IN RE: FLORIDA POWER AND LIGHT COMPANY; DUVAL-RAVEN 230KV TRANSMISSION LINE SITING APPLICATION NO. TA16-17 vs *, 16-000276TL (2016)
Court: Division of Administrative Hearings, Florida
Number: 16-000276TL
Visitors: 12
Petitioner: IN RE: FLORIDA POWER AND LIGHT COMPANY; DUVAL-RAVEN 230KV TRANSMISSION LINE SITING APPLICATION NO. TA16-17
Respondent: *
Judges: BRAM D. E. CANTER
Agency: Department of Environmental Protection
Locations: Macclenny, Florida
Filed: Jan. 19, 2016
Status: Closed
Settled and/or Dismissed prior to entry of RO/FO on Monday, May 23, 2016.
Latest Update: Dec. 23, 2024
Docket for Case No: 16-000276TL
Issue Date |
Proceedings |
May 24, 2016 |
Transmittal letter from Claudia Llado forwarding FPL Duval - Raven 230-kV Transmission Line Certification Application to the Department.
|
May 23, 2016 |
Order Closing File and Relinquishing Jurisdiction. CASE CLOSED.
|
May 23, 2016 |
Order.
|
May 23, 2016 |
Certificate of Service -Peterson Lewis filed.
|
May 20, 2016 |
Notarized Signature Sheet filed.
|
May 20, 2016 |
Response to Motion to Dismiss filed.
|
May 16, 2016 |
Order to Show Cause.
|
May 16, 2016 |
Order (on joint motion to alter timeframes and amend pre-hearing instructions).
|
May 13, 2016 |
Florida Power & Light Company's and the Florida Department of Environmental Protection's Stipulation and Joint Motion to Alter Timeframes and Amend Pre-hearing Instruction Discovery Deadlines filed.
|
May 13, 2016 |
Florida Power & Light Company's Motion to Dismiss and Response in Opposition to Sonja Peterson-Lewis' Petition to Intervene as a Party filed.
|
May 10, 2016 |
Joint Stipulation and Motion of the Parties to Cancel Certification Hearing and to Relinquish Jurisdiction to DEP for Entry of Final Certification Order filed.
|
May 10, 2016 |
Petition to Intervene as a Party (filed by Sonya Peterson-Lewis) filed.
|
May 09, 2016 |
St. Johns River Water Management District's Notice of Intent to Be a Party filed.
|
May 06, 2016 |
Supplemented Appendices (Appendix III Public Comment) filed.
|
May 06, 2016 |
State of Florida Department of Environmental Protection's Notice of Filing Supplement to Project Analysis Report Appendix filed.
|
May 05, 2016 |
Appendices filed by Benjamin Melnick.
|
May 05, 2016 |
Florida Department of Environmental Protection's Notice of Filing Project Analysis Report filed.
|
Apr. 27, 2016 |
Notice of Filing Witness Disclosure filed.
|
Apr. 27, 2016 |
Notice of FPL's Witness Disclosure filed.
|
Apr. 27, 2016 |
City of Macclenny's Agency Report filed.
|
Apr. 25, 2016 |
Suwannee River Water Management District's Notice of Filing Agency Report filed.
|
Apr. 25, 2016 |
Notice of Appearance (George Reeves) filed.
|
Apr. 25, 2016 |
Baker County's Agency Report: Pursuant to Section 403.526(2)(a), Florida Statues filed.
|
Apr. 21, 2016 |
Undeliverable envelope returned from the Post Office.
|
Apr. 11, 2016 |
Florida Department of Transportation's Agency Report filed.
|
Apr. 11, 2016 |
Columbia County, Florida's, Agency Report Pursuant to Fla. Stat. Section 403.526(2)(a) filed.
|
Apr. 11, 2016 |
St. Johns River Water Management District's Notice of Filing Agency Report filed.
|
Apr. 07, 2016 |
Florida Power & Light Company's Notice of Submittal of Proof of Publication of Notice of Certification Hearing on Proposed Electrical Transmission Line Corridor filed.
|
Apr. 07, 2016 |
Town of Glen St. Mary's Agency Report Pursuant to Fla. Stat. Section 403.526(2)(a) filed.
|
Apr. 07, 2016 |
Notice of Appearance (Jonathan Bense) filed.
|
Mar. 23, 2016 |
Florida Department of Environmental Protection's Notice of Determination of Completeness filed.
|
Mar. 23, 2016 |
Florida Department of Environmental Protection's First Determination of Incompleteness filed.
|
Mar. 14, 2016 |
Florida Power & Light Company's Notice of Submittal of List of Landowners and Residences Notified of Filing of Site Certification Application filed.
|
Mar. 10, 2016 |
Order of Pre-hearing Instructions.
|
Mar. 10, 2016 |
Notice of Hearing (hearing set for June 6 and 7, 2016; 10:00 a.m.; Macclenny, FL).
|
Mar. 02, 2016 |
Notice of Submittal of Responses to the Completeness Questions of the Agencies filed.
|
Feb. 17, 2016 |
Florida Department of Environmental Protection's First Determination of Incompleteness filed.
|
Feb. 17, 2016 |
Submittal of Certified Proofs of Publication for Notice of Filing of Application for Transmission Line Site Certification filed.
|
Feb. 01, 2016 |
Order Establishing Schedule.
|
Jan. 20, 2016 |
Initial Order.
|
Jan. 19, 2016 |
Transmission Line Certification Application filed.
|
Jan. 19, 2016 |
Schedule for Review of Corridor Certification Application filed.
|
Jan. 19, 2016 |
Department of Environmental Protection's Request for Assignment of Administrative Law Judge filed.
|