The Issue Petitioner, Florida construction Industry Licensing Board (hereafter FCILB) seeks to revoke the building contractors license of Respondent, John N. Lambert (hereafter Lambert), on the ground that Lambert willfully or deliberately disregarded and violated applicable building codes of Metropolitan Dade County in violation of Section 468.112(2)(a), Florida Statutes. Initially, Lambert was also charged with abandonment of a construction project in violation of Section 468.112(2)(h), Florida Statutes. However, at the hearing, FCILB abandoned the charge.
Findings Of Fact Lambert is the holder of an inactive building contractors license number CBC009927 which legally qualified Lambert to act for Allstate Homecrafts, Inc., a corporation located in Miami, Florida, engaging in contracting work. Lambert was employed by the corporation but was not an officer or shareholder. On June 10, 1976, Lambert initiated a building permit application for work proposed to be done on the home of Mr. Nelson Tower. Mr. Tower had entered into a contract with Allstate Homecrafts, Inc., on June 4, 1976. The contract reflects that Mr. Neal Phillips acted as a corporate representative and not Lambert. The building permit was issued on August 11, 1976. On July 24, 1976, Allstate Homecrafts, Inc., contracted with a Mr. William Millman, and once again the contract reflects that Neal Phillips was the corporate representative and not Lambert. On September 13, 1976, and again on September 30, 1976, Lambert made application for a building permit with she City of Coral Gables, Florida, for the Millman job. Work was commenced on both projects. Work was still in progress on October 26, 1976, when Lambert wrote a letter to FCILB requesting that his qualification as contractor for Allstate Homecrafts, Inc., cease immediately. The reasoning given by Lambert, without further explanation, was that he could "in good conscience no longer comply" with Florida law regarding licensing of construction industry. Lambert further requested in the letter that he be requalified as an individual licensee. On the same date, Lambert terminated his employment with Allstate Homecrafts, Inc. The Tower project continued on until January, 1977, when it was abandoned by Allstate Homecrafts, Inc. The contract price was $30,000.00 and over $25,000.00 in draws were made. Five thousand dollars ($5,000.00) was drawn on November 2, 1977 $5,000.00 wad drawn on November 24, 1976, and $5,000.00 was drawn on December 16, 1976. These occurred after Lambert terminated his relationship with Allstate Homecrafts, Inc. After the contract was abandoned in January, 1977, Tower spent another $23,000.00 to finish the project. The Millman job continued until December, 1976, at which Lire it was abandoned at about 60 percent completion. A $10,000.00 draw was made on November 4, 1976, and a $5,000.00 draw was made on December 2, 1976. Millman spent an additional $10,000.00 to finish the project. Neither Tower nor Millman ever saw Lambert. All monies paid were given to other corporate representatives. While there was some evidence that violations of applicable building codes did occur, there was a complete absence of evidence to establish that Lambert willfully or deliberately disregarded the South Florida Building Code 4501.2(d)(4); failure to correct an electrical hazard. On February 2, 1978, the Dade County Construction Trade Qualifying Board reported that it had found that there was a prima facie showing of the charges brought against Lambert.
The Issue The issue presented is whether Respondents are guilty of violating Section 471.033(1)(g), Florida Statutes, and if so, what penalty should be imposed?
Findings Of Fact At all times material to the allegations in the Administrative Complaint, Julian Irby was a licensed Professional Engineer with license number PE 43316 and Irby Engineering & Construction, Inc., held Certificate of Authorization #9511 issued by the Board of Professional Engineers. Mr. Irby has been licensed in the State of Florida as a professional engineer since 1990 and spent 21 years in the United States Navy Civil Engineer Corps. He is also a licensed general contractor. Respondent Irby was the engineer of record, with the firm name on the title block of plans for a residential construction project described as, "House Relocation, Foundation Design, 1000 Blk La Paz St., Pensacola, FL" (the relocation project). On or about June 2, 2004, Irby signed and sealed page one of one with a site plan and foundation pier detail for House Relocation at 1000 La Paz Street, and filed it with the Building Inspections Department of Escambia County (Building Department). On or about June 7, 2004, Irby signed and sealed page one of one with a site plan and foundation pier detail for House Relocation at 1000 La Paz Street, and filed it with the Building Department. On or about June 25, 2004, Irby signed and sealed six of six pages of plans (the June 25 plans) for House Relocation at 1000 La Paz Street, and filed them with the Building Department. Permitting for the project was performed in a two- step process, with a preliminary foundation plan submitted before the house was moved from the old site in order to obtain a moving permit and foundation permit. After those permits were issued, Respondents received test results from a geotechnical firm that caused some alteration in the design of the footings to accommodate the water table at the new site. The plans upon which the building permits were ultimately issued and which were used by the construction crew in the building process were the June 25 plans. On or about February 1, 2005, Irby signed and sealed seven of seven pages of plans for House Relocation at 1000 La Paz Street, and filed them with the Building Department on February 24, 2005. The seven pages of plans for the House Relocation signed and sealed February 1, 2005, and filed with the Building Inspections Department of Escambia County on February 24, 2005, represent the relocation project as completed. Changes made during construction and approved in the field are reflected in this set of plans. The Florida Building Code 2001, as amended 2003, is applicable to this case. The relocation project involved moving an existing home from Perdido Bay to a location several hundred feet further inland. The house was an elevated structure at the original location and was elevated at the La Paz address. Respondent Irby was not only the engineer of record but was also the contractor for the project. Certain features of the construction and design of the original structure were not known at the time the original plans were submitted for the foundation. For example, there was a façade that hid from view the I-beam, stringers and pipe posts under the floor of the home. These features could not be seen until the façade was removed in preparation for the move. Relocation projects are subject to certain exceptions under the Florida Building Code. Some design specifications normally required when building a house are not required for a relocation project, because the existing structure need not be redesigned or brought up to code as long as it meets conditions specified in Florida Building Code Section 101.4.2.3. There is no allegation that those conditions were not met in this case. The primary requirement for a relocation design is foundation plans sealed by a professional engineer or architect, if required by the Florida Building Code for residential buildings or structures of the same occupancy class. Respondents' plans filed with the Escambia County Building Inspections Department included foundation plans. Both witnesses testifying for the Petitioner stated that they did not review or prepare any calculations related to the plans and there was no evidence presented that the Building Department had required the calculations to be submitted with the plans. James Lane, who testified on behalf of the Petitioner, acknowledged that there is nothing in the Florida Building Code to prevent an engineer from using the dead weight of the house on the piers and the friction it creates as a method of construction. If the dead load of the house and the friction transfer from the house to the top of the piers is sufficient to address the lateral wind requirements, then straps (also referred to as connectors) would not be necessary to meet the requirements of the Florida Building Code. The main wind force resisting system for the relocation project was the embedment of the foundation piers in the fiberglass reinforced slab and continuous footing in the garage area. Page 6 of the June 25 plans specifies a four-inch minimum monolithic concrete slab with fiberglass reinforcement, using 3,000 PSI concrete, as well as number 4 rebar throughout the footings. There is no requirement that the exact location of rebar splicing be noted on the plans, and the plans are not deficient for failing to provide that information. Moreover, the Florida Building Code requires that a minimum of 2,500 PSI concrete be used. Respondents' design exceeded this requirement. Respondent Irby performed calculations, using the dead load weights in Florida Building Code Appendix A, that showed that the dead load of the existing house sitting on piers with the friction it created was more than sufficient to withstand the required lateral wind load. Mark Spitznagel, P.E., reviewed both the plans and the calculations and visited the construction site. He opined that the calculations showing wind loads could be supported using dead load friction between the house and the piers were correct, and that the Florida Building Code does not require an engineer to explain that no connector, or strap, is required under this circumstance. His testimony is credited. Despite the fact that no connectors were actually required, page six of the June 25 plans included directions for connectors that were used to provide additional support. The Administrative Complaint alleges that the plans do not provide adequate guidance for transfer of horizontal wind loads from the house to the supporting piers and posts or how the supporting piers and posts are to resist imposed loads from the house. The evidence presented at hearing did not indicate what information the Petitioner believed would be sufficient to meet the applicable standard of care. Moreover, the evidence presented supports the conclusion that the metal posts were never intended to transfer lateral wind loads, but were to support vertical loads. The metal posts were part of the existing house and not subject to redesign under the exemption afforded in Florida Building Code Section 101.4.2.3. Shear walls were not considered in the calculations performed by Irby. However, the June 25 plans included shear walls around the garage area, which served to provide extra support over and above what would be required by Irby's calculations. The detail provided on page 6 of the June 25 plans provided a clear load path from the foundation through the shear walls to the upper original structure. The June 25 plans admittedly do not provide wall thickness or metal yield strength for the pipe posts, nor weld attachment, size or thickness for top and bottom plates for the pipe posts. This information is not provided because the pipe posts were part of the original structure and there was no need to redesign them or include them in the foundation plans. The slab beneath the structure was also shown on sheets 1-3 and 6 of the June 25 plans. The slab characteristics are shown in the monolithic footing detail. The upper floor framing members, including the floor joists and the stringers and the I-beam atop the pipe posts were part of the original house design. The house was elevated at its original location, and the stringers, I-beam and pipe posts were part of the original structure. These components did not need to be shown on the plans because of the exemption provided in Florida Building Code Section 101.4.2.3. Respondents did not include main wind force resisting loads for the structure because the Florida Building Code does not require them to be shown for residential, as opposed to commercial, projects. Based on the evidence presented, only component and cladding pressures are required to be shown on the plans, and page 6 of the June 25 plans clearly provides this information. In accordance with Florida Building Code Section 1606.1.7, wind loads for components and cladding were provided showing that the structure was designed to withstand winds up to exposure category D, at 140 miles per hour. The house was actually moved and put in place on the foundation piers three days prior to Hurricane Ivan. Hurricane Ivan was a major hurricane causing extensive damage to the Pensacola area. According to the National Weather Service's Tropical Cyclone Report for the storm, Perdido Key was "essentially leveled." The house relocation project sustained no structural damage in Hurricane Ivan.
Recommendation Upon consideration of the facts found and conclusions of law reached, it is RECOMMENDED: That the Administrative Complaint against Respondents be dismissed. DONE AND ENTERED this 29th day of August, 2006, in Tallahassee, Leon County, Florida. S LISA SHEARER NELSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 2006. COPIES FURNISHED: Bruce Campbell, Esquire Florida Engineers Management Corporation 2507 Callaway Road, Suite 200 Tallahassee, Florida 32303-5267 A. G. Condon, Jr., Esquire Emmanuel, Sheppard & Condon 30 South Spring Street Post Office Drawer 1271 Pensacola, Florida 32596 Paul J. Martin, Executive Director Board of Professional Engineers Department of Business and Professional Regulation 2507 Calloway Road, Suite 200 Tallahassee, Florida 32303-5267 Doug Sunshine, Esquire Florida Engineers Management Corporation 2507 Callaway Road Tallahassee, Florida 32303-5267 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
The Issue At the commencement of formal hearing, Petitioner voluntarily dismissed Paragraphs 5 and 7 of the pending Administrative Complaint, and the formal hearing proceeded upon Paragraphs 1-4 and 6 of the Administrative Complaint. The Department of Professional Regulation prosecuted Respondent for one count of the following enumerated alleged violations: Sections 489.129(1)(d), willful or deliberate disregard of building codes; (j), failure in any respect to comply with the Act; (m), fraud, deceit, or gross negligence; and 489.105(4), Florida Statutes, all of which arise out of a single incident.
Findings Of Fact At all times material to the Administrative Complaint, Respondent, Leonardo Sanchez, was licensed by the State of Florida as a certified general contractor holding license numbers CG C004810 and CG CA04810. Robert G. Wolf, Investigator Specialist II with Petitioner, investigated a complaint made by Mirta Garcia against a contractor named Leonardo Sanchez. Ms. Garcia told him she had entered into a contract with a Mr. Sanchez; that she had paid Sanchez a sum of money for an addition to her house; that Sanchez never supplied her a written contract; and that Sanchez pulled a permit for the work and never completed it. Ms. Garcia did not appear and testify at formal hearing and her representations to Mr. Wolf are mere hearsay. They do, however, supplement or explain other competent proof. Mr. Wolf spoke with a Mr. Sanchez who, in Mr. Wolf's words "acknowledged the contractual relationship with the Garcias." (TR-15) Mr. Wolf visited Ms. Garcia's home and determined that a job of construction had been begun there but that interior work had yet to be completed. John Delaney is Assistant Chief Code Enforcement Officer for the Board of Rules and Appeals for the Building and Zoning Department, Dade County. He also visited the Garcia home and on August 18, 1987 it was approximately 80 per cent complete, in his opinion. He presented as a certified business record, a building permit application for an owner "Mirta Garcia" by "Caribean Window" [sic] applied for in the name of Leonardo Sanchez, dated "accepted 12/9/85," and carrying the contractor number CGC004810 and the social security number 109-42- 4859 (P-2). The contractor number and social security number on the application match Respondent's contractor's license and social security number. "Caribbean Window" is one of the entities for which Respondent is the registered qualifying agent. Dade County Ordinance 57-22 establishes that the South Florida Building Code was in effect in Dade County at all times material to this Administrative Complaint. Section 305.2(a) of the South Florida Building Code establishes a mandatory duty for the permit holder to obtain a reinforcing inspection. Mr. Delaney also presented a certified computer printout of a Building Inspection log or record (P-3) showing that no one, including Respondent, had obtained the required reinforcing inspection related to the Garcia job as of the date of the computer inquiry. The computer printout reflects the dates of other inspections and the date and number of the application to which it pertains; it does not clarify when Mr. Delaney made his computer inquiry but a reasonable inference is that it was made the date of his visit to the Garcia home, August 18, 1987. No reason was presented to excuse Respondent as permit holder from obtaining the appropriate inspection.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating Section 489.129(1)(d), assessing an administrative fine therefor of $250.00, and dismissing the remaining charges. DONE and RECOMMENDED this 29th day of December, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of December, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-3445 The following constitute specific rulings upon the parties' respective proposed findings of fact (PFOF) pursuant to Section 120.59(2), Florida Statutes. Petitioner's PFOF 1-7 are accepted as modified to reflect the evidence of record. Respondent's PFOF Respondent submitted no proposals. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 G. W. Harrell, Esquire, and Donald Osterhouse, Qualified Representative Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Leonardo Sanchez 12700 Southwest 37 Street Miami, Florida 33175 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
Findings Of Fact On or about March 3, 1976, the Board served its Administrative Complaint upon the Licensee. On May 18, 1976 the Licensee filed its Answer to the Administrative Complaint. The final hearing in this case was scheduled by Notice dated April 13, 1976, and was rescheduled by Notice dated May 27, 1976. John C. Ledbetter holds Certified General Contractor's License No. CG C5281 issued by the Florida Construction Industry Licensing Board. The Licensee Ledbetter has been a certified contractor at all times relevant to this proceeding. The Licensee was the co-developer of a condominium project known as Ocean Palm Villas South or Ocean Palms Riverfront Condominium. Gerald M. Hadley, Sr., a certified contractor was initially listed as the general contractor for the project. Later Neil Wayne Smith was designated the general contractor. Smith was discharged as the general contractor, and by letter dated June 11, 1973 the Licensee notified the North Peninsular Zoning Commission that he would be substituted as the general contractor. Shortly thereafter Gerald M. Hadley was again designated the general contractor, and the change was acknowledged by the forth Peninsular Zoning Commission by letter dated August 28, 1973. Construction on Ocean Palm Villas South did not commence until after August 28, 1973. No construction was undertaken during the time that Ledbetter was designated as the general contractor. The general contractor was responsible for installation of the walls in Ocean Palm Villas South. A subcontractor was utilized to install the dry wall, but the wall construction was supervised by the general contractor. The original plans called for use of 5/8" thick gypsum wallboard. The wall units were to be installed in the manner depicted in Board Exhibit 5. The gypsum was to be nailed on either side of 4" studs, with insulating material laid between the studs. 5/8" gypsum was not available to the general contractor. 1/2" gypsum wallboard was utilized. A new wall assembly was planned. With this assembly gypsum wallboard was nailed to studs, but the wallboard on the other side of the wall was nailed to alternately interspaced studs. Insulating material was woven between the interspaced studs. (See: Board Exhibit 3). The decision to use this assembly was made by Gerald A. Hadley, a labor foreman. Hadley's father was the general contractor, and was consulted in making the decision. A Mr. Rasmussen, the building inspector, was consulted about the wall assembly, and he gave his approval. At the time that construction was under way on the Ocean Palm Villas South project, the 1965 Edition with Revisions of the Southern Standard Building Code was in effect in the North Peninsular Zoning District of Volusia County. The Ocean Palm Villas South project lied within that district. The wall assembly utilized by the general contractor does not precisely follow any of the assemblies set out as appropriate in the code. The wall assembly utilized does, however, meet the one hour fire resistance standard required by the code. There was no evidence presented at the hearing from which it could be concluded that the Licensee Ledbetter had any knowledge of the wall assembly utilized in this project other than what was set out in the original plans. Ledbetter was not the contractor for the project when the assembly was constructed.
Findings Of Fact At all times material to this proceeding, Respondent was a registered roofing contractor, having been issued License No. RC0034672, in the name of John M. Sneed, Beall and Associates Roofing Corp., 7650 Southwest 135th Street, Miami, Florida 33156. Sometime during the month of October, 1951, Jerry Stamos entered into an oral agreement with Bill Parry and Billy Duncan, to have Parry and Duncan reroof Stamos's home at 441 Castonia Avenue, Coral Gables, Florida. The contract price for the reroofing work was $4,000. At no time was either Duncan or Parry licensed to perform roofing work. As a result, after Mr. Stamos was unable to obtain a building permit in his own name to perform the work, Duncan contacted Respondent, and requested that Respondent pull the building permit for the job. On October 20, 1981, Respondent obtained City of Coral Gables, Department of Building and Zoning Permit No. A48375 to perform the work on the Stamos's property. At the time the building permit was pulled by Respondent, no work had commenced on the job. Duncan and Parry were paid a total of $4,000 for the job, $100 in cash; $2,000 on October 13, 1981; and an additional $1,900 on October 22, 1981. Shortly after the building permit was pulled and work had been commenced on the property by Duncan and Parry, Duncan and Parry stopped work on the roof and never returned. Respondent was on the job site on at least one occasion when work was being performed. No notice was furnished to Mr. Stamos concerning cessation of work on the project, nor was he ever given an explanation of why work stopped and was never recommenced by Parry, Duncan, or Respondent. Respondent never supervised any of the work performed by Parry or Duncan, nor did he ever call for any inspection of the project by the City of Coral Gables, Department of Building and Zoning. The South Florida Building Code, Section 3401.1(b) provides as follows: INSPECTION. The Building Officials shall be notified by the permit holder and ample time for mandatory inspections to be made as follows: At the time the anchor sheet is being mopped to non-nailable decks. At the completion of mechanically fastening the anchor sheet to nailable decks and before mopping. During the operation of shingling or tiling. Upon completion of the roof covering. On December 1, 1981, Respondent contacted the City of Coral Gables, Department of Building and Zoning, and cancelled the permit previously obtained by him on October 20, 1981. At that time, Respondent represented to city officials that construction had never started on the project, although he knew that representation to he false. The building project remained unfinished for a period in excess of ninety days before Mr. Stamos had the job finished by another contractor.
Findings Of Fact In General: Respondent is, and was at all times material to the Administrative Complaint, a certified general contractor, having been issued license no. CG C016774 by the Florida Construction Industry Licensing Board. At no time material to the Administrative Complaint was Stephen Karlan licensed, registered or certified by the Florida Construction Industry Licensing Board. As to Counts I--III: There is no evidence, direct or indirect, to tie any participation by Stephen Karlan to any event at the Reyes' home (Administrative Complaint Counts I--III). Mrs. Carolyn Reyes is the wife of Augustin Reyes, both of whom have resided at 9355 Southwest 180th Street, Miami, Florida, for approximately 12 years. They first met with Respondent Gomez sometime in July of 1983, and after a series of discussions concerning the work which the Reyes' desired, their budget restrictions, and charges proposed by Respondent, a contract was prepared by Respondent on Respondent's stationery. (P-3) The contracted work included: completely remodeling the kitchen and living room; the installation of central air conditioning and heating; the construction of a swimming pool; and the construction of a covered patio. The Reyes provided Respondent with a check in the amount of $4,227.40, representing a twenty percent down payment on the contract price of $24,237.00. Although signed by Mr. Reyes, who did not testify, Mr. Reyes' signature was identified by Mrs. Reyes on the contract and on the September 20, 1983 check. She was present at the execution of the contract and tendering of the check on the Reyes' joint bank account to Respondent Reyes on September 20, 1983. Existence of this contract and its terms is not disputed by Respondent. Subsequently, approximately $3,100.00 was deducted from the total contract price by way of a change order. This amount represented the cost of installing a roof over the patio and brought the new contract price to $21,137.00. (P-3 and P-6) A change order, prepared by Respondent, and signed by Mrs. Reyes, was agreed to approximately October 18, 1983, for installation of more expensive bronze-tone sliding glass doors in the family room and $250.00 was paid additionally by the Reyes. From September through November, 1983, Respondent performed construction work at the Reyes' residence. Under the terms of the contract, the Reyes provided Respondent with the following amounts, mostly by checks drawn on their joint account and issued over Mrs. Reyes' signature. DATES AMOUNTS September 20, 1983 $ 4,227.40 (20 percent down payment) October 5, 1983 $ 1,056.85 (installation of kitchen cabinets) October 13, 1983 $ 3,170.55 (pool framing inspection) October 24, 1983 $ 250.00 (change order--glass doors) October 25, 1983 $ 2,137.00 (air conditioning equipment) October 28, 1983 $ 2,137.00 (pool gunnited) November 3, 1983 $ 1,056.85 (kitchen remodeling) November 4, 1983 $ 1,056.85 (plumbing payment) November 21, 1983 $ 2,000.00 (kitchen and den) November 23, 1983 $ 1,000.00 (kitchen and den) November 28, 1983 $ 982.00 December 6, 1983 $ 2,137.00 (pool decking) $21,211.50 TOTAL (P-6) All of these checks were cashed by Respondent. During October and November, 1983, work was localized in the kitchen. Mrs. Reyes recalled not being able to use her kitchen for Thanksgiving, 1983. Except for recurring problems of improperly installed tiles, cabinets and appliances, related infra., Respondent completed the bulk of the kitchen remodeling in early December, 1983. Also in early December, 1983, the swimming pool was dug and gunnite was sprayed for the pool. Gunnite is a base of a spray used for installing the concrete bottom of a swimming pool prior to installing further marble-type finishing material, tile, and accouterments. In this same time period, the overhang above the anticipated patio was torn off the existing house by Respondent with the apparent goal of tying the existing roof beams into the new roof. After December 6, 1983, Respondent failed to perform any actual construction at the Reyes' residence until May, 1984. 2/ His crew only worked there one day in December of 1983. Approximately December 20, renegotiation of pool costs and kitchen tile costs were indulged-in by the the participants. The final result was that the Reyes would pay $80.00 more for kitchen tiles and $106.00 more for pool tiles and would be permitted by Respondent to deduct $246.00 from the total owed on the contract to him. Mrs. Reyes purchased the pool materials and paid cash for them rather than turning over any monies to Respondent but she stored them on her property so that the work could go forward. Respondent testified that shortly before that point in time, he realized that he had underestimated the cost of doing the Reyes' job by $6,000.00 to $7,000.00 and attempted to explain to them that having received approximately 90 percent of the contract price, but having not completed that much of the work contracted-for, he would have to do the work as he was able between other jobs in order to stay afloat financially. Respondent's proposal was not initially acceptable to the Reyes and they hired a lawyer who thereafter prohibited Respondent making direct contact with the Reyes. At that time, the following items remained to be completed at the Reyes' residence. The pool tile had not been installed; the pool equipment had not been purchased or installed; the living room windows had not been installed; and the patio roof had not been completed. There were also numerous problems with the quality of the workmanship of the completed items. The kitchen cabinets and the dishwasher were both initially improperly installed. As a result of the Reyes complaining to the Metropolitan Dade County Building and Zoning Department, one of that agency's code enforcement officers, John Delaney, inspected the Reyes' home on April 20, 1984. At that time, Mr. Delaney noted all of the items listed in Paragraph 8 as needing completion and also noted that the patio roof overhang was still exposed to the elements and that the air conditioning unit was only balanced on a concrete slab. Mr. Delaney estimated that at that time the contract work was approximately 55 percent to 60 percent complete. Upon investigation and a record search, Mr. Delaney determined that Respondent had obtained an approved building permit for the construction of the swimming pool and the open beamed porch. (P-13) The building permit did not specify installation of the pool's piping. Likewise the building permit did not specify that Respondent might perform the interior remodeling work. This permit which Respondent did obtain lists, and Respondent's signature acknowledges, that Respondent knew that "unless specifically covered by this permit" separate permits must also be obtained for electrical, plumbing, roofing, and paving and pool, among other items. Upon concluding his investigation, Mr. Delaney felt sufficient evidence existed to charge Respondent with violation of Section 10-22 of the Metropolitan Dade County Code and forwarded his investigative report to the official for the appropriate unincorporated municipality. This report indicates that Respondent also pulled permits for mechanical air conditioning and heating and an electrical permit for the swimming pool. To Mr. Delaney's knowledge, no charges were ever filed by that official against Respondent. 3/ Mr. Delaney conceded that a state certified general contractor such as Respondent can legitimately do pool piping and that the only failure of Respondent was in not pulling the county permit. He indicated that the kitchen work in the Reyes' home would require a special permit because there is electrical and plumbing work in replacing old appliances with new. However, as to the kitchen cabinets he felt it would be permissible for either the general contractor to pull a general permit or for a subcontractor to pull a specialty cabinet permit. By questions on cross-examination of Mr. Delaney, Respondent asserted that no electrical work was done, no switches were moved and his only work was replacement of kitchen cabinets, floor, and acoustical tile but this is in the form of his questions and not sworn testimony. Respondent eventually came back to the Reyes job. He finished the pool in July, 1984. He finished the open beamed roof in October 1984. Respondent's carpenters or subcontracting cabinetmakers Carlos and Hector eventually fixed a kitchen door drawer Mrs. Reyes had complained about. (It was never established what these workers' status was/is.) Despite her general dissatisfaction with the tiles in her kitchen, despite a chipped sink, and despite personally having to explain to the plumber (again the tile setter and plumber's contract or employment relationship with Respondent is unclear) how to install the dishwasher, Mrs. Reyes currently feels 95 percent of the contract work has been completed by Respondent. 4/ She acknowledged that Respondent has provided additional bronze fixtures in her family room by way of mitigation. As to Counts IV--VII: In March, 1982, June Mildred Cooper contracted with one Steve Karlan for the construction of a bathroom addition on a residence located at 4835 Westwood Lakes Drive, Miami, Florida. The contract price was $6,700.00. Steve Karlan is not registered, certified, or otherwise licensed by the Florida Construction Industry Licensing Board. See supra. All oral representations made by Karlan to Mrs. Cooper are total hearsay and excludable, but it is clear that Respondent was never mentioned or otherwise identified during the contract negotiation of Cooper and Karlan. Cooper submitted contract payments directly to Karlan and never paid anything to Respondent. Cooper found Respondent on the job one day and thinks he said something to her like, "I'm the boss," but her memory of the exact language, if any, is vague. Cooper was admittedly not on the premises most of the time the construction was in progress because she repeatedly visited her other residence in Indianapolis for several months at a time. Respondent admits he was approached by Steve Karlan to give an estimate for the bathroom job and they thereafter agreed that Respondent should do the work. Respondent admits Karlan later gave him a piece of paper, probably a tax assessment, showing June Cooper's name as the owner, which Respondent used as the basis for filling out the building permit application which he applied for and received covering the portion of the construction work he did at her Florida residence. At the conclusion of his job, Respondent also executed a waiver-of- mechanic-lien affidavit which did not specify any owner and gave it to Karlan. Gomez never inquired into the relationship between Karlan and Cooper and just assumed Karlan was a relative, probably a son, living at the same address, and initially assumed Karlan had authority to authorize the work because Karlan opened the door to him the first time Respondent came to do the requested estimate. At the time Karlan opened the door to Respondent, some construction was already in progress in the house. Respondent represents that this scenario of obtaining a construction job is so customary in the trade that he never questioned Karlan's statement until Mrs. Cooper ultimately complained about the construction after completion. He recalls meeting her at the house twice during construction, but does not think he told her he was the boss. In mitigation, he represents that he made good on Mrs. Cooper's complaints. Respondent admits he later entered a contract with Steve Karlan as a "salesman" after satisfying Mrs. Cooper but that contract had nothing to do with the Cooper job.
Recommendation Accordingly, upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Florida Construction Industry Licensing Board enter a final order requiring Respondent to pay a penalty of $1,000.00 and monitoring his license for one year in a probationary status. DONE and ORDERED this 18th day of July, 1985, in Tallahassee, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 1985.
The Issue Whether pursuant to Sections 57.111 or 120.595(1), Florida Statutes, Petitioner Rafael R. Palacios (Palacios) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by the Respondent, Department of Business and Professional Regulation (Department). Whether pursuant to Section 120.595(1), Florida Statutes, Petitioner Steven L. Johns (Johns) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by Respondent.
Findings Of Fact Petitioner, Steven L. Johns, is a Florida Certified General Contractor and the principal qualifier for C. G. Chase Construction Company (Chase Construction). In 1994, Chase Construction entered into a construction contract with Carnival Cruise Lines for an expansion project at the Port of Miami. Chase Construction subcontracted the mechanical work to R. Palacios & Company. Petitioner, Rafael R. Palacios, is the president, primary qualifier, and 100 percent stockholder of R. Palacios & Company. Palacios' principal place of business is located in Miami, Florida. In July and December 1998, Palacios employed less than 25 employees and had a net worth of less than $2,000,000. The contract for the Port of Miami project consisted of two phases. Phase I was to construct an arrival lobby and an enclosed walkway to a terminal. Phase II included the addition of boarding halls, the renovation of an existing elevated area, and the addition of baggage areas. A foundation permit had been pulled for Phase I. The foundation work was quickly completed, and Chase Construction representatives advised both the Port of Miami and Carnival Cruise Lines that they could go no further without a permit. Work stopped for a short period of time. In June 1995, a Representative from the Port of Miami called Chase Construction and told them to go to the Dade County Building and Zoning Department (Building Department) the next day to meet with Port of Miami officials, the architect, and building and zoning officials. Johns sent Dave Whelpley, who was a project manager and officer of Chase Construction. Palacios did not attend the meeting. Dr. Carlos Bonzon (Bonzon) was the director and building official of Dade County's Building Department during the majority of the construction activities at the Port of Miami by Chase Construction. As the building official, Dr. Bonzon gave verbal authorization for the work on the project to proceed above the foundation without a written permit. Inspections were to be done by the chief inspectors for Dade County. After the meeting with the Building Department officials in June 1995, Johns understood that authorization had been given by the building official to proceed with construction without a written permit. Work did proceed and inspections were made on the work completed. The Dade County Building Code Compliance Office (BBCO) had the responsibility to oversee Dade County's Building Department. In early 1996, an officer of the BBCO accompanied a building inspector during an inspection of the Port of Miami project. It came to the attention of the BBCO officer that no written permit had been issued for the project. The BBCO officer notified the chief of code compliance for Dade County. A written permit was issued for Phase II of the Port of Miami Project on February 6, 1996, at which time approximately 80 percent of the work had been completed. On the same date, Chase Construction issued a memorandum to its subcontractors to secure the necessary permits. Shortly after the permits were issued, an article appeared in the Miami Herald concerning the project and the lack of written permits. Respondent, Department of Business and Professional Regulation (Department) became aware of the situation as a result of the newspaper article and began an investigation. Diane Perera (Perera), an attorney employed by the Department since 1993 to prosecute construction-related professional license law violations, played a major role in determining and carrying out the Department's subsequent actions regarding the Port of Miami project and persons licensed by the Department who had been involved in the project. The Department opened investigations against eight Department licensees. Those licensees included two building officials, Bonzon, and Lee Martin; four contractors, Johns, Palacios, Douglas L. Orr, and D. Jack Maxwell; one engineer, Ramon Donnell; and one architect, Willy A. Bermello. By Administrative Complaint prepared by Perera and filed on September 9, 1997, before the Building Code Administrators and Inspectors Board (BCAIB), the Department charged Bonzon with various violations of Part XIII of Chapter 486, Florida Statutes, for having allowed above-grade construction on the project to proceed in the absence of approved plans and building permits. In conjunction with the Bonzon case, Charles Danger (Danger), a licensed professional engineer and Director of BBCO testified in a deposition that above-grade construction of the project had proceeded without a building permit and without approved plans in violation of Chapter 3, Section 301 of the South Florida Building Code. He also testified that Bonzon had exceeded his authority under the South Florida Building Code by authorizing the above-grade construction and that the contractors who performed the work did so in violation of the South Florida Building Code. The Department's charges against Bonzon were resolved through a settlement agreement, whereby Bonzon agreed to relinquish his building code administrator's license. A final order of the BCAIB accepting the settlement agreement was filed on July 2, 1998. In the settlement agreement, Bonzon specifically agreed that his interpretation of the South Florida Building Code provisions, including portions of Section 301, was erroneous. On June 24, 1998, the Department presented the Department's Case Number 97-17322 involving Johns to the Division I Probable Cause Panel (PCP) of the Construction Industry Licensing Board (CILB). The panel members on this date were Gene Simmons and Wayne Beigle. Stuart Wilson-Patton and Leland McCharen, assistant attorneys general, were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the panel was Perera. The Department was requesting a finding of probable cause against Johns for a violation of Section 489.129(1)(d), Florida Statutes, for knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and specifications. Prior to the meeting of the Division I PCP of the CILB, Perera had furnished the two panel members documentary evidence pertaining to the case, copies of which were received in evidence at the final hearing as Respondent's Exhibits 5 and 13, with the exception of a letter dated July 31, 1998, from Petitioners' attorney, Renee Alsobrook. Respondent's Exhibit 5 consisted of materials taken from the Bonzon and Lee Martin cases, including the transcript of the December 22, 1997, deposition of Charles Danger, who was the building officer for the BBCO from 1991 to 1998. Respondent's Exhibit 13 was the investigative file for the Johns' case. The Division I PCP discussed Johns' case and voted to request additional information regarding whether any fast track ordinance existed in Dade County, and if so, how it might have applied to the Port of Miami project. On June 24, 1998, the Division II PCP of the CILB met and discussed the Palacios case, which was designated as the Department's Case No. 97-17313. The members of the panel were James Barge and Richard Cowart. Mr. Wilson-Patton and Mr. McCharen were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the PCP was Perera. The Department was requesting a finding of probable cause against Palacios for violating Section 489.129(1)(d), Florida Statutes, by knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and a building permit. Prior to the Division II PCP meeting, the panel members were provided with materials which were received in evidence at the final hearing as Respondent's Exhibits 5 and 14, with the exception of letters dated July 31 and August 26, 1998, from Renee Alsobrook. Respondent's Exhibit 14 is the Department's investigative file on the Palacios case. Following a discussion of the Palacios case, one of the panel members made a motion not to find probable cause. The motion died for lack of a second, and the panel took no further action on the case that day. Pursuant to Section 455.225(4), Florida Statutes, the case was treated as one in which the PCP failed to make a determination regarding the existence of probable cause and was presented to Hank Osborne, Deputy Secretary of the Department, to make a determination whether probable cause existed. On July 2, 1998, Deputy Secretary Osborne found probable cause, and the Department filed an Administrative Complaint against Palacios, charging a violation of Section 489.129(1)(d), Florida Statutes. The Department never served Palacios with the Administrative Complaint filed on July 2, 1998. The Department did not notify Palacios that the Administrative Complaint had been filed and did not prosecute the Administrative Complaint. At the time the Administrative Complaint was filed, the Department believed that the Legislature was in the process of enacting legislation to repeal Section 489.129(1)(d), Florida Statutes. Chapter 98-419, Laws of Florida, which became law on June 17, 1998, repealed Section 489.129(1)(d), Florida Statutes, effective October 1, 1998. Because of the repeal and the lack of a savings clause for pending cases, the Department determined that as of October 1, 1998, the Department did not have authority to take disciplinary action based on a violation of Section 489.129(1)(d), Florida Statutes. On December 18, 1998, the Department presented the Department's Case Nos. 97-17133 and 97-1732 to the PCPs for a second time with a recommendation to find probable cause that Johns and Palacios had violated Section 489.129(1)(p), Florida Statutes, for proceeding on any job without obtaining applicable local building permits and inspections. Mr. McCharen was present to provide legal advice to the PCPs. Ms. Perera was also present during the meetings of the PCPs. Documentary materials presented to the PCP considering Palacios' case included the materials on the Bonzon and Martin cases which had been previously presented to the PCP panel in June 1998 and the investigative files on Palacios. The investigative file included letters with attachments from Palacios' attorney Rene Alsobrook concerning the materials contained in the Bonzon and Martin cases as they related to Palacios and the investigative file on Palacios. Additionally, the investigative file contained a report from Frank Abbott, a general contractor who had been asked by the Department to review the file on Palacios. Mr. Abbott concluded that Palacios had violated several provisions of Chapters 489 and 455, Florida Statutes, including Section 489.129(p), Florida Statutes. The PCPs found probable cause in the Johns and Palacios cases. On December 23, 1998, the Department filed administrative complaints against Palacios and Johns alleging violations of Section 489.129(1)(p), Florida Statutes. The cases were forwarded to the Division of Administrative Hearings for assignment to an administrative law judge. Palacios and Johns claimed that they were relying on the authorization from Bonzon when they proceeded on the above-grade construction work. No formal administrative hearing was held on the administrative complaints filed on December 23, 1998. On December 18, 1998, a Recommended Order was issued in the related case against Lee Martin, Department Case No. 97-11278, finding that Mr. Martin, the building official who replaced Bonzon and assumed responsibility for the Port of Miami project, had the discretion to allow the remaining construction to proceed while taking action to expedite the plans processsing. A Final Order was entered by the Department dismissing all charges against Mr. Martin. On February 26, 1999, Petitioners Palacios' and Johns' Motions to Dismiss and Respondent's responses were filed. The Motions to Dismiss did not request attorney's fees or costs and did not reference Section 120.595(1), Florida Statutes. The motions did contain the following language: The DBPR has acted in an improper and malicious manner by precluding the Respondent from asserting his response to the second draft Administrative Complaint and requesting the Panel to find probable cause for reasons other than whether there was probable cause to believe the Respondent violated specific disciplinary violations. On March 19, 1999, the cases were consolidated and noticed for hearing on May 12-13, 1999. Section 489.129, Florida Statutes, was amended during the 1999 legislative session to provide: A contractor does not commit a violation of this subsection when the contractor relies on a building code interpretation rendered by a building official or person authorized by s. 553.80 to enforce the building code, absent a finding of fraud or deceit in the practice of contracting, or gross negligence, repeated negligence, or negligence resulting in a significant danger to life or property on the part of the building official, in a proceeding under chapter 120. . . . On April 15, 1999, the Department filed a Motion for Leave to Revisit Probable Cause Panel and to Hold in Abeyance. On April 20, 1999, Petitioners filed a response, stating they did not object to the granting of the motion to hold in abeyance. The final hearing was cancelled, and the cases were placed in abeyance. On May 24, 1999, the Department submitted a Status Report, stating that the cases would be placed on the next regularly scheduled PCP meeting scheduled for June 16, 1999. By order dated May 25, 1999, the cases were continued in abeyance. On July 1, 1999, Palacios and Johns filed a Status Report, indicating that the cases would be presented to the PCPs sometime in July and requesting the cases be continued in abeyance for an additional 30 days in order for the parties to resolve the issues. On July 30, 1999, Palacios and Johns filed a Status Report, stating that the cases were orally dismissed on July 28, 1999, and that a hearing involving issues of disputed facts was no longer required. Based on Johns' and Palacios' status report, the files of the Division of Administrative Hearings were closed by order dated August 3, 1999. No motion for attorney's fees and costs was filed during the pendency of the cases at the Division of Administrative Hearings. On August 3, 1999, orders were entered by Cathleen E. O'Dowd, Lead Attorney, dismissing the cases against Palacios and Johns.
Findings Of Fact At all times relevant to this proceeding, the Respondent was licensed as a contractor by the Florida Construction Industry Licensing Board. His license for the 1979-1981 license period had not been renewed at the time that the hearing was conducted, and he was therefore delinquent. [This finding is determined from Petitioner's Exhibit 1.] During June, 1977, the Respondent entered Into a contract with Emily D. Wohanka and Ruby Sue Dennard. Ms. Wohanka and Ms. Dennard, who are sisters, agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a single-family dwelling on the lot. The parties agreed to an addendum to the contract during July or August, 1977. The addendum included some specifics with respect to construction and provided: Home will be complete and ready for occupancy within a reasonable period of time--normally three to five months. [This finding is determined from Petitioner's Exhibits 8 and 9, and the testimony of Wohanka and Jordan.) The lot which Ms. Wohanka and Ms. Dennard purchased was not cleared until December, 1977. No progress on construction was made during January or February, 1980. The Respondent obtained a building permit from the City of Satellite Beach, Florida, on February 20, 1978. Construction work commenced in either March or April, 1978. By June, 1978, Ms. Wohanka became concerned that work was commencing too slowly. She told the Respondent that she needed to move in by the end of July. Respondent told her that it was probable that construction would not be completed until mid-August. By September, the project was still not completed. Ms. Wohanka tried to reach Respondent by telephone, but he would not return her calls. She tried to locate him at home, but no one would answer the door. She complained to the building official in the City of Satellite Beach, but the building official had similar problems reaching the Respondent. Ms. Wohanka also complained to N. M. Jordan, the real estate agent who had negotiated the contract. Ms. Jordan was able to locate the Respondent, and the Respondent told Ms. Jordan that he could not complete the project because he was losing money. In late September or early October, Ms. Wohanka and her sister located the Respondent at his home. The Respondent was just walking out of the front door when they arrived. The Respondent told them that he could not discuss the matter, that he had turned it over to Ms. Jordan, and that he was not a part of it anymore. [This finding is determined from Petitioner's Exhibits 2 and 3; and from the testimony of Wobanka, Hijort, and Jordan.] When Ms. Wohanka contacted the Respondent in late September or early October, no work had been done on the project for at least a month, and the house was not completed. Light fixtures, appliances, and air conditioning had not been installed. Cabinets and other fixtures were stored in a bathroom. Inside doors had not been installed. Flooring was not completed. No sidewalks or concrete driveway had been constructed. There had been no landscaping or sodding, and the sprinkler system had not been installed. The plumbing was not operational. Ms. Wohanka contracted with a new builder to complete the project. She was able to move into the residence on December 28, 1978, but work was not finally completed until late January, 1979. Additional expenses beyond those agreed to by the Respondent were incurred by Ms. Wohanka. The Respondent had drawn on a construction loan; but, there is no evidence in the record that the Respondent used these funds for any purposes other than the construction of the dwelling. [This finding is determined from the testimony of Wohanka.] During July, 1977, the Respondent entered into a contract with James and Eleanor A. Lawrence. The Lawrences agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a duplex dwelling on the lot. The Respondent obtained a building permit from the City of Satellite Beach on February 22, 1978. Unknown problems developed, and the project was not being completed. The Satellite Beach building official had difficulty locating the Respondent, but he was ultimately assured by the Respondent that the project would be completed. The Respondent told the realtor who negotiated the contract, Ms. Jordan, that he could not complete the 3 reject because he was losing money. The Lawrences did not testify at the hearing, and specifics regarding their relationship with the Respondent are not known. It is not known whether the Respondent abandoned the project uncompleted without notifying the Lawrences, or whether some agreement was made between them regarding completion of the project. There is no evidenced that the Respondent diverted any funds from the project. [This finding is determined from the testimony of Hjort and Jordan.] No building codes from the City of Satellite Beach were received into evidence. There is no evidence in the record from which it could be concluded that the Respondent violated any provisions of the building codes in either the Wohanka or Lawrence transactions.
Findings Of Fact The Respondent, Hodges J. Jefferson, is a registered general contractor having been issued License No. CGC004463. The Petitioner is an agency of the State of Florida charged with regulating the licensure status of contractors in the State of Florida, and with enforcing the requirements of Chapter 489, Florida Statutes, pertaining to licensing and regulation of the practices of general contractors in Florida. On or about March 3, 1979, Respondent, doing business as H. J. Jefferson Brothers Construction, Inc., entered into a contract with Gladston Kemp to construct a room addition on his residence for a total sum of $14,900. The construction loan by which Mr. Kemp was to finance the addition was ultimately approved sometime in April 1979. The Respondent commenced work on the property after the first check was paid him by Mr. Kemp on May 3, 1979. The Respondent worked for two to three days digging the foundation, constructing the foundation and the brick wall involved and then stopped work for a period of four to five weeks. He then came back and worked on the addition, finishing construction of the foundation, the block walls, the tie beam and the bedroom portion of the roof up to the first layer of tar paper on one side of the addition. The other side of the addition to Mr. Kemp's house was left at that point with the roof not being constructed at all. Up to July 20, 1979, Mr. Kemp had paid the Respondent a total of $7,500, inasmuch as the contract called for payments in one-third increments of the total contract price at various stages of construction. At that point the Respondent left the job after being paid $7,500 of the total price. By letter of July 24, 1979, the Respondent demanded an additional $2,900 which would complete approximately the second one-third of the total contract price and on the following day, July 25, Mr. Kemp paid the Respondent the $2,900. Thus, at that point, July 25, 1979, Mr. Kemp had paid the Respondent a total of $10,400. The Respondent did not come back and continue construction of the project. Mr. Kemp tried repeatedly to contact the Respondent, to no avail. After numerous efforts, he contacted him by telephone and the Respondent assured him that he would come by and send "his man" out to commence work, but no one ever appeared to continue the construction. Finally, in October, 1979, Mr. Kemp contacted the Respondent and he once again assured Mr. Kemp that he would come back to finish the job. Additionally, sometime after July 25, 1979, the Respondent demanded $375 from Mr. Kemp to pay for the architectural plans drafted by Edna Mingo, the architect who drafted the plans for the job in January, 1979. Mr. Kemp had already paid the $375 to Edna Mingo in January of 1979. In any event, he relented and gave the Respondent the additional $375 in order to induce him to come back and finish the job. Finally, in the latter part of October 1979, the Respondent returned to the job and began putting rafters on the bedroom portion of the addition. He then asked Mr. Kemp to advance him some more money, over and above the $10,775 Mr. Kemp had already paid him. The roof on one-half of the addition was still not finished, but Mr. Kemp gave the Respondent another $1,700 by check dated November 16, 1979. Approximately two weeks thereafter Mr. Kemp gave the Respondent another $500 in cash. Shortly before Thanksgiving 1979, the Respondent came to the project and asked Mr. Kemp to advance him some more money which Mr. Kemp refused to do. Several days later Mr. Kemp received a "demand letter" from the Respondent asking for more money and reminding him of his obligation to honor the contract. At that point Mr. Kemp contacted the Respondent and met with him at the job site, whereupon Mr. Kemp displayed to him all the checks he had already paid him, informing him of the total amount of money paid and that he did not feel that he owed him any more money. He demanded that the Respondent complete his job. The Respondent, in turn, sent Mr. Kemp a letter on November 21,1979, informing him that he would complete the job if Mr. Kemp gave him the last one- third of the contract price. At that point Mr. Kemp had already given the Respondent $12,975, so, less than one-third of the contract price was still outstanding. The Respondent assured Mr. Kemp in that letter (Petitioner's Exhibit 17, in evidence) that he would complete the job by December 15, 1979. Mr. Kemp gave the Respondent another $2,100 making a total of $15,075 paid to the Respondent (the contract price being $14,900). Respondent did not complete the job in December 1979 and indeed never completed it. He went to Mr. Kemp's house "one night in December" and discussed the job with Mrs. Kemp's wife and assured her that he was going to try and get the job "out of the way" by January. The Respondent never came back to continue working on the job and never communicated with the Kemps after December 1979, except for a fist fight between Mr. Kemp and the Respondent engendered by the bitterness resulting form this dispute which occurred in July 1980. Mr. Kemp and his wife, however, went to the Respondent's home in January 1980 to ask him when he would complete the job. He became abusive and would not give them a copy of the plans so that the Kemps had to get a duplicate copy from the architect so Mr. Kemp could then obtain the appropriate inspections from the building department. There were no extra additions to the contract and the only work ever required of the Respondent was that described on the building plans. The fees fro the electrical, plumbing, and building permits were paid by Mr. Kemp. At the time the Respondent left the job it was approximately 55 percent complete. The roof was incomplete. Mr. Kemp had to do the "rough plumbing," the "finish plumbing," install a half bath, a utility room and a full bath in the bedroom. Mr. Kemp also had to "rough in" the electrical wiring, that is, run the electrical service wiring inside the house for the finish electrical work. Mr. Kemp also had to install drywall and plaster inside and outside the house and completely "finish out" the addition to his home. He supplied some of the labor for this himself and hired various subcontractors to do other portions of the work such that he ultimately spent approximately $9,000 in excess of the amount paid Respondent in order to finish the job in accordance with the building plans. Completion of the work thus cost the Kemps an additional $9.000 above the $15,075 already paid the Respondent, with the use of the monies paid Respondent for the last 45 percent of the work required of him by the contract being unexplained, except for the Respondent's general statement that some of that money was attributable to unaccounted for "overhead" costs. The Respondent left the job in terms of performing any work in October 1979, promised to finish it in December and later in January 1980, and never returned to finish the job or perform any more work such that sometime in the summer of 1980 the Kemps ultimately finished the job through their own labors and that of various subcontractors and materialmen they were forced to hire and pay.
Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED that the contractor's license of Hodges J. Jefferson be suspended for a period of 5 years, provided however, that if he makes full restitution to the Kemps of all monies they expended for labor, materials and permits to complete the work he was contractually obligated to complete within one year from a Final Order herein that that suspension should be terminated and his license reinstated. DONE AND ENTERED this 14th day of March 1984 in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of March 1984. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Hodges J. Jefferson 2250 Northwest 194th Terrace Miami, Florida 33156 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue The Florida Construction Industry Licensing Board, Petitioner, seeks to revoke the registered contractor's license of Stephen J. Borovina, Respondent, based on allegations, which will be set forth in detail hereafter, that he engaged in conduct violative of Chapter 468, Florida Statutes. The issue presented is whether or not the Respondent aided or abetted and/or knowingly combined or conspired with Mr. Howard North, an uncertified or unregistered contractor, to evade the provisions of Chapter 468.112(2)(b), and (c), Florida Statutes, by allowing North to use his certificate of registration without having any active participation in the operations, management, or control of North's operations. Based on the testimony adduced during the hearing and the exhibits received into evidence, I make the following:
Findings Of Fact The Respondent is a certified general contractor who holds license no. CGC007016, which is current and active. On or about July 25, 1976, Mr. and Mrs. Julius Csobor entered into a contract with Mr. and Mrs. Howard North for the construction of a home in Martin County, Florida, for a total price of $35,990. Neither Mr. or Mrs. North are certified or registered contractors in the State of Florida. (Petitioner's Composite Exhibit #2). Respondent applied for and was issued a permit by the Martin County Building Department to construct a residence for the Csobors at the same address stipulated in the contract between the Csobors and the Norths, i.e., Northwest 16th Street, Palm Lake Park, Florida. (Petitioner's Composite Exhibit #1). Howard North, a licensed masonry contractor for approximately nine (9) years was contacted by the Csobors through a sales representative from a local real estate firm. It appears from the evidence that North had previously constructed a "spec" house which the local realtor had sold and thus put the Csobors in contact with Mr. North when they were shown the "spec" house built by North. Evidence reveals that North contacted Borovina who agreed to pull the permit "if he could get some work from the job and could supervise the project". Having reached an agreement on this point, North purchased the lot to build the home for the Csobors and he orally contracted with the Respondent to, among other things, pull the permit, supervise construction, layout the home and do trim and carpentry work. North paid Respondent approximately $200 to layout the home for the Csobors. By the time that North had poured the slab and erected the subfloor, the Csobors became dissatisfied with his (North's) work and demanded that he leave the project. According to North, Respondent checked the progress of construction periodically. Prior to this hearing, the Csobors had never dealt with Respondent in any manner whatsoever. According to Csobor, North held himself out as a reputable building contractor. A contractor is defined in relevant part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. . . . real estate for others. . . Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby recommended that the complaint filed herein be dismissed in its entirety. RECOMMENDED this 4th day of November, 1977, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 Stephen J. Borovina 2347 Southeast Monroe Street Stuart, Florida 33494 J. Hoskinson, Jr. Chief Investigator Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 STEPHEN J. BOROVINA, CG C007016, 2347 S. E. Monroe Street, Stuart, Florida 33494, Respondent. / This cause came before the FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD at its regular meeting on February 10, 1978. Respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did not appear The FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD on February 10, 1978, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded voted to revoke the certified general contractor's license of STEPHEN J. BOROVINA. It is therefore, ORDERED that the certification of respondent STEPHEN J. BOROVINA, Number CG C007016, be and is hereby revoked. Respondent is hereby notified that he has 30 days after the date of this final order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. DATED this 13th day of February, 1978. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President ================================================================= SECOND AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD STEPHEN J. BOROVINA, CG C007016, Respondent/Appellant, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner/Appellee. / This cause came before the Florida Construction Industry Licensing Board at its regular meeting on August 3, 1979. The respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did appear. The Florida Construction Industry Licensing Board, on August 3, 1979, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded, voted to revoke the certified general contractor's license of Stephen J. Borovina, No. CG C007016. On February 13, 1978, the certification of respondent, Stephen J. Borovina, No. CG C007016, was revoked by order of the Florida Construction Industry Licensing Board. On April 25, 1979, the District Court of Appeal of the State of Florida, Fourth District, in Case Number: 78-527, reversed the final order of the Florida Construction Industry Licensing Board. That Court remanded the above captioned case to the Board to further consider the matter and enter such order as it may be advised in conformity with Section 120.57(1)(b)(9), Florida Statutes (1977). In accordance with the decision of the Florida District Court of Appeal, Fourth District, the Board has reconsidered the above captioned matter and finds as follows: The Board rejects the recommended order as the agency's final order. The Board adopts the first paragraph of the hearing officer's finding of fact. The Board, however, rejects the findings of fact found in the second paragraph of the hearing officer's findings. The second paragraph states as follows: A contractor is defined in relevent(sic) part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. real estate for others...Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety. The findings of fact found in the above-quoted paragraph were not based upon competent substantial evidence. The competent substantial evidence supports a finding that the respondent, Stephen J. Borovina, did not supervise the project and that Borovina evaded the provisions of Chapter 468, Florida Statutes. The following evidence supports the Board's position: There was no written agreement entered into between Howard North and the respondent which indicated that the respondent was to supervise the construction of the Csobors' house (T- 14); It was conceded at the hearing that the only subcontractors or draftmen who worked on the Csobors' house were contracted solely by Howard North and they had no contract whatsoever with the respondent (T-19, 25); The respondent never advised or informed Mr. and Mrs. Csobor that he was the contractor on the job. (T-51); At all times during the act of construction of the house, Mr. and Mrs. Csobor were under the impression that Howard North was the contractor (T-44-51). It is, therefore, ORDERED: That the certification of respondent, Stephen J. Borovina, Number CG 0007016, be and is hereby revoked. Respondent is hereby notified that he has thirty (30) days after the date of the Final Order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. Dated this 3rd day of August, 1979. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President