KAREN LECRAFT HENDERSON, Circuit Judge:
In 2007, the United States Army Corps of Engineers (Corps) issued Mingo Logan Coal Co. (Mingo Logan) a permit to excavate the tops of several West Virginia mountains, extract exposed coal and dispose of the excess soil and rock in three surrounding valleys containing streams. Four years later, after additional study, the United States Environmental Protection Agency (EPA) decided that the project would result in "unacceptable adverse effect[s]" to the environment. See 33 U.S.C. § 1344(c). The EPA therefore withdrew approval from two of the disposal sites, which together "make up roughly eighty eight percent of the total discharge area authorized by the permit." Mingo Logan Coal Co. v. EPA (Mingo Logan I), 850 F.Supp.2d 133, 137 (D.D.C. 2012). In 2013, Mingo Logan challenged the EPA's statutory authority to withdraw the two sites from the Corps permit after it had been issued but we determined that the Clean Water Act (CWA) authorized the EPA to do so. See Mingo Logan Coal Co. v. EPA (Mingo Logan II), 714 F.3d 608, 616 (D.C. Cir. 2013). We then remanded the case to the district court to consider Mingo Logan's remaining Administrative Procedure Act (APA) challenges. See id. The district court thereafter rejected them. See Mingo Logan Coal Co. v. EPA (Mingo Logan III), 70 F.Supp.3d 151, 183 (D.D.C. 2014).
Mingo Logan now appeals the district court's resolution of its APA claims. Specifically, the company argues that the EPA failed to engage in reasoned decisionmaking by ignoring Mingo Logan's reliance on the initial permit, impermissibly considering the effects of downstream water quality and failing to explain adequately why the project's environmental effects were so unacceptable as to justify withdrawal. We conclude that the EPA did not violate the APA in withdrawing specification of certain disposal areas from the permit; rather, it considered the relevant factors and adequately explained its decision. The EPA's ex post withdrawal is a product of its broad veto authority under the CWA, not a procedural defect. Accordingly, we affirm.
Under the CWA, 33 U.S.C. §§ 1251 et seq., a party must generally obtain a permit from the relevant state and/or federal authority before discharging "any pollutant"
Under section 404, the Corps and qualified states are authorized to issue permits allowing "the discharge of dredged or fill material" into bodies of water "at specified disposal sites." Id. § 1344(a), (g). The permit is required if, as here, a permit applicant plans to remove soil or rock from one location (i.e., "fill material"
Id.
Although the EPA does not issue the 404 permit directly, it has "a broad environmental `backstop' authority over the [Corps's] discharge site selection." Mingo Logan II, 714 F.3d at 612. Specifically, under section 404(c), the EPA may "deny," "restrict" or "withdraw[]" specification of a site for disposal of dredge-and-fill material. 33 U.S.C. § 1344(c). The EPA is authorized to exercise this authority "whenever [the EPA Administrator] determines, after notice and opportunity for public hearings, that the discharge of such materials into such area [specified for disposal] will have an unacceptable adverse effect on municipal water supplies, shellfish beds and fishery areas (including spawning and breeding areas), wildlife, or recreational areas." Id. (emphasis added). In Mingo Logan II, we held that the EPA could exercise this "backstop" authority both pre-permit and post-permit; that is, the EPA may prevent the Corps from issuing a 404 permit specifying a disposal site or it may withdraw specification of a disposal site after the Corps has issued a permit. Mingo Logan II, 714 F.3d at 612-14, 616.
EPA regulations further define the adverse environmental effects the Administrator must identify before stepping in to deny, restrict or withdraw a 404 permit. Specifically, the EPA has interpreted "unacceptable
Section 402 of the CWA establishes a separate permitting scheme, called the National Pollutant Discharge Elimination System (NPDES), under which the EPA is authorized to issue a permit for the discharge of all pollutants other than dredge-and-fill material. See 33 U.S.C. § 1342(a); see also Coeur Alaska, Inc. v. Se. Alaska Conservation Council, 557 U.S. 261, 273, 129 S.Ct. 2458, 174 L.Ed.2d 193 (2009). Alternatively, a state may assume authority for issuing a NPDES permit "for discharges into navigable waters within its jurisdiction." 33 U.S.C. § 1342(b). If a state submits a description of its planned permitting program to the EPA and its plan meets the relevant CWA criteria, the EPA "shall approve" the program. Id. The state then becomes responsible for issuing a NPDES permit for pollutant discharge, see id. and the federal NPDES permitting program is suspended for qualified waters within that state's jurisdiction, see id. § 1342(c)(1).
The EPA, however, maintains an oversight role. It may "withdraw approval of [the state] program" if it determines that the program is not being administered in accordance with the CWA and the state takes no corrective action. See id. § 1342(c)(3). Further, a state must submit to the EPA a copy of each permit application it receives and must keep the EPA informed of the state's consideration of the application. Id. § 1342(d)(1). The EPA, acting through its Administrator, may object to the issuance of a state NPDES permit within ninety days of receipt thereof and, if it does so, the state may not issue the permit. See id. § 1342(d)(2). If the state fails to revise the permit to comply with CWA guidelines and requirements, the EPA may issue a revised permit that complies with the CWA. See id. § 1342(d)(4). Importantly, "[o]nce a section 402 permit has been issued, it may only be modified by the entity that issued the permit." Mingo Logan III, 70 F.Supp.3d at 155 (citing 40 C.F.R. §§ 122.2, 122.62, 124.5(c)).
In 1997, Hobet Mining, Inc., Mingo Logan's predecessor, began the process of securing the various permits required for operation of the Spruce No. 1 Mine, a proposed large-scale surface mining operation in West Virginia. Mingo Logan planned to use a surface-mining technique known as mountaintop mining at Spruce No. 1, whereby large swathes of land are removed from the surface, exposing coal deposits underneath. See generally Ohio Valley Envtl. Coal. v. Aracoma Coal Co., 556 F.3d 177, 186 (4th Cir. 2009). The excess soil and rock ("spoil" or "overburden") is then relocated to adjacent valleys, "creating a `valley fill' that buries intermittent and perennial streams in the process."
Mingo Logan's final proposal for the mine designated three sites for disposal of spoil, resulting in the burial of approximately 7.48 miles of three streams: (1) Seng Camp Creek; (2) Pigeonroost Branch; and (3) Oldhouse Branch. Because the streams were also going to be affected by the discharge of treated water, the project required both a 404 permit from the Corps for disposal of the spoil and an NPDES permit from West Virginia, which had secured an EPA-approved permitting plan under section 402.
Hobet Mining initiated the application process for a NPDES permit from West Virginia's Department of Environmental Protection (WVDEP) in late 1997. Consistent with its CWA obligations, WVDEP notified the EPA of the application and forwarded it a proposed permit. The EPA initially objected but, after WVDEP placed additional conditions on the NPDES permit, the EPA withdrew its objections in December 1998 and approved the modified permit in January 1999. West Virginia thus issued a valid NPDES permit to Hobet Mining on January 11, 1999. The permit was modified in 2003 and 2005, which modifications were eventually approved by the EPA. The NPDES permit has since been renewed and remains in effect.
The 404 permitting process was much more extensive. Hobet Mining first applied to the Corps for an individual 404 permit in 1999, triggering a lengthy review process. After a seven-year consultation with Mingo Logan, the EPA and West Virginia, the Corps produced a 1600-page draft Environmental Impact Statement (EIS) on March 31, 2006. Although the EPA "expressed its concern that `even with the best practices, mountaintop mining yields significant and unavoidable environmental impacts that had not been adequately described in the document,'" Mingo Logan II, 714 F.3d at 610 (quoting Letter from EPA, Region III to Corps, Huntington Dist., at 1 (June 16, 2006)), it ultimately "declined to pursue a[n] ... objection" to the issuance of a 404 permit, id. Specifically, in an email, William Hoffman, Director of the EPA Office of Environmental Programs, told the Corps that it "ha[d] no intention of taking [its] Spruce Mine concerns any further from a Section 404 standpoint." E-mail from EPA to Corps (Nov. 2, 2006), Joint App'x (J.A.) 292. On January 22, 2007, the Corps issued the 404 permit allowing the disposal of spoil into the three specified stream areas.
Mingo Logan's 404 permit was almost immediately challenged in court by environmental groups, which added the permit to ongoing litigation challenging other coal-mining permits. See Ohio Valley Envtl. Coal. v. U.S. Army Corps of Eng'rs (OVEC), 243 F.R.D. 253, 255, 257 (S.D.W.Va. 2007).
In response, on April 2, 2010, the EPA intervened directly. Invoking its veto authority under section 404(c), the EPA published a Proposed Determination withdrawing the 404 permit specification of the (as yet unused) Pigeonroost and Oldhouse Branch disposal sites. These disposal sites together amounted to approximately eighty-eight per cent of the area the original permit allowed for valley fills.
The EPA gave two primary reasons for its withdrawal: (1) the "unacceptable adverse impacts" resulting from "direct impacts to wildlife and wildlife habitat" in each area where the fill was in fact to occur (the fill "footprint"), see Final Determination of the U.S. Environmental Protection Agency Pursuant to § 404(c) of the Clean Water Act Concerning the Spruce No. 1 Mine, Logan County, West Virginia (Final Determination), at 47, 50 (Jan. 13, 2011); and (2) the "[u]nacceptable adverse impacts" on wildlife occurring "downstream of the footprint of the fills and sediment ponds," id. at 50. As to the first basis, the EPA determined that "[t]he destruction of 6.6 miles of high quality stream habitat ..., and the subsequent loss of many populations of macroinvertebrates, salamanders, fish and other wildlife dependent upon that aquatic habitat area for survival, ... will result in a loss of regional biodiversity and the broader ecosystem functions these populations provide." Id. at 47. It cited specific concerns for each population described and, in view of its conclusion that the affected streams "are some of the last, rare and important high quality streams in the watershed," it decided that the adverse effect on the local wildlife "is one that the aquatic ecosystem cannot afford." Id. at 50. As for the adverse environmental impact downstream, the EPA concluded that removing the Pigeonroost and Oldhouse Branches "as sources of freshwater dilution and converting them to sources of pollution" would increase water contamination and salinity, both producing a negative effect on various wildlife, including macroinvertebrates, salamanders, fish and water-dependent birds. Id. at 50, 60-73.
Once the EPA issued its Final Determination, Mingo Logan filed suit in district
On remand, the district court concluded that the EPA's Final Determination complied with the APA. See Mingo Logan III, 70 F.Supp.3d at 154-55. It noted that both bases the EPA asserted for withdrawing the permit — the direct effects to wildlife within the valley fills' footprint and the effects of the valley fills on downstream wildlife — independently supported its revocation decision, concluding that the EPA had not acted arbitrarily or capriciously in identifying "unacceptable adverse effect[s]" under both rationales. Id. at 175-76 (effects within the footprint); id. at 181-83 (downstream effects). Accordingly, it granted summary judgment to the EPA. Id. at 183. Mingo Logan now appeals. Our review is de novo. Murphy v. Exec. Office for U.S. Attorneys, 789 F.3d 204, 208 (D.C. Cir. 2015); see also Holland v. Nat'l Mining Ass'n, 309 F.3d 808, 814 (D.C.Cir.2002) ("[W]e review the administrative action directly, according no particular deference to the judgment of the District Court.").
The general legal principles attending our review are well-settled. The APA directs us to "set aside agency action" that is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A). Agency action is "arbitrary and capricious if the agency has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, [or] offered an explanation for its decision that runs counter to the evidence before the agency." Motor Vehicle Mfrs. Ass'n of the U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983). Although we must ensure that "an agency's decreed result [is] within the scope of its lawful authority" and that "the process by which it reaches that result [is] logical and rational," Michigan v. EPA, ___ U.S. ___, 135 S.Ct. 2699, 2706, 192 L.Ed.2d 674 (2015) (quoting Allentown Mack Sales & Serv., Inc. v. NLRB, 522 U.S. 359, 374, 118 S.Ct. 818, 139 L.Ed.2d 797 (1998)), we are "not to substitute [our] judgment for that of the agency," State Farm, 463 U.S. at 43, 103 S.Ct. 2856. Whether we would have done what the agency did is immaterial; so long as the agency "examine[d] the relevant data and articulate[d] a satisfactory explanation for its action[,] including a `rational connection between the facts found and the choice made,'" we will ordinarily uphold it. Id. (quoting Burlington Truck Lines v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962)).
When an agency changes policy, however, it must in some cases "provide a more detailed justification than what would suffice for a new policy created on a blank slate." FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515, 129 S.Ct. 1800, 173 L.Ed.2d 738 (2009). Changing policy does not, on its own, trigger an especially "demanding burden of justification," Ark Initiative v. Tidwell, 816 F.3d 119, 127 (D.C. Cir. 2016); indeed, the agency "need not demonstrate to a court's satisfaction that
In this case, Mingo Logan claims that the EPA's post-permit revocation is the epitome of arbitrary-and-capricious agency action. Not only did the EPA "entirely fail[] to consider an important aspect of the problem," Mingo Logan claims, it also "relied on factors which Congress has not intended it to consider" and "offered an explanation for its decision that runs counter to the evidence." See State Farm, 463 U.S. at 43, 103 S.Ct. 2856. This "rare and impressive trifecta," Appellant's Br. 4, is particularly egregious, Mingo Logan avers, given that the EPA was subject to Fox's more detailed justification standard, see 556 U.S. at 515-16, 129 S.Ct. 1800. As Mingo Logan sees it, because the EPA did not veto the Spruce No. 1 permit the first time around, it must provide a weighty basis for withdrawing specification of two disposal sites four years later. We disagree with Mingo Logan's assessment and address each prong of the alleged "trifecta" in turn.
Mingo Logan first argues that the EPA "entirely failed to consider an important aspect of the problem" — the costs Mingo Logan incurred in reliance on the permit and its history of compliance with the permit's conditions. Appellant's Br. 18-19 (quoting State Farm, 463 U.S. at 43, 103 S.Ct. 2856). As Mingo Logan sees it, the EPA may revoke a permit only if it balances resulting adverse environmental effects against the permittee's sunk costs and record of permit compliance; "[i]n practice, that means that [the] EPA may withdraw a specification when circumstances have changed radically or when the withdrawal has only a minor impact on the operations envisioned (and reliance interests generated) by the permit." Id. at 18. Because the EPA did not "balance" these "competing considerations," see id. but instead based its decision only on the existence vel non of adverse environmental effects, Mingo Logan cries foul.
In response, the EPA concedes that it did not consider Mingo Logan's reliance costs or its compliance history and, in its view, neither the CWA nor the APA requires it to do so. It contends, however, that we need not reach this issue because Mingo Logan failed to make the argument to the agency or to the district court and has thus forfeited it.
We agree with the EPA that the argument is forfeited and doubly so. "Simple fairness to those who are engaged in the tasks of administration, and to litigants, requires as a general rule that courts should not topple over administrative decisions unless the administrative body not only has erred but has erred against objection made at the time appropriate under its practice." United States v. L.A. Tucker Truck Lines, Inc., 344 U.S. 33,
Here, Mingo Logan did not argue the reliance-costs and compliance-history issue before the EPA or in district court, notwithstanding numerous opportunities to do so. Indeed, the EPA's process for finalizing its decision afforded Mingo Logan numerous chances to make the claim. The EPA first published a Proposed Determination detailing its environmental concerns in part as follows: "[C]onstruction of Spruce No. 1 Mine as authorized would destroy streams and habitat, cause significant degradation of on-site and downstream water quality, and could therefore result in unacceptable adverse impacts to wildlife and fishery resources." Proposed Determination to Prohibit, Restrict, or Deny the Specification, or the Use for Specification (Including Withdrawal of Specification), of an Area as a Disposal Site; Spruce No. 1 Surface Mine, Logan County, WV, 75 Fed Reg. 16,788, 16,789 (Apr. 2, 2010). It then proposed to withdraw specification of the Pigeonroost and Oldhouse Branch sites, see id. at 16,805, and solicited comments on its proposal, see id. at 16,807-08, thereby providing Mingo Logan notice and an opportunity to put forward the factors that it believed the EPA was required to consider — and had failed to consider — in reaching its initial conclusion.
Mingo Logan responded to the Proposed Determination with 172 pages of comments. Conspicuously absent therefrom, however, was any argument that the EPA had to balance the environmental effects against the costs Mingo Logan had incurred in reliance on the permit before reaching a final decision.
After reviewing these and other comments on the Proposed Determination, an EPA Regional Director then published a Recommended Determination, again proposing to withdraw specification of the Pigeonroost Branch and Oldhouse Branch sites and again inviting comments. See Recommended Determination of the U.S. Environmental Protection Agency Region III Pursuant to Section 404(c) of the Clean Water Act (Sept. 24, 2010). Yet again, other than a single reference in introductory material — "[n]ow, more than three years after the issuance of the permit, as Mingo Logan is actively mining the site in an attempt to recoup its decade-long investment, EPA has declared that the impacts that it had approved are now unacceptable, and seeks to revoke the permit," Mingo Logan Coal. Co., Comments in Response and in Opposition to the Recommended Determination 2 (Nov. 29, 2010) — Mingo Logan never claimed that the EPA had to balance reliance costs against environmental effects
Once the EPA published its Final Determination withdrawing specification of the disposal sites, Mingo Logan filed suit, eventually composed of a fourteen-count amended complaint. None of the counts alleged that the EPA's Final Determination was arbitrary and capricious because it had failed to weigh Mingo Logan's reliance costs. Again, other than one general allegation in the factual background — that "[a]fter receiving its Permit, Mingo Logan spent millions of dollars preparing the site and commencing construction and operations," Am. Compl. ¶ 141 — Mingo Logan did not assert an APA claim based on the EPA's failure to consider its reliance costs.
After we decided Mingo Logan II, the case returned to the district court for consideration of the procedural issues. At the
Supplemental Br. in Supp. of Mingo Logan's Mot. for Summ. J. at 1-3, Mingo Logan III, 70 F.Supp.3d 151 (No. 10-cv-541), ECF No. 99. Once the court resolved these four questions, according to Mingo Logan, it could move on to the fifth and final question warranting review:
Id. at 3.
Conspicuously absent from this list — yet again — is the question Mingo Logan now presents for our review — whether the EPA's failure to consider Mingo Logan's reliance costs and compliance history renders its decision arbitrary and capricious. It is also worth noting, for good measure, that in an hours-long hearing on the procedural issues, covering over one hundred pages of transcript, Mingo Logan never once raised the reliance-costs claim to the district court. See generally Transcript of 7/30/14 Hearing, Mingo Logan III, 70 F.Supp.3d 151(No. 10-cv-541). Unsurprisingly, having never been presented with the question, the district court did not address it.
This record notwithstanding, the dissent disagrees with our conclusion that Mingo Logan forfeited its reliance-costs claim. Dissenting Op. at 737-38. Our disagreement, it seems, is attributable to two differences between us. First, he believes that merely mentioning the "millions of dollars" allegedly spent in reliance upon a permit is sufficient to preserve an argument that the EPA must weigh those reliance costs against environmental harms, see id. at 738-39, 740; we do not. But, as recently noted in Encino Motorcars, LLC v. Navarro, "[t]he extent to which [an agency] is obliged to address reliance will be affected by the thoroughness of public comments it receives on the issue.... An agency cannot be faulted for failing to discuss at length matters only cursorily raised before it." ___ U.S. ___, 136 S.Ct. 2117, 2128 n. 2, 195 L.Ed.2d 382 (2016) (Ginsburg, J., concurring). Our cases have likewise demanded that parties "forcefully present[]" their arguments to the agency to preserve them on appeal. Vill. of Barrington, 636 F.3d at 656. A handful of offhand references to "millions of dollars" primarily in introductory material — and never raised in the context of a claim that the EPA must balance these costs against the environmental effects it identified — is insufficient to preserve the claim Mingo Logan now pursues on appeal.
In support of his view that Mingo Logan preserved its reliance-costs claim, our dissenting colleague cites a number of instances in the record where Mingo Logan asserted that the EPA should be subject to an explanatory standard for withdrawing a permit different from the standard for objecting to one initially. See id. at 738-39. In our view, this argument is distinct from Mingo Logan's claim that reliance costs must be considered. Because both arguments rely on language from Fox, it is tempting to conflate them. But there are important differences. In its reliance-costs argument, Mingo Logan claims that the EPA was required to balance the costs it incurred in reliance on the permit against the environmental concerns the EPA identified. As the dissent suggests, in that case the remedy would be to remand to the EPA to do the necessary balancing. See id. at 741. As discussed, the remedy informs in part our conclusion that Mingo Logan forfeited that argument because it failed to detail the costs in a way that the EPA could do what Mingo Logan now says it should do. See supra at 737-40.
Mingo Logan's inadequate-explanation argument, in contrast, relies on Fox for a different argument. It claims that the EPA is subject to a heightened standard to justify its withdrawal decision and that, under that standard, the EPA's explanation is insufficient. The remedy regarding this argument would be a remand to the EPA to better support revocation but the EPA could not balance reliance costs against environmental effects in doing so for the reasons already discussed. It would simply have to do a better job explaining why withdrawal was necessary in 2011 when it was not so in 2007. Like our colleague, we believe that Mingo Logan sufficiently pressed this argument before the EPA and in district court. Indeed, as the dissent points out, see Dissenting Op. at 738-39, Mingo Logan consistently argued that a different standard applied post-permit and that, accordingly, the EPA had to identify substantial new information to support its post-permit decision. Thus, this argument is properly before us and we address it (and reject it), see infra 726-30. But Mingo Logan's post-permit heightened-standard claim does not preserve its reliance-costs claim. They are different claims supported by different arguments. Accordingly, having been forfeited not once, but twice (and perhaps thrice), we do not consider Mingo Logan's
Mingo Logan's second argument is that the EPA's revocation decision was arbitrary and capricious because it "relied on [a] factor[] which Congress has not intended it to consider," see State Farm, 463 U.S. at 43, 103 S.Ct. 2856 — water quality downstream from the valley fill. As mentioned, the EPA offered multiple bases for its decision in its Final Determination. It first identified adverse effects to wildlife within the footprint of the valley fills — that is, the area where the spoil was in fact to be disposed of. It then identified adverse effects to wildlife downstream from the fills attributable to increased levels of selenium and conductivity
Mingo Logan argues that the EPA cannot rely on downstream water quality as a basis for finding adverse environmental effects. Because the "Congress has delegated responsibility for considering water quality to [West Virginia], not [the] EPA," Appellant's Br. 47, and West Virginia has granted Mingo Logan a section 402 permit that governs downstream water quality, Mingo Logan argues that the EPA has intruded upon West Virginia's exclusive regulatory power over its "navigable waters," see 33 U.S.C. § 1342(b). Mingo Logan also contends that the EPA impermissibly applied its own water-quality standards in considering downstream effects. The application of such "ad hoc" standards, according to Mingo Logan, is arbitrary and capricious. Appellant's Br. 56-57.
We reject this argument for several reasons. As an initial matter, section 404(c) allows the EPA to consider the effects of spoil disposal downstream from the fill itself and downstream water quality may enter the equation. The statute authorizes the Administrator "to deny or restrict the use of any defined area for specification" if he determines "that the discharge of such materials into such area will have an unacceptable adverse effect on municipal water supplies, shellfish beds and fishery areas..., wildlife, or recreational areas." 33
Mingo Logan essentially concedes the general point;
Mingo Logan's argument fundamentally misinterprets what the EPA does in evaluating changes in water quality attributable to the disposal of spoil in designated streams. It is true that section 402 grants a qualifying state broad authority to regulate its water quality, see 33 U.S.C. § 1342, and that regulation under sections 402 and 404 is generally distinct, see Coeur Alaska, Inc., 557 U.S. at 274, 276-77, 129 S.Ct. 2458. As the district court concluded, however, there is an important difference between "regulating" pollutant discharge under section 402 and identifying unacceptable adverse effects on four specific categories of resources as a result of spoil disposal under section 404(c). See Mingo Logan III, 70 F.Supp.3d at 177. Indeed, we do not take issue with Mingo Logan's contention that, here, the primary authority under section 402 lies with West Virginia. Under the NPDES program, West Virginia permits the discharge of water from sediment ponds into natural streams based upon state water-quality criteria and sets conditions on those discharges to manage the flow of pollutants into natural waters within its jurisdiction. See 33 U.S.C. § 1342. In contrast, the EPA does none of these things; it does not intrude on West Virginia's authority to regulate water quality under section 402 because the EPA is not regulating the discharge of pollutants into West Virginia waters downstream from the fill. It is instead assessing whether discharging spoil into a particular stream will produce "unacceptable adverse effect[s]" on wildlife. Id. § 1344(c). And it evaluates the effects of that spoil — both inside and outside the fill's footprint — in making its assessment, including the changes the spoil might bring about in downstream water quality.
This raises a third, related point. Although Mingo Logan makes much of the "EPA's consideration of water quality," see Appellant's Br. 53, the EPA did not base its revocation decision on an evaluation of downstream water quality per se; rather, evaluating downstream water quality was just one step in its process of evaluating "unacceptable adverse effect[s]" on wildlife under section 404(c), see 33 U.S.C. § 1344(c). The EPA must connect conclusions it makes about downstream water to adverse effects on the specific resources listed in section 404(c) — municipal water
Mingo Logan's final argument is that the EPA failed to adequately explain its revocation decision given that it allowed the 404 permit to proceed four years earlier. Mingo Logan argues that this change triggers the "more detailed" justification standard discussed in Fox, 556 U.S. at 515, 129 S.Ct. 1800, and because the "EPA cannot point to any new information — let alone substantial or more detailed information — that overcomes" its original decision not to veto the permit, Appellant's Br. 32, we must set its Final Determination aside. Mingo Logan argues further that even under the ordinary APA explanation standard articulated in State Farm, 463 U.S. at 43, 103 S.Ct. 2856, the EPA has failed to adequately explain its decision to revoke; the "unacceptable" effects the EPA identified, Mingo Logan claims, typically result from any large-scale surface coal mine.
The district court rejected Mingo Logan's assertion that a more detailed justification standard applies, concluding that, notwithstanding the EPA's original acquiescence, it did not amount to a "policy"; accordingly, the EPA's subsequent withdrawal decision was not a change of course triggering the more detailed Fox standard. Mingo Logan III, 70 F.Supp.3d at 163-68. We need not resolve the question of whether a "more detailed" explanatory
Final Determination, at 8. The EPA then went on to describe — in detail — its assessment of the "unacceptable adverse effect[s]" both within the fills' footprint and downstream from the valley fill.
Mingo Logan's challenge to the adequacy of the EPA's justification focuses exclusively on the EPA's discussion of adverse effects in the valley fills' footprint; it does not contest the sufficiency of the EPA's downstream-effects justification.
The EPA first noted that the sheer size of the Spruce No. 1 Mine project rebutted Mingo Logan's characterization of the project's effects on wildlife as routine. As the EPA explained, "[t]he Spruce No. 1 Mine... is one of the largest mountaintop mining projects ever authorized in West Virginia," affecting approximately 3.5 square miles and resulting in the burial of approximately 7.48 miles of high-quality streams. Final Determination, at 15. "By way of comparison," the EPA noted, "the project area would take up a sizeable portion of the downtown area of Pittsburgh, PA." Id. Relatedly, the EPA cited the large number of species within the proposed fill, noting that watersheds within the Central Appalachian region are some of the continent's most biologically diverse and that the Pigeonroost Branch and Oldhouse Branch watersheds are no exception. Id. at 30-31, 47. The EPA gave great weight to both of these factors, explaining that a large part of the "significance" of the adverse environmental effects it predicted results from such a large-scale ecosystem disruption in one of most biologically diverse areas in the country. See id. at 30-31, 50.
The EPA also detailed the adverse effects — and the implications for the broader ecosystem — on specific categories of wildlife. The EPA explained that Pigeonroost Branch and Oldhouse Branch are home to a particularly diverse group of macroinvertebrates and wide-scale elimination of these populations would have a significant negative impact on the broader "faunal food web" given that macroinvertebrates form its foundation. Id. at 47, 49-50. The EPA further explained how burying 6.6 miles
Moreover, these explanations were not, as Mingo Logan suggests, Appellant's Br. 44-45, based purely on information the EPA had at its disposal before the 404 permit issued. Rather, it relied on a variety of post-permit data to support its conclusions and, where relevant, explained how circumstances had changed over time.
First, the EPA's analysis cited several post-permit studies suggesting headwater streams like Pigeonroost Branch and Oldhouse Branch play an outsized role in the creation and preservation of a robust and diverse regional ecosystem. As the EPA explained, after the permit was issued, "the scientific literature reflected a growing consensus of the importance of headwater streams." Final Determination, at 20. "Many [post-permit] studies," the EPA went on, "now point to the role headwater streams play in the transport of water, sediments, organic matter, nutrients, and organisms to downstream environments; their use by organisms for spawning or refugia; and their contribution to regional biodiversity." Id.
This general shift in perspective on the importance of headwater streams — undergirded by post-permit scientific evidence — permeates the EPA's entire analysis of the environmental effects of the valley fill within the fills' footprint. The EPA concluded that many of the direct adverse effects on wildlife within the disposal area are "unacceptable" because Pigeonroost Branch and Oldhouse Branch are "some of the last remaining streams within the Headwaters Spruce Fork sub-watershed and the larger Coal River sub-basin that represent `least-disturbed' conditions and habitat that is essential for many species in the watershed." Id. at 49. Consequently, the EPA explained, the streams "perform critical hydrologic and biological functions, support diverse and productive biological communities, contribute to prevention of further degradation of downstream waters, and play an important role within" the larger regional ecosystem. Id. Given "the evidence that these streams are some of the last, rare and important high quality streams in the watershed," the EPA concluded that burying 6.6 miles of the streams with spoil would produce an "adverse impact ... that the aquatic ecosystem cannot afford." Id. at 50.
Second, the EPA discussed additional post-permit evidence suggesting that its original estimates about the return of salamanders to the area were flawed. Pre-permit density measurements suggested that the spoil would kill approximately 250,000 salamanders within the fill area. According to the EPA, "it had been assumed that species populating these waters would return, sometimes years later, to reestablish a community." Appellee's Br. 43-44. Post-permit data suggested, however, that even after twenty years, salamanders were not returning as expected to sedimentation ditches generated by now-closed West Virginia coal mines. See Final Determination, at 48.
Third, although pre-permit data suggested few fish would be affected by the project, post-permit data suggested additional species would experience adverse effects. As the EPA explained, sampling for the environmental study of the project suggested only a limited number of species lived in the Pigeonroost Branch and Oldhouse Branch streams. Id. at 38. The EPA concluded, however, that the pre-permit data were not reliable because the sampling had been conducted during a drought period. See id. It cited post-permit fish sampling data from 2008 and 2009 that "revealed a fish assemblage" in the two streams. Id. Specifically, "[m]ottled sculpin, as well as sporadic populations of
Thus, assuming arguendo that the EPA was subject to the "more detailed justification" standard described in Fox, 556 U.S. at 515, 129 S.Ct. 1800, we conclude that its Final Determination satisfied that requirement. It plainly relied upon new data — including data from the Spruce No. 1 Mine site itself — and explained the relevance of these data in concluding that the project would have unacceptable adverse effects on wildlife downstream from the fill sites. It also adequately explained how the valley fill would have an unacceptable adverse effect on wildlife within the fill and it specifically explained the new "consensus" on the importance of headwater streams, id. at 20, new scientific evidence about salamander repopulation, and new, more representative data about the fish species living in the fill area in doing so.
A few words in closing are in order. First, we do not hold that the EPA is generally exempt from considering costs in evaluating whether to withdraw a previously approved disposal site under section 404(c). We need not and do not decide precisely what the EPA may and must consider in making a post-permit withdrawal decision; we hold only that it is not expected to balance costs never presented to it. Second, we do not hold whether the EPA's site withdrawal after the Corps has issued a 404 permit must always satisfy the more detailed justification standard articulated in Fox, 556 U.S. at 515-16, 129 S.Ct. 1800. Again, we need not and do not decide that question because, even assuming the Fox standard applies, the EPA's explanation satisfies it. Finally, we note that post-permit withdrawal under section 404(c) is a mighty power and its exercise will perhaps inevitably leave a permittee feeling as if the rug has been pulled out from under it. Nonetheless, this power is one the Congress has authorized the EPA to exercise and where, as here, the EPA has adequately explained why mine spoil disposal at two sites would cause "unacceptable adverse effect[s]" on "wildlife," 33 U.S.C. § 1344(c), we must uphold its decision.
For the foregoing reasons, the judgment of the district court is affirmed.
So ordered.
KAVANAUGH, Circuit Judge, dissenting:
EPA must consider both costs and benefits before it vetoes or revokes a permit under Section 404 of the Clean Water Act. That much is common sense and settled law. See Michigan v. EPA, ___ U.S. ___, 135 S.Ct. 2699, 192 L.Ed.2d 674 (2015). Here, however, EPA revoked a Clean Water Act permit without considering the costs of doing so. For that reason, EPA's decision must be vacated. In my view, EPA must go back to the drawing board and weigh both the costs and benefits of revoking the permit before making its decision.
The case concerns Mingo Logan, a coal mining company that planned to engage in surface coal mining in West Virginia. Under the Clean Water Act, the Company first needed to obtain what is known as a Section 404 permit. The Section 404 permit would allow Mingo Logan to dump into nearby streams the excess rubble generated by its surface mining operation — known under the Act as "fill material." Mingo Logan's ability to dispose of fill material into those streams was critical to the viability
By statute, the Army Corps of Engineers oversees Section 404 permits. The Corps has the power to grant and revoke permits. To grant a Section 404 permit, the Corps must determine that the permit application meets guidelines developed jointly by the Corps and EPA. Among other things, the guidelines require the permit applicant to show that its planned disposal of fill material minimizes environmental impacts, to the extent practicable. The Corps may also revoke a previously issued Section 404 permit, but only after the Corps considers a variety of factors such as the permittee's investment-backed reliance on the permit.
In addition, Section 404(c) of the Clean Water Act grants EPA concurrent authority to (i) veto the issuance of a permit or (ii) revoke a previously issued permit.
In 2007, Mingo Logan obtained a Section 404 permit from the Corps. By its terms, the permit allowed the Company to dispose of fill material for 24 years at three disposal sites, subject to various conditions and mitigation measures. Understandably relying on that permit, Mingo Logan subsequently spent millions of dollars on the mining operation and hired coal miners and other employees.
In 2007, EPA could have exercised its Section 404(c) authority to veto the issuance of Mingo Logan's permit, but EPA chose not to do so. In 2011, EPA reversed course and exercised its Section 404(c) authority to revoke Mingo Logan's permit and shut down the mining operation.
EPA provided one reason for its 2011 revocation decision: Contrary to what it had concluded four years earlier, EPA now believed that Mingo Logan's coal mining operation would have an "unacceptable adverse effect" on certain animals, particularly certain species of salamanders, fish, and birds. (There was no stated risk to humans or to drinking water from Mingo Logan's disposal of fill material into the streams.) In EPA's view, revoking Mingo Logan's permit would mitigate the adverse effect on animals.
Mingo Logan complains that EPA considered only the benefits and did not consider any of the costs associated with revoking Mingo Logan's permit. Those costs encompassed, for example, the negative financial impacts on Mingo Logan's owners and shareholders, including those who relied on the permit; on the coal miners who would lose their jobs; on the collateral businesses that sold services and products for the mining operation or otherwise depended on the mining operation; on the consumers who pay less for electricity when additional sources of energy are available; and on West Virginia's tax revenues. According to Mingo Logan, EPA also failed to provide the "more detailed justification" required by Supreme Court precedent when an agency changes course and revokes a previously issued permit on which the permittee had relied. FCC v. Fox Television Stations, Inc., 556 U.S. 502,
The bottom line is that EPA considered the benefits to animals of revoking the permit, but EPA never considered the costs to humans — coal miners, Mingo Logan's shareholders, local businesses, and the like — of revoking the permit. In my view, EPA's utterly one-sided analysis did not come close to satisfying the agency's duty under the Administrative Procedure Act and relevant Supreme Court precedents to consider and justify the costs of revoking Mingo Logan's previously issued permit.
To be clear, I am not here deciding how EPA should weigh the costs and benefits of revoking the permit, or what outcome the agency should reach when it conducts that analysis. Cf. Michigan, 135 S.Ct. at 2711 (same); White Stallion Energy Center, LLC v. EPA, 748 F.3d 1222, 1266 (D.C. Cir. 2014) (Kavanaugh, J., dissenting) (same). I am merely making the narrow but critical point that EPA must in fact consider both costs and benefits before deciding whether to revoke the permit. See Michigan, 135 S.Ct. 2699. EPA did not do so here. Under the Administrative Procedure Act and applicable Supreme Court precedent, that is not acceptable. I respectfully dissent.
By omitting consideration of costs, EPA's decision revoking Mingo Logan's permit was doubly deficient under the Administrative Procedure Act. First, EPA failed its most basic duty under the Administrative Procedure Act to consider all of the relevant factors, including costs. Second, because EPA changed its position by revoking a previously issued permit, EPA not only had to consider costs, but also had to provide a more detailed justification for its change in position.
It is a fundamental principle of administrative law that federal "administrative agencies are required to engage in reasoned decisionmaking." Michigan v. EPA, ___ U.S. ___, 135 S.Ct. 2699, 2706, 192 L.Ed.2d 674 (2015) (internal quotation marks omitted). To engage in reasoned decisionmaking, an agency must consider all of the factors that are relevant to the particular decision facing the agency. Id. In other words, an agency must consider each "important aspect of the problem." Motor Vehicle Manufacturers Association of the United States v. State Farm Mutual Automobile Insurance Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983). An agency must also articulate a "rational connection" between the factors considered and the choice made. Id. In short, agency action must be "reasonable and reasonably explained." Communities for a Better Environment v. EPA, 748 F.3d 333, 335 (D.C. Cir. 2014).
As a general rule, the costs of an agency's action are a relevant factor that the agency must consider before deciding whether to act. See Michigan, 135 S.Ct. at 2707. In Michigan v. EPA, the Supreme Court was unanimous in articulating this principle. The Court divided 5-4 only on whether the agency had in fact considered costs. Id. at 2714 (Kagan, J., dissenting) ("I agree with the majority — let there be no doubt about this — that EPA's power plant regulation would be unreasonable if the Agency gave cost no thought at all.") (internal quotation marks and brackets omitted).
An agency must consider costs because reasoned decisionmaking requires assessing whether a proposed action would do more good than harm. As the Supreme Court has emphasized, the costs imposed
Leading jurists and scholars have long recognized that consideration of costs is an essential component of reasoned decisionmaking under the Administrative Procedure Act. Consider the following:
To be sure, Congress may bar an agency from considering the costs of certain actions. See Whitman v. American Trucking Associations, 531 U.S. 457, 464-71, 121 S.Ct. 903, 149 L.Ed.2d 1 (2001). But absent a congressional directive to disregard costs, common administrative practice and common sense require an agency to consider the costs and benefits of its proposed actions, and to reasonably decide and explain whether the benefits outweigh the costs.
In this case, instead of considering the costs and benefits of revoking Mingo Logan's permit, EPA focused like a laser on one benefit that would flow from the revocation — namely, the prevention of an adverse effect on a few animals, such as salamanders, fish, and birds in and near the disposal sites. (To reiterate, there was no stated risk to humans or to drinking water from Mingo Logan's disposal of fill material into the streams.)
But EPA ignored the costs to humans caused by the revocation of Mingo Logan's permit, such as the harm to Mingo Logan's owners and shareholders and to the coal miners who had been or would be employed at the mine. By ignoring costs, EPA in essence discounted the costs to humans all the way to zero. That's how EPA was able to conclude that the harm to some salamanders, fish, and birds from the mining operation outweighed the loss of jobs for hundreds of coal miners, the financial harm to Mingo Logan's owners and
EPA ignored the costs to humans because, in EPA's view, Congress prohibited the agency from considering costs under Section 404(c). Section 404(c), to repeat, authorizes EPA to prohibit the disposal of fill material into any disposal site if EPA determines that the disposal "will have an unacceptable adverse effect on municipal water supplies, shellfish beds and fishery areas (including spawning and breeding areas), wildlife, or recreational areas." 33 U.S.C. § 1344(c) (emphasis added).
According to EPA, the phrase "unacceptable adverse effect" bars EPA from considering costs, or may be reasonably construed to allow EPA to ignore costs. But EPA is badly mistaken. Far from prohibiting EPA from considering the costs of its actions, Section 404(c) reinforces the agency's bedrock duty under the Administrative Procedure Act to consider costs.
The word "unacceptable" is capacious and necessarily encompasses consideration of costs. Like the word "appropriate" at issue in Michigan v. EPA, the words "acceptable" and "unacceptable" are commonly understood to necessitate a balancing of costs and benefits. See Michigan, 135 S.Ct. at 2707-08; cf. Turner v. Murray, 476 U.S. 28, 36, 106 S.Ct. 1683, 90 L.Ed.2d 27 (1986) ("[W]e find the risk that racial prejudice may have infected petitioner's capital sentencing unacceptable in light of the ease with which that risk could have been minimized.").
To illustrate, suppose that the disposal of fill material from a surface mining project is certain to harm some salamanders. Does the disposal activity have an "unacceptable adverse effect" on salamanders? The answer would presumably be yes if the disposal activity could be prohibited at zero cost — say, if the fill material could just as easily be dumped at another site devoid of salamanders. On the other hand, the answer would presumably be no if the mining project would contribute millions of dollars to the local economy and lower the price of electricity. In some cases, the question of whether the adverse effect on salamanders is "unacceptable" may be a close call. But the point for present purposes is that the balance of the benefits of reducing the adverse effect on animals and the costs of shutting down the mining operation plainly influences the determination whether or not the adverse effect is "unacceptable."
Indeed, consider an analogous phrase recently analyzed by the Supreme Court: undue burden. See Whole Woman's Health v. Hellerstedt, ___ U.S. ___, 136 S.Ct. 2292, 195 L.Ed.2d 665 (2016). The Supreme Court explained that in assessing whether a law constitutes an "undue burden" on abortion access, courts must "consider the burdens a law imposes on abortion access together with the benefits those laws confer." Id. at 2298. If the word "undue" at issue in Whole Woman's Health requires a balancing of costs and benefits, the word "unacceptable" at issue here similarly requires a balancing of costs and benefits.
Moreover, even if the word "unacceptable" does not unambiguously require EPA to consider costs, it certainly allows EPA to consider costs. Cf. Michigan v. EPA, 213 F.3d 663, 674-79 (D.C. Cir. 2000) (per curiam) (statutory term "significant" allowed EPA to consider costs). And if the word "unacceptable" allows EPA to consider costs, it is necessarily unreasonable for EPA not to consider costs. See Michigan, 135 S.Ct. at 2706-08. That proposition follows from the general reasonableness principle embodied in State Farm and Chevron: To act reasonably, an agency must consider the costs of its actions unless
So whether EPA's interpretation of Section 404(c) is analyzed under Chevron step one or Chevron step two or State Farm, the conclusion is the same: In order to act reasonably, EPA must consider costs before exercising its Section 404(c) authority to veto or revoke a permit.
EPA responds that Section 404(c) is more akin to the statutory provision at issue in Whitman v. American Trucking than the provision at issue in the Supreme Court's Michigan v. EPA case. Whitman dealt with a provision of the Clean Air Act that directed EPA to set ambient air quality standards at levels "requisite to protect the public health" with "an adequate margin of safety." 42 U.S.C. § 7409(b)(1). The Court said that the statute precluded EPA from considering costs.
EPA advanced the same Whitman-based argument in Michigan v. EPA. It failed. Here too, EPA's reliance on Whitman is misplaced. In Whitman, the Court explained that the statute specifically focused on "public health" and "safety" — two factors on the other side of the balance from costs. See Whitman, 531 U.S. at 468-69, 121 S.Ct. 903. The Court found it "implausible" that Congress — through the modest words "requisite" and "adequate margin" — granted EPA the significant power "to determine whether implementation costs should moderate national air quality standards." Whitman, 531 U.S. at 468, 121 S.Ct. 903.
Here, by contrast, Section 404(c)'s text — in particular the word "unacceptable" — contemplates that costs must be considered. So does the statutory context and purpose: After all, it would be surprising — shocking, truth be told — if EPA did not have to consider costs under Section 404(c) when deciding whether to veto or revoke permits.
In short, bedrock principles of administrative law, as well as the terms of the statute setting forth EPA's substantive authority to revoke permits, required EPA to consider the costs of revoking Mingo Logan's permit. By failing to do so, EPA ignored "an important aspect of the problem." State Farm, 463 U.S. at 43, 103 S.Ct. 2856.
In this case, moreover, EPA's failure to consider costs was doubly problematic because EPA changed its position in 2011 by revoking a permit previously issued in 2007. It would be bad enough if EPA had merely blocked issuance of a Section 404 permit without considering costs. But it is far worse that here, EPA changed course and revoked a previously issued permit without considering costs, including the costs of reliance on the permit.
As a general rule, when an agency changes an existing policy or changes its position on an issue, the agency "need not demonstrate to a court's satisfaction that the reasons for the new policy are better than the reasons for the old one." FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515, 129 S.Ct. 1800, 173 L.Ed.2d 738 (2009). The agency must show only that there are "good reasons" for the new policy or position. Id.
But the Supreme Court has carefully articulated an exception to that general principle: An agency must provide a "more detailed justification" for a change in position if the agency's prior position "engendered serious reliance interests." Id.; see also Smiley v. Citibank (South Dakota), N.A., 517 U.S. 735, 742, 116 S.Ct. 1730, 135 L.Ed.2d 25 (1996). "In such cases it is not that further justification is demanded by the mere fact of policy change; but that a reasoned explanation is needed for disregarding
The Supreme Court's recent decision in Encino Motorcars, LLC v. Navarro, ___ U.S. ___, 136 S.Ct. 2117, 195 L.Ed.2d 382 (2016), illustrates the point. In that case, the Department of Labor changed its longstanding interpretation of the Fair Labor Standards Act. The retail car and truck dealership industry had long relied on the Department's prior interpretation. When justifying its change in position, the Department nonetheless failed to consider the industry's reliance. Id. at 2121-24, 2126. The Supreme Court found the Department's change in course problematic. The Court said that, in light of the industry reliance on the Department's prior position, "the Department needed a more reasoned explanation for its decision to depart" from its prior interpretation of the Fair Labor Standards Act. Id. at 2126-27.
The Supreme Court requires a "more reasoned" or "more detailed" justification in those circumstances because an agency change that undermines serious reliance interests disrupts settled expectations, thereby imposing a significant cost on regulated parties and contravening basic notions of due process and fundamental fairness. Here, as elsewhere, the law seeks to protect those kinds of settled expectations. Cf. Landgraf v. USI Film Products, 511 U.S. 244, 265, 114 S.Ct. 1483 (1994), 128 L.Ed.2d 229 ("settled expectations should not be lightly disrupted"); Hilton v. South Carolina Public Railways Commission, 502 U.S. 197, 202, 112 S.Ct. 560, 116 L.Ed.2d 560 (1991) ("Stare decisis has added force when the legislature, in the public sphere, and citizens, in the private realm, have acted in reliance on a previous decision, for in this instance overruling the decision would dislodge settled rights and expectations....").
Put another way, when an agency changes position in a way that frustrates reliance interests, the agency's action is more costly to regulated parties than when the agency develops a policy or announces a decision on a clean slate, all else being equal. This is a commonplace phenomenon in law and life. To take one example, declining to hire someone is usually less disruptive to the individual than firing someone. In the administrative context, the presence of that extra cost — the reliance cost — triggers a heightened burden of agency justification: The agency must consider the reliance cost and must justify its action despite that additional cost.
To be sure, as Justice Ginsburg pointed out in her concurring opinion in Encino Motorcars, the presence of reliance interests does not "pose an insurmountable obstacle" to an agency's desired change in course. Encino Motorcars, ___ U.S. at ___, 136 S.Ct. at 2128 n. 2 (Ginsburg, J., concurring). But reliance does pose an obstacle. And the agency must take that obstacle into account. As Justice Ginsburg put it, the agency must determine that "the benefits of [its desired action] outweigh those costs." Id. at 2121-22.
Reliance interests pose an especially formidable obstacle to an agency's desired change in course in the context of government-issued permitting. A government-issued permit typically embodies a limited-time bargain between a private party and the relevant government agency. If the private party complies with the permit's conditions, the government will allow the party to engage in certain conduct — whether driving a truck, building a new store, or disposing of fill material, for example — for a specified period of time. Therefore, the issuance of a permit is typically intended to, and typically does, engender
When a permit induces reliance, it has long been recognized that those settled expectations should not be lightly disturbed by intervening government action. See, e.g., Dainese v. Cooke, 91 U.S. 580, 583-84, 1 Otto 580, 23 L.Ed. 251 (1875) (The government "should make a clear case of departure from the permit, or danger to public interests, before appellant should be arrested midway in the construction of the buildings, and have them summarily torn down, with all the necessary loss and expense to him of such a course."). For example, under the state common law doctrines of "vested rights" and "equitable estoppel," state agencies are often precluded from nullifying investments made in reasonable reliance on a valid building or development permit. See 2 E. C. Yokley, Zoning Law and Practice § 14-5 (4th ed. 2009); see also, e.g., Avco Community Developers, Inc. v. South Coast Regional Commission, 17 Cal.3d 785, 132 Cal.Rptr. 386, 553 P.2d 546, 550 (1976) ("It has long been the rule in this state and in other jurisdictions that if a property owner has performed substantial work and incurred substantial liabilities in good faith reliance upon a permit issued by the government, he acquires a vested right to complete construction in accordance with the terms of the permit.").
Here, the Section 404 permit afforded Mingo Logan 24 years to engage in an activity that was essential to the economic viability of its coal mining operation. After obtaining its permit in 2007, Mingo Logan spent millions of dollars preparing the site for mining operations. Mingo Logan's large expenditures easily qualify as "serious reliance" upon the permit. Fox, 556 U.S. at 515, 129 S.Ct. 1800. And those investments have been rendered all but worthless by EPA's 2011 decision to revoke the permit.
Under Fox, because EPA's change affected "serious reliance interests," EPA needed to provide a "more detailed justification" for its revocation of Mingo Logan's permit. Id. And because EPA was revoking a Section 404 permit, EPA's more detailed justification needed to explain why the benefits of revoking Mingo Logan's permit outweighed all of the relevant costs, including the significant cost of frustrating Mingo Logan's investment-backed reliance on a government-issued permit. As already discussed, however, EPA did not even acknowledge the costs of revoking Mingo Logan's permit, much less provide the more detailed justification for revoking the permit that is required by Fox.
To sum up: An agency must consider both costs and benefits of a proposed agency action unless Congress has barred consideration of costs. When an agency changes course by revoking a permit, one cost is the frustration of reliance interests. When reliance interests are frustrated in that way, the agency must not only consider that cost but must also provide a "more detailed justification" for its action revoking the permit. FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515, 129 S.Ct. 1800, 173 L.Ed.2d 738 (2009). That more detailed justification must consider all of the relevant costs, including the frustration of reliance interests. In this case, EPA
How does the majority opinion deal with EPA's failure to consider costs? The majority opinion does not address the issue. Rather, the majority opinion concludes that Mingo Logan forfeited the argument that EPA had to consider and justify the costs of revoking the permit. I disagree.
To preserve an issue, a party challenging an agency action arising in an administrative adjudication such as this ordinarily must raise the issue before the agency and, if applicable, before the district court. See Shea v. Kerry, 796 F.3d 42, 56 (D.C. Cir. 2015); Advocates for Highway & Auto Safety v. Federal Motor Carrier Safety Administration, 429 F.3d 1136, 1148 (D.C. Cir. 2005). The majority opinion says that Mingo Logan failed to raise its argument about the costs of revocation before EPA and again before the district court. But in my view, Mingo Logan raised its costs argument in both proceedings.
First, during the EPA proceeding, Mingo Logan informed EPA that the agency should consider the costs of the proposed permit revocation, not just the benefits. In its written comments to EPA, Mingo Logan argued that Section 404(c) of the Clean Water Act requires EPA to consider all the costs of revoking a permit: "`Unacceptable,' like `significant,' is a relative term that must be weighed against the endangerment of the species, the size of the project, and any economic benefit from the project." Mingo Logan, Comments in Response and in Opposition to the Recommended Determination of the U.S. Environmental Protection Agency Region III 6 n.11 (Nov. 29, 2010) (emphasis added), at Joint Appendix 712.
Indeed, it is self-evident that Mingo Logan raised a costs argument because EPA itself responded to Mingo Logan's costs argument, stating: "[Mingo Logan's] contention that the word `unacceptable' `must be weighed against the endangerment of the species, the size of the project, and any economic benefit from the project' is without merit." EPA, Final Determination of the U.S. Environmental Protection Agency Pursuant to § 404(c) of the Clean Water Act Concerning the Spruce No. 1 Mine, Logan County, West Virginia app. 6 (Jan. 13, 2011) (hereinafter EPA Final Determination), at Joint Appendix 955.
Moreover, Mingo Logan specifically informed EPA of the costs it had incurred — namely, the significant investments that the Company had made in reliance on the permit: "After receiving its Section 404 permit, Mingo Logan spent millions of dollars preparing the Spruce No. 1 site and commencing its operations." Mingo Logan, Comments in Response and in Opposition to the Proposed Determination 33 (June 3, 2010), at Joint Appendix 403. Mingo Logan added: "Now, more than three years after the issuance of the permit, as Mingo Logan is actively mining the site in an attempt to recoup its decade-long investment, EPA has declared that the impacts that it had approved are now unacceptable, and seeks to revoke the permit." Mingo Logan, Comments in Response and in Opposition to the Recommended Determination of the U.S. Environmental Protection Agency Region III 2 (Nov. 29, 2010), at Joint Appendix 708.
Mingo Logan explained, in addition, that EPA must provide a more detailed justification for revoking a Section 404 permit: Mingo Logan stressed that while "the 404(c) standard pre-permit is high; the standard post-permit is even higher." Mingo Logan, Comments in Response and in Opposition to the Recommended Determination of the U.S. Environmental Protection Agency Region III 8 (Nov. 29, 2010), at Joint Appendix 714.
Second, before the District Court, Mingo Logan continued to press the same claim that it had made before EPA. Mingo Logan again discussed the "millions of dollars" the Company had spent preparing the mining site for operations. Amended Complaint at 19, Mingo Logan Coal Co. v. EPA, No. 10-541 (D.D.C. Feb. 28, 2011), at Joint Appendix 68. And Mingo Logan maintained that "long-settled legal principles" required EPA "to explain a change in course" in order to account for the "investment-chilling prospect of post-permit action." Supplemental Brief in Support of Mingo Logan's Motion for Summary Judgment and in Opposition to EPA's Motion for Summary Judgment at 9, Mingo Logan Coal Co. v. EPA, No. 10-541 (D.D.C. May 28, 2014). Mingo Logan continued to press that point in a hearing before the District Court: "[I]t is a fundamental precept of administrative law that an agency can't just change its mind without any reason. We've cited several cases in our brief. There's the [State Farm] case, the [Jicarilla] case, that if an agency changes its position it has to articulate a reason for the change. That's a fundamental precept of administrative law for any change." Tr. of Motion Hearing at 9, Mingo Logan Coal Co. v. EPA, No. 10-541 (D.D.C. July 30, 2014). Mingo Logan therefore raised its costs argument before the District Court.
Put simply, Mingo Logan made both a State Farm argument and a Fox argument. The State Farm argument was that EPA had to consider all of the relevant factors, one of which was costs. The Fox argument was that the agency had to provide a more detailed justification because it was changing course and revoking a previously issued permit. As a matter of common sense and settled law, those arguments required EPA to consider not just the benefits of revoking the permit, but also the costs. How else could EPA perform its duty under State Farm and Fox without considering the downside costs as well as the upside benefits of revoking the permit? See Michigan v. EPA, ___ U.S. ___, 135 S.Ct. 2699, 2707, 192 L.Ed.2d 674 (2015) ("Consideration of cost reflects the understanding that reasonable regulation ordinarily requires paying attention to the advantages and the disadvantages of agency decisions.").
The majority opinion concludes that Mingo Logan forfeited its costs argument for two distinct reasons.
First, the majority opinion says that Mingo Logan failed to make a costs argument at all. But the majority opinion acknowledges, as it must, that Mingo Logan preserved the argument that "EPA is subject to a heightened standard to justify its withdrawal decision." Maj. Op. at 723. The majority opinion nonetheless says that "Mingo Logan's post-permit heightened-standard claim does not preserve its reliance-costs claim." Id. at 723.
That makes little sense to me. Those are one and the same argument. After all, EPA must provide a more detailed justification post-permit, as the Supreme Court has carefully explained many times, precisely because a revocation (that is, a change in position) frustrates reliance interests. See Fox, 556 U.S. at 515, 129 S.Ct. 1800. So when Mingo Logan argued that EPA had to provide a more detailed justification for its revocation decision — an argument that the majority concedes Mingo Logan has preserved — Mingo Logan necessarily made the lesser-included argument that EPA had to consider costs. Again, the agency could not perform its
To illustrate the point, assume that when EPA decided not to veto the permit, EPA believed that the loss of one coal miner's future job was a tolerable cost so long as two salamanders were saved. Once the permit was issued, the coal miner was hired and investments were made in the mining operation. So when EPA decided to revoke the permit, EPA had to explain how its calculus changed given that its revocation decision would cause the loss of existing jobs — not just hypothetical future ones — and existing investments. That's what providing a "more detailed justification" entails in this context. Fox, 556 U.S. at 515, 129 S.Ct. 1800. EPA could not rationally provide a more detailed justification in this case without considering costs. Therefore, Mingo Logan necessarily made a costs argument when it asked EPA to provide a more detailed justification for its revocation decision.
Second and alternatively, the majority opinion suggests that even if Mingo Logan did raise an argument about costs, Mingo Logan "failed to detail" its reliance costs. Maj. Op. at 723. In the end, this seems to be the crux of the majority opinion's objection. To begin with, even on its own terms, that objection fails. Mingo Logan told the agency that it had spent "millions of dollars" in reliance on the permit. That is at least $2 million. Moreover, EPA knew that the costs of revocation to Mingo Logan were significant. After all, in its decision revoking the permit, EPA itself "recognize[d] that Mingo Logan has made significant investments in planning for operations at the Spruce No. 1 Mine." EPA Final Determination at app. 6, at Joint Appendix 1236. At that time, EPA further noted that the "Spruce No. 1 Mine ... is one of the largest mountaintop mining projects ever authorized in West Virginia." Id. at 15, at Joint Appendix 806. EPA should have weighed the costs of revocation in the balance. It did not do so.
There is also a far more fundamental problem with the majority opinion's argument that Mingo Logan failed to detail its costs. EPA's legal theory throughout these proceedings has been that costs are irrelevant to permit revocation decisions. Yet now EPA is faulting Mingo Logan for not adequately detailing its costs to the agency. That's a bit rich. It is not as if EPA said it would consider costs and then Mingo Logan failed to present evidence. Rather, as reflected in its decision revoking the permit, EPA made clear that costs were irrelevant and said it would make its decision based solely on the adverse effect on animals. See id. at app. 6, at Joint Appendix 955. It flatly violates SEC v. Chenery for EPA now to rely on Mingo Logan's supposed failure to detail its costs when EPA (over Mingo Logan's objection) said at the agency stage and in the District Court that costs were irrelevant. See SEC v. Chenery Corp., 318 U.S. 80, 63 S.Ct. 454, 87 L.Ed. 626 (1943); SEC v. Chenery Corp., 332 U.S. 194, 67 S.Ct. 1760, 91 L.Ed. 1995 (1947). The forfeiture argument advanced by EPA (and accepted by the majority opinion) about Mingo Logan's supposed failure to detail costs is entirely unfair to Mingo Logan. I would not countenance this kind of agency bait and switch.
To be clear, the question whether Mingo Logan failed to adequately detail its costs is distinct from the question whether, in the first place, Mingo Logan sufficiently raised an argument that EPA needed to consider costs. Mingo Logan clearly raised a costs argument as part of its State Farm/Fox argument. If EPA thought that Mingo Logan failed to adequately support its costs estimate as an evidentiary matter, perhaps that could have been a basis for
In short, Mingo Logan argued to both EPA and the District Court that EPA had to consider all of the relevant factors (State Farm) and provide a more detailed justification because it was changing position and revoking a permit on which Mingo Logan had relied (Fox). Mingo Logan preserved the argument that EPA had to consider costs, including reliance costs.
The Corps issued a 24-year permit to Mingo Logan, but EPA then revoked the permit four years later. In revoking the permit, EPA considered the benefits to animals, but none of the costs to humans. Because that cost-blind approach does not satisfy EPA's duty of reasoned decisionmaking, and because Mingo Logan adequately raised that issue, I would direct the District Court to vacate EPA's revocation decision and to remand to EPA for the agency to consider the benefits and costs of its proposed revocation, and to supply a "more detailed justification" for revoking the permit. Fox, 556 U.S. at 515, 129 S.Ct. 1800. I respectfully dissent.