Elawyers Elawyers
Washington| Change

The Florida Paraplegic Assoc. v. Uccello Immobilie, 99-13156 (2000)

Court: Court of Appeals for the Eleventh Circuit Number: 99-13156 Visitors: 163
Filed: Sep. 22, 2000
Latest Update: Feb. 21, 2020
Summary: [PUBLISH] IN THE UNITED STATES COURT OF APPEALS FOR THE ELEVENTH CIRCUIT FILED - U.S. COURT OF APPEALS No. 99-13156 ELEVENTH CIRCUIT SEPTEMBER 22, 2000 - THOMAS K. KAHN CLERK D. C. Docket No. 97-00173-CV-DMM EDWARD RESNICK, an individual, Plaintiff-Appellee, versus UCCELLO IMMOBILIEN GMBH, INCORPORATED, a foreign corporation doing business in Florida, G & K INVESTMENTS MANAGEMENT, INC., a Florida corporation, Defendants-Appellants. - Appeal from the United States District Court for the Southern
More
                                                                                  [PUBLISH]

              IN THE UNITED STATES COURT OF APPEALS
                     FOR THE ELEVENTH CIRCUIT
                                                                            FILED
                        ------------------------------------------- U.S. COURT OF APPEALS
                                     No. 99-13156                     ELEVENTH CIRCUIT
                                                                      SEPTEMBER 22, 2000
                       -------------------------------------------- THOMAS K. KAHN
                                                                                 CLERK
                      D. C. Docket No. 97-00173-CV-DMM


EDWARD RESNICK, an individual,

                                                         Plaintiff-Appellee,

     versus

UCCELLO IMMOBILIEN GMBH, INCORPORATED, a
foreign corporation doing business in Florida,
G & K INVESTMENTS MANAGEMENT, INC., a Florida
corporation,

                                                         Defendants-Appellants.


              ----------------------------------------------------------------
                   Appeal from the United States District Court
                         for the Southern District of Florida
              ----------------------------------------------------------------
                                (September 22, 2000)


Before EDMONDSON, BARKETT and RONEY, Circuit Judges.

PER CURIAM:

     Uccello Immobilien, GMBH (“Defendant”), seeks to reverse a liquidated
damages award ordered pursuant to a settlement agreement with Edward Resnick

(“Plaintiff”),1 and to reverse the denial of a motion to extend the time of

performance. Because the liquidated damages award was punitive, and because the

district court did not abuse its discretion in denying the motion to extend time of

performance, we vacate in part and affirm in part.



                                               A.



       Plaintiff and Defendant entered into a settlement agreement to bring

Defendant’s office building into compliance with the American with Disabilities

Act (“ADA”), 42 U.S.C. § 12182, et seq.2 The settlement required Defendant to

begin construction for the accommodations 30 days after the district court

approved the settlement (subject to Defendant obtaining the necessary building

permits) and to complete the construction four months later. If Defendant could


   1
     Four plaintiffs initially sued Defendant for alleged ADA violations. Resnick is the only
plaintiff that moved to enforce the settlement agreement with Defendant; thus he is the only
plaintiff for purposes of this appeal.
   2
     The accommodations required by the settlement agreement include these things: (1) on-site
disabled parking spaces with a curb cut; (2) a passenger drop-off area with a curb cut; (3) an on-
street disabled parking space with a curb cut; (4) a fire alarm system with 75 candela strobe
lights; (5) lower bank counters with enough space for knee clearance; (6) accessible hardware on
doors; (7) lower drinking fountains; (8) braille in the elevator and on door jambs; (9) a lower
emergency telephone in the elevator; and (10) accessible restrooms with signs indicating such.

                                                2
not complete the project in a timely fashion due to circumstances beyond its

control, then Defendant would be afforded a reasonable delay upon agreement of

the parties or by court order. Otherwise, delay in completion would result in

liquidated damages of $100 per day plus costs and fees.

      On 4 December 1997, the district court approved the settlement and retained

enforcement authority. See Kokkonen v. Guardian Life Ins. Co. of Amer., 114 S.

Ct. 1673, 1677 (1994). Defendant did not apply for a building permit until August

1998. When Plaintiff visited the building in January 1999, he observed that the

accommodations required by the settlement had not been completed; Plaintiff,

however, was still able to transact his business in the building. At Plaintiff’s

request, an ADA consultant then inspected the building to confirm which

accommodations required by the settlement remained incomplete.

      Plaintiff on 2 March 1999 filed a Motion to Enforce the Settlement against

Defendant. After filing four extensions to reply to Plaintiff’s motion, Defendant

responded in June 1999, at which time Defendant also moved to enlarge the time to

satisfy the settlement.

      The district court ordered Defendant to complete the accommodations, to

pay Plaintiff’s attorney’s fees and costs, and to pay liquidated damages of




                                           3
$18,500.003 to a charity as designated by Plaintiff. The court also denied

Defendant’s motion for an extension of time to complete the accomodations.

Defendant now appeals.



                                                B.



       We review a court’s decision to enforce a settlement agreement for an abuse

of discretion. Hayes v. National Serv. Indus., 
196 F.3d 1252
, 1254 (11th Cir.

1999). An error of law is an abuse of discretion per se. Alikhani v. United States,

200 F.3d 732
, 734 (11th Cir. 2000). Principles governing general contract law

apply to interpret settlement agreements. Schwartz v. Florida Bd. of Regents, 
807 F.2d 901
, 905 (11th Cir. 1987); Crosby Forrest Products, Inc. v. Byers, 
623 So. 2d 565
, 567 (Fla. Dist. Ct. App. 1993). And, even though this settlement agreement

arose under the ADA, state contract law directs our analysis here.4 See Hayes, 196

   3
    The district court ordered Defendant to pay $100 per day for each day the improvements
were not complete, dating back to 2 January 1999, four months after the city granted the building
permit, until 7 July 1999, the day of the order.
   4
     We generally disfavor federal common law and apply it in only rare instances concerning
“rights and obligation of the United States, interstate and international disputes implicating the
conflicting rights of States or our relations with foreign nations, and admiralty cases.” Kobatake
v. E.I. DuPont Nemours and Co., 
162 F.3d 619
, 624 n.3 (11th Cir. 1998) (quoting Texas
Industries, Inc. v. Radcliff Materials, Inc., 
101 S. Ct. 2061
, 2067 (1981)); see also City of
Huntsville v. City of Madison, 
24 F.3d 169
, 172 n.3 (11th Cir. 1994). Because this settlement
agreement is between two private parties, federal common law does not apply. Cf. Brewer 
v. 4 F.3d at 1253
(applying state law to construction and enforceability of settlement

agreement arising under Title VII); 
Schwartz, 807 F.2d at 905
(same).

       Liquidated damages arising from breach of contract are appropriate when

(1) damages from the breach are not readily ascertainable, and (2) the sum

stipulated is not grossly disproportionate to the damages reasonably expected to

follow from the breach. MCA Television Ltd. v. Public Interest Corp., 
171 F.3d 1265
, 1271 (11th Cir. 1999); Hyman v. Cohen, 
73 So. 2d 393
, 401 (Fla. 1954) (en

banc). But liquidated damages are inappropriate when they serve only to punish

the breaching party. Lefemine v. Baron, 
573 So. 2d 326
, 328-29 (Fla. 1991).

       For the first element, potential damages arising from breach of this

settlement agreement are not readily ascertainable. Handicapped persons who are

inconvenienced or harmed by Defendant’s failure to comply with the settlement

agreement may suffer some damage of varying degrees from Defendant’s potential

breach of contract. Thus, some amount of liquidated damages might be

appropriate in this context.

       The amount of liquidated damages provided by the settlement agreement,



Muscle Shoals Bd. of Educ., 
790 F.2d 1515
, 1519 (11th Cir. 1986) (applying federal common
law to interpret EEOC predetermination settlement agreement negotiated by EEOC); Eatmon v.
Bristol Steel & Iron Works, Inc., 
769 F.2d 1503
, 1516 (11th Cir. 1985) (applying federal
common law to interpret executive order conciliation agreement between government and
employer).

                                             5
however, is grossly disproportionate to the damages reasonably expected to flow

from the breach. While liquidated damages may or may not precisely compensate

for the actual breach, the disparity may not be so great as to compensate minimal

damages with substantial sums. See MCA Television 
Ltd., 171 F.3d at 1271
(“Parties may not [] use [liquidated damages] provisions as a way to secure for

themselves greater damages in the event of a breach than contract law would

normally allow.”).

      In this case, Plaintiff entered the building in January 1999 and saw that the

settlement requirements had not been met; he seemingly was not denied use of the

building based on his handicap and was still able to complete his business there.

Plaintiff has not alleged that he suffered monetary damages due to the breach; yet

he seeks to enforce a $18,500 liquidated damages award. Absent the liquidated

damages provision, Plaintiff would be entitled to minimal damages at best for the

breach. The gross disparity between the stipulated amount of liquidated damages

and the damages flowing from the beach causes the damages provision to fail.

      That the district court ordered the damages award to be paid to a charity as

directed by Plaintiff further establishes that this award was punitive and that

Plaintiff suffered no actual damages from the breach. Plaintiff seeks no personal

compensation for the breach; payment to the charity serves only to penalize


                                          6
Defendant for nonperformance, much like payment to a public entity for violation

of a local ordinance.

      Plaintiff and the district court rely on Six Cos. of Cal. v. Joint Hwy Dist. No.

13, 
110 F.2d 620
(9th Cir.), rev’d on other grounds, 
61 S. Ct. 186
(1940), to argue

that liquidated damages may be awarded when the breach inconveniences a group

intended to benefit from the contract. In that case, the court awarded a

municipality liquidated damages under a contract to build a highway and tunnel.

The court held that, even where a municipality suffers no actual damages from the

breach, liquidated damages are available for the “inconvenience and loss which

will flow to its inhabitants for whose benefit the improvement is intended and at

whose cost it is to be built.” 
Id. at 625.
      Six Cos. of Cal. is inapplicable to and distinguishable from the present facts.

This contract does not involve a public entity, but instead a private charitable

organization and disabled persons. Unlike public funds used to construct a major

highway, the intended beneficiaries (disabled people who are denied access to

Defendant’s building) under the contract are not paying for the improvements. In

addition, Plaintiff has not asserted that he has even been inconvenienced or

suffered loss from the breach. See Multitech Corp. v. St. Johns Bluff Investment

Corp., 
518 So. 2d
. 427, 433 (Fla. Dict. Ct. App. 1988) (finding it inequitable to


                                             7
enforce liquidated damages for breach that “bore no significance to the

[plaintiff]”).

       Liquidated damages are permissible where the award is intended as

compensation for failure to perform. The liquidated damages provision at issue

here, however, is a penalty intended to induce performance of the settlement

agreement. See 
Hyman, 73 So. 2d at 398
; Multitech Corp., 
518 So. 2d
at 432. The

settlement agreement does not apportion liquidated damages based on the different

accommodations not completed; Defendant is subject to the same penalty whether

substantial or only minor improvements are incomplete. See 
Hyman, 73 So. 2d at 398
; Smith v. Newell, 
20 So. 249
, 251 (Fla. 1896). Even Plaintiff in his filings

refers to the liquidated damages clause as a penalty.

       We vacate the award of liquidated damages because the award is grossly

disproportionate to damages reasonably expected to flow from the breach and is

solely punitive.



                                         C.



       The district court did not abuse its discretion in denying Defendant’s motion

to extend the time for performance. The settlement agreement provided that, if


                                          8
circumstances beyond Defendant’s control delayed performance, then the parties

could agree to a reasonable delay. If the parties could not agree, then the court

could extend the time. Sixteen months after the settlement agreement, Defendant

moved to extend the time to complete performance, which the court denied.

       Defendant’s two excuses – the city required Defendant to upgrade the fire

alarm system in the building and the general contractor needed to be replaced after

suffering a severe car wreck in July 1998 – do not justify Defendant’s failure to

complete, in a timely way, at least some of the accommodations sought in

Plaintiff’s Motion to Enforce. Thus, the district court properly acted within its

discretion in denying the motion to extend time.



                                              D.



       Pursuant to the terms of the settlement agreement, the district court properly

awarded Plaintiff, as the prevailing party, attorney’s fees, costs and expert fees

incurred in litigating at the district court.5 The settlement agreement entitles the

prevailing party in an enforcement action to an award of such fees.

Notwithstanding our decision to set aside the award of liquidated damages, we


   5
    Plaintiff’s motion for fees and costs related to the appeal is DENIED.

                                               9
affirm the district court’s decision to award fees and costs for the proceedings in

district court.

       We remand to the district court to determine the appropriate amount of fees

and costs to be awarded to Plaintiff.

       VACATED in part, AFFIRMED in part, and REMANDED.




                                          10
RONEY, Circuit Judge, dissenting:

      I respectfully dissent. I would affirm the district court’s decision.

      To we who are fully able, it may seem that a disabled person suffers minimal

damage when a building does not conform to the legal requirements, but for the

person whom those regulations seek to protect, the harm may be far more than

minimal. Obviously this is virtually impossible to quantify in economic terms.

That is the exact reason that the law provides for liquidated damages. Otherwise

there is no way to enforce compliance.

      The appellant made an agreement. There is no just reason why it should not

pay damages for failure to fulfill the terms of that agreement. Certainly, if the

requirement was in the form of a mandatory injunction rather than a settlement

agreement, the assessment of the minimal amount here for violation of that

injunction would not be questioned by this Court. Although this is an individual

case, not a class action, the settlement agreement was intended to benefit others

than the plaintiff and it seems to me the district court’s decision should be

reviewed with that in mind.




                                          11

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer