PER CURIAM.
In these consolidated cases, appellant Association of Businesses Advocating Tariff Equity (ABATE) (Docket No. 303009) and appellants Michigan Public Power Agency (MPPA) and Michigan Municipal Electric Association (MMEA) (Docket No. 303040) appeal the February 25, 2011, order entered by the Michigan Public Service Commission (PSC) granting appellee International Transmission Company (ITC) an expedited siting certificate for a wind energy transmission line and authorizing construction of that line on ITC's proposed route.
Before 2008, all location and construction of electric transmission lines of a certain size and length was governed by 1995 PA 30, known as the Electric Transmission Line Certification Act, MCL 460.561 et seq. (Act 30).
The WERZ Board was created on December 4, 2008. In its final report, dated October 15, 2009, the WERZ Board identified four regions in Michigan with the highest wind energy potential. Relevant to this case, Region No. 4, covering Huron, Bay, Saginaw, Sanilac, and Tuscola Counties, had a minimum wind energy generating capacity of 2,367 megawatts (MW) and a maximum of 4,236 MW. Pursuant to MCL 460.1145(6), on November 30, 2009, ITC informed the WERZ Board that
On January 27, 2010, pursuant to MCL 460.1147(1), the PSC formally accepted the WERZ Board's report and designated Region 4 as the primary wind energy resource zone.
Pursuant to MCL 460.1149(4), on February 3, 2010, ITC submitted a letter to the PSC notifying it that, within 60 days or as soon as practicable thereafter, ITC intended to seek approval from the Midwest Independent Transmission System Operator, Inc. (MISO) for a transmission line that would enable realization of the wind power in Region 4. The PSC acknowledged receiving the letter and informed ITC that the letter fulfilled the notice requirements of MCL 460.1149(4). MISO ultimately approved ITC's proposed transmission line in August 2010.
On August 30, 2010, ITC filed an application in the PSC requesting an expedited siting certificate authorizing the construction of a transmission line to enable the wind potential of Region 4 to be realized. The proposed transmission line included "a new 345 kV double circuit tower line and four new substations." Along with the application, ITC filed direct testimony and exhibits addressing specific factors required by MCL 460.1151. The referee granted the petitions to intervene of Consumers Energy, Detroit Edison, MMEA, and MPPA, and ABATE was allowed "permissive" intervention by the PSC.
During the proceedings, appellants argued that ITC's proposed transmission line did not meet the requirements of Act 295(4) because (1) it was oversized, was too costly, and represented an unreasonable threat to the public convenience; (2) Act 295(4) did not provide authorization for construction of a transmission line because that authorization was reserved to Act 30; (3) ITC was still required to undergo the siting process of Act 30; and (4) Act 295(4) was unconstitutional and void because it
The PSC determined that "ITC's proofs fulfill[ed] all of the statutory requirements" under MCL 460.1153 and concluded that the transmission line was of "appropriate capability" because it met or exceeded the maximum load, noting that the 10 percent requirement for production of electricity with renewable energy was "a floor, not a ceiling." It also concluded that the size of the proposed transmission line was reasonable "in light of the risk that underbuilding the line now could result in substantially higher costs and additional environmental impacts in the future if transmission capacity needed to be added." Finally, regarding authorization for construction, the PSC concluded that resolving the alleged conflict between Act 295(4) and Act 30 "belongs to the [PSC's] judicial superiors," but stated that it was "counterintuitive" that the Legislature intended an expedited siting certificate to take 18 months
In March 2011, appellants filed their appeals in this Court; the appeals were administratively consolidated. In re Application of Int'l Transmission Co. for Expedited Siting Certificate, unpublished order of the Court of Appeals, entered March 31, 2011 (Docket Nos. 303009 and 303040). The PSC denied appellants' motion for a stay pending resolution of this appeal.
The standard of review for PSC orders is narrow and well defined. All regulations, practices, and services prescribed by the PSC are presumed, prima facie, to be lawful and reasonable. MCL 462.25; Great Wolf Lodge of Traverse City, LLC v. Pub. Serv. Comm., 489 Mich. 27, 37-38, 799 N.W.2d 155 (2011). A party aggrieved by a PSC order bears the burden of proving by clear and convincing evidence that the order is unlawful or unreasonable. MCL 462.26(8).
An order is also unreasonable if it is totally unsupported by admissible and admitted evidence. Associated Truck Lines, Inc. v. Pub. Serv. Comm., 377 Mich. 259, 279, 140 N.W.2d 515 (1966).
A reviewing court gives due deference to the PSC's administrative expertise and may not substitute its judgment for that of the PSC. Attorney General v. Pub. Serv. Comm. No. 2, 237 Mich.App. 82, 88, 602 N.W.2d 225 (1999). This Court gives respectful consideration to the PSC's construction of a statute that the PSC is empowered to execute and will not overrule
Whether the PSC exceeded the scope of its authority is a question of law that is reviewed de novo. In re Complaint of Pelland Against Ameritech Mich., 254 Mich.App. 675, 682, 658 N.W.2d 849 (2003).
At issue in this case is the proper interpretation of Act 295(4) and Act 30. The primary goal of statutory interpretation is to determine the intent of the Legislature. Joseph v. Auto Club Ins. Ass'n, 491 Mich. 200, 205, 815 N.W.2d 412 (2012). The best indicator of that intent is the language of the statute itself. Id. at 205-206. The words used by the Legislature and any undefined terms are given their common and ordinary meaning. See Nastal v. Henderson & Assoc. Investigations, Inc., 471 Mich. 712, 720, 691 N.W.2d 1 (2005). This Court presumes that the Legislature intended the meaning clearly expressed in unambiguous statutory language and no further construction is required or allowed. Id.
In addition, "[s]tatutes are presumed to be constitutional, and courts have a duty to construe a statute as constitutional unless its unconstitutionality is clearly apparent." Taylor v. Gate Pharm., 468 Mich. 1, 6, 658 N.W.2d 127 (2003). Consistently with this mandate, "`apparently conflicting statutes should be construed, if possible, to give each full force and effect.'" In re Midland Publishing Co., Inc., 420 Mich. 148, 163, 362 N.W.2d 580 (1984), quoting State Hwy. Comm'r v. Detroit City Controller, 331 Mich. 337, 358, 49 N.W.2d 318 (1951).
Appellants first contend that the PSC exceeded its authority by authorizing construction of ITC's transmission line because the expedited siting certificate authorized by Act 295(4) does not authorize actual construction of a transmission line. In addition, having interpreted Act 295(4) to authorize construction, the PSC rendered Act 295(4) unconstitutional because that interpretation created an exception to the requirements of Act 30, thereby violating Const. 1963, art. 4, § 25, which provides, "No law shall be revised, altered or amended by reference to its title only. The section or sections of the act altered or amended shall be reenacted and published at length." There is no question that Act 30 was not reenacted and published at length when Act 295 was passed. Therefore, to determine whether Act 295(4) violates the Constitution, we must decide whether Act 295(4) seeks to revise, alter, or amend Act 30.
Under Act 30, "[i]f ... an independent transmission company plans to construct a major transmission line in this state in the 5 years after planning commences, the ... independent transmission company shall submit a construction plan to the [PSC]." MCL 460.564(1) (emphasis added). There is no dispute that the transmission line for which ITC sought approval was a major transmission line as defined in Act 30. See MCL 460.562(g). MCL 460.565 then provides that "[a]n ... independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under [MCL
Appellees argue that ITC was not required to submit an application under Act 30 because the siting certificate under Act 295(4) authorized construction. The parties agree that none of the provisions in Act 295(4) expressly states that construction is authorized by issuance of a siting certificate. The PSC argues that the Legislature's use of the term "siting" to describe the certificate that is granted indicates an intent to authorize construction. Specifically, "site" means "to place in or provide with a site; locate" or "to put in position for operation[.]" Random House Webster's College Dictionary (1997). Similarly, "construction" is defined under Act 295(4) as "any substantial action constituting placement or erection of the foundations or structures supporting a transmission line." MCL 460.1141(a) (emphasis added). Furthermore, certificates issued under Act 30 are not "siting" certificates but certificates of public convenience and necessity for proposed major transmission lines, MCL 460.562(b), and under Act 295(4), a siting certificate "is conclusive and binding as to the public convenience and necessity for that transmission line...." MCL 460.1153(5). Therefore, interpreting a siting certificate to be a construction certificate would explain why there are separate construction provisions in Act 30 that are not present in Act 295(4) and why each act uses a different type of certificate.
Furthermore, given that "siting" means placement and that "construction" is statutorily defined as "any substantial action constituting placement," construction could be interpreted as a subset of siting. This reading would satisfy the principle of statutory interpretation suggesting that construction and siting have different meanings. See United States Fidelity Ins. & Guaranty Co. v. Mich. Catastrophic Claims Ass'n, 484 Mich. 1, 14, 795 N.W.2d 101 (2009) ("If the Legislature had intended the same meaning ... it would have used the same word."). Accepting that interpretation, the application process itself is arguably "a substantial action constituting placement" and, therefore, constitutes construction. If that is true, then Act 295(4) necessarily authorizes construction because the very act of applying constitutes construction.
Finally, authorization of construction appears implicit from MCL 460.1157, which provides, "This part does not prohibit an... independent transmission company from constructing a transmission line without obtaining an expedited siting certificate." It would be legitimate to interpret the express statement that Act 295(4) does not prohibit construction of transmission lines without obtaining an expedited siting certificate to mean that construction is permitted with an expedited siting certificate. Under that reading, interpreting Act 295(4) not to permit construction would render MCL 460.1157 mere surplusage in violation of the rules of statutory interpretation. See Herald Co., Inc. v. Eastern Mich. Univ. Bd. of Regents, 475 Mich. 463, 470, 719 N.W.2d 19 (2006) (holding that courts must "interpret every word, phrase, and clause in a statute to avoid rendering any portion of the statute nugatory or surplusage").
Accordingly, we hold that the PSC's interpretation of Act 295(4) to mean that
Appellees argue that Act 295(4) has a supremacy clause that trumps the mandatory nature of Act 30. We disagree. Act 295(4) provides, in relevant part: "If the [PSC] grants an expedited siting certificate for a transmission line under this part, the certificate takes precedence over a conflicting local ordinance, law, rule, regulation, policy, or practice that prohibits or regulates the location or construction of the transmission line." MCL 460.1153(4).
"A general rule of statutory construction is that words or phrases shall be read in context and construed according to the rule of grammar and common usage." Deur v. Newaygo Sheriff, 420 Mich. 440, 445, 362 N.W.2d 698 (1984) (quotation marks and citation omitted). In MCL 460.1153(4), the context indicates that the term "local" modifies each noun in the phrase. See Hanselman v. Wayne Co. Concealed Weapon Licensing Bd., 419 Mich. 168, 180, 351 N.W.2d 544 (1984) (concluding that an introductory adjective "modifies each and every one of the subsequent units or persons and does not merely modify the word" directly following the adjective). This interpretation is also consistent with Act 30, which not only contains identical language in MCL 460.570 but also provides, "This act shall control in any conflict between this act and any other law of this state." MCL 460.563(2). If the language of MCL 460.1153(3) in Act 295(4) were actually a supremacy clause, MCL 460.563(2) would have been unnecessary in Act 30 because MCL 460.570 would have already covered that issue. Thus, MCL 460.1153(3) is not a supremacy clause that trumps Act 30. Rather, it is Act 30 that "controls" any conflict.
Appellees also assert that Act 295(4) controls over Act 30 because it is the more specific and more recently enacted statute. The rule is that "a later-enacted specific statute operates as an exception or a qualification to a more general prior statute covering the same subject matter and ... if there is an irreconcilable conflict between two statutes, the later-enacted one will control." In re Midland Publishing Co., 420 Mich. at 163, 362 N.W.2d 580. Although we agree with appellees that Act 295(4) is both more specific and the more recently enacted statute, we hold that the rule is inapplicable in this case because Act 30 explicitly states that it "shall control" in any conflict. MCL 460.563(2). Accordingly, unless and until its supremacy clause is amended, Act 30 controls regardless of whether more specific, later-enacted statutes are passed.
We conclude, then, that because Act 295(4) implicitly permits construction of wind energy transmission lines without undergoing the process in Act 30, Act 295(4) creates an exception to the mandatory nature of Act 30. Therefore, Act 295(4) revises, alters, or amends Act 30 in violation of Const. 1963, art. 4, § 25.
The parties agree that amendment by implication is an exception to Const. 1963, art. 4, § 25. See Alan v. Wayne Co., 388 Mich. 210, 200 N.W.2d 628 (1972); Nalbandian v. Progressive Mich. Ins. Co., 267 Mich.App. 7, 703 N.W.2d 474 (2005). The exception was first recognized in People v. Mahaney, 13 Mich. 481, 496
Thus, an act complete in itself will not be found to violate Const. 1963, art. 4, § 25. See also Alan, 388 Mich. at 277, 200 N.W.2d 628; Nalbandian, 267 Mich.App. at 14-15, 703 N.W.2d 474.
The Alan Court then adopted Justice POTTER'S dissent in People v. Stimer, 248 Mich. 272, 293, 226 N.W. 899 (1929), for the manner in which the determination of whether an act was complete in itself would be made:
Thus, "[i]f a bill under consideration is intended whether directly or indirectly to revise, alter, or amend the operation of previous statutes, then the constitution, unless and until appropriately amended, requires that the Legislature do in fact what it intends to do by operation." Id. at 285, 226 N.W. 899. However,
Accordingly, even though Act 295(4) violates the reenactment and publication requirements of Const. 1963, art. 4, § 25, the act is not unconstitutional if the conflict is accidental or the act meets the requirements of being an act complete in itself.
From an examination of Act 295(4), it does not appear that the conflict between Act 30 and Act 295(4) was accidental or inadvertent. Rather, Act 295(4) "quite clearly resulted from a legislative knowledge of Act 30 and an intent to abrogate that rule with respect to" specific wind energy transmission lines. Nalbandian, 267 Mich.App. at 14, 703 N.W.2d 474. Indeed, the definitions applicable to Act 295 include explicit references to and adopt definitions from Act 30. See MCL 460.1003(d); MCL 460.1007(c). The conflict between Act 295(4) and Act 30 was not the result of "`inadvertence merely,'" but a "failure to make all reasonable efforts to make clear in the statutes what [was] intended...." Alan, 388 Mich. at 286, 200 N.W.2d 628 (citation omitted). Because the Legislature intended to amend Act 30, it was required to comply with the "plain and unequivocal requirements of ... Const. 1963, art. 4, § 25." Id. at 275, 200 N.W.2d 628.
Appellees' reliance on Alan, 388 Mich. at 282, 200 N.W.2d 628, to argue that reenactment and publication was unnecessary because it would have been absurd and unduly burdensome is similarly unavailing. Appellees rely on the following quote from Alan:
However, the very next paragraph in Alan refuted this position and, in fact, adopted the position of the dissent in Stimer. Alan, 388 Mich. at 282-283, 200 N.W.2d 628. The Supreme Court then went on to note "further reasons why the objection that it will be hard work to comply with the constitution is not well taken," including technological advances in printing and copying and the Legislature's "own sophisticated bill drafting and research services...." Id. at 283-284, 200 N.W.2d 628.
We also hold that Act 295 is not complete in itself. Comparing its provisions with the prior laws left in force, i.e. Act 30, Act 295 is not "complete on the subject with which it deals[.]" Alan, 388 Mich. at 279, 200 N.W.2d 628 (quotation marks and citations omitted). Appellees contend that Act 295(4) is complete on the subject with which it deals because it only deals with transmission lines for electricity generated by wind energy conversion. Appellants argue that Act 295(4) deals with transmission lines and, because transmission lines are already addressed under Act 30, Act 295(4) is simply an amendment of Act 30. Both of these arguments miss the mark because they have limited their focus to Act 295(4). The relevant inquiry is whether the act, i.e. Act 295 in its entirety, is complete in itself.
Nevertheless, even if the focus is limited to Act 295(4) and its purpose is defined as appellees argue, the act is still not complete by its own terms because Act 295(4) is optional. Act 295(4) provides that construction of transmission lines is not precluded without an expedited siting certificate. MCL 460.1157. That means there is a mechanism other than Act 295(4) for permitting construction of transmission lines. Indeed, companies can use Act 30 to construct transmission lines, even for those delivering electricity from wind energy
Appellants suggest that the Legislature intended to require companies proceeding under Act 295(4) to also comply with the provisions of Act 30. However, "the so-called `absurd-results rule' applies in Michigan." Detroit Int'l Bridge Co. v. Commodities Export Co., 279 Mich.App. 662, 664, 760 N.W.2d 565 (2008). "[A] statute should be construed to avoid absurd results that are manifestly inconsistent with the legislative intent...." Id. at 674, 760 N.W.2d 565 (quotation marks and citations omitted). Put another way, "a statute need not be applied literally if no reasonable lawmaker could have conceived of the ensuing result." Id. at 675, 760 N.W.2d 565. Considering Act 295 in its entirety, we conclude that it was intended to issue certificates to companies that would permit them to begin construction on transmission lines to harness wind energy in an expedited manner, so that companies could meet their renewable energy requirements by the 2015 deadline. See MCL 460.1027.
The interpretation suggested by appellants, that a company must still comply with Act 30 after completing the process under Act 295(4), eliminates any benefit for proceeding under Act 295(4) and results in the "expedited" process taking up to 18 months, while the traditional process takes 12 months at the most. Appellants assert that the process is not necessarily longer because the two processes can be implemented simultaneously, or the Act 30 process could be started first. However, there is no logical reason why a company would ever use Act 295(4) if Act 30 is still required. Act 30 permits construction once a certificate of public convenience and necessity has been obtained, MCL 460.565, but a siting certificate under Act 295 "is conclusive and binding as to the public convenience and necessity for that transmission line...." MCL 460.1153(5). Thus, having to comply with both Act 295(4) and Act 30 wastes the time and money of both the applicant company and the PSC and provides nothing of value to either the company or the public that cannot be achieved by moving forward solely under Act 30. Rather, the result of each process is a certificate regarding public convenience and necessity, only one of which actually permits construction. Accordingly, even if the process could be structured so that compliance with both acts did not take any longer than simply moving forward under Act 30, Act 295(4) would still be rendered superfluous because no company would ever use it. Therefore, we conclude that the interpretation suggested by appellants constitutes an absurd result that is manifestly inconsistent with the legislative intent. The absurd-results rule, however, cannot render an unconstitutional act constitutional. Rather, it will simply prevent the absurd result.
Thus, although we conclude that the PSC's interpretation of Act 295(4) to permit construction with the issuance of an expedited siting certificate was both reasonable and consistent with the legislative intent, that interpretation creates an exception to the mandatory provisions in Act 30 in violation of Const. 1963, art. 4, § 25. Furthermore, this Court is obligated, when possible, to construe apparently conflicting statutes in a manner that gives each statute full force and effect, In re Midland Publishing Co., 420 Mich. at 163, 362 N.W.2d 580, and to do so in a manner that does not render either statute unconstitutional, Taylor, 468 Mich. at 6, 658 N.W.2d 127.
There is an interpretation of Act 295 and Act 30 that would give each full force and effect without violating the Constitution: A company that obtains a siting certificate under Act 295 must also obtain a certificate of public convenience and necessity under Act 30 before beginning construction. Even though this interpretation appears contrary to the legislative intent and violates the absurd-results rule, neither of these doctrines can render an unconstitutional provision constitutional. The only way to interpret the statutes harmoniously without rendering Act 295 unconstitutional is to conclude that, regardless of whether a siting certificate is obtained under Act 295, Act 30 mandates compliance with its provisions (relating to public convenience and necessity) before construction can commence. Accordingly, we so hold.
Having concluded that there is only one interpretation of Act 295(4) that renders it constitutional, we are, nevertheless, mindful of the effect of our decision. There is no question in our minds that the Legislature did not intend this result, but correcting the unintended result rests with the Legislature. Even so, after taking into account all the circumstances confronting this Court, we conclude that our decision should have only prospective application.
"Although the general rule is that judicial decisions are given full retroactive effect, a more flexible approach is warranted where injustice might result from full retroactivity." Pohutski v. City of Allen Park, 465 Mich. 675, 695-696, 641 N.W.2d 219 (2002) (citations omitted). The threshold question is "whether the decision clearly established a new principle of law." Id. at 696, 641 N.W.2d 219. If so, there are three factors to be considered in determining whether a decision should not have retroactive application: "(1) the purpose to be served by the new rule, (2) the extent of reliance on the old rule, and (3) the effect of retroactivity on the administration of justice." Id.
Although this opinion interprets Act 295(4) in the only manner possible without rendering it unconstitutional, because that result is both absurd and clearly contrary to the intent of the Legislature, "our holding is akin to the announcement of a new rule of law," particularly given the erroneous, albeit reasonable, interpretation adopted by the PSC. Id. Having passed the threshold question, application of the three-part test is appropriate and leads us to conclude that prospective application is appropriate here.
First, the purpose of the new rule is to correct an error in the interpretation of Act 295(4) in order to prevent it from being rendered unconstitutional. We believe this purpose would best be furthered by applying it only to applications made under Act 295(4) after this opinion's date.
Second, we take into account that ITC and unknown other companies relied on the reasonable assumption, and the PSC's ruling, that construction was authorized under Act 295(4) without also having to comply with the requirements of Act 30. Indeed, ITC has already invested at least $110 million in constructing this project in accordance with the PSC's order, which is prima facie lawful and reasonable. See MCL 462.25; Great Wolf Lodge, 489 Mich. at 37-38, 799 N.W.2d 155. Monopoles have been placed, wires strung, and substations built and dedicated. Prospective-only application recognizes that these actions were taken in reliance on that interpretation.
Third, prospective application minimizes the effect of this decision on the administration of justice. Retroactive application could result in additional litigation as the parties attempt to determine whether ITC's completed construction can remain and whether ongoing construction must be stopped. Prospective application eliminates these uncertainties as well as prevents tying up PSC resources on duplicative reconsideration of evidence under Act 30 in cases that have already been thoroughly considered under Act 295(4) and in which construction has already begun. In addition, it provides the Legislature the opportunity to fix the absurd result created by this required interpretation without placing the energy companies at a disadvantage by stopping the ongoing construction of transmission lines that are necessary to help them meet the 2015 deadline for green energy mandates while time and money are spent on duplicative efforts under Act 30.
Accordingly, this decision shall have immediate effect pursuant to MCR 7.215(F)(2) and shall apply only to applications brought under Act 295(4) on or after the date of this opinion.
Appellants also assert that the PSC erroneously concluded that the transmission line proposed by ITC was of an "appropriate capability" as required by MCL 460.1153(3)(d), which provides, "The proposed transmission line will be of appropriate capability to enable the wind potential of the wind energy resource zone to be realized." The PSC stated:
We conclude that the PSC's interpretation is consistent with the language of MCL 460.1153(3)(d). Contrary to appellants' positions, the PSC did not equate "appropriate capability" with maximum. Indeed, because ITC's proposed transmission line has a 5,000 MW capacity, it exceeds the maximum estimate. The PSC also explained that preventing duplicative efforts and costs from piecemeal construction and not building to a size that could become overloaded were considerations for determining what capability was appropriate.
ABATE argues that the PSC erred by declining to determine that appropriate capability means the minimum capacity, not the maximum capacity. However, this contention is at odds with ABATE's own reasoning. If it is erroneous for the PSC to read "maximum" into the statute, then it is equally erroneous for it to read "minimum" into the statute. Furthermore, interpreting the "appropriate capability" to be the minimum wind potential is contrary to MCL 460.1153(3)(d). which requires the line "to enable the wind potential of the wind energy resource zone to be realized." Because the wind potential in Region 4 is a range that goes significantly higher than the minimum, a transmission line built only to handle the minimum wind potential would not enable the wind potential to be realized, only some wind capability. Notably, the minimum and maximum numbers were simply estimates. Thus, there is at least some possibility that more power could be generated. Therefore, the PSC's decision to require the capacity to be greater than the estimated maximum makes sense.
MPPA and MMEA argue that "wind potential" means the amount of wind power reasonably expected to be realized. However, this definition inserts language into the statute that is not there. MCL 460.1153(3)(d) requires an appropriate capacity for "the wind potential [of Region 4] to be realized." MPPA and MMEA attempt to insert a reasonability requirement that does not exist and then attempt to define what would be reasonable. Again, the statute does not authorize a transmission line that will realize some, most, or even a reasonably anticipated amount of wind potential. It says the line must be capable of enabling the realization of the wind potential. Any number less than the maximum estimated capacity arguably fails to meet this standard.
Finally, appellants' argument that the capacity is too large because it exceeds the 10 percent renewable energy standard is meritless. Appellants have ignored the PSC's basis for rejecting that argument — that the 10 percent figure represents a floor, not a ceiling. Indeed, MCL 460.1027(1) explicitly provides that companies meeting or exceeding certain size thresholds "shall achieve a renewable energy capacity portfolio of not less than" the specified amounts. Thus, the fact that ITC's transmission line would exceed the 10 percent requirement is in keeping with the Legislature's mandate of a 10 percent minimum.
Accordingly, appellants have failed to provide a cogent reason to overrule the
Finally, ABATE argues that the PSC's conclusion that the route was both feasible and reasonable was erroneous because a letter from the Department of Agriculture indicated disagreement with ITC's position that the transmission lines would have no impact on land that was enrolled in the state's farmland preservation program and because they were concerned that property in the transmission line route might "be acquired via some other property interest other than an easement." We decline to consider this issue because it is unpreserved and abandoned.
ABATE not only never argued before the PSC about the specific letter from the Department of Agriculture, but it never argued any grounds to the PSC for concluding that the route was not feasible or reasonable. In addition, there is no evidence that the PSC even considered the letter on which ABATE rests its argument. The letter was not marked as received by the PSC until February 1, 2011, long after the December 1, 2010, close of the evidentiary record and only 24 days before the PSC issued its order. Finally, ABATE has not cited a single legal authority for its argument. "A party may not simply announce its position and then leave it to this Court to discover and rationalize the basis for its claims. Furthermore, a party may not give an issue cursory treatment with little or no citation of supporting authority." In re Application of Ind. Mich. Power Co., 275 Mich.App. 369, 376, 738 N.W.2d 289 (2007) (citations omitted). Accordingly, this issue has been abandoned. Id., citing Yee v. Shiawassee Co. Bd. of Comm'rs, 251 Mich.App. 379, 406, 651 N.W.2d 756 (2002).
We hold that the PSC properly issued the siting certificate to ITC, but that it erroneously concluded that construction was authorized by the certificate. The only way to interpret Act 295 harmoniously with Act 30 that does not render Act 295 unconstitutional is to conclude that, regardless of whether a siting certificate is obtained under Act 295, Act 30 mandates compliance with its provisions before construction can commence. Nevertheless, after consideration of the effects of this decision, we hold that this decision is limited to prospective application. Therefore, we affirm the result of the PSC's order in this case.
FITZGERALD, P.J., and METER and BOONSTRA, JJ., concurred.