The Issue Whether pursuant to Sections 57.111 or 120.595(1), Florida Statutes, Petitioner Rafael R. Palacios (Palacios) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by the Respondent, Department of Business and Professional Regulation (Department). Whether pursuant to Section 120.595(1), Florida Statutes, Petitioner Steven L. Johns (Johns) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by Respondent.
Findings Of Fact Petitioner, Steven L. Johns, is a Florida Certified General Contractor and the principal qualifier for C. G. Chase Construction Company (Chase Construction). In 1994, Chase Construction entered into a construction contract with Carnival Cruise Lines for an expansion project at the Port of Miami. Chase Construction subcontracted the mechanical work to R. Palacios & Company. Petitioner, Rafael R. Palacios, is the president, primary qualifier, and 100 percent stockholder of R. Palacios & Company. Palacios' principal place of business is located in Miami, Florida. In July and December 1998, Palacios employed less than 25 employees and had a net worth of less than $2,000,000. The contract for the Port of Miami project consisted of two phases. Phase I was to construct an arrival lobby and an enclosed walkway to a terminal. Phase II included the addition of boarding halls, the renovation of an existing elevated area, and the addition of baggage areas. A foundation permit had been pulled for Phase I. The foundation work was quickly completed, and Chase Construction representatives advised both the Port of Miami and Carnival Cruise Lines that they could go no further without a permit. Work stopped for a short period of time. In June 1995, a Representative from the Port of Miami called Chase Construction and told them to go to the Dade County Building and Zoning Department (Building Department) the next day to meet with Port of Miami officials, the architect, and building and zoning officials. Johns sent Dave Whelpley, who was a project manager and officer of Chase Construction. Palacios did not attend the meeting. Dr. Carlos Bonzon (Bonzon) was the director and building official of Dade County's Building Department during the majority of the construction activities at the Port of Miami by Chase Construction. As the building official, Dr. Bonzon gave verbal authorization for the work on the project to proceed above the foundation without a written permit. Inspections were to be done by the chief inspectors for Dade County. After the meeting with the Building Department officials in June 1995, Johns understood that authorization had been given by the building official to proceed with construction without a written permit. Work did proceed and inspections were made on the work completed. The Dade County Building Code Compliance Office (BBCO) had the responsibility to oversee Dade County's Building Department. In early 1996, an officer of the BBCO accompanied a building inspector during an inspection of the Port of Miami project. It came to the attention of the BBCO officer that no written permit had been issued for the project. The BBCO officer notified the chief of code compliance for Dade County. A written permit was issued for Phase II of the Port of Miami Project on February 6, 1996, at which time approximately 80 percent of the work had been completed. On the same date, Chase Construction issued a memorandum to its subcontractors to secure the necessary permits. Shortly after the permits were issued, an article appeared in the Miami Herald concerning the project and the lack of written permits. Respondent, Department of Business and Professional Regulation (Department) became aware of the situation as a result of the newspaper article and began an investigation. Diane Perera (Perera), an attorney employed by the Department since 1993 to prosecute construction-related professional license law violations, played a major role in determining and carrying out the Department's subsequent actions regarding the Port of Miami project and persons licensed by the Department who had been involved in the project. The Department opened investigations against eight Department licensees. Those licensees included two building officials, Bonzon, and Lee Martin; four contractors, Johns, Palacios, Douglas L. Orr, and D. Jack Maxwell; one engineer, Ramon Donnell; and one architect, Willy A. Bermello. By Administrative Complaint prepared by Perera and filed on September 9, 1997, before the Building Code Administrators and Inspectors Board (BCAIB), the Department charged Bonzon with various violations of Part XIII of Chapter 486, Florida Statutes, for having allowed above-grade construction on the project to proceed in the absence of approved plans and building permits. In conjunction with the Bonzon case, Charles Danger (Danger), a licensed professional engineer and Director of BBCO testified in a deposition that above-grade construction of the project had proceeded without a building permit and without approved plans in violation of Chapter 3, Section 301 of the South Florida Building Code. He also testified that Bonzon had exceeded his authority under the South Florida Building Code by authorizing the above-grade construction and that the contractors who performed the work did so in violation of the South Florida Building Code. The Department's charges against Bonzon were resolved through a settlement agreement, whereby Bonzon agreed to relinquish his building code administrator's license. A final order of the BCAIB accepting the settlement agreement was filed on July 2, 1998. In the settlement agreement, Bonzon specifically agreed that his interpretation of the South Florida Building Code provisions, including portions of Section 301, was erroneous. On June 24, 1998, the Department presented the Department's Case Number 97-17322 involving Johns to the Division I Probable Cause Panel (PCP) of the Construction Industry Licensing Board (CILB). The panel members on this date were Gene Simmons and Wayne Beigle. Stuart Wilson-Patton and Leland McCharen, assistant attorneys general, were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the panel was Perera. The Department was requesting a finding of probable cause against Johns for a violation of Section 489.129(1)(d), Florida Statutes, for knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and specifications. Prior to the meeting of the Division I PCP of the CILB, Perera had furnished the two panel members documentary evidence pertaining to the case, copies of which were received in evidence at the final hearing as Respondent's Exhibits 5 and 13, with the exception of a letter dated July 31, 1998, from Petitioners' attorney, Renee Alsobrook. Respondent's Exhibit 5 consisted of materials taken from the Bonzon and Lee Martin cases, including the transcript of the December 22, 1997, deposition of Charles Danger, who was the building officer for the BBCO from 1991 to 1998. Respondent's Exhibit 13 was the investigative file for the Johns' case. The Division I PCP discussed Johns' case and voted to request additional information regarding whether any fast track ordinance existed in Dade County, and if so, how it might have applied to the Port of Miami project. On June 24, 1998, the Division II PCP of the CILB met and discussed the Palacios case, which was designated as the Department's Case No. 97-17313. The members of the panel were James Barge and Richard Cowart. Mr. Wilson-Patton and Mr. McCharen were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the PCP was Perera. The Department was requesting a finding of probable cause against Palacios for violating Section 489.129(1)(d), Florida Statutes, by knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and a building permit. Prior to the Division II PCP meeting, the panel members were provided with materials which were received in evidence at the final hearing as Respondent's Exhibits 5 and 14, with the exception of letters dated July 31 and August 26, 1998, from Renee Alsobrook. Respondent's Exhibit 14 is the Department's investigative file on the Palacios case. Following a discussion of the Palacios case, one of the panel members made a motion not to find probable cause. The motion died for lack of a second, and the panel took no further action on the case that day. Pursuant to Section 455.225(4), Florida Statutes, the case was treated as one in which the PCP failed to make a determination regarding the existence of probable cause and was presented to Hank Osborne, Deputy Secretary of the Department, to make a determination whether probable cause existed. On July 2, 1998, Deputy Secretary Osborne found probable cause, and the Department filed an Administrative Complaint against Palacios, charging a violation of Section 489.129(1)(d), Florida Statutes. The Department never served Palacios with the Administrative Complaint filed on July 2, 1998. The Department did not notify Palacios that the Administrative Complaint had been filed and did not prosecute the Administrative Complaint. At the time the Administrative Complaint was filed, the Department believed that the Legislature was in the process of enacting legislation to repeal Section 489.129(1)(d), Florida Statutes. Chapter 98-419, Laws of Florida, which became law on June 17, 1998, repealed Section 489.129(1)(d), Florida Statutes, effective October 1, 1998. Because of the repeal and the lack of a savings clause for pending cases, the Department determined that as of October 1, 1998, the Department did not have authority to take disciplinary action based on a violation of Section 489.129(1)(d), Florida Statutes. On December 18, 1998, the Department presented the Department's Case Nos. 97-17133 and 97-1732 to the PCPs for a second time with a recommendation to find probable cause that Johns and Palacios had violated Section 489.129(1)(p), Florida Statutes, for proceeding on any job without obtaining applicable local building permits and inspections. Mr. McCharen was present to provide legal advice to the PCPs. Ms. Perera was also present during the meetings of the PCPs. Documentary materials presented to the PCP considering Palacios' case included the materials on the Bonzon and Martin cases which had been previously presented to the PCP panel in June 1998 and the investigative files on Palacios. The investigative file included letters with attachments from Palacios' attorney Rene Alsobrook concerning the materials contained in the Bonzon and Martin cases as they related to Palacios and the investigative file on Palacios. Additionally, the investigative file contained a report from Frank Abbott, a general contractor who had been asked by the Department to review the file on Palacios. Mr. Abbott concluded that Palacios had violated several provisions of Chapters 489 and 455, Florida Statutes, including Section 489.129(p), Florida Statutes. The PCPs found probable cause in the Johns and Palacios cases. On December 23, 1998, the Department filed administrative complaints against Palacios and Johns alleging violations of Section 489.129(1)(p), Florida Statutes. The cases were forwarded to the Division of Administrative Hearings for assignment to an administrative law judge. Palacios and Johns claimed that they were relying on the authorization from Bonzon when they proceeded on the above-grade construction work. No formal administrative hearing was held on the administrative complaints filed on December 23, 1998. On December 18, 1998, a Recommended Order was issued in the related case against Lee Martin, Department Case No. 97-11278, finding that Mr. Martin, the building official who replaced Bonzon and assumed responsibility for the Port of Miami project, had the discretion to allow the remaining construction to proceed while taking action to expedite the plans processsing. A Final Order was entered by the Department dismissing all charges against Mr. Martin. On February 26, 1999, Petitioners Palacios' and Johns' Motions to Dismiss and Respondent's responses were filed. The Motions to Dismiss did not request attorney's fees or costs and did not reference Section 120.595(1), Florida Statutes. The motions did contain the following language: The DBPR has acted in an improper and malicious manner by precluding the Respondent from asserting his response to the second draft Administrative Complaint and requesting the Panel to find probable cause for reasons other than whether there was probable cause to believe the Respondent violated specific disciplinary violations. On March 19, 1999, the cases were consolidated and noticed for hearing on May 12-13, 1999. Section 489.129, Florida Statutes, was amended during the 1999 legislative session to provide: A contractor does not commit a violation of this subsection when the contractor relies on a building code interpretation rendered by a building official or person authorized by s. 553.80 to enforce the building code, absent a finding of fraud or deceit in the practice of contracting, or gross negligence, repeated negligence, or negligence resulting in a significant danger to life or property on the part of the building official, in a proceeding under chapter 120. . . . On April 15, 1999, the Department filed a Motion for Leave to Revisit Probable Cause Panel and to Hold in Abeyance. On April 20, 1999, Petitioners filed a response, stating they did not object to the granting of the motion to hold in abeyance. The final hearing was cancelled, and the cases were placed in abeyance. On May 24, 1999, the Department submitted a Status Report, stating that the cases would be placed on the next regularly scheduled PCP meeting scheduled for June 16, 1999. By order dated May 25, 1999, the cases were continued in abeyance. On July 1, 1999, Palacios and Johns filed a Status Report, indicating that the cases would be presented to the PCPs sometime in July and requesting the cases be continued in abeyance for an additional 30 days in order for the parties to resolve the issues. On July 30, 1999, Palacios and Johns filed a Status Report, stating that the cases were orally dismissed on July 28, 1999, and that a hearing involving issues of disputed facts was no longer required. Based on Johns' and Palacios' status report, the files of the Division of Administrative Hearings were closed by order dated August 3, 1999. No motion for attorney's fees and costs was filed during the pendency of the cases at the Division of Administrative Hearings. On August 3, 1999, orders were entered by Cathleen E. O'Dowd, Lead Attorney, dismissing the cases against Palacios and Johns.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the documentary evidence received and the entire record compiled herein, I hereby make the following findings of fact: Respondent is, and has been at all times material hereto, a certified building contractor, a registered mechanical contractor and a certified air conditioning contractor in the state of Florida having been issued license numbers CB-CA09793, RM-0031246 and CA-C024348, respectively. At all times material hereto, Respondent's building contractor and air conditioning contractor licenses qualified George E. Bonsino and Associates, Inc., Jacksonville, Florida. In February 1984, Respondent contracted with Carl and Patricia Powers of 4530 Victor Street, Jacksonville, Florida for the construction of a room addition. The contract was presented to the Powers by Peter Stamires. Mr. Stamires was, at the time, acting as sales manager for George E. Longino and Associates, Inc. The contract price was approximately $13,000.00 and construction of the Powers' room addition was estimated to be completed by March 30, 1984. On March 20, 1984 Respondent received from Carl and Patricia Powers a payment of $6,850.00 on the contract. On May 4, 1984 Respondent received from Carl and Patricia Powers an additional payment of $5,000.00 on the contract. The contract called for a "dry-in room" only, i.e., the room was to be put to a stage where water would not penetrate it. The contract also included: (1) covering the existing asbestos shingles with a cut brick and stone veneer; (2) the installation of aluminum windows; (3) the installation of aluminum gables and eaves; (4) re-roofing the entire home; and (5) the installation of overhead lights, light switches and electrical outlets. Respondent's contract with the Powers contemplated that electrical work would be done, but did not include any plumbing. Respondent sub-contracted the Powers' project to two (2) individuals, Mr. Walker and Mr. Todd. Respondent did not know what type of license Mr. Walker or Mr. Todd held and was never shown a license by either individual. Mr. Walker agreed to obtain permits for the Powers' project, to submit building plans and specifications, and to request the mandatory building inspections. Neither the Respondent nor the sub-contractors obtained a City of Jacksonville building permit prior to commencing construction of the Powers' room addition. Neither Respondent nor the sub-contractors submitted building plans and specifications for approval by the, City of Jacksonville Building Department prior to commencing construction at the Powers' residence as required. Neither Respondent nor the sub-contractors requested the City of Jacksonville Building Department to perform any type of building inspections during the process of construction, as required. On June 11, 1984 Respondent obtained building permit no. 7048 from the City of Jacksonville Building and Zoning Inspection Division for the Powers' project. Shortly after construction commenced, the Powers became concerned with the quality of work being performed. Respondent, while at the project site near the end of March, told Mr. Powers that a building permit had been obtained for the project. However, at that time, no building permit had been obtained. Mr. Theron Brannan, a building inspector for the City of Jacksonville, became involved with the Powers' case when Mrs. Powers called in May 1984 and complained about ;he work being performed by Respondent. Mr. Brannan checked and found that no permit had been issued. He then went out and inspected the construction site. Mr. Brannan found that the walls were approximately 3 or 4 inches out of alignment and that the floor was spongy and needed repair. Major work would have been required to straighten the walls. In Mr. Brannan's opinion, the work was well below average and was of very poor quality. Electrical and plumbing work was performed at the Powers' project site. Ten (10) electrical outlets, six (6) overhead lights and six (6) light switches were installed. The electrical work also included a 220 volt outlet for a clothes dryer. Mrs. Powers is a housewife and was present during the time the electrical work was performed. The individual performing the electrical work told Ms. Powers that he worked for Respondent and was being paid on an hourly basis. The plumbing work performed at the Powers' project included: (1) installation of hot and cold water lines for the bathroom sink, which were tied into the existing water supply; (2) a water line to the toilet, and (3) a drain pipe from the toilet to the existing septic tank. The individual performing the plumbing work told Ms. Powers that he worked for Respondent on an hourly basis and that he was a licensed plumber. When Respondent was advised of the problems at the construction site, he immediately obtained the necessary permits and offered to correct some of the building problems. The Powers refused Respondent's offer to correct the problems because they were concerned as to whether the remedial measures proposed by Respondent were actually feasible. From an appearance standpoint, the measures contemplated by Respondent were not feasible. In April 1984, Respondent contracted with Glenn and Debora Blanchard of 521 Astral Avenue, Jacksonville, Florida for the construction of a room addition. The total contract price was $6,780.00. Respondent received $3,390.00 as a down payment on the contract; the balance was due upon completion. The contract called for the construction of a room addition between the existing home and the garage. The room addition was to be completed to the "dry-in" stage only. The contract also included re-roofing the entire residence. The Respondent sub- contracted the Blanchard project to a person by the name of A. Rhoden. Mr. Rhoden agreed to obtain all permits, draw all plans and specifications and obtain all required inspections with the exception of the roofing aspects of the project. Neither Respondent nor the sub-contractor obtained a building permit prior to commencing construction at the Blanchard's residence as required. Neither Respondent nor the sub-contractor submitted building plans and specifications to the City of Jacksonville Building Department prior to commencing construction. Neither Respondent nor the sub-contractor requested the building department perform any type of building inspections during the process of construction In May 1984, Ms. Blanchard became concerned because the concrete slab appeared uneven and had developed a crack. She contacted the City of Jacksonville Building Department because she was concerned with the quality of the work being performed. On May 30, 1984 the City of Jacksonville Building Department and Zoning Inspection Division issued a stop work order on construction work being performed at the Blanchard residence. The Notice of Violation cited the failure to submit building plans and failure to obtain a building permit prior to commencing construction at the project site. On June 11, 1984 Respondent obtained building permit no. 7047 from the City of Jacksonville Building and Zoning Inspection Division for the construction work at the Blanchard residence. Such Permit was obtained after commencement of the project. Shortly after commencement of construction, Respondent met with Mr. Blanchard at the project site to discuss a few changes to the original plans. In late April, 1984, Respondent told Mr. Blanchard that a building permit had been obtained, when in fact, no building permit had been obtained. Respondent told Mr. Blanchard that the permit needed to be kept at his office. The construction of the room addition included the forming and pouring of a monolithic slab. The City building department inspects the excavation of the slab prior to the pouring of concrete. A tie-beam inspection is required after the foundation is poured and the masonry walls are erected. Neither inspection was performed nor requested. The Respondent told Mrs. Blanchard that two (2) inspectors had inspected the property, when in fact no inspectors had inspected the property because no building permit had been applied for at the time Respondent made such statement. Unless a building permit is obtained, the City is generally not aware that a construction project is being undertaken and, therefore, does not conduct building inspections. Lewis D. Franks, an expert in residential construction inspected the work done at the Blanchard's home on behalf of the City of Jacksonville Building Department. Several problems existed in regard to the Blanchard project. There was a large crack in the concrete which resulted from the settling of the southeast corner of the building. The settling of the southeast corner resulted from either an inadequate footing or none at all. Also, the roof rafters were not centered properly and were about fourteen (14) feet off. The Blanchard project was of very poor workmanship, the construction was not structurally sound, and the project failed in several respects to meet requirements of the City of Jacksonville Building Code. When Respondent found out that no permit had been obtained he promptly drew up plans and specifications and obtained a permit from the City of Jacksonville Building Department. The Blanchards, thereafter, refused to allow Respondent to continue working on the project. The roofing portion of the Blanchard project was sub- contracted by Respondent to Richard Davenport. Mr. Davenport holds a state license as a roofing contractor and a local occupational license. Mr. Davenport's sub-contract called for him to tear off the existing roof, carry off the rotten wood and put on a new roof. Respondent was not satisfied with the roofing job done by Mr. Davenport and failed to pay him for such roofing job. Thereafter, Mr. Davenport demanded payment from the Blanchards but they also refused to pay him. Mr. Davenport filed a Claim of Lien against the Blanchards' property. However, the Blanchards hired an attorney and the Claim of Lien was dismissed. Respondent's failure to pay Mr. Davenport was based on his good faith belief that the roofing job was not done in a satisfactory manner.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent be found guilty of failing to supervise the construction activities of the company which he qualified and incompetence in the practice of contracting as alleged in Count One of the Amended Administrative Complaint. It is further recommended that all other alleged violations contained in Count One of the Amended Administrative Complaint be dismissed. That Respondent be found guilty of failing to supervise the construction activities of the company which he qualified and incompetence in the practice of contracting as alleged in Count Two of the Amended Administrative Complaint. It is further recommended that all other alleged violations contained in Count Two of the Amended Administrative Complaint be dismissed. That Count Three of the Amended Administrative Complaint be dismissed, the Petitioner failing to introduce any evidence in regard to Count Three and requesting that it be dismissed. It is further RECOMMENDED that Respondent's building contractor's license be suspended for a period of 6 months and that an administrative fine in the amount of $500.00 be assessed. DONE and ORDERED this 30th day of October, 1985 in Tallahassee, Leon County, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 30th day of October, 1985. * Count Three of the Administrative Complaint was voluntarily dismissed by Petitioner and, in any event, was not established by the evidence. COPIES FURNISHED: Douglas Beason, Esq. Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 M. Carolyn Givens 8741 Free Avenue Jacksonville, Florida 32211 Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, Esq. General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan Executive Director Department of Professional Regulation O. Box 2 Jacksonville, Florida 32202 APPENDIX Pursuant to Section 120.59(2), Florida Statutes (1983), the following is submitted in response to Petitioner's and Respondent's Proposed Findings of Fact: Petitioner's Proposed Findings of Fact: Paragraph Ruling (general finding) Accepted; see paragraph 1, R.O. Accepted; see paragraph 2, R.O. (DPR Case #0049083) Accepted; see paragraph 3, R.O. Accepted; see paragraph 3, R.O. Accepted; see paragraphs 5, 6 and 7, R.O. Partially accepted; see paragraphs 4 & 11 Petitioner's proposed finding "the individual performing the electrical work was Respondent's employee and was being paid on an hourly basis" is rejected on the basis that the evidence presented on that issue consisted of uncorroborated hearsay which did not fit within any recognized exception to the hearsay rule. Partially accepted; see paragraphs 4, 7, 11 and 12, R.O. Petitioner's finding that "the plumbing work was performed by Respondent's employee" is rejected on the basis that the evidence presented on that issue consisted of uncorroborated hearsay. Accepted; see paragraphs 9 and 10, R.O. Accepted; see paragraph 10, R.O. Accepted; see paragraph 13, R.O. Accepted; see paragraph 13, R.O. (DPR Case #0049788) Accepted; see paragraph 14, R.O. Accepted; see paragraphs 15, 16, 17 and 23, R.O. Accepted; see paragraphs 17 and 22, R.O. Partially accepted; see paragraph 17, R.O. Facts not covered by paragraph 17are rejected as irrelevant and immaterial. Accepted; see paragraphs 18 and 19, R.O. Partially accepted; see paragraphs 21 and 23, R.O. Facts not covered therein are rejected as irrelevant and immaterial. Accepted; see paragraph 24, R.O. Accepted; see paragraph 24, R.O. Respondent's Proposed Findings of Fact Finding: Ruling: Accepted; see paragraph 3, R.O. Accepted; see paragraphs 4 and 5, R.O. Accepted; see paragraphs 5, 6, 7 and 13. Partially accepted; see paragraph 13. Findings not covered therein are rejected as irrelevant and immaterial. Rejected as irrelevant and immaterial. Accepted; see paragraph 13, R.O. Rejected as a conclusion of law. Accepted; see paragraph 14, R.O. Respondents claim that the contract called for the construction of a dry-in addition and not a "room addition" is considered immaterial. Accepted; see paragraph 14, R.O. Accepted; see paragraph 26, R.O. Accepted; see paragraph 25, R.O. Accepted; see paragraph 25, R.O. Rejected as irrelevant. Accepted; see paragraph 25, R.O. Rejected as a conclusion of law. ================================================================ =
The Issue At the commencement of formal hearing, Petitioner voluntarily dismissed Paragraphs 5 and 7 of the pending Administrative Complaint, and the formal hearing proceeded upon Paragraphs 1-4 and 6 of the Administrative Complaint. The Department of Professional Regulation prosecuted Respondent for one count of the following enumerated alleged violations: Sections 489.129(1)(d), willful or deliberate disregard of building codes; (j), failure in any respect to comply with the Act; (m), fraud, deceit, or gross negligence; and 489.105(4), Florida Statutes, all of which arise out of a single incident.
Findings Of Fact At all times material to the Administrative Complaint, Respondent, Leonardo Sanchez, was licensed by the State of Florida as a certified general contractor holding license numbers CG C004810 and CG CA04810. Robert G. Wolf, Investigator Specialist II with Petitioner, investigated a complaint made by Mirta Garcia against a contractor named Leonardo Sanchez. Ms. Garcia told him she had entered into a contract with a Mr. Sanchez; that she had paid Sanchez a sum of money for an addition to her house; that Sanchez never supplied her a written contract; and that Sanchez pulled a permit for the work and never completed it. Ms. Garcia did not appear and testify at formal hearing and her representations to Mr. Wolf are mere hearsay. They do, however, supplement or explain other competent proof. Mr. Wolf spoke with a Mr. Sanchez who, in Mr. Wolf's words "acknowledged the contractual relationship with the Garcias." (TR-15) Mr. Wolf visited Ms. Garcia's home and determined that a job of construction had been begun there but that interior work had yet to be completed. John Delaney is Assistant Chief Code Enforcement Officer for the Board of Rules and Appeals for the Building and Zoning Department, Dade County. He also visited the Garcia home and on August 18, 1987 it was approximately 80 per cent complete, in his opinion. He presented as a certified business record, a building permit application for an owner "Mirta Garcia" by "Caribean Window" [sic] applied for in the name of Leonardo Sanchez, dated "accepted 12/9/85," and carrying the contractor number CGC004810 and the social security number 109-42- 4859 (P-2). The contractor number and social security number on the application match Respondent's contractor's license and social security number. "Caribbean Window" is one of the entities for which Respondent is the registered qualifying agent. Dade County Ordinance 57-22 establishes that the South Florida Building Code was in effect in Dade County at all times material to this Administrative Complaint. Section 305.2(a) of the South Florida Building Code establishes a mandatory duty for the permit holder to obtain a reinforcing inspection. Mr. Delaney also presented a certified computer printout of a Building Inspection log or record (P-3) showing that no one, including Respondent, had obtained the required reinforcing inspection related to the Garcia job as of the date of the computer inquiry. The computer printout reflects the dates of other inspections and the date and number of the application to which it pertains; it does not clarify when Mr. Delaney made his computer inquiry but a reasonable inference is that it was made the date of his visit to the Garcia home, August 18, 1987. No reason was presented to excuse Respondent as permit holder from obtaining the appropriate inspection.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating Section 489.129(1)(d), assessing an administrative fine therefor of $250.00, and dismissing the remaining charges. DONE and RECOMMENDED this 29th day of December, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of December, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-3445 The following constitute specific rulings upon the parties' respective proposed findings of fact (PFOF) pursuant to Section 120.59(2), Florida Statutes. Petitioner's PFOF 1-7 are accepted as modified to reflect the evidence of record. Respondent's PFOF Respondent submitted no proposals. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 G. W. Harrell, Esquire, and Donald Osterhouse, Qualified Representative Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Leonardo Sanchez 12700 Southwest 37 Street Miami, Florida 33175 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
The Issue Whether or not upon inspection conducted by the Petitioner on February 26, 1976, the Respondent failed to have installed exit lights, signs, and globes for the first and second floors, in violation of Section 509.211(2), Florida Statutes and Rule 7C-1.04(3), Florida Administrative Code. Whether or not upon inspection conducted by the Petitioner on February 26, 1976, the Respondent failed to provide a handrail installation from the second to the first floor in violation of Rule 7C-1.03(1), Florida Administrative Code.
Findings Of Fact The Respondent now holds, and on February 26, 1976, held license no. 23-893H, with the State of Florida, Department of Business Regulation, Division of Hotels and Restaurants. An inspection conducted by inspectors for the Petitioner on February 26, 1976, done at the Florence Apartments, 710 Northeast 127th Street, North Miami, Florida, revealed globe lights in the areas of the exits of the first and second floors. These lights were white in color and did not indicate by writing that the areas illuminated were in fact exits. There were no other signs or apparatuses indicating the areas as exits. Inspection on that same day, to wit, February 26, 1976, and in the same location revealed that the rear stairwell within the subject building, within the first and second floors of the building, did not have a handrail presently installed on that rear stairway as called for in Rule 7C-1.03(1), Florida Administrative Code. There had been a handrail there before, but it was removed prior to the inspection. The rear stairs were flanked on one side by a full wall running from the floor to the ceiling, and by a parallel waist high wall opposite the full wall, which may be described as a banister. This banister wall was approximately 4" thick, running the length of the stairs, with a flat surface atop the banister. The flat surface spoken of does not serve the function of a handrail. The subject building was constructed prior to January 1, 1970 and is an apartment house within the meaning of Chapter 509,F.S.
Recommendation It is recommended that a fine in the amount of $100.00 be imposed in lieu of suspension or revocation, for the violation as established in count two of the complaint. DONE and ENTERED THIS 8th day of October, 1976, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: George A. Frix Owner 365 Northeast 125th Street North Miami, Florida 33161 Charles F. Tunnicliff, Esquire Division of Beverage The Johns Building 725 Bronough Street Tallahassee, Florida 32304 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF BUSINESS REGULATION DIVISION OF HOTELS AND RESTAURANTS STATE OF FLORIDA, DIVISION OF HOTELS AND RESTAURANTS, Petitioner, vs. CASE NO. 76-1727 FILE NO. 23-893H ROBERT J. GROVER, TRUSTEE, t/a THE FLORENCE APARTMENTS, Respondent. /