Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
TED AND CAROL SULLIVAN vs CITY OF DELTONA AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 04-002412 (2004)
Division of Administrative Hearings, Florida Filed:Deltona, Florida Jul. 12, 2004 Number: 04-002412 Latest Update: Jul. 25, 2005

The Issue The issue is whether the applicant for an Environmental Resource Permit ("ERP"), the City of Deltona ("City" or "Applicant"), has provided reasonable assurance that the system proposed complies with the water quantity, environmental, and water quality criteria of the St. Johns River Water Management District's ("District") ERP regulations set forth in Florida Administrative Code Chapter 40C-4, and the Applicant's Handbook: Management and Storage of Surface Waters (2005).

Findings Of Fact The District is a special taxing district created by Chapter 373, Florida Statutes, charged with the duty to prevent harm to the water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The City of Deltona is a municipal government established under the provisions of Chapter 165, Florida Statutes. The Lake Theresa Basin is comprised primarily of a system of interconnected lakes extending from Lake Macy in the City of Lake Helen to the Butler Chain of Lakes (Lake Butler and Lake Doyle). The Lake Theresa Basin is land-locked and does not have a natural outfall to Lake Monroe and the St. Johns River. In 2003, after an extended period of above-normal rainfall in the Deltona area, the lakes within the land-locked Lake Theresa Basin staged to extremely high elevations that resulted in standing water in residential yards, and rendered some septic systems inoperable. Lake levels within the Lake Theresa Basin continued to rise and were in danger of rising above the finished floor elevations of some residences within the basin. On March 25, 2003, the District issued an Emergency Order (F.O.R. No. 2003-38) authorizing the construction and short-term operation of the Lake Doyle and Lake Bethel Emergency Overflow Interconnection. Since wetland and surface water impacts would occur, the Emergency Order required the City of Deltona to obtain an ERP for the system. The project area is 4.1 acres, and the system consists of a variable water structure on the west shore of Lake Doyle connected to a series of pipes, swales, water control structures, and wetland systems which outfall to a finger canal of Lake Bethel, with ultimate discharge to Lake Monroe and the St. Johns River. The first segment of the system extends downstream from the weir structure on the west shore of Lake Doyle via a pipe entrenched in the upland berm of the Sheryl Drive right-of-way. The pipe passes under Doyle Road and through xeric pine-oak uplands to the northeast shore of a large (approximately 15 acres) deepwater marsh. Water flows south through the deepwater marsh where it outfalls through four pipes at Ledford Drive. Two of the four pipes are overflow structures, controlled by canal gates. The pipes at Ledford Drive discharge into a ditch and into a large (greater than 20 acres) shallow bay swamp. The south end of the bay swamp is defined (and somewhat impounded) by a 19th Century railroad grade. Water flows through the bay swamp where it outfalls through five pipes at the railroad grade. Three of the five pipes are overflow structures, controlled by channel boards. The pipes at the railroad grade discharge to a 1500-foot long finger canal that was dug some time during the period 1940-1972 from the north central shore of Lake Bethel. The overflow interconnection system has three locations whereby the system can be shut down: 1) Lake Doyle--a control weir, controlled by three sluice gates; 2) Ledford Drive--two thirty-inch reinforced concrete pipes, controlled by canal gates; and 3) railroad grade--three thirty-inch reinforced concrete pipes, controlled by channel boards (collectively referred to as "Overflow Structures"). The Overflow Structures are designed to carry the discharge of water from Lake Doyle to Lake Bethel. With the Overflow Structures closed the system returns to pre-construction characteristics, meaning there will be no increase or decrease in the quantity or quality of water throughout the path of the system as a result of the project. An unequivocal condition of the permit is that the system would operate with all of the Overflow Structures closed. As an added assurance, the City proposes to place a brick and mortar plug in the Lake Doyle weir structure outfall pipe to prevent any discharge from the weir. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the water level in Lake Doyle rises above an elevation of 24.5 feet. The District shall require a separate permit application to be submitted for such future plans. Petitioner, Barbara Ash, has lived on Lake Theresa for 19 years. Ms. Ash lives upstream from the area of the weir that will be plugged in accordance with the ERP. She does not trust either the City of Deltona to comply with or the District to enforce the conditions of the ERP applied for by the City. Petitioner, Barbara Ash, also served as the qualified representative for Petitioners, Francell Frei, Bernard J. and Virginia Patterson, and Ted and Carol Sullivan. Ms. Ash represented that Ms. Frei has lived on Lake Theresa for 12 years, and both the Pattersons and the Sullivans live on Lake Louise, which is within the area of concern in this proceeding. Petitioner, Diana Bauer, has lived on Lake Theresa since February 2004. She fears that the lake will become too dry if the system is allowed to flow. She also believes the wildlife will be adversely affected if the water levels are too low since many species need a swampy or wet environment to thrive. She fears her property value will decrease as a result of the approval of the ERP. She also does not trust either the City to comply with or the District to enforce the conditions of the ERP. Petitioner, Howard Ehmer, lives two to three hundred yards down Lake Theresa from Ms. Bauer. He is concerned about the lake bed being too dry and attracting people on all terrain vehicles who enjoy driving around the lake bottom. He is concerned about his property value decreasing if the lake bed is dry. Further, when the lake level is too low, people cannot enjoy water skiing, boating, and fishing on Lake Theresa. Petitioner, Phillip Lott, a Florida native, has also owned and lived on property abutting Lake Theresa since 1995. Mr. Lott has a Ph.D. in plant ecology, and M.P.A. in coastal zone studies, an M.B.A. in international business, and a B.S. in environmental resource management and planning. Mr. Lott has been well acquainted with the water levels on Lake Theresa for many years. Based upon his personal observations of the lake systems in the Deltona area over the years, Mr. Lott has seen levels fluctuate greatly based upon periods of heavy and light rainfall. Mr. Lott is concerned that the District will permit the City to open the weir to let water flow through the system and cause flooding in some areas and low water levels in other areas. He fears that the District will allow the water to flow and upset the environmental balance, but he admits that this ERP application is for a closed system that will not allow the water to flow as he fears. Mr. Lott similarly does not trust the City to comply with and the District to enforce the conditions of the ERP. Petitioners, James E. and Alicia M. Peake, who were represented by Steven L. Spratt at hearing as their qualified representative, live on Lake Louise, which is interconnected with the Lake Theresa basin. The Peakes are concerned that if the level of Lake Louise drops below 21 feet, nine inches, they will not be able to use the boat launch ramps on the lake. Petitioner, Steven L. Spratt, also lives on Lake Louise, and is concerned about the water levels becoming so low that he cannot use the boat launch on the lake. He has lived on the lake since 2000, and remembers when the water level was extremely low. He fears that approval of the ERP in this case will result in low levels of water once again. Petitioner, Gloria Benoit, has live on Lake Theresa for two years. She also enjoys watching recreational activities on the lake, and feels that approval of the ERP will devalue her lakefront property. Ms. Benoit appeared at the first day of the hearing, but offered no testimony on her behalf. J. Christy Wilson, Esquire, appeared prior to the final hearing as counsel of record for Petitioners, Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow. Neither Ms. Wilson nor any of the three Petitioners she represented appeared at any time during the hearing, filed any pleadings seeking to excuse themselves from appearing at the final hearing, or offered any evidence, testimony, pre- or post- hearing submittals. Petitioner, Gary Jensen, did not appear at hearing, did not file any pleadings or papers seeking to be excused from appearing at the final hearing, and did not offer any evidence, testimony, pre- or post-hearing submittals. Both the City and the District recognize that areas downstream from the project site, such as Stone Island and Sanford, have experienced flooding in the past in time of high amounts of rainfall. The system proposed by the City for this ERP will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel. So long as the overflow structures are closed, the system will mimic pre-construction flow patterns, with no increase in volume flowing downstream. The District has considered the environment in its proposed approval of the ERP. The area abutting the project is little urbanized and provides good aquatic and emergent marsh habitat. With the exception of the western shore area of the deepwater marsh ("west marsh area"), the bay swamp and remaining deepwater marsh area have good ecological value. In the 1940's, the west marsh area was incorporated into the drainage system of a poultry farm that occupied the site. This area apparently suffered increased nutrient influxes and sedimentation that contributed to a proliferation of floating mats of aquatic plants and organic debris. These tussocks reduced the deepwater marsh's open water and diminished the historical marsh habitat. Water under the tussocks is typically anoxic owing to total shading by tussocks and reduced water circulation. Thick, soft, anaerobic muck has accumulated under the matted vegetation. Exotic shrubs (primrose willow Ludwigia peruvania) and other plants (cattails Typha spp.) dominate the tussocks. The construction of the project, from the 2003 Emergency Order, resulted in adverse impacts to 1.3 acres of wetlands having moderately high- to high ecological value and 0.2 acres of other surface waters. The 0.2 acre impact to other surface waters was to the lake bottom and the shoreline of Lake Doyle where the weir structure was installed. The 0.3 acres of wetland impacts occurred at the upper end of the deepwater marsh where the pipe was installed. The largest wetland impact (1.0 acre) was to the bay swamp. The bay swamp is a shallow body dominated by low hummocks and pools connected inefficiently by shallow braided channels and one acre is filled with a 1-2 foot layer of sediment following swamp channelization. Disturbance plants (e.g., primrose willow, Ludwigia peruvania, and elderberry Sambucus Canadensis) now colonize the sediment plume. Pursuant to the District's elimination and reduction criteria, the applicant must implement practicable design modifications, which would reduce or eliminate adverse impacts to wetlands and other surface waters. A proposed modification, which is not technically capable of being done, is not economically viable, or which adversely affects public safety through endangerment of lives or property is not considered "practicable." The City reduced and/or eliminated the impacts to the lake bottom and shoreline of Lake Doyle and deepwater marsh, to the extent practicable. The impacts were the minimum necessary to install the weir structure and pipe for the system; the weir structure and pipe were carefully installed on the edges of the wetland and surface water systems, resulting in a minimum amount of grading and disturbance. To compensate for the loss of 1.3 acres of wetlands and 0.2 acres of other surface waters, the City proposes to preserve a total of 27.5 acres of wetlands, bay swamp, marsh, and contiguous uplands. Included in this 27.5 acres are 6.4 acres of the west marsh, which are to be restored. The parties stipulated that the mitigation plan would adequately compensate for losses of ecological function (e.g. wildlife habitat and biodiversity, etc.) resulting from the project. Water quality is a concern for the District. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies for nitrogen, phosphorous, and dissolved oxygen. Water quality data for Lake Monroe indicate the lake has experienced high levels of nitrogen and phosphorous and low levels of dissolved oxygen. Prior to construction of the project, there was no natural outfall from the Lake Theresa Basin to Lake Monroe and therefore no contribution from this basin to nitrogen and phosphorous loadings to Lake Monroe. Lake Colby, Three Island Lakes (a/k/a Lake Sixma), and the Savannah are surface waters within the Lake Theresa Basin for which minimum levels have been adopted pursuant to Florida Administrative Code Chapter 40C-8. The system will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel, resulting in no outfall from the Theresa Basin to Lake Monroe. Minimum flows established for surface waters within the Lake Theresa Basin will not be adversely impacted. Under the first part of the secondary impact test, the City must provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonable expected use of the project will not adversely affect the functions of adjacent wetlands or surface waters. The system is designed as a low intensity project. As proposed, little activity and maintenance are expected in the project site area. The reasonably expected use of the system will not cause adverse impacts to the functions of the wetlands and other surface waters. None of the wetland areas adjacent to uplands are used by listed species for nesting or denning. In its pre-construction state, the project area did not cause or contribute to state water quality violations. Under the second part of the secondary impact test, the City must provide reasonable assurance that the construction, alteration, and intended or reasonably expected uses of the system will not adversely affect the ecological value of the uplands to aquatic or wetland dependent species for enabling existing nesting or denning by these species. There are no listed threatened or endangered species within the project site area. Under the third part of the secondary impact test, and as part of the public interest test, the District must consider any other relevant activities that are closely linked and causally related to any proposed dredging or filling which will cause impacts to significant historical and archaeological resources. When making this determination, the District is required, by rule, to consult with the Division of Historical Resources. The Division of Historical Resources indicated that no historical or archaeological resources are likely present on the site. No impacts to significant historical and archaeological resources are expected. Under the fourth part of the secondary impact test, the City must demonstrate that certain additional activities and future phases of a project will not result in adverse impacts to the functions of wetlands or water quality violations. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the level in Lake Doyle rises above an elevation of 24.5 feet. Based upon the plans and calculations submitted, the proposed future phase, without additional measures, could result in minor increases in the loadings of nitrogen and phosphorous to Lake Monroe. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies due to water quality data indicating the lake has experienced high levels of nitrogen and phosphorous, and low levels of dissolved oxygen. Under this potential future phase, there would be an outfall from the Lake Theresa Basin to Lake Monroe. To address the impact on water quality of this potential future phase, the City has submitted a loading reduction plan for nitrogen, phosphorous, and dissolved oxygen. The plan includes compensating treatment to fully offset the potential increased nutrient loadings to Lake Monroe. Specifically, the loading reduction plan includes: Construction and operation of compensating treatment systems to fully offset anticipated increased nutrient loadings to Lake Monroe. Weekly water quality monitoring of the discharge from Lake Doyle for total phosphorous and total nitrogen. A requirement that the overflow structure be closed if the total phosphorous level reaches 0.18 mg/l or higher or the total nitrogen level reaches 1.2 mg/l or higher in any given week and will remain closed until levels fall below those limits. The implementation of these water quality mitigation measures will result in a net improvement of the water quality in Lake Monroe for nitrogen, phosphorous, or dissolved oxygen. The future phase was conceptually evaluated by the District for impacts to wetland functions. The future phase as proposed could result in adverse impacts to wetland functions. Operation of the system with the overflow structures open could impact the bay swamp and deepwater marsh. The City has demonstrated that any adverse impacts could be offset through mitigation. Based upon the information provided by the City and general engineering principles, the system is capable of functioning as proposed. The City of Deltona will be responsible for the operation, maintenance, and repair of the surface waster management system. A local government is an acceptable operation and maintenance entity under District rules. The public interest test has seven criteria. The public interest test requires the District to evaluate only those parts of the project actually located in, on, or over surface waters or wetlands, to determine whether a factor is positive, neutral, or negative, and then to balance these factors against each other. The seven factors are as follows: the public health, safety, or welfare of others; conservation of fish and wildlife and their habitats; fishing, recreational value, and marine productivity; temporary or permanent nature; 5) navigation, water flow, erosion, and shoaling; 6) the current condition and relative value of functions; and 7) historical and archaeological resources. There are no identified environmental hazards or improvements to public health and safety. The District does not consider impacts to property values. To offset any adverse impacts to fish and wildlife and their habitats, the City has proposed mitigation. The areas of the project in, on, or over wetlands do not provide recreational opportunities. Construction and operation of the project located in, on, or over wetlands will be permanent in nature. Construction and operation of the project located in, on, or over wetlands will not cause shoaling, and does not provide navigational opportunities. The mitigation will offset the relative value of functions performed by areas affected by the proposed project. No historical or archaeological resources are likely on the site of the project. The mitigation of the project is located within the same drainage basin as the project and offsets the adverse impacts. The project is not expected to cause unacceptable cumulative impacts.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered granting the City of Deltona's application for an environmental resource permit with the conditions set forth in the Technical Staff Report, and dismissing the Petitions for Formal Administrative Hearing filed by Gary Jensen in Case No. 04-2405, and by Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow in Case No. 04-3048. DONE AND ENTERED this 27th day of May, 2005, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2005. COPIES FURNISHED: George Trovato, Esquire City of Deltona 2345 Providence Boulevard Deltona, Florida 32725 Diana E. Bauer 1324 Tartan Avenue Deltona, Florida 32738 Barbara Ash, Qualified Representative 943 South Dean Circle Deltona, Florida 32738-6801 Phillip Lott 948 North Watt Circle Deltona, Florida Howard Ehmer Nina Ehmer 32738-7919 1081 Anza Court Deltona, Florida 32738 Francell Frei 1080 Peak Circle Deltona, Florida 32738 Bernard T. Patterson Virginia T. Patterson 2518 Sheffield Drive Deltona, Florida 32738 Kealey A. West, Esquire St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177 J. Christy Wilson, Esquire Wilson, Garber & Small, P.A. 437 North Magnolia Avenue Orlando, Florida 32801 Gloria Benoit 1300 Tartan Avenue Deltona, Florida 32738 Gary Jensen 1298 Tartan Avenue Deltona, Florida 32738 James E. Peake Alicia M. Peake 2442 Weatherford Drive Deltona, Florida 32738 Steven L. Spratt 2492 Weatherford Drive Deltona, Florida 32738 Ted Sullivan 1489 Timbercrest Drive Deltona, Florida 32738 Kirby Green, Executive Director St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177

Florida Laws (3) 120.569120.57373.086 Florida Administrative Code (6) 40C-4.30140C-4.30240C-4.33140C-4.75162-302.30062-4.242
# 1
HARRY PEPPER AND ASSOCIATES, INC. vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 05-002765BID (2005)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 01, 2005 Number: 05-002765BID Latest Update: Jun. 01, 2024
# 2
PALM BEACH COUNTY ENVIRONMENTAL COALITION, STEVEN BELL, ALEXANDRA LARSON, MICHAEL CHRISTIANSON, AND BARRY SILVER vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, PALM BEACH COUNTY, AND LANTANA FARMS ASSOCIATES, INC., 04-003084 (2004)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 02, 2004 Number: 04-003084 Latest Update: Dec. 13, 2004

The Issue Petitioners challenge the South Florida Water Management District’s (the District) proposed action to issue Individual Environmental Resource Permit (ERP) 50-06558-P to authorize conceptual approval of a surface water management (SWM) system to serve 1,919 acres of a phased, multiple-use development referred to as the Palm Beach County Biotechnolgy Research Park (BRP) and to authorize construction and operation of Phase 1A of that proposed project. The ultimate issue is whether the Applicants provided reasonable assurances that the proposed activities will not be harmful to the water resources of the District; will not be inconsistent with the overall objectives of the District; and will comply with the water quantity, environmental, and water quality criteria of the District’s ERP regulations, which are set forth in Part IV of Chapter 373, Florida Statutes, Florida Administrative Code Chapter 40E-4, et. seq.; and the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District – September 2003 (BOR).1

Findings Of Fact THE PARTIES The Florida Wildlife Federation, Audubon Society of the Everglades, and Jupiter Farms Environmental Council, Inc. (d/b/a Loxahatchee River Coalition) are not-for-profit corporations in existence prior to 2003 with more than 25 members in Palm Beach County. Palm Beach County Environmental Coalition was formed in 1997 and is a private, county-wide, non-profit citizen’s organization. Ms. Ketter, Mr. Bell, Ms. Larson, and Mr. Christensen are individuals affected by the proposed BRP. The Respondents stipulated that the parties who remained Petitioners after Mr. Silver’s withdrawal as a Petitioner have standing to bring this proceeding. The District, a public corporation existing by virtue of Chapter 25270, Laws of Florida, 1949, operates pursuant to Chapter 373, Florida Statutes, and Title 40E, Florida Administrative Code, as a multipurpose water management district with its principal office in West Palm Beach, Florida. The County is a duly-constituted governmental entity. THE PROJECT SITE AND ADJACENT LANDS The site of the project is generally referred to as the Mecca Farms, which is a contiguous tract of 1,919 acres of land. At present, the Mecca Farms is used for farming and mining operations. There presently exists a permitted, SWM system on the Mecca Farms that was first permitted in 1979, and has been modified from time to time since then. The existing SWM system includes 73 acres of ditches and a 272-acre above-ground impoundment area. The Mecca Farms site is located within the C-18 Basin. There are no jurisdictional wetlands or delineated surface waters on the Mecca Farms. The following, which is taken from the Staff Report (SFWMD Ex. 1), accurately describes the project site and its adjacent lands: The project site consists of 1,919 acres presently supporting an active orange grove with approximately 73 acres of associated drainage and irrigation ditches/canals and a 30-acre active sand mining operation. The ditches/canals are presently maintained at an elevation of approximately 17 feet NGVD.[3] These ditches/canals provide drainage conveyance to a 272-acre above- ground impoundment located in the northeast corner of the site utilizing four (4) 22,000 gpm pumps. The above-ground impoundment discharges to the west leg of the C-18 Canal via gravity discharge. Project site ditches and canals also connect directly to the C-18 Canal through an 18,000 gpm pump. An additional 224-acre agricultural area east of the 1,919 acres of orange groves is connected to and drains into the canal/ditch system on the project site. This adjacent area was leased from the adjacent land owner by the grove owner for use as row crops and was connected to the grove canal/ditch system for better control of drainage and irrigation. The area is no longer used for row crops. There is also a small area on the site that contains caretaker housing and an equipment maintenance building for the orange groves. These facilities were originally permitted in 1979 under Surface Water Management Permit No. 50-00689-S and subsequent modifications. The citrus grove and primary drainage facilities have been in existence since the 1960s. The Hungryland Slough is located north of the project site, separated from the project site by the C-18 Canal. This area is comprised primarily of publicly-owned natural areas, including an area referred to as Unit 11, which is owned in the majority by Palm Beach County. To the west is the J.W. Corbett Wildlife Management Area (CWMA) owned and managed by the Florida Fish and Wildlife Conservation Commission (FFWCC). To the east, a large area of low-intensity agricultural land exists under the ownership of Charles Vavrus and within the City of Palm Beach Gardens. These lands contain extensive wetlands that are adjacent to the Loxahatchee Slough to the east. The Acreage, a low-density residential area, is located directly to the south of the project site. The only access to the site at this time is an unpaved extension of Seminole Pratt-Whitney Road (SPW), connecting the site at its southwestern corner to the Acreage. THE PROPOSED PROJECT The subject application is for conceptual approval of the SWM system for the BRP and for construction and operation of Phase 1A of the project. All of the proposed Phase 1A construction will occur on the Mecca Farms site. The following, taken from the Staff Report, accurately describes the proposed project: The [BRP] is a phased multiple use development planned for approximately 1,919 acres and will consist of land uses related to science and technology, biotechnology, biomedical, and other related research and development industries and manufacturing. Additionally, proposed support and complementary land uses include educational, institutional, residential, commercial, and recreational facilities, along with utilities and a large created natural area. THE PROPOSED SWM SYSTEM The proposed SWM system will consist of several interconnected lakes that will provide wet detention for storm water runoff from the property site and from 39 acres of off- site flows from SPW Road and a proposed Florida Power and Light (FPL) Substation. The lakes will collect, store, and treat the runoff. The storm water will pass through the lakes, through a 247-acre area referred to as the “Natural Area” (which will be created as part of the mitigation plan), and discharged to the C-18 Canal. To provide additional water quality treatment, these lakes will include planted littoral zones and the southern lake will include a filter marsh. The Natural Area will, in subsequent construction phases, be constructed on the western boundary of the Mecca site with discharge to the C-18 canal, which is adjacent to the northern boundary of the Mecca Farms. The southern boundary of the Natural Area will be the north boundary of the lake that is to be constructed on the southern end of the property. This is the area that is available for use as a flow-way (which will be discussed in greater detail in a subsequent section of this Recommended Order). The Natural Area will be a wetland type system that will move water slowly through that system providing additional storage and water quality benefits prior to discharging through a gravity control structure into the C-18 Canal. The C-18 Canal discharges to either the Northwest or Southwest Fork of the Loxahatchee River, depending on how structures are operated downstream. Discharges travel in the C-18 Canal for approximately nine miles before reaching the Loxahatchee River. The existing SWM system for the Mecca Farms currently discharges to the C-18 Canal, as will the proposed SWM system. The proposed project will not discharge to the CWMA or the Hungryland Slough. The Grassy Waters Preserve and the Loxahatchee Slough are several miles from the project site and will not be affected by the project’s proposed activities. The following, which is taken from the Staff Report, accurately describes the proposed SWM system. The proposed conceptual surface water management system which will serve the 1,919-acre site will consist of site grading, storm water inlets and culverts which will direct all runoff to a series of interconnected lakes for water quality treatment and attenuation of the peak runoff rate. Pumps will control the runoff rate from the developed site into the adjacent onsite BRP natural area. The BRP natural area will discharge into the C-18 canal via a gravity control structure. The system has been designed to accommodate 39 acres of off-site flows from SPW [Road] and a proposed Florida Power and Light (FPL) Substation. The existing control elevation of the citrus grove is 17.0’ NGVD. The proposed control elevations are 18.0’ NGVD for the developed area and 19.0’ NGVD for the natural area. The control elevations are being raised to provide a “step down” of water elevations from wetlands to the north, west and east of the site (20.5’ to 21.0’) to lower elevations to the south (17.0’). PHASE 1A CONSTRUCTION The following, which is taken from the Staff Report, accurately describes the proposed Phase 1A construction: The Phase 1A construction activities will allow the applicant to proceed with lake excavation, clearing and site grading of 536 acres in the southern portion of the site. No permanent buildings or parking areas are proposed at this time. Stormwater from Phase 1A and the remainder of the site, to remain in agricultural use, will be treated in the Phase 1A lakes and then pumped into the existing impoundment for additional water quality treatment and attenuation prior to discharging to the west leg of the C-18 Canal via the existing weir structures. The existing 18,000 gpm pump that connects the on-site ditches and canals directly to the C-18 Canal will remain, but will only be used if the impoundment is full. (See Special Condition No. 21). Approval of Phase 1A authorizes the use of the existing, previously permitted surface water management facilities, therefore, the previous permit no. 50-00689-S is superceded by this permit. The 224 acre agricultural area east of the existing grove that is connected to the grove canal/ditch system will be severed as part of Phase 1A. The pipe connecting this area will be removed and portions of the berm around this area will be regraded so the area will sheetflow into the adjacent pasture land’s canal/ditch system as it did previously [sic] to being connected to the grove system. Of the 536 acres involved in the Phase 1A construction, 87 acres will become lake bottom and 449 acres will remain pervious area, subject only to grading. CONCEPTUAL APPROVAL Pertinent to this proceeding, Florida Administrative Code Rule 40E-4.021(5) defines the term “conceptual approval” to mean an ERP issued by the District which approves a conceptual master plan for a surface water management system or a mitigation bank. Florida Administrative Code Rule 40E-4.305, pertains to conceptual approvals and provides, in relevant part, as follows: Conceptual approvals constitute final District action and are binding to the extent that adequate data has been submitted for review by the applicant during the review process. A conceptual approval does not authorize construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system or the establishment and operation of a mitigation bank. * * * For phased projects, the approval process must begin with an application for a conceptual approval which shall be the first permit issued for the project. An application for construction authorization of the first phase(s) may also be included as a part of the initial application. As the permittee desires to construct additional phases, new applications shall be processed as individual or standard general environmental resource permit applications pursuant to the conceptual approval. The conceptual approval, individual and standard general permits shall be modified in accordance with conditions contained in Chapters 40E-4 and 40E-40, F.A.C. Issuance of a conceptual approval permit pursuant to Chapter 40E-4, F.A.C., shall not relieve the applicant of any requirements for obtaining a permit to construct, alter, operate, maintain, remove, or abandon a surface water management system or establish or operate a mitigation bank, nor shall the conceptual approval permit applicant be relieved of the District’s informational requirements or the need to meet the standards of issuance of permits pursuant to Chapters 40E-4 or 40E-40, F.A.C. . . . PERMITTING CRITERIA In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. The conditions for issuance focus on water quantity criteria, environmental criteria, and water quality criteria. Florida Administrative Code Rule 40E-4.301 contains the following permitting conditions applicable to this proceeding: In order to obtain a standard general, individual, or conceptual approval permit ... an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause adverse flooding to on-site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters ...; will not cause adverse secondary impacts to the water resources; will not adversely impact the maintenance of surface or ground water levels or surface water flows ...; will not cause adverse impacts to a work of the District ...; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with the sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; and will comply with any applicable special basin or geographic area criteria established in Chapter 40E-41 F.A.C. Florida Administrative Code Rule 40E-4.302 provides the following Additional Conditions for Issuance of Permits applicable to this proceeding: In addition to the conditions set forth in section 40E-4.301, F.A.C., in order to obtain a standard general, individual, or conceptual approval permit under this chapter or Chapter 40E-40, F.A.C., an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, and abandonment of a system: Located in, on, or over wetlands or other surface waters will not be contrary to the public interest, or if such an activity significantly degrades or is within an Outstanding Florida Water, that the activity will be clearly in the public interest, as determined by balancing the following criteria as set forth in subsections 4.2.3 through 4.2.3.7 of the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District: Whether the activity will adversely affect the public health, safety or welfare or the property of others; Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activity will be of a temporary or permanent nature; Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed activity. Will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in subsections 4.2.8 through 4.2.8.2 of the Basis of Review. . . . THE BASIS OF REVIEW The District has adopted the BOR and incorporated it by reference by Florida Administrative Code Rule 40E- 4.091(1)(a). The standards and criteria found in the BOR are used to determine whether an applicant has given reasonable assurances that the conditions for issuance of an ERP have been satisfied. Section 1.3 of the BOR provides, in part, as follows: . . . Compliance with the criteria established herein [the BOR] constitutes a presumption that the project proposal is in conformance with the conditions for issuance set forth in Rules 40E-4.301 and 40E-4.302, F.A.C. WATER QUANTITY The term “control elevation” describes the level of freshwater water bodies established by a SWM system. The existing SWM system has a control elevation of 17’ NGVD. The control elevation for the proposed lake system will be raised to 18’ NGVD, and the control elevation for the proposed Natural Area will be raised to 19’ NGVD. Raising the control elevations will permit more treatment of storm water prior to discharge and will permit a more controlled discharge. In addition, raising the control elevation will lessen seepage onto the project site from adjacent wetlands. The Applicants provided reasonable assurances that the proposed project will not cause adverse water quantity impacts to receiving waters and adjacent lands, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E- 4.301(a). The Applicants provided reasonable assurances that the proposed project will not cause adverse flooding to on-site or off-site property, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(b). The Applicants provided reasonable assurances that the proposed project will not cause adverse impacts to existing surface water storage and conveyance capabilities, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(c). VALUE OF FUNCTIONS OF WETLANDS AND SURFACE WATERS Florida Administrative Code Rule 40E-4.301(d), requires the Applicants to establish that “. . . the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system . . .” “. . . will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters.” The District established that the term “value of functions,” as used in the rule, refers to habitat and life support functions. Because there are no wetlands or delineated surface waters on the Mecca Farms site, there are no direct adverse impacts to the functions that wetlands provide to fish and wildlife. The Applicants have provided reasonable assurances to demonstrate that the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters will not be adversely affected. The existing project site does not contain nesting areas for wetland-dependent endangered or threatened wildlife species or species of special concern. The potential for use of the existing project site for nesting by such species is minimal. The existing project site does contain habitat for the American Alligator and foraging habitat for wading birds and birds of prey. The primary foraging habitat on the existing site is around the perimeter of the existing 272-acre impoundment area in the northeast portion of the site. The existing impoundment will be replaced by on-site storm water treatment lakes and the BRP Natural Area that will have shallow banks planted with wetland plant species common to the area. Wildlife is opportunistic; and wading birds commonly feed in areas where there is water, wetland vegetation and wetland plants. The end result will be that the proposed project will have more and better foraging habitat acreage than the existing site. The Natural Area will provide a wetland buffer between the developed area and CWMA that will prevent any adverse impacts both to the wetlands and other surface waters in CWMA and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. The Natural Area will provide a wetland buffer between the developed area and Unit 11 that will prevent any adverse impacts both to the wetlands and other surface waters in Unit 11 and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. There was no competent evidence that the proposed project would impact the ability of the Florida Fish and Wildlife Conservation Commission to manage the CWMA through control burns or otherwise, thereby adversely affecting the diversity or abundance of fish and wildlife (including endangered species and their habitats). Petitioners attempted to raise the issue of mosquito control in their Petitions and at the Final Hearing. The allegations pertaining to mosquito control were struck by the District and Special Condition Number 26 was added before the Petitions were referred to DOAH. Petitioners made no attempt to amend their Petitions and have not challenged Special Condition 26. The Addendum to Staff Report (SFWMD Ex. 2) contains the following Special Condition Number 26: “Upon submittal of an application for construction of any buildings, the permittee shall submit a mosquito control plan for review and approval by District Staff.” Since there will be no buildings containing people or other facilities which would encourage the use of mosquito spraying, it is appropriate for the mosquito control condition to apply to only future phases of construction. There was no competent evidence of impacts attributable to pesticides associated with the application for the SWM system or for Phase 1A construction and operation that would adversely affect the diversity or abundance of fish and wildlife including endangered species and their habitats. The Applicants have satisfied the criteria set forth in Florida Administrative Code Rule 40E-4.301(d). WATER QUALITY The primary concern during Phase 1A construction will be erosion control. Best Management Practices (“BMPs”) are operational and design elements used to either eliminate or reduce the amount of pollutants at the source so they do not get into a SWM system or move downstream. To contain erosion in Phase 1A, the Applicants will use the following BMPs: Silt screens and turbidity barriers within existing ditches and around the perimeter of property. Planned construction sequencing to reduce movement and stock piling of material; Slope stabilization and seeding or sodding of graded areas; and Containment of construction materials with berms. All erosion and turbidity control measures will remain in place until the completion of the on-site construction and approval by the District’s post-permit compliance staff. The Applicants provided reasonable assurances that the proposed Phase 1A construction activities will not adversely impact the quality of receiving waters and that those activities will not violate State water quality standards. Section 5.2.1, BOR, requires that a SWM system provide wet detention for the first one inch of runoff. The proposed SWM system will provide wet detention for one and one-half inches of runoff. The Applicants provided reasonable assurances to demonstrate that the technical criteria in the BOR will be met. Under Section 1.3 of the BOR, compliance with the criteria in the BOR constitutes a presumption that the Proposed Project is in conformance with the conditions for issuance. This presumption was not rebutted by the Petitioners. The lake system will include planted littoral zones to provide additional uptake of pollutants. A filter marsh is also included in the southern lake. All of the storm water runoff from the lakes will pass through the filter marsh, which will be planted with wetland plants. The filter marsh will provide additional polishing of pollutants, uptake, and filtering through the plants. The discharge will then go into the BRP, which will provide the discharge additional uptake and filtering. BMPs utilized during the Operations and Maintenance phase will include regular maintenance inspections and cleaning of the SWM system, street-sweeping, litter control programs, roadway maintenance inspections and repair schedule, municipal waste collection, pollution prevention education programs, pesticides, herbicides and fertilizer storage, and application training and education. The littoral zones, filter marsh, BRP natural area, and BMPs were not included in the water quality calculations and are over and above rule requirements. The Applicants provided reasonable assurances to demonstrate that the proposed project will not adversely affect the quality of receiving waters. Therefore, Rule 40E- 4.301(1)(e), F.A.C., will be satisfied and water quality standards will not be violated. HAZARDOUS SUBSTANCES Pursuant to Section 5.5.5 of the BOR, commercial or industrial zoned projects shall provide at least one-half inch of dry detention or retention pretreatment as part of the required retention/detention, unless reasonable assurances can be offered that hazardous materials will not enter the project's SWM system. The Addendum to Staff Report reflects the following Special Condition 25 pertaining to hazardous materials: Upon submittal of an application for construction of commercial or industrial uses the permittee shall submit a plan that provides reasonable assurances that hazardous materials will not enter the surface water management system pursuant to the requirements of section 5.2.2(a) of the Basis of Review. Applicable permitting criteria does not require the Applicants to present a hazardous substances plan at this point because no facilities that will contain hazardous materials are part of the Phase 1A construction. SECONDARY IMPACTS Florida Administrative Code Rule 40E-4.301(1)(f) and Section 4.1.1(f) of the BOR, require an applicant to provide reasonable assurances that the proposed activities will not cause adverse secondary impacts to the water resources. A secondary impact is an indirect effect of a project resulting in adverse effects to wetlands or other surface waters. The District considers those adverse effects that would not occur "but for" the activities that are closely linked and causally related to the activity under review. This standard is discussed further in the Conclusions of Law section of this Recommended Order. The County’s Exhibit 3 is a secondary impact analysis identifying the secondary impacts that may potentially result from the proposed project. These impacts are: 1) the widening of SPW Road; 2) the construction of an FPL substation; 3) the extension of PGA Boulevard; and 4) the potential relocation of a runway at North County Airport. The secondary impact analysis performed pursuant to the Uniform Mitigation Assessment Method (UMAM) contained in Florida Administrative Code Chapter 62-345 reflects that up to 153.3 acres of wetlands may be partially or completely impacted by these secondary impacts, resulting in approximately 71.21 units of functional loss. Where future activities are expected to directly impact wetlands, secondary impacts were assessed based on the loss of all current functional value within the direct footprint of that activity. Additionally, an assessment was conducted to determine the degree of partial functional loss where impacts beyond the footprint of these activities are anticipated. SPW Road is an existing dirt road which is in the County's five-year road plan to widen as a four-lane paved road. Because the widening of the existing dirt road to a four-lane paved road is part of the five-year road plan, the impacts of that widening are not attributable to the subject project. However, as part of the proposed project, it is proposed to widen SPW Road to a six-lane paved road. The additional impacts associated with the widening from four to six lanes will be caused by, and are linked to, the proposed project. These impacts amount to approximately 2.2 acres. The FPL substation, which is proposed to service the proposed project, may result in 1.6 acres of potential direct impacts to wetlands. In addition, 1.0 acre of potential indirect secondary impacts may occur to wetlands that are not going to be dredged and filled. Those indirect secondary impacts may have some adverse impact on the functional value to those wetlands for wildlife utilization. The extension of PGA Boulevard to the Mecca Farms site has the potential to result in 45.6 acres of direct impacts to wetlands and 56.6 acres of indirect secondary wetland impacts which will not be dredged or filled, but will be in close proximity to the road. The secondary impact assessment for PGA Boulevard assumed the incorporation of wildlife crossings to minimize habitat fragmentation. If the airport runway needs to be shifted, potential direct wetland impacts to an additional 22.7 acres may occur. Indirect impacts to 23.6 acres of wetlands in close proximity could also occur. Runway relocation may or may not be necessary due to the PGA Boulevard extension; however, the analysis assumed the need for the relocation. Each of the projects listed above as potential secondary impacts will require a separate construction and operation permit from the District. The issuance of this permit does not in any way guarantee the issuance of permits for any of these identified potential secondary impacts. MITIGATION PLAN The Applicants provided a conceptual mitigation plan using UMAM to demonstrate how potential secondary impacts could be offset. Mitigation options have the potential to provide more than twice the functional gain than the functional loss from the identified secondary impacts. The conceptual mitigation options include: 194 acres of the land that had been acquired for future mitigation needs in Unit 11. 227 acres of the BRP natural area. 32.6 acres in the southern lake wetland along with proposed upland habitat. Sufficient mitigation is available in these options to offset the potential secondary impacts. The mitigation for the four potential secondary impacts is not required to be implemented now because the impacts are not occurring now. Section 4.2.7 of the BOR requires that the District consider those future impacts now and that a conceptual mitigation plan be provided to demonstrate and provide reasonable assurances that those impacts, in fact, can be offset in the future. The Governor and Cabinet sitting as the Board of Trustees considered and approved a request for public easement of approximately 30 acres to use a portion of CWMA for SPW Road, an FPL substation, and the land area that may be needed by District in the future for the connection to the flow-way. As consideration in exchange for the public easement over 30 acres, the County will transfer fee simple title of 60 acres to the State. This public easement also provides a benefit for CERP as it includes the small portion that the District is going to need for its future CERP project to connect to the flow-way on the proposed project site. The Applicants provided reasonable assurances that mitigation will offset secondary impacts to wetlands and other surface waters. UNIDENTIFIED SECONDARY IMPACTS Testimony at the final hearing raised a question as to whether there is nesting or roosting by listed wading bird species in adjacent off-site wetlands outside the eastern boundary of the project site. Evidence was inconclusive on nesting or roosting in these areas. Because the status of adjacent listed wading bird nesting or roosting is uncertain, the District suggested in its Proposed Recommended Order that a special condition requiring a wildlife survey prior to construction near the eastern project boundary be added to the permit as follows: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicant shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. The District represented in its Proposed Recommended Order that the County has no objection to adding the foregoing condition. CUMULATIVE IMPACTS Pursuant to Section 373.414(8), Florida Statutes, the District is required to consider cumulative impacts upon wetlands and other surface waters delineated in Section 373.421(1), Florida Statutes, within the same drainage basin. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. The cumulative impact analysis is geographically based upon the drainage basins described in Figure 4.2.8-1 of the BOR. Cumulative impacts are unacceptable when they would result in unacceptable adverse impacts to the functions of wetlands and surface waters within a drainage basin. There are no wetlands or other surface waters delineated pursuant to Section 373.421(1), Florida Statutes, on the Mecca Farms site. Therefore, no cumulative impacts are created by the direct impacts of the project. Cumulative impacts may be created by a project's secondary impacts. If a wetland impact has been appropriately mitigated on-site within the drainage basin, there is no residual impact, and therefore no cumulative impact. The PGA Boulevard extension, a portion of the SPW Road widening, and the airport runway relocation are located within the C-18 Basin. The proposed mitigation options are all located in the C-18 Basin and will offset those impacts. Those potential secondary impacts are considered to meet the cumulative impact requirements of Section 373.414(8), Florida Statutes. The Applicants provided reasonable assurances that the proposed project will not result in cumulative impacts to the C-18 Basin. The FPL substation is located within the L-8 Drainage Basin. The majority of the SPW Road expansion is located within the C-18 Basin, but a portion is located on the basin line between the C-18 Basin and the L-8 Basin. Because the mitigation for the L-8 impacts are proposed in a different basin, the Applicants were required to conduct a cumulative impact analysis for the L-8 Basin impacts. Based on the Florida Land Use Cover Classification System, there are 43,457 acres of freshwater wetlands within the L-8 Basin. Approximately 41,000 acres of the wetlands in L-8 Basin are in public ownership. This total constitutes approximately 95 percent of all the wetlands in the L-8 Basin. Public ownership of these wetlands provide a high level of assurance that these lands will be protected in perpetuity. The Respondents established that proposed mitigation can fully offset the potential impacts from the SPW Road expansion and the FPL substation and the approximately four acres of impacted wetlands in the L-8 Basin. The Applicants provided reasonable assurances that there are no unacceptable adverse cumulative impacts on the L-8 Basin.4 GROUND WATER FLOWS, SURFACE WATER FLOWS, AND MINIMUM FLOWS AND LEVELS Florida Administrative Code Rule 40E-4.301(1)(g) requires an applicant to provide reasonable assurances that the proposed activity will not adversely impact the maintenance of surface or ground water levels or surface water flows established pursuant to Section 373.042, Florida Statutes. The term "maintenance of surface and groundwater levels or surface water flows" in Florida Administrative Code Rule 40E-4.301(1)(g) means that a project will not adversely impact the maintenance of surface water flows that contribute to meeting the minimum flow for the water body. An adverse impact to the maintenance of surface or groundwater levels or surface water flows may occur when a project discharging to a water body with a designated minimum flow level is proposed to be diverted. An analysis was done to compare the peak discharge rate from the existing SWM system on the Mecca Farms site with the projected peak discharge rate from the proposed SWM system. The analysis showed that the peak discharge rate under the proposed system will be less than that of the existing system. That result was expected since the proposed system will have higher control elevations, which, as noted above, will provide better treatment and permit a better control of the discharge into the C-18 Canal. Under the existing SWM system, storm event water in a dry period is frequently stored in the existing impoundment for future irrigation purposes. Under the proposed SWM system such storm event water will be discharged downstream, which will benefit those downstream areas during dry periods. The proposed system will also provide better control over pulse discharges during heavy storm events. The Applicants provided reasonable assurances that the proposed activities will not adversely impact the maintenance of surface or ground levels or surface water flows as required by Florida Administrative Code Rule 40E-4.301(1)(g). THE DISTRICT’S OBJECTIVES Sections 373.414 and 373.416, Florida Statutes, require an applicant to provide reasonable assurances that a regulated activity will not be harmful to the water resources and will not be inconsistent with the overall objectives of the District. Congress initially authorized the Central and Southern Florida (“C&SF”) Project in 1948. Thereafter extensive work was undertaken pertaining to flood control; water supply for municipal, industrial, and agricultural uses; prevention of saltwater intrusion; and protection of fish and wildlife. The work included construction of a primary system of 1000 miles each of levees and canals, 150 water-control structures, and 16 major pump stations. Unintended consequences of the C&SF Project have included the irreversible loss of vast areas of wetlands, including half of the original Everglades; the alteration in the water storage, timing, and flow capacities of natural drainage systems; and the degradation of water quality and habitat due to over-drainage or extreme fluctuations in the timing and delivery of fresh water into the coastal wetlands and estuaries. In 1992, Congress authorized the C&SF Project Comprehensive Review Study, which is generally referred to as the “Restudy.” The objective of the Restudy was to reexamine the C&SF Project to determine the feasibility of modifying the project to restore the South Florida ecosystem and provide for the other water-related needs of the region, such as water supply and flood protection. In April 1999, the U.S. Army Corps of Engineers issued the Central and Southern Florida Project Comprehensive Review Study Final Integrated Feasibility Report and Programmatic Environmental Impact Statement (“Restudy Report”). The Restudy Report recommends a comprehensive plan for the restoration, protection, and preservation of the water resources of Central and South Florida. The resulting plan is known as CERP. The North Palm Beach County Part I project, which includes restoration of the Northwest Fork of the Loxahatchee River (“NWFLR”), is a component of CERP. The successful completion of CERP and the successful restoration of the NWFLR are high-priority objectives of the District. The Loxahatchee River is an important feature of the South Florida ecosystem, nationally and internationally unique, and an important natural and economic resource. Rules pertaining to MFL for the NWFLR and for the recovery of the NWFLR are found at Florida Administrative Code Rule 40E-8.011; 40E-8.221(4); and 40E-8.421. Recovery goals, which are not presently being met, have been established; and strategies to meet those goals have been identified. The Mecca Farms site is located within the boundaries of the CERP North Palm Beach County Part I project and has the potential to affect CERP and the restoration of the NWFLR. Projects that potentially would affect or would be within or adjacent to a CERP project are evaluated on a case-by- case basis to determine whether a proposed project would not be inconsistent with CERP and other District objectives. There was a dispute between Respondents and Petitioners as to whether the proposed project was inconsistent with the District’s objectives, including CERP and its goals pertaining to the restoration of the NWFLR. Petitioners contend that the District has insufficient evidence that the Mecca Farms will not be needed for the construction of a reservoir. That contention is rejected. The greater weight of the credible evidence established that sufficient storage is available at a superior site known as the Palm Beach Aggregates (PBA) site in the L-8 Basin, which is a unique geological site that will provide in-ground storage of water.5 Water from the PBA storage site can be conveyed to the NWFLR to increase dry season flows. Water can be stored at the PBA site in the wet season to prevent potentially damaging high flows. The L-8 Basin, which is adjacent to the C-18 Basin, receives more water during the wet season than it uses. This means that at present a significant amount of water must be discharged to tide (lost) during the wet season to provide for flood protection in this area. As envisioned, the water currently lost to tide could be stored at the PBA site for use during the dry season. By combining the water storage in the L-8 Basin with connective flow-ways to the C-18 Canal, water demands within the C-18 Basin, including the NWFLR, can also be met by the PBA storage site.6 An increase in freshwater flows to the NWFLR will further the District’s restoration goals for the NWFLR. Storage at PBA has regional benefits for other significant natural areas because it will provide additional flows to the Loxahatchee Slough and Grassy Waters Preserve. Those additional flows will further the District’s CERP goals. Since October of 2003, County staff and the District’s ERP staff have coordinated review of the subject project with the District’s CERP Planning and Federal Projects Division and other District staff working on projects in this region. The County asked the District to determine if the Mecca Farms’ site could in some way accommodate CERP objectives, and three alternatives were considered: 1) no action; 2) a reservoir; and 3) a flow-way. As opposed to a reservoir, the more valuable and the more practical, use of the Mecca Farms site would be as part of the system to convey the stored water to the areas that would most benefit from its discharge. The proposed flow-way in the BRP Natural Area would be an integral part of that conveyance system and would provide the District with greater flexibility in managing and directing the discharge of the water stored at the PBA site. Prior to the development of the flow-way concept as part of the proposed development, CERP identified a single route to take water from PBA to the NWFLR. The flow-way will provide an additional route from PBA to the NWFLR. That additional route will provide the District with greater operational flexibility. The flow-way will complement the L-8 Basin flow- way and help reduce peak flows to the NWFLR and the Estuary. The flow-way also provides a potential route allowing excess water to be brought back from the C-18 Basin to the PBA site for storage. There are no other potential routes that allow water to be directed from the C-18 Basin in the wet season to the PBA site. The flow-way provides a feature that was not part of the CERP original plan and is therefore an unanticipated benefit for CERP. The Applicants provided reasonable assurances that the proposed project is not inconsistent with the District’s objectives.7

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that the District issue the subject ERP for the conceptual approval of the SWM system for the BRP and the Phase 1A construction and operation subject to the general and special conditions set forth in the Staff Report and the Amended Staff Report. It is further RECOMMENDED that the District add the following special condition: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicants shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. DONE AND ENTERED this 3rd day of December, 2004, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 3rd day of December, 2004.

Florida Laws (9) 120.569120.57120.574267.061373.042373.414373.416373.421403.973
# 3
SOUTH FLORIDA WATER MANAGEMENT DISTRICT vs. GABLES ENGINEERING, INC., 86-003691 (1986)
Division of Administrative Hearings, Florida Number: 86-003691 Latest Update: Sep. 18, 1987

The Issue The issue presented for decision herein is whether or not Respondent, Gables Engineering, is required to obtain a surface water management permit for its property known as the G-Bar-E Ranch in Okeechobee County, Florida.

Findings Of Fact Upon consideration of the witnesses and their demeanor while testifying and documentary evidence received, the following relevant facts are found: The South Florida Water Management District (District) is a public corporation of the State of Florida existing by virtue of Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, Florida Statutes, and Chapter 40E, Florida Administrative Code as a multipurpose water management district with its principal office in West Palm Beach, Florida. Cables Engineering, Inc., owns property known as the G- Bar-E Ranch which is located in Okeechobee County, Florida. The property is located at the confluence of Otter Creek and Taylor Creek. Otter Creek flows into Taylor Creek which flows offsite into Lake Okeechobee. On August 28, 1986, the District issued an Administrative Complaint and Order which ordered Gables to obtain a surface water management permit pursuant to Chapter 373, Part IV, Florida Statutes for the surface water management system on the G-Bar-E Ranch. Gables refused and requested an administrative hearing on the Complaint and Order. Don Dillard is a Vice President of Gables and has overall responsibility for operating the Ranch. He has been employed by Gables for nine years. Gables has in its employ a ranch manager who remains on site. Until recently, Gables operated the property as a cattle ranch. A portion of its herd was sold to a former ranch manager who also remains on site. Alvin Castro is a civil engineer employed by the District as an area engineer which includes the area of Okeechobee County. Mr. Castro conducted a site inspection on the G-Bar-E Ranch on January 6, 1987. The inspection documented that there are two pond systems on the subject property and eleven hydraulic connections from the subject property to Otter Creek and Taylor Creek. One pond system, identified as pond system No. 2, is located in the mid-western area of the ranch east of Taylor Creek. It consists of three main ponds which are interconnected in a chain with hydraulic control structures and outfall ditches. The ponds were at one time natural ponds but have been deepened and improved to provide a water source for cattle and to store and convey water. A water control structure is located at the western end of each of the three ponds. The structures are aligned and installed to convey water from the upstream ponds to the downstream ponds. The control structures are culvert riser type. A culvert is a man-made conduit that conveys water to a point and allows it to flow. A riser is a half-section of a culvert or pipe welded perpendicular to the outfall culvert. Its main function is to serve as a support structure for weirs or flashboards, which regulate the upstream stages in a ditch. It allows water, as its flows over the spillway or weir, to be collected and directed to the outfall pipe or culvert. Mr. Castro observed water flowing, at the time of inspection, through all three outfall ditches to the south and westward from the pond system to a hammock area. The ponds have been cleaned of vegetation and the culverts and risers have been maintained by Respondent. One culvert riser structure conveys water from Pond 1 to Pond 2 which consist of a 96-inch riser and a 60-inch culvert, approximately 50 to 60 feet long. At the time of the inspection, water was being discharged through the control structure to an outfall ditch that connects Pond 1 to Pond 2. The outfall ditch is a man-made ditch. A second control structure connects Pond 2 to Pond 3 and interconnecting ditches consisting of a 96-inch ditch riser with a 60-inch culvert in place to hydraulically connect Ponds 2 and 3. The control structure allows water to flow underneath a private road to Pond 3. Mr. Castro observed water flowing from Pond 2 to Pond 3 at the time of his inspection. In the absence of the culvert, the pond system would run together as a large pond. The culverts alter the natural water storage capacity and drainage arrangement on the G-Bar-E Ranch. The third controlled structure is located on the southwest end of Pond It consists of a 96-inch riser on a 60-inch culvert and a sheet pile weir. At the time of his inspection, Castro observed that there was flow of water from the control structure and Pond 3 through the outfall ditch to a hammock wetland area to the southwest. (Petitioner's Exhibit 3, photos 1-6). The other pond systems, identified as pond system 1, is located in the northern portion of the property near the east bank of Taylor Creek. It consists of three main ponds ranging in size of one to five acres. One pond is connected to an outfall ditch to the southwest through a twenty-four inch culvert which runs underneath an existing grass road. At the time of Mr. Castro's inspection, it was conveying water from the pond westward into a vegetated area. The other two ponds are connected to each other via a 12-inch culvert underneath an existing grass road. The ditch is about three to five feet wide. At the time of Mr. Castro's inspection, there was flow of water between the two ponds. The downstream pond has an open connection (no control structure) to a ditch, which ultimately discharges to Taylor Creek. At the time of the inspection, water flow was observed (by Castro) in the ditch and was being discharged from pond 6 to Taylor Creek. (Petitioner's Exhibit 3, photos 11-14) The ditches in the pond system are prismatic; fairly uniform in cross section top width, depth and bottom width, with a straight alignment which indicates that they are man-made. The pond system is well-maintained by Respondent and free of vegetation. (TR, 21). There are four ditch structural connections from the G- Bar-E Ranch to Otter Creek. The easternmost structure consists of a 24-inch riser with a 15- inch culvert. It serves to convey stormwater from an upstream ditch system on the G-Bar-E property to Otter Creek and thereafter, offsite. There was flow to the structure to Otter Creek at the time of Mr. Castro's inspection. (Petitioner's Exhibit 3, photo 7). The second structure is located westward from the first. It consists of a 20-inch riser and a 13-inch culvert. (Petitioner's Exhibit 3, photo 8). The third structure is located westward from the second. It consists of a 32-inch riser and a 16-inch culvert. Discharge of water from the G-Bar-E property to Otter Creek through the third structure was observed by Mr. Castro during his inspection. (Petitioner's Exhibit 3, photo 9). The fourth structure is located westward from the third, consisting of a 36-inch riser and a 24-inch culvert. (Petitioner's Exhibit 3, photo 10). There are several manmade hydraulic connections to Taylor Creek on the G-Bar-E Ranch. On the eastbank of the Creek, the northernmost, identified as Ditch A, is a straight channel. At the time of Mr. Castro's inspection, it was discharging water from the G-Bar-E property to Taylor Creek by means of a 36- inch riser and a 30-inch culvert. The discharge served to drain the G-Bar-E property. (Petitioner's Exhibit 3, photos 15-16). The next ditch south is a prismatic channel with a straight alignment and uniform cross section, connected to Taylor Creek by a 46-inch riser and a 36-inch culvert. At the time of Mr. Castro's inspection, it was discharging water from the G-Bar E property to Taylor Creek. (Petitioner's Exhibit 3, photos 19-22). The headwaters of the ditch is a hammock wetland area at its upstream reach. (Petitioner's Exhibit 3, photos 19-22). The next ditch south is connected to Taylor Creek via a hydraulic control structure consisting of a 42-inch riser and a 30-inch culvert. The structure has at least one flashboard, which is a temporary barrier affixed to the slots on the riser and used to hold and regulate upstream water levels and to increase or decrease the storage capacity. (Petitioner's Exhibit 3, photos 24-25) The ditch drains a hammock area in the interior of the G-Bar-E property which lies to the northeast. It controls water from the upper end of the G-Bar-E property. On the westbank of Taylor Creek, the northernmost connection is an open connection to Taylor Creek. (Petitioner's Exhibit 2, sheet 1; Petitioner's Exhibit 2, photo 17). South of that connection is another ditch with an open connection to Taylor Creek. To the South is another open channel connection to Taylor Creek which has a non-functional control structure at the downstream end. (Petitioner's Exhibit 3, photo 23). The existing system of ponds and ditches on the G-Bar-E Ranch will collect, convey and can regulate upstream storage and flow rates to Taylor Creek and Otter Creek. In 1963 Gables conveyed to Okeechobee County a permanent easement along Taylor Creek. The Taylor Creek easement runs through the G-Bar-E property, roughly from the northeast corner to the southeasternmost corner. The easement to Okeechobee County covers about 150 feet on each side of Taylor Creek through the property. The purpose of the easement, as stated on the face of the document, is for the construction necessary to improve the Taylor Creek channel including widening, deepening, straightening, spoil placement and spoil disposition, installation of drip and pipe drop spillways; for operation and maintenance of the channel; and for the flowage of water through the channel, spillways, and pipe drop spillways. The grantor (Gables) reserved the right to use the easement land at any time, in any manner and for any purpose not inconsistent with the full use and enjoyment thereof by Okeechobee County. A small portion of the ditches on the G-Bar-E Ranch which connect to Taylor Creek and the control structures in those ditches lie within the area covered by the easement granted to Okeechobee County (approximately 150 feet). However, the major portion of the ditches all lie outside the easement granted to Okeechobee County. (TR 63-64; Respondent's Exhibit 4). The ditches serve to drain the G-Bar-E property into Taylor Creek and benefit the G-Bar-E Ranch property. This use is consistent with and permitted by the county's easement. The ditches and structures serve the purpose of draining the property and facilitating the flow of water to Taylor Creek. Mr. Dillard testified that Gables Engineering has not constructed, repaired or maintained any of the ditches during his nine year tenure with the company. (TR 67). However, no evidence was presented to indicate that the ditches or structures were constructed by Okeechobee County pursuant to the easement or that they benefit Okeechobee County rather than Respondent. In 1966 and 1967, Respondent granted to Okeechobee County a permanent easement along Otter Creek and Bimeny canal, which run roughly from east to west near the northern boundary of the property. The easement is for construction necessary to improve Otter and Bimeny Creek including widening, deepening, straightening, spoil placement and disposition, installation of drop and pipe drop spillways; for operation and maintenance of the channel and the flow of water to the channel, spillways and pipe drop spillways. Gables Engineering, Inc. reserved the right to install pipe drop inlets, retain, impound and regulate the flow of water into Otter Creek and Bimeny Canal lying within the Grantor's land, provided they are installed in conformance with sound engineering practice. Respondent reserved the right to use the easement property at any time and for any purpose not inconsistent with its use by Okeechobee County. (Respondent's Exhibit 2). Four control structures lie within the easement area along Otter Creek and Bimeny Canal. A small portion of the ditches from the G-Bar-E Ranch property leading to the control structure lie within the easement area. There is no record evidence to establish that the control structure, which facilitates the flow of water to Otter Creek and Bimeny Canal, is maintained by Okeechobee County or in any way serve the purposes of the easement to Okeechobee County. It is unclear who actually constructed the structures. The structures serve to convey water from the G-Bar-E property to Otter Creek. (Petitioner's Exhibit 3, photos 7 and 9). This appears consistent with and expressly permitted by the easement granted to Okeechobee County. In 1964 Gables Engineering granted Okeechobee County a bridge and access road easement which consists of an existing graded road forty feet in width running from State Road 15 to the west boundary of Taylor Creek. The easement is for purposes in conjunction with the construction, maintenance and operation of an access road and bridge across Taylor Creek. The access road and bridge across Taylor Creek do not presently exist. The road easement crosses over a culvert between two of the ponds in pond system 2. However the pond system itself, including the outfall structure and ditch at the western end of the system, lie outside the easement. The easement also crosses a culvert in pond system 1, but the remainder of the pond system lie outside the easement. (TR 63-64). The ponds, control structures and ditches on the G-Bar- E Ranch serve to drain the property internally and to Otter Creek and Taylor Creek. One pond system drains water into a hammock area to the southwest. This system consist of three ponds with control structures between each pond and an outfall ditch at the southwestern end of the system. The other pond system drains water to wetland areas and to Taylor Creek. It consists of three ponds, control structures and outfall ditches to a wetland area and to a ditch leading to Taylor Creek. While Respondent maintains that the culverts were installed for the purpose of allowing vehicular access between the southern and northern areas of the Ranch, the credible evidence reveals that the control structures primary purpose is to drain the property and control the flow of water throughout the system.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Petitioner, South Florida Water Management District enter a Final Order requiring Respondent, Gables Engineering, to file an application to obtain a surface water management permit to operate works on the G Bar-E Ranch pursuant to Chapter 373, Part IV, Florida Statutes and that an initial application be submitted to obtain a surface water management permit within 30 days of the entry of the Final Order in this case. RECOMMENDED this 18th day of September, 1987, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of September, 1987. COPIES FURNISHED: Sarah Nall, Esquire South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33402 Robert W. Stewart, Esquire Corrigan, Zelman & Bander, P.A. Rivergate Plaza, Suite 200 444 Brickell Avenue Miami, Florida 33131

Florida Laws (8) 120.57373.019373.403373.406373.416373.616373.6161403.031 Florida Administrative Code (2) 40E-4.02140E-4.041
# 4
FLORIDA AUDUBON SOCIETY, FLORIDA KEYS AUDUBON SOCIETY, AND UPPER KEYS CITIZENS ASSOCIATION vs WILLIAM R. CULLEN AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-003779 (1989)
Division of Administrative Hearings, Florida Filed:Key Largo, Florida Jul. 14, 1989 Number: 89-003779 Latest Update: Aug. 22, 1990

The Issue The central issue in this case is whether the Department of Environmental Regulation (Department) should grant a dredge and fill permit which has been requested by the Respondent, William R. Cullen (Applicant). That proposed permit has been opposed by the Petitioners (who will be referred to collectively as Petitioners for convenience sake).

Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received, the following findings of fact are made: The Department is the state agency authorized to issue permits pursuant to Chapter 403, Florida Statutes. The Respondent, William R. Cullen, filed an application for a dredge and fill permit to construct a slip marina on June 4, 1985. The original request was subsequently amended to seek approval for a forty-two slip commercial marina. The project site for the Applicant's marina is located at Key Largo, Monroe County, Florida. The site is within Buttonwood Sound, Florida Bay. The property is owned by Mr. Cullen and his family. All of the proposed improvements will be constructed on submerged lands or uplands owned or controlled by the Cullen family. The project site is located within a commercial area of Key Largo and contains frontage on both the water, Buttonwood Sound, and the highway, U.S. Highway 1. The project site has a basin which was created by the excavation of materials used for road construction from the shoreline and the installation of an L-shaped rock jetty which runs roughly perpendicular and then parallel to the shoreline. This jetty was installed during the late 1960s. The water depths within the basin range from 3 feet to approximately 14 feet. The water within the basin is subject to the same tidal considerations as the waters within Buttonwood Sound. There is no interruption of the flow of water in and out of the basin from those waters of the Sound. The water within this basin is within an Outstanding Florida Water as defined in Rule 17-3.041, Florida Administrative Code. The Applicant's plan calls for the excavation of appproximately 30,170 square feet of upland area and the dredging of the existing basin for approximately 18,460 dredged square feet. During the construction phases, the Applicant proposes to install turbidity curtains to limit the adverse effects expected during that time. The improvements are intended to be a permanent alteration to the basin design and will permanently modify the marine life habitat within that basin. The Applicant proposes to remove portions of the existing jetty to allow additional water to flow through the basin unimpeded by the jetty walls. The removal of the jetty walls will expedite the dilution and flushing of potential pollutants from the basin on a tidal frequency. That flushing is purported to assure that the water quality within the basin will not be diminished. However, such pollutants will be flushed into Buttonwood Sound. Stormwater accumulating on the upland project is to flow toward a lower upland area and should not to be dumped into the basin. The proposed marina is to have fueling facilities and the Applicant has agreed to design that system to limit inadvertent spillage. Further, as a condition of the permit, the Applicant has agreed to abide by the Department of Natural Resources' spill contingency plan requirements. The proposed marina is designed to provide portable sewage pumpout facilities for each slip. A permanent pumpout facilities will also be available. The Applicant seeks to attract boats in the range of 30 to 50 feet in length at this facility. While there are a number of other marinas in other areas of Key Largo which might accomodate that size boat, the marinas in the immediate vicinity of this project site are designed for smaller craft. The area within the basin consists of unvegetated bottom, submerged rip-rap, sea grasses, and hardbottom/algae communities--the predominant classifications being the latter two. The deeper hardbottom areas are to be filled and portions of the sea grasses will be dredged in order to configure the proposed docks. Additionally, other sea grass areas will be shaded, and thereby disturbed, by the construction of the docks. There are no historical or archaeological features relevant to the proposed site. The area has not been designated as a critical manatee area, however, manatees do frequent the project vicinity and have been observed feeding immediately adjacent to the basin. The permit proposed for this project requires a water quality monitoring plan. In addition to sampling for coliform, diesel by-products, oils, greases, detergents, oxygen, copper, lead and zinc, the plan requires sampling for aluminum, cadmium, and chromium. The monitoring stations are to be located both within the basin (2 stations) and outside the basin (2 stations). Liveaboards or others continuously docked at the marina will create additional shading which will disrupt and adversely affect the sea grass system. In order to provide access to the marina, the Applicant intends to dredge a channel in an area containing sea grass which is undisputedly within the Outstanding Florida Waters. The Department deemed the subject application was complete on February 23, 1988. The Department did not apply the Keys Rule found in Rule 17-312.400, Florida Administrative Code, to this project. The Department also did not apply the Mitigation Rule found in Rule 17-312.300, Florida Administrative Code, to this project. Michael Dentzau has personally reviewed and processed 250-300 dredge and fill permits during his tenure with the Department. Of those projects he has reviewed, he has not recommended that dense sea grass beds of the type located within this project site be dredged in order to construct a commercial marina. Phillip Edwards was responsible for executing the Intent to Issue in this case. In determining that this project had provided reasonable assurances that water quality standards will not be violated, Mr. Edwards weighed the public interests criteria set forth in Section 403.918, Florida Statutes. Because he received letters purportedly from elected officials, Mr. Edwards presumed that the project was in the public interest. That assumption of fact has not been established by this record. According to Mr. Edwards, the adverse effects expected by this project could be adequately addressed by the permit conditions when weighed against the public interest in favor of the project. Since Mr. Edwards' assumptions as to the public interest in this project have not been established, his conclusion regarding the weight that interest should receive can be given little consideration. The project as proposed by the Applicant will not adversely affect navigation or cause harmful erosion or shoaling. The project as proposed by the Applicant will adversely affect fishing or marine productivity within the basin since it will permanently alter the basin biologically by destroying sea grass. The increased boat traffic within the Sound will also detract from the present recreational uses enjoyed by area residents. According to Mr. Edwards, it is very unusual for the Department to issue a permit when sea grasses will be adversely affected. In the 17 years in which he has reviewed permits, only two occasions merited approval when the destruction of sea grasses to the extent in this case would result. Neither of those cases were factually similar to the case at issue. In those cases, however, elected officials advised Mr. Edwards, as he presumed they had here, that there was a public need for the permit. Increased boat traffic will result in increased manatee mortality due to collisions. In order to assure water quality will not be degraded within a marina, the project should have a short flushing time comparable to healthy natural embayments. In this case, the flushing proposed by the Applicant is dependent, in part, on winds which may be inconsistent or relatively minimal during the summer months.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Department of Environmental Regulation enter a final order denying the permit requested by the Applicant. DONE and ENTERED this 22nd day of August, 1990, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings 1230 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1990. APPENDIX TO CASE NOS. 89-3779 et seq. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY PETITIONERS: The first three sentences of paragraph 1 are accepted; the remainder is rejected as argument or irrelevant. Paragraph 2 is accepted. Paragraph 3 is accepted. With regard to paragraph 4, it is accepted that the Department deemed the application complete on February 23, 1988; otherwise, the paragraph is rejected as argument. With regard to paragraph 5, it is accepted that the habitat within the basin is the same as the habitat throughout Florida Bay and that the basin is not "enclosed" hydrologically; otherwise, the paragraph is rejected as argument or comment. Paragraphs 6, 7, 8, 9, 10, 11, and 12 are rejected as argument, conclusions of law, or comment. The paragraphs do not recite facts pertinent to this case. Paragraphs 13, 14, and the first two sentences of paragraph 15 are accepted. The remainder of paragraph IS is rejected as argument. The first two sentences of paragraph 16 are accepted. The remainder of the paragraph is rejected as comment or argument. Paragraph 17 is accepted. Paragraph 18 is rejected as argument. To the extent that paragraph 19 accurately describes Van de Kreeke's assessment of the report it is accepted; otherwise rejected as irrelevant, comment, argument, recitation of testimony or unsupported by the record. The report upon which comment is directed was not offered in this cause to prove its truth/accuracy. Paragraphs 20 through 22 are rejected as comment, argument, recitation of testimony or unsupported by the record-- see comment to paragraph 19 above. Paragraphs 23 through 26 are accepted. Paragraphs 27 and 28 are rejected as argument, comment, or contrary to the weight of the evidence. Paragraphs 29 and 30 are accepted. Paragraph 31 is rejected as argument or contrary to the weight of the evidence. Paragraphs 32 and 33 are accepted. Paragraph 34 is rejected as hearsay, irrelevant, or argument. Paragraph 35 is rejected as comment or argument. Paragraph 36 is accepted. Paragraphs 37 through 40 are rejected as argument or contrary to the weight of the evidence. Paragraphs 41 through 43 are accepted. Paragraph 44 is rejected as contrary to the record. Paragraph 45 is rejected as argument. Paragraph 46 is rejected as argument or contrary to the weight of the evidence. Paragraph 47 is accepted but is comment. Paragraphs 48 and 49 are accepted. Paragraph 50 is rejected as repetitive. Paragraph 51 is rejected as argument or conclusions of law. The first three sentences of paragraph 52 are accepted. The remainder of the paragraph is rejected as argument. The first sentence and that portion of the second sentence of paragraph 53 that ends with the word "authenticity" is accepted. The remainder of the paragraph is rejected as argument or conclusions of law. Paragraphs 54 and 55 are accepted. Paragraph 56 is rejected as irrelevant or hearsay. Paragraph 57 is rejected as hearsay. Paragraph 58 is rejected as argument, comment, or irrelevant. Paragraphs 59 through 66 are accepted. Paragraph 67 is rejected as contrary to the weight of the evidence. Paragraph 68 is rejected as contrary to the weight of the evidence. Paragraphs 69 and 70 are accepted. Paragraph 71 is rejected as repetitive. Paragraph 72 is rejected as argument. The first sentence of paragraph 73 is accepted; the remainder is rejected as contrary to the weight of the evidence. Paragraph 74 is accepted. Paragraphs 75 through 77 are rejected as contrary to the weight of the evidence. Paragraphs 78 and 79 are accepted. Paragraph 80 is rejected as repetitive. With the inclusion of the words "and hardbottom and algae" paragraph 81 is accepted. Paragraph 82 is accepted. Paragraph 83 is accepted. Paragraph 84 is rejected as contrary to the weight of the evidence. 5l. Paragraphs 85 through 89 are accepted. With the substitution of the word "not" for the word "ever" in the last sentence of paragraph 90, it is accepted. Paragraphs 91 through 94 are accepted. Paragraph 95 is rejected as not supported by the record or contrary to the weight of the evidence. Paragraphs 96 through 100 are accepted. Paragraph 101 is rejected as repetitive. Paragraphs 102 through 106 are rejected as argument, comment, or irrelevant. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE DEPARTMENT: Paragraph 1 is accepted. Paragraph 2 is rejected as contrary to the weight of the credible evidence. The waters within the basin are of the same origin as they were prior to the creation of the jetty; no artificial body of water was created. With regard to paragraph 3 it is accepted that the jetty was constructed in the late 1960s. Paragraph 4 is accepted. With regard to paragraph 5 it is accepted that that is the applicants proposal no conclusion as to the likelihood of that is reached. Paragraph 5 is accepted. Paragraph 6 is accepted. Inevitably, however, spills will occur and must be considered as an adverse affect of the project. Paragraph 7 is accepted. Paragraph 8 is rejected as unsupported by competent evidence or contrary to the weight of the evidence presented. Paragraph 9 is rejected as contrary to the weight of the evidence. Paragraph 10 is accepted. Paragraph 11 is accepted but is inadequate to offset the adverse affects to manatees. Paragraph 12 is accepted but is inadequate to limit the adverse affects to sea grass. Paragraph 13 is rejected as contrary to the weight of the evidence. Paragraph 14 is rejected as contrary to the weight of the evidence. Paragraph 15 is accepted. Paragraph 16 is accepted. Paragraphs 17 and 18 are accepted. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE APPLICANT: Paragraphs 1 through the first sentence of paragraph 6 are accepted. The second sentence of paragraph 6 is rejected as contrary to the weight of the evidence. Paragraphs 7 through Il are accepted. Paragraph 12 is rejected as irrelevant. Paragraphs 13 through the first sentence of paragraph 17 are accepted. The remainder of paragraph 17 is rejected as contrary to the weight of the evidence. Paragraph 18 is accepted. Paragraph 19 is rejected as unsupported by the record or contrary to the weight of the evidence. Paragraph 20 is accepted. Paragraphs 21 through 26 are rejected as contrary to the weight of the evidence. Paragraph 27 is rejected as contrary to the weight of the evidence or unsupported by competent evidence. The first sentence of paragraph 28 is accepted, the remainder rejected as speculative, comment, or unsupported by the record. The first sentence of paragraph 29 is accepted, the remainder rejected as contrary to the weight of the evidence. Paragraph 30 is accepted. Paragraph 31 is rejected as contrary to the weight of the evidence. Paragraph 32 is rejected as contrary to the weight of the evidence. Paragraph 33 is accepted but is irrelevant. Paragraph 34 is rejected as contrary to the weight of the evidence. Paragraph 35 is accepted; however, sea grasses not disturbed by dredging will still suffer adverse affects from shading and silting. Paragraph 36 is accepted but see comment to paragraph 35 above. Paragraph 37 is accepted. Paragraph 38 is accepted. Paragraph 39 is accepted but is irrelevant. Paragraph 40 is accepted. Paragraph 41 is accepted. Paragraph 42 is accepted. Paragraph 43 is rejected as irrelevant. Paragraph 44 is rejected as contrary to the weight of the evidence. Paragraph 45 is accepted but it should be noted that is not the extent of the proposal. Paragraph 46 is rejected as contrary to the weight of the evidence. Paragraph 47 is accepted. Paragraph 48 is rejected as contrary to the weight of the evidence. Paragraph 49 is rejected as contrary to the weight of the evidence. COPIES FURNISHED: Pamela Presnell Garvin Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Charles Lee Florida Audubon Society 1101 Audubon Way Maitland, Florida 32751 Robert Routa P.O. Box 6506 Tallahassee, Florida 32314-6506 Linda McMullen McFARLAIN, STERNSTEIN, WILEY & CASSEDY, P.A. 600 First Florida Bank Building Tallahassee, Florida 32301 Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 =================================================================

Florida Laws (2) 120.68267.061
# 5
CITIZENS FOR SMART GROWTH, KATHIE SMITH, AND ODIAS SMITH vs DEPARTMENT OF TRANSPORTATION, MARTIN COUNTY BOARD OF COUNTY COMMISSIONERS, AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 10-003317 (2010)
Division of Administrative Hearings, Florida Filed:Stuart, Florida Jun. 16, 2010 Number: 10-003317 Latest Update: Feb. 14, 2011

The Issue The issues are whether to (a) issue an Environmental Resource Permit (ERP) to the Department of Transportation (DOT) and Martin County (County) authorizing construction and operation of a surface water management system to serve a project known as the Indian Street Bridge; (b) issue DOT a letter of modification of ERP No. 43-00785-S authorizing roadway and drainage modifications to the Kanner Highway/Indian Street intersection; and (c) issue DOT a letter of modification of ERP No. 43-01229-P authorizing roadway and drainage modifications to Indian Street between the intersections of Kanner Highway and Willoughby Boulevard.

Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: The Parties Petitioner Citizens for Smart Growth, Inc., is a Florida 501(c)(3) corporation with its principal place of business in Palm City, Florida. It was formed by Odias Smith in August 2001, who serves as its president. The original directors were Kathie Smith, Odias Smith, and Craig Smith, who is the Smiths' son. The composition of the Board has never changed. According to the original Articles of Incorporation, its objectives are "preserving and enhancing the present advantages of living in Martin County (Quality of Life) for the common good, through public education, and the encouragement of reasonable and considered decision making by full disclosure of impacts and alternatives for the most appropriate use of land, water and resources." The exact number of members fluctuates from time to time. There are no dues paid by any member. At his deposition, Mr. Smith stated that no membership list exists; however, Kathie Smith stated that she currently has a list of 125 names, consisting of persons who at one time or another have made a contribution, have attended a meeting, or asked to be "kept informed of what's going on or asked to be on a mailing list or a telephone list, so they could be advised when we have meetings." No meetings have been held since 2006. Therefore, the Petitions filed in these cases have never been discussed at any meetings of the members, although Ms. Smith indicated that telephone discussions periodically occur with various individuals. Kathie Smith believes that roughly 25 percent of the members reside in a mobile home park north of the project site on Kanner Highway on the eastern side of the St. Lucie River, she does not know how many members reside on the western side of the St. Lucie River, and she is unaware of any member who resides on the South Fork of the St. Lucie River immediately adjacent to the project. Although the three Petitions allege that "seventy percent of the members . . . reside and/or recreate on the St. Lucie River," and in greater detail they allege how those members use that water body or depend on it for their livelihood, no evidence was submitted to support these allegations that 70 percent (or any other percentage of members) use or depend on the South Fork of the St. Lucie River for recreational or other activities. Petitioners Odias Smith and Cathie Smith reside in Palm City, an unincorporated community just south of Stuart in Martin County. They have opposed the construction of the new bridge since they moved to Palm City in 2001. It is fair to infer that Mr. Smith formed the corporation primarily for the purpose of opposing the bridge. Their home faces north, overlooking the South Fork of the St. Lucie River, from which it is separated by Saint Lucie Shores Drive and a narrow strip of common-ownership property. A boat dock extends from the common-ownership property into the St. Lucie River, providing 5 slips for use by the Smiths and other co-owners. The home is located three blocks or approximately 1,000 feet from the proposed western landfall of the new bridge. Due to the direction that the house faces (north) and the site of the new bridge, the surface water management system elements associated with the bridge will not be visible from their property. Mr. Smith believes, however, that when looking south through a veranda window on the second floor of his home, he will be able to see at least a part of the new bridge. From the front of their house, they now have an unobstructed view of the existing Palm City Bridge, a large structure that crosses the St. Lucie River approximately six- tenths of a mile north of their home, and which is similar in size to the new bridge now being proposed by the Applicants. The Smiths' home is more than 500 feet from the Project's right- of-way, and they do not know of any impact on its value caused by the Project. While the Smiths currently engage in walking, boating, running, fishing, and watching wildlife in the neighborhood or the South Fork of the St. Lucie River, there was no credible evidence that the Project would prevent them from doing so after the bridge and other improvements are constructed. Also, there was no evidence showing that the ERP Letter Modifications will cause them to suffer any adverse impacts. In fact, as noted below, by DOT undertaking the Project, the neighborhood will be improved through reduced flooding, improved water quality, and new swales and ponds. The County is a political subdivision of the State. It filed one of the applications at issue in this proceeding. DOT is an agency of the State and filed the three applications being contested. The District has the power and duty to exercise regulatory jurisdiction over the administration and enforcement of ERP criteria pursuant to Part IV, Chapter 373, Florida Statutes, and Title 40E of the Florida Administrative Code. The Department of Environment Protection (DEP) has delegated certain authority to the District, including the authority to authorize an applicant to use sovereign submerged lands via a public easement within the District's geographic jurisdiction. The Project Construction of a new bridge over the St. Lucie River has been studied extensively by the Applicants for over twenty years. DOT has awarded the contract and nearly all of the right-of-way has been purchased. The Project will begin as soon as the remaining permits are acquired. The Project is fully funded through the American Recovery and Reinvestment Act of 2009 and County funding. The Project is located in the County and includes 62.06 acres of roadway bridge development and 12.45 acres of sovereign submerged lands. The Project begins on the west side of the St. Lucie River on County Road 714, approximately 1,300 feet west of Mapp Road in Palm City and ends on the east side of the St. Lucie River approximately 1,400 feet east of Kanner Highway (State Road 76) on Indian Street. It includes construction and operation of a surface water management system to serve the road and bridge project. The total length of the Project is approximately 1.96 miles (1.38 miles of roadway and 0.58 miles of bridge) while the total area is approximately 74.51 acres. After treatment, surface water runoff will discharge to the tidal South Fork of the St. Lucie River. The Project encompasses a bridge crossing the South Fork of the St. Lucie River and the Okeechobee Waterway. Both are classified as Class III waters. The bridge transitions from 4 to 6 lanes east of the Okeechobee Waterway and will require a 55-foot vertical clearance and a 200-foot horizontal clearance between the fender systems at the Okeechobee Waterway. The bridge will cross over a portion of Kiplinger Island owned and preserved by the County. A part of the island was donated to the County in 1993-1994 by The Kiplinger Washington Editors, Inc., and the Kiplinger Foundation, Inc. Audubon of Martin County owns another part of the island. The transfer of title to the County does not include any restriction on the use of the island for conservation purposes only. Documentation submitted at hearing refers to a "two hundred foot wide road right-of-way" easement that the bridge will cross and allows the County to designate where on the island parcel such an easement would be. Therefore, spanning the bridge over a portion of the island owned by the County is clearly permissible. The Project also includes the roadway transition and widening/reconstruction of (a) County Road 714 from the beginning of the Project to Mapp Road from 2-lane to a 4-lane divided roadway; (b) Southwest 36th Street from Mapp Road to the beginning of the bridge from a 2-lane rural roadway to a 4-lane divided roadway with wide roadway swales; and (c) Kanner Highway (along Indian Street) from a 4-lane to a 6-lane divided urban roadway. Drainage improvements on both sides of the St. Lucie River are associated with the roadway construction. DOT proposes to provide both on-site and off-site mitigation for wetland and surface waters impacts pursuant to a mitigation plan approved by the District. The ERP Permitting Criteria In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. Besides these rules, certain related BOR provisions which implement the rules must also be considered. The conditions for issuance primarily focus on water quality, water quantity, and environmental criteria and form the basis of the District's ERP permitting program. The parties have stipulated that the Project either complies with the following rule provisions or they are not applicable: Rules 40E-4.301(1)(a), (b), (g), (g), (h), and (k), and 40E- 4.302(1)(a)3. and 6. All other provisions remain at issue. Where conflicting evidence on these issues was submitted, the undersigned has resolved all evidentiary conflicts in favor of the Applicants and District. Based on the parties' Stipulation, the following provisions in Rule 40E-4.301(1) are in dispute and require an applicant to provide reasonable assurances that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters such that the water quality standards set forth in chapters 62- 4, 62-302, 62-520, 62-522, 62-550, F.A.C., including any anti-degradation provisions of paragraphs 62-4.242(1)(a) and (b), subsections 62-4.242(2) and (3), and rule 62-302.300, F.A.C., and any special standards for Outstanding Florida Waters and Outstanding National Resource Waters set forth in subsections 62-4.242(2) and (3), F.A.C., will be violated; will not cause adverse secondary impacts to the water resources; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; These disputed criteria are discussed separately below. Surface Water Storage and Conveyance Rule 40E-4.301(1)(c) requires that an applicant provide reasonable assurances that a proposed activity will not cause adverse impacts to existing surface water storage and conveyance capabilities. Through unrefuted evidence, this requirement was shown to be satisfied. The evidence also establishes that the surface water in and around the Project will actually improve if the Project is constructed as permitted. Further, it will create improved and upgraded surface water management and treatment in areas that now lack features such as swales, retention/detention ponds, curbs and gutters, and improve the overall surface water storage and conveyance capabilities of the Project and surrounding areas. In its current pre-development condition, flooding has occurred in certain areas adjacent to and within the Project area due to poor conveyance, low storage volume, and high tailwater conditions that result from high tides. The Project will remedy historic flooding issues in the Old Palm City area which lies adjacent to a portion of the Project alignment. Surface water runoff will be captured, controlled, and treated by a system of swales, weirs, and retention/detention facilities for pretreatment prior to discharging into the South Fork of the St. Lucie River. Reasonable assurances have been given that existing surface water storage and conveyance capabilities will not be adversely affected. Value of Functions to Fish, Wildlife, and Species Rule 40E-4.301(1)(d) requires that an applicant provide reasonable assurances that a proposed activity will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. BOR Section 4.2.2 further implements this provision. For the following reasons, the rule and BOR have been satisfied. The evidence shows that the existing functions to fish and wildlife were assessed and analyzed by a number of federal and state fish and wildlife agencies. There were extensive review and site inspections by the District, DOT, United States Fish and Wildlife Service, United States Army Corps of Engineers, and National Marine Fisheries Commission to assess the existence of, and potential impact on, fish and wildlife that may result from the Project. These studies revealed that while portions of the South Fork of the St. Lucie River provide potential habitat for aquatic or wetland-dependent or threatened species of special concern, no nesting or roosting areas within the vicinity of the Project were observed. The evidence further supports a finding that "other surface waters" over and under the Project will not receive unacceptable impacts due to their current condition, the detrimental influences of Lake Okeechobee discharges, and tidal impacts. Many of the wetlands to be impacted by the Project were shown to have been impacted by historic activities, and they provide diminished functions to fish and wildlife. The wetland functions were assessed through the Uniform Mitigation Assessment Methodology (UMAM). The UMAM is a standardized procedure for assessing the functions provided by wetlands and other surface waters, the amount that those functions would be reduced by a proposed project, and the amount of mitigation necessary to offset that loss. Detailed UMAM assessments were prepared by the Applicants and the District. They demonstrate that while certain functional units will be lost, they will be fully offset by the proposed mitigation. No credible evidence to the contrary was presented. Water Quality of Receiving Waters Rule 40E-4.301(1)(e) requires an applicant to provide reasonable assurances that a project will not adversely affect the quality of receiving waters such that State water quality standards will be violated. BOR Section 4.2.4 implements this rule and requires that "reasonable assurances regarding water quality must be provided for both the short term and long term, addressing the proposed construction, . . . [and] operation of the system." The receiving water body is the South Fork of the St. Lucie River, which is designated as an impaired water body. The evidence establishes that the Applicants will avoid and minimize potential short-term impacts to water quality by using silt screens and turbidity barriers, and implementing other best management practices to contain turbidity during construction of the Project. They will also use a temporary trestle rather than barges in the shallow portions of the South Fork to avoid stirring up bottom sediments. Finally, a turbidity monitoring plan will be implemented during construction and dewatering activities for all in-water work. All of these construction techniques will minimize potential impacts during construction. The evidence further establishes that water quality standards will not be violated as a result of the Project. In fact, in some cases water quality will be enhanced due to the installation and maintenance of new or upgraded surface water management features in areas where they do not exist or have fallen into disrepair. Over the long term, the Project is expected to have a beneficial effect on water quality. By improving existing surface water management and adding new surface water treatment features, the Project will provide net improvement to water quality. Wetland Delineation and Impacts The Project includes unavoidable impacts to wetlands and other surface waters. A total of 18.53 acres of wetlands and other surface waters within the Project site will be impacted by the Project, including 3.83 acres of wetlands that will be directly impacted and 14.7 acres of wetlands and other surface waters that will be secondarily impacted. The delineated wetlands are depicted in the Staff Report as wetlands 2a, 19a, 19b, 22, 25-29, 30a, 30b, and 30c, with each having a detailed UMAM assessment of its values and condition. (Impacts to wetland 25 are not included in this Project because they were accounted for in a separate permit proceeding.) Using a conservative assessment and set of assumptions, the District determined that, with the exception of wetlands 19a, 19b, 22, and 27, all wetlands would be impacted by the Project. However, the wetlands that would be impacted suffer from varying historical adverse impacts that have compromised the functions and values they provide to fish, wildlife, and species. This is due to their proximity to urban development, vegetative connectivity, size, historic impacts, altered hydroperiod, and invasive plant species. Likewise, even though the wetlands to be impacted on Kiplinger Island provide certain resting and feeding functions for birds, the value of these functions is comparatively lower than other wetlands due to the presence of invasive species and lack of management. The preponderance of the evidence supports a finding that the Applicants provided reasonable assurances that the Project will not cause adverse impacts to fish, wildlife, or listed species. See Fla. Admin. Code R. 40E-4.301(1)(d). Secondary Impacts Rule 40E-4.301(1)(f) and BOR Sections 4.1.1(f) and 4.2.7. require a demonstration that the proposed activities will not cause adverse secondary impacts to the water resources, both from a wetlands and water quality standpoint. Secondary impacts are those that occur outside the footprint of the project, but which are very closely linked and causally related to the activity to be permitted. De minimis or remotely-related secondary impacts, however, are not considered unacceptable. See § 4.2.7.(a). There will be secondary impacts to 6.83 acres of freshwater wetlands and 7.87 acres of mangroves, or a total of 14.7 acres. To address these secondary impacts, the Applicants have established extensive secondary impact zones and buffers along the Project alignment, which were based in part on District experience with other road projects and another nearby proposed bridge project in an area where a State Preserve is located. While Petitioners' expert contended that a 250-foot buffer on both sides of the roadway's 200-foot right-of-way was insufficient to address secondary impacts to birds (who the expert opines may fly into the bridge or moving vehicles), the greater weight of evidence shows that bird mortality can be avoided and mitigated through various measures incorporated into the Project. Further, the bird mortality studies used by the expert involved significantly different projects and designs, and in some cases involved projects outside the United States with different species concerned. Engineering and Scientific Principles Rule 40E-301(1)(i) requires that an applicant give reasonable assurance that a project "be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Unrefuted evidence establishes that the proposed system will function and be maintained as proposed. Financial, Legal and Administrative Capability Rule 40E-4.301(1)(j) requires that an applicant give reasonable assurance that it has the financial, legal, and administrative capability to ensure that the activity will be undertaken in accordance with the terms of the permit. The evidence supports a finding that Applicants have complied with this requirement. Elimination and Reduction of Impacts Before establishing a mitigation plan, Rule 40E- 4.301(3) requires that an applicant implement practicable design modifications to eliminate and reduce wetland and other surface water impacts. In this case, there are unavoidable, temporary wetland impacts associated with the construction of the Project, as well as unavoidable wetland impacts for direct (project footprint), secondary, and cumulative impacts of the Project. The record shows that the Applicants have undertaken extensive efforts to eliminate and reduce wetland and other surface water impacts of the Project. For example, DOT examined and assessed several innovative construction techniques and bridge designs to eliminate and avoid wetland impacts. To eliminate and reduce temporary impacts occurring during construction, DOT has reduced the effect of scour on the pier foundation and reduced the depth of the footing to minimize the amount of excavation on the mangrove island. Also, during construction, the contractor is prohibited from using the 200- foot right-of-way on the mangrove island for staging or stockpiling of construction materials or equipment. The majority of the bridge width has been reduced to eliminate and avoid impacts. Also, the Project's alignment was adjusted to the north to avoid impacts to a tidal creek. Reasonable assurances have been given that all practicable design and project alternatives to the construction and placement of the Project were assessed with no practicable alternatives. Public Interest Test Besides complying with the requirements of Rule 40E- 4.301, an applicant must also address the seven factors in Rule 40E-4.302(1)(a)1.-7., which comprise the so-called "public interest" test. See also § 373.414(1)(a), Fla. Stat. In interpreting the seven factors, the District balances the potential positive and negative effects of a project to determine if it meets the public interest criteria. Because Petitioners agree that factors 3 and 6 of the rule are not at issue, only the remaining five factors will be considered. For the following reasons, the Project is positive when the criteria are weighed and balanced, and therefore the Project is not contrary to the public interest. Public Health, Safety, and Welfare The Applicants have provided reasonable assurance that the Project will not affect public health, safety, and welfare. Specifically, it will benefit the health, safety, and welfare of the citizens by improving traffic conditions and congestion, emergency and hurricane evacuation, and access to medical facilities. In terms of safety, navigation markers are included as part of the Project for safe boating by the public. See Fla. Admin. Code R. 40E-4.302(1)(a)1. Conservation of Fish and Wildlife The activity will not adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The mitigation projects will offset any impacts to fish and wildlife, improve the abundance and diversity of fish and wildlife on Kiplinger Island, create mangrove habitat, and add to the marine productivity in the area by enhancing water quality. See Fla. Admin. Code R. 40E-302(1)(a)2. Fishing or Recreational Values The Project has features that allow for pedestrian and bicycle utilization and observation areas which should enhance recreational values. The Old Palm Bridge, approximately one mile north of the Project, has had no adverse impact on the fishing recreation along the South Fork of the St. Lucie River. Navigation will not be affected due to the height and design of the new bridge. Finally, the bridge is expected to be a destination for boating, kayaking, fishing, and bird watching. See Fla. Admin. Code R. 40E-4.302(1)(a)4. Whether the Activity is of a Permanent Nature The parties have stipulated that the Project is permanent in nature. No future activities or future phases of the project are contemplated. Temporary and permanent impacts are all being fully mitigated. See Fla. Admin. Code R. 40E- 4.302(1)(a)5. Values of Functions Being Performed in Affected Areas Due to historic impacts to the areas affected by the Project, the current condition is degraded and the relative value of functions is minimal. Although Kiplinger Island will have temporary impacts, that island is subject to exotic species and has no recreational use or access by boaters or members of the public. The Applicants propose mitigation which will improve and enhance these wetland functions and values in the areas. See Fla. Admin. Code R. 40E-4.302(1)(a)7. Summary The evidence supports a finding that the Project is positive as to whether it will affect the public health, safety, welfare, or property of others; that the Project is neutral with respect to navigation, erosion and shoaling, and water flow, as well as to historical and archaeological concerns; and that the Project is positive as to conservation of fish, wildlife, recreational values, marine productivity, permanency, and current values and functions. When weighed and balanced, the Project is not contrary to the public interest. Cumulative Impacts Rule 40E-4.302(1)(b) requires that an applicant give reasonable assurance that a project will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in BOR Sections 4.28 through 4.2.8.2. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. An analysis is geographically based upon the drainage basins described in BOR Figure 4.4.1. Petitioners' contention that Figure 4.4.1 is inaccurate or not representative of the basin in which the Project is located has been rejected. In this case, the North St. Lucie Basin was used. To assess and quantify any potential unacceptable cumulative impacts in the basin, and supplement the analyses performed by the Applicants, the District prepared a Basin Map that depicted all the existing and permitted wetland impacts as well as those wetlands under some form of public ownership and/or subject to conservation restrictions or easements. The District's analysis found that the wetlands to be mitigated were of poor quality and provided minimal wildlife and water quality functions. Cumulative impacts from the Project to wetlands within the basin resulted in approximately a four percent loss basin-wide. This is an acceptable adverse cumulative impact. Therefore, the Project will not result in unacceptable cumulative impacts. Mitigation Adverse impacts to wetlands caused by a proposed activity must be offset by mitigation measures. See § 4.3. These may include on-site mitigation, off-site mitigation, off- site regional mitigation, or the purchase of mitigation credits from mitigation banks. The proposed mitigation must offset direct, secondary, and cumulative impacts to the values and functions of the wetlands impacted by the proposed activity. The ability to provide on-site mitigation for a DOT linear transportation project such as a bridge is limited and in this case consists of the creation of mangrove and other wetlands between the realigned St. Lucie Shores Boulevard and the west shore of the St. Lucie River, north and south of the proposed bridge crossing. BOR Section 4.3.1.2 specifically recognizes this limitation and allows off-site mitigation for linear projects that cannot effectively implement on-site mitigation requirements due to right-of-way constraints. Off-site mitigation will offset the majority of the wetland impacts. Because no single on-site or off-site location within the basin was available to provide mitigation necessary to offset all of the Project's impacts, DOT proposed off-site mitigation at two established and functioning mitigation areas known as Dupuis State Reserve (Dupuis), which is managed by the County and for which DOT has available mitigation credits, and the County's Estuarine Mitigation Site, a/k/a Florida Oceanographic Society (FOS) located on Hutchinson Island. Dupuis is outside the North St. Lucie Basin and was selected to offset direct and secondary impacts to freshwater wetlands. That site meets the ERP criteria in using it for this project. The FOS is within the North St. Lucie Basin and was selected to offset direct and secondary impacts to estuarine wetlands. Like Dupuis, this site also meets the ERP criteria for the project. The preponderance of the evidence establishes that the on-site and off-site mitigation projects fully offset any and all project impacts, and in most instances before the impacts will actually occur. Sovereign Submerged Lands and Heightened Public Concern Chapter 18-21 applies to requests for authorization to use sovereign submerged lands. The management policies, standards, and criteria used to determine whether to approve or deny a request are found in Rule 18-21.004. For purposes of granting a public easement to the Applicants, the District determined that the Project is not contrary to the public interest and that all requirements of the rule were satisfied. This determination was not disputed. The only issue raised by Petitioners concerning the use of submerged lands is whether the application should have been treated as one of "heightened public concern." See Fla. Admin. Code R. 18-21.0051(5). If a project falls within the purview of that rule, the Board of Trustees of the Internal Improvement Trust Fund (Board), rather than the District, must review and approve the application to use submerged lands. Review by the Board is appropriate whenever a proposed activity is reasonably expected to result in a heightened public concern because of its potential effect on the environment, natural resources, or controversial nature or location. Id. In accordance with established protocol, the ERP application was sent by the District to DEP's review panel in Tallahassee (acting as the Board's staff) to determine whether the Project required review by the Board. The panel concluded that the Project did not rise to the level of heightened public concern. Evidence by Petitioners that "many people" attended meetings and workshops concerning the Project over the last 20 years or so is insufficient to trigger the rule. Significantly, except for general project objections lodged by Petitioners and Audubon of Martin County, which did not include an objection to an easement, no adjacent property owner or other member of the public voiced objections to the construction of a new bridge. Revised Staff Report On October 20, 2010, the District issued a Revised Staff Report that merely corrected administrative errors or information that had been previously submitted to the District. Contrary to Petitioners' assertion, it did not constitute a material change to the earlier agency action either individually or cumulatively. Therefore, it was properly considered in this proceeding. Letter Modifications The Letter Modifications were used as a mechanism to capture minor alterations made to previously issued permits for Kanner Highway and Indian Street. Neither Letter Modification is significant in terms of water quality, water quantity, or environmental impacts. Both were issued in accordance with District rules and should be approved.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order granting Application Nos. 091021-8, 100316-7, and 100316-6. DONE AND ENTERED this 28th day of December, 2010, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of December, 2010. COPIES FURNISHED: Carol Ann Wehle, Executive Director South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33406-3007 Jeffrey W. Appel, Esquire Ray Quinney and Nebeker, P.C. 36 South State Street, Suite 1400 Salt Lake City, Florida 84111-1401 Bruce R. Conroy, Esquire Department of Transportation 605 Suwannee Street Mail Station 58 Tallahassee, Florida 32399-0458 David A. Acton, Esquire Senior Assistant County Attorney Martin County Administrative Center 2401 Southeast Monterey Road Stuart, Florida 34996-3397 John J. Fumero, Esquire Rose, Sundstrom & Bentley, P.A. 950 Peninsula Corporate Circle Suite 2020 Boca Raton, Florida 33487-1389 Keith L. Williams, Esquire South Florida Water Management District 3301 Gun Club Road Mail Stop 1410 West Palm Beach, Florida 33406-3007

Florida Laws (4) 120.569120.57373.413373.414 Florida Administrative Code (2) 40E-4.30140E-4.302
# 6
CAPTIVA CIVIC ASSOCIATION, INC., AND SANIBEL CAPTIVA CONSERVATION FOUNDATION vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT AND PLANTATION DEVELOPMENT, LTD, 06-000805 (2006)
Division of Administrative Hearings, Florida Filed:Fort Myers Beach, Florida Jan. 03, 2007 Number: 06-000805 Latest Update: Feb. 14, 2008

The Issue The issue in this case is whether the South Florida Water Management District (SFWMD, or District) should issue a Modification to Environmental Resource Permit (ERP) No. 36-00583- S-02, Application No. 050408-15 to Plantation Development, Ltd. (PDL), for construction and operation of a surface water management system serving a 78.11-acre condominium development known as Harbour Pointe at South Seas Resort, with discharge into wetlands adjacent to Pine Island Sound.

Findings Of Fact Based on the evidence and arguments, the following facts are found: The Parties PDL, the applicant, is a limited partnership which is the successor to Mariner Group, Inc. (Mariner). SFWMD has jurisdiction over PDL's application, as amended, and has given notice of its intent to grant PDL's application, as amended, with certain conditions. Petitioners, CCA and SCCF, and Intervenor, CSWF, are Florida not-for-profit corporations that challenged the proposed ERP. Development and Permit History The property subject to PDL's application was part of approximately 310-acres on the northern end of Captiva Island in Lee County, Florida. Redfish Pass is to the immediate north, separating Captiva Island from North Captiva Island. Farther to the north is Cayo Costa Island, a large island to the south of Boca Grande Pass. Most of Cayo Costa is a State Park. To the south of Captiva Island is Sanibel Island, the site of the Ding Darling National Wildlife Refuge. To the northeast of Sanibel Island and to the east of the rest of the string of barrier islands just mentioned is Pine Island Sound, which is to the west of Pine Island. Pine Island Sound is a state-designated Aquatic Preserve and Outstanding Florida Water (OFW). Pine Island Sound also is state-designated Class II water, but shell-fishing is prohibited in the immediate vicinity of Captiva Island. To the east of Pineland Island is Little Pine Island, which is surrounded by the Matlacha Pass Aquatic Preserve, which includes the Matlacha Pass National Wildlife Refuge. All of these features are part of the Charlotte Harbor National Estuary (CHNE). San Carlos Bay is farther south. The Lee County mainland is to the east of Matlacha Pass and San Carlos Bay. The 310-acre site was purchased by Mariner in 1972 for development of a resort that became known as the “South Seas Plantation.” Mariner's property included both Captiva Island proper and a smaller island immediately to the east across Bryant Bayou to the north and Chadwick Bayou farther to the south. Bryant Bayou has a narrower inlet from the north, and Chadwick Bayou has a narrower inlet to the south. Both inlets lead to Pine Island Sound. When Mariner purchased the property, it theoretically was possible to develop a maximum of 3,900 dwelling units on the 310-acre property, pursuant to Lee County zoning. In 1973, Mariner submitted an application to Lee County for the right to develop of 912 dwelling units on its 310 acres. PDL characterizes this as a "voluntary down-zoning" for the purpose of protecting the environment and unusual for a developer to do at that point in time. However, it is speculative how much more than 912 dwelling units would have been approved by Lee County at the time. The purpose of Mariner’s application to Lee County was to create a resort where recreational, single family, multi- family, and some commercial uses would coexist in a resort setting. The overall development plan was to construct the resort while conserving many of the property’s natural resources, including several miles of mangrove and Gulf of Mexico shoreline. Lee County approved the rezoning and the concept of the South Seas Plantation in 1973. Mariner's development began with Captiva Island proper and included a marina, golf course, and a variety of residential condominiums and single-family home sites. Some of the residential units were sold, and others remained in Mariner's ownership. Mariner marketed the rental of units at South Seas Plantation and served as rental agent for units not owned by Mariner. Development of the marina included dredging, and spoil was deposited on the northern tip of the smaller island, helping to create approximately 1.4 acres of upland there. In the 1950's or 1960's, a natural sand-and-shell berm along the eastern shore of the smaller island was built up and maintained by addition of fill material to create a two-track sand/shell road, which was used for vehicular access to the northern tip via an east-west road that divided the smaller island roughly in half and connected it to Captiva Island proper and the main road at South Seas Plantation. At a later point in time, the east-west portion of the road was paved for better access to a drinking water plant, a wastewater treatment plant, and a helicopter pad used by the Lee County Mosquito Control District. In 1985, Mariner received from SFWMD a “Master Stormwater Permit” for its entire development (the 1985 Permit). At that time, SFWMD did not regulate wetland impacts, only surface water management systems. The Department of Environmental Regulation regulated wetland impacts through its dredge and fill permit program, and there was no evidence relating to any dredge and fill permitting on the property. The 1985 Permit was for surface water management systems for construction in uplands on the property. No surface water management systems were needed or permitted in any wetlands. The 1985 Permit included a surface water management system for an 18-unit hotel on the spoil uplands of the northern tip of the smaller island. Permit drawings showed plans for a golf course on much of the remainder of the smaller island, which consisted mostly of wetlands. Access to the facilities was envisioned to be by water taxi, with emergency access via the utility and sand/shell road. Together, the hotel and golf course was to become a part of the resort known as Harbour Pointe. The 1985 Permit was modified several times in the years since its initial issuance, during which time Chapter 373, Florida Statutes, was amended to give SFWMD authority to regulate activities in waters and wetlands. However, until the pending application, none of the modifications had wetland impacts. In 1998, Mariner negotiated the sale of ten resort properties it owned in Florida, including South Seas Plantation, to Capstar, which later became Meristar S.S. Plantation Co., LLC (Meristar). Meristar was a real estate investment trust which specialized in hotels. Because it was not in the development business, Meristar was not interested in purchasing the as-yet undeveloped Harbour Pointe portion of South Seas Plantation, or Mariner's remaining development rights. As a result, Meristar purchased all the developed land on South Seas Plantation but not the approximately 78 acres of undeveloped land which is the subject of the pending application, or any of Mariner's development rights. Thus, after the sale of South Seas Plantation, Mariner retained its development rights and the 78 acres of undeveloped land, which are the subject of PDL's application. In 2002, Lee County issued an Administrative Interpretation which clarified that those development rights consisted of a maximum of 35 more residential units. Eleven units subsequently were built, leaving a maximum of 24 residential units when PDL filed its application in this case. The 78-acre Harbour Pointe site consists of mangrove wetlands, privately owned submerged lands, the 1.4-acre upland area at the northern tip of Harbour Pointe and another 1.4 acres of upland, which contain a Calusa Indian mound, known as the Chadwick Mound for its location west of Chadwick Bayou. While agreements between Meristar and PDL contemplate that PDL's subsequent development at Harbour Pointe would be marketed as part of the South Seas Resort and share some amenities and services, the parcels which comprise the Harbour Pointe development are the only undeveloped lands PDL owns or controls. PDL has no contractual or other legal right to develop on property owned by Meristar. Because it was modified several times since issuance, the 1985 Permit has not expired. However, Harbour Pointe never was constructed, and that part of the 1985 Permit expired in that Mariner lost its entitlement to proceed with construction. Instead, development of Harbour Pointe would require a permit modification under the new laws and rules, which included the regulation of wetland impacts. The Application and Proposed ERP In October 2003, PDL applied to SFWMD to further modify the 1985 Permit for construction of a water taxi dock for access to Harbour Pointe. After being informed by SFWMD that modifications to the 1985 Permit for development of Harbour Pointe would be reviewed under current laws and regulations, PDL withdrew the application. In April 2005 PDL applied for modification of the 1985 Permit to construct six 9,500 square-foot, four-plex condominium buildings (each two stories over parking, and accommodating units having 3,600-3,800 square feet of air-conditioned living space), a pool and spa, a tennis court, an access road, a filter marsh and surface water management facilities. Additionally, the site plan deleted all boat docks, except for a single water taxi slip and possibly a dock for launching kayaks and canoes and proposed a drawbridge across the inlet to Bryant Bayou to connect the project site to the South Seas Resort and eliminate the need for the emergency access road on the smaller island. This application described a development site of 7.4 acres, which included 4.8 acres of direct impacts to (i.e., destruction and fill of) mangroves and .1 acre of shading impacts from construction of the drawbridge. The proposed mitigation for the mangrove impacts included: restoration (by removal and replanting) of .6 acre of the north-south sand/shell road, with resulting enhancement of the adjacent preserved mangrove wetlands through improved hydrologic connection across the former shell/sand road and improved tidal connection to Pine Island Sound to the east; and preservation of the rest of PDL's property. The preserved areas would include: approximately 36 acres of mangrove wetlands adjacent to and south of the impacted wetlands (included the road to be restored) (Parcel A); 24.5 acres of mangrove wetlands south of the utility road and east of the narrow inlet to Chadwick Bayou (Parcel B); 9.3 acres of mangrove wetlands (7.9 acres) and tropical hardwoods (1.4 acres, which includes the Chadwick Mound), south of the utility road and west of the inlet to Chadwick Bayou, (Parcel C); .9 acre of mangrove wetlands to the west of Parcel C and the South Seas Resort main road (Parcel D); and .8 acre of mangrove wetlands separated from Parcel A by Bryant Bayou and adjacent to the South Seas Resort main road. A monitoring program lasting at least five years was offered to ensure success of the restoration and mitigation proposal. The application itself incorporated some reduction and elimination of wetland impacts. The total site consists of five separate tax parcels which could be developed into a number of single-family home sites. Such a development plan would have greater direct impacts than the proposed project and would require the shell/sand road to be significantly widened to meet current code requirements. By using the bridge as access, .11 acre of wetlands would be disturbed, as compared to 3.9 acres of total impact that would occur because of the widening the road. This approach results in the entire project causing less wetland impact than would occur from the use of the road alone. After the application was filed, PDL responded to two written requests for additional information and several other questions raised during meetings, phone conversations, and email exchanges with one or more SFWMD staff members. During this process, the application was amended. The tennis court was eliminated, and the filter marsh was replaced by a five dry detention ponds. In addition, the resulting development was concentrated more into the northern tip of the island to reduce and eliminate the greater secondary impacts (from more "edge effect") to the preserved wetlands to be expected from a more linear site plan. These changes reduced the footprint of the proposed project to 5.24 acres, the building size to 6,400 square feet each, the residential unit size to 2,400 to 2,600 square feet each, and wetland impacts to 2.98 acres, plus .11 acre of shading impacts from construction of the drawbridge. In addition, since the project was more concentrated at the northern tip, another tenth of an acre of the sand/shell road was to be restored. A conservation easement was offered for the 73.31 acres to be preserved, including 71.10 acres of wetlands, in Parcels A through E. PDL also offered to purchase .11 credits of offsite mitigation from the Little Pine Island Wetland Mitigation Bank (LPIWMB). On February 2, 2006, SFWMD's staff recommended approval of the amended application with 19 standard general conditions and 30 special conditions. Some of the special conditions in the Staff Report addressed prevention of erosion, shoaling, silt, turbidity, and water quality problems during construction or operation; remediation of any such problems not prevented; and restoration of any temporary wetland impacts. A pre-construction meeting was required to discuss construction methods, including construction dewatering. Although PDL indicated that dewatering would not be necessary for construction of the project, the Staff Report recommended that a dewatering plan be submitted before any dewatering occurred and noted that PDL would have to obtain all necessary Water Use authorizations, unless the work qualified for a No-Notice Short-Term Dewatering permit pursuant to Rule 40E- 20.302(3) or is exempt pursuant to Rule 40E-2.051.1 On February 8, 2006, SFWMD's Governing Board gave notice of its intent to approve the amended application with two additional conditions that were added to the Staff Report: PDL was required to apply for and receive a permit modification for the roadway necessary to access the project (i.e., the road leading from the South Seas Resort main road to the proposed drawbridge), and the applicant for the road to the drawbridge was required to document that proposed construction was consistent with the design of the master surface water management system, including land use and site grading assumptions; and a perpetual maintenance program for restored and preserved areas, including removal of exotic and nuisance vegetation in excess of five percent of total cover between regular maintenance activities, or such vegetation dominating any one section, was required to ensure integrity and viability. The parties interpreted the first of the two additional conditions to mean that construction access to build the project would be via the new roadway and drawbridge. On May 30, 2006, to address certain issues raised by the pending challenge to SFWMD's intended action, PDL further amended the application to substitute two wet retention ponds and three dry retention ponds for the five dry detention ponds and to make associated minor changes to the proposed surface water management system's water quality treatment methods to further reduce water quality impacts from the discharge of the system into the adjacent preserved wetlands. In addition, in view of disagreements among the parties as to the ability of PDL's onsite mitigation proposal to offset wetland impacts, PDL offered to increase offsite mitigation by purchasing as many additional credits from the LPIWMB as necessary to completely offset wetland impacts, as determined by the Uniform Mitigation Assessment Methodology (UMAM). Water Quantity Impacts Pursuant to Rule 40E-4.301(1), an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause adverse flooding to on- site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities. Section 6.0 of the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District (BOR), entitled Water Quantity Criteria, outlines the criteria that the applicant must meet for water quality at the project site. As outlined in BOR Section 6.2, the off-site discharge is limited to rates not causing adverse impacts to existing off- site properties. The proposed surface water management system consists of a series of swales, dry retention, and then a wet retention system with an outfall into the areas to the south. Ordinarily, stormwater runoff eventually will be absorbed into the ground. Any discharge associated with the system, typically only in conjunction with major rain events, will flow into a preserved wetland that will be hydrologically connected to Bryant Bayou and Pine Island Sound. As outlined in BOR Section 6.2, the off-site discharge rate is limited to historic discharge rates. As required by BOR Section 6.3, a storm event of 3-day duration and 25-year return frequency is used in computing off- site discharge rates. As required by BOR Section 6.4, building floors must be at or above the 100-year flood elevations. PDL conducted a hydrologic analysis of the existing condition of the property, analyzed the runoff patterns that would result during the 25-year rainfall event and then compared the development plan hydrologic analysis to the existing condition. The conclusion was that the development plan would not adversely affect offsite area. PDL analyzed a series of storm conditions for the protection of road elevations and the protection of finished floors. There are no off-site areas that contribute to runoff through this piece of property. The proposed system will not cause adverse water quantity impacts to waters and adjacent lands, flooding to onsite or offsite properties, or adversely impact existing surface water storage and conveyance capabilities. Water Quality Impacts Rule 40E-4.301(1)(e) requires an applicant to provide reasonable assurances that the proposed project will not adversely affect the quality of receiving waters so that State water quality standards will not be violated. BOR Section 5.0 is entitled Water Quality Criteria. BOR Section 5.1 states that projects shall be designed and operated so that offsite discharges will meet State water quality standards. BOR Section 5.2.1 requires that either retention or detention, or both retention and detention be provided in the overall system in one of the following three ways or equivalent combinations thereof: Wet detention volume shall be provided for the first inch of runoff from the developed project, or the total runoff of 2.5 inches times the percentage of imperviousness, whichever is greater. Dry detention volume shall be provided equal to 75 percent of the above amounts computed for wet detention. Retention volume shall be provided equal to 50 percent of the above amounts computed for wet detention. Retention volume included in flood protection calculations requires a guarantee of long term operation and maintenance of system bleed-down ability. BOR Section 5.9 states that all new drainage projects will be evaluated based on the ability of the system to prevent degradation of receiving water and the ability to conform to State water quality standards. In the design of the system, PDL proposed a series of best management practices. The first is to treat runoff through grassed swale areas adjacent to buildings and some of the internal roadways. From there, the water would discharge through a series of dry retention areas where there would be further removal and treatment. The water would discharge through a proposed wet retention area prior to outfall under more significant rainfall events, southward into the preserved wetland area. Because of the hydrological connection from there to Bryant Bayou and Pine Island Sound, a more detailed evaluation was conducted. PDL's detailed evaluation included source control measures. The first one is a construction pollution prevention plan. PDL also proposed an urban storm water management plan. PDL is going to provide guidance to property owners about pesticide and fertilizer management control. The Applicant also submitted a street-sweeping proposal. The design of the system incorporates an additional 50 percent water quality treatment volume, over and above the requirements of the BOR. The wet retention system, located to the north of the proposed outfall structure, incorporates submerged aquatic vegetation. That is not a requirement of the District. It is an extra measure that will remove additional levels of pollutants prior to outfall. PDL proposed an urban stormwater management plan. The plan requires annual inspection of the water management facilities, and it must be documented that the system is functioning as originally designed and built. The stormwater management system is capable, based on generally accepted engineering and scientific principles, of functioning as proposed. The stormwater management system satisfies the District's water quality criteria. Petitioners and Intervenor criticized the method used by PDL's water quality consultant, Dr. Harvey Harper, for projecting and evaluating water quality impacts to be expected from PDL's stormwater management design. They contended that the so-called "Harper method" has been criticized by other experts, none of whom testified. Dr. Harper ably defended himself against the criticism leveled at him. He testified that most if not all of the components he has incorporated into his evaluation method are not new but rather have been accepted and used by experts in his field for years. He also explained that he refined his evaluation method in response to some early criticism and that the method he used in this case has been peer-reviewed and accepted by the Department of Environmental Protection for evaluation of stormwater design criteria. While some of the assumptions incorporated in his evaluation method are simple averages of a relatively small samples, and sometimes averages of averages, Dr. Harper was confident in the ability of his method to accurately evaluate the expected water quality impacts from PDL's system. While there is potential for error in any projection, Dr. Harper's evaluation provided reasonable assurances that utilization of PDL's proposed stormwater management and treatment method will not result in violation of any State water quality standards or significantly degrade the water quality of Bryant Bayou or Pine Island Sound. Value of Wetland and Surface Water Functions In general, as part of the CHNE, the mangrove wetlands to be impacted by the proposed ERP are very important. The CHNE Coast Conservation Management Plan identifies three major threats to the estuary and local ecosystem: fish and wildlife habitat loss; water quality degradation; and hydrological alteration. The plan calls for the preservation of mangroves within the CHNE. A wide array of wildlife uses the habitat in the vicinity of the mangrove wetlands to be impacted. The site is in an important coastal fly-way for migratory birds, including numerous species of waterfowl and songbirds that migrate across the Caribbean and Gulf of Mexico to and from South and Central America. The project area also provides habitat for several listed wildlife species, including the American crocodile, wood stork, and West Indian manatee. The mangrove wetlands that will be impacted directly and indirectly by the proposed ERP are in relatively good condition and are very important due primarily to their location near Redfish Pass at the northern end of Captiva Island and to their relationship to the rest of the relatively large area of contiguous and relatively undisturbed wetlands in Parcels A through E. These attributes make them especially important as a nursery ground for several valuable fish species. Existing impacts attributable to the spoil and other disturbances in the adjacent uplands, the northernmost extent of the sand/shell road, and the South Seas Plantation/Resort development to the west across the inlet to Bryant Bayou keep these impacted wetlands from being of the very highest quality. Clearly, and obviously, the project will destroy and fill 2.98 acres of these wetlands. Indirect (secondary) impacts to the adjacent preserved wetlands will result from alteration of hydrology of the 2.98 acres of directly impacted wetlands. Instead of sheet-flowing across the uplands on the northern tip of Harbour Pointe into those wetlands, surface water on the 5.24- acre development project will be directed into a series of swales, to the dry retention ponds, and to the wet retention ponds with an outfall to the adjacent preserved wetlands to the south. Secondary impacts from the Harbour Pointe project will be similar to the existing secondary impacts to the 2.98 acres attributable to the adjacent spoil and the South Seas Plantation/Resort development, if not somewhat greater due to the absence of any buffer like the inlet. On the other hand, PDL's mitigation proposal will restore .7 acre of wetlands where the northern end of the north- south sand/shell road now exists. Eventually, the restored wetland would be expected to become an extension of the existing, adjacent red and basin black mangrove forest. In addition, the resulting improved hydrologic connection to Pine Island Sound will enhance the value of functions in the preserved wetlands, including possibly expanding the existing fish nursery and making it accessible to fish larvae and juvenile fish entering from the east as well as from the west via Bryant Bayou. There was much debate during the hearing as to whether the sand/shell road is natural or man-made and whether it is reducing what otherwise would be the natural tidal and hydrologic connection between the wetlands to the west of the road and Pine Island Sound. As indicated, a prior owner added fill material to the natural sand and shell berm in the 1950's and 1960's to create better vehicular access. See Finding 9, supra. The evidence was reasonably persuasive that those man-made changes have altered hydrology and tidal connection to some extent and that the restoration project will enhance the value and functions of the preserved wetlands to some extent. Impacts to the value of wetland and surface water functions, and corresponding mitigation for impacts, are required to be assessed using UMAM. See Fla. Admin. Code R. 62-345.100. While the mitigation assessment method might be uniform, its application and results are not. Three different experts used UMAM with differing results. SFWMD's expert, Mr. Cronyn, and PDL's consultants, Kevin L. Erwin Consulting Ecologist, Inc. (KLECE), conferred after their initial assessments, resulting in changed results by both (as well as correction of errors in initial scoring by Mr. Cronyn.) Dave Ceilley, an expert for Petitioners and Intervenor, scored the 2.98 acre impact area significantly higher in its current state than the final score of either Mr. Cronyn or KLECE, resulting in a higher functional loss from its destruction and filling. He also gave no credit for restoration of the sand/shell road, in contrast to KLECE and Mr. Cronyn, and scored PDL's mitigation proposal as it affected 36.6 acres of preserved wetlands (essentially, Parcel A) as a functional loss instead of a functional gain, as scored by KLECE and Mr. Cronyn. Mr. Ceilley also scored PDL's mitigation proposal as it affected 24.5 acres of preserved wetlands (Parcel B) as a functional loss instead of a functional gain, as scored by KLECE and Mr. Cronyn. Finally, he gave no credit for preservation of Parcels A through E via a conservation easement because he was under the mistaken impression that the land already was under a conservation easement in favor of Lee County. (Actually, PDL had agreed to preserve 65 acres of mangrove forest in return for the right to develop Harbour Pointe, although a conservation easement actually was imposed on only about six acres. Although not identified, the 65 acres probably would have included the preserved wetlands in the proposed ERP.) Mr. Cronyn gave credit for preservation of Parcels B through E. KLECE did not claim credit, because KLECE did not think it was necessary, but KLECE accepts Mr. Cronyn's assessment of those parcels. Mr. Ceilley's recent onsite field work was extremely limited, and much of his assessment was based general knowledge of the area and dated (14-year old) onsite field work. In addition, this was the first "real-life" UMAM assessment performed by Mr. Ceilley. His only other use of UMAM was for practice in training. Finally, his assessment was entirely independent without the input of any other consultants to aid him. In contrast, both KLECE and Mr. Cronyn had extensive prior experience using UMAM. In addition, KLECE functioned as a three- man team in performing its UMAM assessments and talked out any initial discrepancies and disagreements (albeit with Mr. Erwin being the final arbiter). KLECE and Mr. Cronyn also consulted with one another, as well as experts in other related fields before finalizing their respective UMAM assessments. KLECE was able to draw on field work conducted during over 200 man-hours onsite in recent years. While KLECE was the retained consultant and agent for the applicant in this case, Mr. Ceilley conceded that Mr. Erwin adheres to high ethical standards. Petitioners and Intervenor were critical of credit given in the UMAM assessments performed by Mr. Cronyn for preservation of Parcels B through E. (KLECE did not claim credit for their preservation in its UMAM assessment.) Petitioners and Intervenor contend that PDL already has agreed to preserve the wetlands in those parcels in return for the ability to utilize the remaining 24 residential units of development rights at Harbour Pointe and that development of the Chadwick Mound is unlikely. Actually, as found, PDL's agreement with the County only specified six of the 65 acres of wetlands to be preserved. Besides, the preserved wetlands in the proposed ERP would implement the agreement with the County. As for the Chadwick Mound, preservation without the proposed ERP is not a certainty, although residential development there would be difficult now that its existence is common knowledge. In any event, the relative unlikelihood of development in Parcels A through E, especially after development of 24 units at Harbour Pointe, was taken into consideration by Mr. Cronyn in determining the amount of credit to be given for their preservation. Taking all the evidence into account, Mr. Cronyn's UMAM assessment of the value of wetland functions with and without the proposed ERP are accepted. According to his assessment, the proposed ERP will result in a functional loss of .34 functional units, meaning an equivalent amount of mitigation credit would have to be purchased from the LPIWMB to offset wetland impacts. Based on the functional assessment used to permit that mitigation bank, approximately an additional .9 of a mitigation bank credit would be needed, in addition to the .11 already offered. The evidence as to cumulative impacts did not clearly define the pertinent drainage basin. Logically, the pertinent drainage basin either would encompass all land draining to surface waters connected to Pine Island Sound, which would include Little Pine Island, or would be limited to the land that is subject to the proposed ERP. If the former, all offsetting mitigation would be within the same drainage basin. If the latter, there would be no cumulative impacts, since the proposed ERP would complete all development. Reduction and Elimination of Wetland Impacts According to BOR Section 4.2.1.1, if a proposed surface water management system will result in adverse impacts to wetland or other surface water functions such that it does not meet the requirements of Sections 4.2.2 through 4.2.3.7, the District must consider whether the applicant has implemented practicable design modifications to reduce or eliminate such adverse impacts. The term "modification" does not mean not implementing the system in some form, or requiring a project that is significantly different in type or function, such as a commercial project instead of a residential project. Elimination and reduction also does not require an applicant to suffer extreme and disproportionate hardship--for example, having to construct a ten mile-long bridge to avoid half an acre of wetland impacts. However, Anita Bain, SFWMD's director of ERP regulation, agreed that, in interpreting and applying BOR Section 4.2.1.1, "the more important a wetland is the greater extent you would require elimination and reduction of impact." As reflected in Findings 17-19, supra, PDL explored several design modifications in order to reduce and eliminate impacts to wetland and other surface water functions. However, several options for further reducing and eliminating wetland impacts were declined. PDL declined to eliminate the swimming pool and move one or more buildings to the pool's location at the extreme northern tip of Harbour Pointe because that would not be a practicable means of reducing the Harbour Pointe footprint. First, the undisputed testimony was that a residential building could not be sited as close to the water's edge as a swimming pool could. Second, because it would block the view from some of Meristar's residential properties, and Meristar has the legal right to approve or disapprove PDL's development on Harbour Pointe. PDL declined to reduce the number of buildings because, without also reducing the number and/or size of the residential units, reducing the number of buildings would make it difficult if not impossible to accommodate all cul-de-sacs required by Lee County for use by emergency vehicles and meet parking needs beneath the buildings, as proposed. (In addition, it would reduce the number of prime corner residential units, which are more marketable and profitable.) PDL declined to further reduce unit size because a further reduction to 2,000 square feet would only reduce the footprint of the six proposed buildings by a total of 5,000 square feet--less than a ninth of an acre. Reducing unit size to much less than 2,000 square feet would make it difficult if not impossible to market the condos as "luxury" units, which is what PDL says "the market" is demanding at this time (and also what PDL would prefer, since it would maximize PDL's profits for the units.) But it was not proven that smaller condos could not be sold at a reasonable profit. PDL declined to reduce the number of condo units at Harbour Pointe (while maintaining the conservation easement on the remainder of PDL's acreage, which would not allow PDL to develop all of the 24 dwelling units it wants to develop and is entitled to develop on its 78 acres, according to Lee County). However, it was not proven that such an option for further reducing and eliminating wetland impacts would not be technically feasible, would endanger lives or property, or would not be economically viable. With respect to economic viability, SFWMD generally does not examine financial statements or profit-and-loss pro formas as part of an analysis of a site plan's economic viability. This type of information is rarely provided by an applicant, and SFWMD does not ask for it. As usual, SFWMD's reduction and elimination analysis in this case was conducted without the benefit of such information. Rather, when PDL represented that any reduction in the number of units would not be economically viable, SFWMD accepted the representation, judging that PDL had done enough elimination and reduction based on the amount of wetland impacts compared to the amount of wetlands preserved, in comparison with other projects SFWMD has evaluated. As Ms. Bain understands it, "it's almost like we know it when we see it; in that, you wouldn't ask an applicant to build a ten-mile bridge to avoid a half an acre wetland impact, so something that's so extreme that's obvious, rather than how much profit would a particular applicant make on a particular project." Although SFWMD did not inquire further into the economic viability of modifications to reduce and eliminate wetland and surface water impacts, Petitioners and Intervenor raised the issue and discovered some profit-and-loss pro formas that were presented and addressed during the hearing. A pro forma prepared in August 2003 projected a profit of $2.79 million for the first 8 of 12 units and an additional $1.72 million profit on the next four units (taking into account construction of a drawbridge and road to the west at a cost of $1.8 million). This would result in a total profit of $4.51 million, less $800,000 for a reserve to pay for maintenance of the drawbridge (which PDL said was required under timeshare laws). Another pro forma prepared in February 2004 projected profits of $11.99 million on 16 "big-sized" units (3,000 square feet), $11.81 million on 20 "mid-sized" units (2,200 square feet), and $13.43 million on 24 "mixed-size" units (16 "mid- sized" and 8 "small-sized" at 1,850 square feet), all taking into account the construction of the drawbridge and road at a cost of $1.8 million. After production of the earlier pro formas during discovery in this case, PDL prepared a pro forma on June 7, 2006. The 2006 pro forma projected net profit to be $4.9 million, before investment in the property. However, PFL did not make its investment in the property part of the evidence in the case. In addition, Petitioners and Intervenor questioned the validity of the 2006 pro forma. PDL answered some of the questions better than others. To arrive at the projected net profit, PDL projected significantly (33%) higher construction costs overall. The cost of the drawbridge and road to the west was projected to increase from $1.8 million to $2.5 million. Based on its experience, PDL attributed the increase in part to the effect of rebuilding activity after Hurricane Charlie and in part to the effect of Sanibel Causeway construction (both increased overweight charges and limitations on when construction vehicles could cross the causeway, resulting construction work having to be done at night, at a significantly higher cost). At the hearing, PDL did not present any up-to-date market surveys or other supporting information on construction costs, and the Sanibel Causeway construction is expected to be completed before construction on the Harbour Pointe project would begin. In addition, without a full enough explanation, PDL replaced the bridge operation and maintenance reserve of $800,000 with an unspecified bridge reserve fund of $2 million. On the revenue side of the 2006 pro forma, gross sales of $1.9 million per unit were projected, which is less than PDL was projecting per square foot in February 2004, despite the assumed increased construction costs. PDL also attributes this to the effects of Hurricane Charlie. Again, there were no market surveys or other information to support the pricing assumptions. Besides predicting lower price potential, the 2006 pro forma deducts a pricing contingency of $2.3 million. PDL did not calculate or present evidence on whether it could make a profit building and selling 16 or 20 units, thereby eliminating a building or two (and perhaps some road and stormwater facility requirements) from the project's footprint. The absence of that kind of evidence, combined with the unanswered questions about the 2006 pro forma for the maximum number of units PDL possibly can build, constituted a failure to give reasonable assurance that wetland and surface water impacts would be reduced and eliminated by design modifications to the extent practicable, especially given the very high importance of the wetlands being impacted. Public Interest Test An ERP applicant who proposes to construct a system located in, on, or over wetlands or other surface waters must provide reasonable assurances that the project will “not be contrary to the public interest, or if such an activity significantly degrades or is within an Outstanding Florida Water, that the activity will be clearly in the public interest.” § 373.414(1)(a), Fla. Stat.; Rule 40E-4.302(1)(a); and SFWMD BOR Section 4.2.3. This is known as the “Public Interest Test,” and is determined by balancing seven criteria, which need not be weighted equally. See Lott v. City of Deltona and SJRWMD, DOAH Case Nos. 05-3662 and 05-3664, 2006 Fla. Div. Adm. Hear. LEXIS 106 (DOAH 2006). The Public Interest criteria are as follows: Whether the activity will adversely affect the public health, safety or welfare or the property of others. There are no property owners adjacent to the site, and the closest property owners to the site are located across the inlet which connects Bryant Bayou to Pine Island Sound. While mangrove wetlands generally provide maximum protection from hurricanes, it does not appear from the evidence that existing conditions would provide appreciably more protection that the conditions contemplated by the proposed ERP. Otherwise, the project would not adversely affect the public health, safety or welfare, or property of others. Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The proposed ERP would impact (fill and destroy) 2.98 acres of very important, high quality mangrove wetlands. Even with the restoration or creation of .7 acre of probable former wetlands and improvements in the hydrologic connection of the 36.5-acre preserved wetland (Parcel A) to Pine Island Sound, the proposed ERP probably will have a negative effect on the conservation of fish and wildlife, including listed species. However, the negative effect would not be considered "adverse" if the elimination and reduction requirements of BOR 4.2.1.1 are met. Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling. The proposed drawbridge will be constructed over the inlet connecting Bryant Bayou with Pine Island Sound, a distance of approximately 65 feet. Boaters use the inlet for navigation. However, by its nature, a drawbridge allows for and not adversely affect navigation. The proposed ERP does not contain specifics on operation of the drawbridge, but PDL's consultant, Mr. Erwin, testified that there would be no adverse effect on navigation, assuming that the bridge would remain in the open position between use for crossings by road. The drawbridge would not adversely affect the flow of water or cause harmful erosion or shoaling. Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity. The question whether the proposed ERP will adversely affect fishing or recreational values is informed by both the UMAM functional assessment and the reduction and elimination analysis. If impacts to wetlands and surface waters are reduced and eliminated, and offset by mitigation, there should be no significant adverse effects on fishing and recreational values. Whether the activity will be of a temporary or permanent nature. The proposed development is permanent in nature. vi. Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, Florida Statutes. There are no significant archaeological resources on the Harbour Pointe project site. Although shell scatter left by the Calusa Indians has been found on Parcel A, they have been evaluated in the permit application process by Corbett Torrence, an archeologist, and found to be of limited historical or archaeological value. The reduced scope of the project avoids most of these areas. The proposed ERP will, however, enhance significant archaeological resources by placing a conservation easement on Parcel C, which is the site of the Chadwick Mound, one of the largest Calusa Indian mounds in Lee County. Further studies of this site could lead to a much better understanding of the Calusa culture. This Indian mound is a very valuable historical treasure, and its protection through inclusion in a conservation easement is very much in the public interest. vii. The current condition and relative value of functions being performed by areas affected by the proposed activity. This subject also was considered in the reduction and elimination analysis and in the UMAM functional assessment. As in the Findings the current condition and relative value of the functions being performed by the areas affected by the proposed activity are very valuable. That is why the reduction and elimination analysis is particularly important in this case. Assuming appropriate reduction and elimination, mitigation according to the UMAM assessment can offset unavoidable impacts to the functions performed by the areas affected by the proposed activity. Standing of CCA, SCCF, and CSWF CCA, SCCF, and CSWF each has at least 25 current members residing within Lee County and was formed at least one year prior to the date of the filing of PDL's application. CCA's mission statement includes protection of "our residents' safety, the island ecology, and the unique island ambience . . . ." CCA also is dedicated to "preserving and expanding, where possible, the amount of native vegetation on Captive Island" and preservation of natural resources and wildlife habitat on and around Sanibel and Captiva Islands. SCCF's mission is the preservation of natural resources and wildlife habitat on and around Sanibel and Captiva. It manages just over 1,800 acres of preserved lands, including mangrove forest habitat similar to that being proposed for development by PDL. Management activities involve invasive non- native plant control, surface water management, prescribed burning, native plant habitat restoration and wildlife monitoring. CSWF's purpose is to sustain and protect the natural environment of Southwest Florida through policy advocacy, research, land acquisition and other lawful means. Its four core programs are: environmental education; scientific research; wildlife rehabilitation; and environmental policy. Of CCA's 464 members, approximately 115 live within the boundaries of South Seas Plantation/Resort. Approximately 277 of SCCF's 3,156 members live on Captiva Island, and 40 live within the boundaries of South Seas Plantation/Resort. The members of CCA and SCCF who own property on Captiva Island rely on the mangrove systems for protection from storms. A substantial number of the Captiva Island residents and the other members of CCA and SCCF engage in recreational activities in the vicinity of PDL's property, including boating, fishing, bird-watching, wildlife observation, and nature study that would be adversely affected by significant water quality and wetland impacts from the proposed ERP. CSWF has 5,600 family memberships, approximately 400 in Lee County, and 14 on Sanibel. No members live on Captiva Island. There was no evidence as to how many of CSWF's members use the natural resources in the vicinity of the proposed ERP for recreational purposes or otherwise would be affected if there are water quality and wetland impacts from the proposed ERP.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the proposed ERP be denied; however, if wetland and surface water impacts are reduced and eliminated to the extent practicable, the proposed ERP should be issued with the additional conditions, as represented by PDL's witnesses: that the proposed drawbridge be left drawn except when in use for road access; that construction access be via the proposed drawbridge only; and that there be no construction dewatering. DONE AND ENTERED this 8th day of November, 2006, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th of November, 2006.

Florida Laws (8) 120.52120.569120.57267.061373.042373.4136373.414403.412 Florida Administrative Code (7) 40E-2.05140E-4.09140E-4.30140E-4.30262-302.30062-345.10062-4.242
# 8
BROOKSVILLE ASSOCIATES vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 92-007064 (1992)
Division of Administrative Hearings, Florida Filed:Brooksville, Florida Nov. 25, 1992 Number: 92-007064 Latest Update: Aug. 20, 1993

Findings Of Fact The Parties and the Property. The Respondent, HORNE, owns or has options to purchase approximately 24.35 acres of real property at the southwest corner of U.S. Highway 41 and State Road 50 Bypass in Brooksville, Florida. The Petitioner, the ASSOCIATES, owns approximately 67.5 acres of real property to the south and downstream from the HORNE property. The ASSOCIATES' property is presently undeveloped. The HORNE property contains an existing Publix shopping plaza, a mobile home sales office and vacant lands. The Publix plaza was previously permitted by the DISTRICT before it was constructed. The Surface Water Permit Application On August 7, 1992, HORNE submitted its application for surface water permit No. 400317.02. The application sought approval to construct a surface water management system for a proposed new K-Mart store on HORNE's property. On November 3, 1992, the DISTRICT issued notice of final agency action approving issuance of permit No. 400317.02 to HORNE. The day before the original final hearing in this matter scheduled for March 1993, new information from a study called the Peck Sink Watershed Study came to light which rendered the project as then designed unpermittable. This information resulted in the surface water management system being redesigned. On April 1, 1993, the DISTRICT notified all of the parties that the redesigned surface water management met District rule criteria. This resulted in issuance of what became known as the April 1 submittal. On May 12, 1993, in response to concerns raised by the ASSOCIATES at depositions on May 10, 1993, HORNE produced the May 12 submittal and provided it to all parties on that same date. The changes in design reflected on the May 12 submittal related to lowering the pond bottoms one foot below the orifices and changing the contour lines on the outside of Pond 5A. On May 13, 1993, further minor changes were made to the permit materials. Specifically, the changes were: reflecting on the engineering worksheets the lowering of the pond bottoms accomplished on the May 12 submittal, correction of the contour line on the outside of Pond 5A and showing the amount of additional fill into the 100-year floodplain caused by the addition of the contour line to the outside of Pond 5A. In reviewing HORNE's application, the District applied the standards and criteria set forth in Chapter 40D-4, Florida Administrative Code, and the Basis of Review for Surface Water Management Permit Applications. Compliance with DISTRICT Permitting Criteria Water Quantity The main two areas considered by the DISTRICT in assessing water quantity in a closed basin are: attenuating the peak rate of discharge for the 25 runoff for the 100 The peak rate of runoff for this project for the 25 (2) cubic feet per second (cfs) less in the post-developed condition than in the pre-developed condition, as shown on the April 1 submittal. No changes were made between the April 1 and May 12 or 13 submittals relating to the peak rate of discharge. The difference in the volume of runoff between the pre-developed and post-developed condition during the 100-year storm is being retained on site, as shown on the April 1 submittal. Therefore, DISTRICT rule criteria for the peak rate and volume of runoff were met on the April 1 submittal. Lowering the bottoms of the detention ponds on the May 12 and 13 submittals resulted in additional post 100 system, as redesigned to retain this additional 100-year volume, exceeds the DISTRICT's 100 Floodplain Encroachment Under the DISTRICT's floodplain encroachment standards, any fill within the 100 out an equivalent volume of fill elsewhere on the property. HORNE's application satisfies the DISTRICT's floodplain standards. HORNE is filling 1.59 acre feet of the floodplain and creating 1.75 acre feet of compensation. The floodplain compensation will be above the seasonal high water table, as required by Section 3.2.1.4 of the DISTRICT's Basis of Review. The original, existing seasonal high water table will be lowered as a result of the excavation so that the entire floodplain compensation area will be above the seasonal high water table. Water Quality A wet detention system as proposed by HORNE is an acceptable means under the DISTRICT's rules of treating runoff for water quality purposes. The bottoms of the ponds, as shown on the May 12 submittal, are all at least one foot below the orifice elevations, as required by the Basis of Review. Thus, the project met all relevant DISTRICT water quality requirements as of the May 12 submittal. Operation and Maintenance DISTRICT rules require that reasonable assurances be provided that the surface water management system can be effectively operated and maintained. HORNE will be the operation and maintenance entity for this surface water management system. The DISTRICT's main concerns at the time of permit review are that the design of the surface water management system not be an exotic design, that the design insure that littoral zones can be established, that the system orifice can be cleaned, that the overall system will be stable and that there is a viable operation and maintenance entity. HORNE's project can be effectively operated and maintained. Remaining District Rule Criteria As stipulated to by the parties that the project will not cause adverse impacts to wetlands and will not diminish the capability of a lake or other impoundment to fluctuate through the full range established for it in Chapter 40D Additionally, the proof establishes that the project will not cause adverse impacts on surface and groundwater levels and flows will not adversely affect the public health and safety; is consistent with the requirements of other public agencies; will not otherwise be harmful to the water resources within the District; will not interfere with the legal rights of others as defined in Rule 17 Objections Raised by the ASSOCIATES at the Hearing Pond Slopes and Operation and Maintenance Contrary to the assertion that the pond slopes will not be stable and cannot be effectively operated and maintained, the pond side slopes at this project are going to be constructed out of a heavy clay type of soil. Sodded side slopes of 1:1, as proposed for three of the ponds, can be stabilized and effectively operated and maintained. Although there is no DISTRICT requirement that sodded side slopes be mowed, so on these slopes could, if necessary, be cut. In the event the side slopes were to erode, easy repair is possible. All of the ponds except one side of one pond have areas at least 20 feet wide and slopes no steeper than 4:1 where maintenance can be performed. With regard to the pond that does not have this characteristic, equipment can enter and perform necessary maintenance. Water Quality Treatment Concerns that at least a portion of the bottoms of the ponds need to be below the seasonal high water table and that circulation of the ponds needs to be maximized in order to meet water quality treatment criteria are misplaced since there is no requirement that the pond bottoms be below the seasonal high water table in wet detention systems such as the one at issue in this case. Further, the entire bottoms of the ponds are littoral zone and meet DISTRICT rule requirements that 35 per cent of the pond be littoral zone, concentrated at the outfall. Additionally, the ponds at issue maximize circulation through the location of points of inflow and outflow. Floodplain Mitigation Concerns that volume in the floodplain mitigation area is not available because of problems with the seasonal high water table are also misplaced. Specifically, the floodplain area encroachment requiring mitigation relates to Pond 5A. There is more than enough volume within the area which will be excavated to compensate for the area where the fill will be deposited. The seasonal high water table will be at or below the floodplain mitigation area after the required excavation takes place. Although the seasonal high water table will be lowered where the excavation or cut is made and later raised where the fill is placed, no adverse effects on the water table will result from such lowering and raising of the water table. Volume In Pond 5A Allegations that the May 12 and 13 submittals reflect that Pond 5A has less volume available than the modeling calculations contemplate are incorrect. The changes in the contour lines of Pond 5A on the May 12 and 13 submittals from what was shown on the April 1 submittal occurred on the outside of the pond. The volume on the inside of the pond was not reduced actually increased when the pond bottom was lowered for water quality purposes. In determining how much volume a pond is to have when it is constructed, the computer modeling figures take precedence over the scaled plan drawings. In this case, the computer modeling figures never changed after the April 1 submittal. HORNE submitted a computer model that calculated the volume of Pond 5A. The output data clearly reflects that the top of the bank was 82 feet. Publix's Status as an Existing Site Assertions that the Publix site should have been considered in its pre-developed state since there will be approximately one acre foot of volume of runoff, or possibly less, leaving the site without retention are without validity. The Publix plaza was permitted by the DISTRICT in 1985 and constructed in 1986. The amount of peak flow discharge and overall discharge is currently authorized by a valid MSSW permit. When the DISTRICT reviews a permit application, all existing permitted surface water management systems must be accepted in their present state. There is no authority in the DISTRICT's rules to consider an existing permitted site in its pre Even if the Publix site is considered in its pre project has only .02 of an acre foot more volume of runoff in its post-developed condition than in the pre Storage of 100-Year Volume Allegations that the amount of 100-year volume being retained on site in the ponds has been incorrectly calculated by the DISTRICT and HORNE are also invalid. The DISTRICT's rules require that the difference between the pre- and post-development volume for the 100-year storm be retained on site. In the ponds which are the subject of this proceeding, the 100-year volume is retained in the ponds below the orifice. This volume cannot leave the site through the orifice; it can only leave the site by percolation into the ground or evaporation into the air.

Recommendation Based on the foregoing, it is recommended that the Southwest Florida Water Management District enter a final order granting HORNE's Application for Surface Water Management Permit No. 400317.02. RECOMMENDED this 25th day of June, 1993, in Tallahassee, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 1993. APPENDIX The following constitutes my rulings, in accordance with Section 120.59, Florida Statutes, on proposed findings of fact submitted by the parties Proposed findings submitted by Petitioners (Petitioner's proposed findings begin at paragraph number 13.) 13.-19. Accepted. 20.-30. Rejected, unnecessary. 31.-44. Rejected, subordinate to hearing officer findings. 45.-47. Accepted. 48.-77. Rejected, subordinate to hearing officer findings. 78.-79. Rejected, recitation of documents. 80.-84. Rejected, weight of the evidence. 85.-88. Rejected, unnecessary. 89.-93. Rejected, weight of the evidence. 94.-95. Rejected, unnecessary. 96. Accepted. 97.-98. Rejected, subordinate, weight of the evidence. 99.-100. Rejected, unnecessary. 101.-126. Rejected, subordinate. 127. Accepted. 128.-129. Rejected, unnecessary. 130.-135. Rejected, argument. 136.-144. Rejected, weight of the evidence. Respondents Joint Proposed Findings. 1.-56. Accepted, though not verbatim. 58.-59. Rejected, unnecessary. COPIES FURNISHED: David Smolker, Esquire Honigman, Miller, Schwartz & Cohn 2700 Landmark Centre 401 East Jackson Street Tampa, Florida 33602 Rodney S. Fields, Jr., Esquire Blain & Cone, P.A. 202 Madison Street Tampa, Florida 33602 Richard Tschantz, Esquire Mark F. Lapp, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, FL 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (1) 40D-4.301
# 9
MICHAEL C. BROWN vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT AND CENTEX HOMES, 04-000476 (2004)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Feb. 04, 2004 Number: 04-000476 Latest Update: Sep. 13, 2004

The Issue The issues are whether Respondent Centex Homes is entitled to the issuance of an environmental resource permit to construct a 2665 square-foot boat dock and authorization of a lease of 7807 square feet of sovereign submerged land in the portion of the Intracoastal Waterway known as Lake Worth Lagoon in Palm Beach County.

Findings Of Fact In this case, Respondent South Florida Water Management District (District) has proposed to issue to Respondent Centex Homes (Centex) an environmental resource permit (ERP) and authorization to lease sovereign submerged land. The purpose of the ERP and lease authorization is for Centex to construct a dock to serve a multifamily development known as Ocean Cay. Ocean Cay is a 56-unit townhouse development located on a five-acre parcel in Hypoluxo, Florida, bordered on the west by U.S. Highway 1, on the east by the Lake Worth Lagoon, and on the north and south by developed residential areas. At the time of the hearing, Centex had closed on the sale of 50 of the residential units, was finishing construction of the final six units, and had entered into contracts to sell three of these six units. The Lake Worth Lagoon is a Class III water and is not an aquatic preserve. The Intracoastal Waterway channel is in the middle of the lagoon. The proposed dock would be about 1.5 miles north of the South Lake Worth Inlet (a/k/a Boynton Inlet) and 13 miles south of the Lake Worth Inlet (a/k/a Palm Beach Inlet). As measured from the project location to the opposite shoreline, the length of the dock is more than 25 percent of the width of the waterbody. Petitioner Michael C. Brown resides at 131 Las Brisas Circle, Hypoluxo, Florida. Intervenor O'Brien resides at 124 Park Lane East, Hypoluxo, Florida. Intervenors Evlyn and Vern Hakes reside at 140 Park Lane East, Hypoluxo, Florida. As stipulated by Respondents, Petitioner and Intervenors have standing, so this Recommended Order will not restate the substantial evidence in the record of the standing of Petitioner and Intervenors. Three of the objections raised by Petitioner and Intervenors involve procedural issues that are easily dismissed on factual grounds. The first objection is that Centex lacks the requisite equitable interest in the upland to obtain a lease of sovereign submerged land. The second objection is that the Ocean Cay Homeowners' Association lacks the financial, legal, and administrative resources to ensure the performance of all permitting obligations, as they may arise in the future. The third objection is that District staff, not the Governing Board of District, issued the proposed agency action on the ERP. As for the first procedural objection, Centex acquired the parcel by special warranty deed, which vests fee simple interest in Centex and contains all the customary warranties of title. The title insurance policy obtained by Centex for the parcel insures fee simple interest in Centex, subject to undescribed reservations contained in the deed from the Board Trustees of the Internal Improvement Trust Fund (Trustees), any part of the parcel lying below the mean high water line, and public rights "to use the waters over the submerged land lying adjacent to or within the Intercoastal [sic] Waterway for boating, fishing, swimming and other public purposes, together with the rights of the State of Florida and United States to regulate the use of the navigable waters." Not only does Centex enjoy full beneficial ownership of the upland, subject to the rights of its grantees who have purchased townhouse units, but Centex's title extends approximately 250 feet waterward of the mean high water line by operation of a deed from the Trustees to a predecessor in interest of Centex. If the ownership of submerged land between the submerged land for which an applicant seeks a lease and adjacent uplands also owned by an applicant has any effect at all, it only emphasizes the legitimate, nonspeculative interest of such an applicant in obtaining the sought-after lease. As for the second procedural objection, Centex is a sophisticated land-development entity with ample financial, legal, and administrative resources to ensure the satisfaction of any permitting obligations imposed upon it in connection with this case. At present, Centex controls the Ocean Cay Homeowners' Association. So, at present, the concerns of Petitioner and Intervenors about the ability of the homeowners' association to satisfy its obligations are unfounded. It is true that, upon the closing of the sale of sufficient units, Centex will transfer control of the homeowners' association to the homeowners. The record does not describe the financial, legal, and administrative resources of the homeowners' association following the withdrawal of Centex, but they will presumably not approach the substantial resources of Centex. District claims that Centex may not transfer the ERP without District's approval; however, ERP Special Condition 2 identifies the operating entity responsible for the docking facility as Ocean Cay Homeowners' Association, even though the ERP identifies the applicant as Centex. Fatal to the argument of Petitioner and Intervenors, though, are the facts that the proposed lease of sovereign submerged land is for only five years, a failure to discharge permit obligations that should be incorporated verbatim into the lease militates against any lease renewals, and the removal of the dock would substantially cure any deficiencies in its maintenance. As for the third procedural objection, District staff, on November 21, 2003, proposed to issue a standard general ERP for the construction and operation of a 2665 square-foot docking facility with nine boat slips for use by the residents of Ocean Cay and to approve the lease of 7807 square feet of sovereign submerged land under and surrounding the docking facility. Staff issues a proposed standard general ERP when a permit does not conflict with existing law or policy or a work of the District. District's Governing Board issues a proposed standard individual ERP in the relatively rare case in which a permit conflicts with existing law or policy or a work of the District. Again, the objections of Petitioner and Intervenors lack factual support. Here, the Governing Board, not staff, will receive the Recommended Order and issue the Final Order. So, as Petitioner and Intervenors wish, the Governing Board, not staff, will take the final agency action in this case. Under these circumstances, the record reveals no harm in the fact that District staff issued the proposed agency action. The remainder of the ERP provisions bears on the substantive objections raised by Petitioner and Intervenors. As amended at the final hearing by District and accepted by Centex, ERP Special Condition 9 provides: A permanent sign shall be installed at the docking facility entrance to notify boat owners that mooring at the docking facility shall be limited to no more than a total of nine vessels. Vessels moored in slips 1-2 and 7-9 shall be limited to outboard powered vessels, not more than 27 feet in length as reported by the manufacturer exclusive of engines and any bow pulpit. Vessels moored in slips 3 and 6 shall be limited to not more than 27 feet in length as reported by the manufacturer exclusive of engines and any bow pulpit. Vessels moored in slips 3 and 6 are not limited to outboard power. Vessels moored in slips 4 and 5 shall be limited to 36 feet in length, as reported by the manufacturer exclusive of engines and any bow pulpit. Vessels in slips 4 and 5 are not limited to outboard power. Slips are identified by number in the discussion below. As amended at the final hearing by District and accepted by Centex, ERP Special Condition 10 provides: "Dock, walkway, and seagrass sign pilings shall be constructed of plastic, concrete or greenheart, non-CCA treated wood or wood wrapped in 30 to 60 mil pvc." ERP Special Condition 11 provides that construction of the dock shall be in accordance with the locations and dimensions shown on the enclosed exhibits. The referenced drawings depict the adjacent upland, submerged bottom, and proposed dock. The drawings describe sufficient detail of the adjacent upland. The north and south property lines of the 190- foot wide parcel run due east and west. At mean high water, the parcel's shoreline runs about 210 feet in a south-southwesterly direction from the north property line. Waterward of the mean high water line is a thin band of sand, varying portions of which are exposed between mean high water and mean low water. The drawings describe the submerged bottom in great detail as to seagrass and reasonable detail as to water depths. Waterward of the beach is a band of Halodule wrightii (shoal grass). The drawings describe the shoal grass in this area as "sparse." The drawings depict mean low water depths along three transects at 25-foot intervals, starting roughly at the landward commencement of the shoal grass. (All water depths are based on mean low water.) If the property lines were extended into the water, the north transect is 25 feet south of the north property line, and the south transect is 25 feet north of the south property line. The middle transect is an equal distance between the north and south transects. Along the north transect, the band of shoal grass is about 25 feet wide. Along the south transect, the band narrows to about six feet wide. Along the middle transect, the band is about 50 feet wide. Waterward of the band of sparse shoal grass, according to the drawings, is a band of "mixed Halodule and sparse Johnson's." The reference to "Johnson's" is to Halophila johnsonii (Johnson's grass), which is a rare species of seagrass that is listed by the U.S. Environmental Protection Agency as threatened. 50 C.F.R. § 17.12(h). Johnson's grass is found only on the east coast of Florida from the Indian River Lagoon to Biscayne Bay and is a fragile species of seagrass. The band of mixed shoal grass and sparse Johnson's grass reflects the same pattern as the shoal grass closer to shore: thinner at the north and south ends and wider in the middle. Along the north transect, the band of the two species is about 162 feet wide. Along the south transect, the band is about 212 feet wide. Along the middle transect, the band is about 240 feet wide. Waterward of the middle band of mixed shoal grass and sparse Johnson's grass, according to the drawings, is "scattered isolated blades of H. Decipiens and [Johnson's grass]." "H. Decipiens" is Halophila decipiens (paddle grass). Waterward of the north and south ends of the mixed shoal grass and sparse Johnson's grass are triangular-shaped areas of "sparse Johnson's." Along the north transect, this band of sparse Johnson's grass is about 75 feet wide. Along the south transect, this band of sparse Johnson's grass is about 50 feet wide. Waterward of these bands of sparse Johnson's grass is "scattered, isolated blades of H. Decipiens and [Johnson's grass]." Measured from the mean high water line, the band of mixed shoal grass and sparse Johnson's grass extends about 275 feet along the north transect, 312 feet along the middle transect, and 300 feet along the south transect. Water depths are shallow throughout almost the entire project area. Starting from shore, water depths are almost entirely less than 1.0 feet within the area of sparse shoal grass, although depths reach 1.2 feet along the middle transect. Proceeding waterward along the north transect, the depths within the area of mixed shoal grass and sparse Johnson's grass range from 0.7 feet at the landward end to 2.2 feet at the waterward end. Proceeding waterward along the middle transect, the depths within the area of mixed shoal grass and sparse Johnson's grass range from 1.2 feet to 4.2 feet. Proceeding waterward along the south transect, the depths within the area of mixed shoal grass and sparse Johnson's grass range from 1.0 feet to 2.7 feet. The water continues to deepen in the triangular-shaped areas of sparse Johnson's grass, through which the north and south transects run. Along the north transect, the water depths range from 2.2 feet to 3.1 feet. Along the south transect, the water depths range from 2.7 feet to 3.6 feet. The drawings depict depths waterward of the start of scattered, isolated blades of paddle grass and Johnson's grass. These reported depths extend to a point roughly parallel to the end of the proposed dock along the north transect, about 12 feet waterward of the end of the proposed dock along the middle transect, and about 37 feet waterward of the end of the proposed dock along the south transect. Along the north transect, the depths remain constant, at about 3.5 feet, until the most waterward 25 feet, along which the water deepens 0.5 feet to 4.1 feet. Along the middle transect, the depths deepen about 0.5 feet to around 5.0 feet for about 75 feet, then deepen to 5.4 feet a few feet landward of the most waterward portion of the dock. About 10 feet waterward of the end of the dock, the depth reaches 5.7 feet, which is the deepest reported depth in the project area. Along the south transect, the depths deepen about one foot over the first 100 feet waterward from the start of the scattered, isolated blades of paddle grass and Johnson's grass. From a point parallel to the end of the dock, the water along the south transect deepens another 0.5 feet to about 5.2 feet. The drawings also describe the proposed dock in great detail. The dock, oriented due east and west, runs a distance of 420 feet from its landing, at the mean high water line, to its waterward terminus. The dock is four feet wide, except for a 10-foot long section, at about midpoint, that is six feet wide to facilitate wheelchair access. At the urging of District, to reduce seagrass impacts, Centex moved the dock ten feet south and extended it ten additional feet into deeper water. Because of the former of these modifications, the dock runs ten feet south of the middle transect. The main deck of the dock is grated, so as to allow at least 46 percent of the light to pass through it, from the waterward extent of the sparse shoal grass to the waterward extent of the mixed shoal grass and sparse Johnson's grass, which is a distance of about 250 feet. Although the drawings specify only a value of 46 percent light transmissibility, testimony established that this criterion would require the use of fiberglass decking material. Perhaps the most prominent feature of the dock, in addition to its length, is its height. The deck is five feet above mean high water. Mean high water is 1.7 feet National Geodetic Vertical Datum (NGVD). Mean low water is -0.8 feet NGVD. Five decks run perpendicular to the main deck--three on the south side and two on the north side--to form the slips at the waterward terminus of the dock. The most landward of these decks is four feet wide and 30-feet long and runs south of the main deck, at a point about 330 feet waterward of the landing. Two more decks, both of the same dimensions as the first deck, join the main deck at a point about 375 feet waterward of the landing. Thirty-eight feet separate the two southern decks, so that the two slips created between them (Slips 9 and 8, from landward to waterward) each is 18-19 feet wide. The most landward slip formed north of the main deck (Slip 1) is also 18-19 feet wide. Two pilings north of the main deck and two pilings south of the main deck define these first three slips. The remaining perpendicular decks form the terminus of the entire dock. These decks are eight-feet wide and run 38 feet north and 38 feet south of the edges of the main deck. The four slips immediately landward of these decks are 18-19 feet wide. Moving clockwise from the northwest corner, these slips are Slips 2, 3, 6, and 7. The remaining two slips are waterward of the eight-foot wide deck. The northern slip is Slip 4, and the southern slip is Slip 5. According to the drawings, the waterward extent of the proposed lease is 18 feet waterward of the waterward end of the dock. The waterward extent of the proposed lease is 425 feet from the landward end of the Intracoastal Waterway channel (the 415 feet shown in the drawings is wrong), which, as established by testimony, is 125 feet wide at this location. The drawings also depict a 42-inch high handrail running from the landing to the most landward perpendicular deck. The purpose of the handrail, whose vertical slats are eight inches apart, is to discourage mooring of vessels to the main dock landward of the slips. Every 50 feet, at the base of the handrails on either side of the dock, is a sign prohibiting docking, mooring, loading, or unloading of vessels. At the terminus of the dock, the drawings show a rock crib structure that rises about one foot from the submerged bottom along the entire 80-foot length of the eight-foot wide perpendicular deck. Apparently, the rock crib is eight-feet wide, so that it extends, beneath the surface of the water, under the entire area of the eight-foot wide perpendicular deck. Extending above the rock crib, along this 80-foot long deck, is a wave attenuator. The drawings also depict a couple of seagrass warning signs north and south of the dock, about 20-30 feet waterward of the waterward extent of the sparse Johnson's grass, at the north and south portions of the project area, and the mixed shoal grass and sparse Johnson's grass, in the middle of the project area, just a few feet north of the dock. The drawings also show pilings at a minimum of 10-foot intervals along the entire length of the main deck, as well as pilings for the perpendicular decks at the dock's terminus. Special Condition 12 prohibits fueling facilities or hull-painting or -cleaning at the dock. Special Condition 13 prohibits liveaboards. Special Condition prohibits subleasing of the docking facilities and limits their use to residents of Ocean Cay. Special Conditions 14 and 15 detail various manatee- protection provisions. Special Condition 19 requires the implementation of a turbidity-control plan during construction. Special Condition 18 prohibits construction under the ERP until the Department of Environmental Protection has issued a submerged land lease. As amended at the final hearing by District and accepted by Centex, Special Condition 20 requires Centex to maintain at least one trash receptacle at the terminus of the dock. The District staff report states that Centex has minimized the impacts of the project by reducing the length of the dock from 550 feet and its capacity from 22 slips. The staff report notes, as mentioned above, the relocation of the dock ten feet to the south and ten feet waterward, both changes to reduce impacts on seagrasses. The District staff report states that manatees probably use the area of the project for travel and foraging nearshore seagrass beds. Concerning the lease of sovereign submerged land, the District staff report acknowledges the waterward extent of Centex's ownership of submerged lands. As for the sovereign submerged land, the District staff report states, without explanation, that the docking facility is not more than 25 percent of the width of the "navigable portion of the waterbody," pursuant to Florida Administrative Code Rule 18-21.004(4)(a)3, and is more than 100 feet from the federal navigation channel, as required by Florida Administrative Code Rule 18-21.004(4)(a)4. The District staff report attaches "Recommended Special Lease Conditions for Ocean Cay." These include a restriction that vessels moored at the dock clear the submerged bottom by at least one foot at all times while moored. Other provisions correspond to the special conditions attaching to the ERP, as described above. As discussed in the Conclusions of Law, analysis of the proposed activity requires three determinations: first, does the proposed activity, unmitigated, adversely impact surface waters; second, if so, has Centex reduced or eliminated all such impacts through design modifications to the extent practicable; and third, if so, but if net impacts remain, has Centex adequately mitigated these net impacts? Absent mitigation, the construction of a 420-foot dock covering 2665 square-feet of water adversely impacts the water resources, most obviously by the immediate destruction of the seagrasses occupying the area in which at least 80 pilings will be installed and by the gradual destruction of the seagrasses that will be shaded by the dock and lose the light necessary for survival. Centex has incorporated into the proposed dock design all practicable modifications that could eliminate or reduce these adverse impacts to the surface waters. Centex has proposed a dock that is narrow, high, translucent, and nontoxic. To minimize the risk of prop dredging of the seagrass and bottom sediments, the dock's length and railings would limit mooring to relatively deeper water, and the boat-length restriction would effectively limit the reach of prop dredging. Even after these design modifications, however, adverse impacts to the surface waters remain that Centex must mitigate. The ultimate issue, then, is whether Centex has adequately mitigated the remaining impacts of the proposed activity by proposing sufficient affirmative acts to offset the remaining adverse impacts. Strictly speaking, mitigation consists of activities that are unnecessary for the desired activity--here, the construction of a dock--but are performed to offset the adverse impacts of the desired activity. In this case, Centex proposes three mitigation activities: the construction of a rock crib, the installation of a wave attenuator, and the erection of two seagrass warning signs. The adequacy of this proposed mitigation requires identification of the specific impacts to the surface waters and the efficacy of the mitigation in offsetting these impacts. As cited in the Conclusions of Law, the public-interest criteria set forth the elements requiring consideration. Except to the extent discussed in navigation, the dock will not adversely affect the public health, safety, or welfare or property of others. The narrow, long dock, which restricts mooring activity to its terminus over 400 feet from the shoreline, has no impact on the riparian rights of adjacent or nearby upland owners. Thus, no mitigation is necessary for this criterion. Even after mitigation, the dock will adversely affect the conservation of fish and wildlife, including listed species, and their habitats. The most immediate impact of the dock is upon the seagrasses that presently grow on the bottom. Seagrasses, which are among the most productive communities known to nature, are vital to the health of the Lake Worth Lagoon. Seagrasses perform numerous functions important to the surface waters and, specifically, the conservation of fish and wildlife and their habitats: shelter for small fish and shellfish; food for a variety of small and larger organisms, including manatee and sea turtles; stabilization of bottom sediments, which improves water clarity; recycling of nutrients, including nitrogen--an important function for the water quality of the nitrogen-limited Lake Worth Lagoon; and formation of a substrate on which epiphytes may attach and provide food for a variety of organisms, including manatee and sea turtles. The mitigation activities offset some, but not all, of the functions provided by the seagrass that are lost by the construction of the dock. The rock crib probably will replace the function of the seagrass in stabilizing sediments. The rock crib probably will replicate some of the shelter function of the seagrass, although nothing in the record would support a finding that the crevices of the rock crib provide exactly the same shelter as the seagrass patches that will be destroyed by the dock. Thus, there is no basis to assume that the shelter functions of the seagrass are replaced by the shelter functions of the rock crib. Undoubtedly, the rock crib will not replace the food function of the seagrass. Some predators may find the same juvenile fish in the rock crib as they have found in the seagrass, and some organisms may find the same epiphytes attaching to the rock crib as they have found attaching to the seagrass. However, the organisms, such as manatee and sea turtles, that eat the seagrass itself will find the rock crib a poor food substitute. Additionally, the rock crib will perform none of the nutrient-fixing that seagrasses perform. The rock crib thus fails to perform the vital functions of seagrass in providing food for important species, such as the manatee, and fixing nutrients, which is important to improving or maintaining water quality. The wave attenuator is a potentially useful form of mitigation. Although a slight over-generalization, the seagrass thins to the point of near disappearance at a point in which the slope of the submerged bottom breaks--very roughly at about three feet deep. Centex's witnesses offered the better explanation of this phenomenon by linking it to the strong wakes produced by vessels motoring in the Intracoastal Waterway. Although the area of the proposed project is permanently slow speed, no wake, the Intracoastal Waterway channel has no speed limit, and the wakes from vessels in the channel pound the shallows, focusing considerable energy upon the rising bottom at the point at which the water depth reduces to three feet. The main problem with the wave attenuator as mitigation is one of scale. Nothing in the record suggests that the attenuator, even in conjunction with the rock crib beneath it, will attenuate the incoming waves along the entire length of the dock. The attenuator will absorb the energy of the waves, whether from passing vessels or storms, but the interrupted waves will rejoin a short distance landward of the attenuator, possibly waterward of the first appearance of significant seagrass. The wave attenuator is thus inadequate in preserving or enhancing the remaining seagrass following the construction of the dock. The signs suffer two shortcomings. First, they are as likely to attract fishers as they are to deter recreational boaters, so the record permits no finding as to their efficacy in preserving or enhancing the remaining seagrass following the construction of the dock. Second, the record discloses little prop dredging of the seagrasses in the proposed vicinity of the dock, so the effect of the signs is not to ameliorate the damage historically done in this area by boats. To the contrary, at best, the signs may reduce some of the prop dredging that would occur in the future by boats drawn close to shore by the presence of the dock, which will attract fish and, thus, fishers. For these reasons, the signs are inadequate mitigation. Considered in conjunction with each other, the three mitigation activities fail to address the important food and nutrient-fixing functions of the seagrass that would be destroyed by the dock. Ignoring the failure of the proposed mitigation to address two of the most important functions of the seagrass, District and Centex contend that the mitigation is adequate for other reasons. District and Centex contend that the loss of seagrass is de minimis, consisting of not more than .03 acres of destroyed seagrass, or about 2.2 percent of the seagrass in the project area. Although the east-west orientation of the dock results in more shading than an identical dock oriented north- south, the shading loss could be less due to commendable design modifications involving the width, height, and translucent materials of the dock. Adding to the loss of seagrass from shading is the loss from the "halo effect," which is the wider area of seagrass loss probably resulting from the effect of the dock in artificially attracting and retaining seagrass consumers, like parrot fish. The record thus affords no basis for a finding of a loss of less than .03 acres. Nor does the record afford any basis for determining that the seagrass loss is de minimis. If Lake Worth Lagoon has seagrass to spare, the record does not support such a finding. If the lost functions of the seagrass--primarily, providing food and fixing nutrients--are not de minimis, the question remains whether practicable mitigation for these functions exists. Although transplantation of seagrass may be impracticable due to poor water clarity, even one of Centex's experts noted the importance of filling holes for seagrass recruitment, given the inability of seagrass to extend roots laterally up or down slopes. District's expert identified backfilling submerged holes and scraping spoil islands as two means of encouraging natural seagrass recruitment. District's expert noted a practical consideration favoring rock cribs versus more elaborate, higher-maintenance mitigation. Rock cribs are low- or no-maintenance projects that require no monitoring, enforcement, or enhancement. However, these same considerations underscore the complexity of the functions provided by seagrass lost to the proposed activity. Mitigating the loss of these functions may be difficult and high-maintenance, if the mitigation is to offset the loss. On this record, a finding of impracticability of such mitigation activities would be speculative, given the absence of evidence of impracticability, such as in the form of the absence of nearby depressions with suitable recruitment conditions or seagrass restoration projects in which Centex could participate. An unusual factor militating against a finding of adequate mitigation is that one of the seagrasses is itself a protected species. Johnson's grass is rare and fragile. The dock would displace Johnson's grass in a location less than one mile north of one of ten federally designated Critical Habitats for Johnson's Seagrass and one of two such habitats in Lake Worth Lagoon. 50 C.F.R. § 226.213(h). In contrast to the permit conditions directly protecting the manatee, the record is silent as to any effort by District to coordinate this permit with the work of the federal government and possibly the state and local governments to preserve Lake Worth Lagoon's seagrass, including the threatened Johnson's grass. On balance, even after mitigation, the dock will adversely affect the conservation of fish and wildlife, including listed species, and their habitats. The dock will not adversely affect navigation, the flow of water, and erosion or shoaling. Located only 1.5 miles from the inlet, tidal flows are good in the project area. The rock crib and wave attenuator, which tend to restrict east-west flows and waves, will have little impact on the tidal flows, which are predominantly in a north-south direction. The dock will not cause any erosion or shoaling. The dock will be lighted and should not present a navigation hazard. Larger vessels will remain a safe distance from the dock as they travel in the Intracoastal Waterway channel. Under normal boating conditions, small boats, such as kayaks, canoes, and small motorboats, can safety navigate under the five-foot deck and between the pilings spaced at a minimum distance of ten feet apart. The dock will not adversely affect the fishing or recreational values in the vicinity. To the contrary, the structure provided by the dock will probably attract and concentrate fish, making them easier to catch. In the longer term, even after mitigation, the dock will adversely affect marine productivity for the reasons discussed in connection with the conservation of fish and wildlife and their habitat. The dock will not adversely affect any historical or archaeological resources. Even after mitigation, the dock will adversely affect the current conditions and relative value of functions for the reasons discussed in connection with the conservation of fish and wildlife and their habitat. For the reasons set forth above, Centex has failed to provide reasonable assurance that the proposed activity, even after mitigation, is not harmful to the District's water resources, is not inconsistent with District's overall objectives, is not contrary to the public interest, will not adversely impact the value of functions provided to fish and wildlife and listed species by surface waters, and will not cause adverse secondary impacts to the water resources

Recommendation It is RECOMMENDED that the South Florida Water Management District enter a final order denying Centex Homes' request for an environmental resource permit and approval to lease sovereign submerged lands for the purpose of constructing the above- described dock at Ocean Cay in the Lake Worth Lagoon. DONE AND ENTERED this 2nd day of August, 2004, in Tallahassee, Leon County, Florida. S ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 2004. COPIES FURNISHED: Henry Dean, Executive Director South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida Marcy I. LaHart 33416-4680 Marcy I. LaHart, P.A. 711 Talladega Street West Palm Beach, Florida 33405 Ashley D. Foster South Florida Water Management District 3301 Gun Club Road Mail Stop Code 1410 West Palm Beach, Florida 33406 J. Kendrick Tucker Huey, Guilday, Tucker, Schwartz & Williams, P.A. Post Office Box 12500 Tallahassee, Florida 32317-2500

CFR (1) 50 CFR 17.12(h) Florida Laws (18) 120.569120.5717.12253.01253.02253.03267.061373.042373.086373.413373.4136373.414373.416373.421373.427373.43040.011403.031
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer