Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE G. VINCENT, 82-001341 (1982)
Division of Administrative Hearings, Florida Number: 82-001341 Latest Update: Apr. 27, 1983

Findings Of Fact The Respondent is a registered roofing contractor, having been issued license number RC 0034898. He operates a business known as B & P Roofing at 244 Tollgate Trail, Longwood, Florida. The Respondent has appropriately qualified the business name of "B & P Roofing" with the Petitioner. The Petitioner is an agency of the State of Florida charged with enforcing the provisions of Chapter 489, Florida Statutes, with regard to licensure of building contractors, the regulation of their licensure status and methods of operation and practice. During June of 1981, the Respondent, doing business as B & P Roofing, contracted to perform a re-roofing job with Mr. Jack Mewhirter, whereby he was to put a new roof on a residence at 137 Variety Tree Circle, Altamonte Springs, Florida. The construction of the roof was contracted for and completed during June, 1981. The Respondent failed to obtain a building permit before or during construction of the roof and also failed to obtain a final inspection of the roof when it was finished in June, 1981. The Respondent's testimony establishes that the Respondent was familiar with the building code adopted in Seminole County and familiar with the requirement that he was responsible as the contractor, to obtain a permit before commencing construction of the roof and that he was also responsible for obtaining a final inspection by the Seminole County Building Official. In response to a complaint from Mr. Mewhirter, the owner of the residence, the Seminole County Building Officials, Mr. Flippent and Mr. Del'Attibeaudierer became aware that no building permit had been obtained for the re-roofing job and that no final inspection had been obtained pursuant thereto. Accordingly, Mr. Del'Attibeaudierer inspected the roof in November, 1981, and Mr. Flippent informed the Respondent of the necessity to obtain a building permit and a final inspection. Thus, on November 10, 1981, the Respondent obtained the building permit and called for the final inspection. Mr. Del'Attibeaudierer was unable to sign the final inspection document as "satisfactory" because he was unable to adequately inspect the roof once it was finished. He had been unable to inspect the method by which it was installed during its construction due to the Respondent failing to inform him or his superiors that the roof was under construction and that inspections were needed at that time. hen the Respondent entered into the contract with Mr. Mewhirter, he informed Mr. Mewhirter that he would not obtain a building permit because that would "drive the cost up." The Respondent, in his testimony, denied that he made such a statement, but Mr. Mewhirter's testimony is here found more credible because of the facts established by Mr. Del'Attibeaudierer's testimony that a random check of the roof after he finally was able to inspect it in November, 1981, revealed that all the shingles he examined were nailed with only three nails and were nailed too high up near the upper edge of the shingle, which is a substandard method of installing the roof and which permits storm winds or rain to raise the shingles, causing possible damage to the roof. The fact that the roof was installed in this fashion and that fact that the Respondent admittedly knew of the requirements of the building code and the requirement that a permit be obtained and inspections be made during the course of and at the conclusion of the job, indicated that the Respondent was knowingly trying to avoid the necessity of obtaining a permit and a final inspection and thus lends sufficient credibility to Mr. Mewhirter's testimony regarding the reason the Respondent obtained no permit. In any event, the roof was shown to not be constructed in accordance with the building code. In summary, it was established that the Respondent knew of the appropriate building code, was thoroughly familiar with it and and indeed had installed an excess of seven hundred roofs since he entered the business. He was aware, in connection with the need for obtaining a building permit, that he should also obtain inspections during the construction and a final inspection when the roof was finished, which he failed to do until reminded of his violation by the building department five months after the roof was completed, at which time it was too late to perform the appropriate inspections. Thus, the roof could not be approved by the building department of Seminole County. The Respondent admitted to only being present on the subject job site for approximately an hour and a half during the entire construction of the roof and he admittedly did not bother to look to see if a permit was on the job site at that time, or any other time. Finally, although the Respondent remonstrated that his failure to get a building permit at the appropriate time was inadvertent and due to his assumption that other office personnel had taken care of the obtaining of the permit, that testimony is not found to be credible since it was established, through the testimony of Mr.. Mewhirter, that the Respondent consciously decided not to obtain a permit prior to starting construction of the roof.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record and the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is, therefore RECOMMENDED: That the Respondent, George G. Vincent, be found guilty of the charges contained in Counts I and II of the Administrative Complaint and that an administrative fine of $1,000 be imposed. DONE and ENTERED this 23rd day of February, 1983, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of February, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 Gary Siegel, Esquire 292 U.S. Highway 17-92 P.O. Drawer 965 Fern Park, Florida 32730 James A. Linnan, Executive Director Construction Industry Licensing Board P.O. Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, v. DPR Case No. 0017669 DOAH Case No. 82-1341 GEORGE C. VINCENT B & P Roofing RC 0034898 244 Tollgate Trail Longwood, Florida 32750, Respondent. /

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs RONALD W. STEADMAN, 97-001365 (1997)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Mar. 14, 1997 Number: 97-001365 Latest Update: Nov. 10, 1998

The Issue The issue presented is whether Respondent is guilty of the allegations contained in the Administrative Complaints filed against him, and, if so, what disciplinary action should be taken against him, if any.

Findings Of Fact At all times material hereto, Respondent was licensed as a certified general contractor in the State of Florida, having been issued license number CG C000942. At all times material hereto, Respondent was the licensed qualifying agent for Twenty First Century Construction Management, Inc. On September 5, 1992, Willie Janes, doing business as Janes Roofing Contractor, entered into a contract with Debourah Benjamin to replace the roof at her residence located in Margate, Florida. The contract price was $6,748, but Janes later agreed to do the work for $6,248, which was all Benjamin's insurance company would pay. On November 26, 1992, Benjamin gave Janes a check in the amount of $2,200 as a down payment on the work. The check was payable to Willie Janes. At the time Janes entered into his contract with Benjamin, his local roofing license had expired, and he was not licensed as a roofing contractor by the State of Florida. Respondent applied for the roofing permit for the Benjamin job. The City of Margate Building Department issued permit number 11525-R by and through Respondent's licensure on December 3, 1992. Janes commenced work on the Benjamin project on November 26, 1992. On December 8, 1992, the City of Margate Building Department performed a tin tag inspection of the work done by Janes. The work failed the inspection that day but passed two days later. On January 11, 1993, Benjamin issued a second check, in the amount of $2,300, payable to Willie Janes, for the purchase of roof tile. Janes did not order and did not pay for the roof tile until approximately June 25, 1993. The tile was delivered to Benjamin's residence a few days later and placed on the roof for installation but Janes did not return to the project site. The amount of tile delivered to Benjamin's residence was not sufficient to cover the entire roof. On approximately June 25, 1993, Benjamin noticed for the first time that the name of the company on the permit posted at her residence was Twenty First Century Construction. Neither the Respondent nor Twenty First Century Construction Management, Inc., had any involvement in Benjamin's project other than obtaining the building permit. Benjamin contacted the building department which issued the permit and was referred to Petitioner. An employee of Petitioner advised her that the qualifier for Twenty First Century Construction was Respondent. Benjamin had never heard of Respondent at the time. Benjamin contacted Respondent by telephone several times about completing the work commenced by Janes. Respondent repeatedly promised to finish the roof but never did. Benjamin next contacted the Margate Police Department to report the activities of Respondent and Janes. On September 3, 1993, Officer Liberatori of the Margate Police Department spoke to Respondent by telephone, and Respondent promised to complete the work within 30 days. However, Respondent did nothing to complete the work. The last inspection performed on the Benjamin project under permit number 11525-R was the dry-in inspection performed on February 8, 1993. Permit number 11525-R expired on July 8, 1993. In December 1993 Benjamin had the project completed by another contractor. On November 16, 1992, Delos and Barbara Johnson entered into a written contract with Respondent to remodel a porch enclosure at the Johnson residence in Coral Springs, Florida, for a contract price of $10,250. The Johnsons made three payments to Respondent: $1,000 on September 28, 1992; $5,000 on November 17, 1992; and $3,000 on December 2, 1992. On October 12, 1992, Respondent applied for a building permit from the City of Coral Springs for the Johnson remodeling. The City of Coral Springs issued permit number 920004472 by and through Respondent's licensure on November 30, 1992. When the City of Coral Springs issues a building permit, it provides with the permit a list of the required inspections. Respondent proceeded with the construction until December 2, 1992, when he received the third payment. Thereafter, Respondent ceased all construction activities on the Johnson project. Shortly thereafter, the Johnsons learned from the Coral Springs Building Department that their remodeling project had failed to pass the required inspections. When they confronted Respondent regarding his failure to obtain the required inspections, he represented to them that he had made a videotape of all the work he performed, that he himself was a building inspector and could inspect his work, and that he could get a special inspector to inspect the project from the videotape. At no time material hereto was Respondent a certified building inspector. Videotaping a construction project in lieu of obtaining required inspections is not permitted under the South Florida Building Code nor is it permitted by the City of Coral Springs Building Department. Of the required nine inspections for the project, Respondent only obtained three inspections. Of those three, he only passed two. Respondent's failure to obtain the required inspections constitutes a violation of the South Florida Building Code, the minimum standard required for any type of building construction in South Florida. A contractor's failure to adhere to that minimum standard causes harm to the public from deteriorating construction. The Johnsons and the City of Coral Springs Building Department gave Respondent an opportunity to obtain and pass the required inspections and complete the construction project. When Respondent declined to do so, the attorney hired by the Johnsons discharged Respondent. The Johnsons had paid approximately 90 percent of the money they had saved for the porch enclosure to Respondent, and they could not afford to continue with the construction project using the services of another contractor until November 1994. Rick Hugins of Hugins Construction Corp., the remedial contractor, needed to pass the required inspections that Respondent had neglected in order to be permitted by the City of Coral Springs Building Department to complete the project. Work that needed to be inspected was concealed by subsequently- installed construction materials which had to be removed in order that the required inspections could be performed. Numerous code violations were discovered in the concealed work. The work performed by Respondent was below industry standards. The Johnsons paid Hugins Construction Corp. $10,000 to correct the code violations, to pass the required inspections Respondent had missed, and to complete the project. Hugins completed the project by January 23, 1995. Respondent has been previously disciplined by Petitioner on charges of assisting unlicensed activity and of failing to notify Petitioner of his current mailing address and telephone number. That discipline included the payment of an administrative fine and an assessment of costs associated with that investigation and prosecution.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Respondent guilty of the allegations contained in Counts I and III of the Administrative Complaint filed against him in DOAH Case No. 97- 1365, finding Respondent guilty of the allegations contained in Counts I and II of the Administrative Complaint filed against him in DOAH Case No. 97-1368, requiring Respondent to pay restitution to the Johnsons, assessing against Respondent the costs of investigation and prosecution through the time the final order is entered, and revoking Respondent's certification as a general contractor in the State of Florida. DONE AND ENTERED this 10th day of July, 1998, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of July, 1998. COPIES FURNISHED: Dorota Trzeciecka, Esquire Department of Business and Professional Regulation 401 Northwest Second Avenue, No. N-607 Miami, Florida 33128 Edward Conrad Sawyer, Esquire 1413 North 58th Avenue Hollywood, Florida 33021 Rodney Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (4) 120.569120.5717.001489.129 Florida Administrative Code (1) 61G4-17.002
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE E. LONGINO, 85-000340 (1985)
Division of Administrative Hearings, Florida Number: 85-000340 Latest Update: Oct. 30, 1985

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the documentary evidence received and the entire record compiled herein, I hereby make the following findings of fact: Respondent is, and has been at all times material hereto, a certified building contractor, a registered mechanical contractor and a certified air conditioning contractor in the state of Florida having been issued license numbers CB-CA09793, RM-0031246 and CA-C024348, respectively. At all times material hereto, Respondent's building contractor and air conditioning contractor licenses qualified George E. Bonsino and Associates, Inc., Jacksonville, Florida. In February 1984, Respondent contracted with Carl and Patricia Powers of 4530 Victor Street, Jacksonville, Florida for the construction of a room addition. The contract was presented to the Powers by Peter Stamires. Mr. Stamires was, at the time, acting as sales manager for George E. Longino and Associates, Inc. The contract price was approximately $13,000.00 and construction of the Powers' room addition was estimated to be completed by March 30, 1984. On March 20, 1984 Respondent received from Carl and Patricia Powers a payment of $6,850.00 on the contract. On May 4, 1984 Respondent received from Carl and Patricia Powers an additional payment of $5,000.00 on the contract. The contract called for a "dry-in room" only, i.e., the room was to be put to a stage where water would not penetrate it. The contract also included: (1) covering the existing asbestos shingles with a cut brick and stone veneer; (2) the installation of aluminum windows; (3) the installation of aluminum gables and eaves; (4) re-roofing the entire home; and (5) the installation of overhead lights, light switches and electrical outlets. Respondent's contract with the Powers contemplated that electrical work would be done, but did not include any plumbing. Respondent sub-contracted the Powers' project to two (2) individuals, Mr. Walker and Mr. Todd. Respondent did not know what type of license Mr. Walker or Mr. Todd held and was never shown a license by either individual. Mr. Walker agreed to obtain permits for the Powers' project, to submit building plans and specifications, and to request the mandatory building inspections. Neither the Respondent nor the sub-contractors obtained a City of Jacksonville building permit prior to commencing construction of the Powers' room addition. Neither Respondent nor the sub-contractors submitted building plans and specifications for approval by the, City of Jacksonville Building Department prior to commencing construction at the Powers' residence as required. Neither Respondent nor the sub-contractors requested the City of Jacksonville Building Department to perform any type of building inspections during the process of construction, as required. On June 11, 1984 Respondent obtained building permit no. 7048 from the City of Jacksonville Building and Zoning Inspection Division for the Powers' project. Shortly after construction commenced, the Powers became concerned with the quality of work being performed. Respondent, while at the project site near the end of March, told Mr. Powers that a building permit had been obtained for the project. However, at that time, no building permit had been obtained. Mr. Theron Brannan, a building inspector for the City of Jacksonville, became involved with the Powers' case when Mrs. Powers called in May 1984 and complained about ;he work being performed by Respondent. Mr. Brannan checked and found that no permit had been issued. He then went out and inspected the construction site. Mr. Brannan found that the walls were approximately 3 or 4 inches out of alignment and that the floor was spongy and needed repair. Major work would have been required to straighten the walls. In Mr. Brannan's opinion, the work was well below average and was of very poor quality. Electrical and plumbing work was performed at the Powers' project site. Ten (10) electrical outlets, six (6) overhead lights and six (6) light switches were installed. The electrical work also included a 220 volt outlet for a clothes dryer. Mrs. Powers is a housewife and was present during the time the electrical work was performed. The individual performing the electrical work told Ms. Powers that he worked for Respondent and was being paid on an hourly basis. The plumbing work performed at the Powers' project included: (1) installation of hot and cold water lines for the bathroom sink, which were tied into the existing water supply; (2) a water line to the toilet, and (3) a drain pipe from the toilet to the existing septic tank. The individual performing the plumbing work told Ms. Powers that he worked for Respondent on an hourly basis and that he was a licensed plumber. When Respondent was advised of the problems at the construction site, he immediately obtained the necessary permits and offered to correct some of the building problems. The Powers refused Respondent's offer to correct the problems because they were concerned as to whether the remedial measures proposed by Respondent were actually feasible. From an appearance standpoint, the measures contemplated by Respondent were not feasible. In April 1984, Respondent contracted with Glenn and Debora Blanchard of 521 Astral Avenue, Jacksonville, Florida for the construction of a room addition. The total contract price was $6,780.00. Respondent received $3,390.00 as a down payment on the contract; the balance was due upon completion. The contract called for the construction of a room addition between the existing home and the garage. The room addition was to be completed to the "dry-in" stage only. The contract also included re-roofing the entire residence. The Respondent sub contracted the Blanchard project to a person by the name of A. Rhoden. Mr. Rhoden agreed to obtain all permits, draw all plans and specifications and obtain all required inspections with the exception of the roofing aspects of the project. Neither Respondent nor the sub-contractor obtain ed a building permit prior to commencing construction at the Blanchard's residence as required. Neither Respondent nor the sub-contractor submitted building plans and specifications to the City of Jacksonville Building Department prior to commencing construction. Neither Respondent nor the sub-contractor requested the building department perform any type of building inspections during the process of construction In May 1984, Ms. Blanchard became concerned because the concrete slab appeared uneven and had developed a crack. She contacted the City of Jacksonville Building Department because she was concerned with the quality of the work being performed. On May 30, 1984 the City of Jacksonville Building Department and Zoning Inspection Division issued a stop work order on construction work being performed at the Blanchard residence. The Notice of Violation cited the failure to submit building plans and failure to obtain a building permit prior to commencing construction at the project site. On June 11, 1984 Respondent obtained building permit no. 7047 from the City of Jacksonville Building and Zoning Inspection Division for the construction work at the Blanchard residence. Such Permit was obtained after commencement of the project. Shortly after commencement of construction, Respondent met with Mr. Blanchard at the project site to discuss a few changes to the original plans. In late April, 1984, Respondent told Mr. Blanchard that a building permit had been obtained, when in fact, no building permit had been obtained. Respondent told Mr. Blanchard that the permit needed to be kept at his office. The construction of the room addition included the forming and pouring of a monolithic slab. The City building department inspects the excavation of the slab prior to the pouring of concrete. A tie-beam inspection is required after the foundation is poured and the masonry walls are erected. Neither inspection was performed nor requested. The Respondent told Mrs. Blanchard that two (2) inspectors had inspected the property, when in fact no inspectors had inspected the property because no building permit had been applied for at the time Respondent made such statement. Unless a building permit is obtained, the City is generally not aware that a construction project is being undertaken and, therefore, does not conduct building inspections. Lewis D. Franks, an expert in residential construction inspected the work done at the Blanchard's home on behalf of the City of Jacksonville Building Department. Several problems existed in regard to the Blanchard project. There was a large crack in the concrete which resulted from the settling of the southeast corner of the building. The settling of the southeast corner resulted from either an inadequate footing or none at all. Also, the roof rafters were not centered properly and were about fourteen (14) feet off. The Blanchard project was of very poor workmanship, the construction was not structurally sound, and the project failed in several respects to meet requirements of the City of Jacksonville Building Code. When Respondent found out that no permit had been obtained he promptly drew up plans and specifications and obtained a permit from the City of Jacksonville Building Department. The Blanchards, thereafter, refused to allow Respondent to continue working on the project. The roofing portion of the Blanchard project was sub- contracted by Respondent to Richard Davenport. Mr. Davenport holds a state license as a roofing contractor and a local occupational license. Mr. Davenport's sub-contract called for him to tear off the existing roof, carry off the rotten wood and put on a new roof. Respondent was not satisfied with the roofing job done by Mr. Davenport and failed to pay him for such roofing job. Thereafter, Mr. Davenport demanded payment from the Blanchards but they also refused to pay him. Mr. Davenport filed a Claim of Lien against the Blanchards' property. However, the Blanchards hired an attorney and the Claim of Lien was dismissed. Respondent's failure to pay Mr. Davenport was based on his good faith belief that the roofing job was not done in a satisfactory manner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent be found guilty of failing to supervise the construction activities of the company which he qualified and incompetence in the practice of contracting as alleged in Count One of the Amended Administrative Complaint. It is further recommended that all other alleged violations contained in Count One of the Amended Administrative Complaint be dismissed. That Respondent be found guilty of failing to supervise the construction activities of the company which he qualified and incompetence in the practice of contracting as alleged in Count Two of the Amended Administrative Complaint. It is further recommended that all other alleged violations contained in Count Two of the Amended Administrative Complaint be dismissed. That Count Three of the Amended Administrative Complaint be dismissed, the Petitioner failing to introduce any evidence in regard to Count Three and requesting that it be dismissed. It is further RECOMMENDED that Respondent's building contractor's license be suspended for a period of 6 months and that an administrative fine in the amount of $500.00 be assessed. DONE and ORDERED this 30th day of October, 1985 in Tallahassee, Leon County, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 30th day of October, 1985.

Florida Laws (4) 120.57489.105489.115489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROGER S. WILLIAMS, 81-002194 (1981)
Division of Administrative Hearings, Florida Number: 81-002194 Latest Update: Sep. 03, 1982

Findings Of Fact At all times relevant hereto, Respondent, Roger S. Williams, held registered building contractor license number RB0026339 issued by Petitioner, Department of Professional Regulation, Construction Industry Licensing board, authorizing him to perform contracting under his individual name. Respondent, Frederick S. Schreiner, held certified general contractor's license numbers CG C004811 and CG CA04811 also issued by Petitioner authorizing him to perform contracting under his individual name and under Cape Development Corporation. Williams served as president of Architectural Builders, Inc. (ABI), a development firm located in Palm Bay, Florida. Schreiner was engaged in the contracting business generally in the Brevard County, Florida area. He has done construction work for ABI and Williams for the past eight or nine years. ABI held no licenses from either the state or local governments. On October 31, 1979, ABI entered into a construction contract with Jack and Stella Oleksy to construct a home at 842 South Becker Street, Palm Bay, Florida. The contract was approved by R. S. Williams as president of ABI. At a later undisclosed date, Williams attempted to pull a City of Palm Bay building permit on behalf of ABI. Whether the City gave formal or informal approval at that point is not clear; in any event the construction of the home began shortly thereafter. Several weeks later the City's chief building official told Williams that because he did not have local competency with the City, he could not pull a permit for a job. Williams was also advised that a recent change in state law required ABI to qualify to do business if ABI intended to construct homes within the City. When told that Frederick Schreiner would be constructing the home for ABI and that Schreiner held an appropriate license, the City official told Williams to have a construction contract executed between ABI and Schreiner to build the home. Thereafter, Schreiner pulled a permit for the job and posted it on the building site. He also gave the City a contract executed by he and ABI and which was dated November 29, 1979. During the course of the construction, Schreiner visited the building site approximately six to eight times. The work was done entirely by subcontractors who had been used on other construction jobs by Williams and Schreiner. The subcontractors were paid by ABI but worked under the supervision of Schreiner. When the job was completed Williams signed the final payment affidavit on which it was indicated that Williams was the contractor on the job. Oleksy was on the site daily to inspect the work. He complained periodically about various aspects of the job to Roger Williams. His main complaint concerned the trusses on the roof which he contended were out of alignment causing a wavy and uneven roof line. After the house was essentially completed, Oleksy lodged a complaint with Williams concerning the workmanship on the roof. Williams sent a carpenter to visit the premises who found some "variations" and worked for approximately three hours to correct the problem. He was then told by Oleksy it looked okay. Within the next few days, Oleksy again complained to Williams that the roof was wavy. Williams then sent out a roofing crew to attempt to correct the problem. After they completed their work, Williams received no further indication that the owner was unhappy. Williams later had a local relator familiar with the subdivision and an experienced carpenter who had framed more than 150 homes to view the roof. Both concluded the roof was of good workmanship and of similar quality to other homes in the neighborhood. Oleksy later filed a complaint with the City of Palm Bay concerning his roof. The City sent its chief building official to inspect the home. He described the roof as being of "poor workmanship". The same conclusion was reached by the city building inspector who also inspected the property. Because of this, the City made the notation "Hold problem roof" in its file and did not issue a certificate of occupancy to Oleksy. However, the City did not construe the roof to constitute a violation of the building code. Respondents asserted that a 1979 change in the law as to the qualification of agents caused doubt and confusion as to what was required by ABI and Williams. They also point out that if indeed a violation occurred, it was not intentional. Rather, Respondents simply desired to comply with all applicable statutes and regulations so that their construction businesses could continue to operate in a lawful manner. Other than the alleged violations herein, Respondents were not shown to have been subject to any prior disciplinary proceedings.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Roger S. Williams, be found guilty as charged in Count I, and be given a public reprimand. the remainder of the charges should be dismissed. It is further RECOMMENDED that Respondent, Frederick L. Schreiner, be found guilty as charged of all allegations except willfully and deliberately violating a state law, and be given a public reprimand. DONE and ENTERED this 29th day of June, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1982.

Florida Laws (4) 120.57489.119489.127489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs EDUARDO KIRKSEY, 90-007869 (1990)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 14, 1990 Number: 90-007869 Latest Update: Jun. 05, 1992

Findings Of Fact Eduardo Kirksey is licensed as a certified residential contractor, holding license CR C012717. He qualified a corporation known as Modern Construction Company, Inc. (Modern) to engage in contracting.Modern entered into a contract on about July 28, 1986 with Ira Goldstein of 4440 Southwest 32nd Drive, Hollywood, Florida for construction of two-story room addition which would include a family room, bedroom and bath. Modern was to provide the plan by which the addition would be built. A rough sketch of the addition is included on the contract. More specific plans, which are similar to architectural drawings, were thereafter prepared for submission with the building application, which Modern filed with the Broward County Building and Zoning Enforcement Division. The contract was later amended to add a balcony around the second floor of the addition. The plans which are in evidence as Department Exhibit 4 are the second set of plans. According to these plans, the second floor bedroom had a 6" x 6" sliding glass door. The door opened on to a balcony which was created by cantilevered joists consisting of 2" x 10" pieces of lumber bolted to 2" x 12" rafters between the first and second floor. These 2" x 10" members extended out four feet from the building. According to the plans, 2" x 6" decking was to be placed across these joists, and an appropriate railing would then be placed around the balcony. Mr. Kirksey submitted the amended application for the permit and the plan to the Broward County Plan Review Board for approval, and it was approved. After construction began, Mr. Goldstein determined that he did not wish the floor of the balcony to be pressure treated wooden decking. Instead, he wanted a tile floor on the deck. Mr. Kirksey had already filed two sets of plans with Broward County on the project, the first for the addition without the balcony, and the second for the addition with the balcony. He did not want to file a third building permit application which would also require the submission of new drawings. Mr. Kirksey did agree to change the construction to accommodate Mr. Goldstein's desire to tile the balcony but declined to do the tile work himself as part of his contract with Mr. Goldstein. Mr. Goldstein was to arrange for the tiling of the deck. The original design for the decking would have spaced the 2" x 6" lumber which made up the decking with small spaces between each piece of lumber to allow water to fall through during rain. In order to lay tile down, it was necessary to place plywood across the joists, rather than 2" x 6" pressure treated lumber. Before the plywood could be laid, however, Mr. Kirksey had to remove the 2" x 10" cantilevered joists from between the first and second floor, because the original design called for those joists to be level. They were reinstalled at about a 1/2 inch slant so that the water would then drain from the balcony after it had been tiled. In addition, Mr. Kirksey then had to place soffit under the balcony, and put facia around the bottom of the deck. Neither the soffit nor the facia were required in the plans. Although it was more expensive for Mr. Kirksey to add these items, Mr. Goldstein was not charged any additional money for this work. The plywood that was put down over the 2" x 10" rafters instead of the pressure treated 2" x 6" lumber was 3/4 inch exterior grade plywood. Pressure treated plywood was not used because the plywood was to be covered with tile, and if properly tiled, pressure treated plywood is unnecessary. Moreover, even if tile is put over pressure treated plywood, if tile is not laid properly, the pressure treated plywood will rot as well as exterior plywood will rot. It would not have been possible to place tile over the 2" x 6" pressure treated lumber which the amended plan filed with the Broward Building and Zoning Enforcement Division had called for. The 2" x 6" members would shrink and move, causing the tile to crack. Some type of plywood had to be used instead of decking to permit Mr. Goldstein to tile the deck. The 3/4 inch plywood which Mr. Kirksey used met or exceeded the standards established by the South Florida Building Code. No sealant, or paint, was applied to the plywood, nor was the deck covered with visquine. Preparation of the plywood before the tile was placed over it would be the job of the person doing the tile work. An inspector from the Broward County Building and Zoning Enforcement Division visited the site on a number of occasions. During the course of those inspections some of the work was originally rejected by the inspector. For example, the balcony railing pickets had a spacing greater than 5 inches and the top of the rail was only 36 inches high, not 42 inches high. As a result of this rejection, the picket spacing and railing were changed. Ultimately, the inspector gave final approval after having seen the plywood deck, even though no new plans had been submitted to change the deck to have a plywood floor for tile rather than the originally permitted 2" X 6" pressure treated lumber deck. When the job was completed by Modern it was in the condition a project would normally have been left where the contractor was not responsible for laying the tile over the balcony floor. Because the floor was to be tiled, there was no reason for Mr. Kirksey to have painted the balcony floor. In addition, the contract did not require that any painting be done. Mr. Goldstein did the tile work on the deck himself although he had no prior experience in laying tile. Mr. Goldstein spoke with one of Modern's workmen about how to lay tile. This was an informal conversation, and Mr. Kirksey, the contractor, never advised Mr. Goldstein on how to lay tile. I do not accept the testimony of Mr. Goldstein that the employee of Modern who explained to him how to lay tile was the job foreman. Nothing in the contract with Modern required Modern to lay tile, or to advise Mr. Goldstein how to lay tile, so whether the person who discussed laying tile with Mr. Goldstein was a foreman is not significant. Sometime after all the work had been completed by both Modern and Mr. Goldstein, Mr. Goldstein's daughter Evette stepped out onto the balcony, and her foot and leg went through the balcony. This occurred because the plywood had not been sealed or protected before the tile was laid by Mr. Goldstein. As a consequence, the plywood had rotted under the tile. The rot also extended to the supporting joists. Broward County has adopted and incorporated into the Broward County Charter, Chapter 71-575, Laws of Florida, a Special Act of the Legislature. Both adopt for Broward County the "South Florida Building Code, Dade County 1970 edition, as amended." The Department included with its proposed recommended order portions of the South Florida Building Code, 1986 Broward County edition, for the purpose of demonstrating that the conduct of Mr. Kirksey violated Section 301(a) and 302.1(e) of that 1986 code. As a matter of evidence, the 1986 Broward County edition of the Southern Florida Building Code does not appear to apply. The Department's exhibit 7, which is "a copy of the Broward ordinance which adopts the South Florida Building Code" (Tr. 6) shows that it is the South Florida Building Code, Dade County 1970 edition which applies in Broward County. No portion of that document has been offered in the record of this case. As a consequence, there is no record evidence that Mr. Kirksey has violated a portion of an applicable code. It is true that Mr. Joseph Montagnino testified that Section 301(a) of the South Florida Building Code would not permit a change in a plan once it had been approved (Tr. 22, 104). In a case such as this, however, it is necessary for the Department to produce the text of the applicable building code, which has been adopted either by State statute or local ordinance. It cannot prove a violation through the testimony of a witness who merely characterizes his recollection of the text of an authoritative code. Moreover, other witnesses who are experts in construction trades in Broward County testified that it is common for inspectors to approve changes such as that made by Mr. Kirksey here, at the request of Mr. Goldstein, to substitute plywood flooring for pressure treated decking, without the need for amended plans or permits. (Tr. 75-77, 88- 89). Without evidence of the text of the applicable code, it is not possible to determine whether these experts, or Mr. Montagnino are correct. Since Mr. Goldstein, the homeowner, intended to do the tile work, it would not have been Mr. Kirksey's responsibility to pull additional permits for the tile work. At most, Mr. Kirksey's duty might have been to have obtained approval of amended plans, showing the slight pitch of the joists supporting the balcony floor, and the substitution of plywood and tile for 2" X 6" pressure treated lumber as the flooring for the balcony. Mr. Kirksey is in no way responsible for the inadequate preparation of the plywood surface for the application of the tile. Mr. Kirksey is in no way responsible for informal advice given by an employee of Modern, whose identity cannot be determined from the evidence in this case, to Mr. Goldstein about the proper way to prepare the plywood deck for tiling. Tiling was not part of the construction contract which Mr. Goldstein entered into with Mr. Kirksey's company. Mr. Kirksey is therefore not liable for inadequate supervision of employees on the job. Mr. Kirksey's employees performed the work required under the agreement which Modern had with Mr. Goldstein, as the parties amended it after the construction began.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that a Final Order be entered by the Board finding Eduardo Kirksey not guilty of the violations set out in Counts I, II or III of the Administrative Complaint. RECOMMENDED this 24th day of December, 1991, at Tallahassee, Florida. WILLIAM R. DORSEY, JR. Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of December, 1991.

Florida Laws (3) 120.57489.105489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN N. LAMBERT, D/B/A ALLSTATE HOMECRAFTS, INC., 78-000404 (1978)
Division of Administrative Hearings, Florida Number: 78-000404 Latest Update: Oct. 18, 1979

The Issue Petitioner, Florida construction Industry Licensing Board (hereafter FCILB) seeks to revoke the building contractors license of Respondent, John N. Lambert (hereafter Lambert), on the ground that Lambert willfully or deliberately disregarded and violated applicable building codes of Metropolitan Dade County in violation of Section 468.112(2)(a), Florida Statutes. Initially, Lambert was also charged with abandonment of a construction project in violation of Section 468.112(2)(h), Florida Statutes. However, at the hearing, FCILB abandoned the charge.

Findings Of Fact Lambert is the holder of an inactive building contractors license number CBC009927 which legally qualified Lambert to act for Allstate Homecrafts, Inc., a corporation located in Miami, Florida, engaging in contracting work. Lambert was employed by the corporation but was not an officer or shareholder. On June 10, 1976, Lambert initiated a building permit application for work proposed to be done on the home of Mr. Nelson Tower. Mr. Tower had entered into a contract with Allstate Homecrafts, Inc., on June 4, 1976. The contract reflects that Mr. Neal Phillips acted as a corporate representative and not Lambert. The building permit was issued on August 11, 1976. On July 24, 1976, Allstate Homecrafts, Inc., contracted with a Mr. William Millman, and once again the contract reflects that Neal Phillips was the corporate representative and not Lambert. On September 13, 1976, and again on September 30, 1976, Lambert made application for a building permit with she City of Coral Gables, Florida, for the Millman job. Work was commenced on both projects. Work was still in progress on October 26, 1976, when Lambert wrote a letter to FCILB requesting that his qualification as contractor for Allstate Homecrafts, Inc., cease immediately. The reasoning given by Lambert, without further explanation, was that he could "in good conscience no longer comply" with Florida law regarding licensing of construction industry. Lambert further requested in the letter that he be requalified as an individual licensee. On the same date, Lambert terminated his employment with Allstate Homecrafts, Inc. The Tower project continued on until January, 1977, when it was abandoned by Allstate Homecrafts, Inc. The contract price was $30,000.00 and over $25,000.00 in draws were made. Five thousand dollars ($5,000.00) was drawn on November 2, 1977 $5,000.00 wad drawn on November 24, 1976, and $5,000.00 was drawn on December 16, 1976. These occurred after Lambert terminated his relationship with Allstate Homecrafts, Inc. After the contract was abandoned in January, 1977, Tower spent another $23,000.00 to finish the project. The Millman job continued until December, 1976, at which Lire it was abandoned at about 60 percent completion. A $10,000.00 draw was made on November 4, 1976, and a $5,000.00 draw was made on December 2, 1976. Millman spent an additional $10,000.00 to finish the project. Neither Tower nor Millman ever saw Lambert. All monies paid were given to other corporate representatives. While there was some evidence that violations of applicable building codes did occur, there was a complete absence of evidence to establish that Lambert willfully or deliberately disregarded the South Florida Building Code 4501.2(d)(4); failure to correct an electrical hazard. On February 2, 1978, the Dade County Construction Trade Qualifying Board reported that it had found that there was a prima facie showing of the charges brought against Lambert.

# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs CAYETANO F. ALFONSO, 04-004363PL (2004)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 09, 2004 Number: 04-004363PL Latest Update: May 02, 2005

The Issue Whether Respondent, who is licensed as a Plans Examiner, a Building Inspector, and a Building Code Administrator, committed the offenses alleged in the three-count Administrative Complaint and, if so, the penalties if any that should be imposed.

Findings Of Fact Petitioner is the agency of the State of Florida with the responsibility to regulate Building Code Administrators and Inspectors pursuant to Section 20.165, Chapter 455, and Part XII of Chapter 468, Florida Statutes. At all times relevant to this proceeding, Respondent held licenses as a Standard Plans Examiner in Building and Mechanical; a Standard Inspector in Building and Mechanical; and a Building Code Administrator. Section 468.603(1), Florida Statutes, provides the following definitions relevant to this proceeding: Building code administrator" or "building official" means any of those employees of municipal or county governments with building construction regulation responsibilities who are charged with the responsibility for direct regulatory administration or supervision of plan review, enforcement, or inspection of building construction, erection, repair, addition, remodeling, demolition, or alteration projects that require permitting indicating compliance with building, plumbing, mechanical, electrical, gas, fire prevention, energy, accessibility, and other construction codes as required by state law or municipal or county ordinance. This term is synonymous with "building official" as used in the administrative chapter of the Standard Building Code and the South Florida Building Code. . . . Section 468.603(2), Florida Statutes, provides the following definition relevant to this proceeding: (2) "Building code inspector" means any of those employees of local governments or state agencies with building construction regulation responsibilities who themselves conduct inspections of building construction, erection, repair, addition, or alteration projects that require permitting indicating compliance with building, plumbing, mechanical, electrical, gas, fire prevention, energy, accessibility, and other construction codes as required by state law or municipal or county ordinance. Section 468.603(6), Florida Statutes, provides the following definitions relevant to this proceeding: "Categories of building code inspectors" include the following: "Building inspector" means a person who is qualified to inspect and determine that buildings and structures are constructed in accordance with the provisions of the governing building codes and state accessibility laws. * * * (e) "Mechanical inspector" means a person who is qualified to inspect and determine that the mechanical installations and systems for buildings and structures are in compliance with the provisions of the governing mechanical code. Section 468.603(7), Florida Statutes, provides the following definitions relevant to this proceeding: "Plans examiner" means a person who is qualified to determine that plans submitted for purposes of obtaining building and other permits comply with the applicable building, plumbing, mechanical, electrical, gas, fire prevention, energy, accessibility, and other applicable construction codes. Categories of plans examiners include: (a) Building plans examiner. * * * (c) Mechanical plans examiner. Section 468.603(7), Florida Statutes, provides the following definitions relevant to this proceeding: "Building code enforcement official" or "enforcement official" means a licensed building code administrator, building code inspector, or plans examiner. Ramon Melendez, doing business as R.E.M. Roofing, Inc., was not licensed as a construction contractor in Florida at any time relevant to this proceeding. Mr. Melendez was not individually licensed as a construction contractor in Florida at any time relevant to this proceeding. R.E.M. Roofing, Inc., was not qualified as a construction business by any certified or registered contractor in Florida at any time relevant to this proceeding. On or about March 20, 1998, Mr. Melendez, doing business as R.E.M. Roofing, Inc., contracted with Pedro Camacho to re-roof the residence located at 3961 N.W. 170th Street, Miami, Florida, for the sum of $3,000. Mr. Camacho paid Mr. Melendez the agreed sum in cash based on the contract dated March 20, 1998. On or about June 3, 1998, Mr. Melendez, doing business as R.E.M. Roofing, Inc., contracted with Santos Valentin to re- roof the residence located at 4412 N.W. 185th Street, Opa Locka, Florida, for the sum of $2,800. Mr. Valentin paid R.E.M. Roofing, Inc. the sum of $1,400 on June 8, 1998. Mr. Valentin paid Mr. Melendez the additional sum of $800 on June 10, 1998. Both payments, which were by check, were for the roofing work described in the contract dated June 3, 1998. On April 6, 1998, Respondent applied for and obtained a permit for the Camacho roofing work. This permit application was submitted to the Metropolitan Dade County Department of Planning Development and Regulation. Respondent signed the permit application as “the contractor” and inserted his contractor license number and social security number on the application. The application submitted by Respondent on April 6, 1998, was a fraudulent sham. At no time was Respondent the contractor for the Camacho roofing work. Respondent’s action in obtaining the building permit aided and abetted an unlicensed contractor to engage in contracting. On June 8, 1998, Respondent applied for and obtained a permit for the Valentin roofing work. This permit application was submitted to the Metropolitan Dade County Department of Planning Development and Regulation. Respondent signed the permit application as “the contractor” and inserted his contractor license number and social security number on the application. The application submitted by Respondent on June 8, 1998, was a fraudulent sham. At no time was Respondent the contractor for the Valentin roofing work. Respondent’s action in obtaining the building permit aided and abetted an unlicensed contractor to engage in contracting. Miami-Dade County Compliance Investigator Daniel Vuelta filed criminal charges against Respondent in two separate criminal cases. One case was for his involvement in the Camacho roofing project and the other was for his involvement in the Valentin roofing projects. These cases were brought in Miami- Dade County Court and assigned case numbers M99-57926 and M99- 57931. In each case, Respondent was charged with one count of Unlawful Application for Building Permit and one count of Aiding and Abetting an Unlicensed Contractor. All charges were first- degree misdemeanors. On February 22, 2001, Respondent entered into a plea agreement to resolve those criminal charges. Respondent entered a plea of guilty to each of the two counts in Case M99-57931, and he was subsequently adjudicated guilty of each count. As part of the plea agreement, the State agreed to nolle pross Case M99-57926. The crimes to which Respondent entered a guilty plea involved fraudulent building permits and, consequently, were directly related to building code enforcement. Petitioner’s investigative costs for this case, excluding costs associated with any attorney’s time, were $427.29.

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that Petitioner enter a final order finding Respondent guilty of the offenses alleged in Counts I, II, and III. It is further RECOMMENDED that the final order revoke Respondent’s licensure and impose an administrative fine against him in the amount of $3,000. It is further RECOMMENDED that Petitioner order Respondent to pay its investigative costs, excluding costs associated with any attorney’s time, in the amount of $427.29. DONE AND ENTERED this 7th day of April, 2005, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of April, 2005.

Florida Laws (6) 120.5720.165455.227468.221468.603468.621
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL FOWLER, 81-002991 (1981)
Division of Administrative Hearings, Florida Number: 81-002991 Latest Update: Dec. 04, 1990

Findings Of Fact Daniel Fowler, a general contractor licensed in Florida (T. 289), qualified Raben-Pastal, A Joint Venture, under license No. CG CA15439 on August 15, 1980, and renewed the license for the period 1981 to 1983. Petitioner's Exhibit No. 1. At all pertinent times, he was employed as a construction superintendent for Raben-Pastal, at a residential development in the City of Coconut Creek known as The Hammocks at Coconut Creek, Phase II (The Hammocks), and answered to Paul Pariser, president both of Raben Builders and of Pastal Construction, Inc., and himself a general contractor licensed in Florida. Before construction began, Raben-Pastal secured a building permit for a two- story building (No. 280-81), Petitioner's Exhibit No. 2, on February 19, 1981, and for a four-story building (No. 344-81), Petitioner's Exhibit No. 3, on March 4, 1981. Respondent personally signed the applications, listing certificate of competency No. CG CA15439 on each. PLANS CHANGE After work had begun, Raben-Pastal decided on a change of floor plan for the two-story building. Their architect, Donald Bryan, approached James Cowley, Director of Planning and Zoning, and building official for the City of Coconut Creek. Mr. Bryan offered the building official an amended floor plan, but, after discussing it, the two men agreed that new elevations were involved as well as plumbing location changes, which should be reflected on additional drawings. Thereafter, Mr. Bryan "went back and submitted an entirely new set of working drawings and all of the architectural sheets to reflect" (T. 246) the changes. Eight or nine of the twelve pages in the amended application differed from the original application. The only structural change was in the balcony areas. (T. 238.) At the time the change of plans application was submitted on February 27, 1981, Petitioner's Exhibit No. 4, work on the two-story building had progressed through completion of the foundation. STOP WORK ORDER ENTERED On March 2, 1981, Mr. Cowley wrote and had delivered by hand a letter to "Daniel Fowler, Raben/Pastal" in which he stated: Please be advised that until such time that the Revised Plans have been reviewed and approved, permit #280-81 is suspended and that the previously approved plans are to be considered disapproved. All work on the building shall cease immediately. A notice to this effect will be attached to the permit board as of this date. While in all probability a new permit fee will not be necessary the standard plan examination fee shall be required prior to the resumption of work. For your reference, the following are the applicable South Florida Building Code 1/ Sections, 302.1(E), 302.4(H), 303.4 and 304.4 (A)(B). Petitioner's Exhibit No. 5. The following day, Mr. Pariser wrote Mr. Cowley, as follows: In response to your letter of March 2nd, it is our opinion that stopping work on the building under code numbers 301.3, 302.3, 303.4 and 304.4 is invalid. We have contacted both our architect and structural engineer and confirmed that the 2 story revised plans have no revisions to the super structure. Since for the next 3 weeks we are doing nothing but super structure work, and certainly within that time frame, you will have had enough time to process the revised plans, we will continue to build the building as per permit #280-81 with our independent inspector making inspections per the South Florida Building Code requirements. . . Respondent's Exhibit No. 16. Mr. Pariser wrote Mr. Cowley a second letter on March 3, 1981, to the same general effect enclosing a letter signed by the building's architect and an engineer, which "represent[ed] that there are no structural changes outside of a minor slab configuration." Respondent's Exhibit No. 17. On March 4, 1981, Mr. Cowley wrote Mr. Pariser, with a copy to Mr. Fowler, as follows: I am in receipt of your letter of March 3, 1981, wherein you stated the stop work order issued pursuant to my letter of March 2, 1981 was invalid. My position, of course, is that my action was not only valid, but in fact mandated by code. After meeting with your architect, Mr. Bryan, I propose the following solution. The stop work order will remain in effect for Construction only, i.e. steel re-inforcement, concrete, etc. could not be placed. Site work could continue i.e. soil preparation, filling, compacting, placing of batter boards, excavation for footings and forming. If the above meets with your approval, please acknowledge. Respondent's Exhibit No. 15. To this, Mr. Pariser responded the following day with this letter: In response to your letter of March 4th, the construction that we are proceeding with is just the very 1st floor lift of columns. That lift of columns is the same as shown on the plans for permit #280-81. There is no reason why you could not look at the set of plans you now have in your office for permit #280-81 and make a determination on the number of bars, sizing and location of same. I believe there is a total of 23 columns. Independent of this, you have already received a letter from our architect and an independent engineer stating that these columns will remain the same and you will have an independent engineer's inspection signed off on the permit card. My sincere appreciation for your understanding and return of this letter with your signature below acknowledging acceptance. If however, there is any further harassment in this matter, we will have no alternative but to invoke Chapter 71-575 Section 4 a of the South Florida Building Code, which states in part. . ."if any elected or appointed officials prohibit by any means, directly or indirectly, the use of any materials, types of construction and methods of design authorized by the code or alternate materials, types of construction and methods of design approved by the provisions of the Code, then the elected or appointed official may be removed from office for nonfeasance, misfeasance or malfeasance in office". . .Respondent's Exhibit No. 19. On March 10, 1981, the amended plans were approved. After still further correspondence, Mr. Cowley wrote Mr. Pariser, with a copy to Mr. Fowler, advising that "receipt of the required $200.00 Plan Exam Fee. . .re[s]cinded the suspension of Permit #280-81," Petitioner's Exhibit No. 8, effective April 7, 1981. STOP WORK ORDER VIOLATED By the time the stop work order was rescinded, the two-story building's superstructure was finished. No work accomplished before April 7, 1981, differed from that called for in the original plans. Through respondent and others, Raben-Pastal placed steel-reinforced concrete and performed other work in violation of the stop work order, without testing the validity of the order before the Board of Rules and Appeals or by initiating mandamus or other judicial proceedings. Respondent directed and participated in this work deliberately and with awareness that a stop work order was outstanding. At no time between March 2, 1981, and April 7, 1981, was anybody aware of the design defects that later came to light. STRUCTURAL PROBLEMS In late April of 1981, Coconut Creek's Mr. Cowley learned of cracking in concrete slabs around columns in both the two-story and the four-story buildings. By this time, roof slabs on both buildings had been poured, but neither ground slab had been finished. On the city's behalf, Mr. Cowley engaged D. E. Britt & Associates, consulting engineers, to examine the buildings. After Duncan Britt telephoned to say the buildings should be shored, Mr. Cowley orally advised respondent Fowler that shoring was necessary, on May 6 or 7, 1981. SHORING ORDERED On May 7, 1981, Mr. Cowley wrote and caused to be delivered by hand to Paul Pariser a letter in which he stated: I have just received instructions from Mr. Britt of D. E. Britt and Associates to the effect that a minimum of four shores must be placed around ALL columns in the above referenced buildings. Said shores shall be placed immediately and remain in place until such time that the structural adequacy evaluation has been completed. Petitioner's Exhibit No. 10. A copy of this letter reached Mr. Fowler on May 8, 1981. On May 11, 1981, Mr. Pariser replied: I am in receipt of your letter of May 7, 1981, please be advised that even though Raben-Pastal is respecting your wishes as to the reshoring, we would like to know specifically by what basis in South Florida building code you are requesting same. Also, what is the time frame which we can expect to have this lifted? Respondent's Exhibit No. 6. In a separate letter dated May 11, 1981, Mr. Pariser wrote Mr. Cowley: I take exception to the fact that you have predetermined that there are structural deficiencies. According to Mr. Bromley, our structural engineer, both buildings, as they stand now, are structurally sound. We, at Raben-Pastal, will stop work on anything that is related to column and plate slabs until the Britt analysis has been submitted. Respondent's Exhibit No. 8. Also on May 11, 1982, in response to a mailgram from respondent Fowler, Mr. Cowley wrote respondent to the effect that his order requiring shores around columns should not be construed as a stop work order. Respondent's Exhibit No. 7. A mailgram confirmation stamped received May 12, 1981, states, over respondent's name: Per your instructions requiring 4 post shores to be placed around our columns on building C-46 and C-47, Raben-Pastal will immediately commence this remedial work. Respondent's Exhibit No. 5. During this period, the engineers advising Raben-Pastal continued to believe that both buildings were sound and this was communicated to Messrs. Fowler and Pariser. FIRST-STORY CEILING SLAB ESSENTIALLY UNSHORED Mr. Cowley, Duncan Britt, Ron Thomas, and Henry A. Luten, Britt's chief engineer, among others, visited the site of the four-story building on May 14, 1981. The building was 240-feet long and had more than 30 columns; the slab on grade had still not been poured. The upper floors had been shored, possibly in the process of flying the forms, but there were no more than two or three shores in place underneath the lowest slab then poured, i.e., the first-story ceiling. If done properly, shoring would have begun at ground level with shores placed on the concrete pads around the columns; work would have progressed upward floor by floor; and no more than two or three shores a day, on average, would have been dislodged by the contraction and expansion of concrete in response to temperature changes. Shoring upper floors without shoring the bottom floor may have enhanced rather than diminished the risk that the building would fall. On May 15, 1981, Mr. Cowley wrote respondent Fowler, as follows: Yesterday, May 14, Mr. Britt, Mr. Ludin [sic], Mr. Thomas and I made an inspection of the above referenced buildings. We were appal[l]ed to find that our reshoring instructions had not been carried out on the ground floor of the four story building, permit number 344-81. Considering that a potentially hazardous situation exists, you leave me no choice but to issue the following order. YOU SHALL IMMEDIATELY SHORE THE GROUND AND SECOND FLOOR COLUMNS IN THE FOLLOWING MANNER: TWO (2) SHORES ON EACH SIDE AND ONE (1) ON EACH END. ALL SHORES ARE TO BE WEDGED TIGHTLY IN PLACE. GROUND FLOOR SHORES ARE TO BARE [sic] ON FOUNDATION. Failure to comply will result in a Stop Work Order which will remain in effect until such time the engineer of record, Mr. Arthur Bromley, determines what measures are required to correct the existing structural deficiencies. Petitioner's Exhibit No. 11. To this letter Mr. Fowler replied, also on May 15, 1981: Please be advised pursuant to your letter of today, that to the best of my knowledge we proceeded to a completed state, the shoring on both C-46 [the four-story building] and C-47 [the two-story building] per your request on May 7th. It may appear, without further investigation, that for whatever reason some of the shor[e]s may have come loose, however in your letter of May 7th, not received until May 8th, you asked for all columns in both the 2 story and 4 story buildings, with no mention of the bearing on the foundation. As you well know, your letter was untimely since we had poured our slab on C-47 on the 7th of May and have shored from the slab on grade, on certified compacted sub soil to the 1st raised slab. However in this new letter you are only asking for 2 floors of the 4 story building. Am I to understand that that is the total requirement? On May 7th your letter, specific in nature, required only 4 shor[e]s and this new letter requires 6 shor[e]s. Which is it? Respondent's Exhibit No. 10. The last hour of the working day on May 15, 1981, Mr. Fowler ordered all his men to spend shoring the four-story building. Just how much additional time was devoted to shoring was not clear from the evidence. On May 16, 1981, respondent Fowler wrote Mr. Cowley that "we have already expended. . .64 man hours in reshoring these buildings per your specifications." Respondent's Exhibit No. 11. At the final hearing, however, Mr. Fowler testified that, on May 7, 1981, "five men working on the two buildings [did] nothing but shoring. . .four of those men eight hours and one of those men for four hours," (T. 304-305) (May 7: 36 hours); on May 8, 1981, "seven men working on the shoring on the two buildings for a period of time varying between six and eight hours per man," (T. 305) (May 8: 42 to 56 hours); on May 9, 1981, "five men for half a day. . .[did] nothing but shoring on the two buildings," (T. 305) (May 9: 20 hours); on May 11, 1981, "five men working on shoring for a period varying between five hours and eight hours on the two buildings," (T. 306) (May 11: 25 to 40 hours); on May 12, 1981, "six men working on the shoring. . .one man at four hours and one man at five hours and four men at eight hours," (T. 306) (May 12: 41 hours); on May 13, 1981, "five men working on shoring. . .two for four hours and three for eight hours," (T. 306) (May 13: 32 hours); and, on May 15, 1981, seven men each working one hour (May 15: 7 hours). In short, respondent testified at hearing that 203 hours, at a minimum, were spent shoring both buildings from May 7, 1981, through May 15, 1981. This testimony has not been credited because of the witness's interest, because it exceeds by a factor of three the contemporaneous estimate or claim in Respondent's Exhibit No. 11, and because it does not square with the time sheets, Respondent's Exhibit No. 26, or with the progress reports, Respondent's Exhibit Nos. 27 and 28, on which Mr. Fowler purported to base his testimony. Mr. Goode was one of the workmen who eventually placed shores in the four-story building, working from the ground up. Read most favorably to respondent, Mr. Goode's testimony was that two men could shore one floor of the four-story building in seven hours. This, too, supports the view that Mr. Fowler's testimony about shoring was grossly exaggerated. The record is clear, however, that work of some kind, including work that was not shoring nor incident to the load test nor remedial took place on and under the four-story building between May 7, 1981, and May 15, 1981, thereafter. See Respondent's Exhibit Nos. 26-28; Testimony of Goode, Williams, Fowler. LOAD TEST As late as May 16, 1981, Mr. Pariser wrote Mr. Cowley that "Bromley's letter. . .coupled with the inspection reports list. . .should, beyond a doubt, put your mind, and anyone else's mind, at ease that the buildings. . .are structurally sound." Respondent's Exhibit No. 13. About a week later, a load test was begun by a testing laboratory using criteria agreed on by Henry A. Luten for the City and by Arthur H. Bromley for Raben-Pastal. In order to perform the load test, the shoring under two bays was removed and scaffolding was erected in its place. Afterward, the scaffolding was removed and shores were reinstalled. LAWYERS' MISUNDERSTANDING Construction at The Hammocks had received increasingly strident publicity, depressing sales of prospective condominium apartments. Raben-Pastal was concerned that premature disclosure of the results of the load test might aggravate the situation. John R. Young, Esquire, raised the matter with Paul Stuart, Coconut Creek's city attorney. Mr. Young proposed that the city be represented at the test by its consulting engineers but that no city employee observe the test, against the possibility that a Sunshine Law disclosure requirement would result in dissemination of a public employee's notes or report on the load test, before those conducting the test had been afforded time to evaluate the significance of things like cracks. Mr. Stuart agreed to communicate this proposal to Mr. Cowley and did in fact do so. Mr. Stuart left town, and Mr. Young eventually assumed that his proposal had been accepted. That it had been accepted, he told Mr. Pariser in Mr. Fowler's hearing as fact. Messrs. Pariser and Fowler were surprised to learn then, on the day of the load test, that Ron Thomas, chief building inspector of Coconut Creek, had accompanied Benjamin Eigner, an employee of D. E. Britt & Associates, to the site. Raben-Pastal employees confronted Mr. Thomas, at the edge of the property, and Lee Smith radioed Mr. Pariser's office. Mr. Fowler went to the scene of the controversy and Mr. Pariser telephoned the police. After the police arrived and while Mr. Fowler was talking to a policeman, Mr. Thomas started in the direction of the load test being performed on the second floor of the four-story building; Mr. Fowler ran toward the building and physically interposed himself, blocking Thomas's way. At this juncture, Mr. Fowler was arrested. He was eventually acquitted of criminal charges arising out of this episode. BUILDER'S ENGINEER STOPS TEST Mr. Bromley, who was also on site for the load test, recommended to Raben-Pastal that it be stopped before completion, because "the deflection was at a point that if there was anything further, it would cause permanent structural damage." (T. 234.) Most of the engineers involved later came to agree that there was insufficient post-tension cable in the slabs and that there was a "punching shear problem," a 122-percent "over-stress in the punching shear area." (T. 238.) Punching shear occurs when the "concrete that adheres around the column leaves the rest of the floor area or the floor area separates from the concrete that adheres to the column," (T. 235) with the collapse of the building a possible result. Raben-Pastal's own engineer testified at the hearing that, "It was a dangerous situation, yes." (T. 235.) (Widening the columns eventually remedied the problem.) SECOND STOP WORK ORDER ENTERED On May 28, 1981, Mr. Cowley wrote Mr. Pariser that he had visited the site on Sunday, May 25, 1981, found it deserted and "observed that the load test had very prudently been stopped slightly past the half way point." Petitioner's Exhibit No. 12. The letter continued: With this knowledge, I have no choice but to place you on notice that the above referenced buildings are unsafe and constructed in a dangerous manner. Pursuant to section 201.9 of the South Florida Building Code and more specifically the fact that over-stressing and a danger of collapse was emminent [sic] if loading were continued. During a meeting held on May 27, 1981, with Mr. Britt, Mr. Luten, Mr. Rodriguez, Mr. Bromley, Mr. Adams and myself in attendance, Mr. Bromley concluded that all work on the above referenced be stopped, with the exception of remedial repairs and additional testing if necessary until further notice. I am in complete accord and do so order. Petitioner's Exhibit No. 12. By the time Mr. Pariser received this letter, he had already ordered all work stopped on or under both buildings, except for shoring, testing, or remedial work. Neither he nor respondent ever authorized any work in violation of the stop work order of May 28, 1981. On June 1, 1981, the day after respondent returned from vacation, Mr. Thomas visited the site and observed and photographed a workman standing on the ground underneath the four-story building, even though respondent had personally ordered everybody to stay out except for replacing shores as necessary. On or before May 29, 1981, the scaffolding installed for the load test had been removed and most, but not all, of the shores had been replaced. Some rested, however, not on the concrete pads around the columns but on scrap lumber and pieces of plywood. Also on June 1, 1981, at least one workman went underneath the four-story building to fetch a piece of PVC pipe.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's license for six months. DONE AND ENTERED this 3rd day of September, 1982, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of September, 1982.

Florida Laws (1) 489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer