Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HENRY C. HOLLENBECK, 82-002941 (1982)
Division of Administrative Hearings, Florida Number: 82-002941 Latest Update: Dec. 02, 1983

Findings Of Fact The following facts, a through d, were stipulated to by the Petitioner and Respondent and are found to be true facts by the undersigned Hearing Officer. Respondent is a registered pool contractor having been issued License No. RP0033408. Respondent did not qualify Acme Building Company or Acme Pools Incorporated until October, 1981. In October, 1981, Respondent qualified Acme Pools Incorporated. On November 20, 1978, the Respondent executed and signed a contract with Mr. and Mrs. C. S. Jarrell to construct a swimming pool at the Jarrell residence. The contract price was $6,500.00. The named party to the contract with the Jarrells was Acme Pools. On September 8, 1979, the Respondent signed and executed a contract with Mr. and Mrs. James Costin to construct a swimming pool at the Costin residence. The contract price was $6,835.00. The named party to the contract with the Costins was Acme Pools. Subsequent to the execution of the contract, the Jarrell swimming pool was completed by the Respondent. Shortly following completion, the swimming pool began leaking and continues to leak. Water must be added to the pool daily. The Jarrell pool was constructed with sidewalls consisting of pre-cast concrete panels which are imbedded in the floor of the pool. The leaks occurred as a result of inadequate back bracing behind the panels. This is a construction defect. When they discovered that their pool was leaking, the Jarrells immediately contacted the Respondent. The Respondent attempted to repair the leaks on two different occasions. Both attempted repairs were unsuccessful. Respondent became aware, after construction of the Jarrell pool, that there was something basically wrong with the construction of the Jarrell pool, but the Respondent did not accomplish a permanent repair of the problem. Subsequent to executing the contract with Mr. and Mrs. Costin, the Respondent completed a swimming pool at the Costin residence. Within a day after the Costin pool was completed, Mr. Costin noticed that the pool was losing water. The pool had a substantial leak, losing as much as four to five inches per day of water in the 16 feet by 32 feet pool. Mr. Costin, after discovering the leak, immediately notified the Respondent. The Respondent made several attempted repairs of the leaks. Some of the repairs temporarily stopped the leaking, but no permanent repair of the leaks has been accomplished. The last attempted repair by the Respondent was in September, 1981. During construction of the Costin pool, the Respondent performed the electrical work on the pool. No electrical permit was obtained from Okaloosa County building officials as required by Okaloosa County Ordinance No. 75-4. It was Respondent's responsibility to obtain or make certain that his subcontractor obtained the necessary permits for construction of the Costin swimming pool. During construction, Mr. Costin and the Respondent discussed permits and the Respondent did obtain the building permit for the construction. The Respondent was aware some type of electrical permit was required. In August, 1978, Respondent purchased Acme Building Company and did business as Acme Pools until October, 1981. Respondent, prior to October, 1981, ran a fictitious name ad in the newspaper for Acme Pools and registered Acme Pools with the county but did not qualify Acme Pools. During the period August, 1978, to October, 1981, the Respondent was licensed individually as a registered pool contractor. Respondent had been in business less than one year when he constructed the Jarrell and Costin pools. The construction method of using pre-cast concrete panels is more likely to crack and leak than other available methods of swimming pool construction. The Respondent now constructs only fiberglass pools. He no longer builds the type of pools constructed for Mr. and Mrs. Jarrell and Mr. and Mrs. Costin.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Respondent be found guilty of the violations alleged in Counts I and II and that the Board impose upon the Respondent an administrative fine of $1,500.00. It is further recommended that Counts III, IV, and V of the administrative complaint be dismissed and that the Respondent be found not guilty of the violations alleged in those counts. DONE and ENTERED this 1st day of June, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of June, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 Henry C. Hollenbeck 405 Marshall Court Ft. Walton Beach, Florida Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (3) 455.227489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILIP J. MAINS, 80-002231 (1980)
Division of Administrative Hearings, Florida Number: 80-002231 Latest Update: Jul. 08, 1981

Findings Of Fact In early September of 1979, John and Ruth E. Lockwood contracted with P & P Custom Pools, Inc. (P & P), for the construction of a swimming pool at their home, 231 El Dorado Drive, Debary, Florida. Respondent, Philip J. Mains, signed the contract on behalf of P & P and later obtained a building permit. He and his men began excavating on site in mid-September. The Lockwoods paid respondent $700.00 on September 6, 1979. As construction progressed, they paid him $1,706.25 on September 27, 1979; $1,000.00 on October 26, 1979; $1,047.50 on October 29, 1979; and $1,706.25 on November 20, 1979. At the appropriate times, a building inspector was summoned, who inspected the project, including the placement of reinforcing steel, ground wiring, and lights. Neither the "steel inspection" nor the "deck inspection" revealed any problem. The workmanship was excellent, as far as it went, but the Volusia County building inspector's office was never asked to perform a final inspection. As respondent promised there would be, there was water in the swimming pool by Christmas of 1979, but respondent did no further work after December, 1979. He never installed the pump, filter, diving board, or hand bars called for in the Lockwoods' contract. Earlier in 1979, Patrick T. Ryan, the other principal in P & P, left town and abandoned the business which was then $37,000 in debt. In November of 1979, respondent turned the company's books over to an accountant. In January of 1980 the business' financial problems became critical and, at the accountant's suggestion, respondent so advised the eight homeowners for whom he was building swimming pools, including, in January or February, Mr. Lockwood, who reacted angrily. Respondent testified that Mr. Lockwood "cussed him out." Thereafter respondent avoided the Lockwoods until April of 1980 when they found him working on another pool. There was enough money owed on the eight contracts as a group to finish all the pools, according to respondent's uncontroverted testimony, at the time the Internal Revenue Service levied on respondent's bank account and seized his tools and equipment. Even then respondent offered to finish the Lockwoods' pool if they would buy the materials. Respondent's wife asked Mrs. Lockwood to write a check to a supplier for a pump and filter so that respondent could install them and get water in the pool circulating. Instead, during the last week of April, 1980, the Lockwoods contracted with somebody else to finish the job and paid him $1,200. Respondent subcontracted with a Jacksonville cement company to pour concrete for the pool. After the concrete had been poured, the Lockwoods got a registered letter from the subcontractor threatening to place a lien on their property if he were not paid. According to Mr. Lockwood, the problem was that some check [supposedly drawn by respondent in favor of the subcontractor] had been delayed in the mail. In any event, there was no indication in the evidence that the Lockwoods heard anything further from the subcontractor.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration for thirty (30) days. DONE AND ENTERED this 29th day of April, 1981, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1981. COPIES FURNISHED: Charles F. Tunnicliff, Esquire 130 North Monroe Street Tallahassee, Florida 32301 Philip J. Mains c/o Sue Mains Route 2, Box 799A DeLand, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs. CASE NO. 80-2231 PHILIP J. MAINS, RP 0024663, Respondent. /

Florida Laws (1) 489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs DOMINICK SOLITARIO, 90-004600 (1990)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 27, 1990 Number: 90-004600 Latest Update: Feb. 08, 1991

The Issue The issue in this case is whether the Respondent, Dominick A. Solitario, committed the offenses alleged in the Amended Administrative Complaint and, if so, what disciplinary action should be taken.

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. At all times pertinent to this proceeding, Respondent, Dominick Solitario, was licensed as a certified pool contractor in the state of Florida, having been issued license no. CP CA17558. At all times pertinent to this proceeding, Respondent was the licensed qualifying agent for Jade Pools, Inc. Sometime around February of 1988, Respondent contracted with Michael and Linda Skidd to remarcite the swimming pool at the Skidd's home in Coral Springs, Florida. The contract price for the remarciting of the Skidd's pool was $2000.00. Respondent has been paid in full for this work. There is no evidence that there were any leaks in the Skidd's pool prior to the time the work was undertaken by Respondent. At the time the work was begun, one of the Respondent's employees discovered an expansion plug that had been inserted in the main drain. The employee inquired as to whether the Skidds had experienced any problems with the drain. The Skidds denied having any problems. The evidence presented at the hearing was inconclusive as to whether the main drain was working properly. At the time the Respondent began work under the contract, the Skidds were using a "creepy crawler" to clean the pool. This device required the main drain to be shut off. While Mrs. Skidd testisfied that she thought the main drain was working properly, she admitted that her husband was more familiar with the cleaning and mechanical aspects of the pool. Mr. Skidd did not testify. Respondent contends that Mr. Skidd was present at the time the plug was removed from the main drain and that the condition was brought to his attention. However, it does not appear that either Respondent or Mr. Skidd knew why the drain was plugged or the significance of the situation. Respondent proceeded with his contractual work without conducting any tests to determine whether there was a leak in the main drain. When the work was completed, the workers directed the Skidds not to use their main drain. No explanation was given for this instruction. After the work was completed, the Skidds turned on the main drain and lost approximately four inches of water from the pool in a relatively short time. The Skidds turned off the drain and called Jade Pools. An employee of Jade Pools came out and inspected the premises. He advised the Skidds not to use the main drain, but instead to use their "creepy crawler." The Respondent's employee indicated that there was a leak in the main drain. It is not cler how he reached that conclusion. In order to complete the work on the Skidd contract, Respondent's employees were required to install a pressure release valve near the pool's main drain by drilling through the bottom of the pool. The hole for this valve was drilled several inches away from the main drain and its plumbing. Petitioner suggests that the Respondent's employees may have punctured the main drain or its plumbing when this hole was drilled. However, no persuasive evidence was introducted to prove this allegation. Respondent contends that the pool was improperly constructed and/or that the main drain line had been previously damaged and plugged shut to avoid detection of the leak. In order to perform the contracted work, Respondent's employees unplugged the drain and the alleged preexisting leak became evident. Respondent has inserted a plug into the main drain and claims that the pool is now in the same condition it was when he began his work. Respondent has refused to repair the main drain or perform any additional work unless he is paid for it. At the time that Respondent first proposed to enter into a contract with the Skidds, he was told by the Skidds that there was a suction leak at the pump. In retrospect, Respondent contends that this suction leak confirms the preexisting problem with the main drain. No conclusvie evidence was presented to establish why the pool is leaking. As of the date of the hearing, the Skidds are still unable to use their main drain. The Petitioner did not present persuasive evidence to establish that Respondent was responsible for the leak in the Skidds' pool. While it is possible that the Respondent's employees caused the leak when they drilled the hole for the pressure release valve, an equally likely explanation is that there was an existing problem that had been obscured by the prior plugging of the main drain. On or about June 29, 1987, Respondent contracted with Anthony Gallagher to construct a swimming pool and a deck at Mr. Gallagher's home in Coral Springs, Florida for the contract price of $17,800.00. Respondent has been paid in full for this work less $100 for damage caused during construction. The contract with Mr. Gallagher called for Respondent's company to top the existing patio slab and tie it into a newly added patio deck surrounding the pool. The building permit for this work was pulled by Jade Pools. Although the work on the Gallagher deck and pool was completed sometime in late 1987 or early 1988, the pool and deck have still not passed final inspection by the City. The local building officials have refused to approve the final inspection on the Gallgher's deck because of the excessive slope from the back of the house to the pool. The pitch of the deck constructed by Respondent's company from the back of the Gallagher's house to the pool is very severe, effectively rendering a portion of the deck unusable. A table cannot sit flat on this portion of the deck because of the slope. The Respondent's construction of a deck with such a severe slope that it is incapable of passing final inspection constitutes incompetency in the practice of contracting. In order to provide a usable deck, Respondent should have ripped out the existing deck or placed the pool at a higher elevation. Respondent contends that his contract did not call for him to rip out the existing deck, but only to top it. He claims the existing deck that was topped had a similarly severe pitch. Nonetheless, Respondent is responsible for insuring that his final product is functional and able to pass inspection. Respondent has failed to take any remedial action to obtain a successful final inspection. During construction, the Gallaghers, on several occassions, expressed displeasure with the deck and its excessive slope in some areas. On two occasions, Respondent sent his workmen out to correct certain aspects of the construction that the Gallaghers found unacceptable. Ultimately, the homeowners paid the Respondent in full and instructed Respondent to stay off their property. Although Respondent's presentation was somewhat unclear, he appears to argue that these actions by the Gallaghers relieve him of any liability for his work under this contract. However, the evidence established that the Respondent was never able to obtain a successful final inspection of his work at the Gallagher home. This failure is the direct result of the excessive pitch in the patio he constructed. While the Gallaghers have paid the full amount of the contract and are apparently using the pool and patio, these facts do not relieve Respondent from responsibility for the incompetently constructed deck. The City of Coral Springs requires a deck electrical inspection to insure that all the steel in the deck is on the same electrical field (same electrical bond) as the pool. Jade Pools failed to call for this electrical bond inspection before pouring the Gallagher's deck. Ultimately, the city building officials required the Respondent's company to expose a portion of the steel in the deck to confirm that the pool was properly bonded. This test indicated that the pool was in fact properly bonded. On or about August 10, 1988, Respondent contracted with Kevin Fusco to construct a swimming pool and deck at Mr. Fusco's home in Boca Raton, Florida for a total contract price of $10,030.00. Respondent has been paid in full under this contract. Jade Pools obtained the building permit for the Fusco's pool. Therefore, Respondent's company was responsible for obtaining all of the inspections for the construction, including the final inspection. Prior to the time that work was begun on the Fusco contract, Respondent's employees inspected the property and were advised as to some existing problems with drainage in the backyard of the house. The Fusco's lot was designed to drain from back to front. A berm runs behind the Fusco property and causes water to drain through the backyard. On some occasions prior to construction, this drainage situation resulted in standing water against the back of the house. The installation of the Fusco's pool seriously affected the drainage plan for the property. After the pool was installed, there was often standing water all around the deck following a rain. After construction was started and the deck was formed out, the county refused to give approval for pouring the deck because of anticipated problems with drainage in the backyard. One of Respondent's employees advised the Fuscos that if they removed approximately three feet of soil from around the deck, the county would allow them to proceed with pouring the deck. Based upon this recommendation, the Fuscos entered into a contract with a company recommended by Respondent. That company removed approximately six or eight feet of soil all around the deck and installed a rock bed in the area. The cost of this removal was in addition to the contractual price agreed to between Respondent and the Fuscos and was borne by the Fuscos. As indicated above, the installation of the pool greatly exacerbated the drainage problems that previously existed on the property. Respondent did not warn the homeowners prior to construction to expect this result nor did the Respondent take steps to preclude these additional drainage problems. While Respondent contends that the Fusco's property was inappropriately graded prior to the time the work was initiated, Respondent never brought this fact to the attention of the homeowners until after the pool was installed and the increased drainage problems became evident. After the work was completed, the county inspectors advised the homeowners that the pool did not pass final inspection because of drainage problems caused by the pool and deck. By the time the Fuscos found out the pool had not passed final inspection, Respondent had been paid in full under the contract. The Fuscos contacted Jade Pools, which refused to take any corrective action. The Respondent claimed that drainage problems were not part of his company's responsibility and refused to return to the property to correct the problem even though the pool had not passed final inspection. The Fuscos hired an engineer to design an acceptable solution to the drainage problem and arranged for the completion of the work at their own expense. In accordance with this solution, the homeowners installed a series of french drains around the back yard in order to try to get the water to percolate into the ground. After this additional work was completed, the pool passed final inspection by the county. It was approximately one year after Jade Pools finished its work before the final inspection was passed. The Fuscos continue to experience increased drainage problems on their property as a result of the installation of the pool and deck. These problems include standing water around the deck after a heavy rain and, in some instances, an overflow of water into the pool. While the Respondent was installing the Fusco's pool, Respondent was concurrently installing a pool at the house next door. There has been no drainage problems on the property next door because the elevation on that house is higher. The Fusco's pool was actually installed at a level that was at or below the surrounding ground level. The problems associated with such an installation were never explained to the homeowners prior to the time the work was commenced. Respondent contends that this situation was necessary because of the existing elevations of the house and lot. He says that the pool and deck had to be installed in a manner that provided a four inch step down from the house and also matched the existing slab. The drainage problems could have been minimized by swaling out from the pool area to the side of the house. While Respondent contends that such "landscaping" efforts were not part of his contract, he should have not undertaken the work unless he could adequately deal with the drainage problem and ensure that the final installation would pass inspection. The pool contractor is responsible for insuring that, after the pool is built, proper drainage is obtained around the pool. The efforts undertaken by the Respondent were insufficient to deal with the resulting drainage problems and constitute incompetency in the practice of contracting.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violations of Section 489.129(d) and (m), Florida Statutes, in connection with the Fusco and Gallagher contracts, issuing a reprimand and imposing a fine on Respondent in the amount of $2,000.00 for having committed these violations. In addition, Respondent should be placed on probation for two years and required to reimburse the Fusco's for the money they have expended to correct the drainage problems caused by Respondent. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 8th day of February, 1991. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of February, 1991.

Florida Laws (5) 120.57455.225489.105489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. NORMAN RIVERS, 77-000474 (1977)
Division of Administrative Hearings, Florida Number: 77-000474 Latest Update: Nov. 09, 1977

The Issue The basic allegations of the complaint having been proven or admitted, the sole question at hearing was one of mitigation.

Findings Of Fact Rivers is a licensed general and a licensed pool contractor. All the complaints against Rivers arose in relationship to his pool contracting activities. Rivers did begin construction of two pools in Levy County without first obtaining a building permit as required by the Levy County Building Code, a certified copy of which was identified by the Levy County Building official. Rivers paid a late fee in both instances. Although in one instance all inspections were made, in the second instance no inspections were possible because construction was essentially complete when the construction was discovered by the Levy County Building official. Rivers did fail to pay materialmen on two pools although he received payment in full for the jobs. His failure resulted in materialmen's liens being placed on the property, although Rivers provided each owner a written statement that all bills had been paid. Rivers admitted that he had not paid the materialmen because he lacked funds to do so. His contract with both parties for construction of a specified pool contained a provision stating that he would provide them an affidavit that all labor and material had been paid prior to receipt of final payment on the contract.

Recommendation Based upon the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Residential Pool Contractor's License and General Contractor's License of Norman Rivers be suspended for a minimum of ninety (90) days and that thereafter be reinstated upon his satisfying the Board of his ability to meet his financial obligations. DONE and ORDERED this 15th day of September, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488 9675 COPIES FURNISHED: Mr. J.K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 Mr. Norman Rivers 1710 South East 19th Street Ocala, Florida 32670

# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIAM R. MACKINNON, 76-000026 (1976)
Division of Administrative Hearings, Florida Number: 76-000026 Latest Update: Sep. 28, 1976

The Issue Whether Respondent's License as a residential pool contractor should be suspended for alleged violation of Section 468.112(7), Florida Statutes. The Respondent did not appear at the hearing although proper notice thereof had been furnished under date of February 11, 1976 to him by the hearing officer. Accordingly, the hearing was conducted as an uncontested proceeding.

Findings Of Fact Respondent has been licensed as a registered pool contractor by the Florida Construction Industry Licensing Board since June 20, 1974. The license was not renewed for 1975/76 (Exhibit 4). Respondent filed a Voluntary Petition in Bankruptcy in the U.S. District Court for the Northern District of Florida, Bankruptcy No. TBK 75-25, on March 13, 1975 (Exhibit 5).

Recommendation That the registration of William R. MacKinnon as a residential pool contractor be suspended until such time as he meets the qualifications and other requirements for renewal of registration and applies therefor. DONE and ENTERED this 5th day of April, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of April, 1976. COPIES FURNISHED: David Linn, Esquire 217 South Adams Street Tallahassee, Florida 32301 Mr. William R. Mackinnon Route 3, Box 584C Tallahassee, Florida 32303

# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEVEN A. MELNIKOFF, 88-000567 (1988)
Division of Administrative Hearings, Florida Number: 88-000567 Latest Update: Jun. 29, 1988

Findings Of Fact Melnikoff is the holder of a certified pool contractor's license, having been issued license No. CP C032540. Melnikoff used this license to qualify Ken-Mel Enterprises and license no. CB C029067 was issued to Melnikoff qualifying Ken-Mel Enterprises. Ken-Mel entered into a contract with John and Edythe Milton to construct a residential pool at 7336 Pineville Drive, Jacksonville, Florida. Melnikoff applied for a building permit with the City of Jacksonville to construct the pool for the Miltons. His application included a set of plans and a site plan to be approved by the City of Jacksonville. The City of Jacksonville issued a building permit and provided an inspection sign-off card to be placed at the residence where the pool was to be constructed. Melnikoff and Ken-Mel constructed the pool and were paid in full. Melnikoff failed to request or obtain any inspections of the pool construction. This is a violation of the City of Jacksonville Building Code, Section 320.504. The pool is constructed in such a way that it is flawed, deficient and hazardous. Specifically, the water slide is hooked to a potable water system and to the hot water, which is both a serious code violation and a serious and hazardous condition. The water slide is positioned improperly and attached incorrectly, such that there is a danger of injury and this is a hazardous condition. The marcite is very rough and has started to peel away from the gunnite. The marcite is stained from the finish of the pool deck. The slurry from the gunnite and pool deck is buried near the pool and is improperly disposed of. Persons are mildly shocked when touching the railing in the pool, indicating that the pool is not properly bonded, which is a hazardous condition. The pool is not level or symmetrical and there are many imperfections in the continuous curve of the wall. Steel reinforcing bars are actually protruding through the concrete near the top of the pool. Building Code requires that there be a minimum coverage of 1 1/2" of concrete. The ceramic tile is falling off the wall and it is a very poor ceramic tile job. The expansion joints are improperly placed. The main drain cover has not been fastened down, which is a very dangerous situation and a code violation. There is no means or plan for discharging water from the pool, in violation of code. Part of the deck drain is under the slab of the Milton's house which is a serious problem. The pool is deeper than the plans indicated, in violation of the building code. The pool deck is very rough in places, does not drain away from the pool, and is cracked from improper compaction and improper placement of expansion materials. All of these defects and hazardous conditions establish that Melnikoff was grossly negligent and incompetent in the construction of this pool.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order finding Steve A. Melnikoff guilty of the violations charged and revoking Melnikoff's license as a certified pool contractor. DONE and ORDERED this 29th day of June, 1988, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1988. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 88-0567 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the Petitioner in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Department of Professional Regulation, Construction Industry Licensing Board 1. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1); 2(2); 3-5(3); 6(4); 7(5); and 8 & 9 (6) COPIES FURNISHED: John O. Williams, Attorney at Law 1343 E. Tennessee St. Tallahassee, Florida 32308 Steven A. Melnikoff 710 Rosedale Drive Stephens City, VA 22655 Tom Gallagher, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.105489.119489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MARTIN R. MCANDREW, 78-000103 (1978)
Division of Administrative Hearings, Florida Number: 78-000103 Latest Update: Dec. 04, 1990

Findings Of Fact Martin R. McAndrew is a licensed general contractor and licensed pool contractor holding general contractor's license number RG 0020560 and pool contractor's license number RP 0024861. Martin R. McAndrew was provided notice in accordance with the applicable rules and statutes of the formal hearing to consider the allegations of the administrative complaint filed against him by the Florida Construction Industry Licensing Board. Ray Dowell identified a notice of violation served on McAndrew by the Florida Construction Industry Licensing Board which was received into evidence as Exhibit 1. This notice of violation related to the construction undertaken by McAndrew for Lynn McMillan. Melvin C. Huebschman entered into a contract with McAndrew for the construction of a pool. The contract price for the pool was $5,000.00. Huebschman paid McAndrew $2,000 in two payments. The first payment was in the amount of $300.00 to cover the cost of transportation of the pool materials to Pensacola, Florida. The second payment in the amount of $1,700.00 was for the first phrase of construction on the pool. Subsequent to receiving payment McAndrew provided no materials or labor pursuant to the contract. Huebschman talked with McAndrew concerning completion of the work pursuant to the contract and McAndrew failed to perform under the contract throughout the spring and summer of 1977. In August, 1977, Huebschman wrote McAndrew advising him that it had been over ninety days since they entered into the contract and McAndrew had not performed any services pursuant to the contract. Huebschman gave McAndrew thirty days within which to commence work. McAndrew did not respond to this notice. McAndrew did not return any portion of the $2,000.00 paid to him by Huebschman. Lynn McMillan entered into a contract, identified as a portion of Exhibit 4, with McAndrew. This contract called for the construction of a pool for a contract price of $5,800.00. Pursuant to that contract, McMillan paid to McAndrew $4,350.00. Subsequent to payment of the third draw, McAndrew failed to complete the job. The last work performed by McAndrew on this construction project was on May 17, 1977. Prior to May 17, 1977, all materials for completing the pool were on the site and installed. Before abandoning the project, McAndrew removed from the building site all portions of the pool construction except the poured concrete and vinyl lining. McMillan subsequently entered into a contract with Surf Side Pools for the completion of the pool. The contract price was $1275.00, which included $800.00 for equipment and materials necessary to complete the pool. In addition, McMillan found it necessary to pay $230.00 to O'Brian Enterprises to remove stumps and spoil left on the construction project by McAndrew. McMillan also paid $200.00 to Warrick Electric Company to satisfy a claim by Warrick for materials and labor provided by Warrick to McAndrew. Finally, American Ready Mix Concrete filed a claim of lien in the amount of $436.80 against the property of Lynn McMillan for labor and materials provided under the contract with McAndrew which McAndrew did not pay. On May 27, 1977, McAndrew wrote a letter to McMillan advising that he would like the opportunity to finish the pool and was invited to do so. However, McAndrew did not return to the construction site or provide any further labor or materials pursuant to the contract. Sarah White Witt entered into a contract with McAndrew for the construction of a pool at a contract price of $4,500.00. Witt paid McAndrew $500.00; however McAndrew did not finish the pool construction. Subsequently, Witt was advised by the materialmen and labors of various liens against her property totalling $2,200.00. Daryl Jernigan, electrical and pool inspector for Escambia County, inspected the work done by McAndrew on the McMillan pool. He found that the pool had been filled with water but that the equipment necessary to recirculate and chlorinate the water had been removed from the pool, thereby permitting the water to stagnate. This inspection was conducted in June, 1977. Prior to that time, Jernigan had found it necessary to order work on a pool begun by McAndrew halted because McAndrew had failed to acquire a building permit prior to commencing construction.

Recommendation Based upon the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that Florida Construction Industry Licensing Board revoke the licenses of Martin R. McAndrew as a general contractor and as a pool contractor, and further fined a sum of $500.00. DONE and ORDERED this 24th day of May, 1978, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: J. K. Linnan Executive Director Florida Construction Industry Licensing Board P. O. Box 8621 Jacksonville, Florida 32211 Michael E. Egan, Esquire Attorney at Law 217 South Adams Tallahassee, Florida Martin R. McAndrew 3313 N. 17th Avenue Pensacola, Florida 32502

# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer