C. JOHNSON, J.
¶ 1 This case involves a claim for damages relating to a drilling contract between Petitioner Elcon Construction and Respondent Eastern Washington University. In the suit, tort and contract claims were alleged by Elcon. The contract claims were resolved by arbitration. In dismissing the tort claims, the trial court applied the independent duty rule formerly known as the economic loss rule, which the Court of Appeals similarly applied in affirming.
¶ 2 Eastern relies on two on-campus wells for its water supply (wells 1 and 2), both of which draw from what is called the Wanapum Aquifer. Beginning in 1987, Eastern requested approval from the Department of Ecology (DOE) to consolidate its water rights. In 2003, the DOE approved Eastern's request, thereby allowing Eastern to "refurbish" its two existing on-campus wells to increase their individual yields.
Clerk's Papers (CP) at 1113-14. Prior to bidding, Elcon contacted Eastern and requested all the information it had about the project, about other wells in the area, or about the geology relating to wells in the area of the drill site. Three years earlier, in 2000, Eastern had hired Varela & Associates to conduct a water capacity study, seeking to identify future options for expanding its water supply. Varela, in turn, hired Golder Associates to perform a hydrogeological investigation. The "Golder Report," based primarily on published reports and selected drillers' logs obtained from the DOE, contained information about the regional hydrology and recommended future wells be drilled into the Grande Ronde Aquifer below the Wanapum Aquifer at a depth of between 700 to 1,500 feet. CP at 338, 340. Per Elcon's request, Eastern provided Elcon a well log for well 2 and a video of well 1 but did not provide the Golder Report. CP at 864. Elcon submitted the low bid ($1,516,635) and was awarded the contract. CP at 1106-07.
¶ 3 The contract required Elcon to drill two replacement wells to an "estimated" depth of 750 feet.
¶ 4 In July 2003, work started on replacement well 1. Drilling stopped soon after it started, however, when an unforeseen layer of sand disrupted the work. Then, upon learning that it may have to drill significantly deeper than 750 feet, Elcon insisted upon payment for increased costs. Eastern terminated the contract for convenience instead and solicited a final pay request, which Elcon submitted to Eastern on June 4, 2004.
¶ 5 Upon learning of previously unknown damage to replacement well 1, Eastern issued a termination for cause letter on October 22, 2004, a copy of which was sent to Elcon's bond surety. Elcon filed this lawsuit claiming breach of contract, in addition to various tort claims.
¶ 7 We review summary judgment orders de novo and perform the same inquiry as the trial court, viewing all facts and reasonable inferences in the light most favorable to the nonmoving party. Hisle v. Todd Pac. Shipyards Corp., 151 Wn.2d 853, 860, 93 P.3d 108 (2004) (citing Kruse v. Hemp, 121 Wn.2d 715, 722, 853 P.2d 1373 (1993)). The grant of summary judgment is appropriate where there is "no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law." CR 56(c). "A material fact is one that affects the outcome of the litigation." Owen v. Burlington N. Santa Fe R.R., 153 Wn.2d 780, 789, 108 P.3d 1220 (2005) (citing Hisle, 151 Wash.2d at 861, 93 P.3d 108). Where no dispute as to the material facts exists, summary judgment is proper.
¶ 8 The trial court and the Court of Appeals applied the independent duty doctrine, formerly referred to as the economic loss rule, to dismiss Elcon's tort claims. This was a misapplication of the doctrine, though an inconsequential one. Because Elcon's tort claims factually fail, we affirm the Court of Appeals regardless.
¶ 9 The independent duty doctrine is "an analytical tool used by the court to maintain the boundary between torts and contract." Eastwood v. Horse Harbor Found., Inc., 170 Wn.2d 380, 416, 241 P.3d 1256 (2010) (Chambers, J., concurring). In Eastwood, we adopted the term "independent duty doctrine" because it more accurately captured the principle behind the rule: "An injury," we held, "is remediable in tort if it traces back to the breach of a tort duty arising independently of the terms of the contract." Eastwood, 170 Wash.2d at 389, 241 P.3d 1256. To date, we have applied the doctrine to a narrow class of cases, primarily limiting its application to claims arising out of construction on real property and real property sales. "We have done so in each case based upon policy considerations unique to those industries. We have never applied the doctrine as a rule of general application outside of these limited circumstances." Eastwood, 170 Wash.2d at 416, 241 P.3d 1256 (Chambers, J., concurring). Indeed, in Eastwood
¶ 10 We have not applied the independent duty doctrine to bar a claim for fraud, and we see no basis to utilize it in this case. Even in the real property context, where we have been the least hesitant to apply the doctrine, we have repeatedly recognized a fraud claim to be outside the doctrine's scope, allowing such claims to be decided based on established tort precedent. See Alejandre, 159 Wash.2d at 689-90, 153 P.3d 864; Atherton Condo. Apartment-Owners Ass'n Bd. of Dir. v. Blume Dev. Co., 115 Wn.2d 506, 523-27, 799 P.2d 250 (1990). We find no compelling reason, whether based on common sense, justice, policy, or precedent, to bar Elcon's fraud or tortious interference claim under the independent duty doctrine. The doctrine simply does not apply under these circumstances.
¶ 11 The trial court and the Court of Appeals also determined that Elcon's fraud in the inducement claim was factually insufficient. We agree. There are nine essential elements of fraud, all of which must be established by clear, cogent, and convincing evidence: (1) a representation of existing fact, (2) its materiality, (3) its falsity, (4) the speaker's knowledge of its falsity, (5) the speaker's intent that it be acted upon by the person to whom it is made, (6) ignorance of its falsity on the part of the person to whom the representation is addressed, (7) the latter's reliance on the truth of the representation, (8) the right to rely upon it, and (9) consequent damage. Williams v. Joslin, 65 Wn.2d 696, 697, 399 P.2d 308 (1965) (citing Michielli v. U.S. Mortg. Co., 58 Wn.2d 221, 361 P.2d 758 (1961)). Elcon claims that Eastern misrepresented the necessary depth of the replacement wells and its knowledge of subsurface conditions by failing to produce the Golder Report. This misrepresentation, it claims, induced it to bid the job and contract with Eastern, thereby causing it injury. This argument ignores the contract's bidding instructions and the character of the Golder Report.
¶ 12 The trial court and the Court of Appeals determined the Golder Report was not relevant to the refurbishment project. We agree. Importantly, the report was not prepared for the project, having been commissioned three years before the DOE authorized Eastern's consolidation. Moreover, it recommended drilling future wells in an area geographically separate from wells 1 and 2. CP at 338-40. When asked whether there was a hydrology report for this project, Eastern replied there was not. CP at 673. Based on the character of the Golder Report, this was not a false statement.
¶ 13 The trial court also found that the bidding instructions required Elcon to take steps reasonably necessary to ascertain the nature and location of the drilling, including the conformation and conditions of the ground, and the character of equipment needed for the performance of the work. CP at 1380. Yet, despite this requirement, Elcon did little more than request all of Eastern's available information. CP at 1211-12. The instructions further notified bidders that "[n]o statement made by any officer, agent, or employee of the Owner or [Architect/Engineer] in relation to the physical conditions pertaining to the site of the work will be binding on the Owner or [Architect/Engineer]. CP at 1114. Thus, even with the Golder Report in hand, Elcon still would have been required to conduct its own reasonable investigation. The trial court determined that Elcon failed to do so. CP at 1380. We agree.
¶ 14 The Golder Report was not relevant to Elcon's contractual duty to investigate under the bidding instructions. Evidence of Elcon's justifiable and reasonable reliance on the information provided by Eastern is therefore lacking. And since the report did not contain information or data of specific relevance to the drill site, not providing the report had no impact on the bidding
¶ 15 Despite the trial court and the Court of Appeals' reliance on the independent duty doctrine, we conclude the doctrine is irrelevant to the above analysis. In so concluding, we note this is a tort case unrelated to real property. Under these circumstances, the independent duty doctrine does not apply.
¶ 16 Elcon argues Eastern intentionally interfered with its contractual relationship by sending a copy of the termination for cause letter to Elcon's surety. According to Elcon, the letter impaired its bonding capacity causing it injury. The trial court determined Elcon's intentional interference claim was factually insufficient. We agree. A claim of intentional interference requires (1) the existence of a valid contractual relationship of which the defendant has knowledge, (2) intentional interference with an improper motive or by improper means that causes breach or termination of the contractual relationship, and (3) resultant damage. Cornish Coll. of the Arts v. 1000 Virginia Ltd. P'ship, 158 Wn.App. 203, 225, 242 P.3d 1 (2010) (citing Leingang v. Pierce County Med. Bureau, Inc., 131 Wn.2d 133, 157, 930 P.2d 288 (1997)), review denied, 171 Wn.2d 1014, 249 P.3d 1029 (2011) Exercising one's legal interest in good faith is not improper interference.
¶ 17 Eastern acted on information disclosed prior to the dispute and converted the termination for convenience to a termination for cause. In May 2004, Eastern received a high-resolution video of the work performed by Elcon on replacement well 1. According to Eastern, review of the video revealed previously unknown damage that, after consultation with Eastern's engineering consultant, was determined to be caused by Elcon's nonconforming work. CP at 1099. Once such a determination was made, Eastern converted the termination to one "for cause." CP at 852-53. Believing Elcon may owe decommissioning costs, Eastern had an interest in notifying Elcon's bond surety of Eastern's potential claim. That the arbitrator ultimately ruled Eastern could not convert to a termination for cause does not somehow make Eastern's interest illegitimate.
¶ 18 More importantly, by itself, the letter does not show improper purpose. And Elcon, by merely labeling the letter as "intentional and vindictive," has not met its burden of showing such a purpose. CP at 815-16. If Eastern was motivated by greed, retaliation, or hostility in sending a copy of the termination letter to Elcon's surety, Elcon has failed to show such a motive. Conclusory statements and speculation will not preclude a grant of summary judgment. Greenhalgh v. Dep't of Corr., 160 Wn.App. 706, 714, 248 P.3d 150 (2011) (citing Grimwood v. Univ. of Puget Sound, Inc., 110 Wn.2d 355, 360, 753 P.2d 517 (1988)). Elcon claimed to have suffered damage as a result of its surety having knowledge of Eastern's attempted conversion,
¶ 19 Elcon argues entitlement to statutory interest on the arbitrator's award under RCW 39.76.011, which requires public bodies to pay interest whenever they fail to make "timely payment" on amounts due on written contracts for public works. Payment is considered untimely if it is not made within 30 days of receipt of a "properly completed invoice or receipt of goods or services." RCW 39.76.011(2)(a). Rather than requesting statutory interest at arbitration, Elcon requested the interest in a postaward motion. CP at 404-05. The arbitrator denied the motion, determining he lacked postfinal award jurisdiction to address the issue pursuant to the arbitration statutes. CP at 387. The trial court determined it did not have jurisdiction to award interest on the arbitrator's award. CP at 1019. We agree.
¶ 20 In Westmark Properties, the Court of Appeals held that adding prejudgment interest to an arbitration award was error on the part of the trial court: "[The trial court] has no basis for determining whether the amount awarded met the test for [prejudgment] interest; this was part of the merits of the controversy, forbidden territory for a court." Westmark Props., Inc. v. McGuire, 53 Wn.App. 400, 404, 766 P.2d 1146 (1989) (quoting Sch. Dist. 5 Snohomish County v. Sage, 13 Wn. 352, 43 P. 341 (1896)). Similarly, in Fluor Daniel, Inc., we noted that the majority of courts considering this issue have found that adding prejudgment interest is an inappropriate modification of the arbitrator's award. In this case, the trial court appropriately limited its review. Dep't of Corr. v. Fluor Daniel, Inc., 160 Wn.2d 786, 792, 161 P.3d 372 (2007). Elcon may not recover statutory interest on the arbitrator's award through a postaward motion.
¶ 21 Both Elcon and Eastern request attorney fees under RAP 18.1. However, neither cites "applicable law" warranting such an award. We therefore deny both parties' RAP 18.1 request. Elcon also requests fees under RCW 39.76.040, which provides: "In any action brought to collect interest due under this chapter, the prevailing party is entitled to an award of reasonable attorney fees." Because Elcon does not prevail on its statutory interest claim, we deny its request.
¶ 22 The trial court and Court of Appeals misapplied the independent duty doctrine to bar Elcon's tort claims in this case. Regardless, Elcon's claims factually fail. Viewing all facts and reasonable inferences in the light most favorable to Elcon, no genuine issues of material fact exist with respect to Elcon's fraud in the inducement or tortious interference
WE CONCUR: TOM CHAMBERS, SUSAN OWENS, MARY E. FAIRHURST, JAMES M. JOHNSON, and DEBRA L. STEPHENS, Justices, and GERRY L. ALEXANDER, Justice Pro Tem.
MADSEN, C.J. (concurring).
¶ 23 We took review of this case to address the issue whether the plaintiff is restricted to contract remedies or may also assert tort claims. I agree with the majority that we need not reach this issue because each of the tort claims asserted by Elcon Construction, Inc., fails for want of sufficient evidence of an essential element of the claim. This being the case, the majority should refrain from any discussion of the so-called "independent duty rule" because it has no bearing on the disposition of this case. We should, in this case, follow the same principle we have often applied, that is, we should decline to address issues where it is unnecessary to do so. See e.g., Wash. Farm Bureau Fed'n v. Gregoire, 162 Wn.2d 284, 297 n. 20, 174 P.3d 1142 (2007); Alejandre v. Bull, 159 Wn.2d 674, 690 n. 6, 153 P.3d 864 (2007); In re Marriage of Langham & Kolde, 153 Wn.2d 553, 569, 106 P.3d 212 (2005).
¶ 24 The wisdom of doing so is demonstrated by the majority's mistaken statement that the "independent duty rule" was formerly known as the "economic loss rule," as if the two are and have been the same. Majority at 967. This is not the case, and it will only add to the confusion engendered by this new rule. The economic loss rule is unlike the "independent duty rule" that has been described in recent opinions. E.g., Affiliated FM Ins. Co. v. LTK Consulting Servs., Inc., 170 Wn.2d 442, 243 P.3d 521 (2010) (plurality); Eastwood v. Horse Harbor Found., Inc., 170 Wn.2d 380, 241 P.3d 1256 (2010) (plurality). The economic loss rule defaults to contract remedies where both are available. The "independent duty rule" defaults to tort remedies.
¶ 25 The economic loss rule rests on the principle that contracting parties should be limited to their contract remedies when loss potentially implicates both tort and contract relief. It is a "device used to classify damages for which a remedy in tort or contract is deemed permissible, but are more properly remediable only in contract.... `[E]conomic loss describes those damages falling on the contract side of "the line between tort and contract".'" Berschauer/Phillips Constr. Co. v. Seattle Sch. Dist. No. 1, 124 Wn.2d 816, 822, 881 P.2d 986 (1994) (quoting Wash. Water Power Co. v. Graybar Elec. Co., 112 Wn.2d 847, 861 n. 10, 774 P.2d 1199, 779 P.2d 697 (1989) (quoting Pa. Glass Sand Corp. v. Caterpillar Tractor Co., 652 F.2d 1165, 1173 (3d Cir.1981))).
¶ 26 Thus, the economic loss rule presumes that both contract and tort remedies may be available, and then the rule is used to help determine whether the loss is the type that is remedial under the terms of the parties' written agreement.
¶ 27 However, according to the majority's dicta in this case (it has nothing to do with the disposition of the case), the policy considerations used to determine whether an independent tort duty exists are considerations of common sense, justice, policy, and precedent. Majority at 969; see Affiliated FM, 170 Wash.2d at 449-50, 243 P.3d 521 (plurality) (also including "logic"); Eastwood, 170 Wash.2d at 389, 241 P.3d 1256 (plurality) (also including "logic").
¶ 28 The analysis to determine whether the independent duty exists is no different from the analysis used in any case to decide whether a tort duty exists. There is nothing that analytically differentiates the situation from any other case where a contracting party argues that a tort claim may be brought. Therefore, although the "independent duty rule" is described as a tool used to preserve the boundary between torts and contract, majority at 969, it does no such thing. Nothing about the rule preserves the value of agreement to the remedies that will exist if the contract is breached.
¶ 29 Rather, this rule appears to mean that if a tort duty is cognizable in the circumstances, the tort claim will be allowed. See id. The "independent duty" theory is not an effective tool to determine whether a party will be restricted to agreed-upon contract remedies in the event both contract and tort remedies are available because under the "independent duty rule" once a tort duty is recognized, the party can assert the tort claim. Indeed, the "independent duty rule" does not ask what limitations on remedy are imposed or contemplated by the contract.
¶ 30 All that is required for a contracting party to completely bypass the contract remedies for which the parties expressly bargained is that the court acknowledge that a tort claim in fact exists. Since the whole point of the exercise, ostensibly, is to provide a framework for deciding when a party may assert a tort claim despite existence of contract remedies, the analysis simply ends with the recognition that the tort remedies potentially exist.
¶ 31 Unlike the economic loss rule, which is designed to determine when a party should be held to agreed-upon remedies, the "independent duty rule" is not defined in a way that provides an effective tool for this determination. I continue to believe that the new "independent duty rule" is not reasonably grounded or defined. See Affiliated FM, 170 Wash.2d at 463-75, 243 P.3d 521 (Madsen, C.J., concurring/dissenting). Rather than attempting to explain this new rule in this case, where it unquestionably does not apply, I would wait for a case that actually presents the issue. Perhaps when this court applies the "independent duty rule" it will make sense. In the abstract it does not.
¶ 32 I am concerned, too, that the majority refers to the decisions of the trial court and the Court of Appeals as if they had employed the "independent duty rule." Both of the courts' rulings predate the unanticipated appearance of the "independent duty rule," and these courts actually decided this case under the economic loss rule. This blurring of historical fact is apt to add to the confusion about the new rule.
¶ 33 In conclusion, although I agree with the majority that the tort claims would fail in this case in any event, I believe it is a mistake to discuss the "independent duty rule." I concur in the result.
WE CONCUR: CHARLES K. WIGGINS, Justice.
CP at 211-12.
CP at 1253. Judge Rielly ruled the e-mail was inadmissible hearsay and dismissed the claim on summary judgment. CP at 1018. On appeal, Elcon argued the e-mail was an admissible business record. The Court of Appeals did not address the issue, holding all Elcon's tort claims barred by the economic loss rule. Because Elcon's tortious interference claim fails on the improper purpose element, we do not address the admissibility of the above e-mail.