STATE OF FLORIDA
DIVISION OF ADMINISTRATIVE HEARINGS
NETWORK ENGINEERING SERVICES, INC., D/B/A BOLTON PEREZ AND ASSOCIATES,
vs.
Petitioner,
Case No. 19-5130
DEPARTMENT OF TRANSPORTATION,
Respondent.
/
RECOMMENDED ORDER
Pursuant to notice, a formal administrative hearing was conducted before Administrative Law Judge ("ALJ") Mary Li Creasy in Tallahassee, Florida, on February 13, 14, and 17, 2020.
APPEARANCES
For Petitioner: George Richard Truitt, Esquire
Anthony Lopez, Esquire Cole, Scott & Kissane, PA
9150 South Dadeland Boulevard, Suite 1400
Miami, Florida 33156
For Respondent: George Spears Reynolds, IV, Esquire
John Ashley Peacock, Esquire
Florida Department of Transportation 605 Suwannee Street, Mail Stop 58
Tallahassee, Florida 32399-0450
STATEMENT OF THE ISSUE
The issue in this administrative proceeding is whether the Florida Department of Transportation’s ("DOT" or "the Department") denial of Petitioner’s, Network Engineering Services, Inc. d/b/a Bolton Perez &
Associates ("BPA"), 2019 application for qualification pursuant to section 337.105, Florida Statutes, and Florida Administrative Code Chapter 14-75, was for good cause due to Petitioner’s participation in the construction of the Florida International University ("FIU") City Prosperity Project ("FIU Bridge project").
PRELIMINARY STATEMENT
On July 11, 2019, DOT issued a Notice of Intent to Deny Request for Qualification ("NOID") to BPA. The NOID removed BPA from consideration for award of professional service contracts with DOT. DOT issued the NOID based upon BPA’s failure to appropriately exercise independent professional judgment required of a construction engineering and inspection firm ("CEI"), as evidenced by the reports issued by the Occupational Safety and Health Administration ("OSHA") and the investigation of the National Transportation Safety Board ("NTSB") concerning the collapse of the FIU Bridge project on March 15, 2018.
On August 1, 2019, BPA filed a Petition for Formal Administrative Hearing. On September 24, 2019, the petition and accompanying documents were filed with DOAH.
A formal hearing was held as scheduled on February 13, 14, and 17, 2020, in Tallahassee, Florida. At the final hearing, BPA presented the testimony of Joaquin "Jake" Perez, BPA’s President and Director of Engineering; Jose Morales, BPA’s CEI Services Manager; and Gustavo Quesada, BPA’s expert witness. BPA’s Exhibits 5, 7, 9, 11 through 18, 29 through 32, 39, and 40 were admitted into evidence.
DOT presented the testimony of William Watts, P.E., Chief Engineer for the Department; Robert V. Robertson, Jr., P.E., State Structures Design
Engineer for the Department; and Carlos Chapman, BPA’s Senior Inspector. DOT’s Exhibits 1, 6, 9 through 16(c), 18 through 29, 33, and 34 were admitted into evidence. DOT's deposition designations of BPA’s corporate representatives, Mr. Perez and Mr. Morales were also admitted and accepted into evidence.
DOT marked the OSHA report as Exhibit 2 for identification. BPA objected to the admissibility of the OSHA and NTSB reports as unreliable hearsay expert testimony and objected to the admissibility of the statements within the report as hearsay within hearsay. Prior to the final hearing, by Order dated January 24, 2020, the undersigned ALJ, upon motion filed by Petitioner, took official recognition of both the OSHA and the NTSB reports. However, despite multiple references to it, the OSHA report was neither moved nor admitted into evidence.
The six-volume final hearing Transcript was filed on February 26, 2020. The parties requested and were granted several extensions of time within which to file proposed recommended orders. Both parties submitted proposed recommended orders which were considered in the drafting of this Recommended Order. All references to statutes refer to the 2019 version, unless otherwise specified.
FINDINGS OF FACT
THE PARTIES
DOT is the state agency responsible for coordinating the planning, construction, and maintenance of a safe, viable, and balanced state transportation system. DOT relies on qualified contractors and professional consultants to provide services for Florida’s transportation needs.
Section 287.055(3), Florida Statues, requires that any firm or individual desiring to provide professional services to a governmental agency must first
be certified by the agency as qualified, pursuant to law and the regulations of the agency. The agency must find that the firm or individual to be employed is fully qualified to render the required service. Among the factors to be considered in making this finding are the capabilities, adequacy of personnel, past record, and experience of the firm or individual. Each agency is also required to evaluate professional services, including capabilities, adequacy of personnel, past record, and experience of the firm or individual.
Section 337.105 and Florida Administrative Code Chapter 14-75 also governs the qualifications of professional consultants and other contractual services providers to DOT. Section 337.105 authorizes DOT to deny or suspend an application for qualification based upon a determination of "good cause," which includes, but is not limited to, nine illustrative examples specified in section 337.105(1)(a)–(i). DOT may, for good cause, deny or suspend for a specified period of time a person or firm from consideration for award of a professional service contract for a particular type of work.
BPA is a multidiscipline engineering firm specializing primarily in transportation related engineering services, including bridge design, roadway design, civil works, construction engineering inspection ("CEI"), and program and construction management. At the time of the hearing, BPA had approximately 38 employees. BPA was formed by Joaquin "Jake" Perez, P.E., and John Bolton, P.E., in 1997 to provide transportation-related engineering services.
BPA’s CEI qualifications are independent from, and do not necessarily mirror, BPA’s design qualifications. In some instances, BPA was qualified to serve as a CEI for categories of structures that the firm was not qualified to design. This is because BPA was internally divided into two core groups: design and CEI. Since inception, BPA’s design group was and continues to be headed by Mr. Perez, and the CEI group headed by Mr. Bolton.
The operations of BPA’s CEI and design groups were completely segregated within the firm. CEI personnel did not work on design projects,
and design personnel did not work on CEI projects. As President, Mr. Perez was involved in pursuing contracts for CEI services, but CEI services were provided only by CEI personnel.
In or about 1999 or 2000, BPA first became qualified to respond to DOT’s request for qualifications to provide professional services to DOT.
Mr. Bolton qualified the firm to provide CEI services, and Mr. Perez qualified it to provide design services. BPA remained qualified with the Department on an annual basis for both CEI and design work for nearly 20 years until
July 2019. At that time, DOT issued a NOID removing BPA from consideration for award of professional service contracts with DOT for 2019- 2020. DOT issued the NOID based solely upon a report issued by OSHA and the investigation of NTSB regarding the collapse of the FIU Bridge project on March 15, 2018.
THE FIU PEDESTRIAN BRIDGE PROJECT
In 2014, DOT entered into a Local Agency Program ("LAP") Agreement with FIU for its pedestrian bridge project, a Category II, complex bridge, that would be constructed along Southwest 109th Avenue and Southwest 8th Street in the City of Sweetwater, Florida (the "project"). As the supervising agency of the LAP program, DOT was responsible for supervising and authorizing work by the local agency.
The design of a Category II structure required an independent peer review by a firm with no other involvement in the project, which was prequalified with DOT. In September 2016, FIGG Bridge Engineers, Inc. ("FIGG"), the Engineer of Record ("EOR") for the project, hired Louis Berger to review FIGG’s plans for bridge foundation, substructure (end bents and center tower), and superstructure. Those plans included construction sequencing (including construction sequence drawings), the covered main span pre-casting, transport of main span, and placement of the main span between end bent 1 (south pier) and the pylon pier. The plans also included the post-tensioning stressing and destressing sequences.
As the Local Agency, FIU was in responsible charge of the day-to-day activities, including project safety issues. Alfredo Reyna, P.E., was the
Department’s LAP Coordinator for the project. Mr. Reyna is a licensed professional engineer, although he is not a structural engineer.
In January 2016, FIU entered into a design-build contract1 with Munilla Construction Management, LLC ("MCM"), to design the bridge and to perform all work and furnish all materials, equipment, supplies, and labor necessary to construct the project. The bridge was designed by FIGG, a member of the MCM design-build team and the EOR. FIGG is a reputable designer who has been recognized internationally for its work. FIGG has experience in designing complex bridges, such as the Sunshine Skyway Bridge near Tampa, Florida.
On September 23, 2016, FIU entered into a Standard Professional Services Agreement with BPA for CEI services (the "CEI Contract"). At the
1 The interaction of the local agency, contractor, designer, EOR, DOT, and the CEI is different between a "conventional" and a "design build" bridge project. In a conventional project, the designer is hired by DOT or owner to create a new bridge. The design goes through a review process at DOT and a final set of plans goes to bid for a contractor. By the time the contractor is selected, the EOR has completed the plans. The EOR is essentially "on call" for the construction phase of the project because the design work is complete. The CEI begins its work when the contractor begins construction. If there is a question in the field, the CEI makes a request for information from the EOR. DOT supplies design and construction managers throughout the process.
In contrast, for a "design build" project, the owner has a conceptual plan for the project. The designer and contractor bid for the job based on the preliminary conceptual plan. The Designer/EOR and contractor work hand in hand from the beginning of the project and are in constant communication. The CEI begins work when the contractor starts work on the project. The CEI facilitates the resolution of any issues between the EOR/designer and the contractor who continue to plan throughout the duration of the project. Like a conventional build project, DOT has construction managers and design project managers involved from the beginning of the project.
If concrete cracking occurs, it is the CEI's obligation to document the cracking and speak to people in the process who can assess and address the cracking. For a conventional build bridge, if cracking is observed, the CEI documents it, copies DOT, and sends it to the EOR for assessment. The EOR provides an assessment by conducting a site visit. The EOR then prepares an Engineering Assessment Report (EAR) for the project team. In a design build bridge job, if cracks are observed, they are documented by the CEI who notifies the EOR. The EOR, who is already on the job site, assesses the cracks and works with the contractor to devise a solution.
time, John Bolton was the CEI qualifier for BPA. As CEI, BPA was to act as the liaison between the project owner (FIU) and the contractor (MCM). The CEI handles quality control, materials, schedules, payments, documents the entire process, and monitors the project.
Jose Morales, P.E., worked under John Bolton as the Senior Project Engineer for the project. Mr. Morales first obtained his professional
engineer’s license in 2006. He had approximately 12 years of CEI experience at the time of the collapse. Although he was the Senior Project Engineer for the project, Mr. Morales had little-to-no design experience.
Mr. Morales was first involved in the early stages of pursuing the CEI Contract for the project. After the project was awarded, BPA was not involved in the design phase, but was later brought back into the fold beginning in October 2016, when BPA received the Notice to Procced and fully staffed its CEI scope of services when construction was scheduled to begin in or about March of 2017.
The "Scope of Services" section (Exhibit B) to the CEI Contract required BPA to be prequalified with the Department in the following work categories: Work Type 10.1--Roadway CEI; Work Type 10.4--Minor Bridge and Miscellaneous Structures CEI; and Work Type 10.5.1--Major Bridge CEI-
-Concrete. For the FIU bridge project, Categories 10.1 and 10.4 were considered to be the "major" type of work while 10.5.1 was considered to be the "minor" type of work. As expressly permitted by the Standard Professional Services Agreement, BPA satisfied the 10.5.1 prequalification requirement through its sub-consultant, The Corradino Group, Inc. ("Corradino").
BPA’s scope of services for the project did not include any design responsibilities. BPA performed constructability review of the plans as part of its CEI scope of work, but it did not review the plans or drawings on a technical level.
The FIU bridge was a Complex Category II structure as defined by the Department’s Design Manual. The structure had a unique, complex design that was meant to be a signature, architectural feature for the area.
The relevant construction sequence for the main span (Span 1) of the FIU bridge consisted of:
casting the main span superstructure in the casting yard;
installing post-tension bars in the diagonal and vertical members of the structure;
stressing of the main-span post-tensioning while the main span is in the casting yard;
removing the temporary formwork and supports;
transporting the main span from the casting yard using a self- propelled modular transporter and placing the structure in a "simply supported" condition on the south pier and pylon pier; and
de-tensioning truss members 2 and 11.
Generally, cracks in concrete are common and are not, in and of themselves, a cause for concern. On a design-build job, when cracks manifest themselves in a concrete element, the CEI must document the cracking and report it to the design-build team, which includes the EOR. Depending on the nature of the cracks, the CEI may request an EAR from the EOR. This process is set out in section 400, subsection 400-21, of DOT’s Standard Specifications for Road and Bridge Construction (the "Standard Specifications").
DOT's Construction Project Administration Manual ("CPAM") includes the procedures to be followed by a CEI in addressing cracks in concrete. The CPAM requires that the CEI identify and document its observations and convey the information to the EOR for a final disposition as to the potential danger of the crack or the need for further evaluation.
The FIU Bridge Cracking and Inspections by BPA
On or about February 6, 2018, while Span 1 of the bridge was still in the casting yard, BPA became aware of certain cracks that had developed in the structure. Mr. Morales personally inspected the structure after the tendons on truss members 2 and 11 were stressed, and he noted that cracks had developed in other locations on the bridge. The cracks observed were very small, approximately 0.004 of an inch wide.
On February 13, 2018, BPA submitted Crack Report #1 to MCM, FIU, and Corradino, documenting the cracks that had developed in the concrete truss members after completing the post-tensioning operations in the casting yard. Despite the small size of the cracks, BPA requested that the EOR provide an assessment of the cracks.
FIGG, the EOR, responded to BPA’s request by stating that the current condition observed was temporary in nature and that the cracks were not an issue.
BPA exercised independent professional judgment when it exceeded the requirements of section 400 of the Standard Specifications and the CPAM by documenting and reporting these initial cracks.
In late February 2018, before the placement of the main bridge span on the permanent pylon and south pier supports, cracks were observed in certain truss members. BPA prepared and submitted Crack Report #2 to FIU and MCM on February 28, 2018, documenting the size and location of these cracks and requested that FIGG evaluate the cracks and provide a disposition.
In its report, BPA called attention to certain cracks that were significant in size. As CEI, BPA was not qualified to determine whether these larger cracks posed an imminent danger of collapse. Further, BPA’s design team was not involved in the design of the bridge and was not qualified to evaluate these cracks from a design engineering perspective due to the category and complexity of the bridge.
At this point, the cracks were not "structural" as defined by
Section 400 of the Standard Specifications. Cracks more than one-half inch in depth are deemed "structural" and trigger the obligation of the CEI to notify the EOR. Nevertheless, BPA, again, exercised its independent professional judgment above and beyond the requirements of the Standard Specifications and CPAM by requesting that the report be forwarded to the EOR and requesting that the EOR provide a response and disposition of the cracks.
