Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
ADLEE DEVELOPERS, INC. vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 92-002798BID (1992)
Division of Administrative Hearings, Florida Filed:Miami, Florida May 06, 1992 Number: 92-002798BID Latest Update: Jul. 31, 1992

The Issue The issue for consideration in this matter is whether Respondent's intended award of a lease for office space to Intervenor, Anthony Abraham Enterprise, is arbitrary and capricious and whether the proposal of the Petitioner, Adlee Developers, the current lessor, is responsive.

Findings Of Fact The parties agreed that on April 7, 1991, the Department issued an Invitation to Bid entitled, "Invitation To Bid For Existing Facilities State Of Florida Lease Number 590:2286, Dade County" This procurement was for the provision of 30,086 net rentable square feet to be used for office space in Dade County. A 3% variance was permitted. The facility was to house the District's Aging and Adult Services office which has been a tenant in Petitioner's building for several years and remained there during the pendancy of this protest process. According to the published advertisement, a pre-proposal conference was to be held on April 22, 1991, with all bids due by the bid opening to be held at 10:00 AM on May 30, 1991. The pre-bid conference was conducted by Philip A. Davis, then the District's facilities service manager and included not only a written agenda but also a review of the evaluation process by which each responsive bid would be examined. Petitioner asserts that the potential bidders were told, at that conference, that annual rental increases for the ten year lease period could not exceed five per cent (5%) and claims that Abraham's bid exceeded those guidelines. Thorough examination of the documentary evidence presented and the transcript of the proceedings, including a search for the reference thereto in Petitioner's counsel's Proposed Findings of Fact, fails to reveal any support for that assertion as to an increase limitation. The ITB for this procurement, in the section related to the evaluation of bids, indicated that pursuant to the provisions of Sections 5-3 and 5-11 of HRSM 70-1, dealing with the procurement of leased space, the responsive bids would be reviewed by an evaluation committee which would visit each proposed facility and apply the evaluation criteria to it in order to determine the lowest and best bidder. The evaluation criteria award factors listed in the ITB defined a successful bid as that one determined to be the lowest and best. That listing of evaluation criteria outlined among its categories associated fiscal costs, location, and facility. As to the first, the committee was to look at rental rates for both the basic term of the lease and the optional renewal period. The rates were to be evaluated using present value methodology applying the present value discount rate of 8.08% and rates proposed were to be within projected budgeting restraints of the Department. The total weight for the rental rate category was to be no more than 40 points with 35 points being the maximum for the basic term and 5 points for the option. Evaluation of the location was to be based on the effect of environmental factors including the physical characteristics of the building and the area surrounding it on the efficient and economical conduct of the operations planned therefor. This included the proximity of the facility to a preferred area such as a co-location, a courthouse, or main traffic areas. This item carried a maximum weight of 10 points. Also included in location were the frequency and availability of public transportation, (5 points); the proximity of the facility to the clients to be served, (5 points); the aesthetics of not only the building but the surrounding neighborhood, (10 points); and security issues, (10 points). The third major factor for evaluation was the facility itself and here the committee was to examine the susceptibility of the offered space to efficient layout and good utilization, (15 points), and the susceptibility of the building, parking area and property as a whole to possible future expansion, (5 points). In that regard, the Bid Submittal Form attached to the ITB called for the successful bidder whose property did not have appropriate zoning at the time of award to promptly seek zoning appropriate to the use classification of the property so that it might be used for the purposes contemplated by the department within 30 days. In the event that could not be done, the award could be rescinded by the department without liability. The committee could award up to 100 points. The basic philosophy of this procurement was found in paragraph 1 of the Bid Award section of the ITB which provided: The department agrees to enter into a lease agreement based on submission and acceptance of the bid in the best interest of the department and the state. After the bid opening, three of the four bids received, excluding Petitioner's which was initially determined to be non-responsive, were evaluated by the Department's bid evaluation committee according to the above point system which allowed no discretion or deviation from the formula in comparing rental rates between bidders. Once Petitioner's bid was thereafter determined to be responsive, it, too was evaluated by the committee. At this second evaluation session, relating to Adlee's bid only, the committee scored the bid and added its scores to the original score sheets upon which the other three bidders' scores had been placed. Abraham had the lowest rental rates for the basic term of the lease and received the maximum award of 35 points for that category while Adlee received points. Abraham received an additional 2.29 points for the optional period rates while Adlee got 0. In the other categories, "location" and "facility", which comprised 60% of the points, Adlee's facility was routinely rated superior to Abraham's except for the area related to susceptibility for future expansion in which Abraham was rated higher by a small amount. Overall, however, Adlee was awarded 620.41 points and Abraham 571.03 points and as a result, Adlee was rated by the committee to be the lowest and best bidder. RCL, another bidder, was rated second, with Abraham third and DCIC fourth. Thereafter, the committee chairman, Mr. VanWerne, forwarded the new (and complete) evaluation results to the District Administrator on June 14, 1991 by an addendum dated June 27, 1991 which recommended award of the bid to Petitioner, Adlee Developers. No award was made at the time. Several factors not pertinent to the issues here caused that delay. Among the major of these was pending legislation which would have transferred the operation needing this space to another agency. This transfer was never consummated, however. On or before March 20, 1992, the new District Administrator, Mr. Towey, who had been appointed to his office in December, 1991, and who was made aware that this procurement had not been finalized, requested all available material on it so that he could study it and make his decision based on his own review of the submission. As a part of his determination process, he visited and inspected both the Adlee and the Abraham sites. One of the factors he considered was what appeared to be the significant monetary discrepancy between the two pertinent bids. Initial calculations indicated that Abraham's bid was approximately $835,000.00 lower than Adlee's over the ten year basic term of the lease. This amount was subsequently determined to be somewhat lower but the discrepancy is still significant. Nonetheless, because of that difference, Mr. Towey called a meeting with the members of the evaluation committee which had evaluated the bidders and had recommended Adlee. His stated reason for calling that meeting was to allow him to hear their reasons for rating the submissions as they had done and to take that information into consideration when he made his final decision. None of the committee members who testified at the hearing at Petitioner's behest indicated any feelings of pressure or intimidation by Mr. Towey. During his meeting with the committee members, Mr. Towey went over several of the evaluation criteria award factors to determine the committee's rationale. Of major importance was the issue of cost, of the availability of the facility to transportation to and from the building, employee security and the ability to control access to the facility, and the availability of on-site parking without cost to both employees and clients. It appears the Adlee facility is a multistory building with some parking available on site and would be easier to control. In addition, it is closer to public transportation access points. There is, however, some indication that on-site parking for clients would not be free and the closest free parking is some distance away. According to Adlee's representative, this matter would not be a problem, however, as adequate, free on site parking, which apparently was not initially identified as a problem, could be provided in any new lease. The Abraham facility is a one story building surrounded by on-site parking. In that regard, however, at hearing, Petitioner raised the claim that the Abraham site did not, in actuality, provide adequate parking because the zoning requirements of the City of South Miami, the municipality in which the facility is located, did not permit the required number of parking spaces to accommodate the prospective need. Petitioner sought and received permission to depose the Building and Zoning Director for the city, Sonia Lama, who ultimately indicated that the Abraham site was grandfathered in under the old zoning rule and, thereby, had adequate parking available. In any case, had this not been true, under the terms of the ITB, any zoning deficiencies could have been corrected after award, or the award rescinded without penalty to the Department. After the meeting with the committee, Mr. Towey indicated he would probably go against the committee's recommendation. One of his reasons for doing so, as he indicated to them, was the appearance certain amenities in the facility would give. In the period between the time the committee met and Mr. Towey was ready to decide, there were several newspaper articles published in the Miami area which were negative in their approach to Department leasing policies and this publicity had an effect on him. In his response to a reporter's question, in fact, Mr. Towey indicated he would not permit the lease of any property which contained such amenities while he was District Director. There is some evidence that the wet bar referred to here was a sink and counter used by agency employees to make coffee. However, before making his decision, Mr. Towey also met with Herbert Adler of Adlee. Mr. Towey advised him he was concerned about the fact that the Adlee property provided a wet bar, a private bathroom and some other amenities in that suite of offices occupied by the Department. Mr. Towey was adamant in his public and private pronouncements on the subject that there would be no such amenities in HRS offices in his District while he was in charge. At the meeting in issue, Mr. Adler made it very clear he was willing to remove all the offending amenities to bring the space into conformity with Mr. Towey's standards. Mr. Towey obviously took Adler at his word as he did not consider this matter to be an issue when he evaluated the bids. Based on his independent evaluation of the proposals, and considering all the pertinent factors, Mr. Towey decided not to concur with the committee's recommendation and instead recommended to the Department's Office of General Services that the bid be awarded to Abraham. Because his recommendation differed from that of the evaluation committee, under the provisions of Section 5-13, HRS Manual 70-1, he was required to forward additional justification for his position. In his forwarding memorandum dated March 20, 1992 to Mr. King Davis of the Department's Office of General Services, Mr. Towey listed as his reasons for disagreement with the committee's recommendation, (1) the lower term cost of Abraham's bid, (2) his opinion that the one story floor plan of Abraham was more convenient and accessible to clients, and (3) the provision for ample free parking at the Abraham site as opposed to the limited parking at the Adlee building. Petitioner claims that Mr. Towey's justification for disagreement was improper because, (a) the rental difference he cited was not based on the ITB formula and did not consider the difference in square footage offered; (b) the rental rate comparison compared a proposed lease with an existing lease, not with a proposal; and (c) the reference to on-site parking referred to the situation under the existing lease with Adlee and not to what could occur under a new lease. The major factor in Mr. Towey's decision was the price differential between the two offerings. While the difference may not have been as great as presented initially by the department staff, even taken in its most conservative light of about half that amount, and considering the appropriate figures, the difference was still considerable and significant. In the continuing period of budgetary austerity under which state operations have been and must continue to be conducted, the financial consideration loomed large in his thinking. As for the parking situation, no change for the better was provided for in Adlee's proposal and even if it were, it was but one of several factors. When Mr. Towey's March 20, 1992 memorandum in justification of his disagreement was evaluated at the Office of General services, it was determined that his decision was rational and objectively justified. Thereafter, by letter dated April 2, 1992, the Office of General Services authorized District 11 to award the lease to Abraham and this decision was transmitted to all responsive bidders by letter dated April 7, 1992. It was this action which prompted Petitioner's protest.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that a Final Order be entered dismissing the protest by Adlee Developers, Inc., of the award of procurement No. 590:2286 to Anthony Abraham Enterprises. RECOMMENDED this 10th day of July, 1992, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of July, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-2798 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: - 4. Accepted and incorporated herein. Accepted. Accepted that the pre-bid conference was held but reject the finding that a 5% limit was mentioned. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. & 11. Accepted and incorporated herein. 12. - 14. Accepted and incorporated herein. 15. - 19. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted except for the next to last sentence which is rejected. Accepted. Accepted and incorporated herein. Accepted but not probative of any material issue. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. & 30. Rejected. - 33. Accepted and incorporated herein. FOR THE RESPONDENT AND INTERVENOR: & 2. Accepted and incorporated herein. 3. - 5. Accepted. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 16. Accepted and incorporated herein. 17. - 19. Accepted and incorporated herein. 20. & 21. Accepted and incorporated herein. Accepted and incorporated herein. - 25. Accepted. COPIES FURNISHED: Melinda S. Gentile, Esquire Ruden, Barnett, McClosky, Smith, Schuster & Russell 200 East Broward Blvd. P.O. Box 1900 Fort Lauderdale, Florida 33302 Paul J. Martin, Esquire Department of Legal Affairs The Capitol - Suite 1501 Tallahassee, Florida 32399-1050 Peter W. Homer, Esquire Greer, Homer & Bonner, P.A. 3400 International Place 100 S.E. 2nd Street Miami, Florida 33131 John Slye General Counsel Department of Health and Rehabilitative Services 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 Sam Power Agency Clerk DHRS 1323 Winewood Blvd. Tallahassee, Florida 32399-0700

Florida Laws (3) 120.53120.57571.03
# 1
ALLIED MOWING SERVICE vs DEPARTMENT OF TRANSPORTATION, 90-003243BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 25, 1990 Number: 90-003243BID Latest Update: Aug. 03, 1990

Findings Of Fact The invitation to bid on state Project Nos. 86906-9093, 86906-9094, and 86906-9085 (the "ITB") contained, among other things, 43 pages of Technical Specifications Roadside and Slope Mowing ("Technical Specifications"). Paragraph VI.A. of the Technical Specifications contained the following provision: When mowing areas within ten feet of the travel way, the equipment shall be operated in the direction of the traffic. This provision does not apply when the specific worksite (sic) is protected in accordance with the Florida Department of Transportation Roadway and Traffic Design standards [attached]. 3/ Respondent amended the ITB by letter dated May 1, 1990, which contained Addendum Nos. 1 and 2. Addendum No. 1 amended the invitations to bid on State Project Nos. 86906-9093 and 86906-9094 by deleting the "last" word "attached" from Paragraph VI.A. Addendum No. 2 amended the invitations to bid on State Project No. 86906-9085 by deleting the "last" word "attached" from Paragraph VI.A. No other changes were made in the amendments to the invitations to bid on the three state projects at issue in this proceeding ("Amended ITB"). The ITB contained a requirement that all bidders attend a Mandatory Pre-Bid Conference to allow bidders an opportunity to speak to Respondent's maintenance engineers about any concerns over the ITB. Petitioner attended the Mandatory Pre-Bid Conference conducted on April 26, 1990, for the ITB. 4/ The ITB and the Amended ITB contained a requirement that each bidder visually inspect the roadside areas to be mowed. Petitioner knew of the requirement for visual inspection and complied with that requirement. Petitioner had previous experience in mowing roadside areas for Respondent. The Florida Department of Transportation Roadway and Traffic Design standards ("Standards Index") was not attached to either the ITB or the Amended ITB. Paragraph 9 of the General District Contract Specifications provided that the successful bidder "...shall adhere to the requirements of Part VI of the Manual on Uniform Traffic Control Devices ("MUTCD")." Neither the ITB nor the Amended ITB included a copy of either the MUTCD or Part VI of the MUTCD. Petitioner received the ITB on April 12, 1990, and requested a copy of the Standards Index at that time from Teresa Martin, Assistant District Contracts Administrator, District Four, Florida Department of Transportation. Ms. Martin advised Petitioner on April 12, 1990, that no copies of the Standards Index were available locally and further advised Petitioner of the location and means for obtaining a copy of the Standards Index in Tallahassee, Florida. Petitioner made no attempt to obtain a copy of the Standards Index at that time. Petitioner again requested a copy of the Standards Index from Ms. Martin on May 2, 1990, and was advised again at that time of the location and means of obtaining a copy of the Standards Index. The bid package did not fail to contain any "plan" referred to in: Section 4, Scope of Work, paragraphs 4.1 and 4.2; Section 5, Control of the Work, paragraph 5.2; Section 12, Work Assignment and Planning for Routine Contract Maintenance, paragraphs 2 and 4-6, page 5, paragraph 1.2, page 20, Section II D., III A., page 24, Section IX, and page 64, Proposal. Petitioner presented no evidence or authority describing the applicable standard for defining a "plan". The ITB and Amended ITB contain a description of which roadsides are to be mowed, the manner in which the work should be performed, each pay item and the quantity estimated for each item, the estimated number of mowing cycles, and numerous other detailed provisions regarding mowing operations, operator safety, equipment maintenance, and conversion charts. While the ITB and Amended ITB are standard forms of contract issued by the Department of General Services, they are tailored to meet the specific needs of a mowing contract by means of the Technical Specifications. In the absence of evidence or authority to the contrary from Petitioner, the ITB and Amended ITB are found to include all relevant plans. Respondent failed to include either the "form of Contract" or "Bond" referred to in pages 1, 10, and 64 of the ITB and Amended ITB. Page 64 contained a form of bid proposal which required each bidder to sign a statement that the bidder had "...carefully and to [its] satisfaction examined the...form of Contract and Bond.. The ITB and Amended ITB did not fail to state standards for what is "customary to the mowing operation". The ITB and Amended ITB were prepared on a standard form of contract issued by the Department of General Services and used by Respondent to solicit bids for various types of commodities and services. The ITB and Amended ITB were used to solicit mowing services for specified roadside areas In Broward County, Florida. They were composed of general specifications, bidding documents, technical specifications, and mowing guidelines. The term "custom" by definition refers to the prevailing practice that has been established over time within a geographical area rather than the written terms of a contract. 5/ The definition of grass or vegetated roadside areas to be mowed, which is set forth in Section I, Description A, page 19, excludes certain plants and vines which are present in the areas to be mowed. 6/ Such a definition does not take into account the different toughness and clumping characteristics of each type of grass or weed within the mowing area. Differences in toughness and clumping characteristics of grasses and weeds can adversely alter the uniformity of cutting height. The Technical specifications neither define the term "routine mowing", as used in Sections II.D. and III.A., nor prescribe how high grass or weeds should be allowed to grow before Respondent issues a work order or a notice to proceed. Grass, weeds, plants, and vines in a roadside area that are left for several months without a work order being issued can grow to a height of 10 feet, develop very hard stems, or lay down during mowing and later rebound. The Technical Specifications do not contain a definition of minimum mower size. The frequency with which Respondent issues work orders or notices to proceed depends on growth conditions in the particular roadside area including rain and drought. The topography of the roadside areas to be mowed includes holes, boulders, and un-repaired washouts. The topographical characteristics of the roadside areas and the toughness and clumping characteristics of the grasses and weeds in the roadside areas adversely affect the ability of a successful bidder to comply with cutting height and green streak requirements in the Technical Specifications. 7/ The ITB and Amended ITB were neither arbitrary, capricious, nor beyond Respondent's discretion. The terms of the ITB and Amended ITB were not inherently uncertain or unreasonable. No evidence was presented that Respondent abused its discretion in soliciting the bids, that the accepted bid, if any, was not a reasonable price for the work solicited, that the law was not complied with, or that the contract to be awarded was not fair and capable of just and lawful enforcement. The ITB and Amended ITB were sufficiently precise to protect the public against collusive contracts, prevent favoritism toward contractors, and secure fair competition upon equal terms to all bidders. The ITB and Amended ITB afforded a basis for an exact comparison of bids among all bidders and did not reserve to an officer of the public body the power to make exceptions, releases, and modifications that would afford opportunities for favoritism after the contract is let.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner's written formal protest be DENIED. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 3rd day of August, 1990. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of August, 1990.

Florida Laws (4) 120.53120.57316.0745337.11
# 2
CHEESBRO ROOFING, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-001348BID (1985)
Division of Administrative Hearings, Florida Number: 85-001348BID Latest Update: Jul. 01, 1985

Findings Of Fact On an undisclosed date, respondent, Department of Transportation (DOT), gave notice to qualified contractors that it would receive sealed bids on State Project Job No. 26000-3624. The job called for removing and replacing the roof on the DOT warehouse at Gainesville, Florida. Such bids were to be filed with the agency no later than January 23, 1985. As is pertinent here, the specifications called for the following type of flexible sheet roofing system: minimum Elastomeric sheet material, manufacturer's standard thickness but not less than 42 mils, 400 psi minimum tensil strength, 250 percent elongation (ASTM D 412), ultraviolet and ozone resistent, low temperature brittleness of -40 F (-40 C)(ASTM D 746), integral color white or aluminum. W. R. Grace and Company (Grace) is one of several companies who manufacture single-ply roof membranes that are generally compatible with DOT specifications. One of its factory representatives, John Cunningham, reviews all bid notices issued by DOT to determine what materials are required for a given project. The representative then calls DOT approved contractors in his service area who use Grace products and advises them of the requirements for the job. In this particular case, Cunningham read the specification for elastomeric sheet material and was initially confused as to whether DOT wanted a factory finish on the membrane or to have it coated in the field. This confusion arose since the specification called for an "integral color" on the material and a "manufacturer's standard thickness, but not less than 42 mils." Grace manufacturers two single-ply roof membranes, one having a 40 mil thickness with a factory applied coating (GRM-500), and one having a 50 mil thickness with a field applied coating (GRM-120). When DOT prepared the bid proposal, it was under the impression that the GRM-500 system would meet the specifications. However, if a factory applied coating on the membrane was desired, the GRM-500 system would not meet the specification as to thickness. Because of this, Cunningham contacted a DOT representative who advised that DOT wanted a factory applied coating, and that all bidders should base their bid using the GRM-500 product even though this appeared to be inconsistent with the specifications. The representative also told Cunningham it was too late to issue an addendum to clarify the matter. Based upon the above representation Cunningham telephoned each qualified contractor in his sales area who used Grace products, including petitioner Cheesbro Roofing, Inc. (Cheesbro), a roofing company located in Ormond Beach, Florida. He told them that DOT apparently wanted a factory applied coating, even though this was inconsistent with the specification as to thickness and that the GRM-500 system should be used. He also advised them that at least one bidder interpreted the specification differently, and was preparing its bid using the GRM-120 product so that the thickness specification as written could be met. Cheesbro had never bid a DOT project and was confused as to the type of product to use in preparing its bid. In an abundance of caution, Cheesbro submitted alternate bids, one with prices based on the GRM-500 system and the other using the GRM-120 system. This resulted in bids of $84,560 and $102,661, respectively. The alternate bid (using the GRM-120 product) was typed on the firm's letterhead and inserted in the bid proposal since the bid form did not contain a place to write an alternate bid. The $84,500 figure was the lowest dollar bid on the project out of twelve bids submitted. At about the same time, a second Grace sales representative, Richard Bray, contacted users of Grace products in his service area including Kent Construction Company, Inc. (Kent) of Chipley, Florida. Bray advised his customers to write their bids using the GRM-500 system. Kent had originally interpreted the specification as requiring the GRM-120 system, but, based upon Bray's representation, it submitted a bid of $86,800 using the GRM-500 system. This was the second lowest dollar bid on the project. By law DOT cannot design specifications with the object of soliciting products made by a specific manufacturer. Even so, there are only a few other manufactured roofing systems which have a factory applied coating and a thickness of at least 42 mils. However, most of the twelve bidders, including the two lowest, submitted bids using Grace products. After the bids were filed and reviewed, DOT noted that Cheesbro had submitted alternative bids. Because this is a ground for rejection, the bid was reviewed initially by a DOT technical awards committee which recommended the bid be rejected as being "irregular". That committee's decision was affirmed by the contract awards committee which reached the same conclusion. Accordingly, Cheesbro's bid, although the lowest, was rejected on February 11, 1985 and Kent's bid accepted on March 6, 1985 as being the lowest and most responsible bidder on the project. That prompted the instant proceeding. DOT bids are governed by the Standard Specifications for Road and Bridge Construction, 1982 Edition. Section 2 - 6 of that document provides as follows: A proposal will be subject to being consid- ered irregular and may be rejected if it shows omissions, alterations of form, addi- tions not called for, conditional or unau- thorized alternate bids, or irregularities of any kind; also if the unit prices are obvi- ously unbalanced, either in excess of or below the reasonable cost analysis values. DOT has relied upon this section as authority for rejecting Cheesbro's bid. Cheesbro did not read this document before submitting its bid. According to DOT, the purpose of the section is to obtain standard bids from all contractors, and to prevent one bidder from having an unfair advantage over others through the use of alternate bids.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that all bids on State Job Project No. 26000-3624 be rejected, and the project be relet for bids. DONE and ORDERED this 1st day of July, 1985, in Tallahassee, Florida. Hearings Hearings DONALD R. ALEXANDER Hearing Officer Division of Administrative The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative this 1st day of July, 1985. COPIES FURNISHED: David H. Burns, Esquire p. O. Box 1694 Tallahassee, Florida 32302 Larry D. Scott, Esquire Haydon Burns Bldg., M.S. 58 Tallahassee, Florida 32301

Florida Laws (2) 120.53120.57
# 3
DINKAR B. KOPPIKAR vs. DEPARTMENT OF INSURANCE AND TREASURER, 89-002152BID (1989)
Division of Administrative Hearings, Florida Number: 89-002152BID Latest Update: Jul. 18, 1989

Findings Of Fact On March 16, 1989, Respondent sent invitations to bid to actuaries who had been listed by the State of Florida, Department of General Services and with whom Respondent had some familiarity. These invitations pertained to two projects. The first project was one in which Respondent sought the services of qualified actuaries for the rendering of expert services in the area of rating requirements and procedures and the review of rate filings for health maintenance organizations and long term care insurance, Bid 119. The second invitation to bid was associated with the attempt to gain services from qualified actuaries pertaining to the review of health insurance filings, Bid 120. Respondent also gave public notice of the invitations to bid in the two projects that have been described. This notice was given in the Florida Administrative Weekly in its publication of March 17, 1989. On March 17, 1989, Petitioner obtained a copy of the bid materials in Bid 119. On March 20, 1989, he obtained a copy of the bid materials associated with Bid 120. In both Bid 119 and Bid 120 there are set out general conditions which are the same for both invitations. Within the general conditions is found paragraph 5 which states: INTERPRETATIONS/DISPUTES: Any questions concerning conditions and specifications shall be directed in writing to this office for receipt no later than ten (10) days prior to the bid opening. Inquiries must reference the date of bid opening and bid number. No interpretation shall be considered binding unless provided in writing by the State of Florida in response to requests in full compliance with this provision. Any actual or prospective bidder who disputes the reasonableness, necessity or competitiveness of the terms and conditions of the Invitation to Bid, bid selection or contract award recommendation shall file such protest in form of a petition in compliance with Rule 13A-1.006, Florida Administrative Code. Failure to file a protest within the time prescribed in Section 120.53(5), Florida Statutes shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. In furtherance of the opportunity to ask questions concerning the conditions and specifications set forth in the two bid instruments Petitioner, by correspondence received by Respondent on March 20, 1989, submitted a separate list of questions for the two projects, Bid 119 and Bid 120. On March 21, 1989, Respondent offered its answers to the Petitioner. Copies of these questions and answers may be found as Petitioner's composite Exhibit No. 5, pertaining to Bid 120 and Petitioner's composite Exhibit No. 6, pertaining to Bid 119, admitted into evidence. No one took advantage of the opportunity set out in paragraph 5 to the general conditions in each invitation to bid, to dispute the reasonableness, necessity or competitiveness of the terms and conditions of the invitations to bid within the prescribed time frame which is set out in Section 120.53(5), Florida Statutes. That time requirement is to make known objections within 72 hours of becoming apprised of the terms and conditions in the invitation to bid. It was only at the point in time at which Petitioner had been found unresponsive in the two bid circumstances and offered his formal written protest on April 11, 1989, that he attempted to advance claims associated with the reasonableness, necessity or competitiveness of the terms and conditions of the invitation to bid. He made further attempts to criticize those terms within the invitation to bid through presentation at hearing and in the course of the proposed recommended orders. All these efforts were untimely. The significance of Petitioner's failure to timely challenge the terms within the invitations to bid, that is the conditions and specifications, means that the facts in dispute are considered on the basis of whether the Petitioner and others who offered their responses to the invitations to bid have complied with those conditions and specifications as written, not as Petitioner would have them be. Bid 119 was responded to by the Petitioner and Touche Ross & Company. Petitioner's response was timely. By committee review of the responses to the invitation to bid performed by the Respondent and approved by the Assistant Director of Administration, Department of Insurance and Treasurer, one Bruce Brown, a decision was reached to reject all bids. Petitioner and Touche Ross were made aware of this rejection. Petitioner made a timely challenge to the rejection of his bid in accordance with Section 120.53(5), Florida Statutes, leading to the present hearing. Touche Ross did not challenge that decision and did not seek to participate in this hearing, although it was noticed of the pendency of these proceedings. Petitioner and Wakely timely responded to the invitation in Bid 120. The review committee with the concurrence of Mr. Brown found Wakely to be responsive and Petitioner to be unresponsive to the terms of the invitation. Petitioner made a timely request to be heard on this decision by the agency leading to the present hearing. Wakely was noticed of the pendency of this hearing as well as the agency's choice to change from a position of accepting the Wakely bid to one of rejecting all bids and has not participated in the process. The reason why the Respondent has chosen to reject the Wakely bid is based upon its belief that to do so would expedite the process of gaining the actuarial services which it seeks under Bid 120 and based upon some concern that if it sought to contract with Wakely, whom it believes to be the only responsive bidder in Bid 120, it would be met with disapproval by the State of Florida, Department of General Services. This resistance by the sister agency is premised upon the opinion that to contract with Wakely would constitute the use of a sole source contract in a setting in which there are numerous choices of actuaries who might be able to perform the work, and General Services who controls sole source purchases would not allow this. Within Bid 119 are various special conditions. Among those is the stated purpose found in paragraph 1.0 and it says: The Division of Insurance Rating (hereinafter "Division") within the State of Florida's Department of Insurance (hereinafter "Department") is seeking one qualified actuary for the rendering of expert services in the area of rating requirements and procedures and review of the rate filings for Health Maintenance Organizations (hereinafter "HMO") and Long Term Care Insurance (hereinafter "LTC"). It is anticipated that the contract will be effective from April 1, 1989 to September 30, 1989, although the precise dates will be dependent upon the date the contract is signed and the schedules of department personnel. By this Invitation to Bid (hereinafter "ITB"), the Division is requesting interested actuaries (hereinafter "respondent") to review the general and specific criteria outlined in this ITB and to present a bid. Other instructions in Bid 119 at paragraph 3.0 state: Emphasis on each bid must be completeness and clarity of content. In order to expedite the evaluation of proposals, it is essential that bidders follow the instructions contained herein. * * * Bidder shall complete the attached Bid Sheet in its entirety. By affixing manual signature on this bid sheet the bidder states that he/she read all bid specifications and conditions and agree to all terms, conditions, provisions, and specifications. Respondent's Credentials and Capabilities Proposals must include substantial evidence of the ability of the respondent to undertake the work required within the parameters and time frames referenced in this ITB. The respondent must be a member of both the American Academy of Actuaries and the Society of Actuaries. Furthermore, the respondent must convincingly demonstrate his or her expertise in both the HMO and LTC areas. Such demonstration must include at least the following: HMO Significant consulting assignment or other work responsibility involving HMO ratemaking in 1988 or 1989. Particulars must be provided, including the specific work product requested, hours spent on the job, the results of the job, and the respondent's precise role. Convincing evidence of familiarity with the Health Maintenance Organization Amendments of 1988 to the Federal Health Maintenance Organization Act. Such evidence might include a completed or ongoing consulting assignment in which knowledge of the new legislation was critical, an article published on the new legislation, or a speech to a professional organization. Public demonstrations of the respondent's expertise in the HMO area, such as speeches, published articles, positions held in HMO professional organizations, or prior full-time employment by an HMO. Assistance in the preparation of HMO rate filings for review by the Department. Assistance in the preparation of rates for federally qualified HMOs. LTC Significant consulting assignments or other work responsibility involving LTC ratemaking in 1988 or 1989. Particulars must be provided, including the specific work product requested, hours spent on the job, the results of the job, and the respondent's precise role. Public demonstrations of the respondent's expertise, such as speeches, published articles, or positions held in professional organizations relative to LTC (i.e., committee assignments) OTHER The respondent should also include a description of prior work assignments involving consulting or other services to state insurance departments. This prior work need not be restricted to HMO or LTC. Note: Evidence of the respondent's expertise must be verifiable. Referenced consulting assignments must include the name, address, and telephone number of an employee of the client who can verify the nature of the assignment. Copies of published articles must be provided, along with the name and date of the periodical in which it was published. Also, copies of speeches must be provided, along with the name of the organization to which the speech was given, a contract person, and the date of the speech. * * * (f) Respondent's Bid In preparing a bid, the respondent should make sure that he or she has submitted at least the following information: A demonstration that all requirements in the "Respondent's Credentials and Capabilities" section are met; An explicit statement as to the proposed hourly rate; A clear statement that the respondent is able to perform the required tasks in the prescribed time frames, as described in "Specific Work Product Required". Such information must be provided together with the bid sheet provided in Section 11. A suggested format is shown in Section 10. In both bid invitations, at paragraph 4.0 of the special conditions, bidders are reminded that bids which do not meet the mandatory technical requirements set out in 3.0 and its sub-parts will not be considered for selection and that the bids that are deemed responsive will be evaluated on the basis of cost and the award made to the lowest responsive bidder at an hourly rate of charges. Both invitations at Paragraph 4.1 indicate that the state has reserved its opportunities to reject all bids if that is felt to be in its best interest. Paragraph 5.2 of the invitation is a further reminder to bidders that any bidder desiring to file a protest arising out of the invitation to bid shall do so in a setting in which Section 120.53(5), Florida Statutes controls. Another specification found in both invitations at paragraph 10.0 entitled, "Respondent's (referring to the bid respondents) Credentials and Capabilities." Under that category it is stated that it is recommended that the format found on that page in the bid specifications be used in supplying the information needed to respond to paragraph 3.0 of the bid specifications for both invitations. Under that paragraph 10.0 there is a place for the respondent's name, the name of his employer, membership year in the AAA, membership designation in the 50A: FSA and ASA and year the 50A designation was awarded. In Bid 119, beyond paragraph 10.0 are found paragraphs 10.1, 10.2 and 10.3, these paragraphs recapitulate those items and the various sub-parts to paragraph 3.0 and provide space for answers to be given to those inquires concerning the Petitioner's credentials and capabilities. There is a paragraph 11.0 in both invitations entitled "Bid Sheet." It has lines related to the hourly rate, vendor name, name of actuary to render services, mailing address, city, state and zip code, authorized signature both manual and typed, telephone number, and the date of submission. This particular paragraph reminds the bidder that by affixing the signature, this is a verification that all bid specifications and conditions have been read and that the terms and conditions, provisions and specifications are agreed to and that certification is made that the services will be provided at the hourly rates stated. Otherwise the basic format for Bid 120 in terms of special conditions is the same as described for the pertinent paragraphs in Bid 119 that have been set out before with the exception of Paragraphs 1.0, and 3.0 (c). They state the following: 1.0 PURPOSE: The Division of Insurance Rating (hereinafter "Division") within the State of Florida's Department of Insurance (hereinafter "Department") is seeking one qualified actuary for the rendering of expert services pertaining to review of Health Insurance rate filings. It is anticipated that the contract will be effective from April 1, 1989 to September 30, 1989, although the precise dates will be dependent upon the date the contract is signed and the schedules of department personnel. * * * 3.0 (c) RESPONDENTS CREDENTIALS AND CAPABILITIES. Proposals must include substantial evidence of the ability of the respondent to undertake the work required within the parameters and time frames referenced in this ITB. The respondent must be a member of both the American Academy of Actuaries and the Society of Actuaries. Furthermore, the respondent must convincingly demonstrate his or her expertise in rating the filing with the Department the following products: Individual Major Medical Medicare Supplement Long Term care Other types of coverage depending upon the needs of the Department and skills of the respondent. Such demonstration must include at least the following: A high degree of familiarity with Chapter 4-58 of the Regulations of the Florida Department of Insurance. Such familiarity should be demonstrated by the respondent providing evidence that he or she submitted at least twenty- five Health Insurance rate filings to the Department which were approved between January 1, 1988 and February 28, 1989. The consultant should demonstrate familiarity with Individual Major Medical, Medicare Supplement, and Long Term Care policies. Such familiarity should be demonstrated by the consultant providing evidence that he or she submitted at least three filings to the Department in each of those areas which were approved between January 1, 1988 and February 28, 1989. NOTE: Only those filings actually certified by the actuary, as provided in 4-58, may be counted in meeting the above requirements. Bid 120 has paragraph 10.1 that refers back to sub-parts within paragraph 3.0(c) and provides space for answering the request for information concerning credentials and capabilities. In both bids Respondent is critical of the Petitioner for not using the format suggested in the various portions of paragraph 10, in essence filling out the specification sheet in the space provided for the answers which the petitioner would give. Having reviewed these materials associated with each bid invitation, the format idea is not a mandatory requirement, it is a suggested requirement. What is incumbent upon the Petitioner is to comply in substance with the requirements set out in the invitations to bid. In that respect the Petitioner is deficient in a material manner. A copy of the requirements Bid 119 may be found in Respondent's exhibit No. 1 admitted into evidence. Petitioner's response to the invitation to bid in Bid 119 is found within Respondent's No. 4 admitted into evidence. In his statement of credentials and capabilities, Petitioner has not utilized the spaces provided in paragraphs 10.1 through 10.3. Instead he has enclosed a letter that includes a statement of work history and professional experience. Under the category of health maintenance organization, the special conditions of paragraph 3.0(c), there is no statement of a consulting assignment or other work responsibility that would involve HMO rate making in the years 1988 or 1989. Furthermore, there is no convincing evidence of familiarity with the health maintenance organization amendments of 1988 to the Federal Health Maintenance Organization Act. There is no reference to public demonstrations of the Petitioner's expertise in the HMO area to include speeches, published articles, positions held in an HMO professional organization or prior full-time employment by an HMO. While there is an indication of experience in rate review from the regulatory point of view in Florida and Massachusetts, there is no indication as required by the specifications and conditions of the preparation of rate filings to be reviewed by a regulator. Finally, under the category of HMO there is no indication of assistance in the preparation of rates for federally qualified HMOs. In the long term care component of the credentials and capabilities portion of Bid 119, Petitioner has offered no explanation of his background. Under the category "other" Respondent has included a description of prior work assignments involving consulting or other services to state insurance departments. On the other hand he has failed to evidence in more specific terms as the note to paragraph 3.0(c) requires, names, addresses and telephone numbers. A copy of the requirements of Bid 120 may be found in Respondent's Exhibit No. 2 admitted into evidence. A copy of Respondent's reply to the invitation to bid may be found in Respondent's Exhibit No. 5 admitted into evidence. As with the previous Bid 119, in Bid 120 Petitioner did not utilize the space available in writing his answers in paragraph 10.1 which relates back to the requirements for credentials and capabilities as announced in paragraph 3.0(c). Instead Petitioner attached a letter in which he attempts to state his compliance with the requirements of the bid. He sets out comments about his work history and professional experience which do not pertain to rating and filing with the Respondent the products of individual major medical, Medicare Supplement, long term care and other types of coverage depending upon needs of the Respondent and skills of the Petitioner. Within Bid 120 in the requirement for familiarity with Chapter 4-58 Florida Administrative Code Petitioner has indicated some involvement with that regulation. However, he has not shown where he had submitted at least twenty- five health insurance rate filings to the Respondent which were approved between the January 1, 1988 and February 28, 1989. In Bid 120 on the topic of demonstration of familiarity with individual major medical, Medicare Supplement and long-term care policies, Petitioner did not demonstrate that he had submitted at least three filings with the Department in each of those areas which were approved between January 1, 1988, and February 28, 1989. By contrast the Wakely response to the invitation to bid, a copy of which is found in Respondent's Exhibit No. 9 admitted into evidence, has adequately responded to the requirements of the Bid 120 in the areas where the Petitioner has been deficient, as well as other areas. As alluded to before Petitioner has failed to make timely challenge to the conditions and specifications associated with the two invitations to bid. Moreover, while allegations in the formal written protest of April 11, 1989 and further remarks of April 20, 1989 addressed to the Insurance Commissioner, together with the proposed recommended order suggest problems with the conditions and specifications associated with the two invitations to bid, proof at hearing submitted by Petitioner did not confirm these allegations. Except in those areas preferred to in the factual discussion above Petitioner's bid responses are adequate to meet the terms of the invitations to bid.

Florida Laws (3) 120.53120.57287.012
# 4
WESTON INSTRUMENTS, INC. vs. HARRIS CORPORATION, HATHAWAY INSTRUMENTS, INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 75-002110BID (1975)
Division of Administrative Hearings, Florida Number: 75-002110BID Latest Update: Oct. 05, 1977

Findings Of Fact In August, 1975, the Department of General Services invited competitive bids for the purchase of supervisory and control equipment and revenue metering equipment for expansion of primary electric utilities in the Capitol Center, a project known as State Project No. DGS-6026/6424, AEP File No. 74288-003. Plans and specifications for the project were developed by the department's consulting architect/engineers Reynolds, Smith and Hills. The Department of General Services (hereinafter Department) and Reynolds, Smith and Hills (hereinafter Reynolds) conducted formal bid opening on September 25, 1975. Bid proposals were received from petitioner, Weston Instruments, Inc. (hereinafter Weston), and from Respondents, Harris Corporation (hereinafter Harris) and Hathaway Instruments, Inc. (hereinafter Hathaway). The amount of the bids were as follows: CONTRACTOR BASE BID ALTERNATE NO. 1-ADD TOTAL Harris 332,000.00 28,649.00 360,649.00 Weston 338,991.00 20,965.00 359,996.00 Hathaway 343,429.00 33,224.00 376,653.00 Hathaway's bid as submitted was responsive to the specifications and other requirements of the bid invitation. Weston's bid was responsive to the specifications and requirements of the bid invitation with the following exception. Specification B-2, in its second paragraph, states: "In order to facilitate the execution of the Agreement, the Bidder shall submit with his proposal a list of and brief description of similar work satisfactorily completed, with location, date of contracts, together with names and addresses of Owners." Weston did not submit that information with its bid but did submit that information on October 9, 1975. The Harris bid as submitted was not responsive to the specifications and requirements of the bid invitation. The material deviations from the specifications found in the Harris bid are as follows: Paragraph 16755-13(c) of the specifications states that data logger equipment by Teletype, Lear Siegler or General Electric will be considered. The Harris bid proposed a data logger manufactured by Practical Automation, Inc. and noted that if Harris was required to conform to the specifications by furnishing a data logger manufactured by one of the three specified manufacturers, its base bid would have to be increased by $635.00. Paragraph 16755-18 of the specifications requires a specific number of supervisory functions at each of the nineteen locations. The Harris bid met the requirements of the specifications at only one of the nineteen locations. At each of the other eighteen locations the Harris bid was from one to three supervisory points deficient. According to the evidence presented it would cost between $250 to $300 per location to furnish the supervisory points left out of Harris' bid. Paragraph 16755-13(d) of the specifications requires that the data logger shall log an uninitiated (alarm) change of status in red lettering. Harris' bid states that the equipment they have chosen is not available with red ribbon printout and that they therefore propose that all changes normally logged in red would instead have an asterisk in the first column. This specification requiring logging in red of an alarm change of status was included by the specifications writer of the architect/engineers as a safety feature. Paragraph 16755-13(e) of the specifications requires that the log shall contain time in a 24 hour format to a tenth of a minute. The Harris bid proposes that the log shall be in seconds rather than tenths of a minute. The specifications require equipment delivery to the job site and substantial completion within 180 calendar days after receipt of Notice To Proceed. The specifications further provide for liquidated damages of $100 per day for each day the contractor fails to meet the above completion date. The Harris bid requested that the liquidated damages clause and the required time for completion be modified to provice that the 180 day period would not commence until all drawings had been approved by the architect/engineers. The architect/engineers, Reynolds, Smith and Hills, calculated that the required drawing time was approximately 60 days. Therefore, the Harris bid proposes that Harris would have 240 days instead of 180 days in which to deliver the equipment to the site and substantially complete the contract. The Harris bid proposed a deviation from the warranty provision of the specifications. The specifications in paragraph E-17 placed the final determination of the need for repairs or changes under the guarantee clause of the specifications with the architect/engineers and the owner. Harris proposes to alter those specifications and place the right of final determination as to the existence and cause of any claim defect with Harris. Harris' bid contained information setting forth their experience with the Micro II System, which is the system they proposed in their bid. That information shows that the Micro II System had been in use no more than two and one-half years at the time of the bid letting. In its evaluation of the bidders' proposals, based upon the data contained in the original bid packages, Reynolds calculated that the deviation from the specifications by Harris gave Harris at least a $10,135 advantage in its bidding (See Petitioner's Exhibit 8). That evaluation did not include a dollar value for the deviation from the specification concerning the warranty. In that evaluation Reynolds noted the failure of Harris to meet the supervisory point requirements. They calculated that this would add $3,900 to Harris' bid based on twelve locations at $300 per location. In fact, Harris failed to meet the requirements at eighteen locations, which at $300 per location, would add $5,400 to Harris' bid. Thus, using the evaluation figures of Reynolds, it appears that Harris' deviations from the specifications gave them at least an $11,635 advantage in the bidding. On October 9, 1975, Reynolds held a conference with each of the three bidders. At that conference Weston provided a list of three names, with addresses of customers for whom Weston had completed work similar to that proposed in its bid. Reynolds did not receive any material information from these references until after October 31, 1975. At least two of the references commented favorably on Weston's performance in letters to Reynolds dated January 13, 1976 and January 20, 1976, respectively. By letter dated October 31, 1975, Reynolds' project manager for this project conveyed the architect/engineers' recommendation for award to the Department. That recommendation was that the contract be awarded to Hathaway Instruments, Inc., for the base bid item only. The recommendation noted that the alternate should be rejected because the bids for the alternate were excessively high. As stated in the letter of recommendation, Reynolds rejected Harris' bid because "there were several major exceptions taken to the specification (sic), the most serious of which was their not being able to meet the delivery schedule." Also, as stated in the letter of recommendation, Weston's bid was apparently rejected because they "could not meet the experience qualifications as specified." Harris, at the time of the bid letting, had five years experience with its Micro I equipment but had only two and one-half years experience with its Micro II equipment. The two lines of equipment constitute two generations of equipment. Neither Harris nor Weston had five years experience with the specific equipment proposed in their bids. Both, however, have had five years experience with the general type system and equipment proposed with Harris being the more experienced of the two. Based upon the evidence presented Weston and Harris are both responsible bidders. In November, 1975, the Department directed Reynolds to contact Harris and determine whether Harris would conform their bid to the specifications. The project manager for Reynolds so contacted Harris and by letter dated November 17, 1975 (Petitioner's Exhibit 4), notified the Department that Harris stated they would deliver the equipment within the time required by the specifications. That letter reiterated Reynolds' recommendation of Hathaway as contained in their letter of October 31, 1975. Reynolds did not retreat from their recommendation of Hathaway and at the final hearing again stated that recommendation. Thereafter, the Department proposed to award the contract to Harris and set the matter for final decision on December 2, 1975. Harris' bid was a responsible offer but was not in full compliance with the bid specifications and conditions. The bids of Weston and Hathaway were responsible offers and were in full compliance with the bid specifications and conditions except as noted in paragraphs 4, 7 and 19 herein. Paragraph B-18 of the Specifications and Contract Documents (Petitioner's Exhibit 1) states that "No bid modification will be accepted after the close of bidding has been announced." Section A of the same document states that bids would be received until 2:00 p.m. EDST, on September 25, 1975. No evidence was presented which would show that the time for receiving bids was extended beyond that set forth above. Therefore, the close of bidding appears to have been at 2:00 p.m., EDST, September 25, 1975. The agreement by Harris to conform their bid to the specifications and conditions constituted a material modification of their bid. This modification occurred in November, 1975, after the close of bidding, and was therefore not allowable under the terms of the Specifications and Contract Documents set forth above. The lowest base bid and alternate bid of those responsible offers received in full compliance with the bid specifications and conditions was that of Weston. No evidence was presented which would show that the Department submitted its complete File on this matter to the Division of Purchasing along with its reasons for recommending a bid other than the low bid meeting specifications, as required by Section 13A-1.02(a), F.A.C.

Florida Laws (2) 287.012287.042
# 5
SIEG AND AMBACHTSHEER, INC. vs DEPARTMENT OF TRANSPORTATION, 98-002420BID (1998)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 22, 1998 Number: 98-002420BID Latest Update: Feb. 05, 1999

The Issue The issue presented is whether Petitioner's bid should be rejected as non-responsive.

Findings Of Fact The Department issued an invitation to bid on State Project No. 93060-3256 for repair and painting of the Flagler Memorial Bridge in Palm Beach County. Since the bridge had tested positive for lead, the advertisement for the project was a standard format utilized by the Department in its District IV for lead-based paint projects requiring QP2 certification. QP2 certification is issued by the Steel Structures Painting Council. The certification demonstrates to the Department that the contractor or subcontractor performing the abatement of lead-based paint on a project has been properly trained to deal with hazardous materials affecting workers and will take the necessary precautions to protect the environment. Utilizing contractors with QP2 certification limits the Department's liability. The certification also ensures that the contractor is familiar with federal Occupational Safety and Health Administration standards. Petitioner is a closely-held corporation. Peter Ambachtsheer is the president and project engineer for the corporation. His sister, Victoria Lane, is the vice president in charge of administration. The advertisement for the project specified that attendance at the pre-bid conference was required in order for any contractor to submit a bid on the project. The mandatory pre-bid conference was held on January 30, 1998, at the District IV office in Fort Lauderdale. Bill Rosenbaum attended the pre- bid conference on behalf of Petitioner. An agenda listing the topics to be discussed and the speakers who would address each topic was distributed to the persons attending the pre-bid conference. The agenda advised that Paul Lampley would discuss "QP2 Certification--Submittal with bid proposal." During his remarks, Lampley specifically told those in attendance that a QP2, Category A, certificate must be submitted with any bid. He read to the persons in attendance the section of the Technical Special Provisions requiring that the QP2, Category A, certificate be submitted with the bid and the provision in the project plans requiring the certificate to be submitted with the bid. Ambachtsheer reviewed the Technical Special Provisions and the plans for the project when Petitioner received the bid package after the pre-bid conference. He understood that the portion of the work involving the lead-based paint must be performed by a contractor or subcontractor holding the required QP2, Category A, certification. Since Petitioner is not so certified, Ambachtsheer contacted Len Hazen Painters, Inc., a company which he knew was certified. Ambachtsheer obtained a quote from Hazen for that portion of the project requiring QP2 certification. He included that amount as part of Petitioner's bid. He told Hazen to fax a copy of its certification to Petitioner so it could be submitted to the Department with Petitioner's bid. Hazen did so, and Petitioner received that certificate before it submitted its bid. Ambachtsheer completed his calculations for the bid and gave his worksheets to Victoria Lane to use in filling in the bid submittal portion of the bid documents. He then left the office to supervise certain work that the company was performing. He did not tell her that the QP2 certificate must be submitted with the bid, and she did not look at the Technical Special Provisions or the project plans since she considers those documents beyond her expertise. Lane prepared the bid submittal sheets using Ambachtsheer's calculations. She submitted the bid so that it was timely received by the Department. She did not include Hazen's QP2 certificate with the bid she submitted on behalf of Petitioner. The Department received Petitioner's bid prior to the deadline. The Department opened the bids it received on Friday, March 13, 1998. Petitioner was the apparent low bidder. When Petitioner learned that it was the apparent low bidder, Ambachtsheer asked to see the bid so he could plan the work on the project. He saw that Hazen's certificate was still in the file and had not been included with Petitioner's bid. He caused the certificate to be faxed to the Department immediately, which occurred late in the morning on Monday, March 16. Upon the next level of review, the Department rejected Petitioner's bid as non-responsive since it failed to include the required QP2 certificate. It is the Department's practice and policy to require that lead-based paint work be performed by a QP2, Category A, certified contractor. The submission of evidence of certification is a material condition of the bid. Petitioner's bid failed to include the required certification. There is, however, some variation among the Department's Districts as to when the required certification should be submitted. That variation did not confuse Petitioner.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Petitioner's bid to be non-responsive and rejecting Petitioner's bid. DONE AND ENTERED this 18th day of August, 1998, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1998. COPIES FURNISHED: Peter Ambachtsheer, President Sieg & Ambachtsheer, Inc. Post Office Box 609 Orange City, Florida 32763 Brian F. McGrail, Esquire Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0458 Pamela Leslie, General Counsel Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450 Thomas F. Barry Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450 ATTN: Diedre Grubbs

Florida Laws (2) 120.569120.57
# 6
CHD MARKETING GROUP AND NORLAKE, INC. vs PALM BEACH COUNTY SCHOOL BOARD, 92-003135BID (1992)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 22, 1992 Number: 92-003135BID Latest Update: Dec. 14, 1992

Findings Of Fact Respondent issued an invitation to bid on March 13, 1992. Bid number SB 92-244I involved the disassembly and removal of an existing walk-in freezer and the furnishing and installation of a new walk-in freezer at Coral Sunset Elementary School. The invitations to bid provided in paragraph Y of the Special Conditions: Failure to file a specification protest within the time prescribed in Florida Statutes 120.53 3.(b) shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. (sic) Bid specifications were included in the invitations to bid issued on March 13, 1992. Twenty-three bids were solicited. There were five responses. One of the responses was submitted by Choice Restaurant Equipment, Inc. ("Choice"). Choice is a vendor for equipment manufactured by Petitioner, Nor-Lake, Inc. ("Nor-Lake"). Nor-Lake is an out-of-state corporation with manufacturer's representatives in numerous states including Florida. 4, Petitioner, CHD Marketing Group ("CHD"), is the manufacturer's representative for Nor-Lake in Florida. CHD represents no other manufacturer of the product included in the bid response. Choice is a sales agent for CHD and other manufacturer's representatives in Florida. Choice sells the products of a variety of manufacturers but is the exclusive sales agent for CHD pursuant to a verbal agency agreement. Choice timely submitted a bid for bid number SB 92-244I on April 8, 1992, prior to the bid deadline of 2:00 p.m. on the same day. The successful bidder submitted its bid by Federal Express at 4:51 p.m on April 8, 1992. Respondent's Department of Purchasing and Stores (the "Department") had stated on March 13, 1992, when the invitations to bid were issued, that bid responses must be received by the Department no later than 2:00 p.m. on April 8, 1992, at the Department's address at 3980 RCA Boulevard/Suite 8044, Palm Beach Gardens, Florida, 33410-4276. Prior to April 8, 1992, the Department relocated to a new facility at 3326 Forest Hill Boulevard, West Palm Beach, Florida. The new address was posted at the old location and Department representatives were present at the old address to accept walk-in bids. Federal Express first attempted to deliver the successful bid at the Department's old address at 10:30 a.m. on April 8, 1992. Federal Express delivered the successful bid to the Department's new address at 4:51 p.m. At 2:00 p.m. on the same day, The Department announced that all bids were in and opened the bids that had been delivered. The successful bid and one other bid were delivered on April 8, 1992, after the public opening conducted at 2:00 p.m. on the same day. Bids were tabulated on April 9, 1992. Bid tabulations were posted on April 13, 1992, and the successful bid was announced. The successful bid was for $8,174.00. Three bids were lower than the successful bid. Choice's bid was for $7,742.56. The other two lower bids were for $8,020.00 and $6,620.00. All three lower bids were rejected as non- responsive. Choice's bid was rejected because it did not meet bid specifications for 22 gauge steel, thermostatically controlled door heaters, and reinforced steel door panels. CHD filed a Notice of Protest on April 14, 1992, and a Formal Written Protest on April 24, 1992. CHD's protest alleges that: Choice's bid was lower than that of the successful bidder; the successful bid was not timely made; the bids were not opened publicly in violation of bidding procedure requirements; and the bid specifications were arbitrary and capricious, favored one bidder, and that Choice's bid was responsive. Neither a notice of protest nor a formal written protest was submitted by Choice or Nor-Lake. Neither Choice nor Nor-Lake attended the informal protest conference conducted on April 30, 1992. On May 7, 1992, Respondent's Office of General Counsel issued its written notice of proposed agency action. The written notice recommended that the bid be awarded to the successful bidder and that CHD's protest be dismissed for lack of standing. CHD requested a formal hearing on May 14, 1992, and the matter was referred to the Division of Administrative Hearings for assignment of a hearing officer on May 15, 1992. The bid submitted by Choice was prepared by CHD but signed by the president of Choice. Neither Nor-Lake nor CHD signed a bid or were otherwise bidders of record for bid number SB 92-244I. Neither Choice, CHD, nor Nor-Lake, filed a notice of protest concerning the bid specifications within 72 hours after Choice received the notice of the project plans and specifications on March 13, 1992. The sole basis upon which CHD claims it is substantially affected is the adverse economic impact caused to it by the proposed agency action. The proposed agency action will result in lost sales from this and future transactions. CHD will lose commissions from this and future transactions. The dealer relationship between CHD and Choice will be damaged because Choice will not want to sell a freezer that is not acceptable to Respondent. The marketing strategy developed between CHD and Nor-Lake will be damaged because it is conditioned upon the award of public contracts.

Florida Laws (1) 120.53
# 7
PADULA AND WADSWORTH CONSTRUCTION, INC. vs BROWARD COUNTY SCHOOL BOARD, 03-002221BID (2003)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jun. 13, 2003 Number: 03-002221BID Latest Update: Dec. 19, 2003

The Issue Whether the Respondent, School Board of Broward County, Florida (Respondent or Board), may reject all bids as proposed for Bid No. 2002-02-FC, Group A1, or whether such action is illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact The Respondent is the entity charged with the responsibility of governing the public schools within the Broward County School District. As such, the acquisition of school properties and attendant improvements fall within the Board's legal authority. These cases involve the procurement of relocatable buildings suitable for classroom purposes. Pursuant to its authority, on or about December 27, 2002, the Respondent issued a bid that is the subject matter of the instant challenge. The bid, identified in this record as Bid 2002-02-FC, sought proposals for the procurement of district-wide relocatable buildings. In a prior time these buildings were known as "portable classrooms" or "portables." In the post-Hurricane Andrew world, these structures are now pre-engineered and constructed of concrete or steel (or a hybrid of both) and must be, by design, capable of being relocated to various sites. The Petitioners, Royal and Padula jointly, and the Intervenor, James B. Pirtle Construction Company, Inc. (Pirtle or Intervenor), design, construct, and install such structures. In these cases the bid sought several distinct proposals. First, the project sought vendors who would provide and deliver concrete relocatable buildings (Group A1). Group A2 (not at issue in this proceeding) sought steel relocatable buildings. Group B (also not at issue in the instant case) sought site adaptation prices for landscaping, lighted covered walkways, steps, ramps, and other engineering incidental to the installation of the buildings. The advertisement for the bid carried the same generic information as to all groups. The bid documents also contained many terms that were applicable to all groups. Pertinent to the issues of these cases are the following excerpts from the bid document (Joint Exhibit 2). The order of the excerpts should not suggest any significance. The excerpts are listed in this manner solely for convenience sake: BASIS OF AWARD In order to meet the needs of the school system . . . each Award will be . . . up to three responsive and responsible bidders meeting specifications, terms and conditions. Individual projects will be issued . . . based upon lowest cost among one or more bidders per project as determined by the project manager. Therefore, it is necessary to bid on every item in the group, and all items in the group must meet specifications in order to have the bid considered for award. Unit prices must be stated in the space provided on Document 00410 Bid Form. SBBC [the Respondent] reserves the right to procure goods from the second and third lowest bidders if: a) the lowest bidder cannot comply with delivery requirements or specifications; b) the lowest bidder is not in compliance with delivery requirements or specifications on current or previous orders; c) in cases of emergency; d) work may be issued to multiple contractors if in the opinion of The School Board of Broward County, Florida or its staff the work cannot be completed by a single contractor in the specified time such as a Summer, Winter or Spring Break or if it is in the best interest of SBBC to do so regardless of reason. ARTICLE 4 BIDDING PROCEDURES 4.01 FORM AND STYLE OF BIDS A. Bids shall be submitted on forms identical to Document 00410, Bid Form, and other standard forms included with the Bidding Documents. The following documents are required to be submitted with the Bid: * * * SIGNED SEALED ARCHITECTURAL AND ENGINEERING DESIGN DRAWINGS OF THE STRUCTURES TO BE PROVIDED (FOR RELOCATABLE BUILDINGS BID ONLY) 5.03 REJECTION OF BIDS AND IRREGULAR PROPOSALS * * * The Owner shall have the right to reject any or all Bids, reject a Bid not accompanied by a required bid security, good faith deposit, or by other data required by the Bid Documents, or reject a Bid which is in any way incomplete, irregular or otherwise not Responsive. The Owner may waive any formality in the bid requirements and award or not award the contract in the best interests of The School Board of Broward County, Florida. (Emphasis in original not shown) In addition to the foregoing, the bid documents contained detailed and specific design criteria that set forth information such as the slope of roofs, the roof spans, the mechanical systems, ventilation, plumbing, windows, and stoops. These design criteria covered hundreds of topics and encompassed virtually every facet of the structures. To review each bid proposal as to whether each design specification was met would require countless man-hours. The issue of how to review the bid proposals was not adequately anticipated by the Respondent. From the outset the bid document evolved from unusual circumstances. Whether the bid document was intended to be a request for proposals (RFP) or an invitation to bid (ITB) was a primary confusion among the Board's staff. If the proposals were to be deemed responsive or not and then ranked solely on price (thus making the bid process more like an ITB) how could staff effectively determine the threshold question of responsiveness? If the proposals were to be ranked based upon a point or qualitative approach (more like an RFP) where were the criteria by which to score the proposals? In fact, there were no objective criteria disclosed in the bid document by which a proposal could be evaluated. More curious is that no bidder brought this lack of evaluation criteria to the Board's attention during the mandatory bidder's conference. Moreover, no one challenged the bid specifications. Presumably, the bidders believed it was an "all or nothing" award. That is, if they were the lowest responsive bidder, they would receive the award. The question of who would be responsive and how that decision would be resolved did not come to light until after the bids had been opened. At the mandatory bidders' conference conducted on January 14, 2003, the bidders posed questions in the form of requests for information. In response, the Respondent issued six addenda intended to cover the questions posed. None of the responses addressed how the bid proposals would be evaluated. If anything, Addendum No. 3 added to confusion related to what documents must be submitted with the bid proposal. More specifically, Addendum No. 3 provided, in pertinent part: [Addendum 3, question and response to inquiry] 9. Can schematics be submitted with the bid instead of the signed and sealed architectural and engineering design drawings of the structures that are requested in Document Article 4.01.A.6? Response: Signed and Sealed Architectural/Structural Drawings are required to be submitted with the Bid. The Requirement for Mechanical and Electrical signed and sealed drawing is waived, however all engineering associated with the Relocatable Buildings will require engineer of record signed and sealed drawings and calculations prior to issuance of building permit DRC review. Nevertheless, when the bid proposals were opened on March 4, 2003, the Petitioners and the Intervenor were found to be the three lowest bidders. If responsive, the Intervenor would be considered the lowest bidder with the Petitioners being considered alternate vendors for the procurement. Unsatisfied with the preliminary determination that the Intervenor was the lowest bidder, the Petitioners timely challenged the bid award. The Petitioners maintained that the Intervenor had not timely provided sealed design drawings as required by the bid document. Petitioners argued that the Intervenor had attempted to impermissibly amend their proposal by late-filing a set of structural drawings for the bid. Thus the initial bid protest sought to determine what design drawings were required by the bid and whether the Intervenor had timely supplied such drawings. The Petitioners contended that the Intervenor's submittal should be rejected as non-responsive to the bid. Whether they had complied with the full dictates of the bid requirements was potentially at issue as well. While the initial bid protest was referred to the Division of Administrative Hearings and scheduled for formal hearing, the parties continued to attempt to resolve the issues. It was apparent that the bidders had not submitted identical proposals. How the proposed products had been compared and evaluated was difficult to determine. From the Respondent's committee members came the disclosure that the decision of determining whether the bidders had complied with the bid ultimately came from three fashioned questions. If the structure proposed was pre- engineered, relocatable to various sites, and suitable for educational purposes, the entry was deemed responsive. Based upon this assessment the Petitioners and the Intervenor were deemed responsive and their bids ranked based upon price. This approach did nothing to discern if the designs were comparable in quality, if they met the bid design criteria, or if the drawings were even sufficient to comply with the dictates of the bid. The first posting of the bid award for Group A1 was entered March 18, 2003. On March 21, 2003, the Petitioners timely filed their notices of intent to protest the award of Group A1 to the Intervenor. Thereafter they timely filed the petitions to protest the award and the initial protest was forwarded to the Division of Administrative Hearings. The protests did not encompass Group A2 or Group B. No bidder protested the proposed awards for Group A2 or Group B. In fact, the Respondent went forward on those procurements and awarded contracts for those groups on April 1, 2003. The Respondent did not award the contract award for the Group at issue in this proceeding. It must be noted that the instant procurement is not the Board's first experience with the procurement of concrete relocatable classrooms. In fact, the Board has purchased similar structures through a procurement contract that the Palm Beach County School Board holds with its vendors. One of the Respondent's concerns when the instant bids were reviewed was why the cost per unit for the bids in this case was higher than the Palm Beach County amount. As it turned out, the installation economy of multiple units at one site directly impacts the cost of the relocatable structures. Royal confirmed this information after the bids had been opened. When the Respondent's staff met with its counsel in preparation for the initial bid dispute (before the Board elected to reject all bids) the cost of the bid, the lack of full evaluation of the bidders' proposals, and the issues of the first protest were openly discussed. By that time any irregularities with the bid documents could not be repaired as to the contracts already awarded, but as to the instant matter the Respondent could revisit the circumstances and determine its best course. As a result of that reassessment, the Respondent elected to reject all bids regarding this group and attempt to re-bid the procurement with more certain terms. To that end on May 9, 2003, the Respondent issued a revised bid decision that provided in pertinent part: The Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on June 3, 2003, reject all bids received for Group A1 and authorize revising the bidding documents and re-bidding. The rejection of all bids received for Group A1 is made due to serious flaws and ambiguities contained in Document 00200 4.01.A-6 as modified by Addendum No. 3. The Division intends to revise the bidding documents to delete the requirements that bidders submit plans with the bids; include ranges of unit quantities within the bid form; include one or more additional types of construction of the classroom buildings including a composite concrete/steel structure; and incorporate within the new Invitation to Bid all revised terms and conditions that were released through addenda in this procurement. The Petitioners timely filed protests regarding this new decision by the Board and the instant action ensued. By issuing the revised decision to reject all bids the Respondent intended to resolve all issues and to cure the perceived problem with the lack of consistent evaluation of the bidders' proposals. More specifically, the Respondent would be able to assure that the project design could comport with the specifications sought; specify whether architectural or engineering drawings were required and when (it was hoped that the confusion over "architect" vs. "engineer" could be eliminated); and obtain a substantial discount based upon economies from multi-unit purchases for a single site. None of the objectives sought were pre-textual or contrived. Additionally, by avoiding any process that would require a detailed reviewed of the bidders' proposals, countless man- hours could be saved.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a Final Order affirming the decision to reject all bids in this matter. DONE AND ENTERED this 20th day of November 2003 in Tallahassee, Leon County, Florida. S ___________________________________ D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of November 2003. COPIES FURNISHED: Dr. Franklin L. Till, Jr. Superintendent Broward County School Board 600 Southeast Third Avenue Fort Lauderdale, Florida 33301-3125 Daniel J. Woodring, General Counsel Department of Education 325 West Gaines Street 1244 Turlington Building Tallahassee, Florida 32399-0400 Usher Larry Brown, Esquire Brown, Salzman, Weiss & Garganese, P.A. 225 East Robinson Street, Suite 660 Orlando, Florida 32801 Steven L. Schwarzberg, Esquire Schwarzberg & Associates Esperante, Suite 210 222 Lakeview Avenue West Palm Beach, Florida 33401 Thomas R. Shahady, Esquire Adorno & Yoss, P.A. 350 East Las Olas Boulevard, Suite 1700 Fort Lauderdale, Florida 33301 Robert Paul Vignola, Esquire Broward County School Board C. Wright Administrative Building 600 Southeast Third Avenue, 11th Floor Fort Lauderdale, Florida 33301

Florida Laws (2) 120.569120.57
# 8
COUCH CONSTRUCTION COMPANY, INC. vs. DEPARTMENT OF TRANSPORTATION, 78-000391 (1978)
Division of Administrative Hearings, Florida Number: 78-000391 Latest Update: Apr. 24, 1978

The Issue The issues presented for determination at the hearing are as follows: 1/ Whether respondent Department of Transportation (D.O.T.) abused its discretion or acted in bad faith, arbitrarily, capriciously, or under a misconception of law in rejecting all bids received on the subject project on December 21, 1977. Whether the decision of the respondent D.O.T. to reject all bids was made in violation of Florida's Government in the Sunshine Law, F.S. s286.011.

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: By a "notice to contractors" dated November 24, 1977, the respondent D.O.T. advertised that it would receive bids on December 21, 1977, from qualified contractors for various construction and maintenance programs. The project which is the subject of this proceeding was contained in this notice, identified as "Gadsden County: Federal Aid Project No. I-10-3(31)157 Contract II (Job No. 50001-3423) SR 8 (I-10)." This project involved the paving of a certain stretch of Interstate Highway 10 in Gadsden County, which stretch was the last remaining unopen portion of I-10. In addition to a short summary of the contents of the project the notice on this project contained the following language which was underlined and capitalized in the notice: NOTE: A PRE-BID CONFERENCE ON THIS PROJECT WILL BE HELD ON WEDNESDAY, DECEMBER 14, 1977, AT 10:00 A.M. IN ROOM 301 OF THE HAYDON BURNS BUILDING, 605 SUWANNEE STREET, TALLAHASSEE, FLORIDA. ALL POTENTIAL BIDDERS WILL BE RE- QUIRED TO ATTEND. NOTE: ON-THE-JOB TRAINING WILL BE REQUIRED FOR THIS PROJECT. Mr. Henry Eugene Cowger, deputy state construction engineer for the D.O.T., made the initial decision to require attendance at a prebid conference for this project, although he himself did not draft the language used in the notice. Cowger felt that a prebid conference would be valuable to bidders and the Department due to the uniqueness of this particular project with regard to the requirements concerning maintenance of traffic and work progress. More specifically, the contract called for a close working relationship and cooperation with the first stage contractor on this stretch of road. The first stage contractor is respondent/intervenor White. Also, it was anticipated that the project would be opened in sections with unusual traffic requirements so that the entire project could be utilized in a limited fashion. Mr. Cowger instructed William F. Ray, the Department's area construction engineer, to arrange for and conduct the prebid conference. No specific instructions were given to Mr. Ray as to which provisions of the contract were to be discussed at the conference. Cowger felt that Ray was knowledgeable with the project and therefore that he needed no instructions. The prebid conference was held as scheduled on December 14, 1977. Representatives of six different construction companies attended, including a representative from respondent White Construction Company. Through neglect or oversight, petitioner Couch did not attend the conference. A memorandum to the file from Mr. Ray indicates that the following occurred at the conference: A statement was made at the beginning of the meeting by W. F. Ray that nothing said by any person at the meeting would change or modify any part of the contract documents. Certain portions of the special Provisions per- taining to maintenance of traffic and limitations of work areas were read and discussed. It was agreed by those present that the intent of these Specials Provisions was clear and under- standable. Mr. McRae of H.D.W. stated that the unknown delay times built into this project would result in much higher than normal bids and his company would probably not enter a bid. After a short discussion of the terms of the contract, the meeting was adjourned. The conference lasted from thirty to forty-five minutes. At the hearing, Mr. Ray related the questions he could remember which were asked by the contractors. It was admitted that virtually all of the provisions and expectations, unique or otherwise, were fully spelled out in the contract documents. Most of the inquiries at the conference related to the absorption of certain maintenance and traffic costs and responsibilities between the contractor and the D.O.T. In each instance, it was disclosed that the D.O.T. would be responsible for these unless the contract specifically provided otherwise. Questions regarding the sequence of operations and the phasing of the work with the first stage contractor were not specifically answered by D.O.T. representatives. Of the three contractors who submitted bids on the subject project on December 21, 1977, only respondent/intervenor White had attended the December 14th rebid conference. Joseph F. Villadsen, petitioner's engineering division vice president, had visited the site of the project and had studied the contract provisions, which appeared clear to him. In numerical order, the bids submitted on December 21, 1977, were as follows: $1,410,730.72 - - petitioner Couch $1,514,272.63 - - respondent/intervenor White $1,579,168.72 - - Contee Sand and Gravel Company, Inc. The respondent has an Awards Committee composed of five executives from the D.O.T. This Committee generally meets once a month to review bids and make a recommendation to respondent's Secretary on the award of contracts for some thirty-five to fifty projects per month. Although Secretary Webb has the authority to make an independent decision and/or to reject the recommendations of the Awards Committee with regard to the acceptance of bids, he could not recall ever having done so. On the afternoon of December 21, 1977, the same day as the bids were received, Mr. Jay Brown, respondent's director of road operations and chairman of the Awards Committee, learned from two representatives of White that the apparent low bidder, petitioner Couch, had not attended the prebid conference. He thereupon called together those members of the Awards Committee who were in the building at that time to discuss what should be done. Brown also counseled with P.E. Carpenter, the division administrator for the Federal Highway Administration, to determine the extent of the federal participation in funding if a bid other than the low bid were accepted. Awards Committee members Brown, Sill Ekey, Peter J. White and Willis Armstrong met on December 21 and 22, 1977. In reaching a determination as to their recommendation to the Secretary, the committee members considered three alternatives -- awarding the contract to Couch as the apparent low bidder, awarding the contract to White as the next lowest bidder and as the only bidder who attended the prebid conference or rejecting all bids received and readvertising for new bids. Each alternative was considered a viable one by the committee members. Although the members felt that the requirement of attendance at a prebid conference was a reasonable requirement due to the uniqueness of the project, no inquiry was made as to what actually transpired at the conference. Nor was any inquiry made as to a reason for petitioner's nonattendance. It was the unanimous decision of those Committee members present that it would best serve the interests of the State to reject all bids and proceed to readvertise. This decision to recommend rejection and readvertisement was based upon several reasons. The prime consideration was that this project involved the last remaining unopen link in Interstate Highway 10 and time was of the essence. It was felt that if the contract were awarded to Couch or to White, there would be litigation causing delay to the completion of Interstate 10. The Committee members were also concerned with the significant amount of difference between the bids of Couch and White. Rejecting all bids appeared to the Committee members to be the "cleaner" way to go. Mr. Brown testified that the D.O.T. does not generally accept the bid where only one bid is received. Here the apparent low bidder and the highest bidder were considered irregular for failure to attend the prebid conference. Thus, the Department was left with only one bid. Through Mr. Brown, Secretary Thomas Webb, Jr., was telephonically notified of the recommendation of the Awards Committee. Mr. Webb concurred with the Committee's recommendation because he was concerned with a possible delay to the project due to litigation were the bid to be awarded to either Couch or to White. Thereafter, the bidders were notified by telegram that all bids on the project had been rejected due to the failure of the low bidder to attend the prebid conference, and that the project would be readvertised. On December 29, 1977, Couch filed a "complaint" with the D.O.T. requesting a hearing pursuant to F.S. s120.57 on the issue of whether the D.O.T. lawfully rejected Couch's bid on the subject project. By Order dated January 9, 1978, Secretary Webb denied Couch's request for a hearing. This denial was appealed by Couch to the District Court of Appeal, First District, and White Construction Company was made a party to that proceeding. After numerous motions were filed and oral argument was had, the District Court, by Order dated February 24, 1978, relinquished jurisdiction for a period of sixty days and remanded the case to the D.O.T. for the purpose of providing Couch a s120.57(1) hearing. The District Court stayed the D.O.T. from awarding the contract for the subject project. Prior to the Orders of the District Court, the D.O.T. readvertised the project, calling for a prebid conference on January 11, 1978, and the receipt of bids on January 12, 1978. This time, attendance at the conference was announced to be "expected," rather than "required." At the hearing, the D.O.T. divulged that attendance at prebid conferences would no longer be required or mandatory in order to avoid the problem inherent in the instant proceeding. Both Couch and White attended the January 11th prebid conference and submitted bids on January 12th. Couch's bid was identical to its December 21, 1977, bid. White submitted a bid approximately $40,000.00 below the bid of Couch. The D.O.T. receives bids on approximately 420 to 550 construction projects a year. During the past ten years, only seven other prebid conferences with required attendance have been held. In those instances, the language contained in the notice was different from the language used in the subject notice. On three occasions the language used was: "ALL PROSPECTIVE BIDDERS MUST ATTEND THIS PRE-BID CONFERENCE AS BIDDING DOCUMENTS WILL NOT BE ISSUED TO CONTRACTORS WHO HAVE NOT BEEN PROPERLY REPRESENTED AT THIS MEETING." On three occasions the language was: "ATTENDANCE WILL BE MANDATORY FOR THOSE INTENDING TO BID ON THIS PROJECT.? On one occasion the language was: "ATTENDANCE WILL BE MANDATORY FOR THOSE INTENDING TO SUBMIT A BID ON THIS PROJECT." The situation where the apparent low bidder has not attended a required prebid conference has never before arisen.

Recommendation Based upon the findings of fact and conclusions of law recited above, it is recommended that the D.O.T.`s decision to reject all bids and readvertise the subject project be affirmed and upheld. Respectfully submitted and entered this 24th of April, 1978, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675

Florida Laws (1) 337.11
# 9
ROYAL CONCRETE CONCEPTS, INC. vs BROWARD COUNTY SCHOOL BOARD, 03-002220BID (2003)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jun. 13, 2003 Number: 03-002220BID Latest Update: Dec. 19, 2003

The Issue Whether the Respondent, School Board of Broward County, Florida (Respondent or Board), may reject all bids as proposed for Bid No. 2002-02-FC, Group A1, or whether such action is illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact The Respondent is the entity charged with the responsibility of governing the public schools within the Broward County School District. As such, the acquisition of school properties and attendant improvements fall within the Board's legal authority. These cases involve the procurement of relocatable buildings suitable for classroom purposes. Pursuant to its authority, on or about December 27, 2002, the Respondent issued a bid that is the subject matter of the instant challenge. The bid, identified in this record as Bid 2002-02-FC, sought proposals for the procurement of district-wide relocatable buildings. In a prior time these buildings were known as "portable classrooms" or "portables." In the post-Hurricane Andrew world, these structures are now pre-engineered and constructed of concrete or steel (or a hybrid of both) and must be, by design, capable of being relocated to various sites. The Petitioners, Royal and Padula jointly, and the Intervenor, James B. Pirtle Construction Company, Inc. (Pirtle or Intervenor), design, construct, and install such structures. In these cases the bid sought several distinct proposals. First, the project sought vendors who would provide and deliver concrete relocatable buildings (Group A1). Group A2 (not at issue in this proceeding) sought steel relocatable buildings. Group B (also not at issue in the instant case) sought site adaptation prices for landscaping, lighted covered walkways, steps, ramps, and other engineering incidental to the installation of the buildings. The advertisement for the bid carried the same generic information as to all groups. The bid documents also contained many terms that were applicable to all groups. Pertinent to the issues of these cases are the following excerpts from the bid document (Joint Exhibit 2). The order of the excerpts should not suggest any significance. The excerpts are listed in this manner solely for convenience sake: BASIS OF AWARD In order to meet the needs of the school system . . . each Award will be . . . up to three responsive and responsible bidders meeting specifications, terms and conditions. Individual projects will be issued . . . based upon lowest cost among one or more bidders per project as determined by the project manager. Therefore, it is necessary to bid on every item in the group, and all items in the group must meet specifications in order to have the bid considered for award. Unit prices must be stated in the space provided on Document 00410 Bid Form. SBBC [the Respondent] reserves the right to procure goods from the second and third lowest bidders if: a) the lowest bidder cannot comply with delivery requirements or specifications; b) the lowest bidder is not in compliance with delivery requirements or specifications on current or previous orders; c) in cases of emergency; d) work may be issued to multiple contractors if in the opinion of The School Board of Broward County, Florida or its staff the work cannot be completed by a single contractor in the specified time such as a Summer, Winter or Spring Break or if it is in the best interest of SBBC to do so regardless of reason. ARTICLE 4 BIDDING PROCEDURES 4.01 FORM AND STYLE OF BIDS A. Bids shall be submitted on forms identical to Document 00410, Bid Form, and other standard forms included with the Bidding Documents. The following documents are required to be submitted with the Bid: * * * SIGNED SEALED ARCHITECTURAL AND ENGINEERING DESIGN DRAWINGS OF THE STRUCTURES TO BE PROVIDED (FOR RELOCATABLE BUILDINGS BID ONLY) 5.03 REJECTION OF BIDS AND IRREGULAR PROPOSALS * * * The Owner shall have the right to reject any or all Bids, reject a Bid not accompanied by a required bid security, good faith deposit, or by other data required by the Bid Documents, or reject a Bid which is in any way incomplete, irregular or otherwise not Responsive. The Owner may waive any formality in the bid requirements and award or not award the contract in the best interests of The School Board of Broward County, Florida. (Emphasis in original not shown) In addition to the foregoing, the bid documents contained detailed and specific design criteria that set forth information such as the slope of roofs, the roof spans, the mechanical systems, ventilation, plumbing, windows, and stoops. These design criteria covered hundreds of topics and encompassed virtually every facet of the structures. To review each bid proposal as to whether each design specification was met would require countless man-hours. The issue of how to review the bid proposals was not adequately anticipated by the Respondent. From the outset the bid document evolved from unusual circumstances. Whether the bid document was intended to be a request for proposals (RFP) or an invitation to bid (ITB) was a primary confusion among the Board's staff. If the proposals were to be deemed responsive or not and then ranked solely on price (thus making the bid process more like an ITB) how could staff effectively determine the threshold question of responsiveness? If the proposals were to be ranked based upon a point or qualitative approach (more like an RFP) where were the criteria by which to score the proposals? In fact, there were no objective criteria disclosed in the bid document by which a proposal could be evaluated. More curious is that no bidder brought this lack of evaluation criteria to the Board's attention during the mandatory bidder's conference. Moreover, no one challenged the bid specifications. Presumably, the bidders believed it was an "all or nothing" award. That is, if they were the lowest responsive bidder, they would receive the award. The question of who would be responsive and how that decision would be resolved did not come to light until after the bids had been opened. At the mandatory bidders' conference conducted on January 14, 2003, the bidders posed questions in the form of requests for information. In response, the Respondent issued six addenda intended to cover the questions posed. None of the responses addressed how the bid proposals would be evaluated. If anything, Addendum No. 3 added to confusion related to what documents must be submitted with the bid proposal. More specifically, Addendum No. 3 provided, in pertinent part: [Addendum 3, question and response to inquiry] 9. Can schematics be submitted with the bid instead of the signed and sealed architectural and engineering design drawings of the structures that are requested in Document Article 4.01.A.6? Response: Signed and Sealed Architectural/Structural Drawings are required to be submitted with the Bid. The Requirement for Mechanical and Electrical signed and sealed drawing is waived, however all engineering associated with the Relocatable Buildings will require engineer of record signed and sealed drawings and calculations prior to issuance of building permit DRC review. Nevertheless, when the bid proposals were opened on March 4, 2003, the Petitioners and the Intervenor were found to be the three lowest bidders. If responsive, the Intervenor would be considered the lowest bidder with the Petitioners being considered alternate vendors for the procurement. Unsatisfied with the preliminary determination that the Intervenor was the lowest bidder, the Petitioners timely challenged the bid award. The Petitioners maintained that the Intervenor had not timely provided sealed design drawings as required by the bid document. Petitioners argued that the Intervenor had attempted to impermissibly amend their proposal by late-filing a set of structural drawings for the bid. Thus the initial bid protest sought to determine what design drawings were required by the bid and whether the Intervenor had timely supplied such drawings. The Petitioners contended that the Intervenor's submittal should be rejected as non-responsive to the bid. Whether they had complied with the full dictates of the bid requirements was potentially at issue as well. While the initial bid protest was referred to the Division of Administrative Hearings and scheduled for formal hearing, the parties continued to attempt to resolve the issues. It was apparent that the bidders had not submitted identical proposals. How the proposed products had been compared and evaluated was difficult to determine. From the Respondent's committee members came the disclosure that the decision of determining whether the bidders had complied with the bid ultimately came from three fashioned questions. If the structure proposed was pre- engineered, relocatable to various sites, and suitable for educational purposes, the entry was deemed responsive. Based upon this assessment the Petitioners and the Intervenor were deemed responsive and their bids ranked based upon price. This approach did nothing to discern if the designs were comparable in quality, if they met the bid design criteria, or if the drawings were even sufficient to comply with the dictates of the bid. The first posting of the bid award for Group A1 was entered March 18, 2003. On March 21, 2003, the Petitioners timely filed their notices of intent to protest the award of Group A1 to the Intervenor. Thereafter they timely filed the petitions to protest the award and the initial protest was forwarded to the Division of Administrative Hearings. The protests did not encompass Group A2 or Group B. No bidder protested the proposed awards for Group A2 or Group B. In fact, the Respondent went forward on those procurements and awarded contracts for those groups on April 1, 2003. The Respondent did not award the contract award for the Group at issue in this proceeding. It must be noted that the instant procurement is not the Board's first experience with the procurement of concrete relocatable classrooms. In fact, the Board has purchased similar structures through a procurement contract that the Palm Beach County School Board holds with its vendors. One of the Respondent's concerns when the instant bids were reviewed was why the cost per unit for the bids in this case was higher than the Palm Beach County amount. As it turned out, the installation economy of multiple units at one site directly impacts the cost of the relocatable structures. Royal confirmed this information after the bids had been opened. When the Respondent's staff met with its counsel in preparation for the initial bid dispute (before the Board elected to reject all bids) the cost of the bid, the lack of full evaluation of the bidders' proposals, and the issues of the first protest were openly discussed. By that time any irregularities with the bid documents could not be repaired as to the contracts already awarded, but as to the instant matter the Respondent could revisit the circumstances and determine its best course. As a result of that reassessment, the Respondent elected to reject all bids regarding this group and attempt to re-bid the procurement with more certain terms. To that end on May 9, 2003, the Respondent issued a revised bid decision that provided in pertinent part: The Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on June 3, 2003, reject all bids received for Group A1 and authorize revising the bidding documents and re-bidding. The rejection of all bids received for Group A1 is made due to serious flaws and ambiguities contained in Document 00200 4.01.A-6 as modified by Addendum No. 3. The Division intends to revise the bidding documents to delete the requirements that bidders submit plans with the bids; include ranges of unit quantities within the bid form; include one or more additional types of construction of the classroom buildings including a composite concrete/steel structure; and incorporate within the new Invitation to Bid all revised terms and conditions that were released through addenda in this procurement. The Petitioners timely filed protests regarding this new decision by the Board and the instant action ensued. By issuing the revised decision to reject all bids the Respondent intended to resolve all issues and to cure the perceived problem with the lack of consistent evaluation of the bidders' proposals. More specifically, the Respondent would be able to assure that the project design could comport with the specifications sought; specify whether architectural or engineering drawings were required and when (it was hoped that the confusion over "architect" vs. "engineer" could be eliminated); and obtain a substantial discount based upon economies from multi-unit purchases for a single site. None of the objectives sought were pre-textual or contrived. Additionally, by avoiding any process that would require a detailed reviewed of the bidders' proposals, countless man- hours could be saved.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a Final Order affirming the decision to reject all bids in this matter. DONE AND ENTERED this 20th day of November 2003 in Tallahassee, Leon County, Florida. S ___________________________________ D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of November 2003. COPIES FURNISHED: Dr. Franklin L. Till, Jr. Superintendent Broward County School Board 600 Southeast Third Avenue Fort Lauderdale, Florida 33301-3125 Daniel J. Woodring, General Counsel Department of Education 325 West Gaines Street 1244 Turlington Building Tallahassee, Florida 32399-0400 Usher Larry Brown, Esquire Brown, Salzman, Weiss & Garganese, P.A. 225 East Robinson Street, Suite 660 Orlando, Florida 32801 Steven L. Schwarzberg, Esquire Schwarzberg & Associates Esperante, Suite 210 222 Lakeview Avenue West Palm Beach, Florida 33401 Thomas R. Shahady, Esquire Adorno & Yoss, P.A. 350 East Las Olas Boulevard, Suite 1700 Fort Lauderdale, Florida 33301 Robert Paul Vignola, Esquire Broward County School Board C. Wright Administrative Building 600 Southeast Third Avenue, 11th Floor Fort Lauderdale, Florida 33301

Florida Laws (2) 120.569120.57
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer