Elawyers Elawyers
Ohio| Change

AVAGO TECHNOLOGIES FIBER IP (SINGAPORE) PTE. LTD. v. IPTRONICS INC., 5:10-cv-02863-EJD. (2015)

Court: District Court, N.D. California Number: infdco20150605987 Visitors: 13
Filed: Jun. 04, 2015
Latest Update: Jun. 04, 2015
Summary: ORDER DENYING MOTION FOR RELIEF FROM THE CASE SCHEDULE Re: Dkt. No. 520 EDWARD J. DAVILA , District Judge . I. INTRODUCTION Plaintiff Avago Technologies Fiber IP (Singapore) Pte. Ltd. initiated this case on July 29, 2010, asserting that then-defendants IPtronics Inc. and IPtronics A/S infringed two of its patents. See Docket Item No. 1. The parties then engaged in claim construction briefing and on September 4, 2012, the court issued an order construing the identified disputed terms fro
More

ORDER DENYING MOTION FOR RELIEF FROM THE CASE SCHEDULE

Re: Dkt. No. 520

I. INTRODUCTION

Plaintiff Avago Technologies Fiber IP (Singapore) Pte. Ltd. initiated this case on July 29, 2010, asserting that then-defendants IPtronics Inc. and IPtronics A/S infringed two of its patents. See Docket Item No. 1. The parties then engaged in claim construction briefing and on September 4, 2012, the court issued an order construing the identified disputed terms from both patents. See Docket item No. 258. Although nearly three years have passed since the claim construction ruling, not much has changed. The same patents are still in-suit.

There have been some changes on the business end, however. As often occurs in the industry, IPtronics A/S was purchased by Mellanox Technologies, Ltd. ("MTL"), its name was changed to Mellanox Technologies Denmark ApS, and its affairs were wound up. Plaintiffs were permitted to file a Fourth Amended Complaint to account for this change. See Docket Item No. 453. They were also permitted to join as defendants the corporate relations of the company formerly known as IPtronics A/S, MTL and Mellanox Technologies, Inc. ("MTI").

Defendants sought to have the claims reconstrued as a result of their entrance into the case. The court disagreed such proceedings were appropriate, explaining that "the Mellanox defendants will not be considered new parties, but rather have entered this action in place of IPtronics and take over the defense where IPtronics left off." See Docket Item No. 517. A case management order was issued without deadlines related to claim construction.

Unsatisfied with the court's explanation, Defendants filed the present motion which they style as one seeking relief from the case schedule. See Docket Item No. 520. Plaintiffs oppose the motion. Having carefully reviewed the arguments, the court is no more persuaded by Defendants' position now than it was previously. The time for claim construction has long since passed, and Defendants have provided no good reason to revisit it. Accordingly, this motion will be denied for the reasons articulated below.

II. DISCUSSION

Despite how Defendants have chosen to arrange this motion, this is essentially a motion seeking reconsideration of decisions the court has already made. Indeed, after reviewing a proposed stipulation submitted on January 22, 2015, which contemplated an additional round of claim construction, the court declined to enter the parties' proposed case schedule and instead ordered them "to file an updated Joint Case Management Conference Statement on or before January 29, 2015, which explains, inter alia, why additional claim construction proceedings should occur in this action." See Docket Item No. 509. The parties did so, and Defendants presented many of the same arguments in support of their position they now repeat in the instant motion. The court considered Defendants' arguments, found them uncompelling in light of its intimate experience with this action, and determined that further claim construction proceedings were unwarranted.

In addition, and although this is not entirely clear, it is worth noting that what Defendants appear to seek here is not the construction of newly-asserted claims or additional claim terms unique to them. Instead, what Defendants seem to want is a claim construction do-over.

The court, however, does not modify orders based on arguments already presented and rejected, nor does it arbitrarily erase work already done and reengage lengthy, time-consuming and expensive proceedings simply because a party asks for it. If that was how it worked, litigation would never conclude. Instead, Civil Local Rule 7-9 requires a party seeking leave to file a motion for reconsideration to make a specified showing: (1) "[t]hat at the time of the motion for leave, a material difference in fact or law exists from that which was presented," (2) "[t]he emergence of new material facts or a change of law occurring after the time of such order; or (3) "[a] manifest failure by the Court to consider material facts or dispositive legal arguments which were presented to the Court before such interlocutory order."

Construing this motion as it should be construed under Rule 7-9, Defendants have failed to justify the need for any sort of relief. They cite no material differences in fact or law, new or otherwise, that have occurred since the court denied Defendant's request for more claim construction.

Nor have Defendants demonstrated some failure to consider material facts or dispositive legal arguments. In this motion, Defendants argue that due process and fairness should entitle them to bypass a significant ruling entered after extensive efforts by all involved. But Defendants already raised this issue in response to the court's request to explain why further claim construction was necessary. There, Defendants indicated at the outset that "[t]he claim construction proceedings are required to allow Mellanox, who has not had an opportunity to present its claim construction issues to the Court, to present any claim constructions issues it may have in accordance with the Local Rules." See Docket Item No. 513. The court read that contention, as it has again in examining this motion, and considered whether or not MTL and MTI would be denied process if it could not present "its claim construction issues," whatever those may be. The court determined that no such denial would occur because it was not, and still has not, been shown that the interests of MTL and MTI are different from, in conflict with, or adversarial to those of the former IPtronics A/S. In fact, the opposite seems to be true. It is admitted that Defendants are related companies, given that MTL acquired IPtronics A/S and changed its name to Mellanox Technologies Denmark ApS, and since each defendant is represented by the same attorneys in this action, the likelihood of disparate interests between them is negligible, if not altogether impossible. The fact they are separate legal entities is of no moment under these circumstances.

The court has reviewed Defendants' legal citations but finds then unpersuasive. None address the situation presented here: whether claim construction must be redone when one company acquires another in the midst of patent litigation. In contrast, they each address whether a defendant is entitled to de novo construction of claim terms previously construed in separate litigation against an unrelated defendant. See Tex. Instruments, Inc. v. Linear Techs. Corp., 182 F.Supp.2d 580 (E.D. Tex. 2002) (holding that constructions issued by one court within litigation against Hyundai Electronics Industries Company do not preclude the construction of those same terms in later litigation against Linear Technologies Corporation); see also Nilssen v. Motorola, Inc., 80 F.Supp.2d 921 (N.D. Ill. 2000) (stating, in a footnote, that independent construction of claim terms would occur even though another judge had construed the same terms in an action against another defendant). They also support this court's opinion that only later-sued defendants with "competing interests and strategies" are entitled to an individualized claim construction hearing. See, e.g., WiAV Networks LLC v. 3COM Corp., No. C 10-03448 WHA, 2010 WL 3895047, at *2, 2010 U.S. Dist. LEXIS 110957 (N.D. Cal. Oct. 1, 2010).

There is rarely a complete "win" in litigation, and the disappointed side of the case cannot sidestep a ruling just because it is not enamored with it. Yet that is exactly what Defendants have tried to do here. Defendants may not like the claim construction order, but that is the order that was entered in this case. In the end, no violation of due process or general fairness can be sustained due to the alliance of interests between MTL, MTI and the company that was IPtronics A/S. There is no reason to conclude otherwise based on this record.

III. ORDER

The Motion for Relief from the Case Schedule (Docket Item No. 520) is DENIED.

IT IS SO ORDERED.

Source:  Leagle

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer