Elawyers Elawyers
Washington| Change

LEE COUNTY vs MOSAIC FERTILIZER, LLC AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 08-003887 (2008)

Court: Division of Administrative Hearings, Florida Number: 08-003887 Visitors: 25
Petitioner: LEE COUNTY
Respondent: MOSAIC FERTILIZER, LLC AND DEPARTMENT OF ENVIRONMENTAL PROTECTION
Judges: D. R. ALEXANDER
Agency: Department of Environmental Protection
Locations: Tallahassee, Florida
Filed: Aug. 08, 2008
Status: Closed
Recommended Order on Thursday, December 18, 2008.

Latest Update: Feb. 03, 2009
Summary: The issues are whether Respondent, Mosaic Fertilizer, LLC (Mosaic), has provided reasonable assurances that the proposed mining and reclamation of the South Fort Meade Mine in Hardee County can be conducted in a manner that comports with the applicable statutes and rules such that the proposed Environmental Resource Permit (ERP), Conceptual Reclamation Plan (CRP), variance from minimum standards for dissolved oxygen, and variance from littoral zone percentage provisions for the Project should be
More
STATE OF FLORIDA

STATE OF FLORIDA

DIVISION OF ADMINISTRATIVE HEARINGS


LEE COUNTY, )

)

Petitioner, )

)

and )

)

SARASOTA COUNTY, )

)

Intervenor, )

)

vs. ) Case Nos. 08-3886

) 08-3887

MOSAIC FERTILIZER, LLC, and ) 08-3888

DEPARTMENT OF ENVIRONMENTAL ) 08-3889

REGULATION, )

)

Respondents. )

)


RECOMMENDED ORDER


Pursuant to notice, these matters were heard before the Division of Administrative Hearings by its assigned Administrative Law Judge, Donald R. Alexander, on November 3-7, 10-14, and 17, 2008, in Tallahassee, Florida.

APPEARANCES


For Petitioner: Edward P. de la Parte, Esquire

Vivian Arenas-Battles, Esquire Kristin A. Yerkes, Esquire

de la Parte & Gilbert, P.A. Post Office Box 2350

Tampa, Florida 33601-2350

For Intervenor: David M. Pearce, Esquire

Assistant County Attorney

1660 Ringling Boulevard, Second Floor Sarasota, Florida 34236-6808


For Respondent: Frank E. Matthews, Esquire (Mosaic) Susan L. Stephens, Esquire

Amelia A. Savage, Esquire Timothy M. Riley, Esquire Hopping Green & Sams, P.A. Post Office Box 6526

Tallahassee, Florida 32314-6526


Roger W. Sims, Esquire Holland & Knight LLP Post Office Box 1526

Orlando, Florida 32802-1526


Christopher Torres, Esquire Greenberg Traurig, P.A.

625 East Twiggs Street, Suite 100

Tampa, Florida 33602-3925

(attended hearing on November 4 only)


For Respondent: Justin G. Wolfe, Esquire (Department) Amanda G. Bush, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

Mail Station 35

Tallahassee, Florida 32399-3000 STATEMENT OF THE ISSUES

The issues are whether Respondent, Mosaic Fertilizer, LLC (Mosaic), has provided reasonable assurances that the proposed mining and reclamation of the South Fort Meade Mine in Hardee County can be conducted in a manner that comports with the applicable statutes and rules such that the proposed Environmental Resource Permit (ERP), Conceptual Reclamation Plan (CRP), variance from minimum standards for dissolved oxygen, and

variance from littoral zone percentage provisions for the Project should be issued by Respondent, Department of Environmental Protection (Department).

PRELIMINARY STATEMENT


On June 30, 2008, the Department issued notices of intent to grant ERP Permit No. 0221122-004, CRP Application Code MOS- SFMHC-CP, Variance No. 0221122-005-EV-VE (DO Variance), and Variance No. 0221122-006-EV-VR (Zone Variance). Following a Department Order granting an extension of time, Lee County filed a Petition for Formal Administrative Hearing (Petition) on August 1, 2008, challenging each of the proposed agency actions. The Petition was referred to the Division of Administrative Hearings on August 8, 2008, with a request that an administrative law judge be assigned to conduct a formal hearing. The ERP, CRP, DO Variance, and Zone Variance were assigned DOAH Case Nos. 08-3886, 08-3887, 08-3888, and 08-3889,

respectively. The cases were initially assigned to Administrative Law Judge Bram D. E. Canter but were transferred to the undersigned on August 12, 2008.

On August 11, 2008, Mosaic filed a Motion for Summary Hearing in Tallahassee pursuant to Section 378.205(3), Florida Statutes (2008).1 That statute provides in part that "[a]dministrative challenges to proposed state agency actions

regarding phosphate mines and reclamation pursuant to this chapter [Chapter 378] or part IV of Chapter 373" are subject to the summary hearing provisions of Section 120.574, Florida Statutes, and that the hearing must be conducted within ninety days after a motion for summary hearing is filed, even if the other parties oppose a summary hearing. On August 26, 2008, the four cases were consolidated; the Motion for Summary Hearing in Tallahassee was granted, and the final hearing was scheduled on November 3-7, 10-14, and 17-21, 2008, in Tallahassee, Florida.

However, the hearing was completed on November 17, 2008. Because additional discovery beyond that contemplated in a regular summary hearing was determined to be necessary by the undersigned, by Order dated September 4, 2008, a detailed discovery schedule was established.

On September 17, 2008, Sarasota County filed its Petition to Intervene in opposition to the proposed agency actions, which was granted by Order dated September 24, 2008.

During the course of this proceeding, numerous procedural and discovery disputes arose. The disposition of those matters is found in separate orders entered in these cases.

At the final hearing, Mosaic presented the testimony of Thomas E. Myers, III, Assistant Vice-President of Mining and accepted as an expert; Dr. John E. Garlanger, a professional

engineer with Ardaman & Associates and accepted as an expert; Bradley S. Pekas, a professional engineer with Environmental Consulting and Technology (ECT) and accepted as an expert; Gary

P. Uebelhoer, a professional engineer with ECT and accepted as an expert; Philip W. Simpson, a scientist with ECT and accepted as an expert; James E. Poppleton, a scientist with ECT and accepted as an expert; Martin J. Boote, a scientist with ECT and accepted as an expert; Robert W. Burleson, a professional engineer with Applied Technology & Management and accepted as an expert; Dr. Mark A. Ross, President of Hydrosystems, Inc., and accepted as an expert; Dr. Douglas J. Durbin, an ecologist with Biological Research Associates, Inc., and accepted as an expert; John Kiefer, a professional engineer with BCI Engineering & Scientist, Inc., and accepted as an expert; Joseph Schuster, a scientist with Ecological Resource Consultants, Inc., and accepted as an expert; John A. Coates, Chief of the Bureau of Mining and Minerals Regulation; and Richard W. Cantrell, Deputy Director of the Division of Water Resource Management and accepted as an expert. Also, it offered Mosaic Exhibits 1A-2N, 3-59, 61-63, 67-78, 84-86, 91-94, 94A, 95-101, 103-105, 107-114, 116-119, 122-204, 208-232, 245-277, 279-286, 300-307, 309-312, 312A, 314, 326, 328, and Rebuttal Exhibits 1-11, 13-15, 18, 19, and 22-28, which were received in evidence. The Department

presented the testimony of Richard W. Cantrell, Deputy Director of the Division of Water Resource Management and accepted as an expert; Orlando Rivera, Program Administrator of the Mandatory Phosphate Section and accepted as an expert; John A. Coates, Chief of the Bureau of Mining and Minerals Regulation and accepted as an expert; Christine Keenan, an Environmental Specialist III and accepted as an expert; and Kevin Claridge, Assistant Director of the Southeast District Office and accepted as an expert. Also, it offered Department Exhibits 1-5, 9,

10a.-d., 10f.-10n., 11a., 11c., 11e.-11i., 12a.-12g., 13a.,


13b., 14.a, 14c., 14d., 15a., 15b., and 15d.-f., 16a.-16j.,


17c., 17d., 17f.-i., 18a., 18c.-g., 19a.-i., 20, 20a.-20c.,


21a., 21.b., 21f., 21h., 22a.-i., 23b.-23x., 24a.-d., 25a.,


25b., 26a.-26e., 27a.-k., 28a.-e., and 30-38, which were received in evidence. Lee County presented the testimony of Philip R. Davis, a geologist and President of SDI Environmental Services, Inc., and accepted as an expert; Kevin L. Erwin, an ecologist and President of Kevin L. Erwin Consulting Ecologist, Inc., and accepted as an expert; Dr. Anthony J. Janiki, a scientist and President of Janiki Environmental, Inc., and accepted as an expert; Dr. Thomas H. Fraser, a scientist with Mote Marine Laboratory and accepted as an expert; and Roland E. Ottolini, a professional engineer with the Lee County Division

of Natural Resources and accepted as an expert. Also, it offered Lee County Exhibits 1-5, 7-13, 15-23, 24 (pages 3 and 9

only), 25-29, 32, 33, 35, 36, 43, 48, 518, 723, 724, 735, 754,


and 874, which were received in evidence. Sarasota County presented the testimony of Theresa A. Connor, County Water Resources Manager and accepted as an expert; Andrea P. Lipstein, County Environmental Supervisor and accepted as an expert; John

W. Merriam, Environmental Manager, Water Planning and Regulatory, and accepted as an expert; Kelly J. Pluta, an Environmental Specialist III and accepted as an expert; and John

  1. Ryan, a County Supervisor and accepted as an expert. Also, it offered Sarasota County Exhibits 1-5, 17-24, 26-28, 38, 40, 65-70, 72, 76-78, 95, 104, 105, 107, and 108, which were received in evidence. Finally, the following were officially recognized: Section 373.414(8)(b), Florida Statutes; the Peace River Cumulative Impact Study (January 2007); the Southern Water Use Caution Area Recovery Strategy (March 28, 2006); the Recommended and Final Orders in DOAH Case Nos. 01-1080, 02-4134, and 03-0791; Florida Administrative Code Rule Chapters 62-345, 40D-8, and 40D-80; and the Southwest Florida Water Management District's Basis of Review (BOR).

    The Transcript of the hearing (twenty volumes) was filed on November 18, 2008. Under the terms of Section 378.205(3),

    Florida Statutes, a Recommended Order is required to be issued by December 18, 2008. Proposed Recommended Orders were filed by the Department, Mosaic, Lee County, and Sarasota County on December 3, 2008, and they have been considered by the undersigned in the preparation of this Recommended Order.

    Mosaic's Motion to Strike Extraneous Hearing Testimony and Exhibits from Lee County's Proposed Recommended Order filed on December 4, 2008, is hereby granted. The Proposed Recommended Order of the prevailing party has been substantially used in the preparation of this Recommended Order.

    FINDINGS OF FACT


    Based upon all of the evidence, the following findings of fact are determined:

    1. Mosaic is a limited liability company authorized to do business in the State of Florida and is the applicant in these proceedings. It was formed by the merger of IMC Phosphates Company and Cargill, Inc., in 2004. Mosaic has applied for permits to mine, reclaim, and conduct associated activities on property in Hardee County, Florida, known as the South Fort Meade Hardee County tract. These activities are referred to in this Recommended Order as the "Project" or "site."

    2. The Department is a state agency with jurisdiction over ERP permitting under Part IV, Chapter 373, Florida Statutes, for

      phosphate mining activities with jurisdiction over phosphate mining reclamation under Part III, Chapter 378, Florida Statutes, and with jurisdiction over variances associated with phosphate mining under Section 403.201, Florida Statutes.

      Pursuant to that authority, the Department reviewed the ERP, CRP, DO Variance, and Zone Variance applications for the Project.

    3. Lee and Sarasota Counties are political subdivisions of the State of Florida. Both Counties have filed challenges to other mining applications and have been found to have standing in those cases. The site is located within the Greater Charlotte Harbor Basin, approximately sixty percent of which lies within Lee County. In this case, Lee County is concerned about the potential destruction of stream and wetlands in the mine area and the impact of mining and its effects on Charlotte Harbor and the Peace River. Sarasota County is a member of the Peace River Manasota Regional Water Supply Authority, and they jointly hold a water use permit, which authorizes them to withdraw water from the Peace River for potable supply.

      Sarasota County operates a water treatment plant on the Peace River downstream from the site and is concerned with potential impacts to water quality and wetlands.

    4. After three years of data collection and site analysis, on October 13, 2006, Mosaic filed applications with the Department's Bureau of Mine Reclamation for an ERP/Water Qualify Certification for the disturbance of approximately 7,756 acres of uplands, wetlands, and other surface waters within a 10,856– acre area which makes up the site; a CRP for the same parcel; and the associated Zone and DO Variances. Three sets of additional information were requested by the Department, and on January 31, 2008, the applications were deemed to be complete. On June 30, 2008, the Department issued Notices of Intent to issue the permits and grant the variances.

    5. The Project is located within the Peace River Basin.


      Little Charlie Creek, a tributary to the Peace River, enters the site in the northeast part of the tract and flows diagonally across the tract in a general southwest direction. The Project is located to the east of the Peace River, east of the town of Bowling Green, northeast of the City of Wauchula, and just south of the Polk-Hardee County Line in Hardee County, Florida. The Project site is twenty-nine miles from the Sarasota County line and fifty-three miles from the Lee County line. The Peace River eventually empties into Charlotte Harbor near Port Charlotte in Charlotte County.

    6. The Project consists of approximately eighty percent of upland land cover types, including large acreages converted to agricultural uses, such as cattle grazing, citrus production, and row crop production. The Project site consists primarily of citrus groves and pasture. Richard W. Cantrell, Deputy Director of Water Resources for the Department, has extensive experience and knowledge concerning agricultural parcels of this size in Central Florida. Based on his familiarity with the site, he indicated that all the streams have been impacted, the impacts to some areas of the site are severe, and the "site contains some of the most polluted streams with respect to sedimentation that I have ever seen." The other Mosaic and Department ecological experts familiar with the site concurred in that assessment, and the substantial data collections and application information support that assessment of the site.

    7. Of the 2,590.7 acres of wetlands on the property, approximately 751 acres of wetlands and other surface waters will be impacted. Of that 751, 91 are upland cut ditches or cattle ponds, 108 acres are other surface waters, and 274 acres are herbaceous wetlands.

    8. Virtually all of the native upland vegetation on the site has been destroyed due to the agricultural activities that have been undertaken on the site over time. Only remnant

      patches of native upland remain on the site. These comprise approximately nine percent of the site and are predominantly within the riparian corridors of Little Charlie Creek and the Peace River and are proposed to be preserved.

    9. The evidence established that the majority of the wetlands and streams proposed for impact are lower in quality; the higher quality wetlands are typically associated with the riparian stream corridors and are proposed to be preserved. The preserved uplands are primarily pasture but also include one hundred thirty-nine acres of upland forest.

    10. Twenty-nine distinct vegetative communities were mapped on the site during approximately two years of evaluation and assessment utilizing the Florida Land Use, Cover and Classification System (FLUCCS).

    11. There are numerous natural stream segments that were mapped on the parcel including the primary drainage systems on site, consisting of the Peace River, Little Charlie Creek, Lake Dale Branch, Parker Branch, and Max Branch. Substantial portions of the natural streams and their flood plains will be preserved; sixty-two natural stream segments totaling 58,769 linear feet will be mined.

    12. No sovereign submerged lands are proposed to be impacted by the activities. The Peace River to its ordinary

      high water line is sovereign submerged lands; however, no other streams on site are claimed as sovereign. Therefore, no authorization to utilize or impact sovereign submerged lands is required.

    13. The field work assessing the ecological condition of the site's wetlands, streams, and surface waters consisted of detailed quantitative and qualitative assessments using FLUCCS, the Wetland Rapid Assessment Procedure, and the Uniform Mitigation Assessment Methodology (UMAM) codified in Florida Administrative Code Rule Chapter 62-345.

    14. The level of assessment expended in evaluating the native upland and wetland habitats on the site was considerable and provided reasonable assurances that the current condition and relative value of the systems were adequately considered in the permitting process.

    15. From 2002 to 2004, Mosaic conducted intense ecological evaluations of the site, evaluating historical and aerial photography and other site documentation and conducting extensive examinations in the field, including vegetative, macroinvertebrate, and fish sampling and surveying, surface and ground water quality and quantity monitoring, wildlife observations, surveys and trapping, stream mapping and evaluation, soil analysis, and other efforts, both in areas to

      be mined and areas to be preserved, and in both uplands and in wetlands.

    16. The ecological assessments were primarily conducted prior to the hurricane events of 2004, although additional field work was conducted following the hurricanes. Mosaic and the Department's experts revisited the site in the fall of 2008 and agreed that the various ecological and biological assessments conducted prior to the hurricanes would tend to overstate the quality of the site as compared to its current condition. The hurricanes caused a significant amount of damage to the remaining forested habitats on the site.

    17. A formal wetland jurisdictional determination was issued and published without challenge in 2007 and therefore conclusively establishes the boundaries of the wetlands and surface waters on the site for permitting purposes.

    18. Seasonal surveys for wildlife on the site were conducted in 2003-2004 using the wildlife survey methodology prescribed and approved by the Florida Fish and Wildlife Conservation Commission. Specialized wildlife surveys and night-time surveys were also conducted. A total of 4,600 man hours of effort were expended to evaluate the presence of fish and wildlife, including threatened and endangered species, on the site. The entire site was surveyed, with over 2,600 miles

      of wildlife transects, to assess the presence of wildlife, and detailed information was recorded for all wildlife observations, including anecdotal observations by the ecologists performing the wetland assessments.

    19. Mosaic also engaged in an extensive effort to identify the natural stream channels proposed for impacts on the site. After discussion with the Department staff, Mosaic distinguished the natural streams in accordance with FLUCCS codes 511, 512, 513, and 514, as required by Florida Administrative Code Rule 62C-16.0051(4).

    20. Streams are a subset of the term "other surface waters" for ERP purposes. Although streams are defined in Section 373.019(18), Florida Statutes, as are other watercourses and surface waters, there is no operative use of, or reference to, streams in Part IV, Chapter 373, Florida Statutes, governing ERP permits. Also, there are no specific ERP mitigation requirements applicable to streams. Thus, the only specific regulatory use of the word "stream" occurs in the context of Florida Administrative Code Rule 62C-16.0051, and not the ERP rules. The Department and Mosaic established that the delineation of streams proposed for impact by mining on the site was sufficient and adequate for purposes of the CRP rules. In addition, Mr. Cantrell stated that, for purposes of the acre-

      for-acre, type-for-type (for wetlands) and linear foot (for streams) reclamation requirements in Florida Administrative Code Rule 62C-16.0051, the Department required Mosaic to delineate a stream as such until the point it enters or after it leaves a wetland area and to delineate the wetland polygon itself as a wetland, not a stream. This is true even if water continues to flow through the wetlands and reform as a stream at the other side. If the stream will not be impacted, then nothing in either the ERP or CRP rules requires its precise delineation, because the CRP rules apply only to reclamation of impacted areas. Thus, Lee County's assertion that "streams" has some special status by virtue of the definition in Section 373.019(18), Florida Statutes, has not been accepted.

      Mr. Cantrell further testified that the Department utilizes a substantially similar definition to delineate "streams" pursuant to Florida Administrative Code Rule 62C-16.0051(4), but as noted in Findings of Fact 44-46, subsection (5) of the rule requires restoration on a linear foot basis only of natural streams.

    21. Lee County contended that over 12,000 feet of natural streams were omitted or misidentified in the application. However, based upon the evidence presented, both historical and current, and applying the applicable regulations and statutes, this argument has been rejected. This contention was based on

      after-the-fact approximation of stream locations and lengths plotted from memory in a desktop analysis. Further, during his site visit to mark stream locations, Lee County's expert failed to use a handheld GPS device or maps. Therefore, the evidence submitted by Mosaic and the Department as to the location and length of the streams proposed for impact has been credited.

    22. Mr. Cantrell testified that even the best of the streams proposed for impact have been subjected to at least sixty years of agricultural disturbance and manipulation. For example, the system 22 series of stream segments will be impacted and replaced by the clay settling areas. While the witness characterized segment 22(o) as the most stable and least impacted of the streams to be mined, that segment is 376 feet long and located at the uppermost reach of the 22 systems. It is an extremely small percentage of the overall 12,000 plus feet of less stable and more severely impacted parts of system 22. Mosaic and the Department analyzed the origins and current condition of the streams to be impacted, most of which are less than three-to-four feet wide and one foot or less deep and flow only intermittently and seasonally.

    23. The ecological and hydrologic conditions of the site and its fish and wildlife populations and habitat values were assessed for purposes of the ERP and CRP regulatory criteria.

      Respondents' characterization of the functional value of the wetlands, streams, and surface waters is supported by a preponderance of the evidence. Lee and Sarasota Counties' assertion that the site wetlands and streams are in "good" condition and can be easily restored is not credited in light of the lack of empirical data to support this contention.

    24. The only way to recover the phosphate ore is through mining to remove the overburden layer and expose the phosphate matrix with a dragline.

    25. The first step prior to any land disturbance associated with phosphate mining is the installation of a "ditch and berm" system, which is recognized as a best management practice (BMP) by the Department and the United States Environmental Protection Agency.

    26. Installation of the ditch and berm system proceeds in phases to protect unmined wetlands and habitats from mining impacts as mining progresses; it is not constructed all at once. The ditch and berm remains in place around an individual mining unit until mining and reclamation have been completed and monitoring indicates the revegetation is sufficiently established such that no violations of water quality standards will occur upon re-connection to adjacent and downstream waters.

      It is then removed in accordance with the reclamation plan. The system serves a number of purposes described below.

    27. Berms are required to be constructed in accordance with specific design criteria. The height of the berm will be designed in accordance with rules specific to such structures to prevent water from overtopping the berm during a 25-year, 24- hour storm event, even if the ditch becomes blocked.

    28. Following installation of a ditch and berm system, bulldozers clear the mining area of vegetation. Up to three large electrically powered draglines operate generally in parallel rows to remove the overburden layer (the upper layer of sand and clay soil), which is approximately 23.6 feet thick on average, to expose the phosphate matrix, which is approximately 13-to-15 feet thick on average. The overburden is cast to the side in piles to be later reused in reclamation.

    29. The phosphate matrix is a mixture of sand, clay, and phosphate, which must be separated after mining. At the beneficiation plant, washing, screening, and flotation processes are used to separate the phosphate rock from the sand and clay. After washing and screening, the sand is pumped back to the mine cuts for use in reclamation, and the clay is pumped to clay settling areas (CSAs) in slurry form to decant.

    30. Both the transport of sand back to the mine areas for use in reclamation and the transport of clays to CSAs are considered "mining operations," not "reclamation." See Peace River/Manasota Regional Water Supply Authority, et al. v. IMC

      Phosphates Company, et al., DOAH Case No. 03-0791 (DOAH June 16, 2006; DEP July 31, 2006); Fla. Admin. Code R. 62C-16.0021(10)

      and (15). Thus, contrary to Lee County's allegation, the transportation of clays and sand is not a valid consideration in the financial responsibility required for mitigation.

    31. Through testimony and its materials balance tables, which are part of the application, Mosaic demonstrated that it has sufficient sand tailings and other waste materials to meet all of its reclamation requirements mine-wide, including both the Polk side and the Project site. However, while there is sufficient sand available to create the proposed reclamation topography and contours, the tables and testimony demonstrated a need, on a mine-wide basis, for lakes, as voids will remain otherwise. There will be only a very small pile of available sand remaining after all reclamation obligations on both the Polk side and the Project are met, an insufficient amount to eliminate the need for deep lakes as proposed.

    32. Mr. Myers, Mosaic's Vice-President of Mining, testified as to the three basic ways the waste materials

      generated by the beneficiation plant are disposed of on-site to facilitate reclamation. Sand tailings will be utilized in areas to be reclaimed as native habitats, wetlands, and streams.

      Clays will be disposed of in CSAs. However, based on the materials balance and logistical issues, the "land and lakes" reclamation method, which utilizes only the available overburden material remaining on-site after mining, will be used for the lake reclamation. This method allows sand tailings preferential use in reclamation of native habitats and use of shaped and contoured overburden in areas not proposed for wetland mitigation. Such is the case for the proposed reclaimed lakes.

    33. A CSA is an above-grade impoundment to hold clay slurry pumped from the beneficiation plant. This clay slurry is pumped into one side of a CSA in the form of muddy water. The clay settles to the bottom, and the clear water remains at the top. The clear water is drawn out from the opposite side of the impoundment, where it is recycled back to the beneficiation plant and mine for reuse.

    34. Over time, the clay consolidates and solidifies to form a solid soil, the surface area is drained, and the impoundment reclaimed.

    35. Three CSAs will be constructed on the northern portion of the site to hold the clay that cannot be stored in already-

      permitted CSAs in Polk County. The use of stage filling has allowed Mosaic to have additional usable space in its CSAs, minimizing the footprint of new CSAs in Hardee County. In addition, approximately fifty percent of the clay waste from the site will be disposed of at the Polk site to further minimize the clay disposal footprint and eliminate and reduce impacts.

    36. To evaluate the number of CSAs required, Mosaic asked Ardaman & Associates, a consulting firm, to examine different clay generation scenarios when predicting the CSAs required by mining and beneficiation. The life of mine waste disposal plan, most recently updated in September 2008, indicated that, in all but one scenario (the seventy percent clay containment scenario), all three CSAs would be required. However, Mosaic witness Garlanger established that all three CSAs in Hardee County would be necessary based on the best available information as to the amount of clays reasonably likely to be generated by mining; the seventy percent scenario is not likely. No evidence was presented to rebut that testimony. A diversion system was also voluntarily included for the CSAs by Mosaic. In the highly unlikely event of a dam failure, this system will re- direct any escaped water and/or clay materials to adjacent open mining cuts where they can be safely stored. The diversion system will be reclaimed when the CSAs are reclaimed.

    37. The evidence established that the ditch and berm system, CSAs, and diversionary structure are capable of being constructed and functioning as designed.

    38. The reclamation plan includes avoidance (no mining) of approximately 3,100 acres, or twenty-nine percent, of the site, including more than seventy-one percent of the total wetlands

      on-site. Of this, 2,100 acres will be placed in a perpetual conservation easement. There is a wide gamut of habitat types on the site that will be preserved and not mined, including both streams and wetlands. The most complex and least impacted habitats on the site have generally been included in the preserve area.

    39. The project includes disturbance of 751.3 acres of wetlands and other surface waters, which include non-wetland floodplains, cattle ponds, and upland-cut ditches, and mining of 58,769 linear feet of natural and modified natural streams. An additional 1,661 linear feet of stream channel will be disturbed but not mined for six temporary crossings for dragline/utility/ pipeline corridors.

    40. To mitigate for impacts to streams and wetlands under the ERP rules, Mosaic will create 641 acres of wetlands and other surface waters and 67,397 feet of stream channel and will also provide a conservation easement to the Department on 2,100

      acres of unmined wetland and upland habitat associated with the major riparian systems. The conservation easement area will be permanently preserved and protected from secondary impacts.

    41. The UMAM rule is applied to ERP applications to measure the functional loss to wetlands and other surface waters proposed for impact and the functional gain associated with the proposed mitigation. Functional loss is compared to functional gain to determine whether sufficient mitigation has been offered that offsets the proposed impacts. The proposed preservation and wetland and surface water creation, along with certain upland enhancements, will provide more than enough UMAM mitigation "lift" (with 48 excess credits) to satisfy the ERP mitigation obligations and offset those wetland impacts that cannot be eliminated or reduced. The UMAM scores for the reclaimed areas are conservative, that is, using higher risk factors by assuming muck or other appropriate topsoil will not be available, and take into account the risk or difficulty associated with creation of a particular system, based on actual UMAM scores for existing reclaimed systems.

    42. Time lag, which is normally a factor considered in the UMAM mitigation equation, expressly does not apply to phosphate mines pursuant to Florida Administrative Code Rule 62-345.600. Thus, Lee County's attempt to argue that some greater amount of

      mitigation of streams is required to account for the time required to construct and reinstate flow and vegetation to the streams is not credited.

    43. Mr. Cantrell confirmed that "fat" was built into the foot-for-foot stream reclamation because 7,000 more feet of stream will be reclaimed beyond the amount impacted; some "stream" segments, specifically, stream segment 18(i), probably should not have been required to be reclaimed at all.

    44. Under Florida Administrative Code Rule 62C-16.0051, the 511 and 512 classified "natural" streams are the only streams warranting reclamation as streams under the Department's reclamation rules. Only natural streams currently existing immediately prior to mining are required to be reclaimed on a linear foot basis.

    45. Reclamation meeting the requirements of Florida Administrative Code Rule 62C-16.0051 is adequate mitigation under the ERP program in Part IV, Chapter 373, Florida Statutes, if it maintains or improves the functions of the biological systems currently existing onsite. See § 373.414(6)(b), Fla. Stat. Mr. Cantrell established that, under subsection (5) of the rule, the Department has discretion to request the applicant to restore wetlands and streams to a different type of system than existing on the site if "mitigating factors indicate that

      restoration of previously modified streams as a different type of lotic system would produce better results for the biological system and water quality."

    46. The evidence established that the rules do not require reclamation of artificially created water courses or remnant stream segments that lack the functions or landscape position one normally associates with natural streams. Instead, a better lotic system will be created that will improve existing functions and water quality, consistent with Section 373.414(6)(b), Florida Statutes, and the CRP rules.

    47. In addition to the wetlands and surface waters created to meet mitigation requirements, the Project will also reclaim uplands and will include what is known as "land and lakes" reclamation in the southeastern portion of the site. Utilizing shaped and contoured overburden, Mosaic will create four lakes totaling 180 acres and 43 acres of associated herbaceous littoral zone as CRP reclamation. This is based predominantly on the mine-wide materials balance showing a need for reclaimed lakes to account for mine voids on the Hardee site, the Polk site, or both. As a result, Mosaic has proposed 180 acres of reclaimed lakes in Hardee County in lieu of 500 acres of reclaimed lakes in Polk County, as this results in eliminating overall reclaimed lake acreage while satisfying Hardee County's

      request for deep lakes. In addition, timing and property logistics in that portion of the site make transport of tailings to the area from the beneficiation plant problematic.

    48. As the site is an extension of the existing South Fort Meade Mine in Polk County, Mosaic possesses permits that are not at issue in this proceeding, but are relevant to the project.

    49. Discharges from a mine recirculation system require a National Pollutant Discharge Elimination System (NPDES) permit. Discharges may only occur at specified discharge points upon verification that the discharge meets stringent water quality conditions in the permit, which are set to ensure that water quality standards in the receiving water are met at the point of discharge (without mixing) and that downstream water quality will be protected.

    50. A separate NPDES permit is not needed for the Project, because Mosaic already has a valid NPDES permit for the Polk County beneficiation facility, which will serve the site.

    51. Mosaic currently has a Water Use Industrial Permit (WUP) issued by the Southwest Florida Water Management District (SWFWMD). The WUP includes both the Polk County and Hardee County portions of the South Fort Meade mine and governs both dewatering of the mine area prior to mining and operation of

      water supply wells located in Polk County that will be used to provide supplemental water to the recirculation system.

    52. Mosaic's evidence demonstrated that the Project will not cause adverse water quantity impacts, consistent with Florida Administrative Code Rules 40D-4.301(1)(a), 40D-4.302(1), and 62C-16.0051 and related BOR provisions.

    53. Mosaic presented evidence concerning the potential long term impacts of the proposed project on surface and ground water quantities and flows both during active mining and reclamation activities, and after reclamation is complete. Extensive analyses were presented by Mosaic's expert witnesses and evaluated by the Department. Such analyses showed no adverse impacts to water quantity on the site, adjacent properties, or in the Peace River or Charlotte Harbor.

    54. The site was studied extensively by Mosaic, and detailed hydrology characteristics were assessed as part of the preparation of the ERP and CRP applications. Various surface water stations, topographic maps, and ground water sampling points were utilized and geologic information was developed by evaluation of various borings across the site. Mosaic witness Burleson, a professional engineer, further considered soil types, land use and vegetative cover, and existing site hydrologic factors such as culverts, bridges, and other such

      changes to the site by the prior owners. Mosaic's modeling expert, Dr. Mark Ross, considered these factors on a regional scale in his integrated modeling for the 360 square mile regional basin. In the region of Florida that encompasses the site, there are three major hydrogeologic layers that are significant to a hydrologic analysis: (1) the surficial aquifer system, comprised of the overburden (the top layer of soil) and the phosphate matrix; (2) the confining layer and intermediate aquifer system; and (3) the Floridan, or deep, aquifer system.

      The confining layer separates the surficial from the intermediate and Floridan aquifer systems.

    55. By understanding the surface and ground water systems and physical characteristics of the site, the Mosaic experts were able to apply appropriately-calibrated hydrologic models to assess (1) pre-mining and post-reclamation floodplains and storm event runoff comparisons; (2) base flows to reclaimed streams;

      (3) potential hydrologic impacts of stream crossings; (4) effectiveness of the perimeter "recharge ditches"; (5) hydroperiod of reclaimed wetlands; and (6) potential impacts of the project on flows in the Peace River. These models were used to predict with reasonable certainty the effect of the Project on water quantity on-site, off-site, and on a regional scale.

    56. As set forth below, the evidence established that water quantity and flows in adjacent unmined wetlands and streams will be maintained during mining activities as a result of the installation of the ditch and berm system as proposed.

    57. Before the ditch and berm system is constructed, Mosaic will refine the design of the system based on actual geological data and gradient information to assure the ditch and berm will function as proposed and modeled. The ditch and berm system is inspected regularly. Recharge wells within the recharge ditch are not required unless localized conditions dictate use of the wells. Contrary to Lee County's assertions, this site is distinguishable from the Ona mine site (which is also in Hardee County), and the depth of mining is far more shallow with relatively few areas mined to a depth of fifty feet, which was common at the Ona mine site.

    58. Additionally, Mosaic must install perimeter monitor wells at regular intervals adjacent to and downgradient of the ditch and berm system prior to mining. These wells are monitored prior to mining to establish a baseline and regularly throughout mining in accordance with the requirements of Mosaic's WUP and the ERP to assure that the water table in adjacent areas is not adversely affected by mining activities.

    59. The water in the ditch portion of the perimeter system must be maintained at levels sufficient to maintain groundwater levels in undisturbed areas. Maintaining water in the ditch at appropriate levels precludes drainage of groundwater from adjacent sites into open mine cuts. Mosaic witness Pekas, a professional engineer, conducted modeling to determine whether adequate base flow will be provided to protected streams and reclaimed streams during mining. Provided the ditch and berm system is operated properly, proper base flows will be maintained.

    60. All of the hydrologic experts agreed that proper operation of a ditch and berm system assures that adequate groundwater outflow, or base flow, is available to support adjacent streams and wetlands during mining.

    61. During active mining operations, the ditch and berm system collects rainfall on areas within the system. The ditch and berm system temporarily detains this rainfall, preventing the direct discharge of untreated, turbid runoff to adjacent wetlands and waters, but does not permanently retain the rainfall. The evidence demonstrated that most of the rainfall that falls on areas disturbed by mining and mining-related activities is detained by the perimeter ditches, routed to the mine recirculation system, and is subsequently discharged, when

      it meets water quality standards, through NPDES-permitted outfalls to waters of the state. This will serve to attenuate surface water flows, allowing surface water retained during storm events to be discharged during extreme low flow events, providing for less "flashiness" in the streams. Lee County's assertion that runoff will be permanently retained is not credited; the evidence clearly established that controlled releases of treated stormwater occur through the permitted NPDES outfalls.

    62. The evidence shows that Mosaic will re-connect mined and reclaimed areas at the mine in Polk County at a rate exceeding the rate at which the Project's mine areas will be diverted by the ditch and berm system. Thus, any potential downstream impact of the ditch and berm construction on the site will be offset and buffered beyond the safeguards incorporated in the project design.

    63. The evidence demonstrated that the proposed ditch and berm recharge and monitoring system described here is capable, based upon generally accepted engineering principles, of being effectively performed and functioning as proposed and will preclude any adverse impact on the surficial aquifer beneath the preserved areas and adjacent properties and on adjacent surface waters and wetlands.

    64. The Department will apply the relevant BOR criteria concerning water quantity impacts on a pre-mining/post- reclamation basis consistent with the application of these same criteria to other non-mining ERP applicants. In this case, the Department reviewed Mosaic's submittals, assessed the impacts, and determined no adverse impacts to water quantity would occur during mining.

    65. Mosaic submitted a detailed analysis of potential surface water quantity impacts that may occur after reclamation is complete. This analysis included evaluation of post- reclamation floodplains and storm event run-off compared to pre- mining patterns, and characteristics of reclaimed natural systems. Floodplains, run-off, and reclaimed natural systems were assessed in the manner described below.

    66. Mosaic modeled potential impacts of the project on surface water flow using existing site conditions to calibrate and verify the model.

    67. Mr. Pekas developed a water balance hydroperiod spreadsheet model calibrated using existing, on-site wetlands to evaluate the expected hydroperiods of various types of wetland systems proposed to be reclaimed at the site. The evidence shows that the Pekas spreadsheet model was an appropriate model for predicting hydroperiods for reclaimed wetlands.

    68. Appropriate ranges for the expected hydroperiods and other hydrological characteristics needed for the different types of wetland systems to be created in the post-reclamation landscape were established. In order to reflect natural conditions, the Department specifically requested that the targets for expected hydroperiods of reclaimed wetlands vary across the established range of the hydroperiod for the type of wetland at issue, and these target hydroperiods are summarized in Table E-6 to the draft ERP.

    69. Mosaic demonstrated and verified that the Pekas spreadsheet reasonably predicts the hydroperiods to be expected from a given design for a proposed reclaimed wetland. After mining, site-specific conditions such as hydraulic conductivity will be reassessed and final design parameters will be developed accordingly.

    70. Lee County's witness Jonas demonstrated the importance of hydraulic conductivity when she adjusted the value for wetland 2-1C (one of Mr. Pekas' verification wetlands) from 0.5 to 30, based on a value not from the Project site, but from an off-site reclamation project. Not surprisingly, she concluded that a conductivity of 30 would not provide hydrology to support the wetland functionality. Her analysis demonstrates the importance of requiring reclamation of subsurface hydrology not

      based on an off-property conductivity value, but on site- specific hydraulic conductivity information. In his own analysis, Mr. Pekas relied on actual soil borings on-site, and at wetland 2-1C the average hydraulic conductivity was 0.5, which when modeled, provided appropriate hydrology for that wetland. Furthermore, ERP Specific Condition 11 requires Mosaic to reclaim wetlands with functionally equivalent hydraulic conditions based on verified field information as to site- specific hydrologic properties existing after mining, and the wetlands will not be released until functioning as required.

    71. The preponderance of the evidence demonstrates that reclaimed wetland can be designed and built in a manner that will achieve the required hydroperiods for each wetland type proposed to be disturbed and reclaimed at the site, including the bay swamps. In addition, each of the wetlands must be individually evaluated immediately prior to construction to provide additional verification of site-specific hydrologic conditions to assess, re-model, and verify the final wetland designs prior to construction. Condition 11c of the draft ERP also requires Mosaic to mimic the existing hydraulic conductivity and gradients near streams to ensure that base flows will be present post-reclamation. All of this will ensure that reclaimed streams will be hydrologically supported, and

      wetlands with the target hydroperiods requested by the Department will be constructed. The contrary testimony of Lee County's hydrologists does not credibly rebut this evidence. In performing their calculations, they utilized unrealistic numbers. The claim of Lee and Sarasota Counties' experts that they lacked sufficient information to form an opinion as to the accuracy of the modeling is not sufficient to overcome the evidence submitted by Mosaic to meet this criterion. See, e.g., National Audubon Society, et al. v. South Florida Water Management District, et al., DOAH Case No. 06-4157, 2007 Fla.

      ENV LEXIS 164 at *21 (DOAH July 24, 2007, SFWMD Sept. 13, 2007).


    72. Mr. Burleson determined that the original drainage patterns of the site would be restored post-reclamation.

    73. Mosaic provided reasonable assurances that the proposed reclamation is capable of being constructed and functioning as proposed.

    74. The preponderance of the evidence demonstrated that the proposed mining and reclamation of the site will not cause adverse water quantity impacts post-reclamation, as addressed by Florida Administrative Code Rules 40D-4.301(1)(a) and (c), associated BOR provisions, and Florida Administrative Code Rule 62C-16.0051(8)(b).

    75. Mosaic presented evidence demonstrating reasonable assurances that the proposed project will not cause adverse flooding to on-site or off-site property, consistent with Florida Administrative Code Rules 40D-4.301(1)(b) and 62C- 16.0051(8) and associated BOR provisions.

    76. During mining, there is no reasonable likelihood that active mining and reclamation activities at the site will result in any increased flooding conditions upstream of, on, or downstream of the site. The ditch and berm system reduces direct surface water runoff from areas disturbed by mining operations during peak rainfall events. Subsequent NPDES discharges of water typically lag slightly behind the rainfall events. This lag during mining decreases peak discharges in adjacent streams while augmenting lower flows slightly, thereby attenuating peak flows.

    77. Mr. Burleson evaluated the pre-mining and post- reclamation peak flow analyses for the project site to determine whether the post-reclamation topography, soils, and vegetative cover would result in flooding, using the Interconnected Pond Routing program or "ICPR" model, an accepted model for stormwater modeling, as required by the BOR.

    78. Mosaic's evidence established that the Project will not adversely impact existing surface water storage and

      conveyance capabilities, consistent with Florida Administrative Code Rule 40D-4.301(1)(c) and related BOR provisions.

    79. Additionally, Mosaic proposes to preserve from mining the 100-year flood plain of Little Charlie Creek and the Peace River and most of the higher quality small tributaries on the site. The smaller streams to be mined will be restored in a way that maintains or improves pre-mining conditions and will not cause harmful or erosional flows or shoaling.

    80. The federal Hydrologic Engineering Center Reservoir Analysis System and the National Flood Frequency Program were used by Mr. Burleson to verify the floodplains are accurately mapped and also that there will not be an increase in flood risk in the post-reclamation condition.

    81. The preponderance of the evidence demonstrates reasonable assurances that the proposed mining and reclamation activities at the site will not result in adverse flooding impacts, consistent with Florida Administrative Code Rules 40D- 4.301, 40D-4.302(1)(a)3., and 62C-16.0051(8), and the BOR, including water quality standards in Chapter 4.

    82. The evidence presented by Dr. Ross established that the proposed mining and reclamation activities on the site will not adversely impact flows in the Peace River. No adverse

      effects of the Project will be observable at the Zolfo Springs United States Geological Survey (USGS) gauging station.

    83. A minimum flow for the Upper Peace River has been established pursuant to Section 372.042, Florida Statutes. A minimum low flow of 45 cfs from April to June (Upper Peace MFL) was established at Zolfo Springs by the SWFWMD; since the MFL has not been met since adoption, a recovery plan has been instituted. See Fla. Admin. Code R. 40D-8.041(7). Lee County asserts that the Project will violate the Upper Peace MFL and the recovery plan, arguing that a reduction in average annual flow, regardless of how infinitesimal, constitutes a violation of Florida Administrative Code Rule 40D-4.301(1)(g). This argument was refuted by Dr. Ross, who established that the project would increase flows during low flow periods. The Department concurred with, and the evidence supports, Dr. Ross' assessment that the project would not exacerbate the Upper Peace MFL or interfere with the recovery plan.

    84. Dr. Ross created a regional-scale integrated model utilizing public domain computer programs in an iterative fashion that coupled surface water and ground water to comprehensively evaluate the effects of the project on the flows in the Peace River post-reclamation.

    85. The regional approach included a full range of upstream and downstream influences on the site, not simply mining, that could affect the hydrologic evaluation of any impacts from the Project on the Peace River. The model domain included 360 square miles. To account for site-specific impacts in the model, Dr. Ross increased the refinement and discretization over the site. Thus, the model was capable of considering impacts from the site in its entirety within the region as measured at the Zolfo Springs USGS gauging station. Zolfo Springs is the first USGS gauging station directly downstream of the site and is the point of compliance for minimum flows adopted for the Upper Peace River system.

    86. The regional model predicted virtually no change in flows at the Zolfo Springs gauging station after the project as proposed is reclaimed, and that both the high and low flows observed at Zolfo Springs would be maintained post-reclamation. Dr. Ross concluded that there would not be any reduction of low flows at Zolfo Springs due to the Project. He further concluded that the Project will not impact or affect the recovery of minimum flows.

    87. Dr. Ross calculated the differences between the model- predicted high flows and low flows from the observed flows and found that the modeled high flows were slightly attenuated and

      the modeled low flows were slightly augmented at Zolfo Springs. The attenuation is consistent with the increased storage for water in the post-reclamation system.

    88. Consistent with Florida Administrative Code Rule Chapter 40D-8, the Department considered potential impacts to low flows as the determining factor in determining whether a minimum low flow requirement like the one set for the Upper Peace MFL will be met. It concluded that the project is consistent with the Upper Peace MFL and its recovery strategy. The recovery strategy discusses projects which, like the one proposed, would yield a long-term increase in low flow conditions by storing some peak flow volumes and releasing them in low flow conditions. The Department's interpretation of its ERP rules and BOR provisions regarding MFLs, as well as other governing rules, is reasonable and has been accepted. Lee County's experts based their MFL testimony on an inappropriate use of annual average flow information and improper interpretation of Mosaic's data. Further, they inappropriately attempted to reach conclusions by estimates and extrapolation, and the overall weight of the evidence supports Mosaic's evidence that mining and reclamation will not cause a violation of the Upper Peace MFL.

    89. Accordingly, Mosaic has provided reasonable assurances that the requirements of Florida Administrative Code Rule 40D- 4.301(1)(g) and associated BOR provisions have been satisfied.

    90. The ditch and berm system and other proposed BMPs, such as silt fences, at the site will provide water quality protection to adjacent undisturbed surface waters and wetlands during mining and reclamation activities. The actual construction of the ditch and berm and stream crossings will be conducted using BMPs to avoid adverse construction-related impacts. During mining, the ditch and berm system will preclude uncontrolled releases of turbid water to adjacent un-mined areas.

    91. The evidence established that the proposed Project will not cause a violation of water quality standards, either in the short-term or long-term. Dr. Durbin, an ecologist, evaluated water quality data from the existing South Fort Meade mine in Polk County and compared data from the 10-year period before the mine opened against the 10-year period after the mining began, finding water quality to be equivalent or better after mining began in Polk County. This allowed him to conclude that water quality on the site will not be adversely affected and, in light of existing agricultural activities, will be maintained or improved both during mining and post-reclamation;

      water quality in reclaimed systems will be sufficient to maintain designated uses of the systems. Dr. Durbin opined that the ERP contains detailed water quality monitoring requirements that, based on his long experience, are sufficient to establish a baseline, assess compliance, and detect significant trends.

      Sarasota County's witness has no experience in ERP or CRP permitting and his suggestion for far more frequent monitoring is not credited. No additional monitoring conditions or criteria are warranted.

    92. For the above reasons, Mosaic has demonstrated by a preponderance of the evidence that reasonable assurances that water quality standards will not be violated either during mining, while reclamation is underway, or post-reclamation. The evidence further established that accepted BMPs will be used during mining to protect the water quality of adjacent and downstream waters, and that these measures can be expected to be effective to prevent any violations of water quality standards. Dr. Durbin provided unrebutted evidence that water quality standards in waters of the state and downstream of the project will be met post-reclamation and existing water quality in the unmined and reclaimed wetlands and waters will be maintained or improved post-reclamation. Thus, no adverse water quality

      impacts to the Peace River or Charlotte Harbor will occur during mining or post-reclamation.

    93. Therefore, reasonable assurances have been given that the requirements of Sections 373.414(1) and 373.414(6)(b), Florida Statutes, Florida Administrative Code Rules 40D- 4.301(1)(e) and 62C-16.0051(7), and associated BOR provisions are satisfied as to water quality.

    94. There is a wide range of habitat types on the site that will be preserved and not mined, including both streams and wetlands. The most complex and least impacted habitats on the site have generally been included in the no-mine and preserved areas.

    95. Mosaic does not propose to mine all or even most of the jurisdictional wetland and surface waters. In fact, seventy-one percent will be avoided. When developing a mining plan, Mosaic considers how to eliminate or reduce proposed impacts to waters and wetlands.

    96. The evidence established that Mosaic and the Department engaged in a protracted elimination and reduction discussion throughout the review process associated with the site's ERP/CRP applications. BOR Section 3.2.1 emphasizes the effort required to assess project design modifications that may be warranted to eliminate and reduce impacts to ecological

      resources found on the site. This effort was undertaken with the Department as early as 2004 during the DRI pre-application conferences. The major project design modifications involved the preservation of the named stream channels, the 100-year floodplain of the Peace River and Little Charlie Creek, and the 25-year floodplain of the other named tributaries. These areas will be permanently preserved by a 2,100-acre conservation easement; 1,000 additional acres will remain unmined. Also, the project design was modified and developed to maximize resource protection by integrating the Polk and Hardee mining operations. The testimony established how the activities at the Hardee operation will be greatly facilitated by relying upon and using the beneficiation plant and infrastructure already in place and permitted at the Polk site. Almost fifty percent of the clays generated at the Hardee mine will be disposed of in the existing Polk County CSAs, thereby eliminating one CSA altogether and substantially reducing the footprint needed for CSAs on the site. Likewise, the Department established that mine-wide, approximately 320 acres of lakes were eliminated.

    97. The Department discussed further modifications to the mine plan with Mosaic throughout the lengthy review process, doing a wetland and stream-by-stream assessment of the functions provided and the reclamation capability to maintain or improve

      the functions of the biological systems present prior to mining. The balance was struck between temporary resource extraction, recognized by Florida law as inextricably related to wetland disturbance, and the significantly altered natural resource features found on the site. In light of the 3,100 acres already eliminated and reduced from impact consideration, the Department in its discretion did not find it necessary to pursue economic data or analysis on the "practicability" of any further reductions. The highly disturbed nature of the wetlands and other surface waters being impacted gave the Department a high degree of confidence that mitigation and reclamation of these areas would in fact maintain and improve the functions provided prior to mining.

    98. Specifically, Mosaic has eliminated impacts to stream systems to the greatest extent practicable. Based on a Department field evaluation in late August 2008, Mosaic was directed to revise the no-mine line in the 3A stream system to more accurately reflect the floodplain of the stream draining the two bay heads north of the stream. In October 2008, Mosaic made the revision to add approximately 2.7 acres to the no-mine area. The majority of the streams proposed for impact by mining cannot be avoided, given the location of the three CSAs that are required for clay disposal associated with mining. The evidence

      established that there is no other location for the three CSAs that will have a lesser ecological or public health, safety, or welfare impact than the proposed location, given the site topography. As noted above, the volume of clays to be disposed of on the site has been reduced by half, and three CSAs are still needed. The location was chosen to move the CSAs as far from the Peace River and Little Charlie Creek as possible in light of the site topography, and this location avoids all impacts to named stream systems.

    99. As set forth above, Mosaic has demonstrated by a preponderance of the evidence that the best and most complex habitats on the site have been preserved at the expense of a loss of a significant amount of phosphate reserves in the preserved areas. All significant stream systems have been avoided to the extent practicable in light of the necessary CSAs. Both Mosaic and Department witnesses testified that the proposed no-mine area was the result of design modifications to eliminate or reduce impacts to wetlands to the greatest extent practicable. This satisfies the requirements of applicable rules and Section 373.414(1)(b), Florida Statutes.

    100. Florida Administrative Code Rule 62C-16.0051(4) and


      (5) provides specific guidance on the classification and reclamation of natural streams. The Department provided

      direction to the applicant through the review process in the identification of natural streams and the design guidance manual to ensure foot-for-foot replacement and functional replacement or improvement. The permit reflects the 58,769 feet of the streams identified as numbers 511 and 512 to be impacted, and Mosaic has proposed approximately 65,700 feet of restored stream. Lee County's assertion that 2.3 miles of additional unmapped streams should be added to the reclamation obligation has been rejected.

    101. It is clear many of the areas alleged to be unmapped streams were depressions, low lying areas, or standing water within wetland areas more accurately identified as marshes or swamps. The fact that a discernible natural stream channel exists upstream and downstream of a wetland did not change the accuracy of acknowledging the different structure, form, and functional attributes that result in the wetland being distinct from the stream. Also, many of the alleged unmapped streams were located in the no-mine areas, and thus the alleged lack of delineation is of no consequence.

    102. Lee County's witness Erwin admittedly took no measurements of the alleged streams. Also, he provided no evidence that he or his staff delineated the alleged streams on- site. Rather, he reconstructed where they were located as a

      desktop exercise from memory, without any aids or tools used in the field. He then superimposed an alignment and put it on a GIS layer over an aerial photograph, resulting in an electronically generated approximation. The witness offered no physical evidence of depth, width, length, or bankfull width of stream function, but merely an assertion as to areas that appeared to have a bed or channel, even if dry, and the attributes or functions of a stream were immaterial or irrelevant to his analysis. No other independent witness attested to the alleged stream discrepancy, whereas both Mosaic's expert, Mr. Kiefer, a recognized fluvial geomorphologist, and the state's expert on jurisdictional delineations, Mr. Cantrell, who was the author of the applicable rules, expressly disagreed with these allegations. The testimony of Mosaic and the Department is found to be the most persuasive on this issue.

    103. Mosaic and the Department established that the proposed stream restoration plan is more than adequate to meet the requirements of Florida Administrative Code Rule 62C- 16.0051(5) and will ensure the reclaimed streams maintain or improve the biological function of the streams to be impacted.

    104. Dr. Janicki, a scientist who testified on behalf of Lee County, was critical of the stream restoration plan.

      However, he acknowledged he was not an expert in stream restoration and that part of his job was to "look at how we might improve . . . on some of those shortcomings in the [stream] restoration plan." Dr. Janicki incorrectly assumed the design curve numbers were based on regional curves from north and northwest Florida rather than site-specific measurements.

      He stated that the guidance document was generalized and lacking specificity, but Table 4 contained in the guidance document contains nineteen stream morphological parameters for all forty- nine of the stream segments to be reclaimed. Dr. Janicki has never designed nor implemented a stream restoration project, and he acknowledged that he is not a fluvial geomorphologist.

      Conversely, Mosaic witnesses Boote and Kiefer, both accepted in this area, stated unequivocally that the plan was sufficiently detailed and that a qualified restoration and construction contractor could implement the plan in the field with appropriate field adjustments and construction level refinements based on site conditions. The allegation that the plan does not comport with ERP and CRP requirements because it lacks sufficient specificity is not credited. First, the ERP rules do not contain stream-specific restoration criteria. Second, the CRP stream rules adopted in May 2006 have never been applied in a prior case, and in this case the Department determined in its

      discretion that the plan as proposed meets the stream reclamation requirements of the CRP rules.

    105. Similarly, the stream restoration plan was criticized because measurements from every single segment or reach of stream were not used to develop the post-mining stream.

      However, Mr. Boote and Mr. Kiefer confirmed that only the most stable and least impacted of the stream segments on site were used as templates for stream reclamation. None of the recognized stream experts suggested that erosive, unstable "F" and "G" classified stream segments should be replaced in that unstable form or used as the template for reclamation.

    106. By a preponderance of the evidence, Mosaic has established that the reclamation plan for the site will more than offset any adverse impacts to wetlands resulting from the mining activities, because it will maintain or improve water quality and the functions of biological systems present on the site today, as required by Sections 373.414(1) and 373.414(6)(b), Florida Statutes.

    107. The evidence established that applicable Class III water quality standards will not be violated and that the water in wetlands and surface waters on-site post-reclamation will maintain or improve and be sufficient to support fish and

      wildlife in accordance with Florida Administrative Code Rules 62C-16.0051 and 40D-4.301(1)(e) and relevant BOR provisions.

    108. The proposed mitigation will also restore a more appropriate or more natural hydrologic regime that will allow for a better propagation of fish and invertebrates in reclaimed systems. The reclamation plan will maintain the function of biological systems of wetlands to be mined on-site by replacing the wetlands to be impacted with wetlands of the same type and similar topography and hydrology in the post-reclamation landscape. In many cases, it will enhance the function of those systems by improving the landscape position of the wetlands, relocating them closer to the preserved Little Charlie Creek corridor, and moving cattle ponds and pasture away from the corridor. Likewise, the existing streams proposed for mining will be replaced with stream reaches modeled on streams that are comparable or better than the existing, unstable, and eroded streams. The Department has determined that Mosaic can reclaim the streams and wetlands to at least as good as or better than existing condition on the site.

    109. Mosaic has provided reasonable assurances that the proposed reclamation plan will maintain or improve the existing function of biological systems. Mosaic's reclamation plan for the site therefore satisfies the mitigation requirements of Part

      IV, Chapter 373, Florida Statutes, and the implementing regulations and the BOR, as applied to phosphate mining activities through Section 373.414(6)(b), Florida Statutes.

    110. Through the testimony of witnesses Durbin, Kiefer, and Simpson, as well as documentary evidence, Mosaic has established that the proposed project, as reclaimed, will cause no adverse impacts on the value of functions provided to fish and wildlife and will not adversely affect the conservation of fish and wildlife, including endangered or threatened species and their habitats, as required by Section 373.414(1)(a)2., Florida Statutes, Florida Administrative Code Rules 40D- 4.301(1)(d) and 40D-4.301(1)(a)2., as well as the associated BOR Section 3.2.2 provisions. Likewise, the CRP criteria pertaining to fish and wildlife will be met. See Fla. Admin. Code R. 62C- 16.0051(11).

    111. Mosaic's reclamation and site habitat management plan will maintain or improve the functions of the biological systems on the site with respect to fish and wildlife, including threatened and endangered species and their habitat.

    112. Mosaic witness Simpson provided unrebutted testimony that the proposed mining and reclamation will not have adverse impacts on wildlife populations or conservation of wildlife including threatened or endangered species and their habitats

      and that proposed reclamation would maintain or improve wildlife habitat values.

    113. The evidence shows that the mining and reclamation will not have adverse impacts on fish populations or conservation of fish. The fish habitat on the site will either be preserved or, if mined, will be replaced with in many cases superior habitat. There will be a net increase in suitable fish habitat post-reclamation. The wetland and stream fish habitats on the site will provide appropriate habitat for the fish and wildlife that can be expected to occur in the region. The sampling described above can be expected to reflect the majority, if not all, of the fish species reasonably expected to be present on the site. Mosaic witness Durbin further confirmed that the fish species collected on-site are consistent with similar sites in the immediate vicinity with similar agricultural usage with which he is familiar. In August and September 2008, verification of that fish sampling effort was performed by Dr. Durbin, an outside consulting firm (ECT), and the Department. They confirmed that the fish collection efforts reasonably reflect the native and exotic fish species that are likely to occupy the site.

    114. Through the testimony of Dr. Fraser, Lee County compared two streams on the Ona mine site with three stream

      segments on the Project site. However, the sole basis of the witness' comparison was recollections of field work he participated in over four years ago and photos taken at that time compared with photos taken at the new site. The witness conceded that he did not consider or compare sedimentation levels in the two stream systems. On the other hand, Department witness Cantrell established that the streams compared by

      Dr. Fraser were dissimilar. In fact, one of the streams Dr. Fraser held up as an apparent example of prime aquatic habitat was Stream 20C, which Mr. Cantrell demonstrated is nearly completely choked by sand and sedimentation.

    115. All of the streams proposed for impact are first or second order streams; most of them are intermittent, carrying flow only seasonally and therefore are only periodically occupied by fish and macroinvertebrate communities. The fish that do tend to utilize such systems in the wet season tend to be very small, usually less than one inch in size. The proposed preservation will preserve the best aquatic habitat on the property; the streams to be preserved are the main pathways and aquatic habitats utilized by fish. Mosaic witnesses Durbin, Keenan, and Kiefer all testified that the reclamation plan will restore better aquatic habitat for fish and other aquatic organisms than exists presently on site on a greater than acre-

      for-acre, type-for-type and linear foot basis. They further testified that the proposed reclamation will provide better aquatic habitat for fish and wildlife than currently provided, consistent with both ERP and CRP requirements.

    116. In addition, Dr. Fraser's suggestion that the fish sampling done on the site was insufficient and that the ERP should be modified to require fish collection as a success criterion for the reclaimed streams is not credited. This is because such a proposal is not a requirement of the ERP or CRP rules. Dr. Fraser's comparisons of reclaimed to unmined streams were inconsistent with his own anecdotal fish observations, and he testified as to the difficulty of ensuring adequate fish sampling or knowing where fish will be on any given day, given their mobility. Also, he provided no comparisons as to how the reclaimed streams sampled are constructed compared to the plan for the site and admitted he did not know how or when they were built. Dr. Fraser's discussion of fish in basins where mining has occurred was discredited by his own data showing that no reduction in the number of native fish species has occurred over time in those basins.

    117. Mosaic's reclamation plan, which consolidates the native upland and wetland habitats along the Little Charlie Creek corridor, will improve the fish and wildlife function of

      those systems and increase fish and wildlife abundance and diversity, as set forth above.

    118. There will be no adverse impacts to fish and wildlife and their habitat or to the conservation of fish and wildlife, including listed species, post-reclamation, because the fish and wildlife function of the tract will be maintained and in many cases improved by the reclamation and habitat management plans. This is particularly true in light of the existing condition, hydrologic connection, location, and fish and wildlife utilization of the wetlands and surface waters on site. Therefore, Mosaic has provided reasonable assurances that the requirements of Section 373.414(1)(a)2., Florida Statutes, Florida Administrative Code Rules 40D-4.301(1)(d) and 40D- 4.302(1)(a)2., and the relevant BOR provisions have been satisfied.

    119. Mosaic demonstrated that it has reclaimed wetlands, uplands, and streams consistent with the regulatory requirements and permit conditions in place at the time the area was reclaimed. Indeed, many of these reclaimed areas, whether or not under different ownership and control or whether released from further regulatory requirements, continue to demonstrate that they are successful and functioning ecosystems.

    120. The reclamation proposed for the site is state-of- the-art, reflecting the most recent evolution of reclamation techniques for uplands, wetlands and streams, with more planning and detail that should achieve the reclamation goals faster.

    121. Many older wetland projects were designed to meet a

      +/- 1-foot contour and were designed with older generations of equipment and survey techniques. However, Mosaic's third party contractor's bulldozers/tractors are now equipped with GPS and sensors to enable grade tolerances within two inches, allowing for much more accurate backfilling and wetland construction.

      Accordingly, Mosaic's newer wetlands contain both deep and shallow areas with gradation/zonation in between. Hydrologic regimes and hydroperiods can thus be effectively created to target and achieve more specific hydrologic conditions required by certain wetland systems such as seepage slopes and wet prairies. Nonetheless, the projected UMAM scores for the reclaimed systems take into account a higher risk factor for systems that historically were more difficult to reclaim.

    122. Mosaic has provided reasonable assurances of its ability to restore the hydrology and types of vegetation found on the site and of its ability to create ecosystems that will maintain or improve the function of the biological systems proposed for mining on the site.

    123. Mosaic has restored wetlands in a variety of configurations ranging from small round depressions of less than

      a few acres to large complex polygons in excess of two hundred acres, as well as wetlands with low slope gradients. For example, Mr. Kiefer described and depicted Mosaic's ability to restore a bay swamp at point 84(5) at the Fort Green Mine and at Alderman Bay. Lee and Sarasota Counties focused on bay swamps in particular, but failed to acknowledge that Mosaic will be reclaiming 98.5 acres of bay swamps while only impacting 62.1 acres.

    124. Mosaic demonstrated that herbaceous and forested wetlands can be and have been restored by Mosaic and its predecessors.

    125. Mosaic has demonstrated that it can restore the various zones and depths of freshwater marshes, including shrub marshes, from the deep emergent zone to the wet prairie fringe, and has demonstrated that these zones in reclaimed marshes are providing important and key wetland functions, such as water quality, food chain support, habitat, and other functions, similar to those functions provided by site marshes. This evidence was not effectively rebutted by Lee or Sarasota Counties. In fact, Sarasota County witness Lipstein acknowledged Mosaic is proposing to mitigate for all impacts. When asked if the proposed bay swamps will be successful or

      unsuccessful, she replied that she did not know and, "you will have to just wait and see if it reaches that success criteria."

    126. There have been different success criteria applied in Department permits over the years, and Mosaic has demonstrated the ability to meet those changing and more stringent criteria.

    127. In the past, stream restoration was accomplished relatively simply by contouring the stream valley and floodplain to support wetland vegetation, then allowing a flow channel to self-organize. While this technique has resulted in successful streams that met Department permit criteria, it can take many years to occur. For example, Dogleg Branch (which is located on the site of another mining operation) took almost twenty years to achieve success.

    128. Mosaic has previously developed successful stream restoration projects which have been documented to provide flow regimes similar to that of natural flatwoods streams, with in- stream aquatic habitat diversity similar to or better than the stream segments proposed for mining at the site and which met reclamation criteria. Mosaic witness Kiefer demonstrated this with evidence of the functions that various reclaimed streams provided. He also showed that, in newer stream restoration projects, like Maron Run, certain functions and form, such as habitat availability, bank stability, meander, and pool-riffle

      sequence, are developing rapidly. Also, Department witness Rivera testified to Mosaic's commitment to achieving stream success in its efforts to retrofit certain of these earlier reclaimed streams to achieve greater function and habitat diversity.

    129. Using an average sinuosity of 1.35, over 65,700 linear feet of streams will be created as part of the mitigation plan. The foot-for-foot requirement for the reclaimed streams will be exceeded by 7,000 feet.

    130. Mosaic's mitigation proposal incorporates state-of- the-art stream restoration techniques and the post-reclamation topography to be used as guidance for the final construction plans. The guidance is based on extensive data collected from twenty-one cross sections of reference reaches within the project area, including measurements for channel dimensions, sinuosity, bankfull, and entrenchment ratios.

    131. Snags, debris, and other woody material will be placed at appropriate intervals within the channel to provide in-stream habitat and aid in-channel stabilization and development.

    132. Restored streams will have primarily forested riparian zones. Trees will be planted using techniques that will assist rapid canopy closure and aid in rapid bank

      stabilization. Biodegradable erosion control blankets will be used to control erosion.

    133. The streams will be designed such that the stream morphology fits within the Rosgen Stream Classification System (Rosgen) described in the reference reaches.

    134. To create a design template, Mosaic's experts carefully measured the important geomorphic characteristics of the stream segments to be disturbed. The plan incorporates, among other factors, design specifications for meander patterns, longitudinal valley and bed slopes, bank slopes, cross-sectional area, widths, depths, large woody debris, pools, riffles, bends, and sediment composition. It is the second known low-order stream creation plan in Florida to provide this level of detail.

    135. The stream plan represents an overall improvement upon the existing conditions at the site, as Mosaic is generally only mining small, shallow, intermittent stream segments of significantly lower ecological value and will create streams that are less erosive and will have greater in-stream habitat diversity and availability than the segments to be mined. Accordingly, the reclaimed streams segments will at least maintain and in many cases improve the ecological functions served by the existing segments.

    136. Special emphasis has been placed on assuring that post-reclamation soils are a suitable growing medium for the proposed reclaimed habitat. Soils will be used to closely mimic the native Florida soils profile.

    137. Mosaic witness Schuster established that proposed reclaimed soil conditions do not pose limitations on Mosaic's ability to create upland and wetland ecosystems.

    138. The soil reclamation plan uses parent materials available after mining in a sequence similar to the textural or horizon sequence in soils present at the site before mining. This soil profile will have a created topsoil layer as a suitable growing medium and subsurface layers whose thicknesses can be adjusted to achieve the drainage class, that is, hydraulic conductivity or permeability, that is needed to support the post-reclamation hydrology.

    139. The overburden used to form the lower part of the reclaimed soil sequence is native Florida soil and underlying geologic material. The overburden is excavated so that the matrix can be mined, but then the material is put back in the mined areas in a sequence that resembles native soil horizons.

    140. Where available, the top layer of the soil sequence will be a direct transfer of muck/topsoil pursuant to the permit conditions. Where donor topsoil is not available, other

      appropriate materials can be used if approved by the Department. Possible methods may include establishment of cover crops, green manuring, mulching, and sod placement, all of which have been demonstrated to provide organic matter and a suitable growing medium for reclaimed wetlands and will facilitate success of the wetlands. These methods comport with the requirements of Florida Administrative Code Rule 62C-16.0051(3).

    141. For reclamation, Mosaic will use various thicknesses of materials including sand tailings and overburden, depending on the area to be reclaimed and the needed hydraulic conductivity as dictated by the modeling that is required. Sand tailings will be utilized in native habitats. Sand tailings have a much higher rate of hydraulic conductivity than overburden, which is low, but not impermeable.

    142. Reclaimed soils behave similarly to native soils. On site development of soil morphology at reclaimed sites has occurred, including organic matter accumulation in the topsoil formation of redox concentrations, and other components of soil structure, which evidence that the same natural processes are present in both reclaimed and native soils. Lee County's witnesses incorrectly assumed an overburden cap that will not be present.

    143. Mosaic has provided appropriate cost estimates for financial assurances of reclamation and has satisfied the BOR requirements of providing third-party estimates and draft financial assurance documentation. The first three years of mitigation at one hundred ten percent is $3,957,356.00. This amount is determined to be sufficient. Lee and Sarasota Counties' witnesses could provide no contrary cost estimates of actual comparable large-scale projects. The proffered costs of Lee County witness Erwin were rejected in another mining case (the Ona case), they ignore the definitions of "waste" and "mining operations," and they assume mitigation requirements not found in the BOR.

    144. The evidence supports a finding that all adverse impacts, including any secondary impacts, associated with the Project will be temporary and will be offset by the proposed reclamation.

    145. All of the proposed impacts from the Project will occur within the Peace River Basin, and Mosaic's proposed mitigation will all occur within the Peace River Basin as well.

    146. Therefore, the cumulative impacts review requirements of Section 373.414(8)(a), Florida Statutes, and Florida Administrative Code Rule 40D-4.302(1)(b) are satisfied.

    147. The BMPs put into place will prevent adverse secondary impacts from occurring during mining, and no adverse secondary impacts are expected from the project post- reclamation. No secondary impacts to listed wildlife are reasonably expected to occur, based on the buffers and on the post-reclamation habitat that will exist. In summary, Mosaic has demonstrated by a preponderance of the evidence that the proposed project meets the permitting criteria of Florida Administrative Code Rule 40D-4.301 and associated BOR provisions.

    148. Florida Administrative Code Rule 40D-4.302(1)(a) requires reasonable assurances the proposed activities "will not be contrary to the public interest" as determined by balancing seven factors. See also § 373.414(1), Fla. Stat. For the reasons set forth below, the preponderance of evidence supports a finding that the public interest factors set forth in the statute and rule weigh in favor of issuing the permit.

    149. The Florida Legislature has recognized that phosphate mining "is important to the continued economic well-being of the state and to the needs of society." See § 378.202(1), Fla. Stat. Mosaic has demonstrated by a preponderance of evidence that both the public and the environment will benefit from the project as described above.

    150. Mining of the site will also result in a more general benefit to the public, including local residents. It is estimated that mining of the site will result in fifty million tons of recoverable phosphate rock reserves, which will be used to make fertilizer. Mosaic employs 272 people at its South Fort Meade facility and spends approximately $75,000.00 per employee per year for direct wages, benefits, and compensation. In addition, it has been estimated there are four to five persons employed in support industries for each direct Mosaic employee, considering contractors, vendors, and suppliers.

    151. The site project is expected to generate up to $23 million in severance taxes, tangible taxes, property taxes, and other benefits to Hardee County over the life of the mine.

    152. The evidence shows that the proposed activities will not cause adverse impacts to the public health, safety, or welfare or to the property of others. Fla. Admin. Code R. 40D- 302(1)(a)1. Witness Burleson established that the water quantity criteria in BOR Chapter 4 have been satisfied and that no flooding problems will occur.

    153. No environmental hazards or public health and safety issues have been identified. Section 373.414(1)(a)1., Florida Statutes, Florida Administrative Code Rule 40D-4.302(1)(a)1., and BOR Section 3.2.3.1 have accordingly been satisfied.

    154. The evidence established that the proposed mining and reclamation will not cause adverse impacts to the conservation of fish and wildlife or their habitat, including endangered or threatened species, satisfying Florida Administrative Code Rule 40D-4.302(1)(a)2. and BOR Sections 3.2.2, 3.2.2.3, and 3.2.3.2.

    155. The evidence shows that the proposed activities will not cause adverse impacts to navigation or flow and will not cause harmful erosion or shoaling. Fla. Admin. Code R. 40D- 4.302(1)(a)3.

    156. The evidence shows that the proposed activities will not cause adverse impacts to fishing or recreation or marine productivity, and the lakes will enhance fishing and recreation. Fla. Admin. Code R. 40D-4.302(1)(a)4.

    157. As a matter of law, Section 378.202(1), Florida Statutes, provides that phosphate mining is a temporary activity. Fla. Admin. Code R. 40D-4.302(1)(a)5.

    158. The parties have stipulated that there will be no adverse impacts on historical or archaeological resources. Fla. Admin. Code R. 40D-4.302(1)(a)6.

    159. The evidence shows that the current condition and relative value of functions of the site landscape have been significantly affected over time by agricultural activities, causing alteration of natural streams and wetlands and low fish

      and wildlife utilization. A preponderance of the evidence established that these negative impacts will be ameliorated by the proposed reclamation. Fla. Admin. Code R. 40D-4.302(1)(a)7.

    160. In light of the above, Mosaic has provided reasonable assurances that Section 373.414(1)(a), Florida Statutes, Florida Administrative Code Rule 40D-4.302(1)(a), and associated BOR requirements for the public interest test have been satisfied, and those criteria weigh in favor of issuing the permit.

    161. Section 373.414(6)(b), Florida Statutes, establishes the appropriate mitigation for wetland and surface water impacts associated with phosphate mines as follows: "Wetlands reclamation activities for phosphate and heavy minerals mining undertaken pursuant to chapter 378 shall be considered appropriate mitigation for this part if they maintain or improve the water quality and the function of the biological systems present at the site prior to the commencement of mining activities." Part III of Chapter 378, Florida Statutes, addresses phosphate land reclamation, and the Department has adopted specific regulations pursuant to this part, which are found in Florida Administrative Code Rule 62C-16.0051.

    162. For the reasons set forth below, Mosaic has demonstrated by a preponderance of the evidence that the

      reclamation and restoration standards in Florida Administrative Code Rule 62C-16.0051 have been met.

    163. The parties stipulated the Project will meet the safety standards in subsection (1) of the rule. Any temporary structures will be removed following mining and the area then reclaimed. Appropriate BMPs will also be installed.

    164. The Project will meet the backfilling and contouring requirements of subsection (2). Specifically, the evidence shows that the area will be backfilled and contoured to achieve the desired landforms; slopes will be no steeper than a 4:1 ratio; bank stabilization techniques will be used; and post- reclamation contouring and topography will help ensure that the reclamation plan and hydrologic response is successful.

    165. The reclamation will meet the requirement in subsection (3) that Mosaic use good quality topsoil when available and other suitable growing media to achieve the planned vegetative communities.

    166. The Project will meet the acre-for-acre requirement for wetlands because more acres of wetlands and surface waters are being proposed to be restored than will be impacted.

    167. The Department uses FLUCCS Category II to determine whether the minimum type-for-type requirement is met. Thus, the type-for-type requirement is met by looking at the forested

      wetlands acreage overall and the herbaceous wetlands acreage overall. Subsection (4) has been satisfied by the proposed CRP.

    168. While the herbaceous wetland fringe of the lakes is included in the acre-for-acre, type-for-type calculation, the open waters of the lake are not. The Project will meet the type-for-type requirement in the rule because, category-by- category, type-for-type, more than a 1:1 ratio of forested and herbaceous wetlands are being restored.

    169. As noted above, the wetlands and streams were mapped during the application process in accordance with the directives of the Department and the requirements of subsection (4).

    170. Where wetlands are directly associated with or adjacent to streams, restoration of both is integrated and included in the restoration plan. Non-wetland and wetland floodplains will be restored as directed by the Department in accordance with this rule. No natural lakes or ponds exist on site, thus the portion of this rule related to natural lakes does not apply.

    171. All natural streams proposed for impact will be restored foot-for-foot based on Rosgen Level II. More stream linear feet (65,700 feet) are being replaced than are being mined (58,769 feet). Therefore, the requirements of subsection

      (5) have been met.

    172. Subsection (6) has been satisfied after accounting for the Littoral Zone Variance described below authorized by Florida Administrative Code Rule 62C-16.0051(13). The design of the reclaimed wetlands and lakes will maximize beneficial drainage, provide fish and wildlife habitat, maintain downstream water quality, and incorporate a variety of vegetation and hydraulic zones. Greenbelts of vegetation are incorporated.

    173. Subsection (7) has been satisfied. There will be no water quality concerns either during mining or post-reclamation with the reclaimed streams, lakes, wetlands or other surface waters.

    174. Subsection (8) has been met; the Project is not expected to cause flooding, and the original drainage pattern will be restored to the extent possible.

    175. Subsection (9) has been satisfied with respect to waste disposal. Areas used for clay settling will be minimized, and only three CSAs are proposed for the site, as fifty percent of the clays generated at the site will be disposed of in previously-permitted CSAs in Polk County. Backfilling of mine cuts is the highest priority use for the site's sand tailings. No tailings will be sold. The evidence showed that sand tailings will not be permanently stored above natural grade, although temporary stock piles are authorized to facilitate

      reclamation. Reclamation of CSAs will occur as expeditiously as possible. Solid waste was not an issue in this proceeding.

    176. The revegetation proposed for the Project will succeed to achieve permanent revegetation and meets the requirements of subsection (10). Mosaic has submitted a plan for revegetation that lists species by species what will be replaced through planting or seeding into each of the different types of wetlands. The revegetation plan and planting tables provide clear guidance to the entire reclamation plan and will minimize erosion, conceal the effects of mining, and recognize the requirements for fish and wildlife habitat.

    177. Upland cover and forested upland requirements in the rule will be met under the CRP; the appropriate forested densities are set forth in the CRP and can reasonably be expected to be established within one year.

    178. Likewise, the wetland vegetative cover requirements in the CRP meet the rule requirements and can be easily met. As set forth above, the wetlands to be created are of the types Mosaic has successfully recreated in the past, and advances in reclamation and maintenance techniques will further ensure the vegetation plan is successfully implemented. The vegetative plans, including the stream plan, provide appropriate habitat for fish and wildlife.

    179. The best available technologies will be used to restore and revegetate wetlands.

    180. Furthermore, the vegetation plan meets and exceeds the requirements for the use of indigenous species. Native plants and grasses will be used in all native habitats.

    181. As required by subsection (11), measures have been identified and incorporated into the CRP to offset fish and wildlife values lost as a result of mining operations. Special programs to restore and/or reclaim particular habitats, especially for endangered and threatened species have been identified. A Site Habitat Management Plan has been incorporated to prevent adverse impacts to threatened and endangered species, and the proposed conservation easement and reclamation plan will protect and restore currently impaired habitat to a better condition. Specifically, Dr. Durbin testified with respect to the CRP requirements for aquatic species, including fish and macroinvertebrates; the best fish and wildlife habitat onsite will be preserved.

    182. Mr. Simpson testified regarding habitat preservation and reclamation activities, the proposed wildlife management plans, and the proposed enhancements to habitat that will benefit wildlife, including listed wildlife.

    183. Mosaic has sufficiently addressed the requirements of subsection (11) of the rule in the CRP.

    184. Subsection (12) has been satisfied. The proposed mining and reclamation schedule in the application documents comports with the rule requirements by including time schedules for mining, waste disposal, contouring, and revegetation, and the completion dates for such activities comport with the rules.

    185. Mosaic has proposed, and the DEP has indicated an intent to issue, the Littoral Zone Variance as an experimental technique to improve the quality of the reclaimed lakes pursuant to this subsection and Section 378.212(1)(e), Florida Statutes.

    186. Given the depth of the proposed reclamation lakes, Mosaic applied for, and the Department has proposed to grant, a variance from the water quality standard for DO in the lower portions of the lakes. The DO Variance from Florida Administrative Code Rule 62-302.530(31) is being sought pursuant to Sections 373.414(6)(a), 373.414(17), and 403.201(1)(a), Florida Statutes, which provide the minimum standards for DO levels in surface waters.

    187. Class III freshwater water quality standards apply to those portions of the site that constitute surface waters as defined by Florida law. For at least those reclaimed lakes that will connect offsite to downstream waters or wetlands (Lakes 1,

      3, and 4), there is no dispute that Class III water quality standards would apply. The minimum water quality standard for DO in freshwater systems is 5.0 milligrams per Litre (mg/L).

    188. The evidence demonstrated that alternatives to the lakes in terms of both size and location were considered. The Department considered the proposed lakes as part of the elimination and reduction of overall wetland impacts on both South Fort Meade Polk and Hardee. On balance, it is a preferable alternative to use the available sand resulting from mining of the Hardee County portion of the South Fort Meade mine to eliminate lakes and create additional wetlands on the Polk County portion of the mine rather than utilize that sand to eliminate all lakes on the Hardee County portion of the site. This is especially true given the desire of Hardee County for recreational lakes and the Department's preference to reduce the overall acreage of the reclaimed lakes at the South Fort Meade mine. It is not feasible to make the lakes shallower given the available materials.

    189. There is no practicable means known or available for increasing DO in the deep pockets of lakes of the proposed depths that would not have a potential negative effect. This fact has been established and recognized by the Florida Legislature in Section 373.414(6)(a), Florida Statutes, which

      provides that the deep pits left by mining operations may not meet the DO criteria below the surficial layers of the lakes. The Legislature has further provided that a variance from the DO standard can be issued where deep lakes must be left as part of the reclamation plan. Id.

    190. The evidence established that lower DO levels may at times occur in the deep pockets of some of the reclaimed lakes to the same extent and effect as those lower levels occur in natural lakes of similar depths. This effect will occur only in the hypolimnion, or lower levels, of the lakes in the hotter summer months. The evidence likewise established that it is very unlikely that DO levels below 1.0 mg/L will occur at any time in any of the proposed reclaimed lakes. Provided the DO levels do not drop below 1.0 mg/L for any extended period of time, the only expected effect of the occasional seasonal reduction in DO in the lowest level of the reclaimed lakes will be to temporarily exclude fish from those lower portions of the lake during the summer months, which is also true of natural deep lakes. The evidence established that reclaimed lakes function well and provide habitat for fish and wildlife. Water quality standards will be met in all of the lakes other than occasional seasonal DO violations in the lower portions of the

      deepest lake. All water quality standards, including DO, will be met at all lake outlets and discharge points.

    191. All other applicable regulatory criteria will be met in the reclaimed lakes. Dissolved oxygen levels in the upper layers of the lakes are expected and required to meet the minimum DO criteria in Florida Administrative Code Rule 62-

      302.530 and will be adequate to support healthy fish populations. The evidence showed no downstream impacts will occur due to the DO Variance for the lakes.

    192. The evidence showed reclaimed lakes support healthy fish and macroinvertebrate communities and provide recreational fishing opportunities. Even older lakes, such as the Tenoroc lakes (located in an old mining area in Polk County), provide substantial recreational fishing and wildlife utilization opportunities. This testimony was not rebutted.

    193. The evidence offered by Lee and Sarasota Counties as a means to increase DO levels in the reclaimed lakes actually demonstrated that artificially attempting aeration of a deeper lake can have negative environmental effects. Therefore, the testimony of witnesses Janicki and Merriam has not been credited. By a preponderance of the evidence, Mosaic proved entitlement to the DO Variance for the lakes pursuant to Sections 373.414(6)(a) and 403.201(1)(a), Florida Statutes.

    194. Given the location of the reclaimed lakes and as a means of experimenting with different reclamation planting techniques to create a variety of shorelines, Mosaic also applied for, and the Department has proposed to grant, a variance from the reclamation requirements in Florida Administrative Code Rule 62C-16.0051 pertaining to the planting of littoral shelves or zones around reclaimed lakes. The Littoral Zone Variance is being sought under Section 378.212(1)(e), Florida Statutes, from Florida Administrative Code Rule 62C-16.0051(6)(a) and (b), which provides minimum water zones for emergent and submerged vegetation, known as the littoral zones of the lakes.

    195. Subsection (6) of the rule provides for a twenty-five percent high-water zone of water fluctuation to encourage emergent and transition zone vegetation, and that a twenty percent low water zone between the annual low water line and six feet below the annual low water line to provide fish bedding areas and submerged vegetation zones. These vegetative zones are collectively known as the littoral zone of a lake. Traditionally, these percentages have been met in reclaimed lakes by sloping and creation of a uniform fringe of herbaceous wetland vegetation completely encircling the lake; however, such uniform fringes are not typical around natural lakes, which vary

      in composition and width. Rather than create a uniform band of vegetation around the lakes, Mosaic has proposed to reclaim the littoral zones around the reclaimed lakes by concentrating them in several broad, shallow areas, including the outlets of the lakes where such outlets occur (Lakes 1, 3 and 4). Of the proposed lakes, one will meet the littoral zone requirement, two will have over twenty percent of the total area in littoral zone, and the remaining lake will have a littoral zone of just under fourteen percent of the total area.

    196. The littoral zones will be reclaimed by constructing broad shelves of differing depths and planting the shelves with herbaceous wetland plant species. This design provides the environmental benefit of herbaceous vegetation at the outlet to provide increased filtration of nutrients or sediments of any water overflowing from the lakes during other high water events. This increases environmental benefits at the outlet of the lakes and has the potential to improve water quality downstream. Further, the proposed clustering of the littoral zones in several broad shallow shelves, rather than creation of a thin fringe around the lakes as is customary, will benefit wildlife and fish by creating a more extensive wetland ecosystem in lieu of the monoculture typically created by the thin littoral fringe. The proposed littoral zone clustering also creates more

      useable shoreline for boating, fishing, and recreational activities in the areas where the littoral zones are not clustered, with the added benefit of tending to separate the wildlife usage in the littoral zone clusters from the human usage in the upland forested areas of the shoreline where minimal littoral zones are planned. This is an experimental technique that advances reclamation methods by balancing habitat, water quality, and recreational considerations.

    197. Mosaic has demonstrated that the Littoral Zone Variance comports with Section 378.212(1)(e), Florida Statutes, and may be issued.

      CONCLUSIONS OF LAW


    198. The Division of Administrative Hearings has jurisdiction over the subject matter of and the parties to this proceeding pursuant to Sections 120.569, 120.57(1), and 120.574, Florida Statutes.

    199. Section 403.412(5), Florida Statutes, provides automatic standing to political subdivisions of the state that file a verified pleading asserting that the activity to be permitted has or will have the effect of impairing, polluting, or otherwise injuring the air, water, or other natural resources of the state. Lee and Sarasota Counties have satisfied this requirement and have standing in this proceeding.

    200. As the applicant, Mosaic has the burden of showing by preponderance of the credible and credited evidence that it is entitled to the approvals at issue here. See Department of Transportation v. J.W.C. Company, Inc., et al., 396 So. 2d 778, 789 (Fla. 1st DCA 1981). By a preponderance of the evidence, Mosaic has established its entitlement to the requested approvals. While Lee and Sarasota Counties offered conflicting evidence regarding many of the findings which support this conclusion, the more credible and persuasive evidence was accepted in favor of Mosaic and the Department. Therefore, the applications for the ERP, CRP, and two Variances should be approved.

RECOMMENDATION


Based on the foregoing Findings of Fact and Conclusions of Law, it is

RECOMMENDED that the Department of Environmental Protection enter a final order granting Mosaic's applications for the requested permits and variances.

DONE AND ENTERED this 18th day of December, 2008, in Tallahassee, Leon County, Florida.

S

DONALD R. ALEXANDER

Administrative Law Judge

Division of Administrative Hearings The DeSoto Building

1230 Apalachee Parkway

Tallahassee, Florida 32399-3060

(850) 488-9675 SUNCOM 278-9675

Fax Filing (850) 921-6847 www.doah.state.fl.us


Filed with the Clerk of the Division of Administrative Hearings this 18th day of December, 2008.


ENDNOTE


1/ All references are to the 2008 version of the Florida Statutes.


COPIES FURNISHED:


Lea Crandall, Clerk

Department of Environmental Protection 3900 Commonwealth Boulevard

Mail Station

Tallahassee, Florida 32399-3000


Edward P. de la Parte, Esquire De la Parte & Gilbert, P.A. Post Office Box 2350

Tampa, Florida 33601-2350


David M. Pearce, Esquire Assistant County Attorney

1660 Ringling Boulevard, Second Floor Sarasota, Florida 34236-6808

Frank E. Matthews, Esquire Hopping Green & Sams, P.A. Post Office Box 6526

Tallahassee, Florida 32314-6526


Roger W. Sims, Esquire Holland & Knight LLP Post Office Box 1526

Tallahassee, Florida 32802-1526


David Weinstein, Esquire Greenberg Traurig, P.A.

625 East Twiggs Street, Suite 100

Tampa, Florida 33602-3925


Justin G. Wolfe, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

Mail Station 35

Tallahassee, Florida 32399-3000


Thomas M. Beason, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard

Mail Station 35

Tallahassee, Florida 32399-3000


NOTICE OF RIGHT TO SUBMIT EXCEPTIONS


All parties have the right to submit written exceptions within 15 days of the date of this Recommended Order. Any exceptions to this Recommended Order should be filed with the agency that will render a final order in this matter.


Docket for Case No: 08-003887
Issue Date Proceedings
Feb. 03, 2009 Final Order filed.
Feb. 03, 2009 Lee County`s Exceptions to Recommended Order filed.
Feb. 03, 2009 Sarasota County`s Exceptions to Recommended Order filed.
Feb. 03, 2009 Mosaic Fertilizer LLC`s Response to Petitioner`s and Intervenor`s Exceptions to Recommended Order filed.
Feb. 03, 2009 Respondent Department of Environmental Protection`s Response to Lee and Sarasota County`s Exceptions to Recommended Order filed.
Dec. 18, 2008 Recommended Order cover letter identifying the hearing record referred to the Agency.
Dec. 18, 2008 Recommended Order (hearing held November 3-7, 10-14 and 17, 2008). CASE CLOSED.
Dec. 10, 2008 Lee County`s Response to Mosaic`s Motion to Strike Extraneous Hearing Testimony and Exhibits from Lee County`s Proposed Recommended Order filed.
Dec. 08, 2008 Letter to Judge Alexander from J. Wolfe enclosing Exhibit No. 9 (exhibit not available for viewing) filed.
Dec. 04, 2008 Mosaic Fertilizer LLC`s Motion to Strike Extraneous Hearing Testimony and Exhibits from Lee County`s Proposed Recommended Order filed.
Dec. 04, 2008 Lee County`s Proposed Recommended Order filed (bound copy).
Dec. 04, 2008 Sarasota County`s Proposed Recommended Order filed (bound copy).
Dec. 03, 2008 Department of Environmental Protection`s Proposed Recommended Order filed.
Dec. 03, 2008 Mosaic`s Proposed Recommended Order (bound copy) filed.
Dec. 03, 2008 Lee County`s Proposed Recommended Order filed.
Dec. 03, 2008 Sarasota County`s Proposed Recommended Order filed.
Nov. 26, 2008 Order (Joint Motion for Leave to Expand Page Limit of Proposed Recommended Order is denied).
Nov. 25, 2008 Mosaic Fertilizer LLC`s Response to Joint Motion for Leave to Expand Page Limit of Proposed Recommended Order filed.
Nov. 25, 2008 Joint Motion for Leave to Expand Page Limit of Proposed Recommended Order filed.
Nov. 24, 2008 Order (request to establish a uniform outline for all filings is hereby denied).
Nov. 21, 2008 Lee County`s Notice Concerning Page Limit for Propsed Recommended Orders filed.
Nov. 21, 2008 Mosaic Fertilizer, LLC`s Response to Lee County`s and Sarasota County`s Joint Emergency Motion for Uniform Outline for Proposed Recommended Orders filed.
Nov. 20, 2008 Lee County`s and Sarasota County`s Joint Emergency Motion for Uniform Outline for Proposed Recommended Orders filed.
Nov. 20, 2008 Notice of Filing Transcript Corrections (Volume XIV, pages 1883-1888) filed.
Nov. 20, 2008 Notice of Filing Transcript Corrections (Volume III, page 383, line 12) filed.
Nov. 18, 2008 Transcript of Proceedings (Volumes I-XX) filed.
Nov. 12, 2008 Mosaic Fertilizer, LLC`s Motion in Limine to Exclude Ralph Montgomery as a Witness filed.
Nov. 10, 2008 CASE STATUS: Hearing Held.
Nov. 03, 2008 CASE STATUS: Hearing Partially Held; continued to November 10, 2008; 9:00 a.m., Tallahassee, FL.
Nov. 03, 2008 Mosaic Fertilizer, LLC`s Response to Emergency Motion to Exclude Mosaic`s Hudrological Model or for Alternative Relief filed.
Nov. 03, 2008 Mosaic Supplemental Filing to Pre-Hearing Stipulation Listing Objections to Final Witness and Exhibit Lists filed.
Nov. 03, 2008 Mosaic Supplemental Filing to Pre-hearing Stipulation Listing Objections to Final Witness and Exhibit Lists filed.
Nov. 03, 2008 Notice of Filing Exhibits to Mosaic Fertilizer, LLC`s Response to Emergency Motion to Exclude Mosaic`s Hydrological Model or for Alternative Relief filed.
Oct. 31, 2008 Lee County`s and Sarasota County`s Joint Notice of Filing Objections to Final Witness List and Final Exhibit List filed.
Oct. 31, 2008 Mosaic Fertilizer LLC`s Response to Emergency Motion to Exclude Mosaic`s Hydrological Model or for Alternate Relief filed.
Oct. 30, 2008 Respondent Mosaic Fertilizer LLC`s Supplemental Final Exhibit List filed.
Oct. 30, 2008 Joint Prehearing Stipulation filed.
Oct. 30, 2008 Department of Environmental Protection`s Final Witness and Final Exhibit List filed.
Oct. 30, 2008 Department of Environmental Protection`s Amended Final Witness List and Final Exhibit List filed.
Oct. 29, 2008 Lee County`s Final Exhibit List filed.
Oct. 29, 2008 Lee County`s Final Witness List filed.
Oct. 29, 2008 Department of Environmental Protection`s Final Witness List and Final Exhibit List filed.
Oct. 29, 2008 Sarasota County`s Final Exhibit List filed.
Oct. 29, 2008 Lee County`s Emergency Motion to Exclude Mosaic`s New Hydrologic Modeling or for Alternative Relief filed.
Oct. 29, 2008 Sarasota County`s Final Witness List filed.
Oct. 29, 2008 Letter to Clerk from H. Kreher enclosing cd containing Lee County`s Motion for Official Recognition filed.
Oct. 27, 2008 Notice of Appearance of Additional Counsel for Respondent, Mosaic Fertilizer, LLC filed.
Oct. 24, 2008 Lee County`s Motion for Official Recognition filed.
Oct. 24, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Reclaimed Site Inspection filed.
Oct. 24, 2008 Lee County`s Notice of Filing Original Acknowledgements filed.
Oct. 23, 2008 Mosaic Fertilizer LLC`s Notice of Continued Deposition Duces Tecum of Dr. Anthony Janicki, PH.D filed.
Oct. 22, 2008 Order Granting Unopposed Motion for Protective Order.
Oct. 20, 2008 Lee County`s Response in Opposition to Mosaic`s Request for Official Recognition of Legal Presumption of Section 373.414(8)(b), Florida Statutes, Regarding Cumulative Impacts filed.
Oct. 20, 2008 Lee County`s Response in Opposition to Mosaic`s "Request for Official Recognition of Legal Presumption of Section 373.414(8)(b), Florida Statutes, Regarding Cumulative Impacts" filed.
Oct. 20, 2008 Mosaic Fertilizer, LLC`s Unopposed Motion for Protective Order on Copying and Use of Mosaic`s Electronic Data filed.
Oct. 17, 2008 Order Approving Joint Stipulation and Protective Order.
Oct. 16, 2008 Lee County`s Notice of Withdrawing its Emergency Motion to Compel Electronic Copies of Pekas`s DVDs and Other Information, to Exclude Expert Testimony, to Waive or Modify Lee County`s Deadline to Finalize Expert Opinions, and/or for Other Sanctions and Relief filed.
Oct. 15, 2008 (Proposed) Order Approving Joint Stipulation and Protective Order filed.
Oct. 15, 2008 Respondent Mosaic Fertilizer, LLC`s Responses to Sarasota County`s First Request for Production to Mosaic filed.
Oct. 15, 2008 Joint Stipulation as to Production of Selected Mosaic GIS Coverages and Other Databases and Proposed Protective Order filed.
Oct. 15, 2008 Mosaic Fertilizer LLC`s Amended Notice of Taking Depositions Duces Tecum of Kevin Erwin filed.
Oct. 14, 2008 Mosaic Fertilizer LLC`s Notice of Taking Deposition Duces Tecum of Mike Jones filed.
Oct. 14, 2008 Sarasota County`s Response to "Respondent Mosaic Fertilizer, L.L.C. Reques for Official Recognition of Legal Presumption of Section 373.414(8)(b), Florida Statues, Regarding Cumulative Impacts" filed.
Oct. 14, 2008 Lee County`s Emergency Motion to Compel Electronic Copies of Pekas`s DVDs and Other Information, to Exclude Expert Testimony, to Waive or Modify Lee County`s Deadline to Finalize Expert Opinions, and/or for Other Sanctions and Relief filed.
Oct. 14, 2008 Intervenor, Sarasota County`s Response to Respondent, Mosaic Fertilizer, LLC`s First Request for Production of Documents filed.
Oct. 13, 2008 Lee County`s Emergency Motion to Compel Electronic Copies of Pekas`s DVDs and Other Information, to Exclude Expert Testimony, to Waive or Modify Lee County`s Deadline to Finalize Expert Opinions, and/or for Other Sanctions and Relief filed.
Oct. 13, 2008 Lee County`s Emergency Motion to Compel Electronic Copies of Pekas`s DVDs and Other Information, to Exclude Expert Testimony, to Waive or Modify Lee County`s Deadline to Finalize Expert Opinions, and/or for Other Sanctions and Relief filed.
Oct. 13, 2008 Lee County`s Emergency Motion to Compel Electronic Copies of Pekas`s DVDs and Other Information, to Exclude Expert Testimony, to Waive or Modify Lee County`s Deadline to Finalize Expert Opinions, and/or for Other Sanctions and Relief filed.
Oct. 13, 2008 Intervenor, Sarasota County`s Notice of Serving Responses to Respondent, Mosaic Fertilizer, LLC`s First Set of Interrogatories filed.
Oct. 13, 2008 Respondent Mosaic Fertilizer, LLC Request for Official Recognition of Legal Presumption of Section 373.414(8)(B), Florida Statues, Regarding Cumulative Impacts filed.
Oct. 13, 2008 Order Denying Motion to Compel.
Oct. 10, 2008 Mosaic Fertilizer LLC`s Amended Notice of Taking Deposition Duces Tecum of Cathleen Jonas filed.
Oct. 10, 2008 Order Approving Joint Stipulation and Protective Order.
Oct. 10, 2008 Order on Motions (Emergency Motion for Protective Order is denied; Motion for Notification of and Leave to Attend Future Site Visits is granted in part).
Oct. 09, 2008 Joint Stipulation as to Production of Selected Mosaic GIS Coverages and Other Databases and Proposed Protective Order filed.
Oct. 08, 2008 Respondent Mosaic Fertilizer, LLC`s Response to Lee County`s Emergency Motion for Protective Order filed.
Oct. 08, 2008 Mosaic Fertilizer LLC`s Response to Lee County`s Motion for Notification of and Leave to Attend Future Site Visits filed.
Oct. 08, 2008 Mosaic Fertilizer, LLC`s Response in Opposition to Lee County`s Motion to Compel to Permit Copying of Mosaic`s Electronically Stored Data filed.
Oct. 08, 2008 Order Denying Emergency Motion.
Oct. 07, 2008 Mosaic Fertilizer LLC`s Amended Notice of Taking Depositions Duces Tecum for Lee County filed.
Oct. 07, 2008 Lee County`s Emergency Motion for Protective Order filed.
Oct. 07, 2008 Lee County`s Motion for Notification of and Leave to Attend Future Site Visits filed.
Oct. 07, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Emergency Motion to Compel Discovery filed.
Oct. 07, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Emergency Motion to Compel Discovery filed.
Oct. 07, 2008 Lee County`s Second Amended Notice of Taking Deposition Duces Tecum of Boote, Burleson, Pekas, Durbin and Kiefer filed.
Oct. 06, 2008 Mosaic Fertilizer LLC`s Notice of Taking Depositions Duces Tecum for Sarasota County filed.
Oct. 06, 2008 Mosaic Fertilizer LLC`s Notice of Taking Depositions Duces Tecum for Lee County filed.
Oct. 06, 2008 Mosaic Fertilizer LLC`s Notice of Taking Depositions Duces Tecum of Kevin Erwin filed.
Oct. 06, 2008 Sarasota County`s Emergency Motion to Compel Discovery filed.
Oct. 06, 2008 Respondent Mosaic Fertilizer, LLC`s Amended Notice of Site Inspection and Response to Sarasota County`s Request for Site Inspection filed.
Oct. 06, 2008 Lee County`s Amended Notice of Taking Deposition Duces Tecum of Boote, Burleson, Pekas, Durbin and Kiefer filed.
Oct. 02, 2008 Lee County`s Motion to Compel to Permit Copying of Mosaic`s Electronically Stored Data filed.
Oct. 02, 2008 Order (Mosaic Fertilizer, LLC`s Motion for Reconsideration of Order Denying Mosaic`s Motion to Disqualify de la Parte & Gilbert is denied).
Oct. 01, 2008 Sarasota County`s First Request for Production to Respondent, Mosaic Fertilizer, LLC filed.
Oct. 01, 2008 Sarasota County`s Request for Site Inspection filed.
Oct. 01, 2008 Sarasota County`s Preliminary Witness List filed.
Oct. 01, 2008 Sarasota County`s Preliminary Exhibit List filed.
Oct. 01, 2008 Lee County`s Notice of Taking Deposition Duces Tecum of Boote, Burleson, Pekas, Durbin and Kiefer filed.
Oct. 01, 2008 Lee County`s Notice of Taking Deposition Duces Tecum of Boote, Burleson, Pekas, Durbin and Kiefer filed.
Oct. 01, 2008 Order (Mosaic Fertilizer, LLC`s Motion for Protective Order and Memorandum of Law is granted).
Sep. 30, 2008 Lee County`s Response to Mosaic`s Motion for Protective Order filed.
Sep. 29, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Site Inspection by Lee County filed.
Sep. 29, 2008 Order (parties are directed to confer and agree upon a mutually-acceptable time during the first week of the hearing to depose the witness).
Sep. 29, 2008 Lee County`s Preliminary Exhibit List filed.
Sep. 26, 2008 Lee County`s Preliminary Witness List filed.
Sep. 26, 2008 Resondent Mosaic Fertilizer, LLC`s Notice of Filing First Set of Interrogatories to Intervenor filed.
Sep. 26, 2008 Respondent Mosaic Fertilizer, LLC`s First Request for Production of Documents to Intervenor Sarasota filed.
Sep. 26, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Filing Amended Attachment "B" to Mosaic`s Response to Lee County`s First Set of Interrogatories filed.
Sep. 26, 2008 Presondent Mosaic Fertilizer, LLC`s Notice of Serving List of Proposed Witnesses and Documetary Exhibits filed.
Sep. 26, 2008 Lee County`s Preliminary Witness List filed.
Sep. 26, 2008 Department of Environmental Protection`s Proposed Witness and Exhibit List filed.
Sep. 26, 2008 Notice of Appearance of Additional Counsel for Respondent, Department of Environmental Protection filed.
Sep. 26, 2008 Lee County`s Notice of Taking Deposition Duces Tecum of John Coates, Richard Cantrell, Christine Keenan and Greg Henderson filed.
Sep. 26, 2008 Lee County`s Notice of Taking Deposition Duces Tecum of John Coates, Richard Cantrell, Christine Keenan and Greg Henderson filed.
Sep. 26, 2008 Lee County`s Response to Mosaic`s Motion for Reconsideration of Mosaic`s Motion to Disqualify de la Parte & Gilbert filed.
Sep. 25, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Inspection and/or Copying of Requested Documents filed.
Sep. 24, 2008 Motion for Reconsideration of Order Denying Mosaic`s Motion to Disqualify De La Parte & Gilbert filed.
Sep. 24, 2008 Order (granting Sarasota County`s Petition to Intervene).
Sep. 24, 2008 Mosaic Fertilizer LLC`s Response to Lee County`s Motion to Amend Order on Pre-hearing Instructions Due to Unavailability of Kevin Erwin and Motion to Exclude Testimony filed.
Sep. 24, 2008 Letter to Judge Alexander from S. Stephens enclosing case documents (documents not available for viewing) filed.
Sep. 24, 2008 Mosaic Fertilizer LLc`s Response to Lee County`s First Set of Interrogatories filed.
Sep. 24, 2008 Notice of Filing Mosaic Fertilizer LLC`s Response to Lee County`s First Set of Interrogatories filed.
Sep. 24, 2008 Lee County`s Motion to Amend Order on Pre-hearing Instructions Due to Unavailability of Kevin Erwin filed.
Sep. 24, 2008 Lee County`s Response to Mosaic`s First Requests for Admission filed.
Sep. 24, 2008 Lee County`s Response to Mosaic`s First Request for Production of Documents filed.
Sep. 24, 2008 Lee County`s Notice of Serving Response to FDEP`s First Set of Interrogatories filed.
Sep. 24, 2008 Lee County`s Notice of Serving Response to Mosaic`s First Set of Interrogatories filed.
Sep. 23, 2008 Respondent Mosaic Fertilizer, LLC`s Motion for Protective Order and Memorandum of Law filed.
Sep. 23, 2008 Respondent Mosaic Fertilizer, LLC`s Responses to Lee County`s First Request for Production to Mosaic filed.
Sep. 23, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Filing Response to Lee County`s First Set of Interrogatories filed.
Sep. 23, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Filing Response to Lee County`s First Set of Interrogatories filed.
Sep. 23, 2008 Department of Environmental Protection`s Response to Lee County`s First Request for Production filed.
Sep. 23, 2008 Notice and Certificate of Service of Respondent Department of Environmental Protection`s Answers to Lee County`s First Set of Interrogatories filed.
Sep. 23, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Petition to Intervene filed.
Sep. 23, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Petition to Intervene filed.
Sep. 23, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Petition to Intervene filed.
Sep. 23, 2008 Mosaic Fertilizer LLC`s Response to Sarasota County`s Petition to Intervene filed.
Sep. 22, 2008 Order (denying Motion to Disqualify de la Parte & Gilbert, P.A.).
Sep. 18, 2008 Lee County`s Request for Site Inspection filed.
Sep. 17, 2008 Sarasota County`s Petition to Intervene filed.
Sep. 15, 2008 Lee County`s Response in Opposition to Mosaic`s Motion for Leave to Reply to Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel filed.
Sep. 15, 2008 Motion for Leave to Reply to Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel filed.
Sep. 12, 2008 Lee County`s Suggestion that Mosaic`s Reply to Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel Violates the ALJ`s Order of Pre-hearing Instructions filed.
Sep. 12, 2008 Reply to Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel filed.
Sep. 10, 2008 Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel filed.
Sep. 10, 2008 Lee County`s Response in Opposition to Mosaic`s Motion to Disqualify Counsel filed.
Sep. 10, 2008 Request for Oral Argument on Respondent, Mosaic Fertilizer, LLC`s, Motion to Disqualify de la Parte & Gilbert, P.A. as Counsel for Petitioner, Lee County filed.
Sep. 08, 2008 Notice and Certificate of Service of Respondent Department of Environmental Protection`s Interrogatories to Lee County filed.
Sep. 08, 2008 Lee County`s First Request for Production to Florida Department of Environmental Protection filed.
Sep. 08, 2008 Respondent Mosaic Fertilizer, LLC`s First Request for Production of Documents to Plaintiff filed.
Sep. 08, 2008 Respondent Mosaic Fertilizer, LLC`s First Set of Requests for Admissions to Petitioner filed.
Sep. 08, 2008 Respondent Mosaic Fertilizer, LLC`s Notice of Filing First Set of Interrogatories to Petitioner filed.
Sep. 08, 2008 Responsdent, Mosaic Fertilizer, LLC`s, Motion to Disqualify de la Parte & Gilbert, P.A. as Counsel for Petitioner, Lee County, and Incorporated Memorandum of Law filed.
Sep. 04, 2008 Order of Pre-Hearing Instructions.
Sep. 03, 2008 Amended Notice of Hearing (hearing set for November 3 through 7, 10 through 14 and 17 through 21, 2008; 9:30 a.m.; Tallahassee, FL; amended as to dates of hearing).
Sep. 03, 2008 Mosaic Fertilizer LLC`s Response to Lee County`s Proposed Discovery Schedule filed.
Aug. 29, 2008 Lee County`s Proposed Discovery Schedule filed.
Aug. 29, 2008 Notice of Proposed Discovery Schedule filed.
Aug. 26, 2008 Notice of Hearing (hearing set for November 3 through 7, 10 through 14 and 17 through 21, 2008; 9:30 a.m.; Tallahassee, FL).
Aug. 26, 2008 Order (DOAH Case Nos. 08-3886, 08-3887, 08-3888, and 08-3889 are consolidated).
Aug. 22, 2008 CASE STATUS: Motion Hearing Held.
Aug. 22, 2008 Letter to Clerk from Kay Skipper regarding enclosing identical responses (Response to Initial Order and Motion for Summary Hearing) filed.
Aug. 21, 2008 Mosaic`s Response to Lee County`s Opposition to Motion for Summary Hearing and in Opposition to Lee County`s Petition filed.
Aug. 19, 2008 Department of Environmental Protection`s Response to Initial Order filed.
Aug. 18, 2008 Lee County`s Response in Opposition to Motion for Summary Hearing and Request for Oral Argument filed.
Aug. 18, 2008 Lee County`s Response to Initial Order filed.
Aug. 12, 2008 Initial Order.
Aug. 08, 2008 Diskette filed.
Aug. 08, 2008 Notice of Related Cases and Motion to Consolidate filed. (DOAH Case No`s 08-3886, 08-3887, 08-3888, and 08-3889)
Aug. 08, 2008 Approval of the Conceptual Reclamation Plan for the Mosaic South Fort Meade Hardee County Mine filed.
Aug. 08, 2008 Affidavit of Roland Ottolini filed.
Aug. 08, 2008 Petition for Formal Administrative Hearing filed.
Aug. 08, 2008 Request for Assignment of Administrative Law Judge and Notice of Preservation of Record filed.

Orders for Case No: 08-003887
Issue Date Document Summary
Feb. 02, 2009 Agency Final Order
Dec. 18, 2008 Recommended Order Applications for ERP, CRP, and two variances approved where Mosiac gave reasonable assurances that all relevant statutes and rules were satisfied.
Source:  Florida - Division of Administrative Hearings

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer