Findings Of Fact On December 9, 1982, Petitioner filed with Respondent a dredge and fill permit application to remove gates and wing-walls from a double-lock canal system presently installed at the Palmetto Point Subdivision in Lee County, Florida, adjacent to the Caloosahatchee River. On January 6, 1983, Respondent sent a "completeness summary" to Petitioner, along with a letter advising Petitioner that its permit application was incomplete, and requesting additional information. Petitioner responded to the January 6, 1983, completeness summary by submitting additional information to Respondent on or about February 23, 1983. On March 21, 1983, Respondent sent a second completeness summary requesting further additional information from Petitioner. By letter dated May 18, 1983, Petitioner's attorney advised Respondent that submission of additional requested hydrographic information and water quality data was not justified. The letter further advised that Petitioner intended to rely on the information already submitted, and requested, pursuant to Section 403.0876, Florida Statutes, that Respondent begin processing the permit application. The letter further indicated that petitioner was submitting under separate cover a request that Respondent apply the "moderating provisions" of Rule 17-4.244, Florida Administrative Code, to the application. The aforementioned rule is entitled "Mixing Zones: Surface Waters." Also on May 18, 1983, Petitioner's counsel sent another letter to Respondent requesting the aforementioned "Mixing Zone." The letter requested the "maximum mixing zone" allowed under the applicable Provisions of Rule 17- 4.244, Florida Administrative Code. Petitioner had not requested a mixing zone be applied to the permit application prior to the request contained in its May 18, 1983, letter. By letter dated June 17, 1983 Respondent, in response to Petitioner's May 18, 1983, letters, advised that: The additional information [which] was received on May 19, 1983, was reviewed; however, the items listed on the attached sheet remain incomplete. Evaluation of your proposed project will continue to be delayed until we receive all requested information. Respondent's June 17, 1983, letter included a completeness summary, which asked for additional information, including the following requests concerning mixing zones: Your request for a mixing zone is applicable pursuant to F.A.C. Rule 17-4.244(6). Please provide a map indicating the outermost radius of the mixing zone (no more than 150 meters) and the period of time required. The completeness summary acknowledged Petitioner's refusal to supply additional information concerning hydrographic data and water quality information, and indicated that Respondent would evaluate the project accordingly. By letter dated August 29, 1983, Respondent advised Petitioner that it had been 73 days since notification of the incompleteness of the permit application with regard to the mixing zone request. This letter requested Petitioner to advise Respondent if it wished to withdraw the application, request additional time, or discuss questions regarding the application. The Petitioner did not respond to this communication. On September 9, 1983, Petitioner's attorney forwarded a letter to Respondent requesting a default permit pursuant to Sections 120.60(2) and 403.0876, Florida Statutes. Until this letter, other than a prior oral communication on September 2, 1983, notifying Respondent that the default request was forthcoming, Petitioner had not contacted Respondent concerning the permit application since its May 18, 1983, letters. On October 13, 1983, Respondent advised Petitioner by letter that the mixing zone request constituted a revision of the application and that the information received to evaluate the mixing zone request was incomplete. Petitioner was also advised that since the additional information requested had not been received, the application remained incomplete and Petitioner was not entitled to a default permit. Whether or not a mixing zone is applied to a permit application is significant because it determines where state water quality standards must be met, either adjacent to the proposed project, or up to 150 meters away from the project location. Under Rule 17-4.244(6), Florida Administrative Code, the 150 meter radius is measured from the point of generation of turbidity or pollution. Since the two locks to be removed were 80 feet apart, it was unclear whether Petitioner intended the point of generation for measuring the radius of the mixing zone to be the northern lock, the southern lock, or some other point. It is equally unclear whether Petitioner intended the mixing zone to extend south into the canal as well as north into the Caloosahatchee River. Petitioner never contacted Respondent to clarify the dimensions of the mixing zone being sought, even after Respondent requested a map indicating the outermost limits of the mixing zone in the June 17, 1983, completeness summary.
Findings Of Fact Harold Click and Harold Peterson, Petitioners, are sole owners of property which borders Dunn's Creek, one of the largest tributaries to the St. John's River in Putnam County, and which is described as Lots 80, 88, and 89, Section 38, Township 11 South, Range 27 East. Dunn's Creek is a Class III water body of the state. Petitioners applied for a dredge and fill permit initially in 1980 but Respondent issued an Intent to Deny in January, 1981. A second permit application was submitted in 1982 on behalf of Petitioners following a site visit by representatives of Respondent in June, 1981, but again an Intent to Deny was issued in September, 1982. A third application was submitted on or about May 3, 1984, following another site visit by Respondent's representatives, but the Intent to Deny which resulted in this hearing was issued on December 5, 1984. During these site visits, Respondent's representatives offered suggestions about what might be an acceptable project but gave no assurances that the application, as submitted on May 3, 1984, would be permitted. The project which Petitioners now propose would include the placement of pilings and other fill materials within the waters and landward extent of the waters of the state which would result in the alteration of at least 10,000 square feet of the swamp floodplain community of Dunn's Creek. This proposed filling will degrade the water quality of the areas affected by replacing periodically inundated wetlands with uplands. Although the project also includes construction of a fill road with a bridge over a natural slough on Click's lot, Respondent's expert witness Tyler testified that this portion of the project alone would not have resulted in the Intent to Deny. According to Tyler, the key area of objection was the .23 acres Petitioners proposed to fill which was within Respondent's jurisdiction and which would have widened an already existing berm. This widening would have allowed the placement of two septic tanks and two, dwellings on pilings on the property and an access driveway through Click's portion of the property to Peterson's. As proposed, fill was to be placed over a total of .35 acres, with .23 acres being in the waters of the state or to the landward extent of waters of the state. Bald cypress trees or other species listed in Rule 17-4.02(17), Florida Administrative Code, are present in part of the wetland area occupied by the project site in greater numbers, biomass, and aerial extent than competing plant species or communities. Without appropriate pollution control measures, the proposed project could reasonably be expected to result in an adverse change in the biological integrity, bacteriological quality, biochemical oxygen demand and the concentration of dissolved oxygen, turbidity and nutrients in some of the waters on the project site, in Dunn's Creek, and in discharge areas elsewhere. The filling associated with the project can be expected to have a long- term detrimental impact on water quality and biological resources, according to Respondent's expert witness Deuerling. Natural habitats and rainwater storage areas would be destroyed or detrimentally altered, as would the natural filtration function performed by the swamp areas to be filled. In the immediate vicinity of Petitioners' lots, Respondent has denied two dredge and fill permits and there are an additional two permit applications which are pending. Deuerling has also performed site visits at three other locations along Dunn's Creek in the immediate vicinity of Petitioners' lots, and it can be expected that other permit applications for similar projects will be submitted if Petitioners are granted a permit.
Recommendation Based upon the foregoing it is recommended that Respondent enter a Final Order denying Petitioners' application for a permit. DONE and ENTERED this 5th day of September, 1985, at Tallahassee, Florida. DONALD D. CONN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1985. COPIES FURNISHED: Peter B. Heebner, Esquire 523 North Halifax Avenue Daytona Beach, Florida 32018 Ross S. Burnaman Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue The issue for consideration herein is whether Sarasota County Utilities should be issued a consumptive use permit to draw water from the 14 wells in issue here located in Sarasota County.
Findings Of Fact At all times pertinent to the issues herein, the Respondent, District, was the state agency responsible for themanagement of water resources within its area of geographical jurisdiction. Included therein was the responsibility for the permitting of consumptive water use. The Respondent, Sarasota County, is a political subdivision of the State of Florida and operates a public utilities division which is charged with meeting, among other things, the potable water needs of the residents of the County. Petitioners Wyatt S. Bishop and Joan Jones are both residents of Sarasota County and both draw their potable water from wells which utilize the aquifers pertinent to the wells for which the permit in issue here relate. Mr. Bishop lives approximately 7.5 miles north of the Carlton Reserve, the property on which the wells in issue are located, and Ms. Jones lives approximately 7 miles from the Reserve, but in a different direction. Sarasota County filed an application for a consumptive use permit with the District on January 28, 1987 requesting an average daily withdrawal of 10.71 million gallons per day, (mgd), and a peak monthly withdrawal of 15.55 mgd. This application, assigned number 208836.00, was, over the next three years, amended by the County four separate times. These amendments reflected revised water demand determinations and were submitted to provide additional information requested by the District. The District issued a preliminary staff report and proposed intent on March 26, 1991 reflecting an approved withdrawal in the amount of 7.28 mgd average daily withdrawal and 11.1 mgd peak monthly withdrawal. These figures were revised, however, byan amendment by the District on July 8, 1991, and as amended, authorize 7.303 mgd average daily withdrawal and 9.625 mgd peak monthly withdrawal. The County's application was reviewed by an experienced hydrologist in the District office with extensive permit review experience who utilized, in his evaluation of the permit, the pertinent District rules and policies. By way of background, to more easily understand the circumstances here, Sarasota entered into a contract with Manatee County in 1973 which called for the latter to provide up to 10 mgd of water for a period of 40 years, up to and including the year 2013. However, in 1979, Manatee County's utilities director advised Sarasota County that it, Sarasota County, could not continue to rely on Manatee County's water after the expiration of the current contract, and would, therefore, have to become self sufficient in water. Since the MacArthur tract, now known as the Carlton Reserve, had just recently been identified by, inter alia, the United States Geological Service as a potential long term water source for Sarasota County, after Manatee County advised Sarasota County of its future expectations, Sarasota County and the Manasota Basin Board hired a consulting firm to conduct hydrological testing on the Carlton Reserve. This study concluded that the Reserve had sufficient water resources to satisfy the needs of the unincorporated areas of Sarasota County for an extended time into the future. In 1985, because of its increased water needs and thetime necessary to complete required studies on the utilization of the Myakka River, a surface water resource, Sarasota County concluded that it was suffering a water supply shortage and entered into a supplemental contract with Manatee County to provide 2 million gallons of water per day over a 5 year period which would expire in 1990. Sarasota County had not, however, been idle with regard to the investigation of other water resources. Studies done included not only the Myakka River mentioned above but a reservoir owned by the City of Bradenton, and the Peace River. Nonetheless, it was determined that the Carlton Reserve was the best source available overall, and in 1987, the County filed the application in issue here. The permit was under consideration for approximately 3 1/2 years before the initial decision by the District to grant it. During that time the County experienced a significant deficiency in its water sources and found it necessary, on February 5, 1991, to enter into another contract with Manatee County to supply an addition 5 mgd. Terms of that contract clearly indicate the expectations of both parties that Sarasota County will take reasonable steps to develop its own water resources. It is not as though Sarasota County sat quietly in the interim, however, and allowed the situation to develop. A building moratorium to halt additional construction was proposed and as a result, economic forces in the County indicated a potential loss of jobs to County residents. None of this would be desirable from an economicstandpoint. In the course of the permit application process, 12 test wells were sunk to conduct aquifer pump tests; to assess water quality, amounts and availability, aquifer characteristics and drawdown; and to determine the impact of withdrawal on water quality. Eight of these 12 wells are located on the Carlton Reserve. The other 4 are located on property owned by the MacArthur Foundation which is contiguous to the Carlton Reserve property and from which Sarasota has a right by easement to draw water. The 2 wells yet to be constructed will be on Sarasota County property. Sarasota County currently receives 10 mgd of water under its contract with Manatee County; an additional 5 mgd under the February 5, 1991 contract; 2 mgd from the University wellfield, (with a peak withdrawal rate of 3 mgd); and .9 mgd from the Sorrento wellfield, (with a peak withdrawal rate of 1.1 mgd). This latter source is only producing currently .6 mgd of potable water due to constraints imposed by the water treatment requirements. Taken together, the current Sarasota County supply constitutes 18.6 mgd. The above does not take into account the County's agreement with the City of Sarasota calling for the purchase of up to 2 mgd. Since this source is not reliable, it is not included in the total, and the City is not considered an available water source. In addition, the District and Sarasota County stipulated on July 15, 1991 that within 30 days, the County would apply tophase out routine water production from the Sorrento wellfield, relying on it only in emergency situations with District consent. For this reason, it, too, is not considered an available water supply source. These currently existing sources, with modifications as described, will be the primary sources of potable water provided to 6 major service areas in Sarasota County when the County's water treatment plant and transmission system are complete in 1993. In attempting to define the County's future water requirements, two major criteria were considered. The first was the County's historical water demand, and the second, modifying it, relates to the demand arising as a result of new water users being added to the system as a result of the County's capital improvements and acquisition program. Water resources are not unlimited. Current resources come primarily from Manatee County and there are constraints on this supply as it is made available to Sarasota County. For example, the 10 mgd contract expires in 2013. The 5 mgd contract expires in 2001. Though the latter is subject to renewal, renewal is contingent upon the availability of water supply at that time, and that is not a sure thing. It can, therefore, readily be seen that 15 out of the 18.6 mgd routinely available now comes from Manatee County, and those sources are not perpetual. In addition, it is conceivable that Manatee County may pre-blend the water it delivers to Sarasota County with water of lesser quality, so that the delivered water may exceed the total dissolved solids standard of 500 ppm for potable water. If thewater from Manatee County were reduced to that quality, the University wellfield supply, which currently exceeds standards itself, and which relies on blending with better quality Manatee County water to be potable, would also be removed as a source of potable water to Sarasota County. In order to comply with the provisions of Section 373.171, Florida Statutes, which requires the District to regulate the use of water by apportionment, limitation, or rotating uses, to obtain the most beneficial use of water resources and to protect the public health, safety and welfare, the District analyzed the available water sources and determined that Sarasota County relies upon its 10 mgd supply from Manatee County and the 2 mgd supply from University wellfield to constitute 12 mgd usable water. The 5 mgd from Manatee County would be used only in an emergency situation, and the Sorrento wellfield would be abandoned. Future water demands must be predicted relying in great part upon an historic record of prior water use. Utilizing a statistical procedure called linear regression, a methodology accepted by the District, indicated a water demand figure for the period from 1992 to 1997 based upon six use points extending from 1985 to 1990. These use records reflected a low of 9.733 mgd and a high of 12.808 mgd, the former being in 1985 and the latter in 1990. In addition, the County estimated that its capital improvement program would add between 10 and 12 thousand customers who presently use private wells, whose water use would constitute approximately 2 mgd of additional demand. The County's program toacquire some 42 private franchises now serving customers would add an additional demand of 2 mgd. Taken together, these programs would add in approximately 1.8 mgd per year to the need assessment, and it would therefore appear that by 1997, the County's average daily demand, considering all new users, would be 17.84 mgd. The water to be drawn from the Carlton Reserve is not currently potable and will require some form of treatment to render it so. Sarasota County proposes to use the Electrodialysis Reversal process, (EDR), because, in the County's judgement, it is more efficient than others such as reverse osmosis and ion exchange. Whereas EDR is rated at up to 85% efficient, the others range between 50% to 75% efficient. In that regard, in order to determine the maximum amount of water to be drawn, providing a safety factor for a treatment plant operation that is not working up to peak capacity in computing the water needs, the EDR process was determined to be no more than 80% efficient. Factoring in that efficiency potential, when the 1997 average daily demand is subtracted from the County's projected water capacity, the withdrawal need in 1997 is determined to be 7.303 mgd. However, as a part of its permitting process, the County also calculated its peak month daily demand. This is a figure which represents the maximum amount permitted to be drawn on a daily basis during the peak demand period. This peak period was determined under Section b 3.2 of the District's Basis of Review by taking the 1989 daily flow and using a sliding 31 day calendar to determine the highest historical 31 day flow. Thisresulted in a peak month coefficient of 6.16 which was then multiplied by the 1997 average daily demand of 17.842 mgd which resulted in a peak month daily demand of 20.7 mgd. When existing water supplies are removed and the 80% EDR treatment process factor is applied, the amount of raw water needed from the wellfield in issue on a peak monthly basis would be 9.625 mgd. This peak monthly basis figure is considered because of the intermittent periods of low rainfall and high water demand within the County. Accepting the 1.8 gpd yearly increase; the peak factor of 1.16; and the assumed water supply capacity of 18.6 mgd; Sarasota County's need will exceed its available supplies by 1993. In fact, the County is already experiencing low water pressure in part of its service area during peak demand periods. County experts estimate that without the requested water from the Carlton Tract, Sarasota County can expect to experience dry periods as early as 1993 during the periods of peak water usage, generally between April and June. For the above reason, when the application and its supporting information was reviewed by Mr. Basso, the District hydrologist with extensive experience reviewing more than 300 water use application, he determined that the water supplies requested are necessary to meet the County's certain reasonable demand, and that this meets the criteria set out in Rule 40D - 2.301(1)(a), F.A.C. Turning to the issue of hydrologic and environmental impacts, the District's Basis For Review of Water Permit Applications provides for the use of a "water use model" inevaluating water needs and the appropriateness of a proposed withdrawal. In preparing its submittal to the District, Sarasota County performed certain tests and modeling to derive the statistical and scientific information used in support of its application. Specifically it used the USGS' MODFLOW model utilizing information obtained from the pump tests run on the wells in the pertinent areas. Consistent with the District's rule, the water data and aquifer drawdown were determined by simulated pumping. The tests run also provided the information on water quality in the aquifer and physical characteristics including transmissivity, storage coefficient, specific yield and leakance between aquifers. This data also helped in defining the hydrogeologic framework of the Carlton Reserve. The Carlton Reserve's hydrogeology listed in descending order from the surface, includes a surficial aquifer which varies in depth between 19 and 70 feet across the Reserve; a semi-confining clay unit separating it from the intermediate aquifer; the upper intermediate and lower intermediate aquifer which range in depth from 140 to 180 feet across the Reserve; another confining layer, and the Upper and Lower Floridan aquifers. The hydrology and groundwater modeling expert who constructed the model used in Sarasota County's permit application concluded that the water table drawdown at the Reserve property boundary in the surficial aquifer would be less than .3 of a foot; less than .4 of a foot in the intermediate aquifer; and 2.9 feet in the Upper Florida aquifer. The water to be drawn consistentwith this instant permit, if approved, would come from the Upper Floridan aquifer on the Reserve. The County's experts were conservative in the assumptions used in the groundwater model. It was assumed there would be no lateral water flow into the model area and no recharge. In addition, the model called for all pumps to run simultaneously at a maximum drawdown of 12.65 mgd for 90 days rather than at the requested quantity of 9.625 mgd. Utilization of these assumptions provided a scenario wherein "severe" impacts would be encountered. Based on the testing and the modeling done, expert opinion was that there would be no quantity or quality changes that would adversely effect water resources including ground and surface water. This meets the criteria of Rule 40D-2.301. This opinion was concurred in the District's hydrology expert. Nonetheless, in its proposed approval, the District has imposed special permitting conditions which require the County to monitor, analyze, and report water quality and water table level information to the District on a monthly and annual basis. When it evaluates the information supplied by an applicant relating to ground water monitoring, the District is required to consider certain presumptions set forth in its Basis For Review. For example, the District presumes that if there is a drawdown of more than 1 foot in the surficial aquifer at a wetland, adverse environmental impacts will occur. In the instant case, the County model concluded that the actual drawdown in the surficial aquifer at the Carlton Reserve is less than .6 of onefoot and, therefore, there should be no adverse environmental impact resulting from the withdrawal. Nonetheless, the County has developed several plans designed to provide information on environmental impacts which will continuously monitor such parameters as rainfall and evaporation, wetlands hydroperiod changes and vegetative changes in the wetlands to detect any changes which might be attributed to the water pumping. These plans have been made special conditions to the water use permit, and in the opinion of the County's ecology and hydrology expert, would enable the County to adequately monitor and detect any pertinent changes to the pertinent factors concerned on the Carlton Reserve. If wetland changes are detected, a contingency plan will be in effect which will require an alteration of pumping schedules or other action to minimize any adverse impacts. The District expert in wetlands and wildlife habitat has opined that these measures, with which he is familiar, are adequate to insure that adverse impacts to the wetlands will not occur. This is consistent with the provisions of Rule 40D-2.301(1). As was stated previously, the water to be drawn pursuant to this permit will be drawn from the Upper Floridan aquifer. This water is not potable but is treatable and is the lowest quality water which can be economically used by the County. Water of a lower quality does exist in the Lower Florida aquifer, but it is not economically treatable, and, in addition, use of this Lower Floridan aquifer might cause vertical movement of the poorer quality water into the upper strata. For all practical purposes,then, the lowest quality water available to it will be used by the County and this is consistent with the District's basis for review. Expert testimony indicates that saline water will not be infused into the Upper Floridan aquifer. Salt water intrusion generally occurs when groundwater is brought to a level below sea level. Even at the point of maximum actual drawdown as a result of pumping on the Reserve, the fresh water level will remain at least 20 feet above sea level, and as a result of the difference in water level, no saline water intrusion into the fresh water supply will occur even though salt water intrusion can also occur as a result of upward vertical movement of lower quality water due to withdrawal. The District's hydrologist and reviewing official also concluded that because of the confining layer below the aquifer from which water will be withdrawn, there would not be any significant upward movement of lesser quality water. The District's basis of review also envisions an aquifer pollution if a proposed withdrawal would spread an identified contamination plume. Here no contamination has been identified in the area from which the water will be drawn, and therefore, contamination would not be spread. The Basis for Review also infers there will be adverse impact to off site land if there is a significant drawdown of surface water bodies or if damage to crops or other vegetation can be expected. Here, the water table drawdown at the boundary of the Carlton Reserve is anticipated at less than .3 of one foot and any drawdown further out from the Reserve can be expected tobe even less. As a result, no adverse impact to existing off site land useage is expected. With regard to Rule 40D-2.301(1)(i), relating to an adverse impact on existing legal uses, the District presumes that no adverse impact will exist if the drawdown in the water table is no more than 2 feet at an affected well, or the potentiometric surface at the well is not lowered by more than 5 feet. Here, again applying the County's groundwater modeling demonstrates that the drawdown at its worst, in the Upper Floridan aquifer, would be no more than 2.9 feet at the Reserve boundary and much less at the Petitioners' wells. Both Mr Bishop's and Ms. Jones' wells are approximately 7.5 and 7 miles, respectively, from the closest well on the Reserve property. Ms. Jones' well is drilled into the intermediate aquifer which is above that which the County proposes to use and should not be impacted. Mr. Bishop draws water from the intermediate and surficial aquifers, both of which are above the Upper Florida aquifer identified for use here, and the groundwater modeling would suggest that his well would not be impacted either. Sarasota County's application contains reference to numerous proposals for water conservation measures which it intends to implement or has already implemented. It has adopted ordinances to enforce the District's watering restrictions and is currently implementing a block inverted use rate structure to promote conservation. It has developed programs for use in the schools outlining water conservation efforts and is developing programs topromote the increased use of treated waste water for golf course irrigation. The requirement for a water conservation plan such as is described and envisioned by the County is a condition of the water use permit proposed, and in addition, the County has adopted an Ordinance, (90-38) which modifies its building code to require installation of water conservation devices in new buildings erected in the County. It has developed proposals for conservation measures such as water auditing, meter testing, leak detection, system looping, and pressure reduction, and has selected the EDR process of water purification as the most efficient use of groundwater resources. Petitioner, Bishop, testified to his belief that approval of this permit and the resultant water withdrawal on the Carlton Reserve would necessitate an expansion of the boundaries of the District's Eastern Tampa Bay Water Use Caution Area to a point where his property would be encompassed therein. In support of his position, Mr. Bishop offered a notice to the effect that new ground water withdrawals would not be permitted within a certain "most impacted area" within the caution area. There was, however, no independent evidence from hydrologists, geologists, or other conservationists, or individuals familiar with the water conservation process, to support Mr. Bishop's contention that either the boundaries would be expanded or that withdrawal of the proposed permitted amounts of water from the Carlton Reserve would cause the boundaries to be expanded. By the same token, Mr. Bishop's contention that theproposed withdrawal from the wells here in issue would adversely effect his ability to draw water from his existing well was not supported by any expert testimony or documentary evidence tending to support or confirm his contention. He had no evidence tending to contradict the County's and District's experts, all of whom indicated there would be no adverse impact on the environment or water resources as a result of the instant permit. Similarly, neither Petitioner offered any evidence of a demonstrative nature that would draw any connection between the proposed permitted withdrawals and potential salt water intrusion and water level drawdown in their wells. The County introduced construction permits issued by its own health department covering 8 of the 12 wells which have been drilled on the Carlton Reserve as test wells. These wells were clearly sunk pursuant to an agreement between the District and the County's public health unit which delegates authority for water well construction permitting to the County. Taken together the documentation indicates that these 12 wells on the Reserve were installed and permitted pursuant to and consistent with appropriate permitting processes, and the testimony of Mr. Bassarab, the County's expert who oversaw the installation of the wells, reflects they are appropriately grouted and sealed. Therefore, there will be no mixing of lower quality water from the lower portion of the Floridan aquifer with the better quality water from the upper portion of that aquifer. The County's evidence clearly refutes the allegation by Mr. Bishop that the 12 test wells currently existingon the Carlton Reserve were neither permitted nor inspected as required by the District. County Commissioner Hill, who testified on behalf of the Petitioners, indicated that the wells applied for here are unnecessary and an inappropriate expenditure of County funds. She claimed there are other valid sources of water available to the County, including that extracted from excavated shell pits and seawater from the Gulf of Mexico which could be treated and desalinated. The Commissioner's comments as to alternate sources are not specifically rebutted. However, she is neither an expert in hydrology or hydrogeology, and her testimony is not persuasive. While other water sources may exist, the better evidence clearly indicates that those sources are not sufficient to meet the County's needs or are otherwise inappropriate for use by the County in sufficient quantity to satisfy those needs.
Recommendation Based on the foregoing Findings of fact and Conclusions of Law, it is, therefore: RECOMMENDED that consumptive water use permit No. 208836.00, providing for authorized quantities as outlined in the intent to issue, subject to conditions contained therein, be issued to Sarasota County. RECOMMENDED in Tallahassee, Florida this 5th day of September, 1991. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1991. APPENDIX TO RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONERS: Rejected as not supported by the evidence. Accepted. Accepted. - 8. Resolved against the Petitioners on the basis information presented by Respondents. 9.- 13. Accepted and incorporated herein. 14. - 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. 20. - 23. Accepted. Accepted but not dispositive of any issue. Accepted. & 27. Noted as citation of authority. Rejected. & 30. Accepted as restatements of evidence but not as Findings of Fact. 31. Irrelevant. 32. Rejected 33. & 34. Not a error is, in fact, it is such. 35. - 38. Irrelevant. 39. - 43. Accepted. 44. Accepted. 45. Rejected. 46. Accepted and incorporated herein. 47. & 48. Rejected as a mere citation of testimony. 49. Not understandable. Not a Finding of Fact. 50. Accepted. 51. Evidence is acceptable. 52. Not sufficiently specific to rule upon. 53. Not proven. 54. Not specific. 55. & 56. Rejected. FOR THE RESPONDENTS: 1. - 4. Accepted and incorporated herein. 5. & 6. Accepted and incorporated herein. 7. & 8. Accepted and incorporated herein. 9. - 14. Accepted and incorporated herein. 15. - 17. Accepted and incorporated herein. 18. - 21. Accepted and incorporated herein. 22. & 23. Accepted and incorporated herein. Accepted. - 27. Accepted and incorporated herein. 28. & 29. Accepted and incorporated herein. 30. - 32. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted. - 37. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. - 43. Accepted and incorporated herein. Accepted. Accepted and incorporated herein, - 48. Accepted and incorporated herein. Accepted - not a Finding of Fact. Accepted and incorporated in substance herein. Not correct as stated. Sarasota County will not be withdrawing saline water from the upper Floridan aquifer. The remaining discussion is accepted. Accepted and utilized. & 54. Accepted. Accepted and incorporated herein. Accepted. - 59. Accepted and incorporated herein. 60. Accepted. 61 - 63. Not Findings of Fact but comments on the evidence. Accepted and incorporated herein. & 66. Not Findings of Fact. COPIES FURNISHED: Wyatt S. Bishop, Jr. 5153 Tucumcari Trail Sarasota, Florida 34241 Joan Jones 719 East Baffin Road Venice, Florida 34293 William A. Dooley, Esquire Nelson, Hesse, Cyril, Smith, Widman, Herb, Causey & Dooley 2070 Ringling Blvd. Sarasota, Florida 34237 Cathy Sellers, Esquire Steel, Hector & Davis 215 S. Monroe Street Tallahassee, Florida 32301-1804 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Edward B. Helvenston, Esquire Vivian Arenas, Esquire SWFWMD 2379 Broad Street Brooksville, Florida 34609-6899
The Issue The issue in this proceeding is whether the District should approve FRI's consumptive use permit application, no. 2-019-0012AUR, pursuant to Chapter 40C- 2, Florida Administrative Code The FRI is seeking permission to withdraw an annual average daily rate of million gallons per day (mgd) of water and 762.85 million gallons per year of ground water for hydraulic dredging, cleaning and purification of sand at the Goldhead Sand Mine. Subject to certain limiting conditions to be set forth in the FRI's consumptive use permit, the water is proposed to be produced from three Floridan aquifer wells. District proposed to grant the permit application which was challenged by LBCA, resulting in the formal administrative proceeding. LBCA challenged the issuance of the permit to FRI on the basis of the FRI's alleged failure to comply with the applicable requirements of Chapter 3V3, Florida Statutes (E.S.), and Chapter 40C-2, Florida Administrative Code (F.A.C.), and other applicable law. RULINGS ON EXCEPTIONS TO FINDINGS OF FACT LBCA Exception Number 1 The LBCA takes exception to the hearing officer's Finding of Fact 2 that a necessary component of FRI's operation is its withdrawal of approximately 2.09 mgd of ground water for the production of sand. The 2.09 mgd is the average daily usage rate to who the parties stipulated prior to the hearing. The maximum daily usage rate is 3.75 mgd. However, FRI cannot exceed 762.5 million gallons for the year which is an average of 2.09 mgd. (Prehearing Stip. pp. 1,9). In the LBCA Proposed Recommended Order paragraph 25, the LBCA states that the operation "necessitates FRI's pumping allocation of an average daily 2.09 million gallons of water from the Floridan aquifer." Additionally, LBCA acknowledges in its Exception No. 2 that it is "known that approximately 2 mgd are pumped into the system." If a hearing officer's finding is supported by any competent substantial evidence from which the finding could reasonably be inferred, then it cannot be disturbed. Berry v. Dept. of Environmental Regulation, 530 So.2d 1019 (Fla. 4th DCA 1988). This exception is rejected because the finding is supported by competent substantial evidence. (T. 41-42, 104, 913-914). LBCA Exception Number 2 The LBCA takes exception to the hearing officer's Findings of Fact 8 and 28 that the receiving water from the mine site is primarily the surficial aquifer which recharges the downgradient lakes and that the surficial aquifer recharge will result in a positive or immeasurable effect on the lakes. The exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. It is improper for this Board to retry the case after the hearing has concluded by altering findings supported by evidence and reweighing evidence. Tampa Wholesale Liquors, Inc. v. Div. of Alcoholic Beverages and Tobacco, 376 So.2d 1195 (Fla. 2d DCA 1979). The decision to believe one expert over another is left to the hearing officer, and the decision cannot be altered absent a complete lack of competent substantial evidence from which the finding could be reasonably inferred. Fla. Chapter of Sierra Club v. Orlando Utility Comm., 436 So.2d 383, 389 (Fla. 5th DCA 1983) This Board cannot reweigh conflicting evidence, judge credibility of witnesses, or otherwise interpret the evidence to reach a desired result. Heifetz v. Dept. of Business Regulation, 475 So.2d 1277 (Fla. 1st DCA 1985); Freeze v. Dept. of Business Regulation, 556 So.2d 1204 (Fla. 5th DCA 1990). If a hearing officer's finding is supported by any competent substantial evidence from which the finding could reasonably be inferred, then it cannot be disturbed. Section 120.57(1)(b)10., Fla. Stat.; Berry v. Dept. of Environmental Regulation, 530 So.2d 1019 (Fla. 4th DCA 1988). This exception is rejected because the findings are supported by competent substantial evidence. (T. 105, 120-129, 146, 170, 187-190, 208-209, 235, 248, 256-257, 972-973, 1085-1093, 1139). LBCA Exception Number 3 The LBCA takes exception to the hearing officer's Finding of Fact 11 that the aquifer characteristics in the Floridan aquifer beneath and around the mine site are relatively uniform. The exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 180, 926-927). LBCA Exception Number 4 The LBCA takes exception to a mischaracterization of the hearing officer's Finding of Fact 13 regarding lake leakance by stating that the hearing officer found that some of the lakes at issue do not have leakance to the Floridan aquifer. In fact, it is contextually clear that the Hearing Officer was referring to "many of the lakes within the region." This exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 77-80). LBCA Exception Number 5 The LBCA takes exception to the hearing officer's Finding of Fact 16 that very little, if any, of the groundwater flowing into the Floridan aquifer beneath Lake Brooklyn flows toward the mine site. In making its argument, LBCA inaccurately attributes testimony to FRI witness Fountain when the referenced testimony was testimony of LBCA witness Boyes. This exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 1145-1146). LBCA Exception Number 6 The LBCA takes exception to the hearing officer's Findings of Fact 22 and 55 that the data collection effort of FRI and the District was far more extensive than is normally conducted for a mine of this size and that sufficient site-specific information was developed to be able to determine the effects of the proposed use of water at the mine operation. This exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. The findings are supported by competent substantial evidence and therefore the exception is rejected. (T. 103, 201, 238, 918-919; FR Ex. 5). LBCA asserts that FRI did not evaluate the "worstcase" scenario in order to establish permit entitlemet LBCA provides no legal citations to support its exception. LBCA's assertion lacks legal as well as factual support. LBCA has criticized FRI's aquifer performance test and modeling effort without presenting the elusive "worstcase scenario" which presumably would show impacts greater than those modeled by FRI. LBCA seeks to impose a burden of proof which is insupportable in law. It is not FRI's burden to show a violation of the criteria in Chapter 40C-2, Fla. Admin. Code, is a scientific impossibility, only to show that the non-occurrence of such violation is reasonably assured by the preponderance of the evidence in the proceeding. The Corporation of the President v. SJRWMD and City of Cocoa, Case Nos. 89-828, 89-751 (SJRWMD Dec. 13, 1990), aff'd, 590 So.2d 427 (Fla. 5th DCA 1991). An agency cannot assume the worst-case scenario unless that condition is reasonably foreseeable. Florida Audubon Society, supra..; Rudloe and Gulf Stream Specimen Co. v. Dickerson Bayshore, Inc., 10 F.A.L.R. 3426 (Florida Department of Environmental Regulation, June 8, 1988). As delineated in FRI's response to this exception, FRI and the Distract presented evidence of numerous investigations regarding this application, including testing and analyses of the impact of withdrawals at greater than the average and maximum daily pumping rates. (See Record citations on pp 17-20 of FRI's Response to Exceptions; T. 115-116, 126, 176-177, 918- 920). LBCA failed to present any citation to the record where it presented testimony evincing that another scenario which would result in greater impacts than those predicted by the applicant were reasonably like to occur. LBCA's speculation that another undefined scenario of pumping would show greater impacts was rejected by the hearing officer. The applicant has provided reasonable assurances with regard to the effects of the proposed withdrawal. LBCA Exception Number 7 The LBCA takes exception to the hearing officer's purported inference in Finding of Fact 23 that the aquifer performance test (2T) measured impacts significantly greater than could be expected to occur under "worst case" conditions as a result of the mining operation. The finding actually states "the (aquifer performance) test measured effects of pumping from the mine production wells for periods ranging from 78 hours to 108 hours at approximately twice the average rate of 2.09 mgd." As discussed in the ruling on exception no. 6, LBCA's assertion of a "worstcase scenario" has factual support in the instant case. The applicant is required to provide reasonable assurance that the proposed use is reasonable, beneficial, will not impact existing legal uses and is consistent with the public interest. The applicant is not required to evaluate LBCA's unspecified worst case scenario or prove the use will not cause any impacts. Florida Audubon Society, supra..; Rudloe, supra.. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 113-115, 141, 920). LBCA Exception Number 8 The LBCA takes exception to the hearing officer's Finding of Fact 23 that no changes in the lake levels are attributable to the pumping at the mine. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. In Finding of Fact No. 24, the hearing officer found that the effects of pumping were not distinguishable from the declines which occurred before and after the ADT test. Therefore, his conclusions are not inconsistent as alleged by the LBCA. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 120-130, 146, 759, 928- 933, 942, 944- 948, 1015-1016, 1122-1123, 1168; Dist. Ex. 5). LBCA Exception Number 9 The LBCA takes exception to the hearing officer's Finding of Fact 24 that the actual effects of the pumping will be approximately one half of the observed amounts of the 2T test on an average pumping day. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 113-117, 923-996; Dist. Ex. 5). LBCA's claim that this finding is irrelevant since only a "worstcase" scenario is pertinent is likewise rejected. Initially, it is noted that LBCA cites no legal support for its arguments. Furthermore, there is no requirement in the District's rules governing consumptive use which mandates consideration of only "worstcase" scenarios. Furthermore, an agency cannot assume worst case scenarios unless they are reasonably foreseeable, which determination is a case by case factual issue. See Florida Audubon Society, supra., Rudloe, supra.. LBCA Exception Number 10 The LBCA takes exception to the hearing officer's Finding of Fact 26 that Dr. Stewart testified that the Floridan aquifer is rarely completely homogenous and isotropic but that he and other modelers regularly make that assumption. This Board cannot judge credibility of witnesses or otherwise interpret the evidence to reach a desired result. Heifetz, supra.; Freeze, supra.. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding supported by competent substantial evidence and therefore the exception is rejected. (T. 738). LBCA Exception Number 11 The LBCA takes exception to the hearing officer's Finding of Fact 27 that the maximum drawdown in the Floridan aquifer under normal pumping conditions is modeled to be 0.1 to 0.2 feet beneath White Sands Lake. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 129, 182). For the same reasons stated in the ruling on exceptions no. 9 and 7, the LBCA's claim regarding irrelevancy is rejected. LBCA Exception Number 12 The LBCA takes exception to the hearing officer's Finding of Fact 28 that a decrease in lake levels will be less than that of the decrease in the Floridan aquifer, depending on the rate of leakance and that the drawdown effect will not accumulate over time, but rather will remain constant after reaching steady state conditions. The LBCA is simply rearguing their case. This Board cannot reweigh conflicting evidence, judge credibility of witnesses, or otherwise interpret the evidence to reach a desired result. Heifetz, supra.; Freeze, supra.. This exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 118-120, 129, 237, 706-708, 758). LBCA's irrelevancy argument is rejected for the reasons stated in the ruling on exceptions no. 9 and 7. LBCA Exception Number 13 The LBCA takes exception to the hearing officer's Findings of Fact 42 through 54 as being conclusion of law rather than findings of fact. The LBCA does not cite to the record or make legal argument to support the exception as required by Rule 40C-1 .564, F.A.C. Without said citation or argument, the exception is rejected. Corporation of the President, supra.. The hearing officer's recitation of the individual criteria of Rules 40C-2.301 (2), (4) and (5), F.A.C., serve as introduction to and reference for the specific findings with regard to each criterion to provide clarity in the order. To the extent that expert witnesses presented testimony on the criteria and how the applicant satisfied the criteria through proof, the elements are findings or fact. These additional reasons also serve as ground for rejection of the exception. LBCA Exception Number 14 The LBCA takes exception to the hearing officer's Finding of Fact 56 that LBCA's referenced exhibits do not correlate with normal conditions when compared with longer periods of time. The exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. In addition, the hearing officer ultimately did not admit the exhibits and therefore, the Finding of Fact becomes irrelevant. (T. 1152-1168, 411-416, 930- 933, 948, 969; FR Ex. 50A, SOB). Contrary to Rule 40C-1.564(3), F.A.C., LBCA fails to state wish particularity citations to the record or legal basis as required by Rule 40C-1.564, F.A.C., in support of its attack on finding 56 and its inferential attack on findings 23, 24, 30, 31, 32, 33, 34 and conclusions 62 and 63. The entire exception is rejected. LBCA Exception Number 15 The LBCA takes exception to the hearing officer's Conclusion of Law 66 that LBCA's exhibits 61, 64, 65, 71, 75, 76, 78-80, 82 and 83 have limited probative value to the extent it is predicated on FRI's rebuttal testimony. The LBCA argues that the rebuttal testimony is of low probative value. This Board cannot reweigh conflicting evidence, judge credibility of witnesses, or otherwise interpret the evidence to reach a desired result. This exception goes to the weight of the evidence and inferences drawn there from by the hearing officer. The finding is supported by competent substantial evidence and, therefore, the exception is rejected. (T. 1152-1168, 411-416, 930-933, 948, 969). Exception is also taken to Findings of Fact Nos. 32, 36, and 56 and Conclusion of Law 62 because LBCA argues that the testimony on which they are based exceeded the scope of direct examination and the LBCA was not given the opportunity to object. The correct time to object was when the alleged improper testimony was elicited. The LBCA did not object to preserve the record and therefore, has waived the objection. Section 90.104(1)(a), Fla. Stat. Finally, LBCA asserts that it was denied the opportunity to present rebuttal testimony in violation of Section 120.57(1)(b)4., Fla. Stat. To the contrary, LBCA was not denied the opportunity to present rebuttal testimony but failed to request surrebuttal and consequently failed to preserve any denial of that request by an objection on the record. (T. 1188-1190). Since LBCA never requested surrebuttal, the hearing officer never denied that request and, therefore, LBCA's argument is without merit. Furthermore, pursuant to the order of presentation under Rule 40C- 1.5434(1), F.A.C., which is followed in a permitting proceeding (applicant, petitioner, district), LBCA's entire case tended to be in the nature of rebuttal to the applicant's case. While the hearing officer did state that he did not ordinarily allow surrebuttal (T. 1169) before the rebuttal testimony was concluded, LBCA never affirmatively requested to present surrebuttal evidence or testimony nor did LBCA proffer any such evidence or testimony. Since no proffer was made of any relevant surrebuttal testimony which LBCA contends was excluded, and no objection was made in the record to LBCA's belief that it was prohibited from adducing surrebuttal evidence, it is now precluded from complaining about this perceived adverse ruling. King v. Estate of King, 554 So.2d 600 (Fla. 1st DCA 1989); Holmes v. Redland Construction Co., 557 So.2d 911 (Fla. 3rd DCA 1990); Roberts v. Hollway, 581 So.2d 619 (a. 4th DCA 1991); Diaz v. Rodriguez, 384 So.2d 906 (Fla. 3rd DCA 1980). The exception is rejected. LBCA Exception Number 16 The LBCA takes exception to the hearing officer's Findings of Fact 17, 18, 19, 20, 21, 52 and 55 and Conclusions of Law 62 and 63. Findings of Fact 18, 19, 21, 52 and 55 and Conclusions of Law 62 and 63 are discussed in subsequent exceptions and therefore arc not addressed in this ruling on exceptions. LBCA's exception to Finding of Fact 20 fails to state with particularity any supporting citations to the record or legal argument as required by Rule 40C- 1.564 (3), F.A.C., and is therefore, rejected. LBCA takes exception to Finding of Fact 17 that the hearing officer incorrectly refers to three distinct water quality studies. In fact, the hearing officer actually refers to "numerous analyses" LBCA also objects to the reference to "unknown persons" in the finding and apparently to the statement: "They include analyses conducted by the District in 1989 and 1992, including sampling of water quality and an analysis of the background levels of certain parameters, and an assessment of data from HRS testing in March 1989 and May 1992." Clarification that HRS personnel conducted sampling in 1989 and 1992 is provided; however, since these personnel were never specifically named, to that extent the hearing officer's reference to "unknown persons" is accurate. (T. 1035, 379). The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 102-103, 130- 133, 451, 1023-1037, 1041- 1048, 1151-1152). LBCA Exception Number 17 The LBCA takes exception to that part of the hearing officer's Finding of Fact 18 that states: "This theory was predicated on... an assumption that a chemical reaction was occurring because herbicides were used in the dredge pond." LBCA fails to prove any supporting transcript citations in violation of Rule 40C- 1.564 (3), F.A.C. In Finding of Fact 18, the hearing officer reached the conclusion that none of the water quality samples taken from the mine site indicate a violation of state water quality standards. The exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. It is improper for this Board to retry the case after the hearing has concluded by altering findings and reweighing evidence. Tampa Wholesale Liquors, Inc., supra.. This Board cannot judge credibility of witnesses or otherwise interpret the evidence to reach a desired result. The finding is supported by competent substantial evidence and the exception is rejected. (T. 133, 575, 1024-1025). LBCA Exception Number 18 The LBCA takes exception to the hearing officer's Finding of Fact 19 by arguing that water quality on the mine site says nothing about off site impacts and positing that the finding is predicated on certain speculation. LBCA offers no helpful record citations supporting these allegations. Expert testimony established that water quality sampling by FRI and the District of the surficial aquifer at the locations chosen was where water quality impacts would be most likely to be revealed and consequently was a conservative approach. (T. 133, 144, 1029-1030, 1061, 1073). This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 130-139, 141-144, 575-576, 1028-1031, 1061-10 65, 1073, 1136-1139). LBCA Exception Number 19 The LBCA takes exception to the hearing officer's Finding of Fact 21 by stating that it misleadingly implies that 212 homes were tested for water quality by HRS. To the contrary, the hearing officer's finding states "12 out of 212 homeowners" (emphasis added) south of the mine site were tested, not 212. In addition, the exhibits referenced do not reflect the testing of 212 homes. The finding is supported by competent substantial evidence and the exception is rejected. (T. 167-168, 379, 990, 1036-1037, 1041, 1048-1050, 1052-1053). LBCA Exception Number 20 The LBCA takes exception to the hearing officer's Finding of Fact 21 on the basis that it is a legal conclusion which misrepresents and misapplies the state water quality standards. However, LBCA cites no authority or record citation for the argument as required by Rule 40C-1.564(3), F.A.C. The finding actually states "with the exception of one well... the water from the homeowners' wells did not exceed background water quality for iron and manganese"; clearly, this is a factual statement. This exception, under the guise of an unsupported legal argument, goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial, and uncontroverted, evidence which, incidentally, includes explanation and citation to the relevant exception/standard. Furthermore, the parties stipulated that official recognition was taken of chapter 17-520, F.A.C. The exception is rejected. (T. 1034, 1041, 1077-1078; Prehearing Stip. p 12; Rules 17- 520.420(2) and 17-520.200(11), F.A.C.) LBCA Exception Number 21 The LBCA takes exception to the hearing officer's Finding of Fact 21 that the 1989 water quality samples by HRS were unreliable because of the uncertainty regarding the sampling technique protocol. This exception erroneously states there was no evidence of sampling protocol used by HRS. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 1039-1049). LBCA Exception Number 22 The LBCA takes exception to the hearing officer's Finding of Fact 52 that the receiving body of water will not be seriously harmed, by characterizing the finding as being predicated on an unproven theory that the surficial aquifer receives all groundwater discharged from one site. LBCA has failed to read the entire finding which clearly reveals that the hearing officer did not confine his consideration to the surficial aquifer. He found that water quality standards would not be violated in the surfical aquifer, where the highest concentrations of any potential contaminants would appear, then they would not be violated in any intermediate aquifer similarly, no violations would occur in one Floridan aquifer. The decision to believe one expert over another is the role of the hearing officer, and the decision cannot be altered absent a complete lack of competent substantial evidence from which the finding could be reasonably inferred. Fla. Chapter of Sierra Club, supra.. This Board cannot reweigh conflicting evidence, judge credibility of witnesses, or otherwise interpret the evidence to reach a desired result. Heifetz, supra.; Freeze, supra.. If a hearing officer's finding is supported by any competent substantial evidence from which the finding could reasonably be inferred, then it cannot be disturbed. Berry, supra.. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 105, 141-142, 1025-1030, 1034-1035). LBCA Exception Number 23 The LBCA takes exception to the hearing officer's Finding of Fact 55 that water quality sampling was collected to evaluate a water budget for the dredge pond. In their responses to this exception, FRI explicitly notes it has no response to this exception and District counsel concedes that although water quality samples were taken from the dredge pond and a water budget was calculated for the dredge pond, these two procedures were not linked to one another. The testimony of FRI witnesses is that water quality sampling and data to determine the water budget for the dredge pond were performed. (T. 76, 103). Counsel for FRI and the District have stipulated that the testimony does not support the finding that the water quality samples were used to evaluate the water budget. Since, as stipulated, this portion of the hearing officer's finding is not supported by any evidence in the record, the exception is accepted. LBCA Exception Number 24 The LBCA takes exception to the nearing officer's Finding of Fact 55, arguing that the applicant did not perform an environmental assessment of Lake Brooklyn, and thus cannot fairly draw any conclusions about its operation's impact on that lake. The Finding of Fact describes the site-specific information which supports the application. The pertinent part of the finding states: "FRI conducted an assessment of the environmental impacts to the wetland and wildlife resources of the area lakes, including White Sands, Spring and Gator Bone Lakes." To the extent Lake Brooklyn is encompassed by use of the term "area lakes", the existence of an assessment of the impacts to Lake Brooklyn is supported by expert testimony. (T. 281, 899). Additionally, the finding is otherwise supported by competent substantial evidence. (T. 266-280). The exception is rejected. LBCA Exception Number 25 The LBCA takes exception to the hearing officer's Finding of Fact 31 which states in pertinent part: "petitioner's witness Dr. Stewart opined that there is insufficient data to determine whether any impacts to lake levels are occurring." LBCA is essentially complaining that the entirety of Dr. Stewart's testimony should be credited not just a portion. The role of the hearing officer is to consider and weigh all the evidence, resolve conflicts and judge credibility of the witnesses. The hearing officer apparently did not view all of Dr. Stewart's testimony in the same manner as LBCA's attorney; such is his legal prerogative. If a hearing officer's finding is supported by any competent substantial evidence from which the finding could reasonably be inferred, then it cannot be disturbed. Berry, supra.. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 784-786, 145- 146, 232-233, 285-286, 288-289, 897-898, 1085). LBCA Exception Number 26 The LBCA takes exception to the hearing officer's Finding of Fact 24 that the rate of decline (in Spring, White Sands and Gator Bone Lakes) during the APT test was not distinguishable from the declines which occurred before or after the test. LBCA provides no record citations to support its argument that since the hearing officer rejected its use of certain APT data in an attempted correlation between pumping and Lake Brooklyn levels, that all the APT data was entirely discredited and could have no value in an analysis regarding Spring, White Sands or Gator Bone Lakes. If a hearing officer's finding is supported by any competent substantial evidence from which the finding could reasonably be inferred, then it cannot be disturbed. Berry, supra.. This exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. The finding is supported by competent substantial evidence and therefore the exception is rejected. (T. 941-948, 1015-1016, 1123, 1168). RULINGS ON EXCEPTIONS TO CONCLUSIONS OF LAW LBCA Exception Number 1 The LBCA takes exception to the hearing officer's Conclusion of Law 62 and 63 and Findings of Fact 42 through 54 (which LBCA alleges should be conclusions of law) that FRI has established its entitlement to the permit. LBCA argues that the applicant failed to present sufficient information about conditions at Lake Brooklyn. LBCA's numerous "factual" statements in this exception are unsupported by record citations. The burden of proof in an administrative hearing falls initially upon the party asserting the affirmative of an issue, i.e. entitlement to a permit. Rules 40C-1.545 and 40C-2.301(7), F.A.C.; Capeletti Brothers v. Department of General Services, 432 So.2d 1359 (Fla. 1st DCA 1983); Department of Transportation v. J.W.C., Inc., 396 So.2d 778 (Fla. 1st DCA 1981). The party must prove its case by a preponderance of the evidence. Florida Audubon Society v. South Florida Water Management District, 13 F.A.L.R. 4169 (undated). The applicant's burden is to establish reasonable assurances that the proposed use is a reasonable-beneficial use, will not interfere with any presently existing legal use of water, and is consistent with the public interest. Section 373.223, Fla. Stat. The burden of reasonable assurances is not one of absolute guarantees. City of Sunrise v. Indian Trace Community Dev. Dist., 14 F.A.L.R. 866 (January 16, 1992). The impacts which are reasonably expected to result from issuance of the permit must be addressed, not potential impacts or those that might occur Hoffert v. St. Joe Paper Co., 12 F.A.L.R. 4972 (December 6, 1990); Chipola Basin Protective Group Inc. v. Florida Chapter of Sierra Club, 11 F.A.L.R. 467 (Department of Environmental Regulation, December 29, 1988); Florida Keys Citizen Coalition v. 1800 Atlantic Developers, 8 F.A.L.R. 5564 (Department of Environmental Regulation, October 17, 1986). Once the party asserting the affirmative, FRI, has presented its prima facia case, the burden shifts to the LBCA to present contrary evidence. 1800 Atlantic Developers, supra.; Hoffert, supra.. LBCA cites Booker Creek Preservation, Inc. v. Mobil Chemical Co., 481 So.2d 10 (Fla. 1st DCA 1986) in support of the exception. In Booker Creek, the Court held that additional testing, beyond that offered by the applicant, should have been done before the permit could be issued. Booker Creek was limited to its unique set of facts by the case of Berry v. Dept. of Env. Regulation, 530 So.2d 1019 (Fla. 4th DCA 1988). The Berry Court, in dealing with a dredge and fill permit, refused to extend the Booker Creek holding to such permits, noting that the permit under consideration in Berry, was not a pollutant discharge permit. The permit in issue here also is not a pollutant discharge permit. More importantly, like the applicant in Berry, FRI offered evidence of extensive testing and analysis regarding where water comes from and goes to at the mine site and in the surrounding vicinity. Finding of Fact No. 55. LBCA incorrectly argues that the modeling information submitted by FRI has no applicability to impacts at Lake Brooklyn, because the model "did not include Lake Brooklyn". Particularly, in view of findings of fact 23, 28, 31-36 (exceptions to which have been previously rejected), it is apparent that the hearing officer rejected LBCA's view of the "facts" stated in this exception. While the model boundary (which is based on water level data for Floridan wells in the region (T. 164)) is between Lake Brooklyn and the pumping wells at the mine, the drawdown at the model boundary is based on a distance-drawdown relationship that relates to the pumping rate at the mine. The 1991 transient model showed that within the 9 square mile boundary, the impacts at the boundary were no more than 0.1 feet. (T. 129, 178). The reduced boundaries in the 1992 model accurately predicted what was happening at the mine site. (T. 178). The distance-drawdown relationship established by the model shows that the drawdown contour ceases before the model boundary is reached and therefore, before Lake Brooklyn is reached. (FR Exs. 5, 22). Impacts to Lake Brooklyn were also assessed through the review of water levels in the Floridan aquifer well (C- 120) between 1960 and 1992. (T. 928-933). The data showed that water levels in the well at Lake Brooklyn actually continued to rise when the 1989 and 1991 pump tests were conducted. (T. 411-412, 931-933; SJRWMD Ex. 13). In addition, when the pumping wells at the mine were turned off, the water level in the well at Lake Brooklyn did not recover. This indicates that there were outside influences for the fluctuation in the well. (T. 415, 933). The data does not show impacts from the pumping at the sand mine. (T. 942). LBCA also erroneously states that groundwater in the Floridan aquifer beneath Lake Brooklyn flows toward the mine. (See ruling on LBCA's factual exception 5). As listed in responses to LBCA's factual exceptions, particularly those regarding exceptions 8 and 12, there is competent, substantial evidence to support the bindings regarding no adverse impact to Lake Brooklyn. The hearing officer found that the applicant met its burden or proof in Conclusion of Law 62. In Conclusion of Law 63, the hearing officer concluded that the LBCA did not meet its burden of presenting contrary evidence that the withdrawals at the sand mine correlate with the decline in water levels at Lake Brooklyn. The exception goes to the weight of the evidence and inferences drawn therefrom by the hearing officer. This Board cannot reweigh conflicting evidence, judge credibility of witnesses, or otherwise interpret the evidence to reach a desired result. Heifetz, supra.; Freeze, supra.. This exception is rejected. LBCA Exception Number 2 The LBCA takes exception to the hearing officer's Conclusion of Law 63 that additional permit conditions in the case of a water shortage or a shorter permit duration are not necessary. The LBCA is reargue their case in the exception. The District has authority to require FRI to reduce its water use during a water shortage within the seven year life of the permit. Sections 373.175 and 373.246, Fla. Stat., and Rules 40C-2.381(2)(a)2. and 40C-21.271, F.A.C. Rule 40C-2.381(2)(a)2., F.A.C., which is incorporated into the permit as a limiting condition, states: Nothing in this permit should be construed to limit the authority of the St. Johns River Water Management District to declare a water shortage and issue orders pursuant to section 373.175, F.S., or to formulate a plan for implementation during periods of water shortage, pursuant to section 373.246, F.S. In the event a water shortage, is declared by the District Governing Board, the permittee must adhere to the water shortage restrictions, as specified by the District, even though the specified water shortage restrictions may be inconsistent with the terms and conditions of this permit. (emphasis added). Rule 40C-21.271, F.A.C., General Water Use Restrictions, specifies the restrictions which may be imposed during a water shortage on all water users and states, in pertinent parts: The Board may order use of general water use restrictions and the water use restrictions specified in Part VI for the appropriate water shortage phase for each affected source class. Further, the Board may order any combination in lieu of or in addition to the restrictions specified in Part VI of the restrictions described in Subsection (3), by use or method of withdrawal class, within each source class, if necessary to achieve the necessary percent reduction in overall demand. (emphasis added). General water use restrictions which may be imposed include provisions that facilitate the right of water users in an area to make voluntary agreements among themselves, with the concurrence of the Board or the Executive Director, providing for the mutual reduction, sharing, or rotation of use; restrictions on the total amount of water that may be used, diverted, impounded, extracted, or withdrawn during any day, month, or year during the declared shortage; restrictions on the timing of use, diversion, impoundment, extraction, or withdrawal of water; restrictions on pumping rates and schedules or diversion rates and schedules; or such other provisions or restrictions as are necessary to protect the water resources from serious harm. With the above cited authority, the District can require the withdrawals at the sand mine to be reduced during periods of water shortage within the seven year term of the permit by reducing the total amount withdrawn, controlling the schedule of withdrawals or "by other restrictions which arc necessary to protect the water resources." The hearing officer's conclusion is consistent with the rules and statutes which govern the Board. The exception is rejected. LBCA Exception Number 3 The LBCA takes exception to the hearing officer's Conclusion of Law 63 and Finding of Fact 47 that FRI satisfied the criteria regarding water conservation measures. See Rule 40C-2.301(4)(e), F.A.C. The LBCA reargues the facts which the hearing officer found to support the conclusion. However, the LBCA offered no evidence to rebut the testimony of FRI. In addition, the LBCA cites no authority that the hearing officer's conclusion is contrary to law. Florida Audubon Society v. Department of Environmental Regulation, 9 F.A.L.R. 565 (October 31, 1986). LBCA also renews its attack on the allocation amount, essentially iterating its factual exception which is rejected for the reasons set forth therein. It is improper for this Board to retry the case after the hearing has concluded by altering findings and reweighing evidence. Tampa Wholesale Liquors, Inc., 376 So.2d 1195 (Fla. 2d DCA 1979). LBCA's exception lacks any record citations or legal authority in support of this exception. The conclusion and finding are supported by competent substantial, and uncontroverted, evidence and the exception is rejected. (T. 43-52, 106, 234- 237, 988-989, 1103- 1104, 1111, 1132-1133) LBCA Exception Number 3 (sic). The LBCA takes exception to the hearing officer's Conclusion of Law 63, by arguing that the use of water from the surficial aquifer requires a separate permit. Section 40C-2.051, F.A.C., states: No permit shall be required under the provisions of this rule for the following water uses: Withdrawals of ground or surface water to facilitate construction on or below ground surface ..., in the following circum- stances: ground water may be withdrawn if it is recharged on site to the aquifer from which it was withdrawn by either infiltration or direct injection; surface water may be withdrawn only from wholly owned impoundments or works which are no deeper than the lowest extent of the uppermost water bearing stratum and which have no surface hydrologic connection off site, and the surface water must be recharged on site to the uppermost water bearing stratum by either infiltration or direct injection. This exemption from permitting is applicable here, and therefore, no additional permit is required. An agency's interpretation of its rules is afforded great weight. Franklin Ambulance Service v. DHRS, 45 So.2d 580 (Fla. 1st DCA 1989). LBCA offered no auth-orty or evidence that the District's interpretation is contrary to established law. This conclusion is supported by competent substantial evidence. The exception is rejected. (T. 38-39, 105, 249, 972, 1101-1102). RULINGS ON EXCEPTION TO CONCLUSIONS OF LAW CONTAINED IN POST- HEARING EVIDENTIARY RULING LBCA excepts the hearing officer's rulings in Finding of Fact No. 56 and Conclusion of Law No, 66 excluding LBCA exhibits nos. 61, 64, 71, 75, 76, 78, 79, 80, 82 and 83 as inadmissible for failure of LBCA to comply with subsection 90.956, Fla. Stat., regarding use of summaries of evidence. LBCA takes exception to FRI's objection post-hearing alleging that the exhibits had been admitted. In fact, the exhibits were not admitted at hearing. The LBCA's citation to the transcript is not the hearing officer's ruling on the exhibits. The hearing officer did not admit the ten exhibits on the record, as he did with every other exhibit that he admitted. The LBCA's assertion that it believed the exhibits were admitted is belied by LBCA's failure to list them as admitted in its Proposed Recommended Order on page 3. Therefore, LBCA's claim that FRI's continuing objection was a surprise is without merit. LBCA asserts that FRI cannot make a post-hearing objection to the exhibits in its Proposed Recommended Order and infers gnat FRI's objection to the admission of the exhibits was not preserved at hearing. Rule 40C-1.561, F.A.C., provides for the submission of legal briefs along with proposed findings of fact and conclusions or law. For matters that remain pending at the close of a hearing, a party may file a legal brief in support of its position. FRI did not object to the opinion testimony of the LBCA expert witness, only to the graphic depictions of such testimony. (T. 356). LBCA stated at hearing that the excluded exhibits were simply graphic depictions of the expert's opinion testimony. (T. 354). The record is abundantly clear that FRI preserved its objection to the exhibits and the hearing officer reserved ruling on their admission until the recommended order was issued. (T. 353, 358, 360, 363, 369, 370, 375, 377, 524, 531, 537, 1079-1080, 1178). LBCA essentially asserts that the exhibits are not "summaries" and therefore not subject to subsection 90.956, Fla. Stat., which, of course, the fact-finder found otherwise. LBCA's reliance on Marks v. Marks, 576 So.2d 859 (Fla. 3d DCA 1989) is misplaced. Marks did not hold that expert testimony is not subject to subsection 90.956, but only that an expert is not required to utilize subsection 90.956 when presenting underlying data relied on for his opinion. The hearing officer found that the hydrographs were summaries and the underlying information was not indicated on the summary. The hearing officer allowed FRI time to review the data and present rebuttal. The fact-finder is entitled to great latitude in admitting or excluding summary evidence. Wright v. Southwest Bank, 554 F.2d 661 (5th Cir. 1977)(trial court without jury is entitled to great latitude covering the admission or exclusion of summary evidence). LBCA has failed to show that the hearing officer abused this discretion in excluding the exhibits. LBCA also takes exception that LBCA was denied rebuttal, or surrebuttal, on FRI's rebuttal case. As discussed in the ruling on LBCA's Exception 15, LBCA failed to request rebuttal of FRI's case. The hearing officer allowed cross-examination and LBCA did not offer any additional evidence from LBCA witnesses. Since the LBCA never requested to offer rebuttal testimony, then the hearing officer could not and did not deny that request. It is well-settled that an objection must be preserved during an administrative proceeding or it will be deemed waived. DeMendoza v. First Federal Savings and Loan, 585 So.2d 453 (Fla. 4th DCA 1991)(even if mistake was made in trial, party's waived its right to appeal the issue since it failed to call the deficiency to the court's attention during trial); Yachting Arcade, Inc. v. Riverwalk Condominium Assoc., 500 So.2d 202 (Fla. 1st DCA 1986)(party's failure to object to matters at administrative hearing made those matters unreviewable, even though party claimed fundamental procedural errors, it failed to show how it was prejudiced by any such action or omission; National Dairy Products, Corp. v. Odham, 121 So.2d 640 (Fla. 1959). Therefore, LBCA's exception based on the denial of rebuttal is rejected. LBCA argues that-the proper vehicle for the objection was a motion for rehearing. LBCA does not cite authority for its assertion. Since the hearing officer never ruled on the admissibility, there was no order on which to base a motion for rehearing. Nevertheless, the alleged error, if any, of excluding the exhibits, was harmless. Sims v. Brown, 574 So.2d 131 (Fla. 1991)(exclusion of manual was harmless since experts testified to the same matters in the manual); Little v. Banker's National Life Insurance Co., 369 So.2d 637 (Fla. 3d DCA 1979)(harmless error to exclude letter since witnesses otherwise testified at length as to its contents and conclusions). The LBCA expert testified extensively regarding the basis of each excluded exhibit and the information it depicts in relation to the conclusions of his expert opinion which the hearing officer weighed in rendering his factual findings and conclusions. (T. 346, 349, 351, 352, 358, 359, 364, 366, 371, 373, 411, 456, 457, 458, 481, 486, 501, 504, 507, 509, 511, 512, 516, 517, 518, 519, 542). The hearing officer concluded that even if the exhibits had been admitted it would not have altered his factual findings stating that they had limited probative value. (Conclusion of Law No. 66). Therefore, the exception is rejected. RULING ON RECOMMENDED ORDER'S COMPLIANCE WITH SECTION 120.59(2), FLA. STAT. LBCA asserts that the hearing officer failed to comply with subsection 120.59(2), Fla. Stat., by not providing a sufficiently explicit ruling on each of the parties' proposed findings of fact. Section 120,59(2), Fla. Stat., requires "a ruling upon each proposed finding" The Appendix to the Recommended Order does not contain an omnibus "blanket" ruling on all of LBCA's proposed findings which the courts have found inadequate. Cf. Island Harbor beach Club v. DNR, 476 So.2d 1350 (Fla. 1st DCA 1985); Health Care Management, Inc. v. DHRS, 479 So.2d 193 (Fla. 1st DCA 1985). The Appendix clearly contains a ruling upon each of LBCA's proposed findings. Section 120.59(2), Fla. Stat., requires no more. LBCA relies on Island Harbor Beach Club v. DNR, 476 So.2d 1350 (Fla. 1st DCA 1985), to support this argument. Island Harbor Beach Club, differs significantly from this case. The order Island Harbor Beach Club did not individually address each specific proposed finding as the Recommended Order in this case does. The only reference to proposed findings made in the Island Harbor Beacon Club order was a single paragraph which stated: The parties proposed findings of fact have been considered and where unsupported by the weight of the evidence, immaterial, cumulative, or subordinate. This differs from the Recommended Order in the instant case which specifically addresses each proposed finding and specifies where (by paragraph) in the Recommended Order that proposed finding is addressed. It is elementary to then read the paragraph referred to in the Recommended Order to determine what portion of the proposed finding was accepted. More applicable to this case is the case of Schomer v. Department of Professional Regulation, 417 So.2d 1089 (Fla. 3d DCA 1982). The order in Schomer did not contain specific rulings on each proposed finding submitted by the Appellant. The substance of the final order, however, demonstrated that each finding had been considered and ruled on. The Court noted that, for purposes of complying with Section 120.59(2) Fla. Stat., It would not elevate form over substance." An agency need not Independently quote verbatim each proposed finding and independently dispose of that proposed finding; rather, it is sufficient that the agency provide in its decision a written foundation upon which the reviewing court may assure that all proposed findings of fact have been consider and ruled upon and not overlooked or concealed. Id. at 1090. The Court held that it could discern from the substance of the order that each of the proposed findings were addressed, and to the extent the technical requirements of Section 120.59(2), Fla. Stat., were departed from, the departure did not materially impair the fairness or correctness of the proceedings. Id. at 1091. LBCA merely has to compare the hearing officer's findings with its proposed findings to discern those portions accepted. Therefore, the exception is rejected. RULING ON MOTION FOR REMAND Pursuant, to Rule 1.540(b), Fla. R. Civ. P., LBCA has filed a Motion for Remand asserting that newly discovered evidence establishes that a finding by the hearing officer is inaccurate because of allegedly false testimony by District expert witness, Dr. Larry Lee. The hearing officer found that Lake Brooklyn had been in a period of decline before and after the 1989 aquifer pump test and that due to rainfall deficits Brooklyn Bay was separated from the main body of Lake Brooklyn for at least 18 to 24 months before and during the 1989 aquifer performance test. The hearing officer determined that the rate and character of declines during the pumping were not distinguishable from the declines occurring before and after the test. Thus, he found that impacts to Lake Brooklyn water levels from the pumping were indistinguishable from the declines due to drought. (Finding of Fact No. 30). LBCA asserts that a newly discovered Department of Transportation (D.O.T.) survey, dated October 11, 1988, shows that Brooklyn Bay was not segregated from the remainder of the lake due to drought conditions prior to the 1989 aquifer pump test as testified by Dr. Lee and seeks the Board to remand the issue to the hearing officer for consideration of this new evidence. The only reasons for remand regarding fact finding are if an erroneous legal conclusion by a hearing officer warrants taking of evidence on the issue, or if a factual issue was never ruled upon by the hearing officer. See Miller v. Dept. Envt'l Reg., 5504 So.2d 1325 (Fla. 1st DCA 1987)(agency's modification of legal conclusions necessitated factual findings on issue which hearing officer had initially disregarded as irrelevant) and Cohn v. Dept. of Prof. Reg., 477 So.2d 1039 (Fla. 3d DCA 1985)(when the hearing officer fails to find a specific fact, agency must remand to the hearing officer to do so). Clearly, neither of these reasons have any application to Petitioner's arguments. Although subsection 40C-1.512, F.A.C., provides that the Florida Rules of Civil Procedure are applicable to District administrative proceedings to the extent not inconsistent with Chapter 120 or Chapter 40C-1, the applicability of Rule 1.540(b), Fla. R. Civ. P., is problematic and inconsistent with a subsection 120.57 proceeding. First, the civil procedure rule only applies to final judgments and in this subsection 120.57 administrative proceeding LBCA is attempting to apply the civil procedure rule to a nonfinal recommended order. Second, LBCA has not expressly excepted Finding of Fact No. 30 as not supported by competent substantial evidence or that a Board rule or policy has been incorrectly interpreted /1 , but actually seeks the Board to allow LBCA to supplement the record after remand with new facts for the hearing officer to weigh in applying those facts to the applicable District rules. Thus, unlike a trial court, Finding of Fact No. 30 cannot be altered by this Board if supported by any competent substantial evidence. Section 120.57(1)(b)10., Fla. Stat.; Freeze v. Dept. of Business Regulation, 556 So.2d 1204 (Fla. 5th DCA 1990); School Board of Leon County v. Weaver, 556 So.2d 443 (Fla. 1st DCA 1990). The Board may only consider whether the findings actually made by the hearing officer are sustained by the evidence, and whether, if so, they support the recommended legal conclusions. Cohn v. Dept. of Professional Regulation, 477 So.2d 1039 (Fla. 3d DCA 1985). Unlike a judge with plenary and equitable powers in a judicial setting, this Board, under Chapter 120, cannot authorize fact- finding after a hearing's conclusion except in the most narrow circumstances, none of which are applicable to the motion before the Board. Cf. Manasota 88, Inc. v. Tremor, 545 So.2d 439 (Fla. 1st DCA 1989)(may remand if hearing officer makes erroneous legal interpretation); Cohn, supra.. (may remand if a necessary factual issue was not determined by the hearing officer); Friends of Children v. DHRS, 504 So.2d 1345 (Fla. 1st DCA 1987)(may remand if hearing officer makes erroneous evidentiary ruling). In effect, LBCA wants to utilize a civil procedure rule for the Board to authorize additional fact-finding on a matter already considered by the hearing officer regarding a finding supported by competent substantial evidence. Section 120.57, Fla. Stat., simply does not authorize the Board to take such action. Section 120.57(1)(b)10, Fla. Stat.; Dept. of Transportation v. J.W.C. Co., Inc., 396 So.2d 778 (Fla. 1st DCA 1981)(chapter 120 does not allow additional or cumulative evidence on matters already considered and the APA does not envision a never-ending process). Consequently, the application of Rule 1.540(b), Fla. R. Civ. P., is inconsistent with Chapter 120 and LBCA is free to raise any alleged error at hearing on appeal of the final order. Even assuming Rule 1.540(b), Fla. R. Civ. P., is applicable to this subsection 120.57 proceeding, LBCA has failed to clearly establish the extraordinary circumstances warranting the granting of its motion. The material issue of whether FRI's proposed pumping would impact the area lake levels already effected by a rainfall deficit was expressly raised by LBCA in its initial petition for hearing as far back as August 1992 and was also an issue stipulated in the Prehearing Stipulation prior to the February 1993 hearing. (Petition for Administrative Hearing paragraph f. 2, 3, 4.; Prehearing Stip. paragraphs B. 2, G. 1). Consequently, LBCA had over five months prior to hearing to elicit all relevant evidence to that Issue. If Rule 1.540(b) was applicable, LBCA's burden would be to clearly establish the following to receive relief: (1) it must appear that the evidence is such as will probably change the-result if a new trial is granted; (2) that it has been discovered since the trial; (3) that it could not have been discovered before one trial by the exercise of due diligence; and (4) that it is material and not merely cumulative or impeaching. City of Winter Haven v. Tuttle/White Construction Inc., 370 So.2d 829 (Fla. 2d DCA 1979); King v. Harrington, 411 So.2d 912 (Fla. 2d DCA 1982), rev denied, 418 So.2d 1279 (Fla. 1982). The predicate for LBCA's motion is that Dr. Lee's testimony regarding the lake separation was false, therefore LBCA could not have exercised due diligence in discovering the alleged new evidence. LBCA has filed no express exception with record support establishing that Finding of Fact No. 30 is not supported by competent substantial evidence and therefore the Board by law cannot alter that factual finding. Section 40C-1.564(3), F.A.C.; Section 120.37(1)(b)10., Fla. Stat.; Freeze, supra.. Consequently, Dr. Lee's testimony is not false. Importantly, Dr. Lee's testimony was not the only evidence supporting this finding. LBCA's own witness, the president of the association, testified that Brooklyn Bay had been segregated for four or five years from the main part of the lake and that he had been able to walk across the lake without getting wet for the last four or five years. (T. 863, 870). Likewise, LBCA's own expert stated that Lake Brooklyn's condition between 1989 to 1991 had receded to such an extent as it was no longer a continuous lake. (T. 317). Accordingly, the predicate for LBCA's motion is factually inaccurate and misplaced. Furthermore, LBCA must clearly establish that even though the exercise of due diligence before the hearing, it would not have discovered the 1988 D.O.T. survey. Brav v. Electric Door-Lift Inc., 558 So.2d 43 (Fla. 1st DCA 1989)(movant's burden to establish due diligence); Plisco v. Union Railroad Co., 379 F.2d 15 (3d DCA 1967)(motion for new trial on newly discovered evidence is granted only where extraordinary circumstances are present). Even though the effects of FRI's proposed pumping on lake levels in time of rainfall deficit was an issue dating back to August 1992, LBCA asserts that it could not have obtained the survey prior to hearing in February 1993 "because of the logistics of requesting public records and the delay in delivery of same." LBCA could have reasonably anticipated that witnesses would testify regarding the disputed issue, particularly its own witnesses, and obtained the survey with the exercise of due diligence. LBCA offers no basis why D.O.T. would not have supplied the survey as required by law or that LBCA could not obtain it and, in fact, the public records law contains a provision for obtaining immediate relief if a request for records is denied. See subsection 119.11, Fla. Stat. In Florida Audubon Society v. Ratner, 497 So.2d 672 (Fla. 3d DCA 1986), a 1981 judgment had been entered finding that limestone mining would be inconsistent with the water management purposes of a water management district's flowage easement on platiff's property. Plaintiff sought a new trial because of newly discovered opposing evidence in a 1980 Corps of Engineers report on the effects of limestone mining. The trial court denied the motion. The appellate court agreed finding that the granting of such motions was disfavored and that the report was prepared in September 1980 well before the trial and judgment in June 1981 and could have been discovered prior to the with the exercise of due diligence. Likewise in this proceeding, the proffered D.O.T. survey was prepared in October 1988, nearly four and one-half years before the February 1993 hearing and LBCA has failed to show that due diligence would not have discovered the survey prior to the administrative hearing in this proceeding. See also, Morhaim v. State Farm Fire & Casualty Co., 559 So.2d 1240 (Fla. 3d DCA 1990)(no new trial granted based on post-judgment affidavits regarding evidence on known issue that could have been discovered prior to trial). LBCA also asserts that Dr. Lee misrepresented the contents of Clark's "Report of Investigations No. 33-Hydrology of Brooklyn Lake Near Keystone Heights, Florida" regarding its conclusions and his opinion concerning the separation of Brooklyn Bay from Lake Brooklyn and thus prejudiced LBCA's case. LBCA argument is an attack on the weight of the conflicting evidence which is the job of the hearing officer to resolve. An expert witness is not required to disclose the facts and data underlying his opinion. Marks v. Marks, 576 So.2d 859 (Fla. 3d DCA 1991). LBCA could have cross examined Dr. Lee regarding the separation. LBCA was aware of the "Clark Report" (T. 844) and even anticipated testimony regarding water levels in its case in chief (T. 846). Indeed, the report was listed by LBCA as its Exhibit 13 in the Prehearing Stipulation, although LBCA chose not to introduce it into evidence during the hearing. Dr. Lee testified not once but twice about the location of the staff gauge (T. 946 and 962-966). On cross, LBCA did not inquire about the location of the staff gauge or the lack of water beneath the bridge. (T. 991-1017). It was LBCA's burden to challenge the factual basis for Dr. Lee's opinion. City of Hialeah v. Weatherford, 466 So.2d 1127 (Fla. 3d DCA 1985). An insufficiency in the expert opinion offered, if any, should have been addressed in cross-examination by LBCA, not by a post-hearing motion. LBCA alleges that the outcome would be different if the DOT survey were part of the evidence. The Board cannot accept new evidence or rule on the admissibility of evidence which was not presented to the hearing officer. The Finding of Fact to which LBCA refers states six reasons why the correlation between the pumping at the sand mine and its effects on Lake Brooklyn water level were not established. See Recommended Order, Finding of Fact 32. The location of the staff gauge in Brooklyn Bay rather than Lake Brooklyn was one of those six. LBCA's error was in not knowing the location of the staff gauge (T. 418-420) rather than the testimony of Dr. Lee. Therefore, LBCA's allegation that but for the testimony of Dr. Lee, the hearing officer would have found differently is unfounded. The mere chance that the hearing officer might have found differently is insufficient to remand the hearing for additional fact finding. Cluett v. Dep't of Professional Regulation, 530 So.2d 351, 355 (Fla. 1st DCA 1988). The courts look with disfavor on motions based on newly discovered evidence because to look with favor would bring about a looseness in practice and encourage counsel to neglect to gather all available evidence for a first trial by speculating upon the outcome, and then, being defeated, become for the first time duly diligent in securing other evidence to cure the defects or omissions in their showing upon the first trial. Rushing v. Chappell, 247 So.2d 749 (Fla. 1st DCA 1971); Henderson Sians v. Fla. Dept. of Transp., 397 So.2d 769 (Fla. 1st DCA 1981). It is well-settled that no abuse of discretion occurs on the part of an agency by refusing to direct a remand to receive evidence which could have been introduced during the course of the original proceedings. Department of Transportation v. J.W.C., Inc., 396 So.2d 778 (Fla. 1st DCA 1981) LBCA has failed to clearly establish a right to relief and therefore the motion is denied. RULING ON MOTION FOR OFFICIAL RECOGNITION AND MOTION TO SUPPLEMENT THE RECORD LBCA has filed a Motion for Official Recognition and to Supplement the Record seeking the Board to accept into evidence the October 11, 1988 D.O.T. survey which was the subject of LBCA's Motion for Remand and also the U.S.G.S. publication "Report of Investigations No. 33-Hydrology of Brooklyn Lake Near Keystone Heights, Florida", by Clark, also referenced In LBCA's Motion for Remand. The Board is not a fact-finder in this subsection 120.57 proceeding and it is reversible error for the Board to supplement the record through post-hearing evidence. Section 120.57(1)(b)10, Fla. stat., Marks v. Northwest Florida Water Management District, 566 So.2d 46 (Fla. 5th DCA 1990)(court refused to take judicial notice of factual matter based on records that could have been offered at administrative hearing); Nest v. Dept. of Professional Regulation 490 So.2d 987 (Fla. 1st DCA 1986); Shongut v Mark, 173 So.2d 708 (Fla. 3d DCA 1965)(Where matters raised on motion for relief from judgment could have been available to movant during trial proceedings, denial of motion was not abuse of discretion); Weaver, supra.. Moreover, the Motion for Remand has been denied. LBCA's post- hearing motions will be available as part of the record of this proceeding for purposes of any appeal which may be pursued. ACCORDINGLY, IT IS HEREBY ORDERED: The Recommended Order dated June 4, 1993, attached hereto as Exhibit A, is adopted in its entirety except as modified by the final action of the Governing Board of the St. Johns River Water Management District (Ruling on LBCA Exception 23). Florida Rock Industries' application for consumptive use permit no. 2-019-0012AUR is hereby granted under the terms and conditions as provided herein. The post-hearing Motion for Remand, Motion for Official Recognition and Motion to Supplement the Record filed by LBCA are hereby denied. DONE AND ORDERED this 14th day of July 1993, in Palatka, Florida. ST. JOHNS RIVER WATER MANAGEMENT DISTRICT By: JOE E. HILL CHAIRMAN RENDERED this 14th day of July 1993. By: SANDRA L. BERTRAM ASSISTANT DISTRICT CLERK
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background Respondent, Florida Rock Industries (FRI or applicant), a Florida corporation, operates a nine hundred and eighty acre sand mine known as the Goldhead Sand Mine (Goldhead) in Clay County, Florida. The mine is located approximately six miles northeast of Keystone Heights and fifty miles southwest of Jacksonville. FRI has operated the mine since 1958. With the exception of eighty acres of land owned by FRI, the remainder of the land on which the mine is located is owned by Carroll-Phillips Investors and has been leased to FRI since 1973. The mine lies within the jurisdictional boundaries of respondent, St. Johns River Water Management District (District), a special taxing district created by the legislature and charged with the responsibility for administering and enforcing permitting programs for consumptive uses of water. FRI is accordingly subject to the District's regulatory authority. As a necessary component of its operation, FRI withdraws approximately 2.09 million gallons per day (MGD) of groundwater from the Floridan Aquifer which is used in the production of sand. This use of water is made pursuant to a consumptive use permit (no. 2-019-0012U) issued to FRI by the District on December 11, 1984, and which allows it to consume 762.85 million gallons per year of groundwater for hydraulic dredging, cleaning and purification of sand at the Goldhead mine. The permit was issued for seven years. In order to continue groundwater withdrawal and use, FRI has applied to the District for a seven-year renewal of its permit with no request for an increase in allocation. That request, which has been identified as application no. 2-019-0012AUR, is the subject of this proceeding. After conducting a review of the application, making site inspections, and performing various studies and analyses, on July 28, 1992, the District, through its staff, gave notice of its intent to approve the application with certain conditions. Thereafter, on August 6, 1992, petitioner, Lake Brooklyn Civic Association, Inc. (petitioner), a nonprofit corporation made up of property owners in adjacent areas of Clay County, filed a petition under Subsection 403.412(5), Florida Statutes, seeking to contest the proposed action. Petitioner is a citizen of the state and has an interest in activities that may injure or harm the state's water resources. Thus, it has standing to bring this action. As twice amended, the petition generally alleged that the consumptive use would (a) cause an unmitigated adverse impact on adjacent land uses, including a significant reduction in water levels in Lake Brooklyn and Spring, Gator Bone, and White Sands Lake, which lie generally to the south and southwest of the mine site, (b) cause a deterioration in water quality, (c) cause economic or environmental harm, and (d) be for purposes other than operating a sand mine. The broad three-pronged test to be used in determining whether the permit should be issued is whether the proposed consumptive use is a reasonable- beneficial use, whether it will interfere with presently existing legal uses of water, and whether it is consistent with the public interest. In addressing this test, the parties have presented extensive expert testimony involving highly technical subject matter. As might be expected, the experts reached different conclusions as to whether the criteria have been met. In resolving these conflicts, the undersigned has accepted the more credible and persuasive evidence, and this accepted testimony is recited in the findings below. The Mining Site Operations The entire mine site is around 7,000 feet east to west, about one mile north to south in a rectangular shape, and lies within the lake region of northeast Florida. The mine's product is silica sand used for concrete and masonry mortar for construction throughout northeast Florida. As such, it produces an economic benefit to the region. The mine is located on one of the few sites in the northeast Florida area with deposits suitable for construction purposes and is the closest sand mine to the Jacksonville market. In 1958, FRI installed three ten-inch diameter production wells in the center of the mine site. One well is 450 feet deep while the other two are 460 feet deep. The 1984 permit authorizes withdrawals of 762.85 million gallons of water per year, an average rate of 2.09 MGD, and a maximum rate of 3.75 MGD. This rate is consistent with the amount of water used at other mines in north Florida and is based on FRI's projected maximum annual use. The use is industrial commercial for sand mining while the source is the Floridan Aquifer, the lowest acceptable water quality source available capable of producing the requested amount of water. Water use withdrawal from the three wells is monitored by in-line flow meters installed in 1991 as a water control and conservation measure. The pumping rate depends on the number of fixtures and valves open in the system at the time of pumping. However, the actual rate of water production cannot be varied at any of the pumps since the wells are connected to "on or off" pumps. The need for water in the dredge pond and processing plant dictates how long FRI will have a pump in operation. Water from the wells is first discharged into a dredge pond, twenty feet deep, which is an approximately 155-acre excavation lake located in the southwest portion of the mine site. In periods of low water, the water is used to float the dredge, which requires some three feet of water to float, and in conjunction with a bulldozer, to wash sand down from the bank toward the dredge. After the dredge sucks up sand and water from the bottom of the pond, this mixture is slurried to an on-site processing plant where more water is added to sort and wash the sand. The end product (silica sand) is then loaded onto trucks which haul the product to the market. After processing, the moisture content of the sand product is only 5 percent. The tailings (unusable waste product) and wash water are then routed by a slurry pipe to settling areas and eventually recirculated through a system of ditches, canals and water control structures back into the dredge pond. No chemicals are used in the operation. Although FRI's contract with the lessor of the property requires it to maintain the dredge pond elevation at a specified elevation, this requirement cannot be fulfilled during drought conditions. The mining operation is a closed system to the extent there is no point source (surface water) discharge from the system. Even so, a significant amount of water loss occurs during the process, mainly through percolation into the ground. Other water loss occurs through evaporation. The receiving water from the site is primarily the surficial aquifer which recharges the downgradient lakes, including Gator Bone, White Sands, and Spring Lakes. Water may also travel through the surficial aquifer into the sinkholes on site and thence to the Floridan Aquifer. However, not all water is lost to sinkholes in the settling area because they are filled with fine materials. This is confirmed by the fact that water returns to the dredge pond. The mining operation has not affected this pattern. The lakes in the region are replenished solely by rainfall, either by direct rain on the lakes or through water seeping through sands. FRI plans to mine approximately thirty additional acres at the Goldhead Site during the next seven years. To this end, it has secured a management and storage of surface waters permit from the District which allows construction of this additional acreage. It also has acquired an industrial waste water discharge permit from the Department of Environmental Regulation. It is expected that within the next two to four years, FRI will abandon the current dredge pond and start a new one on the north side of the property to accommodate mining operations, or in the alternative, extend the current pond to the north. Water conservation A water conservation plan has been submitted by FRI. Measures already implemented include (a) using in-line flow meters to monitor amounts of withdrawal, (b) not pumping for more than seventeen hours per day to prevent exceeding the maximum allotment per day, (c) regularly monitoring withdrawals to ensure allocations as not being exceeded, (d) extending the plant discharge further past the sinkholes in the settling area to maximize return water to the dredge pond, (e) raising water levels in the settling area to facilitate flow back to the dredge pond, (f) during periods of drought using bulldozers instead of water spray to break loose sand formations, (g) curtailing production when further production would cause the plant to exceed allocations, (h) replacing water-cooled bearings in plant machinery with bearings that do not require water, and (i) restricting dredge mobility to allow operation in shallower water. No other water conservation measures are economically, environmentally or technologically feasible. Hydrogeologic characteristics at the mine site The mine site, which is located within the Upper Etonia Creek surface water drainage basin, generally slopes from 200 feet NGVD on the north to 120 feet NGVD on the south, and is underlain, in order, by approximately 10 to 50 feet of sand (known as the surficial aquifer), 200 feet of dense, moist clay (known as the Hawthorn Formation), and then a highly transmissive limestone formation (known as the Floridan Aquifer). The surficial aquifer flows from north to south across the site while water falling on the site primarily moves downgradient through the surficial aquifer. There are five sinkholes on the site, all having predated the mining activities, which may provide a conduit for recharge from the surficial aquifer to the Floridan aquifer. Except where the Hawthorn formation, a confining unit to the Floridan aquifer, is breached, recharge through the Hawthorn formation is very slow because of the dense clays of that formation. Aquifer characteristics within the Floridan aquifer beneath the site and immediately adjacent thereto are relatively uniform. As noted earlier, 5 percent of the water leaves the mine site as moisture in the sand product. The remaining 95 percent of water is immediately recharged on site to the surficial aquifer through various impoundments, and after entering the surficial aquifer, that portion of the water which is not recirculated to the dredge pond for reuse in the mining process moves either vertically into the Hawthorn formation, vertically into the Floridan aquifer through a sinkhole, downgradient through the surficial aquifer to one of the lakes south of the mine, or evaporates. It is noted that notwithstanding the mining operations, the flow in the surficial aquifer system still parallels the topography as it existed prior to mining, and the same saturated thickness within the surficial aquifer exists on site as existed before mining occurred. Hydrogeologic Characteristics of the Region The region in which the mine is located is very high in topographic altitude indicating that it is a groundwater recharge area. Like the mine site, the region has three distinct geologic units underlying the surface, including sands and clayey sands (surficial aquifer), thick clays (Hawthorn formation) and limestones and dolomites (Floridan aquifer). The Hawthorn unit serves as a confining unit or semi-confining unit between the surficial aquifer, or water table, in the upper unit and the Floridan aquifer in the lower unit. When solution channels develop within the limestones in the lower unit, the openings can cause the overlying units to collapse, forming sinkholes. Thus, when the Hawthorn formation is breached by the development of a sinkhole, water can move rapidly through the overlying units to the Floridan aquifer. Many of the lakes within the region exist over collapsed features within the limestone units beneath them and are referred to as sinkhole lakes. The rate of recharge from each lake depends on the rate of leakance into the Floridan aquifer. Some lakes leak fast, others not at all. For example, Lake Brooklyn fluctuates about two feet, Lake Johnson about thirteen feet, and Pebble Lake about thirty feet. Lake Brooklyn, which lies several miles to the southwest of the mine, is the fourth lake in a chain of lakes consisting of Blue Pond, Sand Hill Lake, Lake Magnolia, Lake Brooklyn, Keystone Lake, Lake Geneva, Oldfield Pond, and Half Moon Lake. All of these lakes are in a different surface water drainage sub-basin within the larger Upper Etonia Creek Basin than the mine site. The lakes above Lake Brooklyn in the chain are at higher elevations than Lake Brooklyn, and when rainfall is sufficient, water flows from Blue Pond to Sand Hill Lake, to Lake Magnolia, and then to Lake Brooklyn through Alligator Creek. Direct rainfall and surface water inflows from Alligator Creek represent the most significant sources of water to Lake Brooklyn. Other pertinent lakes in the area are Spring, White Sands and Gator Bone Lakes, which lie almost directly along the mine site's southern boundary and are each less than a mile from the mine's dredge pond. During the period records have been maintained for water levels in Lake Brooklyn, it has fluctuated over a range of slightly more than twenty feet. Although average rainfall within the Upper Etonia Creek Basin is approximately fifty-one inches per year, during the period from 1974 through 1990 the basin experienced a continuing period of below normal rainfall resulting in a cumulative deficit of rainfall for this period of minus seventy-eight inches. Since 1988, the lake region has experienced a severe drought. Because the lakes in the region have risen or fallen in correlation with periods of below normal or above normal rainfall, lake levels have fallen dramatically in recent years. Water levels in Lake Brooklyn began declining in 1974 at the same time the period of below normal rainfall began and continued declining until 1991, a year in which the region experienced above normal rainfall. These low water levels were exacerbated by the cessation of surface water inflows from Alligator Creek in late 1988 which continued until late 1992 when such flows resumed. The cessation of surface water flows into Lake Brooklyn during the period from 1988- 1992 were a direct consequence of the extended period of below normal rainfall in the region. Finally, very little, if any, of the groundwater flowing in the Floridan aquifer beneath Lake Brooklyn flows toward the mine site. Water Quality Impacts Numerous analyses have been conducted to determine water quality of the site, water quality in nearby homeowners' water systems, and water quality impacts of the proposed consumptive use. They include analyses conducted by the District in 1989 and 1992, including sampling of water quality and an analysis of the background levels for certain parameters, and an assessment of data from HRS testing in March 1989 and May 1992. In addition, FRI conducted water quality sampling on site in eight wells, the dredge pond and a settling pond. Finally, petitioner reviewed water quality samples from off-site private water supply wells taken on March 1, 1989, and on July 22, 1992, by unknown persons. As to this latter sampling, petitioner had no knowledge of the protocol used in obtaining the 1989 samples and offered no evidence of reliability of the 1992 data. Thus, the reliability of its assessment is in doubt. None of the water quality samples taken from the mine site indicate a violation of state water quality standards. However, petitioner posits that a chemical reaction is likely occurring at the deeper levels of the dredge pond, possibly causing undissolved iron in sediments to become dissolved, and then traveling in solution through the clays of the Hawthorn formation into transmissive units and finally to off-site homeowners' wells which may be in those units. This theory was predicated on the results of 1989 HRS sampling which revealed some wells near White Sands Lake experienced elevated levels of iron and manganese, and an assumption that a chemical reaction was occurring because herbicides were used in the dredge pond. However, only one application of a herbicide occurred, and that was in 1990, or one year after iron was detected in the off-site homeowners' wells. Petitioner agreed that the 1990 application of herbicide could not have affected the 1989 sampling. It also agreed that these reactions were less likely to be occurring in a pond with water flowing through it. In this case, water is circulated through the dredge pond by being pumped into it, pumped out of it, and allowed to flow back into the pond. FRI determined that no state water quality standards were exceeded for iron, manganese, zinc, turbidity, total dissolved solids, chloride and nitrate in the surficial aquifer and Hawthorn formations at the site. The wells used for monitoring water quality were installed and sampled using standard quality assurance techniques. Water quality from the surficial aquifer was emphasized because if iron or manganese were present in the water, it would most likely be detected in wells in the surficial aquifer because they are detected in wells immediately downgradient of the source. If the chemical reaction is occurring, water leaving the dredge pond is contaminated, and such water will follow the path of least resistance by going either to the Hawthorn formation or the surficial aquifer. Because of the geologic properties of the Hawthorn, this path is the surficial aquifer. At least 70,000 gallons per day enter the surficial aquifer from the bottom of the dredge pond. Since contaminated water would receive water quality treatment by absorption of the Hawthorn but not in the surficial, water in the surficial aquifer represents the worst case scenario as to the possible presence of contaminated water. The chemical reactions which petitioner believes may be occurring in the deeper portions of the dredge pond require the presence of an acidic environment and reduced oxygen levels in the water. FRI's water quality testing indicates that water in the dredge pond is not acidic, but rather is neutral. Therefore, any reaction which might be occurring could not be on a large enough scale to affect water quality. Moreover, even if the reactions were occurring, it was established that the clays in the Hawthorn formation would absorb iron, and such absorption would not take place in the surficial aquifer. Therefore, it is found that there would be no adverse impact to groundwater including the surficial aquifer and that water quality standards will be met. Although petitioner presented evidence that in 1989 HRS testing of 12 out of 212 homeowners south of the mine site indicated that three homeowners had iron concentrations in excess of state drinking standards and two had manganese concentrations in excess of state drinking water standards, this is insufficient to prove that the mining operation has an adverse impact on water quality. To begin with, some of the wells sampled were thirty to fifty years old even though the life expectancy of a well is fifteen to twenty years. Some were constructed of galvanized steel pipe, and those wells also indicated high turbidity levels. High turbidity levels are caused by a number of unrelated factors and will result in increased iron levels that are not representative of the quality of the groundwater in the formation, but rather of the iron-laden sediments in the formation, or from the casing material. With the exception of one well (the Sutton well), the water from the homeowners' wells did not exceed background water quality for iron and manganese. The elevated iron and manganese concentrations in the Sutton well are caused by a number of factors other than the mine. Then, too, a proper sampling technique may not have been followed during the 1989 sampling event thus rendering the results unreliable. Finally, properly constructed monitoring wells should be used to assess the quality of the groundwaters, and the wells sampled in 1989 and 1992 were not of that type. The Mine's Impact on Water Levels Perhaps the issue of primary concern to members of petitioner's organization is whether the mining operations have contributed to the decline in water levels of nearby lakes, including Lake Brooklyn. This is because of serious declines in the levels of those water bodies over the past years, and a concomitant decrease in the value of homes which surround the lakes. In an effort to resolve this and other water level issues, the parties made numerous studies of the current and anticipated water level impacts from the site. This data collection effort was far more extensive than is normally conducted for a mine of this size. They included aquifer performance tests by FRI and the District, steady state and transient computer modeling of impacts on the Floridan and surficial aquifers by FRI, an analysis of correlations of pumping and water level changes in lakes and aquifers by FRI and petitioner, photolinear and fracture trace analyses of structural conditions by FRI and petitioner, a stratigraphic analysis of a geologic core retrieved from the site by FRI, installation of deep and shallow wells for groundwater monitoring by FRI, groundwater flow mapping by FRI, review of literature by all parties, review and analysis of rainfall data by all parties, analysis of evaporation data by the District and petitioner, and an analysis of geophysical logs from wells by FRI and the District. Aquifer performance tests Aquifer performance tests, which enable hydrologists to reach conclusions regarding the characteristics of the aquifers tested, were conducted in January 1989 by the District and June 1991 by FRI. In a typical pump test, an aquifer production well pumps at a constant rate, while water levels are monitored in observation wells at specified distances from the pumping well. In this case, the tests measured effects of pumping from the mine production wells for periods ranging from 78 hours to 108 hours at approximately twice the average rate of 2.09 MGD. The zone of influence of pumping was measured at wells placed at the property boundaries, at Gold Head State Park, east of the mine, as well as wells to the south of the mine for the 1989 tests. During the 1989 tests, lake levels for Lake Brooklyn and Gator Bone, White Sands and Spring Lakes were recorded. The effects of pumping were approximately equal for wells spaced approximately equal distances along the east, south and west. Thus, for purposes of analysis, the Floridan aquifer was considered isotropic and homogeneous. This is consistent with assumptions commonly made by geologists in Florida. Computer models were calibrated with actual results of these tests to account for variations caused by this assumption. The District has concluded, and the undersigned so finds, that no changes in the levels of the lakes are attributable to pumping. Further, the aquifer itself will not be harmed by the use of the amount of water requested in the application. The tests indicate the maximum amount of drawdown in the Floridan aquifer from pumping at twice the average rate is 0.1 to 0.6 foot in neighboring wells. Effects of actual pumping will be approximately one-half the test observed amounts on an average pumping day. For example, based on the 1989 test results, drawdowns in the Floridan aquifer at the boundary of the FRI property during an average day of pumpage should not exceed 0.2 to 0.3 feet while drawdowns beneath Spring, White Sands and Gator Bone Lakes to the south of the mine should be less than 0.2 feet. The tests provide actual measurements of the effects of pumping. Indeed, all three lakes were declining before the 1989 test began and continued to decline after the test was ended. However, the rate of decline during the seventy-eight hours of the test was not distinguishable from declines which occurred before or after the test. Computer modeling As a supplement to the aquifer performance tests, FRI performed computer modeling to determine effects of the water withdrawal and use on the Floridan and surficial aquifers. These models are used by hydrologists to predict impacts associated with a particular source of stress, such as pumpage, to an aquifer and, in this case, occurred in three phases. The first was an impact model which determined the drawdown in the Floridan aquifer. The second occurred as a result of questions raised by residents of the sand mine area and included a "steady state" model simulation of impacts of the Floridan and surficial aquifers. The third occurred as a result of questions raised by petitioner and included new data along with both a "transient state" and "steady state" simulation. All three phases of modeling were consistent in finding that the effects of pumping are non-existent or negligible, that is, a predicted drawdown in various locations of the Floridan aquifer of from less than 0.1 to 0.3 feet on an average pumping day, and they corroborated the drawdowns observed during both the 1989 and 1991 aquifer performance tests. Petitioner's witness Dr. Stewart criticized FRI's 1992 "steady state" computer modeling on the grounds FRI had insufficient data to conduct the modeling, the constant head boundaries were set too close to the pumping, a transient model should have been run, and the modelers assumed that the Floridan aquifer is isotropic and homogeneous. However, Dr. Stewart failed to review or consider (a) any technical data or information gathered since September 10, 1992, (b) the 1991 transient model, (c) the December 1992 transient model, (d) the computer disc for the July 1992 steady state model, (e) the December 1992 steady state model, (f) the December 1992 calibration, (g) the basis for setting the constant head boundaries, or (h) the data from the 1989 and 1991 pump tests. All of this data was part of the evidence FRI's experts used in formulating their opinions. Dr. Stewart agreed that he could not form any conclusions on this data and that the Floridan aquifer is rarely completely homogeneous and isotropic, but that he and other modelers regularly make that assumption. The modeling was calibrated to replicate actual subsurface and pumping conditions. Maximum drawdown in the Floridan aquifer under normal pumping conditions is modeled to be 0.1 to 0.2 feet beneath White Sands Lake. This is drawdown with no replacement, although there will be leakance back to the Floridan aquifer through sinkholes on the site and surcharge to Gator Bone, White Sands and Spring Lakes through the surficial aquifer. The impact to the Floridan is minor compared to normal water level fluctuations in that aquifer of 3 to 5 feet per year. In fact, barometric pressure changes can cause water level changes of up to one foot per week. Lake levels Because many of the lakes in the area leak downward, water levels in the lakes could be affected by the changes in levels in the Floridan aquifer. Indeed, for lakes connected to the Floridan aquifer, changes in the level of the potentiometric surface (or pressure) in the Floridan aquifer can have an impact on the level of the lakes. However, a decrease in lake levels will be less than that of the decrease in the Floridan aquifer, depending on the rate of leakance. Consequently, even if Lake Brooklyn and Gator Bone, White Sands or Spring Lakes do leak to the Floridan aquifer, the amount of decline in lake levels attributable to pumping at the mine will be less than the 0.1 to 0.2 foot modeled by FRI. This drawdown effect will not accumulate over time, but rather will remain constant after reaching steady state conditions. Even if levels in Gator Bone, White Sands and Spring Lakes are affected by drawdowns in the Floridan aquifer, that effect will be more than offset by surcharge to the surficial and Floridan aquifers from the dredge pond. The net effect to the lakes would be either positive or immeasurable. This is confirmed by the computer modeling results. Lake stage and precipitation data for Spring, White Sands and Gator Bone Lakes indicates that these lakes, like other lakes in the region, rise and fall in correlation with precipitation patterns. For example, in 1991, a year with above normal rainfall, Spring Lake rose 4.1 feet in elevation, White Sands Lake 2.9 feet in elevation, and Gator Bone Lake rose 3.5 feet in elevation. Similarly, water levels were monitored before, during and after the 1989 aquifer performance test in a portion of Lake Brooklyn known as Brooklyn Bay. Because of low rainfall, Brooklyn Bay was separated from the main body of Lake Brooklyn for at least eighteen to twenty-four months before and during the 1989 aquifer performance test. The lake had been in the midst of a long term decline both before and after the test, and the rate and character of declines during the period of pumping were not distinguishable from the declines occurring before or after the test. It is accordingly found that the impacts on water levels in Lake Brooklyn, if any, as a result of pumping from the Floridan aquifer are immeasurable. According to petitioner's witness Boyes, activities at the mine have an influence on water levels in Gator Bone, White Sands and Spring Lakes by "increasing the rate of decline". However, the witness could not quantify the degree of impact but stated the impacts during the 1989 aquifer performance tests were a decline of .03, .03 and less than .03 foot, respectively, for each lake. The witness also opined that, based on District staff guage readings during the 1989 aquifer performance testing, pumping at the mine resulted in a .04 foot decline in lake level for Lake Brooklyn during the 1989 testing period. This decline had a net result of .8 acre decrease in the previously 600 acre plus Lake Brooklyn. By comparison, the drought caused a decline of 162 acres in 1989 and an additional 158 acres in 1990. It is noted that the decline in each lake would be less during average pumping conditions, or about one-half of the .04 foot decline, since average pumping is one-half of the aquifer performance test pump rate. Finally, petitioner's witness Dr. Stewart opined that there is insufficient data to determine whether any impacts to lake levels are occurring. It is found, however, that these drawdowns are less than the .1 to .2 foot modeled by FRI and should have no significant adverse impacts on water levels. Preferential flow theory Petitioner presented evidence of a purported correlation between pumping at the mine and water levels in a Floridan aquifer well located on the southwest side of Lake Brooklyn, 4.3 miles from the mine, and lake levels in Brooklyn Bay, 3 miles from the mine. According to petitioner, this serves as proof of a "preferential flow pattern" in the Floridan from Lake Brooklyn to the mine, and that this preferential flow results in a .04 to .05 foot drawdown in the Floridan aquifer at Lake Brooklyn. However, this correlation is deemed to be incorrect for several reasons. First, if a true correlation existed, recovery from pumping effects would occur after pumping ceased, but the Lake Brooklyn well showed recovery in the Floridan aquifer prior to cessation of pumping, and did not recover when pumping stopped at the end of the 1989 aquifer performance testing. Second, if the premise is correct, impacts from pumping would occur in wells closer to the pumping earlier than in wells farther away, but the Lake Brooklyn well, 4.3 miles from pumping, showed drawdown began before that of the Goldhead well, only 1,000 feet from pumping. Third, levels for the Lake Brooklyn well should have declined during both the 1989 and 1991 aquifer performance tests but the levels rose during the 1991 tests. As to the water level changes in the well during the 1989 test, witness Boyes believed these may reflect declines due to hydrologic conditions rather than the pump test. Fourth, if a true correlation existed, impacts would be experienced following the same hydrographic pattern as pumping, but the Lake Brooklyn well's hydrographics did not correlate to the pumping schedule at all times of the year. It should also be noted that at least two other large scale water users are withdrawing water from wells within 1.25 miles from the Lake Brooklyn well and may affect that well's water levels. Further, the variations in the well may be explained by many other variables, such as barometric pressure changes, diurnal fluctuations in water levels, rainfall, and pumping from closer wells. Finally, Brooklyn Bay is now physically separated from Lake Brooklyn, and it was improper for petitioner to rely on lake level information from Brooklyn Bay to support its theory regarding Lake Brooklyn. To further support its hypothesis that a preferential flow path exists between the mine and Lake Brooklyn, petitioner utilized a "photo linear analysis" or "fracture trace analysis", which is based on an interpretation of surface topographic features to determine the presence of subsurface hydrogeologic features such as solution channels in the limestones of the Floridan aquifer. However, without extensive subsurface testing, which is not present here, such analyses are only interpretative to determine what, if any, subsurface features are present and their hydrogeologic effect. It is noted that subsurface fractures are present less than 50 percent of the time, and if present, the features may be hydrologic barriers as well as preferential flow paths. According to witness Boyes, a photolinear feature (fracture) exists from Lake Brooklyn through Spring Lake and across the mine property to Goldhead State Park. If such a feature did exist, however, the drawdown during the aquifer performance tests and other pumping would be greater adjacent to Spring Lake than adjacent to Lake Brooklyn. This was not observed. Moreover, petitioner's witness Dr. Stewart thought the photolinear was only inferred and had a lower degree of confidence that it exists. FRI's witness Fountain established that elongated surface features are more likely to demonstrate linear subsurface features. Both witness Boyes and Dr. Stewart agreed with this conclusion. That being the case, the postulated Lake Brooklyn-mine photolinear is not demonstrated, and continuation of the elongated axis of Lake Brooklyn and Brooklyn Bay would bypass the mine site altogether. Because no investigations have been conducted to demonstrate that these postulated photolinear features exist, and the more reliable results of the aquifer performance tests indicate otherwise, the preferential flow path theory is deemed at best to be highly speculative. If the Lake Brooklyn-mine photolinear feature offered a preferential flow path as opined by witness Boyes, the resulting drawdown would be elongated with a zone of influence extending from the mine westward toward Lake Brooklyn. Therefore, areas closer but not on the feature would experience less drawdown than areas farther away which are on the feature, the zone of influence would extend from the mine's wells through Spring Lake toward Lake Brooklyn causing declined water levels along the feature, and areas closer to the pumping wells, such as Spring Lake, would experience a greater decline than areas farther away, such as Lake Brooklyn. However, evidence offered by petitioner shows that the water levels between Lake Brooklyn and the mine are actually higher than in surrounding areas. Finally, even if petitioner's preferential flow path theory were true, there is no evidence that the pumping from the mine is resulting in significant and adverse impacts as required by District rules. Therefore, it is found that the sand mine does not cause significant and adverse impacts on the water levels in the Floridan aquifer or on the water levels of Lake Brooklyn or Gator Bone, White Sands or Spring Lakes. Rather, the lake levels in each of the four lakes in issue here are directly or indirectly a function of rainfall. Intermediate and surficial aquifers Whether an intermediate aquifer is present beneath the mine site is subject to dispute. All parties agree that, on a regional scale, the Hawthorn formation contains some discontinuous water-bearing lenses that in some places produce water in quantities sufficient for household use. The lenses occur in carbonate deposits in the formation, although not all carbonate deposits or all water bearing units will necessarily transmit water. The evidence is less than persuasive that the Hawthorne formation contains carbonate units which are present on the sand mine site as transmissive beds. This finding is based on FRI's review of on-site core boring information and other data from the site. In addition, this finding is corrorborated by District witness Lee, who concluded that water from the site is not discharging into the Hawthorn, but rather into the surficial aquifer. This is because clays comprising the Hawthorn have low permeability, causing water to flow laterally through the surficial aquifer rather than into the Hawthorn. With respect to impacts to the surficial aquifer, FRI presented evidence that during mining operations, the surficial aquifer will be surcharged by up to five feet. When mining operations cease, water levels will return to natural conditions. This evidence was not contradicted. Impacts on Property Values and Recreation Testimony regarding the property values for lake front properties on Lake Brooklyn and Gator Bone, White Sands and Spring Lakes was offered by petitioner's witness Price. He established that values have declined since mid- 1989 as a result of a loss of recreational value suffered as water levels have receded. However, witness Price stated that he would not expect a 0.1 foot drop in lake levels to negatively affect property values. Since the declines predicted by petitioner are far less than a 0.1 foot drop, it is apparent that FRI's water use will not result in harm to property values in the area. Similarly, while it is true that declining water levels have impaired recreational uses of Lake Brooklyn and Gator Bone, White Sands and Spring Lakes, FRI's water use cannot be blamed for such impairment. Environmental Impacts The anticipated impacts of the water use on the wetlands and wildlife resources of the area were addressed by FRI witnesses Peacock and Lowe. According to Peacock, who analyzed the wetland vegetation, the dominant species and their adaptions, the wildlife resources and their adaptions, and the general ecology of the area, the water levels in the adjacent lakes have historically fluctuated greatly, and wildlife that use the lakes have adapted to these fluctuations. His opinion that the mine's water use will not have any significant adverse impact on the environment of Lake Brooklyn and Gator Bone, Spring or White Sands Lakes is hereby accepted. Based upon witness Lowe's inspection of the three downgradient lakes, his past knowledge of Lake Brooklyn, the aquifer performance tests, and Dr. Lee's conclusion that the maximum drawdown in the lakes would be 0.1 foot, Lowe opined that the proposed water withdrawal will not cause environmental harm. In addition, such a drawdown will not adversely affect off-site vegetation or cause unmitigated adverse impacts on adjacent wetlands or other types of vegetation. These conclusions were not contradicted and are hereby accepted. Compliance with rule criteria To obtain a consumptive use permit, an applicant must give "reasonable assurance" that the proposed water use is a reasonable beneficial use, will not interfere with any presently existing legal use of water, and is consistent with the public interest. These broad criteria are further explained by criteria enunciated in Rule 40C-2.301(3)-(6), Florida Administrative Code, and sections 9.0 et seq. and 10.0 et seq. of the Applicant's Handbook adopted by reference in Chapter 40C-2, Florida Administrative Code. Findings as to whether these criteria have been satisfied are set forth below. To obtain a renewal of a consumptive use permit, an applicant must first give reasonable assurance that the proposed use of water is a "reasonable beneficial use". For a use to be considered reasonable beneficial, the criteria enumerated in Rule 40C-2.301(4) and (5), Florida Administrative Code, must be satisfied. First, paragraph (4)(a) of the rule and section 10.3(a) of the handbook require that the water use must be in such quantity as is necessary for economic and efficient utilization, and the quantity requested must be within acceptable standards for the designated use. The evidence shows that FRI has used a reasonably low amount of water necessary to continue operations at the mine, it has implemented some water conservation methods and tried or considered others that proved to be inefficient or not economically feasible, and the requested amount of water is within acceptable standards for sand mines operating within the District. Then, too, some ninety-five percent of the water pumped from the wells is recirculated for reuse in the mining process or is recharged back into the surficial and Floridan aquifers on site. Finally, there is no surface discharge of water outside the mining site. Accordingly, it is found that this criterion has been satisfied. Paragraph (4)(b) of the rule and section 10.3(b) of the handbook require that the proposed use be for a purpose that is both reasonable and consistent with the public interest. The proposed use of the water is to produce sand used in construction materials. This is a reasonable use of water and results in an economic benefit to the region by producing a valuable product. Accordingly, it is found that the use is both reasonable and consistent with the public interest. All parties have stipulated that the Floridan aquifer is capable of producing the requested amounts of water. This satisfies paragraph (4)(c) of the rule and section 10.3(c) of the handbook which impose this requirement. The next criterion, paragraph (4)(d), as amplified by section 10.3(d) of the handbook, requires that "the environmental or economic harm caused by the consumptive use must be reduced to an acceptable amount." The evidence shows that during mine operations, the surficial aquifer is being surcharged by up to five feet. When they cease, the water levels return to natural conditions. The maximum drawdown anticipated in the Floridan aquifer at the property boundary was 0.3 feet and less than or equal to 0.1 feet for most of the area outside the mine site. At most, this equates to a maximum lake level decline of 0.04 feet at Lake Brooklyn, 0.03 feet at Gator Bone and White Sands Lakes, and less than 0.03 feet at Spring Lake. Thus, FRI's usage of water has had, and will have in the future, little, if any, immediate or cumulative impact on the levels of the area lakes. Further, the more persuasive evidence supports a finding that these lowered lake levels or aquifer levels will not result in environmental or economic harm to the area. In addition, the District has proposed to incorporate into the permit a condition that FRI implement a detailed monitoring plan which will detect any overpumping causing lake level changes and a concomitant adverse impact to off-site land uses. Therefore, this criterion has been satisfied. Paragraph (4)(e) and section 10.3(e) require the applicant to implement "all available water conservation measures" unless the applicant "demonstrates that implementation is not economically, environmentally or technologically feasible." The rule goes on to provide that satisfaction of this criterion "may be demonstrated by implementation of an approved water conservation plan as required in section 12.0, Applicant's Handbook: Consumptive Uses of Water." Because FRI's water conservation plan insures that water will be used efficiently, as required by section 12.3.4.1. of the handbook, this criterion has been met. The next paragraph provides that "(w)hen reclaimed water is readily available it must be used in place of higher quality water sources unless the applicant demonstrates that its use is either not economically, environmentally or technologi-cally feasible." Since the unrebutted testimony establishes that reclaimed water is not readily available to the mine site, it is found that paragraph (4)(f) has been satisfied. Paragraph (4)(g) of the rule and section 10.3(f) of the handbook generally require that the lowest acceptable quality water source be used. Since the evidence shows that the Floridan aquifer is the lowest acceptable quality water source, this requirement has been met. Paragraphs (4)(h) and (i) provide that the consumptive use "should not cause significant saline water intrusion or further aggravate currently existing saline water intrusion problems" nor "cause or contribute to flood damage." The parties have stipulated that these requirements are not in dispute. The next paragraph provides that the "water quality of the source of the water should not be seriously harmed by the consumptive use." The uncontradicted evidence shows that the source of the water for the proposed use will not be seriously harmed from either saltwater intrusion or discharges to the Floridan aquifer. Paragraph (4)(j) and section 10.3(g) have accordingly been met. Paragraph (4)(k) and section 10.3(k) require that the water quality of the receiving body of water "not be seriously harmed" by the consumptive use. In this case, there is no surface water discharge from the mine site. Thus, the only relevant inquiry here is whether the receiving water (surficial aquifer) will be "seriously harmed" by the consumptive use. To determine compliance with this criterion, the District compared water quality samples from the mine site and surrounding areas with the DER monitoring network to ascertain whether state water quality numerical standards and natural background levels were exceeded. The relevant standards are found in Rule 17-520.420, Florida Administrative Code. Monitoring data from eight wells and from the dredge pond indicate there are no water quality violations resulting from the sand mine operations. Petitioner has contended that water from the dredge pond provides a significant source of water to an intermediate aquifer, which would also be a receiving body of water. However, the evidence shows that any contaminants resulting from the dredge pond flowing into an intermediate aquifer will also be contained in the surficial aquifer. The clays of the Hawthorn formation would absorb and filter out iron and manganese as they traveled to a water transmissive zone. Therefore, the concentrations sampled in the suficial aquifer downgradient from the dredge pond represent the highest concentrations. Since the concentrations in the surficial aquifer do not violate water quality standards, the same finding as to concentrations in the intermediate aquifer can be made. Further, the rule criteria require consideration of the future water use's effect on water quality, and if the intermediate aquifer is in fact a receiving water as contended by petitioner, the reactions which could cause water quality violations are presently occurring. There is no reason to believe they would cease if the mine ceases operation, and the mining operation adds oxygen to the water, which reduces the possibility of the reaction described. Therefore, this criterion has been satisfied. The parties have stipulated that the requirements of paragraph (4)(l) have been fulfilled. Finally, rule 40C-2.301(5)(a) provides that a proposed consumptive use will not meet the criteria for issuance of a permit if such proposed water use will significantly cause saline water encroachment or otherwise cause water flows or levels to fall below certain minimum limits set forth in the rule. The evidence shows that, to the extent these criteria are applicable and in dispute, they have been satisfied. Miscellaneous The contention has been made that insufficient site-specific information was submitted by the applicant to determine the effects of the proposed use of water at the sand mine. In this regard, the evidence shows that FRI consultants installed monitoring wells, performed core borings, and took soil samples at the site. The geology of the site was verified by core boring, review of geologic logs and drilling wells. Slug tests were performed to measure the hydraulic conductivity of the material in which the monitor wells were set, and a step drawdown analysis was performed to measure hydraulic conductivity. A number of monitoring wells to measure water levels data were installed before and after running the 1991 aquifer performance tests, and groundwater modeling in both the transient and steady state modes were run using data that was collected in the field. In addition, water quality samples were collected to evaluate a water budget for the dredge pond, and FRI conducted an assessment of the environmental impacts to the wetland and wildlife resources of the area lakes, including White Sands, Spring and Gator Bone Lakes. Besides this submission and analysis, the District reviewed United States Geological Survey (USGS) topographic maps, potentiometric maps and aerial photographs of the area, water levels of the surrounding lakes, potentiometric surfaces in Floridan and intermediate aquifer wells, geophysical logs for wells, rainfall records, the core generated by FRI consultants, and scientific literature relied upon in making consumptive use permitting assessments. It also monitored the 1991 aquifer performance test and reviewed the resultant model. Before and after submission of the application, the District conducted aquifer performance testing at the site and evaluated the 1991 aquifer performance test conducted by FRI consultants. Finally, the District assessed water quality impacts of the sand mine in 1989 and in the present by site visit, sampling of the Floridan production well and dredge pond, and reviewing sampling data from both monitor wells and homeowner wells. It also reviewed information on water quality data gathered from other sand mines and applied data from the DER background monitoring network. Therefore, the contention that insufficient site-specific information was submitted and considered is rejected. Petitioner has offered into evidence petitioner's exhibits 61, 64, 65, 71, 75, 76, 78-80, 82 and 83. A ruling on the admissibility of the exhibits was reserved. The exhibits, which are based on data collected by the District and the USGS, are hydrographs showing water levels from lakes and monitoring wells during so-called "normal mine operations" on selected dates in 1988, 1989 and 1991. Although FRI was given copies of the exhibits ten days prior to hearing, it was not informed of the source of the data until final hearing. As it turned out, petitioner's witness had reviewed records over an extensive period of time and selected two or three days out of that time period as being representative of "normal" conditions. However, FRI established that, when longer periods of time were reviewed, the correlations alleged to exist by the graphs did not in fact exist and thus they did not represent normal conditions. Attorney's fees and costs FRI has requested an award of attorney's fees and costs on the theories petitioner interposed various papers and brought and participated in this action for "an improper purpose" within the meaning of Subsections 120.57(1)(b)5. and 120.59(6), Florida Statutes. In addition, petitioner has filed a motion for sanctions on the ground four motions filed by FRI were filed for an improper purpose within the meaning of Subsection 120.57(1)(b)5., Florida Statutes. It may be inferred from the totality of the evidence that petitioner did not intend to participate in this proceeding for an improper purpose. Likewise, the same inference may be made with respect to the four motions filed by FRI. Therefore, fees and costs (sanctions) are not warranted for either party.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered by the District granting application number 2-019-0012AUR as proposed by the District in its notice of intent to approve the application issued on August 6, 1992. DONE AND RECOMMENDED this 4th day of June, 1993, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of June, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-5017 Petitioner: 1-3. Partially accepted in finding of fact 1. 4. Partially accepted in finding of fact 2. 5-6. Partially accepted in finding of fact 6. 7. Rejected as being unnecessary. 8. Partially accepted in finding of fact 9. 9. Partially accepted in finding of fact 8. 10-12. Partially accepted in finding of fact 7. Partially accepted in findings of fact 6 and 7. Partially accepted in finding of fact 7. 15-16. Partially accepted in finding of fact 6. 17-18. Partially accepted in finding of fact 7. Partially accepted in finding of fact 6. Partially accepted in finding of fact 7. Rejected as being unnecessary. Partially accepted in finding of fact 11. 23-24. Partially accepted in finding of fact 7. 25. Partially accepted in findings of fact 7 and 8. 26. Partially accepted in finding of fact 7. 27-28. Partially accepted in finding of fact 14. Partially accepted in finding of fact 29. Partially accepted in finding of fact 11. 31-33. Partially accepted in findings of fact 14-16. 34-35. Partially accepted in finding of fact 15. 36-42. Partially accepted in findings of fact 14-16. Partially accepted in finding of fact 16. Partially accepted in finding of fact 31. Rejected as being irrelevant. Partially accepted in finding of fact 28. Partially accepted in finding of fact 33. Partially accepted in finding of fact 32. Partially accepted in finding of fact 23. Partially accepted in finding of fact 12. Partially accepted in finding of fact 14. 52-53. Partially accepted in finding of fact 11. Partially accepted in finding of fact 37. Partially accepted in finding of fact 11. Rejected as being contrary to the more persuasive evidence. See finding 23. 57-58. Partially accepted in finding of fact 11. 59-61. Partially accepted in finding of fact 12. Partially accepted in finding of fact 13. Partially accepted in finding of fact 11. 64-71. Partially accepted in findings of fact 32-36. 72. Partially accepted in finding of fact 11. 73-74. Partially accepted in finding of fact 6. 75. Partially accepted in finding of fact 8. 76-77. Partially accepted in findings of fact 8 and 11. Rejected as being contrary to the more persuasive evidence. See finding of fact 11. Partially accepted in finding of fact 8. Partially accepted in finding of fact 37. Partially accepted in finding of fact 11. Partially accepted in finding of fact 22. 83-120. Partially accepted in findings of fact 23 and 24. 121-139. Partially accepted in findings of fact 25-27. 140-144. Rejected since even if true, the impacts are not significant. 145. Partially accepted in finding of fact 18. 146-158. Partially accepted in findings of fact 18-20. 159-171. Partially accepted in finding of fact 39. 172-177. Partially accepted in findings of fact 40 and 41. Respondent (District): 1. Partially accepted in finding of fact 3. 2-4. Partially accepted in finding of fact 1. 5-6. Partially accepted in finding of fact 2. Partially accepted in finding of fact 3. Partially accepted in finding of fact 2. Partially accepted in findings of fact 1, 3 and 5. Partially accepted in finding of fact 7. Partially accepted in finding of fact 5. Partially accepted in finding of fact 1. Partially accepted in finding of fact 9. Partially accepted in finding of fact 5. Partially accepted in finding of fact 2. Partially accepted in finding of fact 6. 17-18. Partially accepted in finding of fact 7. 19-22. Partially accepted in finding of fact 11. 23. Partially accepted in finding of fact 37. 24-40. Partially accepted in findings of fact 12-16. 41-51. Partially accepted in findings of fact 11. 52-59. Partially accepted in findings of fact 23 and 24. 60-64. Partially accepted in finding of fact 25. Partially accepted in finding of fact 45. Partially accepted in finding of fact 23. 67-69. Partially accepted in finding of fact 11. Rejected as being unnecessary. Partially accepted in finding of fact 7. 72-73. Partially accepted in finding of fact 11. 74-77. Partially accepted in finding of fact 28. Partially accepted in finding of fact 23. Partially accepted in finding of fact 24. 80-81. Partially accepted in findings of fact 23 and 24. 82-83. Partially accepted in finding of fact 29. 84. Partially accepted in finding of fact 11. 85. Partially accepted in finding of fact 28. 86-90. Partially accepted in finding of fact 30. 91. Partially accepted in finding of fact 32. 92-94. Partially accepted in finding of fact 33. 95. Partially accepted in finding of fact 34. 96. Partially accepted in finding of fact 36. 97-100. Partially accepted in finding of fact 17. 101. Partially accepted in finding of fact 19. 102-103. Partially accepted in finding of fact 21. 104-121. Partially accepted in findings of fact 19 and 20. 122-130. Partially accepted in finding of fact 21. 131-133. Partially accepted in finding of fact 20. 134-138. Partially accepted in findings of fact 40 and 41. 139. Partially accepted in finding of fact 33. 140-141. Partially accepted in finding of fact 10. 142. Partially accepted in finding of fact 48. 143. Partially accepted in finding of fact 49. Respondent (FRI): Partially accepted in findings of fact 1 and 2. Partially accepted in findings of fact 3 and 4. Partially accepted in finding of fact 5. Partially accepted in findings of fact 2 and 6. Partially accepted in finding of fact 11. Partially accepted in findings of fact 6 and 7. 7-8. Partially accepted in finding of fact 10. Partially accepted in finding of fact 8. Partially accepted in finding of fact 9. Partially accepted in finding of fact 13. Partially accepted in finding of fact 15. Rejected as being unnecessary. Partially accepted in finding of fact 22. Partially accepted in finding of fact 23. Partially accepted in finding of fact 24. Partially accepted in finding of fact 25. Partially accepted in finding of fact 26. Partially accepted in finding of fact 27. Partially accepted in finding of fact 28. Partially accepted in finding of fact 31. 22-24. Partially accepted in finding of fact 32. Partially accepted in finding of fact 33. Partially accepted in finding of fact 34. Rejected as being unnecessary. Partially accepted in finding of fact 35. 29-30. Partially accepted in finding of fact 36. 31-35. Partially accepted in finding of fact 37. Partially accepted in finding of fact 38. Partially accepted in finding of fact 17. Partially accepted in finding of fact 18. Partially accepted in finding of fact 19. 40-41. Partially accepted in finding of fact 20. 42-45. Partially accepted in finding of fact 21. Partially accepted in finding of fact 40. Partially accepted in finding of fact 41. Partially accepted in findings of fact 40 and 41. 49. Partially accepted in finding of fact 39. 50-51. Partially accepted in finding of fact 42. 52. Partially accepted in finding of fact 43. 53. Partially accepted in finding of fact 44. 54. Partially accepted in finding of fact 45. 55. Partially accepted in finding of fact 46. 56. Partially accepted in finding of fact 47. 57-58. Partially accepted in finding of fact 49. 59. Partially accepted in finding of fact 51. 60. Partially accepted in finding of fact 52. 61. Partially accepted in finding of fact 54. Note - Where a proposed finding has been partially accepted, the remainder has been rejected as being unnecessary, irrelevant, cumulative, not supported by the more credible, persuasive evidence, or a conclusion of law. COPIES FURNISHED: Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Patrice Flinchbaugh Boyes, Esquire Post Office Box 1424 Gainesville, Florida 32602-1424 Peter B. Belmont, Esquire 511 31st Street North St. Petersburg, Florida 33704 Wayne E. Flowers, Esquire Jennifer L. Burdick, Esquire Post Office Box 1429 Palatka, Florida 32178-1429 Marcia Penman Parker, Esquire Emily G. Pierce, Esquire 1301 Gulf Life Drive Suite 1500 Jacksonville, Florida 32207
The Issue The disputed issues are as follows: Whether the proposed Water Conservation Plan is sufficient to meet the requirements of the District rule; Whether the proposed pumping will adversely affect wetlands and wetland vegetation in contravention of District rule; Whether the permit applicant has provided reasonable assurance of entitlement to the requested permit as required by the District rule; and What limiting conditions pursuant to Rule 40C-2.381, F.A.C., should be imposed on the Consumptive Use Permit (CUP).
Findings Of Fact THE PARTIES The Commission was created by the legislature pursuant to Public Law 67-1754 in combination with Public Law 85-503. Its principal office is located in New Smyrna Beach, Volusia County, Florida. The Commission is charged with maintaining a water supply and providing wastewater treatment and electrical power. The District is an agency created pursuant to Chapter 373, Florida Statutes, in charge of regulating, among other things, consumptive uses of water in a 19 county area of the State of Florida, including all of Volusia County. The geographical boundaries of the District are described in Section 373.069(2)(c), Florida Statutes. Vernon and Irene Beckham are property owners of the property proposed for the construction of the new State Road 44 wellfield. Volusia City-County Water Supply Authority is a cooperative created by interlocal agreement in accordance with Section 163.01, Florida Statutes (1991), which party made no appearance at the Formal Administrative hearing but adopted the position of the Commission. Nassau is an individual residing at 4680 Cedar Road, New Smyrna Beach, Florida. THE APPLICATION The present service area of the Commission encompasses approximately 43 square miles, of which only about 15 square miles of the service area are located in the City of New Smyrna Beach. On August 8, 1984, the District issued Consumptive Use Permit No. 2- 127-0214NG to the Commission for its Glencoe and Samsula wellfields, which permit would expire in seven years. The combined authorized withdrawal of the existing wellfields is 5.2 mgd on an average day and 8.31 mgd on a maximum day. In December 1990, the Commission submitted its Consumptive Use Permit Application to renew the existing permit, including the development of an additional water supply wellfield. This application also sought an increased allocation to meet projected demand for the Commission's service area. The total allocation sought was 5.59 mgd on an average day and 8.31 mgd on a maximum day. However, the District has recommended 5.29 mgd on an average day and 7.62 mgd on a maximum day by 1998. The source of the water for all three wellfields is the Floridan aquifer. The Floridan aquifer can produce the volumes of water requested based on the past pumpage from the Samsula wellfield and the Glencoe wellfield. The Glencoe wellfield has been in operation since early 1950. The Samsula wellfield has been in operation since 1982. The Commission has never exceeded the currently permitted withdrawals as measured by annual, daily, or peak basis. WATER DEMAND Approximately 75% of the demand is related to residential consumption. Approximately 10% of the demand is related to commercial and industrial consumption. Approximately 7% of the demand is related to irrigation. Lastly, approximately 8% of the demand is for miscellaneous consumption, including loss that occurs in the treatment process itself. Gross water use in the area served by the Commission is about 138 gallons per person per day. The approximate 103 gallons per person per day (net) used by residences is small as compared to other providers of potable water. The present population of the Commission's service area is approximately 31,570 customers. The projected 1997 population of the Commission's service area is 40,680. The Commission's population projections were obtained by methods consistent with the District's Permit Manual. VI. PERMIT CRITERIA Water Conservation Plan The Commission has submitted a complete Water Conservation Plan. The implementation of that plan is a condition of the permit. The Water Conservation Plan includes a customer audit program of the system to determine how much water is pumped and where the water goes once it is distributed. The customer audit program involves employees of the Commission discussing the historical water usage with the customer, detection of leaks, installation of water restrictors, and the prevention of freezing pipes in the wintertime. The Commission encourages reduced consumption through the water meter charges. Larger meters use more water than smaller meters. The monthly charge for the larger meters is higher thereby encouraging the use of smaller meters. The Water Conservation Plan includes a pressure monitoring program to detect leaks in the system. The program has been implemented. The system pressure monitoring plan measures the pressure in different zones around the Commission's service area and, should a large main burst, an alarm is triggered. Repair of that water main would occur immediately. The Water Conservation Plan includes an analysis of the economic, environmental and technical feasibility of using reclaimed water in Commission's Exhibit No. 14, Reuse of Reclaimed Wastewater Conceptual Planning Document. The Reuse of Reclaimed Wastewater Conceptual Planning Document involves four major phases of construction starting in 1991 with completion in 1995. The first phase is underway. As part of the reuse plan, the Commission is modifying the wastewater treatment plant to accept reuse water. The construction is 99 percent complete. A total cost for that is approximately 1.5 million. The Commission will be replacing some freshwater irrigation sources with reclaimed water. The Commission has valid DER permits for this use of reclaimed water. As part of the reuse plan, the Commission has entered into construction contracts to serve the municipal golf course, the landscape at city hall and city parks with wastewater. The transmission and distribution lines will be completed before October 1992. The cost is approximately $700,000. Other phases of the reuse plan include construction of the major infrastructure inside and outside the city for reuse distribution. Total investment is in excess of five million dollars. Major customers along the route have been identified to increase the demand on the reuse system. The Water Conservation Plan includes an employee awareness program and an educational program as well as a time frame to implement those programs. The Commission has a public relations program to inform the customers about water conservation which includes newspaper publications concerning reading water meters, xeriscaping, and methods to reduce water consumption and the time/temperature machine which has prerecorded messages. The Commission has a program for educating the public and encouraging xeriscaping or the use of drought resistant foliage. Xeriscaping is implemented at the wastewater lift stations. The Commission has used direct mailing to provide water conservation information to customers. The Commission has a program for inspecting and replacing defective meters. If a meter malfunctions, the replacement reduces the system losses and accurately records water usage. The Commission has a program to monitor unmetered uses, which includes reporting from users such as the fire department of their unmetered use. On a monthly basis, the fire department reports its water usage as calculated by its operation schedule. The Commission is using the lowest acceptable quality water source, including reclaimed water, for certain types of needs such as irrigation of golf courses. The Water Conservation Plan addresses the use of treated effluent to minimize withdrawals of groundwater. Issues Related to Reasonable Assurance Hydrogeology The Floridan aquifer occurs at approximately 100 feet below the land surface throughout Volusia County. It's overlain by approximately 100 foot of sandy and clayey material collectively called the Clastic aquifer or the surficial aquifer. The proposed SR 44 wellfield site is underlain by an approximate 900- foot depth of freshwater of the Floridan aquifer. In the high recharge area of the Deland Ridge, water moves rapidly into the surficial aquifer and recharges the Floridan aquifer. A regional groundwater gradient extends from the Deland Ridge towards the east. There is a volume of water in the Floridan aquifer that is constantly moving from the west to the east to replenish water that is being withdrawn. Based on the regional movement of the Floridan aquifer and the nature of the Floridan aquifer, the water that is being replenished by the withdrawal is mainly coming from the Floridan aquifer with some contribution from the surficial. Another way to determine the source of the water is by geochemical analysis. The source of the water for this use is characterized as freshwater category number three meaning that it is Floridan aquifer water that is replenishing the water that is being withdrawn and not surface water that is going directly into the Floridan aquifer system. Aquifer Tests The aquifer performance test at the SR 44 wellfield shows that the aquifer is able to produce the volumes of water requested. The depths of the proposed wells, and APT test well, at the SR 44 wellfield is 250 feet below land surface or 150 feet into the Floridan aquifer. The APT at the SR 44 wellfield site provided for the collection of data to show what happens to the water levels while the aquifer is stressed. The second APT at the SR 44 wellfield site tested the Floridan aquifer at a depth of 750 feet below land surface. The section of the Floridan aquifer tested was 500 feet thick. The second APT and geophysical logs showed that there were not any additional flow zones below the upper Floridan aquifer which would yield additional water. Prior to the pump recovery test at the Samsula wellfield, the wells were pumping at 2.59 million gallons per day for a couple of days prior to shutting them off. For a period of five days, four wells in the vicinity of the Samsula wellfield were monitored by the District for water level recovery. The actual observations and the predicted drawdowns in the model correlated well. Drawdown does occur at homeowners' wells when the Commission's Samsula wellfield is pumping, but it does not interfere with existing legal users based on the District rules. The drawdown will not cause a ten percent reduction in the withdrawal capability of the homeowner's well. Computer Modeling The PLASM model simulates the response of the surficial and Floridan aquifers to pumping. The computer model oversimplifies the nature of the surficial aquifer by characterizing the layer as a solid homogeneous type of a system, basically being all sand. In reality, there are some shell and clay layers or hardpan. The transmissivity or the ability to transmit water through the aquifer for surficial aquifer sand ranges between 1,000 up to about 12,000. The transmissivity in the model is 5,000 gallons per day per foot (gpdpf) for Layer 1 which was reasonable. In Layer 2, the data from the APT produced a value of 50,000 gpdpf and a leakance value, or value that would correspond to water that moves from the surficial aquifer down to the Floridan aquifer, of 0.0012 gpdpf. This 50,000 and 0.0012 values are reasonable numbers for this area of Volusia County. The PLASM model is an accepted model for simulating pumpage. In the PLASM model, the transmissivity was varied in two different directions, but it averaged 50,000 gpdpf in the Floridan aquifer system. In the Floridan aquifer system, water is going to be moving based on the transmissivity of the aquifer and a leakance value from the surficial aquifer. The water primarily flows in a horizontal direction. There is a component of vertical movement. The difference between the horizontal movement and the vertical movement is an order of magnitude. There's an order of magnitude difference between the 50,000 gpdpf and the 0.0012 gpdpf which shows that the majority of the water is coming from a horizontal direction. There is some vertical movement. The vertical movement is not only from above, but because of the Floridan aquifer there is also vertical movement from below. When a well is pumping water, the water is being replenished mostly from the horizontal direction and from the lower direction in the same aquifer system, with some contribution downward based on the leakance value from above. This is demonstrated or shown by a small predicted drawdown in the surficial aquifer and that predicted drawdown is basically two orders of magnitude less than the drawdowns in the Floridan aquifer. Proposed Recommended Withdrawal Rates The proposed recommended withdrawal rate from the SR 44 wellfield is 1.43 mgd for average daily flow. With the proposed recommended withdrawal of 1.43 mgd at the SR 44 wellfield, the maximum drawdown in the surficial aquifer is approximately 0.34 feet. With the proposed recommended withdrawal of 1.43 mgd at the SR 44 wellfield, the maximum drawdown in the Floridan aquifer is approximately ten feet. A withdrawal of 1.93 mgd at the SR 44 wellfield site would result in a maximum drawdown in the surficial aquifer of 0.7 feet and in the Floridan aquifer of thirteen (13) feet. The proposed recommended withdrawal rate from the Samsula wellfield is 1.93 mgd for average daily flow. With the proposed recommended withdrawal of 1.93 mgd at the Samsula wellfield, the maximum drawdown in the surficial aquifer is approximately seven tenths (0.70) of a foot. With the proposed recommended withdrawal of 1.93 mgd at the Samsula wellfield, the maximum drawdown in the Floridan aquifer is approximately seventeen (17) feet. The proposed recommended withdrawal rate from the Glencoe wellfield is 1.93 mgd for average daily flow. Under the existing permit, the Samsula wellfield is withdrawing at the higher rate of approximately 2.59 million gallons per day. The volumes of water requested from both the Samsula wellfield and the SR 44 wellfield have been reduced from what was originally proposed by the Commission. The reduced allocation for the Samsula wellfield will improve groundwater elevations and thereby reduce groundwater impacts. Water Quality The state water quality standard for public drinking water is 250 milligrams per liter (mg/l) chlorides. For water supply systems where the chloride level is below 250 mg/l, the District uses that level to determine whether or not the pumping is going to cause significant saline water intrusion. The proposed use cannot cause the water quality to exceed 250 mg/l in chlorides. The water quality data from the existing Samsula and Glencoe wellfields shows that none of the wells or trends from the indicate that they are either above 250 mg/l or trending in a degradation mode toward 250 mg/l. The water quality in the wells is stable without degradation of the water quality in either of the Glencoe wellfield or the Samsula wellfield. The water quality data collected during the APT at the SR 44 wellfield showed that the chlorides were below 250 mg/l and that during the test, there was no change or a trend of becoming salty. An independent study used geophysical methods to determine the depths below land surface where high concentrations of saline water exist. That depth was at approximately 1200 feet below land surface. Proposed Permit Conditions The Commission accepts the conditions of the permit as proposed in the Commission Ex. 10-B. The proposed conditions require the Commission to limit the withdrawals per wellfield as specified and to monitor each production well with a flow meter, monitor the groundwater levels, monitor the surface water conditions, monitor rainfall, and monitor the wetlands. The proposed permit conditions and the County's ombudsman program adequately address the possible impacts of the proposed wellfield on existing users. The monitoring will be able determine the impact of the wellfield on those users. The Commission accepts the condition to mitigate for interference with existing legal users in compliance with the proposed permit conditions. The Volusia County ombudsman program provides the method of investigating and resolving issues related to interference of the proposed wellfield operation with existing legal users. The Commission will participate in this program. The Commission's purchase of the property is contingent upon obtaining the consumptive use permit. The Commission will own the site as shown on various exhibits. The drainage pattern of Tiger Bay is northerly for most of the basin. A canal located north of the area provides the primary drainage for Tiger Bay. A small drainage area within Tiger Bay of approximately 90 acres drains south into the SR 44 wellfield site. Some of the drainage does come through the two 30-inch culverts under SR 44, and both commingle with the wetlands that are on the site as well as drain into a ditch located along the Ranchette Road. The maximum capacity at ideal conditions for those two culverts would be approximately 300 CFS, cubic feet per second. The entire Tiger Bay drainage basin is approximately 13,000 acres. The volume of surface water which can flow from Tiger Bay is 13,000 cfs. That volume could not flow through the culverts at SR 44 without overtopping the road. Ecology The upland communities surrounding the Samsula wellfield are primarily pine flatwoods and mixed pine forested areas. The proposed 1.93 mgd average day withdrawal quantity being recommended by the District for the Samsula wellfield will not adversely affect these upland communities because: (a) the upland communities do not rely on inundated or saturated conditions so the proposed consumptive use will not adversely affect the hydrology these upland communities rely on; and (b) the magnitude of the predicted drawdown will not cause a shift in vegetation meaning a change in the types of plants that already exist there. The wetland communities surrounding the Samsula wellfield site consist of cypress dome and bay swamp communities. With the projected drawdowns information for the Samsula wellfield, there will not be significant adverse impacts to uplands or wetlands that would be identifiable based upon the projected wellfield withdrawal rates as recommended by the District. Any potential for impacts has been reduced in that the current pumpage rates are projected to decrease. The proposed 1.93 mgd average day withdrawal quantity being recommended by the District for the Samsula wellfield will not cause the water table to be lowered such that these wetland communities will be significantly and adversely affected for the following reasons: The wetlands in the area of the Samsula wellfield lie in a sloped terrain. Underlying the site is a soil area known as a spodic horizon or a hardpan layer. The spodic horizon is an area where there is a deposition of organics and it has a different chemistry than the surrounding soils. The spodic horizon, when saturated, acts as a semi-impervious or impermeable layer which causes impedance of water as it goes through. This spodic horizon in the area of the Samsula wellfield is typically two feet below the soil surface. The predicted drawdown will not cause water levels to be dropped such that in normal wet season conditions, which is the time when hydrology to a wetland is most important, the spodic horizon will still be saturated so that water is coming into the wetlands through rainfall directly, as well as rainfall that falls on the adjacent uplands and moves laterally through the soils to the wetland above the spodic horizon. Thus, the spodic horizon will prevent a shift in the "water budget" of these wetlands such that the wetlands will not be harmed by the proposed use. The wetlands systems surrounding the Samsula wellfield are primarily densely forested systems with a fairly substantial accumulation of organic or muck type soils in the surface. The soils assist these wetlands in retaining moisture which provides a "built-in system" for the wetlands to withstand fluctuations in hydroperiods. The wetland systems surrounding the Samsula wellfield appear to have an altered hydrology. The identifiable impacts are ditches or shallow swales along State Road 44. The wetlands south of 44 in the vicinity of wells one, two and three have been bisected by roads and there are swales cut adjacent to those roads. The power line that runs north-south has cut off and eliminated half of a cypress wetland south of 44 and about half of a cypress wetland north of 44. It is possible that these ditches and roads may have caused the altered hydrology in these wetlands. It cannot be concluded that the current Samsula wellfield operation has caused this altered hydroperiod. However, the drawdown that is predicted to occur at the Samsula wellfield under the proposed 1.93 mgd average day withdrawal being recommended by the District is much less than the drawdown that is occurring from the current pumpage at this wellfield. The projected drawdowns from the proposed three wellfield configurations indicate less potential for impacts than the current two wellfields as far as Samsula is concerned. Thus, even if the wetlands surrounding the Samsula wellfield have been affected in any way by the current pumpage rate, the reduced drawdown rates that will result from the 1.93 mgd average day proposed pumpage rate will greatly improve this condition. Other than slight alteration along the edge of SR 44, the wetlands in the vicinity of Samsula wells five and six have not been significantly altered. No changes in vegetation and no apparent changes in hydrology occur in those areas. The cypress wetland north of SR 44 has a drainage ditch emerging to the east. Another wetland immediately north of SR 44, north of well four, is adjacent to the road and the roadside swale or ditch in that vicinity. The species of wildlife identified are ones that are adapted to altered conditions. Abundant wildlife is generally found living in association with improved pastures and close proximity to man. Most of the wetlands in the area of the Samsula wellfield, north and south of SR 44, are in improved pasture or where roads and power lines have been cut. There was evidence of impacts to the wetlands and some drainage. The edge of the cypress dome north of SR 44 has blackberries and other weedy type species along the margins of it. The wetland immediately southeast of well one at the Samsula wellfield was a healthy bay dominated area with ferns underneath. The lichen line on the trunk of the tree and the mosses indicate that the water has been up to or near the historical high within the past season or two. Otherwise, the lichens would grow at the base of the tree. At the Samsula wellfield site, there are no wetlands within the inner drawdown contour of 0.7. There are some wetlands between the 0.7 and the 0.5 contours. The upland communities in the vicinity of the proposed SR 44 wellfield are primarily pine flatwoods and improved pasture. In the pine flatwoods areas, the soils indicate that the water table extends from a height of 0.5 feet below land surface and down to a hardpan layer. The water table in the pine flatwoods fluctuates between the hardpan and 0.5 feet below land surface. The proposed 1.43 mgd average daily withdrawal which is being recommended by the District for the proposed SR 44 wellfield will not significantly and adversely affect these upland communities because these upland communities are not reliant on inundated or saturated conditions, and the proposed consumptive use will not cause a shift in hydrology such that the vegetation found in these communities will no longer be there. The wetland communities in the vicinity of the proposed SR 44 wellfield consist of cypress sloughs and cypress domes which also have herbaceous areas with them. The cypress dominated wetlands are on the northeastern portion of the site and the northwestern portion of the site extending down through the central and southeastern part of the site. Cypress dominated wetlands occur on the southwestern border with one in the east-central portion of the site. Between the cypress dominated wetlands and pine flatwoods are grass prairies. The Commission determined the hydroperiod of the wetlands using vegetative physical evidence or biological indicators, such as lichen lines and mosses, and soil physical evidence from soil probes, which are indicators of long-term and sometimes short-term changes. The wetland on the east-central portion of the proposed SR 44 wellfield site inundates to approximately six and one half inches. In the dry season, the soils dry out to 0.15 feet below land surface. In the wet prairie or wet grassy area, the water table seasonally fluctuates between the hardpan layer of 2.2 feet bls and a tenth or two-tenths of an inch above the surface as based on adventitious roots growing from a St. Johns wort plant species. The water table fluctuations explain the seasonal high and the seasonal low water elevations. The factors which most influence the wetlands and their hydrology are subsurface flow during the wet season, the runoff and direct rainfall. The proposed 1.43 mgd average daily withdrawal for the proposed SR 44 wellfield will not significantly and adversely affect these wetland communities because these wetlands are also underlain by a spodic horizon which, as in the case of the Samsula wellfield wetlands, functions to provide lateral movement of water into the wetlands. The predicted drawdowns for the proposed SR 44 wellfield will not lower the water levels in these wetlands so as to prevent the spodic horizon from performing this function. The recommended withdrawal rate of 1.43 mgd for the proposed SR 44 wellfield reduces the opportunity for impacts. The part of the wellfield site where the greatest drawdown of 0.34 feet occurs is the furthest away from the majority of the wetlands on the site. However, the wetland and soil types on the surface layer are different than the wetland and soil types found at the Samsula wellfield site. The District is recommending a pumpage rate for the proposed SR 44 wellfield that would result in a maximum .34 feet of drawdown in the surficial aquifer while recommending a pumpage rate that would result in a maximum .7 foot drawdown in the surficial aquifer for the Samsula wellfield. The wetlands at the proposed SR 44 wellfield site do not have the dense canopy as well as the accumulation of muck soils in the surface that the wetlands at the Samsula site have. Additionally, the wetlands in the vicinity of the proposed SR 44 wellfield site include herbaceous systems which tend to be shallower systems, not as deeply set as the forested cypress systems are, and therefore tend to be more sensitive to changes that occur in the top couple of inches of soil which is above the spodic horizon. Thus, the wetlands in the vicinity of the proposed SR 44 wellfield would be significantly and adversely affected if the Commission were permitted to withdraw water at a pumpage rate that would result in a drawdown of greater that .34 feet. The drawdowns upon which the evaluation of potential wetland impacts are based are predicted drawdowns. Monitoring and Proposed Conditions To provide additional assurance, the District has recommended a series of permit conditions, numbered 31 through 45 on the Commission Ex. 10-B, that will require the permittee to conduct extensive groundwater and surface water monitoring, as well as vegetative monitoring in the vicinity of the proposed SR 44 wellfield and the Samsula wellfield site. Condition number 31 identifies the overall program of wetland and ground and surface water monitoring. Condition number 32 requires the permittee to install surficial aquifer monitoring wells in the vicinity of the wellfield sites. These monitoring wells will be constructed below the spodic horizon and inside and outside the "area of concern" which is the area within the tenth of a foot drawdown contour at the wellfield sites. This condition will enable the District to analyze how the proposed use is affecting the overall groundwater levels unaffected by the spodic horizon. Placing these wells both inside and outside the area of concern will allow the District to determine if any change in groundwater levels is due to the wellfields or normal climatic patterns. Condition number 33 will allow the District to obtain a constant record of information to analyze what trends are occurring in the wetlands in the wellfields and to have sufficient data during normal climatic variations of the wet and the dry seasons to determine the presence of a trend. The required period of record collection, defined in this condition as the shorter of one calendar year or one consecutive wet to dry season, is a sufficient period of record collection because the purpose of this condition is to obtain a picture in time of the existing conditions in the wetlands surrounding the wellfields during the dry season and the wet season. Condition 33 requires the permittee to submit an annual hydrologic report to the District. This is a sufficient time period of reporting because the purpose of the report is to allow the District to accumulate and assess an entire year's of data or the entire dry to wet season variation. With the annual report, any adverse wetland vegetation changes can be detected prior to any permanent harm to the wetlands. Condition number 34 requires the permittee to install shallow piezometers and staff gauges in the monitored and referenced wetland areas. The monitored wetlands are the wetlands inside the "area of concern." The referenced wetlands are outside the "area of concern." Condition number 34 will allow the District to analyze the hydrology above the spodic horizon. This in turn will allow the District to evaluate the hydrology of the monitored wetlands against the hydrology of the referenced wetlands to determine if any adverse impacts are occurring in the wetlands due to the wellfields' operation. Condition Number 35 requires the permittee to submit surveyed cross- sections of each of the monitored wetlands and the referenced wetlands. This condition will allow the District to receive a linear view of both the monitored and referenced wetlands so that when the District receives the groundwater and surface water information required by condition number 34, it can assign that information to a picture, and know what the wetlands look like under varying water conditions. Condition number 36 requires the permittee to select referenced wetlands similar to the wetlands that are going to be monitored in the area of concern. This will ensure that the reference wetlands match vegetatively and hydrologically with the wetlands that are being monitored within the area of concern. Condition number 37 requires the permittee to install rain gauges at both wellfield sites. This will allow the District to compare rainfall to groundwater information and determine what the relationship is between water levels in the surficial aquifer and the amount of rainfall that has occurred. Condition number 38 requires the permittee to monitor, on a weekly interval, the water levels in each of the monitored wetlands and in the referenced wetlands and submit annual reports of this data. Condition number 39 requires the permittee to install continuous recorders on the staff gauges and piezometers in the reference and monitored wetlands. The information gathered will provide the District with detailed records of the water fluctuations in these wetlands systems relative to rainfall input. Condition number 39 requires the permittee to submit annual reports of the information gathered to the District. The annual report will allow the District to determine if any adverse trends are occurring in the wetlands. No permanent adverse change could occur to the wetlands communities surrounding either wellfield before the District receives this annual report. Condition number 40 requires the permittee to conduct baseline water quality monitoring at each of the monitored wetlands. If any adverse change does occur to the wetlands surrounding either wellfield, and if the permittee chooses to mitigate for this adverse change by augmenting the wetland systems, then this permit condition will allow the District to ensure that the water used to augment those wetlands is of the same quality as the water currently found in those wetlands. Condition number 41 requires the permittee to initiate a baseline vegetative monitoring program of the monitored and reference wetlands at both wellfields. This condition will allow the District to have a vegetative picture of the wetlands prior to any pumpage. Condition number 42 requires the permittee to conduct a vegetative monitoring program of the monitored and reference wetlands at both wellfields with the initiation of withdrawals. Condition number 43 requires the permittee to provide a wetland similarity assessment for both wellfields. The permittee must compare the results of the wetland vegetative monitoring program each year against the baseline vegetative monitoring of the same wetland and against the vegetative monitoring of the referenced wetlands. This condition will assist the District in determining if any adverse trends are occurring in the wetlands surrounding either wellfield. Condition number 44 requires the permittee to create two duplicate reference herbarium collections of the flora present in the monitored and referenced wetlands and the adjacent upland areas. This condition will ensure that there is consistency in the vegetative identification throughout the monitoring program. Condition number 45 requires the permittee to mitigate any harm to the wetlands that is detected from the monitoring required by other permit conditions. This condition does not require any particular form of mitigation. The wellfield withdrawals at the projected rates and the suggested permit rates should not have an impact on threatened or endangered plant or animal species in the Samsula wellfield area or the proposed SR 44 wellfield area. The monitoring program will provide the data to determine on a short- term or long-term basis whether the pumpage rates are causing impacts. Potential harm can be mitigated by adjusting the quantities and locations of withdrawal. V. ATTORNEY'S FEES AND COSTS The Commission seeks fees and costs from Petitioner pursuant to Section 120.59(6), Florida Statutes (1991). Such entitlement requires a showing that the Petitioner brought this case or filed a pleading for an improper purpose. While the evidence does show that certain pleadings filed by Petitioner (or his attorney who withdrew 24 hours prior to the beginning of the hearing) may have had as one purpose the delay of the hearing scheduled for March 24, 1992, the totality of the evidence establishes that Petitioner's purposes were not improper. Section 403.412(5), Florida Statutes (1991), establishes the right of any citizen of the state to intervene into "proceedings for the protection of air, water, or other natural resources of the state from pollution, impairment, or destruction " The actions of Petitioner in this proceeding were not clearly shown to be for delay, harassment or other improper purpose. In fact, Petitioner handled himself well as a pro se litigant after his attorney's untimely withdrawal. If anyone acted with an improper purpose in this proceeding, it was Peter Belmont, Nassau's attorney until he withdrew less than 24 hours prior to the hearing. The record shows that Belmont entered into the representation of Nassau with full knowledge that he would seek all possible delays in the proceedings. He engaged in no preparation for the hearing and he left Nassau unprepared also. Belmont's bad faith actions in this case however can only be determined and remediated by the Florida Bar, not by the undersigned through an award of fees and costs. Finally, there has been no delay in these proceedings. The petition was filed with DOAH on January 16, 1992. The District moved to consolidate it with two other pending case set for January 20, 1992. Those cases were voluntarily dismissed. An Initial Order was sent to the parties on January 21, 1992, seeking suggested dates for the hearing. The hearing was set to begin March 16, 1992, less than 60 days from the filing of the case. A one week continuance was granted and the case was heard beginning on March 24, 1992. If anything, this case has proceeded expeditiously.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the St. Johns River Water Management District enter a Final Order GRANTING the Utilities Commission of New Smyrna Beach's Consumptive Use Permit, subject to the March 9, 1992 permit conditions proposed by the District (Commission's Exhibit 10-B). RECOMMENDED this 13th day of May, 1992, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of May, 1992. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-0246 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, William Nassau Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 4(3) and 5(10). Proposed findings of fact 1-3, 6-9, 11, 12, 14, 19, and 22 are subordinate to the facts actually found in this Recommended Order. Proposed findings of fact 13, 15-18, 20, and 21 are unsupported by the credible, competent and substantial evidence. Proposed finding of fact 10 is irrelevant. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Utilities Commission of New Smyrna Beach Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-11(1-11); 13-19(15-21); and 35(12). Proposed findings of fact 12 and 20 are unsupported by the credible, competent and substantial evidence. Proposed findings of fact 32-34 are irrelevant. Proposed findings of fact 21-31 and 36-111 are subordinate to the facts actually found in this Recommmended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, St. Johns River Water Management District Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-21(22-46); 22(16); 23(7); 25(19-21); 29-31(12-14); and 32-142(43-153). Proposed findings of fact 24 and 26-28 are subordinate to the facts actually found in this Recommended Order. COPIES FURNISHED: William Nassau 4680 Cedar Road New Smyrna Beach, FL 32168 Nancy B. Barnard Eric Olsen Attorneys at Law St. Johns River Water Management District P.O. Box 1429 Palatka, FL 32178-1429 Roger Sims Rory Ryan Lynda Goodgame Attorneys at Law Holland & Knight P.O. Box 1526 Orlando, FL 32802 Wayne Flowers, Executive Director St. Johns River Water Management District P.O. Box 1429 Palatka, FL 32178-1429
Findings Of Fact The subject application requests a water use permit from the Central and Southern Florida Flood Control District (FCD) for the supplemental irrigation of 145 acres of citrus lands located in Orange County. Received into evidence at the hearing were the public notice of hearing appearing in the Sentinel Star, permit application number 21424 with an attached report and the Staff Report of the FCD, prepared by Nagendra Khanal. The applicant requested an annual allocation of water in the amount of 120.15 acre-feet or 9.94 inches per year, for a period of twenty (20) years. The Staff Report recommends the issuance of a permit for said amount, with maximum monthly pumpages not to exceed 49.8 acre-feet or 4.13 inches, the permit to expire on January 15, 1978. Several further special provisions were recommended on pages 4 & 5 of the Staff Report, which report is attached hereto. There is no dispute between the applicant and the FCD over the technical aspects of the Staff Report. The protests of the applicant center around the length of the permit and some of the special provisions recommended in the Staff Report, which the applicant feels are vague and ambiguous. Mr. James A. Hinson, the applicant's corporate secretary, felt that the FCD had sufficient data and statistics as to the water resources and agricultural usage within the area to sustain the granting of a twenty year permit. It was further felt that the issuance of a two-year permit for the purpose of gathering information as to the quantity of use would tend to prompt higher usage and even lead to falsification of pumpage records on the part of agricultural users so as to assure the issuance of future permits. The applicant was also concerned with the costs of applying for another permit in two years. Mr. Nagendra Khanal, a hydrologist with the FCD, explained that the purpose of the two-year permit was to obtain information from agricultural users in the area as to the amount of water used and the effect of such usage on the Florida aquifer system. Since the outset of regulatory provisions, the FCD has set the same termination date for each permit for agricultural use within each of the basins. At that expiration time, the pumpage records for all users in the area will be established and present experimental estimates can then be compared with actual usage. Little is known by the FCD about how the Florida aquifer system operates and the data presently in use are experimental. Since all permits within each basin will expire on the same date, the entire basin can then be evaluated at one point in time. It was felt that if falsification of pumpage records were to occur, it could probably be detected by data currently available to the FCD. It was further opined by Mr. Khanal that at, the expiration date of all permits issued in each basin, an automatic conversion into new permits would occur at little or no cost to the applicant. With regard to the special provisions recommended in the Staff Report, Mr. Hinson expressed concern over the manner of compliance. Specifically, he desired more information on the type of equipment or devises required by the FCD when it calls for "minimum head pressures", and "a measuring device on each of the three wells." He also desired information as to the times of year the water quality analyses were to be performed. Mr. Khanal explained that no regulatory criteria had been established by the FCD with regard to pumpage and that the minimum type of measuring device, such as a time clock, on each of the wells would suffice. Further specifications will be supplied to the applicant upon request. It was explained by Khanal that the water quality analyses should be performed once before the rainy season (at the end of May) and once after the rainy season (at the end of October). There was some confusion over the inclusion of the parameter of "specific conductivity" within the definition of a standard complete water quality analysis. Finally, Mr. Khanal listed two amendments to be made in the Staff Report. On page 2, under "B. Existing Facilities", "3,500 gpm" should read "3,600 gpm." The last item on the chart on page 3 of the Staff Report should read "2 in 10 Year Drought" in lieu of "1 in 10 Year Drought."
Recommendation Based upon the findings of fact and conclusions of law recited above, it is recommended that Application No. 21424 be granted and that a permit be issued in accordance with the recommendations and provisions set forth in the Staff Report, as amended. Due to the apparent confusion over the inclusion of "specific conductivity" as a parameter to be included within the definition of a standard complete analysis, it is further recommended that the Staff make further inquiry into its necessity. If the Staff then concludes that "specific conductivity" is necessary to obtain a complete water quality analysis, it is recommended that it remain on the list of parameters. Respectfully submitted this 5th day of March, 1976, in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of March, 1976 COPIES FURNISHED: Thomas C. Garwood, Jr., Esquire Akerman, Senterfitt, Eidson and Wharton 17th Floor CNA Building Orlando, Florida Stephen A. Walker, Esquire Post Office Box V West Palm Beach, Florida 33402
Findings Of Fact On November 1, 1982, Respondent Janson filed a Joint Application for a dredge and fill permit from Respondent, Department of Environmental Regulation, and from the Department of the Army Corps of Engineers. The project described in that application involved the construction of an approximately 1,000-square- foot, pile-supported residence, landward of the mean high water line but within the landward extent of Robinson Creek in St. Johns County, Florida. The proposed project also involved the placement of approximately 35 cubic yards of fill and a 30-foot culvert within a small (approximately 4-foot), tidally- influenced roadside ditch for driveway access and parking. The original application sought permission to place part of a concrete driveway and tool shed within the landward extent of Robinson Creek. The project is to be constructed on Lot 47, J.A. Lew Subdivision. Respondent Janson owns Lot 47, as well as Lots 45 and 46, which lots are north of and adjoining Lot 47 and also adjoining Robinson Creek. The next adjoining property owner to the north is the City of St. Augustine, Florida, which presumably owns the street. The adjoining property owner to the south of Lot 47 is Virginia P. Melichar. Neither Melichar nor the City objected to the Department's approval of the dredge and fill permit application. In support of his application, Janson retained the services of a registered surveyor and civil engineer, who performed a survey on Lot 47 to determine the location of the mean high water line with reference to the proposed project. That expert determined the location of the mean high water line to be at elevation 2.4 feet. Accordingly, all work contemplated by the dredge and fill permit is upland from the mean high water line. T.J. Deuerling, an environmental specialist for Respondent, Department of Environmental Regulation, visited the project site on December 13, 1982 and on December 30, 1982 in order to prepare the Department's Biological and Water Quality Assessment. As a result of those site visits, Deuerling recommended to Respondent Janson that he modify his permit application by moving the concrete slab and tool shed from the marsh area onto the uplands. Janson did so revise his application. In spite of the name of the permit being sought by Respondent Janson, the project involves no dredging. However, the culvert and its attendant fill would be placed in the man-made roadside ditch. That ditch constitutes a very weak transitional marsh. Although the culvert will eliminate some vegetation within that ditch, the effect of the elimination will be insignificant on water quality. The pilings for the pile-supported residence will also eliminate a small area of marsh. The anticipated shading caused by the pile-supported residence may impact somewhat on the vegetation in a small area below the residence; however, due to the fact that the floor of the house will be eight feet above the ground, light will still be able to penetrate. Therefore, the vegetation below the pile-supported residence will continue to act as a filter for pollutants. Janson has mitigated the small loss in wetlands by modifying his project so as to remove the concrete slab and tool shed from the marsh area to the uplands. Due to the project's small size, no storm water impact can be expected. Additionally, no evidence was introduced to show a violation of any water quality standard as a result of the proposed project. On March 16, 1983, Respondent, Department of Environmental Regulation, executed its Intent to Issue the dredge and fill permit in accordance with the revised application and subject to the conditions that: (1) turbidity curtains be employed in the ditch during the placement of fill over the culvert to contain any turbidity generated, and (2) construction on the uplands be confined to periods of normal water level conditions. On July 5, 1983, the Department of the Army Corps of Engineers issued its Permit and Notice of Authorization. The essence of the testimony presented by the Petitioners, including that of the employees of the St. Johns River Water Management District, who testified in opposition to the proposed project, is that even though Janson's proposed project would not impact water quality in a way that was either significant or measurable (although no one even suggested any specific water quality standard that might be violated), approval of Janson's permit might set a precedent for other projects which might then have a cumulative impact in some unspecified way at some unspecified location. No evidence was offered to show that Respondent, Department of Environmental Regulation's review of permit applications is other than site specific. Further, no evidence was introduced to show any proposed project anywhere having any impact with which Janson's project could be cumulative. Petitioners Sandquist and Shuler live in the neighborhood of the proposed project, perhaps as close as two blocks away.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered dismissing with prejudice the petition filed herein as to each individual Petitioner and issuing a dredge and fill permit to Respondent Janson in accordance with his revised application. DONE and RECOMMENDED this 13th day of January, 1984, in Tallahassee, Leon County, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1984. COPIES FURNISHED: Stormy Sandquist 3 Aviles Street St. Augustine, FL 32084 Marion C. Snider Volla F. Snider 79 Fullerwood Drive St. Augustine, FL 32084 Carmen Ashton 51 East Park Avenue St. Augustine, FL 32084 Reuben D. Sitton Gail P.Sitton 35 Seminole Drive St. Augustine, FL 32084 Sandra N. Shuler 22 East Park Avenue St. Augustine, FL 32084 Patty Severt Greg Severt 1 Fern Street St. Augustine, FL 32084 Nancy Moore Paul Moore, Jr. 6 Fern Street St. Augustine, FL 32084 John D. Bailey, Jr., Esq. P.O. Box 170 St. Augustine, FL 32085-0170 Charles G. Stephens, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301
Findings Of Fact Background Petitioner, David E. Musselman, is the owner of Lot 23, Block 22, Cudjoe Gardens Eighth Addition, Cudjoe Key, Monroe County, Florida. The lot measures 127 feet along its front and rear property line, 135 feet along its side property lines and, similar to adjacent lots, its rear property line abuts an artificially created waterway. Currently, most of petitioner's lot enjoys an elevation of six feet; however, from the edge of the waterway landward a distance of approximately 20 feet [to what has been referred to as the "toe of the existing slope" in these proceedings] the surface consists of exposed caprock at an elevation of approximately four inches above mean high water. It is petitioner's desire to construct a single family residence upon such lot and, incident to such construction, to erect a seawall along the edge of the waterway such that the elevation at the waterway will be increased by two feet, and to backfill from the seawall to his home. Such backfilling would require the deposition of approximately 3,540 square feet of fill within the Department's jurisdiction, which was shown to extend from the edge of the waterway to the toe of the existing slope, and would raise the elevation in such area two feet above existing grade. On December 16, 1991, petitioner filed an application with respondent, Department of Environmental Regulation (Department), for an exemption from the Department's wetland permitting requirements. If approved, such exemption would allow petitioner to construct the vertical seawall along the waterway, and backfill from the seawall to his proposed home. By notice of agency action dated February 14, 1992, the Department proposed to deny petitioner's application predicated on its conclusion that his proposal did not meet the exemption criteria established by Rule 17- 312.050(1)(g), Florida Administrative Code. Petitioner filed a timely protest to contest the Department's conclusion. The exemption Pertinent to this case, Rule 17-312.050(1)(g), Florida Administrative Code, exempts from permitting the following activities: (g) Construction of seawalls or riprap, including only that backfilling needed to level the land behind the seawalls or riprap, in artificially created waterways where such construction will not violate existing water quality standards, impede navigation or adversely affect flood control. An artificially created waterway shall be defined as a body of water that has been totally dredged or excavated and which does not overlap natural surface waters of the state. For the purpose of this exemption, artificially created waterways shall also include existing residential canal systems . . . . At hearing, the parties stipulated that the waterway which abuts the rear property line of petitioner's lot is an artificially created waterway, as well as an existing residential canal, and that the proposed project will not violate existing water quality standards, impede navigation, or adversely affect flood control. Notwithstanding, the Department contends that petitioner's application should be denied because no need has been demonstrated that would support the construction of the seawall along the edge of the waterway, as opposed to locating it further inland, and therefore the amount of backfill, with its attendant loss of wetlands, is excessive. For the reasons set forth in the conclusions of law, the Department's position is untenable as a matter of law. 1/
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department enter a final order approving petitioner's application for an exemption to construct a seawall, and to backfill from such seawall to his proposed home, as applied for. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 4th day of June 1992. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of June 1992.
The Issue The issue is whether Respondent, Krista Howard,2/ is entitled to issuance of the Consolidated Environmental Resource Permit and Recommended Intent to Grant Sovereignty Submerged Lands Authorization, Permit No. 53-0351424-001-EI, as announced by Respondent, Department of Environmental Protection, in the Consolidated Notice of Intent to Issue Environmental Resource Permit and Lease to Use Sovereignty Submerged Lands issued on July 28, 2017, and subsequently amended on January 11, 2018.3/
Findings Of Fact The Parties Petitioner Defenders is a Florida non-profit corporation that has been in existence since the mid-1980s or earlier. Defenders' primary purpose is to protect and preserve Crooked Lake so that it may remain an Outstanding Florida Water ("OFW") for all members of the public to use and enjoy. Defenders has more than 25 members who reside in Polk County, Florida. Its membership consists of approximately 100 family memberships, mostly comprised of persons who live on or near Crooked Lake. Petitioners Gerards are riparian landowners on Crooked Lake, whose property is located immediately adjacent to, and slightly to the northwest of, Respondent Howard's property. The Gerards' home address is 1055 Scenic Highway North, Babson Park, Florida 33827. Respondent Howard is the applicant for the Consolidated Authorization for the Dock. Howard's property, which is riparian to Crooked Lake, is located at 1045 Scenic Highway North, Babson Park, Florida 33827. Respondent DEP is the administrative agency of the State of Florida statutorily charged with, among other things, protecting Florida's water resources. As part of DEP's performance of these duties, it administers and enforces the provisions of chapter 373, part IV, Florida Statutes, and the rules adopted pursuant to that statute. Pursuant to that authority, DEP determines whether to issue or deny applications for ERPs. Pursuant to section 253.002, Florida Statutes, DEP also serves as staff to the Board of Trustees of the Internal Improvement Trust Fund ("Board of Trustees") and, in that capacity, reviews and determines whether to issue or deny, applications for approval to use sovereignty submerged lands.5/ DEP Review of the Application The Dock is proposed to be located on sovereignty submerged lands and in surface waters subject to State of Florida regulatory jurisdiction. Therefore, an environmental resource permit and a sovereignty submerged lands lease are required. On or about February 14, 2017, Todd Rickman, Howard's professional contractor who designed the Dock, filed an Application for a Sovereignty Submerged Lands Lease for Existing Structures and Activities6/ ("Application") with DEP's Southwest District Office, seeking approval to construct and operate the Dock. On or about March 15, 2017, DEP requested additional information regarding the project. Howard submitted the requested items, and the Application was determined complete on May 30, 2017. Notice of DEP's receipt of the Lease portion of the Application was provided as required by section 253.115. The comment period commenced on June 15, 2017, and ended on July 6, 2017. As previously noted, on July 28, 2017, DEP issued the Consolidated Notice of Intent, proposing to issue the Consolidated Authorization to construct and operate the Dock. On January 11, 2018, DEP amended the Consolidated Notice of Intent to accurately reflect the "clearly in the public interest" permitting standard for the ERP portion of the Consolidated Authorization, which is applicable to projects proposed in OFWs. Background Crooked Lake Crooked Lake (also, "Lake") is an approximately 4,247-acre freshwater lake in Polk County, Florida. It is an irregularly shaped karst lake roughly resembling an inverted "L," with the longer axis running north to south. It is located on the Lake Wales Ridge. Crooked Lake is designated an OFW by Florida Administrative Code Rule 62-302.700(9)(i)9.7/ The Lake is classified as a Class III waterbody pursuant to Florida Administrative Code Rule 62-302.400(15).8/ The elevations and bottom contours in Crooked Lake vary substantially throughout the Lake. Thus, water depths may, and generally do, vary substantially from one location to another throughout the Lake. The water levels in Crooked Lake fluctuate frequently and, at times, dramatically, depending on rainfall frequency and amounts. A graph prepared by Petitioners' Witness James Tully, using Southwest Florida Water Management District ("SWFWMD") historical water level data for Crooked Lake measured in National Geodetic Vertical Datum of 1929 ("NGVD") shows water levels historically fluctuating from as low as approximately 106 feet in or around 1991, to as high as 123 feet NGVD in or around 1951, 1961, and 2004. Rickman generated a water level graph using the Polk County Water Atlas ("Atlas") website. This graph, which covers the period of 2008 through mid-2017, shows that the water levels in Crooked Lake, for this most recent ten-year period, fluctuated approximately five feet, with the lowest levels falling slightly below 114 feet NGVD for relatively short periods in 2012 and 2013, and the highest level rising to approximately 119 feet NGVD in mid-2017. The competent, credible evidence shows that although water levels in Crooked Lake may occasionally rise to levels at or around 123 feet NGVD, those conditions have been associated with extreme weather events such as hurricanes, are atypical, and are relatively short-lived. The maximum water level in Crooked Lake is subject to control by a weir located south of the Lake. Discharge from the weir occurs at a control elevation of 120 feet NGVD. As such, the water level in parts of Crooked Lake may, at times, temporarily exceed 120 feet NGVD, but will eventually decrease to 120 feet NGVD as the water flows south and is discharged through the weir. To the extent rainfall does not recharge the Lake, water levels may fall below 120 feet NGVD. The ordinary high water line ("OHWL"), which constitutes the boundary between privately-owned uplands and sovereignty submerged lands, has been established at 120.0 feet NGVD for Crooked Lake. Crooked Lake is used for recreational activities such as fishing, swimming, boating, and jet ski use, and there are public and private boat ramps at various points on the lake that provide access to the Lake. There is no marina having a fueling station on the Lake. The credible evidence shows that the northeast portion of the Lake, where the Dock is proposed to be located, experiences a substantial amount of boat and jet ski traffic. This portion of the Lake also is used for swimming, water- skiing, wakeboarding, the use of "towables" such as inner tubes, and for other in-water recreational uses. The Proposed Dock Howard holds fee title by warranty deed to parcel no. 333028-000000-033140 located at 1045 Scenic Highway, Babson Park, Florida.9/ This parcel has approximately 110 linear feet of riparian shoreline on Crooked Lake. The Dock is proposed to be constructed and operated on sovereignty submerged lands adjacent to this riparian upland parcel, which is located on the eastern shore of the northeastern portion of Crooked Lake. The Dock, as proposed, is a private single-family residential dock that will be used by Howard for water-dependent recreational purposes, such as specifically, boating, fishing, swimming, and sunbathing. The Dock is not proposed to be constructed or used by, or to otherwise serve, commercial or multifamily residential development. The Dock is configured as a "T," supported by pilings and consisting of a 4-foot-wide by 152-foot-long access walkway, and an approximately 1,983-square-foot terminal platform comprised of a lower-level platform having four vessel slips and a flat platform roof. Two sets of stairs lead from the lower level of the terminal platform to the platform roof, which will be elevated eight feet above the lower-level platform and will have a railed perimeter. The platform roof will function as a roof for the boat storage area below and a sundeck. The four slips on the Dock's lower-level platform will be used for permanent mooring for up to six watercraft: a 23-foot-long ski boat,10/ a 20-foot-long fishing boat, and four jet skis. As proposed, the Dock will occupy a total area of approximately 2,591 square feet. The lower platform of the Dock is proposed to be constructed at an elevation of 121 feet NGVD. The roof/upper platform will be constructed eight feet above that, at an elevation of 129 feet NGVD. The pilings supporting the Dock will be wrapped in an impervious material to prevent leaching of metals and other pollutants into the water. Pursuant to the Specific Purpose Field Survey ("Survey") for the Lease submitted as part of the Application, the Lease will preempt approximately 2,591 square feet, and closely corresponds to the footprint of the Dock. The submerged lands surrounding the Dock that are not occupied by the footprint of the Dock, including the area between terminal platform and the shoreline, are not included in the preempted area of the Lease.11/ The Survey shows "approximate riparian lines" which delineate Howard's riparian area oriented to the center of the waterbody and to the primary navigation channel in the northeast portion of Crooked Lake. As shown on the version of the Survey initially filed as part of the Application, the Dock was proposed to be located approximately 4.7 feet, at its closest point, from the southern riparian line. However, in response to DEP's request for additional information, the Survey was modified in April 2017, to shift the Dock northward within Howard's riparian area. The Dock is now proposed to be located 25.1 feet, at its closest point, from the southern riparian line, and 29.4 feet, at its closest point, from the northern riparian line. The walkway of the Dock will commence at an approximate elevation of 120 feet NGVD, which corresponds to the OHWL established for Crooked Lake. As previously noted above, the walkway will extend waterward approximately 152 feet, where it will intersect with the terminal platform. The terminal platform will extend another 52 feet waterward. In total, the Dock is proposed to extend waterward approximately 204 feet from the OHWL. Although the Dock would be one of the longest and largest docks on Crooked Lake, the credible evidence establishes that there are several other docks of similar size and/or length on the Lake. Rickman testified that he obtained approvals for, or was otherwise aware of, several docks over 2,000 square feet on the Lake. Additionally, the evidence showed that eight other docks on the Lake are longer than the proposed Dock.12/ Rickman testified that most of the larger docks on Crooked Lake have roofs, and that most of these roofs are pitched, rather than flat.13/ As noted above, the water level in Crooked Lake frequently and, at times, extensively fluctuates. As a result, there are periods during which water depths in parts of the Lake are extremely shallow. Rickman testified that the Dock was designed to extend far enough out into Crooked Lake to reach sufficient water depth to enable Howard to maximize the use of the Dock for boating throughout the year. The Dock is designed to extend out to the point at which the bottom elevation of the Lake is approximately 109.9 feet NGVD. Based on the Atlas' ten-year water level graph for Crooked Lake referenced above, Rickman projected that at this point, the water depth typically would be sufficient to allow Howard to operate her largest vessel, the 23-foot ski boat. The ski boat has a 25-inch draft.14/ The boat will be stored out of the water on a boat lift on the Dock, attached by cables to a sub-roof immediately beneath the platform roof. When being lowered into or hoisted from the water, the boat will be placed in a boat cradle consisting of two containment railings approximately 18 inches high each on either side, and a "V" shaped aluminum bottom with bunks on which the boat is cradled. The aluminum bottom of the cradle was estimated to be two to three inches thick. Although the boat cradle is approximately 18 to 21 inches in "total height,"15/ the cradle does not have to be completely lowered its entire 18- to 21-inch height into the water when used. Steven Howard explained, credibly, that the cradle needs to be lowered into the water only a few inches lower than the ski boat's 25-inch draft to enable the boat to float into or out of the cradle. To that point, Rickman testified that taking into account the 25-inch draft of the ski boat and the "total height" of the boat cradle, between 40 and 44 inches of water depth would be required when the cradle is used in order to avoid coming into contact with the Lake bottom. Based on the Atlas graph showing the lowest water levels for the previous ten-year period at approximately 114 feet NGVD, Rickman designed the Dock to extend out to the 109.9-foot NGVD bottom elevation point. At this point, the projected water depth would be slightly more than four feet during periods of the lowest projected water levels for Crooked Lake. For the Dock to be able to wharf out to 109.9 feet NGVD bottom elevation, it must extend a total of approximately 204 feet waterward into the Lake. The credible evidence establishes that while Howard's ski boat is one of the largest, it is not the largest boat operated on Crooked Lake. Impacts Assessment for Environmental Resource Permit Water Quality Impacts As noted above, Crooked Lake is a Class III waterbody. Accordingly, the surface water quality standards and criteria applicable to Class III waters in Florida codified in rule 62-302.300 apply to Crooked Lake. The Dock, as proposed to be constructed and operated, is not anticipated to adversely affect or degrade water quality in Crooked Lake. Specifically, as required by the Consolidated Authorization, a floating turbidity curtain will be installed around the boundary of the construction area before construction commences, and it must be left in place until construction is complete and turbidity levels in the work area have returned to background levels. Additionally, as noted, the pilings supporting the Dock must be wrapped in an impervious material to prevent leaching of metals and other pollutants into the water over the life of the structure. The Consolidated Authorization also prohibits the installation and use of fueling equipment at the Dock; prohibits the discharge of sewage or other waste into the water; prohibits liveaboards; prohibits fish cleaning or the installation of fish cleaning stations unless sufficient measures such as sink screens and waste receptacles are in place; and prohibits repair and maintenance activities involving scraping, sanding, painting, stripping, recoating, and other activities that may degrade water quality or release pollutants into the water. Although the Consolidated Authorization imposes a specific condition requiring, for all vessels using the Dock, a minimum 12-inch clearance between the deepest draft of the vessel (with motor in the down position) and the top of submerged resources, it does not specifically address circumstances where the use of the boat cradle, rather than the vessel itself, may come into contact with the Lake bottom. DEP's witness acknowledged that if the boat cradle were to come into contact with the Lake bottom, water quality standards may be violated. Given the information presented at the final hearing regarding the operation of the boat lift and the need for sufficient clearance between the bottom of the boat cradle and the lake bottom, the undersigned recommends that a specific condition be included in the Consolidated Authorization prohibiting contact of the Lake bottom by the boat cradle. This recommended condition is set forth in paragraph 73.A., below. Upon consideration of the conditions imposed by the Consolidated Authorization discussed above, including imposing a specific condition that prohibits contact of the boat cradle with the Lake bottom, the undersigned finds that the Dock will not adversely affect or degrade the water quality of Crooked Lake. Water Quantity Impacts The Dock, as proposed, is a piling-supported structure that will not impound, store, or impede the flow of surface waters. As such, the Dock will not cause adverse flooding to on-site or offsite property, will not result in adverse impacts to surface water storage and conveyance capabilities, and will not result in adverse impacts to the maintenance of surface or ground water levels. Impacts to Fish, Wildlife, and Listed Species and Habitat The Application states, in section 5, question 6, that there is no vegetation on Howard's riparian shoreline. However, the Survey depicts an area of emergent grasses approximately 60 feet wide and extending diagonally approximately 70 feet waterward into the Lake. The Survey depicts this grassed area as straddling the riparian line between Howard's property and the adjacent parcel to the south. The Survey shows the Dock as being located a significant distance waterward of the grassed area, such that no portion of the Dock will be located on or near this grassed area. Additionally, an aerial photograph of Howard's property and the Lake waterward of Howard's property shows a smaller patch of what appears to be emergent grasses further offshore. This grassed area is not shown on the Survey, and it cannot definitively be determined, by examining the Survey and the aerial photograph, whether this grassed area is growing in an area that will be impacted by the Dock. Steven Howard acknowledged that this smaller grassed area may be located at or near the jet ski slip on the southeastern side of the Dock. An environmental assessment of this smaller grassed area was not performed or submitted as part of the Application. Thus, any value that this area may have as fish and wildlife habitat was not assessed as part of DEP's determination that the Dock will not adversely impact the value of functions provided to fish, wildlife, and to listed species and their habitat. In order to provide reasonable assurance that the Dock will not adversely impact the value of functions provided to fish, wildlife, and to listed species and their habitat, the undersigned recommends including a specific condition in the Consolidated Authorization requiring this smaller grassed area to be completely avoided during construction and operation of the Dock, or, if avoidance is not feasible, that an environmental assessment be performed prior to construction so that the value of this grassed area, if any, to fish, wildlife, and listed species can be evaluated to determine whether minimization and compensatory mitigation should be required. This recommended condition is set forth in paragraph 73.B., below. As previously noted, the Consolidated Authorization contains a specific condition requiring a minimum 12-inch clearance between the deepest draft of the vessel (with the motor in the down position) and the top of submerged resources for all vessels that will use the docking facility. Compliance with this condition will help ensure that the value of functions provided to fish and wildlife and to listed species and their habitat of any such submerged resources is not adversely impacted by vessels using the Dock. The Consolidated Authorization also contains a specific condition requiring handrails to be installed on the Dock to prevent mooring access to portions of the Dock other than the wetslips. This will help protect submerged resources in shallower areas in the vicinity of the Dock. Fish populations in the immediate area of the Dock site may temporarily be affected during construction of the Dock; however, those impacts are not anticipated to be permanent. Additionally, as previously discussed, the Dock pilings must be wrapped with an impervious material to prevent leaching of pollutants into the water, and once installed, the pilings may provide habitat for fish and a substrate for benthic organisms. Provided that the conditions set forth in the draft Consolidated Authorization, as well as the recommendation regarding the smaller grassed area, are included in the final version of the Consolidated Authorization, it is determined that the construction and operation of the Dock will not adversely impact the value of functions provided to fish, wildlife, or to listed species or their habitat.16/ Impact on Navigation Petitioners assert that the Dock will constitute a hazard to navigation in the northeast portion of Crooked Lake. Specifically, they assert that because the Dock will extend out approximately 204 feet into the Lake, it necessarily will create a navigational hazard to boaters in the vicinity. As support, Petitioners presented evidence consisting of Steven Howard's testimony that an inner tube on which his nephew was riding, that was being pulled behind a motor boat, collided with the Gerards' 84-foot-long floating dock adjacent to Howard's riparian area. Petitioners argue that if an 84-foot-long dock creates a navigational hazard, a 204-foot-long dock would create an even greater navigational hazard. The undersigned does not find this argument persuasive. The portion of Crooked Lake on which the Dock is proposed to be located is approximately a mile and a half to two miles long and one-half to three-quarters of a mile wide. Although this portion of Crooked Lake experiences substantial boat traffic, the evidence shows that the Lake is sufficiently large in this area, even with the Dock in place, to allow safe navigation. To this point, it is noted that there are two other longer docks in the northeastern portion of Crooked Lake, extending 220 and 244 feet into the Lake from the shoreline. There was no evidence presented showing that either of these docks constitutes a navigational hazard.17/ Petitioners also assert that during periods of high water in this portion of Crooked Lake, the Dock will be underwater and thus will present a navigational hazard. In support, they presented photographs taken on October 30, 2017—— approximately six weeks after Hurricane Irma struck central Florida——showing ten docks, out of the 109 docks on Crooked Lake, that were partially or completely submerged.18/ When the photographs were taken, the approximate water elevation was 119.2 feet NGVD. All or a portion of the submerged docks had been constructed at or below the 119.2-foot NGVD elevation. The docks without roofs were mostly or completely invisible under the water. However, for the roofed docks, the roofs remained visible above the water even when their docking platforms were submerged. Here, although the walkway and lower platform of Howard's Dock is proposed to be constructed at an elevation of 121 feet NGVD, the roof will be constructed at an elevation of 129 feet NGVD. Thus, even during the relatively infrequent periods19/ during which the water level in Crooked Lake may exceed 121 feet NGVD, the platform roof will still be visible to vessels navigating in this portion of the Lake. Additionally, the Consolidated Authorization contains a specific condition requiring the waterward end of the Dock to be marked with a sufficient number of reflectors to be visible from the water at night by reflected light. This condition provides additional assurance that the Dock will not present a navigational hazard. For these reasons, it is determined that the Dock will not adversely affect navigation. Other ERP-Related Issues The evidence did not show that the Dock is proposed to be located in or proximate to a "work of the District," as defined in section 373.019(28). The only "work of the District" about which evidence was presented is the weir located south of Crooked Lake. This structure is many thousands of feet south of the Dock. There was no evidence presented showing that the Dock would have any impact on this weir. The Dock, as proposed, was designed by an experienced professional contractor who has designed and installed many docks on Crooked Lake, and, as such, is anticipated to function as proposed. The Dock must be built according to engineering diagrams to the Consolidated Authorization, and as-built drawings must be submitted when Dock construction is complete so that DEP can confirm that the Dock is constructed in accordance with the approved design. The evidence establishes that Howard, as the applicant, and Rickman, as the professional contractor in charge of construction, are financially, legally, and administratively capable of ensuring that the activity will be undertaken in accordance with the terms and conditions of the Consolidated Authorization. No evidence to the contrary was presented. The Dock will be located in the waters of Crooked Lake and will be affixed to the submerged bottom. The Department of State, Division of Historical Resources ("DHR"), did not provide any comments indicating that historical or archaeological resources are anticipated to be impacted by the project. Additionally, the Consolidated Authorization contains a general condition requiring subsurface activity associated with construction of the Dock to immediately cease, and DHR to be contacted, if any prehistoric or historic artifacts, such as pottery or ceramics, stone tools or implements, dugout canoes, or other physical remains that could be associated with Native American cultures or early colonial or American settlements are encountered at any time within the project site area. Additional Recommended Conditions Based on the foregoing, the undersigned recommends that the following specific conditions be included in the Consolidated Authorization, Permit No. 53-0351424-001-EI: A minimum six-inch clearance shall be maintained between the top of all submerged resources and the deepest draft of the cradle of the boat lift while in use. For purposes of this condition, submerged resources consist of the bottom sediment and/or any submerged grasses or other aquatic organisms. Any emergent grasses in the permittee's riparian area shall be avoided during the construction and operation of the Dock. If it is not feasible to avoid these grasses, an environmental assessment of the grassed area shall be performed and submitted to the Department prior to commencing construction, so that the value of this grassed area, if any, to fish, wildlife, and listed species can be evaluated and the extent to which minimization and/or compensatory mitigation is appropriate can be determined. Clearly in the Public Interest Florida Administrative Code Rule 62-4.070, Standards for Issuing or Denying Permits, states in pertinent part: A permit shall be issued to the applicant upon such conditions as the Department may direct, only if the applicant affirmatively provides the Department with reasonable assurance based on plans, test results, installation of pollution control equipment, or other information, that the construction, expansion, modification, operation, or activity of the installation will not discharge, emit, or cause pollution in contravention of Department standards or rules. In addition to the foregoing permitting requirements, because the Dock is proposed to be located in an OFW, Howard also must provide reasonable assurance that the Dock meets the "clearly in the public interest" standard. The "clearly in the public interest" standard does not require the applicant to demonstrate need for the project or a net public benefit from the project. Rather, this standard requires the applicant to provide greater assurances, under the circumstances specific to the project, that the project will comply with the applicable permitting requirements.20/ For the reasons discussed above, and with the inclusion of the additional recommended conditions in paragraphs 73.A. and 73.B., it is determined that the proposed Dock meets the applicable permitting requirements and the "clearly in the public interest" standard for issuance of the ERP. Impacts Assessment for Sovereignty Submerged Lands Lease Water-Dependency of the Proposed Dock A water-dependent activity is one which can only be conducted in, on, over, or adjacent to water areas because the activity requires direct access to the water body or sovereignty submerged lands for specified activities, including recreation, and where the use of water or sovereignty submerged lands is an integral part of the activity. See Fla. Admin. Code R. 18-21.003(71). Petitioners argue that the Dock will not constitute a water-dependent activity because the depth of water in the slips may, at times, be insufficient to allow operation of Howard's vessels while complying with the requirement that a minimum 12- inch clearance be maintained between the lowest draft of the vessel and submerged resources. The undersigned finds this argument unpersuasive. The Dock is being constructed specifically for the purpose of enabling Howard to use her vessels for boating——a recreational activity for which use of the water indisputably is an integral part. The Dock's primary purpose is to moor vessels that will be used for the water-dependent recreational activities of boating and fishing, and other water-dependent recreational uses of the Dock include fishing, swimming and sunbathing. Case law interpreting the Florida Administrative Code Chapter 18-21 makes clear that because docks are used for mooring vessels or conducting other in-water recreational uses, they are "water-dependent" activities for purposes of the rules.21/ Thus, even if water depths in the Dock's slips are at times insufficient for vessel mooring or launching,22/ this does not render the Dock not a "water-dependent activity." Resource Management Requirements The preempted area of the Lease is proposed to be used for a Dock that will be used for boating, fishing, and swimming. These traditional in-water recreational uses are consistent with the management purposes of sovereignty submerged lands as described in rule 18-21.004(2)(a). With the inclusion of the conditions currently proposed in the draft Consolidated Approval, as well as the recommended conditions in paragraphs 73.A. and 73.B., the undersigned determines that the Dock will not result in adverse impacts to sovereignty submerged lands and associated resources. With the inclusion of the conditions currently proposed in the draft Consolidated Approval, as well as the recommended conditions in paragraphs 73.A. and 73.B., the undersigned determines that the Dock is designed to minimize or eliminate impacts to fish and wildlife habitat and submerged resources. With the inclusion of the currently proposed conditions in the draft Consolidated Authorization, as well as the recommended conditions set forth in paragraphs 73.A. and 73.B., it is determined that the Dock, as designed and constructed, will minimize or eliminate cutting, removal, or destruction of wetland vegetation. Additionally, as discussed above, the proposed Consolidated Approval requires the avoidance of adverse impacts to historic and cultural resources. Riparian Rights Consistent with rule 18-21.004(3)(d), the Dock is proposed to be constructed in Howard's riparian area and will be set back more than 25 feet from the northerly and southerly riparian lines shown on the Survey. Rule 18-21.004(3)(a) prohibits activities authorized under chapter 18-21 from being implemented in a manner that would unreasonably infringe on traditional common law riparian rights, as defined in section 253.141, of upland owners adjacent to sovereignty submerged lands. Similarly, rule 18-21.004(3)(c) requires all structures and activities to be designed and conducted in a manner that will not unreasonably restrict or infringe upon the riparian rights of adjacent riparian owners. Collectively, these provisions prohibit an activity that will occur on sovereignty submerged lands from unreasonably infringing on or unreasonably restricting the riparian rights of upland riparian owners. Riparian rights are rights appurtenant to, and inseparable from, riparian land that borders on navigable waters. § 253.141, Fla. Stat.; Broward v. Mabry, 50 So. 830 (Fla. 1909). At common law, riparian rights include the rights of navigation, fishing, boating, and commerce. Hayes v. Bowman, 91 So. 2d 795 (Fla. 1957). The right of navigation necessarily includes the right to construct and operate a dock to access navigable waters. Belvedere Dev. Corp. v. Dep't of Transp., 476 So. 2d 649 (Fla. 1985); Shore Vill. Prop. Owners' Ass'n v. Dep't of Envtl. Prot., 824 So. 2d 208, 211 (Fla. 4th DCA 2002). Common law riparian rights also include the right to an obstructed view. Lee Cnty v. Kiesel, 705 So. 2d 1013 (Fla. 2d DCA 1998). Many of these common law riparian rights have been statutorily codified in section 253.141. Statutory riparian rights include the "rights of ingress, egress, boating, bathing, and fishing and such others as may be or have been defined by law." § 253.141(1), Fla. Stat. At issue in this case are the competing riparian rights of next-door neighbors——i.e., Howard's right to wharf out to navigable waters for purposes of boating and other water- dependent recreational activities, and the Gerards' right to an unobstructed view. The question is whether Howard's proposed construction and operation of a dock of sufficient length to enable her to use her boats would unreasonably infringe on or unreasonably restrict the Gerards' right to an unobstructed view of the Lake. By virtue of the riparian rights appurtenant to Howard's riparian property, she is entitled to wharf out to water deep enough to enable her to navigate. She owns two boats, one of which pulls a draft of 25 inches, and the other, a draft of 20 inches, which she uses to navigate the Lake. Thus, an essential aspect of Howard's riparian right of navigation is her ability to construct and operate a dock long enough to enable her to reach water depths sufficient to use these boats. However, as noted above, this right is not unfettered. Howard's exercise of her riparian navigation right cannot unreasonably infringe on Gerard's right to an unobstructed view. Florida case law holds that the right to an "unobstructed" view does not entail a view free of any infringement or restriction whatsoever by neighboring structures or activities. In Hayes, the court defined the right as "a direct, unobstructed view of the [c]hannel and as well a direct, unobstructed means of ingress and egress . . . to the [c]hannel." Id. at 801 (emphasis added). The court then prescribed the rule that "in any given case, the riparian rights of an upland owner must be preserved over an area 'as near as practicable' in the direction of the [c]hannel so as to distribute equitably the submerged lands between the upland and the [c]hannel." Id. (emphasis added). To the extent there is no channel in this portion of the Lake, Hayes dictates that riparian rights must be apportioned equitably, so that a riparian owner's right to an unobstructed view can extend only from the owner's property in the direction of the center of the Lake. Kling v. Dep't of Envtl. Reg., Case No. 77-1224 (Fla. DOAH Oct. 6, 1977; Fla. DER Nov. 18, 1977) at ¶¶ 11-12 (emphasis added). Here, no evidence was presented showing that the Dock——which will be located immediately south and east of the Gerards' riparian property and attendant riparian area——will present an obstruction to the Gerards' view of the Lake channel. Additionally, the evidence did not establish that Howard's Dock would obstruct the Gerards' view of the center of the northeast portion of Crooked Lake, which is located west and slightly south of their property.23/ Administrative precedent in Florida provides additional support for the determination that the Dock will not unreasonably infringe on the Gerards' right to an unobstructed view. In O'Donnell v. Atlantic Dry Dock Corporation, Case No. 04-2240 (Fla. DOAH May 23, 2005; Fla. DEP Sept. 6, 2005), riparian owners challenged the proposed approval of expansions of sovereignty submerged lands leases authorizing Atlantic Dry Dock, a neighboring commercial shipyard, to expand its shipyard facilities and install new docking facilities. The administrative law judge noted that although the expanded shipyard would further encroach on the riparian owners' already somewhat-restricted view from their property, it would not substantially and materially obstruct the Petitioners' view to the channel. He commented: "it [their view] may be further obstructed to the west in the direction of the Atlantic Marine yard, but not in the direction of the channel." To that point, he found that although "any lateral encroachment on the Petitioners' line-of-sight to the channel by the large eastern dry dock proposed will be an annoyance, . . . [it] will not rise to the level of a substantial and material interference or obstruction of the Petitioners' view to the channel." Id. at ¶ 119. He found that "there is no 'special riparian right' to a view of the sunset, just as there was no right to a particular object of view . . . by the riparian owners complaining in the Hayes case." Id. at ¶ 120. Castoro v. Palmer, Case Nos. 96-0736, 96-5879 (Fla. DOAH Sept. 1, 1998; Fla. DEP Oct. 19, 1998), also is instructive. In Castoro, neighboring riparian owners challenged the proposed issuance of an environmental approval and sovereignty submerged lands lease for a 227-foot-long dock having a terminal platform with boat lift. The owners contended that due to the dock's length, it would impermissibly obstruct their views of the water. The administrative law judge rejected that contention, distinguishing the circumstances from those in Lee County v. Kiesel, 705 So. 2d 1013 (Fla. 2d DCA 1998), in which the construction of a bridge that blocked 80 percent of the riparian owners' view of the channel was held to constitute a "substantial and material" obstruction to the riparian right of view. The ALJ noted that although the dock would have "some impact on the neighbors' views" and their use of the waterbody, it did not unreasonably impact their riparian rights to an unobstructed view or to use of the waterbody. Id. at ¶¶ 73-74. In Trump Plaza of the Palm Beaches Condominium v. Palm Beach County, Case No. 08-4752 (Fla. DOAH Sept. 24, 2009; Fla. DEP Oct. 8, 2009), a condominium association challenged the proposed issuance of a sovereignty submerged lands use approval to fill in a dredged area and create mangrove islands in the Lake Worth Lagoon, alleging, among other things, that the creation of the mangrove islands would unreasonably infringe on their riparian right to an unobstructed view. In rejecting this position and recommending issuance of the submerged lands use approval, the ALJ noted that the area obstructed by the mangrove islands would be negligible compared to the remaining expanse of the view, and further noted that the owners' real concern was directed at the aesthetics of the project——specifically, they did not want to view mangrove islands. The ALJ stated: "[t]he evidence supports a finding that while the project will undoubtedly alter the view of the water from [the riparian owners' property], the impact on view is not so significant as to constitute an unreasonable infringement of their riparian rights." Id. at ¶ 86. Applying these case law principles, it is determined that the Dock will not unreasonably infringe on or unreasonably restrict the Gerards' riparian right to an unobstructed view. To that point, the cases make clear that the right to an "unobstructed" view is not an unfettered right to a view of the water completely free of any lateral encroachment, but, instead is the right of a view toward the channel or the center of a lake without unreasonable infringement or restriction. Here, although the Dock will laterally encroach on the Gerards' full panoramic view of the Lake——and, as such, may even constitute an annoyance, the evidence did not show that the Dock will obstruct or otherwise restrict their view to the channel or the center of the Lake. Moreover, to the extent the Gerards have expressed concern about the Dock interfering with their view of the south shore of the Lake, O'Donnell makes clear the desire to have a particular object of view——here, the south shore of the Lake——is not a legally protected riparian right. It is also found that the Dock will not unreasonably interfere with the Gerards' riparian rights of ingress, egress, boating, or navigation. As previously noted, the Dock will be located at least 25 feet inside the riparian lines established for Howard's upland property, and, it will not be constructed in a location or operated in a manner that will obstruct, interfere with, or restrict the Gerards' access to the Lake or to sufficient water depths to enable navigation.24/ The evidence also did not establish that the Dock will restrict or otherwise interfere with the Gerards' use of their riparian area for ingress and egress, boating, fishing, bathing, or other riparian uses. In sum, it is concluded that the Dock will not unreasonably infringe on or restrict the riparian rights of adjacent upland riparian owners. Accordingly, it is determined that the Dock will meet the requirements and standards in rule 18-21.004(3) regarding riparian rights. Navigational Hazard For the reasons discussed in paragraphs 63 through 67, it is determined that the Dock will not constitute a navigational hazard in violation of rule 18-21.004(7)(g). Not Contrary to the Public Interest Rule 18-21.004(1)(a) requires an applicant to demonstrate that an activity proposed to be conducted on sovereignty submerged lands will not be contrary to the public interest. To meet this standard, it is not necessary that the applicant show that the activity is affirmatively in the "public interest," as that term is defined in rule 18-21.003(51). Rather, it is sufficient that the applicant show that there are few, if any, "demonstrable environmental, social, and economic costs" of the proposed activity. Castoro, at ¶ 69. For the reasons discussed above, and with the inclusion of the additional recommended conditions in paragraphs 73.A. and 73.B., it is determined that the proposed Dock meets the "not contrary to the public interest" standard required for issuance of the Lease. Demonstration of Entitlement to ERP Howard met her burden under section 120.569(2)(p) to present a prima facie case of entitlement to the ERP by entering into evidence the Application, the Notice of Intent, and supporting information regarding the proposed Dock. She also presented credible, competent, and substantial evidence beyond that required to meet her burden under section 120.569(2)(p) to demonstrate prima facie entitlement to the ERP. The burden then shifted to Petitioners to demonstrate, by a preponderance of the competent substantial evidence, that the Dock does not comply with section 373.414 and applicable ERP rules. For the reasons discussed above, it is determined that Petitioners did not meet their burden of persuasion under section 120.569(2)(p) in this proceeding. Accordingly, for the reasons addressed above, it is determined that Howard is entitled to issuance of the ERP for the Dock. Demonstration of Entitlement to Lease As previously discussed, Howard bore the burden of proof in this proceeding to demonstrate, by a preponderance of the evidence, that the Dock meets all applicable statutory and rule requirements for issuance of the Lease for the Dock. For the reasons discussed above, it is determined that Howard met this burden, and, therefore, is entitled to issuance of the sovereignty submerged lands lease for the Dock. Petitioners' Standing Defenders' Standing As stipulated by the parties and noted above, Defenders is an incorporated non-profit entity created for the primary purpose of protecting and preserving Crooked Lake so that it may remain an OFW for all members of the public to enjoy. Defenders has been in existence since at least the mid- 1980s. Robert Luther, the president of Defenders, testified that the organization's purpose also entails providing education and promoting public awareness in order to preserve the natural beauty, water quality, ecological value, and quality of life around Crooked Lake. As stipulated by the parties and noted above, Defenders has more than 25 members. Luther testified that Defenders has approximately 100 family members, most of whom live on or around Crooked Lake. He noted that many of Defenders' members own boats, which they park at a local boat landing on the Lake. Based on this testimony, it is inferred that these members operate their boats on Crooked Lake. After receiving the public notice of the project, Defenders' board of directors voted to oppose issuance of the Consolidated Authorization for the Dock. Luther testified that the board's decision was based on the determination that "it was clearly within the public interest" to oppose the Dock. Gerards' Standing The Gerards reside at 1055 Scenic Highway, Babson Park, Florida. Their riparian property is immediately adjacent to, and northwest of, Howard's property. The Gerards own a floating dock that is located within their riparian area.25/ The dock consists of two 4-foot- wide by 30-foot-long ramps attached to a 24-foot-long by 8-foot- wide pontoon boat. Priscilla Gerard testified that she enjoys spending time sitting and reading books on the beach in front of her property, and that having that area to sit and read is a significant aspect of her enjoyment of her lakefront property. Ms. Gerard observed that extensive boating activities in the northeast portion of the Lake on weekends is disruptive, and interferes with her use of her beach for relaxing and reading. She particularly noted that boats operating very close to the shore cause waves to splash up on her beach, interfering with her ability to sit and read close to the shore. She did not contend that Howard's use of the Dock for boating would contribute to the disruptive nature of existing boat traffic in the vicinity. Ms. Gerard has viewed the plans for the proposed Dock and is very concerned that due to its size, her view of the south side of the Lake will be completely blocked. She acknowledged, and other competent, credible evidence showed, that there are other docks on the Lake in the vicinity of her riparian property. The evidence shows that existing docks having lengths of 145 feet and 170 feet are located in the vicinity of, and are visible from, the Gerards' property. She testified that an existing dock and tiki hut block her view of the Lake to the north. She acknowledged that although Howard's Dock, if constructed as proposed, may somewhat obstruct her view to the left (south) of her property, it would not block her view straight out into the Lake. Phillip Gerard testified that he has boated extensively on Crooked Lake in a variety of vessel types. He further testified that he has observed a range of boating practices on Crooked Lake, including seeing water skiers and persons being towed behind motorized vessels on inner tubes and other types of "towables." He testified that, based on his personal observations, persons being towed do not have independent control of the speed or direction of the "towable"; thus, depending on the direction in which the towing vessel turns, the towable may be slung to the left or the right. Gerard commented that such lack of control could result in a person riding on a towable colliding with a dock, and he noted that Howard's nephew, who was riding on an inner tube being towed by a boat, was involved in such a collection with his (Mr. Gerard's) own dock. Mr. Gerard did not testify that the Dock would present a navigational hazard to, or otherwise interfere with, the Gerards' riparian right of ingress and egress. Neither of the Gerards testified that the Dock would impact their ability to access navigable waters in the Lake. Mr. Gerard acknowledged that if Howard's Dock were constructed, boats that currently travel very close to the shoreline of his property would be forced to swing further out in the Lake, away from his riparian shoreline, in order to avoid the Dock.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order approving the issuance of Consolidated Environmental Resource Permit and Recommended Intent to Grant Sovereignty Submerged Lands Authorization, Permit No. 53-0351424-001-EI, on the terms and conditions set forth in the Consolidated Notice of Intent and attached draft of Permit No. 53-0351424-001-EI, as modified to include the Additional Recommended Conditions set forth in paragraphs 73.A. and 73B. DONE AND ENTERED this 5th day of July, 2018, in Tallahassee, Leon County, Florida. S CATHY M. SELLERS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of July, 2018.
The Issue The issue is whether the City's applications for an individual stormwater permit and a noticed general environmental resource permit for Phase 1A of the proposed Hogtown Creek Greenway should be approved.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In these two cases, Respondent, City of Gainesville (City), seeks the issuance of a stormwater system management permit (stormwater permit) to construct a 2,000-foot long asphaltic trail/boardwalk, a parking facility and associated improvements for Phase 1A of the Hogtown Creek Greenway project in the north central portion of the City. That matter is docketed as Case No. 97-2845. The City also seeks the issuance of a noticed general environmental resource permit (NGP) to construct 481 square feet of piling supported structures over wetlands or surface waters for the same project. That matter has been assigned Case No. 97-2846. Respondent, St. Johns River Water Management District (District), is the regulatory agency charged with the responsibility of reviewing and approving the requested permits. Petitioner, Greenspace Preservation Association, Inc., is a not-for-profit Florida corporation primarily composed of persons who own real property adjacent to the route proposed by the City, as well as local environmental interests. Petitioners, Frank Ward, Sal Locascio, Frederick P. Peterkin, and Harold M. Stahmer, are individuals who own real property adjacent to the route proposed by the City for the Greenway. The parties have stipulated that Petitioners are substantially affected by the District's proposed action and thus have standing to initiate these cases. On March 28, 1997, the City filed applications for a stormwater permit and a NPG for Phase IA of the Hogtown Creek Greenway project. After conducting a review of the applications, including an on-site visit to the area, in May 1997, the District proposed to issue the requested permits. On June 9, 1997, Petitioners timely filed a Petition for Initiation of Formal Proceedings as to both intended actions. As amended and then refined by stipulation, Petitioners generally allege that, as to the stormwater permit, the City has failed to provide reasonable assurance that the project meets the permitting requirements of the District; the City has failed to provide reasonable assurance that the stormwater system will not cause violations of state water quality standards; the City has failed to provide reasonable asurance that the project satisfies the District's minimum required design features; and the City has failed to provide reasonable assurance that the stormwater system is capable of being effectively operated and maintained by the City. As to the NPG, Petitioners generally allege that the piling supported structure is not less than 1,000 square feet; the jurisdictional wetlands are greater than the area shown on the plans submitted by the City; the City has failed to provide reasonable assurance that the system will not significantly impede navigation; the City has failed to provide reasonable assurance that the system does not violate state water quality standards; the City has failed to provide reasonable assurance that the system does not impede the conveyance of a watercourse in a manner that would affect off-site flooding; the City has failed to provide reasonable assurance that the system will not cause drainage of wetlands; and the City failed to provide reasonable assurance that the system does not adversely impact aquatic or wetland dependent listed species. Respondents deny each of the allegations and aver that all requirements for issuance of the permits have been met. In addition, the City has requested attorney's fees and costs under Section 120.595(1)(b), Florida Statutes (Supp. 1996), on the theory that these actions were filed for an improper purpose. A General Description of the Project The Hogtown Creek Greenway is a long-term project that will eventually run from Northwest 39th Street southward some seven miles to the Kanapaha Lake/Haile Sink in southwest Gainesville. These cases involve only Phase 1A of that project, which extends approximately one-half mile. This phase consists of the construction of a 2,000-foot long asphaltic concrete trail/boardwalk, a timber bridge and boardwalk, a parking facility, and associated improvements. The trail will extend from the Loblolly Environmental Facility located at Northwest 34th Street and Northwest 5th Avenue, to the intersection of Northwest 8th Avenue and Northwest 31st Drive. The trail will have a typical width of ten feet. For the majority of its length, the trail will be constructed of asphaltic concrete overlying a limerock base, and it will generally lie at the existing grade and slope away from the creek. Besides the trail, additional work involves the repaving of Northwest 5th Avenue with the addition of a curb and gutter, the construction of an entrance driveway, paved and grassed parking areas, and sidewalks at the Loblolly Environmental Facility, and the widening and addition of a new turn lane and pedestrian crosswalk at the intersection of Northwest 8th Avenue and Northwest 31st Drive. The Stormwater Permit Generally The entire Phase IA project area lies within the Hogtown Creek 10-year floodplain. It also lies within the Hogtown Creek Hydrologic Basin, which basin includes approximately 21 square miles. The project area for the proposed stormwater permit is 4.42 acres. Water quality criteria Phase IA of the Greenway will not result in discharges into surface groundwater that cause or contribute to violations of state water quality standards. When a project meets the applicable design criteria under the District's stormwater rule, there is a presumption that the project will not cause a violation of state water quality standards. There are two dry retention basins associated with the project. Basin 1 is located at the cul-de-sac of Northwest 5th Avenue and will capture and retain the stormwater runoff from the new and reconstructed impervious areas at the Loblolly Facility. Basin 2 is located at the parking area and will capture and retain stormwater runoff at the existing building and proposed grass parking area. Under the stormwater rule, the presumptive criteria for retention basins require that the run-off percolate out of the basin bottom within 72 hours. The calculations performed by the City's engineer show that the two retention basins will recover within that timeframe. In making these calculations, the engineer used the appropriate percolation rate of ten inches per hour. Even using the worst case scenario with a safety factor of twenty and a percolation rate of one-half inch per hour, the two retention basins will still recover within 72 hours. The presumptive criteria for retention basins require that the basin store a volume equal to one inch of run-off over the drainage area or 1.25 inches of run-off over the impervious area plus one-half inch of run-off over the drainage area. The calculations performed by the City's engineer show that the two retention basins meet the District's volume requirements for retention systems. An applicant is not required to utilize the presumptive design criteria, but instead may use an alternative design if the applicant can show, based on calculations, tests, or other information, that the alternative design will not cause a violation of state water quality standards. As a general rule, the District applies its stormwater rule so that water quality treatment is not required for projects or portions of projects that do not increase pollutant loadings. This includes linear bicycle/pedestrian trails. The City's proposed trail will not be a source of pollutants. The City will install signs at both entrances to the trail to keep out motorized vehicles. Except for emergency and maintenance vehicles, motorized vehicles will not be permitted on the trail. The infrequent use by emergency or maintenance vehicles will not be sufficient to create water quality concerns. The construction of a treatment system to treat the stormwater from the trail would provide little benefit and would only serve to unnecessarily impact natural areas. Although treatment of the stormwater run-off from the trail portion of the project is not required under District rules, the run-off will receive treatment in the vegetated upland buffer adjacent to the trail. The District's proposed other condition number 3 will require the City to plant vegetation in unvegetated and disturbed areas in the buffer. This will reduce the likelihood of erosion or sedimentation problems in the area of the trail. Although disputed at hearing, it is found that the City's engineer used the appropriate Manning coefficient in the calculations regarding the buffer. Even without a vegetated buffer, run-off coming from the bicycle trail will not violate state water quality standards. The City will install appropriate erosion and sediment controls. These include siltation barriers along the entire length of both sides of the proposed trail prior to commencing construction. Such barriers will not allow silt or other material to flow through, over, or under them. The City will also place hay bales and any other silt fencing necessary to solve any erosion problem that may occur during construction. In addition, the permit will require an inspection and any necessary repairs to the siltation barriers at the end of each day of construction. Saturation of the limerock bed under the paved portion of the trail is not expected to cause a problem because heavy vehicles will not regularly use the trail. The trail portion of the project can be adequately maintained to avoid deterioration. Sensitive Karst Areas Basin criteria The two proposed dry retention basins for Phase 1A are located within the District's Sensitive Karst Areas Basin. They include all of the minimum design features required by the District to assure adequate treatment of the stormwater before it enters the Floridan aquifer and to preclude the formation of solution pipe sinkholes in the stormwater system. There will be a minimum of three feet of unconsolidated soil material between the surface of the limestone bedrock and the bottom and sides of the two retention basins. The appropriate mechanism for determining the depth of limestone is to do soil borings. The soil borings performed by the City show that there is at least three feet of unconsolidated material between the bottom of the basins and any limerock where the borings were taken. In other words, limestone would not be expected to be within three feet of the bottom of either basin. Based on the soil boring results, the seasonal high water table is at least six feet below ground level. The depth of the two retention basins will be less than ten feet. Indeed, the depth of the basins will be as shallow as possible and will have a horizontal bottom with no deep spots. To make the retention basins any larger would require clearing more land. A large shallow basin with a horizontal bottom results in a lower hydraulic head and therefore is less potential for a sinkhole to form. Before entering the basins, stormwater will sheet flow across pavement and into a grass swale, thereby providing some dispersion of the volume. Finally, the two retention basin side slopes will be vegetated. Special condition number 7 provides that if limestone is encountered during excavation of a basin, the City must over- excavate the basin and backfill with three feet of unconsolidated material below the bottom of the basin. Drainage and flood protection Contrary to Petitioners' assertions, the project will not adversely affect drainage or flood protection on surrounding properties. The trail will be constructed generally at existing grade. Because the trail will be constructed at existing grade, the net volume of fill necessary for Phase 1A is approximately zero. Therefore, there will not be a measurable increase in the amount of runoff leaving the site after construction, and the trail will not result in an increase in off-site discharges. District rules require that the proposed post- development peak rate of discharge from a site not exceed the pre-development peak rate of discharge for the mean annual storm only for projects that exceed fifty percent impervious surface. The proposed project has less than fifty percent impervious surface. Even though it is not required, the City has demonstrated that the post-development rate of discharge will not exceed the pre-development peak rate of discharge. Both basins will retain the entire mean annual storm so that the post-development rate of discharge is zero. Even during a 100-year storm event, the retention basins willl not discharge. Therefore, there will not be any increase in floodplain elevations during the 10, 25, or 100-year storm events from the proposed project. Operation and maintenance entity requirements The applicable requirements of Chapter 40C-42, Florida Administrative Code, regarding operation and maintenance, have been met by the applicant. The City proposes itself as the permanent operation and maintenance entity for the project. This is permissible under District regulations. The duration for the operation and maintenance phase of the permit is perpetual. The City has adequate resources and staff to maintain the phase 1A portion of the project. The public works department will maintain the stormwater management system out of the City's utility fund. The City provides periodic inspections of all of its stormwater systems. These inspections are paid for out of the collected stormwater fees. The City will also conduct periodic inspections of the project area, and the two retention basins will be easily accessed by maintenance vehicles. The City will be required to submit an as-built certification, signed and sealed by a professional engineer, once the project is constructed. Monthly inspections of the system must be conducted looking for any sinkholes or solution cavities that may be forming in the basins. If any are observed, the City is required to notify the District and repair the cavity or sinkhole. Once the system is constructed, the City will be required to submit an inspection report biannually notifying the District that the system is operating and functioning in accordance with the permitted design. If the system is not functioning properly, the applicant must remediate the system. The City will be required to maintain the two retention basins by mowing the side slopes, repairing any erosion on the side slopes, and removing sediment that accumulates in the basins. Mowing will be done at least six times per year. The City will stabilize the slopes and bottom areas of the basins to prevent erosion. The City has a regular maintenance schedule for stormwater facilities. The project will be included within the City's regular maintenance program. The City has budgeted approximately $80,000.00 for maintenance of the trail and vegetated buffer. Also, it has added new positions in its budget that will be used to maintain and manage the Greenway system. Finally, City staff will conduct daily inspections of the Phase 1A trail looking for problems with the vegetated buffer, erosion problems along the trail, and sediment and debris in the retention basin. If the inspections reveal any problems, the staff will take immediate action to correct them. The Noticed General Environmental Resource Permit Generally By this application, the City seeks to construct 481 square feet of piling supported structures over wetlands or surface waters. The proposed structures include a 265 square foot timber bridge over an un-vegetated flow channel, which connects a borrow area to Possum Creek, and a 216 square foot boardwalk over two small wetland areas located south of the flow channel. None of the pilings for the bridge or boardwalk will be in wetlands, and no construction will take place in Hogtown or Possum Creeks. The paved portion of the trail will not go through wetlands, and there will be no dredging or filling in wetlands. The receiving waters for the project are Hogtown and Possum Creeks. Both are Class III waters. Hogtown Creek originates in north central Gainesville and flows southwest to Kanapaha Lake/Haile Sink in southwest Gainesville. Possum Creek originates in northwest Gainesville and flows southeast to its confluence with Hogtown Creek south of the proposed bridge structure. Wetlands The total area of the proposed bridge and boardwalk over surface water or wetlands is approximately 481 square feet. The wetland delineation shown on the City's Exhibit 5A includes all of the areas in the project area considered to be wetlands under the state wetland delineation methodology. The United State Army Corps of Engineers' wetland line includes more wetlands than the District wetland line. The former wetland line was used to determine the area of boardwalk and bridge over wetlands. Even using this line, however, the total area of boardwalk over surface waters or wetlands is approximately 481 square feet and is therefore less than 1,000 square feet. Navigation The proposed system does not significantly impede navigation. Further, the structures will span a wetland area and an un-vegetated flow channel, both of which are non-navigable. In fact, the flow channel generally exhibits little or no flow except after periods of rainfall. Water quality The construction material that will be used for the bridge and boardwalk will not generate any pollutants. Morever, chemical cleaners will not be used on those structures. Silt fences will be used and vegetation will be planted in the vicinity of the bridge and boardwalk to prevent erosion and sedimentation problems. The amount of erosion from drip that comes off the boardwalk will be minimal. Therefore, the bridge and boardwalk will not cause a violation of state water quality standards. Off-site flooding The project will not impede conveyance of any stream, river, or other water course which would increase off-site flooding. The structures will completely span the wetland areas and flow channel, and no part of the structures, including the pilings, will lie within any water or wetland areas including the flow channel. There will be a span of 2.5 to 3 feet from the horizontal members of the bridge and boardwalk down to the ground surface which will allow water to pass through unobstructed. Further, there will not be any cross ties or horizontal obstructions on the lower portions of the boardwalk or bridge pilings. Further, due to the spacing of the pilings, the boardwalk and bridge will not trap sufficient sediment such as leaves to impede the conveyance of the flow channel. Therefore, conveyance through the flow channel will not be affected by the structures. Because the boardwalk and bridge are not over Hogtown or Possum Creeks, they will not cause any obstruction to the conveyance of the creeks. Aquatic and wetland dependent listed species The project will not adversely affect any aquatic or wetland dependent listed species. These species are defined by District rule as aquatic or wetland dependent species listed in Chapter 39-27, Florida Administrative Code, or 50 Code of Federal Regulations, Part 17. No such species are known to exist in the project area, and none are expected to exist in the location and habitat type of the project area. Therefore, contrary to Petitioners' assertions, there are no listed salamander, frog, turtle, or lizard species known to occur within the Hogtown Creek basin. Although it is possible that the box turtle may be found in the project area, it is not an aquatic or wetland dependent listed species. One baby American alligator (between two and three feet in length) was observed in the borrow pit area of the project on September 11, 1997. Except for this sighting, no other listed animal species have been observed in the project area. As to the alligator, the only area in which it could nest would be in the existing excavated borrow pit, and none of the proposed construction will take place in that area. More than likely, the alligator had walked into the area from Clear Lake, Kanapaha Prairie, or Lake Alice. The proposed structures will not affect the movement of the alligator nor its feeding habits. Drainage of wetlands Because the boardwalk and bridge are elevated structures over waters and wetlands, and the City has not proposed to construct ditches or other drainage systems, the proposed system will not cause drainage of the wetlands. Coral/macro-marine algae/grassbeds The proposed system is not located in, on, or over coral communities, macro/marine algae, or a submerged grassbed community. D. Were the Petitions Filed for an Improper Purpose? Prior to the filing of their petitions, Petitioners did not consult with experts, and they prepared no scientific investigations. Their experts were not retained until just prior to hearing. Petitioners are citizens who have genuine concerns with the project. They are mainly longtime residents of the area who fear that the Greenway will not be properly maintained by the City; it will increase flooding in the area; it will cause water quality violations; and it will attract thousands of persons who will have unimpeded access to the back yards of nearby residents. Although these concerns were either not substantiated at hearing or are irrelevant to District permitting criteria, they were nonetheless filed in good faith and not for an improper purpose.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order approving the applications of the City of Gainesville and issuing the requested permits. DONE AND ENTERED this 19th day of December, 1997, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 19th day of December, 1997. COPIES FURNISHED: Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Samuel A. Mutch, Esquire 2790 Northwest 43rd Street Suite 100, Meridien Centre Gainesville, Florida 32606 Jennifer B. Springfield, Esquire Mary Jane Angelo, Esquire Post Office Box 1429 Palatka, Florida 32178-1429 Richard R. Whiddon, Jr., Esquire Post Office Box 1110 Gainesville, Florida 32602-1110