Division of Administrative Hearings, Florida
Filed: Sep. 30, 2016
The issues to be determined in these consolidated cases are whether All Aboard Florida – Operations, LLC (“the Applicant”), and Florida East Coast Railway, LLC (“FECR”), are entitled to an Environmental Resource Permit Modification authorizing the construction of a stormwater management system and related activities to serve railway facilities, and a verification of exemption for work to be done at 23 roadway crossings (collectively referred to as “the project”).Applicants demonstrated their entitlement to an Environmental Resource Permit Modification and a Verification of Exemption for a stormwater management system to serve express passenger train facilities.