Division of Administrative Hearings, Florida
Filed: Jan. 31, 2001
Whether Petitioners' Notice of Proposed Non-Substantial Change should be approved, thereby extending the commencement date and the first two phasing deadlines in their Development Order by four years and 364 days, and extending the termination date by eighteen months less two days.Property owners demonstrated excusable delay and no adverse impacts thereby justifying extension of time for complying with deadlines in development order.