The Issue Whether, in issuing the Revised Recommendation/Tabulation for contracts for Items 1 and 3 for Invitation to Bid No. 15- 048E, Multifunctional Devices, Cost-Per-Copy, Respondent acted contrary to one or more governing statutes, rules, policies, or procurement specifications, or any combination thereof; and if so, for each such instance, whether the misstep was clearly erroneous, arbitrary or capricious, or contrary to competition.
Findings Of Fact On June 3, 2014, SBBC issued ITB No. 15-048E (the ITB) entitled "Multifunctional Devices, Cost-Per-Copy" for the provision and maintenance of copying devices during the contract term. The listed Submittal Requirements were: Manufacturer's Authorization Special Condition 8; Descriptive Literature Special Condition 6; and Material Safety Data Sheets Special Condition 16. A Bidder's Preference Statement was not identified as a Submittal Requirement. Section 4, Paragraph 2, of the ITB was entitled "TERM" and notified bidders that SBBC sought through the award of this bid to "establish a contract for the period beginning from the date of award and continuing through June 30, 2017." The Bid Summary Sheet found at Section 5 of the ITB requested bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months and for 36 months. Page 1 of the ITB contained a certification to be executed by each bidder's authorized representative which stated in pertinent part as follows: Bidder agrees to be bound to any and all specifications, terms and conditions contained in the ITB, and any released Addenda and understand that the following are requirements of this ITB and failure to comply will result in disqualification of bid submitted. All bidders submitted a signed bidder certification. Section 3, Paragraph 1(a), of the General Conditions of the ITB provided as follows: SEALED BID REQUIREMENTS: The "Bidder Acknowledgment Section" must be completed, signed and returned with the bid. The Bid Summary Sheet pages on which the Bidder actually submits a bid, and any pages, upon which information is required to be inserted, must be completed and submitted with the bid. The School Board of Broward County (SBBC) reserves the right to reject any bid that fails to comply with these submittal requirements. BIDDER'S RESPONSIBILITY: It is the responsibility of the Bidder to be certain that all numbered pages of the bid and all attachments thereto are received and all Addendum released are received prior to submitting a bid without regard to how a copy of this ITB was obtained. All bids are subject to the conditions specified herein on the attached bid documents and on any Addenda issued thereto. Section 3, Paragraph 6, of the General Conditions of the ITB provided as follows: AWARDS: In the best interest of SBBC, the Board reserves the right to: 1) withdraw this bid at any time prior to the time and date specified for the bid opening; 2) to reject any or all bids received when there are sound documented business reasons that serve the best interest of SBBC; 3) to accept any item or group of items unless qualified by Bidder; and 4) to acquire additional quantities at prices quoted on this ITB unless additional quantities are not acceptable, in which case, the bid sheets must be noted "BID IS FOR SPECIFIED QUANTITY ONLY." On June 18, 2014, SBBC issued Addendum Number 1 for the ITB which replaced a number of pages within the bidding documents and contained responses to questions posed by prospective bidders. Addendum Number 1 included Question No. 6 in which Xerox inquired whether SBBC "would . . . consider a change to the contract term of the contract to 48 or 60-month term?" SBBC responded through Addendum Number 1 that it had amended the bid "to include additional pricing for 48 or 60-months term[s]," and SBBC continued to request proposals for a 36-month contract term. Addendum Number 1 revised Section 4, Paragraph 2, of the Special Conditions of the ITB to state as follows: TERM: The award of this bid shall establish a contract for the period beginning from the date of award and continuing through an award for a term of 36, 48 or 60 months. Bids will not be considered for a shorter period of time. All prices quoted must be firm throughout the contract period. Items will be ordered on an as needed basis. Addendum Number 1 included an Appendix A–Summary Cost Sheet which required bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months, 36 months, 48 months, and 60 months. On June 20, 2014, SBBC issued Addendum Number 2 for the ITB. The first page of Addendum Number 2 advised prospective bidders, "This Addendum amends the above referenced bid in the following particulars only: 1. DELETE: Appendix A–Cost Summary Sheet INSERT: Revised Appendix A–Cost Summary Sheet." The first page of Addendum Number 2 further cautioned bidders that "[i]t is important to include the REVISED page when submitting your response." Addendum Number 2 went on to provide a Revised- Appendix A-Summary Cost Sheet which stated "A Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months" and included a cost summary sheet for each of those three options. The ITB and addenda numbers 1 and 2 were released by SBBC via Onvia DemandStar, with email notices thereof to prospective vendors who subscribed to its bid notification service. Toshiba downloaded the ITB, Addendum Number 1, and at least the first page of Addendum Number 2 from DemandStar prior to the submission of its bid to SBBC. Again, the first page of Addendum Number 2 cautioned bidders that Appendix A–Summary Cost Sheet had been deleted and replaced and that it was "important to include the REVISED page when submitting your response." No bid specifications protest was filed by any person or entity concerning the ITB or addenda numbers 1 or 2. On July 3, 2014, SBBC opened bids timely submitted in response to the ITB by: Toshiba; ImageNet; Innovative; Lexmark International, Inc.; and Ricoh. Konica had also presented a bid to SBBC in the bid opening room prior to the opening of bids but after the announced time for submittal of bids. The Konica bid was delivered to SBBC but was not opened at the time of the bid opening. Toshiba, the incumbent, was the only bidder that violated the pricing requirements of the ITB. The bid submitted by Toshiba utilized the version of Appendix A-Summary Cost Sheet that was released under Addendum Number 1 and only offered cost- per-copy pricing for the 60-month term option. Toshiba's bid did not submit the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, nor did it contain any bids offering cost per copy pricing to SBBC for the 36 or 48-month term options. Although Toshiba's bid was not rejected as non-responsive for failing to bid on the 36 and 48-month term options and for failing to utilize and complete the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, SBBC's staff later concluded in hindsight that it should have been rejected for such non-compliance. Toshiba's bid included a "Pricing" note immediately prior to its Appendix A–Summary Cost Sheet that stated: [Toshiba] is proposing a 60 month CPC as a response to the [ITB]. Based on the fact the [ITB] has no minimum, cancellation for convenience, ability to upgrade and downgrade with no penalty, it is in the best interest of our organization to bid a term of 60 months. This term allows us to provide the most aggressive price to the [SBBC] and maintain the excellent service and support level in place. SBBC's staff recommended that an award be made under the ITB for pricing offered for a 36-month contract term for Items 1, 2, and 3 for a contract period of August 6, 2014, through September 30, 2017. On July 10, 2014, SBBC posted its initial ITB Recommendation/Tabulation which did not consider the Konica bid. The initial posted Recommendation/Tabulation notified bidders of SBBC's intended award of contracts for Items 1 and 2 to ImageNet as the primary awardee and to Innovative as the alternate awardee for a contract period of August 6, 2014, through September 30, 2017, and recommended the award of contracts for Item 3 to Ricoh as primary awardee and to ImageNet as alternate awardee for a contract period of August 6, 2014, through September 30, 2017. Timely bid protests and bid protest bonds were filed by Konica and by Toshiba concerning SBBC's initial Recommendation/Tabulation of July 10, 2014. SBBC's Bid Protest Committee conducted a meeting with the protestors on August 26, 2014, and determined that Konica's bid had been timely submitted and directed SBBC's Procurement and Warehousing Services Department (the Department) to evaluate Konica's bid for responsiveness. It also directed the Department to revise its recommendation on the ITB to reject Toshiba's bid for Item 2 as the device offered by Toshiba for that item did not meet the ITB's specifications which called for a single device capable of performing 95 copies per minute (cpm) and Toshiba instead offered two devices that performed at 85 cpm. After reviewing Konica's bid for responsiveness, SBBC posted a Revised Recommendation/Tabulation for the ITB on August 29, 2014, which (a) recommended award of Item 1 to ImageNet for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to Innovative as the alternate awardee; (b) recommended award of Item 3 to Ricoh for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to ImageNet as the alternate awardee; and (c) recommended the rejection of Toshiba's bid for Item 2 for its failure to meet the specifications for that Item. On September 4, 2014, Toshiba timely filed its notice of intent to protest the August 29, 2014, posted Revised Recommendation/Tabulation. On September 15, 2014, Toshiba timely filed its Amended Formal Petition Protesting Proposed Revised Recommendation/Tabulation. SBBC's Bid Protest Committee conducted a meeting with Toshiba on November 5, 2014, pursuant to section 120.57(3), SBBC Purchasing Policy 3320, and the ITB, and rejected Toshiba's bid protest. On November 10, 2014, Toshiba timely requested that SBBC forward its bid protest to DOAH for a formal hearing. Toshiba has presented a number of arguments in these proceedings seeking to avoid the circumstances Toshiba created for itself when it failed to comply with Addendum Number 2 and violated the ITB's pricing requirements and the ITB's requirement as to the term of the contract to be awarded, when Toshiba only submitted a single bid and restricted the contract term for which it would be considered to 60 months. First, Toshiba attempts to divest SBBC of its express authority to select proposals for any contract duration for which it solicited bids other than for a month term. Second, Toshiba argues that SBBC was somehow obligated to specify within the bid specifications those business considerations that would inform SBBC's selection of the duration of the contract term to be awarded under the ITB. Third, Toshiba argues that ImageNet was non-responsive regarding the ITB's specifications concerning manufacturer's certifications. Toshiba also argues that all bidders, including itself, were non- responsive with regard to the ITB's specifications regarding bidding preference laws. None of the arguments presented by Toshiba in opposition to SBBC's intended award of Items 1 and 3 are persuasive. The Selection of the 36-Month Term SBBC's recommended award for a 36-month contract period from October 7, 2014, through November 30, 2017, is consistent with the terms and conditions of the ITB and its addenda. At the very start of this competitive solicitation, SBBC informed bidders through Section 4, Paragraph 2, of the ITB and the Bid Summary Sheet at Section 5 of the ITB that it was seeking a contract through June 30, 2017-–i.e., a 36-month contract. SBBC also made it clear in its response to Question No. 6 of Addendum Number 1 that "[t]he contract will be for a full 36 months." Although SBBC revised the bid specifications through Addendum Number 1 to allow bidders to submit "additional pricing for 48 and 60 months term[s]," "to allow the School District to consider a 48 and/or 60 months term contract," and revised Section 4, Paragraph 2, of the ITB to provide for "an award for a term of 36, 48 or 60 months," it was clear under the ITB that SBBC contemplated that a 36-month contract could serve its needs. Addendum Number 2 further revised the bid specifications by providing the Revised–Appendix A–Summary Cost Sheet which informed bidders that "a Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months." SBBC intended to review the additional pricing offered for 48 and 60- month contract terms to determine whether those particular options were a better business decision for SBBC. Several factors were considered by SBBC in selecting the contract duration for the award under the ITB. The selection of the shorter 36-month contract term was consistent with the expressed terms of the ITB and addenda and the expressed preference of SBBC's governing board to refrain from entering into long-term contracts and enabled SBBC to be flexible in finding solutions to its copying needs and to take advantage of changes that may arise in technology; avoided problems the school district was currently experiencing with a long-term cost-per- copy contract which ranged from equipment performance issues to the long-term placement of technology in schools; and enabled the school district to conduct research to determine whether future implementation of a managed print solution would provide the school district with additional cost savings or financial benefits in contrast to the cost-per-copy services being procured through the ITB. Clearly, this selection was neither arbitrary nor capricious. SBBC's elected governing board has made it known by its actions taken at public meetings that it disfavors long-term contracts for the procurement of goods and services and has gone so far as to reduce the term of contracts from the dais. SBBC's staff determined that the pricing offered to SBBC for a 60-month contract term was not significant enough to recommend a contract longer than the 36-month term SBBC had been requesting since the release of the ITB. Any cost advantages offered by Toshiba's bids for Items 1, 2, and 3 were reduced by $525,000 per year due to the disqualification of its bid for Item 2, which failed to meet the ITB's specifications. Consideration of Managed Print Services Xerox Corporation informed SBBC that a managed print services (MPS) program could save millions of dollars per year and later submitted a no bid response to SBBC regarding the ITB because SBBC was not implementing a MPS program under the ITB. SBBC had also received proposals from vendors in October 2013 concerning a MPS program and concluded that there existed a potential annual savings of millions of dollars if such a program could be implemented. All of which were additional reasonable, rational reasons for SBBC to remain consistent with its decision to award the contracts for a term of 36 months and not something longer. The ITB contains standard terms and conditions which enable SBBC to terminate an awarded contract regardless of reason and with or without cause upon 30 days written notice to the other party. Toshiba wants SBBC to rescue Toshiba from its failure to submit required bids for 36-month and 48-month periods by forcing SBBC to award a contract obligating the agency for a longer duration under the ITB than desired by the agency and then have SBBC terminate the 60-month contract award for convenience after 36 months. SBBC includes termination for convenience provisions within its contracts for goods and services due to section 1011.14, Florida Statutes, which restricts the ability of district school boards to obligate public funds for a period beyond one year. The inclusion of the standard termination for convenience clauses in its ITBs enables SBBC to enter into contracts exceeding one year which affords the school district opportunities to obtain continuity of service and price advantages that would not be available under shorter contracts. While SBBC has the ability under the ITB to terminate contracts for convenience upon 30 days' notice, it rarely does so. SBBC has never exercised its right to terminate its two prior contracts for the services sought under this ITB. Any such termination requires action by SBBC's governing board during a public meeting. SBBC's staff would not engage in the sham of recommending a contract to its governing board for a contract term longer than the period for which it intends to procure services from a vendor. SBBC's procurement staff believes that using the termination for convenience clause in the manner Toshiba recommends can have an adverse effect upon the school district's ability to encourage bidders to participate in its competitive solicitations or to offer it their best pricing. Questions 1 and 59 of Addendum Number 1 of the ITB provide evidence of concern within the bidding marketplace that SBBC might exercise its termination for convenience clauses with regard to the services being procured under the ITB and support the perception of SBBC's that it should avoid a reputation for exercising such termination authority. Toshiba argues that SBBC somehow materially misled bidders through the ITB by stating in response to Question No. 3 concerning MPS of Addendum Number 1 that: The School District is not planning to implement a Managed Print Services at this time. The School District would like to receive Additional information regarding other districts that have implemented a Managed Print Services. There are no evaluation points associated with this ITB. SBBC's responses to Question No. 3 of Addendum Number 1 were accurate and did not mislead bidders. Toshiba is the only bidder to claim to have been misled. Section 6, Paragraph 10, of the ITB requested bidders provide SBBC with information about how the awardee could transition SBBC to a MPS model from the cost-per-copy model being offered under its bid. While SBBC requested such information from vendors within the bidding marketplace, there is no evidence that any bidder's provision or omission of such information within its bid submission was considered in the selection of the recommended awardees. In fact, ImageNet was recommended for award even though it did not provide this ancillary information about transition to a MPS delivery model. Rather, the recommended awardees for a 36-month contract term for Items 1 and 3 were determined solely on the basis of cost submitted for those items by the bidders, all in accordance with the ITB. A MPS program was a possible initiative being considered by SBBC's former Chief Information Officer prior to his departure from SBBC in February 2014, at which time the school district's current cost-per-copy contract was nearing its expiration. Although SBBC still had an interest in the possibility of a MPS program, it was not going in that direction at the time it needed to release a bid for copying services to replace its current expiring contract. Toshiba contends that SBBC was somehow required to disclose to bidders whether the potential future implementation of a MPS program might impact the contract award period that SBBC might choose under the ITB. A myriad of business considerations may inform an agency in selecting the length of its contracts for goods and services, and there is no law or rule that requires an agency to specify those factors within an ITB. Responsiveness of the Bidders Toshiba has attempted to argue that ImageNet, the recommended awardee for Item 1 and the alternate awardee for Item 3, was somehow non-responsive under the ITB and ineligible for award. In support of this argument, Toshiba has referenced Section 4, Paragraph 8, of the Special Conditions of the ITB which state as follows: MANUFACTURER'S CERTIFICATION: Bidder must submit with their ITB a notarized letter from manufacturer certifying that bidder is authorized to sell, service and warrant the multifunctional devices offered within this ITB. Failure of the bidder to provide this letter with their submitted bid or upon request shall result in disqualification of entire bid. If the bidder is the manufacturer, then bidder should state that their company is the manufacturer of the equipment provided in this bid (the letter does not need to be notarized). A bid is only disqualified under Section 4, Paragraph 8, of the ITB if (1) a notarized manufacturer's letter is omitted from the bid; and (2) the bidder fails to comply with a subsequent request from SBBC to provide the letter. No bidder, including Toshiba and ImageNet, included a notarized letter from a manufacturer with its bid. SBBC did not request any of the bidders to submit a notarized manufacturer's letter at any time after the submission of bids. As a result, none of the bids, including that of ImageNet, was non-responsive for a failure to satisfy Paragraph 8 of Section 4 of the ITB. Toshiba has also argued that all bids should be rejected due to Section 3, Paragraph 1(d), of the General Conditions of the ITB which concerns bidders' preference laws and states as follows: d) BIDDING PREFERENCE LAWS: ALL BIDDERS MUST COMPLETE AND SUBMIT THE LEGAL OPINION OF BIDDER'S PREFERENCE FORM IN ORDER TO BE CONSIDERED [sic] FOR AWARD. The State of Florida provides a Bidder's preference for Florida vendors for the purchase of personal property. The local preference is five (5) percent. Bidders outside the State of Florida must have an Attorney, licensed to practice law in the out-of-state jurisdiction, as required by Florida Statute 287.084(2), execute the "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form and must submit this form with the submitted bid. Such opinion should permit SBBC's reliance on such attorney's opinion for purposes of complying with Florida Statute 287.084. Florida Bidders must also complete its portion of the form. Failure to submit and execute this form, with the bid, shall result in bid being considered "non-responsive" and bid rejected. No bidder, including Toshiba, included an "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form with its bid. Each bidder's omission of that form was for good reason. Section 3, Paragraph 1(d), of the General Conditions of the ITB is a boilerplate provision within SBBC's standard bidding documents that is included pursuant to section 297.084(2), Florida Statutes, for any competitive solicitations in which personal property is to be purchased by SBBC. In instances in which it solicits bids to purchase personal property, SBBC includes a "Bidder's Preference Statement" form and includes that form among the checked "Submittal Requirements" listed in Section 2, Page 1, of the ITB. This ITB did not include a "Bidders Preference Statement" form among the bidding documents or list it as one of the required submittals. The state law and the boilerplate provision at Section 3, Paragraph 1(d), of the General Conditions of the ITB are only applicable to competitive solicitations for the purchase of personal property and do not extend to competitive solicitations for the purchase of services. As Section 4, Paragraph 12, of the Special Conditions of the ITB makes it clear that the multi-functional devices to be provided by the awardee under the ITB will "remain the property of the vendor," the standard bidder's preference provision contained within the ITB is plainly inapplicable to this procurement.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a final order that adopts the Findings of Fact and Conclusions of Law contained herein, dismisses the protest filed by Toshiba Business Solutions (USA), Inc., and upholds the awards of contracts under the procurement for a 36-month term from October 7, 2014, through November 30, 2017, to ImageNet Consulting of Miami, Inc., as the primary awardee for Item 1 and to Innovative Software Solution, Inc., as the alternate awardee for Item 1, and to Ricoh USA, Inc., as the primary awardee for Item 3 and to ImageNet Consulting of Miami, Inc., as the alternate awardee for Item 3. DONE AND ENTERED this 15th day of June, 2015, in Tallahassee, Leon County, Florida. S MARY LI CREASY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of June, 2015. COPIES FURNISHED: Robert Paul Vignola, Esquire Office of the General Counsel Eleventh Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) William G. Salim, Jr., Esquire Moskowitz, Mandell, Salim and Simowitz, P.A. 800 Corporate Drive, Suite 500 Fort Lauderdale, Florida 33334 (eServed) Eric J. Rayman, Esquire Genovese, Joblove and Battista, P.A. PNC Center, Suite 1110 200 East Broward Boulevard Fort Lauderdale, Florida 33301 (eServed) Albert E. Dotson, Esquire Wendy Francois, Esquire Bilzin, Sumberg, Baena, Price and Axelrod, LLP 1450 Brickell Avenue, Suite 2300 Miami, Florida 33131 (eServed) Matthew Mears, General Counsel Department of Education Turlington Building, Suite 1244 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed) Robert W. Runcie, Superintendent Broward County School Board Tenth Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) Pam Stewart Commissioner of Education Department of Education Turlington Building, Suite 1514 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed)
Findings Of Fact On February 25, 1994, DACS issued an Invitation to Bid ITB/DF-93/94-49 to obtain competitive bids for contractual services involving a biological assessment of approximately 44,334 acres of the Goethe State Forest in Levy County, Florida. The Invitation to Bid provided that the bids received would be opened at 2:30 p.m. on March 21, 1994. The Special Terms, Conditions and Specifications of the Invitation to Bid provided that references submitted by the bidder must be those of the bidder. The General Conditions of the Invitation to Bid provided that the Department may waive any minor irregularity or technicality in the bids received. Bids must be evaluated upon the information furnished with the bid. No other information is used. At the bid opening, Conway was the apparent low bidder at $0.71 per acre for a total of $31,477.14, and Environmental Services was the apparent second low bidder at $1.0438 per acre for a total of $46,275.66. ESP's bid was approximately 47 percent higher than Conway's bid. ESP's bid was responsive to the ITB and ESP is qualified to perform the work required under the ITB. Conway submitted three references with its bid. However, Conway's three references were for work previously performed by Ms. Duever as an individual or as an employee of another company. The references were not those of the bidder, Conway. Linda Duever, the sole officer and director of Conway Conservation, Inc., read the invitation to bid and was aware of the specific requirement for references of the bidder. Ms. Duever thought the Department and the Invitation to Bid emphasized the importance of similar work to that sought by the Department. She did not seek information about the reference requirements, even though she had some doubt about the references she was submitting, thinking she could supplement the bid later if necessary. Nor did she protest the specifications within the timeframes established by Chapter 120, Florida Statutes. Conway is a closely January 26, 1993. However, Conway Conservation, Inc., and Linda Duever are two separate and distinct entities. The evidence demonstrated that the references of the bidders were an important part of the information to consider in the award of this bid since the references indicated that the bidder had the expertise to perform the work required in the bid but also had the financial wherewithal to complete such work and hire the necessary personnel or subcontractors to successfully complete the work required in the Invitation to Bid. In this case, Petitioner's references demonstrated expertise in the areas of knowledge required to complete a biological survey. However, what the references did not show and could not show because they did not reflect business done by Conway, was the financial ability of Conway to adequately complete a biological survey. Such information was very important to the Department and was not a minor irregularity nor technicality which could, or should, have been waived by DACS. Given these facts Petitioner's bid was not responsive to the Invitation to Bid and the Department was correct in rejecting Petitioner's bid and awarding the project to ESP. Finally, Conway is not certified by the Department of Management Services as a minority business enterprise pursuant to Section 288.703(4), Florida Statutes, although the evidence demonstrated that Petitioner could easily be so certified. However, bidder's minority status, either certified or not certified, does not change the result in this case. Status as a Minority Business Enterprise was not a consideration in this bid award. Therefore, Minority Business Enterprise status, or lack thereof, did not and could not have had any impact on the outcome. Moreover, the Department has no authority to change the terms and conditions under which a bid is to be awarded after the bids are opened in order to grant more favorable treatment to a potential minority business.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent issue a Final Order in this case dismissing Petitioner's formal protest and awarding the contract for the Project to Environmental Services and Permitting, Inc. DONE AND ENTERED this 7th day of July, 1994, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of July, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 94-2121BID The facts contained in paragraphs A, B, D, E, F, G, H, I, K, L, M, O, Q, R and S, of Respondent's Proposed Findings of Fact are adopted in substance insofar as material. The facts contained in paragraphs C, J, N and P of Petitioner's Proposed Findings of Fact were subordinate. The facts contained in paragraphs 1, 2, 4, 5, 8, 9, 10, 12, 13 and 14 of Petitioner's Proposed Findings of Fact are adopted in substance insofar as material. The facts contained in paragraphs 3, 6, 7, 11, 15, 19, 20 and 21 of Petitioner's Proposed Findings of Fact are subordinate. The facts contained in paragraphs 17 and 18 of Petitioner's Proposed Findings of Fact were not shown by the evidence. COPIES FURNISHED: Isadore Rommes Senior Attorney Legal Office 515 Mayo Building Tallahassee, FL 32399-0800 Kent A. Zaiser P. O. Box 6045 Tallahassee, FL 32314-6045 Richard Tritschler General Counsel The Capitol, PL-10 Tallahassee, FL 32399-0810 Honorable Bob Crawford Commissioner of Agriculture The Capitol, Plaza Level Tallahassee, FL 32399 John T. Lavia, Esquire Landers & Parsons, P.A. Post Office 271 Tallahassee, Florida 32302
The Issue Should Petitioner Elizabethan Development, Inc. prevail in its challenge of Respondent Department of Health and Rehabilitative Services' Invitation to Bid (ITB) pursuant to Section 120.53(5) F.S. and Rule 10-13.011 F.A.C.?
Findings Of Fact On May 15, 1990, HRS mailed its ITB which is the subject of this proceeding. The ITB sought an existing facility for the agency to lease in Cross City, Florida, for use as a full client service center. Upon the face of the ITB documents, a preproposal conference was scheduled for May 23, 1990. Petitioner Elizabethan Development, Inc. received the ITB on May 16, 1990, as evidenced by a certified mail return receipt for that date. Petitioner filed its written intent to protest dated July 13, 1990 with the HRS agency clerk on July 16, 1990. Petitioner filed nothing with HRS prior to that date. Under the terms of the ITB, sealed bids were due to be received by HRS no later than 2:00 p.m. July 18, 1990. Petitioner filed no bid in response to the ITB prior to bid closing, nor at any other time. HRS proceeded to open and award the lease on July 18, 1990, despite Petitioner's July 16, 1990 intent to protest. Petitioner filed its formal protest dated July 24, 1990 with the agency clerk on July 26, 1990. Petitioner currently leases to HRS the building HRS now occupies in Cross City, Florida, and which HRS occupied at the time the ITB was issued. The July 16, 1990 intent to protest contained no specific information as to the nature of Petitioner's protest. The main thrust of the allegations contained in the July 26, 1990 formal written protest is that the specifications in the May 1990 ITB were so narrowly drawn that only one potential bidder (not Petitioner) could be responsive and that Petitioner could become responsive if ITB specification changes were negotiated. Additionally, the written protest alleged a number of problems which are, in essence, disputed issues with regard to the existing lease contract between Petitioner and HRS, which issues should more properly be brought before an Article V court. Petitioner admitted that its delay in filing its intent to protest and formal protest was occasioned by its conscientious preparation of its protest through undertaking an investigation of the existing available buildings in Cross City, Florida. Petitioner further admitted that its delay in filing its intent to protest and formal protest was voluntary and not induced by any representations by HRS or its employees.
Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health and Rehabilitative Services enter a Final Order determining the Petitioner's intent to protest and formal written protest to be untimely and dismissing same. DONE and ENTERED this 27th day of September, 1990, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of September, 1990. Copies furnished to: Alan Taylor Elizabethan Development, Inc. Post Office Box 7077 Winter Haven, Florida 33883 Frances S. Childers, Esquire HRS District 3 Legal Office 1000 N.E. 16th Avenue Gainesville, Florida 32609 Sam Power, Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
Findings Of Fact Background On February 23, 1988, Respondent, Department of General Services (Department), issued an invitation to bid (ITB) numbered 218-285-400-6, whereby it sought to establish a 24-month term contract for the purchase of large lamps, photo lamps, and studio, theatre, television, and video lamps by all State of Florida agencies. By April l, 1988, the bid opening date, four bids had been filed with the Department. On April 12, 1988, the bid results were posted by the Department. The bid results revealed that Petitioner, Mercedes Lighting and Electrical Supply, Inc. (Mercedes), was the lowest bidder and that Intervenor, Marpan Supply Company, Inc. (Marpan), was the second lowest bidder. The bid results further revealed that the bid of Mercedes had been rejected because it did not include a list of in-state service representative(s) as required by the ITB, and that the Department proposed to award the contract to Marpan. On April 12, 1988, Mercedes timely filed its notice of protest with the Department. Along with its notice of protest, Mercedes submitted a list of its in-state service representatives, and noted on its letter of transmittal that this list was "not included at time of bid." The bid documents Pertinent to this case, the ITB contained the following special condition: Service Availability of in-state representation to assist in proper application and to resolve technical problems is a requirement of this bid and the resulting contract. Bidders must, therefore, include as part of the bid a list of in-state service representative(s) who will be responsible for providing these services during the term of the proposed contract. Failure to comply with this requirement will result in disqualification of bid. . . . The coordination effort will be handled by the specific individual designated on the ordering instruction sheet. The ITB also contained the following general condition: 7. INTERPRETATIONS/DISPUTES: Any questions concerning conditions and specifications shall be directed in writing to this office for receipt no later than ten (10) days prior to the bid opening. No interpretation shall be considered binding unless provided in writing by the State of Florida in response to requests in full compliance with this provision. Any actual or prospective bidder who disputes the reasonableness, necessity or competitiveness of the terms and conditions of the Invitation to Bid, bid selection or contract award recommendation, shall file such protest in form of a petition in compliance with Rule 13A 1.006, Florida Administrative Code. Failure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under Chapter 120 Florida Statutes. Mercedes did not protest the bid specifications or conditions within 72 hours after receipt of the ITB, nor did it seek any interpretation of the conditions specifications. Notably, the only protest filed by Mercedes was after the bid opening. The bid protest At hearing, Mercedes contended that its bid complied with the ITB because it included a list of Mercedes' in-state service representative(s) or, alternatively, that its failure to include a list of its in-state representative(s) was a minor irregularity that the Department should waive. 1/ Mercedes contends that its bid included a list of in-state service representatives, and therefore was responsive to the ITB, because of its response to page 11 of the bid package entitled "Ordering Instructions", and because there appeared on the back of the manufacturer's catalogs and price list, submitted with its bid, a Florida sales office for the manufacturer at which sales and technical information could be obtained. Mercedes' contention and the proof offered to support it are not credible. The form included at page 11 of the ITB provided, and was responded to by Mercedes, as follows: ORDERING INSTRUCTIONS NOTE: ALL ORDERS SHOULD BE DIRECTED TO: FEDERAL EMPLOYER IDENTIFICATION NUMBER (FEID) : 59-1891811 VENDOR: Mercedes Lighting and Electrical Supply, Inc. STREET ADDRESS OR P.O. BOX: 7354 SW 48th St. CITY, STATE, ZIP: Miami, Florida 33155 TELEPHONE: (305) 665-5550 TOLL FREE NO: DELIVERY: DELIVERY WILL BE MADE WITHIN SEE PAGE 4 DAYS AFTER RECEIPT OF PURCHASE ORDER. DELIVERIES IN EXCESS OF SEE PAGE 4 DAYS WILL NOT BE CONSIDERED. TEAMS FOR PROMPT PAYMENT; NET percent 30 DAYS PRODUCT INFORMATION; DIRECT INQUIRY TO: (NAME, ADDRESS, AND TELEPHONE NUMBER OR INDIVIDUAL IN YOUR ORGANIZATION WHO MAY BE CONTACTED REGARDING CONTRACT WHICH MAY RESULT FROM THIS BID.) NAME AND TITLE: Victor J. LaPorta, Vice President ADDRESS: 7354 SW 48th St. CITY, STATE, ZIP: Miami, FL. 33155 TELEPHONE: (305) 665-5550 TOLL FREE NO.: Mercedes did not indicate in its response to the "Ordering Instructions" form that Mr. LaPorta was its in-state service representative, and its response could not reasonably be so construed. The individual a bidder designated on this form was, pursuant to the special condition of the ITB regarding "Service", the coordinator between a purchaser and the in-state service representative. Mercedes' contention that its bid included a list of its in-state service representatives, because the manufacturer's technical catalogs and price list submitted with its bid contained the location and phone number of the manufacturer's sales office in Florida, in addition to 23 other states, is incredible. The manufacture's technical literature and price list was, pursuant to the special conditions of the ITB, a required part of the bid. While the manufacturer may have listed its sales offices on the back of its literature, there is nothing in Mercedes' bid that remotely suggests it intended that listing to be considered its list of in-state service representatives, nor could its response reasonably be so construed. In rejecting Mercedes' contention that its bid was responsive to the ITB, and rejecting its proof as inherently improbable and unworthy of belief, I note that the Department has issued similar ITB's for a number of years. But for the language in this ITB advising bidders that failure to include a list of in-state service representatives would result in disqualification of the bid, the service provision has remained essentially the same, as has the "Ordering Instructions" form and the requirement that the manufacturer's technical literature and price list be included in the bid. When this same contract was let two years ago, Mercedes was a bidder. Included within its response to that ITB was a list of its in-state service representatives. A minor irregularity? While Mercedes did not protest the terms and conditions of the bid within 72 hours of receipt of the ITB, it offered proof at hearing which tended to demonstrate that the demand for technical assistance under the state contract was not frequent. Based on this premise, Mercedes contended that its failure to include a list of in-state service representatives with its bid was a minor irregularity that should be waived by the Department. Again, Mercedes' contentions are not persuasive. Whether the demand for technical assistance is frequent or infrequent may be germane to a timely challenge to the propriety of the ITB requirement that a list of in-state service representative included in the bid. However, where, as here, the bidder did not protest such condition in a timely manner, it has waived its right to a Chapter 120 proceeding to contest its propriety. Under such circumstances, the protest is limited to whether the failure to include such a list was a minor irregularity, and the frequency of demand for technical assistance is not relevant. 2/ Minor irregularity is defined by Rule 13A-1.002(10), Florida Administrative Code, as: ...a variation from the invitation to bid... which does not affect the price of the bid..., or give the bidder... an advantage or benefit not enjoyed by other bidders..., or does not adversely impact the interests of the agency. Variations which are not minor can not be waived. The ITB mandated that failure to include a list of in-state service representatives with the bid would result in the bid's disqualification. Under such circumstances, Mercedes cannot be permitted to correct the deficiency after bid opening, and the deficiency cannot be deemed minor, because it would accord Mercedes an advantage not enjoyed by other bidders. Succinctly, Mercedes could revisit its bid on bid opening, refuse to supply the required list, and thereby effectively disqualify itself and withdraw its bid. The other bidders who timely submitted their lists would not have an opportunity to revisit their bids or withdraw their bids, but would be held to the provision of the ITB that prohibited such withdrawal for 90 days after bid opening. A frivolous protest Mercedes' protest was frivolous. It presented no justifiable question for resolution, and was without basis In fact or in law. Mercedes knew when it submitted its bid that a list of in-state service representatives was required. It simply forgot to include that list. When this oversight was disclosed at bid opening, it tried to supplement its bid. This effort, for the reasons set forth in the conclusions of law, was ineffective. Now, Mercedes would have the hearing officer believe that it intended its response to the "Ordering Instructions" form, as well as the manufacturer's technical literature and price list included in the bid, as its list of in-state service representatives. Such proof is not credible, such was not Mercedes' intent, and its response cannot reasonably be so construed. Mercedes' contention that its failure to include such list should be waived as a minor irregularity is likewise factually and legally without merit. See Saxon Business Products, Inc. v. Department of General Services, 4 FALR 1102-A (1982), wherein this issue was previously resolved adverse to the position advocated by Mercedes. The impact of the protest The current term contract for lamps expires June 9, 1988. Upon expiration of that contract, state agencies will not be accorded the savings generated by a term contract and will be required to competitively bid any lamp purchase over $3,000. Had Mercedes not protested the Marpan award, state agencies would have enjoyed continued savings under a term contract that would have provided them prices 50 percent lower than could be obtained through individual agency bids.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered dismissing the formal protest filed by Mercedes Lighting and Electrical Supply, Inc. DONE AND ENTERED In Tallahassee, Leon County, Florida, this 3rd day of June, 1988. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1050 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of June, 1988.
The Issue This cause has been resolved upon Intervenor's Motion to Dismiss for Petitioner's failure to timely file the formal written protest required by Section 120.53(5) F.S. [1990 Supp.] to protest award of Respondent Alachua County School Board's BID 341 "Bid Proposal For Furnishing Monitoring Security Systems" to Intervenor.
Findings Of Fact Request for Bid 341 "Bid Proposal For Furnishing Monitoring Security Systems" dated June 14, 1991 was issued by Respondent Alachua County School Board and received by Petitioner/protestant Universal Network, Inc. on or about that date. The bid-closing date was 1:30 p.m. July 2, 1991. No one challenged or protested the specifications prior to the bid submittal date. Universal Network, Inc. and Crime Prevention Security Systems were the only bidders who timely filed bids on or before June 2, 1991. The request for bid accompanied by bid specifications had notified all potential bidders that School Board personnel also intended to open the bids on July 2, 1991, and stated that "Bid tabulations with recommended awards will be posted . . . on or about the Monday following bid opening, . . ." The request for bid also provided "Failure to file a protest within the time prescribed in Section 120.53(5) Florida Statutes, shall constitute a waiver of proceedings under Chapter 120, Florida Statutes." (HO Exhibit 6) The bids were opened July 2, 1991, and oral communications were made by Respondent's personnel to the effect that Crime Prevention Security Systems would probably be successful since it was low bidder. However, Respondent's personnel delayed posting a formal intent to award on Monday, July 8, 1991 because Petitioner orally announced itself aggrieved by the process. Eight days after the bid opening, on July 10, 1991, Respondent's personnel met with both bidders in an effort to resolve any issue that could result in a formal protest. This meeting was tape recorded by the Petitioner. After this meeting, Petitioner filed a letter dated July 11, 1991 stating that Petitioner "learned" through "verbal notification" as of the July 10 meeting that it would not be awarded the bid, outlining its own prior contract work for the Respondent School Board, attacking the bid specifications, and notifying the Respondent that Petitioner would cease to monitor security under the existing contract at midnight on July 31, 1991. At hearing, Petitioner acknowledged that it did not rely on this July 11, 1991 letter (HO Exhibit 1) as its notice of protest. Nothing was formally decided until, on July 16, 1991, Respondent, through its employee, David C. Hotary, formally posted its intent to award Bid 341 to Crime Prevention Security Systems. On that date, Respondent also wrote and hand-delivered a formal letter-notice of intent to Petitioner's president. That letter provided, in pertinent part: As follow-up to our meeting of July 10, and your letter of July 11, this is to advise that posting of the recommended bid award to crime prevention security systems occurred as of this date and will remain posted for a three day period. Failure to file a protest within the time prescribed in s. 120.53(5), Florida Statutes, shall constitute a waiver of proceedings under chapter 120, Florida Statutes. (Emphasis supplied) (HO Exhibit 2) There is no dispute that Petitioner actually received this written notice of decision or intended decision on July 16, 1991. This procedure complied with Respondent's obligations to provide notice of the award and a window for Petitioner's bid protest under the provisions of Section 120.53(5)(a). F.S. [1990 Supp.] and Respondent's rule (HO Exhibit 5). On July 17, 1991, the Petitioner's president filed with the Respondent a letter bearing that date which provided, in pertinent part, This letter is to inform you that Universal Network, Inc. is now formally protesting BID 341 "Bid Proposal For Furnishing Monitoring Security Systems." We base our protest on unpublished bid variances. (HO Exhibit 3) There is no dispute that this letter was filed with the Respondent within 72 hours "after the posting of the bid tabulation or after receipt of the notice of agency decision or intended decision." It clearly constituted the "notice of protest" contemplated by Section 120.53(5)(b) F.S. [1990 Supp.] and is timely under that statute. Under that statute and pursuant to Respondent's rule, the 10 days for filing the required formal written protest would have run out on July 29, 1991, a Monday, allowing for Saturday and Sunday. On July 24, 1991, five days before the formal written protest was due, Respondent's personnel telephoned the Petitioner's president and a conversation ensued. Upon the representations at formal hearing of Petitioner's president Daniel Boudreau, it is found that this conversation encouraged him to file another letter to the Respondent on July 31, 1991. (HO Exhibit 4) Petitioner's president asserted that Respondent's July 24, 1991 phone call was only to urge him to file a letter setting out his grounds for protest more fully so that the issues between Petitioner and Respondent could be resolved informally. Filing a letter which sets out the grounds for a notice of protest is a fair description of what a formal written protest is supposed to do, and it was Respondent's position that the phone call was to urge Petitioner to file its formal written protest. Whether or not the filing of this July 31, 1991 letter could constitute a means of informal resolution of the bid dispute as asserted by Petitioner is a legal issue and is discussed in the Conclusions of Law, infra, but it is undisputed that Respondent's telephone call of July 24, 1991 actually encouraged Mr. Boudreau to file a more detailed letter and did nothing to discourage filing a formal written protest, which formal written protest is mandatory under the applicable statute and rule. Nonetheless, Petitioner filed nothing whatsoever in writing with the Respondent between July 17, 1991 (the date of the notice of protest) and July 31, 1991. On July 31, 1991, Petitioner filed with the Respondent its letter which provided, in pertinent part: This letter is to inform you that Universal Network, Inc. has formally protested BID 341 "Bid Proposal for Furnishing Monitoring Security Systems." We base our protest on unpublished bid variances. Universal Network, Inc. is now asking for a formal hearing and also will be willing to submit a new bid with the SBAC corrected bid specification. Petitioner's July 31, 1991 letter goes on to compare how Petitioner's bid would be altered as of July 31, 1991 if the original bid specifications had specified or clarified certain items or terms and to show that Petitioner's July 2, 1991 bid price would have been lower if that had been the case. (HO Exhibit 4) Petitioner's July 31, 1991 letter clearly constituted Petitioner's "formal written protest" as contemplated by Section 120.53(5)(b) F.S. [1990 Supp.] and the rule and is untimely under that statute and rule.
Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the School Board of Alachua County enter a Final Order dismissing the protest/petition of Universal Network, Inc. RECOMMENDED this 19th day of September, 1991, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1991. COPIES FURNISHED: Dale A. Boudreau, President Universal Network, Inc. 1031 NW 6 Street, Suite A-3 Gainesville, FL 32601 Thomas L. Wittmer, Staff Attorney School Board of Alachua County 620 E. University Avenue Gainesville, FL 32601 Robert E. Roundtree, Jr., Esquire 111 SE 1st Avenue Gainesville, FL 32602 Dr. Douglas Magann, Superintendent Alachua County School Board 620 East University Avenue Gainesville, FL 32601
The Issue Whether the Department of Transportation’s decision to reject all bids for Financial Project No. 209278-1-52-01 (J. Turner Butler Blvd.) a major interchange in Duval County, Florida, was exercised illegally, arbitrarily, dishonestly or fraudulently.
Findings Of Fact On April 1, 2004, the Department of Transportation advertised its Bid Solicitation Notice (BSN), for the JTB Project. H. W. Lochner, Inc. (Lochner) designed the JTB Project. Petitioner, Superior Construction, and Archer Western Contractors, LTD, submitted bids on May 26, 2004. Petitioner had the apparent low bid, and Superior had the second apparent low bid. On or about May 27, 2004, Robert Burleson, President of the Florida Transportation Builders Association (“FTBA”), contacted the State Construction Engineer, Ananth Prasad, P.E., and alerted him to potential issues regarding MOT phasing. (T. p. 876, lines 18-24; p. 880, lines 14, 15). Richard Ayers, of Superior Construction, called the Jacksonville Urban Office of the Department of Transportation, District 2, alerting the District to the concerns regarding the maintenance of traffic issues. Ayers had reviewed the bid and plans generally to assess its bid in light of the Petitioner's bid, and had discovered in the process MOT issues that he believed would add substantially to the costs and time required to construct the project. As a result of these calls, Robert Hansgen, P.E., District 2 Resident Engineer, was directed by someone within the Department to review the MOT plans. On June 1, 2004, Mr. Hansgen forwarded to Henry Haggerty and Al Moyle a memorandum outlining seven areas of MOT concern relating to the "constructability" and safety of the JTB project. On June 1, 2004, Hansgen's memorandum was forwarded to Mohammed Majboor, P.E., Design Consultant Engineer for the Department, who forwarded the memo to Lochner. Lochner reviewed its plans in light of the Hansgen memorandum and forwarded its response on June 3, 2004, to Hansgen, who reviewed the responses and added his comments. He e-mailed Henry Haggarty seven concerns he had with the MOT plans. On June 2, 2004, Allen Moyle, Jacksonville Construction Engineer, received Hansgen's and Lochner's responses regarding the MOT plans and determined that the project plans needed revisions because of safety issues. Moyle concluded that all the bids needed to be rejected in light of the MOT revisions. He transmitted a request to Cathy Thomas at the Department's headquarters to arrange a meeting with Lochner to commence revision of the plans at the earliest possible date. On June 8, 2004, Hansgen briefed the District 2 Secretary, Schroeder, and other District 2 staff members on the issues regarding maintenance of traffic issues based on his memo, a marked-up copy of the MOT sheets, and pictures. Rejection of all bids was discussed at this meeting. Mr. Hansgen testified at the formal hearing concerning his findings and his actions with the aid of the original memorandum and Respondent's Exhibits 1 and 2. Mr. Hansgen's concerns were about safety issues and included the reduction of traffic lane widths in areas to 11 feet where barrier walls would be erected on both the inside and outside medians where traffic would be traveling at 55 miles per hour. Another concern was the length of these lanes that would be restricted by concrete barriers. These barriers prevented easy access of emergency vehicles in these areas, which presented a significant hazard at this interchange, which accesses a major hospital complex. Mr. Hansgen’s also identified an inconsistency regarding where the contractor could work in an area close to the barrier wall; a portion of the roadway where a cross slope or tilting of the traveling lane created dangerous vehicle control issues; and plans to widen a portion of the roadway while vehicles traveled on the same portion of roadway which would require further narrowing of lanes. Because the State of Florida has one of the highest fatality records in the nation in work zones, the Department is very concerned about this issue. After the meeting on June 2, 2004, the Jacksonville Urban Office for District 2 recommended rejection to DOT in Tallahassee of all bids based on the need to “clarify uncertainties within the phasing of the maintenance of traffic (MOT) plans.” The recommendation of District 2 was reviewed by the Technical Review Committee, which is comprised of six voting members. On June 9, 2004, the Technical Review Committee recommended rejection of all bids on the JTB Project to the Contract Awards Committee based upon MOT safety issues. The Contracts Award Committee, composed of three voting members, met on June 15, 2004, to consider the recommendations regarding the JTB Project of the Technical Review Committee and District 2. The Contracts Award Committee concurred with the recommendations of the Technical Review Committee and District 2 and rejected all bids based upon MOT safety issues. The Department posted its notice of intent to reject all bids on June 17, 2004. The Petitioner filed a Notice of Intent to Protest the Department’s rejection of all bids with a Formal Written Protest, filed on July 1, 2004, including an appropriate protest bond. The Department’s engineers met with engineers from H.W. Lochner, Inc., to discuss the issues of concern raised in the Hansgen memorandum. The Department commissioned Lochner to revise the plans to enhance the safety features for MOT, and certain other enhancements. Lochner and the Department entered into Supplement Agreement #13 that included both the requested enhancements and the changes to accommodate the concerns referenced in the Hansgen Memorandum. Richard Kelly testified regarding “animus,” and “dislike” displayed by employees of the Department. He pointed to past decisions and actions of Department employees as proof of “dislike” and “animus." These included a Letter of Concern to the Petitioner, on April 16, 2004, from the Department outlining five areas the Department had identified as important in making a determination on the pre-qualification of the Petitioner for bidding on Department contracts for the 2004-2005 fiscal year. Also mentioned were disputed issues between the Department and the Petitioner arising during construction of the I-95/I295 Interchange Project, including Jacksonville ordinances on noise ordinance, and trees and deficiency letters from the Department to AMEC Civil. In addition, the disqualification of Morse Diesel, LLC, as the Petitioner was formerly named, from bidding on construction contracts with the State of Florida, and in 2002, the revocation of the pre-qualification of the Petitioner to bid on DOT projects were described. Ananth Prasad, P.E., who was identified by the Petitioner's witnesses as a primary source to opposition to the Petitioner, testified that he did not hold the position of State Construction Engineer in 2000, and was not involved in the decision to deny pre-qualification of Morse Diesel. Mr. Prasad also was not involved with the initial decision to revoke the pre-qualification of AMEC in 2002. Mr. Prasad does not personally hold a position on the Technical Review Committee. Mr. Prasad did not vote on the decision to recommend rejection of all bids on the JTB project. The decision to reject all bids for the JTB Project was made by the Contracts Award Committee based on recommendations from the Technical Review Committee, and District 2. The Department’s Contracts Award Committee exercised its statutory authority to reject all bids based on concerns regarding the MOT phasing.
Recommendation Based on the foregoing findings of fact and Conclusions of Law, it is Recommended that the Department of Transportation enter a final order dismissing Petitioner’s Formal Written Protest concerning the bid rejection for the project in this litigation. DONE AND ENTERED this 28th day of December, 2004, in Tallahassee, Leon County, Florida. S STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of December, 2004. COPIES FURNISHED: F. Alan Cummings, Esquire S. Elysha Luken, Esquire Smith, Currie & Hancock, LLP 1004 DeSoto Park Drive Post Office Box 589 Tallahassee, Florida 32302-0589 Mike Piscitelli, Esquire Vezina, Lawrence & Piscitelli, P.A. 305 East Las Olas Boulevard, Suite 1130 Fort Lauderdale, Florida 33301 Calvin C. Johnson, Esquire C. Denise Johnson, Esquire Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Station 58 Tallahassee, Florida 32399-0450 James C. Myers, Agency Clerk Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450
The Issue The issue presented is whether the Department should award the contract for State Project numbered DOH 95209100 to Petitioner.
Findings Of Fact State Project numbered DOH 95209100 commenced with an invitation to bid on a construction project which involved the restoration and adaptive use of the Gato Cigar Factory in Key West, Florida. The construction would rehabilitate that existing historic structure and construct internal office and clinic spaces for both Monroe County and the Department of Health. Since both agencies would use the building, the project was divided between them. Monroe County and the Department issued separate invitations to bid for their portions of the structure, and each will enter into its own contract with the winning bidder or bidders. It was not required that a bidder submit a bid for both the Monroe County and the Department portions of the work. Any bidder could bid on one or the other or both. Although the invitations to bid and the contracts to result therefrom were not interrelated, some of the construction work was interrelated as some of the systems being installed under one contract would directly affect the other contract. For example, both the air conditioning system and the roofing system, although being performed under one entity's contract, would be applicable to both projects. The Department's invitation to bid required bidders to submit a base price, plus specific prices on particular items. Alternate numbered 1 added to the base price the cost of a second air conditioning chiller. The base price plus alternate numbered 1, taken together, included all work to be performed under the Department's scope of work. Alternates numbered 2 through 5 were deductions from the work included in the base price. Alternates numbered 2 through 5 were included in the Department's invitation to bid to cover the possibility that all bids might come in over budget. In that event the Department could select Alternates numbered 2 through 5, sequentially, until sufficient items had been deducted from the Department's scope of work to result in bids under the amount budgeted by the Department for the project. Section 01030 of the bid specifications is entitled "Alternates." Section 1.2E of Part 1 provides, in part, as follows: Include as part of each Alternate, miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation whether or not mentioned as part of the Alternate. Each Alternate Bid must interface with the work being constructed under a separate contract with Monroe County. Each Alternate Bid item is also applicable to the Monroe County work. An alternate which is deducted from one project will be added to the other. If bidding both projects, the Deductive Alternate price for one project must match the Add Alternate price for the other project. The prospective bidders were also given this information in the pre-bid meetings. The Department received a number of bids for less than the amount budgeted for its portion of the work. Accordingly, the Department was able to select Alternate numbered l, which taken together with the base bid, covered the entire scope of work allocated to the Department. The lowest bids through Petitioner's bid were as follows: Bidder Total Bid D. L. Porter Construction, Inc. $1,418,744. McTeague Construction Co., Inc. $1,454,500. Lodge Construction, Inc. $1,501,500. Rovel Construction, Inc. $1,559,000. Neither McTeague Construction Co., Inc., nor Lodge Construction, Inc., participated in this proceeding to challenge the Department's intended bid award. For the lowest bidder, Intervenor Porter, discrepancies occurred in its first, third, and fifth alternative prices of $3,500, $375, and $l,497, respectively. For the second lowest bidder, McTeague, a discrepancy of $9,000 occurred in its first alternate price. For the third lowest bidder, Lodge, a discrepancy of $3,165 occurred in its fifth alternate price. For the fourth lowest bidder, Petitioner Rovel, there were no discrepancies in any of its alternate prices. Porter's bid on Alternate numbered 1 for the Department was $38,500. Porter's bid on Alternate numbered 1 for Monroe County was $35,000. Porter's estimating staff overlooked the instruction that the two numbers should match. The reason for the difference between the two Alternate numbered 1 amounts is that the bidders were instructed to prepare the two bids as two separate contracts. Alternate numbered 1 required moving one of two chillers from the Monroe County project to the Department's project. Porter could not assume that it could use the crane from the contractor on Monroe County's portion of the project to install this chiller in the Department's portion of the project. Therefore, the cost of a crane had to be added to the Department's project, but the cost of the crane could not be deducted on the Monroe County bid. Porter was the fourth highest bidder on the Monroe County project. Monroe County has not yet awarded its contract. If the Monroe County project is awarded based upon the bids submitted, Porter will not be awarded the Monroe County project. The Department's bid tabulation and notice of intended award were prepared without any reference to the bid opening for the Monroe County project and before the contents of the Monroe County bids were known by the Department. The deviation in price between Porter's Alternate numbered 1 bids did not give Porter an advantage over the other bidders, several of whom made the same error. It was a minor deviation, not a material one. The price submitted on the Department's bid reflected the actual cost of performing that portion of the work. Petitioner's bid listed Florida Keys Electric, Inc., as its electrical subcontractor, its fire alarm subcontractor, and its lightening protection subcontractor. That company is not certified by the State of Florida, but it is registered. The bid specifications provide in section B-14, in part, as follows: Any bidder who lists a subcontractor not certified and/or registered by the State to perform the work of his trade if, such certification or registration is required for the trade by Florida Laws, will be rejected as non-responsive. No change shall be made in the list of subcontractors, before or after the award of a contract, unless agreed to in writing by the Owner. Section 16010, Part 1, section 1.9, subsection A., of the technical specifications which form a part of the bid specifications involves supervision of the construction and provides, in part, that "At least one member of the Electrical Contracting Firm shall hold a State Master Certificate of Competency." Florida Keys Electric, Inc., would use Delor J. Ellis as its qualifying agent. Although Ellis is certified by the State, at the time of the bid submittal and through the date of the final hearing in this cause, Ellis' license was in an inactive status, and no application to activate his license was pending with the State of Florida. Fire alarm work and lightening protection work require a specialty license in the State of Florida. Florida Keys Electric, Inc., is not licensed to perform either type of work. When Florida Keys Electric, Inc., contracts to perform such work, it does so through its own subcontractor. Although the requirement for certification and/or registration contained in the bid specifications is not consistent with the requirement for State certification contained in the technical specifications portion of the bid specifications, Petitioner did not comply with either provision. Accordingly, Petitioner's bid is not responsive to the bid specifications. Porter, which submitted the lowest bid, is responsive to the bid specifications and is, therefore, the lowest responsive bidder.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Petitioner's bid to be non-responsive, dismissing Petitioner's bid protest, and awarding to D. L. Porter Construction, Inc., the contract for the restoration of the Gato Cigar Factory. DONE AND ENTERED this 27th day of April, 1999, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1999. COPIES FURNISHED: Angela T. Hall, Agency Clerk Department of Health 2020 Capital Circle, Southeast BIN A02 Tallahassee, Florida 32399-1703 Pete Peterson, General Counsel Department of Health 2020 Capital Circle, Southeast BIN A02 Tallahassee, Florida 32399-1703 Robert A. Hingston, Esquire Welbaum, Guernsey, Hingston, Greenleaf & Gregory, L.L.P. 901 Ponce de Leon Boulevard, Penthouse Suite Coral Gables, Florida 33134 Michael E. Cover, Esquire Morton R. Laitner, Esquire Department of Health Miami-Dade County Health Department 1350 Northwest 14th Street Miami, Florida 33125 William G. Christopher, Esquire Brown Clark, A Professional Association 1819 Main Street, Suite 1100 Sarasota, Florida 34236
The Issue The issues in this bid protest are whether Intervenor's bid was nonresponsive because Intervenor, a corporation formed in 2005, lacks the required five years' experience in the tree trimming business; and, if so, whether Respondent's preliminary decision to award Intervenor the contract at issue was clearly erroneous, arbitrary or capricious, or contrary to competition.
Findings Of Fact Pursuant to Invitation to Bid No. 27-054X (the "ITB"), which was issued on August 10, 2006, Respondent Broward County School Board ("School Board") solicited bids for "Tree Trimming, Planting, Hurricane Cleanup, and Removal Service." Interested vendors were instructed to bid prices on numerous items of service. The items were sorted into two groups, Group A and Group B. The School Board intended to designate a "primary vendor" for each group, who in the ordinary course of events would receive the largest volume of work, but it reserved the right to procure services from the second and third lowest bidders in each group should it become necessary or desirable to do so. Bids were due on September 13, 2006. Section 4 of the ITB contained "Special Conditions" applicable to this procurement. Of interest in this case is Special Condition No. 11, which specified the qualifications a vendor needed to be considered for an award: BIDDER'S QUALIFICATIONS: Bidder must have at least five years experience in tree trimming services within the Miami-Dade, Broward and Palm Beach tri-county area. Bidder must submit, with the bid or uponrequest, the attached Bidder's Profile form. This report must include a minimum of three references from commercial jobs. Each reference should include the address of the actual job, work accomplished and a phone number and contact person. (Emphasis in original.) The Bidder Profile form to which Special Condition 11 referred was located in Section 7 of the ITB as Attachment 1. At the top of the Bidder Profile appeared the following direction and warning: THIS INFORMATION MUST BE SUBMITTED WITH THE BID. FAILURE TO COMPLETE THIS SECTION WILLDISQUALIFY THE SUBMITTED BID. (Emphasis in original.) Paragraph 12 of the Bidder Profile form stated as follows: References Required. Contractor to provide a list of three references. Three references from jobs completed in each of the past three years. More than one dozen vendors timely submitted bids, which the School Board opened on September 13, 2006. Among the bidders were Petitioner Phil's Expert Tree Service, Inc. ("Expert") and Intervenor Innovative Environmental Services, Inc. ("Innovative"). After tabulating the bids, the School Board determined that Innovative was the lowest and best bid from a responsive, responsible bidder with regard to Group A, followed by Expert and All County Tree & Landscape Co., Inc. ("All County"), in that order. Thus, when the award recommendations were posted on September 27, 2006, Innovative was named the intended primary awardee for Group A, Expert the first alternate, and All County the second alternate.1 Innovative is a family business whose principals are Craig and Deborah Conway, husband and wife. In the year 2000, the Conways moved to South Florida from Pennsylvania, where, for more than 20 years, they had operated a tree trimming and land clearing business. After arriving in Florida, the Conways entered into a business arrangement with Donald Richter, a certified arborist, whereby they jointly provided tree trimming services under the name "ASAP Tree Service" or "Don Richter's ASAP Tree Service." In October 2002, the Conways formed a corporation called Independent Equipment South, Inc. ("Independent"). Independent operated an equipment sales and rental business whose inventory consisted of equipment that was not being used in the family's tree trimming operations. Eventually, the Conways' tree trimming service become part of Independent's business portfolio as well. In February 2005, Innovative was incorporated. At all times relevant to this procurement, Mrs. Conway has been the sole corporate officer, Mr. Conway the company's Director of Operations. In addition, at all relevant times, Innovative has employed or otherwise retained Mr. Richter as its certified arborist. Although Innovative and Independent are separate corporate entities, the two businesses operate out of the same location, have the same employees, and use the same equipment. The Conways commonly refer to their businesses as "IES," using that acronym interchangeably to mean either Innovative or Independent (or both). Innovative's Bidder Profile, which was submitted together with its bid, referred to——and incorporated——an attachment entitled, "Brief Company History." The Brief Company History provided background information on Innovative's provenance, albeit from a layperson's perspective. Written by nonlawyers, the summary was not always technically precise, from a legal standpoint, in its descriptions of the various business associations in which the Conways have been involved. Seizing on the least artful phrases, Expert contends that some of the statements in the Brief Company History were false and perhaps even fraudulent. The undersigned, however, finds otherwise. To the point, the Brief Company History reflects an honest attempt truthfully to describe the Conways' family businesses, which is reasonably accurate when read and understood from the perspective of the small-business owners who prepared it. That said, the undersigned finds and determines that Innovative——as distinct from its principals and/or personnel—— did not have five years' experience in the tree trimming business when it bid on the contract at hand, notwithstanding the wealth of tree trimming experience at its disposal. Indeed, having been in existence for fewer than two years at the time it submitted its bid, Innovative, as a separate legal entity, could not possibly have garnered, in its own right, five years' experience doing anything. For the same reason, though Innovative provided plenty of references, the ones that stemmed from jobs completed before February 2005 necessarily related to providers other than Innovative, such as ASAP Tree Service, who actually existed then. To be sure, the providers who earned the references from earlier jobs upon which Innovative relied either were predecessor business associations or individuals who would become personnel of Innovative——but they were not Innovative. Innovative simply could not have performed or completed any jobs before its creation. It is determined, therefore, as a matter of ultimate fact, that Innovative's bid did not strictly conform to the plain language of Special Condition No. 11. Like Innovative, Expert is a family-owned business. Founded in 1985 by Philip Simeone, Expert was incorporated in 1992. Though Expert clearly possesses the length of experience for which Special Condition No. 11 called, Expert failed in its Bidder Profile to provide three references "from jobs completed in each of the past three years," as instructed in paragraph 12 of the ITB's Section 7, Attachment 1. Instead, Expert gave two references from jobs completed in 2006 plus another from a job completed in 2004. Expert's bid did not contain a reference from a job completed in 2005. Expert contends that the School Board should have rejected Innovative's bid as materially nonresponsive (for lacking the requisite five years' experience) and awarded the contract to Expert as the lowest responsive bidder. The School Board and Innovative take the position that the School Board's decision to treat Innovative's bid as responsive was not clearly erroneous, arbitrary, or capricious. Turning the tables, the School Board and Innovative argue that Expert's own bid deviated from Special Condition No. 11, in that Expert failed to provide a reference from a job completed in 2005.2 Yet both assert that "it was reasonable for [the School Board] to waive the requirement of the Bidder Profile form that one . . . reference[] be [from] a job completed in the year 2005." Somewhat inconsistently, however, Innovative argues further that Expert's "bid proposal cannot be sustained"——evidently due to its material nonresponsiveness. This apparent inconsistency follows from Innovative's attempt to play down its alternative position, which is that if "a contrary conclusion [had] been reached as to [Innovative's] experience"—— meaning that if the School Board had chosen not to waive any irregularity concerning Innovative's length of corporate experience——then the "same analysis would apply to" Expert—— meaning that Expert's bid too should have been disqualified. Thus, even though Innovative maintains that the School Board reasonably waived any irregularities in Expert's bid, Innovative is unwilling to concede that the School Board did not err in determining that Expert's bid was responsive, evidently out of concern that such an admission might compromise its fallback position. Innovative's bottom line is that if Innovative's bid were to be disqualified as materially nonresponsive, then Expert's bid would need to be rejected, too.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board enter a Final Order that (a) declares Innovative's bid to be materially nonresponsive and, accordingly, rescinds the proposed award to Innovative; and (b) declares Expert's bid to be materially nonresponsive and, accordingly, rejects the same. Because the choice of remedies for invalid procurement actions is ultimately within the agency's discretion, the undersigned declines to make a recommendation as to whether the School Board should award the contract to All County (which was the putative "second alternate") or reject all bids and start over. DONE AND ENTERED this 19th day of March, 2007, in Tallahassee, Leon County, Florida. S JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of March, 2007.
The Issue Whether the Department’s intended award of contract E2K97 for Asset Maintenance of the Duval County Roadways is contrary to the agency’s governing statutes, the agency rules or policies or the bid or proposal specifications.
Findings Of Fact The following facts were agreed between the parties in their Joint Pre-Hearing statement: On June 18, 2007, FDOT posted the solicitation for asset maintenance of the Duval County Roadways through procurement E-2K97. The RFP requested technical proposals and bids for a five-year contract for maintenance of identified roads in Duval County. The RFP provides that the scoring of the technical proposals is to be weighted as follows: Administration Plan (20%), Management and Technical Plan (30%), Operation Plan (30%), and Plan for Compliance with Standards (20%). ESI did not file a protest of the RFP's terms, conditions, specifications, or provisions governing the method of ranking proposals within 72 hours of the posting of the solicitation. A mandatory pre-bid meeting was held on July 10, 2007. The technical and price proposals for this project were due by August 9, 2007. Four firms submitted timely proposals in response to the RFP. They were ESI, DBI, Infrastructure Corporation of America (ICA) and VMS. The proposals were evaluated by three registered civil engineers who are employed by FDOT: Jerry Ausher, Julius Rinosa, and Mark Kuhn. All four firms were determined to be responsive and received scores on their technical proposal and price proposal. DBI's average score on its technical proposal was 88, the highest of the four firms. ESI's average score on its technical proposal was 75.33, the lowest of the four firms. ESI's price proposal bid was $44,759,500.00, the lowest of the four firms. DBI's price proposal bid was $48,748,886.00, the second lowest of the four firms. After combining the technical scores and price proposal scores, the total proposal scores for the four firms were as follows: DBI = 89.14, VMS = 85.19, ESI = 82.73, and ICA = 82.68. On September 4, 2007, FDOT posted its notice of intended award to DBI as the winning bidder. ESI filed a notice of intent to protest on September 7, 2007, followed by a formal written protest on September 17, 2007. DBI filed a Petition to Intervene which was granted on November 7, 2007. As the intended awardee, DBI has a substantial interest in the outcome of this proceeding and thus, has standing to intervene.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that Petitioner’s Amended Formal Written Bid Protest be dismissed. DONE AND ENTERED this 31st day of March, 2008, in Tallahassee, Leon County, Florida. S DON W. DAVIS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of March, 2008. COPIES FURNISHED: Cynthia S. Tunnicliff, Esquire Brian A. Newman, Esquire Pennington, Moore, Wilkinson, Bell & Dunbar 215 South Monroe Street, Second Floor Tallahassee, Florida 32301 Denise Johnson, Esquire Assistant General Counsel Florida Department of Transportation Office of the General Counsel Haydon Burns Building 605 Suwannee Street, Mail Stop 58 Tallahassee, Florida 32399-0458 Brant Hargrove, Esquire 2104 Delta Way, Suite 9 Tallahassee, Florida 32303 J. Reuben Hamlin, Esquire Post Office Box 1620 Newberry, Florida 32669 Stephanie Kopelousos, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Building, Mail Stop 57 Tallahassee, Florida 32399-0450 Alexis M. Yarbrough, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street Building, Mail Stop 58 Tallahassee, Florida 32399-0450 James C. Meyers Clerk of Agency Proceedings Department of Transportation Haydon Burns Building 605 Suwannee Street Building, Mail Stop 58 Tallahassee, Florida 32399-0450
The Issue Whether the Petitioner was the lowest responsive bidder in Bid No. 88-8-1, and therefore entitled to the contract award. Whether the special conditions set forth in the bid documents were timely objected to by the Petitioner, and so ambiguous as to warrant a rejection of all bids in Bid No. 88-8-1.
Findings Of Fact The Department sent invitations to bid in Bid No. 88-4-2 to various providers of telephone answering services within the Brevard County area. The purpose of the invitations was to obtain the lowest responsive bid for an after- hours telephone answering service for a one year period at the Department's Monroe Center in Cocoa Beach, Florida. When the results of the bidding were made known at the public bid opening, Answerphone's bid was recommended for the award as the low bidder. On June 16, 1988, the bidders were notified by mail that the bid would not be awarded as recommended at the public bid opening. The bidders were told that the bids were being reevaluated, and they would be notified later as to when the award would occur. On June 24,1988, the bidders in Bid No. 88-4-2 were notified that the Department rejected all bids because of the belated discovery of inherent ambiguities in the solicitation which made it impossible for the Department to determine the lowest and best bid. The Department did not receive any notices of protest based upon its decision to reject all bids, and the decision became final seventy-two hours after the bidders were notified of the rejection. New bid specifications were created, and the Department sent invitations to bid to Bid No. 88-8-1 to the same list of providers who had received invitations in Bid No. 88-4-2. In paragraph 2 of the new invitation to bid, prospective bidders were notified that questions concerning specifications should be directed in writing to 705 Avocado Avenue, Cocoa, Florida. The invitation cautioned that no interpretation of the specifications should be binding on the Department unless provided in writing. Paragraph 4 of the special bid conditions attached to the invitation allowed the bidders to orally present questions about the bid requirements at the pre-bid conference held on August 30, 1988. Paragraph 6 of the special bid conditions required prospective bidders to file a notice of protest within seventy-two hours after receipt of the bid solicitations if there were concerns about the reasonableness, necessity, or competitiveness of the terms and conditions of the invitation to bid. The Petitioner was represented at the conference and the Department was asked to explain what was meant by the specification which required that the system have the capability of receiving and patching or paging multiple calls at one time if necessary. The Petitioner's representative was told that the system must be able to handle multiple calls at one time without losing a call. The provider should have an adequate system of holding, handling, and routing these calls as specified in items one through four of the list of services required in the bid documents. The Answerphone representative indicated to the Department that all of his questions had been satisfactorily answered before the pre-bid conference was brought to a close. No requests were made to the Department to place its explanation in writing and no written interpretation was provided. A notice of protest by Answerphone about the specifications in the bid solicitation was not filed with the Department prior to the Department's acceptance of bids in Bid No. 88-8-1. When the bids were opened on September 6, 1988, Elite Answer Service, Ltd., was the apparent responsive low bidder in Bid No. 88-8-1. Answerphone filed a protest to contest the award because Elite does not have the technological capacity to complete the contract under the specifications, as interpreted by Answerphone. During the administrative hearing, it was learned that the Department meant the following interpretation to be given to its specification which requires the service to handle multiple calls: During after hours, the Department has one telephone line and one telephone number linked to an answering service. When an incoming call to that number is received by the service, no other callers can dial that number and gain access to the service. The second caller will receive a busy signal. The service must have the capacity to take the call which has been received and call the necessary people at other telephone numbers who might need to speak with each other or the caller, together or separately. Therefore, the service must be able to place various people on hold at different times in the sequence, and patch the appropriate people together at the proper times when the service has been directed to do so. Answerphone interpreted the specifications to mean that the service should be able to handle more than one incoming call to the one local HRS telephone number and telephone line which is available to the public at night. For example, if three different calls were dialed to the local number, all three would be received by the service instead of two receiving a busy signal. The service would then proceed to dispatch the different callers to all of the different people as described above in paragraph 14 of the Findings of Fact. Answerphone has the technological capacity to accomplish this feat. Elite does not.. Answerphone's interpretation of the bid specifications was an untenable one in that it restricted competition instead of promoting it. This is contrary to the clear intent of the Department as set forth in the invitation to bid. The bid specifications were clear and unambiguous in that the Department's requirements from the after-hours answering service were to begin after the dialer's telephone call rang into the answering service. The Department's opportunity to handle more than one incoming call dialed during the time the one line at Monroe Center was already in use was never addressed in the specifications. The mistake in the interpretation of the bid specifications belonged to the petitioner. Paragraph 4(c) of the general conditions place the risk of mistake on the Petitioner. Opportunities to correct possible mistakes in interpretation by the prospective bidders were provided during the bid process. The Petitioner did not avail itself of these opportunities.