Elawyers Elawyers
Ohio| Change

IN RE: JEA BRANDY BRANCH COMBINED CYCLE CONVERSION POWER PLANT SITING APPLICATION NO. PA00-43 vs *, 00-005120EPP (2000)

Court: Division of Administrative Hearings, Florida Number: 00-005120EPP Visitors: 2
Petitioner: IN RE: JEA BRANDY BRANCH COMBINED CYCLE CONVERSION POWER PLANT SITING APPLICATION NO. PA00-43
Respondent: *
Judges: J. LAWRENCE JOHNSTON
Agency: Department of Environmental Protection
Locations: Baldwin, Florida
Filed: Dec. 15, 2000
Status: Closed
Recommended Order on Tuesday, January 15, 2002.

Latest Update: Mar. 29, 2002
Summary: JEA Brandy Branch Combined Cycle Conversion Project was consistent with existing local land use plans and zoning ordinances, subject to amendment to PUD.
00-5120 Remand RO

STATE OF FLORIDA

DIVISION OF ADMINISTRATIVE HEARINGS


IN RE: JEA BRANDY BRANCH ) COMBINED CYCLE )

CONVERSION POWER PLANT ) Case No. 00-5120EPP SITING APPLICATION )

NO. PA00-43. )

________________________________)


RECOMMENDED ORDER ON LAND USE FOLLOWING REMAND


Pursuant to notice, the Division of Administrative Hearings, by its duly-designated Administrative Law Judge,

J. Lawrence Johnston, held a formal hearing in Baldwin, Florida, on land use issues in the above-styled case on April 24, 2001, and on December 4, 2001, following the Order of Remand by the Siting Board.

APPEARANCES


For Applicant JEA:


Douglas S. Roberts, Esquire Hopping, Green & Sams

Post Office Box 6526 Tallahassee, Florida 32314


For Department of Environmental Protection:


Scott A. Goorland, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

Tallahassee, Florida 32399 For City of Jacksonville:

Gregory K. Radlinski, Esquire City Hall at St. James

117 West Duval Street, Suite 480 Jacksonville, Florida 32202

STATEMENT OF THE ISSUE


The issue to be resolved in this portion of this power plant siting proceeding is whether the site for the proposed JEA Brandy Branch Combined Cycle Conversion Project is consistent and in compliance with the applicable land use plans and zoning ordinances of the City of Jacksonville, pursuant to Section 403.508(2), Florida Statutes.

PRELIMINARY STATEMENT


This proceeding was conducted pursuant to the Florida Electrical Power Plant Siting Act (PPSA), Chapter 403, Part II, Florida Statutes, and Chapter 62-17, Florida Administrative Code, to consider JEA's application for power plant site certification of the Brandy Branch Combined Cycle Conversion Project. On December 8, 2000, JEA filed with the Florida Department of Environmental Protection (FDEP) an application for site certification for the Brandy Branch Combined Cycle Conversion Project. By agreement among the parties, this land use hearing, held pursuant to Section 403.508(2), Florida Statutes, was scheduled to be held on April 24, 2001.

After proper notice by the Applicant and by FDEP, the land use hearing was held in Baldwin, Florida, on April 24, 2001, as required by the PPSA. The hearing was conducted for the purpose of receiving evidence as to whether the Project

site was in compliance with the local land use plans and zoning regulations of the City of Jacksonville.

JEA presented the testimony of two witnesses and had JEA Exhibits numbered 1 through 8 admitted into evidence. FDEP did not present any testimony. The City of Jacksonville presented the testimony of Mr. Coen Purvis and offered no exhibits. No other agency or party appeared at the hearing. No member of the general public testified at the public hearing.

Following the conclusion of the land use hearing, a transcript was filed. Citations to the transcript of the land use hearing will be indicated by the name of the witness, followed by "T." and the page number; citations to exhibits admitted at this hearing will be indicated by "Ex." and the exhibit number.

The Joint Proposed Recommended Order of JEA, FDEP, and the City of Jacksonville was timely submitted. A Recommended Order on Land Use was entered on July 5, 2001.

On September 18, 2001, the Siting Board entered an Order of Remand for Further Proceedings, directing that further evidence be taken on the issue of the Project's consistency and compliance of the PUD zoning approval for the Project site with the air permit for the Project.

On December 4, 2001, as part of the scheduled certification hearing, additional evidence was received on the issue of the Project's compliance with the PUD zoning for the Brandy Branch site.

Following the conclusion of the certification hearing, a transcript of the certification hearing was filed. Citations to the transcript of the certification hearing in this Recommended Order on Land Use Following Remand will be indicated by the name of the witness, the symbol "T(2)." and the page number; citations to exhibits admitted at the certification hearing will be indicated by "Ex(2)." and the exhibit number.

A Joint Proposed Recommended Order on Land Use Following Remand was timely submitted and forms the basis of this Recommended Order on Land Use Following Remand.

FINDINGS OF FACT


  1. JEA is a municipally-owned utility that provides electric service in Duval County and surrounding areas. JEA serves approximately 350,000 customers. (Mims, T. 6-7) JEA has been providing electric service in the Jacksonville area since 1895. JEA currently operates four generating stations along with a power plant jointly-owned with Florida Power & Light Company. These existing plants burn a range of fuels, including coal, oil and natural gas. (Mims, T. 6-7) In

    October 2001, JEA will decommission its existing Southside station. (Mims, T. 8)

  2. JEA's Brandy Branch facility is located west of Jacksonville, north of U.S. Highway 90, and approximately one mile to the east of the town of Baldwin, Florida. The Brandy Branch site is approximately 153 acres, with 45 acres containing the electrical generating facilities units. JEA is currently constructing three combustion turbines to operate in the simple cycle mode at its Brandy Branch site. The combustion turbines are in commercial operation. (Mims, T. 8; Mims, T.(2). 19-20) In addition to the simple cycle units, raw water tanks, fuel tanks and stormwater ponds have been constructed on the project site. (Mims, T. 9; JEA Ex. 8A)

  3. The simple cycle combustion turbines at the site operate like a large version of a jet engine. Air is compressed and mixed with either gas or oil, which is converted into mechanical power that turns an electrical generator to create electric power. This power is then distributed out over the electrical transmission grid. This includes the 230 KV transmission lines that currently serve the Brandy Branch site. (Mims, T. 10)

  4. The site is currently served by an existing natural gas pipeline that connects to the Florida Gas Transmission system. In addition, JEA is negotiating for a second gas

    pipeline that may connect the project site to a new line that will come into Florida from Georgia. That second line will be separately owned and operated by the gas pipeline company. (Mims, T. 11-12)

  5. JEA is now proposing to convert two of the simple cycle combustion turbines into a combined cycle unit by installing heat recovery steam generators onto the exhaust system of the gas turbines. A new steam turbine generator will also be installed to the west of the existing units. The combined cycle configuration involves capturing the exhaust gas from the combustion turbine through a heat recovery steam generator that in turn supplies steam to a steam turbine. The steam turbine drives an additional electrical generator. (Mims, T. 12-13; JEA Exs. 7A and 7B)

  6. A new cooling tower will be constructed within the project site as part of the conversion project. The cooling tower will cool the steam that goes through the condenser. Addition of the cooling tower will involve an additional 2.5 acres within the 153 acre JEA Brandy Branch site. No modifications to the existing transmission system will be required as part of the project. (Mims, T. 13-15; JEA Exs. 7A and 7B)

  7. The three simple cycle combustion turbines at the Brandy Branch site will have a generating capacity of

    approximately 520 megawatts (MW). The conversion of the Brandy Branch site to combined cycle operation will add an additional 190 MW of generating capacity. This will result in approximately 700 MW of total generating capacity at the site after the conversion. (Mims, T. 14)

  8. The original development plan for the Brandy Branch site anticipated four simple cycle combustion turbines. After the initial three units were brought into operation, JEA planned to add a fourth combustion turbine as demand for electricity increased on JEA's system. However, JEA decided to convert two of the CTs to combined cycle operation in lieu of constructing the fourth CT because the capacity factor on the units was increasing faster than originally anticipated. JEA found it more economically feasible to add the combined cycle unit rather than adding an additional combustion turbine. (Mims, T. 16-17)

  9. The JEA Brandy Branch site is located in the incorporated area of the City of Jacksonville. The Brandy Branch site is surrounded by pasture and timber land on all sides, with a large dairy farm located to the east. (Kilgo,

    T. 20; Purvis, T. 33; JEA Ex. 8B) The nearest occupied residence is approximately one-half to three-quarters of a mile to the northwest of the generating station. There are no significant environmental resources on the site. An existing

    rails-to-trails facility is adjacent to the southeast corner of the site. (Kilgo, T. 21)

  10. The City of Jacksonville's Comprehensive Plan and Future Land Use Map designate the JEA Brandy Branch site as Public Buildings and Facilities, or PBF. (Kilgo, T. 22-23; JEA Ex. 10) That land use category permits electric power plants as an allowed use. (Kilgo, T. 23; Purvis, T. 33; JEA Ex. 9, at page 41 of 58) Surrounding land use designations generally include Agriculture or AGR-III. (JEA Ex. 10)

  11. In September 1999, at JEA's request, the Jacksonville City Council rezoned the Brandy Branch site from PBF-1 to PUD for the entire 153 acre site. (JEA Ex. 13) The PUD approval accommodates the combined cycle project for the most part. Construction of the additional facilities will be covered by the existing PUD. (Kilgo, T. 24) The PUD zoning application for the Brandy Branch site contained information on air emission limits and on the height of the emissions stacks at the site. The air emissions information concerning the Brandy Branch site contained in the zoning application was incorporated by reference into the PUD approval. (Purvis, T. 35)

  12. On July 27, 2001, JEA requested that the City of


    Jacksonville modify the PUD zoning for the Project site to provide that the Project must comply with any air emissions

    permit issued by the FDEP and to allow a maximum structure height of 199 feet. On August 30, 2001, the City of Jacksonville Planning Commission granted the requested modification, following a recommendation from the City of Jacksonville's planning staff in support of the modification. (Kilgo, T(2). 13-15 ; JEA Exs(2). 8 and 12) The Project as designed will be able to comply with the FDEP air permit and Conditions of Certification, including those related to air emissions. The maximum height structure will be 190 feet. (Mims, T(2). 21; Hillman, JEA Ex(2). 1C pp.5-17; Holscher, JEA Ex(2). 1C, pp. 8-13)

    CONCLUSIONS OF LAW


  13. The Division of Administrative Hearings has jurisdiction of the parties to and the subject matter of this proceeding. The proceeding was conducted in accordance with Section 403.508(2), Florida Statutes, addressing the consistency of the site with local land use plans and zoning ordinances of the City of Jacksonville.

  14. In accordance with Chapter 403, Part II, Florida Statutes and Chapter 62-17, Florida Administrative Code, proper public notice was accorded all persons, entities and parties entitled to such notice. All necessary and required governmental agencies participated in or had the opportunity to participate in the land use hearing.

  15. Unrebutted evidence at the hearings on April 24, 2001 and December 4, 2001, demonstrates that the Brandy Branch combined cycle conversion project and its site are consistent and in compliance with the City of Jacksonville's land use plans and are consistent and in compliance with the applicable zoning ordinances for the site.

RECOMMENDATION


Based upon the foregoing Findings of Fact and Conclusions of Law, it is

RECOMMENDED that the Siting Board find that the site of the JEA Brandy Branch Combined Cycle Conversion Project as described by the evidence presented at the hearing, is consistent and in compliance with existing land use plans and zoning ordinances of the City of Jacksonville as they apply to the site, pursuant to Section 403.508(2), Florida Statutes.

DONE AND ENTERED this 15th day of January, 2002, in Tallahassee, Leon County, Florida.

___________________________________

J. LAWRENCE JOHNSTON Administrative Law Judge

Division of Administrative Hearings The DeSoto Building

1230 Apalachee Parkway

Tallahassee, Florida 32399-3060

(850) 488-9675 SUNCOM 278-9675

Fax Filing (850) 921-6847 www.doah.state.fl.us


Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 2002.



COPIES FURNISHED:


Douglas S. Roberts, Esquire Hopping, Green & Sams

Post Office Box 6526 Tallahassee, Florida 32314


Colin M. Roopnarine, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard Tallahassee, Florida 32399-2100


James V. Antista, Esquire Florida Fish and Wildlife Conservation Commission 620 South Meridian Street Bryant Building, Room 108

Tallahassee, Florida 32399-1600


Bryan Teeple

Northeast Florida Regional Planning Council

9143 Phillips Highway, Suite 350

Jacksonville, Florida 32256


William H. Congdon, Esquire Veronika Thiebach, Esquire

St. Johns River Water Management District Post Office Box 1429

Palatka, Florida 32178-1429


Cathy Bedell, Esquire Robert V. Elias, Esquire Office of General Counsel Public Service Commission 2540 Shumard Oak Boulevard

Tallahassee, Florida 32399-0850


Sheauching Yu, Esquire Department of Transportation 605 Suwannee Street

Haydon Burns Building, Mail Station 58 Tallahassee, Florida 32399-0458

Scott A. Goorland, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000


Gregory K. Radlinski, Esquire City Hall at St. James

117 West Duval Street, Suite 480 Jacksonville, Florida 32202


Kathy C. Carter, Agency Clerk Office of General Counsel

Department of Environmental Protection 3900 Commonwealth Boulevard

The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000


Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard

The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000


NOTICE OF RIGHT TO SUBMIT EXCEPTIONS


All parties have the right to submit written exceptions within

15 days from the date of this Recommended Order on Land Use Following Remand. Any exceptions to this Recommended Order on Land Use Following Remand should be filed with the agency that will issue the Final Order in this case.


Docket for Case No: 00-005120EPP
Issue Date Proceedings
Mar. 29, 2002 Letter to D. Roberts from S. Goorland enclosing copies of the conditions of certification referenced as DEP exhibit 2 filed.
Mar. 26, 2002 Final Order on Land Use and Site Certification (filed via facsimile).
Jan. 15, 2002 Recommended Order on Land Use Following Remand issued (hearing held April 24 and December 4, 2001) CASE CLOSED.
Jan. 15, 2002 Recommended Order on Certification issued (hearing held December 4, 2001).
Jan. 15, 2002 Recommended Order cover letter identifying hearing record referred to the Agency sent out.
Dec. 21, 2001 Notice of Filing Signature Page to Joint Proposed Recommended Order on Certification filed.
Dec. 20, 2001 Proposed Recommended Order on Land Use Following Remand filed.
Dec. 20, 2001 Notice of Filing Joint Proposed Recommended Order on Land Use Following Remand filed.
Dec. 20, 2001 Joint Proposed Recommended Order on Certification for the Jea Brandy Branch Project filed.
Dec. 20, 2001 Notice of Filing Joint Proposed Recommended Order on Certification Hearing filed.
Dec. 13, 2001 Transcript of Administrative Hearing filed.
Dec. 07, 2001 Department of Environmental Protection`s Notice of Filing Exhibit filed.
Dec. 04, 2001 CASE STATUS: Hearing Held; see case file for applicable time frames.
Nov. 30, 2001 Notice of City of Jacksonville`s Concurence in the Prehearing Stipulation (filed by G. Radlinski via facsimile).
Nov. 29, 2001 (Joint) Pre-hearing Stipulation filed.
Nov. 29, 2001 Stipulation Between the St. Johns River Water Management District and Applicant filed.
Nov. 29, 2001 Letter to Judge Johnston from D. Roberts notice of hearing location filed.
Nov. 27, 2001 Amended Notice of Hearing issued. (hearing set for December 4, 2001; 10:00 a.m.; Baldwin, FL, amended as to Start Time and Date).
Nov. 26, 2001 Notice of Substitution of Counsel for Department of Community Affairs (filed via facsimile).
Nov. 21, 2001 JEA-Brandy Branch Site Certification Hearing Testimony filed.
Nov. 21, 2001 Notice of Filing Prepared Directed Testimony and Exhibits filed.
Nov. 13, 2001 Notice of Filing Certified Proof of Publication for Notice of Certification Hearing for a Power Plant Siting Application to be Located in Duval County, Florida: Jea Brandy Branch Generating Station filed.
Nov. 02, 2001 Department of Environmental Protection`s Notice of Filing of Written Analysis; Site Certification Review for JEA Brandy Generating Station Combined Cycle Conversion Case No. PA 00-43 filed.
Sep. 26, 2001 Order of Remand for Further Proceedings filed by the Siting Board.
Sep. 10, 2001 Notice of Sufficiency of Power Plant Siting Aplication (filed via facsimile).
Aug. 07, 2001 JEA`s Notice of Filing Responses to Second Notice of Insufficiency of the Department of Environmental Protection filed.
Aug. 06, 2001 Notice of Hearing issued (hearing set for December 4 through 6, 2001; 9:00 a.m.; Baldwin, FL).
Aug. 06, 2001 Order of Pre-hearing Instructions issued.
Aug. 02, 2001 Letter to Judge Johnston fromD. Roberts regarding hearing location filed.
Jul. 05, 2001 Recommended Order cover letter identifying hearing record referred to the Agency sent out.
Jul. 05, 2001 Recommended Order on Land Use issued. (hearing held April 24, 2001)
Jun. 19, 2001 Order Altering Times issued. (stipulations and motion are approved and granted)
Jun. 15, 2001 JEA, Florida Department of Environmental Protection and City of Jacksonville`s Joint Proposed Recommended Order on Land Use filed.
Jun. 15, 2001 Notice of Filing Joint Proposed Recommended Order on Land Use filed.
Jun. 05, 2001 Joint Stipulation and Motion for Alteration of Time Limits filed.
Jun. 05, 2001 Transcript filed.
May 15, 2001 JEA`s Response to Florida Department of Environmental Protection`s Second Notice of Insufficiency filed.
Apr. 30, 2001 Notice of Second Insufficiency (filed by Respondent via facsimile).
Apr. 24, 2001 CASE STATUS: Hearing Held; see case file for applicable time frames.
Apr. 04, 2001 JEA Brady Branch`s Notice of Filing Responses to Notice of Insufficienty of the Department of Environmental Protection filed by Petitioner.
Apr. 04, 2001 Notice of Filing Certified Proof of Publication for Notice of Land Use Hearing for a Power Plant Siting Application to be Located in Duval County, Florida: JEA Brandy Branch Generating Station filed by Petitioner.
Mar. 02, 2001 Jea`s Response to Florida Department of Environmental Protection`s Notice of Insufficiency filed.
Feb. 16, 2001 Notice of Hearing issued (hearing set for April 24, 2001; 10:30 a.m.; Baldwin, FL).
Feb. 15, 2001 Notice of Insufficiency (filed via facsimile).
Feb. 07, 2001 Letter to Judge J. Johnston from D. Roberts In re: available hearing dates filed.
Feb. 05, 2001 St. Johns River Water Management District`s Notice of Intent to be a Party filed.
Jan. 29, 2001 City of Jacksonville`s Notice of Intent to be a Party filed.
Jan. 29, 2001 Notice of Appearance (filed by V. Thiebach).
Jan. 19, 2001 Notice of Filing Certified Proof of Publication for Notice of Filing Application for a Power Plant Siting Application to be Located in Duval County, Florida: Jea Brandy Branch Generating Station filed.
Jan. 17, 2001 Department of Transportation`s Notice of Intent to be a Party filed.
Jan. 05, 2001 Joint Response to DOAH`s Initial Order filed.
Jan. 02, 2001 Notice of Appearance filed by W. Congdon.
Dec. 29, 2000 Notice of Filing Preliminary Schedule of Significant Dates filed by S. Goorland; Preliminary Schedule of Significant Dates Site Certification Application Review JEA Brandy Branch Combined Cycle Conversion filed.
Dec. 29, 2000 Notice of Filing Site Certification Application filed.
Dec. 28, 2000 Initial Order issued.
Dec. 22, 2000 Statement of Completeness (filed via facsimile).
Dec. 15, 2000 Notice of Filing of List of Affected Agencies (filed via facsimile).
Dec. 15, 2000 Notice of Receipt of Power Plant Siting Supplemental Application and Request for Assignment of Administrative Law Judge (filed via facsimile).

Orders for Case No: 00-005120EPP
Issue Date Document Summary
Mar. 25, 2002 Agency Final Order
Jan. 15, 2002 Recommended Order JEA Brandy Branch Combined Cycle Conversion Project met all power plant siting requirement.
Jan. 15, 2002 Recommended Order JEA Brandy Branch Combined Cycle Conversion Project was consistent with existing local land use plans and zoning ordinances.
Jul. 05, 2001 Recommended Order JEA Brandy Branch Combined Cycle Conversion Project was consistent with existing local land use plans and zoning ordinances, subject to amendment to PUD.
Source:  Florida - Division of Administrative Hearings

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer