Watts Constructors, LLC, ASBCA No. 61493 (2020)

Court: Armed Services Board of Contract Appeals Number: ASBCA No. 61493 Visitors: 6
Judges: Prouty
Filed: Mar. 19, 2020
Latest Update: Apr. 09, 2020
Summary: ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Watts Constructors, LLC ) ASBCA No. 61493 ) Under Contract No. W91238-14-C-0040 ) APPEARANCES FOR THE APPELLANT: Jason R. Thornton, Esq. Jeffrey B. Baird, Esq. Daniel P. Scholz, Esq. Finch, Thornton & Baird, LLP San Diego, CA APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney A.L. Faustino, Esq. Robert W. Scharf, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Sacramento OPINION BY ADMINISTRAT
More
                 ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of --                                    )
                                                )
Watts Constructors, LLC                         )      ASBCA No. 61493
                                                )
Under Contract No. W91238-14-C-0040             )

APPEARANCES FOR THE APPELLANT:                         Jason R. Thornton, Esq.
                                                       Jeffrey B. Baird, Esq.
                                                       Daniel P. Scholz, Esq.
                                                        Finch, Thornton & Baird, LLP
                                                        San Diego, CA

APPEARANCES FOR THE GOVERNMENT:                        Michael P. Goodman, Esq.
                                                        Engineer Chief Trial Attorney
                                                       A.L. Faustino, Esq.
                                                       Robert W. Scharf, Esq.
                                                        Engineer Trial Attorneys
                                                        U.S. Army Engineer District, Sacramento

                   OPINION BY ADMINISTRATIVE JUDGE PROUTY

        Before us is a dispute about whether the terms of the above-captioned contract (the
contract) for the construction of several buildings required appellant, Watts Constructors,
LLC’s (Watts), electrical subcontractor to run electrical power lines in the buildings
through rigid conduit as opposed to using more economical integrated metal clad (MC)
cable. 1 Watts’s electrical subcontractor, Helix Electric, Inc. (Helix), saw what it wished
to see when it reviewed the contract’s plans and specifications and used MC cable
extensively in the construction. This was visible to quality assurance inspectors from the
contracting agency, the United States Army Corps of Engineers (the Corps), but not
objected to by the Corps until relatively late in the game. As will be discussed at length
below, standard contract interpretation supports the Corps’ reading of its contract,
requiring the exclusive use of conduit, not MC. Moreover, though it would have been far
better for the quality assurance inspectors from the Corps to have recognized and halted
Helix’s divergence from the requirements of the contract, their inaction did not change
the meaning of the contract and was insufficient to support a finding of waiver of
contractual compliance by the government.


1
    The reader has likely seen MC cable in their experience: it’s an electrical power
         conductor surrounded by flexible grey metal as a single assembly (tr. 20; see also
         R4, tab 61 (photo) and tr. 165-66 (describing photo)). It comes in spools (tr. 91).
                                   FINDINGS OF FACT

       I. Contract And Subcontract Awards

        In the mid-2000s, the United States Army decided to build a facility for satellite
communications on Camp Roberts, California near the town of Paso Robles (tr. 131 2
(inception of project in 2006)). The contract to accomplish this goal encompassed the
construction of four buildings: a satellite communications operations center (by far, the
largest of the buildings); a command/administrative support center; a repair and utilities
building; and a covered storage shed (R4, tab 2 at 1). This contract, in the amount
of $38,914,500, was awarded to Watts on September 3, 2014 (R4, tab 2 at 2). Shortly
thereafter, Watts executed a subcontract agreement with Helix to perform all of the
electrical work on the project (R4, tab 52 at 14-35; tr. 17-19).

       The contract contained the standard Changes clause, to be found in Federal
Acquisition Regulation (FAR) Part 52.243-4 providing authority of the contracting
officer to change the terms of the contract (R4, tab 2 at 15-16).

       II. The Contractual Requirements Relating To Wiring

       The Corps has an institutional preference for utilizing rigid conduit to run electric
power cable in buildings that it has constructed (tr. 150, 175). This is because the Corps
believes that conduit-installed power lines will last longer (tr. 175-76). Helix personnel
were well aware of this general desire (tr. 79), but held their own preference for power
cabling, which was the use of flexible MC (tr. 22, 35, 81). As we will explain in
Section III, below, although MC shares some of its characteristics, MC is not conduit.

       Despite their concerns that the Corps would not permit the use of MC, Helix
personnel involved in planning the construction found portions of the contract’s
specifications that, they believed, permitted the use of MC cable throughout and which
we note below (tr. 22-24).

       Part 2 of the Interior Distribution System section of the Electrical portion of the
contract’s specifications 3 is titled “Products” and lists required specifications for several
dozen identified electrical distribution products. One of these products is MC, and the
applicable subsection provides, in its entirety:



2
  The hearing for this matter was held on a single day, thus there is only a single
       transcript volume in the record.
3
  Unless stated otherwise, all references to contract sections in this opinion will be to the
       Interior Distribution System section of the Electrical section.
                                                  2
       2.8.6 Metal-Clad Cable

       UL 1569, 4 NFPA 70, 5 Type MC cable.

(R4, tab 4 at 1886 (footnotes not in original))

        A government witness characterized this portion of the contract as “boilerplate”
(tr. 150). Supporting this characterization, there are at least two other products listed in the
Products category that were not applicable to the project: armored cable and flat conductor
cable (tr. 177-78; R4, tab 4 at 1887 (Section 2.8.7, Armored Cable; Section 2.8.9, Flat
Conductor Cable)).

       The other location that MC is mentioned in the contract is in Part 3 of the
specifications, labelled, “Execution.” Section 3.1, “Installation,” includes direction about
how to install different items. MC is included in this section and the applicable
subsection provides, in its entirety:

       3.1.3.2 Metal Clad Cable

       Install in accordance with NFPA 70. Type MC cable.

(R4, tab 4 at 1900) 6

       Neither party has pointed to any other reference to MC in the contract (see app.
br.; app. reply br.; gov’t br.), the government assertion that nothing in the contract
drawings depicts anything other than electrical conduit (gov’t br. at 2-3, citing R4 tab 6
at 474-575 7) has never been fully rebutted by Watts (we discuss its one attempt to find
MC in the drawings below), and we have reviewed the salient drawings 8, ourselves, and
never found any depiction of MC for wiring.



4
  “UL” refers to the Underwriter’s Laboratory (tr. 27).
5
  “NFPA” refers to the National Fire Protection Agency, and the NFPA cited here is a
       national electric code (tr. 27-28).
6
  By contrast, the specifications include approximately four pages governing means and
       methods of conduit installation in the subsections under subsection 3.1.4 (see R4,
       tab 4 at 1900-03).
7
  The documents at tab 6 only go up to page 575, but the drawings referenced are within
       that smaller set.
8
  Namely, drawings E-102, E-103, E-104, E-105, E-106, E-108, E-109, E-110, E-111, E-112,
       E-120, E-121, E-130, and E-131, which all may be found in tab 6 of the Rule 4 file,
       ranging from pages to 492-510.
                                                  3
       Instead, the drawings accompanying the specifications refer only to conduit. The
drawings included a legend for “Circuiting.” This legend referenced “wiring,” though
not MC. One legend depiction shows a horizontal line with three angled lines crossing it.
Next to this are the words:

              CROSSLINES INDICATE NUMBER OF #12
              CONDUCTORS EXCEPT NEUTRAL CONDUCTOR FOR
              MULTIWIRE BRANCH CIRCUIT SHALL BE #10
              CONDUCTOR. EQUIPMENT GROUNDING
              CONDUCTOR IS NOT SHOWN. NO CROSSLINES
              INDICATES 2 - #12, ½” CONDUIT; OTHER
              CONDUCTOR AND CONDUIT SIZES AS INDICATED.

(R4, tab 6 at 474)

        When examined about the meaning of these words by government counsel,
Helix’s project manager, Mr. Shane Doner, agreed that this legend applied to all electrical
lines to be installed under the contract (tr. 65-68). He further conceded that nothing in
the drawings explicitly indicated the use of MC (tr. 65) and generally agreed that the
drawings required the use of conduit (tr. 65, 67-68).

       Watts argues that a portion of the drawings, nevertheless, allows for MC.
Drawing Sheet E-103 (R4, tab 6 at 493) depicts a solid line connecting several power
outlets which, in accordance with the legend discussed above, was generic “conduit,”
thus (as Watts would have it) permitting MC (app. reply br. at 5-6). 9 We will address this
more below.

       The government witnesses involved in the project believed that two provisions of
the contract precluded the use of MC. The first, was the drawings cited above. The
second, included in Part 3 of the specifications, “Execution,” provided in relevant part:

       3.1.3 Wiring Methods

                    Provide insulated conductors installed in rigid steel
              conduit, IMC [a type of conduit 10], rigid nonmetallic conduit,



9
  This argument would have been better made in Watts’s opening brief, rather than in its
        reply. Nevertheless, the government did not object and we may resolve it without
        the government’s input.
10
   See tr. 148, referring to IMC as conduit.

                                                4
                or EMT [another type of conduit 11], except where specifically
                indicated or specified otherwise or required by NFPA 70 to
                be installed otherwise.

(R4, tab 4 at 1899-1900)

       With respect to the salient contract terms, we note that the contract incorporated a
standard clause regarding the relative use of the drawings and specifications that
provided, in relevant part, that, “[i]n case of difference between drawings and
specifications, the specifications shall govern.” (R4, tab 2 at 7 (incorporating by
reference FAR 52.236-21 (FEB 1997) ALT I)).

         III. MC Is Not Conduit As Defined In The Contract

        During the hearing and the post-trial briefing, Watts made an attempt to allege that
MC was a type of conduit, and thus permissible in the contract where it demands conduit
(see app. br. at 9-10; app. reply br. at 6). As a matter of fact finding, we do not find this
allegation persuasive and find that MC is not conduit as referenced in the contract. The
allegation that MC is a type of conduit came from the testimony of Mr. Doner, the Helix
project manager, who testified that he considered conduit to be a “generic” term and that
he thought MC to be a type of conduit since the metal effectively protected the conductor
(tr. 42-44). He did not go so far, however, to call “conduit” a term of art, and testified
that he’d never heard MC embraced as “conduit” by other members of the trade (tr. 45).
Mr. Doner’s testimony, then, was little more than an individual’s personal opinion.

        Despite sharing some characteristics with conduit, MC is not considered conduit
by the contract. First, the conduit described in Section 3.1.3, Wiring Methods (the
portion of the contract that required use of conduit unless specified otherwise), was
referred to as “rigid” (see R4, tab 4 at 1899-1900; see also tr. 118-19 (referring to rigid
conduit)). MC’s great virtue is that it is flexible (see tr. 91 (MC comes in spools)).
Moreover, organizationally, the contract separated conduit from MC (see R4, tab 4
at 1885-86 in which MC is included under subset of “WIRES AND CABLES,”
Section 2.8 of the specifications, while “CONDUIT AND FITTINGS” is in Section 2.2
of the specifications, at R4, tab 4 at 1882). Mr. Doner admitted as much when he
conceded that MC was not included in the conduit described in Section 3.1.3 of the
specifications (tr. 58-59). And, with the exception of Mr. Doner’s testimony that he
considered MC to be functionally conduit, other portions of his testimony casually
referred to conduit and MC as different things (e.g., tr. 33-34). Mr. Woodruff, Helix’s


11
     See e.g., tr. 22-23, referring to EMT, electro-metallic tubing, as conduit and distinct
          from MC (see also tr. 56, indicating EMT was used to replace MC when the Corps
          demanded the use of rigid conduit).
                                                  5
superintendent for the project, also referred to “running conduit” in his testimony as
something separate and distinct from installing MC (tr. 119-20).

       IV. What Helix Did

        Helix, of course, installed much of the wiring as MC, with a significant amount of
conduit in certain places. Its rough estimate is that, for the first three buildings it worked
on, and largely completed, before the Corps directed it to stop, the portion of conduit to
MC was 60/40. (Tr. 34, 101-02) There is no dispute that there was extensive use of MC
in the buildings as reflected in multiple photographs admitted into evidence (see R4,
tabs 61, 66, 72).

       V. What The Corps Did (And Didn’t Do)

        Watts presented testimony purporting to support a finding that the use of MC was
raised with the Corps during the first meeting they had with Helix before the installation
began (see app. br. at 7, citing tr. 86, 91-92). Although Mr. Woodruff testified that the
use of MC came up at that meeting (which occurred on April 28, 2016 (tr. 87-88)), he did
not appear to specifically recall it. Rather, the gist of his testimony was that since it was
in the specification and the specification would be read at the meeting, it would have
been noted, “[b]ut there was no depth to a conversation on MC cable.” (Tr. 86) The
notes of the meeting, which were taken by a Watts employee, Doug Saunders (see tr. 90),
do not mention MC anywhere. They do, however, reference EMT (previously noted to
be a type of conduit) and “rigid (threaded)” conduit. (R4, tab 82; see also tr. 118) Thus,
we find the evidence that the use of MC was discussed and agreed to at this meeting to be
weak. Whatever happened, it certainly was not deeply discussed or analyzed by either
party and we find it unlikely that there was any consideration of what the contract terms
required or what contract requirements the Corps might waive.

        In any event, Corps personnel on site did not prevent Watts from installing MC
during most of the preliminary construction of the project. In fact, on several occasions,
the Corps inspected wiring installation inside walls prior to the “closing” of the walls by
the installation of drywall and made no objection to the use of MC (e.g., tr. 96-99). It is
important to note, however, that the quality assurance person on site for the Corps was
not primarily performing a quality assurance function for electrical work, but was
focused on other disciplines (tr. 134-35). Watts provided testimony from Mr. Woodruff
that Mr. John DeVito, one of the Corps quality assurance representatives, had stated
(after the Corps required the removal of the MC) that he read the specifications as
allowing the use of MC (tr. 105-06).

       On March 9, 2017, the Corps Quality Assurance Electrical Engineer for the
project, Ms. May Okuhara, inspected the work already performed and determined that
Watts had not complied with the contract due to its use of MC, rather than conduit

                                                  6
(tr. 171-72; R4, tab 34). The lower level quality assurance persons on site for the Corps
had never been made aware that Watts’s use of MC was in any way contra-indicated by
the plans and specifications before then (tr. 193-94). There is no evidence in the record
that the contracting officer or any other government employee with authority to change
the contract’s requirements were aware of Watts’s use of MC in lieu of conduit
throughout the project.

       After Ms. Okuhara made her objections to the use of MC known, the Corps
directed Watts to remove the MC and replace it with conduit (R4, tab 29). Watts
complied, which entailed the substantial expense of ripping out walls already emplaced in
order to install the conduit and then replacing the walls (tr. 102-03). MC was permitted
by the Corps for use as a “fixture whip,” which is used to connect lighting fixtures to
their power sources (tr. 103).

       On August 22, 2017, Watts submitted a certified claim to the contracting officer,
passing through the claim it received from Helix, seeking $415,120 for requiring it to use
MC (R4, tab 52). The contracting officer denied this claim in a final decision dated
October 20, 2017 (R4, tab 53). This timely appeal followed.

                                       DISCUSSION

        Notwithstanding the contract’s two mentions of MC, the contract required the use
of specified rigid conduit, not MC. Moreover, the contract terms requiring the use of
conduit were unambiguous. Though the Corps’ failure to object to Watts’s use of MC is
disappointing, it did not change the contract’s requirements or otherwise entitle Watts to
relief. Thus, we deny the appeal.

       I. The Contract Required The Use Of Conduit, Not MC

       The government’s position on the contract is straightforward: Section 3.1.3 of the
specifications required the use of specified conduit unless otherwise noted, and nothing in
the contract noted otherwise. Accordingly, the use of MC was prohibited. (See gov’t br.
at 8). Watts, on the other hand, argues that the contract’s citation to MC in two places
means that it is permitted (app. br. at 5). Watts also argues that MC is conduit, and thus
allowed by the drawings (id at 5-6; app. reply br. at 5-6). The government is correct.

       To resolve the meaning of the contract, we begin with the law of contract
interpretation. Under basic principles of the law, a contract is interpreted “in terms of the
parties’ intent, as revealed by language and circumstance.” United States v. Winstar
Corp., 
518 U.S. 839
, 911 (1996) (citations omitted). Generally, this process begins and
ends with the language of the contract. TEG-Paradigm Envtl., Inc. v. United States, 
465 F.3d 1329
, 1338 (Fed. Cir. 2006). And in reviewing this language, the Board should read
the contract “as a whole and [interpret it] to harmonize and give reasonable meaning to

                                                 7
all its parts,” if possible, leaving no words “useless, inexplicable, inoperative,
insignificant, void, meaningless or superfluous.” Precision Dynamics, Inc., ASBCA
No. 50519, 05-2 BCA ¶ 33,071 at 163,922 (citations omitted); see also Hercules, Inc. v.
United States, 
292 F.3d 1378
, 1381 (Fed. Cir. 2002) (“contract must be construed to
effectuate its spirit and purpose giving reasonable meaning to all parts of the contract”);
Hunkin Conkey Constr. Co. v. United States, 
461 F.2d 1270
(Ct. Cl. 1972) (rejecting
contract interpretation that would render a clause in the contract meaningless).

        To Watts, the existence of language describing MC in the contract means that it
must be permitted because otherwise, the language would be superfluous, which is
disfavored by law (app. br. at 5-7). It is true that the law disfavors superfluous language,
but it is also true that we are interpreting a particular contract that plainly contains
unnecessary “boilerplate” beyond just its reference to MC. As noted above, in addition to
referring to MC, the contract also, indisputably, contains descriptions of armored cable and
flat conductor cable which were not required or ever used in the construction. Thus, an
understanding of the contract as written must reckon with the fact that its drafters included
some unnecessary “boilerplate” describing types of cabling not used. 12 We add that the
language describing MC never said that it should be used in particular cases, just that if it
were used, it should be done in a certain way (see tr. 73 (interpretation by Mr. Doner)).

       Against this rather weak argument, the plainly proscriptive language in Section 3.1.3
leaves no room for doubt that only rigid conduit may be used for power. To be sure, the
Section did provide the “out” that non-enumerated wiring, could be used “where
specifically indicated or specified otherwise or required by NFPA 70 to be installed
otherwise...” but Watts (through Mr. Doner’s testimony referenced above) has conceded
that nowhere in the specifications and drawings is there any specific indication of MC, and
Watts has not alleged that the NFPA required the installation of MC instead of conduit.

        Watts appears to argue that the reference to “conduit” in the legend of the
drawings combined with Mr. Doner’s assertion that “conduit,” as a generic term
embracing MC means that the drawings would permit MC, thereby allowing it to escape
the strictures of Section 3.1.3 (app. br. at 6). As stated earlier, we have made the factual
determination that “conduit” in the contract does not include MC. Moreover, for the
reference to “conduit” in the drawing legend to overcome Section 3.1.3’s requirement for
four specified types of conduit, it would have to “specifically indicat[e]” as much. Even
if we agreed that “conduit” was meant to be a generic term embracing MC (and we
emphatically do not), we would find that use of a generic term in the drawing legend is


12
     The government does not make the argument, but the allowance of MC on the “whips”
         for lighting fixtures could conceivably make the references to MC in the contract
         less superfluous. We need not, however, draw that conclusion to get to the same
         result.
                                                 8
not the kind of specific indication required for use of anything but the specified conduit
in Section 3.1.3. Thus, in accordance with Section 3.1.3 of the contract, the Corps was
right to require the use of conduit over MC.

       II. The Corps’ Failure To Stop Watts From Using MC Provides No Basis
            For Granting Watts Relief

        In terms of equity, the failure of Corps inspectors to halt the use of MC early in the
contract, before the closure of walls and near completion of wiring work, is troubling, to
say the least. Nevertheless, in terms of equity, it was also Watts’s responsibility to
comply with the terms of the contract. Moreover, absent affirmative misconduct (not
alleged or proved here) the government’s failure to enforce the terms of a contract is not a
matter of estoppel. Tech. Sys., Inc., ASBCA No. 59577, 17-1 BCA ¶ 36,631 at 178,387
(“TSI”). Recognizing the implications of TSI, Watts has limited its argument of the
import of the Corps’ conduct to a reflection of how the Corps interpreted the contract
(tr. 7-8; app. br. at 7).

       A. Government Inspectors’ Apparent Acquiescence To The Use Of MC
          Does Not Change The Meaning Of The Contract

        Watts argues that the government’s acquiescence to its use of MC and its
inspectors’ beliefs that MC was permitted provide evidence that the Corps interpreted the
contract the same way that it did, which may be considered by the Board when
interpreting the provisions at issue here (see app. reply br. at 6-7, citing Gresham & Co.,
Inc. v. United States, 
200 Ct. Cl. 97
, 114 (Ct. Cl. 1972) (citing Kraus v. United States, 
366 F.2d 975
, 981 (Ct. Cl. 1966)). We agree that the contemporaneous interpretation of a
contract prior to a dispute is entitled to some consideration. See Aegis Def. Services, LLC,
ASBCA Nos. 59082, et al., 17-1 BCA ¶ 36,915 at 179,856, citing Blinderman Constr. Co.
v. United States, 
695 F.2d 552
, 558 (Fed. Cir. 1982) (contemporaneous construction of an
agreement prior to dispute is entitled to great weight). Nevertheless, under the
circumstances presented here, we find this argument to be unpersuasive.

       Primarily, we reject Watts’s argument because we do not find the contract to be
ambiguous. Accordingly, we need not go beyond the language of the contract to divine
its meaning. 
TEG-Paradigm, 465 F.3d at 1338
. Even if we were inclined to go beyond
the contract language here, however, we would not find the government inspectors’
inaction or their opinions on the meaning of the contract to be particularly helpful. We
may only speculate to what degree any government quality assurance personnel
compared the requirements of the specifications to Watts’s use of MC, and the hearsay
statement that Mr. DeVito thought the contract permitted the use of MC is of little
evidentiary value: why did he think it was permitted? And was this reason based upon
knowledge of the government’s expectations or simply buying into the same oversight as
Helix personnel? Since we do not know the answers to these questions, his opinion has

                                                 9
little persuasive weight in terms of divining the intent of the contract drafters, even if held
by one person who worked for the government. Obviously, Ms. Okuhara, who also
worked for the government but was in a more senior position, held a different opinion.

       B. The Government Did Not Waive Compliance With The Contract’s Terms

       In its reply brief, primarily in a footnote, Watts also makes the argument that the
government waived compliance with the terms of the contract (app. reply br. at 7 n.2).
Were we so inclined, we could reject this argument as being brought too late; moreover,
we are familiar with (and agree with) decisions in other courts that consider arguments
raised only in footnotes to be waived. E.g., United States v. Centeno, 
793 F.3d 378
, 388
n.9 (3d Cir. 2015). In any event, we disagree with Watts on the substance of this
argument.

        There is a line of cases which provides that the government may waive strict
compliance with contractual requirements and be precluded from later re-imposing those
requirements upon the contractor. See, e.g., Gresham & Co. v. United States, 
470 F.2d 542
, 554 (Ct. Cl. 1972) (“There can be no doubt that a contract requirement for the
benefit of a party becomes dead if that party knowingly fails to exact its performance, over
such an extended period, that the other side reasonably believes the requirement to be
dead”); Worldwide Parts, Inc., ASBCA No. 38896, 91-2 BCA ¶ 23,717 at 118,712; Walsky
Constr. Co., ASBCA No. 36940, 90-2 BCA ¶ 22,934 at 115,125; see also Miller Elevator
Co. v. United States, 
30 Fed. Cl. 662
, 687-88 (1994). Notably, though, these cases require
knowing failure to exact performance – presumably by one with authority to waive
contractual terms. As the government points out, there is a long line of cases in which we
have found that erroneous approval of contractors’ work by government inspectors does
not, by itself, constitute waiver by the government. See Atterton Painting & Constr., Inc.,
ASBCA No. 31471, 88-1 BCA ¶ 20,478 at 103,586-87 (citing and quoting cases). Here,
there is no evidence that any government personnel knowingly waived the contractual
terms inasmuch as the quality assurance representatives on site who observed the use of
MC appear to have been of the opinion that it was not precluded by the contract.
Moreover, as a matter of authority, under the Changes Clause, only the contracting officer
is noted as having the authority to alter the terms of the contract on behalf of the
government. Whether such authority may be delegated to such persons as quality
assurance representatives, there is no evidence that they possessed such authority or that
the contracting officer was made aware of any waiver of contract terms by them. Watts has
proved no knowing waiver of adherence to contract terms by anybody who could do so on
behalf of the government.




                                                 10
                                     CONCLUSION

       The direct terms of the contract plainly required the use of conduit, which does not
include MC, and the government never waived compliance with the contract’s terms.
The appeal is denied.

       Dated: March 19, 2020




                                                 J. REID PROUTY
                                                 Administrative Judge
                                                 Vice Chairman
                                                 Armed Services Board
                                                 of Contract Appeals

 I concur                                        I concur




 RICHARD SHACKLEFORD                             ALEXANDER YOUNGER
 Administrative Judge                            Administrative Judge
 Acting Chairman                                 Armed Services Board
 Armed Services Board                            of Contract Appeals
 of Contract Appeals


      I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 61493, Appeal of Watts
Constructors, LLC, rendered in conformance with the Board’s Charter.

       Dated: March 31, 2020

                                                  PAULLA K. GATES-LEWIS
                                                  Recorder, Armed Services
                                                  Board of Contract Appeals


                                               11

Source:  CourtListener