Elawyers Elawyers
Ohio| Change

Backcountry Against Dumps v. Sally Jewell, 13-57129 (2017)

Court: Court of Appeals for the Ninth Circuit Number: 13-57129 Visitors: 9
Filed: Jan. 05, 2017
Latest Update: Mar. 03, 2020
Summary: NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JAN 05 2017 MOLLY C. DWYER, CLERK FOR THE NINTH CIRCUIT U.S. COURT OF APPEALS BACKCOUNTRY AGAINST DUMPS No. 13-57129 and DONNA TISDALE, D.C. No. Plaintiffs-Appellants, 3:12-cv-02211-GPC-PCL v. MEMORANDUM* SALLY JEWELL, in her official capacity as Secretary of the United States Department of the Interior; et al., Defendants-Appellees, OCOTILLO EXPRESS, LLC and PATTERN ENERGY GROUP, LP, Intervenor-Defendants- Appellees. Appeal from the Unite
More
                           NOT FOR PUBLICATION                             FILED
                    UNITED STATES COURT OF APPEALS                          JAN 05 2017

                                                                        MOLLY C. DWYER, CLERK
                            FOR THE NINTH CIRCUIT                        U.S. COURT OF APPEALS




BACKCOUNTRY AGAINST DUMPS                        No.   13-57129
and DONNA TISDALE,
                                                 D.C. No.
              Plaintiffs-Appellants,             3:12-cv-02211-GPC-PCL

 v.
                                                 MEMORANDUM*
SALLY JEWELL, in her official capacity
as Secretary of the United States
Department of the Interior; et al.,

              Defendants-Appellees,

OCOTILLO EXPRESS, LLC and
PATTERN ENERGY GROUP, LP,

              Intervenor-Defendants-
              Appellees.


                    Appeal from the United States District Court
                      for the Southern District of California
                    Gonzalo P. Curiel, District Judge, Presiding

                     Argued and Submitted November 3, 2015
                              Pasadena, California

Before: FARRIS, BYBEE, and N.R. SMITH, Circuit Judges.


      *
             This disposition is not appropriate for publication and is not precedent
except as provided by Ninth Circuit Rule 36-3.
      Backcountry Against Dumps and Donna Tisdale (“Appellants”) appeal the

district court’s order granting summary judgment in favor of Appellees.

Appellants maintain that the Bureau of Land Management (“BLM”) violated (1)

the Federal Land Policy and Management Act (“FLPMA”) in failing to comply

with the California Desert Conservation Area (“CDCA”) Plan, and (2) the National

Environmental Policy Act (“NEPA”) when it granted Ocotillo Express, LLC

(“Ocotillo”) a right of way to construct and operate the Ocotillo Wind Energy

Facility (“OWEF Project” or “the Project”) near Ocotillo, California. We may

affirm a district court’s grant of summary judgment “on any basis supported by the

record.” Gordon v. Virtumundo, Inc., 
575 F.3d 1040
, 1047 (9th Cir. 2009).

Because the parties are familiar with the facts and procedural history of this case,

we will not recount them here.

      1. Appellants first contend the BLM violated the CDCA Plan by failing to

determine whether the OWEF Project met the substantive requirements the Plan

imposes on proposed uses of Class L land—the class of land upon which the

OWEF Project is located. The CDCA Plan governs all land use activities within

the CDCA. Because the OWEF Project is located on CDCA land, the BLM was

required to ensure the Project complied with the Plan before granting the right-of-

way. Significantly, the CDCA Plan includes a Plan amendment process that allows


                                           2
the BLM to make changes to the CDCA Plan for a multitude of reasons, including

accommodating a specific project that might not otherwise comply with the CDCA

Plan. See BLM, California Desert Conservation Area Plan 1980, as amended, at

119 (Mar. 1999) [hereinafter CDCAP].

      In the Record of Decision granting a right-of-way for the OWEF Project, the

BLM adopted a Category 3 Plan amendment to accommodate the Project. See

BLM, Record of Decision Ocotillo Wind Energy Facility and Amendment to the

California Desert Conservation Area Plan, at 39 (May 2012). The BLM amended

the CDCA Plan to designate the approximately 10,151 acres of public land where

the Project was to be located as suitable for wind energy development. 
Id. at 1.
      A Category 3 amendment “accommodate[s] a request for a specific use or

activity [that] will require additional analysis” of its own. CDCAP, at 119. A

Category 3 amendment, like a zoning variance, allows the BLM to carve out an

exception to the CDCA Plan for a specific use or activity. 
Id. Once the
BLM

determines that a specific project warrants a Category 3 amendment, that project is

no longer required to comply with the substantive requirements of the class of land

on which the project is sited. Rather, the project is governed by the Plan

amendment.




                                          3
      When considering a Category 3 amendment, the District Manager begins by

evaluating the “additional analysis” specific to the use or activity for which the

amendment is requested. 
Id. at 121.
This additional analysis is generally an

Environmental Impact Statement (“EIS”); therefore, a Category 3 amendment does

not require its own EIS. 
Id. at 119,
121. If the District Manager approves, he or

she recommends the amendment to the State Director. 
Id. at 121.
If the State

Director agrees, the District Manager renders a decision and issues a public notice

of the amendment decision that clearly explains how the CDCA Plan would be

changed by the amendment. 
Id. The BLM
must then allow thirty days for the

public to object to the amendment. 
Id. After resolving
the objections, the BLM

may approve the amendment. 
Id. The District
Manager also has a series of six

determinations and obligations that must be completed before the amendment can

be approved. 
Id. The BLM
substantially complied with this process.

      Once the BLM adopted this Category 3 amendment to accommodate the

OWEF Project, the Project was no longer required to comply with the multiple-use

class designations, guidelines, or elements for Class L land. Therefore, even if we

agree with Appellants that the BLM failed to determine whether the OWEF Project

met the substantive requirements the Plan imposes on proposed uses of Class L

land, we must nevertheless conclude that the Project did not violate the CDCA


                                           4
Plan. The Project was governed by the Plan amendment rather than the Plan itself.

Accordingly, we affirm the district court’s grant of summary judgment finding that

the BLM did not violate the CDCA Plan.

      2. “NEPA requires agencies considering ‘major Federal actions significantly

affecting the quality of the human environment’ to prepare and issue an

environmental impact statement.” Oregon Nat. Res. Council Fund v. Brong, 
492 F.3d 1120
, 1132 (9th Cir. 2007) (quoting 
42 U.S. C
. § 4332(2)(C)). An EIS must

“provide full and fair discussion of significant environmental impacts and shall

inform decisionmakers and the public of the reasonable alternatives which would

avoid or minimize adverse impacts or enhance the quality of the human

environment.” 40 C.F.R. § 1502.1. We review an EIS “to ensure that the agency

has taken a ‘hard look’ at the potential environmental consequences of [a]

proposed action.” Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 
387 F.3d 989
, 993 (9th Cir. 2004).

      The BLM prepared and issued an EIS for the OWEF Project. Appellants

contend that this EIS was inadequate, and thus violated NEPA, in four respects.

First, Appellants argue that the BLM failed to take a “hard look” at the Project’s

impacts on peninsular bighorn sheep because there were no available studies

demonstrating how the sheep would respond to wind turbines, and the BLM failed


                                          5
to conduct its own independent study. Although both assertions are true, the BLM

did consider a formal Endangered Species Act Section 7 consultation of the

Project’s impact on peninsular bighorn sheep, studies of bighorn sheep responses

to other human activities, and a study of rocky mountain elk responses to wind

turbine facilities. See BLM, Proposed Plan Amendment & Final Environmental

Impact Statement/Final Environmental Impact Report for the Ocotillo Wind

Energy Facility, at 1-15, 4.21-22, 4.21-43 (Feb. 2012) [hereinafter FEIS]. The EIS

for the OWEF Project acknowledged that, although the Project would not directly

affect the “critical habitat” of the peninsular bighorn sheep, the Project would

temporarily impact 124.1 acres and permanently impact 43.1 acres of the of the

“Essential Habitat” of the peninsular bighorn sheep. 
Id. at 4.21-8.
The EIS also

identified possible indirect impacts of the Project’s construction and operation on

the species. See 
id. at 4.21-20
to -22. The BLM sought to minimize and mitigate

these impacts through the adoption of several different “Mitigation Measures,”

which require, inter alia, the BLM to monitor and collect data on the Project’s

impacts on the peninsular bighorn sheep, and to adjust its activities when

appropriate and necessary. See 
id. at 4.21-43
to 4.21-51. Even though the actual

effects the OWEF Project would have on the sheep were uncertain, we conclude

the BLM took the requisite hard look, because it “considered extensively” the


                                          6
potential impacts of the Project and the available mitigation measures. See

Okanogan Highlands All. v. Williams, 
236 F.3d 468
, 477 (9th Cir. 2000).

      Second, Appellants argue the BLM violated NEPA by failing to consider the

full visual impacts of the OWEF Project. Specifically, Appellants argue the BLM

failed to analyze the visual impacts of the Project’s electrical substation, utility

switchyard, operations and maintenance facility, observation tower, and parking

lot. It is true that the EIS focused on the visual impacts of the wind turbines, not

on the Project’s ancillary facilities. However, that analysis was permissible

considering the visual impacts of the wind turbines would far exceed that of the

ancillary facilities. See 40 C.F.R. § 1502.2(b) (“Impacts shall be discussed in

proportion to their significance.”). The EIS did discuss the visual impact of all the

Project’s facilities, from construction to operation to decommissioning, and

discussed measures to mitigate these visual impacts. See FEIS, at 4.18. We

conclude this discussion was sufficient under NEPA.

      Third, Appellants argue that the BLM violated NEPA, because it failed to

consider the health effects of the low-frequence noise (“LFN”) and infrasound that

would be produced by the wind turbines. In the EIS, the BLM acknowledged that

experts are divided on the issue of whether exposure to LFN produced by wind

turbines causes health problems. 
Id. at 5-53.
The BLM then discussed the validity


                                            7
of several studies on both sides of the debate. See 
id. at 4.11-13,
5-53 to 5-55,

App. N at 180. The BLM rejected several studies based on their lack of supporting

documentation or experimental flaws. See 
id. at 4.11-13,
5-53 to 5-55. The BLM

found persuasive several studies that concluded the LFN and infrasound levels,

which would be produced by the OWEF Project, would not cause health problems

for the nearby residents. For example, the BLM found reliable and relevant a 2011

study that measured the LFN outside and inside homes near wind turbines, which

were the same model as the turbines proposed for the OWEF Project. 
Id. at 5-53.
The authors of the study “concluded that no adverse public health effects from

LFN or infrasound would be expected from the types of turbines studied at

distances greater than 300 m[eters].” 
Id. The BLM
then concluded that the

resulting LFN and infrasound that would be produced by the OWEF Project would

be unlikely to cause health problems for the nearby residents because “the closest

turbine is 804.67 m[eters] . . . from the nearest home.” 
Id. We find
the BLM conducted a full analysis of the potential consequences of

LFN and infrasound that would be produced by the Project and, based on the

studies it found reliable, the BLM determined that the health effects would be

minimal. Thus, the BLM took the requisite “hard look” at LFN and infrasound,

and we will defer to the agency’s position on this technical issue. See Nat’l Parks


                                          8
& Conservation Ass’n v. U.S. Dep’t of Transp., 
222 F.3d 677
, 682 (9th Cir. 2000)

(holding that when there are conflicting expert reports, an agency’s “determination

is due deference—especially in areas of agency expertise”).

        Fourth, and finally, Appellants argue that the EIS did not adequately discuss

the reasonable alternatives to the OWEF Project, in part because the BLM drafted

the purpose and need statement too narrowly. An EIS must “[r]igorously explore

and objectively evaluate all reasonable alternatives” to the proposed action. 40

C.F.R. § 1502.14(a). An EIS must also state the “purpose and need” of a project.

City of Carmel-By-The-Sea v. U.S. Dep’t of Transp., 
123 F.3d 1142
, 1155 (9th Cir.

1997). The “purpose and need” section of an EIS “dictates the range of

‘reasonable’ alternatives” that the agency must consider. 
Id. We “review
purpose

and need statements for reasonableness.” Alaska Survival v. Surface Transp. Bd.,

705 F.3d 1073
, 1084 (9th Cir. 2013). We give “agenc[ies] considerable discretion

to define a project’s purpose and need.” 
Id. However, “an
agency cannot define

its objectives in unreasonably narrow terms.” Carmel-By-The 
Sea, 123 F.3d at 1155
. In drafting a purpose and need statement, “an agency must consider the

statutory context of the proposed action,” any applicable “congressional

directives,” and the “private applicant’s objectives.” Alaska 
Survival, 705 F.3d at 1085
.


                                           9
      The BLM’s framing of the purpose and need statement was reasonable. In

the EIS, the BLM separately laid out its objectives and the distinct objectives of the

Corps of Engineers, Ocotillo, and the State of California. FEIS, at 1-3 to 1-5.

Within this discussion, the BLM noted relevant statutes, and congressional and

executive directives. The BLM explained that the Proposed Project would assist it

in addressing Executive Order 13212, the Energy Policy Act of 2005, Secretarial

Order 3285A1, and the California Global Warming Solutions Act, all of which

encourage, or mandate, the increased production of renewable energy. 
Id. Although the
focus of the purpose and need statement was responding to Ocotillo’s

application, this was reasonable in light of the relevant statutes and directives and

the wind resources available at the Proposed Project site.

      Based on the purpose and need statement, the BLM initially considered

eighteen alternatives to Ocotillo’s Proposed Project, including other types of

energy projects. 
Id. at 5-50;
see also 
id. at 2-48
to 2-50. The EIS briefly explains

why the alternatives energy projects were eliminated from consideration. See 
id. at 2-48
to 2-50. For example, a solar power project was eliminated both because it

did not meet the purpose of harnessing wind energy, but also because the

installation of solar panels would cause more land disturbance, which could have

had a greater effect on cultural and biological resources than the Proposed Project.


                                          10

Id. at 2-49.
The BLM also considered other locations for the Project. 
Id. at 2-46.
These alternative sites were eliminated from consideration for a variety of reasons.

Id. Some of
the sites had special designations that precluded them from use, such

as wilderness areas, some of the sites were already in use or had already been

proposed for other wind energy projects, and some of the sites had substantially

lower wind resources. 
Id. Ultimately, the
BLM analyzed six alternatives in detail,

including the required “no project” alternative. We find that the BLM explored

and evaluated all reasonable alternatives to the Proposed Project based on a

reasonably drafted purpose and need statement. Accordingly, we find the BLM did

not violate NEPA.

      AFFIRMED.




                                         11
                                                                             FILED
Backcountry v. Jewell, No. 13-57129 (Pasadena - November 3, 2015)             JAN 05 2017

                                                                         MOLLY C. DWYER, CLERK
BYBEE, Circuit Judge, concurring in the judgment:                          U.S. COURT OF APPEALS



      I respectfully disagree with the majority’s decision to approve the Ocotillo

Wind Energy Facility (“OWEF”) because the BLM amended its California Desert

Conservation Area Plan (“CDCA Plan”). In my view the BLM approved the

OWEF project because it conformed to the CDCA Plan, not as a way of short

circuiting our review.

      Since 1980, the CDCA Plan has provided that wind energy generation

facilities for this land classification “[m]ay be allowed after NEPA requirements

are met.” Here, the BLM did exactly what it was supposed to do. It prepared an

exhaustive environmental impact statement. It carefully considered the impact that

the proposed project would have on cultural and natural resources in the area and,

in response, it reduced the footprint of the project. The BLM also acknowledged

that it could not satisfy all of the competing claims to the land and, in an exercise

of its judgment, it decided to approve the OWEF. Only after it had satisfied itself

that it had heard from all interested parties, considered their views, followed the

processes set forth in the CDCA Plan, and determined that the project conformed

with the Plan’s requirements, did the BLM amend the CDCA Plan. In my view,

the BLM did not amend the CDCA Plan to avoid the Plan’s requirements and this

court’s scrutiny under the APA; it amended the CDCA Plan to reflect that the
OWEF project was consistent with the Plan and to add OWEF to a list of approved

energy development sites in the CDCA. The BLM’s careful and considered

decision was model and is not “arbitrary, capricious, an abuse of discretion, or

otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).

      I concur in the judgment.

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer