Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DEPARTMENT OF ENVIRONMENTAL REGULATION vs. FLORIDA EAST COAST PROPERTIES, INC., 82-001640 (1982)
Division of Administrative Hearings, Florida Number: 82-001640 Latest Update: Sep. 06, 1983

Findings Of Fact Respondent is the owner and developer of the Plaza Venetia Marina, located in Biscayne Bay in Dade County, Florida, immediately north of the Venetian Causeway. The marina is constructed on submerged lands leased from the Board of Trustees of the Internal Improvement Trust Fund. On May 4, 1976, DER issued Permit No. 13-30-0364-6E to Respondent. That permit authorized the construction of two concrete marina docks, one "T" shaped and 255 feet long, and the other "J" shaped and 500 feet long. The project site is north of the Venetian Causeway on the western edge of Biscayne Bay, Section 31, Township 53 North, Range 42 East, Dade County, Florida. On August 18, 1977, DER issued Permit No. 13-30-3984 to Respondent. That permit authorized the construction of a 700 foot long "J" shaped pier with 24 finger piers and associated mooring pilings, and the construction of a 280 foot long "T" shaped pier. This permit authorized construction to be undertaken directly north of the docks authorized by Permit No. 13-30-0364-6E described above. On August 18, 1977, Respondent applied to DER's West Palm Beach office for a permit to construct the center pier of the Plaza Venetia Marina. On October 27, 1977, DER issued Permit No. 13-30-0740-6E to Respondent. This permit, which is the only one of the three permits at issue herein, authorized construction of a boat tie-up and fueling facility for a public marina. This facility represented a final phase of a master plan which includes the two other marinas with tie-up accommodations authorized by Permit Nos. 13-30-0364-6E and 13-30-3984. The drawings which accompanied the permit application carried the designation "FUEL" on the large platform at the end of the center pier of the marina. The cover letter from Respondent's authorized agent explained that " . . . the fueling area has been made sufficiently large so as to isolate the fuel pumps." No specific mention was made in the application or supporting materials of any building to be constructed on the central pier, and none of the permit drawings initially filed with DER depict any such building. DER employees who processed the permit, however, knew at some time during the processing of the permit application that some sort of structure would likely be constructed on the platform at the end of the center pier, although the plans did not disclose such a building, and the agency made no inquiries about, nor requested any additional information from Respondent concerning the type of structure contemplated. At the time of the issuance of Permit No. 13-30-0740-6E Respondent did not know the exact nature, size, or height of any structure that it might wish to build on the central platform. At the time, Respondent had only a conceptual idea of a structure that might accommodate the uses it contemplated for the platform. The words "fueling station" appear on the platform at the end of the center pier in one of the drawings attached to Permit No. 13-30-0740-6E. That drawing was not initially filed with the original permit application, but was provided during the permitting process by Respondent prior to issuance of the permit. Permit No. 13-30-0740-6E was issued to Respondent on October 27, 1977, pursuant to the authority granted DER under Chapters 253 and 403, Florida Statutes. Nowhere in the permit is there any reference to Section 258.165, Florida Statutes. The permit, by its expressed terms, authorized the following: To construct a boat tie-up and fueling facilities [sic] for a public marina. The facility will extend approximately 390 feet into Biscayne Bay from the bulkhead line. The dock will provide tie-up spaces for 20 boats and six fuel slips, and will contain floating oil collars in case of oil or gasoline spillage. This facility represents the final phase of a master plan which includes two other marinas with tie-up facilities . . . On January 11, 1979, some approximately fourteen months after issuance of the permit for the center pier, Respondent sent a letter to DER's West Palm Beach office which read as follows: Enclosed please find a copy of a letter as sent to the Army Corps, re: the service facility you and I discussed for the already approved fuel dock (State No. 13-30-0740-6E) for the Plaza Venetia Marina. I also enclose copy of the plans. Please review as quickly as possible since we intend to start construction on the marina within 30 to 45 days. (Emphasis added.) Enclosed with the January 11, 1979, letter to DER was a copy of a January 11, 1979, letter to the Army Corps of Engineers which read as follows: Recently I reviewed with [a Corps representative] the placement of a small service accommodation facility on the already approved fuel dock for the Plaza Venetia Marina . . . I left a set of plans with [the Corps] at the Corps office in Miami Beach. The facility is in close keeping with the permitted use of the marina. It will occupy less than half the already approved area of the fueling facility. It will be constructed on an already permitted facility. Included are a small bait and tackle shop; convenience store; captains' office; observation area and required bathrooms. The discharge from the bathrooms will flow directly into the main County sewer disposal system and will utilize a sewer pump-out facility located on the fuel dock. * * * After carefully reviewing my existing permit, the limited nature of the facility described, and its sole purpose of servicing the already permitted marina, please advise me if any modifications are required. I look forward to hearing from you as quickly as possible on this matter since construction of the marina is projected to begin within the next 30 to 45 days. A copy of the floor plan of the proposed building was attached to the January 11, 1979, letter received by DER. This floor plan indicates areas to be included in the building for bait and tackle facilities, a food store, storage areas, restroom facilities, and a marina office. Also shown on the floor plan is a storage area for electric carts to be used in servicing vessels utilizing the marina facility. The record in this cause establishes that Respondent never intended its January 11, 1979, letter to DER to be a request for a permit modification or an application for a new permit. Instead, the letter was intended only as a request for DER review of and comments on the proposed structure to be built at the end of the central pier. DER representatives in its West Palm Beach office forwarded the letter to the Tallahassee office of DER. DER never responded either orally or in writing to Respondent's communication of January 11, 1979, enclosing the building plan. On June 19, 1979, DER had opened its file No. 13-9916 in its standard form dredge and fill permitting section in Tallahassee in response to a letter received from Respondent requesting the addition of some dolphin pilings along the bulkhead at the Plaza Venetia Marina. The request from Respondent was treated as standard form application because the scope of the entire marina project exceeded short-form criteria. After receiving this request from Respondent, DER sent a completeness summary to Respondent within 30 days of receipt of the application requesting that Respondent provide approval from the Department of Natural Resources for the use of sovereignty submerged lands. Through various correspondence, this application was expanded to include several additional modifications to the overall marina, including reconfiguration of the fuel dock, addition of finger piers, reconfiguration of the "T" docks, and addition of a 12-foot boardwalk. Finally, the application was modified so that it constituted an application to consolidate the three existing permits. On January 29, 1980, Respondent submitted the last item of information required by the completeness summary except for DNR approval for use of sovereignty submerged lands. The aforementioned letter of January 11, 1979, from Respondent, which included the building floor plan, was apparently placed in DER file No. 13-9916 relating to Respondent's requested permit modification. Although the floor plan is contained in this file, the record in this cause clearly establishes that neither Respondent nor DER treated either the January 11, 1979, letter or the enclosed plan as a request for modification of Permit No. 13-30-0740-6E. DER file No. 13-9916 sat dormant for almost three years awaiting DNR consent for the use of state-owned lands. By letter dated July 10, 1981, DER requested Respondent to indicate whether it wished to pursue the permit modification application further since it had been 1,085 days since DER had notified Respondent of the necessity to furnish notification from DNR concerning further use of state sovereignty submerged lands. By letter dated July 15, 1981, Respondent withdrew its permit modification application. On April 20, 1979, the City of Miami issued a valid building permit for the marina fueling station. Respondent notified DER in July, 1979, that it was beginning construction of the marina. Construction of the central pier began on July 16, 1979, and ended on June 11, 1980. Construction of the fueling platform began on February 28, 1981, with erection of the fueling station walls beginning sometime after April 1, 1981. Subsequent to the commencement of construction DER representatives inspected the building site on several occasions. Respondent was not made aware in advance of when these inspections would occur since they were scheduled at the sole discretion of DER. DER first learned of the actual construction of the marina fueling station after receipt of a citizen complaint on December 1, 1981. Upon inspection of the site by DER personnel on December 2, 1981, it was discovered that the building on the fuel dock was partially complete with finish work and the placement of some interior and exterior walls remaining to be accomplished. DER served a warning notice on Respondent on December 7, 1981, advising Respondent of an alleged violation of its existing permit. A second warning letter was sent to Respondent on January 26, 1982, followed by the issuance of the Notice of Violation by DER. DER incurred costs and expenses of $405.40 in investigating the alleged violation. The structures authorized by Permit Nos. 13-30-0364-6E, 13-30-3984, and 13-30-0740-6E ("the structures") have been constructed by Respondent. The structures are located within the Biscayne Bay Aquatic Preserve ("the Preserve") established by Section 258.165, Florida Statutes. Biscayne Bay at the site of the structures is a navigable water of the State of Florida. A building with a floor area of approximately 3,800 square feet and a roof area of 5,292 square feet has been constructed at a cost of approximately $500,000 on the platform at the end of the center pier of the marina. The net area of the platform contains about 9,640 square feet. It has been stipulated by the parties that construction of the building on the center pier will not result in significant adverse water quality or biological impacts which were not contemplated when the above-referenced permits were issued for the marina. The building as presently constructed has provisions for the following uses: a waiting area for water-borne transportation, a bait and tackle shop and marine supply store, an electric cart parking and recharging station, and an attendant's room with cash register and equipment for the fuel pumps. All of these uses are customarily associated with the operation of marina facilities. The building as constructed differs in several minor respects from the one shown on the plans submitted to DER in the January 11, 1979, letter from Respondent. What had been shown on those plans as outdoor seating has been enclosed, walls and proposed uses have been relocated within the building, and the entire building has been moved back on the fuel dock. It is concluded, however, that these changes are of such a minor nature as to not constitute a material departure from the plans furnished to DER in January of 1979. As-built plans for the building have never been provided by Respondent to DER. At the time of Respondent's application for the permit for the center pier, DER rules required that a permit applicant provide cross-sectional drawings of proposed structures to be built in conjunction with docking facilities such as those proposed by Respondent. Drawings attached to the permit application show two cross sections through the center pier, but neither of these cross sections depict a building to be constructed on the pier. Respondent did not submit cross-sectional drawings for the building at the time of its application, and none had been submitted to DER as of the date of final hearing in this cause. However, DER at no time requested such cross-sectional drawings, despite the fact that those agency representatives processing Respondent's permit application assumed from the outset that some structure would and could be built by Respondent on the platform attached to the central dock under the terms of the October 27, 1977, permit. The estimated cost for removal of the building at the end of the central pier is $150,000-$200,000.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a Final Order be entered by the State of Florida, Department of Environmental Regulation, dismissing the Notice of Violation. DONE AND ENTERED this 3rd day of June, 1983, at Tallahassee, Florida. WILLIAM E. WILLIAMS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of June, 1983. COPIES FURNISHED: Paul R. Ezatoff, Jr., Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Clifford A. Shulman, Esquire and Thomas K. Equels, Esquire Brickell Concours 1401 Brickell Avenue, PH-1 Miami, Florida 33131 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Lee Rohe, Esquire Assistant Department Attorney Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, Florida 32303 Elton Gissendanner, Director Department of Natural Resources Executive Suite 3900 Commonwealth Boulevard Tallahassee, Florida 32303 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION, Petitioner, v. CASE NO. 82-1640 FLORIDA EAST COAST PROPERTIES, INC., Respondent. /

Florida Laws (6) 120.52120.57120.60403.141403.161403.813
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROGER S. WILLIAMS, 81-002194 (1981)
Division of Administrative Hearings, Florida Number: 81-002194 Latest Update: Sep. 03, 1982

Findings Of Fact At all times relevant hereto, Respondent, Roger S. Williams, held registered building contractor license number RB0026339 issued by Petitioner, Department of Professional Regulation, Construction Industry Licensing board, authorizing him to perform contracting under his individual name. Respondent, Frederick S. Schreiner, held certified general contractor's license numbers CG C004811 and CG CA04811 also issued by Petitioner authorizing him to perform contracting under his individual name and under Cape Development Corporation. Williams served as president of Architectural Builders, Inc. (ABI), a development firm located in Palm Bay, Florida. Schreiner was engaged in the contracting business generally in the Brevard County, Florida area. He has done construction work for ABI and Williams for the past eight or nine years. ABI held no licenses from either the state or local governments. On October 31, 1979, ABI entered into a construction contract with Jack and Stella Oleksy to construct a home at 842 South Becker Street, Palm Bay, Florida. The contract was approved by R. S. Williams as president of ABI. At a later undisclosed date, Williams attempted to pull a City of Palm Bay building permit on behalf of ABI. Whether the City gave formal or informal approval at that point is not clear; in any event the construction of the home began shortly thereafter. Several weeks later the City's chief building official told Williams that because he did not have local competency with the City, he could not pull a permit for a job. Williams was also advised that a recent change in state law required ABI to qualify to do business if ABI intended to construct homes within the City. When told that Frederick Schreiner would be constructing the home for ABI and that Schreiner held an appropriate license, the City official told Williams to have a construction contract executed between ABI and Schreiner to build the home. Thereafter, Schreiner pulled a permit for the job and posted it on the building site. He also gave the City a contract executed by he and ABI and which was dated November 29, 1979. During the course of the construction, Schreiner visited the building site approximately six to eight times. The work was done entirely by subcontractors who had been used on other construction jobs by Williams and Schreiner. The subcontractors were paid by ABI but worked under the supervision of Schreiner. When the job was completed Williams signed the final payment affidavit on which it was indicated that Williams was the contractor on the job. Oleksy was on the site daily to inspect the work. He complained periodically about various aspects of the job to Roger Williams. His main complaint concerned the trusses on the roof which he contended were out of alignment causing a wavy and uneven roof line. After the house was essentially completed, Oleksy lodged a complaint with Williams concerning the workmanship on the roof. Williams sent a carpenter to visit the premises who found some "variations" and worked for approximately three hours to correct the problem. He was then told by Oleksy it looked okay. Within the next few days, Oleksy again complained to Williams that the roof was wavy. Williams then sent out a roofing crew to attempt to correct the problem. After they completed their work, Williams received no further indication that the owner was unhappy. Williams later had a local relator familiar with the subdivision and an experienced carpenter who had framed more than 150 homes to view the roof. Both concluded the roof was of good workmanship and of similar quality to other homes in the neighborhood. Oleksy later filed a complaint with the City of Palm Bay concerning his roof. The City sent its chief building official to inspect the home. He described the roof as being of "poor workmanship". The same conclusion was reached by the city building inspector who also inspected the property. Because of this, the City made the notation "Hold problem roof" in its file and did not issue a certificate of occupancy to Oleksy. However, the City did not construe the roof to constitute a violation of the building code. Respondents asserted that a 1979 change in the law as to the qualification of agents caused doubt and confusion as to what was required by ABI and Williams. They also point out that if indeed a violation occurred, it was not intentional. Rather, Respondents simply desired to comply with all applicable statutes and regulations so that their construction businesses could continue to operate in a lawful manner. Other than the alleged violations herein, Respondents were not shown to have been subject to any prior disciplinary proceedings.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Roger S. Williams, be found guilty as charged in Count I, and be given a public reprimand. the remainder of the charges should be dismissed. It is further RECOMMENDED that Respondent, Frederick L. Schreiner, be found guilty as charged of all allegations except willfully and deliberately violating a state law, and be given a public reprimand. DONE and ENTERED this 29th day of June, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1982.

Florida Laws (4) 120.57489.119489.127489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT G. FELLENZ, 87-005327 (1987)
Division of Administrative Hearings, Florida Number: 87-005327 Latest Update: May 23, 1988

Findings Of Fact At all times material to these proceedings, Section 4-67 of the Building Regulations, Supplement Number 44, Pasco County Ordinances were in effect and said regulation is the applicable local law. During the applicable time period, the Respondent, ROBERT G. FELLENZ, SR., was registered by the State of Florida as a roofing contractor and held license number RC0027998. Mr. Fellenz is the qualifying agent for Fellenz Roofing Co., Inc. On or about March 24, 1987, the Respondent, FELLENZ entered into a contract with James J. Hoover to re-roof a portion of his residence located at 822 Crestfield Avenue, Holiday, Pasco County, Florida. On April 1, 1987, the Respondent went to the building department in Pasco County to acquire the necessary permit to begin the Hoover project. During the processing of the permit, the Respondent learned that a stop order had been placed on the job. His work crew had disobeyed his direct orders and began work before the permit was obtained. While the Respondent was in the process of having the stop order removed, he learned that his liability insurance had expired. Proof of liability insurance coverage was needed by the Respondent in order for the building permit to be issued by Pasco County on the Hoover project. The Respondent contacted his customer, Mr. Hoover, and explained that he had an insurance coverage problem which he needed to straighten out before work could continue on the roof, and before he could obtain the building permit. Mr. Hoover was not home on the day the re-roofing project was begun and completed by the Respondent. On April 3, 1987, the Respondent obtained liability insurance coverage which went into effect on that date. He began and completed the Hoover re- roofing project on that date. On April 6, 1987, the building department issued the building permit on the Hoover project. A final inspection was never called for by the Respondent. The Respondent has previously been found to have violated Section 489.129(1)(d), Florida Statutes, in Case No. 69097 Construction Industry Licensing Board.

Florida Laws (4) 120.5717.001489.105489.129
# 7
DEPARTMENT OF TRANSPORTATION vs. LUST INDUSTRIES, 82-002185 (1982)
Division of Administrative Hearings, Florida Number: 82-002185 Latest Update: May 21, 1990

Findings Of Fact Prior to March of 1981, Maxmedia held permits 8463-6 and 8462-6 issued by the Department for signs on property leased from Lust Industries located approximately at the intersection of U.S. 17/92 and Virginia Avenue in the city of Orlando, Florida. On March 23, 1981, Maxmedia advised the Department that the sign for which it held the above permits had been dismantled, and permits numbered 8463-6 and 8462-6 were returned to the Department for cancellation. On March 18, 1981, the Department received the application of Lust Industries for a sign at the location where the Maxmedia sign had been permitted, to be erected on property owned by Lust Industries. This application contained several irregularities, and the Department accepted it as an application only for the south face of the proposed sign. On May 27, 1981, the Department received the application of Lust Industries for the north face of this sign. The requested permits were issued by the Department on May 27, 1981. On February 24, 1981, Maxmedia executed a lease to property located approximately 30-50 feet south of the Lust Industries property. The term of this lease was to run from April 1, 1981 to April 1, 1984. On March 21, 1981, the Department received an application from Maxmedia for permits to erect signs at the location 30-50 feet south of the location owned by Lust Industries where Maxmedia had permits until it surrendered them. These permits were denied by the Department because of the permit application already received from Lust Industries for a sign 30 to 50 feet to the north. On March 23, 1981, Maxmedia applied to the city of Orlando for a building permit to erect the sign at its leased location south of the Lust Industries property, and this permit was issued to Maxmedia by the city. In January or February, 1981, Lust Industries had applied to the city of Orlando for a permit to build a sign on property near the sign of Maxmedia which was dismantled in March of 1981, but the requested city permit was denied because of the proximity of this location to the Maxmedia sign. After, the Maxmedia sign had been taken down, Lust Industries again applied for a city of Orlando building permit, but this was after the city permit had already been issued to Maxmedia; thus, the city again denied a permit to Lust Industries due to the existence of the outstanding permit held by Maxmedia. In May or June of 1981, after having received a building permit from the city of Orlando, and after having leased the property, Maxmedia proceeded to erect the sign 30-50 feet south of the Lust Industries property. It is this sign that is the subject of the Department's violation notice issued on June 30, 1982. It is the existence of this sign of Maxmedia, permitted by the city of Orlando, and erected on land currently leased, that prevents Lust Industries from obtaining the city of Orlando building permit it needs in order to be able to erect a sign 30 to 50 feet to the north. Thus, the Department seeks to revoke the state permits it issued to Lust Industries which violate the harmony of regulations provisions of the statutes and rules.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department issue its Final Order revoking the permits held by Lust Industries, dismissing the Notice of Violation against Maxmedia, Inc., and granting the application of Maxmedia, Inc., for permits as requested in its application received on March 24, 1981. THIS RECOMMENDED ORDER entered on this 18th day of April, 1984, in Tallahassee, Florida. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of April, 1984. COPIES FURNISHED: Charles G. Gardner, Esquire Haydon Burns Building, M. S. 58 Tallahassee, Florida 32301-8064 William F. Poole IV, Esquire 644 West Colonial Drive Orlando, Florida 32802 Gerald S. Livingston, Esquire P. O. Box 2151 Orlando, Florida 32802 Paul N. Pappas, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301

Florida Laws (4) 120.57479.07479.08479.15
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ANTONIO BERRIZ, 88-000654 (1988)
Division of Administrative Hearings, Florida Number: 88-000654 Latest Update: Aug. 31, 1988

The Issue Whether or not the business Respondent was associated with exceeded the scope of his contractor's license concerning the type of work undertaken, as described in the Amended Administrative Complaint, thereby violating Sections 489.129(1)(j), 489.115(1) and 489.117(2), F.S.? Whether or not Respondent failed to properly supervise the job site activities on that job, thereby violating Sections 489.129(1)(m), (j); 489.119, and 489.105(4), F.S.? Whether or not Respondent committed gross negligence, incompetence, or misconduct in connection with said job in violation of Section 489.129 (1)(m), by failure to supervise the contracting activities of the contracting business he was responsible for, so that Jorge Otero, President of Deluxe Construction Co., could obtain a building permit, exceed the scope of Respondent's license, and perform work that exhibited numerous defects? BACKGROUND AND PROCEDURE At the commencement of formal hearing, the parties stipulated ore tenus that Paragraph 6 of the Amended Administrative Complaint would be further amended to read: The business Respondent was associated with exceeded the scope of his license concerning type of work, violating Section 489.129(1)(j); 489.115(1)(b); 489.117(2). Thereafter, they entered into certain stipulated facts which are reflected among additional facts as found in this recommended order. Petitioner presented the oral testimony of Lolv Jaramillo, Herbert Gopman, Jorge Otero, and Frank Abbott, and had admitted four exhibits. Respondent presented neither oral testimony nor offered any exhibit. No transcript was provided. Respondent late-filed its post-hearing proposals, but each party's proposed findings of fact have been considered and are ruled upon in the appendix to this recommended order, pursuant to Section 120.59(2), F.S.

Findings Of Fact At all times material, Respondent was a licensed certified building contractor in the State of Florida, holding license number CB C002799 and was listed as the sole qualifying agent for Deluxe Construction Company. Deluxe could have had more than one qualifying agent but it did not. Jorge Otero was the sole owner, officer, and director of Deluxe Construction Company (Deluxe). He is not now, and never has been, a licensed contractor. Deluxe was formed in 1986, and Otero operated the company out of his home. In August 1986, Deluxe contracted with Lolv Jaramillo to remodel the Jaramillo residence in Miami for $23,800. Prior to the Jaramillo job, Deluxe had remodeled or added to several other residences. On those jobs, Respondent signed the building permit applications brought to him by Otero and made periodic inspections of the work, but Respondent never accepted any compensation from Deluxe for his services as qualifying agent of the company. Respondent was employed full-time otherwise. Before the Jaramillo job, Otero had had similar relationships with other contractors. Prior to beginning construction, Respondent met the Jaramillos at their residence at the request of Otero to discuss the possibility of the Jaramillos arranging a second mortgage through the brokerage firm which was Respondent's regular full-time employer. The Jaramillos were not told, and were not aware, that Respondent was affiliated with Deluxe. They relied on no representations of Respondent in eventually selecting Deluxe to do their construction job. The eventual contract between the Jaramillos and Deluxe was not conditioned on borrowing from Respondent's regular employer, and, in fact, the Jaramillos did not borrow from Respondent or his employer and obtained their financing elsewhere. The Jaramillos eventually instructed Otero to begin work, which he did. Otero first obtained the necessary building permit by going to the building department, filling in Respondent's contractor's license number on the application there, and signing his own name as qualifier. When Otero signed for the building permit, Respondent was out of town. Otero did not inform Respondent in advance of what he was going to do nor did Respondent discover Otero had done this until much later. On all previous contracts, Respondent had signed the permit applications and made the inspections in the manner described in finding of fact 5, supra. Respondent had done nothing to encourage Otero to think he could obtain a building permit as he did for the Jaramillo job. After Deluxe began construction at the Jaramillos' home, Otero was the sole supervisor on the job. After the Jaramillos paid Deluxe $14,000 of the contract price, they became dissatisfied with the pace and quality of the work done by Deluxe and they terminated the contract. According to Harry Gopman, structural engineer, the work done by Deluxe contained violations of local construction codes, but there is no evidence that Otero, Respondent, or anyone associated with Deluxe was convicted or found guilty of any crime. The work undertaken by Deluxe included plumbing work which Respondent was not licensed to perform. The work done by Deluxe and subcontractors under its supervision contained deviations from acceptable industry practice, including rendering a major load-carrying girder useless by penetrating it for the insertion of an air duct for the central air-conditioning system; cutting a concrete doorway lintel for insertion of another air duct, thus destroying the structural integrity of that lintel; and creating a structural hazard by placing a flat roof on the rear addition which severely "ponded" in rainstorms. From the evidence as a whole, it may be inferred that Respondent originally knew he was the sole qualifying agent for Otero/Deluxe. Otero did not affirmatively tell Respondent he had another qualifying agent for the job. However, since Otero kept telling Respondent that the Jarmillos were still having trouble getting financing, it was reasonable for Respondent to believe a building permit was not needed and construction would not begin until financing was found. It was after the commencement of construction, but prior to the termination of the contract by the Jaramillos, that Otero finally informed Respondent that he had begun work on the Jaramillo residence. It is not clear whether Respondent knew that the building permit bore his license number until after the termination of the contract. Respondent never visited the Jaramillo job site during construction. Respondent did not monitor the company finances, did not review subcontractual agreements, did not review invoices from subcontractors and materialmen, and did not call for inspections on the Jaramillo job. There is unrefuted expert testimony by Frank Abbott, architect and licensed general contractor, that a qualifying agent should do the things, but there is insufficient evidence to show that Respondent had a clear understanding that such was his position for the Jaramillo job.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing all charges against Respondent. DONE and RECOMMENDED this 31st day of August, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-0654 The following constitute rulings pursuant to S. 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of fact (FOF). Petitioner PFOF: 1-7, and 9-15. Accepted as modified to more exactly reflect the unrefuted testimony. 8. Accepted except for hearsay and subordinate and unnecessary material. Respondent's PFOF: 1-5, 7, 9. Accepted as modified to more exactly reflect the unrefuted testimony. 6. Rejected as stated. FOF 7 and 12 more correctly reflects the state of the record as a whole. 8. Rejected as stated because as stated it is a legal conclusion. A finding of fraud requires a finding of an affirmative intent which cannot be made upon the evidence presented. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 103 North Monroe Street Tallahassee, Florida 32399-0750 Lance Armstrong, Esquire 1035 Northwest 11th Avenue Miami, Florida 33136 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (6) 120.57489.105489.115489.117489.119489.129
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer