinellas County School Board enter a final order finding that the rejection of all bids submitted in response to ITB 13-803-205 was not illegal, arbitrary, dishonest, or fraudulent, and dismissing Tamco Electric, Inc.'s instant protest. DONE AND ENTERED this 16th day of October, 2013, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 2013.
The Issue Whether the Palm Beach County School Board (hereinafter referred to as the "School Board") should sustain Petitioner's challenge to the preliminary determination made with respect to School Board Project No. 349661 to reject all bids submitted and to readvertise.
Findings Of Fact Based upon the evidence adduced at hearing, and the record as a whole, the following Findings of Fact are made: In March of 1993, the School Board issued an Advertisement for Bid (hereinafter referred to as the "Advertisement") through which it solicited the submission of bids on a construction project (School Board Project No. 349661, which is hereinafter referred to as the "Project") involving HVAC replacement, reroofing and other renovation work at Jupiter High School's Building No. 2. The School Board indicated in the Advertisement, among other things, that it "reserv[ed] the right to waive informalities in the Bids, or to reject all Bids." The Advertisement, along with the other bid documents issued in conjunction with the Advertisement, including, but not limited to, the Instructions to Bidders (hereinafter referred to as the "Instructions") and the Proposal Form, were compiled in a Project Manual that was made available for public inspection. Section 00100 of the Project Manual contained the Instructions, which provided, in pertinent part, as follows: Definitions Bidding Documents include the Advertisement for Bid, Notice to Prospective Bidders, Policies of the School Board, Instructions to Bidders, Contract, General Conditions, Supplementary General Conditions, Special Conditions, Bid Bond, Performance and Payment Bond, Proposal Form, and the proposed Contract Documents including all drawings, specifications and addenda issued prior to bid opening. Addenda are written or graphic instruments issued prior to the execution of the Contract which modify or interpret the Bidding Documents, including Drawings and Specifications, by additions, deletions, clarifications or corrections. Addenda will become part of the Contract Documents when the Construction Contract is executed. Bidding Procedures All Bids must be prepared using the forms contained in these specifications and submitted in accordance with the Instructions to Bidders. A Bid is invalid if it has not been deposited at the designated location prior to the time and date for receipt of Bids indicated in the Advertisement for Bid, or prior to any extension thereof issued to the Bidders. Unless otherwise provided in any supplement to these Instructions to Bidders, no Bidder shall modify, withdraw or cancel his Bid or any part thereof for sixty (60) days after the time designated for receipt of Bids in the "Advertisement for Bid." Preparation and Submission of Bid Proposal Form: Each Bidder shall use Proposal Form contained in these specifications, indicate his Bid prices thereon in proper spaces, for the entire work and for the alternates, if applicable. Any erasures or other corrections in the proposal must be explained or noted over the signature of the Bidder. Proposals containing any conditions, omissions, unexplained erasures, alternates, items not called for or irregularities of any kind may be rejected by the Owner. Each proposal shall specify a price written in ink in both words and figures for each of the separate items, as called for, except when the Bid is called for on a lump sum basis. Lump sum Bids shall be shown in both words and figures; where there is a variation between the written amount and figures, the lower amount will be taken as the Bid price. Bid Modification: Bid Modification will be accepted from Bidders if addressed to the Owners, at the place where Bids are to be received, and if received prior to the opening of Bids. Modifications must be in writing and must be signed. . . . Modifications will be read by Owner or Architect prior to opening formal Bids. Withdrawal of Bids: Bids may be withdrawn on written request received from Bidders prior to the time fixed for opening. . . . Negligence on the part of the Bidder in preparing the Bid confers no right for withdrawal of the Bid after it has been opened. 4. Examination of Bidding Documents: 4.01 Each Bidder shall examine the Bidding Documents carefully and, not later than eight (8) days prior to the receipt of Bids, shall make written request to the Architect for interpretation or correction of any ambiguity, inconsistency or error therein which he may discover. Any interpretation or correction will be issued as an Addendum by the Architect. Only a written interpretation or correction by Addendum shall be binding. No Bidder shall rely upon any interpretation or correction given by any other method. . . . 6. Rejection of Bids 6.01 The Bidder acknowledges the right of the Owner to reject any or all Bids and to waive any informality or irregularity in any Bid received. In addition, the Bidder recognizes the right of the Owner to reject a Bid if the Bidder failed to furnish any required Bid security, or to submit the data required by the Bidding Documents, or if the Bid is in any way incomplete or irregular; to reject the Bid of a Bidder who is not in a position to perform the Contract; and to readvertise for other or further Bid Proposals. Award of Contract The Contract, if awarded by the Owner, will be awarded to the lowest bona fide responsible Bidder; provided the Bid is reasonable and it is in the interest of the Owner to accept the Bid. The method of determining the lowest bona fide Bid from Bidders shall be the Base Bid price plus or minus Alternate Prices listed on the Bid Proposal Form which are accepted by the Owner. Alternates will be considered for acceptance by the Owner as set forth in the Alternate section of the Specifications, Division One-General Requirements, Section 101030-Alternates. Section 101030 of the Project Manual, which addressed the subject of "Alternates," provided, in pertinent part, as follows: 1.3 Related Work Described Elsewhere: Pertinent sections of these specifications describe materials and methods required under the various alternates. . . . The method for stating the proposed Contract Amount is described on the Proposal Form, Section 00310. Base Bid: A. Shall include all HVAC replacement, construction of the building roofing and all items shown on drawings and included in these specifications other than as specifically listed alternates. Alternate Number One: Provide an Architect/Owner on-site construction trailer of size and features stipulated below in lieu of such being provided by the Owner. Section 00310 of the Project Manual contained the Proposal Form that all bidders were required to use. It provided, in pertinent part, as follows: DATE SUBMITTED: TO: The School Board of Palm Beach County, Florida 3326 Forest Hill Boulevard West Palm Beach Florida 33406 PROPOSAL FOR: JUPITER HIGH SCHOOL BUILDING NO.2- HVAC REPLACEMENT/REFOOF/RENOVATIONS 500 NORTH MILITARY TRAIL JUPITER, FLORIDA 33458 PROJECT NO. 349661 Having become familiar with conditions at the Project Site and having carefully examined the Bidding Documents, including the Advertisement, Instructions to Bidders, and the Contract Documents, including but not limited to the General Conditions, Supplementary Conditions, Specifications, Details, Schedules, Addenda and Drawings, the Undersigned proposes to furnish all materials, labor equipment and anything else required for the entire Project in accordance with the Documents for the following sum: BASE BID: STATE PRICE IN WORDS AND FIGURES: ($ ) (PRICE IN WORDS) (FIGURES) ALL ALTERNATES MUST BE BID FOR BID TO BE RESPONSIVE. State price in words and figures. ADDITIVE ALTERNATE NO. 1: (Owner/Architect On-Site Construction Trailer) ($ ) (PRICE IN WORDS) (FIGURES) * * * If he is notified of the acceptance of this Bid within sixty (60) days of the time set for the opening of Bids, the Undersigned agrees to execute a Contract for the above Work within eight (8) Owner business days after notice that his Bid has been accepted for the above stated compensation minus or plus any accepted Alternates in the form of a contract presented by the Owner. . . . On March 30, 1993, the School Board issued Addendum No. 1, which added a fire protection system to the Project's scope of work and provided as follows: RE: Jupiter Community High School Building No. 2 HVAC Replacement, Reroof, Renovations The School Board of Palm Beach County, Florida School Project No. 349661 OEF Project No. 50-005625 P&L Project No. 92-061 To all bidders on the above project: Please note contents hereon and insert into the bidding documents that were issued to you on the above entitled project. The following supersede and supplant corresponding items in the specifications, drawings and details. It will be required that each Contractor- Builder/Developer, upon submitting his proposal for this project, indicate on the proposal form in the space provided that all addenda are included in his proposal. Failure to do so may cause rejection of a company's bid or proposal. The School Board of Palm Beach County, Peacock & Lewis Architects and Planners, Inc. and their consultants assume no liability or responsibility for the information on printed materials for this project that were not distributed from the office of Peacock & Lewis Architects and Planners, Inc. GENERAL: AD1-1: FIRE PROTECTION SYSTEM Contractor shall include within his bid and itemize on the proposal form the cost for a complete and functioning fire protection system as described by the attached specification Section 15500- Fire Protection dated 3/30/93, Addendum No. 1. Paragraph 1.2 A.6 of Section 15500, which was attached to Addendum No. 1, provided as follows: Contractor shall identify the cost associated with this scope of work on the proposal form as an itemized price which shall be included within the total bid price. Refer to proposal form. On April 5, 1993, the School Board issued Addendum No. 2, which revised the Proposal Form to reflect the additional pricing requirements imposed by Addendum No. 1. Addendum No. 2 added to the Proposal Form, immediately under the space provided for "Additive Alternative No. 1," the following: UNIT PRICE NO. 1: (Fire Protection System) Contractor shall include within his bid and itemize on the proposal form the cost for a complete and functioning fire protection system as described by the attached specification Section 15500- Fire Protection dated 3/30/93, Addendum No. 1. ($ ) (PRICE IN WORDS) (FIGURES) No other changes material to the instant case were made to the Proposal Form or to any of the other bid documents. It was the intention of those who were responsible for the preparation and issuance of Addenda Nos. 1 and 2 to require bidders to include the price of the fire protection system in their "Base Bid;" 1/ however, they failed to clearly and unambiguously express their intention in these addenda or any of the other bid documents. No other bid document aside from the revised Proposal Form made any reference to a "unit price." Unit prices are typically used in the construction industry to price work added to the initial scope of work, as was the fire protection system in the instant case. In interpreting the bid documents, Joseph Pirrotta, Petitioner's chief executive officer, relied upon his many years of experience in the construction industry. Based upon his reading of these documents, he reasonably believed that the "Unit Price No. 1 (Fire Protection System)" was a separate and distinct component of the "total bid price" and that, although it was to be included in the "bid" he submitted, it was not to be a part of the "Base Bid." While the bid documents were also susceptible to a contrary construction, Pirrotta's was the more reasonable of the two interpretations. Pirrotta completed the revised Proposal Form accordingly. Petitioner was one of three bidders to submit bids in response to the Advertisement. The other two bidders were Intervenor and Janus & Hill Corporation (hereinafter referred to as "Janus"). Petitioner quoted the following prices on the completed revised Proposal Form it submitted: "Base Bid"- $1,672,000.00; "Additive Alternate No.1"- $3,400.00; and "Unit Price No. 1"- $80,000.00. As noted above, Petitioner's "Base Bid" did not include the price of the fire protection system. Intervenor quoted the following prices on the completed revised Proposal Form it submitted: "Base Bid"- $1,947,000.00; "Additive Alternate No.1"- $6,000.00; and "Unit Price No. 1"- $36,484.00. Unlike Petitioner, Intervenor included in its "Base Bid" the price of the fire protection system; however, even if it had not done so, its "total bid price" would still have been substantially higher than Petitioner's. Janus quoted the following prices on the completed revised Proposal Form it submitted: "Base Bid"- $1,970,000.00; "Additive Alternate No.1"- $2,020.00; and "Unit Price No. 1"- $90,000.00. 2/ After bid opening, the School Board's contract administrator for the Project, Albert Paglia, correctly determined that Petitioner was the lowest responsive bidder. Thereafter, he telephoned Pirrotta to congratulate him on his company's successful bid. Before his telephone conversation with Pirrotta, Paglia assumed that Petitioner's "Base Bid" included the price of the fire protection system. He learned otherwise, however, after speaking with Pirrotta, who informed him that Petitioner's "total bid price," excluding "Additive Alternate No. 1," was its "Base Bid" of $1,672,000.00, plus the $80,000.00 for the fire protection system reflected as "Unit Price No. 1" on its completed revised Proposal Form. Paglia and others with whom he was working on the Project perceived this as a problem. They therefore brought the matter to the attention of Lawrence Zabik, the School Board's assistant superintendent for support services. Zabik's initial reaction was to award the contract for the Project, including the fire protection system, to Petitioner for $1,672,00.00, Petitioner's "Base Bid." Pirrotta was unwilling to undertake the Project for that amount. By letter to Zabik dated May 5, 1993, Intervenor gave notice to the School Board of its intent to protest any award made to Petitioner. The letter provided as follows: Based on our review of the Bid Documents submitted by J.D. Pirrotta on April 20, 1992, we are notifying you of our intent to protest the award of the above referenced project to any firm other than Milne & Nicholls, Inc. We will base our protest on the non- responsiveness of J.D. Pirrotta's bid. As you are aware, Mr. Pirrotta requested an additional $80,000 to compensate him for his misinterpretation of Unit Price #1 as an additive alternate. It is now apparent that his bid is incomplete and therefore non- responsive. Please advise us of the Owner's intention with regard to the Award on this project. Zabik referred the letter to the School Board's Office of the General Counsel. By letter dated May 13, 1993, authored by one of the School Board's attorneys, the School Board announced that it intended to reject all bids and readvertise, giving the following explanation: In the instant case, since the bid is susceptible to two interpretations, one of which would be that the Fire Protection System was included in the base bid, and the other that it was not leads to an unfair economic advantage by one bidder over others. The example would be that the low bidder in the instant case is permitted to add the Fire Protection System on as an alternate when it was not intended. Given the ambiguity, the bid should be rejected and the specifications rewritten and readvertised. [Citations omitted.] In the instant case, rejection of all bids is the only reasonable solution so that all parties are given a fair playing field. The School Board has not acted arbitrarily or capriciously in arriving at this decision to readvertise, given the parties place a different interpretation on the bid proposal form. The concerns expressed in the letter that Pirrotta obtained an "unfair economic advantage" over the other bidders as a result of the "ambiguity" in the bid documents are unwarranted.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Palm Beach County School Board enter a final order sustaining the instant bid protest and awarding to Petitioner, as the lowest and best responsive bidder, the contract for School Board Project No. 349661 for $1,752,000.00, plus the price for "Additive Alternate No. 1" should the School Board choose to include this alternate within the Project's scope of work. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 7th day of July, 1993. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of July, 1993.
Findings Of Fact On February 28, 1990, Respondent issued an invitation to bid (ITB) on a construction project referred to as Florida Atlantic University Modulars. The ITB required a base bid and bids on five alternates to the base project. Each bidder was instructed that it must bid on the base project and on each alternate for its bid proposal to be considered responsive. On March 19, 1990, Addendum 1 to the ITB was issued to all prospective bidders. This was an informational addendum and advised the date, time, and location of the posting of the award recommendation. Addendum 1 was not required to be returned by the bidder as a part of the response to the ITB. On March 21, 1990, Addendum 2 to the ITB was issued to all prospective bidders. This was also an informational addendum and advised as to a non- mandatory, pre-bid conference to be held March 27, 1990. Addendum 2 was not required to be returned by the bidder as a part of the response to the ITB. On March 30, 1990, Addendum 3 to the ITB was issued to all prospective bidders. This addendum advised that the date and time for the bid opening had been changed to April 9, 1990, at 2:00 p.m. Addendum 3 also contained modifications, explanations and corrections to the original drawings and specifications which impacted the cost and scope of the project. Immediately above the signature line on the cover page of Addendum 3 was the following: This document must be returned in it's [sic] entirety with the bid. Please sign below to verify that you have read and understand all the changes. Item 2 on page ADD-1 of Addendum 3 required each bidder to submit its per unit price structure with its response to the ITB and provided, in pertinent part, as follows: ... The unit price shall not be included in Base Bid. Submit a separate sheet with bid package. The following instructions are given in Paragraph 1(c) of the Instructions to Bidder: NO ERASURES ARE PERMITTED. If a correction is necessary, draw a single line through the entered figure and enter the corrected figure above it. Corrections must be initialed by the person signing the bid. Any illegible entries, pencil bids or corrections not initialed will not be tabulated. The instructions are repeated in Paragraph 1 of the General Conditions of the ITB: EXECUTION OF BID: ... No erasures are permitted. If a correction is necessary, draw a single line through the entered figure and enter the corrected figure above it. Corrections must be initialed by the person signing the bid. Any illegible entries, pencil bids, or corrections not initialed will not be tabulated. The following is contained as part of the Instructions to Bidder: Failure to complete, sign, seal and return the required documents will result in rejection of your bid. Any questions should be directed to Susan Kuzenka, (305) 761-7460, Purchasing Department, Broward Community College. (Emphasis in the original.) Paragraph 8 of the General Conditions portion of the bid package provided, in pertinent part, as follows: 8. AWARDS. As the best interest of Broward Community College may require, the right is reserved to reject any and all bids and to waive any irregularity in bids received ... On April 9, 1990, Petitioner submitted a bid to Respondent in response to the ITB. Petitioner had received the complete bid package, including all instructions and addenda to the bid package. At the pre-bid conference held March 27, 1990, an employee of Respondent emphasized to the attendees that it was necessary for the bidders to return Addendum 3 in its entirety. Petitioner did not attend the non-mandatory, pre-bid conference. The base bid submitted by Petitioner was $1,085,790.00. The base bid of Double E Construction Co., the next low bidder and the bidder to whom Respondent intends to award the contract, was $1,113,300.00. Petitioner's bid for each of the alternates was lower than that of Double E Construction Co. Petitioner failed to return the entire Addendum 3 as instructed. On page four of the bid package Petitioner acknowledged that it had received Addendum 3, and it signed and returned the cover sheet to Addendum 3 under the language quoted in the foregoing Paragraph 4. Respondent considered this an important requirement because it wanted to prevent a bidder from later claiming that it had not received Addendum 3 or that it had received information different than that contained in Addendum 3. Petitioner made a correction to its bid for Alternate Number 3 found on page 5 of 13 of Petitioner's bid. Petitioner's bid for this alternate was $88,000. In the space for the written amount of the bid, Petitioner's president inserted by hand the words "Eighty-eight Thousand". In the space for the numerical insertion of the bid he initially wrote the sum $125,000 (which was the amount of Petitioner's bid for Alternate 4). He struck through the figure $125,000 and wrote above the stricken figure the figure $88,000. He did not initial his change. Respondent has never accepted changes to price quotations which were not initialed because it is concerned that uninitialed corrections on bids may result in challenges to the integrity of the bid process and may expose its staff to charges of collusion from a disgruntled bidder. Pioneer did not include a unit price structure in its bid as required by Addendum 3. The unit price structure is an informational item that is not separately considered by Respondent to determine the lowest bidder on this project. On April 6, 1990, Petitioner's estimator on this bid telephoned Susan Kuzenka regarding the unit price structure sheet to inquire as to the format that should be followed in submitting the unit price structure. Ms. Kuzenka is named in the Instructions to Bidder as the person in Respondent's purchasing department to whom questions about the bid process should be directed. Petitioner's estimator was told that the unit prices would be required to be submitted by the successful bidder at the pre-construction meeting after the bids were opened, but that the unit price structure need not be submitted with the bid. Petitioner's president verified this information on April 9, 1990, prior to the bid opening, during a telephone conference with the project engineer employed by Respondent for this project. In reliance on the information that was supplied by Respondent's agents, Petitioner did not submit its unit price structure sheet with its bid. Following its examination of all bids, the bid of Petitioner was disqualified on three grounds. The first reason cited by Respondent was that Petitioner failed to return the entire Addendum (3) as required. The second reason was that Petitioner did not initial a correction to a quoted price figure. The third reason was that Petitioner did not include the unit price structure as required in Addendum (3). Petitioner thereafter timely protested its disqualification and the intended award of the contract to Double E Construction Co. Petitioner contends that the reasons cited by Respondent for its disqualification are minor irregularities that should be waived by Respondent. Additionally, Petitioner contends that the third reason should not disqualify it because Petitioner acted in reliance upon the instructions of Respondent's agents in not submitting the unit price structure along with its bid package. This proceeding followed.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Broward Community College, enter a final order which denies the bid protest of Petitioner, Pioneer Contracting, Inc. DONE AND ENTERED this 29th day of June, 1990, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1990. APPENDIX TO THE RECOMMENDED ORDER The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioners. The proposed findings of fact in paragraphs 1, 2. 6 and 7 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 3 are rejected as being subordinate to the findings made in paragraph 10. The proposed findings of fact in paragraph 4 are adopted in part by the Recommended Order. The proposed findings in the last sentence of paragraph 4 are rejected as being unnecessary to the conclusions reached because of the clear instructions contained in Addendum 3. The proposed findings of fact in paragraph 5 are adopted in part by the Recommended Order. The proposed findings in the last two sentences of paragraph 5 are supported by the evidence, but are not adopted as findings of fact because they are unnecessary to the conclusions reached. All proposed findings of fact submitted on behalf of the Respondent are adopted in material part. Copies furnished: Eric L. Dauber, Esquire Beyer & Dauber Suite 5300 2101 W. Commercial Boulevard Ft. Lauderdale, Florida 33309 James D. Camp III, Counsel Broward Community College Fort Lauderdale Center 225 East Las Olas Blvd. Fort Lauderdale, Florida 33301 Janet Rickenbacker Director of Purchasing Broward Community College Fort Lauderdale Center 225 East Las Olas Blvd. Fort Lauderdale, Florida 33301
The Issue Whether Respondent properly rejected Petitioner's bid on the grounds that the bid did not meet a fatal item requirement.
Findings Of Fact On April 24, 1992, Respondent published a Request for Proposals (RFP) for the provision of housekeeping services to South Florida State Hospital. Attached to the RFP as Appendix I was a blank copy of Respondent's "Standard Contract" which is also referred to as its "core model contract". Paragraph 1.a. of Section D of the RFP contains the following instructions to bidders: BIDDER RESPONSE a. State of Florida Request for Proposal Contractual Services Acknowledgment Form, Pur 7033 The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, Appendix II must be signed and returned ... with the proposal or submitted by itself if you choose not to submit a proposal and wish to remain on the department's active vendor list. Paragraph 1.g. of Section D of the RFP, contains the following instructions to bidders: Required Bidders Certification Contract Terms and Conditions The proposal must include a signed statement in response to the RFP indicating acceptance of the terms and conditions of provisions of service as specified in the RFP and contained in the core model contract. Bidders were provided a copy of the RFP rating sheet which contained the following under the heading of Fatal Items: The following criteria must be met in order for the proposal to be considered for evaluation, failure to receive a "Yes" response for any time [item] will result in automatic rejection of the proposal. * * * Does the proposal include a statement agreeing to terms and conditions set forth in the core model contract and the RFP? Petitioner was represented at a "Bidders' Conference" held May 15, 1992, at which the fatal items were discussed. Bidders were advised that it would be necessary for the responses to contain a statement agreeing to the terms and conditions set forth in the core model contract. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, contains the following certification: I certify that this proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same contractual services, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. In submitting a proposal to an agency for the State of Florida, the proposer offers and agrees that if the proposal is accepted, the proposer will convey, sell, assign or transfer to the State of Florida all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti-trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the State of Florida. At the State's discretion, such assignment shall be made and become effective at the time the purchasing agency tenders final payment to the proposer. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was signed by Richard A. Cosby on behalf of Petitioner and submitted as part of Petitioner's response to the RFP. Upon receipt of all responses, Respondent convened an evaluation committee to evaluate the responses. The evaluation committee determined that the response submitted by Petitioner did not contain the required statement agreeing to the terms and conditions set forth in the core model contract and the RFP. Consequently, the evaluation committee rejected Petitioner's proposal from further consideration. Petitioner does not challenge the specifications of the RFP, but, instead, asserts that Mr. Cosby's execution of the State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was sufficient to meet the requirement the evaluation committee found lacking. The language of the Contractual Services Acknowledgment Form, PUR 7033, that most closely approximates the certification that the bidder accepts the terms and conditions set forth in the core model contract and of the RFP is as follows: I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. The proposal submitted by Petitioner did not contain any other statement which could be construed as accepting the terms and conditions set forth in the core model contract and the RFP. The broad language of the Contractual Services Acknowledgment Form, PUR 7033, upon which Petitioner relies does not state that the bidder accepts the terms and conditions set forth in the core model contract and the RFP. The evaluation committee properly determined that Petitioner's response failed to meet this fatal item. In this proceeding, there was evidence that the Respondent routinely inserts in its Request for Proposals the fatal item requirement that the bidders agree in writing to accept the terms and conditions set forth in the core model contract and the RFP, and that Respondent has never waived that fatal item requirement. There was no evidence that Respondent was using this fatal item requirement to discriminate against or in favor of any bidder.
Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of August, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1992. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 92-4311BID The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioner. 1. The proposed findings of fact submitted by Petitioner are accepted in material part by the Recommended Order. Petitioner's conclusions based on those facts are rejected for the reasons discussed in the Recommended Order. The following rulings are made on the proposed findings of fact submitted on behalf of the Respondent. 1. The proposed findings of fact submitted by Respondent are adopted in material part by the Recommended Order. COPIES FURNISHED: Richard A. Cosby, Vice President National Cleaning of Florida, Inc. 1101 Holland Drive, #32 Boca Raton, Florida 33487 Colleen A. Donahue, Esquire District 10 Legal Office Room 513 201 West Broward Boulevard Fort Lauderdale, Florida 33301-1885 Sam Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Slye, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
The Issue The issues are: (1) whether the Petitioner's notice of bid protest filed on June 5, 1996, was timely under Section 120.53(5), Florida Statutes, and, if not, whether Petitioner has waived its right to participate in bid protest proceedings; and (2) if Petitioner's bid protest was timely filed, whether the Respondent acted fraudulently, arbitrarily, illegally or dishonestly in rejecting the Petitioner's bid.
Findings Of Fact The Petitioner is a general contractor which operates in Alachua County and surrounding areas. The Respondent is the governing body of the school district in Alachua County. In April and May, 1996, the Respondent publicly advertised an Invitation to Bid on the Project which consists of hard courts for basketball, driveway paving and new drainage provisions. Petitioner and three other bidders timely submitted sealed bids to the Respondent at its office located at the E. Manning, Jr. Annex, 1817 East University Avenue, Gainesville, Florida. Petitioner's bid proposal included a Contractor's Qualification Statement setting forth Petitioner's experience and financial qualifications to act as the general contractor for the Project. There is no evidence that Petitioner is disqualified as a responsible bidder because: (a) it colluded with other bidders; (b) it based its proposal on bid prices which were obviously unbalanced; (c) it included any false entry in its bid proposal; or (d) it failed to completely fill out the required list of subcontractors. The Invitation to Bid does not set forth any other specific conditions which would disqualify an otherwise responsible bidder. However, Respondent reserves the right to reject any and all bids when it determines that such rejection is in its interest. Respondent publicly opened the bids and read them aloud at 2:00 P.M. on May 9, 1996 as required by the Invitation to Bid. Petitioner did not attend the opening of the bids. The Invitation to Bid specified that the bids would be "tabulated and evaluated by the Superintendent of Schools of Alachua County or member or members of his staff or other individual or individuals designated by him." Edward Gable is Respondent's Director of Facilities. The Superintendent designated Mr. Gable to evaluate bids received for facility projects and to formulate recommendations to Respondent. The Invitation to Bid does not set forth a time certain in which Respondent will notify bidders of its decision or intended decision. However, it does state as follows: At the next regular or special meeting of the Board or at the designated meeting thereafter, the bids, as so opened, tabulated and evaluated, and the recommend- ation of the Superintendent of Schools of Alachua County regarding them shall be presented to the lowest responsible bidder meeting the requirements of the law and the State Board of Education Regulations. In Section 19.1 of the Instructions to Bidders, Respondent informs bidders that it will award the contract to the lowest bidder as soon as possible provided that the lowest bid is reasonable and in Respondent's best interest. The Invitation to Bid provides bidders with the following notice relative to Respondent's decision or intended decision concerning a contract award: The Board shall provide notice of its decision or intended decision concerning a contract award. Notice shall be given either by posting the bid tabulation at the location where the bids were opened or by certified United States mail, return receipt requested. Failure to file a protest within the time prescribed in s. 120.53(5), Florida Statues, shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Any person who is affected adversely by the decision or intended decision shall file with the Board a written "Notice of Protest" within seventy-two (72) hours after posting or notification. A formal written protest shall be filed within ten (10) calendar days after filing the 'Notice of Protest.' Section 17.1 of the Instructions to Bidders contains the following language concerning Respondent's decision or intended decision: 17.1 The Board shall provide notice of its decision or intended decision concerning a contract award. For any other decision, notice shall be given either by posting the bid tabulation at the location where the bids were opened or by certified United States mail, return receipt requested. Section 18.1 of the Instructions to Bidders provides as follows: Bid tabulations with recommended awards will be posted for review by interested parties at the Planning and Construction Department, 1817 East University Avenue, Gainesville, Florida, following the bid opening, and will remain posted for a period of 72 hours. Failure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute as (sic) waiver of proceeding under Chapter 120, Florida Statutes. The Invitation to Bid and the Instructions to Bidders distinguish between a protest concerning a contract award and a protest related to the specifications contained in an invitation to bid or in a request for proposals. In the latter context, a bidder must file a written protest within seventy-two (72) hours after receipt of the project plans and specifications. This case does not involve a protest of a bid solicitation. By virtue of the above referenced provisions in the Invitation to Bid and the Instructions to Bidders, Respondent gave all bidders sufficient and reasonable notice that a posted tabulation together with its recommendation constituted Respondent's intended decision. The bid specifications in the instant case required bidders to submit a bid on a base contract for certain school facility improvements with alternate bids relative to additional improvements in the event Respondent decided to include such features in the Project. Petitioner's base bid was $135,000; it was the lowest bid submitted. The next low bid was from Watson Construction Company, Inc. (Watson) at $133,345. Two additional bids were higher than Watson's bid. On the morning of May 30, 1996 one of Petitioner's employees, Roger "Dave" Williams" phoned Mr. Gable to inquire about the status of the bid award. Mr. Gable was unavailable to take the call. Mr. Williams left a message for Mr. Gable to return the call. Next, at approximately 10:00 a.m. on May 30, 1996, Mr. Williams called a member of Mr. Gable's staff who stated that, as far as he knew, Respondent had not made a decision on the contract. Mr. Gable completed his evaluation and posted the bid tabulation on May 30, 1996 at 3:00 p.m. Included on the bid tabulation was the following statement: RECOMMENDED ACTION: It is recommended that the Board reject the low base bid as submitted by D. E. Wallace Construction Corporation, Alachua, Florida, due to past unsatisfactory contract performance. It is recommended that the Board accept the base bid of $133,345. and award a contract for construction totaling $133,345. to Watson Construction, Gainesville, Florida. Completion of this project shall be within ninety (90) consecutive calendar days from the date indicated in the 'Notice to Proceed.' The bid tabulation clearly notes that "[f]ailure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under chapter 120, Florida Statutes." Respondent regularly posts notices of intended decisions concerning bid awards on a bulletin board in the main hallway of the E. D. Manning Annex. A title at the top of the bulletin board identifies it as the location for bid postings. Respondent posts a copy of Section 120.53(5), Florida Statutes, and a copy of the Respondent's Policy DJC--Bidding Requirements below the title of the bulletin board. Respondent has adopted Policy DJC as a rule through a formal rulemaking process. Policy DJC states as follows in pertinent part: The Board shall provide notice of its decision or intended decision concerning a bid solicitation or a contract award. For a bid solicitation, notice of a decision or intended decision shall be given by United States mail or by hand delivery. For any other Board decisions, notice shall be given either by posting the bid tabulation at the location where the bids were opened or by certified United States mail, return receipt requested. The notice shall contain the following two paragraphs. Failure to file a protest within the time prescribed in s. 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Any person who is affected adversely by the decision or intended decision shall file with the Board a written notice of protest within 72 hours after the posting or notification. A formal written protest shall be filed within 10 calendar days after filing the notice of protest. . . . Failure to file a timely notice of protest or failure to file a timely formal written protest shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Immediately below Policy DJC is a space where Respondent always posts its bid tabulations which include the recommended action on each project and notice that "[f]ailure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under chapter 120, Florida Statutes." The bottom of the board, in large letters, contains the following words: "Failure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under Chapter 120, Florida Statutes." This permanent bulletin board, read as a whole, contains more than enough information to provide bidders with notice of an intended decision and the time frames within which a disappointed bidder must file a written protest. Although he was not required to do so, Mr. Gable telephoned Petitioner's office on the afternoon of May 30, 1996 to advise its president, D. Wallace, of the recommendation. Petitioner was not available to accept that call. Mr. Gable placed another courtesy telephone call to Petitioner on the morning of May 31, 1996. During that conversation, Mr. Gable informed Mr. Wallace of the recommendation for Respondent to reject Petitioner's bid and accept the next lowest bid. Petitioner's representative inspected the posting board in the afternoon on May 31, 1996. On June 3, 1996, Respondent sent Petitioner by facsimile transmission a copy of the agenda for Respondent's June 4 meeting, items H.1. of which was: H.1. Bid Award for Project SBAC CB436 - Newberry High School Site Improvements. Bids for the construction of this project were received on May 9, 1996. Recommendation will be presented. The seventy-two hour window in which a bidder may file a protest does not include Saturdays, Sundays or holidays. Therefore, the time in which a bidder could have filed a protest of Respondent's intended decision in this case, expired June 4, 1996 at 3:00 p.m. No bidder had filed a written protest at that time. Respondent held a regular meeting on June 4, 1996, at 7:00 p.m. When Respondent considered the bid award for Project SBAC CB 436, Mr. Gable presented the recommendation that the Board reject Petitioner's bid and accept Watson's bid due to Petitioner's past unsatisfactory contract performance. Petitioner's counsel spoke against the recommendation. At that time the Petitioner had not filed any written notice of protest. After discussion, Respondent voted to award the contract to Watson. Respondent and Watson executed a contract for the construction of the Project on June 4, 1996. The next day, on June 5, 1996, at 3:40 p.m., Petitioner filed with Respondent, by facsimile transmission, a Notice of Protest challenging the award of the contract for the Project to Watson. The filing of this protest was untimely. Therefore, Petitioner waived its right to protest Respondent's decision or intended decision on the Project. The basis of Respondent's intended decision and ultimate final decision to reject Petitioner's low bid was due to Petitioner's past unsatisfactory performance. The following facts support a finding that Petitioner was not a responsible bidder. Respondent awarded Petitioner the contract for a previous construction project, Project SBAC CA 149, Additions and Renovations for Terwillegar Elementary School. That project included the construction of a number of school buildings. The contract amount was approximately 5.1 million dollars. The last building in the Terwillegar project became "substantially complete" in September, 1995. In January, 1996, Mr. Gable wrote a letter to Petitioner, informing him of the outstanding punch list items for the Terwillegar project. A contractor must complete punch list items and have them approved prior to "final completion." In the Terwillegar Project, the contract provided for compilation of items on the punch list within thirty (30) days from "substantial completion." As of May 30, 1996, Petitioner had not responded to Mr. Gable's letter about the Terwillegar punch list, nor had it completed the punch list. Many of the items on the list were minor, but some of the items involved the safety or integrity of the building structure. The Terwillegar project contract also contained a project closeout section which listed a variety of documents and other materials that Petitioner had to provide to Respondent as part of the "final completion." Included in the Terwillegar project's closeout were items such as insurance change-over requirements, warranties, workmanship bonds, maintenance agreements, final certifications, a final payment request, consent of surety, maintenance manuals, record drawings, record specifications, record project date, and operating instructions. As of May 30, 1996, Petitioner had not provided any of the Terwillegar project closeout materials to the Respondent. The delay in project closeout, after substantial completion, is completely unacceptable to the Respondent. Prior to the opening of bids in this case, Petitioner filed a civil suit against Respondent seeking approximately $1,500,000 representing the unpaid contract balance, subcontractors' and material suppliers' claims for labor and material, and other delay-related damages on the Terwillegar project. Petitioner's claim that Respondent's intended decision and/or final decision was based on personal animosity and bias against Mr. Wallace is contrary to more persuasive evidence. Specifically, Petitioner's Exhibit 6 is not persuasive evidence of bias. The Petitioner's president, D.E. Wallace, has over 30 years in the construction field, including 22 years as an owner/operator of a general contractor company. He has completed more than 100 projects in north Florida in the past eighteen (18) years, including 30 school board construction projects. Mr. Wallace has worked on approximately nine (9) school board projects in Alachua County. He holds himself out as being "completely familiar and knowledgeable in government and building codes, ordinances, regulations, etc."
Recommendation Based upon the findings of fact and the conclusions of law, it is, RECOMMENDED: That the Respondent enter a final order dismissing the Petitioner's protest as untimely. DONE and ENTERED this 9th day of October, 1996, in Tallahassee, Leon County, Florida. SUZANNE F. HOOD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 9th day of October, 1996. COPIES FURNISHED: David L. Worthy, Esquire 4128 Northwest 13th Street Gainesville, Florida 32609 Thomas L. Wittmer, Esquire 620 East University Avenue Gainesville, Florida 32601 Robert W. Hughes, Superintendent Alachua County School Board 620 East University Avenue Gainesville, Florida 32601-5498 Frank T. Brogan, Commissioner Department of Education The Capitol, Plaza Level 08 Tallahassee, Florida 32399-0400