Filed: Sep. 20, 2013
Latest Update: Mar. 28, 2017
Summary: Stonestreet and Weybosset are both Rhode Island companies.continued project costs; The jurisdictional, issue in this case centers around the reach of federal jurisdiction, to include state law claims between non-diverse parties;against Allstate.We affirm the district court's discovery ruling.
United States Court of Appeals
For the First Circuit
No. 12-2431
ALLSTATE INTERIORS & EXTERIORS, INC.,
Plaintiff,
v.
STONESTREET CONSTRUCTION, LLC,
Defendant/Third Party Plaintiff-Appellee,
v.
WEYBOSSET HOTEL, LLC,
Third Party Defendant-Appellant.
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF RHODE ISLAND
[Hon. Mary M. Lisi, U.S. District Judge]
Before
Lynch, Chief Judge,
Torruella, Circuit Judge,
and Stearns,* District Judge.
Thomas More Dickinson for appellant.
Christine K. Bush, with whom Anastasia A. Dubrovsky and Scott
& Bush Ltd. were on brief, for appellee.
September 20, 2013
*
Of the District of Massachusetts, sitting by designation.
LYNCH, Chief Judge. After a ten-day bench trial, the
district court awarded a judgment against Weybosset Hotel, LLC
("Weybosset") and in favor of its construction company, Stonestreet
Construction, LLC ("Stonestreet"), in the sum of $571,595.
Stonestreet and Weybosset are both Rhode Island companies.
Weybosset appeals, arguing that there was no federal jurisdiction,
and the $571,595 was awarded in error.
Weybosset argues that the district court erred in
exercising supplemental jurisdiction over this case following the
settlement of some of the dispute between the case's two diverse
parties, Stonestreet and Allstate Interiors & Exteriors. It also
challenges one of the district court's discovery rulings, along
with its interpretation of the governing construction contract.
We affirm.
I. Background
All of the claims in this case arise from the Hampton Inn
& Suites renovation and construction project in Providence, Rhode
Island. Stonestreet, as the construction manager and general
contractor, entered into a construction contract ("Contract") with
Weybosset in November 2007, with an initial project completion date
of November 25, 2008. Largely as a result of cost overruns and
other delays, disputes relating to the Contract have now been the
subject of litigation in state and federal court.
-2-
A. Key Contract Provisions
The main compensation provision in the Contract is its
Guaranteed Maximum Price (GMP), which is defined as the sum of the
"cost of work" and the "construction manager's fee." The GMP was
not to exceed the maximum of $11,250,000 originally set by the
contract, "but was subject to additions and deductions by changes
in the Work as provided in the Construction Documents." The GMP-
adjustment mechanism came in the form of "Change Order Requests"
(CORs), under which Stonestreet could seek additional funds if
project timing or cost requirements changed. Throughout the
project, CORs were typically prepared by Stonestreet and submitted
to Weybosset for approval and signature.
Included in the GMP was $809,888, which represented a
lump sum of Stonestreet's "general conditions" costs from the
preconstruction and construction phases of the project. The lump
sum included more specific line-item estimates, including the costs
of an administrative assistant, project executive, and project
manager. During the project, Stonestreet divided the lump sum
equally across its monthly payment requisitions until the original
lump sum was fully billed by November 2008.
Generally, Stonestreet paid its subcontractors pursuant
to its standard form contracts, which contained a pay-when-paid
clause that stated: "It is agreed that the Contractor
[Stonestreet], as a condition precedent to payment of any monies
-3-
which become due to the Subcontractor, must first receive payment
from the Owner." The timing disconnect between the pay-when-paid
provision and the payment schedule under the Contract between
Weybosset and Stonestreet, which was based on the overall progress
of the project, led to several instances of subcontractors not
being paid after their work was completed.
B. Project Delays
The main project delay concerned the provision of
"permanent power" to the building. In the early stages of the
project, Weybosset's existing structures provided temporary power;
however, Stonestreet eventually required a permanent power supply
to continue work on the project.1 In the construction contract,
the parties agreed that "[p]rimary service, cable and transformer"
were excluded from Stonestreet's scope of work, and were thus
controlled by Weybosset. At trial, witnesses testified that
"primary service" means "permanent power."
Stonestreet initially anticipated having permanent power
at the project site during the summer of 2008. Power was in fact
not supplied at that time, and the delay in supplying permanent
power led to delays in, among other things, installation of the
mechanical, electrical, and elevator systems. As a result of these
1
Stonestreet's witnesses testified at trial that without
delivery of permanent power, Stonestreet could not disconnect any
of the old electrical panels, nor could it fully supply power to
the renovated building so that it could perform required life
safety testing.
-4-
delays, Stonestreet generated an updated project schedule on
October 27, 2008, which reflected a revised completion date of
January 28, 2009; at that point, the remaining elements of the
project could not be completed without permanent power at the site.
Power was ultimately provided on January 6, 2009.
In light of these delays, Stonestreet submitted COR 127,
which sought an increase in the total GMP of $152,473.20 to cover
increased general conditions costs that resulted from the overall
project delays. In January 2009, Stonestreet submitted a draft of
Requisition 14, which sought payment for December 2008 work as
specified in COR 127. At the time of submission, Stonestreet was
not advised that it would not be paid for its continued work on the
project (as reflected in COR 127), and it continued to install
systems once permanent power was supplied to the building. In
March and April, Stonestreet twice updated COR 127 to reflect
continued project costs; Weybosset did not respond to either
submission. On May 29, 2009, Edmund Landry, Weybosset's
representative, formally rejected COR 127.
C. Procedural History
The case was originally filed on June 26, 2009 in the
U.S. District Court for the District of Rhode Island by Allstate
Interiors & Exteriors ("Allstate"), one of the subcontractors on
the project, against Stonestreet. Allstate sought payment of an
outstanding balance of $244,725, and Stonestreet counterclaimed
-5-
that Allstate had not completed the work as originally agreed
between the parties. In addition, Stonestreet filed a third-party
complaint against Weybosset, bringing several state law causes of
action arising from the construction project. The claims included
breach of contract, breach of good faith and fair dealing, unjust
enrichment, and tortious interference with contractual relations.
Stonestreet also argued that Weybosset's failure to pay Stonestreet
certain sums caused Stonestreet to breach its contract with
Allstate and other subcontractors on the project, and that
Weybosset should therefore indemnify Stonestreet for damages
sustained as a result of such breaches.
While this case was pending in federal court, all three
parties were involved in parallel litigation in Rhode Island state
court. That litigation dealt with two mechanics' liens, filed
against Weybosset by Allstate and Stonestreet, respectively. The
dispute between Allstate and Weybosset in state court was resolved
by settlement.
When Allstate resolved its claim against Weybosset in
state court, it effectively resolved most of Allstate's claims
against Stonestreet in federal court. Stonestreet's counterclaim
against Allstate remained outstanding, and Allstate remained a
party to the case. While the resolution of Allstate's claim
against Stonestreet, confirmed during a January 21, 2010 hearing
before the district court, came relatively quickly after the
-6-
initiation of this case, Allstate participated in discovery along
with Stonestreet and Weybosset. Additionally, because
Stonestreet's counterclaim against Allstate was still pending,
Allstate remained a party to the case regardless of the state court
settlement.
Following this partial settlement, Weybosset filed a
motion to dismiss Stonestreet's third-party complaint for lack of
subject matter jurisdiction in November 2009. It argued that the
main dispute in the case concerned state law claims between two
non-diverse parties, Weybosset and Stonestreet (both Rhode Island
companies), and that exercising federal jurisdiction over the
dispute between those parties following the resolution of some
claims between Allstate and Stonestreet (the two diverse parties)
was therefore improper. Notably, Allstate remained a party to the
case following the partial settlement, as Stonestreet's
counterclaim against Allstate was not part of the settlement. The
district court denied Weybosset's motion on February 24, 2010.
Before trial, Weybosset filed a series of discovery
motions, each seeking to strike certain of Stonestreet's materials
from the record. The district court denied all three motions, and
Weybosset appeals from one of those rulings.
-7-
Following a partial grant of summary judgment in
Weybosset's favor that is not at issue in this appeal,2 the
district court conducted a ten-day bench trial. After the trial
and the filing of post-trial memoranda, the district court issued
its final order on October 31, 2012. As it is relevant to this
appeal, the district court ruled in favor of Stonestreet on the
core breach of contract claim and awarded damages in the amount of
$571,595. Before this court, Weybosset appeals three of the
district court's rulings: (1) the exercise of supplemental
jurisdiction following Allstate and Stonestreet's partial
settlement; (2) the interpretation of the construction contract for
the purpose of calculating damages; and (3) the denial of
Weybosset's discovery motion regarding supplemental expert reports.
II. The District Court's Exercise of Supplemental Jurisdiction
We review a district court's decision regarding the
exercise of supplemental jurisdiction for abuse of discretion.
Vera-Lozano v. Int'l Broad.,
50 F.3d 67, 70 (1st Cir. 1995).
Finding that the district court did not abuse its discretion in
exercising jurisdiction over the dispute between Stonestreet and
Weybosset, we find no error.
2
Weybosset's motion for partial summary judgment was filed
with respect to $1,016,499 in subcontractor costs that Stonestreet
sought to recover. Because Weybosset had already partially settled
these claims by paying $893,521 to the subcontractors directly, the
district court granted Weybosset's motion with respect to the sums
already paid.
-8-
It is plain -- and the parties do not dispute -- that the
district court initially had supplemental jurisdiction over the
claims between Weybosset and Stonestreet under section 1367(a),
which states:
[I]n any civil action of which the district
courts have original jurisdiction, the
district courts shall have supplemental
jurisdiction over all other claims that are so
related to claims in the action within such
original jurisdiction that they form part of
the same case or controversy under Article III
of the United States Constitution. Such
supplemental jurisdiction shall include claims
that involve the joinder or intervention of
additional parties.
28 U.S.C. § 1367(a) (emphasis added); see Godin v. Schencks,
629
F.3d 79, 83 (1st Cir. 2010). State and federal claims are part of
the same "case or controversy" for the purposes of section 1367(a)
if they "'derive from a common nucleus of operative fact' or 'are
such that [they] . . . would ordinarily be expected to [be] tr[ied]
. . . in one judicial proceeding.'" Penobscot Indian Nation v. Key
Bank of Me.,
112 F.3d 538, 564 (1st Cir. 1997) (second, third, and
fourth alterations in original) (quoting United Mine Workers v.
Gibbs,
383 U.S. 715, 725 (1966)). Weybosset does not dispute that
at the outset of the dispute, it was proper for the district court
to exercise supplemental jurisdiction over Stonestreet's state law
claims against Weybosset under section 1367(a).
Instead, Weybosset argues that the district court's
decision on the jurisdictional issue is governed by
-9-
section 1367(b). In cases where the district court's original
jurisdiction is based solely on diversity jurisdiction, that
section strips federal jurisdiction "over claims by plaintiffs
against persons made parties under Rule 14, 19, 20, or 24 of the
Federal Rules of Civil Procedure . . . when exercising supplemental
jurisdiction over such claims would be inconsistent with the . . .
requirements of [diversity jurisdiction]." 28 U.S.C. § 1367(b).
Weybosset was made a party to the case under Rule 14, and argues
that even though section 1367(b) applies to claims of "plaintiffs,"
the underlying rationale of that section should counsel against the
district court's decision to exercise jurisdiction over this case.3
Weybosset claims that we should read section 1367(b) to strip the
district courts of jurisdiction over claims made by either
plaintiffs or third-party plaintiffs against non-diverse parties
brought into a case pursuant to Rule 14. Stonestreet's rebuttal is
that Weybosset's reading of section 1367(b) is contrary to the
3
Weybosset's reliance on Genesis Healthcare Corp. v. Symczyk,
133 S. Ct. 1523 (2013), is misplaced. Weybosset argues that
Genesis Healthcare "suggests that where the underlying claim that
invokes federal jurisdiction has been resolved -- even if not
formally disposed -- there is no 'case or controversy' sufficient
to invoke jurisdiction under Article III." Genesis Healthcare
turned on a question of mootness in a collective action under the
Fair Labor Standards Act (FLSA). In that case, the lead
plaintiff's claim was satisfied, and the Court held that once that
individual claim was moot, so too was the larger suit because the
lead plaintiff had no personal interest in representing other
members of the group in the case. Id. at 1532. The jurisdictional
issue in this case centers around the reach of federal jurisdiction
to include state law claims between non-diverse parties; mootness
principles do not control the outcome.
-10-
plain language of the statute and in conflict with established case
law. Stonestreet is correct.
Although we have not previously addressed this issue
directly, we now hold that "plaintiff" in section 1367(b) refers to
the original plaintiff in the action, and not to a defendant that
also is a third-party plaintiff. In so holding, we join several
other circuits that have come to the same conclusion. See State
Nat'l Ins. Co. v. Yates,
391 F.3d 577, 580 (5th Cir. 2004); Grimes
v. Mazda N. Am. Operations,
355 F.3d 566, 572 (6th Cir. 2004);
Viacom Int'l v. Kearney,
212 F.3d 721, 726-27 (2d Cir. 2000);
United Capitol Ins. Co. v. Kapiloff,
155 F.3d 488, 492 (4th Cir.
1998); Dev. Fin. Corp. v. Alpha Hous. & Health Care, Inc.,
54 F.3d
156, 160-61 (3d Cir. 1995). This holding is consistent with
Congress's intent that section 1367(b) should "prevent original
plaintiffs -- but not defendants or third parties -- from
circumventing the requirements of diversity." Grimes, 355 F.3d at
572; see also United Capitol Ins. Co., 155 F.3d at 493 ("Because
defendants are involuntarily brought into court, their joinders and
impleaders were not deemed [by Congress] as suspect as those of the
plaintiff, who is master of his complaint."). On this reading of
section 1367(b), because Stonestreet was not a plaintiff in the
original action, the statute cannot operate to withdraw
jurisdiction from subsequent claims made pursuant to Rule 14.
-11-
In the alternative, Weybosset argues on the basis of
section 1367(c), which lists circumstances in which the district
courts "may decline to exercise supplemental jurisdiction" over a
claim that would otherwise be a proper subject for supplemental
jurisdiction. 28 U.S.C. § 1367(c) (emphasis added). One such
circumstance is if "the [state] claim substantially predominates
over the claim or claims over which the district court has original
jurisdiction." Id. § 1367(c)(2). We find that the decision to
exercise jurisdiction over the dispute between Stonestreet and
Weybosset was not an abuse of discretion.
The district court's evaluation of Weybosset's
jurisdictional argument focused on two key issues. Allstate had
not dismissed its claim against Stonestreet in federal court
because Stonestreet was still pursuing its related counterclaim
against Allstate. Not only did Allstate remain a party to the
case, but it was integrally involved in the case before Weybosset
filed its motion to dismiss for lack of subject matter jurisdiction
on November 12, 2009.
Perhaps more serious than Weybosset's contention that
Allstate's partial settlement justified dismissal is its
predominance argument. Weybosset's core claim is that the district
court should have declined to exercise supplemental jurisdiction
under section 1367(c)(2) because the state claims between the non-
diverse parties to the case predominated over all other claims at
-12-
issue. Section 1367(c) codifies the holding of United Mine Workers
of America v. Gibbs,
383 U.S. 715 (1966), where the Supreme Court
clarified that a district court may dismiss state claims "if it
appears that the state issues substantially predominate, whether in
terms of proof of the scope of the issues raised, or of the
comprehensiveness of the remedy sought." Id. at 726. As the
district court noted, both the Allstate-Stonestreet dispute and the
Stonestreet-Weybosset dispute arose from the contracts relating to
the same construction project. Although Stonestreet's claims
against Weybosset involved a greater monetary claim than its
remaining dispute with Allstate, both sets of claims thus depended
on the same body of evidence and sought a similar legal remedy in
the form of contractual damages. Stonestreet's non-diverse claims
against Weybosset did not clearly predominate over the remaining
diverse claims.
Furthermore, while section 1367(c) provides that a
district court "may decline to exercise supplemental jurisdiction"
under certain circumstances, it does not obligate a district court
to do so. Although the grounds enumerated in section 1367(c)
ordinarily lead to dismissal of state claims, "this praxis is not
compelled by a lack of judicial power" and "in an appropriate
situation, a federal court may retain jurisdiction over state-law
claims notwithstanding." Rodriguez v. Doral Mortg. Corp.,
57 F.3d
1168, 1177 (1st Cir. 1995); see also Oneida Indian Nation of N.Y.
-13-
v. Madison Cnty.,
665 F.3d 408, 439 (2d Cir. 2011) ("To be sure,
the fact that one or more of the grounds for declining to exercise
supplemental jurisdiction set forth in section 1367(c) applies does
not mean that dismissal is mandated.").
In light of the substantial parity between the diverse
and non-diverse cases and the district court's discretion over
remaining supplemental jurisdiction under section 1367(c), we
cannot find that the district court erred by deciding to exercise
jurisdiction in this case.
III. The District Court's Interpretation of the Contract Under
Rhode Island Law
On appeal from a bench trial, pure issues of law are
reviewed de novo, while findings of fact are reviewed for clear
error. Litif v. United States,
670 F.3d 39, 43 (1st Cir. 2012).
Weybosset challenges two sums included in the district
court's judgment: $65,665 (for secretaries and estimators at
Stonestreet's office) and $182,956 (for personnel, insurance,
dumpsters, and other costs following the construction delay
period).4 Weybosset argues the district court's inclusion of these
amounts in the judgment amounted to a violation of Rhode Island
4
In its reply brief, and for the first time before this
court, Weybosset contested the inclusion of $81,050.67 in
preconstruction costs. Issues advanced for the first time in reply
briefs are deemed waived. Waste Mgmt. Holdings, Inc. v. Mowbray,
208 F.3d 288, 299 (1st Cir. 2000). Even if this challenge were
properly before us, however, it suffers from the same legal
deficiencies as those above.
-14-
contract law. Both challenges lack merit, and we affirm the
district court.
Weybosset argues that including the sum for secretaries
and estimators was in error under § 6.2.1 of the Contract, which
generally excludes (1) the salaries of Stonestreet's personnel at
Stonestreet's principal office, (2) the expenses of that office,
and (3) overhead and expenses, all except as specifically provided
elsewhere in the contract. Weybosset argues that the parties never
formally altered this provision per the modification section of the
contract, which required modifications to be in writing. This
argument is unavailing: at the outset of the project, when the
parties agreed that Stonestreet would be paid for its "general
conditions costs" in a lump sum, the now-disputed line items were
explicitly included in the original breakdown of that lump sum. In
effect, there was a writing -- implicitly approved by both parties
-- that resulted in this modification. In short, the district
court correctly held that Weybosset waived its challenge to these
line items both when it agreed to the lump sum general conditions
and when it paid Stonestreet's first thirteen requisitions (which
included portions of this lump sum) without challenge.
Further, the district court upheld the use of the lump
sum as a valid modification of § 6.2.1 of the construction contract
under Rhode Island law. See Fondedile, S.A. v. C.E. Maguire, Inc.,
610 A.2d 87, 92 (R.I. 1992) ("[P]arties to a contract can mutually
-15-
assent to modify a contract if the modification does not violate
the law or public policy and if the modification is supported by
adequate consideration."). In this case, the mutual assent came
from the initial approval of the lump sum, and then from the
conduct of the parties surrounding the payment of the first
thirteen requisitions. Rather than a "sua sponte modification" of
the contract as Weybosset contends, the district court's ruling was
instead a valid finding of a contract modification and waiver based
on the parties' continuing course of conduct during the project.
The district court did not err in applying Rhode Island contract
law.
Weybosset's argument opposing the judgment in
Stonestreet's favor for "personnel, insurance, dumpsters[,] and
other costs" is particularly tenuous and ill-specified. Neither
the "other costs" nor their connection to the disputed contract
provision are ever specified in Weybosset's briefing. That portion
of Weybosset's argument, at the very least, is waived. See United
States v. Zannino,
895 F.2d 1, 17 (1st Cir. 1990) ("[I]ssues
adverted to in a perfunctory manner, unaccompanied by some effort
at developed argumentation, are deemed waived.").
The remaining claims are advanced in such a cursory
fashion that they could also be waived under Zannino; however, on
the merits, Weybosset's argument likewise fails. The district
court's findings with regard to dumpster costs and additional
-16-
clean-up costs were based on trial testimony: the costs were
included in COR 127 and arose as a result of project delays caused
by Weybosset's failure to deliver primary power to the project on
time. This testimony, and the district court's resulting finding,
was consistent with § 7.3.6 of the Contract, which stated that
Stonestreet was entitled to increased costs (including labor costs)
that resulted from increases in the scope of work that were
attributable to Weybosset. At trial, the district court noted
Weybosset's failure to present any testimony or evidence to counter
Stonestreet's explanation of these charges, and went on to note
Weybosset's failure "to demonstrate that those charges were not
legitimate." On appeal, Weybosset likewise offers no evidence on
this point, and we see no reason to disturb the district court's
considered determination.
IV. Discovery Motion
In managing discovery disputes, we recognize the district
court's broad discretion. As such, we disturb a trial court's
determination on a discovery matter "only upon a clear showing of
manifest injustice, that is, where the lower court's discovery
order was plainly wrong and resulted in substantial prejudice to
the aggrieved party." Mack v. Great Atl. & Pac. Tea Co.,
871 F.2d
179, 186 (1st Cir. 1989); see also Brandt v. Wand Partners,
242
F.3d 6, 18 (1st Cir. 2001) ("Discovery decisions by the . . .
district court are reviewed for abuse of discretion, and the
-17-
discretion in this area is very broad, recognizing that an appeals
court simply cannot manage the intricate process of discovery from
a distance."). In light of this standard, we affirm the district
court's rulings on Weybosset's discovery motion.
Weybosset's appeal on this point centers on Stonestreet's
provision -- shortly after expert discovery closed, but a year
before trial -- of a supplemental interrogatory response and
supporting documentation from one of Stonestreet's experts. The
district court found that these corrected disclosures in fact were
timely and contemplated by Rule 26(e)(2). See Fed. R. Civ. P.
26(e)(2) (providing that a party's duty to supplement an expert's
report "extends both to information included in the report and to
information given during the expert's deposition," and that this
information "must be disclosed by the time the party's pretrial
disclosures under Rule 26(a)(3) are due").
It is clear that Stonestreet's supplemental materials
were disclosed in a timely fashion; further, Weybosset falls well
short of proving prejudice resulting from the district court's
ruling. It claims that the district court's ruling on the
discovery motion "impeded Weybosset's ability to prepare for trial
and put counsel in the position of having no opportunity to inquire
on these documents until the trial itself." This contention is
without merit. Not only did Stonestreet's supplemental materials
reflect a change in calculations in Weybosset's favor, but at
-18-
trial, Weybosset's expert testified that his review of
Stonestreet's supplemental materials did not change the opinions
initially expressed in his expert report. Finally, the one-year
lag between the disclosure of the supplemental materials and trial
make plain that Weybosset had ample time to inspect the materials
prior to trial.
We affirm the district court's discovery ruling.
V. Conclusion
The district court's judgment is affirmed. Costs are
awarded to Stonestreet but we deny its request for an award of
double costs.
-19-