Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
GERALDINE HIDI LEIGH vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 84-001757 (1984)
Division of Administrative Hearings, Florida Number: 84-001757 Latest Update: Mar. 27, 1985

Findings Of Fact On September 9, 1983, Intervenor, Jacksonville Port Authority (JPA), made application to Respondent, Department of Environmental Regulation (DER), for a dredge and fill permit and water quality certification, to construct a commercial docking facility on the west channel of Blount Island, and to dredge material adjacent to the proposed dock for a navigation channel. JPA is a body-politic and corporate operating under the authority of Chapter 63-1447, Laws of Florida. It was expressly created for the public purpose of constructing, developing and operating marine and airport terminals in Jacksonville, Florida. Blount Island is a spoil island comprised of approximately 800 acres, and lies in the St. Johns River, at Jacksonville, Florida. In 1964 the island was deeded by the State of Florida to the JPA for the purpose of constructing a port. To date, approximately 40 percent of the island has been developed. There are 4,300 feet of dock on the main channel and one dock under construction on the west channel. Over two and a half million tons of cargo presently pass through the Blount Island terminal each year. The permit, if granted, would allow JPA to construct a "T" shaped docking facility on the northwest shoreline of Blount Island. The pier would be 59 feet wide and extend 250 feet from the shoreline toward the west channel. The pier would terminate with a "T" head, 70 feet wide and 200 feet long. Associated mooring and bresting dolphins connected to a 1,500 foot catwalk would be constructed parallel to, and shoreward of, the "T" head. JPA proposes to construct the facility on open concrete piles. No fueling or toilet facilities will be constructed on the pier. The proposed facility is graphically illustrated by the attached excerpt from Intervenor's Exhibit 1. The permit would also allow the placement of riprap along the shoreline adjacent to the facility and landward of the Mean Highwater (MH) line, and the dredging of approximately 35,000 cubic yards of material to provide a 126 foot by 2,000 foot access channel, with a depth of -30 feet Mean Sea Level, to the facility from the existing west channel. The proposed facility, a roll-on/roll-off dock (RO-RO dock) would accommodate two deep water vessels at any one time. The vessels would moor stern to the dock, and containerized cargo would be loaded or unloaded from the ship's rear unloading ramp by trucks towing the wheeled containers. The facility, and associated water runoff, will not pose a water quality problem. On April 9, 1984 DER issued its notice of intent to grant the permit to JPA. A timely request for hearing, pursuant to Section 120.57, Fla. Stat., was filed by Petitioner. JPA proposes to dredge the subject channel by using a hydraulic suction dredge. The dredge would pump a slurry of water and the dredge material through a pipeline to the dredge spoil disposal area on the island. The dredge would act as a vacuum cleaner. As the materials were dislodged from the bottom, they would be immediately sucked into the dredge pipe where they would remain until they were ejected at the spoil site. Samples of the materials to be dredged establish that they are nontoxic and consist of relatively clean silky sand. Because of the sand's particle size, settlement time and chemical constituents, the dredge materials will pose no water quality problems. JPA proposes to dispose of the spoil materials at an existing spoil disposal site on Blount Island. The disposal area consists of two settlement ponds of different elevations, connected by throttling pipes. The dredge materials will be deposited in the upper pond and over the course of two and a half days the materials will settle, and the waters will be slowly returned to the St. Johns River. Turbidity at the point of discharge will not exceed the background. The shoreline area immediately adjacent to the proposed dock contains a zone of tidal shoreline marsh varying in width from 15 to 60 feet. This area will not be disturbed. No submerged vegetation exists. While some benthic organisms will be eliminated during the dredging, the area will quickly recolonize. No clam or oyster beds exist in the vicinity of the project. Petitioner expressed her personal concern about the potential impact of the proposed facility on the manatee. Although manatee have in the past been sighted in the west channel, there was no credible evidence that they currently frequent the area or that the construction and operation of the facility will impact adversely on them. Petitioner further expressed concern that, if not properly managed, the spoil disposal site might be a source of particulate matter (dust)--air pollution. However, JPA's Blount Island operation is not a complex air source, and the disposal site, if properly managed, will not be a source of particulate matter. JPA has agreed to properly manage the disposal site.

Florida Laws (1) 120.57
# 1
DAVID BRENNER AND MRS. DAVID BRENNER vs. THE DAVID J. JOSEPH COMPANY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 88-006009 (1988)
Division of Administrative Hearings, Florida Number: 88-006009 Latest Update: Jun. 21, 1989

The Issue The issue in this case is whether the Department of Environmental Regulation (Department) should issue a solid waste construction permit to the David J. Joseph Company (Applicant) to construct lined cells at its existing Class I solid waste landfill in Tampa, Hillsborough County, Florida. It is the position of the applicant and the Department that all statutory and rule criteria for the issuance of said permit have been met, while Mr. & Mrs. David Brenner (Petitioners) contend that the application fails to meet the criteria for the issuance of this permit.

Findings Of Fact The applicant filed an application for a solid waste construction permit with the Department on May 2, 1988. This application was given permit number S029-77041. The applicant proposes to expand its existing solid waste Class I sanitary landfill located near Kingsway Road and Interstate 4, east of Tampa, Hillsborough County, Florida, through the construction of a lined addition. This entire site consists of approximately 16 acres, but the lined portion for which this permit is sought comprises about eight acres. This site was purchased by the applicant in 1978, to landfill shredder waste, or "fluff", produced at its Tampa shredder. In fact, the applicant has operated this site as a landfill since 1978, under two previous permits issued by the Department in 1978 and 1983, and approximately nine acres of the site have already been filled. The Department gave notice of its intent to grant this permit on September 23, 1988, subject to specified conditions. The Petitioners, thereafter, timely requested this administrative hearing. The applicant is engaged in the ferrous scrap business at fourteen locations throughout the United States, and provides steel mills with raw material for their use in the production of new steel. It operates a large shredding plant in Tampa, Florida, which consists primarily of an automobile shredder and related equipment. The shredder is a large crushing and grinding piece of equipment which, in approximately 20 seconds, grinds scrap autos into small chunks of scrap the size of a man's fist. A conveyor system separates the scrap produced in the shredding process into three streams. The first stream consists of steel scrap that is sold to a steel mill. Approximately 80% of automobile scrap is steel. The second stream consists of non-ferrous material, primarily aluminum, zinc, copper, brass and other non-steel items found in autos, which are then sold to dealers in that particular type of metal. The third stream is waste material, or "shredder fluff". Approximately 17% of the material in automobile scrap is fluff. Guidelines have been established by the applicant which limit the type of material which will be accepted at the shredder facility as feedstock for the shredder operation. These guidelines prohibit acceptance of lead-acid batteries, gas tanks, tires, catalytic converters, and loose mufflers and tail pipes. Automobiles which are accepted by the applicant at its Tampa plant have already been crushed at separate locations by other companies engaged in the car crushing business prior to their purchase by the applicant. In the crushing process, most automobile fluids are liberated, but oil and other fluids not liberated during the crushing process are then liberated in the shredding process, and are intermingled with all three product streams produced at the shredder mill. Shredder fluff consists largely of automotive components such as upholstery, plastic, glass, rubber, dirt, and other non-magnetic and non-ferrous materials. The applicant's shredder operation in Tampa generates approximately seven to eight tractor trailer loads of fluff per day which are deposited at their current landfill. During 1988, the fluff from approximately 200,000 autos was disposed at this site. The existing landfill is located approximately 550 feet off of the roadway, and is accessible by an entrance road leading to the main gate of the site. The landfill is completely fenced with barbed wire around its perimeter, and there is a locked gate at the access road. There is a full time manager on site. Only shredder fluff produced by the applicant's Tampa shredder is deposited at this site. The applicant delivers its waste to this landfill using its own equipment and personnel. The applicant has taken reasonable steps to insure that only authorized persons enter the landfill site, and that there will be no unauthorized dumping. In order to continue using this landfill site, the applicant proposes to construct a liner system and leachate collection system for the remaining unfilled portion of the landfill, and also to establish a stormwater management system serving the entire site. A geotechnical and foundation investigation has been performed on the site to determine the physical and chemical characteristics of site soils, and the ability of those soils to support the landfill construction. The potential for movement in foundation soils was specifically addressed. It is to be noted that the applicant has been operating a landfill at this site for ten years without any sinkhole or foundation problems. There are no active sinkholes on the site, nor was there competent substantial evidence that any sinkhole had historically existed on this site. While the site geology is complex, the soils and subsurface geology will support the proposed project. Thus, the site is suitable for construction of lined Class I landfill cells. Beneath a surficial sand layer of approximately 30 feet in depth, lies an interbedded layer of sands, clay and heavily weathered limestone lenses approximately 40 feet thick, under which lies the Floridan Aquifer. The applicant will excavate below the level of the existing pit floor to remove any limestone protrusions which could adversely affect liner integrity. A dense clay layer, graded to remove rocks and other protrusions, will be used as a secondary barrier to retard the movement of contaminants into groundwater, and to further minimize the potential impact from limestone pinnacles upon liner integrity. The primary containment system will be a liner system constructed of a thick, high density, 60 millimeter polyethylene membrane, applied to both the bottom and sides of the landfill. Below-grade portions of the landfill will be lined completely. A layer of geotextile material is placed between the synthetic liner and clay layer to act as a cushion against stresses on the liner. The liner will be constructed in 30 foot wide strips with welded seams, every inch of which is vacuum tested. Laboratory testing is also conducted on sample coupons of welded seams to insure that the seams are as strong, or stronger, than the original material, and the areas from which coupons are taken are then extrusion welded and vacuum tested. The liner system is designed to withstand stresses, and any differential settlement, that are reasonably expected to occur at this site. It will minimize the risk of leakage of leachate to the environment, as was recognized by Dr. Richard Strom, an expert in hydrogeology called by Petitioners, who stated this is an improvement in the previous unlined operations at this site, and decreases, although it does not completely eliminate, the possibility of ground water pollution. The applicant's project design includes a leachate collection system which will allow leachate generated in the landfill to flow through a 12 inch thick gravel layer, which will act as a drain in the base of the landfill. Fluids will run to low spots and will then be channeled to sumps, where leachate is collected so that it can be disposed of by pumping away from the liner system and spraying onto the active face of the landfill. Natural evapotransporation will then reduce the volume of the leachate. An approved groundwater monitoring program is currently in place, and is being operated at the applicant's existing landfill. It consists of an upgradient well in the northeast corner of the site, and three down gradient wells, one in the southwest corner, one on the west and one on the south sides of the property. These down gradient wells are adequately placed to intercept groundwater flow from the site since the predominate groundwater flow is from the northeast to southwest. These wells all monitor the Floridan Aquifer. The applicant's groundwater monitoring program is adequate and appropriate to detect any leachate or other contaminates emanating from the landfill which might pollute the groundwater, and provides reasonable assurance that water quality standards will not be violated by the landfill operations. The applicant has proposed a stormwater management system for the entire site which is designed to separate non- contact stormwater from that water which actually falls on, or comes into contact with, the waste material. All rainwater coming in contact with waste will be treated as leachate, and handled through the leachate collection system. The non-contact stormwater will be collected in a series of bermed drainage ditches around the site, and will be drained away to retention ponds for infiltration. During times of normal rainfall, there will be sufficient capacity in retention ponds to store all non- contact stormwater on site until it either evaporates or percolates into the ground. During extreme storm events, excess stormwater can be channeled off site to a nearby sinkhole for discharge. Routine monitoring will be conducted to ensure that water in the system has not been contaminated with leachate. The Department has delegated stormwater plan approval authority to the Southwest Florida Water Management District, which reviewed and approved the applicant's stormwater management system through the issuance of a permit in 1988. Noxious odors do not emanate from the existing landfill operations, although there is a slight odor similar to an auto garage service bay close to the disposal materials. This is not a sickening or noxious odor, as acknowledged even by Dr. Strom. The applicant has provided reasonable assurance that leachate sprayed on the active face of the landfill, after having been collected through the leachate collection system, will not result in, or cause, noxious odors at the landfill site. The applicant has established that this project to enlarge its existing landfill with a lined addition will not release contaminants into the underlying soils and groundwater.

Recommendation Based upon the foregoing, it is recommended that the Department of Environmental regulation enter a Final Order approving the application of the David J. Joseph Company and issuing permit number S029-77041. DONE AND ENTERED this 21st day of June, 1989 in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 21st day of June, 1989. APPENDIX (DOAH Case No. 88-6009) Rulings on the Petitioners' Proposed Findings of Fact: Rejected in Findings 1, 9-12. Rejected in Findings 10-14. Rejected in Finding 16. Rejected in Finding 16, but Adopted in part in Finding 13. Rejected in Findings 10-12. Rejected in Finding 15. Rejected in Finding 14. Rulings on the Respondents' Proposed Findings of Fact: 1. Adopted in Findings 1, 2. 2-3. Adopted in Finding 3. Adopted in Finding 4. Adopted in Finding 5. Adopted in Finding 6. 7-8. Adopted in Finding 1. 9-10. Adopted in Finding 7. 11. Adopted in Finding 8. 12-15. Adopted in Findings 9-11. Adopted in Finding 12. Adopted in Finding 9. Adopted in Finding 13. 19-21. Adopted in Finding 14. Adopted in Finding 15. Adopted in Findings 9 and 16. Adopted in Finding 17. COPIES FURNISHED: John W. Wilcox, Esquire Katherine Harasz, Esquire 100 South Ashley Drive Suite 1650 Tampa, FL 33602 William D. Preston, Esquire Thomas M. DeRose, Esquire 123 South Calhoun Street Tallahassee, FL 32301 Richard T. Donelan, Jr., Esquire Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Dale Twatchmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esquire General Counsel 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57403.087403.707
# 2
FLORIDA AUDUBON SOCIETY, TROPICAL AUDUBON SOCIETY vs. CITY OF NORTH MIAMI, MUNISPORT, INC., AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000316 (1978)
Division of Administrative Hearings, Florida Number: 78-000316 Latest Update: May 31, 1979

The Issue Whether permit application SWO 13-5152, should be granted under Chapter 403, Florida Statutes. This case involves the application of Respondents City of North Miami and Munisport, Inc. to Respondent Department of Environmental Regulation (DER) for an operating permit under the provisions of Chapter 403, Florida Statutes, and Chapter 17-7, Florida Administrative Code, to operate a sanitary landfill located in North Miami, Florida. DER granted provisional approval of the application by the issuance of a Notice of Intent to issue the permit on January 27, 1978. Petitioners filed the instant petition of February 13, 1978, challenging the issuance of the proposed permit. Final hearing herein was originally scheduled for April 7, 1978, but at the instance of the parties was continued and reset to commence on October 18, 1978. During the course of the final hearing, 29 witnesses presented testimony, including six public witnesses. (List of public witnesses - Hearing Officer's Exhibit 3) A total of 35 exhibits were admitted in evidence. Three exhibits (Exhibits 5, 13 and 15) were rejected by the Hearing Officer.

Findings Of Fact By application dated November 14, 1977, Respondent City of North Miami, Florida, as owner, and Respondent Munisport, Inc. as the "responsible operating authority" requested Respondent DER to issue a permit to operate a solid waste resource recovery and management facility consisting of 345.90 acres located at 14301 Biscayne Boulevard, North Miami, Florida. The site, known as the North Miami Recreation Development, had been operating as a sanitary landfill under temporary operating permits (TOP) issued by the DER on May 8, 1975 and September 21, 1976. The 1976 TOP provided for an expiration date of July 1, 1977, and contained various conditions designed to give the permittees a reasonable period of time to conform to the DER regulations relative to sanitary landfills. These included standard requirements such as the rendering of reports on the operation of the facility and prohibiting the deposit of raw and infectious waste, or hazardous waste that had not been rendered safe and sanitary prior to delivery. Additionally, the permit conditions required the facility to be so operated that it would cause minimum adverse effects on the environment, such as objectionable odors, contaminated storm water runoff, or leachates causing degradation of surface of ground waters. Further, the permit provided for a three-month review program after its issuance to consider the feasibility of dumping solid waste in 63 acres of submerged land subject to previous filling with clean fill and/or construction debris, filling of land above mean high water with garbage either above clean fill or above trenches filled with wood and construction debris and covered with clean fill, and a six-week period of weekly water quality monitoring at agreed to sites for analysis by both permittees and the Dade County Environmental Resources Management (DERM). The permit further prohibited the placement of refuse waterward of the mean high water line or in trenches cut below the natural ground water table. (Exhibits 1, 4). By letter of January 27, 1978, DER gave notice to the applicant of its intent to issue the requested operation permit for the solid waste disposal facility and stated therein the following reasons for its determination: The solid waste disposal site is in the public interest. The Department feels that the site will not substantially affect the water quality or interfere with the area's wildlife. The applications and plans for this facility have been evaluated and found to be in conformance with Chapter 403, F.S., Chapter 17-4, FAC, and Chapter 17-7, FAC. The letter stated standard conditions to which the permit would be subject, including special conditions that had been noted in the 1976 TOP. It also prescribed specific conditions that no solid wastes could be placed within 30 feet of any existing or future lake area, no dumping below water at any time nor in any dewatered excavations, and that a quarterly water quality monitoring program at monitoring wells No. 4 through 12 be sampled for specified substances. Proposed Condition 16 stated as follows: Solid waste shall be deposited in locations consistent with those approved in the Army Corps of Engineers' dredge and fill permit #75B-0869. No solid waste shall be deposited in the areas commonly known as the wetlands and transitional zones of said wetlands, as shown on the attached map. Subject to the Corps approval of proposed modifications to permit #75B-0869, a revised DER solid waste permit will be issued consistent with the approved modifications. A sketch of the landfill site purporting to designate the landfill deposal area, wetlands and transitional zone, and mean high water line was attached. (Exhibit 3) The Petitioners consist of the Florida Audubon Society, which has some 2,000 members residing in Dade County, Tropical Audubon Society, which is affiliated with Florida Audubon Society; Keystone Point Homeowners Association, Inc., comprised of approximately 425 owners of mostly waterfront or canal homes in North Miami within a mile of the landfill site; Thomas Pafford, North Miami, Florida, who uses the waters of Biscayne Bay and nearby wetlands for recreational purposes; and Maureen B. Harwitz, who resides within a half mile of the landfill site and uses Biscayne Bay and the mangrove preserve adjacent to the landfill site for recreational purposes. Members of the above-named organizational groups use the waters surrounding the landfill site for recreational purposes and are concerned that the waters and fish and animal life therein will be adversely affected if the operation permit is granted. (Testimony of Lee, Brown, Pafford, Lippelman, Harwitz) Munisport has been operating the North Miami landfill under a lease with the City of North Miami since approximately 1974. The ultimate aim is to convert the area into a recreational complex consisting of golf courses, club house, and other sports facilities. The site was used as an unregulated dump for many years prior to initiation of the Munisport operation. The site has been the subject of previously issued state and Corps of Engineer dredge and fill permits which are not the subject of this proceeding. The landfill site occupies an area generally between Northwest 135th Street on the south and Northwest 151st Street on the north. It lies between Biscayne Boulevard on the west, and state mangrove preserves and land of Florida International University on the east. It is less than a mile to Biscayne Bay on the east side of the landfill. The nearest point of entry is in the southeast area where Arch Creek empties into the Bay. At this time, Munisport has filled approximately 210 acres at the site with ten feet or more of fill material. A final cover has been completed over about 70 acres of this land and a golf course is presently being constructed. Pursuant to the dredge and fill permits, five lakes approximately 35 feet deep are nearly completed and some six or seven more are to be dug in the future pursuant to those permits. These lakes are separated from the solid waste by a 30 foot wide dike of clean fill. Although some cover material has been trucked to the site, about 1.6 million cubic yards of fill from the excavated lakes have been or will be utilized in cover operations for the landfill. The solid waste layer averages 15 feet in depth and lies about two feet above the ground water table. About 230 acres lie within the upland fill area above the mean high water line which is not within the area of jurisdiction of the Army Corps of Engineers. The mean high water line has been established by appropriate procedures under Chapter 177, F.S., and the surveying procedures were approved by the Department of Natural Resources on April 6, 1978. Although not stated in the Notice of Intent to issue the requested permit, DER intends to restrict the life of any permit to the time when the Metropolitan Dade County Resources Recovery Facility commences operation in approximately two years. The applicants and Dade County also have a memorandum of understanding to this effect. (Testimony of Stotts, Checca, Exhibits 1, 2, 35, 36, Hearing Officer's Exhibit 1) Munisport receives solid waste from a variety of firms, institutions, and surrounding municipalities. Its procedures are for vehicles to enter and exit the site from an access road leading to Biscayne Boulevard. A sign is located along the road indicating the operating hours, fee schedule, waste restrictions and other pertinent information. A large portion of the site is virtually inaccessible due to dense mangroves and mosquito control canals and ditches. At the check-in gate, a cursory inspection of vehicle loads is made by Munisport personnel who check the contents for quantity. Each load is directed to a designated place at the site where Munisport employees spread and compact the waste. At this stage, they are instructed to look for any unauthorized materials, such as hazardous and infectious waste. If such wasted is found, the offending party is required to remove it from the site. compactors and bulldozers push the solid waste to the face of the landfill and spread it out to facilitate compaction. During the hours of 6:00 P.M. to 6:00 A.M., a watchman is on duty at the site to accommodate customers. If less than four or five truckloads arrive during the night hours, the material is not processed. If a larger quantity is involved, a Munisport employee moves and covers the material prior to the following workday. Due to the high ground water tabled, the area method is used for filling the site. This is a procedure by which refuse cells are constructed in lifts not to exceed ten feet in vertical height. They are composed of cells which constitute a one-day quantity of refuse. Six inches minimum cover of clean fill is applied daily, and a one foot intermediate cover is applied within a year after compaction. The cells are compacted in two-foot layers and, upon completion of a particular area, a minimum of two feet of final cover is applied. A dike constructed of compacted limerock borders the east side of the site and basically constitutes the present mean high water line. It is designed to protect the adjoining 129 acres of mangrove preserve and Biscayne Bay from any adverse water quality which might occur from runoff of degraded waters from the landfill site in the event of contamination. (Testimony of Haddad, Checca, Exhibit 1, 9) The shallow soil underlying the landfill at depths ranging to almost ten feet consists of a combination of organic matter and debris from prior dump use, muck, and sand. Soil borings taken at the site show that limestone or calcareous rock known as Miami oolite is about eight feet below the soil layer. At this depth is found the Biscayne aquifer that carries the unconfined ground water in the area. The aquifer is approximately 160 feet deep under the site and constitutes the major source of water supply in Dade County. The gradient of the water table for the landfill site runs in a southeasterly direction toward Biscayne Bay. Approximately 75% of the surface soil layer consists of organic muck, whereas in approximately 25% of the area, which was previously filled in the southern and westerly portions before commencement of the Munisport operation, the soil is primarily of a sandy type. (Testimony of Checca, Pitt, Exhibit 1) Leachate is produced in sanitary landfills by precipitation that percolates down through decomposing refuse cells and picks up polluting substances created from the decaying solid waste. It can form a "plume" or "bubble" that takes the course of least resistance in flowing laterally or vertically through a landfill site. The strength and concentration of the leachate is dependent upon various factors including the composition, compaction, and the age of decomposing refuse, and the amount of water being introduced into the area. As it passes slowly through the soil beneath the solid waste material, the unsaturated soils act as filters and permit ion exchange which reduces the quantity of contaminants. Dilution takes place where leachate comes in contact with ground water and leachate movement occurs gradually through the ground water aquifer in its direction of the flow. The presence and movement of leachate normally can be detected by analysis of ground water samples taken at various places throughout the landfill site. (Testimony of Checca, Pitt, Coker, Exhibit 1) Commencing in 1975, a monitoring program was instituted at the sanitary landfill to determine its effects on the ground water regime. A number of monitoring wells at various depths were constructed at different sites at the landfill, and samples were withdrawn and evaluated periodically to determine the types and degrees of pollution being generated by the landfill. Background samples were also obtained from wells off the site to establish the general character of water quality in the area and to compare these samples with those obtained from the site. Additionally, "grab" samples were taken of water from the bay and nearby canals and wetlands. Locations of the background and sampling wells were established by the applicants in conjunction with the DER and the Environmental Protection Agency. To determine the amount of leachate that probably would be generated at the site, the "water balance method" of computing the estimated time required to produce leachate, as well as the quantity that probably would be generated upon completion of the landfill, was made by representatives of the EPA in 1975 utilizing specific climatological and surface conditions at the site. This study indicated that percolation of surface water would increase during the operation of the landfill and before final soil and vegetative cover were in place, and that leachate would occur in about a year in larger quantities than would be produced by a completed landfill. Tests conducted during the ensuing three-year period of both surface and ground water through the monitoring program have failed to produce evidence that water quality is not within acceptable parameters or that water quality in the area surrounding the landfill site has been degraded. No significant differences in the concentrations of various ground water constituents were found between samples obtained at the disposal site and those collected in the adjacent mangrove forest or background areas. Neither was any evidence of contamination from leachate found in samples of surface water collected in the vicinity of the landfill or in nearby natural areas. (Testimony of Checca, Pitt, Linett, Perez, Exhibit 1, Exhibit 33) Three basic factors have undoubtedly accomplished reduction in the amount of leachate generated at the landfill. These are (a) attenuation and filtration of pollutants by unsaturated soils between and beneath the refuse cells, (b) biological assimilation by organisms living within the refuse cells and underlying soils, and (c) dilution upon contact with the ground water. A hydrogeologic study shows that the uppermost 14 feet of the aquifer immediately below the landfill represents only 0.2% of the total discharges with a ground water velocity of less than 0.1 foot per day. This part of the aquifer therefore provides considerable detention time for the water that percolates through the landfill. The strata, as well as the overlying organic marine soils, provide the absorption and assimilation that removes pollutants from the water. After water percolates through this layer, it reaches the highly permeable Miami oolite that carries about 43% of the ground water flow. The effects of soil absorption, filtration through the upper 14 feet of the aquifer, and dilution within the aquifer have demonstrably been sufficient to assimilate the water that percolates through the landfill. It is estimated that the time of travel of ground water from the landfill site to the closest discharge point in Biscayne Bay is approximately 68 years. Although the attenuation capability of the organic muck soil underlying the greater part of the landfill is high, the older area of the site in the southwestern portion which had been filled before the Munisport operation commenced, has no muck and consists primarily of sand with a higher rate of permeability. (Testimony of Checca, Pitt, Teas, Exhibits 1, 33) The fact that the organic muck material under the landfill is not uniform throughout the site, plus the fact that there have been various breaches in the permeable oolite layer below the soil, will, in the opinion of some experts, eventually lead to the generation and movement of a leachate plume into such breaches and ultimately to Biscayne Bay. These breaches consist of the deep lakes at the site, the Arch Creek Canal to the south of the site and a dredged excavation at the exit of that body of water into the bay some 3,600 feet distant from the landfill. Additionally, these experts postulate that the dike located on the eastern border of the site will not prevent leachate from moving into the surrounding mangrove area. It is therefore estimated that in the above ways, large amounts of leachate would enter the bay and adjacent wetlands within a period of five to ten years. (Testimony of Coker, Hudson, Pasley, Browder, Exhibits 12, 14, 29, 30) Although water monitoring at various levels in and at probable discharge points near the site have not found degradation of water quality, the applicants propose to address any future leachate problems in a variety of ways. These include continuous periodic testing of water quality and monitoring wells, excavation of a canal on the upland side of the site to intercept leachate and treatment of any contaminated water therein or by pumping the water to an interior lake for treatment. Based on the particular type of any degradation, chlorination and precipitators would be utilized. Long-range problems will be further reduced by the ultimate construction of the golf courses and placement of final soil and vegetative cover to reduce percolation of surface water. This will be aggravated to an undetermined degree, however, by periodic irrigation of the golf courses. (Testimony of Checca, Pitt, Kelman, Exhibits 1,33) During the early years of the Munisport operation, a number of violations of the conditions of the temporary operating permit occurred, but for the most part these were caused either through simple negligence of landfill personnel, breakdown of equipment, or introduction of unauthorized materials to the site by Munisport customers. In these situations, Munisport usually took prompt and effective action to prevent recurrence and to remedy the problem. For example, on one occasion in 1977, some 12 drums containing residue of a chemical substance deemed to constitute "hazardous waste" was brought into the site by persons unknown and was found leaking into the ground. A number of violations and warning notices were issued to Munisport by the Dade County Department of Environmental Resources Management (DERM), primarily in 1976, involving the placement of tree cuttings and wood scraps into excavations containing water at the south end of the site. These occurred, however, during a period when Munisport was engaging in tests to determine the suitability of such operations in conjunction with DER. Additionally, in 1976 and 1977, Munisport was advised of violations in the placement of garbage in exposed water, uncovered garbage, and delivery of garbage after hours. Munisport has had a continuing problem over the years with the unauthorized delivery of hospital wastes from various customers to the landfill in spite of letters written to hospital facilities and delivery firms cautioning them concerning the prohibition against the introduction of such material to the landfill. DERM personnel concede, however, that the operation has been continuously improved and that it is well-conducted in comparison with other landfills in the country. However, they believe that lakes should not exist in landfills and that the North Miami landfill is too close to the wetlands. (Testimony of Morrissey, Karafel, Sobrino, Haddad, Checca, Exhibits 6-11, 17, 18, 20-24, 27, supplemented by testimony of Pafford and Exhibit 16) In a letter of January 17, 1977, DERM expressed concerns about the Munisport operation to DER. One of these concerns was that leachate would migrate to proposed golf course lakes and the resulting pollution would produce poor water quality. Although 1976 testing of then existing lakes at the site reflected unusually high amounts of fecal coliform, subsequent tests in late 1978 showed very little, but tests again in January, 1979, showed that several lakes were again somewhat high in coliform. Coliform is not considered to be a strong parameter in assessing the presence of leachate and amounts vary considerably from day to day in lake areas. Additionally, great numbers of birds are normally present on the landfill site during operations and contribute in raising coliform readings to some extent. Dade County has a current policy that does not permit lakes to be excavated on landfills operated by the county. (Testimony of Checca, Morrissey, Sobrino, Karafel, Kosakowski, Linett, Newman, Kelman, Perez, Exhibits 17, 19, 20, 24, 25, 31, 32, 37, 38)

Recommendation That a permit be issued to the City of North Miami, Florida and Munisport, Inc. to operate the solid waste disposal facility as described and under the conditions stated in the letter of the Department of Environmental Regulation, dated January 27, 1978, wherein it gave notice of its intent to issue the said permit. DONE and ENTERED, this 13th day of April, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: David Gluckman, Esquire 5305 Isabelle Drive Ken VanAssenderp, Esquire Tallahassee, Florida Smith, Young and Blue, P.A. Post Office Box 1833 Josepy D. Fleming, Esquire 620 Ingraham Building Marvin Sadur and 25 Southeast Second Avenue Richard J. Potash, Esquires Miami, Florida 33131 2000 L Street NW - Suite 612 Washington, D.C. 20036 Silvia Alderman, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (3) 403.703403.707403.708
# 3
RAYMOND AND IRENE MACKAY vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 84-002897 (1984)
Division of Administrative Hearings, Florida Number: 84-002897 Latest Update: Jul. 26, 1985

Findings Of Fact Description of Proposed Fill Project DER proposes to deny three alternative proposals to fill all or part of Petitioners' real property located in Key West, Florida. The property is rectangular, approximately three acres in size, with 300 feet bordering Roosevelt Boulevard (High-Way A1A) to the south and approximately 300 feet bordering Key West International Airport to the north. The easterly property line is 489.4 feet and the westerly line is 434.63 feet. The Straits of Florida (Atlantic Ocean) are immediately on the other side of Roosevelt Boulevard to the south. The property has a strip of approximately 90 feet of upland and transitional wetland adjacent to Roosevelt Boulevard, with the rest of the property being covered by a salt pond of approximately 40 acres in size (Jnt. Ex. 1). Petitioners initially submitted a permit application in July, 1983, to fill the entire property for construction of multifamily housing units. On May 4, 1984, after discussion with a DER permitting official, Petitioners submitted a second application containing two alternative, less extensive development proposals. The first alternative involves the placement of fill over a 300' x 230' area (approximately 9722 cubic yards) extending 230 feet from the property along Roosevelt Boulevard out into the water. This alternative would entail construction of 24 family housing units, consisting of six basic structures, each four-stories high. The second alternative involves subdividing the property into six separate lots connected by a central fill road with cul-de- sac. Each lot, approximately .4 acres in size, would contain a single family house on pilings and an associated fill pad for parking. The fill pads would be connected to a approximately 300' x 30' entrance road constructed on fill material. Presumably, this second alternative would contain the same amount of total fill as required in the first. As it presently exists, the salt pond (a part of which applicant would fill) serves several significant and beneficial environmental functions. In regard to water quality, the pond stores, filters, and purifies large quantities of storm water which drain from the airport and South Roosevelt Boulevard. The filling of any portion of this pond would diminish this capacity. (Jnt. Ex. 1) Because of their relatively isolated nature, the organic detrital material that is produced from the leaf litter of fringing mangroves is broken down into a very fine and readily usable form by bacteria. As a result, when there is an occasional exchange between the salt pond and tidal waters, the exported organics are in a very desirable form for higher trophic levels in the food web such as small fish, crustaceans, filter feeders, and various larval forms of marine life. (Jnt. Ex. 1) The salt pond proper provides valuable habitat for fish and wildlife, most notable of which are avifauna. The pond has apparently become established as a healthy, self-sustaining ecosystem providing permanent and temporary food, shelter and refuge for many faunal species which play significant and necessary ecological roles both in the salt ponds and other tidal and brackish water systems. (Jnt. Ex. 1) Through the placement of fill and the displacement of present salt pond habitat, water quality and the biological resources in the immediate and surrounding areas would be expected to undergo degradation. (Jnt. Ex. 1) Through the encroachment of development in this area, which presently lacks residential development, biological integrity standards would be expected to fall below acceptable levels. The proposed fill areas would reduce wind- driven circulation in the pond so as to stress levels of oxygen, salinity, temperature and turbidity. Runoff from the proposed fill would introduce nutrients and elevate turbidity during storm events. Finally, elevated turbidity levels could be expected during the actual filling process and the various species of fish and wildlife now located over the project site would be temporarily disturbed by construction activities and permanently displaced in the long term through the loss of habitat. (Jnt. Ex. 1) There is a 40' zoning setback and another 50' easement owned by the City of Key West, which together form a 90' strip on the property adjacent to Roosevelt Boulevard. This 90-foot strip is largely upland and some transitional wetland. There is no zoning impediment to any of the development alternatives proposed by Petitioners. The property is currently zoned R2H (multifamily residential) by the City of Key West. II. DER's Action on the Application After DER received and reviewed Petitioners initial application on July 22, 1983, a completeness summary was sent on August 17, 1983, requesting additional information. DER received the additional information on March 23, 1984, after which it notified Petitioners that additional information was needed. Petitioners met with DER officials on April 20, 1984, and submitted additional information on May 4, 1984, including the two alternative proposals. DER issued the "Intent to Deny" all three of the proposed projects on July 19, 1984 (Jnt. Ex. 1). On May 16, 1984, a DER Environmental Specialist visited the site of the proposed projects and conducted a biological and water quality assessment. This assessment was later submitted, in report form, as the Permit Application Appraisal, dated June 7, 1984. This appraisal, uncontested by Petitioners, indicates that each of the three fill proposals would take place in waters of the state and result in water quality violations under Rules 17-3.051(1), 17- 3.061(2)(c), (j) and (r); 17-3.121(7), (13) and (28); Chapter 17-4, Florida Administrative Code; and Chapter 403, Florida Statutes. Water quality problems associated with the project were identified as diminished storm water treatment, reduced beneficial deterital material, stress on oxygen levels, salinity, temperature, and turbidity, and an introduction of nutrients. (Jnt. Ex. 1) Although a DER dredge and fill permitting official testified that any filling of the salt pond would be detrimental to the birds and animals which feed there on a daily basis, and that, in his view, a "substantial amount" of filling would not be allowed by DER, there are development projects (other than the three presented by Petitioners) which, in his view, may qualify for a permit under DER rules. DER has, in the past, issued permits authorizing the construction of above-ground residences over wetland properties. Under DER's permitting standards, one or more single-family residences could be built on the property if the structures were built on stilts, did not violate water quality standards, had acceptable drainage, and did not result in adverse storm water discharges. In evaluating such an application, any mitigation an applicant could provide, such as enhancing flushing in the salt ponds by the installation of a culvert to open water, would be balanced against any adverse impacts expected from the filling activity. The three alternative filling proposals submitted by Petitioners (including drawings and designs) do not, however as yet, fall within or satisfy these general perimeters of permitting acceptability.

Recommendation Based on the foregoing, it is RECOMMENDED: That Petitioners' application to fill (containing three alternative proposals) be denied for failure to prove compliance with applicable permitting standards contained in Chapter 403, Florida Statutes, and Chapters 17-3 and 17- 4, Florida Administrative Code. DONE and ORDERED this 26th day of July, 1985, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of July, 1985.

Florida Laws (3) 120.57403.087403.90
# 4
JOHN L. SULLIVAN, JR. vs T. L. C. PROPERTIES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 91-000282 (1991)
Division of Administrative Hearings, Florida Filed:Panama City, Florida Jan. 14, 1991 Number: 91-000282 Latest Update: Jun. 10, 1991

The Issue Whether petitioner has standing to challenge a consent order negotiated by respondents to resolve an enforcement proceeding? If so, whether the consent order comports with statutes and rules regulating dredging and filling in wetlands?

Findings Of Fact Without securing DER permits, TLC built two dirt roads, one perpendicular to the other, both in Gulf County, east and south of property petitioner John L. Sullivan, Jr. owns and lives on. Between them, the roads, each 20 to 25 feet wide, traversed wetlands (recognized as such by DER regulations and the DER environmental specialist when he visited the site in May of 1990) in three separate places. None of the affected wetlands drain in the direction of petitioner's property. TLC dredged and placed 36-inch culverts before filling at two of the sites, and placed fill at all three sites, constructing roadbed and shoulders. One of the sites, connected by a 200-foot ditch to other wetlands, DER's Larry Taylor eventually characterized as "isolated." He directed TLC to fill the ditch to destroy the connection, on the theory this would divest DER of jurisdiction. At hearing, John L. Sullivan, Jr. testified that the project had not affected him financially, and said he was affected only as a citizen of Florida. The wetlands crossed by the roads drain (or, in one instance, did drain before the ditch was filled) easterly to Stonemill Creek, which flows southeasterly toward the Dead Lakes.

Recommendation It is, accordingly, recommended that DER dismiss the letter or petition with which these formal administrative proceedings began. RECOMMENDED this 10th day of June, 1991, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of June, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 91-0282 Petitioner's proposed finding of fact No. 1 has been adopted in substance. Petitioner's proposed findings of fact Nos. 2 and 3 pertain to immaterial matters. Petitioner's proposed finding of fact No. 4 was not proven. Respondent's proposed findings of fact Nos. 1, 2, 5, 6 and 10 (i.e. the final proposed finding of fact) have been adopted, in substance, insofar as material. With respect to respondent's proposed finding of fact No. 3, a parcel 96 feet by 60 feet was involved at only one of the three sites. With respect to respondent's proposed finding of fact No. 4, the conclusion that "the jurisdictional aspect ceased to exist" is not adopted. With respect to respondent's proposed finding of fact No. 7, whether the violation was "resolved" is a conclusion of law. With respect to respondent's proposed finding of fact No. 8, the allegations of the petition were not proven. With respect to respondent's proposed finding of fact No. 9, not all uncontradicted evidence has been credited. COPIES FURNISHED: Carol Browner, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 John L. Sullivan, Jr. Post Office Box 1298 Wewahitchka, FL 32465 Richard L. Windsor, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Bill R. Hutto, Esquire Hutto, Nabors, Bodiford and Warren 101 East 23rd Street Panama City, FL 32405

Florida Laws (2) 120.57403.412
# 5
DEPARTMENT OF ENVIRONMENTAL PROTECTION vs SOUTH PALAFOX PROPERTIES, LLC, 14-003674 (2014)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida Aug. 12, 2014 Number: 14-003674 Latest Update: Jan. 15, 2016

The Issue The issue is whether Respondent's Construction and Demolition Debris Disposal Facility Permit No. 003397-013-SO (the Permit) should be revoked and the facility closed for the reasons stated in the Department of Environmental Protection's (Department's) Notice of Revocation (Notice) issued on July 31, 2014.

Findings Of Fact A. The Parties, the Property, and the Dispute The Department administers and enforces the provisions of chapter 403 and the rules promulgated thereunder, including those applicable to construction and demolition debris (C & D) disposal facilities. Respondent is a Florida limited liability corporation that owns real property located at 6990 Rolling Hills Road, Pensacola, Escambia County (County), Florida. The large, odd- shaped parcel (whose exact size is unknown) is south-southwest of the intersection of Interstate 10 and Pensacola Boulevard (U.S. Highway 29) and has Class III fresh surface waters running in a northeast-southwest direction through the middle of the property. See Resp. Ex. 28. The entire site is surrounded by a six-foot tall fence or is separated from adjoining properties by natural barriers. A railroad track borders on the eastern side of the parcel; the western boundary fronts on Rolling Hills Road; and the northern boundary appears to be just south of West Pinestead Road. Id. The area immediately south of the parcel appears to be largely undeveloped. See Dept. Ex. 40. The Emerald Coast Utilities Authority (ECUA), a local government body, has an easement that runs along the eastern side of the property adjacent to the railroad track on which a 48-inch sewer pipe is located. An older residential area, known as Wedgewood, is located northeast of the facility on the north side of West Pinestead Road. Id. The closest Wedgewood homes appear to be around 400 or 500 feet from the edge of Respondent's property. A community and recreational center, the Marie K. Young Center, also known as the Wedgewood Center, serves the Wedgewood community, is northwest of the facility, and lies around 500 feet from the edge of the property. Established in 2012 where a school once stood, it has more than 200 members. Although non- parties, it is fair to say that the Wedgewood community and County strongly support the Department's efforts to revoke Respondent's permit. Respondent acquired the property in 2007. At that time, an existing C & D disposal facility (the facility) was located on the property operating under a permit issued by the Department. The Permit was renewed in February 2013 and will expire in early 2018. Besides the general and specific conditions, the renewed Permit incorporates the terms and conditions of a Consent Order executed in November 2012, as well as detailed requirements relating to the operation of the facility, water quality monitoring, an odor remediation plan, financial assurance and cost estimates, and closure of the facility. The latter requirements are found in four Appendices attached to the Permit. The facility operates under the name of Rolling Hills Construction and Demolition Recycling Center. All material received by the facility is disposed of in an active disposal pile known as cell 2, located in the middle of the northern section of the parcel. Cell 1, southwest of cell 2 and just east of Rolling Hills Road, was closed a number of years ago by the prior operator. Respondent operates the only C & D facility in the County.1/ It currently serves around 50 to 60 active customers, employs 16 persons, and operates between the hours of 7:00 a.m. and 5:00 p.m. The former manager, Charles Davidson, who had overseen operations since 2010, was replaced in June 2014, and Respondent blames him for ignoring or failing to address most of the problems encountered during the last three years. Since June, the managing partner of the LLC, Scott C. Miller, has overseen the operations. Unlike Class I or III landfills, a C & D landfill may accept only construction and demolition debris. Construction and demolition debris is defined as "discarded materials generally considered to be not water soluble and non-hazardous in nature." § 403.703(6), Fla. Stat.; Fla. Admin. Code R. 62- 701.200(24). Debris includes not only items such as steel, glass, brick, concrete, asphalt material, pipe, gypsum wallboard, and lumber that are typically associated with construction or demolition projects, but also rocks, soils, tree remains, trees, and other vegetative matter that normally result from land clearing or land development operations. Id. No solid waste other than construction and demolition debris may be disposed of at the facility. See Fla. Admin. Code R. 62- 701.730(4)(d). To address and resolve certain violations that predated the renewal of the Permit, the Department and Respondent entered into a Consent Order on November 14, 2012. See Dept. Ex. 2. These violations occurred in 2011 and included the storage and/or disposal of non-C & D debris, and a failure to timely submit an appropriate Remedial Action Plan (RAP). Id. Among other things, the Consent Order required that within a time certain Respondent submit for Department review and approval an RAP; and after its approval to "continue to follow the time frames and requirements of Chapter 62-780, F.A.C." Id. Those requirements included the initiation of an active remediation system and site rehabilitation within a time certain, and the continued monitoring and related corrective action for any water quality violations or impacts. Id. To ensure that it has the financial ability to undertake any required corrective action, the Permit requires Respondent to provide proof of financial assurance for the corrective action program cost estimates. See Fla. Admin. Code 62-701.730(11)(d); § 2, Spec. Cond. F.1. This can be done through a number of mechanisms, such as a performance bond, letter of credit, or cash escrow. The Permit also requires Respondent to provide proof of financial assurance to demonstrate that it has the financial ability to close the facility and otherwise provide for the long-term care cost estimates of the facility. See Fla. Admin. Code R. 62-701.630; § 2, Spec. Cond. F.2. Rather than using a cash escrow or letter of credit, Respondent has chosen to use a performance bond for both requirements. These bonds must be updated annually to include an inflation adjustment. Given the many requirements imposed by the Permit and Consent Order, in 2013 and 2014 several follow-up site inspections of the facility were conducted by the Department, and a review of the operations was made to determine if the various deadlines had been met. Also, in 2014, the Department received complaints from the County and neighboring property owners, almost exclusively by those residing in the Wedgewood community, regarding offensive odors emanating from the facility. Based on field observations, the review of operations, and odor complaints, on July 31, 2014, the Department issued a Notice containing eight counts of wrongdoing. The Notice was issued under section 403.087(7)(b), which authorizes the Department to revoke a permit when it finds the permit holder has "[v]iolated law, department orders, rules, or regulations, or permit conditions." To Respondent's consternation, the Department opted to use that enforcement mechanism rather than initiating an enforcement action under section 403.121 or executing another consent order, both of which would likely result in a sanction less severe than permit revocation.2/ The Notice contains the following charges: exceeding surface water quality standards in rules 62-302.500 and 62- 302.530 (Count I); failing to implement an RAP as required by the Consent Order and Permit (Count II); failing to provide adequate financial assurances for facility closure costs (Count III); failing to provide financial assurances for the corrective action required by the RAP (Count IV); failing to reduce on-site and off-site objectionable odors and to implement a routine odor monitoring program (Count V); disposing non-C & D waste on site (Count VI); failing to remove unauthorized waste (Count VII); and disposing solid waste outside of its permitted (vertical) dimension of 130 feet National Geodetic Vertical Datum (NGVD) (Count VIII). These allegations are discussed separately below. Although the Notice is based on violations that occurred on or before July 31, 2014, the undersigned denied the Department's motion in limine that would preclude Respondent from presenting mitigating evidence concerning circumstances surrounding the violations and efforts to remediate them after July 31, 2014. Given that ruling, the Department was allowed to present evidence to show that Respondent's remediation efforts have not been successful and that some violations still existed as of the date of final hearing. Respondent disputes the allegations and contends that most, if not all, are either untrue, inaccurate, have been remedied, or are in the process of being remedied. As noted above, Respondent considers the revocation of its permit too harsh a penalty in light of its continued efforts to comply with Department rules and enforcement guidelines. It contends that the Department is acting at the behest of the County, which desires to close the facility to satisfy the odor complaints of the Wedgewood residents, and to ultimately use the property for a new road that it intends to build in the future. Count I - Water Quality Violations The Notice alleges that two water quality monitoring reports filed by Respondent reflect that it exceeded surface water quality standards at two monitoring locations (MW-2 and SW-6) sampled on August 26, 2013, and at one monitoring location (MW-2) sampled on March 4, 2014. The Notice alleges that these exceedances constitute a failure to comply with Class III fresh surface water quality standards in rules 62-302.500 and 62- 302.530 and therefore violate conditions in the Permit. These standards apply in areas beyond the edge of the discharge area (or zone of discharge) established by the Permit. To ensure compliance with water quality standards, when the Permit was renewed in 2013, a Water Quality Monitoring Report (Appendix 3) was attached to the Permit. It required Respondent to monitor surface water for contamination, identify the locations at which samples must be collected, and specify the testing parameters. All of these conditions were accepted by Respondent and its consultant(s). The monitoring network, already in place when Respondent purchased the facility, consists of six ground water monitoring wells and three surface water monitoring stations. The surface water stations, which must be sampled to determine compliance with water quality criteria, are SW-5, a background location, and SW-6 and MW-2, both compliance locations located outside the zone of discharge. A background location is placed upstream of an activity in order to determine the quality of the water before any impacts by the activity. A compliance location is placed downstream of an activity to determine any impacts of the facility on surface water. The Water Quality Monitoring Plan and Permit require Respondent to submit semi-annual water quality reports. To conduct the preparation and filing of the reports, Respondent used an outside consulting firm, Enviro Pro Tech, Inc. (EPT). On November 5, 2013, EPT submitted a Second Semi-Annual 2013 report. See Dept. Ex. 5. According to Mr. Miller, who now oversees operations at the facility, EPT did not provide Respondent a copy of the report, or even discuss its findings, before filing it with the Department. A Department engineer reviewed the report and noted that surface water samples exceeded the Class III Fresh Water Quality Standards for iron, copper, lead, zinc, nickel, and mercury at SW-6 and for iron at MW-2. See Dept. Ex. 6. A copy of the Department's report was provided to Respondent and EPT. Notably, the report indicated that background levels were lower than the down-gradient results. Under Department protocol, if the samples at the compliance locations exceed both the regulatory levels and the background, there is a violation of water quality standards. This accepted protocol differs from Respondent's suggested protocol that the background level should be added to the regulatory standard before a comparison with the sample results is made. In sum, except for the reported nickel value at SW-6, a violation which the Department now says it will not pursue, all exceedances shown on Department Exhibits 5 and 6 are violations of the standards. On April 1, 2014, EPT submitted a First Semi-Annual 2014 report. See Dept. Ex. 7. A Department engineer reviewed the report and noted that the surface water samples at one monitoring location, MW-2, did not meet water quality standards for iron; however, background levels for iron were much higher than downstream. See Dept. Ex. 8. No other exceedances were shown. Although the Department engineer considered the higher background level for iron to be an "inconsistency" since it varied from the prior reports, the reported iron value was treated as a violation when the Notice was drafted. In its PRO, however, the Department concedes that it did not establish a violation of standards for iron, as alleged in paragraph 7 of the Notice. While having no concerns with sampling taken at MW-2, Respondent's expert contends that the reported values for SW-6 are unreliable because the samples taken from that location were turbid and filled with large amounts of suspended solid matter. He noted that the well is located in a wetland area that is "clogged with vegetation." The expert estimated the turbidity at the site to be in the range of 480 to 500 Nephelometric Turbidity Units (NTUs) and believes the sample was taken in a "high turbid sediment laden area," thus rendering it unreliable. However, at the time of the sample collection, turbidity was measured at 164 NTUs, or much less than the amount estimated by the expert. See Dept. Ex. 5, p. 147. There is no rule or procedure that disallows the use of turbid samples. In fact, they can be representative of actual water quality. Also, rule 62-302.500(2)(d) provides that if an applicant for a C & D permit believes that turbid samples are not representative of water quality, it may use filtered samples by establishing a "translator" during the permitting process. Respondent did not request a translator during the permitting process, nor is any such translator provision found in the Permit. The expert also criticized EPT for holding the 2013 sample for iron for 22 days after collection before reanalyzing it without providing any explanation for this delay. A reasonable inference to draw from the data, however, is that iron was present in the original sample at levels that required dilution and reanalysis. Respondent's expert testified that even though off- site stormwater is discharged onto the property, no offsite monitoring locations exist, and therefore any offsite exceedances would not be reported. He also criticized the sampling locations that were selected by EPT. In fairness to Respondent, a repositioning of the monitoring network and retesting of the samples might have produced more favorable results. But these are measures that should have been addressed long before this proceeding was initiated. Finally, Respondent's expert testified that the implementation of its RAP, now partially completed, will cure all of the reported exceedances. Assuming this unrefuted testimony is true, it should be taken into account in determining an appropriate penalty. Count II - Failure to Implement an RAP In this Count, the Department alleges that after the issuance of an RAP Approval Order on July 3, 2013, Respondent was required to implement the RAP within 120 days. The Notice alleges that as of July 31, 2014, the RAP had not been implemented. An RAP was first filed by Respondent on November 15, 2010. See Dept. Ex. 3. When the Department determined that changes to the RAP were necessary, the Consent Order imposed a requirement that an RAP addendum be filed within 150 days. The date on which the addendum was filed is not known. However, an RAP Approval Order was issued on July 3, 2013. See Dept. Ex. 4. The terms and conditions in the RAP were incorporated into the renewed Permit. The work required by the RAP consists of two phases, with all work to be completed within 365 days, or by early July 2014. Phase I related to the initiation of an active remediation system within 120 days, or by October 31, 2013. This phase requires Respondent to install a pump and treat system at the facility, which will withdraw contaminated groundwater through recovery wells, pump the water to aeration basins to treat the water, and then re-infiltrate the treated water back into the ground. As noted below, the system was not operational until the second week in December 2014. Respondent's failure to implement the approved RAP by the established deadline constitutes a violation of rules 62- 780.700(11) and 62-780.790 and Permit conditions, as charged in the Notice. While Respondent concedes that it did not comply with the deadline for implementing the RAP, it points out that work on Phase I was begun in a timely manner. However, on October 16, 2013, or just before the 120 days had run, a Notice of Violation was issued by the County. See Resp. Ex. 2. The effect of the Notice of Violation was to halt much of the work on Phase I until Respondent obtained a County stormwater permit. Respondent asserts that this was responsible for all, or most, of the delay. The record shows that the EPT consultant did not apply for the County permit until September 10, 2014, or almost one year after the Notice of Violation was issued. Additional information was required by the County, which was supplied on October 23, 2014, but final sealed documents were not filed by the consultant until around Thanksgiving. The permit was issued by the County "a week or so" before the final hearing. Respondent attributes the delay in applying for a County permit to its former manager and his failure to coordinate with the EPT engineers assigned to the project. It also claims that the County failed to process the application in an expeditious fashion. However, the facts suggest otherwise. Once the permit was issued, Phase I was completed on December 8, 2014, and it was operational at the time of the final hearing. Respondent's expert, hired in August 2014, has proposed a modification to the RAP that would avoid impacting the existing stormwater pond. However, the modification must be reviewed and approved by the Department, and as of the date of the hearing, it had not been formally submitted. The Department asserts that the only reason the modification is being sought is to reduce the cost of a performance bond. In any event, in its PRO, Respondent does not argue that the proposed modification excuses its 13-month delay in completing the requirements of Phase I, or the second phase of the project, which should have been completed by early July 2014. Count III - Failure to Provide Financial Assurance This Count alleges that Respondent failed to provide the required annual 2014 financial assurance mechanism that demonstrates proof of financial assurance for closure and long- term cost estimates of the facility. At the beginning of 2014, Respondent had an $836,000.00 financial performance bond in place for closure and long-term costs. The Permit requires that on or before March 1 of each year Respondent revise the closure cost estimates to account for inflation in accordance with rule 62-701.630(4). See § 2, Spec. Cond. F.2. Once the estimates are approved, the performance bond must be updated within 60 days. In this case, an increase of around $18,000.00 was required. The annual inflation adjustment estimate was not submitted until April 15, 2014. The Department approved the cost estimates the following day and established a due date of June 16, 2014, for submitting a revised financial assurance. Respondent did not have a revised performance bond in place until a "week or two" before the hearing. Other than Respondent's manager indicating that he had a new bonding agent, no evidence was presented to mitigate this violation. The failure to timely update its financial assurance for closure and long-term costs constitutes a violation of rule 62-701.630, as charged in the Notice. Count IV - Financial Assurances for Corrective Action In the same vein as Count III, the Notice alleges that Respondent failed to maintain a financial assurance mechanism to demonstrate proof that it can undertake the corrective action program required under the RAP. Respondent was required to submit proof of financial assurance for corrective actions within 120 days after the corrective action remedy was selected. On July 3, 2013, the RAP Approval Order selected the appropriate remedy. On August 8, 2013, the Department approved Respondent's corrective action program cost estimates of $566,325.85 and established a deadline of October 31, 2013, for Respondent to submit this proof. When the Notice was issued, a corrective action bond had not been secured, and none was in place at the time of the final hearing. This constitutes a violation of rule 62-701.730(11)(d) and applicable Permit conditions. Respondent's manager, Mr. Miller, concedes that this requirement has not been met. He testified that he was not aware a new bond was required until he took over management of the facility and met with Department staff on June 17, 2014. Due to the Notice, Mr. Miller says he has had significant difficulty in securing a bond. He explained that the bonding company is extremely reluctant to issue a bond to an entity faced with possible revocation of its permit, especially if such revocation might occur within a matter of months. Mr. Miller says the bonding company wants 100 percent collateralization to put a bond in place. Nonetheless, he is confident that a bond can be secured if only because its cost will dramatically drop when the RAP project is completed. However, even at hearing, he gave no timeline on when this requirement will be fulfilled. Count V - Objectionable Odors One of the driving forces behind the issuance of the Notice is the complaint about off-site objectionable odors. A considerable amount of testimony was devoted to this issue by witnesses representing the Department, County, Wedgewood community, and Respondent. The Notice alleges that during routine inspections in April, May, and July 2014, mainly in response to citizen complaints, Department inspectors detected objectionable odors both at the facility and off-site. The Notice further alleges that Respondent failed to immediately take steps to reduce the odors, submit an odor remediation plan, and implement that plan in violation of rules 62-296.320(2) and 62-701.730(7)(e) and section 2, Specific Condition E of the Permit. Notably, the Department has never revoked a landfill permit due solely to objectionable odors. Several Department rules apply to this Count. First, objectionable odors are defined in rule 62-210.200(200). Second, a C & D facility must control objectionable odors in accordance with rule 62-296.320(2). Finally, if odors are detected off-site, the facility must comply with the requirements of rule 62-701.530(3)(b). That rule provides that once off-site odors have been confirmed, as they were here, the facility must "immediately take steps to reduce the objectionable odors," "submit to the Department for approval an odor remediation plan," and "implement a routine odor monitoring program to determine the timing and extent of any off-site odors, and to evaluate the effectiveness of the odor remediation plan." These same regulatory requirements are embodied in the Permit conditions. See § 2, Spec. Cond. E. At least occasionally, every landfill has objectionable odors emanating from the facility. As one expert noted, "The trick is, how can you treat it." The technical witnesses who addressed this issue agree that the breakdown of drywall, wall board, and gypsum board, all commonly recycled at C & D facilities, will produce hydrogen sulfide, which has a very strong "rotten egg" type smell. The most effective techniques for reducing or eliminating these odors are to spray reactant on the affected areas, place more cover, such as dirt or hydrated lime, on the pile, and have employees routinely patrol the perimeters of the property and the active cell to report any odors that they smell. Although the facility has been accepting waste products for a number of years, the last seven by Respondent, there is no evidence that the Department was aware of any odor complaints before April 2014. While not an active participant in the operations until recently, Mr. Miller also testified that he was unaware of any citizen complaints being reported to the facility prior to that date. However, in response to citizen complaints that more than likely were directed initially to the County, on April 14, 21, and 24, 2014, the Department conducted routine inspections of the facility. During at least one of the visits, objectionable odors were detected both on-site, emanating from cell 2, and off-site on West Pinestead Road, just north of the facility. See Dept. Ex. 14. Because the inspector created a single report for all three visits, he was unsure whether odors were detected on more than one visit. After the inspection report was generated, Department practice was to send a copy by email to the facility's former manager, Mr. Davidson. A Department engineer who accompanied the inspector on at least one visit in April 2014 testified that she has visited the site on several occasions, and on two of those visits, the odor was strong enough to make her physically ill. On a follow-up inspection by the Department on May 22, 2014, the inspector did not detect any objectionable odors. See Dept. Ex. 17. In June 2014, however, a County inspector visited the Wedgewood Center area in response to a complaint that dust was coming from the facility. He testified that he detected a rotten egg type smell on the Wedgewood Center property. At a meeting attended by Mr. Miller and County and Department representatives on June 17, 2014, the Department advised Respondent of its findings and provided Mr. Miller with copies of the inspection reports. On July 1, 2014, the Department conducted a follow-up inspection of the facility. The inspector noted a hydrogen sulfide odor on the north, south, and west sides of the disposal area of the facility, and on the top of the disposal pile at the facility. See Dept. Ex. 18. Another inspection conducted on July 9, 2014, did not find any objectionable odors. See Dept. Ex. 19. On July 18, 2014, the Department conducted a follow-up inspection of the facility. The inspector again noted objectionable odors at the facility but none off-site. Id. On July 24, 2014, Department inspectors noted objectionable odors on top of the pile, the toe of the north slopes, and off-site on West Pinestead Road. See Dept. Ex. 20. An inspection performed the following day noted objectionable odors on top of the pile and the toe of the north slopes, but none off-site. Id. The Notice, which was already being drafted in mid-July, was issued a week later. In response to the meeting on June 17, 2014, Respondent prepared a draft odor remediation plan, made certain changes suggested by the Department, and then submitted a revised odor remediation plan prior to July 31, 2014. A Department engineer agrees that "in the strict sense it meets the requirements of the rule" and "could work," but there are "two or three things that still needed . . . to be submitted in order for it to be completely approvable." For example, she was uncertain as to how and when dirt cover would be applied, and how erosion would be controlled. Although the plan was filed, it was never formally approved or rejected, and the "two or three things" that the witness says still needed to be done were never disclosed to Respondent. Under these circumstances, it is reasonable to accept Respondent's assertion that it assumed the plan was satisfactory and complied with the rule. After the Notice was issued, Respondent set up a hotline for community members to call and report odors. A sign on the property gives a telephone number to call in the event of odors. At an undisclosed point in time, Respondent began requiring employees to walk the perimeter of the facility each day to monitor for odors; spreading and mixing hydrated lime to reduce the odors around the facility; and increasing the amount of cover applied to the working face of the facility. The parties agree that these measures are the best available practices to monitor and eliminate objectionable odors at a C & D facility. Despite these good faith measures, Mr. Miller acknowledged that he visited the facility during the evening a few days before the final hearing in December 2014 and smelled hydrogen sulfide around the ECUA sewer pipe and "a very mild level" by the debris pile. Respondent does not deny that odors were emanating from the facility during the months leading up to the issuance of the Notice. But in April 2014, the County experienced a 500- year storm event which caused significant flooding and damaged a number of homes. Because Respondent operates the only C & D facility in the County and charges less than the County landfill, it received an abnormal amount of soaked and damaged C & D debris, which it contends could have generated some, if not all, of the odors that month. Given the magnitude of the storm, this is a reasonable explanation for the source of the odors at that time. Respondent also presented evidence that an underground ECUA sewer pipe that runs on the eastern side of the property was damaged during the storm, causing it to rupture and be exposed. Although ECUA eventually repaired the damaged pipe at a later date, the pipe is still exposed above ground. Until the pipe was repaired, Respondent's assumption that it likely contributed to some of the odors detected by the Department appears to be valid. Finally, Respondent's expert attributes some of the odors to biological degradation from other sources both on-site and off-site, including a large wetland area running through the middle of the property. To a small degree, County testing later that fall confirms this assertion. The County has also been an active participant in the odor complaint issue. In response to complaints received from residents of Wedgewood, in July 2014 it began collecting hydrogen sulfide data using a device known as the Jerome 631X Hydrogen Sulfur Detector. This equipment is used to monitor for the presence of hydrogen sulfur. On July 21 and 22, 2014, samples were taken documenting that hydrogen sulfide was coming from the facility. In early September the County set up a fixed station at the Wedgewood Center, around 500 feet from the edge of Respondent's property, to continuously and automatically collect the data. During September and October 2014 the detector reported the presence of hydrogen sulfide at that location 64 percent of the days in those months, and this continued into the month of November. Seventy-five percent of the exceedances occurred when wind was blowing from the south, or when winds were calm. The data also reflected that when the wind was blowing from the meter to the facility, or to the south, hydrogen sulfide was still detected on some occasions. A resident of the Wedgewood community testified that on multiple occasions she has smelled objectionable odors in her home and yard and at the Wedgewood Center, and that these odors have been emanating from the facility for a number of years. Because of the odors, she says fewer citizens are participating in programs hosted by the Wedgewood Center.3/ The evidence establishes that before the Notice was issued, Respondent filed an odor remediation plan that was never rejected; therefore, the allegation that a plan was not submitted has not been proven. However, objectionable odors were detected off-site in June and July 2014, or after the April inspection reports were provided to the facility, and they continued throughout much of the fall. Therefore, the Department has established that the plan was not properly implemented. These same findings sustain the allegation that steps were not immediately taken to reduce the objectionable odors. Counts VI and VII - Disposal and Failure to Remove Unauthorized Waste Counts VI and VII allege that on April 14, 2014, the Department documented the disposal of prohibited or unauthorized waste, including waste tires; and that on July 18, 2014, the Department conducted a follow-up inspection that documented the disposal of unauthorized waste, including waste tires, clothing, shoes, and Class I waste, including one electronic item and a grill, in violation of rule 62-701.730(4)(d). The Permit specifies that the facility can only accept for disposal C & D debris. See § 2, Spec. Cond. C.2. Another condition provides that if unauthorized debris is spotted after a load is received, the unpermitted waste should be removed and placed in temporary storage in a bin at the sorting area. See § 2, Spec. Cond. C.3. The Operations Plan spells out these procedures in great detail. Photographs received in evidence show that during the inspection on April 14, 2014, the following unauthorized items were observed at the facility: tires, a basketball goal, Quiklube material, chromated copper arsenate treated wood, a toy, and a crushed electronic item. See Dept. Ex. 22. Photographs received in evidence show that during an inspection on July 18, 2014, the following unauthorized items were observed at the facility: blanket or clothing, a shoe, a bag of Class I garbage, several bags of household garbage, furniture, an electronic item and garbage, drilling mud, a suitcase, and tires. See Dept. Ex. 23. Respondent's expert, who has trained numerous spotters, including a current Department inspector, established that a de minimis amount of unpermitted waste, which is easily hidden in the debris, is not unusual and would not constitute a violation of the rule. For example, when a building is torn down, numerous thermostats containing mercury vile will be in a C & D container but very difficult to see. Also, workers at construction sites may throw small amounts of leftover food in the pile of debris that goes to the facility. However, he agrees that most, if not all, of the items observed during the two inspections would not be considered de minimis. Respondent does not deny that the unauthorized waste was present on two occasions. However, it contends that one would expect to find some of the items in a C & D dumpster. It also argues that the amount of unauthorized waste was minimal and not so serious as to warrant revocation of its Permit. The evidence supports a finding that on two occasions Respondent violated two conditions in its Permit by accepting non-C & D waste and failing to remove it. Therefore, the charges in Counts VI and VII have been proven. Count VIII - Facility Outside of Permitted Dimensions This Count alleges that on May 22, 2014, the Department conducted an inspection of the facility in response to a complaint that Respondent had disposed of solid waste outside its permitted (vertical) limit of 130 NGVD; that on July 25, 2014, the Department had a survey performed at the facility that confirmed this violation; and that this activity violated section 2.3 of the facility's Operation Plan and Specific Condition C.10 in the Permit. Section 2.3 provides that "the proposed upper elevation of waste at the [facility] will range up to 130-feet, NGVD, which is slightly above original grade[,]" while Specific Condition C.10 provides that "[t]he final (maximum) elevation of the disposal facility shall not exceed 130 feet NGVD as shown on Attachment 3 - Cell 2 Closure Grading Plan." Respondent admits that on July 25, 2014, the maximum height of the disposal pile exceeded 130 feet NGVD. However, it argues that, pursuant to Specific Condition C.10, which in turn refers to the Permit's Cell 2 Closure Grading Plan, the 130-foot height limitation comes into play only when cell 2 is being closed and is no longer active. This interpretation of the conditions is rejected for at least two reasons. First, a disposal pile in excess of the established height would trigger concerns about the integrity of the foundation of the facility. When the 130-foot ceiling was established by the Department at the permitting stage, it was based on calculations that the ground could support the weight of the waste. Second, the facility's financial assurance calculations are based on a set dimension of the site; these calculations would likely be impacted if there were no height restrictions. The Department's interpretation is more reasonable and limits the height of the pile to no more than 130 feet NVGD at any time when the cell is active. The Department has established that Respondent violated Permit conditions by disposing of waste outside its maximum permitted height of 130 feet NVGD. To Respondent's credit, its new consultant, Charles Miller, completed preparation of a height reduction plan on September 3, 2014. See Resp. Ex. 4. Although Mr. Miller says the plan was being implemented at the time of final hearing, it has never been formally submitted to the Department for approval. Under the plan, Respondent proposes to extract all of the existing waste from the pile in the next two years. To reduce the volume of new waste being accepted, Respondent recently purchased a Caterpillar bulldozer, low-speed grinder, and Trommel screener. New waste will be shredded, screened to separate sand and dirt from the material, and then ground and compacted. Mr. Miller anticipates that the facility can achieve up to an eight to one (or at a minimum a five to one) reduction in the size of the waste. This will dramatically reduce the height of the pile and bring it well below 130 feet at closure. But whether cell 2 is now below 130 feet NGVD is unknown. In any event, these proposed remediation steps should be taken into account in assessing an appropriate penalty.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order revoking Respondent's C & D Permit. DONE AND ENTERED this 2nd day of March, 2015, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 2015.

CFR (1) 40 CFR 264 Florida Laws (10) 120.52120.57161.054403.021403.061403.087403.121403.703403.704403.865 Florida Administrative Code (1) 62-602.870
# 6
TOWN OF SURFSIDE vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-001021 (1978)
Division of Administrative Hearings, Florida Number: 78-001021 Latest Update: Apr. 17, 1979

The Issue The manner and extent to which the criteria of Rule 17-7.07, F.A.C., entitled "Dump Closing" may be required by Respondent with respect to the Town of Surfside Dump.

Findings Of Fact In 1949, Petitioner purchased approximately 378.8 acres of land located in the northwest section of Miami, Florida. It sold approximately 250 acres of the eastern portion in 1959 to County Line Development Company. Petitioner utilized the remaining land as a solid waste disposal facility known as the "Surfside Dump," and in early 1955, other municipalities in North Dade and South Broward Counties also began using the facility for waste disposal. Originally, "white" goods, rubbish, garden trash, vehicle bodies, and tires were disposed of at the site, in addition to domestic garbage. Somewhat later, the receipt of vehicle bodies and other oversize waste was discontinued. For a number of years, the basic procedure for disposal was to dump the refuse into open trenches where it was compacted by bulldozers and covered with a layer of locally available material. The dump presently is bounded by Northwest 215th Street on the north, Northwest 47th Avenue on the west, Snake Creek Canal on the south, and the land previously conveyed to County Line Development Company on the east. A large portion of the dump area on the west side has not been used since 1972. (Petitioner's Exhibits 1, 3) Inspections of the dump conducted by Department of Pollution Control representatives at various times from 1973 through 1975 revealed that waste was not being covered in a satisfactory manner in that trenches were dug from old refuse, raw garbage was pushed into the water-filled trenches and then recovered with the old refuse. In 1975, the County Line Land Company filed suit against the Petitioner in the Dade County Circuit Court complaining that the dump constituted a public and private nuisance and was being operated in violation of the county code relating to uncovered garbage, Chapter 10D-12 of the Rules of the Department of Health and Rehabilitative Services governing disposal of garbage, and Chapter 17-7 of the Department of Pollution Control pertaining to regulation of solid waste. The Circuit Court found that the dump adversely affected the health and welfare of the surrounding area, and that although the facility was being used for revenue purposes by Petitioner, the conditions existing there had not been improved over the years. It therefore enjoined Petitioner from accepting further refuse at the site commencing June 30, 1976, except from within its own boundaries. It further gave Petitioner until August 1, 1976, to show that it had complied with Chapter 17-7 of the rules of Respondent or that it had received a temporary operating permit under the pertinent regulations. The decision was affirmed by the First District of Appeal on January 4, 1977. State regulations in effect since 1962 have required sanitary landfills to dispose of garbage in compacted layers with not less than a daily six inches of cover material and a final covering of two feet of compacted earth unless otherwise approved by the regulating state agency. (Rule 170C-10.07, State Board of Health; Rule 10D-12.07, Department of Health and Rehabilitative Services)(Respondent's Exhibits 1-3) On February 4, 1975, the Department of Pollution Control sent Petitioner a Letter of Notice advising that the Surfside Dump was in violation of various provisions of Chapter 403, Florida Statutes, and Chapter 17-7, Florida Administrative Code, by not applying for a temporary operation permit. By letter of March 28, 1975, that Department sent a Warning Notice to Petitioner along the same lines and advising of civil penalties for violation of pollution control laws. On May 3, 1975, Petitioner filed an incomplete application for the temporary operating permit. However, it was not until January 20, 1976, that Petitioner ostensibly furnished the necessary exhibits and public notice of its application. By letter of February 9, 1976, the acting district manager of the Respondent, which had succeeded the Department of Pollution Control, informed Petitioner that the Public Notice which had been published did not meet departmental requirements. (Testimony of Quaas, Respondent's Exhibits 5, 13) On June 1, 1976, the Respondent issued a Notice of Violation to Petitioner which stated that the Surfside Dump was being operated without a valid and current permit in an unsafe and unsanitary manner and thereby had violated various provisions of Chapter 403, Florida Statutes, and Chapter 17-7 Florida Administrative Code. The notice included a section entitled "Orders for Corrective Action" which provided that the Petitioner should reimburse the Respondent for expenses, cease to accept any solid material as of September 30, 1976, and implement a specified system of operation and render monthly reports on the same. It also required Petitioner to close the site no later than July 1, 1977, with a final cover of two feet of clean compacted fill with side slopes not to exceed 3:1 slope, and for the entire site to be seeded or planted with grass or other suitable cover vegetation. The orders also required the Petitioner to complete his operating permit application by sending Respondent a compliance schedule and proof of publication of a Public Notice. Subsequently, on January 16, 1977, the parties entered into a "Consent Agreement and Final Department Orders" after having conducted informal negotiations in the matter. The agreement provided that Petitioner waived any right to a hearing under Chapter 120, F.S., and that it would close the site or convert it to a sanitary landfill within the time established in Rule 17-7.07, F.A.C. It required Petitioner to submit plans for closing or converting the site within a certain time period and for implementation of an Operation plan to cover each day's waste and any existing exposed waste with six inches of clean compacted fill. It further required the Petitioner to submit a plan for monitoring ground water for leachate no later than January 30, 1977. Thereafter, on February 25, 1977, Nathaniel M. Zemel, a consulting engineer employed by Petitioner, submitted a "Landfill Closing Plan" to Respondent's West Palm Beach office which provided for a minimum of 24 inches of earth cover over all refuse on the site. Mr. Zemel estimated that between 250 thousand and 300 thousand cubic yards of fill material would be required to complete the covering operation. However, by letter of March 25, 1977, Petitioner advised Respondent that it did not concur in Mr. Zemel's plan and that Dr. Damodar S. Airan would "further refine the plan to reflect new information." The Airan report was submitted to Respondent on October 5, 1977, and essentially concluded that the existing vegetation on the site would be killed and that other harmful effects would result if a final cover of two feet of fill were to be placed over the landfill area. The report therefore recommended that exposed areas of the dump be covered with approximately six inches of clean fill and that corrective measures for surface drainage be accomplished, including sloping, grading, and possible catchment and retention of surface runoff by a drainage canal leading to a small retention basin on the site. A closing plan with drawings to accomplish the report's recommendations was filed with Respondent on November 1, 1977. (Petitioner's Exhibit 1, Respondent's Exhibits 6, 7, 14-17) Respondent's staff reviewed the Airan report and closing plan and was of the opinion that the study did not prove the basic premise that six inches of cover over the dump area was adequate. Thereafter, on December 4, 1977, Respondent issued a Final Consent Order for Dump Closing," Order No. 91, which ostensibly permitted the Petitioner time to undertake a soil and vegetation effectiveness study conditioned upon its agreement to implement and adhere to a final closing and cover plan as determined by the Department upon its review of the results of the study. This order obviously had been framed prior to the submission of the Airan report since that report was the "soil and vegetation effectiveness study" referred to in the consent order which was to be submitted not later than October 5, 1977. The order also provided that Respondent's determination of a final closing and cover plan would be made no later than December 1, 1977 and that the final closing would be accomplished no later than March 1, 1978. Again, the terms of the Consent Order provided that the Petitioner waived any right to a hearing or administrative or judicial review of its terms. Respondent's review and determination of Petitioner's aforesaid study was reflected in a letter to Petitioner from its subdistrict manager, Warren G. Strahm, dated January 3, 1978. It stated that Petitioner's study did not provide evidence that six inches of final cover would minimize and control potential water pollution from vertical percolation of surface water, but that Petitioner's own report showed that thirty-two million gallons more of percolation would result from a six inch as opposed to a two foot final cover. The letter therefore directed Petitioner to implement and adhere to a final closing and cover plan that included a final cover of no less than two feet of compacted earth, grading and sloping of the area, seeding or planting the site with grass or suitable cover vegetation, monitoring of ground water for leachate , and compliance with all other requirements of Rule 17-7.07, F.A.C., by March 1, 1978. Petitioner thereafter filed suit against Respondent in the First District Court of Appeal, Case No. 11-447. The suit was dismissed on May 19, 1978, by joint stipulation of the parties wherein it was agreed that Petitioner would seek a Section 120.57, F.S., hearing. On May 25, 1978, Petitioner filed such a petition with Respondent seeking to have that agency declare Petitioner's final cover and closing plan requiring six inches of final cover to be valid, and that final cover only be required on those portions of the Surfside Dump which were actually used on or after October 1, 1974. (Petitioner's Exhibit 2, Respondent's Exhibits 8, 18, 19) The Surfside Dump has been closed to the receipt of solid waste since March 1977. Although some clandestine dumping of waste has occurred since that time, it has mostly been confined to an area outside of the fenced portion of the site. There are presently relatively small areas of exposed waste in about fifty per cent of the landfill area. Some waste may be seen at the ground level in vegetated areas. A certain amount of ponding occurs in areas of both sparse and dense vegetation. There is a heavy vegetative growth over approximately 90 to 95 per cent of the dump site, consisting primarily of torpedo grass, para grass, guineagrass, common rag weed, caster bean, and sedge. Torpedo grass is a principal species and is abundant in about two thirds of the vegetated area. (Testimony of Quaas, Conn, Hudson, Stotts, Hussin, Gatewood, Busey, Airan, Petitioner's Exhibits 1, 4, 5, Respondent's Exhibits 10-12) Ground water or infiltrating surface water moving through solid waste can produce leachate, a solution containing dissolved and finely suspended solid matter and microbial waste products. Leachate may leave a landfill at the ground surface as a spring or percolate through the soil and rock that underlie and surround the waste. However, since the solid waste is of variable composition, it is not possible to accurately predict contaminant quantities. In completed fills, the amount of leachate can be expected to decrease with time. Leachate percolating through soils underlying and surrounding the solid waste is subject to purification of the contaminants in a variety of ways, but is diluted very little in ground water. Although leachate from a landfill can contaminate ground water, it is necessary to determine the quality of ground water and the aquifer's flow rate and direction to assess its results. Grading of the landfill is a means of diminishing surface infiltration by promoting surface water runoff. Vegetation of a landfill helps to stabilize cover material and thus reduce infiltration. It also reduces infiltration by intercepting and evapotranspiring some of the precipitation. The soil cover over a landfill also reduces percolation into the landfill depending upon its permeability. Clayey and silty loams are well suited for final cover, but are not readily available in South Florida. Sandy soils are primarily available in that area, but allow increased infiltration of precipitation. As a landfill ages, the earth cover will be subject to settlement and maintenance may be required to fill in depressions to avoid ponding of rain water. Such a program should provide for repairing cracks in the fill area due to uneven settlement and reseeding and fertilizing as necessary on the repaired areas, to prevent major erosion and surface water ponding. Leachate leaving the bottom of solid waste can be undesirable for drinking water, surface water, industrial water or irrigation water. However, it is most difficult to determine the character and amount of leachate from a particular area due to the many complex factors involved in such an assessment. The most common method for leachate control is to minimize the amount of water infiltrating the site. Ground water monitoring is accomplished by obtaining samples from wells placed at various locations on and near the landfill. It is generally agreed among the expert authorities that a minimum of two feet of compacted soil is required for the final cover when closing a landfill under normal circumstances. It has been the policy of Respondent to apply the sanitary landfill closing requirements of a two foot final cover, as specified in Rule 17- 7.05(3)(m), F.A.C., to the closing of dumps. (Testimony of Quaas, Conn, Hudson, Stotts, Hussin, Busey, Snider, Respondent's Exhibits 21-27) Expert testimony establishes that most of the vegetative cover on the Surfside Dump will be killed if a two foot cover is placed over it. The plants would re-colonize after such disturbance, but it takes almost two years for new plant growth to reach maturity. The present vegetation has been on the site for a number of years. Vegetation normally will grow at a better rate if its roots extend through the cover soil into the solid waste. However, certain gases created from waste material can be deleterious. A six inch final cover over vegetation would permit certain species to survive well, including torpedo grass, which is abundant on the site. In bare areas, it is best to sprig torpedo grass which provides relatively rapid growth, or to plant bahia grass. (Testimony of Hudson, Gatewood, Busey, Petitioner's Exhibit 1) The landfill site consists of an undulating terrain with surface drainage going in different directions from high to low level areas, but the overall drainage pattern is in a northerly direction. Two low-lying areas in the center and eastern portions of the landfill are subject to ponding after rainfall. These areas need to be filled, graded and planted in order to provide an overall northward direction of flow, together with grading and sloping on the eastern and southern boundaries of the area. Petitioner proposes to install subsurface drainage pipes, if found necessary, to promote horizontal movement of surface water and to provide catchment and retention of surface runoff diverted from the landfill area. This may include a shallow drainage canal along the northern boundary leading to a small retention basin in the northwest corner. Although these proposals were included in Petitioner's final closing plan submitted to Respondent, they were not considered by the latter's staff in evaluating requirements for the dump closing. Some profile corrections of the site were accomplished during the past year which eliminated ponding in the southwest corner of the landfill and improved drainage in the western portion. When further profile corrections are made to remove the remaining low spots, it is estimated that surface and subsurface runoff would increase and result in less leachate reaching the ground water table. (Testimony of Hudson, Airan, Petitioner's Exhibits 1, 4) Field and laboratory tests performed to determine the permeability of the soils on the landfill were performed by Petitioner at representative sites and by surface and subsurface soil samples. These tests showed that the infiltration rate at unvegetated locations was lower than that of adjacent vegetated areas, but this was attributed to the fact that in unvegetated areas, the soil is heavily compacted, very rocky, or no fill material is present. When infiltration was measured directly on waste material, it was found to be lower than that for surface soil. Mathematical calculations as a result of the tests showed that a maximum of 32 million gallons more would percolate annually through a six inch soil cover than a two foot cover. However, these calculations did not take into consideration the amount of surface and subsurface runoff. Petitioner's experts estimate that at least half of the percolation would be dissipated in that manner, leaving approximately 16 million gallons annually that would penetrate through the solid waste to the ground water. In considering this fact and the amount of water flowing laterally through the waste material, Petitioner concludes that only approximately one per cent of the total water flowing through the average ten foot waste layer under the water table would consist of vertical percolation. (Testimony of Airan, Petitioner's Exhibits 1, 4, 6-8, 10-13, Respondent's Exhibit 31-33) The Surfside Dump overlies the Biscayne aquifer. The Snake Creek Canal at the southern boundary of the dump site flows into Biscayne Bay some miles distant. There is a well field approximately one mile south of the dump at Carol City. Upstream of the Snake Creek Canal to the west is the North Dade County Landfill which is still in use. Snake Creek Canal is approximately fifteen feet wide and the bottom of the canal is approximately fifteen feet below original ground level. It is approximately thirty feet below the top of the landfill surface. Ground water flows generally in a southeasternly direction through the landfill. Approximately ten per cent of the ground water flows through the solid waste and the remaining 90 per cent bypasses and goes around the perimeter of the landfill. In May, 1977, a water quality monitoring program was undertaken by Petitioner that utilized nine sampling wells in three clusters of three each located in the northwest corner, center, and southeast corner of the landfill. In each cluster, one well was drilled to about five feet below the solid waste layer, the second ten feet below that point, and the third was ten feet above the waste layer. Water samples were taken in 1977 and in 1978. Tests of the samples showed that water quality generally improved with the depth of the well, and that the center group of wells had the highest level of contaminants because they were drilled in the middle of solid waste layers. In a number of instances, the pollutant levels for various substances were in excess of state standards. One well in the center of the landfill was dry during the rainy season which could indicate that the center of the landfill is less permeable than the outer layers and that a certain amount of water had been subject to subsurface runoff. It is conceded by both parties that the location and method of sampling wells does not provide sufficient definitive information concerning water quality in the area and that further monitoring needs to be undertaken in the future. Testing of Snake Creek Canal from points upstream and downstream of the Surfside Dump show that the surface water quality is most affected by contaminants from upstream. The North Dade County Landfill west of the Surfside Dump is undoubtedly a major influence on the quality of Snake Creek Canal water prior to reaching the Surfside Dump area. Leachate has not been found in canal water samples even though it is sufficiently deep to intercept the same if present. However, it is conceivable that any leachate plume could extend below the bottom of the canal. (Testimony of Stotts, Hussin, Snider, Airan, Patton, Petitioner's Exhibits 1, 4, 9, 12, Respondent's Exhibits 29 a-f) Based on the foregoing Findings of Fact, it is further found: The Surfside Dump presently is contributing to contamination of the ground water table in an unknown amount and is a potential source of pollution to the Snake Creek Canal and Biscayne Bay; The amount of pollution caused by leachate can be reduced through the implementation of corrective measures for surface drainage, including the filling of low lying areas, and grading and sloping to permit maximum surface water runoff. Additionally, infiltration of water into the landfill will be reduced by preserving the existing vegetation thereon which is an important factor in stabilizing surface cover and reducing percolation through evapotransportation most of the present vegetation will not survive if a two foot cover of soil is placed over it, and reestablishment of vegetation to its present state will take approximately two years. A surface cover of six inches over the vegetation would permit survival of most existing vegetation.

Recommendation That Respondent issue a final order requiring Petitioner to comply with the requirements set forth in paragraph 6 of the foregoing Conclusions of Law with regard to closing the Surfside Dump. DONE and ENTERED this 11th day of January, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Silvia M. Alderman, Esquire Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Joseph C. Jacobs, Esquire Melissa L. Allaman, Esquire Ervin, Varn, Jacobs, Odom and Kitchen Post Office Box 1170 Tallahassee, Florida 32302 Stephen Cypen, Esquire 825 Arthur Godfrey Road Miami Beach, Florida ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION TOWN OF SURFSIDE, Petitioner, vs. CASE NO. 78-1021 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION, Respondent. /

Florida Laws (7) 120.5717.02403.061403.121403.161403.2017.05
# 7
DEPARTMENT OF ENVIRONMENTAL REGULATION vs. JACK E. MOORE, 83-001487 (1983)
Division of Administrative Hearings, Florida Number: 83-001487 Latest Update: Nov. 01, 1991

Findings Of Fact Jack E. Moore is the owner of real property in Fort Myers Beach known as Lot 9 of Indian Bayou, a subdivision in Section 33, Township 46 South, Range 24 East, Lee County, Florida. Moore's property is bordered on the north by the waters of Indian Bayou and Estero Bay. The northern portions of Moore's property are vegetated by juvenile and mature red and black mangroves. Red and black mangrove are the dominant species of vegetation on the northernmost portions of the property, waterward of the fill pad on which Moore's house is built. Sometimes during July, 1982, Moore used a shovel to excavate a channel from the open waters of Estero Bay to a dock existing at the edge of the fill pad. Approximately 48 cubic yards of excavated material was piled up along the banks of the channel. The channel measured approximately 1.5 feet deep (at low tide) by 9 feet wide by 70 feet long. The channel was dug so that Moore could got his boat in and out from the dock at medium tide. The passage to the deck was already possible at high tide, as Moore had a shallow draft pontoon boat. In July, 1981, Moore constructed a rip-rap revetment with backfill the northern side of his house fill pad. The back fill area contains approximately 160 cubic yards of fill, and is approximately 10 feet wide by 110 feet long. Red mangrove and black mangrove are and were the dominant vegetational species in the area where the channel was dug, where the excavated material was placed, and where the revetment and fill was constructed. The area of dominant mangrove vegetation extends from the work areas to the open waters of Estero Bay. Moore did not apply for or receive a permit from DER prior to undertaking the work referenced above. Upon discovery of the work in September, 1982, DER notified Moore that a permit was needed for the excavation and filling he conducted. In October, 1982, Moore agreed to fill in the channel and remove all unauthorized fill by January 19, 1983. Inspection by DER on January 26, 1983, showed that restoration had not been started, and in fact more work had been done on the channel. DER issued a Notice of Violation and Orders for Corrective Action (NOV) to Respondent on March 29, 1003, alleging violations of Chapter 403, Florida Statute's, and DER rules and requiring restoration of the areas dredged and filled. Upon service of the Notice of Violation by the Sheriff, Respondent petitioned for this hearing. DER incurred costs of 5101.88 in investigating the violations alleged in the NOV. As of the date of the hearing, restoration work still had not been performed. Although the spoil piles alongside the channel are now diminished, the channel itself was deep as it previously had been and the rip-rap revetment and backfill had not been removed.

Florida Laws (5) 120.57403.031403.087403.141403.161
# 8
LEAGUE OF WOMEN VOTERS OF CLEARWATER/UPPER PINELLAS COUNTY vs. FAIRFIELD FLORIDA COMPANIES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 85-002755 (1985)
Division of Administrative Hearings, Florida Number: 85-002755 Latest Update: Feb. 14, 1986

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that a dredge and fill permit be issued to Fairfield to fill 2.1 acres of wetlands and to create 2.1 acres of wetlands as mitigation, including the planting of Spartina to be maintained at an 80% survival rate for a period of five years and the provision of erosion control measures in and adjacent to Lake Avoca and St. Joseph's Sound. Respectfully submitted and entered this 14th day of February, 1986 in Tallahassee, Leon County, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of Feburary, 1986. APPENDIX The proposed findings of fact submitted by the Petitioner and the Respondent Fairfield have been accepted and/or incorporated in this Recommended, except as noted below: Petitioner page 3, 3rd full paragraph, Rejected; not supported last sentence: by competent substantial evidence. page 4, 1st paragraph: Rejected; contrary to the greater weight of the evidence. page 5, 1st full sentence: Accepted, but irrelevant and immaterial to disposition of any issue. pages 5 and 6, starting with Rejected; contrary to the 1st full paragraph: greater weight of the evidence. Respondent Fairfield page 4, 2nd full paragraph: Rejected; mere recitation of testimony and conclusions of law as opposed to factual findings. page 13, 1st paragraph: Rejected: irrelevant and immaterial. NOTE: Many of the proposed findings of fact submitted by the Petitioner and the Respondent Fairfield constitute either recitations of testimony or legal conclusions. While these have not technically been rejected by the undersigned, they are not appropriate for the findings of fact section and are discussed in the conclusions of law. COPIES FURNISHED: Victoria Techinkel Secretary Twin Towers Office Bldg. 2600 Blairstone Road Tallahassee, FL 32301 Mary f. Smallwood General Counsel Twin Towers Office Bldg. 2600 Blairstone Road Tallahassee, FL 32301 William W. Deane, Esquire Hanley and Deane, P.A. 465 Second Avenue North P. O. Box 7473 St. Petersburg, FL 33734 Julia D. Cobb Deborah Detzoff Richard Tucker 2600 Blairstone Road Tallahassee, FL 32301 Terry E. Lewis Steve Lewis Messer, Vickers, Caparello, French & Madsen P. O. Box 1876 Tallahassee, FL 32302 =============================================================== AGENCY FINAL ORDER =============================================================== STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION LEAGUE OF WOMEN VOTERS OF CLEARWATER-UPPER PINELLAS COUNTY, Petitioner, v. DOAH CASE NO. 85-2755 DDT OGC FILE NO. 85-0822 DEPARTMENT OF ENVIRONMENTAL REGULATION and FAIRFIELD COMMUNITIES, INC., Respondents. /

Florida Laws (4) 120.57120.68380.06403.412
# 9
DEPARTMENT OF COMMUNITY AFFAIRS vs MORTIMER AND GAY HALL, PIERCE CONSTRUCTION AND BUILDERS, AND MONROE COUNTY, 92-002958DRI (1992)
Division of Administrative Hearings, Florida Filed:Key West, Florida May 14, 1992 Number: 92-002958DRI Latest Update: Jun. 06, 1996

Findings Of Fact Petitioner is the state land planning agency charged with the responsibility to administer the provisions of Chapter 380, Florida Statutes, and the regulations promulgated thereunder. Petitioner has the authority to appeal to the Florida Land and Water Adjudicatory Commission any development order issued in an area of critical state concern. The appeal in the instant proceeding was timely. Monroe County is a political subdivision of the State of Florida and is responsible for issuing development orders for development in unincorporated Monroe County. Monroe County issued the development order that is the subject of this appeal. Respondents, Mortimer and Gay Hall, are the owners of real property known as Lots 60 and 61, Block 19, Breeze Swept Beach Estates on Ramrod Key in unincorporated Monroe County. The Halls have constructed a single family dwelling on that property, but the building permit for the construction of the dwelling is not at issue in this proceeding. Most of Monroe County, including the subject property, is within the Florida Keys Area of Critical State Concern as designated under Sections 380.05 and 380.0552, Florida Statutes. On January 21, 1992, Monroe County issued the subject building permit, Permit Number 9010001679, to Mortimer and Gay Hall as owners and Pierce Construction and Builders as contractor. The subject permit would be subject to certain conditions imposed by the Florida Department of Natural Resources (DNR). As permitted, the use of the structure would be limited to swimming and recreation. Boating, or the mooring of boats, would not be permitted. By letter dated December 17, 1991, DNR authorized the project subject to certain conditions and limitations, and provided, in pertinent part, as follows: Mort and Gay Hall are hereby authorized to proceed with the construction of a swim platform as proposed This authorization is specifically conditioned upon the following: * * * The structure shall be used only for passive recreational activities such as swimming and fishing. Mooring of vessels at the facility either on a temporary or permanent basis is strictly prohibited. The platform and walkway shall be elevated four feet above mhw [mean high water]. Handrails at a height of four feet shall be installed along the walkway and around the platform. Handrails shall be two feet above the platform deck. Install at least three "NO MOORING" signs along the perimeter of the platform. Install a ladder on the waterward terminus of the platform for water access. The application submitted by the Halls to Monroe County that resulted in the subject permit incorporated the DNR conditions and described the project as follows: Applicant wishes to install a wooden swim platform (20 ft. length x 8 ft. width) and a wooden elevated access walkway (25 ft. length x 4 ft. width) to access this platform; for the purpose of using the channel cut for swimming activities at their existing single family residence. Monroe County's comprehensive plan, which has been approved by the Petitioner and by the Administration Commission, is implemented through its adopted land development regulations, codified in Chapter 9.5, Monroe County Code. Section 9.5-345(m)(2), Monroe County Code, referred to as the four foot rule, provides as follows: (2) All structures on any submerged lands and mangroves shall be designed, located and constructed such that: * * * No structure shall be located on submerged land which is vegetated with sea grasses except as is necessary to reach waters at least four (4) feet below mean low level for docking facilities; No docking facility shall be developed at any site unless a minimum channel of twenty (20) feet in width where a mean low water depth of at least minus four (4) feet exists; Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, provides, in pertinent part, as follows: The Florida Keys are dependent on nearshore water quality for their environmental and economic integrity. The heart of the Florida Keys economy, the means by which Monroe County exists as a civil and social institution, is based on its unique oceanic character. If nearshore water quality is not maintained, then quality of life and the economy of Monroe County will be directly and immediately impacted. OBJECTIVES 1. To protect, maintain and, where appropriate, to improve the quality of nearshore waters in Monroe County. * * * POLICIES 1. To prohibit land use that directly or indirectly degrade nearshore water quality. * * * To prohibit the development of water dependent facilities, including marinas, at locations that would involve significant degradation of the biological character of submerged lands. To limit the location of water-dependent facilities at locations that will not have a significant adverse impact on off-shore resources of particular importance. For the purposes of this policy, off-shore resources of particular importance shall mean hard coral bottoms, habitat of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of less than four (4) feet, and all designated aquatic preserves under Florida Statutes section 258.39 et seq. By Final Judgment entered June 7, 1991, the Honorable Richard G. Payne, Judge of the Circuit Court of the Sixteenth Judicial Circuit, in and for Monroe County, Florida, ruled in Stanton v. Monroe County, Case No. 91-20-035- CA-18, that Monroe County's four foot rule does not apply to swimming piers, concluding, in pertinent part, as follows at page five of the Final Judgment: 5. To the extent that the County's Comprehensive Plan and Land Development Regulations fail to provide for swimming piers ... the court finds that it is unreasonable to treat such piers as if they were docks at which boats are to be moored. Pursuant to the judicial review authority of Chapter 163, Fla. Stat., the court declares ... [the four foot rule] inapplicable to piers at which boats are not to be moored. The County has adequate judicial remedies, including injunction, to prevent the use of such piers, including the subject pier, for the mooring of boats. Despite the Stanton ruling, supra, Monroe County has interpreted the four foot rule as being applicable to swimming piers such as the one the Halls wish to construct. Monroe County's long-standing interpretation of the four foot rule would not prohibit the permit because of the minimal effect such construction would have on the nearshore waters. Since 1986, Monroe County has adopted an interpretation of Section 9.5-345(m)(2), Monroe County Code, and of Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, that would permit the construction of the subject project. That interpretation permits the development of docks in subdivisions that were under development in 1986 if there is at least four feet of water at the terminal point of the dock at mean low tide. The structure that is the subject of this proceeding is in a subdivision that was under development prior to 1986 and would, if permitted, terminate in a channel more than 20 feet wide with water at least six feet deep at mean low tide. Monroe County's interpretation of the four foot rule is that the rule was intended to restrict the development of boating access facilities in new, undeveloped subdivisions and to regulate proposed expansion of existing marinas and the development of new marinas. Monroe County considers the subject application by the Halls to meet all of its permitting criteria. The structure will be constructed in a dredged area of adequate size for swimming. Access to the structure by boat is unlikely because the swimming area is surrounded by a reef and hard bottom that is extremely shallow, even at high tide. At low tide much of this surrounding area is above water, and the deepest area of water is approximately six inches. At high tide, the water depth of the surrounding area ranges from approximately four inches to approximately eighteen inches. On the waterward side of the surrounding area, the water depths are less than four feet. Petitioner's concern is that boats will moor at the structure regardless of the restrictions on the permit and that these boats will cause degradation to the nearshore waters while crossing to deep water. Benthic communities exist in the waters between the Halls's property and deep water, such as rock-hard bottom, sea grasses, algae, and hard coral. Turtles, manatees, sharks, stingrays, eagle rays, snapper, pink shrimp, mullet, and other marine animals populate those waters. Sea grass beds play an important role in water quality maintenance in the Keys through filtration, nutrient uptake, stabilization of the bottom, and as a habitat for commercially important species. One cannot reach deep water by boat from the Halls's property without crossing areas in which the water depth is less than four feet at low tide. Petitioner speculates that prop dredging, and the resulting damage to seagrass beds and shallow water marine communities, would result if one were to attempt to navigate these shallow waters by a propeller powered boat. Petitioner's concern is premised on the unwarranted assumptions that the structure will be illegally used at some point in the future by boats. Petitioner has failed to establish that this concern justifies denial of the permit. Petitioner did not establish that damage would be done to the environment by swimming in the area of the proposed swimming platform. Respondents presented evidence that several similar projects were permitted at approximately the same time as the Halls's permit without Petitioner filing an appeal. This evidence was insufficient to establish that Petitioner should be estopped to appeal the subject permit, that Petitioner engaged in selective enforcement of its regulatory power, or that Petitioner otherwise brought the subject appeal for an inappropriate purpose.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that the Florida Land and Water Adjudicatory Commission enter a final order affirming Monroe County's decision to issue building permit number 9010001679, and dismissing the appeal filed by the Department of Community Affairs. DONE AND ENTERED this 26th day of January, 1993, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of January, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-2958DRI The following rulings are made on the proposed findings of fact submitted on behalf of Petitioner. The proposed findings of fact in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, and 14 are adopted in material part by the Recommended Order. The proposed findings of fact in the first sentence of paragraph 11, 12, 13, and 16 are subordinate to the findings made. The proposed findings of fact in paragraph 15 are rejected as being unnecessary to the conclusions reached because the use of the platform is limited. The testimony by Robert L. Herman as to the purpose and interpretation of the four foot rule by Monroe County is found to be a more persuasive than Mr. Metcalf's testimony. The following rulings are made on the proposed findings of fact submitted on behalf of Respondents. The proposed findings of fact in paragraphs 1, 2, 3,4, and 8 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraphs 5 and 6 are rejected as being subordinate to the findings made. The proposed findings of fact in paragraph 8 are rejected as being unnecessary to the conclusions reached. COPIES FURNISHED: Lucky T. Osho, Esquire David Jordan, Esquire Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Theodore W. Herzog, Esquire Theodore W. Herzog, P.A. 209 Duval Street Key West, Florida 33040 Linda Loomis Shelley, Secretary Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 G. Steven Pfeiffer, General Counsel Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 James T. Hendrick, Esquire Attorney for Monroe County Post Office Box 1117 Key West, Florida 33040 Carolyn Dekle, Director South Florida Regional Planning Council 3400 Hollywood Boulevard Suite 140 Hollywood, Florida 33021 Pierce Construction and Builders Route 4, Box 319 Summerland Key, Florida 33042 Bob Herman, Herb Rabin, Lorenzo Aghemo, Pat McNeese Monroe County Growth Management Division Public Service Building, Wing III 5100 Junior College Road West Stock Island Key West, Florida 33040 William R. Kynoch, Deputy Director Florida Land and Water Adj. Commission Executive Officer of the Governor 311 Carlton Building Tallahassee, Florida 32301

Florida Laws (7) 120.57120.68258.39380.05380.0552380.07380.08
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer