Findings Of Fact On June 15, 1977, Respondent Department of Transportation (DOT) filed application with Respondent Department of Environmental Regulation (DER) for a permit to relocate 5,188 linear feet of an existing canal commonly referred to as Cypress Strand Canal in Manatee County, Florida. The application and accompanying drawings show that the scope of the project is not merely limited to relocation of the canal, but other dredge and fill activities in the surrounding area incident to the construction of a highway interchange over State Road 64 approximately four and one-half miles east of Bradenton, Florida. On March 15, 1978, DER issued a Notice of Intent to issue a permit for the application pursuant to Chapter 403, Florida Statutes, and Public Law 92-500. In its notice, the extent of the project was described as follows: PROJECT: To construct an interchange where I-75 will intersect SR-64 by: filling 5,188 linear feet of a channelized cypress stand by placing 27,100 cubic yards of fill in the existing ditch; excavation of 38,250 cubic yards of material to create a new ditch 4,455 feet long; placement of 195,176 cubic yards of fill in an existing borrow pit to construct a road causeway with 241 linear feet of 72 inch RCP and 288 linear feet of 54 inch RCP placed under the causeway to provide water exchange; placement of 161 linear feet of double 8 ft. by 7 ft. box culvert in the new ditch for the crossing of SR-64; placement of 292 linear feet of 8 ft. by 7 ft. box culvert in the new ditch for the crossing of I-75; placement of two 24 inch and one 42 inch pipe to drain runoff from the interchange into the new ditch. The notice also stated that the proposed permit would be subject to certain conditions, including the placement of silt screens downstream from any construction, completion of ditch (canal) relocation and box culvert construction prior to placing fill in the existing canal, sodding of side slopes of causeway fill, and submission of weekly monitoring reports of turbidity before and during construction at certain locations. The letter provided that if monitoring revealed apparent violations of state water quality standards for turbidity, construction activities must cease immediately and not resume until corrective measures have been taken and turbidity has returned to acceptable levels. The letter also required that state water quality standards prescribed in Chapter 17-3, Florida Administrative Code, must be met by the DOT. (Exhibits 21 -22) The general area surrounding the project site consists of partially wooded pasture land and some residential development in the southwest portion. A cypress "head" consisting of almost eight acres lies east of the existing Cypress Strand Canal on the south side of SR-64 in the area where the relocated canal is proposed. The proposed roadway also will go through part of this cypress area. The bald cypress trees there are quite old and most reach a diameter of eight to ten feet. It is considered to be one of the few cypress stands to be found in Manatee County. In order to avoid the construction of bridges for the proposed highway in this area, DOT plans to fill approximately five and one-half acres with consequent removal of most of the existing trees in the filled area. Although there is standing water in the cypress hammock area, only an insignificant amount of surface water flows from there to the canal due to the higher elevation of the canal. It was for this reason that the DER supervisor of the dredge and fill section determined that the cypress head was not contiguous to waters regulated by the department. This decision, which was adopted by the Director of the DER Division of Environmental Permitting, in effect, overruled a recommendation by a DER field representative who had conducted an appraisal of the application and determined that the cypress head acts as a preliminary filtering are before the waters empty into the cypress creek salt marsh which then flows into the Manatee River. Expert testimony establishes that the DER position is correct in this respect and that only an insignificant amount of water leaves the cypress pond area into the canal. (Testimony of Allen, McWilliams, Wanielista, Exhibits 6-13, 17, 18, supplemented by Exhibits 15-16, 20.) On the north side of SR 64, the proposed relocated canal and roadway would be constructed through a "borrow pit" which covers approximately 39 acres. It is proposed to fill approximately 12 acres of this area. The remainder will contain water which acts as a "kidney" to filtrate water flowing from the canal and this area will be more than sufficient to adequately perform such a function. (Testimony of Allen, Wanielista, Exhibits 17-18.) The proposed roadway and ramps at the interchange over SR 64 are designated to retard or slow down the surface water movement to minimize degradation of water quality. To this end, the amount of exposed earth fill will be limited to the extent possible, and after the fill is placed in position, various types of erosion control will be accomplished, such as sodding slopes and building earth berms along the top of the roadway. Hay bales will be placed at the "toe" of the slopes during construction to further retard water movement and the introduction of sediment into waterways. Silt barriers termed "Florida diapers" which consist of a floating barrier of vinyl material will be placed strategically to prevent movement of silt past the barrier. This type of screening has proved to be effective in the past in situations involving relatively still water. Although various nutrients, metals, and chemicals will accumulate on the roadway and slopes during operations, the foregoing methods of retarding flow will serve as filters to reduce degradation of water quality. Additionally, depressions will be made in median areas to permit percolation into the roadway fill material. The "infield" or areas inside the circular ramps, consisting of approximately 20 acres, will be vegetated by the planting of some 150 cypress trees. The 80-foot-wide median area will also be vegetated. The concrete box culverts for the crossing of the proposed roadway will replace some 550 feet of the existing canal and will cause a somewhat accelerated flow of water. Overall, however, in the opinion of Respondents' expert witness, runoff from the interchange area will not measurably increase pollution in the Cypress Strand Canal or the Manatee River. It is his view that much of the water will percolate into the interchange ground area and that any remaining flow will result in 90 percent removal of pollutants by the various proposed methods of erosion control. In fact, the expert is of the view that the project is "overdesigned" at the present time and that the interchange infield design plus the filtering action that will take place in the borrow pit is more than sufficient to insure minimum degradation of water quality. (Testimony of Allen, Wanielista, Exhibit 13, 23.) All contracts for DOT roadway construction involve a special clause termed "Erosion Control and Pollution Abatement" that requires the building contractor to perform the various erosion control measures connected with the project. At a preconstruction conference, the contractor is required to tell DOT the specific manner in which such measures will be accomplished. During the construction phase, representatives of DER monitor the progress and recommend any necessary changes to meet State water quality requirements. Similar monitoring is required after construction and during operation of the roadway for the life of the permit. Although no precise data on the extent of any water degradation can be obtained until after construction commences, past experiences of the DER with the standard DOT construction contracts have proved the measures taken thereunder effectively maintain water quality standards. On this basis, the DER determined that DOT had provided reasonable assurances that construction of the interchange would not result in exceeding State water quality standards. (Testimony of Allen, McWilliams.) Various objections against granting the requested permit have been expressed by members of the public and environmental groups. Although most of these witnesses acknowledge the need for the I-75 extension, they were of the opinion that the roadway should be relocated to the east away from the cypress wetlands area. Additionally, written communications received in evidence from the U.S. Department of Commerce, Florida Division of Forestry, Manatee Health Department, and the United States Department of Fish and Wildlife Service raised objections to the proposed project based upon the elimination of the Cypress Stand area and recommended either relocation of the interchange or preservation of the existing wetlands. (Testimony of Duisburg, Belmont, Miller, Flisik, Matey, Quy, Exhibits 4, 14-16, 19.) Other public witnesses representing the City Council of Palmetto, Florida, the Board of County Commissioners of Manatee County, Florida, Manatee County Chamber of Commerce, City Commission of Bradenton, Florida, and private interests recommended approval of the application. The testimony of these witnesses and various resolutions from governmental bodies primarily focused on the urgent need for construction of the I-75 interchange to promote the economic and general welfare of the area residents and promote safety on the highways. (Testimony of Gallon, Holland, Prather, Neal, Price, Reasoner, Coates, Wiseman, T. Harllee, Jr., T. Harllee, Pinardi, Harden, Exhibits 1-3, 5, 24.)
Recommendation That the Department of Environmental Regulation issue the requested permit to the Department of Transportation. DONE AND ENTERED this 19th day of July 1978 in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of July 1978. COPIES FURNISHED: Honorable Jay Landers, Jr. Secretary Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32301 Alfred W. Clark, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32301 James W. Anderson, Esquire Assistant General Counsel Department of Transportation Haydon Burns Building Tallahassee, Florida 32304 Judith Smith Kavanaugh, Esquire 543 Tenth Street, West Bradenton, Florida 33505
The Issue The issue is whether an Environmental Resource Permit should be issued to KGB Lake Howell, LLC, authorizing the construction of a surface water management system to serve an apartment complex known as the Estates at Lake Howell in the City of Casselberry, Florida.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this proceeding, Respondent, St. Johns River Water Management District (District), proposes to issue an Environmental Resource Permit to Respondent, KGB Lake Howell, LLC (Applicant), authorizing the construction of a stormwater management system to serve a 240-unit apartment complex known as the Estates of Lake Howell. The project will be located on an undeveloped tract of land in the City of Casselberry (City), Seminole County, Florida, just north of the Orange County line. It will include ten three-story buildings, parking, clubhouse/ administration building, amenity complex, and wet detention pond. The project also incorporates a 3.62-acre stormwater pond, now owned and used by Seminole County (County), lying east of Lake Ann Lane across from the project site, which was included in the overall acreage calculations for the purpose of increasing apartment density on the site. The Applicant has authorization from the County to apply for the permit incorporating that tract of land. The pond will continue to function as a stormwater facility for the County and will not accommodate stormwater from the project site. The project site consists of 38.9 acres located on the north side of Howell Branch Road, east of State Road 436 (also known as Semoran Boulevard), and west of Lake Ann Lane in the City. The site is currently undeveloped and includes an abandoned orange grove and upland pine flatwoods community, which make up approximately 14.6 acres, while the remaining 24.3 acres is a mixed forested wetland system. The property is now owned by the Harold Kasik Living Trust (Kasik property), which has a contract for purchase with the Applicant. The Kasik property is in the shape of a rectangle, 648 feet by 2,530 feet, with its long sides running north- south. It is bordered on the north and east by single-family residential and vacant land, to the south by commercial development, and to the west by high-density residential and commercial development. The property has a high elevation of approximately 83 feet on its southeastern corner and falls to the north/northeast, where the edge of the wetland system is at an elevation of 63 or 64 feet. The major development constraint on the site is the large wetland tract on the northern portion of the property. In order to minimize proposed impacts to the wetlands, the Applicant proposed the transfer of the development entitlements from the County land to benefit the Applicant's property. More specifically, the Applicant will acquire the County property, the Applicant will simultaneously grant a perpetual drainage easement over the property to the County, the Applicant will maintain the landscaping of the property in perpetuity, the Applicant will convey around five acres of wetlands on the northern end of the Kasik property to the County in fee simple, and the City will allow the transfer of development rights from the property. The project will adversely impact 0.99 acres of low- quality wetlands, of which 0.72 acres are to be dredged and 0.27 acres are to be filled to provide the fencing around the wet detention facility. To offset this impact, the Applicant proposes to preserve 17.8 acres of forested wetlands, plus 1.2 acres of forested uplands, or a mitigation ratio of 18:1. The District's guidelines for preservation mitigation applicable to this project are 10:1 to 60:1 for wetland impacts and 3:1 to 20:1 for upland impacts; thus, the mitigation plan falls within these guidelines. Under current conditions, stormwater runoff from the project site sheet flows into the on-site wetland and ultimately Lake Howell (the Lake), a Class III water body which meets all applicable water quality standards and is not an Outstanding Florida Water. After development occurs, stormwater from the developed portions of the property will be conveyed to a wet detention pond for required water quality treatment and peak discharge rate attenuation. After treatment in the detention pond, the water will discharge to the on-site wetland, as it does now, and eventually will be conveyed into the Lake. Off-site flows will continue to be conveyed into the on-site wetland. The wet detention pond, which has a minimum depth of twelve feet and a permanent pool of water with a mean depth of two to eight feet, has been designed to accommodate a 25-year, 24-hour storm. Post-development discharge will be less than pre-development, and the outfall structure has been designed to avoid channelization in the wetlands after the point of discharge. Since at least the late 1940's, Petitioner, Shirley Haynes, or her relatives, have owned, or resided on, a multi-acre tract of land just north of the project site at 2764 Lake Howell Lane. She has substantial frontage on the south side of the Lake. The southern portion of her property, which are wetlands, adjoins the northern boundary of the project site. For the past three years, Petitioner, Egerton van den Berg, has resided on a ten-acre tract of land at 1245 Howell Point, which is northeast of the project site. He has approximately 235 feet of frontage on the south side of the Lake. As argued in their Proposed Recommended Order, Petitioners generally contend that the application is "materially deficient" in several respects in violation of Rule 40C-4.101; that the Applicant has failed to satisfy Rule 40C-4.301(1)(c) and (d), which in turn constitutes a failure to meet the requirements of Rule 40C-4.302(1)(a)-(c); that the Applicant failed to satisfy the criteria in Sections 12.2.3(a)-(f), 12.2.1, 12.2.1.1, 12.2.1.3, 12.2.2.3(a)-(e), 12.2.2.4(a) and (b), 12.3.2.2(c), and 12.3.8(a) of the Applicant's Handbook: Management and Storage of Surface Waters (Applicant's Handbook); that the District did not adequately consider the cumulative impacts of the project as required by Section 373.414(8)(a), Florida Statutes; that a low flow analysis of the Lake was not performed, as required by Rule 40C-8.011(5); that the Applicant did not submit detailed mitigation plans as required by Section 12.3.3.2 of the Applicant's Handbook; that the 18:1 ratio for mitigation proposed by the Applicant is inappropriate; and that the District should not approve the density of the apartments established by the City. These concerns, to the extent they have been identified as issues in the parties' Pre-Hearing Stipulation, are addressed in the findings below. Where contentions have been raised by Petitioners, such as the placement of the detention pond over a depressional area, and they have not been argued in the Proposed Recommended Order, they have been deemed to be abandoned. Conditions for issuance of permits Rule 40C-4.301(1)(a)-(k), Florida Administrative Code, specifies eleven substantive requirements for which reasonable assurance must be given in order for a standard permit to be issued. Subsection (3) of the same Rule provides that the standards and criteria contained in the Applicant's Handbook shall determine whether the foregoing reasonable assurances have been given. Additional conditions for the issuance of a permit are found in Rule 40C-4.302(1) when the project, or any part of it, is located in, on, or over wetlands or other surface waters. Therefore, because a part of the Applicant's system will be located in wetlands, the Applicant must also give reasonable assurance that the project will not be contrary to the public interest, and that it will not cause unacceptable cumulative impacts upon the wetlands or surface waters. a. Rule 40C-4.301 Paragraphs (a)-(c) of the Rule require that an applicant provide reasonable assurance that the project will not cause adverse water quantity impacts to receiving waters and adjacent lands, adverse flooding to on-site or off-site property, or adverse impacts to existing surface water storage and conveyance capabilities. If a system meets the requirements of Section 10.2.1(a) through (d) of the Applicant's Handbook, there is a presumption that the system complies with the requirements of Paragraphs (a) through (c). This presumption has been met since the evidence supports a finding that the post- development peak rate of discharge will be lower than the pre- development peak rate of discharge for a 24-hour, 25-year storm event. Therefore, the Applicant's system meets the requirements of these Paragraphs. Paragraph (d) of the Rule requires that an applicant give reasonable assurance that the project "will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters." To satisfy this requirement, an applicant must also demonstrate compliance with the two-prong test in Sections 12.2.2 and 12.2.2.4 of the Applicant's Handbook. Section 12.2.2 requires that an applicant provide reasonable assurance that a regulated activity will not impact the values of wetlands and other surface water functions so as to cause adverse impacts to the abundance, diversity, and habitat of fish, wildlife, and listed species. In its proposal, the Applicant proposes to fill a total of 0.99 acres of wetlands. Since these impacts will eliminate the ability of the filled part of the on-site wetland to provide functions to fish and wildlife, the filling will cause adverse impacts. Under these circumstances, Section 12.2.1.1 requires that the Applicant either implement practicable design modifications to reduce or eliminate these adverse impacts or meet one of the exceptions under Section 12.2.1.2. Under Section 12.2.1.1, a proposed modification which is not technically capable of being done, is not economically viable, or which adversely affects public safety through the endangerment of lives or property is not considered practicable. The Applicant’s design for the proposed project went through a number of iterations prior to submittal to the District to reduce adverse impacts to the wetlands. During the permitting process, the District requested that the Applicant consider a number of other suggestions to reduce or eliminate the adverse impacts to wetlands such as adding a fourth floor to the apartment buildings to eliminate the need for one apartment building, building a parking garage for the tenants, and eliminating the tennis and volleyball courts. Because the Applicant provided detailed reasons why none of those suggestions were practicable, it was not required to implement any of those design modifications. In addition, the Applicant’s decision not to include a littoral zone around the stormwater pond did not increase the amount of wetland impacts as that engineering decision resulted in a stormwater pond that was simply deeper and not wider. Therefore, the Applicant has met the requirement to reduce or eliminate adverse wetland impacts. Section 12.2.1.1 only requires an elimination and reduction analysis when: (1) a proposed system will result in adverse impacts to wetland functions and other surface water functions so that it does not meet the requirements of Sections 12.2.2 through 12.2.3.7, or (2) neither one of the two exceptions within Section 12.2.1.2 applies. In determining whether one of the two exceptions in Section 12.2.1.2 applies, the District must evaluate the long- term ecological value of the mitigation proposed by the Applicant. If the mitigation is not adequate to offset the adverse impacts of the proposed system, then it is unlikely either exception in Section 12.2.1.2 will apply. As noted above, the Applicant’s proposed dredging and filling of the southern edge of the wetlands on the project site will eliminate the ability of that wetland area to provide functions to fish and wildlife. However, the Applicant’s mitigation plan of placing 17.8 acres of wetlands and 1.2 acres of uplands under a conservation easement to preserve that property in its natural state in perpetuity will fully replace the types of functions that the part of the wetlands proposed to be impacted provides to fish and wildlife. The mitigation plan will also offset the adverse impacts that this project will have on the value and functions provided to fish and wildlife by the impacted part of the wetlands. In this case, the first exception under Section 12.2.1.2(a) applies as it meets that Section's two requirements: the ecological value of the functions provided by the area of wetland to be adversely affected is low, and the proposed mitigation will provide greater long-term ecological value than the area or wetland to be adversely affected. Also, the quality of the wetland to be impacted is low. All of the proposed impacts will occur in the area of the wetland that was historically disturbed and in which nuisance and exotic species are prevalent. Due to nuisance and exotic vegetation, the ecological value provided by that area to wildlife is low. The mitigation for the proposed project will provide greater long-term ecological value to fish and wildlife than the part of the wetland proposed to be impacted because the proposed mitigation will preserve eighteen times more wetlands that are of higher quality and provide greater value than the wetland area to be impacted. The type of wetland to be preserved, a mixed forested wetland containing hardwoods, is rare for the area. Although the mitigation plan will provide greater long-term ecological value to fish and wildlife than the part of the wetland proposed to be impacted, the Applicant did not meet the second exception in the elimination and reduction rule under Section 12.2.1.2(b) because the wetlands to be preserved are not regionally significant. In addition to meeting the elimination and reduction rule through implementation of practicable design modifications, the Applicant also satisfied the same rule by meeting the first exception found in Section 12.2.1.2(a). Thus, the Applicant has satisfied Section 12.2.2, which is the first prong of the test to determine compliance with Paragraph (d). The second prong of the test to determine whether Paragraph (d) of the Rule has been satisfied is found in Section 12.2.2.4. That Section requires that an applicant give reasonable assurance that the activity will not change the hydroperiod of a wetland so as to affect wetland functions. For the following reasons, that prong of the test has been satisfied. Since the wetlands are primarily groundwater-influenced, the construction of the stormwater pond between the project and the wetlands will not adversely affect the wetlands. As the soils surrounding the pond are very porous with a high infiltration and percolation rate, water from the stormwater pond will still reach the wetlands through lateral seepage. Further, the Applicant will install an energy dissipating device on the outfall spout at the point of discharge so that water will be spread out from the stormwater pond as it discharges into the receiving wetlands. As noted earlier, this will prevent an adverse channelization effect. Finally, stormwater runoff from the surrounding basins that currently discharge into the wetlands will not be affected by the construction of the stormwater system. That runoff will continue to flow into the wetlands on the project site. Because the Applicant has satisfied Sections 12.2.2 and 12.2.2.4, Paragraph (d) of the Rule has been met. Paragraph (e) of the Rule generally requires that an applicant provide reasonable assurance that a project will not adversely affect the quality of receiving waters. Here, the Applicant has provided such assurance. This is because the system has been designed in accordance with all relevant District criteria. Also, the Applicant has proposed to revise Permit Condition 26 as follows: Condition 26. This permit authorizes construction and operation of a surface water management system as shown on the plans received by the District on June 14, 2001, and as amended by plan sheet C4 (Sheet 07 of 207) received by the District on January 23, 2002. In view of this revision, the Applicant's wet detention system complies with all of the design criteria contained in Rule 40C-42.026(4). Under Rule 40C-42.023(2)(a), compliance with the design criteria contained in Rule 40C-42.026 creates a presumption that state water quality standards, including those for Outstanding Florida Waters, will be met. This presumption has not been rebutted; therefore, the requirements of Paragraph (e) of the Rule have been satisfied. Further, Sections 12.2.4.1 and 12.2.4.2 state, in part, that reasonable assurance regarding water quality must be provided both for the short term and the long term, addressing the proposed construction, alteration, operation, maintenance, removal, and abandonment of the system. The Applicant has provided reasonable assurance that this requirement is met through the design of its surface water management system, its long-term maintenance plan for the system, and the long and short-term erosion and turbidity control measures it proposes. If issued, the permit will require that the surface water management system be constructed and operated in accordance with the plans approved by the District. The permit will also require that the proposed erosion and turbidity control measures be implemented. Section 12.2.4.5 does not apply because there are no exceedances of any water quality standards at the proposed receiving water. Also, Sections 12.2.4.3 and 12.2.4.4 do not apply because the Applicant has not proposed any docking facilities or temporary mixing zones. Paragraph (f) of the Rule requires that an applicant not cause adverse secondary impacts to the water resources. Compliance with this requirement is determined by applying the four-part test in Section 12.2.7(a) through (d). As to Section 12.2.7(a), there are no secondary impacts from construction, alteration, and intended or reasonably expected uses of the proposed system that will cause water quality violations or adverse impacts to the wetland functions. The Applicant chose not to provide buffers abutting the wetlands but rather chose measures other than buffers to meet this requirement. The Applicant has provided reasonable assurance that secondary impacts will not occur by placing the stormwater pond between the planned project and the wetlands, so that the pond itself will serve as a buffer by shielding the wetland from the lighting and noise of the project, and by acting as a barrier to keep domestic animals out of the wetlands. In addition, the Applicant increased the amount of property to be preserved as mitigation by adding 2.97 acres of wetlands and 1.2 acres of uplands to the mitigation plan to mitigate for any remaining secondary impacts. Accordingly, the first part of the secondary impacts test in Section 12.2.7(a) is satisfied. As to Section 12.2.7(b), because there is no evidence that any aquatic or wetland-dependent listed animal species use uplands for existing nesting or denning adjacent to the project, the second part of the test has been met. No adverse secondary impacts will occur under the third part of the test in Section 12.2.7(c) because the proposed project will not cause impacts to significant historical or archaeological resources. Finally, adverse secondary impacts as proscribed by Section 12.2.7(d) will not occur because no evidence was presented that there would be additional phases or expansion of the proposed system or that there are any onsite or offsite activities that are closely or causally linked to the proposed system. Therefore, the proposed project satisfies Paragraph (f) of the Rule. Paragraph (g) of the Rule requires that an applicant provide reasonable assurance that a project will not adversely impact the maintenance of surface or ground water levels or surface water flows established in Chapter 40C-8. Minimum (but not maximum) surface water levels have been established for the Lake pursuant to Chapter 40C-8 for the basin in which the project is located. The project will not cause a decrease of water to, or cause a new withdrawal of water from, the Lake. Therefore, the project satisfies this requirement. Finally, Petitioners have acknowledged in their Proposed Recommended Order that the Applicant has given reasonable assurance that the requirements of Paragraphs (h), (i), (j), and (k) have been met. The parties have also stipulated that the receiving water (Lake Howell) meets all Class III water quality standards. Therefore, the project satisfies the requirements of Subsection 40C-4.301(2). Rule 40C-4.302 - Public Interest Test Under Rule 40C-4.302(1)(a)1.-7., an applicant must provide reasonable assurance that the parts of its surface water management system located in, on, or over wetlands are not contrary to the public interest. Similar requirements are found in Section 12.2.3. The Applicant has provided reasonable assurance that the parts of the project that are located in, on, or over wetlands (mainly the detention pond and fill) are not contrary to the public interest, because the evidence showed that all seven of the public interest factors to be balanced are neutral. Because the proposed permanent mitigation will offset the project’s adverse impacts to wetlands, no adverse effects to the conservation of fish and wildlife due to the project’s permanent nature will occur. The evidence also showed that best management practices and erosion control measures will ensure that the project will not result in harmful erosion or shoaling. Further, it was demonstrated that the project will not adversely affect the flow of water, navigation, significant historical or archaeological resources, recreational or fishing values, marine productivity, or the public health, safety, welfare or property of others. Finally, the evidence showed that the project’s design, including permanent mitigation, will maintain the current condition and relative value of functions performed by parts of the wetland proposed to be impacted. Therefore, the project meets the public interest criteria found in Rule 40C-4.302(1)(a). Rule 40C-4.302(1)(b) - Cumulative Impacts Rule 40C-4.302(1)(b) and Section 12.2.8 require that an applicant demonstrate that its project will not cause unacceptable cumulative impacts upon wetlands and other surface waters within the same drainage basin as the regulated activity for which the permit is being sought. Under this requirement, if an applicant proposes to mitigate the adverse impacts to wetlands within the same drainage basin as the impacts, and if the mitigation fully offsets these impacts, the District will consider the regulated activity to have no unacceptable cumulative impacts upon wetlands and other surface waters. The Applicant has chosen to mitigate for the impacts to 0.99 acres of wetlands by preserving 17.8 acres of wetlands and 1.2 acres of uplands on-site. Since this mitigation will occur in the same drainage basin as the impacts and the mitigation fully offsets those impacts, the Applicant satisfies the requirements of the Rule. Rule 40C-4.302 - Other Requirements The parties have stipulated that the requirements of Paragraphs (c) and (d) of Rule 40C-4.302(1) do not apply. There is no evidence that the Applicant has violated any District rules or that it has been the subject of prior disciplinary action. Therefore, the requirements of Subsection (2) of the Rule have been met. Miscellaneous Matters County Pond Site The Seminole County pond site located on the east side of Lake Ann Lane and across the street from the project is not a jurisdictional wetland and does not have any wetland indicators. It is classified as an upland cut surface water. The Applicant is not proposing to impact any wetlands at the pond site, and the site is not part of the proposed mitigation plan for the project. The permit in issue here is not dependent on the pond site, and nothing in the application ties the project with that site. Indeed, the transfer of density rights from the County property is not relevant to the District permitting criteria. Review of Application When the decision to issue the permit was made, the District had received all necessary information from the Applicant to make a determination that the project met the District's permitting criteria. While certain information may have been omitted from the original application, these items were either immaterial or were not essential to the permitting decision. The application complies with all District permitting criteria. Contrary to Petitioners' contention, the Applicant does not have to be the contract purchaser for property in order to submit an application for that property. Rather, the District may review a permit application upon receipt of information that the applicant has received authorization from the current owners of the property to apply for a permit. In this case, the Applicant has the permission of the current owners (the Harold Kasik Living Trust).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order granting the requested permit as described above. DONE AND ENTERED this 29th day of March, 2002, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of March, 2002. COPIES FURNISHED: Kirby B. Green, III, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Shirley B. Haynes 2764 Lake Howell Road Winter Park, Florida 32792-5725 Egerton K. van den Berg 1245 Howell Point Winter Park, Florida 32792-5706 Charles A. Lobdell, III, Esquire St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Meredith A. Harper, Esquire Shutts & Bowen Post Office Box 4956 Orlando, Florida 32802-4956
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Respondent owns real property located in Township 2 North, Range 7 East, Section 32, in Madison County, Florida, that has surface water flowing through it and is encompassed within what is defined as "wetlands." Respondent is in control and possession of the property in question and all work on the property that is material to this proceeding is under the control or direction of the Respondent. There were access roads on the property as early as 1973 as reflected by Respondent's exhibit 2, a 1973 aerial photograph, but the width of the roads or the existence of ditches or culverts cannot be determined from the photograph. Petitioner's exhibit 2, a 1981 aerial photograph, shows the roads still in existence in 1981 but the width of the roads or existence of ditches or culverts cannot be determined from the photograph. Sometime before the Respondent purchased the property and began construction to expand the roads, ditches and culverts were in place; however, there was no evidence as to when the ditches and culverts came to be in place. A 1976 survey of the property reflects 60 foot roads which were to provide access to platted but unrecorded lots. These roads had not been constructed when Respondent purchased the property or began construction to expand the roads. The newly constructed portions of the road indicates an attempt to build the roads in accordance with the 1976 survey. The previously existing roads attempted to follow the natural contour of the land and as a result were not always straight, and only had a negligible effect on the flow or storage of surface water in regard to the property. Sometime around October 1987, Respondent began to rebuild and construct roads on the property by straightening existing curves, removing fill material from adjacent wetlands to widen and heighten the existing roadbed or construct a new roadbed, and to increase the depth and width of existing ditches or dig new ditches. The initial portion of the existing road providing access to the property from the county graded road has been substantially rebuilt with portion of the roadbed being 40 to 43 feet wide. Ditches along this portion of the roadbed have had their width increased up to 14 feet and their depth increased up to 6 and 8 feet. Other portions of the road has been expanded beyond the previously existing roadbed by increasing the width and height of the roadbed. The increased size of the ditches and the expanded roadbed has increased the interception of surface water above that already being intercepted by the previous roadbed and ditches and, as a result, there is an increased amount of surface water impounded or obstructed. The effect is that surface water is removed from Respondent's property at a faster rate than before road construction began and, as a result, sheet flow of surface water is decreased which diminishes the storage of surface water on the property. Although new culverts were installed during road construction, there was insufficient evidence to show that these new culverts were in addition to the culverts already in place or if they replaced old culverts. There was insufficient evidence to show that the new culverts allowed water to flow in a different direction or be removed from the property at a faster rate than before or if they impounded or obstructed surface water more so than before. The previously existing roads had sufficiently served an earlier timber harvest on the property and, by Respondent's own testimony, were sufficient for his ongoing hog and goat operation. The extensive rebuilding and constructing of roads in this case was neither necessary nor a customary practice for construction of farm access roads in this area. Respondent is engaged in the occupation of agriculture in that he has a bona fide hog and goat operation. However, Respondent's silviculture occupation is somewhat limited in that he is presently harvesting the timber but shows no indication of replanting or continuing the forestry operation upon completing the present harvesting operation. The extensive rebuilding and constructing of roads in this case goes beyond what is necessary or is the customary practice in the area for a hog or goat operation or forestry operation such as Respondent's and is inconsistent with this type of agriculture or silviculture occupation. Respondent has never applied for nor received a surface water management permit from the Petitioner even though the Petitioner has informed Respondent that a permit was required for the work being done on his property. The present alteration of the topography of the land by Respondent has obstructed and impounded surface water in such a fashion that the interruption of the sheet flow of surface water has been increased, causing the storage of surface water on the property to be diminished. At the present time, Respondent has been enjoined by the Circuit Court of Madison County, Florida, from any further activity on this project. However, should Respondent be allowed to complete this project, it is evident that the sole and predominant purpose would be to impound and obstruct the sheet flow of surface water and diminish the storage of surface water on the property in question.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore, RECOMMENDED that the Petitioner, Suwannee River Management District, enter a Final Order requiring Respondent, Norman Leonard, to: (a) remove all unauthorized fill material placed within jurisdictional wetlands and return those areas to predevelopment grades and revegetate with naturally occurring local wetlands species to prevent erosion; (b) back fill excavated swale ditches, return road beds and excavated ditches to predevelopment condition and grades and seed disturbed non-wetland areas with a 50:50 mix of bahia and rye grass and; (c) refrain from any other development until and unless a required permit is obtained for such development. Respectfully submitted and entered this 13th day of February, 1989, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 1989. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 88-1445 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner 1. Adopted in Finding of Fact 1. 2.-3. Adopted in Finding of Fact 2. 4.-7. Are unnecessary findings for this Recommended Order. Adopted in Finding of Fact 18. Adopted in Finding of Fact 19. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Subordinate to the facts actually found in this Recommended Order. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12. Rejected as conclusions of law. Adopted in Findings of Fact 3 and 4. Adopted in Finding of Fact 8. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 8. Adopted in Finding of Fact 6. Adopted in Finding of Fact 7. Adopted in Finding of Fact 6. Adopted in Finding of Fact 10. Adopted in Findings of Fact 15 and 17. 26.-29. Adopted in Finding of Fact 12. 30. Adopted in Finding of Fact 13. 31.-32. Subordinate to facts actually found in this Recommended Order. Adopted in Finding of Fact 12. Adopted in Finding of Fact 16. 35.-38. Subordinate to facts actually found in this Recommended Order. 39.-42. Rejected as not being relevant or material. Specific Rulings on Proposed Findings of Fact Submitted by Respondent 1. The first paragraph adopted in Finding of Fact 16. The balance is rejected as a conclusion of law. 2.-3. Rejected as not being relevant or material. Not a finding of fact but a statement of testimony. However, it is subordinate to facts actually found in this Recommended Order. Rejected as not supported by substantial competent evidence in the record. The more credible evidence is contrary to this finding. COPIES FURNISHED: Janice F. Baker, Esquire Post Office Box 1029 Lake City, Florida 32056-1029 Norman Leonard, Pro Se Route 2, Box 172-D Live Oak, Florida 32060 Donald O. Morgan Executive Director Suwannee River Water Management District Route 3, Box 64 Live Oak, Florida Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400
The Issue The issues for determination in this case are whether Respondent Jeffrey Hill should pay the administrative penalty and investigative costs, and should undertake the corrective actions that are demanded by the Florida Department of Environmental Protection (“Department”) in its Notice of Violation, Orders for Corrective Action, and Civil Penalty Assessment (“NOV”).
Findings Of Fact Respondent is the owner and operator of a community water system and its associated piping, designated PWS No. 2124409, located on parcel ID No. 03-4S-17-07486-001 on Country Club Road, in Lake City, Columbia County, Florida (“the property”). Respondent is a “person” as defined in section 403.852(5), Florida Statutes. Respondent is a “supplier of water” as defined in section 403.852(8). The water system is a “public water system” and a “community water system” as defined in sections 403.852(2) and (3), respectively. The community water system is a Category V, Class D water system with a capacity of 28,800 gallons per day that supplies between 25 and 3,300 people, using groundwater as its source. Count I Count I of the NOV charges Respondent with failure to sample for nitrate and nitrite in 2012 and 2013, which was admitted by Respondent. Count II Count II of the NOV charges Respondent with failure to sample for primary inorganic contaminants for the 2011-2013 compliance period, which was admitted by Respondent. Count III Count III of the NOV charges Respondent with failure to analyze for secondary contaminants in the 2011-2013 compliance period, which was admitted by Respondent. Count IV Count IV of the NOV charges Respondent with failure to sample for volatile organic contaminants in the 2011-2013 compliance period, which was admitted by Respondent. Count V Count V of the NOV charges Respondent with failure to sample for synthetic organic contaminants in the 2011-2013 compliance period, which was admitted by Respondent. Count VI Count VI of the NOV charges Respondent with failure to sample for total coliform from June 2013 to date, which was admitted by Respondent. Count VII Count VII of the NOV charges Respondent with failure to employ an operator for the system since May 2013, which was admitted by Respondent. Count VIII Count VIII of the NOV charges Respondent with failure to submit test results required by Florida Administrative Code Chapter 62-550, and failure to file a monthly operation report since April 2013, which was admitted by Respondent. Count IX Count IX of the NOV charges Respondent with failure to issue Tier 3 notices in May 2013 and March 2014, advising customers of the failure to monitor for certain contaminants, which Respondent admitted. Count X Count X of the NOV charges Respondent with failure to provide a consumer confidence report to his customers in 2012 and 2013, which was admitted by Respondent. Count XI In Count XI of the NOV, the Department states that it incurred $530 in investigative costs related to this enforcement matter, which is admitted by Respondent.
The Issue The issues presented in this matter concern the request by the Petitioner to be granted a management and storage of surface waters permit by Respondent. Respondent proposes to deny the permit based upon the perception that the activities contemplated by Petitioner: (1) are not consistent with the public interest as envisioned by Section 373.016, Florida Statutes, and 40C- 4.301(1)(b), Florida Administrative Code, (2) are not a reasonable and beneficial activity, per Section 40C-4.301(1)(a), Florida Administrative Code, alter the peak discharge rate of runoff from the proposed activity or the downstream peak stage or duration for the 1 in 10 year design storm, per Section 40C-4.301(3)(a), Florida Administrative Code, (4) cause an increase in velocity or flood stage on lands other than those owned, leased, or otherwise controlled by the applicant for the design storm, per Section 40C-4.301(3)(b), Florida Administrative Code, (5) cause an increase in flow or stage such that it would adversely affect lands other than those owned, leased, or otherwise controlled by the applicant, per Section 40C-4.301(3)(c), Florida Administrative Code. 1/
Findings Of Fact A predecessor applicant had requested permission to construct and operate the water management system which is the subject of this controversy. The approximate acreage involved was 197 acres in Lake County, Florida. This acreage and requested activity was subject to the regulatory requirements of St. Johns River Water Management District. Clay Island Farms, Inc., hereinafter referred to as CIF, was substituted for the initial applicant and this matter has been litigated before the Division of Administrative Hearings on the continuing application of the Petitioner. The permit application number is 4- 8089. This application was considered with application number 4-8088, pertaining to property owned by A. Duda and Sons, Inc. Subsequently, the latter application shall be referred to as the Duda request for permit. Certain additional information was sought by Respondent from the applicants, CIF and Duda, in the permit review, by correspondence dated October 2, 1981. A copy of that correspondence may be found as Petitioner's Exhibit No. 16 admitted into evidence. In particular, CIF was requested to prepare pre and post-development runoff rates in the 1 in 10, 1 in 25,and 1 in 100-year storms, to include stage-storage and stage-discharge rates for any and all retention facilities within the project design. Petitioner's Composite Exhibit No. 1 admitted into evidence contains a copy of the engineering report by CIF which are CIF's responses to the request for information. The date of the engineering report is July 12, 1982. The CIF application, as originally envisioned, called for the construction of exterior and interior ditches to be placed around a dike of 71 feet MSL elevation. The dike would enclose a proposed farm operation of approximately 197 acres, should the permit be granted. Within that 197 acre plot, would be found numerous drainage ditches to include major ditches and minor arterial ditches. The purpose of those ditches found in the 197 acres would be to serve as a conveyance for rainfall runoff. The system of conveyance would be connected to an existing conveyance system already in place and related to farm operations of A. Duda and Sons. The runoff would be eventually placed in a retention pond and at times discharged from that retention pond or basin into Lake Apopka by means of gravity flow. The particulars of the development of the 197 acre plot and its service dike, canals, and ditches are more completely described in Petitioner's Exhibit No. 1, which is the engineering report for the surface water management permit application. The CIF application was reviewed by the staff of the Respondent. Recommendation was made to deny the permit. Details of that denial may be found in Respondent's Exhibit No. 1. In the face of the denial, CIF requested an administrative hearing. This request was made on August 27, 1982, by petition for formal Subsection 120.57(1), Florida Statutes, hearing to determine Petitioner's entitlement to the requested permit. St. Johns River Water Management District, in the person of its governing board, determined to refer this matter to the Division of Administrative Hearings to conduct the formal proceeding and the request for the assignment of a hearing officer was received by the Division on September 13, 1982, leading to the final hearing in this cause. During the course of the final hearing, the CIF permit application was modified in a fashion which reduced the amount of acreage sought for cultivation. Now, approximately 122 acres would be farmed per the amended proposal. A general depiction of the design of the project in its amended form may be found in the engineer's sheet, which is Petitioner's Exhibit No. 20 admitted into evidence. When contrasted with the engineering drawings set out in Petitioner's Composite Exhibit No. 1, the new design is essentially the same as contemplated in the original permit application, on a lesser scale. Other than dimensions, the basic concepts of the CIF operation would remain the same under the amended proposal. At present, Petitioner proposes to remove the vegetation which covers the subject 122 acre plot and to conduct a muck farming operation. That vegetation is mostly mixed hardwood with the primary species being red maple. The soil in this area is constituted of monteverde muck, which is conducive to the production of corn and carrots, the crops which Petitioner would plant, to prepare the land for the operation, the system of ditches dikes and canals described would be installed following the cleaning, draining, and leveling of the 122 acres. Petitioner's Exhibit No. 10 admitted into evidence depicts land which has been cultivated and the subject 122 acres in its undisturbed state. Petitioner's Exhibit No. 4 admitted into evidence shows the overall CIF area is outlined in red, except for its southerly extent, which carries a red and yellow line on the exhibit. This exhibit depicts Wolfshead Lake which is a small interior lake in the southeastern corner of the overall CIF property. The yellow line in the middle of the CIF property represents, the location of a former north-south canal. The westernmost north-south reach, which is shown with a red line, depicts a canal which runs north from Wolfshead Lake into the existing Duda system of canals and ditches. The Duda operation has attempted to plug that north-south canal on the western fringe to stop the flow from the area of Wolfshead Lake, but has been unsuccessful and the water still enters the Duda farm ditches and canals. In the 1940's and early 1950's, the CIF property had been partially developed for a cattle operation and truck farming. Those canals, as described before, were installed, together with the diagonal yellow line on Petitioner's Exhibit 4, which represents a canal that was built with an axis running northeast and southwest. In addition, there was a centrally placed east-west canal and a slough running from Wolfshead Lake in a southeasterly direction. The slough is still there, although water that might be diverted from the Wolfshead Lake area into the slough is flowing north in the westerly north-south canal at present. If the project were allowed, most of the water flowing in and around the Wolfshead Lake would be introduced into the slough and from there exit to Lake Apopka. The center north-south canal and the interior east-west canal, together with the diagonal canal, are not in operation at present. The center north-south-canal would become the approximate eastern boundary of the 122 acres with the western north-south canal representing the approximate western boundary of the 122 acre plot. The northern boundary of the CIF property is constituted of an east-west canal which is part of the present Duda system. This is the only one of the canals associated with the former farming operation on the CIF property which is part of any maintained system of conveyances presently in existence. Approximately 1,000 acres are being farmed by Duda and Sons in property north of the proposed project. The Duda permit application, 4-8088 as granted, is described in Petitioner's Exhibit No. 13 which is a copy of the permit. This acreage is generally found to the northwest of the CIF plot, and would allow an additional 300 acres to be farmed in that muck area, on land which has been cleared for the most part and/or which has an elevation predominantly above 68.5 feet MSL. Eighty acres of the proposed Duda permit application was denied based upon the fact that it had not been cleared prior to the Duda permit application and in consideration of the amount of the 80 acre segment which lies below 68.5 feet MSL. The elevation 68.5 feet MSL represents the flood plain for the 1 in 10 year rainfall event for Lake Apopka. The area of the Duda permit is depicted on Petitioner's Exhibit No. 4 and outlined on that exhibit with lines of green and yellow at the southern end, green and yellow and red and yellow on its western flanks, red at the north end and by red on the east side, together with a Duda drainage ditch, which runs north from the terminus of the north-south drainage ditch coming from Wolfshead Lake and the east-west drainage ditch at the northern extent of the CIF property. Exhibit No. 4 was made prior to clearing operations depicted in Petitioner's Exhibit No. 10 and that letter exhibit is a more correct indication of the appearance of the new Duda permit property today. A green diagonal line running northwest and southeast intersecting with a line running east-west and a line running north-south depicts the approximate part of the 80 acres, which lies below 68.5 feet MSL, as shown in Petitioner's Exhibit No. 4. Farm operations, in keeping with the authority of Permit No. 4-8088, have not commenced. If the CIF permit application is successful, the original 1,000 acres, approximately 300 acre area of the Duda permit and the 122 acres of CIF, would be tied in by a system of conveyance ditches or canals allowing the interchange and transport of water through and around the three farm areas. The existing retention pond would be expanded to accommodate the additional farm acreage. The Petitioner is willing to increase the present retention pond to a design capacity which would equal one acre of basin for each ten acres of farm land, at the place in time when all three elements of the muck farm operation were under way. This again pertains to the existing 1,000 acres, the approximately 300 acre recent Duda permit, and the 122 acres related to the CIF application. With the addition of the CIF acreage, when water in the ditches reached 67.1 feet MSL, this would cause the engagement of a 40,000 GPM pump allowing the ditch water influent into the retention pond. The pump automatically would shut off at any time the water level in the access ditches to the pond dropped below 61 feet MSL. The primary purpose of the retention pond is to make water available for irrigation of crops, in its present state, and as contemplated with the addition of the CIF project. The pond does and would detain farm water for a period of about a day allowing the settling out of certain nutrients which are in particulate form. The existing pond and in its expanded form does not and would not filter nutrients which have been dissolved and have become a part of the water column. At times of high incidence of rainfall, when the crops are inundated with water for a 48-hour period of time, the retention pond is now designed and as contemplated by the addition of the CIF farm land, would allow for the discharge of effluent into Lake Apopka through two discharge culverts. The discharge is by means of gravity through an adjustable riser system. The retention pond as presently designed and as contemplated in its expansion has established the height at which water would be released from the retention pond into Lake Apopka through the riser at 68 feet MSL. The occasion of high incidence of rainfall occurs during the normal rainy season in a given year. Discharge could also be expected in the 1 in 10 year, 24hour storm event. During that storm event or design, Lake Apopka would rise to a level of 68.54 feet MSL, a level which would correspond to the 10year flood plain. Whether in the pre or post-development phase of the 122 acres, waters from that acreage would be discharged during the course of the storm through culverts leading from the retention pond into Lake Apopka. This process would continue until the gravity flow stopped at the moment where the water level in the pond and the water level in Lake Apopka adjacent to the discharge culverts achieved equilibrium of elevation. At that point in time, the gravity flow or discharge from the retention basin would cease, there no longer being a positive gradient from the detention pond to Lake Apopka. There will be some amount of discharge in the 24-hour storm event through the culverts at the retention pond either in the pre or post-development phases of the project, because, at present, the western most north-south ditch, which is found at the western boundary of the CIF property, allows water to flow north into the present Duda ditch system, water which has fallen on the 122 acres in question. From the ditch system, that water finds its way into the retention pond and thus into the lake. The contemplated system to be installed with the 122 acres at build-out would also allow water from the 122 acres to go through a system of conveyances and to the retention pond and from there into Lake Apopka. Although considerable testimony was presented by both parties on the subject of comparing pre-development and post-development peak discharge rates of runoff from the proposed activity, in the 1 in 10 year, 24-hour storm design or event, neither party has satisfactorily proven the dimensions of the pre-development and post-development peak discharge rates of runoff from the proposed activity. This determination is made having reviewed the testimony and the exhibits in support of that testimony. Notwithstanding a lack of proof of this differential with exactitude, it has been shown by the testimony and exhibits that the post- development peak discharge rate of runoff in the 1 in 10 year, 24-hour design storm or event can be expected to exceed that of the pre-development rate. On the associated topic of the ability of the post-development design to accommodate the differential in peak discharge rate of runoff between pre- development and post-development, Petitioner has failed to establish this proof. The modeling that was done by the Petitioner, in an effort to depict the differential as 10 acre feet with an available capacity of attenuation approximating 26 acre feet within the system of ditches, is not convincing. Nor has petitioner shown that there is sufficient storage in the retention pond, in the course of the storm event. The data offered in support of Petitioner's position does not sufficiently address accommodation of the drainage from areas surrounding the 122 acres in question, which are not part of the Duda system; the amounts of water already found in the system of ditches and canals at the onset of the storm event; the amount of water located on the crops at the onset of the storm event, which would have to be removed; and the amount of water already found in the retention pond at the time of the storm event. During the 1 in 10 year 24-hour storm, the CIF 122 acres will be protected by the 71-foot MSL dike, in that the expected elevation of Lake Apopka would not exceed 68.54 feet MSL. The dike would also protect the 122 acres in the 25, 50, and 100-year, 24-hour storm events whose elevations are anticipated to be 68.98, 69.28, and 69.56 feet MSL, respectively. As a consequence, an increase in flood stage would occur on lands other than those controlled by CIF. The amount of increase in flood stage would be approximately .046 inches during the 1 in 10 year storm, and an increasingly greater amount for the larger storms. It was not established where the amount of water which could not be staged on the 122 acres would be brought to bear through the surface flow on the 31,000 acres of water which constitute Lake Apopka. Nonetheless, that water could be expected to increase the flood stage on lands other than those of the Applicant. Possibly the dikes protecting the muck farms on the northern side of Lake Apopka could be influenced by the .046 inches in elevation due to the forces associated with the 1 in 10 year storm event, such as winds and movement of the water in the lake. This is true, notwithstanding the fact that the design goal of the dikes in the area is 71 feet MSL. The dikes are constituted of muck and are susceptible to overtopping, erosion, or blowout. By history, there have bean dike failures in the northern end of Lake Apopka, and associated increases in stage or flood stage. This incremental increase in water level in the 1 in 10 year storm event, due to the CIF development, when considered in the context with the other influences of that storm event, could possibly be the determining incident leading to dike failure in the northern perimeter of Lake Apopka. However, given the history of dike failures, prior to this potential loss of the storage area on the applicant's property, it has not been shown that the proximate cause of dike failure in the 1 in 10 year storm could be expected to be the contribution of an additional .046 inches of water on the lake surface. Those failures existed prior to the potential for the addition of water and were the result of inadequate maintenance of a structure which demanded a better quality of attention. Nonetheless, the additional amount of water could be expected to exacerbate the extent of a dike breach in any 1 in 10 year storm event that occurred subsequent to the development of the CIF 122 acres. In summary, the likelihood that the increase in elevation of water caused by the loss of storage on the subject property will be the critical event that causes a dike failure is not accepted. A dike could breach because of the influence of the storm even itself, without regard for the incremental increases in water elevation due to loss of water storage on the CIF property. The poor condition of some dikes due to less than adequate design or maintenance, would promote that dike failure and be exacerbated to the extent of more water being introduced on that property through the incremental amount of increase due to loss of storage on the CIF property. The dike failure circumstance in and of itself would not be sufficient to deny the permit application; however, the applicant had the burden of addressing the possible problem of increases in stage or flood stage on other properties, not its own, which are not protected by dikes. This showing was not made by the applicant, notwithstanding the fact that an increase in stage or flood stage could be expected to occur on property fronting Lake Apopka, which property is not protected by any form of artificial barrier. The installation of the protective dike aground the 122 areas of the CIF property in the 1 in 10 year design storm and potentially at times of lesser rainfall events, could be expected to increase the stage or flood stage on lands unprotected by dikes and thereby adversely affect lands other than those controlled by the applicant. Most of the 122 acres and the property to the east of that development and a portion of the undeveloped 80 acres in the recent Duda permit would be inundated in the 1 in 10 year storm event, prior to development. This is true because the elevation of much of that property is approximately 67.5 foot MSL. During the 1 in 10 year storm event, it would store approximately one foot of water, as presently constituted. It could also be expected to be inundated on an average of approximately once in two years. Lake Apopka is a part of a controlled system of lakes known as the Oklawaha River chain of lakes. Respondent regulates the water level in that chain of lakes by operation of a lock on the Apopka-Beauclair canal. The maximum desirable elevation of 67.5 feet MSL for Lake Apopka is a part of the regulation schedule found in Respondent's Exhibit No. 2 admitted into evidence. In the 1 in 10 year or better storm event, the Apopka-Beauclair system could not draw down the surface water at a rate faster than 27 days per foot, even assuming the lock was fully open to flow. Consequently, those properties that were suffering an, increase in flood stage on their surface could not expect to gain prompt relief through the regulation of waters in the Oklawaha River chain of lakes. Lake Apopka is an hyper-eutrophic lake. Although it is classified as Class III water body (ambient water quality) within the meaning of Section 17- 3.161, Florida Administrative Code, it fails to match that classification in terms of its actual water quality. This is as a consequence of its highly eutrophic state, brought about by the age of the lake and the contributions of man. Some of the contributors to the eutrophication have been removed from the lake area and water quality has improved. Those facilities removed were sewage treatment and citrus processing plants around the Lake Apopka rim. The muck farms remain and the quality of the water in the retention basins or ponds when compared to the receiving waters of Lake Apopka is similar in nature. Consequently, the receiving waters are not enhanced in their water quality when the retention ponds discharge water into Lake Apopka. As stated before, the retention ponds do not have as their primary purpose the treatment of water. Any water quality improvement is a secondary function of the retention pond. The retention ponds do improve the water somewhat, as described, and are adequately sized to fulfill that partial cleansing. Whether the water quality in Lake Apopka would ever improve sufficiently to allow Lake Apopka to become a more diversified habitat for fish and wildlife is not certain, even if all contributing discharges of pollutants were curtailed, to include the discharge of water from the muck farms with its high nutrient loads. Nonetheless, Lake Apopka cannot accomplish the recovery if the effluent from the muck farms continues to be introduced into the lake with the present constituents found in the water. Out of concern for the water quality in Lake Apopka, officials of the University of Florida have conducted experiments on nutrient removal which they hoped would approximate the quality of removal accomplished by transitional vegetation and swamp. (The 122 acres at issue and the western and eastern adjoining property are constituted of these water treatment zones.) This experiment of nutrient removal through use of retention ponds calls for the retention of the muck farm water for a period of six days allowing settlement of particulates and for the vegetation within those experimental retention basins to uptake dissolved nutrients. Several types of vegetation are used to gain a better quality of nutrient uptake add the vegetation is harvested every six to eight weeks to improve that performance. The experiment has shown that the quality of water discharged from the ponds utilized by the University of Florida was comparable in its quality to the natural wetlands system water discharge. The natural wetlands discharge is of a better quality than the receiving waters. Unlike the university experiment, the pond contemplated by CIF primarily emphasizes detention for a shorter period of time than was used in the experiment and allows highly eutrophic water to be mixed with that quality of water already found in Lake Apopka. The only exception to that comment is that water flowing from Wolfshead Lake, which is south of the proposed 122 acres, is a high quality of water, and through the project as contemplated, this water would be directly introduced into Lake Apopka through a flow over a natural wetlands system. This is in opposition to the present situation where the water from Wolfshead Lake flows primarily to the north through an existing canal and is mixed with water from the muck farm and is, therefore, of the eutrophic character as opposed to the high quality character. The Duda permit, which was issued, would allow the introduction of water which is similar in character to the water of Lake Apopka, through the system of ditch conveyances, placement in the retention pond, and at times, flow to the lake. In its effect, the nutrient loading which occurs by introduction of waters from that new farm, would be similar to that proposed in the CIF project. The fact of this similarity does not prohibit the district from evaluating water quality matters on the occasion of the CIF permit decision. Should the 122 acres be converted from natural vegetation to a muck farm, wildlife and fish habitat would be adversely impacted. The habitat provided by the plot is in scarce supply and is essential to the maintenance of a diversified fish population. The hardwood swamp, which is part of and adjacent to the 122 acres of the CIF application, supports benthic invertebrates, which are a food source for game fish. The type of vegetation found in the lake, due to its eutrophic state, is plankton and one of the by- products of the reproduction of that plant through the process and respiration is the destruction of the fish population. This occurs in the summer months. The plankton has replaced the emergent and submergent vegetation which once covered as much as two-thirds of Lake Apopka and now represents .05 percent of the lake. As a consequence, game fish have diminished over a period of years with plankton feeding fish predominating. Consequently, the fish population is less diverse and the removal of the vegetation becomes a significant contributor to the imbalance in fish population.
Findings Of Fact Petitioner, Robert Brown, is the co-owner of Lot 13 and the northern half of Lot 14, Block 7, Lake Addition to Boynton in Boynton Beach, Palm Beach County, Florida. The property consists of a parcel approximately 150 by 150 feet and is located along the western edge of the Intra-coastal Waterway at N.E. 8th Ave. and N.E. 7th Street in Boynton Beach. At all times pertinent to the issues herein, Petitioner was the owner of this property which is vegetated along the Eastern half with mature mangrove trees which extend back from the water's edge approximately one half the depth of the lot. These mangroves include red, black, and white species and the larger are approximately between 18 and 22 years old. The majority of the trees, however, are younger than that. The Western half of the property is sparsely vegetated and in the heavily vegetated half, there is an open area approximately 30 by 30 feet which appears to have been cleared and on which there are no mature mangrove trees. On July 19, 1984, Petitioner filed an application for a permit to construct a 1625 square foot house on pilings together with a 164 by 4 foot boardwalk extending in a west to east direction from the westernmost edge of the mangrove community to the waterside of the proposed dwelling giving access thereto. The eastern half of the property in question appears to be lower in elevation than the western half and experiences some tidal inundation during periods of high tide. Though there is a riprap deposit along the eastern edge of the property and two berms extending along the landward side of the riprap, water from the Intra-coastal Waterway periodically flows through the riprap, over the berms, and onto Petitioner's property. This water is afforded access onto the property also, by a northwest running ditch located south of the southern boundary of the property which ditch is connected to the waterway. It intersects with another ditch which runs due north to an intersection with an east-west depression, also connected to the Waterway, running along the northern boundary of the property. Mangroves of some size are found in and on the edges of this ditch. Petitioner's construction proposal, involving the driving of supporting pilings for the dwelling, is a dredge and fill activity as defined by the Department of Environmental Regulation's (DER), experts and requires the issue of a dredge and fill permit. There is a conflict between the Petitioner's evidence regarding the physical location of his proposed dwelling and boardwalk and that of the agency personnel who, with benefit of a survey, determined that the larger clearing referenced by the Petitioner does not lie on his property and that the indicated cleared cut through the mangrove community to the waterway on Petitioner's property for the walkway does not lie on Petitioner's property but instead is approximately 30 feet south of the southern boundary. Having reviewed the application submitted by Petitioner, DER requested additional information regarding construction techniques and plans. These have not, to this date submitted in a tangible form the information requested. Petitioner's attorney provided some of the information requested orally to DER at some time in the past, giving some assurances that the disruption of water quality during construction would be kept at a minimum and would be only temporary. However, since DER did not have available to it the additional information it requested so as to appropriately evaluate the true proposal by Petitioner and the effect of any modifications, based on the failure of Petitioner to provide adequate assurances that water quality standards would not be violated and that the project was not contrary to public interest as is required of him by Section 403.918, Florida Statutes, on January 23, 1985, the Department issued an intent to deny the permit. As a part of this intent to deny, the agency suggested that the project be relocated to the upland one-half of the Petitioner's property. Construction there would not have involved any mangrove disturbance and would have been consistent with the agency's standards and policies. Historically the property owned by Mr. Brown did not border the open body of water which now constitutes Lake Worth or the Intra-coastal Waterway. As far back as 1872, the property was dry and supported no mangrove growth. Mangroves existing currently on the property have developed there since the construction of the Intra-coastal Waterway and its joinder with Lake Worth and the installation of the inlets which connect this water body with the Atlantic Ocean. On the property directly north of Petitioner's boundary sits a house built on fill approximately one and a half feet above the gradient of Mr. Brown's lot. Immediately south of his property is a condominium building also located on fill bordering the Intra-coastal Waterway. Evaluation of photographs of the area reveals that both pieces appear to have been identical in make-up to that owned by Petitioner in both topography and vegetation prior to being filled for construction. In fact, this parcel lies in a rapidly developing commercial and residential area. Petitioner also presented the testimony of two long time residents of the area who indicate that prior to the widening of the Intra-coastal Waterway, Petitioner's property did not border the open water of Lake Worth or the waterway. Back in the 1940's and before, the property was not covered with mangrove trees and was, in fact, used as farmland by Mr. Pinder, one of these two witnesses, who grew bell peppers and squash there. Mr. Pinder was hired by Palm Beach County during the 1940's and 1950's to dig mosquito control ditches on the property and Petitioner contends that it was these ditches which developed the connection with the Intra-coastal Waterway and thereby created a jurisdictional wetland. The weight of the evidence, however, indicates that though ditches were dug for mosquito control as described by Mr. Pinder and even before, it was not these ditches which changed the character of the property to jurisdictional wetland. Review of the maps submitted by Mr. Brown shows to a very limited degree some reference to ditches on or near the property in question but neither this evidence nor the testimony of both long-time residents is sufficiently clear and convincing to establish to the satisfaction of the Hearing Officer that the character of Mr. Brown's property was so radically changed by the digging of these ditches as to become jurisdictional because of them. Turning to the question of the impact of the proposed construction on the mangrove system, the evidence presented by the agency and to a lesser degree by Petitioner himself shows that there would be some adverse impact on the mangrove system through the direct destruction of some existing trees and saplings, the trimming of some of the overhanging mangrove canopy, and the subsequent shading of immature mangroves by the construction of the dwelling and the boardwalk. The evidence available indicates that the construction of the dwelling itself cannot be contained within the existing clearing and for the construction of the boardwalk, an additional cut and shading will be required. Mangroves play an important part in the water quality and biological considerations of Section 403.918 Florida Statutes. The deterioration of fallen mangrove vegetation constitutes an important part in the food chain of fish and small invertebrates. Existing trees and roots provide habitat for various birds, invertebrates, mammals, and reptiles and the water quality considerations relating to the filtering of run-off water from uplands and the assimilation of pollutants in the passing water is significant. DER was and is concerned that the proposed project does not provide reasonable or adequate assurances that water quality standards will not be violated. Turbidity, transparency, and dissolved oxygen standards may well be violated during the construction phase and the agency's concerns have not been addressed or lessened by Petitioner's unformed proposals for modification. The fourth standard, that involving biological integrity, will be a continuing and ongoing consideration due to the fact that the shading created by the house and boardwalk will be constant. After full consideration of the application and those limited matters submitted in response to the agency's expression of concern, the agency has concluded that the project will adversely impact the conservation of fish and wildlife and their habitats in the area; will adversely affect fishing and recreational values and marine productivity; will adversely effect current and relative values of functions performed in the area; and will be of a permanent nature. The agency has not, however, quantified these negative effects or demonstrated that they will be of any significant magnitude. It is difficult to conceive that in an area already violated by the encroachment of civilization as demonstrated by the unrestrained fill both to the north and to the south of Petitioner's property, that the preservation of a relatively miniscule enclave, on highly valuable waterfront property, will have any substantial beneficial effect on the overall biological, ecological, or water quality considerations of the Intra-coastal Waterway, Lake Worth, or the Atlantic Ocean. The construction disruption will be minimal and for a limited period of time. The effects of shading will be of a longer duration but would appear to be miniscule in comparison to the surrounding area. DER and its subordinate associate, the Palm Beach County Health Department, both recommend that the application be denied because of Petitioner's failure to provide reasonable assurances that the project will not violate water quality standards and will not be contrary to the public interest. The cumulative impact concerns of both DER and the Health Department are valid in theory but inappropriate here. Evidence that the recent mangrove destruction in this area has been been extensive cannot be debated. No doubt it has been. The fact remains, however, that this property is in a highly desirable location. The area has not been preserved by the State in its program for the accumulation and preservation of wetlands under a state umbrella and is of such a small size that the cumulative impact to be felt from the limited destruction of mangroves here would be minimal. There is some evidence to indicate that a permit was issued to a previous owner of this property allowing the destruction of mangrove seedlings in the western section of the community and this action has not been undertaken. This permit has not expired and is transferable to Petitioner.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of Environmental Regulation issue permit number 5008992206 to the Petitioner, Robert 8rown for the construction of the house and walkway as proposed, under the provision of adequate and firm reasonable safeguards to minimize water quality disruption during construction by Petitioner. RECOMMENDED this 11th day of February, 1987, at Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this llth day of February, 1987. COPIES FURNISHED: Dale Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Terrell K. Arline, Esquire 325-C Clematis Street West Palm Beach, FL 33401 Karen A. Brodeen, Esquire Douglas MacLaughlin, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 APPENDIX The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. By the Petitioner 1 Incorporated in Finding of Fact 1. 2. Incorporated in Findings of Fact 2 & 3. 3 & 4. Incorporated in Finding of Fact 4. Incorporated in Finding of Fact 4. Incorporated in Finding of Fact 10. 7 & 8. Incorporated in Findings of Fact 9 & 11 Incorporated in Finding of Fact 11. Incorporated in Findings of Fact 3 6 13. Accepted and incorporated in Findings of Fact 7 & 8. Accepted and incorporated in Findings of Fact 7 & 8. Not a Finding of Fact but a comment on the evidence. By the Respondent Incorporated in Finding of Fact 1. Incorporated in Finding of Fact 3. 3 & 4. Incorporated in Findings of Fact 2 & 4. 5. Incorporated in Finding of Fact 5. 6. Incorporated in Findings of Fact 3 & 6. 7. Incorporated in Finding of Fact 6. 8. Incorporated in Finding of Fact 7. 9 & 10. Incorporated in Finding of Fact 8. 11 Incorporated in Finding of Fact 13. 12. Incorporated in Finding of Fact 14. 13. Incorporated in Finding of Fact 15. 14-16. Incorporated in Finding of Fact 16. 17. Incorporated in Finding of Fact 15. 18. Incorporated in Finding of Fact 17. 19 & 20. Incorporated in Finding of Fact 11. 21-24 Incorporated in Findings of Fact 11 & 12. 25. Incorporated in Findings of Fact 17 & 18. ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION ROBERT BROWN, Petitioner, DOAH CASE NO. 85-0517 OGC FILE NO. 85-0122 vs. STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION Respondent. /
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that a dredge and fill permit be issued to Fairfield to fill 2.1 acres of wetlands and to create 2.1 acres of wetlands as mitigation, including the planting of Spartina to be maintained at an 80% survival rate for a period of five years and the provision of erosion control measures in and adjacent to Lake Avoca and St. Joseph's Sound. Respectfully submitted and entered this 14th day of February, 1986 in Tallahassee, Leon County, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of Feburary, 1986. APPENDIX The proposed findings of fact submitted by the Petitioner and the Respondent Fairfield have been accepted and/or incorporated in this Recommended, except as noted below: Petitioner page 3, 3rd full paragraph, Rejected; not supported last sentence: by competent substantial evidence. page 4, 1st paragraph: Rejected; contrary to the greater weight of the evidence. page 5, 1st full sentence: Accepted, but irrelevant and immaterial to disposition of any issue. pages 5 and 6, starting with Rejected; contrary to the 1st full paragraph: greater weight of the evidence. Respondent Fairfield page 4, 2nd full paragraph: Rejected; mere recitation of testimony and conclusions of law as opposed to factual findings. page 13, 1st paragraph: Rejected: irrelevant and immaterial. NOTE: Many of the proposed findings of fact submitted by the Petitioner and the Respondent Fairfield constitute either recitations of testimony or legal conclusions. While these have not technically been rejected by the undersigned, they are not appropriate for the findings of fact section and are discussed in the conclusions of law. COPIES FURNISHED: Victoria Techinkel Secretary Twin Towers Office Bldg. 2600 Blairstone Road Tallahassee, FL 32301 Mary f. Smallwood General Counsel Twin Towers Office Bldg. 2600 Blairstone Road Tallahassee, FL 32301 William W. Deane, Esquire Hanley and Deane, P.A. 465 Second Avenue North P. O. Box 7473 St. Petersburg, FL 33734 Julia D. Cobb Deborah Detzoff Richard Tucker 2600 Blairstone Road Tallahassee, FL 32301 Terry E. Lewis Steve Lewis Messer, Vickers, Caparello, French & Madsen P. O. Box 1876 Tallahassee, FL 32302 =============================================================== AGENCY FINAL ORDER =============================================================== STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION LEAGUE OF WOMEN VOTERS OF CLEARWATER-UPPER PINELLAS COUNTY, Petitioner, v. DOAH CASE NO. 85-2755 DDT OGC FILE NO. 85-0822 DEPARTMENT OF ENVIRONMENTAL REGULATION and FAIRFIELD COMMUNITIES, INC., Respondents. /
The Issue The issues presented for decision in this case are: whether Martin County should be granted the re-issuance of Water Use Permit No. 43-00752W for the Tropical Farms Water Treatment Plant and associated wells; and (2) whether Martin County should be granted Water Well Construction Permit No. SF032696B for the construction of Well No. 10 of the Tropical Farms Water Treatment Plant, pursuant to the permitting criteria of Chapter 373, Parts II and III, Florida Statutes; Chapters 40E-2 and 40E-3, Florida Administrative Code; and the Basis for Review for Water Use Permit Applications of the South Florida Water Management District.
Findings Of Fact Petitioner James W. Slusher, Jr., and his wife, Diane L. Slusher, own a residential lot located in unincorporated Martin County at 2376 SW Ranch Trail, Stuart, Florida 34997. On the lot is a single family home. The size of the residential lot is approximately 2.25 acres. Mr. and Mrs. Slusher purchased the subject residential lot and home in September of 1994 from Mrs. Stella Kassinger. Mrs. Kassinger and her late husband (the “original owners”) had the home built on the residential lot in approximately 1980. When the original owners built the home, they had a hole or “pit” dug in the rear portion of the lot. From aerial photographs taken at the time (1979-1980), and based upon the common practice in the area, it appears that the material from the “pit” was spread on-site to provide additional elevation for, and to minimize the potential for flooding of, the home and driveway that were constructed on the lot. Thus, the original “design function” of the “pit” was to provide fill for construction. The original owners thereafter allowed the “pit” to accumulate water and stocked it with fish so that Mr. Kassinger could use it recreationally as a fishing pond. The “design function” of the original “pit” was thus changed so that it would serve as a recreational amenity on the property. During the subsequent 14 years that the original owners lived in the home, they did nothing further to alter or improve the fishing pond. Over the years, the area immediately around the fishing pond became heavily vegetated and was used from time to time by various wild birds and animals. The fishing pond was used by the original owners for fishing and for observing the wildlife it attracted. After purchasing the home, Mr. Slusher also stocked the fishing pond with various fish over the years so that he and his family could continue to use it recreationally. The fishing pond continued to be used by the Slushers for fishing, for observing wildlife, and as a swimming area for their dogs. Currently, the overall dimensions of the fishing pond are approximately 90 feet wide, by 122 feet long, by 10 feet deep at its deepest part, when filled to the level that was natural prior to the operation of Water Well No. 10. Potable water for the Slusher home is obtained from a well drilled on the property, not from the public water system of the County. The Slusher well is located approximately 33 feet from the home. It is attached by PVC pipe to a pump located next to the home. The original owners caused the well to be drilled. The record in this case does not contain any persuasive evidence regarding the details of the Slusher residential water well. Specifically absent are such details as the depth to which the well was originally drilled, the material from which the well tube was made (i.e., cast iron or PVC), and the current physical condition of the sub-surface portions of the well. Mr. Slusher has not done anything to repair or replace the well since he and his wife purchased the home. On August 2, 2000, Mr. Slusher filed a petition with the SFWMD challenging the issuance of Water Well Construction Permit No. SF032696B, and the "use of the well." On November 3, 2000, Mr. Slusher filed an amended petition with the Division of Administrative Hearings, challenging the issuance of Water Use Permit No. 43-00752W and Water Well Construction Permit No. SF032696B. Martin County (“the County”) is a political subdivision of the State of Florida, established in 1925 pursuant to Section 7.43, Florida Statutes, and Section 1, Chapter 10180, Laws of Florida. SFWMD is an independent state agency, operating pursuant to Chapter 373, Florida Statutes. SFWMD originally issued Water Use Permit No. 43-00752W to the County on April 15, 1993. The “water use permit” was for wells and associated equipment at the Tropical Farms Water Treatment Plant (“Tropical Farms WTP”). SFWMD re-issued Water Use Permit No. 43-00752W to the County on March 14, 1996. The re-issued “water use permit” allowed additional wells to be drilled and additional draws of water by the County at the Tropical Farms WTP. One of the additional wells included in the re-issued water use permit was “Well No. 10.” SFWMD issued Water Well Construction Permit No. SF032696B to the County on March 28, 1996, allowing the construction of Well No. 10 at the Tropical Farms WTP. In accordance with the restrictions imposed by the water well construction permit, the County drilled Well No. 10 on a site located at least 100 feet in distance from the fishing pond on the Slushers’ property. The physical location of Well No. 10 is essentially “adjacent to” the Slusher property. County Well No. 10 is approximately 120 feet deep and draws water from the surficial aquifer. It commenced operation in December of 1996. It is uncontested that the operation of the well field, especially County Well No. 10, has caused drawdowns of the pond level and of the groundwater in the area of Mr. Slusher's residential water well. The MODFLOW model used by the County in support of its application indicates a maximum drawdown of 7.4 feet. The persuasive expert opinion evidence in this case indicates that maximum draw downs of 7 or 8 feet would be expected in the area of Mr. Slusher's residential water well. The County has acknowledged that the operation of Well No. 10 has had a significant effect on the drawdown of the water table in the area of the pond. County Well No. 10 appears to have been constructed in a manner consistent with the applicable rules. The well was properly drilled and grouted, the correct materials were used, and the well was constructed in a manner that did not result in harm to the water resources. The water use permit was issued prior to the well construction permit, as is appropriate. Although permitted originally in 1993 and again in 1996, the Tropical Farms WTP did not begin regular operations until June of 1997. It is now part of a consolidated system which includes four other water treatment plants, all operated by the County for the purpose of obtaining and providing potable water to the public county-wide. In support of its applications for the issuance and re-issuance of the water use permit, the County provided SFWMD with so-called “MODFLOW calculations” done by a professional engineering firm retained by the County. MODFLOW was developed by the U.S. Geologic Survey and is considered the standard for assessment of ground water resource impacts. The results of the three-dimensional MODFLOW modeling showed that the drawdown effect on the water table of the proposed wells for the Tropical Farms WTP would be unlikely to cause any adverse effect on typical wells used by homeowners, even if the latter were located within the same small “square” as one of the County’s wells. Prior to the commencement of the operation of Well No. 10 by the County, the water level in the fishing pond on the Slusher property would vary only a few inches up or down during the course of a typical year. After the County began to operate County Well No. 10, Mr. Slusher observed and videotaped much greater variations in the water level in the fishing pond on his property. After County Well No. 10 began to operate, the pond water level dropped to the extent that it would become virtually empty of water from time to time. At other times, however, the fishing pond would refill with water, such as in September of 1999, and in August of 2001. When the water in Mr. Slusher's pond gets very low, it has an adverse impact on the fish in the pond; the fish die because they have insufficient water. Mr. Slusher has not done anything over the years since the operation of County Well No. 10 began to attempt to prevent the variations in the water level of the fishing pond, or to mitigate the occurrence of such variations. The County (together with the rest of southern Florida) has experienced several periods of severe drought over the past few years. Yet other “ponds” on other properties in the same neighborhood as the Slusher property have not experienced the significant variance in water level that has occurred in the fishing pond on the Slusher property since the County began drawing water from Well No. 10. The County does not operate Well No. 10 continuously. Rather, it has attempted to reduce its use of the well. SFWMD has never issued any notice to the County that any mitigation was required on the Slusher property pursuant to the limiting conditions of the water use permit. The County does not dispute that its operation of Well No. 10 has contributed to a drawdown in the level of the water table in the surrounding area, nor that such a drawdown has contributed to the variance in the water level in the pond on the Slusher property. Indeed, the drawdown of the water table generally was fully anticipated and predicted in the materials submitted by the County to SFWMD. The use of County Well No. 10 to draw water from the surficial aquifer is not the only factor contributing to the variances in the water level of the fishing pond on the Slusher property. Evaporation and natural variances in the level of the water table also contribute to changes in the water level of the fishing pond. Bentonite is a naturally occurring clay that is mined for a variety of uses, including the “lining” or “waterproofing” of reservoirs, lagoons, ponds, ditches, and other man-made bodies of water in order to seal them and to prevent or minimize seepage or percolation of the water into the ground. Even repeated wetting and drying of the clay does not reduce its effectiveness. Bentonite is widely used and has not been found to have any harmful or toxic effects on either human beings or wildlife. In some applications, bentonite clay is a superior lining material when compared to a man-made liner, such as a plastic or polymer sheet. In a small scale application where the volume of water in a lined pond is relatively low, a man- made liner could be forced away (“balloon up”) from the bottom of the pond by the pressure of a rising natural water table. Lining the pond on the Slusher property with Bentonite (or some similar clay) would create a virtually impervious layer that would separate the water in the pond on the Slusher property from the surrounding water table. With such a lining in place, County Well No. 10 would have no significant effect on the water level of the pond. The water level in the pond on the Slusher property could also be stabilized at or near its normal level prior to the operation of County Well No. 10 by installation of a water supply that would add water to the pond whenever the pond dropped below a specified level. Mr. Slusher first complained to the County about the effect of the County’s operation of Well No. 10 in 1997, when he spoke with Jim Mercurio, a County water utilities employee. Mr. Slusher also complained at about the same time to SFWMD, which resulted in a “field investigation” in September 1997. At that time, Mr. Slusher complained about the lowering of the water level in the pond on his property, but specifically denied any adverse effect on the water from his residential water well. Mr. Slusher began to complain about the water quality and water pressure in his residential water well sometime in 2000. The water flowing from Mr. Slusher's residential water well now has an unpleasant odor, taste, and color, and the water causes rust stains. The water pressure of the water flowing from Mr. Slusher's residential water well is less than it was before the construction of County Well No. 10. The rust stains, odor, taste, and color are all due to iron oxidation of the water drawn from the well on the Slusher property. The County regularly experiences similar problems with iron oxidation in the water that it draws from its own wells in the same area as the Slusher property, which the County must treat at the Tropical Farms WTP. The problem of iron oxidation (and accompanying odor and taste deficiencies) in the water is thus not unique to the water drawn from the well on the Slusher property. Iron oxidation in well water is not harmful to human beings. The evidence in this case does not include any evidence of any testing of the water quality of the water coming from the Slusher residential well. Similarly, there is no persuasive evidence as to the current condition of the sub- surface portions of the Slusher residential well. Further, the evidence regarding the cause of any deterioration of the water quality and/or the water pressure of the Slusher residential water well is both anecdotal and speculative, and is not a persuasive basis for determining the cause of any deterioration of the water quality and/or water pressure of the subject residential well. Specifically, the evidence is insufficient to establish that the water quality and water pressure deterioration complained of by Mr. Slusher are a result of the operation of County Well No. 10. Such deterioration could be caused by other circumstances or conditions, including the uninspected sub-surface condition of Slusher's residential water well. The water quality and water pressure problems currently experienced by Mr. Slusher could be minimized or eliminated by connecting his residence to the residential water supply system operated by the County. A branch of the County's public water system already exists in Mr. Slusher's neighborhood within a few hundred feet of his property. The application and information provided to SFWMD by the County were determined by SFWMD to provide “reasonable assurances” that existing legal users would not be adversely affected by the proposed wells or water treatment facility.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby recommended that the Governing Board of the South Florida Water Management District enter a final order issuing Water Well Construction Permit No. SF032696B and re- issuing Water Use Permit No. 43-00752W to Martin County, subject to the general and special conditions set forth therein. DONE AND ENTERED this 31st day of May, 2002, in Tallahassee, Leon County, Florida. MICHAEL M. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of May, 2002. COPIES FURNISHED: Howard K. Heims, Esquire Virginia P. Sherlock, Esquire Littman, Sherlock & Heims, P.A. 618 East Ocean Boulevard, Suite 5 Post Office Box 1197 Stuart, Florida 34995-1197 Douglas H. MacLaughlin, Esquire South Florida Water Management District 3301 Gun Club Road Post Office Box 24680 West Palm Beach, Florida 33416-4680 David A. Acton, Esquire Senior Assistant County Attorney Martin County Administrative Center 2401 Southeast Monterey Road Stuart, Florida 34996-3397 Frank R. Finch, Executive Director South Florida Water Management District Post Office Box 24680 West Palm Beach, Florida 33416-4680
Findings Of Fact Harold Click and Harold Peterson, Petitioners, are sole owners of property which borders Dunn's Creek, one of the largest tributaries to the St. John's River in Putnam County, and which is described as Lots 80, 88, and 89, Section 38, Township 11 South, Range 27 East. Dunn's Creek is a Class III water body of the state. Petitioners applied for a dredge and fill permit initially in 1980 but Respondent issued an Intent to Deny in January, 1981. A second permit application was submitted in 1982 on behalf of Petitioners following a site visit by representatives of Respondent in June, 1981, but again an Intent to Deny was issued in September, 1982. A third application was submitted on or about May 3, 1984, following another site visit by Respondent's representatives, but the Intent to Deny which resulted in this hearing was issued on December 5, 1984. During these site visits, Respondent's representatives offered suggestions about what might be an acceptable project but gave no assurances that the application, as submitted on May 3, 1984, would be permitted. The project which Petitioners now propose would include the placement of pilings and other fill materials within the waters and landward extent of the waters of the state which would result in the alteration of at least 10,000 square feet of the swamp floodplain community of Dunn's Creek. This proposed filling will degrade the water quality of the areas affected by replacing periodically inundated wetlands with uplands. Although the project also includes construction of a fill road with a bridge over a natural slough on Click's lot, Respondent's expert witness Tyler testified that this portion of the project alone would not have resulted in the Intent to Deny. According to Tyler, the key area of objection was the .23 acres Petitioners proposed to fill which was within Respondent's jurisdiction and which would have widened an already existing berm. This widening would have allowed the placement of two septic tanks and two, dwellings on pilings on the property and an access driveway through Click's portion of the property to Peterson's. As proposed, fill was to be placed over a total of .35 acres, with .23 acres being in the waters of the state or to the landward extent of waters of the state. Bald cypress trees or other species listed in Rule 17-4.02(17), Florida Administrative Code, are present in part of the wetland area occupied by the project site in greater numbers, biomass, and aerial extent than competing plant species or communities. Without appropriate pollution control measures, the proposed project could reasonably be expected to result in an adverse change in the biological integrity, bacteriological quality, biochemical oxygen demand and the concentration of dissolved oxygen, turbidity and nutrients in some of the waters on the project site, in Dunn's Creek, and in discharge areas elsewhere. The filling associated with the project can be expected to have a long- term detrimental impact on water quality and biological resources, according to Respondent's expert witness Deuerling. Natural habitats and rainwater storage areas would be destroyed or detrimentally altered, as would the natural filtration function performed by the swamp areas to be filled. In the immediate vicinity of Petitioners' lots, Respondent has denied two dredge and fill permits and there are an additional two permit applications which are pending. Deuerling has also performed site visits at three other locations along Dunn's Creek in the immediate vicinity of Petitioners' lots, and it can be expected that other permit applications for similar projects will be submitted if Petitioners are granted a permit.
Recommendation Based upon the foregoing it is recommended that Respondent enter a Final Order denying Petitioners' application for a permit. DONE and ENTERED this 5th day of September, 1985, at Tallahassee, Florida. DONALD D. CONN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1985. COPIES FURNISHED: Peter B. Heebner, Esquire 523 North Halifax Avenue Daytona Beach, Florida 32018 Ross S. Burnaman Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301