Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
INDUSTRIAL ENTERPRISES SANDBLAST AND PAINTING, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003592BID (1985)
Division of Administrative Hearings, Florida Number: 85-003592BID Latest Update: Dec. 11, 1985

Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547

Florida Laws (2) 120.57337.11
# 2
CHD MARKETING GROUP AND NORLAKE, INC. vs PALM BEACH COUNTY SCHOOL BOARD, 92-003135BID (1992)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 22, 1992 Number: 92-003135BID Latest Update: Dec. 14, 1992

Findings Of Fact Respondent issued an invitation to bid on March 13, 1992. Bid number SB 92-244I involved the disassembly and removal of an existing walk-in freezer and the furnishing and installation of a new walk-in freezer at Coral Sunset Elementary School. The invitations to bid provided in paragraph Y of the Special Conditions: Failure to file a specification protest within the time prescribed in Florida Statutes 120.53 3.(b) shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. (sic) Bid specifications were included in the invitations to bid issued on March 13, 1992. Twenty-three bids were solicited. There were five responses. One of the responses was submitted by Choice Restaurant Equipment, Inc. ("Choice"). Choice is a vendor for equipment manufactured by Petitioner, Nor-Lake, Inc. ("Nor-Lake"). Nor-Lake is an out-of-state corporation with manufacturer's representatives in numerous states including Florida. 4, Petitioner, CHD Marketing Group ("CHD"), is the manufacturer's representative for Nor-Lake in Florida. CHD represents no other manufacturer of the product included in the bid response. Choice is a sales agent for CHD and other manufacturer's representatives in Florida. Choice sells the products of a variety of manufacturers but is the exclusive sales agent for CHD pursuant to a verbal agency agreement. Choice timely submitted a bid for bid number SB 92-244I on April 8, 1992, prior to the bid deadline of 2:00 p.m. on the same day. The successful bidder submitted its bid by Federal Express at 4:51 p.m on April 8, 1992. Respondent's Department of Purchasing and Stores (the "Department") had stated on March 13, 1992, when the invitations to bid were issued, that bid responses must be received by the Department no later than 2:00 p.m. on April 8, 1992, at the Department's address at 3980 RCA Boulevard/Suite 8044, Palm Beach Gardens, Florida, 33410-4276. Prior to April 8, 1992, the Department relocated to a new facility at 3326 Forest Hill Boulevard, West Palm Beach, Florida. The new address was posted at the old location and Department representatives were present at the old address to accept walk-in bids. Federal Express first attempted to deliver the successful bid at the Department's old address at 10:30 a.m. on April 8, 1992. Federal Express delivered the successful bid to the Department's new address at 4:51 p.m. At 2:00 p.m. on the same day, The Department announced that all bids were in and opened the bids that had been delivered. The successful bid and one other bid were delivered on April 8, 1992, after the public opening conducted at 2:00 p.m. on the same day. Bids were tabulated on April 9, 1992. Bid tabulations were posted on April 13, 1992, and the successful bid was announced. The successful bid was for $8,174.00. Three bids were lower than the successful bid. Choice's bid was for $7,742.56. The other two lower bids were for $8,020.00 and $6,620.00. All three lower bids were rejected as non- responsive. Choice's bid was rejected because it did not meet bid specifications for 22 gauge steel, thermostatically controlled door heaters, and reinforced steel door panels. CHD filed a Notice of Protest on April 14, 1992, and a Formal Written Protest on April 24, 1992. CHD's protest alleges that: Choice's bid was lower than that of the successful bidder; the successful bid was not timely made; the bids were not opened publicly in violation of bidding procedure requirements; and the bid specifications were arbitrary and capricious, favored one bidder, and that Choice's bid was responsive. Neither a notice of protest nor a formal written protest was submitted by Choice or Nor-Lake. Neither Choice nor Nor-Lake attended the informal protest conference conducted on April 30, 1992. On May 7, 1992, Respondent's Office of General Counsel issued its written notice of proposed agency action. The written notice recommended that the bid be awarded to the successful bidder and that CHD's protest be dismissed for lack of standing. CHD requested a formal hearing on May 14, 1992, and the matter was referred to the Division of Administrative Hearings for assignment of a hearing officer on May 15, 1992. The bid submitted by Choice was prepared by CHD but signed by the president of Choice. Neither Nor-Lake nor CHD signed a bid or were otherwise bidders of record for bid number SB 92-244I. Neither Choice, CHD, nor Nor-Lake, filed a notice of protest concerning the bid specifications within 72 hours after Choice received the notice of the project plans and specifications on March 13, 1992. The sole basis upon which CHD claims it is substantially affected is the adverse economic impact caused to it by the proposed agency action. The proposed agency action will result in lost sales from this and future transactions. CHD will lose commissions from this and future transactions. The dealer relationship between CHD and Choice will be damaged because Choice will not want to sell a freezer that is not acceptable to Respondent. The marketing strategy developed between CHD and Nor-Lake will be damaged because it is conditioned upon the award of public contracts.

Florida Laws (1) 120.53
# 3
WESTON INSTRUMENTS, INC. vs. HARRIS CORPORATION, HATHAWAY INSTRUMENTS, INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 75-002110BID (1975)
Division of Administrative Hearings, Florida Number: 75-002110BID Latest Update: Oct. 05, 1977

Findings Of Fact In August, 1975, the Department of General Services invited competitive bids for the purchase of supervisory and control equipment and revenue metering equipment for expansion of primary electric utilities in the Capitol Center, a project known as State Project No. DGS-6026/6424, AEP File No. 74288-003. Plans and specifications for the project were developed by the department's consulting architect/engineers Reynolds, Smith and Hills. The Department of General Services (hereinafter Department) and Reynolds, Smith and Hills (hereinafter Reynolds) conducted formal bid opening on September 25, 1975. Bid proposals were received from petitioner, Weston Instruments, Inc. (hereinafter Weston), and from Respondents, Harris Corporation (hereinafter Harris) and Hathaway Instruments, Inc. (hereinafter Hathaway). The amount of the bids were as follows: CONTRACTOR BASE BID ALTERNATE NO. 1-ADD TOTAL Harris 332,000.00 28,649.00 360,649.00 Weston 338,991.00 20,965.00 359,996.00 Hathaway 343,429.00 33,224.00 376,653.00 Hathaway's bid as submitted was responsive to the specifications and other requirements of the bid invitation. Weston's bid was responsive to the specifications and requirements of the bid invitation with the following exception. Specification B-2, in its second paragraph, states: "In order to facilitate the execution of the Agreement, the Bidder shall submit with his proposal a list of and brief description of similar work satisfactorily completed, with location, date of contracts, together with names and addresses of Owners." Weston did not submit that information with its bid but did submit that information on October 9, 1975. The Harris bid as submitted was not responsive to the specifications and requirements of the bid invitation. The material deviations from the specifications found in the Harris bid are as follows: Paragraph 16755-13(c) of the specifications states that data logger equipment by Teletype, Lear Siegler or General Electric will be considered. The Harris bid proposed a data logger manufactured by Practical Automation, Inc. and noted that if Harris was required to conform to the specifications by furnishing a data logger manufactured by one of the three specified manufacturers, its base bid would have to be increased by $635.00. Paragraph 16755-18 of the specifications requires a specific number of supervisory functions at each of the nineteen locations. The Harris bid met the requirements of the specifications at only one of the nineteen locations. At each of the other eighteen locations the Harris bid was from one to three supervisory points deficient. According to the evidence presented it would cost between $250 to $300 per location to furnish the supervisory points left out of Harris' bid. Paragraph 16755-13(d) of the specifications requires that the data logger shall log an uninitiated (alarm) change of status in red lettering. Harris' bid states that the equipment they have chosen is not available with red ribbon printout and that they therefore propose that all changes normally logged in red would instead have an asterisk in the first column. This specification requiring logging in red of an alarm change of status was included by the specifications writer of the architect/engineers as a safety feature. Paragraph 16755-13(e) of the specifications requires that the log shall contain time in a 24 hour format to a tenth of a minute. The Harris bid proposes that the log shall be in seconds rather than tenths of a minute. The specifications require equipment delivery to the job site and substantial completion within 180 calendar days after receipt of Notice To Proceed. The specifications further provide for liquidated damages of $100 per day for each day the contractor fails to meet the above completion date. The Harris bid requested that the liquidated damages clause and the required time for completion be modified to provice that the 180 day period would not commence until all drawings had been approved by the architect/engineers. The architect/engineers, Reynolds, Smith and Hills, calculated that the required drawing time was approximately 60 days. Therefore, the Harris bid proposes that Harris would have 240 days instead of 180 days in which to deliver the equipment to the site and substantially complete the contract. The Harris bid proposed a deviation from the warranty provision of the specifications. The specifications in paragraph E-17 placed the final determination of the need for repairs or changes under the guarantee clause of the specifications with the architect/engineers and the owner. Harris proposes to alter those specifications and place the right of final determination as to the existence and cause of any claim defect with Harris. Harris' bid contained information setting forth their experience with the Micro II System, which is the system they proposed in their bid. That information shows that the Micro II System had been in use no more than two and one-half years at the time of the bid letting. In its evaluation of the bidders' proposals, based upon the data contained in the original bid packages, Reynolds calculated that the deviation from the specifications by Harris gave Harris at least a $10,135 advantage in its bidding (See Petitioner's Exhibit 8). That evaluation did not include a dollar value for the deviation from the specification concerning the warranty. In that evaluation Reynolds noted the failure of Harris to meet the supervisory point requirements. They calculated that this would add $3,900 to Harris' bid based on twelve locations at $300 per location. In fact, Harris failed to meet the requirements at eighteen locations, which at $300 per location, would add $5,400 to Harris' bid. Thus, using the evaluation figures of Reynolds, it appears that Harris' deviations from the specifications gave them at least an $11,635 advantage in the bidding. On October 9, 1975, Reynolds held a conference with each of the three bidders. At that conference Weston provided a list of three names, with addresses of customers for whom Weston had completed work similar to that proposed in its bid. Reynolds did not receive any material information from these references until after October 31, 1975. At least two of the references commented favorably on Weston's performance in letters to Reynolds dated January 13, 1976 and January 20, 1976, respectively. By letter dated October 31, 1975, Reynolds' project manager for this project conveyed the architect/engineers' recommendation for award to the Department. That recommendation was that the contract be awarded to Hathaway Instruments, Inc., for the base bid item only. The recommendation noted that the alternate should be rejected because the bids for the alternate were excessively high. As stated in the letter of recommendation, Reynolds rejected Harris' bid because "there were several major exceptions taken to the specification (sic), the most serious of which was their not being able to meet the delivery schedule." Also, as stated in the letter of recommendation, Weston's bid was apparently rejected because they "could not meet the experience qualifications as specified." Harris, at the time of the bid letting, had five years experience with its Micro I equipment but had only two and one-half years experience with its Micro II equipment. The two lines of equipment constitute two generations of equipment. Neither Harris nor Weston had five years experience with the specific equipment proposed in their bids. Both, however, have had five years experience with the general type system and equipment proposed with Harris being the more experienced of the two. Based upon the evidence presented Weston and Harris are both responsible bidders. In November, 1975, the Department directed Reynolds to contact Harris and determine whether Harris would conform their bid to the specifications. The project manager for Reynolds so contacted Harris and by letter dated November 17, 1975 (Petitioner's Exhibit 4), notified the Department that Harris stated they would deliver the equipment within the time required by the specifications. That letter reiterated Reynolds' recommendation of Hathaway as contained in their letter of October 31, 1975. Reynolds did not retreat from their recommendation of Hathaway and at the final hearing again stated that recommendation. Thereafter, the Department proposed to award the contract to Harris and set the matter for final decision on December 2, 1975. Harris' bid was a responsible offer but was not in full compliance with the bid specifications and conditions. The bids of Weston and Hathaway were responsible offers and were in full compliance with the bid specifications and conditions except as noted in paragraphs 4, 7 and 19 herein. Paragraph B-18 of the Specifications and Contract Documents (Petitioner's Exhibit 1) states that "No bid modification will be accepted after the close of bidding has been announced." Section A of the same document states that bids would be received until 2:00 p.m. EDST, on September 25, 1975. No evidence was presented which would show that the time for receiving bids was extended beyond that set forth above. Therefore, the close of bidding appears to have been at 2:00 p.m., EDST, September 25, 1975. The agreement by Harris to conform their bid to the specifications and conditions constituted a material modification of their bid. This modification occurred in November, 1975, after the close of bidding, and was therefore not allowable under the terms of the Specifications and Contract Documents set forth above. The lowest base bid and alternate bid of those responsible offers received in full compliance with the bid specifications and conditions was that of Weston. No evidence was presented which would show that the Department submitted its complete File on this matter to the Division of Purchasing along with its reasons for recommending a bid other than the low bid meeting specifications, as required by Section 13A-1.02(a), F.A.C.

Florida Laws (2) 287.012287.042
# 4
MARPAN SUPPLY COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 96-002777BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jun. 11, 1996 Number: 96-002777BID Latest Update: Nov. 26, 1996

The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.

Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.

Florida Laws (6) 112.061120.57215.422287.001287.012287.057 Florida Administrative Code (1) 60A-1.001
# 5
NATIONAL ADVANCED SYSTEMS CORPORATION vs. ORANGE COUNTY SCHOOL BOARD, 81-001493 (1981)
Division of Administrative Hearings, Florida Number: 81-001493 Latest Update: Nov. 12, 1983

Findings Of Fact On October 26, 1976, the School Board of Orange County and ITEL Data Product Corporation (ITEL) entered into a lease agreement providing for the lease of data processing equipment to the Board from ITEL by which ITEL supplied a computer central processing unit (CPU) and related equipment. Concomitantly, by agreement, ITEL provided for servicing and maintenance of the equipment. In October, 1977, IBM announced its new 303X series of computers with delivery schedules to customers for the newly introduced equipment to take up to two years. IBM has had a long-standing policy, well-known in the data processing industry, of filling customer orders for equipment in the sequence in which they are received, called "sequential delivery." With public agency customers, such sequential orders are not envisioned by the agency nor IBM to be a firm order because of the often protracted procurement process, involving competitive bidding, that public bodies typically have to engage in before making such a major purchase. IBM therefore permits public agencies, such as the School Board in this case, to place non-binding orders in anticipation of a future procurement so that a sequential delivery position will be available to the public agency and thus cause no delay in acquisition of the equipment should IBM become the successful bidder upon a particular procurement. On October 6, 1977, the School Board placed a "reservation" for an IBM 3031 CPU and related data processing equipment. In a letter of October 11, 1978, the School Board informed IBM that this equipment would be needed in approximately November, 1979, subject to availability of funds and subject to IBM being selected as a winning vendor in a competitive bidding process. There was no executed contract or other commitment between IBM and School Board at this point in time. Sometime in the summer of 1979, the School Board, which had become dissatisfied with the service and maintenance it had received from ITEL pursuant to the ITEL lease, engaged certain members of its staff in a study regarding its future data processing equipment needs. The School Board staff study resulted in a determination by the staff, and ultimately by the Board, to acquire additional data processing equipment capacity in excess of the capacity supplied under the ITEL lease. On August 28, 1979, the School Board terminated the ITEL lease effective December 31, 1979, and on or about September 5th, notified ITEL of that termination. On or about October 2, 1979, after determining that it wished to lease new and greater capacity equipment, the School Board Issued an "Invitation to bid" to eleven vendors, providing for the leasing, with option to purchase, of an IBM 3031 CPU and related equipment "or their equal." In response to this invitation to bid, ITEL, Menrex Corporation, as well as IBM, submitted bids and on November 13, 1979, the School Board rejected all the bids as being not responsive, as it had reserved the right to do in the invitation to bid document. The rejection of these bids on November 13, 1979, provided only slightly over a month during which the School Board would have to acquire equipment by rental or purchase and have it installed, since the ITEL lease would be terminated on December 31, 1979. Accordingly, acting on the advice of counsel, the School Board determined that it could legitimately develop an interim emergency leasing plan for meeting its data processing needs upon the expiration of the ITEL lease starting December 31, 1979. This leased equipment was expected to be in place for approximately three to six months or until such time as a new bidding effort and procedure could be developed. The School Board, upon advice of counsel, determined that under its procurement regulations, it could rent equipment on a month to month basis without engaging in a competitive bidding process if it solicited quotations from at least three vendors. Thus, on November 13, 1979, the School Board solicited quotations from three potential vendors, Comdisco, ITEL and IBM, for purposes of securing an interim rental of an IBM 3031 CPU, "or equal", and related equipment. IBM and the Petitioner herein, NAS, which is the successor in interest to ITEL, responded to the solicitation of quotations and NAS informed the Board that it could not supply the particular equipment specified, but offered a NAS CPU at a monthly charge and suggested other related equipment to the Board that NAS considered to be suitable. The School Board staff informed NAS that the CPU unit itself would be a suitable alternative to the IBM 3031 CPU mentioned in the solicitation of quotations. On November 20, 1979, the School Board elected to select IBM's quotation and entered into the lease arrangement with IBM on a month-to-month rental basis. NAS did not challenge that action by the School Board. This rental agreement was entered into on or about December 7, 1979. It was a standard IBM lease and contained a provision whereby IBM offered the customer an option to purchase the equipment, although there was no obligation imposed therein on the customer to purchase the equipment, which was the subject of the lease. The agreement provided that the customer would be contractually entitled to certain "purchase-option credits" or accruals if it was leasing the equipment on a long-term basis and subsequently elected to exercise the option to purchase that same equipment. IBM grants such purchase-option credits as a general rule in month-to-month rental situations such as this, although they are not always a matter of contractual right on behalf of the customer. In any event, no consideration was shown to have been given at the time of entering this rental agreement to the existence or non-existence of any purchase-option credit provision since the only authorized contract at that time was a month-to- month rental agreement. No purchase or option to purchase which would be binding on either party was contemplated since both IBM and the School Board were aware that before a purchase of this magnitude could be made, that a competitive bidding procedure must be utilized. Equipment was installed pursuant to the rental agreement in December, 1979. Neither at the time of the contracting, nor at the time of the installation of the IBM 3031 CPU, did NAS or Comdisco challenge the award of the month-to-month rental contract to IBM. In early 1980, the rental agreement being only temporary, the School Board began studying various alternatives for making a permanent acquisition of needed data processing equipment. In early May of 1980, upon advice of its attorney and various staff members assigned to study the matter, the School Board determined that it would be more economical for the School Board to purchase a CPU and related equipment and service either by cash or installment payment, than to continue renting a CPU and related equipment or to lease those items with an option to purchase as had originally been contemplated in the October, 1979, aborted procurement effort. Thus, it was that on about April 20, 1980, the School Board appointed a committee of five persons to help draft technical specifications to ultimately be promulgated in bidding invitation documents with a view toward acquiring the required data processing equipment through competitive bidding and ultimate purchase. The committee included School Board employees and outside consultants with knowledge of the field of data processing. The members were: Louis Nall, Education Consultant with the Florida Department of Education; Kim Anderson, Information Systems Consultant with the Florida Department of Education; David Andrews, Coordinator, Systems Support, School Board; Mike Staggs, Coordinator, Operations for the School Board; and Craig Rinehart, Director of the Systems Development/Systems Support staff of the School Board. Upon this committee agreeing upon required specifications for the equipment to be acquired, the bidding documents or "invitation to bid" and related supporting documents were developed by the committee in conjunction with assistance of certain other members of the staff of the Board as well as the School Board's attorney. The bid documents were approved by the School Board on May 27, 1980, and they were issued on May 23, 1980, to eight potential vendors, including NAS, IBM, and Amdahl Corporation. The bid documents invited bids for the sale of an IBM 3031 CPU and related equipment "or their equal" (plus service and maintenance) for delivery no later than July 15, 1980. In addition to specifying an IBM 3031 CPU and related equipment "or their equal.," the pertinent specifications contained in the invitation to bid documents provided as follows: The manufacturer of the equipment described in the bid was required to currently manufacture it and offer for sale or lease along with it, an upgradable attached word processor subsystem the same as, or equal to, the IBM 3031 "attached pro- cessor." The Central Processing Unit, or CPU, being bid had to be capable of hosting or accommodating an attached processor. (The purpose of requiring this was so that the School Board could later ob- tain more processing capability if and when it needed it, rather than having to pay for more capacity than it needed at the time of the initial purchase. The vendors were not required by the bidding documents, however, to bid at the time of this procurement for the actual sale of such an attached processor, to be added later.) The School Board reserved the right to reject any and all bids and to waive any informal- ity in any bid. The bid documents initially stated that the School Board would not pay any separately stated interest or finance charges in arriving at its total purchase price for all equipment to be bid. Each bidder was required to offer a certain number of support or maintenance personnel in the Orlando area at the time the bid was submitted and the Board would enter into a separate service and maintenance agreement with the successful vendor. NAS did not protest the bid specifications contained in the invitation to bid documents. NAS did request and receive several interpretations and clarifications of the bid documents from the Board in a manner favorable to NAS. These favorable clarifications or interpretations were as follows: The unavailability of serial numbers for data processing equipment at the time the bid was prepared would not adversely affect the bid's validity. NAS could temporarily rent equipment from other manufacturers which it could not itself deliver by the July 15, 1980, date required in the bid documents. (emphasis supplied) NAS would be deemed by the Board to comply with the requirement that support personnel be present in the Orlando area, provided it had the required support personnel in the area at the time the equipment was actually delivered, rather than at the originally stated time of submission of the bid. The NAS 7000N CPU, which was a computer of greater capacity than the IBM 3031, even after the IBM had the attached processor added, was specifically determined by the Board to be con- sidered as equivalent to the IBM 3031 and thus ap- propiately responsive to that specification and the invitation to bid documents. NAS would be deemed by the Board to comply with the term "manufacturer" even though NAS did not in itself manufacture the equipment, but only marketed it for the maker, Hitachi Corporation. IBM also had a role in determining and securing clarifications or interpretations of the specifications in the invitation to bid from the School Board. Thus, it was that IBM suggested that the Board could save money if it allowed each vendor (not just IBM) to separately state an interest or finance charge in its bid, since IBM was of the opinion that the Internal Revenue Service would not tax as ordinary income to the vendor any separately stated interest charges or financing charges received by such vendor from a public governmental body such as the School Board. Thus, to the extent that vendors could save on income taxes from the total payment, if successful, then the School Board could reasonably expect all vendors to submit correspondingly lower bids in response to the invitation to bid. In response to IBM's request, the School Board amended the bid documents to allow a "separately stated time-price differential" for any item of equipment, not to exceed seven and one-half percent of that item of equipment. At NAS' request, the School Board also amended the bid documents to state that a single central processor (the NAS 7000N), with equivalent power to the IBM 3031 CPU, which was upgradable in the field, would be an acceptable alternative to the requirement that a separate processor must be capable of being attached to the CPU in order to increase data processing capacity. In fact, the NAS 7000N actually has somewhat greater data processing capacity than the IBM 3031. A further amendment to the bid documents provided that in determining the lowest and best bid, the Board would consider each vendor's total charges for service, maintenance and support of the equipment for a one- year period following the award of bids. Additionally, at the request of IBM, an amendment was approved to the bid documents stating that instead of seeking equipment "new and not refurbished," that that requirement would be changed to "new and not refurbished or not more than one-year old." These amendments were sent to all potential bidders. Prior to disseminating the May, 1980, invitation to bid documents, the School Board established an Evaluation Committee to review and analyze bids to be received in response to those documents. The Committee was composed of the following individuals: David Brittain, the Director of the Educational Technology Section, Florida Department of Education; William Branch, Director of Computer Service, University of Central Florida; Louis Nall, Education Consultant, Florida Department of Education; Ronald Schoenau, Director of Northeast Regional Data Center, Florida University System; Craig Rinehart, Director of Systems Development/Systems Support of the Orange County School Board; Mike Staggs, Coordinator, Operations of the School Board; David Andrews, Coordinator, Systems Support, School Board; Dale Brushwood, Director of Production Control, School Board; and David Brown, Attorney for the School Board. The Evaluation Committee was charged with conducting a review and analysis in accord with certain instructions given by the Board and to recommend to the Board the bid the Committee believed was the lowest and best bid. The Committee was instructed that objectivity is of prime importance. Five vendors submitted bids in response to the Invitation documents, as amended. They were NAS, IBM, Amdahl, CMI and Memorex. On June 17, 1980, the bids were opened by the Board. On a recommendation of the Evaluation Committee, the School Board found the bids submitted by CMI and Memorex to be not responsive to the bid documents. The bids submitted by NAS, IBM and Amdahl Corporation were found responsive to the bid document. The Evaluation Committee met for approximately 5 hours evaluating the bids by a number of different criteria, including the consideration of both a one-year and a three-year maintenance cost, as well as an assumption arguendo that the bid documents did not merely call for the IBM 3031 CPU upgradable by the addition of an attached processor, as the specifications actually requested, but instead that the $330,000 (estimated) attached processor was to be bought at the outset from IBM. The result was that the Evaluation Committee reported that the IBM bid was the lowest and best response, even if the cost of a $330,000 attached processor was added to their bid, which was not actually to be the case because the attached processor was not included in this procurement process. Even had that been added to the IBM bid, making it the second lowest dollar bidder, the Evaluation Committee still felt it to be the lowest, best bid. The IBM bid for the 3031 CPU and related equipment was $1,412,643 plus a time-price differential of $58,738 for a total of $1,471,381. The related bid for service, maintenance and support for the first year was $74,201.34, making a grand total for IBM's bid of $1,545,582.34. The NAS bid for the sale of an NAS 7000N CPU and related equipment was the next lowest bid at $1,575,751 plus a time-price differential of $74,722 for a total of $1,650,473. The accompanying bid for service, maintenance and support for the first year was $64,603. The total of the NAS bid was thus $1,715,076. The Amdahl Corporation's bid was higher than either IBM or NAS. In evaluating and in arriving at the decision that the IBM bid was the lowest and best, the Evaluation Committee was concerned with the previous poor record of maintenance and support provided by NAS's predecessor in interest, ITEL Corporation, as well as by the fact that there were then no NAS 7000N computer systems installed in the United States, so that some knowledge of its performance record could thus be gained. Further, the residual value for NAS' equipment had not yet been proven to the extent that IBM's had. Thus, the Committee determined that the IBM bid would still be the lowest and best even had the attached processor, at an estimated cost at time of $330,000, been added to the bid, making it the second lowest in dollar terms because the IBM bid combined the least risk, with the maximum equipment capacity growth flexibility at maximum benefit to the School Board in terms of financial flexibility. The NAS machine would provide more capacity than the Board needed for several years at higher cost, without the Board having an option regarding when that extra capacity should be obtained. The financial flexibility benefit of the IBM bid in terms of allowing for future capacity growth was borne out because the attached processor, by the time it was actually acquired from IBM in 1982, only cost $172,000, due to price decreases made possible by technological advances. The Evaluation Committee unanimously recommended acceptance of the IBM bid as the lowest and best received, and in official session on June 24, 1980, after hearing presentations by an NAS representative, the School Board unanimously voted to award IBM the contract for the subject equipment. On July 1, 1980, the contract submitted by IBM was executed by IBM and the School Board. It provided for a purchase by the Board of the equipment and services described above, payable in two installments, $600,000 on or before August 15, 1980, and the balance on or before July 5, 1981. On July 16, 1980, NAS filed a petition for administrative hearing with the Board, also filing an emergency motion for stay with the School Board, seeking a stay of all further agency action on the contracts with IBM, including any payment, pending disposition of the case. On July 29, 1980, the School Board, after hearing argument of NAS counsel, denied that petition for Administrative Hearing and motion for stay on the basis that the contract between the Board and IBM had already been executed and that the NAS request for a 120.57(1), Florida Statutes, hearing was not timely. On August 4, 1980, NAS appealed the Board's decision to deny a hearing to the Fifth District Court of Appeal and also filed an emergency motion for stay pending appeal. The emergency motion requested the court to prohibit any further action pursuant to the contract, including payment of any sums pending determination of the issues raised in the appeal. On August 15, 1980, the court granted the emergency motion for stay on the condition NAS post a supersedes bond on or before August 18, 1980. On August 26, 1980, the court vacated that order because of failure to timely post the supersedes bond. The School Board then paid IBM the first installment payment of $600,000, when due, shortly thereafter. On May 6, 1981 the Fifth District Court of Appeal ultimately rendered a decision that NAS ". . . should have an opportunity to present evidence and arguments, pursuant to Section 120.57(1)(b)4, Florida Statutes, (Supp. 1980), that its bid was the lowest and best response to the bid document." Thus, the case was remanded to the Board to conduct an administrative hearing, and the Board referred the matter to the Division of Administrative Hearings. On June 4, 1981, NAS filed with the Board a motion for stay to prevent the Board from making the final payment to IBM on the purchase price. After hearing arguments of NAS' attorney, the Board, on June 23, 1981, denied the motion for stay and NAS appealed. On July 3, 1981, the Fifth District Court of Appeal affirmed the School Board's denial of the stay. Final payment was thereafter made by the Board to IBM, thus completing the purchase and all performance of the contract.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is RECOMMENDED: That a final order be entered by the School Board of Orange County denying the relief requested by the Petitioner. DONE and ENTERED this 22nd day of September, 1983, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of September, 1983. COPIES FURNISHED: John A. Barley, Esquire 630 Lewis State Bank Building Post Office Box 10166 Tallahassee, Florida 32302 William M. Rowland, Esquire Post Office Box 305 Orlando, Florida 32802 Peter J. Winders, Esquire Nathaniel L. Doliner, Esquire Post Office Box 3239 Tampa, Florida 33601 Daniel E. O'Donnell, Esquire 400 Colony Square, Suite 1111 Atlanta, Georgia 30361 James L. Scott, Superintendent Orange County Public Schools Post Office Box 271 Orlando, Florida 32802

Florida Laws (2) 120.57582.34
# 6
SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 7
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 8
LIDO LINES, INC. vs. LEE COUNTY SCHOOL BOARD, 87-003338BID (1987)
Division of Administrative Hearings, Florida Number: 87-003338BID Latest Update: Sep. 25, 1987

Findings Of Fact In June 1987 The School Board of Lee County, Florida invited the submission of sealed bids for grading and drainage improvements at the new Multipurpose Building at Fort Myers High School. In addition to requiring grading, the project involves the erection or placement of structures in the nature of a drainage system consisting of culverts, pipes, and concrete inlets with grates, to be tied into the existing drainage system off School Board property across a county right-of-way into a culvert for discharge across the street, and which on School Board property attaches to and becomes a part of an existing building. Sealed bids were submitted by Systems Technologies Co. of Ft. Myers, Inc. (hereinafter "Systems Technologies") and by Ledo Lines, Inc. Respondent determined Systems Technologies to be the lowest responsible bidder and advised Ledo Lines, Inc., that it would be awarding the contract to Systems Technologies. Warren W. Hunt is the president and the qualifying agent of Systems Technologies. Hunt has an underground utilities contractor's license which has been inactive since it was obtained by him in March, 1986, being inactive therefore both at the time that Hunt submitted the bid on behalf of Systems Technologies and at the time of the final hearing in this cause. The inactive status results from Hunt's failure to complete the license process with the State of Florida. Since Hunt's license was inactive due to being incomplete at the times material to this cause, neither Hunt nor Systems Technologies was a licensed contractor and Systems Technologies was not a responsible bidder at the time that the bid was submitted. The contract specifications set forth the method by which the bids would be evaluated. Paragraph numbered 2.9 on page PD-4 provides as follows: Comparison of Proposals - Proposals will be compared on the basis of total computed price for each division of work. Total computed price equals the sum of the prices for the lump sum Contract Item, plus the sum of the total prices for the unit price Contract Items for each Division of work. The total price for each unit price Contract Item will be obtained by multiplying the estimated quantity of each item by the correspond- ing unit price set forth in the Proposal form[.] That provision, accordingly, requires that the bids be evaluated based upon the sum of all line items rather than based only upon their total or "bottom line" figure. Respondent's Director of Facilities Planning admitted that he failed to comply with this provision of the contract specifications in evaluating the two bids submitted to him and in determining that the bid should be awarded to Systems Technologies. In Systems Technologies' bid, the sum of the prices for the lump sum contract items plus the sum of the total prices for the unit price contract items amounts to $30,109.60. However, in submitting its bid Systems Technologies incorrectly added its column of figures and incorrectly computed its Total Contract Price (Estimated) to be $29,768. Since the contract specifications envision a unit price bid rather than a lump sum bid, the amount of the bid of Systems Technologies is in fact the amount of $30,109.60. The bid of Ledo Lines, Inc., is for $29,913.84. Ledo Lines, Inc., is, therefore, the low bidder on this project. The contract specifications when read in their entirety clearly require that the low bid be determined by adding the unit price and lump sum components rather than relying on the lump sum "bottom line" figure shown for Total Contract Price (Estimated). Employees of the consultant who Prepared the specifications testified that they expect to be able to hold the bidders to the unit prices but not to the Total Contract Price (Estimated) because the estimated quantities may change. Thus, the evidence is uncontroverted that the determination of low bidder pursuant to the contract specifications is based upon the total of the unit price provisions and not by the single figure at the bottom of the page which adds those individual prices and which was added erroneously in this case by Systems Technologies. In their Prehearing Stipulation, the parties stipulated that the School Board is subject to mandatory competitive bidding for this project. They further stipulated that where there is mandatory competitive bidding, the contract must be awarded to the lowest qualified, responsive bidder. Since Systems Technologies is neither a qualified, responsive bidder nor the lowest bidder, it is clear that Ledo Lines, Inc., is the lowest responsive bidder for the project in question.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that a Final Order be entered determining Ledo Lines, Inc., to be the lowest responsive bidder and awarding the contract for grading and drainage improvements to the Multi- purpose Building at Fort Myers High School to Ledo Lines, Inc. DONE and RECOMMENDED this 25th day of September, 1987, at Tallahassee, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of September, 1987. COPIES FURNISHED: James E. Melvin, Superintendent School Board of Lee County 2055 Central Avenue Fort Myers, Florida 33901 E. G. Couse, Esquire Post office Drawer 1647 Fort Myers, Florida 33902 Harry A. Blair, Esquire Post Office Box 1467 Fort Myers, Florida 33902

Florida Laws (3) 120.53120.57489.105
# 9
GLOBAL MARKETING OF NORTH CAROLINA vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 91-002222F (1991)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 08, 1991 Number: 91-002222F Latest Update: Aug. 09, 1991

Findings Of Fact Respondent issued an Invitation To Bid (ITB) for Bid No. 91-04, entitled "Granular Activated Carbon (GAC) Filter Installations and Exchanges" in September, 1990. Two bids were received in response to Respondent's ITB 91-04; one from Petitioner for a composite total price of $748,355.00 and one from Continental Water Systems, Inc. (Continental), for a total composite price of $904.475.00. An intended contract award was delayed until the bids were evaluated. Subsequently, Respondent determined to award the bid to Continental on October 12, 1990. The issue in the ensuing bid dispute in Division of Administrative Hearings Case No. 90-6962BID was the responsiveness of Petitioner's bid on carbon specifications to be used in water filters. The bid document did not require manufacturers' specifications, requiring instead only generic specifications or a description of the product to be used. Respondent awarded the bid to Continental after determining Petitioner's bid to be nonresponsive, although the bid appeared facially responsive. In the course of evaluating the bids, Respondent's personnel went beyond the bid submissions and telephoned the manufacturer of the carbon proposed to be used in Petitioner's bid submittal. The manufacturer confirmed the content of Petitioner's bid that a lot analysis and hand selection could be done to select lots of carbon of a specified iodine number of 950 or greater in satisfaction of Respondent's specifications. Absent such a selection process, no manufacturer in this country produces a standard carbon which meets Respondent's bid specifications. While the ITB required bidders to submit specifications for products, it did not require submission of manufacturer's specifications. However, Petitioner's bid submittal included the manufacturer's specification sheet for an activated charcoal product known as GAC 30. The iodine number 950 appeared on the sheet with an asterisk next to it. At the bottom of the page was a typed note explaining that lots with this iodine rating would be specifically selected to meet or exceed all bid requirements. In reviewing Petitioner's bid, Respondent's personnel were aware that Petitioner had been using selected lots of GAC 30 in fulfilling a previous bid award for the same project from the Department of Agriculture and Consumer Services which specified carbon with an iodine number of 950. Further, Respondent's personnel knew that lot analyses were provided to the Department of Agriculture and Consumer Services to confirm the carbon's standards. As a result of that knowledge, a provision for an analysis of each carbon lot to be used was included in Respondent's ITB. On October 9, 1990, when Respondent's employee telephoned the manufacturer whose specification sheet was submitted by Petitioner, he was orally informed that while the iodine number for GAC 30 is 900, the actual iodine number for GAC 30 is often above 950 and that lot selections of carbon could be made meeting or exceeding 950. Later, per the employee's request for written confirmation, he received a facsimile letter dated October 10, 1990, from the manufacturer. Without regard for these findings, Respondent rejected Petitioner's bid because the actual manufacturer's specification for the carbon proposed by Petitioner did not meet bid requirements. 1/ While Respondent's personnel deemed it appropriate to consider information from the manufacturer of GAC 30 that its actual specifications were different from those submitted by Petitioner, the manufacturer's confirmation of Petitioner's explanation that lots would be selected to meet bid requirements was rejected. Petitioner is a corporation which, at the time of the bid submittal, had its principal office in Winter Haven, Florida. At that time, Petitioner had 12 employees. Petitioner is a prevailing small business party and was awarded the bid by Final Order of Respondent dated February 18, 1991. In the course of the administrative litigation culminating in Respondent's Final Order, Petitioner incurred attorney's fees in excess of $15,000.

Florida Laws (3) 120.57120.6857.111
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer