MAXA, J.
¶ 1 Snohomish County, King County, and the Building Industry Association of Clark County (collectively, appellants) appeal the Pollution Control Hearings Board's (Board) order holding that condition S5.C.5.a.iii in the 2013-2018 Phase I Municipal Stormwater Permit (the 2013-2018 Permit) issued by the Washington Department of Ecology (Ecology) does not violate the vested rights of property developers. The 2013-2018 Permit requires Phase I permittees, which include certain counties and cities, to adopt by June 30, 2015 regulations for controlling stormwater drainage and runoff to municipal stormwater sewer systems for new development, redevelopment, and construction activities. Condition S5.C.5.a.iii provides that the new regulations will apply to all development applications submitted after July 1, 2015 and submitted before July 1, 2015 if construction is not started by June 30, 2020.
¶ 2 The statutory vested rights doctrine provides that a land use application generally must be considered under the zoning or other land use control ordinances in effect at the time the application was submitted. The appellants argue that enforcement of condition S5.C.5.a.iii would require permittees to violate the vested rights of developers because
¶ 3 Ecology and Puget Soundkeeper Alliance (PSA) (collectively, Ecology) argue, and the Board ruled, that the 2013-2018 Permit would not require permittees to violate the vested rights doctrine because the required regulations are environmental regulations, not land use control ordinances. They also argue that even if the regulations are land use control ordinances, federal law preempts Washington's vested rights statutes.
¶ 4 We hold that (1) the 2013-2018 Permit's required stormwater regulations are "land use control ordinances" under the vested rights statutes, (2) enforcement of condition S5.C.5.a.iii would violate the statutory vested rights of developers who submit applications before July 1, 2015 but do not begin construction until after June 30, 2020, and (3) federal law does not preempt Washington's vested rights statutes. Accordingly, we reverse the Board's order and remand to the Board to direct Ecology to revise condition S5.C.5.a.iii to specify that the 2013-2018 Permit applies only to those completed applications submitted after July 1, 2015.
¶ 5 The federal Clean Water Act (CWA)
¶ 6 In August 2012, Ecology issued the 2013-2018 Phase I Municipal Stormwater Permit.
¶ 7 Ecology implements the 2013-2018 Permit at the local level by mandating that each local permittee be responsible for compliance with the 2013-2018 Permit's terms. The 2013-2018 Permit requires all permittees to create a stormwater management program. That program must include the enactment of local ordinances or other governing documents regulating development within each permittee's jurisdiction. The 2013-2018 Permit requires several conditions that permittees must implement through their ordinances. Condition S5.C.5 is one such condition.
¶ 8 Condition S5.C.5 focuses on preventing and controlling stormwater runoff from new development, redevelopment, and construction activities. This condition applies to those projects that meet certain thresholds specified in Appendix 1 of the 2013-2018
¶ 9 Condition S5.C.5 includes a lengthy set of minimum performance measures, one of which includes site and subdivision scale requirements implementing the "[m]inimum [r]equirements, thresholds, and definitions" in Appendix 1 of the 2013-2018 Permit for new development, redevelopment, and construction sites. Site and subdivision scale requirements that developers must implement include preparing stormwater site plans; drafting stormwater pollution prevention plans; utilizing all known, available, and reasonable source control best management practices; maintaining natural drainage patterns to the maximum extent practicable; and implementing on-site stormwater management best management practices to the extent feasible in various contexts. In addition, certain projects trigger additional minimum requirements that developers must comply with. These include constructing stormwater treatment facilities to treat stormwater runoff, implementing flow control standards to reduce the impacts of stormwater runoff, ensuring that projects draining into wetlands comply with various guide sheets and construction restrictions, and maintaining an operation and maintenance manual.
¶ 10 Condition S5.C.5.a.iii provides that permittees must adopt and make effective a stormwater management program that meets the 2013-2018 Permit requirements no later than June 30, 2015. The second sentence of the condition addresses the applicability of the new program to development projects:
Certified Appeal Board Record (CABR) at 27 (emphasis added) (footnotes omitted).
¶ 11 Snohomish County, King County, Pierce County, Clark County, and the Building Industry Association of Clark County appealed the 2013-2018 Permit to the Board.
¶ 12 In October 2013, the Board issued a summary judgment order ruling that the 2013-2018 Permit's requirements were environmental regulations and therefore that condition S5.C.5.a.iii did not violate Washington's vested rights doctrine or finality doctrine. The Board stated that it "has consistently ruled that the requirements imposed by NPDES stormwater permits are not land use control ordinances that are subject to state vesting laws." Clerk's Papers (CP) at 56. Moreover, the Board rejected the notion that the doctrines of vested rights and finality of land use decisions could control and limit the application of state and federal water quality requirements.
¶ 13 However, the Board's summary judgment order did require Ecology to modify the second sentence of condition S5.C.5.a.iii. The Board directed Ecology to replace the phrase "projects approved" with "application submitted."
¶ 14 Following a trial on the remaining issues in the case, the Board issued its final decision and order. The appellants separately appealed the Board's October 2013 decision to the Thurston County Superior Court.
¶ 15 The Administrative Procedures Act (APA) governs our review of Board decisions. See RCW 34.05.570(1)(b); Cornelius v. Dep't of Ecology, 182 Wn.2d 574, 584-85, 344 P.3d 199 (2015). We apply the APA to the administrative record. Cornelius, 182 Wash.2d at 585, 344 P.3d 199. We may grant relief from an order based on several reasons listed in RCW 34.05.570(3), including that the order is (1) outside the statutory authority of the agency, and (2) based on an erroneous interpretation or application of the law. RCW 34.05.570(3)(b), (d). The burden of demonstrating the invalidity of agency action is on the party asserting invalidity. RCW 34.05.570(1)(a).
¶ 16 We review questions of law de novo. Cornelius, 182 Wash.2d at 585, 344 P.3d 199. When a statute is ambiguous and falls within Ecology's area of expertise, we give great weight to Ecology's interpretation if it is consistent with the statutory language. Clark County v. Rosemere Neigh. Ass'n, 170 Wn.App. 859, 871, 290 P.3d 142 (2012). However, we are not bound by an agency's interpretation of a statute. See RCW 34.05.570(3)(d); see also. Postema v. Pollution Control Hr'gs Bd., 142 Wn.2d 68, 77, 11 P.3d 726 (2000). The Board's order was made on summary judgment, which we also review de novo. Cornelius, 182 Wash.2d at 585, 344 P.3d 199.
¶ 17 The appellants challenge the second sentence of condition S5.C.5.a.iii, which requires permittees to apply the new stormwater regulations to property development applications filed before July 1, 2015 if construction on those projects has not started by June 30, 2020. The appellants focus specifically on the application of the new stormwater regulations to local building permit and subdivision applications and development agreements. They argue that condition S5.C.5.a.iii conflicts with the statutory vested rights doctrine. We agree.
¶ 18 The vested rights doctrine generally provides that certain land development applications must be processed under the land use regulations in effect when the application was submitted, regardless of subsequent changes to those regulations. Town of Woodway v. Snohomish County, 180 Wn.2d 165, 172-73, 322 P.3d 1219 (2014). Development rights "vest" on a date certain — when a complete development application is submitted. Id. The purpose of the vested rights doctrine is to provide certainty to developers and to provide some protection against fluctuating land use policy. Noble Manor Co. v. Pierce County, 133 Wn.2d 269, 278, 943 P.2d 1378 (1997). The doctrine recognizes that development rights are valuable property interests and ensures that new land use regulations do not interfere with those rights. Town of Woodway, 180 Wash.2d at 173, 322 P.3d 1219.
¶ 19 The vested rights doctrine originated at common law, but the legislature has codified the doctrine with regard to building permits (RCW 19.27.095(1)), subdivision applications (RCW 58.17.033(1)), and development agreements (RCW 36.70B.180).
¶ 20 The issue here is whether the 2013-2018 Permit's required stormwater regulations constitute "other land use control ordinances" under RCW 19.27.095(1) and RCW 58.17.033(1) and/or "development standard[s] or regulation[s]" under RCW 36.70B.180. If so, the statutory vested rights doctrine applies to those stormwater regulations. If not, the vested rights doctrine does not apply.
¶ 21 Determining whether the statutory vested rights doctrine applies to the 2013-2018 Permit's required stormwater regulations involves the interpretation of the pertinent statutory language. Statutory interpretation is a matter of law that we review de novo. Jametsky v. Olsen, 179 Wn.2d 756, 761, 317 P.3d 1003 (2014).
¶ 22 The goal of statutory interpretation is to determine and give effect to the legislature's intent. Id. at 762, 317 P.3d 1003. To determine legislative intent, we first look to the plain language of the statute. Id. We consider the language of the provision in question, the context of the statute in which the provision is found, and related statutes. Protect the Peninsula's Future v. Growth Mgmt. Hr'gs Bd., 185 Wn.App. 959, 969, 344 P.3d 705 (2015). Undefined terms are given their plain and ordinary meaning, which can be derived from a dictionary. Estate of Haselwood v. Bremerton Ice Arena, Inc., 166 Wn.2d 489, 498, 210 P.3d 308 (2009). If a statute is unambiguous, we apply the statute's plain meaning as an expression of legislative intent without considering other sources of such intent. Jametsky, 179 Wash.2d at 762, 317 P.3d 1003.
¶ 23 If the plain language of the statute is susceptible to more than one reasonable interpretation, the statute is ambiguous. Id. We resolve ambiguity by considering other indications of legislative intent, including principles of statutory construction, legislative history, and relevant case law. Id.
¶ 24 RCW 19.27.095(1) and RCW 58.17.033(1) both provide that building permit and land division applications must be considered under the "zoning or other land use control ordinances" in effect at the time the application is submitted. Neither statute defines the term "land use control ordinance." However, the appellants rely on Washington cases that do define the term and on this court's holding in Westside Business Park, LLC v. Pierce County, 100 Wn.App. 599, 607, 5 P.3d 713 (2000) to support their contention that stormwater drainage ordinances are land use control ordinances.
¶ 25 In New Castle Investments v. City of LaCenter, this court first discussed the meaning of "land use control ordinance" in RCW 58.17.033(1). 98 Wn.App. 224, 228, 989 P.2d 569 (1999). We focused on the word "control," which is defined in part as "`[t]he ability to exercise a restraining or directing influence over something.'" Id. at 229, 989 P.2d 569 (quoting BLACK'S LAW DICTIONARY 329 (6th ed.1990)). Accordingly, we suggested that a land use control ordinance was one that "exercise[d] a restraining or directing influence over land use." New Castle, 98 Wash.App. at 229, 989 P.2d 569. This court subsequently adopted this definition of land use control ordinance in Westside, 100 Wash.App. at 607, 5 P.3d 713. Division One of this court also has adopted this definition. Graham Neigh. Ass'n v. F.G. Assocs., 162 Wn.App. 98, 115, 252 P.3d 898 (2011).
Id. at 237, 989 P.2d 569 (quoting Lincoln Shiloh Assocs. v. Mukilteo Water Dist., 45 Wn.App. 123, 128, 724 P.2d 1083 (1986)). We concluded:
Id. at 237-38, 989 P.2d 569.
¶ 27 In Westside, we addressed an issue very similar to the one here — whether an ordinance imposing increased stormwater drainage requirements was a land use control ordinance subject to the vesting rights provision of RCW 58.17.033. 100 Wash.App. at 602, 5 P.3d 713. After relying on New Castle to define "land use control ordinance" as an ordinance that exerts a restraining or directing influence over land use, we stated:
Westside, 100 Wash.App. at 607, 5 P.3d 713 (emphasis added).
¶ 28 We also relied on Phillips v. King County, 136 Wn.2d 946, 963, 968 P.2d 871 (1998), where the Supreme Court stated that the vested rights doctrine applied to surface water drainage regulations. Westside, 100 Wash.App. at 607, 5 P.3d 713. We stated that "because the Phillips court plainly considered whether surface water drainage ordinances are within the ambit of the vested rights doctrine, ... we are not prepared to say that storm water drainage ordinances are not subject to the vesting rule." Id. at 607-08, 5 P.3d 713.
¶ 29 Ecology essentially ignores Westside. And PSA argues that the discussion in Westside regarding the definition of "land use control ordinance" is dicta and the case neither controls nor is informative here because the deciding issue was the adequacy of an application to invoke vesting.
¶ 30 Here, there is no indication that the effect of the stormwater regulations the 2013-2018 Permit requires would be appreciably different than the stormwater drainage ordinances discussed in Westside. Therefore, in the absence of some reason to treat the regulations adopted pursuant to the 2013-2018 Permit differently than other stormwater drainage ordinances, we hold that Westside is controlling authority.
¶ 32 Ecology argues that stormwater regulations adopted as required in the 2013-2018 Permit are not land use control ordinances for several reasons. First, Ecology argues that because the 2013-2018 Permit's required regulations are environmental regulations, they cannot be considered land use control ordinances. Ecology points out that the purpose of the regulations adopted pursuant to the 2013-2018 Permit is to control pollution discharges, not control the use of land. The Board's summary judgment order also focused on the purpose of the regulations at issue:
CP at 57-58.
¶ 33 Ecology's argument seems to be based on the assumption that a regulation can either be an environmental regulation or a land use control regulation, but not both. However, Ecology does not cite any case authority for this proposition. And several cases address the application of the vested rights doctrine to regulations that can be classified as "environmental." See, e.g., Lauer v. Pierce County, 173 Wn.2d 242, 258-263, 267 P.3d 988 (2011) (watercourse buffer regulations); Phillips, 136 Wash.2d at 951, 968 P.2d 871 (water drainage regulations); Julian v. City of Vancouver, 161 Wn.App. 614, 619, 626-28, 255 P.3d 763 (2011) (riparian buffer regulations); Westside, 100 Wash.App. at 601, 5 P.3d 713 (storm drainage regulations adopted in part as a response to the CWA). Nothing in Washington case law suggests that simply characterizing a land use control ordinance as an environmental ordinance limits the application of the vested rights doctrine.
¶ 34 Ecology emphasizes that the Board has held that NPDES permit requirements do not constitute land use control ordinances. See Rosemere Neigh. Ass'n. v. Dep't of Ecology & Clark County, No. 10-103, 2010 WL 3420570 (Wash. Pollution Control Hr'gs Bd. Aug. 26, 2010), affirmed, Clark County v. Rosemere Neigh. Ass'n, 170 Wn.App. 859, 875-76, 290 P.3d 142 (2012) (refraining from addressing the legal vesting issue); Cox v. Dep't of Ecology, No. 08-077, 2009 WL 542494 (Wash. Pollution Control Hr'gs Bd. Feb. 26, 2009). However, we are not bound by an agency's interpretation of a statute. Postema, 142 Wash.2d at 77, 11 P.3d 726. Here, the Board's rulings are inconsistent with the language of the vested rights statutes, which do not carve out an exception for environmental regulations, and applicable case law.
¶ 35 Second, Ecology quotes language from New Castle that "`[t]he vested rights rule is generally limited to those laws which can loosely be considered `zoning' laws.'" 98 Wash.App. at 232, 989 P.2d 569 (quoting
¶ 36 Third, Ecology argues that the purpose of the vested rights doctrine is only to limit the exercise of municipal discretion, rather than limiting the state's ability to implement environmental regulations necessary to comply with state and federal water pollution laws. Ecology relies on Erickson & Assocs., Inc. v. McLerran, where the Supreme Court recognized that:
123 Wn.2d 864, 873, 872 P.2d 1090 (1994) (quoting West Main Assocs. v. City of Bellevue, 106 Wn.2d 47, 51, 720 P.2d 782 (1986)). Ecology states that permittees do not exercise municipal discretion when they implement environmental conditions imposed by the state to meet water pollution laws.
¶ 37 However, Erickson does not stand for the proposition that the vested rights doctrine applies only to limit municipal discretion and cannot apply to environmental requirements enacted pursuant to state direction. The language quoted above addressed an ordinance that determined the vesting date of certain permits, not land use control ordinances. Erickson, 123 Wash.2d at 869-71, 872 P.2d 1090. And Ecology cites to no authority holding that the vested rights statutes do not apply to local regulations that are state mandated.
¶ 38 Fourth, Ecology argues that controlling water pollution is an exercise of a local municipality's police powers, which extinguishes a developer's vested right. Ecology quotes a 1905 case stating that "[t]here is no such thing as an inherent or vested right to imperil the health or impair the safety of the community." City of Seattle v. Hinckley, 40 Wn. 468, 471, 82 P. 747 (1905). Ecology also relies on Rhod-A-Zalea & 35th, Inc. v. Snohomish County, 136 Wn.2d 1, 6, 959 P.2d 1024 (1998), where the Supreme Court addressed whether a nonconforming peat mining operation was subject to a county's police power regulations enacted for the health, safety, and welfare of the community. The court held that the peat mining operation was subject to subsequent police power regulations and that local governments may "preserve, regulate and even, within constitutional limitations, terminate nonconforming uses." Id. at 8, 959 P.2d 1024. Ecology emphasizes that the court suggested that a nonconforming factory would not be exempt from later enacted pollution regulations. Id. at 15, 959 P.2d 1024.
¶ 39 However, Ecology did not argue below that the stormwater regulations may be enacted pursuant to a municipality's police powers. And the Board did not address this issue. Therefore, whether a local municipality could impose police power conditions on a development application is not before us.
¶ 40 Fifth, Ecology argues that it could require permittees to use their authority under SEPA to enforce stormwater discharge regulations. SEPA regulations are exempt from the vested rights doctrine. RCW 19.27.095(6); RCW 58.17.033(3). However, once again Ecology did not argue below that it was requiring permittees to enact regulations pursuant to SEPA. And the Board did not base its decision on SEPA. Therefore, whether a local municipality could enact certain regulations under SEPA that would not be subject to the vested rights doctrine is not before us.
¶ 41 Sixth, Ecology argues that applying the vested rights doctrine here would conflict with the legislature's intent, expressed in RCW 90.48.010, to "maintain the highest possible standards to insure the purity of all waters of the state ..., and to that end require the use of all known available and reasonable methods by industries and others" to control water pollution. However, as noted above, RCW 19.27.095(6) and RCW 58.17.033(3) do not contain any exception for environmental regulations. And Ecology has not cited to any expression of a legislative intent to have NPDES permit requirements supersede the vested rights doctrine. Further, to the extent that RCW 90.48.010 and the vested rights statutes conflict, the more general policy statement in RCW 90.48.010 must yield to the more specific vested rights statutes. See Ass'n of Wash. Spirits & Wine Distribs. v. Wash. State Liquor Control Bd., 182 Wn.2d 342, 356, 340 P.3d 849 (2015)(a general statutory provision must yield to a more specific provision).
¶ 42 Under a plain reading of RCW 19.27.095(1) and RCW 58.17.033(1), in combination with our case law interpreting these provisions, regulations enacting the 2013-2018 Permit requirements constitute local land use ordinances because the regulations will restrain and direct the use of land. Because development rights vest upon filing a completed building or land division application, condition S5.C.5.a.iii conflicts with the vested rights doctrine as stated in RCW 19.27.095(1) and RCW 58.17.033(1) because it could require a permittee to enforce regulations adopted after development rights had been vested. Accordingly, we hold that condition S5.C.5.a.iii of the 2013-2018 Permit is invalid.
¶ 43 RCW 36.70B.180 provides that a development agreement is not subject to an amended or new "zoning ordinance or development standard or regulation adopted after the effective date of the agreement." The statute does not define "development standard or regulation." And there are no cases or statutes that define this term. However, the ordinary meaning of "development regulation" is a regulation that affects the development of land. Using this meaning, there is no reason to interpret development regulation differently than land use control ordinance. Similarly, the ordinary meaning of "development standards" is a standard that affects the development of land. Although "standard" may have a narrower meaning than "regulation," again there is no reason to interpret development standards differently than land use control ordinances.
¶ 44 We hold that under a plain reading of RCW 36.70B.180, local regulations enacting the 2013-2018 Permit requirements constitute development regulations and development standards. Accordingly, we hold that condition S5.C.5.a.iii conflicts with the vested rights doctrine as stated in RCW 36.70B.180, and therefore is invalid.
¶ 45 We hold that condition S5.C.5.a.iii of the 2013-2018 Permit conflicts with RCW 19.27.095(1), RCW 58.17.033(1), and RCW 36.70B.180. The appellants contend that this
¶ 46 An administrative regulation that conflicts with a statute is invalid. See Cannabis Action Coal. v. City of Kent, 180 Wn.App. 455, 481, 322 P.3d 1246 (2014). Such a conflict exists when an ordinance permits what state law forbids or forbids what state law permits. Id. at 482, 322 P.3d 1246. "`The conflict must be direct and irreconcilable with the statute, and the ordinance must yield to the statute if the two cannot be harmonized.'" Id. (quoting City of Tacoma v. Luvene, 118 Wn.2d 826, 835, 827 P.2d 1374 (1992)).
¶ 47 Here, condition S5.C.5.a.iii requires that permittees apply the new 2013-2018 Permit requirements to completed building and subdivision permit applications and executed development agreements that were submitted before July 1, 2015 that have not started construction by June 30, 2020. The vesting rights statutes provide that certain land development projects must be processed under the land use or development regulations in effect at the time the completed building or land division application is submitted or the effective date of the development agreement regardless of when construction starts. Therefore, there is a direct conflict between the condition and the statutory provisions because condition S5.C.5.a.iii requires imposition of new regulations on those applications and agreements that had development rights vested before the new regulations were adopted.
¶ 48 The proper remedy is to reverse the Board's order and remand to the Board to direct Ecology to revise condition S5.C.5.a.iii to specify that the 2013-2018 Permit applies only to those completed applications submitted after permittees adopted the new Permit requirements. See Puget Soundkeeper Alliance v. State, 189 Wn.App. 127, 131, 152, 356 P.3d 753 (2015) (reversing Board order and remanding to Ecology to revise permit condition).
¶ 49 Ecology argues that even if Washington's vested right doctrine applies to the 2013-2018 Permit's required regulations, the federal CWA preempts that doctrine. Ecology contends that preemption applies here because the application of the vested rights doctrine to the 2013-2018 Permit requirements would prevent accomplishing the purposes and objectives of Congress. We disagree and hold that the CWA does not preempt Washington's vested rights doctrine.
¶ 50 The Supremacy Clause of the United States Constitution gives the federal government the power to preempt state law. Hillman v. Maretta, ___ U.S. ___, 133 S.Ct. 1943, 1949, 186 L.Ed.2d 43 (2013). "Conflict preemption" occurs when (1) federal and state laws conflict, making compliance with both an impossibility, or (2) state law "`stands as an obstacle to the accomplishment and execution of the full purposes and objectives of Congress.'" Id. at 1950 (quoting Hines v. Davidowitz, 312 U.S. 52, 67, 61 S.Ct. 399, 85 L.Ed. 581 (1941)). "[S]tate laws are not superseded by congressional legislation unless that is the clear and manifest purpose of Congress." McKee v. AT & T Corp., 164 Wn.2d 372, 387, 191 P.3d 845 (2008). Courts should not seek out conflict where none actually exists. Chevron U.S.A., Inc. v. Hammond, 726 F.2d 483, 499 (9th Cir.1984).
¶ 51 Significantly, there is a strong presumption against preemption under Washington law. Nw. Wholesale, Inc. v. Pac Organic Fruit, LLC, 184 Wn.2d 176, 184, 357 P.3d 650 pet. for cert. filed sub nom. Ostenson v. Holzman, No. 15-763 (U.S. Dec. 9, 2015). "Preemption is the exception, not the rule in Washington." Hisle v. Todd Pac. Shipyards Corp., 151 Wn.2d 853, 864, 93 P.3d 108 (2004).
¶ 52 We review federal preemption issues de novo. Wal-Mart Stores, Inc. v. United Food & Commercial Workers Int'l Union, 190 Wn.App. 14, 21, 354 P.3d 31 (2015).
¶ 53 Washington's vested rights doctrine does not directly conflict with the CWA. The CWA does not provide that state agencies must require local municipalities to enact certain stormwater regulations applicable to land development. Instead, Congress has delegated implementation of general pollution control guidelines to the states. As a result, the requirements of condition S5.C.5.a.iii reflect Ecology's interpretive choices meant to effectuate a framework of federal and state environmental guidelines. Further, there is no counterpart to condition S5.C.5.a.iii in the CWA. And nothing in the CWA requires that stormwater regulations be applied within a set deadline. Accordingly, we hold that the CWA does not directly conflict with Washington's vested rights doctrine.
¶ 54 Ecology argues that the second prong of conflict preemption applies here. To determine whether this prong applies, we must determine the purposes and objectives of Congress that are embodied in the CWA and determine whether the vested rights doctrine stands as an obstacle to the accomplishment of those objectives. Beatty v. Fish & Wildlife Comm'n, 185 Wn.App. 426, 454, 341 P.3d 291, review denied, 183 Wn.2d 1004, 349 P.3d 856 (2015). "The obstruction strand of conflict preemption focuses on both the objective of the federal law and the method chosen by Congress to effectuate that objective." McKee, 164 Wash.2d at 388, 191 P.3d 845.
¶ 55 The CWA is a comprehensive water quality statute with the stated goal of "restor[ing] and maintain[ing] the chemical, physical, and biological integrity of the Nation's waters" and achieving or maintaining "water quality which provides for the protection and propagation of fish, shellfish, and wildlife." 33 U.S.C. § 1251(a)(2). Under the statute, the administrator of EPA is charged with the responsibility of "establish[ing] and enforc[ing] technology-based limitations on individual discharges into the country's navigable waters from point sources." PUD No. 1 of Jefferson County v. Wash. Dep't of Ecology, 511 U.S. 700, 704, 114 S.Ct. 1900, 128 L.Ed.2d 716 (1994) (citing 33 U.S.C. §§ 1311, 1314). The states also are required to provide water quality standards, which may be more stringent than the federal standards but cannot be less protective than the federal standards. Jefferson County, 511 U.S. at 705, 114 S.Ct. 1900; 33 U.S.C. § 1370.
¶ 56 The key provision of the CWA regarding stormwater pollution is 33 U.S.C. § 1342(p)(3)(B)(iii), which states that permits issued for discharges from municipal storm sewers "shall require controls to reduce the discharge of pollutants to the maximum extent practicable." Ecology argues that the stormwater requirements in the 2013-2018 Permit will reduce the discharge of pollutants to the maximum extent practicable, and therefore allowing the vested rights doctrine to prevent application of these requirements to certain developments would be an obstacle to the accomplishment of the objectives of 33 U.S.C. § 1342(p)(3)(B)(iii).
¶ 57 However, 33 U.S.C. § 1342(p)(3)(B)(iii) does not require controls to reduce the discharge of pollutants to the maximum extent possible. Congress used the word "practicable." 33 U.S.C. § 1342(p)(3)(B)(iii). This language necessarily provides some flexibility to the states in adopting stormwater control regulations. Consistent with 33 U.S.C. § 1342(p)(3)(B)(iii), a state may legitimately determine that it is not "practicable" to impose new NPDES permit requirements on those projects with development applications that have already vested under state law.
¶ 58 Further, as noted above, the CWA contains no timeline for adopting controls to reduce the discharge of pollutants. The absence of any directive requiring the adoption of new regulations within a specific timeframe necessarily provides some flexibility to the states in implementing stormwater control regulations. Ecology itself recognized this flexibility by delaying the application of the 2013-2018 Permit requirements until
¶ 59 In enacting the CWA, Congress chose not to adopt rigid requirements for the immediate elimination of the discharge of pollutants to stormwater collection systems. Instead, Congress developed the NPDES permit program to gradually reduce such discharges. This choice suggests that some delay in the implementation of NPDES permit requirements would not necessarily prevent the accomplishment of Congress's broad purposes and objectives. As the United States Supreme Court noted, "[b]y establishing a permit system for effluent discharges, Congress implicitly has recognized that the goal of the CWA — elimination of water pollution — cannot be achieved immediately." Int'l Paper Co. v. Ouellette, 479 U.S. 481, 494, 107 S.Ct. 805, 93 L.Ed.2d 883 (1987).
¶ 60 Further, Congress did not retain control over the specific terms of NPDES permits. Instead, Congress provided EPA with the authority to delegate the NPDES permit program to approved state agencies, with the requirement that state standards not fall below federal standards. 33 U.S.C. § 1370. This delegation suggests that Congress intended that the implementation of CWA objectives would occur within the framework of state law, not that it intended to preempt state law. Although the application of Washington's vested rights doctrine may delay the application of Ecology's current permit requirements for a limited number of developments, the doctrine itself does not prevent the accomplishment of Congress's broad purposes and objectives.
¶ 61 Given the strong presumption against preemption under Washington law, we hold that that the CWA does not preempt Washington's statutory vested rights doctrine.
¶ 62 We reverse the Board's order and remand to the Board to direct Ecology to revise condition S5.C.5.a.iii in the 2013-2018 Phase I Municipal Stormwater Permit to specify that the 2013-2018 Permit applies only to those completed applications submitted after July 1, 2015.
I concur: LEE, J.
BJORGEN, J. (dissenting).
¶ 63 The application of the vested rights doctrine proposed by Snohomish County, King County, and the Building Industry Association of Clark County (collectively appellants), in my view, is both preempted by federal law and in conflict with governing state law. Therefore, I would affirm the decision of the Pollution Control Hearings Board (Board).
¶ 64 The issue in this appeal is whether the state vested rights doctrine excuses a specific class of applicants from compliance with new storm water regulations adopted by local governments to implement the 2013-2018 Phase I Municipal Storm Water NPDES
¶ 65 The pulse of the federal Clean Water Act (CWA) is set by 33 U.S.C. 1311(a), which bans the discharge of any pollutant from a point source into the nation's navigable waters, unless within applicable standards and subject to a permit. See also 33 U.S.C. 1312,
¶ 66 Of the various types of discharges,
Envtl. Def. Ctr., Inc. v. United States Envtl. Prot. Agency, 344 F.3d 832, 840-41 (9th Cir. 2003) (footnotes and internal quotation marks omitted). To implement CWA requirements, Ecology issued the 2013-2018 Permit authorizing discharges from large and medium municipal storm water systems, subject to standards and conditions. Of those, Condition S5.C.5 imposes new requirements on specified land development, including source control, flow control, and treatment, among others. Under this condition, local governments covered by the 2013-2018 Permit must adopt plans and regulations imposing these requirements on development proposals by June 30, 2015. At the heart of this appeal, Condition S5.C.5.a.iii states that these plans and regulations shall apply to all applications submitted after June 30, 2015 "and shall apply to applications submitted no later than June 30, 2015, which have not started construction by June 30, 2020."
¶ 67 Subject to the intricacies and exceptions unpacked by the case law, vesting
Noble Manor Co. v. Pierce County, 133 Wn.2d 269, 275, 943 P.2d 1378 (1997). As noted, the 2013-2018 Permit required local governments to adopt new storm water regulations by June 30, 2015. With that, appellants argue, the Permit violates the vested rights doctrine, since Condition S5.C.5.a.iii imposed those new regulations on applications submitted before that date, as long as construction will not have started by June 30, 2020. Whether the appellants are correct in this, however, need not detain the analysis, since relieving this class of applicants from compliance with the new regulations is preempted by the CWA.
¶ 68 State law is preempted "`to the extent of any conflict with a federal statute.'" Hillman v. Maretta, ___ U.S. ___, 133 S.Ct. 1943, 1949-50, 186 L.Ed.2d 43 (2013) (quoting Crosby v. Nat'l Foreign Trade Council, 530 U.S. 363, 372, 120 S.Ct. 2288, 147 L.Ed.2d 352 (2000)). Conflict preemption occurs "when compliance with both federal and state regulations is impossible ... or when the state law stands as an obstacle to the accomplishment and execution of the full purposes and objectives of Congress." Hillman, 133 S.Ct. at 1950 (internal citations omitted) (quoting Hines v. Davidowitz, 312 U.S. 52, 67, 61 S.Ct. 399, 85 L.Ed. 581 (1941)).
¶ 69 The objective of the CWA is to "restore and maintain the chemical, physical, and biological integrity of the Nation's waters" and to achieve or maintain "water quality which provides for the protection and propagation of fish, shellfish, and wildlife." 33 U.S.C. § 1251(a); Pub. Util. Dist. No. 1 of Jefferson County v. Washington Dep't of Ecology, 511 U.S. 700, 704, 114 S.Ct. 1900, 128 L.Ed.2d 716 (1994). To serve this goal, the CWA broadly prohibits "the discharge of any pollutant by any person," except as authorized by enumerated statutory provisions. 33 U.S.C. § 1311(a); Puget Soundkeeper Alliance v. State, Pollution Control Hr'gs Bd., 189 Wn.App. 127, ¶ 18, 356 P.3d 753 (2015). More specifically, the CWA mandates that permits for discharges from municipal storm sewers require controls to reduce the discharge of pollutants to "the maximum extent practicable." 33 U.S.C. § 1342(p)(3)(B).
¶ 70 State agencies may not issue NPDES permits
40 C.F.R. § 122.4(a), (d) (alteration in original). Washington law makes clear that these requirements apply to each discharge: WAC 173-220-150(1)(c) provides that "each issued [NPDES] permit shall require that ... [a]ny discharge of any pollutant ... at a level in excess of that identified and authorized by the permit shall constitute a violation of the terms and conditions of the permit." Puget Soundkeeper, 189 Wash.App. at ¶ 20, 356 P.3d 753.
¶ 71 The appellants do not argue that the specific standards of the 2013-2018 Permit are not strict enough to serve the CWA's purposes. Therefore, they do not dispute that the 2013-2018 Permit is a method of achieving the "maximum extent practicable" standard of 33 U.S.C. § 1342(p)(3)(B). Similarly, the Board concluded in its findings of fact, conclusions of law and order, dated March 21, 2014 (2014 decision), that the 2013-2018 Permit's low-impact development requirements, including those covering permeable pavement, bioretention, and the phasing of watershed basin planning "constitute... MEP," which is the abbreviation for "maximum extent practicable." Clerk's Papers at 248.
¶ 72 Against this background, one must conclude that the permit's standards are reasonably necessary to reduce the discharge of pollutants to "the maximum extent practicable," as required by federal law. Among those standards is the one at issue here: that the Permit's substantive requirements apply to projects for which applications were filed before July 1, 2013, but which will not have commenced construction by June 30, 2020. Similarly, one must conclude that this temporal choice of law provision is also reasonably necessary to meet the "maximum extent practicable" standard of 33 U.S.C. § 1342(p)(3)(B).
¶ 73 The state's vested rights doctrine would directly obstruct these federal purposes. Under the permit, projects with applications submitted before July 1, 2015 and which did not commence construction by 2020 would be subject to the standards of the 2013-2018 Permit. Under the vested rights doctrine as expounded by appellants, projects within this window would escape those standards. Thus, the proposed application of the doctrine would result in greater discharge of pollutants into receiving waters and consequent greater compromise to the purity of those waters. While the CWA may not require choosing the least polluting of all conceivable alternatives in every situation, it does require that permits for municipal storm sewers reduce the discharge of pollutants to "the maximum extent practicable." 33 U.S.C. § 1342(p)(3)(B). Applying the vested rights doctrine as appellants urge would frustrate the achievement of that standard, since, as shown above, subjecting projects within this window to the specific controls of the 2013-2018 Permit is a part of the Permit's reduction of polluting discharges to the maximum extent practicable.
¶ 74 The United States Congress recognized that the goals of the CWA cannot be achieved immediately, setting in 33 U.S.C 1251(a)(1) the goal that the discharge of pollutants into the navigable waters be eliminated by 1985. Thirty years have now passed since the 1985 deadline. To use the flexibility shown by that deadline as a license for further delay thirty years after its expiration is to risk passage into the absurd. Because application of the vested rights doctrine would frustrate accomplishment of the federal purposes, it is preempted under Hillman, 133 S.Ct. at 1950.
¶ 75 The policy of the water pollution control statute at chapter 90.48 RCW is "to maintain the highest possible standards to insure the purity of all waters ... and to that end require the use of all known, available and reasonable methods by industries and others to prevent and control the pollution of the waters of the state of Washington." RCW 90.48.010. Similarly, RCW 90.54.020(3)(b) states:
These designs are also reflected in the state anti-degradation policy to "[r]estore and maintain the highest possible quality of the surface waters of Washington" and to "[e]nsure that all human activities that are likely to contribute to a lowering of water quality, at a minimum, apply all known, available, and reasonable methods of prevention, control, and treatment (AKART)." WAC 173-201A-300(2)(a), (d).
¶ 76 Conclusions 10, 17 and 43 of the Board's 2014 decision determined that the 2013-2018 Permit's low-impact development requirements, including those covering permeable pavement, bioretention, and the phasing of watershed basin planning "constitute AKART." The 2013-2018 Permit thus would require AKART of projects with applications submitted before July 1, 2015, and which did not commence construction by June 30, 2020. The theory of the vested rights doctrine urged by appellants would relieve that class of projects from the duty to provide AKART. Thus, this application of the vested rights doctrine would conflict with RCW 90.48.010, RCW 90.54.020(3)(b), and WAC 173-201A-300 (2). The proper resolution of that conflict depends on the source of the vested rights doctrine.
¶ 77 In West Main Associates v. City of Bellevue, 106 Wn.2d 47, 51, 720 P.2d 782 (1986), our Supreme Court struck down Bellevue's local vesting ordinance, because it did not meet the due process standards of the Fourteenth Amendment. West Main, 106 Wash.2d at 52, 720 P.2d 782. The ordinance provided that rights would vest only upon filing a building permit application, but prohibited the filing of such an application until up to eight other permits or reviews had been approved. Id. at 49, 720 P.2d 782. The ordinance further barred filing a building permit application until any appeal of four of these other approvals had been resolved. Id. Not surprisingly, the court found this artifice to be unconstitutional. The court, however, did not hold that the state's general vesting rule, that projects are subject to the law in effect when a complete application is filed, is compelled by either the state or federal constitution. To do so would have approached the extremity of implying that the reliance-based vesting rule current in the great majority of states was unconstitutional. More recently, our Supreme Court held in Town of Woodway v. Snohomish County, 180 Wn.2d 165, 173, 322 P.3d 1219, remanded, 2014 WL 6968436 (May 2014), that "[w]hile it originated at common law, the vested rights doctrine is now statutory." Accord, Potala Vill. Kirkland, LLC v. City of Kirkland, 183 Wn.App. 191, 202, 334 P.3d 1143 (2014), review denied, 182 Wn.2d 1004, 342 P.3d 326 (2015). Although arbitrarily fluctuating governmental standards may scant the degree of fairness required by the constitution, our minority vesting doctrine is not constitutionally required medicine for that problem.
¶ 78 For these reasons, the conflict between the appellants' view of the vested rights doctrine and state water quality law must be analysed as a conflict between two statutes. When faced with apparently conflicting statutes, we employ a two-step process. See Gorman v. Garlock, Inc., 155 Wn.2d 198, 210, 118 P.3d 311 (2005). First, we examine whether the statutes can be harmonized and effect given to both. City of Lakewood v. Pierce County, 106 Wn.App. 63, 71, 23 P.3d 1 (2001). Then, if the statutes truly conflict and cannot be reconciled, we give preference to a more specific or more recently enacted statute. Tunstall ex rel. Tunstall v. Bergeson, 141 Wn.2d 201, 211, 5 P.3d 691 (2000).
¶ 79 Turning to the first step, the conflict between the two positions seems beyond the reach of harmonization: one would exempt a certain class of projects from the new standards and one would not. Chronology likewise is of little help. On one hand, the
¶ 80 A better window into legislative intent lies in the nature of the competing statutes. The vested rights doctrine is a general rule covering all development within its scope, without specific regard to the effects or interests at stake. RCW 90.48.010 and WAC 173-201A-300, in contrast, are aimed at protecting a specific resource, the waters of the state, from a specific threat, pollution. Chapter 90.54 RCW is of similarly focused scope, directed at ensuring the proper utilization of the state's water resources. RCW 90.54.010. These measures were enacted pursuant to legislative recognition of the value of the resource and the presence of the threat. RCW 90.48.010; RCW 90.54.010. The narrowed circumference of both focus and purpose in the water quality measures suggests that within those bounds the more general vesting doctrine must give way.
¶ 81 This conclusion flows also from our Supreme Court's view of the purpose of the vested rights doctrine. In West Main the court held that the purpose of the vesting doctrine is to allow developers to determine, or "fix," the rules that will govern development. 106 Wash.2d at 51, 720 P.2d 782. The court then took a more nuanced view in Erickson & Associates, Inc. v. McLerran, 123 Wn.2d 864, 873-74, 872 P.2d 1090 (1994), recognizing that
¶ 82 To use the vested rights doctrine to exempt from compliance those who filed before July 1, 2015, but who still have not begun construction over five years later, is to engage in the sort of subversion of the public interest against which Erickson warned. Reversing the defilement of our public waters stands high in any ranking of public interest. On the other hand, the public interest in allowing applicants to proceed under the standards current when they applied declines with time, as those standards become more obsolete and the excuses for inaction become weaker. Perhaps more to the point, the 2013-2018 Permit was adopted in 2012, effective in 2013. Thus, there can be little surprise in applying the permit's standards to those applying before July 1, 2015.
¶ 83 The purposes of the vested rights doctrine and our clean water laws are not in equipoise. The scrutiny of those purposes, as well as the specific nature of the latter, shows that protection of the state's waters must prevail in its conflict with the vested rights doctrine. By relieving a class of projects from the duty to provide AKART, the vested rights doctrine would conflict with RCW 90.48.010, RCW 90.54.020(3)(b), and WAC 173-201A-300 (2). In resolving that conflict, these statutes have the last word.
¶ 84 For the reasons set out above, I would affirm the order of the Board.