Elawyers Elawyers
Washington| Change

Expresser Transport Corporation, ASBCA No. 61464 (2018)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61464 Visitors: 5
Judges: Melnick
Filed: Dec. 07, 2018
Latest Update: Mar. 03, 2020
Summary:  The relevant portions of the charter are its provision, permitting government contract personnel to serve aboard Bonnyman, the, government's promise to indemnify Expresser for liabilities resulting from the carriage, of such personnel, and Article 38, stating that [a]ll claims ...
                  ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of --                                  )
                                              )
Expresser Transport Corporation               )      ASBCA No. 61464
                                              )
Under Contract No. N00033-82-C-1013           )

APPEARANCE FOR THE APPELLANT:                        Patrick H. Mccaffery, Esq.
                                                      General Counsel

APPEARANCES FOR THE GOVERNMENT:                      Craig D. Jensen, Esq.
                                                      Navy Chief Trial Attorney
                                                     Robert R. Kiepura, Esq.
                                                      Senior Trial Attorney

              OPINION BY ADMINISTRATIVE JUDGE MELNICK
          GRANTING SUMMARY JUDGMENT FOR THE GOVERNMENT

       This is an appeal from the government's denial of an indemnification claim.
Because the claim was waived by the contract's express terms, summary judgment is
granted to the government and the appeal is denied. The following facts are undisputed.

       In 1983, the contractor, Expresser Transport Corporation, and the United States
entered into the time charter contract identified above (which was then amended and
restated in 1985) for the Military Sealift Command (MSC) to hire MV 1s1 Lt Alex
Bonnyman to support the prepositioning of military equipment and supplies (compl.
111-2; R4, tab 1 at 1-6, 55). 1 The 145-page agreement (not counting annexes)
contained extremely detailed language governing the parties' relations, obligations,
and responsibilities (R4, tab 1). Consistent with the nature of a time charter, Expresser
remained responsible for operating the ship, which it contractually accomplished
through its parent company, Maersk Line, Limited (compl. 1 1; R4, tab 1 at 6).
However, the government could place civilian contractors aboard for communications
and cargo maintenance (compl. 13; R4, tab 1 at 77). The government agreed to
"indemnify [Expresser] for liabilities resulting from the carriage of such personnel"
(compl. 1 4; R4, tab 1 at 78).



1
    While discussing the vessel bearing his name, it is worth noting that Lt Bonnyman
       was a United States Marine posthumously awarded the Congressional Medal of
       Honor for heroic actions in 1943 during the battle of Betio Island, Tarawa. See
       http://www.marinemedals.com/bonnymanalexander.htm.
        Article 38 of the charter was entitled "WAIVER OF CLAIMS." It stated:

                       All claims whatsoever for moneys due the
               Contractor under this Charter must be submitted in
               accordance with the applicable Military Sealift Command
               billing instruct~ons within two years of the date of
               redelivery of the Vessel, except as otherwise provided in
               Article 44(a). Except as so provided, all claims not
               submitted within the two-year limit shall be deemed to
               have been waived by the Contractor.

(R4, tab 1 at 120)2 The charter also incorporated Defense Acquisition Regulation
(DAR) 7-103.12, DISPUTES (JUN 1980) (R4, tab 1 at 149). This clause stated the
charter was "subject to the Contract Disputes Act of 1978 (P.L. 95-563)" (CDA), and
in relevant part described the procedures for pursuing a claim. See Santa Fe Eng 'rs,
Inc., ASBCA No. 36292, 92-2 BCA ,r 24,795 at 123,677. 3

        On May 11, 2007, a government contract employee stationed aboard Bonnyman
suffered an injury leaving him a paraplegic. In June of 2008, the employee filed suit in
the United States District Court for the Southern District of Ohio against, among
others, the government and Maersk. (Compl. ,r,r 5-6) The complaint sought damages
for maintenance, cure, wages, attorney fees, and punitive damages (R4, tab 2).
Expresser was added as a defendant by an amended complaint (R4, tab 5.18).

       The charter was terminated by the government for its convenience on July 15,
2009 (compl. ,r 2). Neither party disputes that Bonnyman was redelivered on that date
(gov't mot. at 4; app. opp'n at 4).

        In May of 2010, the district court dismissed the government from the employee's
suit (compl. ,r 7). On March 21, 2011, the employee settled with Expresser and Maersk,
releasing them from liability in exchange for $2,500,000 (compl. ,r 9; gov't mot. ,r 7).
Slightly less than six years later, on March 15, 2017, Mr. Steven E. Hadder, President of
Expresser and Vice President of Maersk, submitted a certified claim to the contracting
officer seeking $2,782,088.62 in reimbursement for the settlement and for legal fees
(compl. ,r 10; R4, tabs 3-4). Mr. Hadder contended that Expresser and Maersk were
entitled to recover based upon the government's indemnification of Expresser for liabilities


2
    Article 44(a) contained exceptions neither party contends are relevant here (R4,
        tab 1 at 139).
3
    The Board requested the government to provide a copy of the actual clause as it
        existed in 1980, but it was unable to do so. Santa Fe Engineers recites its
        relevant portions.

                                            2
resulting from the carriage of private civilian contractors aboard Bonnyman. The
contracting officer denied the claim on October 3, 2017 (R4, tab 3). This appeal followed.

                                         DECISION

I.       The Merits

       The government moves to dismiss the appeal for failure to state a claim upon
which relief may be granted. 4 Because the parties rely upon statements and materials
outside the pleadings, the motion is treated as one for summary judgment. 5 See FED.
R. CIV. P. 12(d). Summary judgment should be granted if there are no genuine issues
of material fact and the moving party is entitled to judgment as a matter of law.
Celotex Corp. v. Catrett, 477 U.S. 317,322 (1986).

        The government's argument is fairly simple. Article 38 of the charter stated
that "[a]ll claims ... for moneys due ... under [the] Charter must be submitted in
accordance with the applicable Military Sealift Command billing instructions within

4
     The claim letter opens by referring to Maersk as MLL. Later it states that
        "Expresser and MLL are hereinafter referred to collectively as 'MLL. "'
         Mr. Hadder's certification, located at the end of the letter, included the
         statement "that the amount requested accurately reflects the contract adjustment
        for which MLL believes the Government is liable; and that I am duly authorized
        to certify the claim on behalf of MLL." By order issued September 18, 2018,
        the Board inquired of the parties whether this language complied with the
        reference to "contractor" contained in 41 U.S.C. § 7103(b)(l)(C).

                  In response, the government advances a request to dismiss the appeal for
         lack of jurisdiction, observing that Maersk is not the contractor and suggesting that
         "[t ]he fact that the letter indicates that the claim was being certified by 'MLL,'
         meaning Maersk, means that the claim contains no certification at all" (gov't resp.
         to Bd. inquiry 823 F.3d 622
, 627 (Fed. Cir. 2016)
(quoting FAR 2.101). Expresser argues it cannot be the case that it agreed to waive
potential claims that might not have accrued before Article 38's deadline. Such a
result would deny it recourse under the CDA, which it says conflicts with the Board's
decision in Ikhana, LLC, ASBCA No. 60462 et al., 17-1 BCA ,r 36,871. Citing
Rejlectone v. Dalton, 
60 F.3d 1572
, 1577 (Fed. Cir. 1995) (en bane), Expresser alleges
that it functioned under the "assumption" that Article 38 only restricted the time within
which "routine" requests for payment could be submitted. It implies that its
indemnification claim is not routine and therefore not restricted by Article 38.
According to Expresser, all that limits the submission of its indemnification claim is
the doctrine of laches. 6

       · "A contract must...be construed as a whole and 'in a manner that gives meaning
to all of its provisions and makes sense.'" Bel/Heery v. United States, 
739 F.3d 1324
,
1331 (Fed. Cir. 2014) (quoting McAbee Constr., Inc. v. United States, 
97 F.3d 1431
,
1435 (Fed. Cir. 1996)). The relevant portions of the charter are its provision
permitting government contract personnel to serve aboard Bonnyman, the
government's promise to indemnify Expresser for liabilities resulting from the carriage
of such personnel, and Article 38, stating that "[a]ll claims ... for moneys due"
Expresser under the charter "must be submitted ... within two years of the date of
redelivety" of Bonnyman. All "claims not submitted within the two-year limit shall be
deemed to have been waived by" Expresser. Expresser suggests DAR 7-103.12(b) is
also relevant.



6
    The parties agree that the CDA's own six-year limit upon the submission of claims,
        provided now at 41 U.S.C. § 7103(a)(4), does not apply. That statutoty
        provision had not been enacted in 1985 at the time the restated charter was
        executed, and is not retroactive. See Motorola, Inc. v. West, 
125 F.3d 1470
        (Fed. Cir. 1997).

                                           4
         The sensible meaning of all the charter's relevant provisions is that the government
indemnified Expresser for liabilities resulting from the carriage of government contract
personnel. However, the government's exposure to such claims was not open ended.
Claims not submitted by Expresser within two years of Bonnyman's redelivery were
waived. That Expresser may now find Article 38 "unacceptable," because it waived
claims that might not have accrued before the deadline, does not change what it agreed to.
It is far from surprising that the charter's comprehensive treatment of the parties' rights
established a firm date beyond which any claims for money due would not be viable. As
Expresser observed, claims made against it could take an indeterminate amount of time to
resolve, potentially delaying the accrual of its own claims upon the government for
indemnification for an unknown period. By limiting that exposure, Article 38 is
comparable to a statute of repose, which "cuts off a cause of action at a certain time
irrespective of the time of accrual." Weddel v. Secy ofHealth and Human Servs.,
100 F.3d 929
, 931 (Fed. Cir. 1996). Contrary to Expresser's suggestion, nothing in
DAR 7-103.12(b) conflicts with this conclusion. That provision merely stated that "all
disputes arising under or relating to [the charter] shall be resolved in accordance with this
clause." It did not forbid the contractual expiration of Expresser's right to seek payments
under the charter.

         Notably, the scenario Expresser suggests is objectionable about Article 38, that
its indemnification claim could have been waived before it accrued, did not happen.
The parties disagree over when Expresser's indemnification claim accrued, with the
government contending it occurred on the date the employee was injured in May of
2007, and Expresser maintaining that the sum certain it seeks could not be known until
it settled with the employee on March 21, 2011. There are other possible dates in
between that could apply. However, even if Expresser's March 21 date is correct, it
had from then until July 15 to submit a claim to the contracting officer before it was
waived. Expresser does not suggest it could not do so.

        Expresser represents that it assumed Article 38 only applied to "routine"
requests for payment, implying its indemnification claim is not routine. However, it
presents no tangible evidence that it interpreted the charter that way. Mere argument
by its attorney is not evidence. Gemtron Corp. v. Saint-Gobain Corp., 
572 F.3d 1371
,
1380 (Fed. Cir. 2009). Moreover, even if Expresser had submitted otherwise
competent extrinsic evidence of the charter's meaning, it would be irrelevant given that
Article 38 is unambiguous. See Auto. Mgmt. Servs. FZE, ASBCA No. 58352, 15-1
BCA ,r 36,119 at 176,329 (holding the Board does not consider extrinsic evidence to
interpret an unambiguous contract). Nothing in it or any other part of the charter
limited the waiver provision merely to "routine" requests for payment.

      Also, Expresser's reliance upon Rejlectone to establish the distinction it
proposes is misplaced. Rejlectone holds that a written demand seeking the payment of
money as of right need not already be in dispute when submitted to the contracting


                                            5
officer to constitute a CDA claim, except if it is a voucher, invoice or other routine
request for payment. 
Reflectone, 60 F.3d at 1577
. If Expresser is correct that its claim
is non-routine (and the government does not contest that assertion) than that simply
means it was ripe for submittal to the contracting officer regardless of whether it was
previously in dispute. Rejlectone does not govern the merits of a claim or restrict the
parties from agreeing to the conditions of its waiver.

        Jkhana does not favor Expresser either. There, a contractor purported to assign to
its surety its "contract rights," after which the surety attempted to dismiss the
contractor's appeal to this Board and release the government from all claims. The Board
rejected the idea that such an assignment could preclude the contractor from exercising
its statutory right of appeal to this Board. Noting the CDA is intended to equalize the
parties' bargaining power by guaranteeing at least one impartial review of contracting
officer decisions, the Board observed that "[p]ermitting parties to contract away Board
review entirely would subvert this purpose." 17-1 BCA ,r 36,871 at 179,731 (quoting
Burnside-Ott Aviation Training Ctr. v. Dalton, 
107 F.3d 854
, 859 (Fed. Cir. 1997)). The
statutory right to appeal from contracting officer final decisions is unwaivable. 
Id. Article 38
does not waive any of Expresser's statutory rights, much less its right
to appeal to this Board. Thus, this appeal is here. Article 38 places substantive
limitations upon Expresser's contract rights by waiving claims not submitted within two
years of vessel redelivery. Nothing in lkhana, or any other authority cited by Expresser,
forbids the parties from arranging their contractual relationship in this manner.

II.    Discovery

        In its supplemental submission, Expresser argues that "several genuine issues of
material fact exist which Expresser should be permitted to examine in the course of
discovery" (app. supp. br. at 4). In particular, it seeks discovery into whether the MSC
billing instructions with which claims had to be in accord under Article 38 support its
position that an indemnification claim is not within the scope of Article 38. It suggests
the meaning of the article is a genuine issue of material fact. Expresser also implies it
needs discovery into other issues, including whether its claim accrued when the
contractor employee was injured, whether there is a factual basis "for the Government's
defense of laches" (id. at 7), and whether its CDA certification is defective.

       "In deciding motions for summary judgment, the Board looks to Rule 56 of the
Federal Rules of Civil Procedure for guidance." Board Rule 7(c)(2). Federal Rule of
Civil Procedure 56(d) provides that a court may allow time for discovery if the
nonmoving party shows by affidavit or declaration that "for specified reasons, it
cannot present facts essential to justify its opposition" to the motion. Expresser has
not met the threshold requirement for an affidavit or declaration making the showing
required by Rule 56(d). See Brubaker Amusement Co. v. United States, 
304 F.3d 6
( among other reasons, rejecting appeal from denial of discovety before summaiy
judgment given that there was no affidavit). 7

        Furthermore, summaiy judgment need not be deferred or denied to permit
discoveiy based upon a mere speculative hope that a claimant might find evidence to
support its case. Brubaker 
Amusement, 304 F.3d at 1361
. Though it does not have to
be clairvoyant, Expresser must "state with some precision the materials [it] hope[s] to
obtain with further discoveiy, and exactly how [it] expect[s] those materials would
help [it] in opposing summaiy judgment." Simmons Oil Corp. v. Tesoro Petroleum
Corp., 
86 F.3d 1138
, 1144 (Fed. Cir. 1996) (quoting Krim v. BancTexas Grp., Inc.,
989 F.2d 1435
, 1443 (5 1h Cir. 1993)). Expresser is not "allowed to conduct discovety
that has no chance of leading to the denial of summaiy judgment for" the government.
Jiang/in Zhou v. United States, 
727 F. App'x 651
, 654 (Fed. Cir. 2018) (quoting RQ
Squared, LLC v. United States, 
119 Fed. Cl. 751
, 758 (2015)). Nor is it enough to
imply that "something will tum up." Simmons 
Oil, 86 F.3d at 1144
.

       Expresser is clear enough that it seeks to take discovety about the MSC billing
instructions applicable to Article 38 claims, but it is far less apparent what they might
reveal to help its case. It speculates they might "support Expresser's contention that
the 2-year limitation in Article 38 ... does not bar the submission of a claim for
indemnification." It suggests they might say that an indemnification claim need not be
submitted under them. Expresser provides no explanation as to why it expects they
might say that. Indeed, Article 38's scope was unlimited. It applied to "[a]ll claims
whatsoever for moneys due the Contractor under this Charter" and it required them to
be "submitted in accordance with applicable ... billing instructions within two years of
the date of redeliveiy" (R4, tab 1 at 120). Though the billing instructions might dictate
the procedures for submitting claims, Article 3 8 did not provide any basis for them to
carve out a class of claims for moneys due that could be excluded from its time limits.
Thus, even if the Board were to look past Expresser's failure to present an affidavit or

7
    Brubaker Amusement addressed Rule 56(g) of the Rules of the United States Court
       of Federal Claims as they existed at that time. That rule was substantively
       similar to the current version of Federal Rule of Civil Procedure 56( d), stating:

              Should it appear from the affidavits of a party opposing the
              motion that such party cannot for reasons stated present by
              affidavit facts essential to justify such party's opposition,
              the court may refuse the application for judgment or may
              order a continuance to permit affidavits to be obtained or
              deposition to be taken or discoveiy to be had or may make
              such other order as is just.

       Bntbaker 
Amusement, 304 F.3d at 1361
n.4.

                                            7
declaration, Expresser's reasons for seeking the billing instructions rely upon flawed
logic, do not rise above the level of a speculative hope, and amount to little more than
the suggestion that something might turn up.

        The remaining three reasons Expresser gives for seeking discovery are even less
compelling. First, there is no need for discovery into whether Expresser's claim
accrued when the contractor employee was injured, as the government contends. As
explained above, assuming Expresser's claim accrued as late as March 21, 2011, as it
suggests, the claim was still waived by the time Expresser submitted it in 201 7.
Second, contrary to Expresser's suggestion, the government has not premised its motion
upon the defense of laches. Third, the government's motion to dismiss based upon the
absence of a certification has been denied. Accordingly, discovery for the purposes of
these last three reasons has no chance of leading to the denial of summary judgment for
the government. Expresser's request to take discovery is therefore denied.

                                        CONCLUSION

      Summary judgment is granted in favor of the government. The appeal is denied.

      Dated: December 7, 2018



                                                .;]£(~
                                                  MARK A. MELNICK
                                                  Administrative Judge
                                                  Armed Services Board
                                                  of Contract Appeals



I concur                                          I concur


    +=P     C>-

R1C1{] SHACKLEFORD                                J. REID PROUTY
Administrative Judge                              Administrative Judge
Acting Chairman                                   Vice Chairman
Armed Services Board                              Armed Services Board
of Contract Appeals                               of Contract Appeals




                                           8
      I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 61464, Appeal of
Expresser Transport Corporation, rendered in conformance with the Board's Charter.

      Dated:



                                                 JEFFREY D. GARDIN
                                                 Recorder, Armed Services
                                                 Board of Contract Appeals




                                          9

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer