Findings Of Fact The Petitioner is the Department of Professional Regulation. The Respondent is Phillip Whitaker, Jr., holder of certified pool contractor license number CP-C008325 at all times pertinent to these proceedings. He is the qualifying agent for the business known as Sunshine State Pools pursuant to requirements of Chapter 489, Florida Statutes. He is responsible for actions of that business relating to construction of the swimming pool which is the subject of this proceeding. His address of record is Miami, Florida. The customer, Ken Gibson, signed a contract with Sunshine State Pools on September 15, 1986. The contract called for construction of a residential swimming pool at 15840 S.W. 155th Avenue, Miami, Florida. The total contract price was $12,700. Testimony adduced at hearing establishes that Sunshine State Pools completed the layout of the customer's swimming pool and the excavation of soil from the proposed pool site by October 1, 1986. These tasks were accomplished under the Respondent's supervision. Metropolitan Dade County issued a building permit for construction of the swimming pool in response to a permit application bearing the signature of Phillip E. Whitaker. The permit and application are both dated October 10, 1986. At hearing, the Respondent acknowledged that initiation of construction prior to pulling the permit and termed this action an "oversight." Based on the candor, demeanor and experience of the Respondent, his explanation of the failure to timely obtain the construction permit is not credited. Initiation of construction for a swimming pool prior to obtaining permits constitutes a violation of part 301.1(n), of the South Florida Building Code and, by stipulation of the parties at hearing, the building code of Metropolitan Dade County. The Respondent was responsible for supervision of the actual pool shell construction. After completion and removal of the wood forms used in the process, steel rods or "rebar pins" required as support during the construction process were not removed. These rods extended some distance above the ground and posed a substantial hazard to Respondent's children while playing. Finally, the steel rods were removed by the customer a week after he requested the Respondent to remove them. Respondent admitted some of these reinforcements could have been left by his subordinates. Respondent admits responsibility for the "back fill" process completed on October 25, 1986. This was originally a responsibility of the customer under the contract as the party responsible for deck construction. The "back fill" process consists of compacting loose soil between the outside of the pool walls and surrounding earth by use of special tamping or pounding equipment. Under terms of the contract, the customer was responsible for construction of a sizeable two part deck surrounding at least sixty percent of the pool's circumference. There now exists a substantial height difference between the coping surrounding the perimeter of the pool and the deck or patio surface. The coping is elevated above the top of the patio approximately two to four inches. As adduced from testimony of Ben Sirkus (stipulated by both parties as an expert in swimming pools and swimming pool construction), coping along the top of the pool walls consists of flagstone rock in conformity with the contract terms. Some of the rocks are cracked. The rocky edge of the coping extends over the pool wall and has a dangerously sharp edge. The sharp edge of the coping overhang could have been avoided by cutting the flagstone coping smooth prior to installation, the acceptable practice among pool contractors. The bottom step to one set of the pool steps has a hazardous 19 inch riser as opposed to the 12 inch distance required by the building code. No hand rail is present. Hollow space under some of the coping stones are the result of either improper installation, dirty cement or sinking of the deck as a result of improper "back filling" upon completion of the pool shell. On one occasion, Respondent admitted responsibility for deficiencies in the pool coping to an employee named Rick Miro. The Respondent further stated to this employee that he intended to do nothing about the problem. Respondent was present during some, but not all, of the coping installation. The "skimmer," the apparatus by which debris is cleared from the pool water, is inoperable as a result of faulty construction of the pool. The failure of the Respondent, who admits to successful completion of approximately 2500 pools with only three complaints, to properly supervise job site activities was the major cause of the pool deficiencies identified at hearing.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be placed on probation for a period of two years upon such terms and conditions as may be determined by the Construction Industry Licensing Board and assessed an administrative penalty in the amount of $1500. DONE AND RECOMMENDED this 29th day of February, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5053 The following constitutes my specific ruling on proposed findings of fact submitted by the parties. Petitioner's Proposed Findings Included in finding 2. Included in finding 3. Included in finding 4. Included in findings 5, 6 and 7. Included in findings 5 and 6. Included in finding 8. Included in finding 10 with exception of hearsay statement. Included in finding 11.1 Included in finding 12. Included in finding 11. Included in finding 11. Included in finding 11. Included in finding 11. Rejected as unnecessary. Rejected as unnecessary. Included in finding 11. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark D. Press, Esquire 2250 Southwest Third Avenue 5th Floor Miami, Florida 33129 William O'Neil General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 =================================================================
Findings Of Fact At all times material hereto Respondent, George W. Boukater, was a certified general contractor, license number CG C012598, and a registered pool contractor, license number RP 0032042. Respondent was the qualifier for Swimming Pools by M.J. Donohue, Inc. (Donohue), under license number RP 0032042, from February 1979 until June 30, 1985. On July 29, 1984 Donohue contracted to construct a swimming pool at the residence of Ms. Loretta Hunley in Fort Lauderdale, Florida, for the sum of $6,400.00. Respondent, on behalf of Donohue, applied for and received the building and plumbing permits for the pool. Apart from securing the permits, Respondent had no contact with the job and never inspected its progress. By August 30, 1984, Donohue had substantially completed the pool. All that remained to be done was to marcite the pool, hook up the pool light and plumbing, and install the pumps. However, before these items could be completed it was necessary that the area surrounding the pool be backfilled, the patio poured, and the electric installed. Under the July 29, 1984 contract Ms. Hunley did not contract with Donohue for any patio, electric or fence work. She expressly retained responsibility for that work in an effort to save money on the pool construction. The area surrounding the pool was not backfilled and the patio slab approved by the Broward County Building and Zoning Department (County) until September 14, 1984. As of September 5, 1985, the fence work was still in violation of the County code. The electric work received the County's final approval on January 8, 1986. In October 1984 demands were exchanged between Ms. Hunley and Donohue. Ms. Hunley demanded that the pool be completed. Donohue demanded adequate electrical service so the pool could be pumped and cleaned for marciting, and dates when someone would be available at the premises. In November 1984 Donohue got its pumps in operation, however Ms. Hunley disconnected them in the evenings. Consequently, the pool could not be drained and cleaned to marcite it. In November 1984 Ms. Hunley ejected Donohue from the job site. Subsequently, Ms. Hunley and Donohue formally settled their dispute.
The Issue This case concerns the issue of whether the Respondent's license as a certified general contractor should be suspended, revoked, or otherwise disciplined for multiple violations of Chapter 489 of the Florida Statutes. Specifically, the Respondent is charged with having been found guilty of a crime which relates directly to the practice of contracting in violation of 489.129(1)(b)(1979); willfully or deliberately disregarding and violating the applicable building code in violation of Florida Statute 489.129(1)(d)(1979); aiding and abetting an unlicensed person in his evasion of the Contracting Practice Act in violation of 489.129 (1)(e)(1979); knowingly combining or conspiring with an unlicensed person by allowing Respondent's license to be used by said unlicensed person with the intent to evade the provisions of the Contracting Practice Act in violation of Florida Statute 489.129 (1)(f)(1979); and, violating Florida Statute 489.129(1)(j)(1979) by failing to renew his license every two years and by failing to supervise a construction project. At the formal hearing, the Petitioner called as witnesses the Respondent, Frederick G. Gervia, Leroy S. Duncan, John Knezevich, and Evodio Llevado. Respondent testified on his own behalf and also called as a witness Mr. L. Perry Curtis. Petitioner offered and had admitted without objection eight exhibits. The Respondent offered no exhibits into evidence.
Findings Of Fact The Respondent is a certified general contractor holding License No. CG C003114. Respondent is also a registered general contractor having been issued License No. RG 0009802. Respondent's license CGC003114 was delinquent as of December 7, 1981, and had not been renewed for the 1981-83 licensing period. On October 11, 1981, Fiberglass Pools of South Florida, Inc. entered into a contract with Mr. Leroy Duncan to construct a fiberglass pool at Mr. Duncan's residence located at 1385 N.W. 192nd Terrace, Miami, Florida. On November 10, 1981, Respondent applied for a building permit (see Petitioner's Exhibit 2) for the pool construction at Mr. Duncan's home. The Respondent signed the application in the block designated "Signature of Qualifier or Owner-Builder". The application named Gervia Construction Company, address 2810 S.W. 78th Court as the building contractor. Gervia Construction Company was neither the general contractor nor a subcontractor in connection with the construction of the Duncan pool. At the time that he applied for the building permit, Respondent was qualifying agent for Gervia Construction Company, 2810 S.W. 78th Court, Miami, Florida 33155. The Respondent has made no request to qualify under either of his licenses as the qualifying agent for Fiberglass Pools of South Florida, Inc. Neither Fiberglass Pools of South Florida, Inc. or its principals were licensed. Prior to and during construction, Mr. Leroy Duncan had no dealings at all with the Respondent or Gervia Construction Company. Mr. Duncan's dealings were primarily with Douglas Lake of Fiberglass Pools of South Florida, Inc. Mr. Duncan observed a substantial portion of the construction, but was not present during the form work for the deck. At no time did Mr. Duncan observe the Respondent working on the construction of the pool at his home. The only work performed by Mr. Gervia on the Duncan pool contract was to check the plumbing prior to the county inspection. The pool was actually installed by two principals of Fiberglass Pools of South Florida, Inc. and two helpers. These persons were neither supervised nor controlled by the Respondent during construction. During the time period October 11, 1980, through initial construction of the Duncan pool, the Respondent was employed by Fiberglass Pools of South Florida, Inc. at a salary of $350 per week. One of his duties was to pull permits. Although the Respondent was also hired to supervise all field construction, at the time the Duncan pool was contracted for and constructed, his supervisory status had been eliminated. The Respondent performed no supervisory duties in connection with the Duncan pool construction. All payments from Mr. Duncan, including two checks totaling $950 and a cash payment of $6,230 were made to Fiberglass Pools of South Florida, Inc. No payments were made to the Respondent or Gervia Construction Company. Mr. Gervia did not hire or fire any of the persons who worked on the Duncan pool and kept no records relating to payments received or monies spent on the job at the Duncan residence. Subsequent to the pool being completed, substantial problems and flaws in the Duncan pool developed. The following problems were present in the pool: (See Petitioner's Exhibit 5.) Seven patches on South wall, below water line, are rough, discolored and flaking. The largest two are approximately 12" in diameter and 12" x 4". There is a very small depression in the shallow end seat. The pool flange at the ladder is full of depres- sions, making the edge very rough. Flange cracks at three corners are excessive and need repair. The Southwest corner has a vertical crack down the wall about 1'. See exhibits II, III, IV, and V. The pool wall thickness at corners was 3/8" but north, south and west wall were 7/32" to 1/4" thick. Several dark circles about 2" in diameter are located around perimeter flange and show where holes were drilled and patched poorly. . . Four hydrostatic valves seem high to effectively counteract buoyancy, but approved plan approves 1' above floor at deep end plus one valve in main drain [could not check with pool full]. See notes 9, 10 & 11 - William Meyers plan. 13' x 30' x 72" pool actually measures 12'-11" x 29'-8" x 71 1/8" deep. Vertical floor variations in shallow end are about 1 3/4". Seems depressions occur between ribs. A small bow occurs at Northwest corner near surface of water. Area covers about 18" square. Some concrete voids occur beneath pool lip. Pursuant to an agreement with Mr. Duncan, the Respondent and Fiberglass Pools of South Florida, Inc. have repaired those items listed in paragraph 9 in an excellent manner and to the full satisfaction of the owner, Leroy Duncan. On November 17, 1982, the Respondent was convicted in the County Court of Dade County, Florida, of unlawfully aiding and abetting an unlicensed contractor in violation of Section 10-22(h) of the Metropolitan Dade County Code. Adjudication of guilt was withheld and Respondent was required to pay a $500 fine. The Respondent has been a licensed certified general contractor in the State of Florida since November, 1971, and has had no other charges or actions against his license. There have also been no other complaints filed with the Petitioner regarding the Respondent.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Respondent be found guilty of those specific violations as set forth in the Conclusions of Law above and that his license as a certified general contractor be suspended for a period of six months and that the Respondent be required to pay an administrative fine of $250.00. DONE and ENTERED this 20th day of July, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of July, 1983. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Frederick G. Gervia 2810 Southwest 78th Court Miami, Florida 33155 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202
Findings Of Fact Based on the evidence presented, the following facts were found: At all times pertinent to this case, Respondent held two active contractor's licenses issued by the State of Florida, RP 0033354 and CP 015029. Respondent's current address is 1316 Hoffner Avenue, Orlando, Florida 32809. At all times pertinent to this case, Respondent owned the firm Family Pools and did business as a pool contractor under that name. At no time did Respondent ever qualify his firm, under whose name he did business, with the Florida Construction Industry Licensing Board (CILB). On some date not specified, in June, 1980, Alphonse J. and Pauline L. Rodier contracted with Family Pools to build a pool at their residence at 601 Michigan Avenue, Englewood, Sarasota County, Florida for a price of 6,700. The contract was signed by Respondent for Family Pools. The pool price was to include a screened enclosure and deck, and the entire package was to be completed by July 4, 1980. The pool was paid for by two checks from Coast Federal Sayings and Loan Association in Sarasota from the proceeds of a home improvement loan and by a final check in the amount of $900 from the Rodiers, direct, on October 13, 1980. Respondent subcontracted the pool enclosure to Climatrol Screen Company of Enqlewood, Florida, for $2,065 but failed to pay this subcontractor. As a result, on November 26, 1980, Climatrol filed a lien against Rodier's property which was released only when the Rodiers paid an additional $790 which had not been satisfied by the Respondent. Respondent had satisfied part of the debt to Climatrol by relinquishing title to a truck he owned. On July 3, 1980, Family Pools contracted with Elmer J. and Carla T. Taylor, of Bunnell, Florida, to build an above-ground pool on their property for $4,800.00. The pool was to have a one year warranty against defective parts and a 20-year prorated replacement policy. According to the contract, the pool price included the pump, liner, filter, and walls, along with all other parts. The pool was constructed by employees of Family Pools about three or four weeks after the contract was signed. Not long after the pool was completed and filled, Mr. Taylor noticed that the vinyl liner was protruding out beneath the bottom of the metal retaining wall. His calls to Family Pools were never answered by Respondent with whom he asked to talk and repair work on this problem was not accomplished by the Respondent or Family Pools. Mr. Taylor had to do the work himself and Family Pools would not honor the warranty. Respondent offers the completion certificate executed by the Taylors on August 21, 1980,as evidence the pool was installed properly and the Taylors were satisfied. Mr. Taylor indicates he signed that certificate in blank under pressure from Respondent's agent, who cajoled him into doing it on the basis that if he did not, Family Pools could not be paid by the finance company under the installment sales contract. Also, during the period of the one year warranty, the pool pump burned out. Mr. Taylor had to replace that and pay for it himself, as the warranty was not honored. Respondent contends only a 90-day warranty on the pump, but that appears nowhere in the contract, which, in its description of the pool covered by the one year warranty, includes the pump. On August 29, 1980, Family Pools contracted with Janice Conover to build a swimming pool at her home in Venice, Florida for $4,780. The pool was to be completed approximately 30 days after excavation at the site. Between August 29, 1980, and December, 1980, Ms. Conover paid Family Pools a total of $4,741 by checks which were endorsed by "P. Vescera d/b/a Family Pools" or "Pasquale M. Vescera." On October 2, 1980, Respondent pulled a permit No. 7330- N from the Sarasota County Building Department, in his own name, to construct Ms. Conover's pool. In February, 1981, when the pool was only about fifty percent complete, Respondent ceased work on Ms. Conover's pool without giving her any notice or reason therefor. When Respondent stopped work, he had only dug the hole for the pool. The liner had been delivered but was not installed. The braces were there but not affixed, notwithstanding Ms. Conover had paid almost in full for the pool. As a result, she contracted with Richard Thompson, Respondent's former employee, to finish the work Respondent had started because at this point she could not find the Respondent. Thompson installed the brackets, the liner, and the deck. She had to pay extra for the pump, the chemicals, and the sweep--all of which, except for the sweep, she had paid for when she paid Respondent's price. Respondent never returned to complete Ms. Conover's pool. On July 7, 1980, Family Pools contracted with Robert A. and Florence L. Peipher to build a pool at their property in Port Charlotte, Florida, for a price of $6,900. Between July 7 and November 28, 1980, the Peiphers paid Family Pools, by checks, the sum of $6,905. All checks-were endorsed for deposit, "P. Vescera d/b/a Family Pools." The pool price was to include a screened pool enclosure and in September 1980, Family Pools contracted with Climatrol to build the screened enclosure for Peipher's pool for $1,807. Respondent and Family Pools failed to pay Climatrol for the enclosure and as a result, Climatrol filed a lien against the Peipher's property for $1,807 which was satisfied on March 9, 1981, by the Peiphers who paid Climatrol the amount owed. On March 2, 1981, the Peiphers filed a complaint against Respondent with the Contractor License Division of the Charlotte County Building Department because of Respondent's failure to pay Climatrol and the resultant cost to them. As a result of this complaint and the subsequent investigation into the allegations, the matter was referred to the Charlotte County Building Board which, at its meeting on May 7, 1981, after notice to Respondent, voted to revoke Respondent's permit privileges in Charlotte County until he made restitution to the Peiphers and to notify the State of Respondent's actions requesting state action against his license. Respondent suffered severe financial setbacks just about the time of these incidents. He was hospitalized for a period of five or six weeks and upon his return to his business found that he had been "robbed" of approximately $50,000 worth of fully paid for inventory. When he reported the shortage to the local law enforcement officials, they told him that since there was no evidence of a breaking in, they could do nothing about it. In addition, he could not recover from his insurance company for the same reason. There was no evidence other than Respondent's sworn testimony that there was a shortage or that he reported the loss to either agency. Respondent has been in the pool business in Florida for five years and in New Jersey for 32 years before that. He feels the cause of his problem is the fact that he trusted the people who worked for him who took advantage of him. During the entire period of time he was in business in Florida he took no money from the company for his personal use, living instead on income from a mortgage he owned in New Jersey. He subsequently filed for bankruptcy on March 9, 1981. The $15,000 in current accounts receivable he had on the books at that time was utilized in the bankruptcy proceeding to pay creditors. He got-none of it. He is now working in Orlando, Florida, for a pool rehabilitation company owned by his wife and her father. Respondent alleges that on July 15, 1980, he paid Richard Thompson $1,100 to complete work started on several pools, including that of Ms. Conover. Review of the prior findings of fact, however, shows that the contract with Ms. Conover was not entered into until approximately 45 days after Respondent supposedly made this payment to cover the work left undone on her pool. In light of that development, I find his contention completely without merit or basis in fact. Respondent admits that people were hurt as a result of his actions and he regrets this. However, he claims these few incidents are insignificant when compared with the over 500 satisfied customers he alleges he has served over the years. Finally, Respondent contends that early in 1980, after being advised that he had passed the test to be a certified pool contractor, he wrote to Petitioner and, after advising how he was registered and doing business, asked if he needed to make any changes in license registration. He did in fact do this and received no reply. He thereafter assumed he was acting correctly in that regard and that appears to be a justified assumption.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's license as a contractor be suspended for two years and that he be assessed an administrative fine of $500. RECOMMENDED this 16th day of May, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Pasquale M. Vescera 1316 Hoffner Avenue Orlando, Florida 32809 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying and the entire record compiled, the following relevant facts are found. Bradford Clough, Respondent, is a registered pool contractor who holds license No. RP 0031551, which license is current and active. Respondent was first licensed on December 6, 1977, as qualifier of Aqua-Vac Self Clean Swim Pools. (Petitioner's Exhibit 1.) Arnold Verway has been the Building Director for Charlotte County since May 8, 1978. As Building Director, Mr. Verway is in charge of receiving and investigating complaints filed by homeowners against contractors licensed by the Charlotte County Building Board. In this regard, on October 5, 1978, the Charlotte County Building Board listened to two complaints which had been filed with the Department against Respondent "for not fulfilling his contract and for jobs done in an unworkmanlike manner . These complaints were filed by Mr. and Mrs. Phillip J. Greulich and Mr. and Mrs. George Beveridge, of Port Charlotte. After discussion, the Board sent formal notification to Respondent to attend the Board's next regular meeting in order to allow him an opportunity to present any defense respecting the above referenced complaints. Respondent was notified by certified letter dated October 13, 1978, return receipt requested. (Petitioner's Exhibit 2.) At the Board's meeting on November 2, 1978, complainants George Beveridge and Phillip Greulich restated their complaints which had earlier been made to the Board at its October 5, 1978, meeting. Respondent had not resolved the complaints to the satisfaction of complainants as of the date of this hearing. Respondent did not appear at the Board's November 2, 1978, meeting. The Board suspended Respondent's certificate of competency "until such time as he demonstrated to the Board that he had rehabilitated himself and was thus eligible and capable of working in Charlotte County". (Petitioner's Composite Exhibit 3.) The Petitioner has reviewed the disciplinary action taken by the Charlotte County Building Board. (Testimony of Petitioner's investigator, John Viking.) RESPONDENT'S DEFENSE As stated, Respondent did not appear at this hearing or at the hearing before the Charlotte County Building Board, despite proper notice.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED: That the Respondent's registered pool contractor's license, RP 0031551, be REVOKED RECOMMENDED this 30th day of April, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675
Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material hereto, Respondent was a certified pool contractor, holding license no. CP-C033753, issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board. At all times material hereto, Respondent's certified pool contractor's license qualified Artistic Pools and Spas, Inc. with the Florida Construction Industry Licensing Board. On or about May 19, 1986, Respondent, d/b/a Artistic Pools and Spas, Inc. entered into a contract with Joseph and Joyce Malinoski for the construction of a swimming pool at 31 Sea Harbour Drive, Ormond Beach, Florida for a contract price of $9,737.75. The contract required a down payment of ten per cent (10 percent) of the contract amount ($973.78) which was paid by the Malinoskis on May 19, 1986. The Malinoskis resided in Massachusetts at the time they contracted for the swimming pool with Respondent and had contracted for the construction of a home in Ormond Beach, Florida to begin upon the pool shell being in place. The Malinsokis returned to Massachusetts upon execution of the contract expecting Respondent to commence work on the pool two weeks after he was notified by the builder that the survey was completed and the benchmark in place. On or before June 18, 1986, Respondent contacted the Malinoskis by phone to advise them that the pool was under construction, that Respondent was ready to start pouring concrete, and that he needed the next two (2) installments (20 percent due on day of excavation and 35 percent due on day of concrete shell installation) in the amount of $5,355.76. On or about June 18, 1986, the Malinoskis forwarded a cashier's check in the amount of $5,355.76 made payable to Respondent with the understanding from Respondent that the pool was under construction. On or about June 25, 1986, the Malinoskis were advised by their building contractor that the pool was not under construction. On or about July 5, 1986, the Malinoskis returned to Ormond Beach and found that the pool was not under construction. Although the business phone at Artistic Pools and Spas, Inc. had been disconnected, the Malinoskis ultimately located the Respondent but were unable to resolve the problem until after a complaint had been filed. In early August, 1986, an agreement was reached with the Malinoskis, Respondent and David Larsen whereby Respondent would furnish the labor to build the pool, Larsen would pay the bills and the Malinoskis would pay the balance owed on the contract to Larsen and at end of construction Larsen would give the Malinoskis release of liens. The pool was constructed without the Malinoskis having to pay any additional money on the contract. The money used by Larsen to purchase materials above the amount paid to Larsen by the Malinoskis was repaid to Larsen by Respondent. Respondent supplied all the labor to construct the pool. The testimony of Respondent, which I find credible, was that the funds received by Respondent were frozen due to an Internal Revenue Service levy on the Respondent's business account which resulted in the IRS taking all the funds in the bank account, including the money from the Malinoskis. There was insufficient evidence to show that Respondent diverted the Malinoskis' funds or that the Respondent was unable to fulfill the terms of the contract. On or about November 15, 1985 Respondent, d/b/a Artistic Pools and Spas, Inc. contracted with John and Louise McGowan for the construction of a swimming pool and spa at 1266 Robbin Drive, Port Orange, Florida for an original contract price of $11,500. These were 2 addendums to the original contract bringing the total contract price to $13,005.75. The contract provided for the spa to be 7 feet long by 5 feet wide with a depth ranging from 18 inches to 36 inches. As constructed, the spa was 5 feet long by 5 feet wide with a depth of 44 inches. The spa was also unlevel resulting in water spilling on to the deck rather than into the spillway to the pool. The therapy jets were located too deep in the spa to allow them to function properly. The spa has never been operational. Respondent was aware of the deficiencies in the construction of the spa but failed to correct them. The deck around the pool was not properly finished in that it is uneven and rough in several locations and is pitched toward the pool rather than away from the pool. The deck also has several facial cracks (not structural) which indicate a nonuniform thickness. As contracted, the pool was to have 3 return fittings of which only 2 were installed. The contract called for the installation of a heater by the Respondent. Although the heater was installed, it was improperly placed resulting in the inspector putting a "red tag" on the heater and having the gas company disconnect it. The McGowans have paid all but $575 of the contract price but refuse to pay the balance until corrections are completed. Respondent was aware of the deficiencies in the construction of the pool but failed to correct them. The evidence is clear that Respondent failed to properly supervise the construction of the McGowans' pool and spa, thereby resulting in poor workmanship in the construction of the pool and spa.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED that the Florida Construction Industry Licensing Board (Board) enter a final order finding Respondent guilty of violating Section 489.129(1)(j) and (m), Florida Statutes and for such violation it is Recommended that the Board assess the respondent with an administrative fine of $500.00 and suspend the Respondent's pool contracting license for a period of two (2) years, stay the suspension, and place Respondent on probation for a period of two (2) years, provided the Respondent pays the administrative fine of $500.00 within sixty days of the date of the Final Order. It is further Recommended that the charges of violating Section 489.129(1)(h) and (k), Florida Statutes be DISMISSED. Respectfully submitted and entered this 17th day of September, 1987, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of September, 1987.
Findings Of Fact Petitioner is the Department of Professional Regulation. Respondent is James J. Hastings, the holder, at all times pertinent to these proceedings, of general contractor license number CG C009847. He is also the qualifying agent for Hastings Construction Co., Inc. James and Susan Cesiro, owners of a residence in Palm Bay, Florida, entered into a contract on June 13, 1985, with Mike Boyer, proprietor of a business known as American Fiberglass Pools, to furnish and install a swimming pool. The total contract price was $8500. The owners gave Boyer a $1,500 check at the time the contract was executed. On July 9, 1985, Boyer's employee obtained a second check from the owners for an additional $1,500 allegedly to complete the $3,000 required down payment. Unfortunately, the employee persuaded the owners to make this check payable to the employee personally. The employee subsequently disappeared after cashing the check. This complication resulted in some delay in the initiation of construction activities. On August 12, 1985, the owners were informed by Boyer that a contractor had been retained to install the fiberglass pool. On August 28, 1985, Respondent obtained a building permit from the City of Palm Bay authorizing the pool construction. The permit identified Respondent's company, Hastings Construction Co., Inc., as the contractor. The owners issued a check in the amount of $2,500 on September 6, 1985. Delivery of the check was made to Boyer, but was made payable to Respondent. In view of their past experience with furnishing a check payable to a party other than Boyer or his company, the owners obtained a receipt for the check from Boyer. The owners gave another check in the amount of $500 to Boyer on September 9, 1985. This check was also made payable to Respondent. Again, a receipt was obtained from Boyer by the owners. On September 23, 1985, Respondent personally received another check from the owners in the amount of $2,500. In September, 1985, after receipt of funds from the owners, Respondent and Boyer proceeded with the pool installation. While Boyer was present at the site more than Respondent, the Respondent was present every day at periodic intervals. The owners had the impression that Respondent was new at the installation of this type of pool. Boyer seemed to be more in charge of the construction and Respondent appeared to defer to him on questions asked by the owners during the installation process. This impression was confirmed at hearing by Respondent's admission that this was his first experience with this kind of pool. He had never "lifted pools over houses" and viewed the entire job as a "learning experience." Because of the tutorial nature of the situation, Respondent said he didn't enter into a formal contract with the owners. In May 1986, cracks appeared in the bottom of a portion of the pool. Respondent took the position that the pool should be repaired by Boyer under terms of the owners agreement with that individual. Respondent never prepared or accepted an assignment of the contract made by Boyer with the owners. Respondent is not an officer or employee of Boyer's business. Respondent is not a qualifying agent for Boyer or American Fiberglass Pools and those names do not appear on his license. The owners were never apprised that Respondent was "their" contractor. Respondent's testimony that a letter was sent from him to the owners on August 30, 1985, informing them of this fact is not credited in view of the Respondent's candor and demeanor while testifying on this point, the fact that he had obtained the building permit on August 28, 1985, and the owners denial that such letter was ever received. Respondent's credibility on this point was further undermined at one point in the hearing when he stated he was given this job by Boyer. Mike Boyer is not, and has never been, licensed by the Florida Construction Industry Licensing Board in accordance with Chapter 489, Florida Statutes. Respondent was aware that Boyer was not a licensed contractor. Respondent was previously disciplined by the Florida Construction Industry Licensing Board in Petitioner's case numbers 430077 and 50057, on or about October 29, 1984 and February 4, 1985, respectively. Discipline in the form of a $250 fine was imposed in the former case for Respondent's failure to qualify a company through which he was doing business and for deceptive representations in the practice of contracting. The latter disciplinary action resulted in the imposition of a $250 fine upon Respondent or suspension of his license for 60 days due to aiding and abetting an unlicensed individual and failing to qualify a business with the Board.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered suspending Respondent's licensure to practice contracting for one year and assessing an administrative fine in the amount of $2000. DONE AND RECOMMENDED this 18th day of March, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of March, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5328 The following constitutes my specific rulings on findings of fact submitted by the Petitioner. Included in finding number 2. Included in findings numbered 3 and 15. The last sentence is rejected as noncorroborative hearsay. Included in part in finding number 4. Included in part in finding number 5. Included in finding number 6. Included in findings numbered 7, 8, and 9. Included in finding number 10. Included in finding number 12. Included in finding number 13. Included in finding number 16. The Respondent submitted a document entitled Proposed Findings of Fact. The document consists of five unnumbered paragraphs in the nature of a closing argument as opposed to proposed findings of specific facts. This document of the Respondent has been reviewed by the Hearing Officer and numbers 1-5 applied to the paragraphs therein. Rulings on those paragraphs are as follows: Rejected as unnecessary. Rejected as unnecessary with the exception of the proffered August 30, 1985 letter. In this regard see finding number 14. Rejected as not supported by the evidence. Rejected as a conclusion of law not supported by the evidence. Rejected as unnecessary. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mr. James J. Hastings 836 19th Place Vero Beach, Florida 32962 William O'Neil Department of Professional Regulation General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seeley, Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201
The Issue The issue is whether the Respondent's license as a registered pool contractor should be revoked or otherwise penalized based on the acts alleged in the Administrative Complaint.
Findings Of Fact At all times material hereto, Respondent, William Losciale, was a licensed registered pool contractor in the State of Florida, having been issued license number RP-0032951, by the State of Florida, and was the qualifier of Lynn Pools. On or about October 2, 1987, John J. Kerry entered into a contract with Respondent d/b/a Lynn Pools for the Respondent to construct a pool and screen enclosure on Mr. Kerry's property located at 633 South Little John Street in Inverness, Florida. The total cost of the pool and enclosure was $19,600.00. During construction various problems developed. Among them were delays in completion, the failure to obtain the proper permits, the installation of an inadequate and improper filter, the delayed removal of excavated dirt, the gouging up of the homeowner's yard, and the improper positioning of the septic tank after relocation. At the time the pool deck was being designed, the homeowner told the Respondent that it appeared to the homeowner that the deck was slanted towards the house and would cause flooding problems. The Respondent told the homeowner that the Respondent knew what he was doing and no such problem would develop. During construction of the pool, the homeowner pointed out to the Respondent that it appeared that the pool was being constructed higher than the patio which, if true, would also cause flooding problems. Again, the Respondent denied that the pool was being constructed higher than the patio and that flooding problems would occur. During construction, Respondent removed a rain downspout which, prior to construction, was located between the patio and the screen enclosure. The pool patio was then poured without replacing the downspout underneath the patio. As a result of one or more of the foregoing conditions, the homeowner's house was almost flooded on one occasion. Thereafter, the homeowner had to put a drain hole in the patio in an attempt to prevent future flooding. Since completion of the pool, when it rains, rainwater flows down the patio towards the house. Additionally, rainwater is directed from the roof through the gutter onto the patio towards the house and occasionally water overflows from the pool towards the house. While the house has not been flooded, the pool deck floods during certain rains. During construction, the Respondent removed all of the ground wires off electrical fixtures located in the homeowner's yard without replacing them after being requested to replace them by the homeowner. After the deck was poured, it was covered with kool deck. The kool deck was soft and had indentations in it. The Respondent agreed with the homeowner that the deck was bad and that the homeowner should not accept it. The Respondent the replaced the kool deck with river rock. The deck now has ripples in it. The Respondent tried to charge the homeowner an additional $1,200 for the river rock. The homeowner had the river rock installed for an additional $850.00 by a third party. Prior to entering into the contract for the pool and enclosure with Respondent, the home owner told the Respondent that he wanted the biggest water heater available to heat the pool water instantly. When the water heater was being installed, the homeowner questioned the Respondent whether or not the water heater was big enough to meet the homeowner's requirements. The Respondent said that it was. After installation, the heater did not come close to meeting the home owner's requirements. The homeowner then called the manufacturer of the heater and was told that the installed heater was too small. The Respondent, at the homeowner's request, then changed the heater to one that would supposedly heat the pool water faster. It did not. The homeowner then called the heating company again and was told that the new heater was only one size up from the original heater and still would not meet the homeowner's requirements. That heater remains on the homeowner's property and does not meet the homeowner's requirements. Mr. Kerry paid the Respondent $5,500.00 on December 7, 1987, which made a total of $19,000.00 the homeowner had paid the Respondent. The homeowner has paid more than $600.00 in repairing and/or correcting work that was the obligation of the Respondent. Correction of all these problems has been to the homeowner's financial detriment. In the latter part of December, 1987, the Respondent entered into an oral contract with All Wright Aluminum to have All Wright Aluminum install an L- shaped pool enclosure over the pool at the Kerry residence. The total contract price was $5,185.10. Payment for the construction was due within ten days of completion which occurred on January 6, 1988. All Wright Aluminum received a $1,000.00 payment from the Respondent on or about February 2, 1988. That payment was a check from a customer of the Respondent, made payable to the Respondent's order in partial payment on pool repairs which the Respondent made for that customer. The Respondent endorsed that check and made it payable to All Wright Aluminum. On February 15, 1988, All Wright Aluminum in compliance with the mechanic's lien law, filed a valid claim of lien against Mr. Kerry's property in the amount of $4,185.10 for failure of the Respondent to pay All Wright for the construction of the pool enclosure. On May 10, 1988, the Respondent paid All Wright Aluminum $1,000.00 towards that lien. On September 16, 1988, the Respondent paid All Wright $2,000.00 towards the satisfaction of that lien from his personal account. On September 16, 1988, the Respondent gave All Wright Aluminum a personal promissory note in the amount of $1,135.10 for the balance of the lien amount. On that date All Wright Aluminum satisfied its previously filed claim of lien. Respondent has previously been disciplined by the Florida Construction Industry Licensing Board.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order and therein penalize the Respondent, William Losciale, as follows: Assess a fine of $750 for the violation of Section 489.129(1)(h) Assess a fine of $750 for the violation of Sections 489.129(1)(j) , 489.105(4), and 489.119. Assess a fine of $1500 for the violation of Section 489.129(1)(m) Suspend the license of Respondent for a period of six (6) months. DONE and ENTERED this 19th day of October, 1989, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-3296 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Department of Professional Regulation, Construction Industry Licensing Board 1. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-20 (1-20). COPIES FURNISHED: Jack M. Larkin Attorney at Law 806 Jackson Street Tampa, Florida 33602 William Losciale 6491 Mobile Street Inverness, Florida 32652 Kenneth E. Easley General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202