On March 7, 2018, FIGG replied to Crack Report #2, stating, in part, that the cracks appeared small, that they were not concerned about these types of cracks in the particular region shown in the report, and that MCM would need to seal the cracks in accordance with the Department’s specifications. As the EOR, FIGG did not have any structural concerns regarding the cracks in Crack Report #2.
On March 7, 2018, FIGG representatives were on site and observed the cracks referenced in Crack Report #2. After observing the cracks, FIGG did not delay the bridge movement that was scheduled to take place three days later on March 10th.
As of March 8, 2018, BPA had no concerns regarding the integrity of the structure or public safety because the EOR had looked at the cracks in- person and assured the project team that the cracks were not a safety issue or structurally significant. These assurances came two to three days prior to the bridge being moved over Southwest 8th Street and placed on the permanent pylon and pier supports. The bridge movement was not delayed due to the cracks observed by the EOR.
On March 10, 2018, Span 1 was moved from the casting yard and placed on the permanent pylon and south pier supports. After the placement and de-tensioning of diagonal members 2 and 11, cracks began to appear at the construction joint of diagonal 11, the deck, and at the top of diaphragm II.
At approximately 11:00 a.m. on March 13, 2018, two days before the collapse, BPA circulated a draft of Crack Report #3 to MCM, recommending
further monitoring and documenting of the cracks to determine whether they were active or dormant, and requesting that BPA be informed of the outcome of the EOR’s EAR and course of action. At 5:18 p.m. on March 13, 2018, the EOR responded to MCM with additional recommendations and stated "[a]gain, we have evaluated this further and confirmed that this is not a safety issue."
Because BPA’s design team was not involved in the project, no BPA design personnel were aware of the documented cracking on the structure until sometime after Crack Report #3 was generated. At that time,
Mr. Morales provided Mr. Perez with a copy of a draft of Crack Report #3. Mr. Perez briefly reviewed the draft report and confirmed with Mr. Morales that the CEI team had elevated the issue to the EOR.
At all times in the documented communication relating to the cracks, the EOR and members of the FIGG design team represented to BPA that the cracks were not a safety concern, without reservation.
Starting on March 13, 2018, FIGG directed MCM to implement an initial, temporary measure to address observed cracking in the member 11/12 nodal region. At that time, BPA was not aware of this communication between the EOR and the contractor. To restore the temporary support conditions when the structure was in the casting yard, MCM placed shims between diaphragm II and the pylon on March 13, 2018.
FIGG also directed re-tensioning the post-tensioning rods in truss member 11 to begin on March 15, 2018. The re-tensioning operation was made as a "rushed request" to the post-tensioning subcontractor by MCM on March 14, 2018. "FIGG recommends to stress these PT bars as soon as possible but again, this is not a safety concern."
MARCH 15, 2018, AND THE BRIDGE COLLAPSE
Rather than waiting for the EAR, BPA once again exercised its independent, professional judgment and went above and beyond the requirements of the Standard Specifications, CPAM, and Contract
Documents when it further escalated the issue of the cracks by calling for a meeting with the EOR. On the morning of March 15, 2018, a meeting requested by BPA and coordinated by MCM, was held in Miami, Florida.
Representatives of FIGG, MCM, DOT, FIU, and BPA were present.
At the March 15th meeting, BPA first became aware of the EOR’s instruction to MCM to proceed with a second temporary measure. This subsequent temporary measure was to reinstate the post-tensioning compression force back in member 11 as per the previous construction phase. As explained by the EOR, both temporary measures (shims and re- tensioning) were intended to restore the temporary support conditions when the structure was in the casting yard.
Prior to the start of the meeting, the EOR, other FIGG engineers, and DOT’s LAP Coordinator inspected the bridge and the cracks in the nodal region of members 11/12.
Only FIGG had structural engineers at the meeting. No other engineers present at the meeting had a background in structural engineering, including those in attendance on behalf of BPA. The meeting was called for purposes of discussing the concrete cracking on Span 1, and specifically the concrete cracking in nodal connection between truss members 11 and 12 and the bridge deck. At this meeting, BPA informed FIGG that the cracks in the bridge were lengthening and growing daily. Though not formally invited, Mr. Reyna attended this meeting in his capacity as DOT’s consultant/Assistant LAP Coordinator.
At the March 15th meeting, the EOR presented FIGG's assessment of the cracking after having reviewed the three BPA crack reports and having personally inspected the cracks on at least the following two occasions:
(1) prior to the bridge being moved from the casting yard over Southwest 8th Street; and (2) on the morning of the March 15th meeting. The EOR’s presentation consisted of a lengthy and comprehensive PowerPoint slide presentation on the conditions of the bridge, structural analysis by
calculations and 3D modeling of the loads and forces the area of member 11/12 nodal region cracks, and an evaluation of the safety of the span over Southwest 8th Street for workers and the public.
Throughout the March 15th meeting, BPA exercised its independent professional judgment by actively participating in the EOR’s presentation, questioning and challenging the EOR. For example, BPA:
inquired as to whether temporary shoring was needed;
sought clarification regarding the mechanism being used to capture the load from the node and whether it would have to be integrated with the pylon diaphragm;
requested clarification on the amount of transferred post- tensioning assumed for the nodal shear stability analysis;
inquired as to whether there were any restrictions on load;
inquired as to whether there would be a crack monitoring plan;
requested a copy of the EOR’s presentation;
inquired as to whether it had been peer reviewed and commented that it wanted more eyes on the presentation calculations; and
BPA requested a copy of the stressing procedure that was being recommended by the EOR.
Throughout the presentation, and during the question and answer phase of the meeting, the EOR assured BPA and the other attendees that the structure was safe. These assurances were based on statements made by the EOR as well as its calculations and modeling, which were part of its slide presentation at the meeting.
In the presentation on the slide entitled "Safety," FIGG stated that "…[it] had conducted sufficient supplemental/independent computations to conclude that there is not any concern with safety of the span suspended over the road." At the end of the presentation, the EOR concluded the meeting with "[b]ased on conservative calculations, it is concluded that the design meets LRFD strength requirements for this temporary condition and
therefore there is no safety concern relative to the observed cracks and minor spalls."
During the meeting, the EOR stated that some cracking similar to the ones on the structure, were expected. The EOR further stated during the meeting that the top deck spalls could not be replicated, but that the spalled areas were minor and they should be repaired during the next phase of work when the pylon concrete was to be placed.
No engineer at the meeting, including DOT's representative,
Mr. Reyna, requested or recommended a complete road closure to protect the public safety or that the bridge be shut down. BPA had no reason to request a full road closure of Southwest 8th Street. There was no preplanned complete road closure, there was no maintenance of traffic ("MOT") deficiency, and, based on the EOR’s presentation, BPA was reasonably satisfied that no safety issues required a road closure.
Towards the end of the meeting on March 15th, MCM informed BPA that a specialty contractor, Structural Technologies ("VSL"), was already onsite to conduct the re-tensioning operation. Without BPA’s knowledge, VSL had already mobilized on site to perform the remedial re-tensioning. BPA was not involved in pre-coordination for the re-tensioning operation. Therefore, BPA’s sub-consultant, Corradino, was not onsite to participate in monitoring of the re-tensioning procedure.
Corradino’s role, as BPA's sub-contractor, was that of a 10.5.1 CEI (Major Bridge CEI--Concrete). Corradino was responsible for monitoring and documenting the post-tensioning operations. The post-tensioning operation after placement of the span had already occurred and therefore, Corradino was not on-site on March 15, 2018.
Based on the safety assurances and conservative calculations presented by the FIGG EOR that the structure was safe, BPA, and the other professional engineers present at the meeting, including those representing FIU and DOT, followed the recommendations of the FIGG EOR to bring the
main span condition back to its pre-existing state when the span was in the casting yard.
BPA did not have the expertise or the contractual duty to perform its own analysis of the cracking on this complex bridge and override, or even call into question, FIGG’s unequivocal assessment that the bridge was safe.
During the restressing operation of member 11, the roadway below the bridge had two westbound lanes closed as per the blanket, two-lane, closure permit issued by DOT. This blanket, two-lane, closure permit was obtained by MCM to provide workspace underneath the bridge to conduct the remedial action. MCM obtained the blanket, two-lane, closure permit from the Department the morning of March 15, 2018, before conducting the remedial action.
A CEI’s authority to request a partial or complete road closure is defined by the contract plans and roadway closure permits, which is implemented using the procedures outlined by the CPAM and the CEI Scope of Services of the CEI Contract. A CEI is authorized to request the contractor to either partially or fully close a road if there is an MOT deficiency, as contemplated by CPAM Section 9.1.8--"Recommended Action to Shut Down a Project Due to MOT Deficiencies." Lastly, a CEI has authority to request a partial or full road closure if it is aware of a safety issue.
None of these conditions existed on the project in the days leading up to the collapse in light of the EOR’s comprehensive presentation regarding the cracking conditions of the bridge, strength in the area of member 11/12 nodal region, safety of the span over Southwest 8th Street, and repeated, unequivocal reassurances that the structure did not pose a safety concern.
Ultimately, BPA’s authority to request a partial or complete road closure on the project was a collective effort with the Department and FIU. BPA did not have the authority or ability to act on its own to close the road.
The FIU Pedestrian Bridge collapsed during the re-tensioning of the truss member 11 post-tensioning rods on the afternoon of March 15, 2018.
Six people died as a result of the FIU bridge collapse, including one bridge worker and five vehicle occupants. Ten people were critically injured as a result of the FIU bridge collapse, including two BPA employees, Mr. Morales and Carlos Chapman.
Mr. Chapman was on the canopy of the bridge during the re- tensioning operation, observing the work being performed by VSL and communicating the progress to Mr. Morales who was on the deck of the bridge. Because of the representations made by the EOR, neither
Mr. Chapman nor Mr. Morales was concerned for his own safety or well-being when they went on the bridge on the day it collapsed.
BPA’s role, responsibilities, and scope of work on the FIU Bridge project as the CEI was that of a contract administrator, not as a structural engineer with the capability to analyze the structural behavior of the bridge sufficient to determine if the cracks posed any danger of collapse. BPA had no basis, ability, or contractual obligation, to perform its own analysis of this complex structure sufficient to override the FIGG EOR’s unequivocal safety assessment and recommendations. BPA performed its CEI duties and utilized its independent professional judgement when it documented and monitored the cracks and requested an immediate structural evaluation by the FIGG EOR.
Ultimately, the bridge collapse was caused by a fundamental design error.
THE OSHA AND NTSB INVESTIGATIONS
Shortly after the collapse, both OSHA and NTSB began investigating the causes of the collapse. OHSA completed its investigation and released a written report of its findings in June 2019.2 The June 2019 OSHA report was
2 DOT failed to enter into evidence the OSHA report on which it relies. However, prior to the final hearing, DOT filed a Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse ("Motion"). The Motion was opposed by BPA on the basis that the first OSHA report was not final because a second report was issued, and is hearsay. By Order dated January 24, 2020, the undersigned officially recognized both the
issued without prior review or comments from all party members who willingly cooperated with and were involved in the investigation, including NTSB and BPA. OSHA released an amended report on the collapse of the FIU Bridge project in July 2019; however, none of the amendments in the report pertained to the actions of BPA on the FIU Bridge project. NTSB completed its investigation and issued its report in October 2019.
Significantly, no evidence was presented at the final hearing regarding from whom either agency conducted the investigations or drafted the reports, the qualifications or expertise of the investigators, the methodology used in the investigations, or the ability of any of the participants in the investigation to rebut the findings or conclusions.
BPA willingly participated in both the OSHA and NTSB investigations, working with investigators and providing them with information, photographs, and details on the FIU Bridge project. Both OSHA and NTSB also conducted interviews of BPA personnel involved with the FIU Bridge project as part of their investigations.
In its report, OSHA found that BPA failed to classify the concrete cracks, which were structural in nature, in accordance with DOT requirements. OSHA determined that BPA, as CEI, was expected to exercise its own independent professional judgment in accordance with their contract with FIU and DOT requirements. With intimate knowledge of extensive
initial OSHA report and the NTSB report. Accordingly, references to the report in this Recommended Order are based upon the official recognition.
As noted in the Order on the Motion, official recognition of the OSHA and NTSB reports, however, does not make the statements contained therein automatically admissible. "The distinction between noticing the contents of a record and noticing the truth of the contents resembles the distinction in the hearsay doctrine between offering an out-of-court statement simply to show it was said, and offering it for the truth of the matter asserted." C. Ehrhardt, Florida Evidence § 201.1 (2011 Edition)(quoting Wright & Graham, Federal Practice and Procedure: Evidence § 6337). Although the existence of the report and its findings were officially recognized, the greater weight of the evidence supports that the contents were not accurate as to the exercise of independent judgment of BPA.
cracking on the bridge, BPA failed to recognize the bridge was in danger of collapsing, and did not recommend to FIU, MCM, or others to close the street and shore the bridge, regardless of the opinion held by the EOR. As a result, OSHA imposed a monetary fine on BPA for its conduct and failure to take appropriate action in the days leading up to the collapse of the main bridge span.
In its October 2019 report (issued after the NOID to BPA in this case), NTSB found that beginning with the cracking identified on February 24, 2018, the distress in the main bridge span was active, continued to grow, and was well documented by all parties involved in the design, construction, and oversight of the bridge. Neither FIU, MCM, FIGG, nor BPA took responsibility for declaring that the cracks were beyond any level of acceptability and did not meet DOT standards. Further, NTSB concluded that under the terms and conditions of the CEI Contract, BPA had the authority to direct or authorize partial or complete road closures as necessary, acting in concert with DOT and FIU; however, none acted to close the road under the bridge, contributing to the severity of the impact of the bridge collapse.
BPA POST-COLLAPSE ACTIVITIES AND 2018 APPLICATION FOR QUALIFICATION
On May 3, 2018, BPA submitted its Request for Qualification for the July 1, 2018, through June 30, 2019, fiscal year ("2018 Application"). BPA’s 2018 Application was for the same Work Groups that would eventually be included in the 2019 Request for Qualification.
Each work category is tied to a distinct job function. There is no relationship or similarity between CEI services (Work Group 10) and the other work groups.
On June 27, 2018, DOT accepted BPA’s Request for Qualification in all work categories. In processing the application, the Department did not ask BPA any questions regarding its involvement in the project, offer any criticisms of BPA in response to the application, request to interview any
BPA employees, or raise any concerns at all regarding BPA’s participation in the project.
From the date of the collapse on March 15, 2018, to December 2018, DOT awarded two contracts to BPA directly for CEI and design services, respectively. During the same period, DOT allowed BPA to participate as a qualified sub-consultant on one CEI contract, three design contracts, and one traffic task work order contract. During the 2018-2019 fiscal year, before
DOT attempted to suspend BPA’s qualifications, BPA was able to win several jobs in both the prime and sub-consultant role, including projects in which BPA would be providing CEI services.
In October 2018, approximately seven months after the collapse, BPA applied to change its CEI qualifier from John Bolton to Jose Morales because John Bolton wanted to retire. DOT approved the request and did not object or raise any concerns with respect to Jose Morales serving as BPA’s qualifier for CEI services.
On December 19, 2018, nine months after the collapse, DOT expressed concern for the first time about BPA’s role in the bridge project, staffing of current DOT projects, quality assurance/quality control ("QA/QC") plans, and professional liability insurance. DOT sent BPA a "Qualifications Letter of Concern," stating that it had "serious concerns regarding [BPA]’s involvement as the Construction Engineering Inspection consultant on the Florida International University (FIU) pedestrian bridge project[.]" DOT requested in its letter, among other things, "a detailed explanation of the firm’s actions on the FIU pedestrian bridge project and… any controls or changes in personnel, policies or practices that [BPA] has implemented subsequent to the collapse."
On December 21, 2018, BPA responded to the Letter of Concern addressing each concern raised by the Department, in detail, including providing a copy of its Certificate of Liability Insurance demonstrating that there was no lapse in professional liability insurance coverage.
On February 12, 2019, DOT responded to BPA’s correspondence dated December 21, 2018, requesting additional detail from BPA relative to its revised QA/QC plan and punctuated the correspondence by stating that DOT would refuse to process any further qualification requests from BPA, including ministerial prequalification name changes, until the matter was addressed to the Department’s satisfaction.
Around this time, BPA submitted a request to change its name with DOT to reflect its business name with the Division of Corporations. BPA requested that DOT update this information on its website, but DOT refused to process the request due to its concerns with BPA’s qualifications.
On February 20, 2019, BPA provided further detail regarding the specific policies and procedures that have been implemented to its CEI services. Specifically, BPA provided extensive detail regarding its revised QA/QC plan, which included a section dedicated to Category II type bridge structures and included a copy of the revised QA/QC program for DOT review. DOT never responded or requested any additional information in this regard.
On March 15, 2019, one year to the day after the collapse, DOT issued a Notice of Intent to Suspend BPA’s existing certificate of qualifications. DOT attempted to suspend BPA’s qualifications in all Work Groups and declare BPA non-responsible for a period of one year for good cause. DOT further claimed that BPA "failed to adequately address the Department’s concerns regarding the firm’s performance of the contract, and the [BPA] staff directly involved with the FIU project who continue to work on other Department structural contracts." No further explanation was provided as to how BPA failed to address these concerns.
BPA timely responded to the Notice of Intent to Suspend by way of a Notice of Contest, requesting an administrative hearing on the issues raised therein. Despite the Notice of Contest, DOT suspended BPA’s qualification, and sent written notice to its various offices stating, among other things, that
BPA had been removed from DOT’s prequalification list. Ultimately, DOT reinstated BPA’s qualifications, but never formally withdrew the Notice of Intent to Suspend.
However, in reinstating BPA’s qualifications, DOT neglected to reinstate BPA’s Small Business Enterprise ("SBE") designation, which
negatively affected BPA’s ability to obtain points for SBE participation. The points add value in scoring competing responses to Requests for Proposals for DOT contracts. BPA repeatedly requested that this be corrected. BPA’s requests went largely ignored for nearly two months.
On April 2, 2019, after BPA had an in-person meeting with Courtney Drummond, DOT's Assistant Secretary of Engineering and
Operations, BPA submitted a qualifications modifications package to replace Jose Morales, P.E., with John Bolton, P.E., as the qualifier for the CEI Work Group to address Mr. Drummond's and DOT’s concerns about BPA staff involved on the FIU project working on other DOT contracts.
On April 5, 2019, in response to the Notice of Intent to Suspend, BPA provided specific facts in support of BPA’s proper performance of the CEI Contract. As an accommodation to DOT, BPA further proposed a solution to DOT's concern about the staff involved in the FIU project. BPA stated that it was "willing to immediately remove the BPA staff directly involved in the FIU Bridge project from working on any Department contracts or qualifying the company for CEI services" and resubmitted its qualifications application with those changes.
2019 BPA REQUEST FOR QUALIFICATION REJECTION
On May 7, 2019, BPA submitted its 2019 Request for Qualification to the Department early due to the lack of response from DOT on BPA's April 5, 2019, correspondence. BPA sought qualifications for design work and CEI services in the same work categories it was qualified in for the prior fiscal year.
On June 10, 2019, BPA’s counsel met with DOT representatives in Tallahassee to discuss several outstanding issues relative to BPA’s current qualification, the upcoming renewal, and DOT’s failure to reinstate BPA’s SBE designation. DOT responded by promising to correct the "mistake" that same day. Inexplicably, it took another two weeks and several reminders from BPA for DOT to finally correct the SBE designation.
BPA’s 2018-2019 qualifications expired on June 30, 2019. The next day, on July 1, 2019, DOT untimely responded to BPA’s Request for Qualification with a letter titled "Incomplete Renewal Applications for Pre- Qualification." DOT's letter raised the same concerns regarding BPA’s involvement in the bridge project and, again, requested "a detailed
explanation of BPA’s actions on the FIU pedestrian bridge project and…any controls or changes in personnel, policies or practices that BPA has implemented subsequent to the collapse." This is the same request that had been previously made by DOT in its December 19, 2018, Qualifications Letter of Concern, February 12, 2019, Qualifications Letter of Concern, March 15, 2019, Notice of Intent to Suspend, and April 26, 2019, denial of BPA’s Submittal for Modification.
BPA had already provided the information requested several months prior to DOT's July 1, 2019, correspondence.
On July 11, 2019, DOT issued its Notice of Intent to Deny Request for Qualification directed to BPA’s 2019 Request for Qualification. In issuing its denial of BPA’s Request for Qualification, DOT relied solely on the findings and conclusions of the June 2019 OSHA Report as they relate to the CEI services provided by BPA on the project and referenced the pending NTSB investigation.
The Department’s Notice of Intent to Deny was executed by William Watts, the Department’s Chief Engineer. Mr. Watts admitted at final hearing that he does not have the training or experience necessary to
evaluate a CEI’s performance on a CEI contract. Moreover, neither Mr. Watts
nor DOT retained or consulted with any individuals with CEI expertise prior to issuing the Notice of Intent to Deny. When he issued the Notice of Intent to Deny, Mr. Watts was completely unfamiliar with the following: the terms of BPA’s CEI Contract; BPA’s Request for Qualification; BPA’s past
performance on CEI or any other Department contract; and BPA’s professional reputation.
Mr. Watts did not evaluate BPA under the criteria required by Florida Statutes and the Florida Administrative Code prior to denying BPA’s Request for Qualification for good cause. Mr. Watts did not receive any
analysis from the Department’s prequalification staff regarding their evaluation of BPA’s application under the statutory criteria.
Mr. Watts admitted that he was aware that BPA documented the cracking on the bridge, reported the cracking to the design-build firm, and requested an EAR from the EOR--actions which were all in accordance with BPA's obligations as CEI pursuant to the CPAM and its contractual obligations with FIU.
Mr. Watts’ only reason for issuing the Notice of Intent to Deny, as Chief Engineer for DOT, was because BPA was under investigation by OSHA and the NTSB, and OSHA’s release of its June 2019 Report. However,
Mr. Watts did not know the author of the June 2019 OSHA Report, whether the author of the report was qualified to evaluate the performance of a CEI under Florida Statutes and the Florida Administrative Code, or whether the author of the OSHA report did anything to evaluate BPA’s performance relative to any other CEI, at the same time, and/or in the same community.
DOT did not investigate the structure or organization of BPA to determine whether the issues raised in the OSHA report, regarding BPA’s performance of the CEI Contract, would reflect negatively on other groups or divisions within BPA that provided services exclusively under other non-CEI work categories (design services).
Prior to issuance of the NOID, Mr. Watts did not undertake a review of BPA’s past performance or professional reputation--both of which were beyond reproach.
DOT evaluates its consultants’ performance on all projects approximately every six to eight months. These evaluations produce a score that ranges from one to five, five being the highest possible score. A perfect score of five is uncommon and a score of four is outstanding. In the five years prior to the final hearing, DOT evaluated BPA’s performance on projects involving both design and CEI services. Specifically, DOT scored BPA’s performance in Work Groups 3.1, 3.2 (Highway Design), 4.12 (Bridge Design),
5.1 (Bridge Inspection), 7.2 (Traffic Operations Design), and 10.1 and 10.3 (CEI). During that period, BPA averaged a score of outstanding to nearly- outstanding on all projects, including outstanding and nearly-outstanding scores for inspection services on bridge rehabilitation projects, which involved cracking concrete elements.
In May of 2019, prior to denying BPA’s request for qualifications for the fiscal year July 1, 2019, through June 20, 2020, Mr. Drummond personally presented BPA with an award from the American Council of Engineering Companies ("ACEC"), for excellence in major urban reconstruction. Specifically, the award was for CEI services on the State Road 7 project, and the ACEC recognized two-and-a-half-years of excellence in CEI services from late-2016/early-2017 through 2019. DOT's District Construction Engineer, District 6 Secretary, and Headquarters were intimately involved in the selection and vetting process that, ultimately, resulted in BPA receiving the award.
In September 2019, after denying its request and three months after the release of the June 2019 OSHA Report, DOT voted that BPA receive another award for excellence in CEI services. As a member of the selection committee, DOT chose BPA to receive an award from the Florida Transportation Builders Association ("FTBA"), for excellence on the Baker’s
Haulover Bridge rehabilitation project. By this award, FTBA and DOT recognized BPA’s excellence in CEI services, which spanned from one year before the collapse to one year after the collapse.
The Experts 3
Gustavo Quesada, P.E.
At the Final Hearing, BPA presented the expert testimony of Gustavo Quesada, P.E., a CEI with over 30 years of experience. The ALJ finds that Mr. Quesada is a qualified expert on the standard of care for a CEI and his opinions in that regard are based on competent substantial evidence.
As explained by Mr. Quesada, the role of a CEI with respect to cracks in concrete is to identify the cracks and make sure they do not go unseen or undetected and that an EOR is engaged for purposes of addressing the cracking. Pursuant to the CPAM, when a CEI encounters cracks in concrete, a CEI is required to document the observation and make a disposition on the cracks based on Section 400 of the Standard Specifications. Moving forward, the CEI is also required to monitor any changes in the cracks. A CEI is not responsible for making a determination as to whether a crack is potentially dangerous. This is a determination for the EOR, who has an understanding of the structure, its design, and how the structure is expected to behave. A CEI is not charged with making judgment calls on the design of a structure or whether its integrity has been jeopardized.
BPA documented, monitored, and reported the cracks on the project in compliance with the industry standards for CEIs working on Complex Category II Bridges, as well as the relevant sections of the CPAM and Section 400 of the Standard Specifications. BPA’s Senior Project Engineer, Mr. Morales, exercised his independent professional judgment in elevating
3 DOT intended to offer Mr. Watts at hearing as an expert to testify to the "good cause" DOT had when issuing the NOID to BPA. BPA filed a Motion in Limine to exclude or limit the testimony of both Mr. Watts and Mr. Robertson. The motion was argued at the outset of the final hearing. The undersigned precluded Mr. Watts from testifying as an expert in the field of CEI. Mr. Watts was allowed to testify as to DOT's qualification process and did so as a fact witness, rather than an expert.
the issue of the cracks to the EOR even before he was required to do so under the CPAM and Section 400 of the Standard Specifications.
At the meeting called by BPA on the morning of March 15, 2018, BPA exercised its independent professional judgment and complied with the applicable standard of care when Mr. Morales asked the EOR a series of
questions in response to the EOR’s presentation and evaluation of the cracks on the bridge.
According to Mr. Quesada, professional engineers are expected to rely on other engineers with superior or specialized knowledge when exercising their independent professional judgment. BPA’s role, responsibilities, and scope of work on the project as the CEI was largely that of a contract administrator, and a liaison between FIU and MCM--not as a structural engineer with the capability to analyze the structural behavior of the bridge sufficient to determine if the cracks posed any danger of collapse.
Robert V. Robertson, P.E.
DOT presented the testimony of Robert V. Roberson as an expert on the standard of care for CEIs. Mr. Robertson has served as DOT's State
Structure’s Design Engineer for 13 years. Mr. Robertson has been a professional engineer for 35 years.
Although preliminarily accepted by the undersigned as an expert in this field, it became apparent through cross-examination that Mr. Robertson has no significant CEI experience. Mr. Robertson has not worked in the CEI industry in the last 26 years, nor has he ever graded a CEI’s performance. Mr. Robertson was not involved in the Department’s evaluation of BPA’s performance of the CEI Contract. Accordingly, Mr. Robertson's testimony was of limited value.
Mr. Robertson acknowledged that the FIU bridge was a complex concrete bridge structure that required a separate design qualification and that BPA did have such qualification. Mr. Robertson admitted that BPA’s contract with FIU did not require BPA to be qualified to inspect complex
concrete bridges because BPA was allowed to satisfy that particular qualification requirement of the contract through a sub-consultant (Corradino).
Mr. Robertson testified that any licensed engineer with a college degree in engineering should have known, based on the photographs in Crack Report #3, that the cracks were dangerous and should have acted to stop work on the project and close the road. However, DOT's LAP representative at the March 15, 2018, meeting held prior to the bridge collapse, Mr. Reyna, a licensed professional engineer with a college degree in engineering, failed to raise any concerns at the March 15th meeting or act to cease bridge work, shore the bridge, or close Southwest 8th Street under the bridge.
Mr. Robertson opined that the re-tensioning operation of the bridge should have been peer reviewed. In his opinion, BPA failed to use sufficient independent judgment. BPA, as the CEI, should have recognized the bridge was in danger and known to stop traffic and shut down the road. However, Mr. Roberston admitted that he did only a cursory review of the PowerPoint presentation provided on the morning of March 15, 2018, in which FIGG, as the EOR, stated it had no safety concerns.
Mr. Robertson stated that he performed no analysis on anything other than BPA's CEI work relative to the FIU bridge. He had no information about BPA's design group or its qualification in any work category. However, he suggested the denial of BPA's application for qualification across the board, in all work categories because he questioned "the culture at BPA." Significantly, concerns regarding "the culture" of BPA was not cited by DOT as a basis for the NOID.
Most significantly, Mr. Robertson testified that six months prior to the issuance of the NOID, he had a conversation with Mr. Drummond during which Mr. Drummond recommended that the qualification of all parties involved with the FIU Pedestrian Bridge project should be suspended. Importantly, this was prior to the issuance of either the OSHA or NTSB
reports and seemingly with no analysis of the role of any party to the possible prevention of the bridge collapse, injuries, or loss of life.
Ultimate Findings of Fact
DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise its independent professional judgment by not acting to cease bridge work, shore the bridge, or close Southwest 8th Street under the bridge in light of the documented cracking on the structure in the days leading up to the collapse.
The evidence shows that BPA documented, monitored, and reported the cracks pursuant to the CPAM, Section 400 of the Standard Specifications, and industry standards. BPA involved the EOR in evaluating the cracks even before it was required by the CPAM, Section 400 of the Standard Specifications, and industry standards. BPA was assured time and again by the EOR that the bridge did not pose a danger to the travelling public and that the structure was safe. At the meeting on the morning of March 15, 2018, BPA inquired as to whether temporary shoring was needed, and the suggestion was rejected by the EOR who had inspected the cracks on the structure just moments before the meeting. There is no evidence that BPA deviated from the standard of care for CEIs on design-build projects or that BPA failed to exercise its independent professional judgment. To the contrary, BPA met all of its obligations pursuant to contract and state regulation.
DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise independent professional judgment by not acting to cease bridge work, shore the bridge, and close Southwest 8th Street under the bridge pending a peer review of the re-tensioning plan proposed by the EOR at the March 15th meeting.
At the March 15th meeting, BPA was reasonably convinced by the EOR that the structure was safe and that the re-tensioning plan was a temporary measure that should be implemented as soon as possible. BPA had
already engaged the EOR to prepare an EAR to address the cracking observed on the bridge, which would have included signed and sealed calculations and a repair protocol that would have been implemented in a later phase of construction. On March 15, 2018, the cracks were not a safety concern such that BPA should have overridden the EOR’s directive to MCM and required that the re-tensioning operation be postponed pending a peer- review of the re-tensioning plan. There is no evidence in the record that BPA deviated from the standard of care for CEIs on design-build projects or allegedly failed to exercise its independent professional judgment by allowing the re-tensioning procedure to proceed as directed by the EOR. Conversely, the evidence supports a finding that BPA acted appropriately in relying on the recommendations of the EOR who was uniquely qualified to evaluate the safety of the structure and who had specialized knowledge of its design.
DOT failed to demonstrate that BPA, as the CEI, fell below the standard of care by failing to exercise independent professional judgment by not acting to cease bridge work, shore the bridge, and close Southwest 8th Street under the bridge until the Corradino Group could arrive on the project site to observe the re-tensioning operation proposed by the EOR during the meeting on March 15, 2018. Corradino’s role on the project was to monitor and document post-tensioning operations. By the time the meeting was over, MCM’s specialty contractor, VSL, was mobilized and prepared to proceed with the re-tensioning operation. BPA was not involved in the pre- coordination of this work. Ultimately, the bridge collapsed due to an inherent design error in the plans and not due to Corradino’s absence from the re- tensioning operations.
The findings of the OSHA report and the pendency of the NTSB investigation, standing alone, were insufficient "good cause" for DOT to deny BPA’s 2019 Request for Qualification.
CONCLUSIONS OF LAW
DOAH has jurisdiction over the parties to and the subject matter of this proceeding. §§ 120.569 and 120.57, Fla. Stat.
A hearing involving disputed issues of material fact under section 120.57(1) is a de novo proceeding, and the agency’s initial action
carries no presumption of correctness. See § 120.57(1)(k), Fla. Stat.; Moore v. State, Dep’t. of HRS, 596 So. 2d 759 (Fla. 1st DCA 1992); Fla. Dep’t. of Transp. v. J. W. C. Co., 396 So. 2d 778 (Fla. 1st DCA 1981).
"The general rule is that a party asserting the affirmative of an issue has the burden of presenting evidence as to that issue." Dep’t of Banking & Fin., Div. of Sec. & Inv'r Prot. v. Osborne Stern & Co., 670 So. 2d 932, 934 (Fla. 1996)(quoting Osborne Stern & Co. v. Dep’t of Banking and Fin., 647 So. 2d 425 (Fla. 1st DCA 1994)(Booth, J. concurring and dissenting)); Fla. Dep’t of Transp. v. J.W.C. Co., 396 So. 2d 778 (Fla. 1st DCA 1981).
"[W]here [an] agency proposes to deny the license because the applicant is unfit, it has the burden to prove the applicant’s unfitness." Fla. Dep’t of Child. and Fams. v. Davis Fam. Day Care Home, 160 So. 3d 854, 857 (Fla. 2015)(citing Osborne Stern, 670 So.2d at 934 ("[T]he Department had the burden of presenting evidence that appellants had violated certain statutes and were thus unfit for registration.").
In this case, the Department is asserting the affirmative, namely, that it had good cause to deny BPA’s Request for Qualification due to the findings in the June 2019 OSHA Report as they relate to BPA’s CEI services.
To the extent that denial of Petitioner’s application for qualification is akin to denial of a renewal of a license, the Department bears the burden of proving good cause for denying renewal by "clear and convincing evidence." See Coke v. Dep’t of Child. & Fam. Servs., 704 So. 2d 726, 726 (Fla. 5th DCA 1998)(Department "had the burden of proving [petitioner’s] lack of entitlement to a renewal of her license and that the evidence needed to be clear and convincing.")(citing Osborne Stern, 670 So. 2d at 933; Dubin v.
Dep’t. of Bus. Reg., 262 So. 2d 273 (Fla. 1st DCA 1972)).4 Otherwise, the Department bears the burden of proving good cause by a "preponderance of the evidence." See § 120.57(1)(j), Fla. Stat. ("Findings of fact shall be based upon a preponderance of the evidence, except in penal or licensure disciplinary proceedings or except as otherwise provided by statute, and shall be based exclusively on the evidence in the record and on matters officially recognized.").
In Florida Department of Children and Families v. Davis Family Day Care Home, 160 So. 3d 854 (Fla. 2015), the Florida Supreme Court recognized that the preponderance of the evidence burden of proof, not the clear and convincing burden, is applicable to initial license application proceedings.
Id. at 857. The Court explained that although it had not previously addressed the situation where an agency erroneously references its disciplinary authority in the context of noticing its intent to deny an initial license application, "it is the nature of the agency's action and the underlying rights implicated by the action that govern the applicable evidentiary standard[.]" Id. In reaching its conclusion, the Davis Family court reaffirmed its holding in Department of Banking and Finance v. Osborne Stern and Company, where the court distinguished cases involving denials of initial applications (in which the Department must prove good cause for the denial by a "preponderance of the evidence") from cases involving revocations or denials of renewal applications (which the Department must prove good cause for the denial by "clear and convincing evidence"). See Davis Family, 160 So. 3d at 856 (citing Dep't of Banking & Fin., Div. of Sec. & Inv'r Prot. v. Osborne Stern & Co., 670 So. 2d 932, 933 (Fla. 1996)).
4 At the Final Hearing, counsel stipulated that the burden of proof was a preponderance of the evidence. (T. 129) However, "[i]t is well settled that a court is not bound to accept as controlling stipulations as to questions of law[.]" Alvarez v. Smith, 714 So. 2d 652, 653 (Fla. 5th DCA 1998)(quoting Clark v. Munroe, 407 So. 2d 1036, 1037 (Fla. 1st DCA 1981) ("The parties cannot by stipulation control questions of law.")). The Department’s burden of proving that it had good cause to deny BPA’s Request for Qualification is by clear and convincing evidence.
This is a renewal case (like Ferris and Coke)--not an initial application case (like Davis Family and Osborne Stern). Here, BPA had been prequalified with the Department for the last 20 years. In May 2019, BPA attempted to renew its qualifications for the same Work Groups as the previous fiscal year. DOT relied on the disciplinary section of the Florida licensing statute as grounds to support its denial of BPA’s renewal. DOT’s action is disciplinary in nature and subject to the clear and convincing standard.
In denying BPA’s Request for Qualification, DOT relied on
section 287.055 and Florida Administrative Code Chapter 14-75. DOT cited no other authority in its Notice of Intent to Deny.
As described above, section 287.055(3) requires that any firm or individual desiring to provide professional services to a governmental agency must first be certified by the agency as qualified pursuant to law and the regulations of the agency.
Rule 14-75.0022(4), entitled "Consultant Qualification Process," provides, in pertinent part, as follows:
Upon receipt of a complete application the Department shall make such inquiries and investigations as deemed necessary to verify and evaluate the applicant's statements and determine competency for qualification.
Information which the Department shall consider in determining whether a consultant is qualified to perform the types of work shall include:
Current license or registration as regulated by the State of Florida or national organizations, as appropriate.
Personnel with appropriate experience and training as detailed in the type of work qualifications.
Registration with the Florida Department of State, if the applicant is a corporation or limited partnership.
Past performance on Department contracts.
Integrity and responsibility, which shall include history of debarment or suspension from consideration for work with any other governmental entity.
Rule 14-75.0051(1), entitled "Revocation, Denial, or Suspension of Qualification," provides in part that "the Department will, for good cause, deny or suspend the qualification of any professional consultant, or other provider of service, to render services to the Department." "Good cause" includes instances where the consultant's work performance in one of the work types is not satisfactory. Unsatisfactory performance shall result in "revocation, denial, or suspension of qualifications for that type of work for a period not to exceed one year."
Rule 14-75.0051(1)(c), further provides that good cause also includes "any other good cause, as defined in Section 337.105(1), F.S., established by the factual circumstances."
Section 471.033, Florida Statutes, and Florida Administrative Code Chapter 61G15-19 establishes the grounds for disciplinary proceedings against licensed professional engineers in Florida. Under section 471.033, engaging in negligence or misconduct in the practice of engineering, or otherwise violation of chapter 455, Florida Statutes, are grounds for
disciplinary action against the status of a professional engineer’s license with the State of Florida. Under section 455.227(1)(o), performing professional responsibilities the licensee knows, or has reason to know, they are not
competent to perform constitutes grounds for disciplinary action against the status of a professional engineer’s license with the State of Florida.5
There is no evidence that BPA deviated from the standard of care for CEIs on design-build projects or that BPA failed to exercise its independent professional judgment regarding the FIU Bridge project.
The record is devoid of any evidence that DOT examined any of the criteria listed in rule 14-75.0022(4) to determine if BPA met qualification standards for 2019.
For "good cause," DOT relies entirely on the OSHA Report. The statements and opinions contained in the OSHA report are hearsay, and the author of the report was not called to testify as an expert and was not subject to cross-examination.
Absent from the OSHA report was any reference to BPA's design services because BPA had no design responsibility for the project. Yet it is this very document DOT relies on to deny BPA's request for qualification in all work groups, including those exclusively related to design, rather than CEI, work.
It is undisputable that the bridge collapse was a horrific tragedy with long term consequences to the community, the victims, and those involved with the project, including BPA and DOT. Understandably, it was politically expedient for DOT to disqualify those entities that worked on the FIU Bridge project. However, the plain language of the applicable statutes and regulations required DOT to engage in an analysis of BPA's 2019 Request for Qualification application. That analysis simply did not occur.
5 Florida Administrative Code Rule 61G15-19.001(6), defines the term "misconduct" as used in section 471.003 in part, as "[p]erforming an engineering assignment when not qualified by training or experience in the practice area involved." Although the Department cited
rule 61G15-19.001(6) in its Pre-Hearing Statement, none of the three instances of BPA’s alleged failure to exercise its independent professional judgment include an allegation that BPA undertook activities or services outside of its training or experience. This issue was not plead or framed by the Department’s Pre-Hearing Statement. At the Final Hearing, BPA contemporaneously objected to the presentation of evidence on this unpled theory that BPA allegedly performed services it was not prequalified to perform.
Under either a preponderance of the evidence, or by a clear and convincing evidentiary standard, DOT did not meet its burden with respect to the issues framed by its Pre-Hearing Statement and Notice of Intent to Deny.
Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered by the Department of
Transportation finding that good cause does not exist to deny BPA’s 2019 Request for Qualification.
DONE AND ENTERED this 17th day of April, 2020, in Tallahassee, Leon County, Florida.
S
MARY LI CREASY
Administrative Law Judge
Division of Administrative Hearings The DeSoto Building
1230 Apalachee Parkway
Tallahassee, Florida 32399-3060
(850) 488-9675
Fax Filing (850) 921-6847 www.doah.state.fl.us
Filed with the Clerk of the
Division of Administrative Hearings this 17th day of April, 2020.
COPIES FURNISHED:
George Spears Reynolds, IV, Esquire Florida Department of Transportation 605 Suwannee Street, Mail Stop 58
Tallahassee, Florida 32399-0450 (eServed)
Scott Kirschbaum, Esquire Cole, Scott & Kissane, P.A.
9150 South Dadeland Boulevard, Suite 1400
Miami, Florida 33156
Anthony Lopez, Esquire Cole, Scott & Kissane, P.A.
9150 South Dadeland Boulevard, Suite 1400
Miami, Florida 33156
George Richard Truitt, Esquire Cole, Scott & Kissane, PA
9150 South Dadeland Boulevard, Suite 1400
Miami, Florida 33156 (eServed)
John Ashley Peacock, Esquire Department of Transportation
605 Suwannee Street, Mail Stop 58
Tallahassee, Florida 32399-0450 (eServed)
Andrea Shulthiess, Clerk of Agency Proceedings Department of Transportation Haydon Burns Building
605 Suwannee Street, Mail Stop 58
Tallahassee, Florida 32399-0450 (eServed)
Erik Fenniman, General Counsel Department of Transportation Haydon Burns Building
605 Suwannee Street, Mail Stop 58
Tallahassee, Florida 32399-0450 (eServed)
Kevin J. Thibault, P.E., Secretary Department of Transporation Haydon Burns Building
605 Suwannee Street, Mail Stop 57
Tallahassee, Florida 32399-0450 (eServed)
NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
All parties have the right to submit written exceptions within 15 days from the date of this Recommended Order. Any exceptions to this Recommended Order should be filed with the agency that will issue the Final Order in this case.
Issue Date | Document | Summary |
---|---|---|
Jul. 16, 2020 | Agency Final Order | |
Jul. 16, 2020 | Agency Final Order | |
Apr. 17, 2020 | Recommended Order | DOT's reliance on the OSHA report and NTSB's investigation into the FIU bridge collapse was insufficient "good cause" to deny BPA's request for qualification for 2019. DOT failed to demonstrate BPA failed to exercise independent judgment as a CEI. |