Filed: Jun. 14, 2005
Latest Update: Mar. 02, 2020
Summary: Opinions of the United 2005 Decisions States Court of Appeals for the Third Circuit 6-14-2005 Longport Ocean Plaza v. Robert Cato Assoc Precedential or Non-Precedential: Non-Precedential Docket No. 03-3814 Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2005 Recommended Citation "Longport Ocean Plaza v. Robert Cato Assoc" (2005). 2005 Decisions. Paper 1022. http://digitalcommons.law.villanova.edu/thirdcircuit_2005/1022 This decision is brought to you for
Summary: Opinions of the United 2005 Decisions States Court of Appeals for the Third Circuit 6-14-2005 Longport Ocean Plaza v. Robert Cato Assoc Precedential or Non-Precedential: Non-Precedential Docket No. 03-3814 Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2005 Recommended Citation "Longport Ocean Plaza v. Robert Cato Assoc" (2005). 2005 Decisions. Paper 1022. http://digitalcommons.law.villanova.edu/thirdcircuit_2005/1022 This decision is brought to you for ..
More
Opinions of the United
2005 Decisions States Court of Appeals
for the Third Circuit
6-14-2005
Longport Ocean Plaza v. Robert Cato Assoc
Precedential or Non-Precedential: Non-Precedential
Docket No. 03-3814
Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2005
Recommended Citation
"Longport Ocean Plaza v. Robert Cato Assoc" (2005). 2005 Decisions. Paper 1022.
http://digitalcommons.law.villanova.edu/thirdcircuit_2005/1022
This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
University School of Law Digital Repository. It has been accepted for inclusion in 2005 Decisions by an authorized administrator of Villanova
University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
NOT PRECEDENTIAL
UNITED STATES COURT OF APPEALS
FOR THE THIRD CIRCUIT
No. 03-3814
No. 03-3882
LONGPORT OCEAN PLAZA CONDOMINIUM, INC.
v.
ROBERT CATO & ASSOCIATES, INC., ET AL.
and
THE WINDOW ASSOCIATES, INC., ET AL.
The Window Associates, Inc.,
Appellant in No. 03-3814
LONGPORT OCEAN PLAZA CONDOMINIUM, INC.
v.
ROBERT CATO & ASSOCIATES, INC., ET AL.
and
THE WINDOW ASSOCIATES, INC., ET AL.
Robert Cato & Associates, Inc.,
Appellant in No. 03-3882
ON APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE
EASTERN DISTRICT OF PENNSYLVANIA
(Dist. Court Nos. 00-cv-02231 and 02-cv-01724)
District Court Judge: The Honorable Ronald L. Buckwalter
Argued: May 27, 2005
Before: SCIRICA, Chief Judge, ALITO and GARTH, Circuit Judges
(Opinion Filed: June 14, 2005)
PAUL A. LISOVICZ (Argued)
TIMOTHY P. SMITH
Coughlin Duffy Kelly Lisovicz Midlige & Wolff, LLP
350 Mount Kemble Avenue
P.O. Box 1917
Morristown, NJ 07962-1917
Counsel for Appellant Robert Cato & Associates, Inc.
RICHARD H. MARTIN (Argued)
MICHAEL P. DEVLIN
Montgomery, McCracken, Walker & Rhoads, LLP
123 South Broad Street
Philadelphia, PA 19109-1099
Counsel for Appellee Longport Ocean Plaza
BARBARA S. MAGEN
GLENN M. CAMPBELL
SHEILA A. HAREN
Post & Schell
1600 John F. Kennedy Boulevard
Four Penn Center, 13 th Floor
Philadelphia, PA 19103
Counsel for Appellee Melrose Enterprise, Inc.
2
OPINION OF THE COURT
PER CURIAM:
Because we write for the parties only, we do not set forth the facts of this case.
Robert Cato & Associates, Inc. (“Cato”) appeals from an award of attorney’s fees and
costs to Longport Ocean Plaza Condominium, Inc. (“Longport”).1 Cato argues that its
contracts with Longport do not provide for the award with the clarity required for them to
be enforced under New Jersey law. We agree with Cato, and we vacate the award.
I.
An award of fees is reviewed for abuse of discretion, but the District Court’s
underlying legal conclusions receive plenary review. See Rode v. Dellarciprete,
892 F.2d
1177, 1182 (3d Cir. 1990). Such conclusions include the Court’s construction of the two
contracts at issue. See Ram Constr. Co. v. Am. States Ins. Co.,
749 F.2d 1049, 1053 (3d
Cir. 1984). Since the District Court’s award depended on its construction of those
contracts, this Court’s review is effectively plenary.
II.
Longport makes two preemptive attacks on Cato’s appeal. It first argues that the
Court lacks jurisdiction to review the award because Cato’s notice of appeal was
1
The Window Associates, Inc., raises its own claims against Longport in No. 03-
3814, though it also joins in Cato’s briefs in No. 03-3882. With the exception of footnote
2, this opinion discusses only Cato’s claims, the remainder of the appeal having been
assigned to mediation.
3
defective. It then argues that Cato failed to preserve its argument that the District Court
misinterpreted the indemnification clauses. Neither claim has merit.
Cato did not file an amended notice after either the October 2003 order modifying
the award or the December 2003 order entering judgment. According to Longport, these
omissions leave this Court without jurisdiction over either order. See Fed. R. App. P.
4(a)(4)(A)(i), (iii), (B)(ii). We disagree. As this Court explained in Polonski v. Trump
Taj Mahal Associates:
[W]here “subsequent appellate proceedings manifest the
appellant’s intent to appeal the attorney’s fees issue,” and
where “the opposing party had and exercised a full
opportunity to brief the issue and did not raise any claim of
prejudice,” this Court has found a notice of appeal specifying
one attorney’s fee order sufficient to confer jurisdiction over
an appeal from another unspecified attorney’s fee order in the
same case.
137 F.3d 139, 144 (3d Cir. 1998) (quoting Bernardsville Bd. of Educ. v. J.H.,
42 F.3d
149, 156 n.10 (3d Cir. 1994)). Cato’s appeal was clearly intended to extend to the
October and December orders. Since Longport has thoroughly briefed the relevant issues
and has offered no evidence of prejudice, we will exercise jurisdiction over them under
28 U.S.C. § 1291.
We also believe that Cato properly preserved its argument that the District Court
misinterpreted the indemnity clauses. In its brief in opposition to Longport’s motion for
fees and costs, Cato argued that the clauses were ambiguous because “‘[i]ndemnification’
is a term that ordinarily suggests, as between two parties, the shifting responsibility for
4
the claims brought by a third.” App. at 291. Cato devoted at least a page of its brief to
this argument. Although the Appendix does not excerpt any more of the brief, we are
satisfied that Cato did not merely “allud[e]” to the issue in “stray comments or passing
references in assorted documents.” Longport’s Br. at 33-34.
Longport argues that Cato was required to raise the issue earlier to preserve it, but
Longport has failed to point to any authority supporting this position. The requirement
that errors be preserved in the trial court conserves judicial resources and serves the
interests of fairness to the District Court and the appellant’s adversary. See Gardiner v.
V.I. Water & Power Authority,
145 F.3d 635, 647 (3d Cir. 1998). It gives the District
Court an opportunity to correct its own errors, obviating costly appeals. See id.; Pfeifer v.
Jones & Laughlin Steel Corp.,
678 F.2d 453, 457 n.1 (3d Cir. 1982), vacated on other
grounds,
462 U.S. 523 (1983). These interests have not been disserved simply because
Cato waited until after trial to raise the issue. Longport had an opportunity to respond to
Cato’s argument, as did the District Court, which found it “without merit.” App. at 293.
We conclude that this sufficed to preserve the issue.2
2
Having so concluded, we deny Longport’s motion to quash the appeal at No. 03-
3882. The motion raises essentially the same forfeiture and jurisdictional arguments
rejected above.
Longport’s motion to quash the appeal at No. 03-3814 is also denied. As
Longport’s reply brief in support of the motion recognizes, Cato’s agreement with The
Window Associates, Inc., may obligate the latter to indemnify Cato for any award to
Longport. As a result, The Window Associates, Inc., shares an interest with Cato in
challenging the award and has every right to join its brief. See Fed. R. App. P. 28(i).
5
III.
We turn to the merits. In New Jersey, indemnification agreements are interpreted
according to familiar rules of contract construction. See Ramos v. Browning Ferris Indus.
of S. Jersey, Inc.,
510 A.2d 1152, 1159 (N.J. 1986). Clear and unambiguous ones are
enforced according to their terms. See Kampf v. Franklin Life Ins. Co.,
161 A.2d 717,
720-21 (N.J. 1960). Ambiguities are resolved by the fact finder, relying on such evidence
as “the language used, the surrounding circumstances, and the objectives sought to be
achieved.” Pepe v. Twp. of Plainsboro,
766 A.2d 837, 840 (N.J. Super. Ct. App. Div.
2001). Should such evidence fail to resolve the ambiguity, however, an indemnity clause
must be strictly construed against the indemnitee. See
id. (citing Ramos, 510 A.2d 1152).
We agree with Cato that neither indemnity clause unambiguously requires it to
reimburse Longport for fees and costs in Longport’s own action against Cato. While each
clause is broadly worded, referring to indemnification “[t]o the fullest extent permitted by
law” for “any and all liability,” this language can sweep only as far as the word on which
it hinges. That hinge is the word “indemnify.” Although this word can imply any right to
reimbursement, it commonly presumes a tripartite arrangement, in which A recovers from
B for losses to C. See Black’s Law Dictionary 784 (Bryan A. Garner, ed. in chief, 8th ed.
2004) (defining indemnity as “esp., the right of a party who is secondarily liable to
recover from the party who is primarily liable for reimbursement of expenditures paid to a
third party”); 41 Am. Jur. 2d Indemnity § 1 (1995) (giving a similar definition).
6
Case law confirms the currency of Cato’s definition. In Valhal Corp. v. Sullivan
Associates, Inc., we explained that an indemnity clause requires the indemnitor “to bear
the cost of any damages for which the indemnitee is held liable.”
44 F.3d 195, 202 (3d
Cir. 1995) (emphasis added); accord Adler’s Quality Bakery, Inc. v. Gaseteria, Inc.,
159
A.2d 97, 110 (N.J. 1960) (“[Indemnity] is a right which enures to a person who, without
active fault on his own part, has been compelled, by reason [of] some legal obligation, to
pay damages occasioned by the initial negligence of another, and for which he himself is
only secondarily liable.” (quoting Builders Supply Co. v. McCabe,
77 A.2d 368, 370 (Pa.
1951))); see also Lee Way Motor Freight, Inc. v. Yellow Transit Freight Lines, Inc.,
251
F.2d 97, 99 (10th Cir. 1957) (explaining that indemnity “implies a primary liability in one
person, although a second person is also liable to a third party”); Strong v. Prince
George’s County,
549 A.2d 1142, 1144 (Md. Ct. Spec. App. 1988) (“Indemnification is
an agreement to reimburse one who has been held liable for the amount of his loss.”);
AMI Ins. Agency v. Elie,
394 So. 2d 1061, 1062 (Fla. Dist. Ct. App. 1981) (same). This
definition presumes an obligation to a third party that triggers the indemnitor’s obligation
to the indemnitee.
Although the word may sometimes have the broader meaning championed by
Longport, that meaning does not emerge unambiguously from its contracts with Cato. In
fact, the surrounding language tends to undermine Longport’s reading. The contracts
require Cato not only to indemnify Longport but also to “hold [it] harmless.” A hold-
7
harmless term normally requires one party to “‘assume[] the liability inherent in the
undertaking, thereby relieving the other party of the responsibility.’”
Valhal, 44 F.3d at
202 n.6 (quoting Blacks Law Dictionary 658 (5th ed. 1979)). Longport has failed to
explain how it could be “h[e]ld harmless” in its own action against Cato. This wrinkle in
the language suggests that the agreements contemplate indemnification only when
Longport defends a third party’s lawsuit.
Longport maintains that Cato’s interpretation renders section 12.1.1 of the
Construction Agreement surplusage, but Longport does not explain why section 12.1.1
should be any more or less expansive than section 12.1.3. Both sections use the word
“indemnify.” According to Longport, this word unambiguously implies a right to
reimbursement even in the absence of liability to a third party. Under a more plausible
reading, section 12.1.1 gives Longport a right to indemnity for any bodily injury and
property damage, whereas section 12.1.3 grants indemnity for a broader class of losses
but only upon a showing of fault. In any event, Longport’s interpretation proves
unsuccessful at explaining the overlap between the two sections and must be rejected.
IV.
After careful consideration of the parties’ arguments and submissions, we
conclude that the Management and Construction Contracts do not set forth Cato’s
indemnity obligations unambiguously. The District Court erred in awarding Longport
fees and costs based on them. On remand, the District Court may consider extrinsic
8
evidence of the parties’ intent. Should such evidence fail to resolve the ambiguity in the
agreements, the two clauses must be construed strictly against Longport.