JOHN A. MENDEZ, UNITED STATES DISTRICT JUDGE.
This litigation concerns three species of threatened fish and two federally-managed dams in the Yuba River. Friends of the River ("Plaintiff" or "FOR") sued the United States Army Corps of Engineers (the "Corps") and National Marine Fisheries Service ("NMFS") (collectively, "Federal Defendants") alleging violations of the Endangered Species Act and Administrative Procedures Act. Yuba County Water Agency ("YCWA" or "Intervenor") intervened in the case. ECF No. 16. Parties filed cross-motions for summary judgment, ECF Nos. 33, 38, 41, which were followed by opposition and reply briefs, ECF Nos. 49, 54, 57. For the reasons set forth below, the Court DENIES Plaintiff's motion, GRANTS Federal Defendants' motion, and GRANTS Intervenor's motion.
The Endangered Species Act of 1973 (ESA) "reflects a conscious decision by Congress to give endangered species priority over the primary missions of federal agencies."
Agency actions that "may affect" a listed species require the acting agency to formally consult with the federal agency responsible for protecting that species. 50 C.F.R. § 402.14(a);
At the end of the formal consultation process, the Secretary of the consulting agency — here, NMFS — must issue a Biological Opinion ("BiOp").
The ESA also prohibits any federal agency from "taking" a listed species. 16 U.S.C. § 1538(a)(1)(B). "Take" is defined as meaning "to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage in any such conduct." 16 U.S.C. § 1532(19). Where a taking is incidental to, rather than the purpose of, a federal action, it is referred to as an incidental take. 16 U.S.C. § 1536(b)(4); 50 C.F.R. § 17.3. An incidental take may be permitted if the consulting agency issues the acting agency an incidental take statement along with the BiOp. 50 C.F.R. § 402.14(i). If the acting agency subsequently modifies the action "in a manner that causes an effect to the listed species or critical habitat that was not considered in the [BiOp]," or if the acting agency exceeds the take authorized in the incidental take statement, the agencies must reinitiate formal consultation. 50 C.F.R. § 402.16.
The Administrative Procedure Act (APA) provides for judicial review of federal agencies' final actions. 5 U.S.C. § 702;
The same standard applies to both new agency policies and changes to previous agency positions.
Central Valley spring-run Chinook salmon ("spring Chinook"), Central Valley steelhead ("steelhead"), and the Southern Distinct Population Segment of North American green sturgeon ("green sturgeon") are anadromous fish. Corps R. 532:42347-42458. Born into freshwater, anadromous fish migrate to the ocean as juveniles and return to freshwater as adults to spawn and die.
Habitat blockage by dams and the degradation and destruction of habitat has decimated fish populations. Corps R. 532:42358. Current populations are a fraction of their historical abundance. Corps R. 532:42351, 42397, 42441. Due to these declines, NMFS listed the spring Chinook, steelhead, and green sturgeon (collectively, "the Listed Species") as threatened under the ESA. 64 Fed. Reg. 50,394 (Sept. 16, 1999) (spring Chinook); 71 Fed. Reg. 834 (Jan. 5, 2006) (steelhead); 71 Fed. Reg. 17,757 (April 7, 2006) (green sturgeon). The Yuba River makes up a portion of the critical habitat for each of the Listed Species. 70 Fed. Reg. 52,488 (Sept. 2, 2005) (spring Chinook, steelhead); 74 Fed. Reg. 52300 (Oct. 9, 2009) (green sturgeon). Despite their listed status, the three species continue to swim towards extinction.
The Yuba River is a Northern California river that flows into the Sacramento and Feather Rivers.
The California Debris Commission constructed Daguerre Point Dam in 1906, diverting the river around it in 1910. Corps R. 532:42464-65. At only 24 feet high, the dam was originally operated to retain mining debris and serves no flood control purpose. Corps R. 532:42322. Daguerre Point Dam serves as a partial to complete barrier in fish passage along the Yuba River. Corps R. 532:42465. Some salmon and steelhead have been able to surmount the dam since fish ladders were constructed in the early 1920s.
The River and Harbors Act of 1935, Pub. L. 409, 74th Congress, approved August 30, 1935, 49 Stat. 1028, authorized construction of public works in the Sacramento River and its tributaries.
The Fish and Wildlife Coordination Act, enacted in 1934, required consultation with the Bureau of Fisheries to prevent loss and damage to wildlife before constructing a water impoundment like Englebright Dam.
This case is one in a series of cases regarding the impact of dams, hydropower facilities, and water diversions on Listed Species within the Yuba River. There are three prior cases within this district.
The first consultation between the Corps and NMFS regarding Yuba River activities occurred around 2000, in response to a lawsuit brought by the South Yuba River Citizens League (SYRCL). Corps R. 356:23031. That year, the Corps requested formal consultation with NMFS in a BA regarding the impact of Englebright and Daguerre Point Dams and water diversions on spring Chinook and steelhead. Corps R. 171:12759. In 2002, NMFS issued a BiOp finding that the dams' operations were not likely to jeopardize the continued existence of the spring Chinook and steelhead or destroy or adversely modify designated critical habitat. Corps R. 356:23066. According to the 2002 BiOp, "[t]he proposed action ... is the continuation of current Corps operations of Englebright and Daguerre Point Dams," and "[a]n important component of the Corps operations is the issuance of permits, licenses and easements to non-federal entities for their operations of water diversion facilities at or near the dams." Corps R. 356:23033.
The Corps's 2007 BA similarly defined the agency action as the "continuation of current Corps operations associated with Englebright and Daguerre Point Dams on the Yuba River" with respect to its impact on spring Chinook, steelhead, and green sturgeon. Corps R. 178:13641-42. In the 2007 final BiOp, NMFS again determined that the agency action was not likely to jeopardize the List Species, but found a
In 2012, the Corps prepared a BA that defined the agency's action differently. Relying on the 1998 FWS and NMFS ESA Consultation Handbook, the Corps determined that the future effects of the dams' presence should be included in the environmental baseline. Corps R. 186:14185. The Corps made this finding based on the argument that the agency did not have the authority to change the presence of these preexisting facilities.
The Corps had "serious concerns" regarding the 2012 BiOp and sought to reinitiate consultation based on "new information." Corps R. 544:43422. In 2013, the Corps reasserted its argument that the dams' continued existence was not an agency action because it was non-discretionary. Corps R. 81:4074. The Corps also broke up what it previously considered one "agency action" along the Yuba River into multiple smaller parts, separating actions connected with the Englebright Dam, Daguerre Point Dam, and licensing. Corps R. 80:4030. The Corps postponed consultation on outgrants for the Narrows I and II and an easement for the Brophy diversion to a later date. Corps R. 81:4095-96. The 2013 Daguerre Point BA sought formal consultation, while the 2013 Englebright BA sought only informal consultation. Corps R. 81:4053.
In May 2014, NMFS changed course from its prior opinion in the 2012 BiOp. Corps R. 532, 581. In its 2014 Englebright Letter of Concurrence ("Letter of Concurrence"), the agency agreed that the Corps's proposed action at Englebright was not likely to adversely affect the Listed Species. Corps R. 581:48897. Similarly, in the 2014 Daguerre Point Dam BiOp ("2014 BiOp"), NMFS concluded that the Corps's proposed action at Daguerre Point was not likely to jeopardize the Listed Species. Corps R. 532:42637.
Plaintiff brought this suit against NMFS and the Corps, as well as the Bureau of Land Management ("BLM"), in April 2016. ECF No. 1. The parties stipulated to dismiss BLM from the case in November 2016. Order, ECF No. 24. In its Amended Complaint, Plaintiff seeks declaratory and injunctive relief.
Plaintiff alleges nine causes of action in its Amended Complaint: one APA claim against the Corps for issuing the 2013 Englebright BA (Count I); four APA claims against NMFS for concurring with the Englebright BA (Count II), issuing the 2014 BiOp (Count III), rescinding the 2012 BiOp (Count IV), and failing to reinitiate consultation with the Corps (Count IX); and four ESA claims against the Corps for inadequate consultation with NMFS (Count V), jeopardizing the Listed Species (Count VI), taking the Listed Species (Count VII), and failing to reinitiate consultation with NMFS (Count VIII). Am. Compl. at 26-38, ¶¶ 96-146.
Following the submission of cross-motions on summary judgment, Plaintiff moved to strike portions of Federal Defendants' Statements of Facts. Mot. Strike II, ECF No. 56. Arguments on the summary judgment motions and the Motion to Strike were heard at oral argument on November 21, 2017. Minute Order, ECF No. 61.
The parties have filed cross-motions for summary judgment. Summary judgment is the appropriate mechanism
Apart from the APA, the Court also grants deference to an agency's interpretation of the statutes and regulations that define the scope of its authority.
In the absence of those formal procedures, other types of deference may still apply. Under
Where an agency's construction of a statute or regulation does not qualify for either
As an initial matter, Federal Defendants have not disputed that Plaintiff, an environmental organization, has standing in this case.
The only party whose standing has been challenged is Intervenor, by Plaintiff in its Reply Brief. FOR Reply, ECF No. 54, pp. 2-4. Plaintiff challenged Intervenor's standing to advance the arguments made in Intervenor's Motion for Summary Judgment.
Earlier in this case, the Court granted Intervenor's unopposed Motion to Intervene as a matter of right. Intervention Order, ECF No. 18. Plaintiff did not oppose that motion.
Plaintiff filed a motion to strike the legal arguments Federal Defendants inserted
The Court treats Federal Defendants' additional objections as factual disputes. Neither Plaintiff's nor the Federal Defendants' statements at oral argument were of help to the Court, as neither party disputes that the Court need not make findings of fact.
Plaintiff seeks to rely on evidence out-side the administrative record to support its claims. FOR Opp'n, ECF No. 49, p. 1. Federal Defendants counter that the scope of review is limited to the administrative record for both APA and ESA claims. Joint Reply, ECF No. 59, p. 1.
In the Ninth Circuit, claims brought under the ESA's citizen suit provision are not subject to the same scope of review restrictions as claims brought under the APA.
Accordingly, the Court has limited its review to the record on Plaintiff's APA claims and has considered extra-record materials with regard to Plaintiff's ESA citizen-suit claims in addition to the over 160,000 pages of the administrative record provided by Federal Defendants.
Eight of Plaintiff's nine claims relate to Federal Defendants' Section 7 consultation duties. In Claim I, Plaintiff argues that the Corps's 2013 Englebright Dam BA violated the APA because it (1) asserted that maintaining the Englebright Dam is not an action subject to consultation; (2) found that the Englebright Dam's maintenance was nondiscretionary; (3) denied that adverse effects on the Listed Species and critical habitat caused by Englebright Dam's existence were effects of the action; and (4) segregated out permits, licenses,
Claim V argues that the Corps violated its procedural duties under ESA Section 7(a)(2) by failing to adequately consult with NMFS about the Corps's Yuba River activities.
At the heart of Plaintiff's Section 7 claims lies a dispute over the scope and definition of the Corps's agency action. According to Plaintiff, Federal Defendants improperly defined, narrowed, segmented, and analyzed the present action in a manner that differed from their previous interpretations.
To weigh the parties' arguments, the Court considers Plaintiff's numerous challenges presented individually. First, the Court resolves whether the Corps's 2013 Englebright BA may be subject to judicial review. Second, the Court examines what actions fall within the environmental baseline, separate from the present agency action. Third, the Court determines whether the Corps's activities fit the ESA's broad definition of agency action. Within this inquiry, the Court explores whether the Corps's activities are (i) affirmative and (ii) discretionary actions that are (iii) guaranteed to occur and (iv) include interrelated and interdependent activities. Fourth, the Court considers whether Federal Defendants properly determined the scope of the action area in the 2013 and 2014 documents. Fifth, the Court reviews the sufficiency of the consultation between the Federal Defendants, including whether (i) NMFS has a duty to reidentify the agency action; (ii) the agency action at Englebright required formal consultation; and (iii) the Corps violated its duty to ensure against jeopardy. Sixth, the Court examines whether any changes in position by Federal Defendants were adequately explained. Seventh, the Court evaluates whether Federal Defendants had a duty to reinitiate consultation.
Section 704 of the APA provides that "final agency action for which
Here, NMFS's Letter of Concurrence expressly relied upon the findings of the Corps's 2013 Englebright BA to find that the action was not likely to adversely impact the Listed Species. Corps R. 581:48881-99. No formal consultation or BiOp took place because of reliance on the BA's determinations and information. While the Letter of Concurrence constitutes the final agency action, the Court is unable to meaningfully analyze it without referencing the BA upon which it was based. So the Court considers the Corps's 2013 Englebright BA to be a final agency action, reviewable under the APA.
The "agency action" is defined as "all activities or programs of any kind authorized, funded, or carried out, in whole or in part, by Federal agencies in the United States or upon the high seas." 50 C.F.R. § 402.02. Distinct from the agency action is the "environmental baseline," to which effects of the agency action are added. 50 C.F.R. § 402.02. The environmental baseline includes "the past and present impacts of all Federal, State or private actions and other human activities in the action area" and "the anticipated impacts of all proposed Federal projects in the action area that have already undergone formal or early section 7 consultation."
In evaluating the environmental baseline in
The Court finds that Federal Defendants provided a satisfactory and thorough explanation for their actions and therefore did not act arbitrarily or capriciously by properly including effects of the dams' existences in the environmental baseline.
The Court construes the term "agency action" broadly.
"An agency must consult under Section 7 only when it makes an `affirmative' act or authorization."
Conversely, the Ninth Circuit has found that a failure to act does not require consultation under Section 7(a)(2).
Plaintiff asserts that the Corps's affirmative actions consisted of (1) the dams' operations and maintenance and (2) operation of ancillary facilities near the dams. Here, the present operations described by the Corps for Englebright Dam include visual security and safety inspections, maintenance of recreational facilities, continued administration of maintenance service contracts, and continued administration of outgrants. Corps R. 581:48882-83. The Corps wrote that operation of out-grants associated with the Englebright Dam hydropower facilities were future actions for which the Federal Energy Regulatory Commission would consult in 2016 and 2023. Corps R. 581:48882. At Daguerre Point Dam, the Corps described its present operations as operating and maintaining the fish passage facilities, maintaining a staff gage, administering licenses for observing fish and installing flashboards, and conservation measures. Corps R. 532:42332-33.
The activities listed by the Corps as actions in the Englebright and Daguerre Point Dams BAs constitute activities affirmatively carried out by a federal agency. 50 C.F.R. § 402.02. Plaintiff has not identified
The Supreme Court has noted that an overly broad reading of ESA Section 7(a)(2), 16 U.S.C. § 1536(a)(2), would "cover[], in effect, almost anything that an agency might do" and "partially override every federal statute mandating agency action."
Section 7 does not require consultation for actions "that an agency is
The Ninth Circuit has considered the discretionary nature of actions several times since the Supreme Court's
Here, where there are multiple dams that were authorized by separate acts and built at different times, several sources of legislative authority must be considered. The Corps cited nine authorities that govern their discretion over the present actions. Corps R. 81:4626-4639, 532:42326-27. Those authorities are (1) The California Debris Act; (2) The Rivers and Harbors Act of 1935; (3) Flood Control Act of 1970; (4) National Dam Inspection Act of 1972; (5) Water Resources Development Act 1986; (6) Water Resources Development Act 1996; (7) National Dam Safety Program Act of 1996; (8) Public Law 109-460; and (9) Engineer Regulation 1105-2-100.
The California Debris Act, 33 U.S.C. §§ 661,
The Flood Control Act of 1970, Section 216, authorizes the Corps to review projects and report "to Congress with recommendations on the advisability of modifying the structures or their operation, and for improving the quality of the environment in the overall public interest." 33 U.S.C. § 549a. The Water Resources Development Act of 1986 and 1996 further authorize the Corps to perform ecosystem restoration, subject to certain limitations. 33 U.S.C. § 2283(b); 33 U.S.C. § 2330(a)(1).
In the realm of dam safety, the National Dam Inspection Act, Pub. L. 92-367 (Aug. 8, 1972) authorizes the Corps to carry out a national program of inspection of non-Federal dams for the purpose of protecting human life and property. The National Dam Safety Program Act of 1996, Pub. L. 104-303 (Oct. 12, 1996), amended in 2006, Pub. L. 109-460 (Dec. 22, 2006), goes further to require Secretary of the Army to undertake a national dam inspection program. 33 U.S.C. § 467d. The Engineering Regulations require authorization by Congress when project purposes are added or deleted. Corps R. 81:4635.
Plaintiff has identified several statutes that it believes grant the Corps broad discretion to determine whether or how to maintain the dams. FOR MSJ, ECF No. 33, pp. 11-12. Those statutes describe the Corps's general duty to adopt plans that improve river navigability, 33 U.S.C. § 664; ability to construct sediment-impounding dams "when appropriations are made therefor by law," 33 U.S.C. § 685; responsibility to include environmental protection as one of its primary missions in operating and maintaining water resources projects, 33 U.S.C. § 2316; authorization to carry out a program to improve environmental quality when feasible and consistent with the project's authorized purpose, 33 U.S.C. § 2309a(a-b); capability to carry out a project that improves the environment's quality and is cost effective, including dam removal, 33 U.S.C. § 2330(a)(1-2); and duty to mitigate fish and wildlife losses for projects constructed after November 17, 1986, 33 U.S.C. § 2283.
The Court has carefully reviewed these sources and finds that the Corps does not have the discretion to discontinue dam inventory and safety inspections. The Corps properly classified these actions as non-discretionary, which does not require Section 7 consultation.
In Claim III, Plaintiff further argues that it was improper for NMFS to consider voluntary conservation measures, subject to funding availability, as part of the agency action in the 2014 BiOp. Am. Compl. at 28-29, ¶ 107. Federal Defendants fail to address this issue in their briefing.
The 2013 Daguerre Point Dam BA includes both "protective conservation measures," which the Corps has committed to incorporate into the Proposed Action, Corps R. 81:4518, and "voluntary conservation measures," which are "subject to the availability of funding." Corps R. 81:4522.
NMFS may rely on mitigation measures to support a finding that an agency action poses no jeopardy to the Listed Species.
Where the allegedly defective mitigation measure was not the primary reason for the agency's no-jeopardy finding, other courts have declined to invalidate the BiOp.
Similar to
Several of Plaintiff's claims take issue with the Corps's exclusion of its issuance and administration of permits, licenses, contracts, and easements from the proposed actions in the 2013 BAs. Am. Compl., pp. 26-28, ¶¶ 97, 107. Plaintiff argues that Federal Defendants acted arbitrarily and capriciously by dividing up activities at Englebright, Daguerre, and the Licensed Facilities into separate unrelated agency actions with smaller action areas. FOR MSJ at 15. The Court disagrees.
While ESA regulations make clear that the Corps's issuance of permits, licenses, contracts, and easements all qualify as "actions" under the ESA.
The ESA requires the consulting agency to consider the "entire agency action."
Segmented consultations of a single agency action are counter to the ESA's requirements because an "agency action could ultimately be divided into multiple small actions, none of which, in and of
Plaintiff argues that the licenses and contracts are interrelated because (1) the two dams were built as part of "an integrated project" to control mining debris within the Yuba River; (2) the Brophy Diversion depends on the existence of the Daguerre dam for its head; (3) the Cordua Diversion is physically attached to Daguerre; and (4) the Narrows 1 and 2 powerhouses draw water from the Englebright Reservoir and their operations are coordinated with the dam. FOR MSJ at 13-14. The Court finds that these activities, however, do not form part of a larger cohesive action. They do not meet the definitions of interrelated or interdependent actions because they do not depend on the presently proposed agency actions — outgrants, recreational activities, and fish ladders — for their justification and have independent utility apart from the proposed actions.
When renewed, these licenses and contracts will be their own agency actions, subject to consultation requirements where the agency yields discretion. Federal Defendants' exclusion of activities from the 2013 Englebright BA and 2014 BiOp was not arbitrary or capricious.
In Claim III, Plaintiff asserts that NMFS violated the APA by improperly identifying the "action area" within the 2014 BiOp. Am. Compl. ¶ 109. Plaintiff contends that the smaller action area in the BiOp failed to consider impacts from Englebright Dam and Narrows 2 in its jeopardy and adverse modification analysis. FOR MSJ at 15 n.10.
"Action area" is defined as "all areas to be affected directly or indirectly by the Federal action and not merely the immediate area involved in the action." 50 C.F.R. § 402.02. Generally, "determination of the scope of an analysis area requires application of scientific methodology and, as such, is within the agency's discretion."
The ESA Consultation Handbook provides that the description of the action area is a biological determination for which the consulting agency — here, NMFS — is responsible. Corps R. 472:37064. Although agreement between the Corps and NMFS is "desirable,"
The 2014 BiOp defines the action area as including "the lower Yuba River starting at a point approximately 135 feet upstream of the downstream of the Narrows II powerhouse and approximately 415 feet downstream of Englebright Dam, downstream to the confluence of the Yuba and Feather rivers." Corps R. 532:42345. The 2014 BiOp goes on to acknowledge that the Listed Species may swim further upstream than the boundary of the action area, up
Although NMFS's action area determination could have been more detailed, this "biological determination" qualifies as a scientific judgment for which the Court must be "at its most deferential."
Plaintiff argues that NMFS abdicated its responsibility to "correctly identify the action that is subject to consultation." Am. Compl. at 28-29. Quoting from the ESA Consultation Handbook, Plaintiff argues that NMFS need not agree with the Corps's identification of the agency action or action area and must instead make its own independent determination. FOR Opp'n at 4.
The statute and accompanying regulations are not clear about the discretion that the consulting agency has to reidentify or redefine the agency's proposed action.
The ESA Consultation Handbook, to which the Court affords
Based on the Handbook's language and the Court's deference to it, the Court finds that NMFS did not act arbitrarily or capriciously in accepting the Corps's identified agency action.
In several claims against Federal Defendants, Plaintiff alleges that the agencies have improperly determined that the proposed action at Englebright is not likely to adversely affect the Listed Species
"If an agency determines that action it proposes to take may adversely affect a listed species, it must engage in formal consultation."
As analyzed above, the Court has found that Federal Defendants' identification of the proposed actions and the Corps's discretion is not arbitrary and capricious. Review of the 2013 Englebright Dam BA and Letter of Concurrence illustrates that Federal Defendants thoroughly reviewed the proposed actions during informal consultation and provided plausible explanations for the finding that these actions were not likely to adversely affect the Listed Species and their critical habitat.
Plaintiff's Claim VI asserts that the Corps violated its duty to ensure against jeopardy, in violation of Section 7(a)(2). Am. Compl. at 31-32 ¶¶ 118-22. Plaintiff bases this claim on the alleged insufficiency of the Letter of Concurrence and 2014 BiOp, as well as "new information" about and a modification of the actions.
"Section 7 of the ESA imposes a substantive duty on the [agency] to ensure that its actions are not likely to jeopardize the continued existence of the listed fish or result in destruction or adverse modification of critical habitat."
Here, the Court has determined that the 2014 BiOp upon which the Corps relied was not flawed, but rather evaluated the agency action and scope of discretion in far greater detail than any of the prior documents. This enhanced scrutiny resulted in NMFS reaching different conclusions and recommendations than were made in the 2012 BiOp. While the scientific information makes clear that the baseline conditions jeopardize the Listed Species, Plaintiff has not provided information that indicates the present proposed actions increase that risk by causing additional harm.
The Court finds that the Corps did not violate its substantive duty under Section 7(a)(2).
In Claim III, Plaintiff alleges that NMFS insufficiently explained the changes in its reasoning between the 2012 BiOp and 2014 BiOp. Am. Compl. 29, ¶ 108.
As the Ninth Circuit recently noted in
The Corps has thoroughly explained the differences in its reasoning from prior BAs.
NMFS's description of its change in reasoning is less detailed. For the most part, NMFS appears to adopt the Corps's reasoning and reconsiders its prior BiOp based on this change:
Corps R. 532:42345. NMFS's explanation, albeit quite brief, indicates that it examined the relevant data, made a rational connection between the facts, and explained its change in position from the 2012 BiOp to the 2014 BiOp and Letter of Concurrence. The Court finds that NMFS's change in position was not arbitrary or capricious.
Plaintiff's eighth and ninth claims allege that Federal Defendants violated the ESA (Claim VIII) and APA (Claim IX) when they failed to reinitiate consultation after the issuance of new information. Am. Compl. at 34-38, ¶¶ 133-46.
"The ESA's implementing regulations require an action agency to reinitiate formal consultation with the consulting agency when `new information reveals effects of the action that may affect listed species or critical habitat in a manner or to an extent not previously considered' (the `new information' reinitiation trigger)."
The Ninth Circuit has found reinitiation is appropriate where a new critical habitat was designated,
Plaintiff believes that new studies and plans, such as the Yuba River Ecosystem Restoration Reconnaissance Study and Habitat Management and Restoration Plan, provide a basis upon which to reinitiate consultation between the agencies. Am. Compl. at 35, ¶¶ 136-37. While Plaintiff repeatedly states that the study and plan provide "new information," at no point does Plaintiff provide any guidance as to how that information details effects not previously considered in the consultation.
As further evidence of new information, Plaintiff's motion cites the declaration of a fisheries biologist who states that the conservation measures in the 2014 BiOp have not improved conditions for the Listed Species because the dams block migration and populations of the Listed Species have continued to decline. FOR MSJ at 22-23; Reedy Decl. ¶¶ 10, 14-20, 25; Ex. B, C. The biologist also states that the large woody material management program did not function as planned because materials washed away during large storm events. Reedy Decl. ¶¶ 24-25, Ex. F. High storm flows similarly closed the fish ladders in early 2017, months after Plaintiff filed its Amended Complaint. Reedy Decl. ¶ 22, Ex. D.
The ESA requires a plaintiff to provide notice of a violation at least sixty days prior to filing suit. 16 U.S.C. § 1540(g)(2)(A)(i). The Supreme Court has concluded strict compliance with citizen-suit timeliness and identification requirements best serves the goal of the notice requirement.
Here, many of the violations alleged in Plaintiff's Motion for Summary Judgment arose not only after Plaintiff's notice to Federal Defendants, but also after amendment of the complaint in December 2016. Plaintiff's notice and reinitiation claims do not adequately notify Federal Defendants of violations arising from new circumstances like the storm events in 2017. Thus, these events fail to provide cause to order Federal Defendants to reinitiate consultation.
In conclusion, the Court grants summary judgment to Federal Defendants and Intervenor on all claims arising under Section 7. Claim I is denied because Plaintiff has not shown that the Corps's 2013 Englebright Dam BA was arbitrary or capricious in its assessment of the present proposed action, the Corps's discretion, and adverse effects. Claim II is denied because Plaintiff has not shown that NMFS was arbitrary or capricious in concurring with the 2013 Englebright Dam BA. Claim III is denied because Plaintiff failed to show that NMFS acted arbitrarily or capriciously in its change of position and issuance of the 2014 BiOp. Claim IV is denied because Plaintiff has not shown NMFS's replacement of the 2012 BiOp with the 2014 BiOp was arbitrary or capricious. Claims V, VIII, and IX are denied because Plaintiff failed to show that Federal Defendants consultation was insufficient and that new information required Federal Defendants to reinitiate consultation. Claim VI is denied because Plaintiff did not show that the Corps violated its duty not to jeopardize Listed Species.
Plaintiff also brings a takings claim under Section 9. Plaintiff's Claim VII alleges that the Corps has violated ESA by taking the Listed Species without authorization. Am. Compl. at 32-34, ¶¶ 123-32. Plaintiff argues that the taking results from the continued existences of the two dams, as well as the fish ladders at Daguerre Point Dam and introduction of invasive species through recreational activities.
"All persons, including federal agencies, are specifically instructed not to "take" endangered species."
NMFS granted the Corps an incidental take statement for its activities related to sediment removal, maintenance and debris removal in the fish ladders, gravel augmentation, and woody instream material management. Corps R. 532:42637-40. Should the Corps exceed the amount or extent of taking specified in the incidental take statement, the agencies must reinitiate consultation. 50 C.F.R. § 402.16. Taking within the limits of the incidental take
The main harms Plaintiff alleges, apart from those covered by the incidental take statement, flow from the dams' existences. The Court has already found Federal Defendants did not act arbitrarily or capriciously in concluding that the dams' existences do not constitute a present or continuing "agency action." Even if the dams' existences did constitute an agency action, this action appears to be outside the agency's discretion. While the Ninth Circuit has not clearly spoken on this issue, a similar case in this district found that an agency cannot be liable where it has no discretion over the activities resulting in the alleged taking.
Relying on the Supreme Court's reasoning in
Because the Corps has not affirmatively engaged in a discretionary activity that had prohibited impact on the Listed Species, Plaintiff has not proven a violation of Section 9.
For the reasons set forth above:
(1) Plaintiff's Motion for Summary Judgment is DENIED;
(2) Federal Defendants' Motion for Summary Judgment is GRANTED; and
(3) Intervenor's Motion for Summary Judgment is GRANTED.
IT IS SO ORDERED.