Filed: Feb. 27, 2019
Latest Update: Mar. 03, 2020
Summary: NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT KENF, L.L.C., ) ) Appellant, ) ) v. ) Case No. 2D18-2804 ) JABEZ RESTORATIONS, INC., a ) Florida corporation, d/b/a SERVPRO ) OF BRADENTON, ) ) Appellee. ) ) Opinion filed February 27, 2019 Appeal from the Circuit Court for Manatee County; Gilbert A. Smith Jr., Judge. Charles V. Barrett III, Tampa; and Frederick W. Vollrath, Tampa, for Appellant. John P. Flec
Summary: NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT KENF, L.L.C., ) ) Appellant, ) ) v. ) Case No. 2D18-2804 ) JABEZ RESTORATIONS, INC., a ) Florida corporation, d/b/a SERVPRO ) OF BRADENTON, ) ) Appellee. ) ) Opinion filed February 27, 2019 Appeal from the Circuit Court for Manatee County; Gilbert A. Smith Jr., Judge. Charles V. Barrett III, Tampa; and Frederick W. Vollrath, Tampa, for Appellant. John P. Fleck..
More
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING
MOTION AND, IF FILED, DETERMINED
IN THE DISTRICT COURT OF APPEAL
OF FLORIDA
SECOND DISTRICT
KENF, L.L.C., )
)
Appellant, )
)
v. ) Case No. 2D18-2804
)
JABEZ RESTORATIONS, INC., a )
Florida corporation, d/b/a SERVPRO )
OF BRADENTON, )
)
Appellee. )
)
Opinion filed February 27, 2019
Appeal from the Circuit Court for Manatee
County; Gilbert A. Smith Jr., Judge.
Charles V. Barrett III, Tampa; and
Frederick W. Vollrath, Tampa, for Appellant.
John P. Fleck, Jr., Bradenton, for Appellee.
VILLANTI, Judge.
KENF, L.L.C., seeks review of the final judgment entered in favor of Jabez
Restorations, Inc., d/b/a ServPro of Bradenton, in this action arising out of an unpaid bill
for services. Because we agree with KENF that the amount of damages awarded in the
final judgment was not supported by the evidence presented at the bench trial, we
reverse the damages award and remand for entry of an amended final judgment. In all
other respects, we affirm.
KENF is the owner of an apartment complex in Bradenton. In early June
2016, a fire broke out in one of the apartments, which caused the fire sprinkler system
to activate and resulted in water damage to three apartments. About a week later,
KENF asked Jabez to inspect the damaged units and prepare an estimate to remediate
and repair them. Based on its initial inspection, Jabez determined that fans and
dehumidifiers would be sufficient to dry out the apartments, after which certain repairs
would be undertaken, and Jabez provided KENF with an estimate for this work.
KENF's local maintenance manager authorized Jabez to go forward with
the work to dry out the apartments; however, before Jabez could actually begin the
work, KENF required Jabez to submit a vendor packet to its home office to become
"approved." Once KENF approved Jabez as a vendor—approximately one week after
the initial inspection—Jabez returned to the damaged apartments and discovered that
the delay in any dry-out and remediation work had resulted in mold growth in the
apartments. Jabez installed dehumidifiers to start drying out the apartments and, with
authorization from KENF's maintenance manager, called a mold assessor to inspect the
apartments and provide a revised scope and cost for full repairs.
While waiting for the mold assessor's report, Jabez continued to run the
dehumidifiers in the water-damaged apartments, checking on them periodically. When
the mold assessor's report was completed, Jabez forwarded it to KENF along with a
revised scope of work necessary to repair the mold damage in addition to the original
water damage. KENF rejected this proposal but requested that Jabez leave the
-2-
dehumidifiers in place and running until a new contractor could get its vendor packet
approved and begin work. Jabez agreed to do so. Once KENF advised Jabez that the
new contractor was on site and that Jabez could remove its equipment, Jabez did so
the same day.
Jabez then invoiced KENF $17,437.19 for the use of the dehumidifiers for
the entire time that they were in place at KENF's request and the cost of the mold
assessor's report. When KENF balked at paying the invoice, Jabez agreed to reduce
the cost of the equipment by $2000, bringing the invoice total down to $15,557.75.
Despite this concession, KENF refused to pay any part of the invoice.
Jabez subsequently sued KENF to recover the amount of its invoice.
While the complaint is not a model pleading, it does allege that Jabez provided services
to KENF with KENF's approval, that KENF accepted the benefit of the services, and that
the value of KENF's property was enriched by the services provided by Jabez. Jabez
specifically alleged in the complaint that KENF owed it $15,557.75 for its services. In its
answer, KENF denied that it had any contract with Jabez and denied that it had
received any benefit from the work Jabez performed.
At the conclusion of the bench trial of this matter, the trial court found in
favor of Jabez, and it awarded Jabez $17,437.19—the amount of the original invoice
before Jabez voluntarily reduced it—on the claim for unjust enrichment. KENF now
appeals this final judgment.
KENF's primary argument on appeal is that the trial court erred in entering
final judgment in favor of Jabez because the evidence presented at the bench trial was
-3-
legally insufficient to prove a claim for unjust enrichment.1 While we disagree with
KENF's position as to its liability for unjust enrichment damages, we agree that the
amount of damages awarded was improper.
"An action for 'unjust enrichment' exists to prevent the wrongful retention
of a benefit, or the retention of money or property of another, in violation of good
conscience and fundamental principles of justice or equity." Henry M. Butler, Inc. v.
Trizec Props., Inc.,
524 So. 2d 710, 711 (Fla. 2d DCA 1988). The elements of such a
claim are: "(1) a benefit conferred upon a defendant by the plaintiff, (2) the defendant's
appreciation of the benefit, and (3) the defendant's acceptance and retention of the
benefit under circumstances that make it inequitable for him to retain it without paying
the value thereof." Rollins, Inc. v. Butland,
951 So. 2d 860, 876 (Fla. 2d DCA 2006).
Essentially, the doctrine operates to imply a contract where none otherwise exists so as
to ensure equity between the parties. See 14th & Heinberg, LLC v. Terhaar & Cronley
Gen. Contractors, Inc.,
43 So. 3d 877, 880 (Fla. 1st DCA 2010).
In this case, the evidence presented at the bench trial established that
Jabez conferred a benefit on KENF in that it ran dehumidification equipment in the
damaged apartments to help prevent further water and mold damage from the date
KENF approved Jabez to do the work until the date KENF requested that the equipment
1KENF also argued that the trial court erred by entering final judgment in
favor of Jabez based on unjust enrichment when such a claim was not properly pleaded
in the complaint. We reject this argument without further discussion. In addition, KENF
argued that the trial court abused its discretion when it sanctioned KENF for failing to
timely file a witness and exhibit list by excluding KENF's witnesses and exhibits at the
bench trial. Because KENF did not provide this court with a transcript of the hearing
that resulted in these sanctions, we have no record basis upon which to conclude that
the trial court abused its discretion. See Applegate v. Barnett Bank of Tallahassee,
377
So. 2d 1150, 1152 (Fla. 1979). Hence, we affirm that ruling as well.
-4-
be removed. It is clear from the evidence that KENF asked for this work to be done,
and it accepted the benefit of this work. Any doubt concerning whether the equipment
conferred a benefit and whether KENF recognized and accepted that benefit was
eliminated by the evidence of KENF's request that Jabez leave the dehumidifiers in
place and running while KENF was waiting for the other contractor to be approved to
start work. At a minimum, this evidence suggested that KENF recognized that the
equipment was performing a function and doing so properly. In light of this, it would be
inequitable to permit KENF to reap the benefit of the dehumidification of the apartments
without paying the value of that benefit to Jabez. Hence, the totality of the evidence
supports the trial court's conclusion that Jabez proved its claim for unjust enrichment.
In support of its argument for reversal, KENF contends that the existence
of any benefit was speculative because Jabez did not offer any evidence of the humidity
levels in the apartments before and after it started work to be able to prove that the
dehumidifiers were actually doing their job. Without such evidence, KENF claims that
Jabez did not and cannot prove that it provided any benefit. However, as mentioned
above, this claim is belied by KENF's request that Jabez keep the dehumidifiers in place
and running during the time that KENF was getting the replacement contractor
approved. If KENF saw no benefit to the dehumidifiers, it would have had no reason to
ask Jabez to keep them installed and running for this additional period of time.
KENF also argues that Jabez provided no benefit to KENF because the
apartments were in the same state of disrepair when Jabez removed its dehumidifiers
as they were when Jabez installed them. But this ignores the evidence that the
equipment provided by Jabez prevented further damage to KENF's apartments. Based
-5-
on the testimony presented, the benefit was the mitigation of the existing damage and
prevention of further damage—not actual repairs to the existing damage. The term
"benefit" does not require a measurable improvement. Black's Law Dictionary defines
"benefit" to include "the helpful or useful effect something has." Benefit, Black's Law
Dictionary (10th ed. 2014). Here, the use of Jabez's dehumidifiers had the helpful effect
of preventing further damage to the apartments. KENF apparently recognized this
benefit when it requested that Jabez leave the dehumidifiers running while a new
contractor was brought on board. In light of this evidence, KENF's argument that there
was no evidence to support the trial court's finding that Jabez conferred a benefit is
unavailing, and we affirm the final judgment to the extent that it finds KENF liable for
damages to Jabez.
As to the amount of those damages, however, we must reverse and
remand for entry of an amended final judgment because the final judgment awards
damages in an amount neither sought nor proved by Jabez. In both its complaint and at
trial, Jabez sought only the amount it ultimately billed KENF, which was $15,557.75.
Nevertheless, the trial court awarded damages in the amount of $17,437.19—the
amount Jabez originally invoiced KENF before Jabez voluntarily reduced that invoice.
Clearly, it is unjust to award Jabez more for its services in the final judgment than it
would have received had KENF properly paid the invoice submitted to it. See 14th &
Heinberg,
LLC, 43 So. 3d at 882 (affirming damages award for an unjust enrichment
claim in the amount of the unpaid balance of the subcontractor's original contract and
noting that "it would be inequitable to award Terhaar the value of the increase in rental
value when it would not have received such value had the contract been performed by
-6-
Montgomery Ward"). Jabez is entitled to be paid for its services, but it is not entitled to
a windfall over and above the amount it actually claimed. Accordingly, we reverse the
damages awarded in the final judgment and remand for the trial court to enter an
amended judgment in favor of Jabez in the amount of $15,557.75.2
Affirmed in part, reversed in part, and remanded with directions.
LUCAS and ROTHSTEIN-YOUAKIM, JJ., Concur.
2This direction as to the amount to be awarded in the final judgment is
limited to the principal amount of damages. We do not preclude any award of any
interest, attorney's fees, or costs to which Jabez may be entitled.
-7-