Findings Of Fact At all times here relevant Respondent was licensed as a roofing contractor and qualifying agent and owner of Handyman Service Company, Pinellas Park, Florida. In November or December 1982, representatives of Sandalwood Club Association contacted Richard Fabrizi, who was acting as sales agent for Handyman Service Company, about some repairs desired at their condominiums. Fabrizi advised Respondent and several meetings were held with Sandalwood representatives after which contract proposals for work desired by Sandalwood were presented by Respondent. It became apparent that complete reroofing of the Sandalwood condominiums was needed; however, the association did not have sufficient funds at that time for such a project. As a result of the negotiations a repair contract was entered into between Handyman and Sandalwood Club whereby Handyman contracted to perform certain work for $16,000 (Exhibit 1). At about the time this contract was entered into Pinellas Park became incorporated and established its own building department. Respondent was qualified to perform roofing contracting in Clearwater, in whose jurisdiction Sandalwood was placed before Pinellas Park, but he had not qualified to contract in Pinellas Park. When this was realized, Respondent engaged the services of Edgar Plumtree, a licensed contractor, to pull permits and supervise the roofing at Sandalwood. The permit for this work (Exhibit 2) was signed by Joseph A. Saturno, contractor, but no evidence was presented regarding Saturno or how his name came to appear on Exhibit 2. Expert testimony was presented that the work proposed to be performed in Exhibit 1 constituted much more than repair work; however, Respondent's witness's testimony that the contract was intended by all parties to be a temporary repair, guaranteed for three years, was unrebutted. Expert testimony that the use of 90# mineral-coated roofing material in valleys did not comply with the Southern Standard Building Codes, which has been made applicable to Pinellas Park, was modified on cross-examination by testimony that such material could be used for repairs if approved by the building inspector. The evidence was unrebutted that the building inspector approved the use of the 90# roofing in the valleys. The expert witness further found violation of codes when a coating material was placed over aggregate surface on a flat roof or aggregate was reused without cleaning; however, on cross-examination this witness acknowledged that rerocking was not a code violation if sold as a repair in lieu of new roof. He did not consider the scope of the work shown in Exhibit 1 to be compatible with a minor repair, despite the intent of the parties to so treat this work. The work on the Sandalwood project was completed in March 1983. Sandalwood was in the process of issuing a contract to replace the shingles on their sloping roofs and in May 1983 Respondent met with Sandalwood Condominium Association as one of the bidders was unhappy with the roofing repairs done by Handyman. Due to brittle shingles the tie-ins were unsatisfactory. An appointment was set up with representatives of the Pinellas Park Building Inspector, Sandalwood representatives, and Handyman representatives. Handyman was also bidding on the shingle replacement contract. On May 26, 1983, this meeting was held including the successful bidder (Baker) on the shingle roof replacement contract. The building inspector, Respondent, Baker, and Sandalwood representatives went on the roofs. The building inspector suggested Baker do the tie-ins from the work done by Handyman, for which the latter agreed to pay, but Baker declined. Thereafter, the flashing between the shingle roofs and the flat roofs was installed by Handyman and the shingles by Baker. Exhibit 6 indicates the shingles do not properly cover the flashing. Respondent's testimony that the work performed by Handyman was exactly what Sandalwood requested them to perform was not rebutted.
Recommendation It is RECOMMENDED that Franklin A. Marciano be issued a letter of reprimand for completing a roofing repair contract in a municipality in which he was not licensed. DONE AND ENTERED this 19th day of October 1984 at Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October 1984. COPIES FURNISHED: Charles Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Frank A. Marciano 11327 43rd Street, North Clearwater, Florida 33520 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan, Executive Director Board of Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202
Findings Of Fact At all times relevant, the Respondent was licensed by the Construction Industry Licensing Board as follows: License No(s): RC 0021957 Licensed as: Registered roofing contractor Address of record is in: New Port Richey, Florida A certain contracting job was undertaken as follows: Customer: Stella Domas Approximate contract date: 6-85 Approximate price: $600 Job location: New Port Richey, Florida Job generally consisted of: Repair roof of Customer's house Said job was undertaken by the contracting business Respondent was associated with and responsible for in his capacity as a licensee. Respondent proceeded without a timely permit having been issued, violating local law, either deliberately or through improper supervision, in violation of 489.129(1)(d), (m), (j) 489.119; and 489.105(4), Florida Statutes. Respondent proceeded without timely obtaining all required inspections, violating local law, either deliberately or through improper supervision, in violation of 489.129(1)(d), (m), (j); 489.119; 489.105(4), Florida Statutes. Respondent gave a guarantee on said job to the Customer, and thereafter failed to reasonably honor said guarantee, in violation of 489.129(1)(m), (j); 489.119; 489.105(4), Florida Statutes. Respondent performed said work in a substantially deficient manner, therefore, violating 489.129(1)(m). Respondent previously has been disciplined by the State Construction Board. STIPULATED DISPOSITION Based on the Stipulated Findings Of Fact and Conclusions Of Law, the parties agree to the following disposition of the Amended Administrative Complaint: The Respondent shall pay a $1500 fine, payable within 60 days from entry of a final order approving this stipulated disposition; and The Respondent's registered roofing contractor license number RC 0021957 shall be suspended for 60 days, beginning 60 days from the entry of a final order approving this stipulated disposition.
Recommendation It is recommended that the Construction Industry Licensing Board enter a final order approving and incorporating the settlement stipulation between the parties. RECOMMENDED 28th day of July, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of July, 1988. COPIES FURNISHED: Jack M. Larkin, Esquire 806 Jackson Street Tampa, Florida 33602 Lee Ellen Acevedo, Esquire 7716 Massachusetts Avenue New Port Richey, Florida 34653 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
The Issue Whether Respondent's registered roofing contractor's license should he revoked, suspended or otherwise disciplined based on charges that he violated Ch. 455, Florida Statutes (1979), by (1) abandoning a construction project; making a misleading, deceptive or untrue representation in the practice of his profession; (3) violating local building codes in two instances; and (4) engaging in the business of contracting in a county or municipality without first complying with local licensing requirements.
Findings Of Fact At all times material hereto, respondent held registered roofing contractor's license, number RC 0033215, issued by the State of Florida. The license has been in a delinquent status since July 1, 1981. (Petitioner's Exhibit 1). Between October 1, 1979, and September 30, 1980, respondent held an occupational license issued by the County of Indian River, Florida, which enabled him to engage in the business of roofing contracting in that county. However, this occupational license expired on September 30, 1980. (Petitioner's Composite Exhibit 9). In February, 1981, respondent entered into a verbal agreement with Ezra Grant to repair, for compensation, all leaks in the front and rear sections of the roof on Grant's home, which was located in Sebastian, Florida. (Testimony of Grant). When respondent and Grant entered into this verbal agreement, respondent gave Grant one of his calling cards. On the face of the calling card, in the lower right corner, was written "licensed and insured." (Petitioner's Exhibit 4; Testimony of Grant). At all time material hereto, respondent was not licensed to engage in the business of roofing contracting in the City of Sebastian, Florida. (Petitioner's Exhibit 5). Pursuant to the agreement, respondent performed roof repairs on Grant's home. (Testimony of Grant). Respondent failed to obtain a permit to perform such roof repairs in violation of Section 105.1, Standard Building Code, as adopted by the City of Sebastian, Florida in Section 7-16, Article II, Sebastian Code of Ordinances. (Petitioner's Exhibits 6 and 8a and b). On February 19, 1981, respondent submitted a bill in the amount of $800.00 to Grant for the roof repairs. The bill described the work performed and stated that the "work is guaranteed for 1 year." (Petitioner's Exhibit 2; Testimony of Grant). On February 20, 1981, Grant paid respondent, in full, for the described roof repairs. (Petitioner's Exhibit 3). Approximately two weeks after respondent performed the roof repairs, the roof over the rear portion of Grant's home began to leak, again, in the area where it was repaired. (Testimony of Grant). Respondent returned to Grant's home, on two occasions1 after the discovery of continuing leakage in the roof over the rear portion of Grant's home. However, respondent did not perform roof repairs on either occasion. On the first occasion, he merely removed equipment which he had left at Grant's home. (Testimony of Grant). After Grant complained to petitioner Department of Professional Regulation, respondent returned a second time. He inspected the rear portion of Grant's roof, removed two layers of slate from the roof, and tested it by pouring water over it. Although this test revealed that Grant's roof still leaked, Grant made no effort to repair the leakage. (Testimony of Grant). Arthur Mayer, then the Building Official for the City of Sebastian, observed respondent removing the slate from the roof. He instructed respondent that, upon finishing the work, he should go to the Sebastian City Hall and apply for a roofer's license and a permit for the roof repairs already performed on Grant's home. Respondent promised to comply. (Testimony of Mayer). But, despite his promise, he failed to apply for and obtain a license to engage in the business of roofing contracting in the City of Sebastian, Florida. He also failed to apply for and obtain a roof permit, and pay the proper late fees, as required by Section 107.2, Standard Building Code, as adopted by the City of Sebastian, Florida, in Section 7-16, Article II, Sebastian Code of Ordinances. (Testimony of Mayer; Petitioner's Exhibits 6, 8a and c). Grant, eventually, had his roof repaired by another contractor at a cost of $150.00. (Testimony of Grant).
Recommendation Based on the foregoing, it is RECOMMENDED: That respondent's registered roofing contractor's license be revoked. DONE AND ORDERED this 28th day of February, 1983, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of February, 1983. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Jerry E. Smith Route 1, Box 111B Fellsmere, Florida 32948 James Linnan, Executive Director Construction Industry Licensing Board P. O. Box 2 Jacksonville, Florida 32202
The Issue Whether Respondent committed the offenses alleged in the Administrative Complaint and the penalties, if any, that should be imposed.
Findings Of Fact At the times pertinent to this proceeding, Respondent was not registered, certified, or otherwise licensed to engage in contracting in the State of Florida. At the times pertinent to this proceeding, Respondent conducted business through an entity known as C. J. Home Improvement Corporation, which was also not registered, certified, or otherwise licensed to engage in contracting in the State of Florida. In 1995, Joseph Pallant was one of the owners and the manager of a commercial building located at 3700 Biscayne Boulevard, Miami, Florida. In January 1995, Mr. Pallant entered into an agreement to lease the building for a term of ten years to a non-profit organization named PWAC, an acronym for People With Aids Coalition. PWAC had an office in the adjacent block and wanted to operate a thrift shop at the subject premises. The roof on the subject building leaked. The parties agreed that Mr. Pallant would pay to replace the roof and that PWAC would thereafter be responsible for maintenance. The officers of PWAC informed Mr. Pallant that they wanted Respondent to do the roofing work. There was a conflict in the evidence as to whether Mr. Pallant knew that Respondent was unlicensed. It is clear that Mr. Pallant and Respondent knew one another prior to January 1995. Based on Mr. Pallant's testimony, which the undersigned finds credible, it is found that Mr. Pallant knew that Respondent was in the building repair business, but that he did not know Respondent was unlicensed. Respondent's assumption that Mr. Pallant knew he was unlicensed is not as credible as Mr. Pallant's direct, unequivocal testimony that he had no such knowledge. After having several conversations with Mr. Pallant by telephone and at the building, Respondent prepared a written proposal on his business form to do the work necessary to replace the roof. The proposal was submitted to PWAC. The proposal described in detail the work that would be done and the materials that would be furnished, the time frame for the work, and the price. The price was set at $6,183.00 plus $400.00 if certain additional work would have to be done on certain drains. PWAC was provided a copy of the proposal that was dated February 25, 1995. Respondent signed this proposal and affixed the corporate seal of his business entity. Under Respondent's signature was the phrase "personally individually guaranteed." At all times pertinent to this proceeding, Respondent knew that Mr. Pallant was one of the owners of the building and that he would be paying for the roofing work. On February 27, 1995, Respondent and Mr. Pallant met. Respondent gave Mr. Pallant an unsigned copy of the written proposal (dated February 27, 1995, but otherwise identical to the form given PWAC, but dated February 25, 1995). After they discussed the work, Mr. Pallant accepted the proposal and gave Respondent a check made payable to C. J. Home Improvement in the amount of $3,100.00. Respondent accepted this check and deposited the proceeds of the check in his company's bank account. Without the prior knowledge or consent of Mr. Pallant, Respondent attempted to subcontract the roofing job to a licensed roofer named Don Palmier.1 No work was started on the job. In March 1995, Mr. Pallant met with representatives of PWAC and Respondent to discuss the lack of progress. As a result of that meeting, Mr. Palmier refused to proceed with the roofing job2 and Mr. Pallant learned that Respondent was unlicensed and could not do the work. During the course of the meeting PWAC cancelled its lease. Mr. Pallant subsequently filed suit against C. J. Home Improvement for the return of the $3,100.00. Despite obtaining a final judgment for that sum plus costs and fees, the Respondent has not satisfied any portion of the judgment. As of April 23, 1998, the Petitioner's costs of investigation and prosecution in this case, excluding costs associated with an attorney's time, totaled $269.62.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a final order that adopts the findings of fact and conclusions of law contained herein; finds Respondent guilty of violating the provisions of Section 489.127(1)(f), Florida Statutes, as alleged in Count I of the Administrative Complaint; dismisses Count II of the Administrative Complaint; imposed an administrative fine against the Respondent in the amount of $2,500.00; and assesses costs against Respondent in the amount of $269.62. DONE AND ENTERED this 10th day of September, 1998, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of September, 1998
Findings Of Fact Jurisdiction findings Petitioner is the state agency charged with regulating licenses for roofing contractors in the State of Florida. At all times material to the allegations of these cases, Respondent held two licenses; he was a certified roofing contractor, license no. CC CO55580, and a registered roofing contractor, license no. RC 0060386. Respondent filed an application to qualify the company, D.S.S. & Sons, Inc., as a licensed roofing contractor; however, he failed to complete all documents necessary for licensure, and his application was closed for lack of response effective August 3, 1993. Respondent's address of record with the Department is 821 SW Dwyer Street, Port St. Lucie, Florida 34983. D.S.S. & Sons, Inc. is not now, nor has it ever been, licensed to perform roofing construction by the State of Florida. Facts common to all consumers On or about August 24, 1992, Hurricane Andrew struck Dade County, Florida, resulting in damage to hundreds of roofs. Roof repair or total replacement following the storm was not uncommon. Due to the large amount of damage, and the demand for roofing materials created by the volume of work to be performed, some contractors had difficulty obtaining roofing supplies. Additionally, some contractors had difficulty hiring qualified labor to perform the extensive roofing that was in great demand. The problems with obtaining materials and labor, however, were short term in that most roofing contractors made arrangements to bring in supplies and staff from other areas. In fact, by the time the work was to be performed in connection with these cases, the problems which had plagued the Dade County contractors were subsiding. Additionally, at all times material to these cases, the weather would not have been a factor to justify the delays complained of by these consumers. Rainy weather did not cause any prolonged work delays after the storm. Findings as to Helmly Charles Helmly resides at 11985 SW 98th Lane, Miami, Florida. His home was damaged by Hurricane Andrew and required roof replacement. Mr. Helmly contracted with Respondent to re-roof his home for the sum of $17,940.00. The contract was signed by Respondent's salesman, Felix Fowler, and identified D.S.S. & Sons, Inc. doing business as Darryl Saibic, Roofing Contractor as the licensed entity. Mr. Helmly paid an initial deposit of $5,382.00 in order for the Respondent to begin work on the project. The next payment, an additional $5,382.00, was to be due at the "dry in" stage of the job, with the final payment (the balance) due on completion. One of the contract provisions Mr. Helmly insisted upon was a completion deadline to be stated in the contract. He was expecting visitors and he was anxious to have the home re-roofed before their arrival. He insisted that a guaranteed completion date of March 7, 1993 be noted on the face of the contract. Mr. Helmly complied with all requirements of the payment schedule outlined by the contract. In fact, he remitted $10,764.00 even though the roof had not been at the "dry in" stage. Between January and February, 1993, the Respondent removed the old roof, installed a base sheet, and nailed a single ply roof membrane to the roof. After February, 1993, the Respondent failed to timely complete the Helmly roof. The value of the work performed by Respondent on the Helmly roof was no more than $3,588.00. The Respondent did not respond to numerous telephone calls and letters from Helmly, and threatened to place a lien on the Helmly property when Mr. Helmly attempted to cancel the contract in May, 1993. Mr. Helmly went to the Dade County Building Department and complained about roof leaks in June, 1993 (Respondent had still not done any further work). On or about June 4, 1993, Respondent sent a crew to the Helmly property to repair the roof. The repairs caused the roof to leak more. Respondent did not refund Mr. Helmly's money, did not complete the roof, and showed a gross indifference to the plight which resulted when he failed to timely complete the project. In July, 1993, desperate to have his roof completed, Mr. Helmly offered to purchase the tiles himself if Respondent would have a crew come install the new roof. Respondent agreed to have a crew install the tile within ten days of its arrival. On September 17, 1993, Mr. Helmly took delivery of the new tile, paid for it in full (a cost of $4,803.00) and notified the Respondent so that the installation could begin. Respondent never returned to complete the re-roofing. He failed to honor his verbal agreement to install the tiles. By letter dated October 1, 1993, Respondent offered to reimburse Helmly for the overage if he would hire another contractor to complete the job. On October 19, 1993, Mr. Helmly hired a new contractor who completed the installation of the new roof in early November, 1993. Approximately eight months after the deadline on Respondent's contract, Mr. Helmly had his new roof. Extra expenses totalling $2,936.21 were paid by Mr. Helmly as a result of the Respondent's abandonment of this job. Findings as to Gurdian On January 14, 1993, the Gurdians contracted with Respondent through his agent, Ed Comstock, to repair the roof on their home located at 13301 SW 110 Terrace, Miami, Florida. The contract was executed as D.S.S. and Sons, Inc. d/b/a Darryl S. Saibic, Roofing Contractor and called for a total payment of $7,725.00 for the work to be done. The Gurdians made a deposit of $2,300.00 on January 14, 1993 by check made payable to D.S.S. and Sons, Inc. and received a partial release of lien. On February 8, 1993, the Respondent pulled a permit for the Gurdian home but never called for inspections on this project. In February, 1993, all the tiles were removed from the roof and roofing paper was installed. On March 1, 1993, the Gurdians made a second payment of $2,300.00 by check made payable to D.S.S. and Sons, Inc. and received another partial release of lien. The Respondent did not timely complete the Gurdian roof. From June through November, 1993, Respondent sent the Gurdians unsigned notices claiming he would return to their job but did not do so. Numerous excuses were offered as to why the project was not completed; however, none of these had merit. The Gurdians waited until April, 1994 hoping the Respondent would return and complete the work. They drove to Respondent's office and left a message seeking assistance. Finally, Respondent recommended a company called CTI to complete the roof work for the Gurdians. When contacted, CTI told the Gurdians it would cost $7,600.00 to complete their job for which they, not Respondent, would be responsible. The Gurdians then attempted to notify the Respondent at his address of record by certified mail of their continuing problems but the letter was returned to them unopened. In June, 1994, the Gurdians hired another company to finish their roof which was finally complete and passed inspections on July 26, 1994. The Gurdians were required to pay a total of $13,475.00 to have their roof replaced because the Respondent failed to perform under the original contract. Due to the Respondent's abandonment and indifference in connection with this project, the Gurdians were damaged in an amount not less than $4,200.00. The value of the work performed by Respondent on the Gurdians' roof did not exceed $1,545.00. Respondent has not refunded any of the funds paid by the Gurdians. Findings of fact as to Vila Marta Vila resides at 11116 SW 133 Place, Miami, Florida 33186. Like the others discussed above, the Vila home was damaged and required a new roof. On January 13, 1993, Vila signed a contract with Ed Comstock acting on behalf of D.S.S. and Sons, Inc., doing business as Darryl S. Saibic, Roofing Contractor, to have her roof repaired for a total contract price of $7,200.00. A down payment of $2,160.00 made payable to the company was made at that time. On February 8, 1993, Respondent pulled a permit to re-roof the Vila home. On February 15, 1993, Vila paid an additional $2,160.00 to Respondent. At that time Respondent removed the tiles from the Vila roof and installed one layer of roofing paper over the roof decking. Despite representations from Respondent that new tiles would be delivered in approximately three to four weeks, the Respondent did not install a new roof on the Vila home. In February and March, 1993, the roof was patched three times to stop leaks but no substantive work was performed to install new tiles. Respondent did not return to the Vila home despite numerous requests from the homeowner for the work to be completed. In June, 1993, Respondent represented that the Vila job might be completed if the tiles were sent out COD. When Vila attempted to verify that information, she was told she had paid enough to not have that concern. However, no tiles were ever delivered to her home. In August, 1993, Vila, after Respondent failed to return telephone calls, wrote to Respondent and demanded a refund. She has not received one. Vila ended up paying $7,754.00 to another contractor to have her roof replaced. The value of the work performed by Respondent on the Vila project did not exceed $1,440.00 yet he has failed or otherwise refused to refund the difference between that amount and what she paid. Vila has suffered monetary damages in an amount not less than $4,800.00 as a result of Respondent's abandonment of this project. Findings of fact as to Bermudez Mr. and Mrs. Bermudez reside at 8335 SW 147th Place, Miami, Florida. On November 30, 1992, they signed a contract with Respondent in the amount of $6,400.00 to correct extensive leakage on both floors of the Bermudez home. Mrs. Bermudez gave a deposit in the amount of $1,860.00 and was told that the repairs would begin in two weeks and be completed in approximately five weeks. In December 1992, and January, 1993, the Respondent performed some minor patching but no significant work was undertaken to repair the Bermudez home. In January, 1993, Respondent pulled a permit to replace the Bermudez roof. Within a week of the permit, Respondent sent an unsigned form letter to the Bermudez advising them that there would be delays. In February and March, 1993, the Respondent's crew stripped the old tile off the Bermudez home and installed batten and roofing paper over the decking. Mrs. Bermudez made deposits totalling $3,720.00 to Respondent in connection with this contract. Despite numerous requests from Mrs. Bermudez, Respondent did not complete the roof. In July, 1993, Respondent sent a crew to the Bermudez home in connection with a leak but the repair did not resolve the problems and did not substantively finish the roof. As with the other cases, between July and November, 1993, Respondent sent numerous unsigned form letters to Mrs. Bermudez offering false or ridiculous excuses for why the project had not been completed. In January, 1994, Mrs. Bermudez filed a formal complaint against Respondent but he never completed the job nor refunded the deposits. Between March and July, 1994, Respondent represented he would complete the Bermudez job but did not do so. The Bermudez roof was not completed until December 13, 1994. As a result of Respondent's incompetence, inability, or refusal to complete the Bermudez roof, the family lived with a leaking roof for approximately two years and incurred unnecessary expenses. Respondent showed a gross indifference to the plight of the Bermudez family. Respondent could not have timely completed the projects described above during the period July, 1993 to July, 1994, as his workers compensation had expired. The numerous promises to perform the contracts as originally agreed were meaningless.
Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order revoking Respondent's licenses, requiring Respondent to make full restitution to the consumers in these cases before being entitled to seek new licensure, imposing an administrative fine in the amount of $10,000, and assessing costs of investigation and prosecution of these cases as set forth in the affidavits filed in this cause. DONE AND RECOMMENDED this 25th day of October, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of October, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 95-1079, 95-1080, 95-1081, 95-1082 Rulings on the proposed findings of fact submitted by the Petitioner: 1. Paragraphs 1 through 155 are accepted. Rulings on the proposed findings of fact submitted by the Respondent: 1. None submitted. COPIES FURNISHED: Elizabeth Masters Senior Attorney Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 230 Jacksonville, Florida 32211 Darryl Saibic 821 S.W. Dwyer Road Port St. Lucie, Florida 34983 Richard Hickok Executive Director Department of Business and Professional Regulation Construction Industry Licensing 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
Findings Of Fact At all times material to these proceedings, the Respondent LARRY DAVID COMES, was licensed by the State of Florida as a registered specialty contractor and held license number RX00400762. Mr. Comes is the qualifying agent for D & L Enterprises. At all times material to these proceedings, the Respondent CHARLES J. GOREE was licensed by the State of Florida as a certified general contractor and held license number CG C007621. Mr. Goree is the qualifying agent for CJC Incorporated. In the beginning of the year 1985, the Island Village Association decided to reroof all six buildings located in the condominium project. At the time of the decision, all of the roofs were leaking. The existing roofs had been repaired and patched numerous times since the condominiums were built in 1973. On February 27, 1985, the Respondents COMES and GOREE submitted a joint proposal to the association to remove the existing built-up roof, apply a Neoprene/Hypalon roof, and remove and reshingle the mansard roof for $19,865.00. On April 15, 1985, a written contract was entered into between Island Village Condominium Association and David L. Comes, d/b/a D & L Enterprises, as contractor for the reroofing of Building "C." The Contract required the contractor to furnish all materials and labor to remove the existing built-up roof. Rotten wood on the deck was to be replaced on a time and materials basis. Damaged scuppers were to be replaced and other scuppers were to be cleaned out by the contractor. The Neoprene/Hypalon system would then be applied to the flat roof and the parapet walls. The mansard roof was to be removed and reshingled. Although Charles J. Goree, d/b/a CJC Incorporated, was not named in the contract, the omission was an oversight. At all times during the course of the reroofing project, the Respondent GOREE was responsible for the removal of the existing built-up roof and the application of new shingles to the mansard roof. The Respondent COMES was responsible for the application of the Neoprene/Hypalon roofing system. The reroofing project was a joint undertaking in which Respondents GOREE and COMES exercised equal authority, joint control, or right of control. The Respondents had a community of interest in the performance of the contract with the association. Respondents GOREE and COMES were familiar with what was required of each of them under the verbal joint venture agreement as they had conducted business in the same manner over an extended period of time on several projects. On May 10, 1985, Respondent GOREE applied for and received a building permit for the reroofing of Building "C" at Island Condominiums. During the removal of the built-up roof, GOREE observed "an absolute mess and disaster." The roof had been patched in various ways on numerous occasions. GOREE observed a few "T nails" in a piece of metal stripping picked up with shovels on the roof. The "T nails" discovered were the type which are shot into materials from a nail gun. (See GOREE Exhibit #2) They are not used to secure plywood on a deck because of their short length. Another "T nail," such as GOREE's Exhibit 2, was found by GOREE lying on the area of the roof by the air conditioners. This area of the existing roof was not removed or disturbed during the reroofing process. In the application of his common sense and knowledge of good construction practices and in light of the material in which the "T nails' were located, Respondent GOREE was not put on notice that these "T nails" may have been used to fasten the plywood decking. The type of "T nail" which was used upon plywood roof decking a few years ago in Florida was longer, thicker, and shaped like an elongated wedge. (See GOREE Exhibit 4) None of the "T nails" formerly used for plywood decking were observed by GOREE on the roof. Once the built-up roof was removed, Respondent COMES acted within the terms of the joint venture agreement by applying the Neoprene/Hypalon roofing system in full compliance with the specifications as set forth in the contract with Island Village Condominium Association. During the application of the system, COMES and his crew did not observe any conditions on the plywood decking which would alert them to the possibility of any future problems with the system. On May 17, 1985, Mr. Jim Peaks, an Inspector for Brevard County, completed a "dry in" inspection of the roof on Building "C" which had been requested by Respondent GOREE. Mr. Peaks placed a stop order on the project because the Neoprene/Hypalon roofing system was not an approved product under the Southern Building Code which he believed was in effect in Brevard County on May 14, 1985. In actuality, the 1982 Standard Building Code was in effect at the time. Upon receipt of the stop order, Respondents COMES and GOREE went to the building department and met with Murray Schmidt, Mr. Peaks' supervisor. Mr. Schmidt had the authority to override Mr. Peaks' stop order. Mr. Schmidt, who was new to the county and his position, discussed the stop order with the Inspector. Mr. Peaks refused to remove his stop order because of the lack of code compliance. Mr. Schmidt verbally allowed the Respondents GORE and COMES to continue to work on the roof. Mr. Peaks was told to investigate the roofing system with the Southern Building Code Conference in Birmingham, Alabama. The Respondents were not notified again as to the status of the stop order, one way or the other. Because the Respondents had been told to continue the work on the roof by Mr. Schmidt, who had the authority to override stop orders, the Respondents reasonably assumed that a stop order was no longer in effect. In fact, the permit had the notation "See Murray" on it after the stop order notation. Upon completion of the project, Respondent COMES contacted the building department and requested a final inspection. In the usual course of dealing between contractors and the building department in Brevard County, a contractor is notified only if there is a problem with the project which needs correction before final approval. Neither COMES or GOREE received notification of a problem. Another recognized, usual course of dealing between a contractor and the building department is that the department notifies an owner or the contractor if a six month permit has expired and a final inspection has not been completed. GOREE was not notified of any permit expiration in this case. Again, the Respondents were given the impression by the inactivity in the building department that business was being conducted in the usual manner. The Respondents believed, based upon past and ongoing dealings with the department, that all of their obligations had been met on the reroofing project. On May 28, 1985, the final payment was received from Island Village Condominium Association and a limited warranty was issued in both Respondents' company names, pursuant to the contract with the association. Shortly after completing the job on Building "C," Respondent COMES was called to repair leaks in the new roof. COMES responded promptly and courteously, and placed the blame for the leakage on various factors such as: (1) The short "T" fasteners had begun popping through the Neoprene/Hypalon and destroyed its ability to prevent water penetration. (2) The roof had an inadequate drain system. (3) The plywood deck was bowed in a concave fashion due to the years of improper weight and excess water on the roof. During a meeting with the board of directors of the association requested by COMES, COMES offered to put on a new roof if the board would install sump pumps to remove standing water. The board rejected COMES offer and authorized the condominium property manager to seek other solutions. The Respondents were not contacted by the board again concerning alternative solutions to the problem. In June of 1986, Mr. Rex Lahr, the condominium property manager, began a review of the roof situation. After consulting with Mr. Tom Butler of the county building department, Mr. Lahr decided that an architect needed to be retained by the association to determine whether a structural deficiency or the new roofing system caused the leaks in the roof. An architect was not hired by the association. A traditional, built- up roof was applied over the Neoprene/Hypalon roofing system. In the application of the new roof, the drainage system was redone and the flat roof was given pitch, thereby redesigning the roof as well. Mr. Robert B. Hilson, who was tendered as an expert witness in the case, opined that the Respondents COMES and GOREE failed to properly determine whether the roof deck was in a condition to accept the Neoprene/Hypalon system. Mr. Robert H. Adams, who was tendered as an expert witness in the case, opined that the leaks which developed soon after the application of the Neoprene/Hypalon system indicated that the deck was not in a condition to accept the system. Although there is some basis in fact for the opinions rendered by the two experts, their opinions must be rejected for the following reasons: (1) The experts did not personally observe the building, nor was a determination made which would exclude the possibility that the roofing system failed as a result of structural or design defects. (2) There is ample evidence in the case to support a finding that the leaks were caused by structural or design defects, as well as latent defects not readily observable to the Respondents at the time the roofing system was applied, and outside the terms of the reroofing contract. Some examples of evidence which support a finding that the leaks were caused by structural or design defects are: (1) Mrs. Delores Hammels' testimony that all six buildings had to be reroofed as they all leaked periodically throughout their 12 years of existence; (2) the redesign of the drainage system and the placement of a pitch on the roof by Mr. Roush; (3) the testimony and sketch submitted by Respondent GOREE (GOREE Exhibit #5) which shows that an identical building with a pitch on the roof allows the drainage system, including the internal hidden piping system, to work correctly. The effective redesign of the roof by Mr. Roush confirms this theory as much as, or more than, Mr. Robert H. Adams' theory that the deck was not in a condition to accept the Neoprene/Hypalon system.
The Issue Whether Respondent's contractor license should be disciplined for alleged violations of Chapters 489 and 455, Florida Statutes.
Findings Of Fact Respondent, James Cooper, was at all times material to this action licensed by the State of Florida as a registered roofing contractor, having been issued license number RC0066905. Mr. Cooper's license is currently classified "Inactive, Issued (09/05/97)." Around March 1, 1996, Marshall Moran was contacted by Julia Jones regarding repairs to the leaky roof on her home located at 209 Cresent Drive, DeFuniak Springs Walton County, Florida. Ms. Jones' home was over one hundred years old with a steep metal roof. The roof she wished repaired was over the enclosed sleeping porch of her house. Over the last ten years, she had various contractors attempt to fix the leak in the sleeping porch roof. These attempts occurred, on average, more than one time per year. The leak always returned. Marshall Moran is an unlicensed and unregistered roofing contractor. Mr. Moran has been a roofing contractor since before the licensure requirements for contractors became law. He elected not to become licensed under those statutes. However, he did have the experience and skills necessary to repair Ms. Jones' roof. Marshall Moran discussed the job with Ms. Jones. Mr. Moran recommended the entire section of the roof be rebuilt and described the anticipated repairs. Ms. Jones would not allow the entire section of roof to be repaired. She thought only the small section where the leak was apparent needed repair. Unknown to Ms. Jones and prior to beginning the work, Mr. Moran contacted Respondent to tell him of Ms. Jones' job and to see if Respondent wanted to do the job. Respondent couldn't do the job with his crew but offered to allow Mr. Moran to "work under his license." Respondent was pursuing a large commercial roofing contract around the same time as the events at issue here. He wanted to keep Moran's crew together in order to be able to complete the large commercial job. He held the crew together by enabling Moran to do the construction at Julia Jones' residence in consideration for taking legal responsibility for the Jones' job. Respondent did not hire Mr. Moran as his employee. Respondent knew Mr. Moran was not registered or certified to practice contracting. He also knew Mr. Moran was well qualified to perform the work on the Jones' job. Respondent admits that he knew that he should not pull permits for anyone, but that he did it just this one time in order to keep the crew together. On March 15, 1996, Respondent obtained City of DeFuniak Springs, Florida, building permit number 1379 for the roof repairs to Ms. Jones' residence. On the application for said building permit, Respondent represented himself (doing business as Cooper Roofing and Repair) as the contractor of record on the aforesaid project. Respondent intended to and did eventually take legal responsibility for the Jones' job. However, he did not supervise Mr. Moran or his crew. Additionally, Ms. Jones was never informed of Respondent's involvement. More importantly, Ms. Jones never contracted with Respondent for either Respondent or his company to perform roof repairs on her home. On March 21, 1996, Mr. Moran provided an estimate for repair of the portion of Ms. Jones' roof she felt needed repair. The estimate bears the name of "AAA Metal Works" and "Marshall Moran." AAA Metal Works was Mr. Moran's company. The estimate does not reference either Respondent or his company. The estimated cost to repair Ms. Jones roof was $2,785. Based on the estimate, Ms. Jones entered into a contract with Mr. Moran and AAA Metal Works to perform the repairs to her roof discussed above. Moran and his crew substantially completed the repairs to Ms. Jones' roof in a few days. However, the roof continued to leak after Moran and his crew ended their work. The continuing leak was not due to any incompetence on the part of Respondent or Moran. Ms. Jones paid for the repairs with two checks made out to AAA Metal Works. The checks were in the amounts of $3,500 and $4,350. Respondent did not receive any of the money for the Jones' job. His only expense was the fee for the building permit. All other expenses were paid for by Mr. Moran. At no time during the formation or performance of the contract with Marshall Moran did Julia Jones have any contact with or knowledge of involvement by Respondent. In fact, Respondent only drove by the job site one time. As indicated, the roof continued to leak. Ms. Jones contacted Mr. Moran on approximately 5-6 occasions notifying him of the continued leaks. Mr. Moran would return to Ms. Jones' home and inspect the problems, but was unable to stop the leaks to Jones' satisfaction. It is not clear whether Mr. Moran kept Respondent informed of these continued service calls. Approximately one year after completion of the initial repairs on Ms. Jones' roof, Respondent received a call from Ms. Jones' tenant and friend, Sharon Jenks, who called posing as a potential new client. Ms. Jenks had gotten Respondent's name from the building permit. Ms. Jenks called Respondent because the house was still leaking approximately one year after the repair was done and intervening visits by Marshall Moran had not fixed the problem. Ms. Jenks arranged for Respondent to visit Ms. Jones' home. Respondent did not recognize the house when he arrived and drove past it. When Ms. Jenks showed Respondent the building permit bearing his name, Respondent showed surprise. He returned the next day with Mr. Moran. Respondent, Mr. Moran, Ms. Jenks and Ms. Jones all met regarding the continued leaking. Respondent and Mr. Moran told Ms. Jones that the metal on the roof was "bad" and needed to be replaced to stop the leaks on the "sleeping porch." Understandably, Ms. Jones did not want to deal any further with Mr. Moran or Respondent and would not permit them to make the recommended necessary repairs. Ms. Jones sued both Respondent and Mr. Moran in a civil action styled: Julia R. Jones v. James K. Cooper and Marshall Moran, Case Number 97-0040-CC, in the County Court of the First Judicial Circuit in and for Walton County, Florida. Following a judge trial, a Final Judgment was entered in favor of Respondent and Mr. Moran on December 9, 1997. Mr. Moran was charged with contracting without a license in violation of Section 489.127, Florida Statutes (1995), in State of Florida v. Marshall Moran, Case Number 97-0549-CF, in the Circuit Court of the First Judicial Circuit in and for Walton County, Florida. That charge was dismissed by Circuit Judge Lewis Lindsey on February 3, 1998.
Recommendation Based upon the findings of fact and conclusions of law, it is, RECOMMENDED: That the Board should find Respondent guilty of violating Chapters 489 and 455, Florida Statutes, and impose an administrative fine of $500.00 on Respondent DONE AND ENTERED this 3rd day of August, 1998, in Tallahassee, Leon County, Florida. DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of August, 1998. COPIES FURNISHED: John O. Williams, Esquire Maureen L. Holz, Esquire Willams and Holz, P.A. 458 West Tennessee Street Tallahassee, Florida 32301 J. LaDon Dewrell, Esquire 207 Florida Place, Southeast Ft. Walton Beach, Florida 32549 Rodney Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the documentary evidence received and the entire record compiled herein, the following relevant facts are found. Jesse Bruce, Respondent herein, is a registered roofing contractor and has been issued license No. RC0022948. On September 2, 1981, Respondent entered into a contract to repair a roof at 3684 NW 29th Street, Lauderdale Lakes, Florida, for Ms. Beryl Babb for the sum of $485.00. Respondent admits that he commenced construction under the above-referenced contract without first having obtained a building permit. Respondent was paid in full under the contract by Ms. Babb on September 4, 1981. Pursuant to the terms of the construction contract, Respondent provided for a two-year warranty on the roof repairs. Within an approximate two-month period following the repairs by Respondent, Ms. Babb made repeated phone calls to Respondent's construction company to report complaints that she was having in that the roof and garage appeared to "leak more than it had leaked prior to the repairs." Ms. Babb made at least six telephone calls to Respondent's construction company to no avail. During November, 1981, Ms. Babb filed a civil complaint in small claims court and during January, 1982, Ms. Babb received a judgment against the Respondent for $300.00. 1/ Respondent ahs been a licensed and registered roofing contractor since October, 1974. Respondent acknowledged that he received complaints from Ms. Babb as was testified herein; however, he states that he was busy during the times in which the complaints were made, an further that he did not want to make repairs inasmuch as Ms. Babb had elected to file a civil complaint against him in small claims court. Finally, Respondent acknowledged that he was obliged to return tot he Babb residence to make the repairs inasmuch as the complaints from Ms. Babb came during the two-year period in which the warranty for the roof repairs was in effect.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Respondent be placed on probation for a period of six (6) months. 3/ RECOMMENDED this 3rd day of February, 1983, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of February, 1983. COPIES FURNISHED: Michael J. Cohen, Esquire Suite 101, Kristin Building 2715 E. Oakland Park Blvd. Ft. Lauderdale, Florida 33306 Jesse Bruce 721 NW 20th Ave. Ft. Lauderdale, Florida 33311 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Mr. Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue The issues that were presented for disposition in the above-styled cases were whether Respondent committed certain alleged violations of Chapter 489, F.S. and if so what discipline is appropriate. As stated below, the parties stipulated to the violations, leaving only the issue of discipline to be resolved.
Findings Of Fact Gordon Lee Cederberg is, and has been at all times material hereto, a licensed registered roofing contractor, having been issued license number RC 0051346, by the State of Florida. At all times material Respondent was the licensed qualifier for Allied American Roofing Company and was responsible in such capacity for supervising its contracting activities. Allied American Roofing Company was dissolved on November 4, 1988. Stipulated Violations By stipulation, Respondent has admitted the following allegations of the amended administrative complaint in DOAH #91-8319: 3. CASE NO. 0106373 COUNT THREE Respondent d/b/a Allied American Roofing contracted with Michael Roberts on April 4, 1988 to reroof a home located at 530 Mason Street, Apopka, Florida. The contract price was $942.80 and was paid in full. Respondent proceeded to complete the job without obtaining a permit and securing required inspections from the City of Apopka Building Department. By the reason of the foregoing allegations, Respondent has violated Section 489.129(1)(d), F.S., in that the Respondent willfully and deliberately disregarded and violated the applicable building code of a municipality, to wit, Apopka, Florida, by failing to obtain a permit and inspection is as required by that municipality. 4. CASE NO. 0107766 COUNT FOUR Respondent's license was under suspension by the Florida Construction Industry Licensing Board between August 10, 1988, and March 3, 1989. Respondent d/b/a Allied American Roofing contracted with Nancy Wiegner on September 22, 1988, to reroof a home located at 15 Kentucky Street, St. Cloud, Florida. The contract price was $1,600.00 and it was paid in full. Respondent commenced work under the contract but failed to obtain a permit prior to commencing such work from the City of St. Cloud, Florida, and the municipality issued a stop order on the job. Respondent further engaged in contracting in a municipality where he had not registered. By reason of the foregoing allegation, Respondent has violated Section 489.129(1)(j), F.S., in that he failed in a material respect to comply with the provisions of Section 489.117(2), F.S., in that he engaged in contracting in a municipality, to wit, St. Cloud, Florida, where he had failed to comply with the local licensing requirements for the type of work covered by his registration. COUNT FIVE By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(d), F.S., in that Respondent willfully deliberately disregarded and violated the applicable building code of a municipality, to wit, St. Cloud, Florida by failing to secure a permit as required by that municipality. COUNT SIX By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S., by engaging in contracting while his license was suspended. COUNT SEVEN By reason of the foregoing allegations, Respondent has violated 489.129(1)(m), F.S., by committing gross negligence, misconduct, and/or incompetency in the practice of contracting. 8. CASE NO. 0112740 COUNT EIGHT Respondent d/b/a Allied American Roofing contracted with Emma Smith on October 3, 1988 to reroof a home at 1911 Mullet Lake Park Road, Geneva, Seminole County, Florida. The contract price was $4,100.00 and it was paid in full. Respondent proceeded to complete the job without obtaining a permit and securing required inspections from the Seminole County Building Department. Respondent failed to properly construct a watertight roof which continued to leak and caused damage to the home. Respondent has failed to honor the five (5) year labor and twenty (20) year material warranty that was part of the said contract, although he was requested to do so. By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(n), F.S., in that the Respondent proceeded on a job without obtaining an applicable local building department permit and inspections. COUNT NINE By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S., by engaging in contracting while his license was suspended. COUNT TEN By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act of gross negligence, incompetency and/or misconduct in the practice of contracting by failing to honor the written warranty described in paragraph twenty-six above. COUNT ELEVEN By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. 12. CASE NO. 89-001674 COUNT TWELVE Respondent d/b/a Allied American Roofing Company contracted with Thelma Beck to reroof a home at 3910 Pineland Ridge Road, Orlando, Orange County, Florida on January 26, 1989 for a price of $2,270.00. Respondent accepted a $100.00 deposit for said job; the work was not begun and the $100.00 deposit was returned to Mrs. Beck. By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S., by engaging in contracting while his license was suspended. COUNT THIRTEEN By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. COUNT FOURTEEN Respondent d/b/a Allied American Roofing contracted with Morris Remmers to reroof a home at 8719 Butternut Boulevard, Orlando, Orange County, Florida, on or about February 23, 1989. The contract price was $2,870.00 and it was paid in full. Respondent proceeded to complete the job without obtaining a permit and securing required inspections from the Orange County Building Department. By reason of the foregoing allegation, Respondent is guilty of violating Section 489.129(1)(n), F.S., in that Respondent proceeded in a job without obtaining an applicable local building department permit and inspections. COUNT FIFTEEN By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S., by engaging in contracting while his license was suspended. COUNT SIXTEEN By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. 17. CASE NO. 89-008737 COUNT SEVENTEEN Respondent d/b/a Allied American Roofing contracted with Robert Speirs to reroof a dwelling at 2467 Fieldingwood Road, Maitland, Seminole County, Florida on or about October 14, 1988. The contract price was $3,600.00. Respondent proceeded to work the job but failed to obtain a permit and secure required inspections from the Seminole County Building Department. Respondent failed to properly construct a water tight roof which continued to leak. Respondent failed to honor the three (3) year labor and twenty (20) year material warranty that was part of the contract although he was requested to do so. By reason of the aforesaid allegations, Respondent has violated Section 489.129(1)(n), F.S., in that Respondent proceeded on a job without obtaining an applicable local building department permit and inspections. COUNT EIGHTEEN By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S., by engaging in contracting while license was suspended. COUNT NINETEEN By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act of gross negligence, incompetency and/or misconduct in the practice of contracting by failing to honor his written warranty described in paragraphs forty-seven above. COUNTY TWENTY By reason of the aforesaid allegations, Respondent is guilty of violating 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. 21. CASE NO. 109636 COUNT TWENTY-ONE Respondent d/b/a Allied American Roofing Company contracted with Daniel J. Doherty to reroof a home at 225 Dover Wood Road, Fern Park, Seminole County, Florida on October 2, 1988, for the contract price of $3,590.00 which was paid in full. Respondent proceeded to complete the job without obtaining a permit and securing required inspections from the Seminole County Building Department. Respondent failed to construct a watertight roof, which contributed to water damage to the interior of Mr. Doherty's home. Respondent failed to honor the five (5) year labor and twenty (20) year material warranty that was part of the contract, although he was requested to do so. By the reason of the foregoing allegations, Respondent has violated Section 489.129(1)(n), F.S., by proceeding on the job without obtaining a local building department permit and inspections. COUNT TWENTY-TWO By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(j), F.S., by failing in a material respect to comply with the provisions of Section 489.127(1)(e), F.S. by engaging in contracting while his license was suspended. COUNT TWENTY-THREE By reason of the foregoing allegations, Respondent has violated 489.129(1)(m), F.S., by committing gross negligence, misconduct, and/or incompetency in the practice of contracting by failing to honor his warranty as described in paragraph fifty-six above. COUNT TWENTY-FOUR By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. COUNT TWENTY-SEVEN Respondent d/b/a Allied American Roofing contracted with Gloria Viruet to reroof a home at 3010 (renumbered to 3007) Northwood Blvd., Orlando, Orange County, Florida on June 7, 1988. The contract price was $3,500.00. Respondent proceeded to complete the job without receiving a permit and securing required inspections from the Orange County Building Department. The Respondent failed to properly construct a watertight roof and a leak developed after construction. Respondent failed to honor the five (5) year labor and twenty (20) material warranty that was part of the said contract, although he has been requested to do so. By reason of the aforesaid allegations, Respondent has violated Section 489.129(1)(d), F.S., in that Respondent willfully and deliberately disregarded and violated the applicable building code of a County, to wit, Orange County, Florida by failing to obtain a permit and inspections as required by that County. COUNT TWENTY-EIGHT By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting, by failing to honor his written warranty described in paragraphs seventy. COUNTY TWENTY-NINE By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. 28. CASE NO. 0108263 COUNT THIRTY Respondent d/b/a Allied American Roofing Company contracted with John E. Hultin to reroof a home located at 3610 Lakeview, Apopka, Florida on November 7, 1987. The contract price was $2,900.00 and it was paid in full. Respondent proceeded to complete the job without obtaining a permit and securing required inspections from the Seminole County Building Department. Respondent failed to properly install a roof covering, violating Section 103 of the Standard Building Code, 1985 Standard of Installation of Roofing Coverings adopted by Seminole County and Seminole County Ordinance Section 40.51. The contract provided for a five (5) year labor warranty and a twenty (20) year material warranty. Respondent made several attempts to correct defects but has not fulfilled his warranty as the roof continued to leak. By reason of the aforesaid allegations, Respondent has violated Section 489.129(1)(d), F.S., in that the Respondent willfully and deliberately disregarded and violated the applicable building code of a county, to wit, Seminole County, Florida by failing to obtain a permit and inspections as required by that county. COUNT THIRTY-ONE By reason of the foregoing allegations, Respondent has violated Section 489.129(1)(d), F.S., in that the Respondent willfully and deliberately disregarded and violated the applicable building code of a county, to wit, Seminole County, Florida by installing the above described roof in a grossly negligent manner and in a manner which violated Section 103 of the Standard Building Code, 1985 Standard of Installation of Roof Covering, adopted by Seminole County and Seminole Ordinances Section 40.51. COUNT THIRTY-TWO By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practices of contracting by failing to honor his written warranty described above. COUNT THIRTY-THREE By reason of the aforesaid allegations, Respondent is guilty of violating Section 489.129(1)(m), F.S., by committing an act or acts of gross negligence, incompetency and/or misconduct in the practice of contracting. FACTS RELATED TO RESPONDENT'S PROPOSED MITIGATION Respondent has been engaged in the practice of roofing contracting for over twenty years. Prior to moving to Florida in 1983 his company worked in Michigan, Ohio and Indiana on large commercial jobs. In 1983 he was employed by the Disney company to do commercial roofing work. After licensure in Florida, Cederberg continued with large public works and commercial jobs in Florida. Sometime around 1988, after a disastrous reversal of fortune, the company filed for bankruptcy. Although he was utterly unfamiliar with the practice of residential roof contracting, particularly the demanding supervision involved, Gordon Cederberg began doing residential work. Around this same time Cederberg's wife left him and he was given custody of three children, ages three, six, and nine. He was emotionally distraught and obtained counseling and financial and other support from his church group. Cederberg's roofing contractor's license was suspended by the Construction Industry Licensing Board from August 1, 1988 to March 1, 1989, during which time he continued to work, due to financial pressures. Warranty work was not done due to his financial and emotional straits. According to Cederberg and his witnesses, he is in the process now of turning his life around. He operates on a smaller scale and is able to handle the work. He has one employee and has been able to avoid new complaints. He is still financially unable to provide restitution to the customers previously harmed.
Recommendation Based on the foregoing it is hereby, RECOMMENDED: that the parties' stipulation with regard to dismissals and admissions described above be accepted by the Board and that the following penalty be imposed: a) 1000.00 fine; one year suspension, with this penalty suspended during, and removed upon successful completion of, probation with an appropriate timetable for restitution and the requirement that appropriate continuing education courses are completed; and payment of costs of investigation and prosecution. DONE and ENTERED this 31st day of December, 1992, at Tallahassee, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of December, 1992. COPIES FURNISHED: Jack McRay, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien, Executive Director Construction Industry Licensing Board P.O. Box 2 Jacksonville, FL 32202 William S. Cummins, Esquire Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Jack Snow, Esquire 407 Wekiva Spings Road, Suite 229 Longwood, FL 32779