Findings Of Fact Brevard applied for a permit to construct a Class I exploratory injection well at the site of the existing South Beaches Domestic Wastewater Treatment Plant, located on U.S. Highway A1A, one mile south of Melbourne Beach, Florida. The exploratory injection well is required to determine if the hydrologic characteristics of the Melbourne Beach area are suitable for deep well disposal of treated domestic waste water. The application proposes that an exploratory well be constructed to meet the Class I standard of Chapter 17-28, Florida Administrative Code, so that it can ultimately be used as a Class I injection well if the required testing indicates the hydrologic formations of the area are suitable for deep well disposal of treated domestic effluent. It is anticipated that a suitable zone for injection bay be found at approximately 3,000 feet below ground level. The conditions required by the Department for issuance of a construction permit would not authorize testing or operation of the well. Once the well is constructed, further approval from the Department is required prior to testing. If the Department authorizes testing, the well will he tested with water from the Indian River. If the test results are favorable, Brevard must then apply for an operation permit authorizing injection of treated effluent. Further Department review will occur prior to issuance of an operation permit. The evidence presented by Brevard and the Department establishes that the design specifications for the exploratory well satisfy the appropriate standards for a Class I exploratory well. The Amended Petition for Hearing raised a number of concerns which were adequately addressed by Brevard and the Department: The Petitioner failed to establish that the documents comprising the application contain false and mis- leading information. The maps and photographs submitted by Brevard adequately depict exist- ing residences, roads, public water systems and water wells. Although well #061 does not appear in the list of owners on the well inven- tory, it clearly appears next to that list on the actual map showing wells within the area of study. Such a clerical error does not draw into question the integrity of Brevard's data. The purpose of constructing and then testing an exploratory well is to determine if the hydrologic environment is suitable for deep well disposal of treated domestic waste water; obviously, it is impossible for Brevard to demon- strate the feasibility of deep well injection until the required testing has been completed. The application and accompanying documents adequately address the design specifications and life expectancy of the proposed well. The application and special conditions of the Department's draft permit provide sufficiently for monitoring during the con- struction and any later testing of the well. The application and the Department's draft permit adequately address the possibility of fluid discharge to surface and ground waters during construction and any later testing of the well. Existing knowledge of the geologic formations in the Brevard County area makes it extremely unlikely that construction and testing of the well could cause an earthquake) Deep well disposal of domestic effluent has been utilized in South Florida for years and has not yet caused an earthquake. No credible evidence was presented by the Petitioner to indicate that an earthquake could result from deep well injection activities in Brevard County. It is important to note that the design specifications and conditions of Brevard's proposal were reviewed and negotiated with the Technical Advisory Committee over a period of many months. Appropriate technical staff from the Department's St. Johns River District office, Brevard County, the St. Johns River Water Management District, and the United States Environmental Protection Agency participated on that Committee.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered issuing a permit to Brevard County to construct the Class I exploratory well proposed in its application. DONE and RECOMMENDED this 22nd day of November, 1983, in Tallahassee, Leon County, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of November, 1983. COPIES FURNISHED: Jeanne Whiteside 10520 South Tropical Trail Merritt Island, Florida 32952 Kenneth C. Crooks, Esquire Post Office Pox 37 Titusville, Florida 32781-0037 Dennis R. Erdley, Esquire Department of Environmental Regulation Twin Towers Office Building 2660 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact Petitioner, Department of Health and Rehabilitative Services, is the state agency charged with regulating waste water treatment facilities and any sanitary nuisance which may emanate as a result of such operations pursuant to Chapters 381 and 386, Florida Statutes. Respondent, Larry G. Delucenay d/b/a Madhatter Utilities, Inc., owns and operates the Foxwood Waste Water Treatment Plant which is permitted and certified by the Department of Environmental Regulation. Respondent, in operating the Foxwood system, discharges its treated effluent water by means of two percolation ponds and a drip field located adjacent to the Cypress Cove Subdivision in Pasco County, Florida. Respondent owns and controls percolation ponds which are located adjacent to the Cypress Cove Subdivision and pumps human waste from a sewage treatment plant to percolation ponds in the Cypress Cove Subdivision. Respondent's percolation ponds are located approximately 50 ft. west of several residences and the ponds are accessible to the public. The ponds are elevated from 3 ft. to 5 ft. above the adjacent residential lots in the subdivision. However, there is a sand berm approximately 8 ft. high with a 12 yd. base which serves as a barrier between the percolation ponds and the Cypress Cove residences. On August 5, 1991, environmental health specialist Burke observed liquid flowing through the sand berm. He also observed erosion patterns in the sand on the berm which indicated liquid was flowing through it. Mr. Burke, while in the company of two other employees of Petitioner, observed liquid flowing from the percolation ponds onto Lake Floyd Drive to the south of the ponds. An improperly designed nearby lake exacerbated the flooding into Lake Floyd Drive. Respondent's waste water treatment system is designed according to the manufacturer's specifications. Pasco County allowed a number of developments to be built in the area without an adequate drainage system which adversely impacts Respondent's system to the point whereby untreated drainage outfall is draining into the southeast areas in Cypress Cove. Specifically, Respondent's pond #4 is designed to handle a water level up to 67.33 ft. During the investigation of the case, the water level in that pond was approximately 3 1/2 ft. higher than the designed capacity and was therefore causing overflow into the southeast areas of the development. (Respondent's Exhibits A, B and C.) Noteworthy also was the fact that a developer failed to complete a connection which has impacted Respondent's percolation pond and has forced the water to rise approximately 9 ft. higher than the designed capacity which has resulted in an overflow approximately 3 ft. to 4 ft. into the neighboring subdivision. As a result of the overflow, waste water spills over the percolation ponds and prevents the water from draining through the berms as designed. Petitioner's consulting engineer, Robert William Griffiths, credibly testified that a number of agencies having oversight responsibility such as Pasco County, the Southwest Florida Water Management District and the Department of Environmental Regulation, mandated that the drainage system be completed prior to the entire build-up of Cypress Cove. Despite the mandate, the drainage system was not completed and the County allowed the development to continue. Respondent is properly treating and chlorinating sewage in its plant which complies with Petitioner's requirements for the treatment of sewage in systems designed such as Respondent's. Respondent properly treats sewage flowing through its ponds and its berms are properly maintained. As early as October 1989, Respondent consulted and retained an engineer, Gerald E. Towson, who was commissioned to investigate the specifics of designing a waste water treatment plant based on concerns raised by the Department of Environmental Regulation (DER). As a result of that charge, Towson investigated the area and observed flooding and the stormwater runoff in the Cypress Cove neighborhood and attempted to find a solution to alleviate the problem. Consultant Towson also investigated Respondent's treatment plant to determine if the system was functioning as designed. Based on his observation and inspection of the treatment facility, the facility was operating as it was designed and properly filters and treats the effluent. However, based on Respondent's inability to control the stormwater runoff in the neighborhood created by the excess buildup, Towson concluded that there was no workable solution to the problem. As a result of Towson's inability to find a workable solution to handle the concerns raised by DER, Respondent suggested that Towson locate another wastewater treatment site which he found in a surrounding area. Respondent negotiated a lease arrangement with the landowner and initiated the permit process with DER. After the completion of numerous documents and engineering studies required by the Department of Environmental Regulation, Respondent was able to get the leased site permitted by DER as a slow drip irrigation system during March 1991. However, while construction of the system was scheduled to start during March 1991, as a result of vigorous protests from area neighbors, construction was delayed. Respondent thereafter investigated several sites but was unable to fine a suitable area near Cypress Cove. Towson completed a lengthy and cumbersome process in getting Respondent's construction application processed by DER. Initially the application was filed and following a DER review, a Notice of Intent to Issue was given. Hillsborough County thereafter reviewed the project and following their review, Hillsborough County issued its Notice of Intent to Grant and public notice was given. Based on Respondent's inability to comply with the neighbor's concerns regarding setback problems, DER withdrew its permit during May of 1991. Thereafter, Petitioner became involved in connecting with the Pasco County Public System. That connection was ultimately made and the County gave its approval following a delay based on a review occasioned by an employee who had been on vacation. Upon getting the approval, Petitioner ordered the equipment from a supplier which included installation of a magnetic meter and the necessary hookups into the Pasco County System. A "phased in" connection has been completed and the stormwater runoff problem has been abated. When the problems raised by DER and ultimately Petitioner was first brought to Respondent's attention, Pasco County did not have the capacity to handle the hookups required by Respondent's system. Respondent, has been involved in the installation of waste water treatment plants since 1967. Respondent is qualified as a Class "A" Licensee Waste Water Operator. He has been accepted as an expert in numerous administrative hearings. Respondent purchased the Foxwood System during 1982. Respondent utilized a 13 acre tract near Lake Floyd Drive. The system was licensed and designed with a flow capacity of 300,000 plus gallons per day. During the time when the Administrative Complaint was issued, the flow capacity was 220,000 gallons per day. The storm water system which was to have been completed by developers in the area was not connected to the public system and the County granted numerous other permits to daycare centers and several parking lots were constructed for other newly constructed commercial buildings in the area. As a result of the excess runoff created by the development in the area, Respondent's system was impacted and the water level was raised in the percolation ponds to the point whereby an overflow resulted. Petitioner adduced no evidence which showed that any physical or emotional harm resulted from the runoff. At all times while the concerns were being raised by Petitioner and other oversite agencies, the effluents in Respondent's systems were properly treated. Respondent vigorously attempted to abate the runoff created by the excess buildup in the area despite the fact that the problem was raised by Pasco County and over which Respondent had no control. Throughout the process of attempting to find alternate solutions and ultimately getting permitting approval to start construction of an alternative waste water treatment system, Respondent operated in good faith. When no alternate site became available, Respondent initially made application to connect with Pasco County System and that connection has now been made.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner enter a Final Order dismissing the Administrative Complaint herein in its entirety. DONE and ENTERED this 29 day of April, 1992, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29 day of April, 1992. COPIES FURNISHED: THOMAS W CAUFMAN ESQ HRS DISTRICT V LEGAL OFFICE 11351 ULMERTON RD - STE 407 LARGO FL 34648 RANDALL C GRANTHAM ESQ COTTERILL GONZALEZ & GRANTHAM 1519 N MABRY - STE 100 LUTZ FL 33549 RICHARD S POWER AGENCY CLERK DEPT OF HEALTH AND REHABILITATIVE SERVICES 1323 WINEWOOD BLVD TALLAHASSEE FL 32399 0700 JOHN SLYE ESQ/GENERAL COUNSEL DEPT OF HEALTH AND REHABILITATIVE SERVICES 1323 WINEWOOD BLVD TALLAHASSEE FL 32399 0700
The Issue Whether Respondent committed the violations as set forth in the Citation for Violation, Onsite Sewage Program/Sanitary Nuisance dated April 28, 2000.
Findings Of Fact Petitioner is authorized and given the jurisdiction to regulate the construction, installation, modification, abandonment, or repair of onsite sewage treatment and disposal systems, including drainfields, by septic tank contractors. At all times material hereto, Respondent was a registered septic tank contractor and, as such, he was authorized to provide septic tank contracting services, including the installation and repair of drainfields. On or about November 2, 1995, Petitioner issued a permit (Permit No. RP648-95) to Wilmar Rodriguez for the repair of a septic tank system at 417-421 Perry Avenue, Greenacres, Florida. The property was a triplex, which was purchased by Mr. Rodriquez in 1981. Mr. Rodriguez has no knowledge as to whether any drainfields were installed or replaced on the property, prior to 1981. The Permit included the installation of a new multi- chambered septic tank, a dosing tank, a lift station, and a new drainfield. The Permit was also for a filled system and called for the drainfield to be 700 square feet. Respondent was indicated as the "agent" on the Permit. Respondent and/or his employees performed the work under the Permit. Respondent was the septic tank contractor for the repair of the septic tank system under the Permit. On November 9, 1995, the construction of the septic tank system was approved by one of Petitioner's inspectors, who was an Environmental Specialist I. Petitioner's inspectors are not present during the entire construction or repair of a septic tank system or drainfield. Usually, inspections are made after the completion of the construction or repair of the septic tank system. Additionally, the inspection of a drainfield is usually performed after the rock has been placed on top of the drainfield. On February 2, 1996, the same inspector performed the inspection after the completion of the construction of the septic tank system, including after the placing of the rock on top of the drainfield. Even though the Permit reflects a filled system, the filled/mound system section on the inspection sheet was crossed out. The inspector considered the system to be a standard system, not a filled or mound system, and, therefore, inspected it as a standard system. In inspecting a drainfield, the inspection by an inspector includes checking to ensure that a drainfield has 42 inches of clean soil below the drainfield. An inspector uses an instrument that bores down through the rock and brings up a sample of the soil, which is referred to as augering. Augering is randomly performed at two locations. For the instant case, the inspector performed the augering in two random locations of the drainfield, which were in the area of the middle top and the middle bottom. The samples failed to reveal anything suspect; they were clean. On February 2, 1996, the inspector issued a final approval for the septic tank system. Final approval included the disposal of "spoil" and the covering of the septic tank system with "acceptable soil". The inspector mistakenly inspected the system as a standard system. He should have inspected the system as a filled system.1 After the repair and installation of the septic tank system by Respondent, Mr. Rodriguez continued to have problems with the septic tank system. He contacted Respondent three or four times regarding problems with the system, but the problems persisted. Each time, Respondent was paid by Mr. Rodriguez. Sewage water was flowing into the street where the property was located and backing-up into the inside of the triplex. Having gotten no relief from Respondent, Mr. Rodriguez decided to contact someone else to correct the problem. Mr. Rodriguez contacted Richard Gillikin, who was a registered septic tank contractor. On October 14, 1999, a construction permit was issued to Mr. Rodriguez for the repair of the septic tank system. Mr. Gillikin was indicated as the agent. Mr. Gillikin visited the property site of the triplex and reviewed the problem. He determined that the drainfield was not properly functioning, but he did not know the cause of the malfunctioning. With the assistance of Petitioner's inspectors, Mr. Gillikin and Mr. Rodriguez attempted to determine the best method to deal with the problem. After eliminating options, Mr. Rodriguez decided to replace the drainfield. To replace the drainfield, Mr. Gillikin began excavating. He began removing the soil cover and the rock layer of the drainfield. Mr. Gillikin also wanted to know how deep he had to dig to find good soil. After digging for that purpose and for 10 to 12 inches, he discovered a drainfield below Respondent's drainfield. The drainfield that Mr. Gillikin discovered was a rock bed 12 inches thick in which pipes were located and, as indicated, 10 to 12 inches below Respondent's drainfield. Mr. Gillikin also dug a hole two to three feet deep, pumped the water out of the hole, and saw the old drainfield. Mr. Gillikin determined that the old drainfield extended the full length of Respondent's drainfield. As a result of Mr. Gillikin's determining that the old drainfield was below Respondent's drainfield, both drainfields had to be removed and the expense of a new drainfield increased. Leon Barnes, an Environmental Specialist II for Petitioner, who was also certified in the septic tank program, viewed the drainfield site. He determined that the old drainfield was below Respondent's drainfield and that, therefore, Respondent had not removed the old drainfield. On or about November 6, 1999, Mr. Barnes' supervisor, Jim Carter, and co-worker, Russell Weaver, who is an Engineer, also visited the drainfield site. Mr. Weaver determined that the old drainfield covered a little more than 50 percent of the area under Respondent's drainfield. On November 8, 1999, a construction inspection and a final inspection of the system installed by Mr. Gillikin were performed. The system was approved. Respondent admits that a new drainfield is prohibited from being installed over an old drainfield. However, Respondent denies that he installed a new drainfield over the old drainfield on Mr. Rodriguez's property. In 1995, Respondent failed to completely remove the old drainfield before he installed the new drainfield. The soil and rocks from the old drainfield, which was not functioning, were contaminated spoil material. Because the old drainfield was not completely removed, the contaminated spoil material remained in the drainfield and was used as part of the material in the installation of the new drainfield. Leaving the contaminated spoil material in the new drainfield, prevented the sewage water from being able to percolate through the ground, which is a method of cleansing the sewage water. Without being able to percolate through the ground, the sewage water remained on the surface of the drainfield, creating a serious sanitary nuisance and health hazard. The sewage water spilled onto the street and backed-up into the triplex. Respondent was issued a Citation for Violation, Onsite Sewage Program/Sanitary Nuisance by Petitioner.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health, Palm Beach County Health Department, enter a final order: Affirming the Citation for Violation, Onsite Sewage Program/Sanitary Nuisance and finding that Noel Sanfiel violated Section 381.0065, Florida Statutes (1995), and Rule 10D- 6.0571(4), now Rule 64E-6.015(6), and Rule 10D-6.0751(1)(l)1, now 64E-6.022(1)(l)1, Florida Administrative Code. Imposing a fine of $500. DONE AND ENTERED this 13th day of February, 2001, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 2001.
Findings Of Fact Petitioner, George H. Hopper, submitted an application for a license to operate a Class "C" wastewater treatment plant to the Respondent on or about April 8, 1977. On November 28, 1977, the Respondent issued a letter of intent to deny the license. This letter of intent was subsequently modified by a letter to petitioner from Respondent dated January 4, 1978. The Respondent, in the above-referenced correspondence, based its letters of intent to deny the Petitioner a Class "C" wastewater treatment plant operator's license based upon two primary grounds. Those grounds are as follows: "This Department has concluded that you have not fulfilled the actual experience requirement of section 17-16.03(2)(b), Florida Administrative Code (F.A.C.), as defined by section 17-16.02(8) F.A.C." (See letter dated November 28, 1977.) "In addition to the above referenced deficiency in actual work experience, it has been noted that you have not completed an approved course related to wastewater treatment plant operation as required by Section 17-16.03(2)(c), Florida Administrative Code." (See letter dated January 4, 1978.) Respecting the second allegation, Petitioner presented testimony during the course of the hearing which, in fact, indicates that he did complete an approved coarse related to wastewater treatment plant operation as required by Section 17-16.03(2)(c), Florida Administrative Code. Additionally, Petitioner presented a diploma supporting this contention. This certificate reflects the fact that the Petitioner satisfactorily completed the course on "Operation of Wastewater Treatment Plants" on or about May 2, 1977. Based thereon, and the testimony of Respondent's certification officer, Robert W. Hall, to the effect that the Respondent did comply with the Code requirement which mandates completion of an approved course related to wastewater treatment plant operation, that ground is no longer a basis for the denial of Petitioner's certification. Petitioner testified, and the other documentary evidence introduced during the coarse of the hearing indicates, that Petitioner was employed from January, 1975, through December 25, 1975, as administrator of the Margate Utility Authority. From December 25, 1975, through February 15, 1976, the Petitioner was employed in a position other than as administrator, his resignation being effective on February 15, 1976. Accordingly, the Petitioner was employed at the Authority for a period in excess of one year. What is at issue, is the Respondent's contention that the Petitioner was not actually performing duties tantamount to fulfillment of the actual experience requirement of Section 17-16.03(2)(b), Florida Administrative Cede, inasmuch as his duties as an administrator were more in the nature of being in charge of the facility, with little practical experience as the term "experience" is meant in Chapter 17 of the Florida Administrative Code. Additionally, it was noted that the Petitioner was re-employed by the City of Margate as a supervisor. During the hearing, the Petitioner outlined his duties as an administrator which included being in charge off the overall operation of the wastewater treatment plant. Petitioner testified that when he was first employed at the Margate Utility Authority, the wastewater treatment plants were not operational. He testified that a water-sewer moratorium had been placed by the Board of Health, citing approximately five violations. Petitioner testified that he instituted numerous changes in the operations of the wastewater treatment facilities which included hiring a contractor to supervise deficiencies in the wastewater treatment plant and its injector systems which were over-pressurized. He testified that within approximately two months of his employment with the Authority, he was able to correct approximately 80 percent of the problems and was able to again make the treatment plant operational. Petitioner testified that he normally worked a five day week; however, he was on duty in excess of forty hours weekly for the resolution of all daily operational problems. Evidence introduced during the course of the hearing reveals that the wastewater treatment facility here involved is fully automated and that the operators have very little to do in terms of manual tasks. In this regard, the Petitioner testified that he was on duty at the facility throughout his employment during the period January, 1975, through December, 1975, to operate the wastewater treatment plant. Additionally, the Petitioner testified that his office, as an administrator, was located in close proximity to the wastewater treatment facilities and he was available to in fact operate the wastewater treatment plant, as needed. Finally, Respondent's certification officer, Robert W. Hall, testified that in his opinion, being available to operate as opposed to actual operation is what is required by the actual experience requirements of the Florida Administrative Code. Based thereon, I shall recommend that the Respondent withdraw its notice of intent to deny Petitioner's application for a Class "C" wastewater treatment plant operator's license.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby, RECOMMENDED: That Petitioner's application for a Class "C" wastewater treatment operator's license be GRANTED. RECOMMENDED this 8th day of May, 1979, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Russell L. Forkey, Esquire 3081 East Commercial Boulevard Fort Lauderdale, Florida 33308 Randall E. Denker, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact South of the intersection of Blue Angel Parkway and Gulf Beach Highway in southwest Escambia County lies the wooded, 69-acre tract, designated "Site F," onto which ECUA proposes to dispose up to three million gallons of wastewater a day. Petitioner Westerman operates a marina nearby. The individual intervenors own houses in the vicinity as, apparently, do other members of the intervening association. A state agency with wide ranging environmental responsibilities, DER permits construction of wastewater treatment facilities in conformity with its rules. Sewage disposal is one of several utility services ECUA provides residents of Escambia County. A Trip to the Beach Under orders from DER and the Environmental Protection Agency (EPA) to cease discharging directly into Bayou Chico ("a very impacted body of water ... [with] very difficult problems" T. 101), ECUA proposes to build a pumping facility and install enough 24-inch pipe to enable it to send effluent from its wastewater treatment plant in Warrington to Site F, for "rapid rate" land application. Upgraded since DER and EPA forbade direct discharges into Bayou Chico, the Warrington plant now employs advanced treatment techniques to remove most phosphorous and nitrogen from its effluent. Nevertheless, in order to mollify regulators, ECUA has plans to ship the effluent through some seven miles of pipe to Site F. In the opinion of its executive director, ECUA is "an easy target . . . . Whether it's practical or fair is really not the question." Id. He feels, "cost is not a factor" (T. 102) that the regulatory authorities have taken into account. Sandy Soils Site F straddles a coastal ridge, vegetated dunes that separate Garcon Swamp from Big Lagoon. Elevations vary from 29 feet above mean sea level at the crest of the ridge to nine feet above mean sea level in the swale that traverses the property. Highly permeable surficial sand extends to depths ranging between 20 and 35 feet below grade. Under the surficial sand, a layer of silty sand, extending down 55 to 60 feet, overlies another layer of very clean sand, much denser than the surficial sand. At depths of 90 to 110 feet, a clay aquiclude undergirds these sandy strata. Using field and laboratory test results, experts put the average hydraulic conductivity of the surficial sands at 35 feet per day, of the silty middle sand layer at 10 to 15 feet per day, and of the clean but dense sands on top of the clay at 5 to 10 feet per day. In addition to laboratory results, two pump tests support these conclusions. Results of two other pump tests indicating hydraulic conductivity of 4.7 and 5.0 feet per day were dismissed as unreliable. Sand caving in compromised at least one of these tests. As far as the record reveals, no bench-scale or pilot-scale hydraulic testing took place. According to DER's Mr. Reinning, there was "more soil testing on this site than [he had] seen on any other permit event." T.II. 217. Although the soils on the site are "relatively uniform," (T.II. 212) no layer of sand is perfectly uniform. Mr. Jacobs, one of ECUA's consultants, testified that a boring on one of the proposed pond sites revealed a one-foot layer of sand and organics with a vertical hydraulic conductivity of one foot per day. T.I. 245. Perhaps Mr. Jacobs was referring to boring B-2, which, according to the log, reflects a two-foot interval of peat and decaying wood, at a depth of slightly more than 13 feet. ECUA's Exhibit 2. No other boring gave evidence of this layer. The nearest bore hole to B-2 was more than 200 feet away. Expert testimony that the borings did not indicate an "extensive pocket," and gave no reason to fear a "per(c)hed water table," (T.II. 214) was not controverted. Construction Plans ECUA proposes to construct 16 percolation ponds or cells on Site F. Seven pairs of cells would be terraced on a north-south axis, with an eighth, noncontiguous pair at an angle in the southwestern portion of the property. Cell bottoms, at elevations ranging between 16 and 27 feet above mean sea level, would have a surface area aggregating some 23 acres (1,027,900 square feet.) ECUA would erect a perimeter fence and install warning signs. Except for valves, "no mechanical equipment [would be) involved in the disposal site," T.123, nor are "bright lights," id. planned. Water flowing into percolation ponds does not create an aerosol. Odors are not foreseen. Encircling each infiltration basin, berms three to three and a half feet higher than the cell bottoms would contain effluent and deflect sheet flow. Except for rain falling directly into the cells, stormwater would not reach the percolation cells. Chances that effluent augmented by rainfall would overflow the berms are remote. A 100-year, 24-hour return storm would not interrupt operation of the facility. No percolation pond site lies within the 100-year flood plain. No percolation basin is to be located within 500 feet of a potable water supply well or class I or class II surface water; or closer than 100 feet to the boundary of the property. Situated within some 20 acres of wetlands, a brackish pond lies about 1,000 feet from the nearest cell planned, between Site F and Big Lagoon into which the pond opens. At the nearest point, Big Lagoon itself comes within 1200 feet of a planned percolation cell. A swale or slough bridged by Blue Angel Parkway runs southwesterly north and west of the main phalanx of percolation ponds ECUA proposes, then turns a corner and runs southeasterly, separating the two cells proposed for the southwest portion of the property from the others. The nearest percolation pond is to be built about 100 feet from wetlands associated with the swale. Loading Rates ECUA plans to direct wastewater into half the cells one week and the remainder the next, alternating like the squares on a chessboard. The exact cycle is not a condition of the construction permit, however, and computer modelers assumed loading cycles consisting of two two-day periods. As applied to the total bottom area of percolation cells, the average daily loading rate for three million gallons a day (mgd) would amount to 2.91 gallons per square foot. Because half the ponds would be resting at any given time, ponds receiving effluent would experience inflow at an average rate of 5.82 gallons per square foot. In deciding the length of the loading cycle, as "the soil gets lower in permeability you have to really stretch your time for loading out, because it takes the water much longer to get out of the loading area." T.I. 188. But, with respect to the long-term capacity of the system, "the period of loading and resting . . . really doesn't significantly affect . . . how the site is expected to perform." T.II. 222. In the absence of bench-scale or pilot-scale tests heretofore, the applicant "intend[s] to load test this site, because just for the various concerns, because it is a big site." T.I. 189. Groundwater Effects Class G-II groundwater under the site now flows generally southerly toward the brackish pond and Big Lagoon. An expert put the rate of flow under the site at .22 feet per day, but concluded that the rate increased to approximately a half foot a day between Site F and Big Lagoon. As far as is known, groundwater under the sites proposed for the infiltration ponds rises no closer to the surface than six to nine feet, even under wet conditions, although the evidence by no means conclusively established that it would never rise higher. Some groundwater emerges in the swale during wet periods, and flows in the swale as far as the brackish pond, to which other groundwater makes regular, direct contribution. At the edge of the lagoon, further out in the lagoon and possibly in the Gulf of Mexico, still other groundwater comes up as springs. At least initially, the sandy soils would accept effluent readily. Until and unless actual experience showed that the facility could handle the three mgd for which it is designed, the plan is to dispose of no more than 2.5 million gallons of effluent a day. Before equilibrium is attained, ongoing disposal of effluent would gradually raise the level of groundwater under the site, inducing, on the preexisting, sloping surface of ambient groundwater, a mound, on which 16 smaller mounds (corresponding to the loading nozzles discharging wastewater into the percolation ponds) would superimpose themselves, half swelling, like so many goose eggs, half subsiding, at any given time. Adding effluent should not materially alter the ultimate direction of flow. For the most part, even groundwater flowing in other directions off the mounds induced under the site would eventually turn south toward the lagoon. But a steeper gradient should speed up the flow. Percolating effluent would increase the volume not only of seepage into the swale but also of subterranean flow reaching both the brackish pond and the lagoon. Increased seepage upslope from the slough would flow down into the swale, along the stream bed, and into the brackish pond. Monitoring As modified at hearing, ECUA's monitoring plan contemplates eight wells and four surface water monitoring points from which water samples would be periodically taken for analysis, to determine levels of nitrogen, phosphorous and other chemical and biological constituents of concern. Once the facility began operating, no well would yield "background" samples uninfluenced by the effluent. T. I. 221. The wells are all to be located on ECUA property and, therefore, close enough to the percolation ponds to receive ground water flows radiating from the mounds adding the effluent would induce. Final Destination Effluent emerging in seepage, perhaps as much as 75 percent of the total (T. III. 47), could reach Big Lagoon, by way of the swale and the brackish pond, soon after regaining the surface of the land. Wetland vegetation would filter such flows, already diluted underground and sometimes by stormwater runoff, on their way to the lagoon. Effluent that mixed with groundwater traveling to Big Lagoon underground would not show up in the lagoon for months or years. But when it arrived, much diluted and after such attenuation of pollutants as the largely inorganic soils afforded, it would also contribute to subtle changes in the waters of Big Lagoon. Virtually all effluent would ultimately end up in Big Lagoon. T.I. 234; T.III.45. Two channels connect Big Lagoon to Pensacola Bay to the east, and a single, more constricted channel connects it to Perdido Bay to the west. Tides influence the circulation of the Class III water within Big Lagoon, variously calculated to amount to some ten or eleven billion gallons of clean salt water. Through Pensacola Bay and Perdido Bay, Big Lagoon communicates with the Gulf of Mexico. As the tide rises, water from the adjacent bays enters the long and narrow reaches of Big Lagoon, at either end. As the tide ebbs, water in the lagoon (including a significant portion of bay water introduced by the preceding tide) flows out either end. ECUA's expert's claim that tides flush the lagoon in less than nine days did not take this back-and-forth movement into account, or look specifically at the four-billion gallon basin into which the brackish pond overflows. Big Lagoon lies south of the mainland and north of Perdido Key, one of the barrier islands paralleling the coast. These islands and waters north of them, extending as far as the southern boundary of the intracoastal waterway, comprise the Gulf Islands National Seashore. By rule, the waters of Big Lagoon south of the intracoastal waterway have been designated Outstanding Florida Waters. Two to three hundred yards wide, the intracoastal lies not far offshore the mainland. Water Quality Analysis of a single ground water sample revealed nutrient levels, but neither the applicant nor DER developed any data specific to Big Lagoon about nutrient levels there. Chemical analyses done on four samples of lagoon water (at petitioner's expense) revealed no nitrate nitrogen above detection levels in any of the samples, and no ammonia nitrogen above detection levels in three of the four samples, but disclosed 0.08 parts per million in the fourth. Three of the four samples contained 0.02 parts phosphorous per million, while the fourth had phosphorous in a concentration of 0.03 parts per million. Tests with water taken from Big Lagoon showed that the addition of both nitrogen and phosphorous compounds (but not the addition of one without the other) coincided with algal growth in one of four sets of samples, each set including a control in which such growth did not occur. In other samples of lagoon water into which algae were introduced, the addition of nitrogen, either alone or in combination with phosphorous, seemed to cause blue-green algae to predominate, instead of the dominant, indigenous pennate diatoms. In these experiments, ammonia chloride was added to produce nitrogen concentrations of 17.5 grams per liter, six times greater than would be allowed in the effluent, as much as 17 times greater than the concentration petitioner's expert predicted for wastewater reaching the lagoon, and two orders of magnitude above ambient levels. The experimenter also added sodium phosphate dibasic heptahydrate to create phosphorous concentrations of four grams per liter, which is also two orders of magnitude above levels naturally occurring in Big Lagoon. Special permit conditions limit (on an annual average) total nitrogen in effluent sent to Site F to 75 pounds per day, and phosphorous to one milligram per liter, which would amount to 25 pounds in three million gallons, the maximum daily flow. Permit conditions also prescribe limits for acidity and alkalinity (pH must be greater than 6.0 and less than 8.5), suspended solids, and biochemical oxygen demand. Basic dis- infection is required. Assuming ECUA disposed of three mgd at Site F, up to 25 pounds of phosphorous could be added to the estuary daily, on average, or more than a ton of phosphorous quarterly, if steady state were attained. Although three times as much nitrogen might occur in the effluent, oxidation and reduction would cause some nitrogen to enter the atmosphere as a gas instead of remaining dissolved until it reached the estuary. Not only organic components of the soil but also organic matter arriving in the effluent and accumulating on pond bottoms would contribute to denitrification. Salinity in the brackish pond would decline. A DER employee, Mr. Swartz, testified that placing three mgd of effluent in the planned percolation ponds "would not result in degradation of the surface water," (T. II. 127) citing "our experience here in Florida." Id. Whatever may be said as regards the brackish pond, no evidence gave substantial reason to question the accuracy of this opinion as it relates to waters south of the intracoastal waterway.
Recommendation It is, accordingly, RECOMMENDED: That DER deny the application, without prejudice to the filing of another after successful bench-scale or pilot-scale hydraulic testing and after ECUA has made arrangements for a ground water monitoring well from which samples unlikely to be affected by the effluent may be drawn. DONE and ENTERED this 2nd day of February, 1990, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of February, 1990. APPENDIX Petitioner's proposed findings of fact Nos. 1 through 8, 13, 14, 16 and 18 have been adopted, in substance, insofar as material. Most of petitioner's proposed finding of fact No. 15 accurately recites testimony adduced, but Shuba testified that algal growth has been stimulated by nutrient concentrations comparable to those Dohms said would occur in water entering Big Lagoon, not in concentrations likely to exist once this wastewater-bearing contribution mixed with other water in the lagoon. Petitioner presented information about nutrient levels in lagoon water at hearing. Computer modeling suggested break out, which has been considered. Petitioner's proposed findings of fact Nos. 17 and 19 accurately recite the testimony. DER's proposed findings of fact Nos. 1, 2, 3, 4, 5, 10, 11, 12, 13, 15, 16, 17, 18, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 42 and 43 have been adopted, in substance, insofar as material. With respect to DER's proposed finding of fact No. 6, the rate of flow increases south of the proposed pond sites. With respect to DER's proposed findings of fact Nos. 7 and 8, seasonal high ground water elevations were not shown conclusively. With respect to DER's proposed finding of fact No. 9, the aquiclude lies 90 to 110 feet below the surface. With respect to DER's proposed finding of fact No. 14, the rule requires a five-day rest. With respect to DER's proposed findings of fact Nos. 33, 34 and 35, the current rules do require mounding analysis, and there seemed to be a consensus that ground water enhanced by effluent would seep to the surface downslope from the ponds. With respect to DER's proposed findings of fact Nos. 36 and 37 and 44, free form agency action is technically immaterial. With respect to DER's proposed findings of fact Nos. 38, 39, 40 and 41, effluent would have mixed with groundwater before reaching Big Lagoon, but increased levels of nitrogen and phosphorous could be detected, as a result. ECUA's proposed findings of fact Nos. 1, 3, 4, 5, 6, 8, 10, 11, 12, 15, 16, 17, 20, 23, 24, 25, 26, 27, 28, 36, 37 and 38 have been adopted, in substance, insofar as material. With respect to ECUA's proposed findings of fact Nos. 2, 13, 21 and 32, the evidence showed that it was not unlikely that effluent, after percolating through pond bottoms and mixing with groundwater, would seep to the surface down slope. With respect to ECUA's proposed finding of fact No. 7, proposed cell bottom elevations fall in this range. With respect to ECUA's proposed finding of fact No. 9, the evidence did not establish that the high water table will always be nine feet below the pond bottoms. With the induced mound, ECUA's proposed finding of fact puts it at one to two feet. With respect to ECUA's proposed finding of fact No. 14, the tidal range is too high and the calculation ignores the back and forth movement of waters at either end of the lagoon. With respect to ECUA's proposed findings of fact Nos. 18 and 19, the current standard pertains total nitrogen. With respect to ECUA's proposed finding of fact No. 22, freeboard will vary with rainfall and effluent levels. ECUA's proposed findings of fact Nos. 29, 30, 31 and 34 relate to subordinate matters. With respect to ECUA's proposed finding of fact No. 33, more than one analysis was done. With respect to ECUA's proposed finding of fact No. 35, the applicant has given reasonable assurance. COPIES FURNISHED: Robert W. Kievit, Esquire Lester M. Westerman 10451 Gulf Beach Highway Pensacola, FL 32507 James Mullins 11001 Gulf Beach Highway Pensacola, FL 32507 Susan Guttman 11315 Sea Glade Drive Pensacola, FL 32507 Cindy L. Bartin, Esquire 15 West Main Street Pensacola, FL 32501 Joseph W. Landers, Esquire 310 West College Avenue Tallahassee, FL 32302 Stephen K. Hall, Esquire Asst. General Council Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 =================================================================
Findings Of Fact On October 15, 1982, Hal Thomas Reid Associates applied for a septic tank permit to serve a 16-room motel. On February 2, 1983, this application was amended to a 5,800 gallon septic tank to serve a 32-unit condominium and office. The lot on which this drain field is to be located is 70 feet by 100 feet. When the application was filed, the lot was inspected by the Citrus County Health Department. The elevation of the land averaged 2.5 to 2.9 feet above mean sea level. The 10-year flood plane in this area is 4.9 feet. Occasional high tides inundate this area; however, the water drains off rapidly and no one testified that water ever remained standing as long as seven consecutive days. Usually the water drains off in less than 24 hours. On March 1, 1983, an extremely high tide flooded this area and roads in the vicinity to a depth of approximately one foot. This water remained on the site less than 24 hours. The site is not located adjacent to state waters, is not an area designated as wetlands, and is without the dredge and fill permitting jurisdiction of the United States Army Corps of Engineers and the Florida Department of Environmental Regulation (Exhibits 20 and 21). By adding five feet of fill to the site, the bottom of the gravel below the drain pipes will be above the 10-year flood plane. The drain field capacity is adequate to handle the flow from 33 bathrooms of residential units. In approving this permit, the Citrus County Health Department used the 150 gallons per day discharge for residential units rather than the 100 gallons per day discharge from a motel unit. The water table at this location is two feet above mean sea level. This is determined by the elevation reached at high tides for 14 consecutive days. As a condition to Citrus County withdrawing as an intervenor in these proceedings, Applicant agrees: To revegetate and restore any alleged wetlands affected by the permit to a like or similar condition; To install three shallow draft monitor wells around the drain field towards the wetlands area adjacent to the site and towards Woods 'n Waters subdivision, establish an existing level of bacteria count prior to the activation of the septic tank, and to monitor said wells through the Citrus County Health Department on a quarterly basis; and In the event any monitor wells shall test at an unsatisfactory level, Applicant will forthwith correct this condition to the satis- faction of the Citrus County Health Department. This application meets all of the code requirements of Chapter 10D-6, Florida Administrative Code.
The Issue The issue in this case is whether the Petitioner has the actual experience required for certification as a Class B domestic wastewater treatment plant operator.
Findings Of Fact By application filed September 16, 1991, James H. Redden applied for certification as a Class B domestic wastewater treatment plant operator. At the time of the application, Mr. Redden was employed as a laboratory technician at a Class B Collier County regional wastewater treatment facility. From August 15, 1978, to July 31, 1989, Mr. Redden was employed at the Colgate-Palmolive Company facility at Jeffersonville, Indiana. The Colgate-Palmolive treatment facility is an Indiana Class D industrial wastewater treatment plant. Mr. Redden is certified by the State of Indiana as a Class D industrial wastewater treatment plant operator. During his employment at the Jeffersonville facility, Mr. Redden held positions as an associate chemist, senior chemist/plant microbiologist, and wastewater treatment plant supervisor. His duties included daily operations and supervision of personnel, scheduling and performance of maintenance activities, budgeting, ordering, materials balance, sludge management, laboratory analysis, quality assurance and quality control programs, and compliance with various state and federal reporting requirements. Mr. Redden has no experience either in the operation of a drinking water or domestic wastewater treatment plant, or at a DER-permitted industrial wastewater treatment plant.
Recommendation Based on the foregoing, it is hereby: RECOMMENDED that the Department of Environmental Regulation enter a Final Order denying the application of James H. Redden for certification as a Class B wastewater treatment plant operator. DONE and RECOMMENDED this 9th day of April, 1992, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 1992. APPENDIX The following constitute rulings on proposed findings of facts submitted by the parties. Petitioner: The Petitioner did not file a proposed recommended order. Respondent: The Respondent's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 2-4. Rejected, unnecessary. COPIES FURNISHED: Carol Browner, Secretary Dept. of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, General Counsel Dept. of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 James H. Redden 1362 Chesapeake, Avenue Naples, Florida 33962 Francine M. Ffolkes, Esq. Assistant General Counsel 2600 Blair Stone Road Tallahassee, Florida 32399
The Issue Is Petitioner guilty of violations of Rule 64E-6.022(1)(p), Florida Administrative Code, improper installation or repair of on-site sewage disposal system, and Rule 64E-6.022(1)(l), Florida Administrative Code, gross negligence and incompetence which causes monetary harm to a customer as charged in the Citation for Violation dated April 4, 2000, and if so, what penalty should be imposed.
Findings Of Fact Based upon the evidence adduced at hearing and the record as a whole, the following findings of fact are made: Pursuant to Section 381.0065, Florida Statutes, the Department has the authority and jurisdiction to regulate the construction, installation, modification, abandonment or repair of on-site sewage treatment and disposal systems (used interchangeably with "septic tank" or "drainfield" throughout this Recommended Order). Septic tank repairs may be made only by individuals who have qualified with and are licensed by the Department and subject to the standards of ethics and competence established by Department rules. See, Section 489.553(3), Florida Statutes (1999). At all times material to this action, Petitioner has been registered with the Department as a septic tank contractor and serves as Vice President of Sales for Allstate Septic Tank Company (Allstate). Allstate is owned by Jack Dunn (Dunn). Petitioner has been employed by Allstate since 1982. At the time Petitioner commenced her employment with Allstate, the company was owned by an individual who sold the business to Dunn in 1995. From 1982 to 1995 when Dunn acquired the business, Petitioner worked as Allstate's office manager. Dunn, not Petitioner, has final authority over how Allstate's work is performed and what accommodations, if any, will be made with dissatisfied customers or with regulatory authorities. At all times material to this case, Cheryl and Kelly Sadar (Owners) owned and resided in a home at 1770 SW 30th Place, Ft. Lauderdale. Like the other homes in this neighborhood, Owners' property relied upon an on-site drainage and sewage system. The drainfield at the Owners' property had been replaced in 1988 and had operated without problem until December 1998. In December 1998, Cheryl Sadar called Allstate and asked the Company to "check out" odors coming from the grass lawn on Owners' property. Pursuant to that request, Petitioner and Dunn visited the Owners' property. In January, 1999, Allstate pumped the Owners' septic tank and told Mrs. Sadar that if the pumping did not work, it would be necessary to replace the existing drainfield. Pumping did not work and in March 1999, the Owners authorized Allstate to replace the existing drainfield with a new drainfield system. Petitioner and Dunn differ from the Owners in their testimony regarding what, if any, requirements Allstate sought to impose upon the Owners in order to assure that the drainfield to be installed by Allstate would work properly, and what, if any, limits the Owners placed upon Allstate's ability to exercise professional judgment as to where the drainfield should be installed. For example, Petitioner claims that Owners forbade Allstate the use of the eastern border of Owners' property because they wanted to store a boat there. Department witnesses deny that Owners ever sought to impose such a restriction. The parties also disagree as to the significance of certain restrictions which the parties agree were in fact imposed. For instance, there is no dispute that Owners were unwilling to cut down a favorite oak tree, despite Allstate's recommendation that they do so. But the parties differ in their recollection of what, if anything, was said to Owners about the impact of that decision upon Petitioner's ability to deliver a working drainfield. The factual disputes regarding limitations allegedly placed upon Petitioner by Owners are resolved in favor of the Department. Having considered the demeanor of the witnesses during their testimony, together with all of the facts and circumstances surrounding the dealings of the witnesses, the undersigned concludes that Owners placed no restrictions upon Allstate in the performance of its contract, save the requirement that the favorite oak tree be left standing. In that instance, the undersigned concludes that the Owners testified truthfully that Allstate informed them that the new drainfield may need to be replaced as soon as a decade after its installation if the oak tree remained, and Owners accepted that particular risk. There was undisputed testimony that other homes in the Owners' neighborhood have drainfields adjacent to mature oak trees, and that proximity has never been known to cause a drainfield failure within months of installation. It is not believable that Owners allowed Allstate to install a drainfield with knowledge that Allstate expected the system to fail within months if the oak tree was not removed. Similarly, there was no evidence, save for the testimony of Petitioner and Dunn, that Owners ever owned a boat, or had plans to buy one. Indeed, Gerald Timmons, who replaced the failed Allstate drainfield with a system which was operating without problems through the date of the hearing, testified that Owners made no attempt to restrict the location of the drainfield, and that he in fact installed his system over the eastern border of the property where Petitioner claimed Owners had denied access. By contract dated March 1, 1999 (Composite Exhibit 17, "the contract"). Allstate undertook to provide a new drainfield to Owners for the price of $2,300.00. Pursuant to the contract, Petitioner undertook to provide the Department with information required to secure necessary Department permits. In the permit application, Petitioner misrepresented the condition of the ground below the drainfield as having suitable soil conditions for the proposed work. In fact, the opposite was true. The presence of the pre-existing drainfield rendered the site unsuitable and indeed, doomed to fail. The site evaluation provided by Petitioner represented an adequate amount of sand in the drainfield area and an observed water table depth of 48 inches below the existing grade. Unrebutted expert testimony demonstrates that these representations could not possibly have been true, due to the presence of the pre-existing drainfield which Petitioner failed to excavate prior to installing a new system directly on top of the pre-existing drainfield. Petitioner testified that she personally probed five feet down the center of the area where the Allstate drainfield was to be placed but found no sign of the pre-existing drainfield which was there. This testimony is belied by the more credible the testimony of the Department's experts, who agreed that if Petitioner's account of her probe were accurate, the pre-existing drainfield would necessarily have been discovered. Petitioner's permit application inaccurately represented the amount of available space for the installation of a drainfield as being limited to 375 square feet. In fact, the owners' property would accommodate a 523 square foot drainfield. The separation between the bottom of the Allstate drainfield system and the water table depth required for the competent installation of a drainfield was not met by Petitioner. The parties expended a great deal of time establishing the hard feelings between Owners and Allstate and between Department officials and Allstate, particularly its owner Dunn. Witnesses aligned with both sides testified at length to various incidents of boorish behavior by Allstate employees and by the Owners. Similarly, there appears to be a history of distrust between at least some Department officials and Dunn, which was exacerbated between November 1999 and March 2000, when the efforts by the Department to mediate the dispute between Allstate and Owners were unsuccessful. Unquestionably, relations between Allstate and Owners deteriorated rapidly upon the failure of the drainfield, but the various exchanges of angry words and the Department's unsuccessful effort to persuade Allstate to partially compensate Owners have no relevance to the question of whether Petitioner did or did not commit the violations alleged in the Administrative Complaint, and have not been considered by the undersigned in resolving those issues. In this case, Allstate did not provide Owners with a written guarantee of its work, and there is no legal requirement that it do so. Neither did Allstate provide Owners with any written disclaimers or instructions for using the system or warnings that certain types of activities would cause the system to fail. Allstate company policy permits the installation of drainfield systems even in cases where Allstate believes the system is not likely to work. The Petitioner's installation was completed in March 1999 and Owners paid Allstate the $2,300.00 contract price. Beginning in the fall of 1999, Owners began to experience problems with the Petitioner's drainfield. Owners contacted Allstate, which rejected Owners' request that it take corrective action. Owners also contacted the Department, which made efforts to mediate between Owners and Allstate. The evidence is inconclusive as to why the Department's mediation efforts failed. At one point, Allstate seemed agreeable to making a partial refund to Owners, but later Dunn changed his mind. However, Allstate and Petitioner have always asserted that the failure of the drainfield was entirely the fault of the Owners. Indeed, throughout the history of Allstate's dealings with Owners, throughout the final hearing and in Petitioner's proposed Recommended Order, Petitioner has offered a variety of theories as to why her work failed. One suggestion was that the use of a lawnmower contributed to the drainfield's failure. Petitioner also insisted that Owners used too much water, causing hydraulic overload and precipitating the failure of Petitioner's system. Petitioner asserts that Owners' water usage increased by 8.85 percent from March 1999 when Petitioner's system was installed to November 1999, when the system began to fail. And in its Proposed Recommended Order, Petitioner asks for the first time that the undersigned take judicial notice that on October 19, 1999, Hurricane Irene "swept through the Fort Lauderdale area", leaving substantial rainfall-related damage in its wake; however, no evidence was offered linking the rains of Hurricane Irene to Owners' drainfield failure. The unanimous weight of expert opinion, save that of Allstate's owner Dunn, is that the various theories advanced by Petitioner as reasons for the failure of her work--singly or in combination--are insufficient to explain the sequence of events at the Owners' property as it relates to the problems they experienced with the Allstate drainfield system. By March 2000, it was clear that the Allstate-installed drainfield had failed. Jerry's Septic Tank Service and its owner, Gerald Timmons, were engaged by the Owners to evaluate the situation and make necessary repairs. A repair permit was issued to Jerry's by Department on March 13, 2000, and work was commenced. Almost immediately it became apparent that an old drainfield was located immediately beneath the Petitioner's drainfield. Jerry Timmons immediately called Owners to notify them of this finding. Owners, in turn, called Department official Jay Morgenstern to advise of Timmons' discovery. Allstate was also informed of the discovery of the preexisting drainfield. Petitioner and Dunn each conversed with Jerry Timmons about the pre-existing drainfield adjacent to the Allstate drainfield. At all times after Allstate was notified of the failure of its system, Allstate and Petitioner continued to maintain that the failure was the fault of the Owners, not Allstate, and that the preexisting drainfield either was not there in March 1999 or was not discoverable by Allstate. Morgenstern personally conducted an inspection and verified Timmons' finding that old drainfield material was clearly visible. Thereafter, the Department issued the Citation for Violation. The services provided by Petitioner in March 1999, constitute an improper and incomplete repair and installation. The improper, incomplete services provided by Petitioner in March 1999, resulted in Owners being required to expend $2,800.00 for the services of Jerry's Septic Tank to excavate the pre-existing drainfield, along with the defective Allstate system, and to provide a functioning septic tank system, in addition to the $2,300.00 previously paid to Allstate.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order finding Petitioner guilty of the unlawful conduct alleged in the Administrative Complaint and disciplining her therefor by fining her in the total amount of $1,000.00. DONE AND ENTERED this 19th day of October, 2000, in Tallahassee, Florida. FLORENCE SNYDER RIVAS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of October, 2000. COPIES FURNISHED: Judith C. Elfont, Esquire Department of Health 2421-A Southwest Sixth Avenue Fort Lauderdale, Florida 33315-2613 William E. Stacey, Jr., Esquire 320 Southeast 9th Street Post Office Box 460053 Fort Lauderdale, Florida 33346 Theodore M. Henderson, Agency Clerk Department of Health 4052 Bald Cypress Way Bin A-02 Tallahassee, Florida 32399-1703 William W. Large, General Counsel Department of Health 4052 Bald Cypress Way Bin A02 Tallahassee, Florida 32399-1701 Dr. Robert G. Brooks, Secretary Department of Health 4052 Bald Cypress Way Bin A00 Tallahassee, Florida 32399-1701
Findings Of Fact On or about October 30, 1984, Lawrence E. Bennett, a consultant engineer for Peninsula, forwarded to DER's domestic waste engineering section an application to construct/operate a domestic wastewater treatment and disposal system along with the appropriate plans and a check for the fee. The package included proposals for construction of a 300,000 gpd splitter box and addition of a 100,000 gpd contact stabilization plant. Thereafter, on May 22, 1985, Mr. Bennett submitted a revised copy of the application pertaining to the 100,000 gpd expansion initially submitted as above. The revised application reflected Peninsula's proposed outfall to the Halifax River which was applied for under separate permit. By application dated October 7, 1983, as revised on May 15, 1985, Peninsula proposed to construct an outfall discharge into the Halifax River from the secondary treatment plant. By letter dated October 29, 1984, Mr. Bennett advised DER, inter alia, that the discharge rate would be an ADF of 1.25 mgd. The application for the additional 100,000 gpd plant and splitter box also provided for a chlorination facility. This expansion was needed because 200,000 gpd capacity is already committed to serve current residents and customers of the utility. The new construction is designed to accommodate established future demand. In Mr. Bennett's opinion, the design of this facility will accommodate all DER criteria and standards. The outfall facility proposed in the second project will be a pvc forced main for a part of the distance with iron pipe for the remainder and a lift station attached to pump the effluent to a point in the river selected where the river is deep enough to meet DER water criteria. The initial permit application on this project called for discharge into a portion of the river which did not meet water quality standards. As a result; DER suggested discharge point closer to the center of the river, and this change is now planned. At this point, the outflow will meet DER standards. Intents to issue the permits, as modified, were issued in August 1985. Peninsula has also filed for permits with the Florida Public Utilities Commission, the United States EPA, and the U.S. Army Corps of Engineers for these projects. The plans are based on the estimated population expansion called for in the next few years. Peninsula is fully capable, financially, of providing and paying for the projected improvements. In the past, it has always provided sufficient funding to do that which is called for under its permits and which is necessary. The waters in question here are Class III waters of the State, mainly recreational. There is no shellfish harvesting in the area because of the pollution of the Halifax River, condition which has existed since at least 1941. Results of tests conducted by experts for Peninsula show the quality of the water presently coming out of the treatment plant is cleaner than that currently existing in the Halifax River. The outfall pipe in question will have the capability of handling approximately 1,200,000 gpd. Latest reports from the water treatment plant indicate that the current average daily flow is 150,000 gpd representing approximately 75% of capacity. The design estimated for this project was based on a 250 gpd per unit use rate multiplied by the estimated number of units presently existing and to be constructed in the period in question. It is estimated however, that within two to three years even this project will be insufficient and Peninsula will have to file an additional request for expansion. Construction will have no detrimental environmental effect on the waters of the Halifax River. Mr. Bennett recommends discharge into the river rather than pumping the effluent backup to Port Orange because the local dissipation rate into the Halifax River, which is called for under these projects, is much quicker than that at Port Orange. Studies run on siting of the outfall pipe location which is close to Daggett Island included studies relating to dilution calculation and water quality of the effluent versus water quality of the river near the outfall. The project was, therefore, sited in such a manner as to provide for the least possible detrimental effect. Those studies, however, were for the original outfall location, not the present location as proposed by DER which is approximately 150 to 200 feet away. In the experts' opinion, however, there is very little difference in the two sites. The Daggett Island site is not unique in any way. It is a mangrove swamp of approximately 3 to 4 acres with nothing on it. Once the pipe is buried, it will be difficult to know that it is there. Even during construction, there would be little detrimental effect or disruption to the river ecology. Mr. Bennett's conclusions are confirmed by Mr. Miller; a DER engineer specializing in wastewater facility permits who has reviewed the plans for expansion of the plant for completeness and adequacy and found that they were both. The approval of the outfall pipe initially was made in Tallahassee based on the original siting. He reviewed it again, however, and determined that both projects are environmentally sound and conform to the DER standards. Rule 17-6, Florida Administrative Code, requires surface water discharge to have secondary treatment activity prior to discharge and the discharge cannot exceed 20% 80D and suspended solids. According to DER studies; the secondary treatment afforded the water at this location was adequate with the caveat that the District might want to require an extension of the outfall to the main channel of the river to promote tidal flushing of the effluent. It was this change which was; in fact, made by the District office. Without the change, the incoming tide would take the wastewater up into Daggett Creek. By moving it as suggested, west of the point of Daggett Island, the tide would go up river rather than into the creek taking the effluent with it. Concern over the creek is due to its limited natural flushing as opposed to the greater natural flushing of the river. It was the intent of all parties to achieve the desired result and move the outfall point; if at all possible, at no increase in cost. Consequently, the pipeline was moved at the same length with a slight possible addition to take the outlet to the same depth and this change became a condition to the issuance of the permit. The Peninsula will also need a dredge and fill permit in order to accomplish the work in question. The outfall plans (both construction and discharge) meet the requirements set forth in the pertinent provisions of Rule 17-6, Florida Administrative Code. DER evaluated post- construction, concluding that the new point source discharge would not violate these standards. However, prior to approval of these projects, DER did not perform a biological, ecological, or hydrographic survey in the area. As a result, it cannot be said that the criteria outlined in Rule 17-4.29(6), Florida Administrative Code, will not be adversely affected by the outfall pipe. Nonetheless, these surveys were not deemed necessary here. EPA denial of the NPDES (National Pollution Discharge Elimination System) permit, would have no impact on DER's intent to issue the instant permits. NPDES permits have no bearing on the state permitting process. If the NPDES permit is denied, the utility cannot discharge its effluent into the river. The state permit merely authorizes the construction. The NPDES permit applies to the outfall portion of the project, not to the treatment plant. Only if it could be shown there was a longstanding adverse effect on the water quality so as to bring it below standards, would this construction not be permitted. The depth of the water in the proposed area of the outfall is five feet. A 12-inch pipe would extend below the soil with an upturn to exit into the bottom of the river. Short term impacts of actual construction are not relevant to the permitting process. If there are any, they would be related to and considered in the dredge and fill permitting process. This conclusion is supported by the testimony of Jan Mandrup-Poulsen, a DER water quality specialist who, in his analysis of the instant projects, first looked at the plans for the outfall just a week before the hearing. By this time, the water quality section of DER had previously considered the project and he is familiar with the suggested change in the outfall location. In November 1985, he spent several days on a boat on the Halifax River in this area collecting data. His inquiry and examination showed that in the area in question, there are no grass beds, oyster beds, or anything significant that would be adversely affected by the location of the pipe and the outlet. The pipe outlet, as suggested, is far enough out into the river to keep it under sufficient water at all times to promote adequate flushing. In his opinion, the proposed discharge will be quickly diluted and will not violate the standards or other criteria set out in Section 17-3.121, Florida Administrative Code. In contrast to the above, Mr. Richard Fernandez, a registered civil engineer with a Master's Degree in environmental engineering, who did a study of these projects for TPI, indicated that the County 201 plan relating to this area, mandated by the federal government, calls for the eventual closing of all independent wastewater treatment plants with ultimate delivery of all wastewater to the Port Orange facility. If implemented, this plan calls for the conversion of the Peninsula facility to a pump station for the transmittal of effluent to Port Orange. In his opinion, the proposed discharge standard, as evaluated here, for the secondary treatment facility, is very high for such a facility. He feels the surface water discharge content of dissolved oxygen and suspended solids should be lower. In addition, he is of the opinion that the degree of treatment of discharged water required by the facilities in question here is too low and lower than typical secondary discharge points elsewhere in the area. Nonetheless, Mr. Fernandez concludes that while the intended facility here would probably not lower the quality of river water below standards, it is not in the public interest to construct it. Having considered the expert testimony on both sides, it is found that the construction requested here would not create sufficient ecological or environmental damage to justify denial. The proposals in the 201 plan calling for the transmittal of all effluent to Port Orange would not be acceptable to DER. The cost of such a project and the ecological damage involved would be so great as to render the project not even permittable. The currently existing percolation ponds used by the facility at Port Orange are not adequate to serve current needs and leech pollutants into the surrounding waterway. While the exact transmission routes called for under the 201 plan are not yet set, there would be substantial ecological problems no matter what routing is selected. There would be substantial damage to bird habitat, mangrove, and other protected living species unless some way were found to get the pipe across the river in an environmentally sound fashion. Consequently, DER has taken the position that the current proposals by Peninsula are superior to any plan to transmit waste to Port Orange.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore RECOMMENDED THAT DER: Enter an order dismissing with prejudice Volusia County's Petition in DOAH Case No. 85-3029 and, Issue permits to Peninsula Utilities, Inc., for the construction of a 100,000 gpd expansion to its existing wastewater treatment plant and to construct a river outfall line as was called for in the amended specifications listed in the application for this project. RECOMMENDED this 25th day of April, 1986, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of April, 1986. COPIES FURNISHED: Martin S. Friedman, Esquire Myers, Kenin, Levinson & Richards 2544 Blairstone Pines Drive Tallahassee, Florida 32301. Deborah Getzoff, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Rd. Tallahassee, Florida 32301 Lester A. Lewis, Esquire Coble, McKinnon, Rothert, Barkin, Gordon, Morris and Lewis, P.A. P. O. Drawer 9670 Daytona Beach, Florida 32020 Ray W. Pennebaker, Esquire Assistant County Attorney P. O. Box 429 Deland, Florida 32720 Victoria Tschinkel Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 APPENDIX The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings Of Fact submitted by the parties to this case. Rulings on Proposed Findings of Fact Submitted by Petitioner, TPI 1-2. Accepted in paragraph 17. 3-4. Rejected as contra to the weight of the evidence. Rulings on Proposed Findings of Fact Submitted by Peninsula 1-13. Accepted in the Findings of Fact of the Recommended Order. Rulings on Proposed Findings of Fact Submitted by Respondent, DER 1. Accepted and incorporated in Finding of Fact 1 and 2. 2-3. Accepted and incorporated in Finding of Fact 5. 4-5. Accepted and incorporated in Finding of Fact 20 and 21. 6. 7. Accepted in Finding of Fact 19. 8. Accepted in Finding of Fact 14. 9. Accepted in Finding of Fact 9. 10. Accepted in Finding of Fact 8 and 21. 11. Accepted in Finding of Fact 14 and 17. 12-13. Accepted in Finding of Fact 14 and 17. 14-15. Rejected as a statement of evidence and not a Finding of Fact. Accepted in Finding of Fact 17. Recitation of Mr. Miller's testimony is not a Finding of Fact. The conclusions of Mr. Mandrup- Poulsen's testimony is not a Finding of Fact. Recitation of Mr. Mandrup-Poulsen's testimony testimony is not a Finding of Fact. Accepted in Finding of Fact 23. Recitation of testimony is rejected as not a Finding of Fact. Conclusions drawn from that testimony accepted in Finding of Fact 24.