Findings Of Fact Standard Specifications are a part of every DOT construction contract issued. Subsection 8-1.1 of these standard Specifications provides that a subcontractor shall be recognized only in the capacity of an employee or agent of the Contractor, and his removal may be required by the Engineer, as in the case of any employee (Exhibit 1). Subsection 8-5 thereof provides the Contractor shall assure that all superintendents, foreman and workman employed by him are competent, careful and reliable (Exhibit 3). All contracts entered into by DOT provide for a contract completion time and provide for adjustment to the contract period for delays in construction due to factors beyond the contractor's control which could not be reasonably anticipated at the time bids for the contract were received (Exhibit 4). Requests for extension of contract time are made by the Contractor to DOT, and each request is evaluated on its merits. Often these requests for extension of contract time are made after the contract is completed and the contractor is seeking relief from penalties accrued as a result of his failure to complete the contract in the time allocated. Prior to 1987, all contracts entered into by DOT contained built-in delays based on average weather conditions expected during the contract period. Since mid-1987, contract delays due to expected adverse weather are not included in the contract time, but the period is subsequently adjusted based on daily recording of weather conditions during the contract period. There is no policy by DOT, as suggested by Petitioner, that delays due to weather outside the initial contract period but within the extension granted due to weather delays will not be considered by DOT in granting extensions of contract time. Federal Department of Transportation grants to Florida DOT for road construction in Florida contain a provision that a certain percentage of the contract must be subcontracted to DBE's. This provision is included in the contracts on which the prime contractors submit bids. In order to qualify as a responsible bidder on these contracts, the Contractor must show compliance with the DBE quota for the job at the time his bid is submitted or show that despite good faith efforts the Contractor was unable to meet the DBE goals. DOT certifies individuals and companies which meet the minority business standards needed for certification and maintains a current list of all potential subcontractors who can be used by the Contractor to meet the DBE quota for the specific contract on which the Contractor bids. These DBE subcontractors are not qualified by DOT as capable to perform the work for which they hold themselves out as able to perform. DOT qualifies no subcontractors, either DBE or non-DBE. In the event the Contractor needs to replace a subcontractor for any reason, his application to replace a non- DBE subcontractor is routinely approved by DOT. However, if the Contractor proposes to replace a DBE subcontractor, the Contractor must replace him with another DBE subcontractor (if this is necessary to retain the required DBE participation) and show to DOT that the replacement was for just cause and does not constitute unlawful discrimination. Accordingly, it is more likely to delay a project if a DBE subcontractor is replaced for failure to perform the work for which he subcontracted than if a non-DBE subcontractor has to be replaced for the same reason. Although DOT individually considers each request for extension of contract time, it treats delays resulting from DBE subcontractor performance the same as it treats delays resulting from non-DBE subcontractor performance. As noted in finding 2 above, the contract provides that subcontractors are agents or employees of the Contractor. Accordingly, extensions of time for completion of the contract are not generally granted when the delay is due to the agents or employees of the Contractor. It is the refusal of DOT to treat DBE subcontractors different from non-DBE subcontractors that forms the basis of Petitioner's challenge to this "policy" that extensions of contract time are not granted when the delay was due to the DBE subcontractor failing to comply with his subcontract which failure was "beyond the control" of the Contractor.
Findings Of Fact Respondent Paul McAllister is a certified general contractor and was the qualifying individual for the firm of Garnett-McAllister Associates, Inc., Fort Lauderdale, Florida, in 1977 and until July, 1978. (Stipulation) On April 8, 1977, Respondent's firm entered into a contract with Ray Borchardt, Westchester, Illinois, for the construction of a four-unit apartment building at Lighthouse Point, Florida. The contract provided for a total price of $139,110.00, payable in five payments or "draws" in various percentages of the contract price at specified stages of construction. However, the contract did not specify a time for performance or completion of the building. It contained a clause stating "Any alteration or deviation from above specifications involving extra costs - will be executed only upon written orders, and will become an extra charge over and above the estimate." Respondent obtained a building permit for the construction of the building from the building official, City of Lighthouse Point, Florida, on May 8, 1977. (Petitioner's Exhibits 1, 2) Prior to the commencement of construction, it was determined that foundation pilings for the building were required and therefore Borchardt sent Respondent the sum of $13,519.65 on June 9, 1977, as an additional sum over and above the contract price. At this time, he also sent the first draw in the amount of $20,866.00 even though such payment was not called for until completion of the foundation and "rough in" of plumbing and electric connections. On August 1, 1977, Borchardt paid the second draw of $20,866.00 although the roof was not on, nor had the beam been poured at the time as called for under the contract. Respondent was delayed approximately three weeks by failure of a supplier to provide the second floor concrete planking. On October 24, 1977, Borchardt paid the third draw in the amount of $34,777.00 although construction was not at the stage called for under the contract. On November 22, 1977, Borchardt paid $18,000.00 of the fourth draw and on January 23, 1978, paid the remaining portion of $16,777.00. At that time, the roof was not completed, tile work had not been started, woodwork was incomplete, and kitchen cabinets and vanities had not been installed pursuant to the terms of the contract. Borchardt had made a number of trips from Illinois to Florida during the construction period and was aware that his various partial payments were made in advance of completion of the several construction phases. He had dealt primarily with Edward J. Garnett, president of Garnett-McAllister Associates, Inc., as to the financial aspects of the project. Respondent primarily was a "field" man in charge of supervising construction. Also, Borchardt's son-in- law, Vincent A. Svegel, had moved to Florida in September, 1977, and acted as Borchardt's contact with Respondent's firm after that time. Both Respondent and Garnett informed Svegel in the fall of 1977 that the building would be completed by December 15. (Testimony of Borchardt, Svegel, Petitioner's Exhibit 1) Although during the early part of 1978, five subcontractor liens were filed against the property for work and materials supplied on the project, three of these liens were eventually paid by Garnett-McAllister and the remaining two totaling over $7,000.00 were eventually paid by Borchardt. One of the latter liens was filed by Pompano Roofing Company, Inc. That firm refused to install the roofing tile until paid and the tile therefore "sat on the roof" for approximately five months. On March 13, 1978, Borchardt filed a complaint with Petitioner based on the fact that the work had not been performed according to the draw schedule and liens had been placed on the property. Borchardt also complained to James P. Simmons, the building official of Lighthouse Point about the project delays and claims of lien. As a result, on March 14, 1978, Simmons referred the complaint to Petitioner because Respondent was certified by the state. Petitioner's local inspector, Wallace Norman, issued a Notice of Violation of Section 468.112(2)(e), F.S., to Respondent on March 15, 1978, for diversion of funds based on the filing of liens by suppliers. In a meeting with Respondent and Garnett, Norman asked for an explanation of the situation. They told him that they had been building a house in Davies, Florida, and had used some of the money that Borchardt had paid them to pay suppliers on that house and they had expected to be able to put the money back into the Borchardt project when they sold and realized a profit on the other house. (Testimony of Borchardt, Svegel, Simmons, Norman, Petitioner's Exhibits 7, 9, 10; Respondent's Exhibit 3) During the period between January and March, 1978, some progress was made toward completing the building, including the rough in of the plumbing and electrical systems, installation of inside lath work, installation of tub and shower stalls, and extension of a kitchen area. As late as April 19, 1978, Respondent accompanied Borchardt to a supplier to purchase windows for the building. (Testimony of Svegel, Respondent, Pet. Ex. 3) On May 29, 1978, Svegel, in behalf of Borchardt, notified building official Simmons that Garnett-McAllister Associates, Inc. had been terminated from any further work on the building due to the fact that the building permit had expired and would not be reissued, and requested authorization to finish the building. Simmons thereafter issued a building permit to complete the building to Borchardt on June 21, 1978. He also instructed his staff not to issue any more permits to Respondent due to his "poor track record" and liens which had been filed against the building under construction. Simmons issued the completion permit under the authority of Section 304.3 of the South Florida Building Code, Broward County Edition, which provided that a building permit expires and becomes null and void if work is abandoned at any time for a period of ninety days. Although Simmons considered that the time limit had elapsed because an inspection had not been called for by the builder for ninety days, he erroneously believed that the last inspection had been on January 4, 1978, when, in fact, the city's inspection records show that the plumbing department had made an inspection of rough plumbing on March 27, 1978. Simmons did not notify Respondent of the issuance of the second permit. He considered that he had inherent authority in his position to prohibit issuance of additional permits to Respondent, but didn't consider his action in this regard to be disciplinary in nature because the City of Lighthouse point does not issue contractor's licenses. Therefore, the matter was referred to Petitioner for any action against Respondent's state certification. (Testimony of Simmons, Svegel, Petitioner's Exhibit 3, 4, 11, Respondent's Exhibit 1) At some time prior to obtaining the permit to complete the building, Borchardt had refused to pay the final draw of $27,824.00 to Garnett-McAllister Associates, Inc. because the firm was so far behind on the job. Garnett had told Borchardt that be was selling another home for $80,000.00 and was going to put some of the money he realized from that sale into the Borchardt project. He wanted Borchardt to loan him $20,000.00 and take back a lien on a boat in order to have money in the interim to work on the building. When Borchardt declined to do so, Garnett told him that he could not complete the job. Borchardt also received a call from Respondent to the effect that he would finish the job on his own for $150.00 a week if Borchardt would pay the remaining costs. Borchardt informed him that he would pay nothing further until the job was completed. Garnett had also told Svegel that he had used some $25,000 to $30,000 of the Borchardt funds to construct the house in Davies and that he would put that money back into the firm's business account to use for the Borchardt building when the house was sold. (Testimony of Borchardt, Svegel, Respondent) At the time Borchardt took over completion of construction, the building was approximately 70-75 percent completed. Borchardt paid an additional sum of about $82,000.00 to complete the building which was some $54,000.00 more than the original contract price. However, about $12,000.00 of this sum constituted changes to the original specifications that had been agreed to by Borchardt during the course of construction. Some of these involved changes due to building code requirements, such as the addition of a ramp for the handicapped. Other changes were made on the recommendation of subcontractors or resulted from requests by Borchardt's daughter and son-in-law who were intending to occupy one of the apartments in the building. None of these changes was reflected in a written change order or supplemental agreement to the contract because Borchardt had agreed to the changes and neither party to the contract apparently considered it necessary to formalize these matters. Additional changes in the sum of some $12,000 were made to the building after Borchardt took over construction. These primarily dealt with carpeting, appliances and the like. (Testimony of Borchardt, Svegel, Simmons, Respondent, Stipulation, Petitioner's Exhibits 5, 8) Respondent testified at the hearing and disclaimed knowledge of the financial affairs of the corporation which he claimed were handled exclusively by Garnett. He denied ever abandoning the project and stated that he was unaware, until June 7, 1978, that Borchardt was taking over the construction project to complete. He acknowledged that funds became a problem about mid- January, 1978, and that he then recognized that the contract price had been set at too low a figure because cost overruns were being experienced. He denied diversion of Borchardt's funds to the Davies house, and claimed that his firm did not purchase supplies for that project. He conceded, however, that the firm had one corporate business account from which suppliers on all jobs were paid. Respondent further testified that when funds for the Borchardt building became scarce, profits from other jobs were used in meeting construction costs on the building. He acknowledged receiving a salary of $8,420.00 during the course of construction and said that Garnett had also drawn a sum of approximately $11,000.00 for himself. (Testimony of Respondent) A review of the books of Garnett-McAllister Associates, Inc. by a certified public accountant indicated that they were not well kept and were frequently in error. The auditor's report reflected that the firm had expended at least $80,675.00 in direct construction costs on the project. Certain cost items could not be verified due to the failure of suppliers to respond to the auditor's inquiry. These accounts were reflected on the books of the firm at a total of approximately $1,000.00. (Testimony of Webb, Respondent's Exhibit 4)
Recommendation That Respondent's certification as a general contractor be suspended for a period of 90 days, but that he be permitted to complete any contracts which are uncompleted at the time suspension is effected. DONE and ENTERED this 25th day of April, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32302 Alan C. Brandt, Jr., Esquire 1040 Bayview Drive Fort Lauderdale, Florida 33304 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211
The Issue Whether Respondent's intended rejection of all responses to its solicitation of "qualifications" from entities interested in contracting with Respondent to perform construction management at risk services in connection with a project at Fort Lauderdale High School is illegal, arbitrary, and/or dishonest, as alleged by Petitioner.
Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: Respondent is a district school board responsible for the operation, control and supervision of all public schools (grades K through 12) in Broward County, Florida (including, among others, Fort Lauderdale High School) and for otherwise providing public instruction to school-aged children in the county. As authorized by Florida Administrative Code Rule 6A- 1.012, Respondent has "establish[ed] purchasing rules" (denominated as "policies"). Respondent's Policy 3320 contains Respondent's "Purchasing Policies." Part III of Respondent's Policy 3320 prescribes "Purchasing Policies" for Respondent's Facilities and Construction Management Division, and it provides, in pertinent part, as follows: All additions, modifications, and alterations to School Board properties shall conform with the State Requirement for Educational Facilities (SREF), Florida Building Code (FBC) and the laws of the State of Florida. School Board administrators shall obtain assistance in preparing bid specifications and applicable building permit(s) from the Facilities and Construction Management division for these items. Part VIII of Respondent's Policy 3320 addresses the subject of "protests arising from the competitive solicitation process" and incorporates the protest procedures found in Section 120.57(3), Florida Statutes. Respondent's Policy 7003 is entitled, "Pre- Qualification of Contractors and Selection of Architects, Engineers, Design Builders, Construction Managers, and Total Program Managers Pursuant to the Consultants Competitive Negotiation Act." It provides, in pertinent part, as follows: The School Board shall pre-qualify bidders for construction contracts, and, publicly announce, in a uniform and consistent manner, each occasion when construction and/or professional services are required to be purchased in compliance with governing statutes and regulations. The Superintendent shall establish procedures for the pre-qualification of contractors and selection of architects, engineers, design- builders, construction managers and total program managers consistent with this policy, applicable statutes and State Requirements for Educational Facilities (SREF). Rules The School Board authorizes the Superintendent to: Receive applications for Contractor Pre- Qualification on the attached application form in compliance with FS 1013.46 and SREF 4.1(8), as amended. . . . * * * 4. Designate an evaluation committee of eleven (11) voting members for the purpose of Pre-Qualification of contractors and selection of architects, engineers, design builders, construction managers and total program managers. * * * The committee shall make recommendations to the Superintendent regarding the pre- qualification of contractors. The Superintendent shall make recommendations to the Board: Along with a report from the committee containing findings of fact indicating the proposers' compliance with the procurement requirements and scoring criteria and the Board shall have the final approval of such recommendations. The Contractor Pre-Qualification Application Form "attached" to Policy 7003 contains the following description of the contractor pre-qualification process: The School Board ("Board") through the Superintendent or his/her designee, shall pre-qualify all "contractors" for construction contracts, and any other contracts that require a certificate issued pursuant to Chapter 489, Florida Statutes, including, but not limited to, all bidders, construction managers, design-builders, job- order contractors, term contractors, and all other types of contractors on an annual basis or for a specific project according to the rules set forth in the State Requirements for Educational Facilities (SREF) Section 4.1(8). Contractors shall be pre-qualified on the basis of the criteria set forth in SREF and included in the foregoing application form. In addition to the foregoing criteria the applicant shall provide the Dun and Bradstreet report indicated in the application. The evaluation committee shall be as set forth in Board Policy 7003. The applicant shall complete the form in its entirety and submit all required documents by the deadline set forth in the public announcement. Separate applications shall be submitted for each desired contracting category. The School Board of Broward County shall receive and either approve or reject each application for prequalification within sixty (60) days after receipt of application in its entirety and all required documents. Approval shall be based on the criteria and procedures set forth in SREF. The Board shall issue to all pre-qualified contractors a certificate valid for one (1) year from the date of approval or for the specific project(s). That certificate shall include the following: A statement indicating that the contractor may bid, propose, or otherwise be considered, on the specific project(s) or for this specific time period. A statement establishing the total dollar value of the work the contractor will be permitted to have under contract with the Board at any one time. The maximum value shall not exceed the contractor's bonding capacity or ten (10) times the net quick assets. A statement establishing the maximum dollar value of each individual project the contractor will be permitted to have under contract with the Board at any one time. The maximum value of each project may be up to twice the value of the largest similar project previously completed but shall not exceed the Contractor's bonding capacity or ten (10) times the net quick assets. A statement establishing the type of work the contractor will be permitted to provide. The expiration date of the certificate. It shall be the responsibility of the contractor to renew annually certificates not for a specific project. Financial statements or written verification of bonding capacity on file with the Board shall be updated annually. Failure to submit a new statement or verification of bonding capacity within thirty (30) days written notice by the Board shall automatically revoke a pre-qualification certificate. 1. Pre-qualified contractors may request a revision of their pre-qualification status at any time they believe the dollar volume of work under contract or the size or complexity of the projects should be increased if experience, staff size, staff qualifications, and other pertinent data justify the action. These procedures are in accordance with requirements set forth in Section 4.1 of the State Requirements for Educational Facilities. As the parties stipulated in Admitted Fact 6, "[o]n May 20, 2008, [Respondent] approved the Request for Qualifications No. 2008-030-FC (RFQ) entitled 'Construction Management at Risk Services for Districts 2, 3 and 4 Projects (Cooper City High School - Project No. 1931-99-02; Fort Lauderdale High School – Project No. 0951-27-01; Margate Elementary School – Project No. 1161-26-01; and Northeast High School – Project No. 1241-27-01),' and authorized the public announcement of the RFQ." "[In] [t]he summary explanation and background [section of] the Agenda Request Form [for this agenda item, it was] stated that the 'Facilities and Construction Management staff recommend[ed] the procurement of construction services utilizing Construction Management at Risk delivery method due to the complexity, scope and scale of the projects.'" This "delivery method" is to be distinguished from the "hard bid" or "design/bid/build" method of procurement, where a contractor is hired only after "the construction documents are completed." Under the "Construction Management at Risk delivery method," contrastingly, the construction manager typically assists in the development and "complet[ion]" of the "construction documents," offering advice and recommendations to maximize quality and cost efficiency. As a result, it is "not uncommon" for there to be post-solicitation changes in a project's scope and budget when this "delivery method" is employed. As the parties stipulated in Admitted Fact 7, "[a]t the time of [Respondent's] approval of the RFQ, the portion of the RF[Q] pertaining to [the FHS Project] had an advertised Proposed Construction Budget of $29,150,340 and a project scope which was described [in RFQ] as follows: 'Concurrent replacement in two phases to include: Phase I – Construct a 3- story Administration Classroom Building of 68,940 GSF to include Administration, 3 general classroom[s], 5 resource rooms, 4 Science Labs and related spaces, a 4-classroom ESE Suite, 1 Business Technology Lab, 1 Family and Consumer Science (ProStart) Lab, 1 Health Occupations Lab, 1 Pre-Law Public Service Education Lab, Custodial spaces, Textbook Storage and Student, Staff and Public Restrooms. Demolish Buildings 1, 2, 3, 4, 11, 12, 13 and 14.'" Phase II of the project was, at the time, described in the RFQ as follows: "Construct Parent drop off & pick up area and Staff/Visitor Parking; Construct Regional Athletic Facility; Renovate Building 8 into Science Labs; Demolish existing tennis courts & replace with 6 tennis courts; Demolish Swimming Pool; Construct basketball courts; Resurface Student Parking." These descriptions represented the "initial concept" of the FHS Project (the design of the project having been then only in the "conceptual stage" of development). Respondent wanted to have the benefit of the input and advice of a construction manager (working together with the architect selected for the project) in developing the project's design beyond the "conceptual stage." As the parties stipulated in Admitted Facts 12 through 19, "[b]etween the initial public release of the RFQ and the submission of proposed qualifications, [Respondent] issued seven (7) addenda revising the RFQ's terms and conditions," with "Addendum No. 4 chang[ing] the scope of the [FHS Project] component of the RFQ as follows": Delete the scope in Phase I to demolish Building #4. Delete the scope in Phase II to construct basketball courts and to resurface student parking. Revise the words "replace with 6 tennis courts" to be the words "construct five (5) tennis courts." Clarify phasing: In Phase I, demolish the existing track and athletic field and relocate existing baseball field. Clarify scope: In Phase II, for the staff parking construct a 3-story parking structure including required access road work. Clarify scope: Phase II includes renovation of existing courtyard to provide ADA access to existing gymnasium and auditorium. (Emphasis, by bolding, supplied in original). Addendum No. 6 "[r]evised the [RFQ's] Submittal Due Date to read 'No later than 2:00 p.m. on September 3, 2008.'" As the parties stipulated in Admitted Fact 20,"[a]fter [the] issuance of Addendum No. 7 to the RFQ, the scope of the [FHS Project] component of the RFQ was described as follows [with strike-throughs and underlining indicating, respectively, post-issuance deletions and additions]: Concurrent replacement in two phases to include: Phase I – Construct a 3-story Administration Classroom Building of 68,940 GSF to include Administration, 3 general classroom[s], 5 resource rooms, 4 Science Labs and related spaces, a 4-classroom ESE Suite, 1 Business Technology Lab, 1 Family and Consumer Science (ProStart) Lab, 1 Health Occupations Lab, [1 Pre-Law Public Service Education Lab], Custodial spaces, Textbook Storage and Student, Staff and Public Restrooms. Demolish the existing track and athletic field and relocate existing baseball field. Demolish Buildings 1, 2, 3, 4, 11, 12, 13 and 14. Phase II – Construct Parent drop off & pick up area and a 3-story parking structure including required road access work for Staff Parking and /Visitor Parking[.] Construct Regional Athletic Facility[.] Renovate building 8 into Science Labs[.] Demolish existing tennis courts & replace with 6 tennis courts construct five (5) tennis courts. Demolish Swimming Pool. Renovate existing courtyard to provide ADA access to existing gymnasium and auditorium. Construct basketball courts. Resurface Student Parking." As the parties stipulated in Admitted Facts 10 and 11, on August 26, 2008, the date that Respondent issued its final addendum to the RFQ (Addendum No. 7), it also issued a Revised Public Announcement publicizing the issuance of the RFQ (as revised by the seven addenda). The Revised Public Announcement read, in pertinent part, as follows: In order to supplement the expertise of the Facilities and Construction Management Department, the Superintendent of Schools, pursuant to Florida Statutes, announces that The School Board of Broward County, Florida, is in need of Construction Management Services, related to new construction and renovations of educational facilities. Pursuant to this request for qualifications, The Board will consider contracts with one of more proposers to provide these services. Services under this contract include, but are not limited to the following items and shall be in accordance with SREF [State Requirements for Educational Facilities] 1999 Chapter 4: Bid and award activities including managing bidder listing, addendum, bidding, proposals, schedule of values, contracts, guaranteed maximum price, value engineering, and bonds. Construction activities including managing meetings, contract administration, monitoring procedures, contract records, inspections, non-conformances, owner- supplied equipment, testing, project accounting, and construction services. Warranty activities including managing claims and periodic inspections. Provide other basic services as required. Refer to the Request for Qualifications for more detailed project scopes. * * * RFQ No. 2008-30-FC Project Nos. 0951 27 01/P000687 Fort Lauderdale High School (proposed construction budget $29,150,340): Phase replacement in 2 phases to include: Phase I - Demolish selected buildings, tennis courts, swimming pool, track and athletic field. Construct a 3-story Administration Classroom Buildings[2] of 68,949 GSF; parent drop off/pick-up area and visitor parking; 5 tennis courts. Relocate existing baseball field. Phase II - Demolish selected building. Construct a 3-story parking structure including required access road work; Regional Athletic Facility. Renovate existing courtyard for ADA access to Gym and Auditorium. Renovate Building 8 into Science Labs. * * * Award: Project will be awarded by Facility. Proposed Construction Budget: Includes all costs inclusive of the Construction Manager's fees, Cost of Work, and any other costs related to construction. Minimum Selection Criteria: Will include the following as a minimum, (refer to document RFQ, Article X Submittal Requirements for expanded list of selection criteria): The company's history, structure, personnel, licenses, and experience. Related projects similar in scope or amount completed by the company, including name of client or its representative. Financial information such as balance sheet and statement of operations and bonding capacity. Project management, scheduling and cost control systems the company uses for similar projects. Proposed minority business involvement in the project. . . . Cost control, value engineering techniques and constructability reviews. Description of litigation, major disputes, contract defaults and liens in the last five (5) years. Interview. Confirmation of references. Consideration of the volume of work previously awarded to each firm, with the object of effecting an equitable distribution of contracts among qualified firms, provided such distribution does not violate the principle of selection of the most qualified firms. * * * The completed RFQ response must be delivered . . . . NO LATER THAN 2:00 PM SEPTEMBER 3, 2008 * * * Qualifications Selection Evaluation Committee (QSEC): After submission, proposers will be evaluated by the Qualification Selection Evaluation Committee (QSEC) based upon the above minimum criteria. The QSEC will select no less than three (3) proposers, ranked in order of tabulated score. The QSEC will recommend the finalist(s) for award of contracts to Construction Managers to the Superintendent. The Superintendent shall either recommend award of contract(s) to the finalist(s) selected by the QSEC or recommend rejection of all proposals to the Board. After the Board approves the recommendations of the QSEC the Board will authorize the Superintendent, or designee, to negotiate a contract for services for fees to provide direct management of the Construction Management at Risk Contract. Recommendations by the Qualification Selection Evaluation Committee do not guarantee a contract will be awarded by the Board. Award of a contract does not guarantee that work will be issued. Fees will be negotiated in accordance with Board Policy 7003 and Section 287.055, F.S. Article I of the RFQ (as revised) listed "General Requirements" that "proposers [had to] meet" "[i]n order to be considered." As the parties stipulated in Admitted Fact 21, Article I.D. of the RFQ (as revised) provided, in pertinent part, as follows: All proposers must be prequalified according to 1013.46 F.S., SREF 4.1(8), and Board Policy 7003 at the time of submittal due date to this RFQ. Article I.H. of the RFQ (as revised) provided as follows: The School Board of Broward County, Florida reserves the right to reject any or all responses, to waive technicalities, or to accept the proposal that, in its sole judgment, best serves the interest of The School Board of Broward County, Florida. Article II of the RFQ (as revised) described the "Selection Process." As the parties stipulated in Admitted Fact 22, Article of the RFQ (as revised) "was entitled 'Proposal Review by Staff' and stated as follows": Facilities and Construction Management Division staff will conduct a review of the proposer's submittal to determine whether the proposer meets the terms of this RFQ, requirements of the Florida Statutes, State Requirements for Educational Facilities regulations, Florida Building Code, and any other code, statute, or standard applicable at the time of response. Facilities and Construction Management Staff will provide information to the QSEC Members showing payments made by the district to the proposing firms over the past three (3) years. Non-compliant proposals will be recommended to the committee for rejection. As the parties stipulated in Admitted Fact 23, Article of the RFQ (as revised) "was entitled 'Shortlist Selection' and stated as follows": The QSEC Members will assign points to each proposer, for each facility, based upon the Selection Criteria below and attached Selection Criteria Score Sheet in the shortlist evaluation process. Each QSEC Member shall assign points for each proposer according to the selection criteria and rank them according to their scores. The proposer receiving the most points by a QSEC Member will be considered the first choice of that QSEC Member. The firm that receives the most first choice votes from the committee will be the top-ranked proposer. The second-ranked proposer will be the proposer that receives the most points, other than the proposer who was already selected as the top-ranked, and so on. In the event of a tie a voice vote will be taken until the tie is broken. If the voice vote is not unanimous, then a roll-call vote will be taken. The selection process will establish a "shortlist" for each facility/project of not less than three (3) proposers and no more than five (5) proposers submitting proposals. Shortlist selection will be done by each facility. Article II.E. of the RFQ (as revised) called for "[p]resentations" to be made to the QSEC by the shortlisted proposers. As the parties stipulated in Admitted Fact 24, Article II.G. of the RFQ (as revised) "was entitled 'Final Selection' and stated as follows": The QSEC will interview and rank the shortlisted firms. The QSEC will assign points to each proposer, for each facility, utilizing the Selection Criteria and point schedule included with the Selection Criteria Score Sheet to finalize the selection. Note, M/WBE staff will provide scores for M/WBE categories. However, such scores are recommendations by M/WBE staff and may be adjusted by individual QSEC Members. Each QSEC Member shall assign points for each proposer according to the selection criteria and rank them according to their scores for each project/facility. The proposer receiving the most points by a QSEC Member will be considered the first choice of that QSEC Member. The proposer that receives the most first choice votes from the committee will be the top-ranked proposer. The second-ranked proposer, will be the proposer that receives the most points, other than the proposer who was selected as the top-ranked proposer, and so on. In the event of a tie a voice vote will be taken until the tie is broken. If the voice vote is not unanimous, then a roll- call vote will be taken. The QSEC will recommend the finalist(s) for award of contract to Construction Manager to the Superintendent. The Superintendent shall either recommend award of contract(s) to the finalist(s) selected by the QSEC or recommend rejection of all proposals to the Board. After the Board approves the recommendations of the QSEC the Board will authorize the Superintendent, or designee, to negotiate a contract with the top-ranked firm according to Section 287.055, F.S. The Board shall have final approval of such recommendations. Final selection will be done by each facility. Article II.H. of the RFQ (as revised) contained the "Minimum Selection Criteria." This provision read as follows: Minimum Selection Criteria: Will include the following as a minimum, (refer to this document Article XI Submittal Requirements for expanded list of selection criteria): The company's history, structure, personnel, licenses, and experience. Related projects similar in scope or amount completed by the company, including name of client or its representative. Financial information such as balance sheet and statement of operations and bonding capacity. Project management, scheduling and cost control systems the company uses for similar projects. Proposed minority business involvement in the project (refer to this document Article I, J for requirements). Cost control, value engineering techniques and constructability reviews. Description of litigation, major disputes, contract defaults and liens in the last five (5) years. Interview. Confirmation of references. Consideration of the volume of work previously awarded to each firm, with the object of effecting an equitable distribution of contracts among qualified firms, provided such distribution does not violate the principle of section of the most qualified firms. As the parties stipulated in Admitted Fact 25, Article III of the RFQ (as revised) "[was] entitled 'Competitive Negotiations' and state[d] as follows": After the QSEC ranks the firms, recommends the finalist(s) to the Superintendent, and the Superintendent recommends the finalist(s) to the Board[,] [t]he Superintendent, or designee will negotiate a contract for services for fees to provide direct management cost of the CM and Guaranteed Maximum Price (GMP). The CM contract shall maintain an "open book" project accounting process, with any savings returned to the Board. Should the negotiations not result in a contract with the finalist at a price determined by both parties to be customary, fair, competitive, and reasonable, negotiations with that firm shall be formally terminated. The Superintendent, or designee, shall undertake negotiation with the second most qualified firm and thereafter, if necessary, with the third firm. Should the Board be unable to negotiate a satisfactory contract with any of the selected firms, additional firms will be selected in accordance with the above- described procedure. Negotiation should continue in accordance with Section 287.055, F.S., or until the Board determines not to proceed and to re-advertise and repeat the process. Article IV of the RFQ (as revised) addressed the "Scope of Services." It simply provided as follows: "Refer to attached Agreement Between Owner and Construction Manager for requirements." Article 3 of the "attached Agreement Between Owner and Construction Manager" (Sample Contract) enumerated the "Construction Manager's Services." Those services to be performed by the hired construction manager during the "Pre-Design Phase" were described in Article 3.2 of the Sample Contract as follows: The Construction Manager shall review project requirements, educational specifications, on and off-site development, survey requirements, preliminary budget, and make value engineering and constructability recommendations for revisions to the Owner and Project Consultant in the form of a written report prior to the final payment for this phase. The Construction Manager shall, subject to Owner's approval and compliance with existing Owner completion schedule, establish a preliminary master project schedule identifying all phases, Critical Path elements, responsibilities of the Owner, Project Consultant, outside agencies, third parties and any other impacts which would affect project schedule and progress and update them monthly throughout the duration of the contract. When the project includes renovation or expansion of an existing Facility, the Construction Manager will assist the Construction Team in preparing an analysis package outlining the condition of the existing Facility, existing structure, existing finishes, and existing equipment, code deficiencies, energy use, and life expectancy of other building systems by providing constructability, value engineering, and cost estimates recommendations. The package should contain the Construction Manager's recommendations, cost estimates and preliminary schedules. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager shall prepare detailed cost estimates and recommendations to Owner and Project Consultant at S.D. (Schematic Design), D.D. (Design Development), C.D. (50% and 100% Construction Documents) phases of the project. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for each phase. The Construction Manager shall provide project delivery options for the design, bid, and bid packaging of the project for efficient scheduling, cost control and financial resource management. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager shall utilize information and reporting systems to provide the Owner with monthly reports containing accurate and current cost controls, work status, including but not limited to Work narrative, Work completed/anticipated, short term and long term schedules, estimated expenditures, and project accounting systems of the project at all times. Such information shall be provided to the Owner and Project Consultant in the form of a written report, prior to final payment for this phase. The Construction Manager shall prepare a report with the Project Team's participation which shall describe, as a minimum, the Work plan, job responsibilities, and written procedures for reports, meetings, inspections, changes to the project, building systems, and delivery analysis and other relevant matters. Such information shall be provided to the Owner and Project Consultant prior to final payment for this phase. The Construction Manager shall provide market analysis and motivation for subcontractor interest and recommendations for minority business participation. This shall include analysis of the Construction Manager's historical data for subcontracting, communication with contractor and trade organizations requesting participation, review of the Owner's M/WBE data, advertising, outreach programs, mailings to all prospective bidders identified by these actions, and reporting of all of the for[e]going to the Owner. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager's personnel to be assigned during this phase and their duties and responsibilities to this project and the duration of their assignments are shown on Exhibit D to the General Conditions. All required reports and documentation shall be submitted and approved by the Owner as pre-requisite to progress payments to the Construction Manager by the Owner during this phase. Those services to be performed by the hired construction manager during the "Design Phase" were described in Article 3.3 of the Sample Contract as follows: The Construction Manager will be required to attend all project related meetings and include a summary of the meeting of its monthly report to the Owner as specified in Document 01310. The Construction Manager will periodically review to the best of their abilities all Contract documents for constructability and compliance with applicable laws, rules, codes, design standards, and ordinances. Such information shall be provided to the Owner and Project Consultant in the form of a written report in the format as noted herein prior to final payment for this phase (Refer to exhibits G and H). The Construction Manager will be required to work with and coordinate [its] activities with any additional consultants, or testing labs and others that Owner provides for the project and report all findings as specified in Document 01310. The Construction Manager shall review all Contract documents for the new and existing buildings and/or building sites and provide value engineering recommendations to minimize the Owner's capital outlay and maximize the Owner's operational resources. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. All such recommendations shall be acknowledged and incorporated into the construction documents by the Project Consultant unless otherwise authorized by the Owner in writing. The Construction Manager will review construction documents and the new and existing buildings conditions and/or building site to reduce to the best of [its] abilities conflicts, errors and omissions and shall coordinate with the Project Consultant in order to eliminate change orders due to errors, omissions and unforeseen conditions. The Construction Manager shall periodically update the master project schedule and make recommendations for recovery of lost time. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager will coordinate with the Project Consultant and provide to the Project Construction Team permitting applications and requirements for the projects. The Construction Manager will periodically update cost estimates and make recommendations to keep the project within the FLCC. AT COMPLETION OF THE CONSTRUCTION MANAGER'S REVIEW OF THE PLANS AND SPECIFICATIONS, EXCEPT ONLY AS TO SPECIFIC MATTERS AS MAY BE IDENTIFIED BY APPROPRIATE WRITTEN COMMENTS PURSUANT TO THIS SECTION, CONSTRUCTION MANAGER SHALL WARRANT, WITHOUT ASSUMING THE PROJECT CONSULTANT'S RESPONSIBILITES, THAT THE PLANS AND SPECIFICATIONS ARE CONSISTENT, PRACTICAL, FEASIBLE AND CONSTRUCTIBLE. CONSTRUCTION MANAGER SHALL WARRANT THAT THE WORK DESCRIBED IN THE PLANS AND SPECIFICATIONS FOR THE VARIOUS BIDDING PACKAGES IS CONSTRUCTIBLE WITHIN THE SCHEDULED CONSTRUCTION TIME. DISCLAIMER OF WARRANTY: THE OWNER DISCLAIMS ANY WARRANTY THAT THE PLANS AND SPECIFICATIONS FOR THE PROJECT ARE ACCURATE, PRACTICAL, CONSISTENT OR CONSTRUCTIBLE OR WITHOUT DEFECT. .10. The Owner may select certain projects for expediting using fast-track construction. When this option is exercised, in writing, by SBBC, it shall be implemented in accordance with the following: A. Design/Construction documents as noted herein shall be submitted by the Consultant for review and approval by SBBC (including Building Code review and Building permit issuance for 100% completion documents), the Construction Manager and others, as applicable, having jurisdiction: Foundation/Structural/LCCA/Site and Off- Site Package-100% Documents A separate 50% completion progress set (for information only) of Building Finish Package drawings shall also be submitted which shall show all of the major characteristics of the project utilities and service, detailed site and floor plans, elevations, section, schedules, etc. Construction may begin after approvals and building permit is obtained for above package. Building Finish Package-100% Documents As mutually agreed by the parties in writing. .11 Guaranteed Maximum Price (GMP): Upon completion of the design phase [construction documents 100% complete] and prior to the bidding and award phase, the Construction Manager shall present to the Owner the GMP for the Owner[']s review and approval in accordance with Article 6 of this Agreement.[3] Those services to be performed by the hired construction manager during the "Bidding and Award Phase" were described in Article 3.4 of the Sample Contract as follows: At this stage the Construction Manager assumes the leadership responsibility for the project team. Upon obtaining all necessary approvals of the Construction Documents including a Building Permit as required by FBC and Owner approval of the latest Statement of Probable Construction Cost, the Construction Manager shall obtain bids and commence awarding construction contracts. The Owner will have the drawings and specifications printed for bidding purposes, either through its open Agreements with printing firms or as a reimbursable service through the Project Consultant, or as set forth in Article 26.03.08 in the General Conditions of this CM Agreement. The Construction Manager shall review the Owner[']s records of pre-qualified contractors, including Minority/Women Business Enterprises (M/WBE) and prepare a list of those recommended for work pursuant to this contract. The Owner reserves the right to reject any or all subcontractors recommended for approval. The Construction Manager shall maintain a list of all potential bidders, including M/WBEs and those who are approved as pre-qualified. The Construction Manager shall prepare and issue the bid packages to cover the scope of the Work for this contract. The Construction Manager, in coordination with the Owner, shall schedule pre-bid conferences as required and issue a written summary of the conference(s). Solicitation of Bids: .1 The Construction Manager shall enter into Contracts with the firm who submits the lowest, responsive and responsible bid. The Construction Manager shall advertise according to SBBC policies as amended from time to time for bids on Documents 00101 at least three (3) times, seven (7) days apart, and with the third (3rd) advertisement prior to a pre-bid conference if applicable and at least seven (7) days prior to the bid opening. Written proposals based on drawings and/or specifications shall be submitted to the Construction Manager. The written proposals shall be opened at the usual location for bid opening. A tabulation of the results shall be furnished by Construction Manager to the Owner. .6 The Construction Manager and Owner shall open at the Construction Manager location and evaluate at least three bids, if possible, for each portion of the Work solicited. The Construction Manager shall also make recommendations to the Owner for award to the lowest, responsive, and responsible bidder. A recommendation for award to other than the lowest bidder shall be justified in writing. Those services to be performed by the hired construction manager during the "Construction Phase" were described in Article 3.5 of the Sample Contract as follows: The Construction Manager shall fully comply with the provision[s] of the Owner's Project Manual, including but not limited to Division 0 and 1, and the attached General Conditions of this contract. In the event of a conflict between this Agreement and such documents the agreement shall control. The Construction Manager shall provide the minimum staffing level as set forth in Exhibit C-F for this project. The Construction Manager shall maintain and prepare monthly updates for all project schedules, including Critical Path elements, provide written progress reports, describe problems and corrective action plan(s) and conduct briefings as required by the Owner. Such information shall be provided to the Owner and Project Consultant in the form of a written report with progress payments requests. The Construction Manager may self perform certain construction work when it benefits the Owner, results in cost and time savings, and is pre-approved by the Owner in writing. The Construction Manager shall coordinate project close-out, operation, and transition to occupancy. The Construction Manager shall coordinate with the Project Consultant to provide complete project records including project manual and electronic Computer Assisted Drafting (CAD) drawings corrected to show all construction changes, additions, and deletions. (Construction Manager shall note all changes on the as-builts for the Project Consultant to reflect on the drawings and CAD disc.) The Construction Manager shall coordinate with the Owner's staff to prepare the Certificate of Final Inspection. The Construction Manager shall obtain and review all warranties, operation and maintenance manuals and other such documents, for completeness, have them corrected if necessary and submit them to the owner. The Construction Manager shall complete all punch list items generated by the Building Code Inspector (BCI), the Owner, the Project Consultant and any others having jurisdiction over the project during its inspections. Those services to be performed by the hired construction manager during the "Warranty Phase" were described in Article 3.6 of the Sample Contract as follows: The Construction Manager shall provide a minimum one (1) year warranty and shall coordinate and supervise the completion of warranty Work during the warranty period. Construction Manager shall participate with the Owner in conducting of warranty inspections held on the sixth (6th) and eleventh (11th) months after occupancy. Construction Manager shall deliver as-built drawings, warranties and guaranties to the Owner. Where any Work is performed by the Construction Manager's own forces or by subcontractors under contract with the Construction Manager, the Construction Manager shall warrant that all materials and equipment included in such work will be new except where indicated otherwise in Contract Documents, and that such Work will be free from improper workmanship and defective materials and in conformance with the Drawings and specifications. With respect to the same Work, the Construction Manager further agrees to correct all work found by the Owner to be defective in material and workmanship and not in conformance with the Drawings and Specifications for a period of one year from the Date of Owner Occupancy of the Project or a designated portion thereof or for such longer periods of time as may be set forth with respect to specific warranties contained in the trade sections of the Specifications or by Florida Law. The Construction Manager shall collect and deliver to the Owner any specific written warranties given by others as required by the Contract Documents. The Construction Manager shall provide a Warranty Summary Report at the end of the 6- month warranty period and 11-month warranty period. This report shall provide at a minimum: Description of each warranty item during the period. Date item reported to Construction Manager. Date item corrected. If more than one trip required, document each. Description of action taken to cure warranty item. Obtain signature of school principal or designee acknowledging warranty items have been completed. Other pertinent information, if applicable. Article V of the RFQ (as revised) provided the following information with respect to "Fees and Pricing": Successful proposers shall negotiate a fee for providing construction management services during the design phase and subsequently shall negotiate a GMP for construction services during the bidding and construction phase. Architectural/Engineering firms will develop Contract documents under separate contract with the Board. As the parties stipulated in Admitted Fact 26, Article VII of the RFQ (as revised) "[was] entitled 'Board's Right to Reject' and state[d] in part as follows": The Board reserves the right to reject any and all proposals and readvertise the project(s) at any time prior to Board approval of the recommended proposer(s) and the negotiated agreement(s). All costs incurred in the preparation of the Proposal and participation in this RFQ process shall be borne by the proposers. Proposals submitted in response to this RFQ shall become property of the Board and considered public documents under applicable Florida law. The District reserves the right to accept or reject any and all submittals, or to waive any technicalities or formalities when and if it is in the best interests of the District. Rejection: A submittal shall be rejected for failure to comply with one or more of the following requirements: The proposer is not licensed or registered in the State of Florida to provide the proposed services. The submittal shall be rejected if not received by The School Board of Broward County, Florida by the specified deadline. Not Applicable. Article XI of the RFQ (as revised) discussed "Submittal Requirements" and contained the following provisions concerning "Related Projects Similar in Scope (to this RFQ)" and "References": Related Projects Similar in Scope (to this RFQ): List educational projects of related scope and size. Provide name and location of project, project owner, project owner name, address phone and contact person, project cost, current project status, firm[']s key personnel assigned to the project. . . . L. References: Provide a list of all projects, clearly stating name of project, using Construction Management at Risk, completed or in progress within the last five (5) years from due date of this RFQ. If Proposer[']s firm also has offices outside the tri-county area (meaning Broward, Miami-Dade, or Palm Beach), then at a minimum provide references for all Construction Management at Risk projects in the tri-county area. List projects that are 75 percent or greater of the construction budget statement in the Public Announcement for each listed project. Provide the address, telephone numbers and contact person(s) listed as references for each project. . . . As the parties stipulated in Admitted Fact 27, "[o]n or about September 3, 2008, [Respondent] received proposed qualifications to provide construction management at risk services for [the FHS Project] from 13 vendors including Petitioner." Among the other "vendors" submitting "proposed qualifications" were Elkins Constructors, Inc., the Morganti Group, Inc., and W. G. Mills, Inc. As the parties stipulated in Admitted Fact 28, "[i]n accordance with the terms and conditions of the RFQ [as revised] and [Respondent's] governing statutes, rules and policies, Respondent's Qualifications Selection and Evaluation Committee ('QSEC') recommended the rejection of certain proposers for their failure to comply with [Respondent's] pre-qualification requirements or limits." There were three such "proposers": Elkins Constructors, Inc.; the Morganti Group, Inc.; and W. G. Mills, Inc. At the time of the "submittal due date to this RFQ [as revised]," neither Elkins Constructors, nor the Morganti Group, was "prequalified according to 1013.46 F.S., SREF 4.1(8), and Board Policy 7003" for any project. W. G. Mills, on the other hand, was "prequalified" for certain projects, but only within the following limits: a "[p]er [p]roject [l]imit [of] $25,000,000 [and an] [a]ggregate [l]imit [of] $250,000,000." The "advertised Proposed Construction Budget" of the FHS Project was $29,150,340, which was more than W. G. Mills' "[p]er [p]roject [l]imit [of] $25,000,000." As of the date "proposed qualifications" were due, there were 11 prequalified firms, including W. G. Mills, who had a "[p]er [p]roject [l]imit" of between $17,000,000 and $26,000,000. These firms were not eligible to be awarded the contract for the FHS Project because the project's "advertised Proposed Construction Budget" was in excess of their "[p]er [p]roject [l]imit." W. G. Mills was the only one of these 11 prequalified firms to respond to the RFQ (as revised). As the parties stipulated in Admitted Fact 29, "[i]n accordance with the terms and conditions of the RFQ [as revised] and [Respondent's] governing statutes, rules and policies, [the] QSEC next evaluated and short-listed the remaining proposers. It thereafter received presentations from the short-listed proposers and, after scoring those short-listed proposers, recommended Petitioner . . . to [Respondent] as the proposer with whom to negotiate a contract for services for fees to provide direct management cost of the construction manager and the project's guaranteed maximum price ('GMP')." As the parties stipulated in Admitted Fact 30, "[o]n October 7, 2008, [Respondent] approved [the] QSEC's selection of Petitioner . . . as the vendor with whom negotiations would be had for [the] Fort Lauderdale High School component of the RFQ [as revised] and 'authorized negotiations for Construction Management at Risk Services.' The scope of Construction Management at Risk services was [as noted above] included within the RFQ [as revised]. The summary explanation and background portion of the agenda item to authorize negotiations stated that the 'Superintendent's designees will negotiate the selected Constriction Management at Risk Services fees for the projects and recommend award of contracts at a future School Board Meeting.'" As the parties stated in the "Statement of the Controversy" section of their Joint Pre-Hearing Stipulation, "[n]egotiations between [Respondent] and [Petitioner] occurred between October 2008 [following Respondent's approval of the QSEC's selection of Petitioner] and December 2009." In December 2009, Cubellis, the architectural firm working on the FHS Project for Respondent, was "experiencing some financial difficulties" and there was uncertainty as to whether it would "be able to continue [on] the project." As a result, negotiations between Respondent and Petitioner were halted. Eventually, Cubellis "assigned [its] contract [with Respondent] to somebody else" (specifically, Manuel Synalovski Associates, LLC), but negotiations between Respondent and Petitioner never resumed. Petitioner's last written contract proposal was dated December 10, 2009. It was based on a proposed construction budget of $18,297,367 and provided for the following "Negotiated Contract Terms": Construction Manager Fees: Pre-Design Not Applicable Design Not Applicable Bidding & Award $37,685 Construction Phase Fee $1,172,370 Warranty $35,000 Overhead $289,200 Profit $185,385 General Conditions $659,846 Total $2,379,489 Above Fees based on scope of work issued "Project Scope" document dated 11/5/2009 per 11/9/2009 letter from M. Decker. CM Performance and Payment Bonds and GL Insurance are included based on budgeted contract amount of $18,297,367. Builders Risk, Contingency, and Subcontractor insurance costs are not included in the fees and will be shown in the schedule of values as separate line items as a cost of work. Should the cost of work increase Bonds and GL insurance fees are to be adjusted at insurance providers' invoiced amount. Overhead, profit and bond allowances for Change Orders: 10% Substantial Completion: 570 Final Completion in General Conditions 25.01.02: 600 Construction Phase Fee and General Conditions in 25.01.02: $3,050 per Consecutive Calendar Day Liquidation Damages for Substantial Completion: $1,000 per Consecutive Calendar Day Liquidation Damages for Final Completion: $600 per Consecutive Calendar Day This contract proposal was made following a December 8, 2009, negotiation session at which Denis Herrmann, Respondent's Director of Design and Construction Contracts, had stated that he had negotiated a construction management at risk contract for another project the previous day where the "Construction Manager Fees" were 13.8 percent of that particular project's proposed construction budget. Mr. Herrmann had relayed this information to Petitioner's representatives at the meeting to give them "a flavor for the range [Respondent was] talking about, not to give them a [specific] number [or percentage] that would be acceptable." The "Construction Manager Fees" proposed by Petitioner in its December 10, 2009, offer were slightly less than 13.8 percent of the $18,297,367 proposed construction budget (but they did not cover any "Pre-Design"-related or "Design"-related work). While Respondent has never, in writing, specifically rejected Petitioner's December 10, 2009, offer, neither has ever formally accepted it. As the parties stipulated in Admitted Facts 45 and 48, respectively, Respondent's "Superintendent of Schools has not placed an item on [the School Board] agenda recommending that [Respondent] enter into a contract with [Petitioner] concerning the RFQ [as revised]," and "[Respondent] has not approved a contract with [Petitioner] concerning [the] RFQ [as revised]." It has been two years since "[Respondent] approved [the] QSEC's selection of Petitioner . . . as the vendor with whom negotiations would be had." Significant changes impacting the FHS Project have occurred over that period of time. Respondent now finds itself in the midst of an "unprecedented budget crisis," making it especially imperative that it "take every [possible] step to maximize the purchasing power of the public's dollars." A precipitous decline in revenue available for capital projects (due, in large measure, to a decline in property values, coupled with a reduction in the capital outlay millage rate) has required Respondent to eliminate or scale back various planned projects. The FHS Project is among the projects that have been scaled back. As the parties stipulated in Admitted Fact 31, "[p]rior to, during and subsequent to its negotiations with [Petitioner], [Respondent] determined on several occasions that the project scope of the [FHS Project] needed to be further adjusted, ultimately resulting [in] the following project scope [with strike-throughs and underlining indicating, respectively, deletions and additions]": Concurrent Replacement in two phases to include: Demolish existing swimming pool (buildings 15 and 16). Demolish existing tennis courts and replace with 6 tennis courts. Demolish Buildings 1, 2, 3, 4, 11, 12, 13, and 14. Construct basketball courts. Construct Regional Athletic Facility. Construct (2) 3-story buildings (1 – Administration & 1 - Classroom) of approximately 68,940 GSF combined to include Administration, 3 general classrooms, 5 resource rooms, 4 science labs and related spaces, 4-classroom ESE suites, 1 Business Technology lab, 1 Family and Consumer Science (ProStart) lab, 1 Health Occupations Lab, 1 Pre-Law Public Service Education Lab, Custodial spaces, Textbook Storage, and Student, Staff and Public Restrooms. Remodel Renovate existing Science Building (building 8). Construct Parent Drop Off and Pick Up area and Staff/Visitor Parking. Resurface Student Parking. Construct New Student parking area on the West side of the site to increase parking capacity by 92 spaces. Modify existing temporary bus loop to meet SREF code and ADA standards; modifications will include barricades and covered sidewalk. Redesign courtyard to meet current ADA standards.' As the parties further stipulated in Admitted Fact 31, "[t]he project scope was revised five (5) times between October 7, 2008 and December 2, 2009[,] [and Petitioner] was notified of the changes in scope and acknowledged the same." "[R]evis[ions]" have also been made to the project's budget. Respondent's "5-Year Plan" allocates funding for all costs (including, but not limited to, construction costs4) associated with each of Respondent's funded capital projects. As the parties stipulated in Admitted Fact 32, "[Respondent] adopts and revises its 5-Year Capital Improvement Plan ('5-Year Plan') each year." As the parties further stipulated in Admitted Fact 33: [Respondent's] 5-Year Plan adopted for Fort Lauderdale High School for Fiscal Years 2009-10 to 2013-14 eliminated the $39,491,259 previously budgeted as "Capacity Additions" . . . . Instead, the 2009-10 to 2013-14 Five Year Plan provided $21,050,000 for Capacity Additions . . . . Respondent's current "5-Year Plan" (for the Fiscal Years 2010- 2011 to 2014-2015), which was adopted on September 7, 2010, allocates $22,366,085 to the FHS Project (as scaled back). The dour economic conditions responsible (in part) for the drop in tax revenues available to fund Respondent's capital projects have also led to increased competition in the construction industry and a resultant decline in construction prices. This increased competition is particularly pronounced "in the procurement area of hard bidding." During "the peak of the construction boom," before the downturn in the economy, it was not atypical for Respondent, when it "hard bid" a construction project, to get just one or even no bids in response to the solicitation. Now, Respondent "expect[s] to see between half a dozen [and] a dozen or more bidders." Moreover, recently, winning bids on "hard bid" projects have been, on average, well below these projects' advertised proposed construction budgets. Respondent has not experienced the same overall cost-savings results when it has used the "Construction Management at Risk delivery method." Given the market conditions that exist today, Respondent estimates that the construction costs for the FHS Project (as scaled back) would be no more than $16,950,000 and possibly as little as approximately $13,000,000 (if a "hard bid" were used). These amounts are considerably less than the "Proposed Construction Budget of $29,150,340" that had originally been "advertised." There are prequalified firms (including W. G. Mills) which were not eligible to be awarded the contract under the RFQ (as revised) because their "[p]er [p]roject [l]imit" was less than $29,150,340, but which would now be able to bid on a scaled-back FHS Project were it to be readvertised (with a proposed construction budget of $16,950,000). Another (and perhaps the most significant) difference between the circumstances existing at present and those that existed two years ago (vis-à-vis the FHS Project) is that the design of the project (as scaled back) has advanced to the point that, with a few revisions,5 the construction documents for the project will be 100 percent complete.6 As a result, Respondent no longer has a need for most, if not virtually all, of the "pre-design" and "design" services, described in Articles 3.2 and 3.3 of the Sample Contract, that, back in 2008, it had wanted a construction manager to perform. In April 2010, Respondent's Office of the Chief Auditor issued a report (April 2010 Audit Report) critical of Respondent's use of the "Construction Management at Risk delivery method" in connection with 14 projects "which were included in the Construction Management at Risk Kitchen/Cafeteria RFQ No. 2006-12-FC." The report read, in pertinent part, as follows: The projects included in RFQ No 2006-12-FC were sufficiently completed by the Architect/Engineer firm(s) prior to being advertised as CM at Risk construction projects. The inability [of] any CM firm to provide "professional services" and scheduling of both design and construction phases represents a deviation from the intent of Florida Statutes, SREF and the School Board's CM at Risk contract.[7] In nearly every executed CM at Risk agreement in the Kitchen/Cafeteria program, the Pre- Design and Design phase responsibilities of the CM were stricken from the contract. That is a further representation that the input required by a prospective CM to qualify for the committee selection process was not, nor was it intended to be provided. F.S. 1013.45(1)(c) also states that the use of the CM at Risk delivery method " . . . shall not unfairly penalize an entity that has relevant experience in the delivery of construction programs of similar size and complexity by methods of delivery other than program management." All of the projects in the Kitchen/Cafeteria program were originally intended to be "hard-bid" but were changed to the CM at Risk delivery method. One project was removed from the group prior to the due date of submittals for RFQ No. 2006-12-FC. That hard bid project, Margate ES, cost approximately $5.6 million, including nearly $466,226 in change orders, which was approximately $3.3 million less, on average, than the fourteen (14) projects that remained in RFQ No. 2006-12- FC. Due to the change in delivery method, general contracting firms could have been "unfairly penalized" by the decision to use the CM at Risk delivery method, as many local general contractors have the relevant experience in the delivery of construction programs of similar size and complexity by methods other than the CM at Risk delivery method.
Recommendation We recommend that Facilities & Construction Management discontinue developing construction procurement packages (i.e. RFQ and RFP) for award of CM at Risk agreements when construction management services requested are associated with reused, prototypical or otherwise sufficiently developed construction documents. Kitchen/Cafeteria program data indicates that the benefits associated with the CM at Risk delivery method were not realized using prototypical designs, as the program resulted in over $24 million in avoidable fees while circumventing applicable laws and regulations. On May 10, 2010, Mr. Herrmann sent a letter to Respondent's General Counsel requesting, in light of the April 2010 Audit Report, a "legal opinion related to the award of a Construction Manager at Risk Agreement (CM) to [Petitioner] and whether such an award would comply with Chapter 1013.45(1)(c), S. and State Requirements for Educational Facilities 1999 (SREF)," given that the FHS Project (as scaled back) was then "in the design phase and Phase III 100% Construction Documents [were] being prepared." The concluding paragraph of the letter read as follows: In this project, The Weitz Company has been selected by the board and we intend to recommend award of a contract within several months. An award of a CM agreement in this case would not violate the specific audit recommendation and we believe such an award does not violate statute or SREF. Please advise whether you concur. Mr. Herrmann has since changed his opinion. He now believes (reasonably so, in the undersigned's view) that "award of a CM agreement" in the instant case would be inconsistent with the "audit recommendation" inasmuch as the FHS Project (as scaled back) now has "sufficiently developed construction documents." On May 18, 2010, Mr. Herrmann sent another letter to Respondent's General Counsel. This letter read as follows: This is to provide you with additional information relating to a request for a legal opinion regarding the award of a Construction Manager at Risk Agreement (CM) to The Weitz Company. Please also refer to the attached memos dated 10/14/09, 11/16/09 and 5/10/10. In summary, we have requested opinions based on the following: Whether such an award would comply with applicable statutes, SREF, and board policy given the extent of the changes to the scope and budget. Whether such an award would comply with Chapter 1013.45(1)(c), F.S. and State Requirements for Educational Facilities 1999 (SREF). We have recently revised the construction cost estimate as a result of current market conditions, and the project consultant, Manuel Synalovski [Associates], LLC agrees with the revised estimate. The change in the cost estimate is as follows: In the RFQ: $29,150,340 October 2009 (Change in scope): $21,770,000 November 2009 (Market conditions): $18,297,367 May 2010 (Market conditions) $16,950,000 Please advise whether we should proceed with the award or reject all bids. Respondent's General Counsel responded to neither of these May 2010, letters from Mr. Herrmann. As the parties stipulated in Admitted Fact 34, "[o]n June 15, 2010, [Respondent] approved Item J-15 during its June 15, 2010, Regular Meeting." The "Requested Action" and "Summary Explanation and Background" section of the Agenda Request Form for this agenda item (J-15) provided as follows: REQUESTED ACTION Approve the change in the delivery method from Construction Management at Risk to Design/Bid/Build and the First Amendment to the Professional Services Agreement with Manuel Synalovski Associates, LLC (MSA) for Fort Lauderdale High School, Phased Replacement Project No. 095-27-01, dated February 12, 2008. SUMMARY EXPLANATION AND BACKGROUND Scope of Work: Basic Services Amended 6/15/10: This item changes the delivery method from Construction Management at Risk to Design/Bid/Build. Demolish existing Swimming pool (Buildings 15 and 16); demolish existing tennis courts; demolish Buildings 1, 2, and 3; construct two 3-story buildings (1 administration and 1 classroom) of approximately 68,940 gross square feet combined to include administration, 3 general classrooms, 5 resource rooms, 4 science labs and related spaces, 4 ESE classroom suite, 1 business technology lab, 1 family and consumer science (ProStart) lab, 1 health occupations lab, 1 pre-law public service education lab, custodial spaces, textbook storage, and student, staff, and public restrooms. Remodel existing science building (Building 8). Construct new parent drop off and pick up areas and staff/visitor parking. Construct new student parking area on the west side of site to increase parking capacity by 92 spaces. Modify existing temporary bus loop to meet SREF, Florida Building Code and ADA Standards. ADA modifications will include barricades and covered sidewalk. Remodel existing courtyard for ADA access to gym and auditorium. MSA and the Superintendent's Negotiations Committee negotiated a total reduction in [architectural] fees from the February 12, 2008 Board approved amount of $2,021,000 to $1,683,650. This decrease in the Basic Services Fees totals $337,350 and is decreased as follows: Phase IV (Bidding and Award) by $54,357, Phase V (Construction Administration) by $269,250, and Phase VI (Warranty) by $13,743. This fee reduction is as a result of a reduction of the original scope as per Attachment 2 to the First Amendment. This First Amendment also reduces the Fixed Limit of Construction Cost (FLCC) from $29,150,340 to $16,950,000 as a result of the reduction in scope and construction costs resulting from current market conditions. The Risk Management Department and the Office of the Chief Auditor have reviewed this First Amendment. The School Board Attorney has approved this First Amendment as to form and legal content. As the parties stipulated in Admitted Fact 35, on June 30, 2010, "[Respondent] posted its Revised Recommendation[] and Tabulation for [the FHS Project, which] set forth the following recommendation": Per Article VII.A of the RFQ, based upon the recommendation of the Qualification Selection Evaluation Committee, the Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on July 20, 2010, reject all responses received for Fort Lauderdale High School Project No. P.000687. The original, intended scope of work as set forth in the original RFQ is substantially and materially different than the revised scope of work and budget in the proposed contracts and such work should be re- advertised and re-bid. This decision to "reject all responses" and "re- advertise[] and re-bid" was based on an honest and good faith exercise of discretion, intended, ultimately, to allow Respondent to receive (in the words of Mr. Herrmann) "more bang for [its] buck." As the parties stipulated in Admitted Facts 39 through 41, Petitioner timely protested Respondent's intended "reject[ion] [of] all responses." As the parties stipulated in Admitted Facts 42 through 44, after the parties had unsuccessfully attempted "to resolve the protest by mutual agreement," Respondent, at Petitioner's request, referred the matter to DOAH on August 23, 2010.
The Issue The ultimate issue to be decided in this proceeding concerns whether the Petitioner C & M Building Systems, Inc. should be granted certification as a minority business enterprise. In order to make that determination it must be decided whether Maxine R. Chentnik, the president of the Petitioner corporation, and its minority group member owner, controls the management and daily operations of C & M Building Systems, Inc.
Findings Of Fact The Petitioner, C & M Building Systems, Inc., was incorporated in Florida on October 15, 1975. The Petitioner at that time operated under the name of Homes Unlimited, Inc. and was primarily engaged in residential construction contracting. Since that time, the name has changed to the present name of the Petitioner corporation and since at least the mid-1980's the primary business of the corporation has been commercial construction contracting. The net worth of the Petitioner corporation is under a million dollars and 60 percent of its stock is owned by Maxine R. Chentnik, an American female. Forty percent of the stock is owned by her husband Chester G. Chentnik. Mr. Chentnik has over 33 years experience in the construction business as well as a doctorate degree in business administration. For some twelve years he taught business management courses at Florida State University. Mrs. Chentnik has a bachelor of science degree in education and attended business college for approximately one year. Additionally, she has taken approximately 15 hours of college level courses in the fields of interior design and architectural drafting. Mrs. Chentnik's experience in the construction industry began when she and her husband built their own home in 1974. They served as their own contractors and Ms. Chentnik was most involved in that construction project since her husband worked full time at the university. This allowed her to gain experience in hiring and negotiating with subcontractors, arranging for payment of them, in ordering materials and supervising the construction of the home. She and her husband were in need of extra income and therefore she conceived the idea of starting their own residential construction business. When their Corporation, Homes Unlimited, Inc. formed, Mrs. Chentnik was unemployed and, since her husband was still employed at Florida State University, she devoted the majority of the time of the two owners and officers, to the operation of the business. After building their own home, various friends and other customers began engaging them to do residential building projects. Thus, from 1974 until 1982, they built approximately 12 residences. Some of these were built for speculation purposes. Mrs. Chentnik did part of the initial design of the homes, obtained prices from subcontractors, exercised supervision at the job site as to the manner of construction and maintained the books and records of the business. Mrs. Chentnik has never held a contractor's license herself. All of these projects were built using Mr. Chentnik's license. He did the estimating of materials needed, material and labor costs involved and arrived at prices to charge the owner or customer. He had similar managerial duties to those of Mrs. Chentnik. The supervision of the home construction was a joint project because Mr. Chentnik had more technical construction knowledge than Mrs. Chentnik due to his years of experience in construction. He had many years of construction experience working with his father prior to obtaining his college education. In 1982, Mr. Chentnik left his employment with Florida State University and engaged in the construction business full time. From 1983 to 1985, Homes Unlimited, Inc. was associated with Paragon Builders, a corporation which was owned by Mr. and Mrs. Chentnik and another couple. Paragon entered into a consultant agreement with Homes Unlimited by which Homes Unlimited was responsible for estimating material and labor needs, as well as job costs, for bidding purposes, and assembling, preparing and submitting bids. It was also charged with performing job site supervision of Paragon's construction projects. Mr. Chentnik performed under this consulting agreement for Homes Unlimited. Mrs. Chentnik was less active in the business operations at that time due to her child rearing duties. In 1985, the relationship between Homes Unlimited and Paragon Builders came to an end and Paragon Builders, Inc. was dissolved. Homes Unlimited had become primarily a commercial construction contracting company and as a result the name was changed to that of C & M Building Systems, Inc. in November, 1985. The initial directors of Homes Unlimited and C & M Building System corporation were Chester G. Chentnik and Maxine R. Chentnik. The articles of incorporation provide that there should not be less than two directors. The articles also provide that the initial bylaws of the corporation must be adopted by the Board of Directors, and that the Board has the power to amend them. Article 3 Section 2 of the Bylaws at present, provides that the number of directors shall be two and that the affairs of the corporation shall be managed by the Board of Directors. The Bylaws provide that the Board of Directors shall be elected by the shareholders at the annual meeting. Section 12 also provides for cumulative voting for election of the Board members, meaning that at each election of the Board, each shareholder shall have the right to vote the number of shares owned by him for as many persons as there are directors to be elected or he may accumulate his votes by giving one candidate as many votes as the number of directors to be elected, multiplied by the number of his shares, or by distributing those votes on the same principle among any number of candidates. The Bylaws provide that a majority of the directors constitutes a quorum for the transaction of business. Article 4 Section 1 of the Bylaws provides for a president, vice president, a secretary, and treasurer. All must be elected by the Board of Directors. The president is the chief executive officer of the corporation, subject to control by the Board. The president may execute contracts or other documents which the Board authorizes, as can the secretary or other officers. In January, 1986, the Board passed a resolution providing that estimates of the costs of work proposed to be done by the corporation are to be prepared by the president or secretary and that any proposal submitted by the corporation must be prepared, examined by and submitted to the president or secretary. It is also required that all orders for materials are to be given in writing by the president and secretary or by either of them acting with the consent of the other. No order is valid unless signed by the president or secretary. Contracts for the performance of work are valid only when signed by the president or vice president and by the treasurer or secretary. In April, 1986, C & M, by resolution of its Board, entered into an agreement with CGC Company whereby CGC would thereafter provide "all bidding, on-site management, and "special administrative services" (subject to the ultimate management power being vested in C & M's Board of Directors). CGC is to be compensated for these services at the rate of $1,000 per month, plus a performance fee at the end of each fiscal year, as determined by C & M's Board of Directors, based upon C & M's profitability during the preceding fiscal year. Chester Chentnik is the president of CGC Company and performs the services involved in construction site management, preparation of bids and the like. Mr. and Mrs. Chentnik have alternated at being president of C & M since its incorporation (under its original name) in 1975. Mr. Chentnik was first elected president and Mrs. Chentnik was elected vice president, as well as secretary- treasurer. Mr. Chentnik was president in 1976, 1978, 1980, 1982, 1984, 1986 and 1987. Mrs. Chentnik was president on alternate years beginning in 1977 and was president in 1988 and to the present. Mr. Chentnik explained that the alternating presidencies were intended to more evenly divide the workload involved in signing documents. Mr. Chentnik is currently the vice president and secretary-treasurer of the corporation. In 1986 and 1987, Mrs. Chentnik was employed with a real estate firm and Mr. Chentnik primarily ran C & M operations by himself. The Petitioner is currently working on construction projects involving the Florida A & M University President's residence, the Department of Transportation building; the computer room in the Carlton Building, a bus washing facility for the Leon County School Board, as well as a renovation project for the Florida Bar. Those projects are being performed under Mr. Chentnik's license. Mr. Richard Farrell was employed with C & M as a building superintendent and placed his contractor's license with C & M. His license was not used for any contracts presently being performed by C & M, however. Mr. Farrell is no longer an employee and is not performing work for C & M. Mr. Farrell now manages a related mill-work manufacturing company owned by the Chentniks, but is not performing any construction work or supervision for C & M. The decision to hire Mr. Farrell was a joint one by both Mr. and Mrs. Chentnik. His direct supervisor was Mr. Chentnik, although both Mr. and Mrs. Chentnik had supervisory authority over him. In any event, Mr. Chentnik's license is now the license qualifying the company as a construction contractor for purposes of Chapter 489, Florida Statutes, and the authority of the Construction Industry Licensing Board. Mr. Chentnik does the estimating for the company, prepares bids for jobs, is responsible for supervision of the construction details of the business, as well as for construction site management. On those bidding situations when he does not prepare the entire bid, he generally prepares the cost estimate portion of it and the remainder of the bid, concerning the addition of "overhead", and profit increments, are prepared jointly with Mrs. Chentnik. He also deals with the architects, engineers, and subcontractors, especially at the job site, and, since Mr. Farrell's departure, has taken over his job site supervision responsibilities. Mr. Chentnik has signed contracts for the company, executed change orders, pay requests, contract amendments, purchase orders and has prepared and submitted bids on behalf of the corporation. Mr. Chentnik signed the Department of Transportation contract in June, 1988 and an amendment to that contract in December of 1988. He also signed signed certain change orders to the Florida Bar contract in both September and November, 1988. The Carlton Building computer room bid was signed by Mr. Chentnik in September, 1988, as well as a change order for the Florida A & M University project which he signed in November, 1988. Mrs. Chentnik does not hold a contractor's license herself. She does all the bookkeeping for the company, pays the bills, and deals with the banks; in terms of checking and savings account deposits, withdrawals, as well as arranging credit. She has signed certain notes and lines of credit herself. She orders supplies and takes care of the insurance needs of the business and monitors which construction projects are coming up for bid, and obtains plans for them for the company to consider. She also contacts subcontractors for prices, attends bid openings, and arranges for bonding for the company for the jobs it undertakes. She assists in preparation of bids, especially the supplying of figures for overhead and profit on bids the company submits. She shares in the supervision of employees with her husband and directly supervises one employee, a part-time clerical helper. The company secures a great deal of its business by competitive bidding. Cost estimating is an important part of the bidding process. This estimating is performed primarily by Mr. Chentnik. Mr. Chentnik also developed the computer program to assist the company in its bidding efforts. The bidding program contains a range of percentages of overhead and profit which the company can add to the cost estimates on its bid to arrive at its most advantageous bid price. Mrs. Chentnik typically chooses a percentage for overhead and profit from the ranges set by the computer program. Mrs. Chentnik does not prepare entire estimates or bids herself. In all nearly cases her husband has assisted her. Mrs. Chentnik did prepare an entire bid for a flagpole project, valued at approximately $3500. In essence then, the decisions concerning which projects the company bids and which it declines to bid on have been joint decisions of Mr. and Mrs. Chentnik. They have usually jointly prepared bids, with Mr. Chentnik doing the greater part of that effort in providing the cost estimates. Both of them have historically negotiated prices with subcontractors in order to obtain figures for costs for a given project, in the course of preparation of a bid, however. The company has a checking account, a money market account and holds certificates of deposit. Both the Chentniks have equal drawing rights on all the accounts. The decision as to what amount of money to be placed in certificates of deposit is usually a joint decision. Both Mr. and Mrs. Chentnik have previously signed as personal guarantors on debt instruments for the company. Although Mrs. Chentnik does most of the banking business on behalf of the company, neither Mr. nor Mrs. Chentnik has sole control or authority over the bank accounts and the banking relationships of the corporation.
Recommendation Having considered the foregoing findings of fact and conclusions of law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore, RECOMMENDED: That a Final Order be entered denying the request for certification as a minority business enterprise of C & M Building Systems, Inc. DONE and ENTERED this 5th day of September, 1989, at Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-2758 Petitioner's Proposed Findings of Fact (The rulings below relate, by number, sequentially, to the unnumbered paragraphs of the Petitioner's proposed findings of fact) Accepted Accepted Rejected as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected as subordinate to the Hearing Officer's findings of fact on this subject matter and as not entirely comporting with the preponderant weight of the evidence. Rejected as subordinate to the Hearing Officer's findings of fact on this subject matter. Accepted in part, but subordinate to the Hearing Officer's findings of fact on this subject matter and not, in itself, dispositive of material issues presented. Respondent's Proposed Findings of Fact 1-15. Accepted Rejected as unnecessary and not dispositive of material issues. Accepted. Accepted. Accepted. Accepted. Accepted. Accepted. Rejected as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected as subordinate to the Hearing Officer's findings of fact on this subject matter. 25-29. Accepted. COPIES FURNISHED: James O. Shelfer, Esquire Gardner, Shelfer & Duggar 1300 Thomaswood Drive Tallahassee, Florida 32312 Susan B. Kirkland General Counsel Department of General Services Room 452, Larson Building 200 East Gaines Street Tallahassee, Florida 32399-0955 Ronald W. Thomas Executive Director Department of General Services Knight Building Koger Executive Center 2737 Centerview Drive Tallahassee, Florida 32399-0950
The Issue The issue is whether Respondent undertook to act as a contractor without a license as charged in the Administrative Complaints, and if so, what disciplinary action should be taken.
Findings Of Fact Pursuant to Section 20.165, the Division of Professions is a subordinate unit of the Department of Business and Professional Regulation (the Department). The Department provides administrative support, including prosecutorial support to the Construction Industry Licensing Board (the Board), which is also located within the Department. Mr. Grandmont is not currently licensed as a State Registered or State Certified Contractor in this state, nor has he ever been licensed by the Board. Mr. Grandmont's last known address is 355 China Berry Circle, Davenport, Florida. He was provided notice of the hearing at that address, and at 7733 Park Road, Charlotte, North Carolina 28210, which is the address he used when demanding a hearing on disputed facts in two of these cases. In DOAH Case No. 06-3279, he provided no address in his demand for a hearing. All attempts by U. S. Mail to notify Mr. Grandmont of the hearing, were returned. Mr. Grandmont is deemed to have known of the time, date, and place of the hearing, and is deemed to have waived his appearance at the hearing. On November 11, 2005, subsequent to Hurricane Wilma, Robert L. Coe, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged mobile home. He provided a written estimate of $10,500. The estimate contained a list of 11 items requiring repair, and stated that he would accomplish the repair of them. He demanded a $4,200 down payment, which Mr. Coe provided in a draft drawn on Fidelity Cash Reserves, and dated November 11, 2005. Mr. Coe never saw Mr. Grandmont again. The repairs set forth in the written estimate were not accomplished. The draft, however, was negotiated by Mr. Grandmont. On November 12, 2005, subsequent to Hurricane Wilma, Joseph Webster, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged residence. Mr. Grandmont discussed charging $13,500 in return for repairing Mr. Webster's residence. After negotiations, Mr. Grandmont agreed to do it for $11,500. No written estimate or contract was prepared. Mr. Grandmont demanded $5,750 payment in advance. Mr. Webster rounded off the down payment to $6,000 and presented Mr. Grandmont an official check of the Taunton Federal Credit Union, of Taunton, Massachusetts, for that amount. The check was negotiated by Mr. Grandmont, but the promised repairs were not accomplished. On November 4, 2005, subsequent to Hurricane Wilma, Ella Arseneau, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to replace her roof. He provided an estimate of $5,500 in return for repairing Ms. Arseneau's residence. He demanded that she pay $3,500 in advance, which Ms. Arseneau provided by presenting Mr. Grandmont a check for $3,500, drawn on an account in Wachovia Bank. The check was negotiated by Mr. Grandmont, but the roof was not repaired as promised. Mr. Coe is 78 years of age, Mr. Webster is 85, and Ms. Arseneau is 77.
Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation impose a fine upon Clifford Grandmont in the amount of $30,000. DONE AND ENTERED this 28th day of November, 2006, in Tallahassee, Leon County, Florida. S HARRY L. HOOPER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th of November, 2006. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Clifford Grandmont 7733 Park Road Charlotte, North Carolina 28210 Nancy S. Terrel, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Simone Marstiller, Secretary Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
The Issue The threshold issue in this case is whether the decisions giving rise to the dispute, which concern the allocation and disbursement of funds appropriated to Respondent by the legislature and thus involve the preparation or modification of the agency's budget, are subject to quasi-judicial adjudication under the Administrative Procedure Act. If the Division of Administrative Hearings were possessed of subject matter jurisdiction, then the issues would be whether Respondent is estopped from implementing its intended decisions to "de- obligate" itself from preliminary commitments to provide low- interest loans to several projects approved for funding under the Community Workforce Housing Innovation Pilot Program; and whether such intended decisions would constitute breaches of contract or otherwise be erroneous, arbitrary, capricious, or abuses of the agency's discretion.
Findings Of Fact Petitioners Pasco CWHIP Partners, LLC ("Pasco Partners"); Legacy Pointe, Inc. ("Legacy"); Villa Capri, Inc. ("Villa Capri"); Prime Homebuilders ("Prime"); and MDG Capital Corporation ("MDG") (collectively, "Petitioners"), are Florida corporations authorized to do business in Florida. Each is a developer whose business activities include building affordable housing. The Florida Housing Finance Corporation ("FHFC") is a public corporation organized under Chapter 420, Florida Statutes, to implement and administer various affordable housing programs, including the Community Workforce Housing Innovation Pilot Program ("CWHIP"). The Florida Legislature created CWHIP in 2006 to subsidize the cost of housing for lower income workers performing "essential services." Under CWHIP, FHFC is authorized to lend up to $5 million to a developer for the construction or rehabilitation of housing in an eligible area for essential services personnel. Because construction costs for workforce housing developments typically exceed $5 million, developers usually must obtain additional funding from sources other than CWHIP to cover their remaining development costs. In 2007, the legislature appropriated $62.4 million for CWHIP and authorized FHFC to allocate these funds on a competitive basis to "public-private" partnerships seeking to build affordable housing for essential services personnel.1 On December 31, 2007, FHFC began soliciting applications for participation in CWHIP. Petitioners submitted their respective applications to FHFC on or around January 29, 2008. FHFC reviewed the applications and graded each of them on a point scale under which a maximum of 200 points per application were available; preliminary scores and comments were released on March 4, 2008. FHFC thereafter provided applicants the opportunity to cure any deficiencies in their applications and thereby improve their scores. Petitioners submitted revised applications on or around April 18, 2008. FHFC evaluated the revised applications and determined each applicant's final score. The applications were then ranked, from highest to lowest score. The top-ranked applicant was first in line to be offered the chance to take out a CWHIP loan, followed by the others in descending order to the extent of available funds. Applicants who ranked below the cut-off for potential funding were placed on a wait list. If, as sometimes happens, an applicant in line for funding were to withdraw from CWHIP or fail for some other reason to complete the process leading to the disbursement of loan proceeds, the highest-ranked applicant on the wait list would "move up" to the "funded list." FHFC issued the final scores and ranking of applicants in early May 2006. Petitioners each had a project that made the cut for potential CWHIP funding.2 Some developers challenged the scoring of applications, and the ensuing administrative proceedings slowed the award process. This administrative litigation ended on or around November 6, 2008, after the parties agreed upon a settlement of the dispute. On or about November 12, 2008, FHFC issued preliminary commitment letters offering low-interest CWHIP loans to Pasco Partners, Legacy, Villa Capri, Prime (for its Village at Portofino Meadows project), and MDG. Each preliminary commitment was contingent upon: Borrower and Development meeting all requirements of Rule Chapter 67-58, FAC, and all other applicable state and FHFC requirements; and A positive credit underwriting recommendation; and Final approval of the credit underwriting report by the Florida Housing Board of Directors. These commitment letters constituted the necessary approval for each of the Petitioners to move forward in credit underwriting, which is the process whereby underwriters whom FHFC retains under contract verify the accuracy of the information contained in an applicant's application and examine such materials as market studies, engineering reports, business records, and pro forma financial statements to determine the project's likelihood of success. Once a credit underwriter completes his analysis of an applicant's project, the underwriter submits a draft report and recommendation to FHFC, which, in turn, forwards a copy of the draft report and recommendation to the applicant. Both the applicant and FHFC then have an opportunity to submit comments regarding the draft report and recommendation to the credit underwriter. After that, the credit underwriter revises the draft if he is so inclined and issues a final report and recommendation to FHFC. Upon receipt of the credit underwriter's final report and recommendation, FHFC forwards the document to its Board of Directors for approval. Of the approximately 1,200 projects that have undergone credit underwriting for the purpose of receiving funding through FHFC, all but a few have received a favorable recommendation from the underwriter and ultimately been approved for funding. Occasionally a developer will withdraw its application if problems arise during underwriting, but even this is, historically speaking, a relatively uncommon outcome. Thus, upon receiving their respective preliminary commitment letters, Petitioners could reasonably anticipate, based on FHFC's past performance, that their projects, in the end, would receive CWHIP financing, notwithstanding the contingencies that remained to be satisfied. There is no persuasive evidence, however, that FHFC promised Petitioners, as they allege, either that the credit underwriting process would never be interrupted, or that CWHIP financing would necessarily be available for those developers whose projects successfully completed underwriting. While Petitioners, respectively, expended money and time as credit underwriting proceeded, the reasonable inference, which the undersigned draws, is that they incurred such costs, not in reliance upon any false promises or material misrepresentations allegedly made by FHFC, but rather because a favorable credit underwriting recommendation was a necessary (though not sufficient) condition of being awarded a firm loan commitment. On January 15, 2009, the Florida Legislature, meeting in Special Session, enacted legislation designed to close a revenue shortfall in the budget for the 2008-2009 fiscal year. Among the cuts that the legislature made to balance the budget was the following: The unexpended balance of funds appropriated by the Legislature to the Florida Housing Finance Corporation in the amount of $190,000,000 shall be returned to the State treasury for deposit into the General Revenue Fund before June 1, 2009. In order to implement this section, and to the maximum extent feasible, the Florida Housing Finance Corporation shall first reduce unexpended funds allocated by the corporation that increase new housing construction. 2009 Fla. Laws ch. 2009-1 § 47. Because the legislature chose not to make targeted cuts affecting specific programs, it fell to FHFC would to decide which individual projects would lose funding, and which would not. The legislative mandate created a constant-sum situation concerning FHFC's budget, meaning that, regardless of how FHFC decided to reallocate the funds which remained at its disposal, all of the cuts to individual programs needed to total $190 million in the aggregate. Thus, deeper cuts to Program A would leave more money for other programs, while sparing Program B would require greater losses for other programs. In light of this situation, FHFC could not make a decision regarding one program, such as CWHIP, without considering the effect of that decision on all the other programs in FHFC's portfolio: a cut (or not) here affected what could be done there. The legislative de-appropriation of funds then in FHFC's hands required, in short, that FHFC modify its entire budget to account for the loss. To enable FHFC to return $190 million to the state treasury, the legislature directed that FHFC adopt emergency rules pursuant to the following grant of authority: In order to ensure that the funds transferred by [special appropriations legislation] are available, the Florida Housing Finance Corporation shall adopt emergency rules pursuant to s. 120.54, Florida Statutes. The Legislature finds that emergency rules adopted pursuant to this section meet the health, safety, and welfare requirements of s. 120.54(4), Florida Statutes. The Legislature finds that such emergency rulemaking power is necessitated by the immediate danger to the preservation of the rights and welfare of the people and is immediately necessary in order to implement the action of the Legislature to address the revenue shortfall of the 2008-2009 fiscal year. Therefore, in adopting such emergency rules, the corporation need not publish the facts, reasons, and findings required by s. 120.54(4)(a)3., Florida Statutes. Emergency rules adopted under this section are exempt from s. 120.54(4)(c), Florida Statutes, and shall remain in effect for 180 days. 2009 Fla. Laws ch. 2009-2 § 12. The governor signed the special appropriations bills into law on January 27, 2009. At that time, FHFC began the process of promulgating emergency rules. FHFC also informed its underwriters that FHFC's board would not consider any credit underwriting reports at its March 2009 board meeting. Although FHFC did not instruct the underwriters to stop evaluating Petitioners' projects, the looming reductions in allocations, coupled with the board's decision to suspend the review of credit reports, effectively (and not surprisingly) brought credit underwriting to a standstill. Petitioners contend that FHFC deliberately intervened in the credit underwriting process for the purpose of preventing Petitioners from satisfying the conditions of their preliminary commitment letters, so that their projects, lacking firm loan commitments, would be low-hanging fruit when the time came for picking the deals that would not receive funding due to FHFC's obligation to return $190 million to the state treasury. The evidence, however, does not support a finding to this effect. The decision of FHFC's board to postpone the review of new credit underwriting reports while emergency rules for drastically reducing allocations were being drafted was not intended, the undersigned infers, to prejudice Petitioners, but to preserve the status quo ante pending the modification of FHFC's budget in accordance with the legislative mandate. Indeed, given that FHFC faced the imminent prospect of involuntarily relinquishing approximately 40 percent of the funds then available for allocation to the various programs under FHFC's jurisdiction, it would have been imprudent to proceed at full speed with credit underwriting for projects in the pipeline, as if nothing had changed. At its March 13, 2009, meeting, FHFC's board adopted Emergency Rules 67ER09-1 through 67ER09-5, Florida Administrative Code (the "Emergency Rules"), whose stated purpose was "to establish procedures by which [FHFC would] de- obligate the unexpended balance of funds [previously] appropriated by the Legislature " As used in the Emergency Rules, the term "unexpended" referred, among other things, to funds previously awarded that, "as of January 27, 2009, [had] not been previously withdrawn or de-obligated . . . and [for which] the Applicant [did] not have a Valid Firm Commitment and loan closing [had] not yet occurred." See Fla. Admin. Code R. 67ER09-2(29). The term "Valid Firm Commitment" was defined in the Emergency Rules to mean: a commitment issued by the [FHFC] to an Applicant following the Board's approval of the credit underwriting report for the Applicant's proposed Development which has been accepted by the Applicant and subsequent to such acceptance there have been no material, adverse changes in the financing, condition, structure or ownership of the Applicant or the proposed Development, or in any information provided to the [FHFC] or its Credit Underwriter with respect to the Applicant or the proposed Development. See Fla. Admin. Code R. 67ER09-2(33). There is no dispute concerning that fact that, as of January 27, 2009, none of the Petitioners had received a valid firm commitment or closed a loan transaction. There is, accordingly, no dispute regarding the fact that the funds which FHFC had committed preliminarily to lend Petitioners in connection with their respective developments constituted "unexpended" funds under the pertinent (and undisputed) provisions of the Emergency Rules, which were quoted above. In the Emergency Rules, FHFC set forth its decisions regarding the reallocation of funds at its disposal. Pertinent to this case are the following provisions: To facilitate the transfer and return of the appropriated funding, as required by [the special appropriations bills], the [FHFC] shall: * * * Return $190,000,000 to the Treasury of the State of Florida, as required by [law]. . . . The [FHFC] shall de-obligate Unexpended Funding from the following Corporation programs, in the following order, until such dollar amount is reached: All Developments awarded CWHIP Program funding, except for [a few projects not at issue here.] * * * See Fla. Admin. Code R. 67ER09-3. On April 24, 2009, FHFC gave written notice to each of the Petitioners that FHFC was "de-obligating" itself from the preliminary commitments that had been made concerning their respective CWHIP developments. On or about June 1, 2009, FHFC returned the de- appropriated funds, a sum of $190 million, to the state treasury. As a result of the required modification of FHFC's budget, 47 deals lost funding, including 16 CWHIP developments to which $83.6 million had been preliminarily committed for new housing construction.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that FHFC enter a Final Order dismissing these consolidated cases for lack of jurisdiction. DONE AND ENTERED this 18th day of February, 2010, in Tallahassee, Leon County, Florida. JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of February, 2010.