Elawyers Elawyers
Ohio| Change

Miller Exploration v. Energy Drilling Co, 02-31020 (2003)

Court: Court of Appeals for the Fifth Circuit Number: 02-31020 Visitors: 19
Filed: Apr. 09, 2003
Latest Update: Feb. 21, 2020
Summary: United States Court of Appeals Fifth Circuit F I L E D UNITED STATES COURT OF APPEALS April 9, 2003 FIFTH CIRCUIT Charles R. Fulbruge III _ Clerk No. 02-31020 (Summary Calendar) _ MILLER EXPLORATION CO, Plaintiff - Counter Defendant - Appellee, versus ENERGY DRILLING CO, Defendant - Counter Claimant -Appellant. Appeal from the United States District Court For the Western District of Louisiana 99-CV-802 Before DAVIS, WIENER, and EMILIO M. GARZA, Circuit Judges. PER CURIAM:* Energy Drilling Co. (“
More
                                                                                  United States Court of Appeals
                                                                                           Fifth Circuit
                                                                                        F I L E D
                            UNITED STATES COURT OF APPEALS
                                                                                          April 9, 2003
                                     FIFTH CIRCUIT
                                                                                    Charles R. Fulbruge III
                                        _________________                                   Clerk
                                            No. 02-31020

                                        (Summary Calendar)
                                        _________________


MILLER EXPLORATION CO,


                                Plaintiff - Counter Defendant - Appellee,

versus


ENERGY DRILLING CO,


                                Defendant - Counter Claimant -Appellant.



                            Appeal from the United States District Court
                               For the Western District of Louisiana
                                            99-CV-802



Before DAVIS, WIENER, and EMILIO M. GARZA, Circuit Judges.

PER CURIAM:*

         Energy Drilling Co. (“Energy”), the appellant, challenges the district court’s interpretation

of a standard form day rate drilling contract, in which Miller Exploration Co., the appellee, hired




         *
               Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R.
47.5.4.
Energy to drill an oil and gas well in Louisiana. At this point in the proceedings, only two narrow

issues remain. Because contractual interpretation is an issue of law for the court, we review the

district court’s ruling de novo. Amoco Prod. Co. v. Tex. Meridian Res. Exploration Inc., 
180 F.3d 664
, 668 (5th Cir. 1999).

        The first issue involves the applicable rate of interest to be paid on the money owed by Miller

to Energy. Paragraph 5.2 of the contract states that late payments “shall bear interest at the rate of

one percent or the maximum legal rate, whichever is less, per month from the due date until paid.”

Id. (emphasis added).
The district court interpreted “maximum legal rate” to be synonymous with

the “judicial rate” under LA. CIV. CODE ANN. art. 2924(A), which is less than one percent per month,

and ruled that the judicial rate applied.

        We disagree with that interpretation. Part (C)(1) of art. 2924 limits the rate of “conventional”

interest to “twelve per cent per annum.” Louisiana law is clear that conventional interest, if stipulated

in writing, is recoverable on debt arising from contract from the date the debt becomes due until the

date it is paid, regardless of whether the debt is the subject of a lawsuit in the meantime. See, e.g.,

Helena Chem. Co. v. Nichols, 
695 So. 2d 1000
, 1000 (La. Ct. App. 1997). Thus, when a contract

refers to a “maximum legal rate,” the most reasonable interpretation of that term is that it refers to

the maximum rate allowed under law for the type of interest recovered in contract. Louisiana has set

a limit for contractual interest in art. 2924(C)(1), and this is the limit referenced in the contract.

        Because Energy is entitled to the lesser of one percent per month or twelve percent per year,

the latter is the applicable rate of interest.1 The judgment of the district court on this issue is



        1
         Energy argues that these two rates are the same. Of course, this is only true if the interest
at issue is simple interest. Either way, twelve percent per year is what Energy is owed.

                                                   -2-
REVERSED.

        Energy also appeals the daywork rate applicable to its loss of use claim. With regard to this

second issue, we find Energy’s argument meritless. As we held in the last appeal, paragraph 10 of

the contract controls Miller’s liability to Energy and it is unambiguous. Thus, we AFFIRM the

district court and hold that the force majeure rate applies until the date Miller terminated the contract.



        JUDGMENT AFFIRMED IN PART; REVERSED IN PART.




                                                   -3-

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer