Elawyers Elawyers
Ohio| Change

Perdoni Brothers Inc v. Concrete Sytems Inc, 93-2178 (1994)

Court: Court of Appeals for the First Circuit Number: 93-2178 Visitors: 14
Filed: Sep. 06, 1994
Latest Update: Mar. 02, 2020
Summary:  The time limit placed upon Perdoni ___ ____ _____ ______ ____ _______ began to run at the time of delivery of the _____ __ ___ __ ___ ____ __ ________ __ ___ manholes, regardless of whether Perdoni knew _________ __________ __ _______ _______ ____ of the breach. Wells Real Estate, 850 F.2d at 810;
USCA1 Opinion












UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT

____________________
No. 93-2178

PERDONI BROTHERS, INC.,

Plaintiff, Appellee,

v.

CONCRETE SYSTEMS, INC.,

Defendant, Appellant.


____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Joyce L. Alexander, U.S. Magistrate Judge]
_____________________


____________________

Before

Breyer,* Chief Judge,
___________

Campbell, Senior Circuit Judge,
____________________

and Cyr, Circuit Judge.
_____________


____________________

John M. Lovely, with whom Daniel F. Cashman and Gelerman &
_______________ ___________________ ___________
Cashman were on brief for appellant.
_______
Valeriano Diviacchi, with whom Diviacchi Law Office was on brief
___________________ ____________________
for appellee.


____________________

September 2, 1994

____________________


____________________

*Chief Judge Stephen Breyer heard oral argument in this matter,
but did not participate in the drafting or the issuance of the panel
opinion. The remaining two panelists therefore issue this opinion
pursuant to 28 U.S.C. 46(d).














CYR, Circuit Judge. Defendant-appellant Concrete
CYR, Circuit Judge
______________

Systems, Inc. (CSI), a New Hampshire producer of pre-cast con-

crete products, contracted in 1985 with plaintiff-appellee

Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construc-

tion firm, to manufacture and deliver 121 custom-designed man-

holes, at a total contract price of $51,670.47, for installation

in a new sewer system in the Town of Ashland, Massachusetts. CSI

contends that the district court committed reversible error in

denying its post-verdict motion for judgment as a matter of law.

See Fed. R. Civ. P. 50. For the reasons hereinafter discussed,
___

we affirm the district court judgment.



I
I

BACKGROUND
BACKGROUND
__________


The first five manholes were delivered to the Perdoni

job site by CSI on July 2, 1985. The remaining 116 manholes were

delivered intermittently in twenty-six shipments extending over

the next thirteen months and invoiced by individual shipment.

Dissatisfied with the CSI manholes (which leaked and

had to be patched),1 Perdoni brought this diversity action in

____________________

1Sewer line manholes must be watertight. A common point of
leakage is the area where the sewer lines enter the manhole
structure. Precise casting, as well as installation of rubber
"boots" to ensure a tight fit between the wall of the structure
and the sewer line itself, is necessary to ensure the integrity
of the manhole. At trial, Perdoni adduced evidence that CSI had
used a defective hole former to cast the manholes for the Ashland
project. Consequently, the pipe openings in the sides of the
manholes were misshapen and the seals between the boot and rim of
the openings were not watertight.

2














federal district court on April 25, 1990, demanding $134,000 in

compensatory damages for breach of the implied warranties of

merchantability and fitness for a particular purpose (implied

warranty claims), see Mass. Gen. L. ch. 106 2-314, 2-315, and
___

additional damages based on a deceptive trade practices claim

under Mass. Gen. L. ch. 93A ("Chapter 93A"). CSI counterclaimed

for $18,561 allegedly due from Perdoni on the Ashland project and

another contract.

Trial was held before a magistrate judge, with the

consent of the parties. See 28 U.S.C. 636(c). The implied
___

warranty claims were tried to a jury, while the Chapter 93A claim

was tried to the presiding magistrate judge. It was not until

after the close of all the evidence that CSI first moved for

judgment as a matter of law on the implied warranty claims

relating to 108 of the 121 manholes. The uncontroverted evidence

demonstrated that only 13 manholes had been delivered by CSI

within four years of the commencement of the present action. CSI

accordingly contended that Perdoni's implied warranty claims

relating to the other 108 manholes were time-barred under Mass.

Gen. L. ch. 106 2-725(1) (prescribing four-year limitation on

Uniform Commercial Code warranty actions); id. 2-725(2) (action
___

for breach of warranty under UCC accrues on "tender of delivery"

of goods). The magistrate judge denied CSI's motion for judgment

as a matter of law.

Thereafter, the magistrate judge convened a charge

conference to consider the jury instructions, including the


3














instruction on the statute-of-limitations defense. Neither party

requested an instruction on the law governing the severability-
___

entirety issue. Although Perdoni unsuccessfully sought an

instruction that the contract should be considered an entirety,

CSI made no corresponding request for an instruction that the

contract be considered severable. Consequently, the magistrate

judge simply instructed the jury that CSI had the burden of

proving that the action was time-barred, and that the four-year

limitation period ran from the "time of delivery." Although both

parties argued the severability-entirety issue, the court made no

explicit reference to it and neither party objected to the jury

instruction as given.2 The jury found in favor of Perdoni-

____________________

2The instruction relating to the statute of limitations
follows:

[T]here is also an issue arising from [CSI's]
asserted defense based on . . . the statute
of limitations.
This is simply a provision that a suit
be commenced on certain types of claims with-
in a prescribed period of time, otherwise,
the suit is barred or precluded. For a
breach of warranty claim, the applicable
statute of limitations for an action on a
contract for the sale of goods is four years.
That means that a plaintiff has four
years to bring a suit for a breach of war-
ranty. The time limit placed upon Perdoni
___ ____ _____ ______ ____ _______
began to run at the time of delivery of the
_____ __ ___ __ ___ ____ __ ________ __ ___
manholes, regardless of whether Perdoni knew
_________ __________ __ _______ _______ ____
of the breach. Thus within four years of the
__ ___ ______
time which Perdoni received the manholes, it
must have commenced this lawsuit.
* * *
It is [CSI's] burden to show that Perd-
oni has not complied with the statute of
limitations, thus [CSI] has the burden of
establishing that Perdoni filed a suit more
than four years after the delivery of the

4














for $48,961, and in favor of CSI for $18,561 on its counter-

claim. CSI then renewed its Rule 50 motion for judgment as a

matter of law and, alternatively, moved for a new trial under

Fed. R. Civ. P. 59. The magistrate judge did not address the

merits of the CSI motion, however, ruling instead that CSI had

waived its severability claim, both by failing to object to the

jury instruction and by failing to raise the severability argu-

ment in its pre-verdict Rule 50 motion.3 Nonetheless, the

____________________

manholes, and if Perdoni did not commence the
suit within the four-year period, Perdoni may
not recover on its warranty theories.

Trial Tr. at 168 (April 16, 1993) (emphasis added).

3The magistrate judge noted that:

This Court instructed [the jury] that,
as an affirmative defense, CSI had the burden
of proving . . . that Perdoni filed the suit
more than four years after delivery of the
manholes. CSI did not object to this
instruction. Nor did CSI submit an
instruction based on the law governing divis-
ibility of performance, entire contracts,
separate contracts and installment contracts.
CSI was apparently content to treat the
question of what constitutes the time of
delivery as an issue of fact. CSI did move
___
for a directed verdict on this issue, but,
again, this motion was predicated on the
evidence being clear as to the tender of
delivery and included no argument as to the
________ __ ________ __ __ ___
law governing divisibility of performance,
___ _________ ____________ __ ___________
entire contracts, separate contracts and
______ __________ ________ _________ ___
installment contracts. CSI's pretrial
___________ _________
memorandum was no more edifying on this
point. . . . This court finds it late in the
day to be raising the legal issue, and deems
the issue waived.

Perdoni Bros., Inc. v. Concrete Sys., Inc., Civ. 90-11046-WF,
____________________ ____________________
Memorandum Order at 7-8 (D. Mass. August 27, 1993) (emphasis
added).

5














magistrate judge, sitting as trier of fact, found Perdoni's

Chapter 93A claim time-barred as it pertained to 108 of the 121

manholes. CSI appealed the denial of its post-verdict motion for

judgment as a matter of law or for a new trial on the implied

warranty claims. See Fed. R. Civ. P. 50(b), 59. CSI's primary
___

appellate target is the district court's waiver ruling on the

severability issue.



II
II

DISCUSSION
DISCUSSION
__________


Leaving aside CSI's failure to object to the jury

instruction on the statute-of-limitations defense, the district

court waiver ruling is fully supported by CSI's failure to raise

the severability argument in its pre-verdict motion for judgment

as a matter of law. The law is crystal clear that a "party may

not base its motion for a judgment n.o.v. on a ground that was

not argued in its motion for directed verdict." Sweeney v.
_______

Westvaco Co., 926 F.2d 29, 37 (1st Cir.) (citing Systemized of
_____________ _____________

New England, Inc. v. SCM, Inc., 732 F.2d 1030, 1035 (1st Cir.
__________________ _________

1984)), cert. denied, 112 S. Ct. 274 (1991); see also 9 Charles
_____ ______ ___ ____

A. Wright & Arthur R. Miller, Federal Practice & Procedure 2537
____________________________

(1971) ("Since it is technically only a renewal of the motion . .

. made at the close of evidence, [a post-verdict Rule 50 motion]

cannot assert a ground that was not included in the motion for a

directed verdict."); 5A James W. Moore, Moore's Federal Practice
________________________

50.08 (2d ed. 1994) (same). Sweeping invocations of conclusory

6














theories or abstract principles will not suffice: "The motion

must . . . be made with sufficient specificity to allow the

district court to understand precisely why the evidence is

insufficient." Wells Real Estate, Inc. v. Greater Lowell Bd. of
_______________________ _____________________

Realtors, 850 F.2d 803, 810 (1st Cir.), cert. denied, 488 U.S.
________ _____ ______

955 (1988); Pstragowski v. Metropolitan Life Ins. Co., 553 F.2d
___________ __________________________

1, 3 (1st Cir. 1977) (where Rule 50 motion was silent as to the

legal theory that plaintiff was obliged to establish malice on

the part of the defendant, there was no basis for an appellate

challenge to the sufficiency of the evidence on the element of

malice). Ultimately, of course, "[a]ppellate review may be

obtained only on the specific ground stated in the motion for

directed verdict." Wells Real Estate, 850 F.2d at 810; Pstragows-
_________________ __________

ki, 553 F.2d at 3 (same).
__

The pre-verdict motion for judgment as a matter of law,

see Fed. R. Civ. P. 50(a),(b), stressed the undisputed fact that
___

108 manholes were delivered more than four years prior to suit,

but presented no authority or argumentation whatever that the

contract should be considered severable (i.e., that Massachusetts
____

law permitted or required that the individual shipments of

manholes receive separate treatment for statute-of-limitation

purposes, rather than as an entire contract for 121 manholes).

The consequences of CSI's cryptic approach were foreordained.

Most importantly, the district court was never fore-

warned of the legal basis for the severability claim first

surfaced by CSI following the adverse jury verdict. Under our


7














precedent, therefore, on appeal CSI was not entitled to challenge

the sufficiency of the evidence supporting the jury verdict on

the limitations issue. See Wells Real Estate, 850 F.2d at 10;
___ _________________

Pstragowski, 553 F.2d at 3. The magistrate judge correctly ruled
___________

that CSI was bound by its own pre-verdict decision to entrust its

severability claim to the jury with no further legal definition

than the unchallenged instruction that "accrual" under the

Massachusetts UCC occurs at the "time of delivery." See United
___ ______

California Bank v. Eastern Mountain Sports, Inc., 546 F. Supp.
_______________ ______________________________

945, 964 (D. Mass. 1982) ("Under Massachusetts law, 'it is clear

that a cause of action . . . accrues when delivery is made

regardless of the buyer's knowledge of the breach.'") (quoting

Wolverine Ins. Co. v. Tower Iron Works, 370 F.2d 700, 702 (1st
__________________ ________________

Cir. 1966)), aff'd, 705 F.2d 439 (1st Cir. 1983); accord Bay
_____ ______ ___

State-Spray & Provincetown S.S., Inc. v. Caterpillar Tractor Co.,
_____________________________________ _______________________

533 N.E.2d 1350, 1353 (Mass. 1989).4

Under Article 2 of the Uniform Commercial Code, the

severability or entirety of a contract of sale turns on the


____________________

4Counsel argued the severability-entirety issue in their
closings. CSI argued that the parties' performance under the
contract demonstrated their practice of treating each separately
________
invoiced shipment of manholes as a distinct transaction. See
________ ___
Trial. Tr. at 141 ("really what is occurring here is a series of
contracts . . . . All the manholes were made to order. The
manholes that were shipped . . . in 1986 have no relation to the
manholes that were delivered as of November 14, 1985.") Perdoni,
on the other hand, urged the jury to view the contract as a
unitary whole, and to recognize that Perdoni required all of the
manholes in order to complete its contract project. Id. at 157
___
("if you ordered 12 eggs, and you get 10, you don't say, 'Thank
you for delivering my eggs.' . . . . [T]he full quantity ordered
was not delivered until July of 1986.").

8














intent of the contracting parties, see, e.g., Carlo Bianchi & Co.
___ ____ ___________________

v. Builders' Equip. & Supplies Co., 199 N.E.2d 519, 528 (Mass.
_______________________________

1964) (severability or entirety of contract dependent on intent

of parties) (citing, inter alia, Bianchi Bros., Inc. v. Gendron,
_____ ____ ___________________ _______

198 N.E. 767, 770 (Mass. 1935)); Belanger v. Haverlock, 537 A.2d
________ _________

604 (Me. 1988) (same); Lake LBJ Mun. Util. Dist. v. Coulson &
___________________________ _________

C.A.E., Inc., 771 S.W.2d 145 (Tex. 1988) (same); Scruggs v.
_____________ _______

Quality Elec. Serv., Inc., 320 S.E.2d 49 (S.C. 1984) (same); In
_________________________ __

re Estate of Wilson, 405 N.E.2d 220 (N.Y. 1980); 1901 Wyoming
____________________ _____________

Ave. Coop. Assoc. v. Lee, 345 A.2d 456 (D.C. 1975); see also 17A
_________________ ___ ___ ____

Am. Jur. 2d 415 (1991) ("Whether a contract is entire or

severable is a question of fact"), a quintessential jury ques-

tion. There can be no question that CSI elected to forego a more
_______

definitive jury instruction on the law governing the severabili-

ty-entirety issue pressed on appeal. As was its right, CSI

simply attempted to persuade the jury that the parties intended a

severable contract. Having once embarked on this course, howev-

er, CSI was not entitled to set out on a new one after its chosen

litigation tactic failed. See Brody v. President & Fellows of
___ _____ _______________________

Harvard College, 664 F.2d 10, 12 (1st Cir. 1981) (noting that
_______________

litigants ordinarily are bound by their tactical decisions at

trial), cert. denied, 455 U.S. 1027 (1982). Thus, the district
_____ ______

court did not err in denying the motion for judgment as a matter

of law, since CSI "forfeited its right to raise the [severability

claim] by waiting to raise it until after the jury reached its




9














verdict." Sweeney, 926 F.2d at 37.5
_______

Next, even assuming that it failed to preserve its

severability claim for appeal, CSI argues that a new trial is

required due to alleged inconsistencies between the jury's award

of damages on the implied warranty claims and the magistrate

judge's resolution of the limitations defense relating to the

Chapter 93A claim. We do not agree.

First, as no special interrogatory was submitted to the

jury on the limitations defense relating to the implied warranty

claims, it would be conjectural to conclude that the damages

awarded by the jury and the finding made by the magistrate judge

are irreconcilable. See Fed. R. Civ. P. 49(a) (right to trial on
___

particular issue waived absent request for specific jury find-

ing); Kavanaugh v. Greenlee Tool Co., 944 F.2d 7, 11 (1st Cir.
_________ __________________

1991) (applying Rule 49 waiver provision). In determining the

intent of the contracting parties in this case, the jury may

either have found (1) that the contract was severable, and made a

generous award of damages (i.e., 37% of the total damages re-
____

quested by Perdoni on only 11% of the units supplied by CSI); or

(2) that the contract was not severable, and made a meager award

(i.e., 37% of the total damages requested by Perdoni on 100% of
____

the units supplied by CSI). The inconsistency posited by CSI is


____________________

5As CSI advances the same arguments in support of its appeal
from the denial of its Rule 59 motion, we conclude that the
district court likewise acted well within its discretion in
denying CSI's motion for new trial on the merits. See Phav v.
___ ____
Trueblood, Inc., 915 F.2d 764, 766 (1st Cir. 1990) ("abuse of
_______________
discretion" standard governs review of denial of Rule 59 motion).

10














predicated on the assumption that the jury made a meager award of

damages, yet there is no record basis for such a conclusion.

Given the strong presumption of regularity attending jury ver-

dicts, see, e.g., Veiga v. McGee, 26 F.3d 1206, 1215 (1st Cir.
___ ____ _____ _____

1994) (noting that reviewing court is compelled to uphold jury

verdict under Rule 50 "even in a close case" unless no reasonable

jury could have reached the same conclusion), we decline to

disturb the verdict on the basis of the assumed inconsistency

posited by CSI.

Second, CSI posits an inconsistency between the results

reached by different decisionmakers on distinct claims, and

incorrectly assumes that the jury verdict must yield. Where an

irreconcilable inconsistency exists between a bench decision and

a jury verdict on different claims arising out of the same

transaction, the jury finding must take precedence in the Seventh

Amendment context: "when a party has a right to a jury trial on

an issue involved in a legal claim, the judge is of course bound

by the jury's determination of that issue as it affects his

disposition of an accompanying equitable claim." Lincoln v.
_______

Board of Regents, 697 F.2d 928, 934 (11th Cir.) (citing Curtis v.
________________ ______

Loether, 415 U.S. 189, 196 n.11 (1974); Dairy Queen, Inc. v.
_______ __________________

Wood, 396 U.S. 469, 470-73 (1962)), cert. denied, 464 U.S. 826
____ _____ ______

(1983); Los Angeles Police Protective League v. Gates, 995 F.2d
_____________________________________ _____

1469, 1473 (9th Cir. 1993) (same); Fowler v. Land Management
______ ________________

Groupe, Inc., 978 F.2d 158, 163 (4th Cir. 1992) (same); Wade v.
____________ ____

Orange Cty. Sheriff's Office, 844 F.2d 951, 954 (2d Cir. 1988)
_____________________________


11














(same); see also Walsh v. Chestnut Hill Bank & Trust Co., 607
___ ____ _____ ________________________________

N.E. 2d 737, 740-41 (Mass. 1993) (noting "equitable" nature of

claims under Chapter 93A; no right to jury trial). Moreover, in

the Chapter 93A context, the court has recognized that judge and

jury, sitting as independent triers of fact, may reach

conflicting conclusions. Wallace Motor Sales, Inc. v. American
__________________________ ________

Motors Sales Corp., 780 F.2d 1049, 1063-67 (1st Cir. 1985)
____________________

(rejecting claim that judge's findings must always conform to

those of the jury; upholding findings made by district judge on

Chapter 93A claim and by jury on Dealers Act claim); accord
______

Fowler, 978 F.2d at 162-63 (concluding that under certain circum-
______

stances "it is entirely acceptable that the two fact-finders

reach conflicting conclusions on the issues"). Thus, even

assuming inconsistent findings, CSI's claim must fail. Cf.
___

Kavanaugh, 944 F.2d at 9 (noting this court's "substantial
_________

reluctance to consider inconsistency [within] civil jury verdicts

a basis for new trials.")

Finally, permitting CSI to employ the bench ruling on

the severability issue as a lever with which to upset the jury

verdict would circumvent the important Rule 50 corollary that "a

party who move[s] for a directed verdict may obtain appellate

review only on the specific ground stated in the motion."
____

Pstragowski, 553 F.2d at 3 (emphasis added); accord Fleming James
___________ ______

Jr. et al., Civil Procedure 7.30 (4th ed. 1992) (observing that
_______________

post-judgment motions for judgment as a matter of law are "limit-

ed to the assertion of issues or grounds specifically raised in


12














the prior motion"); see also Doty v. Sewall, 908 F.2d 1053, 1057
___ ____ ____ ______

n.4 (1st Cir. 1990) (noting that failure to bring issue underly-

ing new trial claim to district court's attention is significant

because "'[b]y doing so . . . [the party] got a chance to see the

verdict and then to seek to overturn it.'") (quoting Caldarera v.
_________

Eastern Airlines, Inc., 705 F.2d 778, 782 (5th Cir. 1983).
________________________

Challenges to jury verdicts must be evaluated against the back-

drop of the case "as submitted" to the jury. See, e.g., Griffin
___ ____ _______

v. Matherne, 471 F.2d 911, 915 (5th Cir. 1973), quoted in 1
________ ______ __

Steven A. Childress & Martha S. Davis, Federal Standards of
_____________________

Review 3.10 (2d ed. 1992).
______

Affirmed.6
Affirmed.























____________________

6Although counsel fees have been awarded on occasion for an
appellate defense of a judgment on a Chapter 93A claim, see,
___
e.g., Manzaro v. McCann, 401 Mass. 880, 885 (1988), there is no
____ _______ ______
basis for a fee award to Perdoni, since CSI did not challenge the
district court judgment on the Chapter 93A claim.

13







Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer