Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES vs. ROBERT E. KLEIN AND CONVALESCENT MANAGEMENT, 83-001519 (1983)
Division of Administrative Hearings, Florida Number: 83-001519 Latest Update: Oct. 28, 1983

Findings Of Fact Certificate of Need No. 1645 was issued to Respondent on July 27, 1981, for construction of a 120-bed nursing home at a cost of $1,830,000 in the city of Safety Harbor, Pinellas County, Florida. Termination date of the certificate was originally July 25, 1982, but was subsequently extended for a period of six months at the request of Respondent. The expiration date of the certificate, as extended, was January 25, 1983. At the time the six-month extension was granted, Petitioner advised Respondent that the project was required to be ". . . under physical and continuous construction prior to the new termination date to have a valid and continuing Certificate of Need." Subsequent to the issuance of the certificate, Respondent retained and engaged personnel and organizations to assist in pursuing the project. The architectural firm of Wilson and Associates ("the architect") was engaged in August of 1981. Additionally, Respondent engaged the Kissell Company to secure financing, and the Hermanson Construction Company ("Hermanson") as the general contractor for the project. Respondent obtained preliminary approval of its site plan for the project from the City of Safety Harbor ("the City"). Additionally, the City created a zoning ordinance specifically for the project to permit a health care facility to be constructed at the proposed site. On September 21, 1981, the architect met with representatives of the HRS Office of Licensure and Certification, Jacksonville, Florida, to submit and review schematic plans for the project. HRS gave preliminary approval to the schematic plans on that same date. The HRS plan review process consists of three stages. The first stage consists of the submission of schematic plans; the second stage is the submission of preliminary plans; and, the third stage consists of submission of construction documents together with the required fee for final plan review. On November 13, 1981, the architect submitted additional schematics to HRS to complete the first stage of the plan submission process. In addition, the architect provided additional information previously requested by HRS on that same date. On December 14, 1981, the architect submitted the second stage documents to HRS. The HRS Office of Licensure and Certification, however, never responded to or commented on the submissions made by the architect in November and December of 1981. In early January, 1982, Respondent closed the purchase of the project site in Safety Harbor. Respondent paid a total of $165,000 for the site. In April, 1982, Respondent met with representatives of the City to discuss the issuance of industrial revenue bonds by the City to finance the project. Further, on April 19, 1982, Respondent purchased a corporate office in Safety Harbor at a cost of $80,000. After meetings between representatives of the City and Respondent, the City agreed to consider the issuance of industrial revenue bonds. Respondent paid $10,000 to the City in June, 1982, to offset any costs that the City would incur in considering the bond issue proposal. In addition, Respondent paid $4,000 to the City to resolve a dispute between the City and the previous owner of the property on which the project was to be located. On June 1, 1982, Respondent entered into a construction contract with Hermanson to construct the proposed nursing home project. A copy of the contract was furnished to the HRS Office of Community Medical Facilities. In August of 1982 Hermanson commenced its activities under the contract. These activities included obtaining proposals from subcontractors for materials and services to be used in the project, and hiring engineers to survey the site, conduct soil borings, and to conduct a tree survey required by local governmental authorities. Respondent secured financing for the project in September, 1982. On September 20, 1982, the City passed a Resolution of Inducement agreeing to issue revenue bonds to finance acquisition, construction, equipping, and furnishing the project. On September 20, 1982, Respondent and the City also entered into a Memorandum of Agreement regarding issuance of revenue bonds. In the latter part of 1982, Respondent was required to obtain approval of the project from numerous other local governmental entities. Specifically, Respondent obtained approval of the Site Development Plan and an amendment to the Land Use Plan from the City's Planning and Zoning Board, the City Commission, and Pinellas County. As part of the Site Development Plan approval, the City required Respondent to agree to make a number of offsite improvements, including the dedication of a 25-foot right-of-way, the paving of an adjacent roadway at Respondent's expense, and the construction of sidewalks. Respondent agreed to the conditions and the City and Pinellas County approved the Site Development Plan and the amendment to the Land Use Plan. Because of the City's requirement that Respondent dedicate a 25-foot right-of-way, Respondent was required to obtain a setback variance from the City because the proposed building location did not meet the City's property line setback limitations. On November 5, 1982, the architect submitted the third stage construction documents and plan review fees to HRS to complete the plan review process. On that same date, the architect spoke with representatives of the HRS Office of Licensure and Certification about obtaining HRS permission for an early construction start on the foundation work for the project. The architect was advised that an early start could not be granted until the third stage submissions had been reviewed. Throughout 1982, Respondent made numerous submissions to the Federal Housing Authority (FHA) and the Department of Housing and Urban Development (HUD) to obtain an FHA commitment to insure project financing. On November 26, 1982, Respondent obtained a conditional commitment from HUD for that purpose. Subsequently, on January 21, 1983, Respondent obtained FHA approval for an early start of project construction. The early start permitted construction costs to be covered by the insurance guarantee, prior to the issuance of the firm commitment. On January 25, 1983, Respondent obtained a firm commitment from HUD to insure project financing. The firm commitment insured both the construction and permanent financing. The FHA and HUD commitments and guarantees were still valid and effective at the time of final hearing in this cause, although a month-to-month extension had to be obtained by Respondent. Prior to January 25, 1983, Respondent had also obtained the following permits or approvals: an exemption from the Florida Department of Environmental Regulation from stormwater discharge permitting requirements; water and sewer service availability from the City; a City occupational license; a building permit from the City; a tree removal permit from Pinellas County; and business licenses from both the City and Pinellas County. Prior to January 25, 1983, the following work had been performed on the project site: a construction trailer was placed on the site; a fence removed and utilities, with the exception of water, were installed; a large lake and related storm sewer system had been relocated on the site; a survey had been performed and the site cleared and trees removed; the site was cut to subgrade and a pad prepared for the building foundation; and the building site had been roughed out and finished floor elevations had been set. As a result, the site is now ready for the placement of footers and foundations. Although the footers and foundation work have not been constructed, the record in this cause establishes that they could be in place within two weeks from the time approval is given for such work. At the time of final hearing in this cause, HRS had not given its approval for construction of the building foundation. Approximately $130,000 has been spent by Respondent on construction work at the site, which includes money paid to subcontractors for work and services provided. When contacted by the architect on January 24, 1983, one day prior to the expiration date of the certificate, the HRS Office of Licensure and Certification advised the architect that the third stage plan review process was at that time only 60 to 75 percent complete. On February 8, 1983, the HRS Office of Licensure and Certification first responded to Respondent's third stage construction documents which had been submitted by the architect on November 5, 1982. HRS advised the architect that it could not approve the project plans and submitted a number of comments and revisions to be incorporated into the plans. On February 17, 1983, the architect submitted the changes and corrections to HRS to comply with the February 8, 1983, HRS letter. On or about February 17, 1983, the architect again spoke with HRS representatives about obtaining permission for an early construction start but, again, permission was not granted. In the first week of March, 1983, Respondent contacted HRS to inquire about the status of his certificate. Respondent was concerned that HRS had not responded to his letter of January 14, 1983, in which he advised HRS that the project was under construction. HRS representatives advised Respondent in the first week of March, 1983, that an investigation of the matter would be made and that HRS would respond at a later date. In late March, 1983, after having received no notification from HRS, Respondent again contacted HRS representatives about the status of the certificate, and was advised that the certificate was considered to be null and void. Subsequently, on April 5, 1983, HRS sent a letter to Respondent advising him that the certificate was null and void since ". . . the project was not under physical continuous construction beyond site preparation by January 25, 1983." Effective June 5, 1979, HRS promulgated Rule 10-5.02(21), Florida Administrative Code, which defined the term "construction" to mean: . . . the commencement of and continuous activities beyond site preparation normally associated with erecting, altering or modifying a health care facility pursuant to construction plans and specifications approved by the department (Emphasis added.) That rule was challenged and ultimately invalidated by a DOAH Hearing Officer by Final Order entered April 18, 1980. The order of the Hearing Officer was subsequently upheld by the First District Court of Appeal in Westchester General Hospital v. State of Florida, Department of Health and Rehabilitative Services, 417 So.2d 261 (Fla. 1st DCA 1982). As a result, on January 25, 1983, the date of expiration of the Certificate of Need at issue in this proceeding, HRS had no "rule" that defined the terms "construction" or "commencement of construction." It is, however, clear from the record in this proceeding that the definition of "construction" contained in the invalidated rule is more restrictive than that generally utilized in the construction industry. In fact, the record in this cause establishes that "construction," as that term is used in the industry, "commences with the execution of a construction contract. Other factors indicative of "commencement of construction" would include the ordering of building materials, the solicitation and signing of contracts with subcontractors, the acquisition of required permits from various governmental entities, the preparation of drawings associated with the project, and the like. All of these activities necessarily precede "site preparation" and the pouring of footers and foundations and the placement of steel. It is undisputed that Respondent had not placed any concrete, steel, or footings on the project site prior to January 25, 1983. However, it is equally clear that those activities outlined above which Respondent had, in fact, accomplished prior to January 25, 1983, conformed to the definition of "commencement of construction" generally accepted by professionals in the construction industry. Conversely, there is no competent or persuasive evidence of record to "elucidate," "explicate," or otherwise support the purported HRS policy of requiring the placement of foundations, footings, concrete, or steel on the job site prior to the expiration date of a certificate of need. Neither is there any evidence of record in this cause to establish that HRS at any time advised Respondent of its policy requiring the placement of footers, foundations, or steel in order to comply with HRS's purported policy.

Florida Laws (1) 120.57
# 1
JAMES P. MORAN, INC. vs DEPARTMENT OF GENERAL SERVICES, 89-006940BID (1989)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Dec. 19, 1989 Number: 89-006940BID Latest Update: Mar. 02, 1990

Findings Of Fact The Department of General Services, (hereinafter "DGS") is a state agency, the responsibilities of which include the management of state construction project. It accomplishes such management through its Division of Building Construction. The Divisions responsibilities include, negotiation of architect/engineer contracts, review of plans and specifications, contract administration, and contract management. One such project is Project No. MA-87080010, the subject matter of which involves repairs and alterations to the National Guard Armory in Fort Lauderdale, Florida, hereinafter referred to as the Armory Project. Certain portions of the bid specification for the Armory Project were prepared by the project architect, Mr. William D. Tschumy, Jr. Other portions, specifically the portions dealing with bidding conditions and contractual conditions, were provisions provided by DGS for inclusion in the specifications. The project architect was not familiar with all of the bid specification provisions provided by DGS. Prior to submitting its bid on the Armory Project, James P. Moran, Inc., had been prequalified for bidding on the project. Such prequalification did not obviate the need for James P. Moran, Inc., to meet the experience requirements in the bid specifications and in Rule 13D-11.904(2)(a)(8), Florida Administrative Code. The bid specifications for the Armory Project include the following provisions: 1/ Section B-2, page 9: 8. Firm experience - must have successfully completed no less than two project of similar size and complexity within the last three years. and; Section B-22, page 16: The owner reserves the right to reject any and all bids when such rejection is in the best interest of the State of Florida and to reject the proposal of a bidder who the owner determines is not in a position to perform the contract and to negotiate the contract in accordance with its Rule 13- D11.08 if the low qualified bid exceeds the project construction budget. James P. Moran, Inc., timely submitted its bid on the Armory Project and was subsequently notified that it had been recommended for contract award by the Director of the Division of Building Construction. This recommendation was made on the basis of a recommendation by the project architect that the bid be awarded to James P. Moran, Inc. At the time of making his recommendation, the project architect was not aware of the firm experience provision in either the bid specifications or the applicable rules. A timely protest was filed by another bidder on the Armory Project, in which the protesting bidder raised the issue of the firm experience of James P. Moran Inc. DGS concluded that the protest was valid and after further deliberation made the determination to reject all bids. All the bids other than the bid submitted by James P. Moran, Inc., exceeded the funds available for construction of the Armory Project. Because the other bids all exceeded the available funds, DGS decided that the best course of action would be to modify the scope and nature of the work involved in the project and then re-bid the project. It is reasonable to expect that the proposed modifications to the project will result in lower bids, because the modifications would permit the work to be done quicker and at less cost to the contractor. James P. Moran, Inc., was incorporated in 1981. However, prior to the summer of 1988, it had submitted no bids acquired no permits, and had neither started nor completed any jobs. The qualifying contractor for James P. Moran, Inc., is Mr. James P. Moran who, for many years prior to the summer of 1988, was an employee, officer, and shareholder of Frank J. Moran, Inc. Mr. James P. Moran holds a State of Florida building contractors license, a State of Florida electrical contractors license, a Dade County electrical masters license, a Broward County electrical masters license, and a State of Maine electrical contractors license. While employed by Frank J. Moran, Inc., Mr. James P. Moran was also the qualifying contractor for that corporation. While so employed, Mr. James P. Moran's primary duties were those of project director and estimator. He was also a corporate officer of Frank J. Moran, Inc. During his employment with Frank J. Moran, Inc., Mr. James P. Moran was the project manager on projects of similar size and complexity to the Armory Project. The construction budget for the Armory Project is approximately 250,000. The dollar values of construction jobs are valid indicators of the comparative sizes of construction jobs. The dollar values of the two largest construction jobs completed by James P. Moran, Inc., are approximately $161,000 and $112,000, respectively. The two largest construction jobs completed by James P. Moran, Inc., are not of similar size to the Armory Project. While DGS is concerned about the qualifications of the personnel employed by a contracting firm, DGS is also concerned about the track record of the firm itself, and, therefore, requires that a firm have completed projects in its own name in order to qualify for a bid award. In other words, a new firm cannot "take credit" for work performed by one of its employees at a time when the employee was working for another firm. Also, DGS does not allow "stacking" of the dollar value of several small jobs in order to demonstrate completion of a job of similar size to the job that is the subject of a bid. The purpose of the experience rule is to require a contracting firm to have completed at least two jobs of similar dollar size to the dollar size of the job being contracted. Among, the reasons stacking is not allowed is that completion of a job of any given size is a more complicated and complex undertaking than completion of a series of smaller jobs that total up to the same dollar value as the job of given size. DGS has now modified the scope of the project and has amended the plans and specifications in such a fashion that it will take less time to complete the modified Armory project and may reasonably be expected to result in lower bids closer to or below the construction budget. The modified Armory project may reasonably be expected to result in a savings of both time and money.

Recommendation For all of the foregoing reasons it is RECOMMENDED that the Department of General Services issue a final order in this case rejecting the bid of James P. Moran, Inc., as being non-responsive, and rejecting all other bids, in order to modify the scope of the project and rebid it. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 2nd day of March 1990. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 1990.

Florida Laws (2) 120.53255.29
# 2
ROGER E. NEWBOLD vs. ALLEN ELECTRIC CO., 77-001207 (1977)
Division of Administrative Hearings, Florida Number: 77-001207 Latest Update: Oct. 05, 1977

Findings Of Fact Roger Newbold was employed by Allen Electric Company, Inc., as a laborer working on its contract with the State. Newbold was employed during two different periods. The first time was prior to January 1, 1977, and the second, from March 13, 1977, to May 22, 1977. The addition to the Polk County Correctional Institution was bid in two phases; the first for heavy construction for site preparation, and the second, the actual building construction. Allen Electric Company, - Inc., had a contract from the general contractor during the first phase to install the main electrical distribution facilities on the site. All of this work was not associated with and carried on prior to the commencement of building construction. The heavy construction was in progress during Newbold's first period of employment with Allen Electric Company, Inc. Allen Electric Company was also a subcontractor with Delta Electric Company on the second phase of construction; however, Allen Electric Company did not do any building construction. They subcontracted with Delta to install secondary distribution lines and perimeter fence lighting on the site. See Delta Electric Company contract, late filed exhibit No. 7. Allen Electric Company did not go into the building with their workmen because their contract called for them to stop five (5) feet outside the building with the secondary distribution lines. All work and wiring done from this point into the building was carried on by Delta Electric. Newbold's job during his entire employment with Allen electric was to dig ditches and lay conduit. The conduit runs then were reinforced with concrete poured over reinforcing steel. During his entire employment, he was involved in digging the necessary ditches, setting the reinforcing rods, and pouring the concrete. The rate for heavy construction laborers under wage rate 398-W filed as a portion of late filed exhibit No. 7 was three dollars and thirty-six cents ($3.36) per hour. The wage rate for laborers working on building construction pursuant to wage rate 397-W also filed as a portion of late filed exhibit No. 7 was six dollars and fifteen cents ($6.15) per hour. Wage scale 397-W specifically states that it is applicable to nonresident building construction. All of the skills listed on the wage rate apply specifically to building construction except the general term "laborer." The record shows that the work done by Allen Electric Company, Inc., in the building construction phase was the same type of work undertaken by Allen Electric in the heavy construction phase. In both phases, Newbold was engaged in exactly the same duties. Newbold did not work on building construction but on laying conduit for secondary distribution systems and perimeter lighting systems during the second phase. All of this work took place outside of the building.

Recommendation The Hearing Officer recommends that the claim of Roger Newbold be dismissed by the agency. DONE and ENTERED this 5th day of 1977, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Marvin Woods, Esquire 440 S. Florida Avenue Post Office Box AR Lakeland, Florida 33801 David A. Perry, Esquire Corporate Officer Allen Electric Company, Inc. 1271 LaQuinta Drive Orlando, Florida 32809 Mr. Luther J. Moore Administrator of Prevailing Wage Department of Commerce Division of Labor 1321 Executive Center Drive Fast Tallahassee, Florida 32301

# 3
RICHARD T. EATON vs. CONSTRUCTION INDUSTRY LICENSING BOARD, 89-001233 (1989)
Division of Administrative Hearings, Florida Number: 89-001233 Latest Update: Jan. 09, 1990

Findings Of Fact Based upon my observation of the witnesses, their demeanor while testifying, the documentary evidence received and the entire record compiled herein, I make the following findings of fact: In order for Petitioner to obtain a license as a building contractor in Florida, he is required to successfully complete a certification examination. The examination is prepared by the ACSI National Assessment Institute arid administered by the Department of Professional Regulation (DPR). The questions on the exam are prepared from specific reference materials disclosed to the applicants, generally accepted industry procedures and standard field knowledge. Petitioner took the building contractor's examination administered by DPR in October, 1988. There were four parts to the examination. No evidence was submitted as to the scores an applicant was required to achieve and/or the number of sections an applicant was required to pass in order to be entitled to licensure. Petitioner did not receive a score on the exam sufficient to entitle him to licensure. However, no evidence was presented as to the grades Petitioner received on the various parts of his exam. Petitioner initially challenged seven of the questions on the Construction Administration part of the exam contending that they were unclear and ambiguous, and that, in any event, he correctly indicated the "closest" answer included for the multiple choice questions. However, for the reasons set forth in the Preliminary Statement above, only two of those questions (CA #19 and CA #24) are at issue in this proceeding. No evidence was of feared as to the value of each of the challenged questions and/or the number of questions Petitioner would have to succeed in challenging in order to obtain a passing grade. The first question challenged by Petitioner, CA# 19 required the exam taker to determine the latest time that a subcontractor could effectively serve a Notice To Owner under the Mechanic's Lien Law. The reference materials provide that the Notice To Owner must be served on the owner within 45 days from the time the lienor first performs labor or delivers material to the site. The reference materials also specifically provide that receipt of the notice on the 46th day is timely where the 45th day is a Sunday. A calendar was provided with the exam materials. The 45th day in question CA #19 fell on a Sunday (September 11). Therefore, the latest day that the Notice To Owner could be served was September 12. Both September 11 and 12 were listed as answers on the exam. Petitioner selected the answer corresponding to September 11. The correct answer was September 12. Petitioner's challenge to question 19 is without merit. Question CA #24 relates to AIA Document A201 and asks the examine taker to draw an analogy between a sub-contractor's responsibilities and obligations to the contractor as being the same as one of four listed choices. According to the Respondent, the correct answer 5 (C) which states that the sub-contractor has the same responsibilities and obligations to the contractor as the contractor has to the architect and owner. Petitioner chose answer (A) which indicates the contractor has the same responsibilities and obligations to the contractor as the architect has to the owner. In support of its position, the Respondent cites paragraph 5.3.1 of AIA Document A201 which states that "by appropriate agreement, ... the Contractor shall require each Sub-contractor, to the extent of the work to be performed by the Sub-contractor, to be bound to the Contractor by terms of the Contract Documents, and to assume towards the contractor all the obligations and responsibilities which the contractor by these documents assumes towards the Owner and Architect." Petitioner interpreted the question as asking the exam taker to draw an analogy between the relationship created by the sub-contract with the other relationships listed in the various answers. Viewed in this context, Petitioner reasoned that, while a contractual relationship existed between the sub- contractor and the contractor, AIA Document A201 specifically does not create a contractual relationship between the contractor and the architect. Therefore, he eliminated answer C and instead chose answer A because there clearly is a contractual relationship between the architect and the owner. Because the question was structured in the form of an analogy, it is misleading and ambiguous and Petitioner's interpretation was reasonable. Unfortunately, while the question was drafted to test the exam taker's familiarity with paragraph 5.3.1, it could also be read to be asking an exam taker to distinguish between the various relationships created through the contract documents. Significantly, the question does not specifically track the language of paragraph 5.3.1 which indicates that the sub-contractor must "assume" all the obligations and responsibilities which the contractor "assumes" towards the Owner and Architect. Therefore, the question is misleading and Petitioner's answer was reasonable under the circumstances.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Petitioner's request that his October, 1988 examination for building contractor's license be regraded be GRANTED and that Petitioner be deemed to have correctly answered question CA #24. DONE AND ENTERED this 9th day of January, 1990, in Tallahassee, Leon County, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 1990. APPENDIX Both parties have submitted Proposed Recommended Orders. The Petitioner's Proposed Recommended Order contains a number of paragraphs of mixed findings of fact and conclusions of law which have not been numbered throughout. To the extent that the proposed findings of fact can be isolated, they are addressed below. The Petitioner's Proposed Findings of Fact The first two and a half pages of Petitioner's Memorandum simply sets forth question CA #24, the "correct" answer as determined by Respondent and Petitioner's answer. These facts are incorporated in Findings of Fact 8. The Remainder of Petitioner's Memorandum is deemed by the undersigned to constitute legal argument. The Respondent's Proposed Finding of Fact Proposed Finding Paragraph Number in the Finding of Fact of Fact Number in the Recommended Order Where Accepted or Reason for Rejection Adopted in substance in Findings of Fact 4. Incorporated in the Preliminary Statement. Also adopted in substance in Findings of Fact 5. Incorporated in the Preliminary Statement. Also adopted in substance in Findings of Fact 5. Incorporated in the Preliminary Statement. Also adopted in substance in Findings of Fact 5. Incorporated in the Preliminary Statement. Also adopted in substance in Findings of Fact 5. Incorporated in the Preliminary Statement. Also adopted in substance in Findings of Fact 5. The first sentence is incorporated in the Preliminary Statement. The second sentence is subordinate to Findings of Fact 7 and 8. Incorporated in the Preliminary Statement. Subordinate to Findings of Fact 7. Subordinate to Findings of Fact 8. COPIES FURNISHED: Kenneth D. Easley, General Counsel Department of Professional Regulation 1940 North Monroe Street, Ste 60 Tallahassee, FL 32399-0792 E. Harper Field Deputy General Counsel Department of Professional Regulation Northwood Centre, Suite 60 1940 North Monroe Street Tallahassee, FL 32399-0792 Curtis A. Littman, Esquire Littman, Littman, Williams & Strike P. O. Box 1197 Stuart, Florida 34995 Fred Seely, Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Richard Eaton 2601 S. D. Miami Street Stuart, Florida 34997

Florida Laws (2) 120.57489.111
# 4
ROBERT J. UEBELACKER vs CONSTRUCTION INDUSTRY LICENSING BOARD, 90-007211 (1990)
Division of Administrative Hearings, Florida Filed:Punta Gorda, Florida Nov. 14, 1990 Number: 90-007211 Latest Update: Apr. 19, 1991

The Issue Whether Petitioner should be granted additional credit for one or more examination questions answered by him during the June 1990 Certified Building Contractor Examination.

Findings Of Fact Petitioner sat for reexamination at the June 1990 certified building contractor examination. On Part II, he received a score of 74.0. A minimum passing score is 69.01. On Part III, he received a score of 67.00. Minimum passing score is 69.01. Petitioner had previously passed Part I of the exam. Petitioner initially challenged question numbers 4, 10 and 17. The National Assessment Institute prepares licensure examinations for building contractors in the State of Florida under authority of the Office of Examination Services, Department of Professional Regulation. The Institute prepared question numbers 4, 10 & 17 for the certified building contractor examination administered on June 26 and 27, 1990. As to question number 4, the only correct response to the question was answer "B". Petitioner's answer to the question was "D", which was not acceptable. As to question number 10, the correct response was answer "C". Petitioner's answer "B", was not acceptable. As to question number 17, the correct response was answer "C". Petitioner's answer "A" was not acceptable. The Department's determination that answers "B", "C" and "C" were the only appropriate answers was not arbitrary and unreasonable.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the challenge by Petitioner that he be awarded a passing grade for Part III of the June 1990 certified building contractors examination be DENIED. DONE AND ENTERED this 19th day of April, 1991, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of April, 1991. COPIES FURNISHED: Robert J. Uebelacker 326 NW Catherine Avenue Port Charlotte, FL 33952 Vytas J. Urba, Esquire Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Jack McRay, Esquire General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.111
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN B. ROBERTS, 82-002414 (1982)
Division of Administrative Hearings, Florida Number: 82-002414 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent is a certified building contractor having been issued license number CB CA03134. At times material herein, the Respondent was the qualifier for and conducted his contracting business through the entity doing business as A-1 Builders, Inc. On June 29, 1981, A-1 Builders, Inc., entered into a contract with Albert E. and Helen E. Chaloux to construct a residence in Sebastian, Florida, for the sum of $53,158.00 (Petitioner's Exhibit 5). The Chalouxs paid the Respondent a $4,000.00 deposit to commence construction (Petitioner's Exhibit 6 and TR pages 8-9). Respondent did not commence construction of the Chaloux residence nor did he return any portion of the tendered $4,000.00 deposit. On February 24, 1981, A-1 Builders, Inc., entered into a contract with Jeffrey and Linda Ferris to construct a residence in Sebastian, Florida, for the sum of $32,849.00 (Petitioner's Exhibit 1). Respondent completed the Ferris residence during July 1981 and A-1 Builders, Inc., through the person of the Respondent, received full payment at the closing (Petitioner's Exhibit 2). At closing, Respondent transmitted a warranty deed to the Ferrises stating that the property was being delivered to them without any encumbrances (Petitioner's Exhibit 3). At the time of closing, Respondent, through the qualifying entity A-1 Builders, Inc., owed several suppliers and contractors monies for material and services which were furnished for the completion of the Ferris residence and remained unpaid. Specifically, Respondent owed the following suppliers and subcontractors monies: Colkitt Sheet Metal and Air Conditioning, Inc. - $1,500.00 (Petitioner's Exhibits 10-11); Russell Concrete, Inc. - $421.20; and White Drywall - $1,634.00 (Petitioner's Exhibit 7). RESPONDENT'S POSITION Respondent acknowledged that he received a $4,000.00 deposit from the Chalouxs and that he did not commence construction as agreed. However, Respondent urges that A-1 Builders underwent financial difficulties based upon unwarranted newspaper accounts and malicious prosecution by the local State Attorney's office and the Petitioner's investigator which forced him near bankruptcy. Respondent did spend some money toward the initial phases of commencing construction for the Chalouxs which consisted primarily of he payment of monies toward the filing of an application fee for the Chalouxs to obtain financing, the preparation of plans and drawings and some unspecified costs respecting the site preparation for the Chaloux residence. Respecting the allegation that Respondent falsely indicated that there were no encumbrances on the Ferris residence, Respondent's only position is that he was forced to foreclose on certain homes and that the various liens and claims of liens which have been filed by the above-referenced suppliers and subcontractors are being paid as monies are received from the foreclosures.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby, RECOMMENDED that the Respondent's certified building contractors' license number CB CA03134 be REVOKED. DONE AND ENTERED this 12th day of April 1984 in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of April 1984.

Florida Laws (3) 120.57455.227489.129
# 6
JORGE L. GARCIA vs. BOARD OF ARCHITECTURE, 86-002195 (1986)
Division of Administrative Hearings, Florida Number: 86-002195 Latest Update: Jun. 12, 1987

Findings Of Fact Petitioner, Jorge L. Garcia, is an applicant for licensure by examination to practice architecture in the State of Florida. The architecture examination in the State of Florida is of seven parts, part of which is the written examination and the rest of which is a site and design examination, which is given in June of each year. Petitioner took the building design portion of the Architecture Registration Examination in June, 1985. This portion of the examination consists of a 12-hour sketch problem involving building design considerations. The examination is administered by the Office of Examination Services of the Department of Professional Regulation, and is supplied to the State of Florida as well as to all of the jurisdictions of the United States by the National Council of Architectural Registration Boards (NCARB). The examination itself involves the design of a structure by an applicant which meets specific requirements for placing the structure on the site, elevations, building cross- sections, facades, and floor plans. The program for the 1985 examination called for the design of a city administration building. Information supplied to the applicant includes a pre-examination booklet setting forth the architectural program to be accomplished and the various requirements to which the applicant is expected to apply himself in order to receive a passing grade. Applicants also may study a series of solutions proposed by previous successful and unsuccessful applicants so that they may anticipate and apply successful solutions when taking their own examination. At the time of the examination itself, other information is supplied to the applicant to enable him to more adequately design the structure requested and perform the necessary technical architectural requirements. In general, the purpose of the examination is to require the applicant to put together a building design solution in response to a program submitted to him by NCARB. This portion of the examination therefore, allows the national testing service grading the examination, and through it, the Florida Board of Architecture, to determine whether the applicant is able to coordinate the various structural, design, technical, aesthetic, energy, and legal requirements. The grading of the building design problem is accomplished by the review of the applicant's proposed examination solution by at least three architects selected by the various architectural registration boards of some 20 states who are then given training by NCARB to standardize their conceptions of the minimal competency required for a passing grade. Each architecture grader is then asked to review various solutions by applicants on a blind grading basis. That is, the grader has no knowledge of the name or state of origin of the applicant whose examination solution he is grading. The grader is instructed to take into consideration various criteria as set forth in Rule - 21B-14.03, Florida Administrative Code. Graders are instructed to make notations or areas of strength and of weakness on the grading criteria and then to determine, based upon an overall conception of each applicant's submission, whether or not a passing grade of 3 or 4 as set forth in Rule 21B-14.04, Florida Administrative Code, has been earned. A method used to ensure independent and confidential grading of a solution is the folding of a single score sheet in such a way as to not allow subsequent graders to see the previous score. Approximately 3 and one-half minutes is utilized as the time in which each grader has to grade each applicant's exam. Page 7 of the Juror's Manual (graders manual) points out: Examinees are entitled to make some mistakes. The program analysis, design , development and drafting are hurriedly executed in a tense situation, without recourse to normal office reference materials (Sweets catalogs Architectural Graphic Standards, etc.) and without customary time for deliberation and critique by others. Jurors (graders) are permitted to recommend changes to an applicant's submission to bring it up to passing. In order for an applicant to pass, he must receive at least two passing grades from the at least three architects who independently grade the applicant's submission. In the instant case, the Petitioner received three 2's (which are failing grades) and one 3 (which is a passing grade). Petitioner's exam solution presented a borderline case since one of the three graders who originally graded his exam gave him a passing grade. His response to notification of failure to pass this portion of the exam was a timely request for a Section 120.57(1) hearing and this proceeding ensued. While Petitioner attempted to comply with the instructions as set forth in the examination and pre-examination booklets, it is clear that in several material areas he failed to achieve requisite minimal competency necessary to receive a passing score on the examination. The testimony of Arnold Butt, Registered Architect, former chairman of the Department of Architecture at the University of Florida and a master grader in the building design examination, is the only expert testimony of record. In Butt's opinion, Petitioner's submission contained several material departures from specific program requirements applicable to the 1985 examination. Specifically, Petitioner failed to place in his submission a delivery system, thus failing to meet program requirements, and showed no method of entry or egress. Further, there was no method of entry or egress from the river walk. Although Butt complimented Petitioner in overcoming one type of circulation problem that was overlooked by many other applicants at the same examination, Petitioner's circulation design was still full of many errors described by Mr. Butt, including life safety factors. Mr. Butt admitted that the graders had not marked life safety as a weakness present in Petitioner's exam. However, Butt's critique of Petitioner's circulation problems shows circulation overlaps into the area of "design logic." For other reasons, including but not limited to Petitioner's showing of certain features such as windows only upon the elevation sheets (as opposed to upon other sheets as well) and failure to show all of an access road, his errors and omissions also overlap into the evaluation criteria of "clarity and completeness of presentation." While Petitioner attempted to show, through use of the publication of NCARB which contains within it samples of various passing and failing examinations, that his examination submission was similar to those which had been recorded as passing grades, he was unsuccessful in discrediting the overall perception of Butt that there were significant difficulties in Petitioner's design solution which, taken as a whole, were much more numerous than the various solutions (both passing and failing) which were compared with Petitioner's solution. In a review of the sample solutions, Butt conceded that some of the errors that Petitioner made were also made by some of the candidates who achieved passing scores. However, Petitioner's examination submission contained a combination of many errors in one paper, which same errors may have existed only individually in some of the passing examples. In short, Petitioner's reliance on the NCARB-produced review booklet is misplaced in that his submitted solution to the problem presented a conglomeration of many of the errors which may have been passing if presented individually in various of the examples contained in the NCARB manual. Petitioner, who has the burden of proof in these de novo proceedings, has therefore failed to demonstrate that his examination solution exhibits minimal competency within the criteria necessary for a passing score.

Recommendation Therefore, it is, RECOMMENDED that the Board of Architecture enter a Final Order affirming that Petitioner has failed the licensure examination for 1985. DONE and RECOMMENDED this 12th day of June, 1987, at Tallahassee, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of June, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-2195 The following constitute rulings pursuant to Section 120.59(2), Florida Statutes, upon the parties' respective proposed findings of fact (FOF). Petitioner's Proposed Findings of Fact: 1-2. Covered in Recommended Order FOF 1-3. 3-4. Covered in FOF 10. 5-7. Those portions not accepted are rejected as not supported by the greater weight of the competent substantial evidence as a whole as set forth in FOF 11-12. Further, Mr. Butt testified that once the Petitioner's solutions to the problem were utilized, it was probable the graders would not give him the benefit of the doubt to recommend changes to his submitted because any reasonable solutions they might propose would require almost total redesign of his proposed building instead of the minimal changes they might be permitted to recommend. Rejected as not supported by the competent substantial evidence as covered in FOF 7. Three and 1/2 minutes was given as a fair estimate of the time actually used, not the time permitted. Covered in FOF 9; see also ruling on proposals 5-7 above. Covered in FOF 10; see also ruling on proposals 5-7 above. Accepted but immaterial and not dispositive of any issue at bar. The graders were not precluded from making more than three recommended marks. Respondent's Proposed Findings of Fact: Covered in FOF 1; that which is rejected is subordinate and unnecessary. Covered in FOE 2. Covered in FOE 4 and 6. Covered in FOF 7 and 10. Covered in FOE 10. 6-7. Covered in FOF 11 and 12 but substantially modified for independent clarity of expression. COPIES FURNISHED: Pat Ard, Executive Director DPR-Board of Architecture 130 North Monroe Street Tallahassee, Florida 32399-0750 Jorge L. Garcia 1744 Southwest First Avenue Miami, Florida 33134 Jorge L. Garcia 231 Southwest 52nd Avenue Miami, Florida John Rimes, Esquire Department of Legal Affairs The Capitol - LL04 Tallahassee, Florida 32399-1050 Joseph A. Sole, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57481.209481.211481.213
# 7
GEORGE SOLAR vs CONSTRUCTION INDUSTRY LICENSING BOARD, 90-006607 (1990)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Oct. 18, 1990 Number: 90-006607 Latest Update: Mar. 28, 1991

The Issue Whether Petitioner should be granted additional credit for one or more examination questions answered by him during the June 1990 Certified Building Contractor Examination.

Findings Of Fact Petitioner sat for the June 1990 certified building contractor examination. On Part II, he received a score of 68.0. A minimum passing score is 69.01. On Part III, he received a score of 71.00. Minimum passing score is 69.01. Petitioner had previously passed Part I of the exam. Petitioner initially challenged question numbers 6, 13 and 14. Upon completion of the testimony, Petitioner withdrew his challenges to question numbers 13 and 14. The National Assessment Institute prepares licensure examinations for building contractors in the State of Florida under authority of the Office of Examination Services, Department of Professional Regulation. The Institute prepared question number 6 for the certified building contractor examination administered on June 26 and 27, 1990. Question number 6 tested the candidate's ability to calculate the time necessary for a crew to excavate, form and pour concrete for a reinforced concrete curb and gutter in a parking area and have it inspected. The candidate was asked to select the earliest date that concrete can be scheduled to be poured. Four dates were given: (A) June 11, (B) June 13, (C) June 15, and (D) June 18, 1990. The Institute determined that the only correct answer was: (D) June 18, 1990. The Petitioner selected: (C) June 15, 1990. Part of the instructions to the examination candidates stated: "The inspection request will NOT be called in the day the work is completed." The evidence was undisputed that preliminary calculations indicate with regard to question 6 the mathematical approach to the solution demonstrates that the work will take nine days (rounded up), starting June 1 and completed on June 13, and, therefore, the inspection is to be called in on Thursday, June 14, 1990. The third paragraph of the question states: Inspections have been taking one day from the time the inspection is called in until the time the inspection is completed. Inspections can NOT be called in or performed on Saturdays or Sundays." The first sentence of the fourth paragraph states: "The concrete is to be placed the day after the inspection is completed." (Emphasis supplied) The Department's position is that the plain language of the question indicates that it would take one day or 24 hours from the date the request for inspection was called in (June 14) until the inspection was completed which would be June 15. Since the instructions were clear that the concrete cannot be poured on the same day the inspection is completed or on Saturdays or Sundays, then the earliest date that the concrete can be scheduled is Monday, June 18, 1990, or answer (D). The Petitioner argues that it is not uncommon in the construction industry to "call in" an inspection in the morning and have it completed on the same date (in one day). Therefore, since it is undisputed that the inspection is to be "called in" on Thursday, June 14, that it was reasonable and logical for him to conclude that the inspection would also be completed the same date. Since the question instructed that the concrete is to be placed the day after the inspection is completed, he selected answer (C), June 15, 1990 (a Friday) as the correct answer. The Department does not dispute that it is common practice in the construction industry for an inspection to be called for and completed in one day. The Department's determination that answer (D) was the only appropriate answer was arbitrary and unreasonable.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that: Petitioner be awarded four points for his answer to question number 6 of Part II of the Certified Building Contractor examination for June, 1990. Petitioner be awarded a passing grade for Parts II and III of the examination. DONE AND ENTERED this 28th day of March, 1991, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March, 1991. APPENDIX The following constitutes my specific rulings, in accordance with section 120.59, Florida Statutes, on findings of fact submitted by the parties. Petitioner's proposed findings of fact. Accepted in substance: paragraphs 1,2,3,4,5,6,7,10 Rejected as argument: paragraphs 8,9 Respondent's proposed findings of fact. Accepted in substance: paragraphs 1,2,3(included in Preliminary Statement), 4(in part),5. Rejected: paragraph 4(in part, as against the greater weight of the evidence and argument), 5 and 6(challenge withdrawn) Copies furnished: George Solar 1302 West Adalee Street Tampa, Florida Vytas J. Urba, Esquire Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Jack McRay, Esquire General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.111
# 8
DENNIS WHITE vs CONSTRUCTION INDUSTRY LICENSING BOARD, 89-006136 (1989)
Division of Administrative Hearings, Florida Filed:Miami, Florida Nov. 09, 1989 Number: 89-006136 Latest Update: Feb. 21, 1990

Findings Of Fact Based upon my observation of the witnesses, their demeanor while testifying, the documentary evidence received and the entire record compiled herein, I make the following findings of fact: In order for Petitioner to obtain a license as a building contractor in Florida, he is required to successfully complete a certification examination. The exam is administered by the Department of Professional Regulation. The questions on the exam are prepared from specific reference materials disclosed to the applicants, generally accepted industry procedures and standard field knowledge. In October of 1988, Petitioner took the examination and achieved a passing score on Part I of the exam but received a failing grade on Part II and Part III. In February of 1989, Petitioner again took Part II and Part III of the exam. This time he achieved a passing score on Part II, but failed Part III. In June of 1989, Petitioner took Part III of the exam for a third time and received a grade of 69. A score of 69.1 was necessary for Petitioner to receive a passing grade on Part III. A correct answer to either of the two challenged questions would give Petitioner a passing grade on Part III. There is no dispute that the answers deemed correct by Respondent in grading the exam were the only right answers to the questions. Petitioner offered into evidence the scratch paper he used while taking the exam. Those papers demonstrate that he correctly calculated the answers to the questions, but incorrectly marked the answers on his answer sheet. The instructions provided to all exam takers at the time of the exam specifically provide that only responses on the answer sheet can be scored.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that Petitioner's request that his June, 1989 examination for a building contractor's license be regraded be DENIED. RECOMMENDED this 21st day of February, 1990, in Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of February, 1990. APPENDIX TO RECOMMENDED ORDER, CASE NUMBER 89-6136 The Respondent submitted a Proposed Recommended Order which includes proposed findings of fact and conclusions of law. The Petitioner did not submit any post-hearing findings. The following rulings are directed towards the findings of fact contained in the Proposed Recommended Order submitted by the Respondent. The Respondent's Proposed Findings of Fact Proposed Finding Paragraph Number in the Findings of Fact of Fact Number in the Recommended Order were accepted or Reason for Rejection. Adopted in substance in Findings of Fact 4. Included in the preliminary statement. Adopted in substance in Findings of Fact 5. Included in the preliminary statement. Adopted in substance in Findings of Fact 6. Adopted in substance in the preliminary statement and in Findings of Fact 7. Adopted in substance in Findings of Fact 8. COPIES FURNISHED: E. Harper Field, Esquire Department of Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, Florida 32399-0792 Dennis White 11401 S. W. 40 Terrace Miami, Florida 33165 Fred Seely, Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Kenneth D. Easley, General Counsel Department of Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.111
# 9
THE WEITZ COMPANY, LLC vs BROWARD COUNTY SCHOOL BOARD, 10-008182BID (2010)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida Aug. 23, 2010 Number: 10-008182BID Latest Update: Feb. 18, 2011

The Issue Whether Respondent's intended rejection of all responses to its solicitation of "qualifications" from entities interested in contracting with Respondent to perform construction management at risk services in connection with a project at Fort Lauderdale High School is illegal, arbitrary, and/or dishonest, as alleged by Petitioner.

Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: Respondent is a district school board responsible for the operation, control and supervision of all public schools (grades K through 12) in Broward County, Florida (including, among others, Fort Lauderdale High School) and for otherwise providing public instruction to school-aged children in the county. As authorized by Florida Administrative Code Rule 6A- 1.012, Respondent has "establish[ed] purchasing rules" (denominated as "policies"). Respondent's Policy 3320 contains Respondent's "Purchasing Policies." Part III of Respondent's Policy 3320 prescribes "Purchasing Policies" for Respondent's Facilities and Construction Management Division, and it provides, in pertinent part, as follows: All additions, modifications, and alterations to School Board properties shall conform with the State Requirement for Educational Facilities (SREF), Florida Building Code (FBC) and the laws of the State of Florida. School Board administrators shall obtain assistance in preparing bid specifications and applicable building permit(s) from the Facilities and Construction Management division for these items. Part VIII of Respondent's Policy 3320 addresses the subject of "protests arising from the competitive solicitation process" and incorporates the protest procedures found in Section 120.57(3), Florida Statutes. Respondent's Policy 7003 is entitled, "Pre- Qualification of Contractors and Selection of Architects, Engineers, Design Builders, Construction Managers, and Total Program Managers Pursuant to the Consultants Competitive Negotiation Act." It provides, in pertinent part, as follows: The School Board shall pre-qualify bidders for construction contracts, and, publicly announce, in a uniform and consistent manner, each occasion when construction and/or professional services are required to be purchased in compliance with governing statutes and regulations. The Superintendent shall establish procedures for the pre-qualification of contractors and selection of architects, engineers, design- builders, construction managers and total program managers consistent with this policy, applicable statutes and State Requirements for Educational Facilities (SREF). Rules The School Board authorizes the Superintendent to: Receive applications for Contractor Pre- Qualification on the attached application form in compliance with FS 1013.46 and SREF 4.1(8), as amended. . . . * * * 4. Designate an evaluation committee of eleven (11) voting members for the purpose of Pre-Qualification of contractors and selection of architects, engineers, design builders, construction managers and total program managers. * * * The committee shall make recommendations to the Superintendent regarding the pre- qualification of contractors. The Superintendent shall make recommendations to the Board: Along with a report from the committee containing findings of fact indicating the proposers' compliance with the procurement requirements and scoring criteria and the Board shall have the final approval of such recommendations. The Contractor Pre-Qualification Application Form "attached" to Policy 7003 contains the following description of the contractor pre-qualification process: The School Board ("Board") through the Superintendent or his/her designee, shall pre-qualify all "contractors" for construction contracts, and any other contracts that require a certificate issued pursuant to Chapter 489, Florida Statutes, including, but not limited to, all bidders, construction managers, design-builders, job- order contractors, term contractors, and all other types of contractors on an annual basis or for a specific project according to the rules set forth in the State Requirements for Educational Facilities (SREF) Section 4.1(8). Contractors shall be pre-qualified on the basis of the criteria set forth in SREF and included in the foregoing application form. In addition to the foregoing criteria the applicant shall provide the Dun and Bradstreet report indicated in the application. The evaluation committee shall be as set forth in Board Policy 7003. The applicant shall complete the form in its entirety and submit all required documents by the deadline set forth in the public announcement. Separate applications shall be submitted for each desired contracting category. The School Board of Broward County shall receive and either approve or reject each application for prequalification within sixty (60) days after receipt of application in its entirety and all required documents. Approval shall be based on the criteria and procedures set forth in SREF. The Board shall issue to all pre-qualified contractors a certificate valid for one (1) year from the date of approval or for the specific project(s). That certificate shall include the following: A statement indicating that the contractor may bid, propose, or otherwise be considered, on the specific project(s) or for this specific time period. A statement establishing the total dollar value of the work the contractor will be permitted to have under contract with the Board at any one time. The maximum value shall not exceed the contractor's bonding capacity or ten (10) times the net quick assets. A statement establishing the maximum dollar value of each individual project the contractor will be permitted to have under contract with the Board at any one time. The maximum value of each project may be up to twice the value of the largest similar project previously completed but shall not exceed the Contractor's bonding capacity or ten (10) times the net quick assets. A statement establishing the type of work the contractor will be permitted to provide. The expiration date of the certificate. It shall be the responsibility of the contractor to renew annually certificates not for a specific project. Financial statements or written verification of bonding capacity on file with the Board shall be updated annually. Failure to submit a new statement or verification of bonding capacity within thirty (30) days written notice by the Board shall automatically revoke a pre-qualification certificate. 1. Pre-qualified contractors may request a revision of their pre-qualification status at any time they believe the dollar volume of work under contract or the size or complexity of the projects should be increased if experience, staff size, staff qualifications, and other pertinent data justify the action. These procedures are in accordance with requirements set forth in Section 4.1 of the State Requirements for Educational Facilities. As the parties stipulated in Admitted Fact 6, "[o]n May 20, 2008, [Respondent] approved the Request for Qualifications No. 2008-030-FC (RFQ) entitled 'Construction Management at Risk Services for Districts 2, 3 and 4 Projects (Cooper City High School - Project No. 1931-99-02; Fort Lauderdale High School – Project No. 0951-27-01; Margate Elementary School – Project No. 1161-26-01; and Northeast High School – Project No. 1241-27-01),' and authorized the public announcement of the RFQ." "[In] [t]he summary explanation and background [section of] the Agenda Request Form [for this agenda item, it was] stated that the 'Facilities and Construction Management staff recommend[ed] the procurement of construction services utilizing Construction Management at Risk delivery method due to the complexity, scope and scale of the projects.'" This "delivery method" is to be distinguished from the "hard bid" or "design/bid/build" method of procurement, where a contractor is hired only after "the construction documents are completed." Under the "Construction Management at Risk delivery method," contrastingly, the construction manager typically assists in the development and "complet[ion]" of the "construction documents," offering advice and recommendations to maximize quality and cost efficiency. As a result, it is "not uncommon" for there to be post-solicitation changes in a project's scope and budget when this "delivery method" is employed. As the parties stipulated in Admitted Fact 7, "[a]t the time of [Respondent's] approval of the RFQ, the portion of the RF[Q] pertaining to [the FHS Project] had an advertised Proposed Construction Budget of $29,150,340 and a project scope which was described [in RFQ] as follows: 'Concurrent replacement in two phases to include: Phase I – Construct a 3- story Administration Classroom Building of 68,940 GSF to include Administration, 3 general classroom[s], 5 resource rooms, 4 Science Labs and related spaces, a 4-classroom ESE Suite, 1 Business Technology Lab, 1 Family and Consumer Science (ProStart) Lab, 1 Health Occupations Lab, 1 Pre-Law Public Service Education Lab, Custodial spaces, Textbook Storage and Student, Staff and Public Restrooms. Demolish Buildings 1, 2, 3, 4, 11, 12, 13 and 14.'" Phase II of the project was, at the time, described in the RFQ as follows: "Construct Parent drop off & pick up area and Staff/Visitor Parking; Construct Regional Athletic Facility; Renovate Building 8 into Science Labs; Demolish existing tennis courts & replace with 6 tennis courts; Demolish Swimming Pool; Construct basketball courts; Resurface Student Parking." These descriptions represented the "initial concept" of the FHS Project (the design of the project having been then only in the "conceptual stage" of development). Respondent wanted to have the benefit of the input and advice of a construction manager (working together with the architect selected for the project) in developing the project's design beyond the "conceptual stage." As the parties stipulated in Admitted Facts 12 through 19, "[b]etween the initial public release of the RFQ and the submission of proposed qualifications, [Respondent] issued seven (7) addenda revising the RFQ's terms and conditions," with "Addendum No. 4 chang[ing] the scope of the [FHS Project] component of the RFQ as follows": Delete the scope in Phase I to demolish Building #4. Delete the scope in Phase II to construct basketball courts and to resurface student parking. Revise the words "replace with 6 tennis courts" to be the words "construct five (5) tennis courts." Clarify phasing: In Phase I, demolish the existing track and athletic field and relocate existing baseball field. Clarify scope: In Phase II, for the staff parking construct a 3-story parking structure including required access road work. Clarify scope: Phase II includes renovation of existing courtyard to provide ADA access to existing gymnasium and auditorium. (Emphasis, by bolding, supplied in original). Addendum No. 6 "[r]evised the [RFQ's] Submittal Due Date to read 'No later than 2:00 p.m. on September 3, 2008.'" As the parties stipulated in Admitted Fact 20,"[a]fter [the] issuance of Addendum No. 7 to the RFQ, the scope of the [FHS Project] component of the RFQ was described as follows [with strike-throughs and underlining indicating, respectively, post-issuance deletions and additions]: Concurrent replacement in two phases to include: Phase I – Construct a 3-story Administration Classroom Building of 68,940 GSF to include Administration, 3 general classroom[s], 5 resource rooms, 4 Science Labs and related spaces, a 4-classroom ESE Suite, 1 Business Technology Lab, 1 Family and Consumer Science (ProStart) Lab, 1 Health Occupations Lab, [1 Pre-Law Public Service Education Lab], Custodial spaces, Textbook Storage and Student, Staff and Public Restrooms. Demolish the existing track and athletic field and relocate existing baseball field. Demolish Buildings 1, 2, 3, 4, 11, 12, 13 and 14. Phase II – Construct Parent drop off & pick up area and a 3-story parking structure including required road access work for Staff Parking and /Visitor Parking[.] Construct Regional Athletic Facility[.] Renovate building 8 into Science Labs[.] Demolish existing tennis courts & replace with 6 tennis courts construct five (5) tennis courts. Demolish Swimming Pool. Renovate existing courtyard to provide ADA access to existing gymnasium and auditorium. Construct basketball courts. Resurface Student Parking." As the parties stipulated in Admitted Facts 10 and 11, on August 26, 2008, the date that Respondent issued its final addendum to the RFQ (Addendum No. 7), it also issued a Revised Public Announcement publicizing the issuance of the RFQ (as revised by the seven addenda). The Revised Public Announcement read, in pertinent part, as follows: In order to supplement the expertise of the Facilities and Construction Management Department, the Superintendent of Schools, pursuant to Florida Statutes, announces that The School Board of Broward County, Florida, is in need of Construction Management Services, related to new construction and renovations of educational facilities. Pursuant to this request for qualifications, The Board will consider contracts with one of more proposers to provide these services. Services under this contract include, but are not limited to the following items and shall be in accordance with SREF [State Requirements for Educational Facilities] 1999 Chapter 4: Bid and award activities including managing bidder listing, addendum, bidding, proposals, schedule of values, contracts, guaranteed maximum price, value engineering, and bonds. Construction activities including managing meetings, contract administration, monitoring procedures, contract records, inspections, non-conformances, owner- supplied equipment, testing, project accounting, and construction services. Warranty activities including managing claims and periodic inspections. Provide other basic services as required. Refer to the Request for Qualifications for more detailed project scopes. * * * RFQ No. 2008-30-FC Project Nos. 0951 27 01/P000687 Fort Lauderdale High School (proposed construction budget $29,150,340): Phase replacement in 2 phases to include: Phase I - Demolish selected buildings, tennis courts, swimming pool, track and athletic field. Construct a 3-story Administration Classroom Buildings[2] of 68,949 GSF; parent drop off/pick-up area and visitor parking; 5 tennis courts. Relocate existing baseball field. Phase II - Demolish selected building. Construct a 3-story parking structure including required access road work; Regional Athletic Facility. Renovate existing courtyard for ADA access to Gym and Auditorium. Renovate Building 8 into Science Labs. * * * Award: Project will be awarded by Facility. Proposed Construction Budget: Includes all costs inclusive of the Construction Manager's fees, Cost of Work, and any other costs related to construction. Minimum Selection Criteria: Will include the following as a minimum, (refer to document RFQ, Article X Submittal Requirements for expanded list of selection criteria): The company's history, structure, personnel, licenses, and experience. Related projects similar in scope or amount completed by the company, including name of client or its representative. Financial information such as balance sheet and statement of operations and bonding capacity. Project management, scheduling and cost control systems the company uses for similar projects. Proposed minority business involvement in the project. . . . Cost control, value engineering techniques and constructability reviews. Description of litigation, major disputes, contract defaults and liens in the last five (5) years. Interview. Confirmation of references. Consideration of the volume of work previously awarded to each firm, with the object of effecting an equitable distribution of contracts among qualified firms, provided such distribution does not violate the principle of selection of the most qualified firms. * * * The completed RFQ response must be delivered . . . . NO LATER THAN 2:00 PM SEPTEMBER 3, 2008 * * * Qualifications Selection Evaluation Committee (QSEC): After submission, proposers will be evaluated by the Qualification Selection Evaluation Committee (QSEC) based upon the above minimum criteria. The QSEC will select no less than three (3) proposers, ranked in order of tabulated score. The QSEC will recommend the finalist(s) for award of contracts to Construction Managers to the Superintendent. The Superintendent shall either recommend award of contract(s) to the finalist(s) selected by the QSEC or recommend rejection of all proposals to the Board. After the Board approves the recommendations of the QSEC the Board will authorize the Superintendent, or designee, to negotiate a contract for services for fees to provide direct management of the Construction Management at Risk Contract. Recommendations by the Qualification Selection Evaluation Committee do not guarantee a contract will be awarded by the Board. Award of a contract does not guarantee that work will be issued. Fees will be negotiated in accordance with Board Policy 7003 and Section 287.055, F.S. Article I of the RFQ (as revised) listed "General Requirements" that "proposers [had to] meet" "[i]n order to be considered." As the parties stipulated in Admitted Fact 21, Article I.D. of the RFQ (as revised) provided, in pertinent part, as follows: All proposers must be prequalified according to 1013.46 F.S., SREF 4.1(8), and Board Policy 7003 at the time of submittal due date to this RFQ. Article I.H. of the RFQ (as revised) provided as follows: The School Board of Broward County, Florida reserves the right to reject any or all responses, to waive technicalities, or to accept the proposal that, in its sole judgment, best serves the interest of The School Board of Broward County, Florida. Article II of the RFQ (as revised) described the "Selection Process." As the parties stipulated in Admitted Fact 22, Article of the RFQ (as revised) "was entitled 'Proposal Review by Staff' and stated as follows": Facilities and Construction Management Division staff will conduct a review of the proposer's submittal to determine whether the proposer meets the terms of this RFQ, requirements of the Florida Statutes, State Requirements for Educational Facilities regulations, Florida Building Code, and any other code, statute, or standard applicable at the time of response. Facilities and Construction Management Staff will provide information to the QSEC Members showing payments made by the district to the proposing firms over the past three (3) years. Non-compliant proposals will be recommended to the committee for rejection. As the parties stipulated in Admitted Fact 23, Article of the RFQ (as revised) "was entitled 'Shortlist Selection' and stated as follows": The QSEC Members will assign points to each proposer, for each facility, based upon the Selection Criteria below and attached Selection Criteria Score Sheet in the shortlist evaluation process. Each QSEC Member shall assign points for each proposer according to the selection criteria and rank them according to their scores. The proposer receiving the most points by a QSEC Member will be considered the first choice of that QSEC Member. The firm that receives the most first choice votes from the committee will be the top-ranked proposer. The second-ranked proposer will be the proposer that receives the most points, other than the proposer who was already selected as the top-ranked, and so on. In the event of a tie a voice vote will be taken until the tie is broken. If the voice vote is not unanimous, then a roll-call vote will be taken. The selection process will establish a "shortlist" for each facility/project of not less than three (3) proposers and no more than five (5) proposers submitting proposals. Shortlist selection will be done by each facility. Article II.E. of the RFQ (as revised) called for "[p]resentations" to be made to the QSEC by the shortlisted proposers. As the parties stipulated in Admitted Fact 24, Article II.G. of the RFQ (as revised) "was entitled 'Final Selection' and stated as follows": The QSEC will interview and rank the shortlisted firms. The QSEC will assign points to each proposer, for each facility, utilizing the Selection Criteria and point schedule included with the Selection Criteria Score Sheet to finalize the selection. Note, M/WBE staff will provide scores for M/WBE categories. However, such scores are recommendations by M/WBE staff and may be adjusted by individual QSEC Members. Each QSEC Member shall assign points for each proposer according to the selection criteria and rank them according to their scores for each project/facility. The proposer receiving the most points by a QSEC Member will be considered the first choice of that QSEC Member. The proposer that receives the most first choice votes from the committee will be the top-ranked proposer. The second-ranked proposer, will be the proposer that receives the most points, other than the proposer who was selected as the top-ranked proposer, and so on. In the event of a tie a voice vote will be taken until the tie is broken. If the voice vote is not unanimous, then a roll- call vote will be taken. The QSEC will recommend the finalist(s) for award of contract to Construction Manager to the Superintendent. The Superintendent shall either recommend award of contract(s) to the finalist(s) selected by the QSEC or recommend rejection of all proposals to the Board. After the Board approves the recommendations of the QSEC the Board will authorize the Superintendent, or designee, to negotiate a contract with the top-ranked firm according to Section 287.055, F.S. The Board shall have final approval of such recommendations. Final selection will be done by each facility. Article II.H. of the RFQ (as revised) contained the "Minimum Selection Criteria." This provision read as follows: Minimum Selection Criteria: Will include the following as a minimum, (refer to this document Article XI Submittal Requirements for expanded list of selection criteria): The company's history, structure, personnel, licenses, and experience. Related projects similar in scope or amount completed by the company, including name of client or its representative. Financial information such as balance sheet and statement of operations and bonding capacity. Project management, scheduling and cost control systems the company uses for similar projects. Proposed minority business involvement in the project (refer to this document Article I, J for requirements). Cost control, value engineering techniques and constructability reviews. Description of litigation, major disputes, contract defaults and liens in the last five (5) years. Interview. Confirmation of references. Consideration of the volume of work previously awarded to each firm, with the object of effecting an equitable distribution of contracts among qualified firms, provided such distribution does not violate the principle of section of the most qualified firms. As the parties stipulated in Admitted Fact 25, Article III of the RFQ (as revised) "[was] entitled 'Competitive Negotiations' and state[d] as follows": After the QSEC ranks the firms, recommends the finalist(s) to the Superintendent, and the Superintendent recommends the finalist(s) to the Board[,] [t]he Superintendent, or designee will negotiate a contract for services for fees to provide direct management cost of the CM and Guaranteed Maximum Price (GMP). The CM contract shall maintain an "open book" project accounting process, with any savings returned to the Board. Should the negotiations not result in a contract with the finalist at a price determined by both parties to be customary, fair, competitive, and reasonable, negotiations with that firm shall be formally terminated. The Superintendent, or designee, shall undertake negotiation with the second most qualified firm and thereafter, if necessary, with the third firm. Should the Board be unable to negotiate a satisfactory contract with any of the selected firms, additional firms will be selected in accordance with the above- described procedure. Negotiation should continue in accordance with Section 287.055, F.S., or until the Board determines not to proceed and to re-advertise and repeat the process. Article IV of the RFQ (as revised) addressed the "Scope of Services." It simply provided as follows: "Refer to attached Agreement Between Owner and Construction Manager for requirements." Article 3 of the "attached Agreement Between Owner and Construction Manager" (Sample Contract) enumerated the "Construction Manager's Services." Those services to be performed by the hired construction manager during the "Pre-Design Phase" were described in Article 3.2 of the Sample Contract as follows: The Construction Manager shall review project requirements, educational specifications, on and off-site development, survey requirements, preliminary budget, and make value engineering and constructability recommendations for revisions to the Owner and Project Consultant in the form of a written report prior to the final payment for this phase. The Construction Manager shall, subject to Owner's approval and compliance with existing Owner completion schedule, establish a preliminary master project schedule identifying all phases, Critical Path elements, responsibilities of the Owner, Project Consultant, outside agencies, third parties and any other impacts which would affect project schedule and progress and update them monthly throughout the duration of the contract. When the project includes renovation or expansion of an existing Facility, the Construction Manager will assist the Construction Team in preparing an analysis package outlining the condition of the existing Facility, existing structure, existing finishes, and existing equipment, code deficiencies, energy use, and life expectancy of other building systems by providing constructability, value engineering, and cost estimates recommendations. The package should contain the Construction Manager's recommendations, cost estimates and preliminary schedules. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager shall prepare detailed cost estimates and recommendations to Owner and Project Consultant at S.D. (Schematic Design), D.D. (Design Development), C.D. (50% and 100% Construction Documents) phases of the project. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for each phase. The Construction Manager shall provide project delivery options for the design, bid, and bid packaging of the project for efficient scheduling, cost control and financial resource management. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager shall utilize information and reporting systems to provide the Owner with monthly reports containing accurate and current cost controls, work status, including but not limited to Work narrative, Work completed/anticipated, short term and long term schedules, estimated expenditures, and project accounting systems of the project at all times. Such information shall be provided to the Owner and Project Consultant in the form of a written report, prior to final payment for this phase. The Construction Manager shall prepare a report with the Project Team's participation which shall describe, as a minimum, the Work plan, job responsibilities, and written procedures for reports, meetings, inspections, changes to the project, building systems, and delivery analysis and other relevant matters. Such information shall be provided to the Owner and Project Consultant prior to final payment for this phase. The Construction Manager shall provide market analysis and motivation for subcontractor interest and recommendations for minority business participation. This shall include analysis of the Construction Manager's historical data for subcontracting, communication with contractor and trade organizations requesting participation, review of the Owner's M/WBE data, advertising, outreach programs, mailings to all prospective bidders identified by these actions, and reporting of all of the for[e]going to the Owner. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager's personnel to be assigned during this phase and their duties and responsibilities to this project and the duration of their assignments are shown on Exhibit D to the General Conditions. All required reports and documentation shall be submitted and approved by the Owner as pre-requisite to progress payments to the Construction Manager by the Owner during this phase. Those services to be performed by the hired construction manager during the "Design Phase" were described in Article 3.3 of the Sample Contract as follows: The Construction Manager will be required to attend all project related meetings and include a summary of the meeting of its monthly report to the Owner as specified in Document 01310. The Construction Manager will periodically review to the best of their abilities all Contract documents for constructability and compliance with applicable laws, rules, codes, design standards, and ordinances. Such information shall be provided to the Owner and Project Consultant in the form of a written report in the format as noted herein prior to final payment for this phase (Refer to exhibits G and H). The Construction Manager will be required to work with and coordinate [its] activities with any additional consultants, or testing labs and others that Owner provides for the project and report all findings as specified in Document 01310. The Construction Manager shall review all Contract documents for the new and existing buildings and/or building sites and provide value engineering recommendations to minimize the Owner's capital outlay and maximize the Owner's operational resources. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. All such recommendations shall be acknowledged and incorporated into the construction documents by the Project Consultant unless otherwise authorized by the Owner in writing. The Construction Manager will review construction documents and the new and existing buildings conditions and/or building site to reduce to the best of [its] abilities conflicts, errors and omissions and shall coordinate with the Project Consultant in order to eliminate change orders due to errors, omissions and unforeseen conditions. The Construction Manager shall periodically update the master project schedule and make recommendations for recovery of lost time. Such information shall be provided to the Owner and Project Consultant in the form of a written report prior to final payment for this phase. The Construction Manager will coordinate with the Project Consultant and provide to the Project Construction Team permitting applications and requirements for the projects. The Construction Manager will periodically update cost estimates and make recommendations to keep the project within the FLCC. AT COMPLETION OF THE CONSTRUCTION MANAGER'S REVIEW OF THE PLANS AND SPECIFICATIONS, EXCEPT ONLY AS TO SPECIFIC MATTERS AS MAY BE IDENTIFIED BY APPROPRIATE WRITTEN COMMENTS PURSUANT TO THIS SECTION, CONSTRUCTION MANAGER SHALL WARRANT, WITHOUT ASSUMING THE PROJECT CONSULTANT'S RESPONSIBILITES, THAT THE PLANS AND SPECIFICATIONS ARE CONSISTENT, PRACTICAL, FEASIBLE AND CONSTRUCTIBLE. CONSTRUCTION MANAGER SHALL WARRANT THAT THE WORK DESCRIBED IN THE PLANS AND SPECIFICATIONS FOR THE VARIOUS BIDDING PACKAGES IS CONSTRUCTIBLE WITHIN THE SCHEDULED CONSTRUCTION TIME. DISCLAIMER OF WARRANTY: THE OWNER DISCLAIMS ANY WARRANTY THAT THE PLANS AND SPECIFICATIONS FOR THE PROJECT ARE ACCURATE, PRACTICAL, CONSISTENT OR CONSTRUCTIBLE OR WITHOUT DEFECT. .10. The Owner may select certain projects for expediting using fast-track construction. When this option is exercised, in writing, by SBBC, it shall be implemented in accordance with the following: A. Design/Construction documents as noted herein shall be submitted by the Consultant for review and approval by SBBC (including Building Code review and Building permit issuance for 100% completion documents), the Construction Manager and others, as applicable, having jurisdiction: Foundation/Structural/LCCA/Site and Off- Site Package-100% Documents A separate 50% completion progress set (for information only) of Building Finish Package drawings shall also be submitted which shall show all of the major characteristics of the project utilities and service, detailed site and floor plans, elevations, section, schedules, etc. Construction may begin after approvals and building permit is obtained for above package. Building Finish Package-100% Documents As mutually agreed by the parties in writing. .11 Guaranteed Maximum Price (GMP): Upon completion of the design phase [construction documents 100% complete] and prior to the bidding and award phase, the Construction Manager shall present to the Owner the GMP for the Owner[']s review and approval in accordance with Article 6 of this Agreement.[3] Those services to be performed by the hired construction manager during the "Bidding and Award Phase" were described in Article 3.4 of the Sample Contract as follows: At this stage the Construction Manager assumes the leadership responsibility for the project team. Upon obtaining all necessary approvals of the Construction Documents including a Building Permit as required by FBC and Owner approval of the latest Statement of Probable Construction Cost, the Construction Manager shall obtain bids and commence awarding construction contracts. The Owner will have the drawings and specifications printed for bidding purposes, either through its open Agreements with printing firms or as a reimbursable service through the Project Consultant, or as set forth in Article 26.03.08 in the General Conditions of this CM Agreement. The Construction Manager shall review the Owner[']s records of pre-qualified contractors, including Minority/Women Business Enterprises (M/WBE) and prepare a list of those recommended for work pursuant to this contract. The Owner reserves the right to reject any or all subcontractors recommended for approval. The Construction Manager shall maintain a list of all potential bidders, including M/WBEs and those who are approved as pre-qualified. The Construction Manager shall prepare and issue the bid packages to cover the scope of the Work for this contract. The Construction Manager, in coordination with the Owner, shall schedule pre-bid conferences as required and issue a written summary of the conference(s). Solicitation of Bids: .1 The Construction Manager shall enter into Contracts with the firm who submits the lowest, responsive and responsible bid. The Construction Manager shall advertise according to SBBC policies as amended from time to time for bids on Documents 00101 at least three (3) times, seven (7) days apart, and with the third (3rd) advertisement prior to a pre-bid conference if applicable and at least seven (7) days prior to the bid opening. Written proposals based on drawings and/or specifications shall be submitted to the Construction Manager. The written proposals shall be opened at the usual location for bid opening. A tabulation of the results shall be furnished by Construction Manager to the Owner. .6 The Construction Manager and Owner shall open at the Construction Manager location and evaluate at least three bids, if possible, for each portion of the Work solicited. The Construction Manager shall also make recommendations to the Owner for award to the lowest, responsive, and responsible bidder. A recommendation for award to other than the lowest bidder shall be justified in writing. Those services to be performed by the hired construction manager during the "Construction Phase" were described in Article 3.5 of the Sample Contract as follows: The Construction Manager shall fully comply with the provision[s] of the Owner's Project Manual, including but not limited to Division 0 and 1, and the attached General Conditions of this contract. In the event of a conflict between this Agreement and such documents the agreement shall control. The Construction Manager shall provide the minimum staffing level as set forth in Exhibit C-F for this project. The Construction Manager shall maintain and prepare monthly updates for all project schedules, including Critical Path elements, provide written progress reports, describe problems and corrective action plan(s) and conduct briefings as required by the Owner. Such information shall be provided to the Owner and Project Consultant in the form of a written report with progress payments requests. The Construction Manager may self perform certain construction work when it benefits the Owner, results in cost and time savings, and is pre-approved by the Owner in writing. The Construction Manager shall coordinate project close-out, operation, and transition to occupancy. The Construction Manager shall coordinate with the Project Consultant to provide complete project records including project manual and electronic Computer Assisted Drafting (CAD) drawings corrected to show all construction changes, additions, and deletions. (Construction Manager shall note all changes on the as-builts for the Project Consultant to reflect on the drawings and CAD disc.) The Construction Manager shall coordinate with the Owner's staff to prepare the Certificate of Final Inspection. The Construction Manager shall obtain and review all warranties, operation and maintenance manuals and other such documents, for completeness, have them corrected if necessary and submit them to the owner. The Construction Manager shall complete all punch list items generated by the Building Code Inspector (BCI), the Owner, the Project Consultant and any others having jurisdiction over the project during its inspections. Those services to be performed by the hired construction manager during the "Warranty Phase" were described in Article 3.6 of the Sample Contract as follows: The Construction Manager shall provide a minimum one (1) year warranty and shall coordinate and supervise the completion of warranty Work during the warranty period. Construction Manager shall participate with the Owner in conducting of warranty inspections held on the sixth (6th) and eleventh (11th) months after occupancy. Construction Manager shall deliver as-built drawings, warranties and guaranties to the Owner. Where any Work is performed by the Construction Manager's own forces or by subcontractors under contract with the Construction Manager, the Construction Manager shall warrant that all materials and equipment included in such work will be new except where indicated otherwise in Contract Documents, and that such Work will be free from improper workmanship and defective materials and in conformance with the Drawings and specifications. With respect to the same Work, the Construction Manager further agrees to correct all work found by the Owner to be defective in material and workmanship and not in conformance with the Drawings and Specifications for a period of one year from the Date of Owner Occupancy of the Project or a designated portion thereof or for such longer periods of time as may be set forth with respect to specific warranties contained in the trade sections of the Specifications or by Florida Law. The Construction Manager shall collect and deliver to the Owner any specific written warranties given by others as required by the Contract Documents. The Construction Manager shall provide a Warranty Summary Report at the end of the 6- month warranty period and 11-month warranty period. This report shall provide at a minimum: Description of each warranty item during the period. Date item reported to Construction Manager. Date item corrected. If more than one trip required, document each. Description of action taken to cure warranty item. Obtain signature of school principal or designee acknowledging warranty items have been completed. Other pertinent information, if applicable. Article V of the RFQ (as revised) provided the following information with respect to "Fees and Pricing": Successful proposers shall negotiate a fee for providing construction management services during the design phase and subsequently shall negotiate a GMP for construction services during the bidding and construction phase. Architectural/Engineering firms will develop Contract documents under separate contract with the Board. As the parties stipulated in Admitted Fact 26, Article VII of the RFQ (as revised) "[was] entitled 'Board's Right to Reject' and state[d] in part as follows": The Board reserves the right to reject any and all proposals and readvertise the project(s) at any time prior to Board approval of the recommended proposer(s) and the negotiated agreement(s). All costs incurred in the preparation of the Proposal and participation in this RFQ process shall be borne by the proposers. Proposals submitted in response to this RFQ shall become property of the Board and considered public documents under applicable Florida law. The District reserves the right to accept or reject any and all submittals, or to waive any technicalities or formalities when and if it is in the best interests of the District. Rejection: A submittal shall be rejected for failure to comply with one or more of the following requirements: The proposer is not licensed or registered in the State of Florida to provide the proposed services. The submittal shall be rejected if not received by The School Board of Broward County, Florida by the specified deadline. Not Applicable. Article XI of the RFQ (as revised) discussed "Submittal Requirements" and contained the following provisions concerning "Related Projects Similar in Scope (to this RFQ)" and "References": Related Projects Similar in Scope (to this RFQ): List educational projects of related scope and size. Provide name and location of project, project owner, project owner name, address phone and contact person, project cost, current project status, firm[']s key personnel assigned to the project. . . . L. References: Provide a list of all projects, clearly stating name of project, using Construction Management at Risk, completed or in progress within the last five (5) years from due date of this RFQ. If Proposer[']s firm also has offices outside the tri-county area (meaning Broward, Miami-Dade, or Palm Beach), then at a minimum provide references for all Construction Management at Risk projects in the tri-county area. List projects that are 75 percent or greater of the construction budget statement in the Public Announcement for each listed project. Provide the address, telephone numbers and contact person(s) listed as references for each project. . . . As the parties stipulated in Admitted Fact 27, "[o]n or about September 3, 2008, [Respondent] received proposed qualifications to provide construction management at risk services for [the FHS Project] from 13 vendors including Petitioner." Among the other "vendors" submitting "proposed qualifications" were Elkins Constructors, Inc., the Morganti Group, Inc., and W. G. Mills, Inc. As the parties stipulated in Admitted Fact 28, "[i]n accordance with the terms and conditions of the RFQ [as revised] and [Respondent's] governing statutes, rules and policies, Respondent's Qualifications Selection and Evaluation Committee ('QSEC') recommended the rejection of certain proposers for their failure to comply with [Respondent's] pre-qualification requirements or limits." There were three such "proposers": Elkins Constructors, Inc.; the Morganti Group, Inc.; and W. G. Mills, Inc. At the time of the "submittal due date to this RFQ [as revised]," neither Elkins Constructors, nor the Morganti Group, was "prequalified according to 1013.46 F.S., SREF 4.1(8), and Board Policy 7003" for any project. W. G. Mills, on the other hand, was "prequalified" for certain projects, but only within the following limits: a "[p]er [p]roject [l]imit [of] $25,000,000 [and an] [a]ggregate [l]imit [of] $250,000,000." The "advertised Proposed Construction Budget" of the FHS Project was $29,150,340, which was more than W. G. Mills' "[p]er [p]roject [l]imit [of] $25,000,000." As of the date "proposed qualifications" were due, there were 11 prequalified firms, including W. G. Mills, who had a "[p]er [p]roject [l]imit" of between $17,000,000 and $26,000,000. These firms were not eligible to be awarded the contract for the FHS Project because the project's "advertised Proposed Construction Budget" was in excess of their "[p]er [p]roject [l]imit." W. G. Mills was the only one of these 11 prequalified firms to respond to the RFQ (as revised). As the parties stipulated in Admitted Fact 29, "[i]n accordance with the terms and conditions of the RFQ [as revised] and [Respondent's] governing statutes, rules and policies, [the] QSEC next evaluated and short-listed the remaining proposers. It thereafter received presentations from the short-listed proposers and, after scoring those short-listed proposers, recommended Petitioner . . . to [Respondent] as the proposer with whom to negotiate a contract for services for fees to provide direct management cost of the construction manager and the project's guaranteed maximum price ('GMP')." As the parties stipulated in Admitted Fact 30, "[o]n October 7, 2008, [Respondent] approved [the] QSEC's selection of Petitioner . . . as the vendor with whom negotiations would be had for [the] Fort Lauderdale High School component of the RFQ [as revised] and 'authorized negotiations for Construction Management at Risk Services.' The scope of Construction Management at Risk services was [as noted above] included within the RFQ [as revised]. The summary explanation and background portion of the agenda item to authorize negotiations stated that the 'Superintendent's designees will negotiate the selected Constriction Management at Risk Services fees for the projects and recommend award of contracts at a future School Board Meeting.'" As the parties stated in the "Statement of the Controversy" section of their Joint Pre-Hearing Stipulation, "[n]egotiations between [Respondent] and [Petitioner] occurred between October 2008 [following Respondent's approval of the QSEC's selection of Petitioner] and December 2009." In December 2009, Cubellis, the architectural firm working on the FHS Project for Respondent, was "experiencing some financial difficulties" and there was uncertainty as to whether it would "be able to continue [on] the project." As a result, negotiations between Respondent and Petitioner were halted. Eventually, Cubellis "assigned [its] contract [with Respondent] to somebody else" (specifically, Manuel Synalovski Associates, LLC), but negotiations between Respondent and Petitioner never resumed. Petitioner's last written contract proposal was dated December 10, 2009. It was based on a proposed construction budget of $18,297,367 and provided for the following "Negotiated Contract Terms": Construction Manager Fees: Pre-Design Not Applicable Design Not Applicable Bidding & Award $37,685 Construction Phase Fee $1,172,370 Warranty $35,000 Overhead $289,200 Profit $185,385 General Conditions $659,846 Total $2,379,489 Above Fees based on scope of work issued "Project Scope" document dated 11/5/2009 per 11/9/2009 letter from M. Decker. CM Performance and Payment Bonds and GL Insurance are included based on budgeted contract amount of $18,297,367. Builders Risk, Contingency, and Subcontractor insurance costs are not included in the fees and will be shown in the schedule of values as separate line items as a cost of work. Should the cost of work increase Bonds and GL insurance fees are to be adjusted at insurance providers' invoiced amount. Overhead, profit and bond allowances for Change Orders: 10% Substantial Completion: 570 Final Completion in General Conditions 25.01.02: 600 Construction Phase Fee and General Conditions in 25.01.02: $3,050 per Consecutive Calendar Day Liquidation Damages for Substantial Completion: $1,000 per Consecutive Calendar Day Liquidation Damages for Final Completion: $600 per Consecutive Calendar Day This contract proposal was made following a December 8, 2009, negotiation session at which Denis Herrmann, Respondent's Director of Design and Construction Contracts, had stated that he had negotiated a construction management at risk contract for another project the previous day where the "Construction Manager Fees" were 13.8 percent of that particular project's proposed construction budget. Mr. Herrmann had relayed this information to Petitioner's representatives at the meeting to give them "a flavor for the range [Respondent was] talking about, not to give them a [specific] number [or percentage] that would be acceptable." The "Construction Manager Fees" proposed by Petitioner in its December 10, 2009, offer were slightly less than 13.8 percent of the $18,297,367 proposed construction budget (but they did not cover any "Pre-Design"-related or "Design"-related work). While Respondent has never, in writing, specifically rejected Petitioner's December 10, 2009, offer, neither has ever formally accepted it. As the parties stipulated in Admitted Facts 45 and 48, respectively, Respondent's "Superintendent of Schools has not placed an item on [the School Board] agenda recommending that [Respondent] enter into a contract with [Petitioner] concerning the RFQ [as revised]," and "[Respondent] has not approved a contract with [Petitioner] concerning [the] RFQ [as revised]." It has been two years since "[Respondent] approved [the] QSEC's selection of Petitioner . . . as the vendor with whom negotiations would be had." Significant changes impacting the FHS Project have occurred over that period of time. Respondent now finds itself in the midst of an "unprecedented budget crisis," making it especially imperative that it "take every [possible] step to maximize the purchasing power of the public's dollars." A precipitous decline in revenue available for capital projects (due, in large measure, to a decline in property values, coupled with a reduction in the capital outlay millage rate) has required Respondent to eliminate or scale back various planned projects. The FHS Project is among the projects that have been scaled back. As the parties stipulated in Admitted Fact 31, "[p]rior to, during and subsequent to its negotiations with [Petitioner], [Respondent] determined on several occasions that the project scope of the [FHS Project] needed to be further adjusted, ultimately resulting [in] the following project scope [with strike-throughs and underlining indicating, respectively, deletions and additions]": Concurrent Replacement in two phases to include: Demolish existing swimming pool (buildings 15 and 16). Demolish existing tennis courts and replace with 6 tennis courts. Demolish Buildings 1, 2, 3, 4, 11, 12, 13, and 14. Construct basketball courts. Construct Regional Athletic Facility. Construct (2) 3-story buildings (1 – Administration & 1 - Classroom) of approximately 68,940 GSF combined to include Administration, 3 general classrooms, 5 resource rooms, 4 science labs and related spaces, 4-classroom ESE suites, 1 Business Technology lab, 1 Family and Consumer Science (ProStart) lab, 1 Health Occupations Lab, 1 Pre-Law Public Service Education Lab, Custodial spaces, Textbook Storage, and Student, Staff and Public Restrooms. Remodel Renovate existing Science Building (building 8). Construct Parent Drop Off and Pick Up area and Staff/Visitor Parking. Resurface Student Parking. Construct New Student parking area on the West side of the site to increase parking capacity by 92 spaces. Modify existing temporary bus loop to meet SREF code and ADA standards; modifications will include barricades and covered sidewalk. Redesign courtyard to meet current ADA standards.' As the parties further stipulated in Admitted Fact 31, "[t]he project scope was revised five (5) times between October 7, 2008 and December 2, 2009[,] [and Petitioner] was notified of the changes in scope and acknowledged the same." "[R]evis[ions]" have also been made to the project's budget. Respondent's "5-Year Plan" allocates funding for all costs (including, but not limited to, construction costs4) associated with each of Respondent's funded capital projects. As the parties stipulated in Admitted Fact 32, "[Respondent] adopts and revises its 5-Year Capital Improvement Plan ('5-Year Plan') each year." As the parties further stipulated in Admitted Fact 33: [Respondent's] 5-Year Plan adopted for Fort Lauderdale High School for Fiscal Years 2009-10 to 2013-14 eliminated the $39,491,259 previously budgeted as "Capacity Additions" . . . . Instead, the 2009-10 to 2013-14 Five Year Plan provided $21,050,000 for Capacity Additions . . . . Respondent's current "5-Year Plan" (for the Fiscal Years 2010- 2011 to 2014-2015), which was adopted on September 7, 2010, allocates $22,366,085 to the FHS Project (as scaled back). The dour economic conditions responsible (in part) for the drop in tax revenues available to fund Respondent's capital projects have also led to increased competition in the construction industry and a resultant decline in construction prices. This increased competition is particularly pronounced "in the procurement area of hard bidding." During "the peak of the construction boom," before the downturn in the economy, it was not atypical for Respondent, when it "hard bid" a construction project, to get just one or even no bids in response to the solicitation. Now, Respondent "expect[s] to see between half a dozen [and] a dozen or more bidders." Moreover, recently, winning bids on "hard bid" projects have been, on average, well below these projects' advertised proposed construction budgets. Respondent has not experienced the same overall cost-savings results when it has used the "Construction Management at Risk delivery method." Given the market conditions that exist today, Respondent estimates that the construction costs for the FHS Project (as scaled back) would be no more than $16,950,000 and possibly as little as approximately $13,000,000 (if a "hard bid" were used). These amounts are considerably less than the "Proposed Construction Budget of $29,150,340" that had originally been "advertised." There are prequalified firms (including W. G. Mills) which were not eligible to be awarded the contract under the RFQ (as revised) because their "[p]er [p]roject [l]imit" was less than $29,150,340, but which would now be able to bid on a scaled-back FHS Project were it to be readvertised (with a proposed construction budget of $16,950,000). Another (and perhaps the most significant) difference between the circumstances existing at present and those that existed two years ago (vis-à-vis the FHS Project) is that the design of the project (as scaled back) has advanced to the point that, with a few revisions,5 the construction documents for the project will be 100 percent complete.6 As a result, Respondent no longer has a need for most, if not virtually all, of the "pre-design" and "design" services, described in Articles 3.2 and 3.3 of the Sample Contract, that, back in 2008, it had wanted a construction manager to perform. In April 2010, Respondent's Office of the Chief Auditor issued a report (April 2010 Audit Report) critical of Respondent's use of the "Construction Management at Risk delivery method" in connection with 14 projects "which were included in the Construction Management at Risk Kitchen/Cafeteria RFQ No. 2006-12-FC." The report read, in pertinent part, as follows: The projects included in RFQ No 2006-12-FC were sufficiently completed by the Architect/Engineer firm(s) prior to being advertised as CM at Risk construction projects. The inability [of] any CM firm to provide "professional services" and scheduling of both design and construction phases represents a deviation from the intent of Florida Statutes, SREF and the School Board's CM at Risk contract.[7] In nearly every executed CM at Risk agreement in the Kitchen/Cafeteria program, the Pre- Design and Design phase responsibilities of the CM were stricken from the contract. That is a further representation that the input required by a prospective CM to qualify for the committee selection process was not, nor was it intended to be provided. F.S. 1013.45(1)(c) also states that the use of the CM at Risk delivery method " . . . shall not unfairly penalize an entity that has relevant experience in the delivery of construction programs of similar size and complexity by methods of delivery other than program management." All of the projects in the Kitchen/Cafeteria program were originally intended to be "hard-bid" but were changed to the CM at Risk delivery method. One project was removed from the group prior to the due date of submittals for RFQ No. 2006-12-FC. That hard bid project, Margate ES, cost approximately $5.6 million, including nearly $466,226 in change orders, which was approximately $3.3 million less, on average, than the fourteen (14) projects that remained in RFQ No. 2006-12- FC. Due to the change in delivery method, general contracting firms could have been "unfairly penalized" by the decision to use the CM at Risk delivery method, as many local general contractors have the relevant experience in the delivery of construction programs of similar size and complexity by methods other than the CM at Risk delivery method.

Recommendation We recommend that Facilities & Construction Management discontinue developing construction procurement packages (i.e. RFQ and RFP) for award of CM at Risk agreements when construction management services requested are associated with reused, prototypical or otherwise sufficiently developed construction documents. Kitchen/Cafeteria program data indicates that the benefits associated with the CM at Risk delivery method were not realized using prototypical designs, as the program resulted in over $24 million in avoidable fees while circumventing applicable laws and regulations. On May 10, 2010, Mr. Herrmann sent a letter to Respondent's General Counsel requesting, in light of the April 2010 Audit Report, a "legal opinion related to the award of a Construction Manager at Risk Agreement (CM) to [Petitioner] and whether such an award would comply with Chapter 1013.45(1)(c), S. and State Requirements for Educational Facilities 1999 (SREF)," given that the FHS Project (as scaled back) was then "in the design phase and Phase III 100% Construction Documents [were] being prepared." The concluding paragraph of the letter read as follows: In this project, The Weitz Company has been selected by the board and we intend to recommend award of a contract within several months. An award of a CM agreement in this case would not violate the specific audit recommendation and we believe such an award does not violate statute or SREF. Please advise whether you concur. Mr. Herrmann has since changed his opinion. He now believes (reasonably so, in the undersigned's view) that "award of a CM agreement" in the instant case would be inconsistent with the "audit recommendation" inasmuch as the FHS Project (as scaled back) now has "sufficiently developed construction documents." On May 18, 2010, Mr. Herrmann sent another letter to Respondent's General Counsel. This letter read as follows: This is to provide you with additional information relating to a request for a legal opinion regarding the award of a Construction Manager at Risk Agreement (CM) to The Weitz Company. Please also refer to the attached memos dated 10/14/09, 11/16/09 and 5/10/10. In summary, we have requested opinions based on the following: Whether such an award would comply with applicable statutes, SREF, and board policy given the extent of the changes to the scope and budget. Whether such an award would comply with Chapter 1013.45(1)(c), F.S. and State Requirements for Educational Facilities 1999 (SREF). We have recently revised the construction cost estimate as a result of current market conditions, and the project consultant, Manuel Synalovski [Associates], LLC agrees with the revised estimate. The change in the cost estimate is as follows: In the RFQ: $29,150,340 October 2009 (Change in scope): $21,770,000 November 2009 (Market conditions): $18,297,367 May 2010 (Market conditions) $16,950,000 Please advise whether we should proceed with the award or reject all bids. Respondent's General Counsel responded to neither of these May 2010, letters from Mr. Herrmann. As the parties stipulated in Admitted Fact 34, "[o]n June 15, 2010, [Respondent] approved Item J-15 during its June 15, 2010, Regular Meeting." The "Requested Action" and "Summary Explanation and Background" section of the Agenda Request Form for this agenda item (J-15) provided as follows: REQUESTED ACTION Approve the change in the delivery method from Construction Management at Risk to Design/Bid/Build and the First Amendment to the Professional Services Agreement with Manuel Synalovski Associates, LLC (MSA) for Fort Lauderdale High School, Phased Replacement Project No. 095-27-01, dated February 12, 2008. SUMMARY EXPLANATION AND BACKGROUND Scope of Work: Basic Services Amended 6/15/10: This item changes the delivery method from Construction Management at Risk to Design/Bid/Build. Demolish existing Swimming pool (Buildings 15 and 16); demolish existing tennis courts; demolish Buildings 1, 2, and 3; construct two 3-story buildings (1 administration and 1 classroom) of approximately 68,940 gross square feet combined to include administration, 3 general classrooms, 5 resource rooms, 4 science labs and related spaces, 4 ESE classroom suite, 1 business technology lab, 1 family and consumer science (ProStart) lab, 1 health occupations lab, 1 pre-law public service education lab, custodial spaces, textbook storage, and student, staff, and public restrooms. Remodel existing science building (Building 8). Construct new parent drop off and pick up areas and staff/visitor parking. Construct new student parking area on the west side of site to increase parking capacity by 92 spaces. Modify existing temporary bus loop to meet SREF, Florida Building Code and ADA Standards. ADA modifications will include barricades and covered sidewalk. Remodel existing courtyard for ADA access to gym and auditorium. MSA and the Superintendent's Negotiations Committee negotiated a total reduction in [architectural] fees from the February 12, 2008 Board approved amount of $2,021,000 to $1,683,650. This decrease in the Basic Services Fees totals $337,350 and is decreased as follows: Phase IV (Bidding and Award) by $54,357, Phase V (Construction Administration) by $269,250, and Phase VI (Warranty) by $13,743. This fee reduction is as a result of a reduction of the original scope as per Attachment 2 to the First Amendment. This First Amendment also reduces the Fixed Limit of Construction Cost (FLCC) from $29,150,340 to $16,950,000 as a result of the reduction in scope and construction costs resulting from current market conditions. The Risk Management Department and the Office of the Chief Auditor have reviewed this First Amendment. The School Board Attorney has approved this First Amendment as to form and legal content. As the parties stipulated in Admitted Fact 35, on June 30, 2010, "[Respondent] posted its Revised Recommendation[] and Tabulation for [the FHS Project, which] set forth the following recommendation": Per Article VII.A of the RFQ, based upon the recommendation of the Qualification Selection Evaluation Committee, the Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on July 20, 2010, reject all responses received for Fort Lauderdale High School Project No. P.000687. The original, intended scope of work as set forth in the original RFQ is substantially and materially different than the revised scope of work and budget in the proposed contracts and such work should be re- advertised and re-bid. This decision to "reject all responses" and "re- advertise[] and re-bid" was based on an honest and good faith exercise of discretion, intended, ultimately, to allow Respondent to receive (in the words of Mr. Herrmann) "more bang for [its] buck." As the parties stipulated in Admitted Facts 39 through 41, Petitioner timely protested Respondent's intended "reject[ion] [of] all responses." As the parties stipulated in Admitted Facts 42 through 44, after the parties had unsuccessfully attempted "to resolve the protest by mutual agreement," Respondent, at Petitioner's request, referred the matter to DOAH on August 23, 2010.

Florida Laws (19) 1010.041011.011011.0121011.061013.351013.451013.461013.61120.569120.57120.68255.05255.103287.012287.017287.055287.09451320.03481.229
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer