Findings Of Fact On November 1, 1982, Respondent Janson filed a Joint Application for a dredge and fill permit from Respondent, Department of Environmental Regulation, and from the Department of the Army Corps of Engineers. The project described in that application involved the construction of an approximately 1,000-square- foot, pile-supported residence, landward of the mean high water line but within the landward extent of Robinson Creek in St. Johns County, Florida. The proposed project also involved the placement of approximately 35 cubic yards of fill and a 30-foot culvert within a small (approximately 4-foot), tidally- influenced roadside ditch for driveway access and parking. The original application sought permission to place part of a concrete driveway and tool shed within the landward extent of Robinson Creek. The project is to be constructed on Lot 47, J.A. Lew Subdivision. Respondent Janson owns Lot 47, as well as Lots 45 and 46, which lots are north of and adjoining Lot 47 and also adjoining Robinson Creek. The next adjoining property owner to the north is the City of St. Augustine, Florida, which presumably owns the street. The adjoining property owner to the south of Lot 47 is Virginia P. Melichar. Neither Melichar nor the City objected to the Department's approval of the dredge and fill permit application. In support of his application, Janson retained the services of a registered surveyor and civil engineer, who performed a survey on Lot 47 to determine the location of the mean high water line with reference to the proposed project. That expert determined the location of the mean high water line to be at elevation 2.4 feet. Accordingly, all work contemplated by the dredge and fill permit is upland from the mean high water line. T.J. Deuerling, an environmental specialist for Respondent, Department of Environmental Regulation, visited the project site on December 13, 1982 and on December 30, 1982 in order to prepare the Department's Biological and Water Quality Assessment. As a result of those site visits, Deuerling recommended to Respondent Janson that he modify his permit application by moving the concrete slab and tool shed from the marsh area onto the uplands. Janson did so revise his application. In spite of the name of the permit being sought by Respondent Janson, the project involves no dredging. However, the culvert and its attendant fill would be placed in the man-made roadside ditch. That ditch constitutes a very weak transitional marsh. Although the culvert will eliminate some vegetation within that ditch, the effect of the elimination will be insignificant on water quality. The pilings for the pile-supported residence will also eliminate a small area of marsh. The anticipated shading caused by the pile-supported residence may impact somewhat on the vegetation in a small area below the residence; however, due to the fact that the floor of the house will be eight feet above the ground, light will still be able to penetrate. Therefore, the vegetation below the pile-supported residence will continue to act as a filter for pollutants. Janson has mitigated the small loss in wetlands by modifying his project so as to remove the concrete slab and tool shed from the marsh area to the uplands. Due to the project's small size, no storm water impact can be expected. Additionally, no evidence was introduced to show a violation of any water quality standard as a result of the proposed project. On March 16, 1983, Respondent, Department of Environmental Regulation, executed its Intent to Issue the dredge and fill permit in accordance with the revised application and subject to the conditions that: (1) turbidity curtains be employed in the ditch during the placement of fill over the culvert to contain any turbidity generated, and (2) construction on the uplands be confined to periods of normal water level conditions. On July 5, 1983, the Department of the Army Corps of Engineers issued its Permit and Notice of Authorization. The essence of the testimony presented by the Petitioners, including that of the employees of the St. Johns River Water Management District, who testified in opposition to the proposed project, is that even though Janson's proposed project would not impact water quality in a way that was either significant or measurable (although no one even suggested any specific water quality standard that might be violated), approval of Janson's permit might set a precedent for other projects which might then have a cumulative impact in some unspecified way at some unspecified location. No evidence was offered to show that Respondent, Department of Environmental Regulation's review of permit applications is other than site specific. Further, no evidence was introduced to show any proposed project anywhere having any impact with which Janson's project could be cumulative. Petitioners Sandquist and Shuler live in the neighborhood of the proposed project, perhaps as close as two blocks away.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered dismissing with prejudice the petition filed herein as to each individual Petitioner and issuing a dredge and fill permit to Respondent Janson in accordance with his revised application. DONE and RECOMMENDED this 13th day of January, 1984, in Tallahassee, Leon County, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1984. COPIES FURNISHED: Stormy Sandquist 3 Aviles Street St. Augustine, FL 32084 Marion C. Snider Volla F. Snider 79 Fullerwood Drive St. Augustine, FL 32084 Carmen Ashton 51 East Park Avenue St. Augustine, FL 32084 Reuben D. Sitton Gail P.Sitton 35 Seminole Drive St. Augustine, FL 32084 Sandra N. Shuler 22 East Park Avenue St. Augustine, FL 32084 Patty Severt Greg Severt 1 Fern Street St. Augustine, FL 32084 Nancy Moore Paul Moore, Jr. 6 Fern Street St. Augustine, FL 32084 John D. Bailey, Jr., Esq. P.O. Box 170 St. Augustine, FL 32085-0170 Charles G. Stephens, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301
Findings Of Fact The Petitioner is the owner of five acres of undeveloped real property in Henderson Creek Basin, Naples, Collier County, Florida. The property is dominated at the tree canopy level by medium-sized cypress. The mid-story plant association is made up of a varying mix of wax myrtle, dahoon holly, seedling cypress, and a lesser amount of slash pine. Hypercium, stillingia, poverty grass, and xyris are the major components of the ground cover. In the vicinity of the proposed homesite, the ordinary mean water depth averages 2-4 inches, as indicated by the water marks on the stems of cypress, stillingia, and cypress knees. Based upon the dominant vegetation, the project site is within the jurisdiction of the Respondent for the regulatory purposes set forth by law. The Petitioner intends to build a house on the property for his personal use. In order to construct the residence, the Petitioner applied to the Respondent for a dredge an fill permit. In the application,, the Petitioner seeks a permit which would allow him to place 1,200 cubic yards of sand fill over a .17 acre area of the submerged land. The proposed location for the housepad, septic tank and drainfield is the center of the five acre parcel. This is the predominant area in which the Petitioner seeks to place the fill. A large portion of this part of the property is low and consists of wetlands. The project, as it is designed in the permit application, does not provide the Respondent with reasonable assurance that the applicable water quality standards for the geographical area will continue to be met. In fact, the proposal demonstrates that a violation of the standards will occur. The Petitioner recently cleared 14,340 square feet of the wetlands in the proposed homesite area. The cypress trees which ware removed acted as a pollution filtration system and aided in the cleansing of the standing waters on site. These waters eventually percolate down to the aquifer to become an important source of fresh water for the state. Without the trees, the water will lose an important aid in the natural purification process. In addition to the adverse impact on water quality, the project will interrupt the natural water flow and filtration which has historically occurred when the water located in the low wetland area on the property has overflowed and eventually run into Henderson Creek. The Respondent is required to consider this natural condition in its determination as to whether or not a permit should be issued. The Respondent has indicated that certain changes should be made to the project in order to make it eligible to receive a permit. The Respondent suggested that the Petitioner relocate the fill area for the house pad eighty- five feet to the west of the proposed site. The septic tank and drainfield should be moved one hundred and ten feet to the west. The drive should be reduced to a single lane which leads directly to the housepad. In addition, three culverts should be placed under the drive. The purpose of these modifications would be to minimize the impact of the project on the wetland site. The movement of the project away from the cypress area would minimize the damage to water quality that would occur if the septic system were placed in the wetlands. If the design for the lane and driveway were modified, the harm to the natural sheet flow of the water through the area on its route to the creek would be greatly reduced. Another suggested modification was to remove exotic vegetation which has been planted or which has begun to dominate in some areas because of the clearing of the property which took place before and after the Petitioner purchased the property. The Respondent also seeks a construction plan from the Petitioner which demonstrates that the fill areas will be adequately stabilized and that turbidity will be controlled during construction. The final modification suggested by the Respondent was for the Petitioner to place a deed restriction on the property which would protect the planting areas and the remainder of the wetlands on the site. The Petitioner's expert, Gary L. Beardsley, has recommended that the proposed circular entrance driveway be eliminated and that a single and straightened lane be substituted its place. He further recommended that one 12" diameter culvert should be installed under the lane near the housepad in order to facilitate or equalize any sheet flow on the downstream side. This recommendation is made to substitute for the agency's proposal that three culverts be placed under the straightened lane. In addition, the Petitioner's expert recommended that the septic drainfield be moved 30 feet westward to reduce the fill slope requirements by abutting the house and septic fill pads. The Petitioner should also be required to replant 5,265 square feet of wetland area that he cleared on site with the approval of the Collier Natural Resource Management Department, but without the approval of the Respondent. The Petitioner has not agreed to any of the proposed modifications, including those proposed by his own expert. The Respondent's request for a deed restriction is not necessary to the agency's regulatory function. There was no reason for the request presented at hearing by the agency.
The Issue The issue for determination in this proceeding is whether Respondent, E. Speer and Associates, Inc. (the "Applicant"), should be granted a permit for the construction of a permanent docking facility pursuant to Sections 403.91-403.929, Florida Statutes, and Florida Administrative Code Chapter 17.
Findings Of Fact Whether Quantified Hydrographic Studies Are Necessary For All Marina Applications To Provide Reasonable Assurance That Flushing Is Adequate To Prevent Violations of Water Quality Standards Speer's Exceptions Nos. 1, 4, 5, 6, 7 and 8 in whole or in part take exception to the Hearing Officer's conclusion (stated as a finding of fact) that it is not possible to demonstrate adequate flushing without "quantifying flushing rates and pollutant dispersal rates using objective methods and appropriate hydrodynamic data." (R.O. at 20, 22-24, 47, 49-50, 54, 57-58; F.O.F. Nos. 33, 35, 38-39, 40, 43-45, 64, 66, and 69) It is clear from the tenor of the entire recommended order that the Hearing Officer believes that as a matter of law an expert's opinion is not sufficient to provide reasonable assurances that flushing will be adequate to prevent violations of water quality standards unless that opinion is based on quantified conclusions generated by objective methods and appropriate hydrodynamic data. (R.O. at 47, 49-50, 57-58) Thus, for example, the Hearing Officer opines that quantification of flushing rates and pollutant dispersal rates using objective measurements of appropriate hydrodynamic data is an essential element of the prima facie showing required to be made by the applicant. (R.O. at 47; C.O.L. No. 11) The Hearing Officer places great significance an the following excerpt from the opinion in 1800 Atlantic Developers v. Department of Environmental Reculation, 552 So.2d 946 (Fla. 1st DCA 1989), rev. den., 562 So.2d 345 (Fla. 1990): 1800 Atlantic filed 34 exceptions to the recommended order, most of which were denied in the Department's final order . . . . The final order approved and adopted most of the findings of fact and conclusions of law in the recommended order and denied the permit. The following stated rulings and reasons there for are significant to the issues on this appeal. (emphasis added) We must note at this point that there is no finding of fact in the hearing officer's recommended order that quantifies how productive the marine habitat may be in this case, and no record support for the suggestion that there would be some quantifiable diminution in the quality of the marine habitat attributable to this project [footnote omitted]. (emphasis added) Exception 23 filed by 1800 Atlantic challenged the hearing officer's finding that the project will adversely affect the conservation of fish and wildlife, fishing or recreational values, and marine productivity in the vicinity . . . The Department rejected this exception based upon the hearing officer's general statements, without any quantification whatsoever, of adverse effects upon these matters . . . (emphasis added) 1800 Atlantic, 552 So.2d at 951-952. I do not concur that 1800 Atlantic stands for the proposition that quantified hydrographic measurement of flushing is in all cases an essential element of a prima facie showing that a marina project will not cause violations of water quality standards. Notwithstanding the above noted statement of the court in 1800 Atlantic that "there is no finding of fact . . . that quantifies 'how productive the marine habitat may be' . and no record support . . . that there would be some quantifiable diminution in the quality of marine habitat attributable to [the] project," 552 So.2d 951, the court did not reject the finding that the project adversely affected the conservation of fish and wildlife, fishing or recreation values, and marine productivity. Indeed, had the court rejected the above finding due to lack of quantified findings the court would never have gone on to reach the issue of mitigation because in 1800 Atlantic mitigation could only become relevant if the applicant was unable to provide reasonable assurance that the project satisfies the public interest criteria of Section 403.918(2) (a), Florida Statutes. See Section 403.918(2)(b), Florida Statutes. I do agree that in some cases quantified hydrographic studies of flushing may be required in order to provide reasonable assurances. Thus, in Rudloe v. Dickerson Bavshore, Inc., 10 FALR 3426 (DER Case No. 87-0816, June 9, 1988), my predecessor held that a dye tracer study was necessary to provide quantitative information about dilution rates and directions on dispersion of pollutants emanating from a proposed marina site which was in "close proximity" to Class II waters approved for shellfish harvesting. 10 FALR at 3447-48. However, the need for such quantified studies must be determined on a case by case basis and is not required as a matter of law for all marinas. 5/ Far me to determine as a matter of law that experts may establish a fact only by certain types of evidence would be an unwarranted and unwise intrusion into the scientific domain of the expert. Thus, in Kralik v. Ponce Marine, Inc., 11 FALR 669, 671 (DER Final Order, Jan. 11, 1989), my predecessor held that expert testimony with regard to flushing does not lack credibility just because a hydrographic study had not been conducted. Of course, the finder of fact has the ultimate say on how much weight an expert opinion should be given if it is not based on a quantified study. Thus, whether an expert testifying on adequacy of flushing has conducted a quantifiable hydrographic study merely goes to the weight of the evidence. Kralik, 11 FALR at 671. I only conclude that a quantified hydrographic study for a proposed marina is not in all cases essential for a showing of reasonable assurances that water quality standards will not be violated. Accordingly, to the extent that the Hearing Officer's findings of fact state that a quantified hydrographic study is required in all cases as a prima facie element of a showing of reasonable assurance that a project will not violate water quality standards, I reject such statement as a mislabled and incorrect conclusion of law. Reasonable Assurance That Flushing Is Adequate To Prevent Violations of Water Quality Standards I read Speer's Exceptions Nos. 1, 3, 4, 5, 6, 7 and 8 in whole or in part as taking exception to the Hearing Officer's finding that under the facts of this case a quantified hydrographic study was needed in order to provide reasonable assurance that the project would not cause violations of water quality standards, and that because such a quantified hydrographic study had not been conducted, reasonable assurances had not been provided. (F.O.F. Nos. 33, 35, 38- 39, 40, 43-45, 64, 66 and 69) As noted by the Hearing Officer, the applicant's expert testimony concerning the adequacy of the flushing consisted of general statements describing visual observations of river and tidal flows which, together with past experience and knowledge of the general area of the project, formed the basis for the experts' opinions that a quantified hydrographic study was not necessary for this project. (R.O. at 22-23) Thus, far example, Mr. Charles C. Isiminger, accepted as an expert in marina design and hydrographic engineering testified that based on his knowledge of the area, its riverine and tidal flows, a hydrographic documentation was not needed to provide reasonable assurance that the project would not cause water quality violations. Mr. Isiminger also testified that any pollutants entering the water from the marina would be flushed out of the area within one tidal cycle. (Tr. at 65-66, 70, 77- 79, 93, 110, 125, 128, 134) Mr. Thomas Franklin, an environmental supervisor from the Department testified that: the hydrographic survey was not really necessary due to the location of the project being in open waters and in close vicinity to the Inlet with a large volume of tidal waters moving in this area, plus the fact that it was further enhanced by flushing due to the St. Lucie River being -- basically coming around Hell Gate point [sic] and funneling out into this estuary. (emphasis added) TR at 437. Other experts also testified that the area was well flushed and that a quantified hydrographic study was not needed in this case. (Jacqueline Kelly, Tr. at 187; John Meyer, Tr. at 319, 322, 341; Gerald Ward, Tr. at 44749) 6/ Speer asserts that the Hearing Officer's finding that a quantified hydrographic study is required in this case cannot stand in light of the unrebutted expert testimony that the marina site will be well flushed and that the rate of flushing provides reasonable assurances the water quality standards will not be violated. I have found no competent substantial evidence in the record which would support a finding that under the facts of this case a quantified hydrographic study is required. I did note that in Footnote 21 of the Recommended Order (R.O. at 20) the Hearing Officer states: Tidal range is only one of the types of data used to quantify flushing rates and pollutant dispersal rates. See TR at 78. Other appropriate data include: overall flow rates, mid tide flow, flow amplitude (the magnitude of the flow without regard to direction, i.e., speed as opposed to velocity), horizontal current distribution, downstream plume characteristics, and field verification using a dye tracer. All of this data is needed to fully describe and quantify flushing rates and pollutant dispersal rates. (citing testimony of Mr. Isiminger at Tr. 88-94) At first blush this may appear to be competent substantial evidence supporting a finding that a quantified hydrographic study is necessary in this case. However, when the testimony is read in its complete context, it is clear that Mr. Isiminger is testifying as to what is necessary to do a hydrographic study when one is needed, and is not testifying that such a study is needed in this case. (Tr. 88-94). I also note that the record contains a memo written by Dr. Kenneth Echternacht, a hydrographic engineer employed by the Department. (Tr. at 67-70) This memo was admitted without objection. (Tr. at 23) The memo states in part that "without . . . hydrographic documentation, reasonable assurance cannot be given that the project will not cause problems." (Tr. at 70; Pet. Exh. No. 10) 7/ Dr. Echternacht was not called as a witness at the hearing and the letter was not offered as evidence of the opinion of Dr. Echternacht or the Department at the time of the de novo hearing. To the contrary, the above noted testimony of Mr. Franklin and the testimony of Jacqueline D. Kelly, an environmental specialist of the Department accepted as an expert in evaluating impacts of environmental dredge and fill projects (Tr. at 187, 195; R.O. at 3), clearly establish that at the time of the de novo hearing the Department was of the opinion that further hydrographic documentation was not needed. The Hearing Officer noted that Mr. Meyer testified that the flushing is a "very, very complicated dynamic situation." (Tr. at 320). The testimony was as follows: Q. So you don't know for sure whether the currents here impact this at all or stay offshore from it? A. Oh, the currents definitelv affect it, and you do have interchange -- as I mentioned before, a very high rate of interchange on a daily basis on every tide. Q. Are you saying that the current that flows through here every day flows right through the site? A. We're dealing with two different things here. We're dealing with your currents, your general migration of waters from the estuary from the inland areas down. You're also dealing with tidal effects coming in and out, and it's a very, very complicated dynamic situation. For me to try to tell you exactly how these things work would be impossible without having a very, very long drawn-out expensive study done on the entire area, and I have not reviewed any studies like that. Tr. at 319-20 (emphasis added) When taken in its context it is clear that Mr. Meyer is testifying that there is a very high rate of exchange on a daily basis on every tide. The fact that he viewed the exact details of the flushing as very complicated in no way retracted his statement that there was a very high rate of exchange on every tide. My review of the record leads me to concur with Speer that no testimony, either on direct, cross-examination, or examination by the Hearing Officer, nor any other evidence was introduced to rebut the expert testimony presented by Speer and the Department that flushing on the site was adequate to provide reasonable assurance that water quality standards will not be violated. 8/ As a general rule, the trier of fact may not arbitrarily reject uncontroverted evidence as proof of a contested fact. Merrill Stevens Dry Dock Co. v. G. & J. Investments, 506 So.2d 30 (Fla. 3d DCA 1987), rev. den., 515 So.2d 229 (Fla. 1987); City of St. Petersburg v. Vinoy Park Hotel, 352 So.2d 149 (Fla. 2d DCA 1977); In Re: Estate of Hannon, 447 So.2d 1027 (Fla. 4th DCA 1984). This does not mean that a mere scintilla of unrebutted evidence is sufficient to establish a contested fact in an administrative hearing. At least in the context of administrative proceedings, the unrebutted evidence still must be competent substantial evidence to support a finding of fact. 9/ There is no suggestion that the Hearing Officer rejected the unrebutted testimony of the experts of Speer and the Department as not being competent substantial evidence. In fact, in the light of the testimony of Mr. Isiminger (Tr. at 65- 66), Mr. Ward ( Tr. at 447-449), Mr. Meyer (Tr. at 238- 239), and Mr. Franklin (Tr. at 345-350), it is beyond peradventure that there is competent substantial evidence to support a finding that flushing is adequate to provide reasonable assurance that the marina will not cause violations of water quality standards. It is clear from the context of the Recommended Order that the Hearing Officer believed that reasonable assurance had not been provided only because he believed that a quantified hydrographic study was required as a matter of law. Although I reject the Hearing Officer's conclusion that a quantified hydrographic study must be conducted as a matter of law for all marina applications, I must still determine whether a quantified hydrographic analysis is required under the facts of this case. In Rudloe v. Dickerson Bayshore, 10 FALR 3426 (DER Final Order, June 9, 1988) it was held that a hydrographic study was not adequate because it did not include a quantified dye tracer study. Id., 10 FALR at 3448. In Rudloe, as in this case, the marina was located in Class III waters, but near Class II waters. However, in Rudloe, the marina site was much closer to the Class II waters (approximately 1,700 feet in Rudloe (10 FAIR at 3430) as compared to approximately 8,000 feet in this case). (R.O. at 16, F.O.F. No. 26) Also, the Rudloe case is significantly different from this case in that competent substantial expert opinion was presented in Rudloe that the marina would adversely impact the Class II shellfish harvesting area. See Rudloe, 10 FALR at 3433-35, 3437-38 (testimony of DNR expert that operation of marina would result in closure of waters to the harvest of shellfish; testimony of Dr. Robert Livingston that the hydrographic drogue studies conducted were inadequate.) In this case, neither expert nor lay testimony was offered by Barringer to show that operation of the marina would result in violation of water quality standards or have any adverse impact on the Class II shellfish waters. 10/ I conclude that the facts of this case as found by the Hearing Officer are not sufficiently similar to the facts of Rudloe so as to justify holding as a matter of law a quantified hydrographic study is necessary to establish the required reasonable assurances. Since the record contains competent substantial evidence that flushing is adequate to provide reasonable assurance that the marina will not cause water quality violations, and since there is no competent substantial evidence in the record to support the Hearing Officer's contrary finding, I must accept the exception of Speer and reject the Hearing Officer's findings of fact to the contrary. In this case I note that I am not so much rejecting findings of fact as rejecting a conclusion of law. As I noted, the Hearing Officer's finding is really based on a conclusion of law which I reject. This leaves only unrebutted competent substantial evidence that there will be adequate flushing to provide reasonable assurance that the operation of the marina will not result in water quality violations. There is no rational basis to reject this unrebutted competent substantial evidence. Therefore, I must accept as proven that the applicant has provided the reasonable assurances that operation of the marina will not result in water quality violations. Merrill Stevens Dry Dock; City of St. Petersburg; Estate of Hannon; supra, Effect On Class II Waters Speer's Exceptions Nos. 7 and 8 take exception to the Hearing Officer's finding that Speer failed to provide reasonable assurance that the marina would not have a "negative effect" an the Class II waters of the St. Lucie Inlet and the Great Pocket. (F.O.F. No. 43) Rule 17-312.080(6)(b), Fla. Admin. Code provides: The Department also shall deny a permit for dredging and filling in any class of waters where the location of the project is adjacent or in close proximity to Class II waters, unless the applicant submits a plan or proposes a procedure which demonstrates that the dredging or filling will not have a negative effect on the Class II waters and will not result in violations of water quality standards in the Class II waters. In this case expert testimony was presented by Speer and the Department that due to the distance of the marina site from the Class II waters (8,000 feet) the marina site was not in close proximity to the Class II waters, and due to the rapid flushing of the area, the construction and operation of the marina would neither have a negative effect nor would result in violations of water quality standards in the Class II waters of St. Lucie Inlet and the Great Pocket. (Isiminger, Tr. at 96, 126-27; Meyer, Tr. at 254-55) I find that the record contains no competent substantial evidence to rebut the evidence introduced by Speer and the Department that the marina will have no negative effect on Class II waters and will not result in violation of water quality standards in Class II waters. Accordingly, I must accept Speer's exception and reject the Hearing Officer's finding. Merrill Stevens Dry Dock; City of St. Petersburg; In Re: Estate of Hannon; supra. Reasonable Assurance That Operation Of The Marina Will Not Result In Prop Dredging Or Violations Of The State Water Quality Criterion For Turbidity Speer's Exceptions Nos. 1, 2, 9-12, and 16 in whole or in part take exception to the Hearing Officer's finding that Speer failed to provide reasonable assurance that the boat traffic from operation of the marina would not cause prop dredging or violations of the water quality criterion for turbidity. (F.O.F. Nos. 33-34, 45, 48, 52-53, 64, and 67) 11/ On one hand, there was testimony that the depths of the marina, in combination with the size of boats allowed in the various slips, would allow for a one foot clearance from the bottom of the boats to the bottom of the marina, and that this clearance, in combination with speed limits in the marina, would provide reasonable assurance that operation of the marina would not result in prop dredging or turbidity violations. (Isiminger, Tr. at 104-107, 118; Meyer Tr. at 263-65, 299, 304- 305; Kelly, Tr. at 189-190; Ward, Tr. at 460) On the other hand, Bruce Graham, admitted as an expert in marine biology testified that: "A large boat, three feet from the bottom, I think would resuspend sediment." (Graham, Tr. at 378). The Hearing Officer, noting that when asked if one foot clearance is sufficient to prevent prop dredging and resultant turbidity violations, a Department witness, testified: I would have to say that we simply don't have enough documentation to know this for a fact. We know that a foot gives us a degree of comfort that there will not be prop wash. In certain instances -- a tug boat, for instance, you know, with huge engines, you're going to have prop wash over a much -- over a large area and with probably much more than a foot of clearance. But for the normal, typical marina a foot, as I say, gives us a degree of comfort that we have settled on. Neyer, Tr. at 264. The Hearing Officer concluded that the witnesses of Speer and the Department could not explain the reasons or efficacy of the "one foot policy" except to say that in their experience the one foot policy was adequate to prevent prop dredging and turbidity violations. (R.O. at 28 n.35)0 The Hearing Officer thus found that Speer and the Department failed to "prove up" the one foot policy -- i.e., failed to elucidate and explicate the reason for the policy. 12/ Clearly the Hearing Officer placed more weight on the testimony of Mr. Bruce Graham than that of Isiminger, Meyer, Kelly and Ward. Since I cannot say that the testimony of Graham was not competent substantial evidence, I am not at liberty to reweigh the evidence or reject the Hearing Officer's finding of fact. See, Florida Dept. of Corrections v. Bradley, 510 So.2d 1122 (Fla. 1st DCA 1987); Heifetz v. Department of Business Regulation, 475 So.2d 1277, 1281 (Fla. 1st DCA 1985); Sections 120.57(1)(b)10., and 120.68(10), Florida Statutes. Speer contends that Barringer presented no evidence that prop dredging will cause sufficient turbidity to violate the state water quality turbidity criterion of 29 NTUs. 13/ That contention misses the point. The burden is on Speer to establish by the preponderance of evidence that reasonable assurance has been provided that operation of the marina will not result in violations of the water quality criterion for turbidity. Florida Department of Transportation v. J.W.C., Co., 396 So.2d 778 (Fla. 1st DCA 1981). The Hearing Officer, as the finder of fact, concluded that Speer failed to do so. Accordingly, I reject the exception of Speer and accept the Hearing Officer's finding of fact that Speer failed to provide reasonable assurance that operation of the marina would not cause prop dredging or violations of the state water quality criterion for turbidity. Manatee Impacts and the Public Interest Test Speer's Exceptions Nos. 13 and 17 take exception to the Hearing Officer's finding that Speer failed to do a quantified study of impacts to manatees and therefore failed to provide reasonable assurance that the marina will not have an adverse impact on manatees, their migratory patterns, and their habitat. (F.O.F. Nos. 61, 64 and 68) The Hearing Officer reasoned as follows: Instead of a traffic study, the Applicant and DER presented evidence in the form of general statements that manatees need not migrate north and south through the approach channel. According to the Applicant and DER, manatees can migrate across the project site by one of two alternative routes. They can migrate in one or two feet of water under moored boats and then under wave breaks on the north and east piers, or they can migrate in the shallow water landward of the west boundary of the project. That evidence was not persuasive and was controverted by competent, substantial, and persuasive evidence that manatees would be deterred from migrating under the project footprint by substantial obstacles in their path. Manatees migrating under the project footprint would be exposed to 86 or more moving boats with powerful engines and drafts of four to five feet in waters covering approximately 20,800 square feet. It could be argued, or course, that 86 or more boats would not be moving in and out of the marina at one time. However, it is impossible to estimate occupancy rates, length of stay, and frequency of boat trips without a traffic study. (R.O. at 35, n. 51) As Speer's exception notes, there was testimony that because of the width of the river and boat speed restrictions in the project area, there would be no adverse impacts an the manatee from the marina. (Kelly, Tr. at 162; Meyer, Tr. at 255-56, 331- 32; Isiminger, Tr. at 130) The St. Lucie/Jupiter/Hobe Sound waterways are a major travel corridor for manatees. (DER Exh. No. 4) Between 1974 and December 1990, there were ten water craft related manatee fatalities within the boating sphere of influence of the project. (DER Exh. No. 4) In order to reduce impacts on the manatees, the proposed permit contains the following specific conditions: S.C. No. 13: The permittee agrees to install and maintain a minimum of one manatee education/display on the main access pier during and after construction. S.C. No. 15: The permittee agrees that any collision with a manatee shall be reported immediately [to DNR and U.S. Fish and wildlife Service]. S.C. No. 18: The permittee shall post four (4) manatee area/slow speed signs, two of which would be spaced along the perimeter pier and two of which would be located on the outside of the marina for all boating traffic to observe within the marina facility. (DER Exh. No. 3) 14/ There was testimony that the piers, once constructed, would not impair the passage of manatees. (Isiminger, Tr. at 114- 115) On the other hand, there was some testimony that manatees may have to go around the project rather than through it. (Meyer, Tr. at 311) The existing boat traffic past the site of the project to the Inlet was "rough1y estimated" at 50 to 100 boats a day. (Meyer, Tr. at 337) The U.S. Fish and Wildlife Service determined that "while [the project] may negatively affect, it is not likely to jeopardize the continued existence of the West Indian Manatee." (Tr. at 120-21) The Hearing Officer concluded that reasonable assurance as to adverse impacts on manatees could not be provided absent a quantified traffic study. (R.O. at 35, n. 51) In Coscan Florida, Inc. v. Department of Environmental Regulation, 12 FAIR 1359 (DER Final Order March 9, 1990), the Department held that the information needed to determine a marina's impact on manatees and the necessary actions to mitigate such impacts must be decided an a case by case basis. For example, in Sheridan v. Deep Lagoon Marina, 11 FALR 4710 (DER Final Order, Aug. 24, 1989), 15/ a marina sought to expand by adding 113 new wet slips. The marina was required to develop a manatee protection plan far the surrounding portions of the Caloosahatchee River, all new slips were limited to sail boats until the manatee protection plan was implemented and enforced, and power boat occupancy was limited to 75% of the total 174 wetslips in any event. The marina also made available a wet slip for use by the Florida Marine Patrol. In this case there is evidence of significant boat related manatee fatalities in the boating sphere of influence of the proposed marina. There is also evidence of existing traffic of 50-100 boats per day past the project site. In view of the fact that this project would add 86 slips and a public fueling facility, it seems likely that that the project will significantly increase both boat traffic and the threat of manatee collisions. Accordingly, I concur with the Hearing Officer that there is competent substantial evidence to support a finding that further studies are needed to determine what, if any, additional manatee protection conditions are needed to provide reasonable assurance that manatees will not be adversely affected. I conclude that the applicant did not provide reasonable assurance that the operation of the marina will not have an adverse impact on manatees, their migratory patterns, and their habitat, and therefore failed to provide reasonable assurance that the project is not contrary to the public interest. Therefore, I reject the exception of Speer. Cumulative and Secondary Impacts Speer's Exception No. 15 takes exception to the Hearing Officer's finding that the applicant failed to provide reasonable assurance that there will be no adverse cumulative pacts created either by the cumulative effects of the object and existing similar projects, or by secondary pacts of the project itself. (F.O.F. No. 66) 16/ Cumulative impact analysis takes into consideration the cumulative impacts of similar projects which are existing, under construction, or reasonably expected in the future. Conservancy v. A. Vernon Allen Builder, supra; Section 403.919, Florida Statutes. Secondary impact analysis considers the impact of the project itself and of any other relevant activities that are very closely linked or causally related to the permitted project. Conservancy, 580 So.2d at 778; J.T. McCormick v. City of Jacksonville, 12 FALR 960, 980. 17/ Thus, in Conservancy the secondary impact analysis was required to consider the environmental impacts of development of 75 estate homes on an island where the development would be reasonably expected as a result of the permitted laying of a subaqueous sewer line. Similarly, in del Campo v. Department of Environmental Regulation, 452 So.2d 1004 (Fla. 1st DCA 1984), the Department was required to consider the environmental impacts of the foreseeable development of an island facilitated by the permitted building of a bridge to the island. In this case there is competent substantial evidence that there are other marinas located 1,750 feet downstream in Willoughby Creek, and 5,000 feet downstream in Manatee Pocket. (R.O. F.O.F. 31; Isiminger, Tr. at 112; Meyer, Tr. at 261) The record contains competent substantial evidence that the cumulative impact of the project and the existing marinas in Willoughby Creek and Manatee Pocket will not result in violations of state water policy. (Isiminger, Tr. at 125; Kelly, Tr. at 167) I cannot say that the testimony of Isiminger and Kelly on cumulative impacts is not competent, substantial evidence. In light of the fact that there is no competent substantial evidence to indicate that cumulative impacts would result in water quality violations, I must accept Speer's exception and reject the Hearing Officer's finding. Merrill Stevens Dry Dock; City of St. Petersbur; In re: Estate of Hannon; supra. As to secondary impacts, the Hearing Officer pointed out that Speer did not introduce any evidence as to whether there would be secondary impacts to water quality as the result of further development or increased utilization of the uplands facilities. (See F.O.F. 66, n.59, R.O. at 39) Such further development or increased utilization of upland facilities is reasonably foreseeable and would be very closely linked or causally related to the building of an 86 slip marina with public fuel services. As noted above, the applicant has the burden of providing reasonable assurances as to cumulative and secondary impacts. Brown v. DER, supra; Conservancy, supra. However, neither the pleadings nor the pre-hearing stipulation raised the issue of the adequacy of the secondary impact analysis. In a case such as this where the Department's notice of intent to issue a permit has been challenged by a third party, the applicant's prima facie case need only include the application and the accompanying documentation and information relied on by the Department as the basis of its intent to issue. Florida Department of Transportation v. J.W.C., 396 So.2d 778, 788 (Fla. 1st DCA 1981). The petitioner challenging the permit must identify the areas of controversy and allege a factual basis for its contentions that the applicant did not provide the necessary reasonable assurances. J.W.C., 396 So.2d at 789. See also Woodholly Assoc. v. Department of Natural Resources, 451 So.2d 1002, 1004 (Fla. 1st DCA 1984). Since Barringer did not identify this issue and did not allege any factual basis for a contention that the secondary impact analysis was inadequate or incorrect, I may not rule on the issue in this order. Miscellaneous Exceptions To Findings of Fact Speer's Exception No. 14 takes exception to the Hearing Officer's finding that Speer failed to provide reasonable assurance that the project will have no adverse impact on (1) the relative value of functions being performed by areas affected by the project, including seagrasses, shell fish, and fin-fish, and (2) recreational and commercial values in the vicinity. (F.O.F. No. 64) Speer contends that this finding is not supported in the record by competent substantial evidence and is contrary to unrebutted testimony of Ms. Kelly and Mr. Isiminger. (Kelly, Tr. at 159, 161-62, 165-67; Isiminger, Tr. at 73) I cannot say that the testimony of Isiminger and Kelly is not competent, substantial evidence, and I find no evidence in the record to rebut the testimony of Kelly and Isiminger. Therefore, I must accept Speer's exception and reject the Hearing Officer's finding. Merrill Stevens Dry Dock; City of St. Petersburg; In re: Estate of Hannon; supra. Speer's Exception No. 3 takes exception to the Hearing Officer's finding that Speer failed to provide a current water quality analysis. (F.O.F. No. 35) A water quality analysis was submitted in April of 1990, shortly after the permit application was filed. (R.O. at 2, 19; F.O.F. No. 34) I find no competent substantial evidence in the record to suggest any reason for believing that the water quality has changed since April of 1990. I agree with Speer that, absent some specific reason for believing that the water quality has changed since the date of a study conducted contemporaneously with the permit application, there is no requirement to provide an updated water quality analysis. RULINGS ON EXCEPTIONS TO CONCLUSIONS OF LAW Need For Quantified Hydrographic Study Speer's Exceptions Nos. 1, 7 and 9, in whole or in part, take exception to the Hearing Officer's conclusions of law that a quantified hydrographic study was needed to provide reasonable assurances that the operation of the marina would not result in violations of water quality standards and would would not have a negative effect on Class II waters. For the reasons stated in Parts III(1), (2) and (3) above, I accept this exception and reject the above noted conclusions of law. Introduction Of Issues Not Set Forth In Pleadings Or Pre-Hearing Stipulations Speer's Exceptions Nos. 1, 2, 3, and 5, in whole or in part, take exception to the Hearing Officer's consideration of issues of (1) the need for a quantified hydrographic study, (2) the proximity of the site to Class II waters, (3) turbidity and prop dredging, (4) cumulative impacts, and (5) the need for a quantified study on manatee impacts. For the reasons set forth in Part 111(6) above, I agree that, absent waiver, a petitioner challenging an intent to issue a permit may not raise issues at the hearing which were not raised in the pleadings or pre-hearing stipulations. However, in this case the issue of manatee impacts was raised in the pleadings, and Speer was on notice that it had the burden of proof on that issue. As to the other issues, even if I accepted far the sake of argument that they were not raised in the pleadings or pre-hearing stipulations, Speer failed to timely object to the raising of these issues at the hearing and therefore waived any objection. See Sarasota County and Midnight Pass Society v. Department of Environmental Regulation, 13 FAIR 1727 (DER Final Order, April 4, 1991). Therefore, I reject the above exceptions. Proximity To Class II Waters Speer's Exception No. 2 takes exception to the Hearing Officer's conclusion of law that Speer was required to submit a plan which demonstrated that the marina would not have a negative effect on Class II waters. (C.O.L. Nos. 12 and 13) I do not agree that where a proposed marina site is 8,000 feet from Class II waters and where the site is rapidly flushed as noted in Parts 111(1), (2) and (3) above, that the site is in close proximity with the Class II waters within the meaning of Rule 17-312.080(6), Fla. Admin. Code. Accordingly, I accept this exception and reject the above note conclusion of law. Public Interest Test Speer's Exception No. 4 takes exception to the Hearing Officer's conclusion of law that Speer failed to provide reasonable assurance that the project was not contrary to the public interest. (C.O.L. Nos. 17 and 20) For the reasons set forth in Parts III(4) and (5) above, I reject this exception. Cumulative Impacts Speer's Exception No. 5 takes exception to the Hearing Officer's conclusion of law that Speer failed to provide reasonable assurances that cumulative impacts would not result in water quality violations, and that such assurances could only be provided by a quantified study. For the reasons set forth in Parts III (1), (2), (3) and (6) above, I accept this exception and reject the above noted conclusions of law. Modification Of Permit Conditions Speer's Exception No. 6 takes Exception to the Hearing Officer's conclusions of law Nos. 24-34. These conclusions of law concern questions of the authority of the Hearing Officer and me to modify the conditions of the permit. I agree with Speer that since none of the parties have requested any modifications, these conclusions of law are irrelevant. 18/ Therefore I accept the exception and reject the above noted conclusions of law as irrelevant. Miscellaneous Speer's Exception No. 8 in part takes exception to the Hearing Officer's conclusion that Speer and the Department failed to provide reasonable assurance as to prop dredging and turbidity violations because neither Speer nor the Department sufficiently proved the basis for the one-foot clearance policy. For the reasons set forth in Part III(4) above, I reject this exception. Speer's Exception No. 8 in part takes exception to the Hearing Officer's conclusion that the question of whether mitigation is adequate is a question of law. I agree with the Hearing Officer and reject this exception. See 1800 Atlantic Developers v. Department of Environmental Regulation, 552 So.2d 946, 955 (Fla. 1st DCA 1989).
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that Respondent, Department of Environmental Regulation, enter a Final Order denying the application for a permit to construct the proposed project and denying the request for determination of improper purposes. RECOMMENDED in Tallahassee, Leon County, Florida, this 16th day of June, 1992. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399 1550 (904) 488 Filed with the Clerk of the Division of Administrative Hearings this 16th day of June, 1992.
The Issue The issues to be determined in this case are: whether Petitioners have standing; and whether Rule 62-302.800(2) is an invalid exercise of delegated legislative authority, as defined by Section 120.52(8)(b) and (c), Florida Statutes.3
Findings Of Fact Petitioner, St. Johns Riverkeeper, Inc. (Riverkeeper), is a nonprofit, membership-based corporation with its principal place of business in Jacksonville, Florida. It is dedicated to the protection, preservation, and restoration of the ecological integrity of the St. Johns River watershed, monitors water quality in the river and its tributaries, and involves citizens in the decisions that affect the health of the river, and organizes regular boat trips for its members and citizens to learn more about the river and how they can participate in its management. Petitioner, Henry O. Palmer (Palmer), uses the lower St. Johns River (LSJR), including its marine portions and tributaries, for kayaking, boating, and observation of wildlife, and a substantial number of Riverkeeper's members use the LSJR, including its marine portions and tributaries, for boating, fishing, crabbing, observing birds and other wildlife, and other water-based recreational activities. Based on undisputed affidavits, Petitioners are substantially affected by algal blooms and decay and vegetation and fish kills in and along the river. These conditions can be caused by excessive nutrients along with other factors. Respondent, Department of Environmental Protection (DEP), has used the procedures in Rule 62-302.800(2) to establish a Type II site-specific alternative criterion (SSAC) for dissolved oxygen (DO) for the LSJR that is lower than the otherwise-applicable, default water quality standard in Rule 62- 302.530(30). See Fla. Admin. Code R. 62-302.800(5)(a). As a result of the SSAC, DEP revised the Total Maximum Daily Load (TMDL) for total phosphorus (TP) and total nitrogen (TN) allowed for the marine portion of the LSJR. Rule 62-302.800 sets out a procedure for establishing a SSAC. Paragraph (1) sets out the procedure for Type I SSACs, which can be established when a "water body, or portion thereof, may not meet a particular ambient water quality criterion specified for its classification, due to natural background conditions or man-induced conditions which cannot be controlled or abated" and "when an affirmative demonstration is made that an alternative criterion is more appropriate for a specified portion of waters of the state." Paragraph (2), which is challenged in this case, sets out the procedure to petition DEP for a Type II SSAC for unspecified "reasons other than those set forth above in subsection 62-302.800(1), F.A.C." Rule 62-302.800(2) provides in part: The Department shall initiate rulemaking for the [Environmental Regulation] Commission to consider approval of the proposed alternative criterion as a rule if the petitioner meets all the requirements of this subparagraph and its subparts. The petitioner must demonstrate that the proposed criterion would fully maintain and protect human health, existing uses, and the level of water quality necessary to protect human health and existing and designated beneficial uses. If the petition fails to meet any of these requirements (including the required demonstration), the Department shall issue an order denying the petition. In deciding whether to initiate rulemaking or deny the petition, the Department shall evaluate the petition and other relevant information according to the following criteria and procedures: The petition shall include all the information required under subparagraphs (1)(a)1.-4. above. In making the demonstration required by this paragraph (c), the petition shall include an assessment of aquatic toxicity, except on a showing that no such assessment is relevant to the particular criterion. The assessment of aquatic toxicity shall show that physical and chemical conditions at the site alter the toxicity or bioavailability of the compound in question and shall meet the requirements and follow the Indicator Species procedure set forth in Water Quality Standards Handbook (December 1983), a publication of the United States Environmental Protection Agency, incorporated here by reference. If, however, the Indicator Species Procedure is not applicable to the proposed site-specific alternative criterion, the petitioner may propose another generally accepted scientific method or procedure to demonstrate with equal assurance that the alternative criterion will protect the aquatic life designated use of the water body. The demonstration shall also include a risk assessment that determines the human exposure and health risk associated with the proposed alternative criterion, except on a showing that no such assessment is relevant to the particular criterion. The risk assessment shall include all factors and follow all procedures required by generally accepted scientific principles for such an assessment, such as analysis of existing water and sediment quality, potential transformation pathways, the chemical form of the compound in question, indigenous species, bioaccumulation and bioconcentration rates, and existing and potential rates of human consumption of fish, shellfish, and water. If the results of the assessments of health risks and aquatic toxicity differ, the more stringent result shall govern. The demonstration shall include information indicating that one or more assumptions used in the risk assessment on which the existing criterion is based are inappropriate at the site in question and that the proposed assumptions are more appropriate or that physical or chemical characteristics of the site alter the toxicity or bioavailability of the compound. Such a variance of assumptions, however, shall not be a ground for a proposed alternative criterion unless the assumptions characterize a factor specific to the site, such as bioaccumulation rates, rather than a generic factor, such as the cancer potency and reference dose of the compound. Man-induced pollution that can be controlled or abated shall not be deemed a ground for a proposed alternative criterion. The petition shall include all information required for the Department to complete its economic impact statement for the proposed criterion. For any alternative criterion more stringent than the existing criterion, the petition shall include an analysis of the attainability of the alternative criterion. No later than 180 days after receipt of a complete petition or after a petitioner requests processing of a petition not found to be complete, the Department shall notify the petitioner of its decision on the petition. The Department shall publish in the Florida Administrative Weekly either a notice of rulemaking for the proposed alternative criterion or a notice of the denial of the petition, as appropriate, within 30 days after notifying the petitioner of the decision. A denial of the petition shall become final within 14 days unless timely challenged under Section 120.57, F.S. The provisions of this subsection do not apply to criteria contained in Rule 62- 302.500, F.A.C., or criteria that apply to: Biological Integrity. B.O.D. Nutrients. Odor. Oils and Greases. Radioactive Substances. Substances in concentrations that injure, are chronically toxic to, or produce adverse physiological or behavioral response in humans, animals, or plants. Substances in concentrations that result in the dominance of nuisance species. Total Dissolved Gases. Any criterion or maximum concentration based on or set forth in paragraph 62-4.244(3)(b), F.A.C. Despite any failure of the Department to meet a deadline set forth in this subsection (2), the grant of an alternative criterion shall not become effective unless approved as a rule by the Commission. Nothing in this rule shall alter the rights afforded to affected persons by Chapter 120, F.S. Rule 62-302.800 cites several statutes as its specific rulemaking authority and specific provisions of law implemented, including Section 403.061, Florida Statutes, which states in pertinent part: The department shall have the power and the duty to control and prohibit pollution of air and water in accordance with the law and rules adopted and promulgated by it and, for this purpose, to: * * * Adopt rules pursuant to ss. 120.536(1) and 120.54 to implement the provisions of this act. . . . . * * * Adopt a comprehensive program for the prevention, control, and abatement of pollution of the air and waters of the state, and from time to time review and modify such program as necessary. Develop a comprehensive program for the prevention, abatement, and control of the pollution of the waters of the state. In order to effect this purpose, a grouping of the waters into classes may be made in accordance with the present and future most beneficial uses. . . . . Establish ambient air quality and water quality standards for the state as a whole or for any part thereof, and also standards for the abatement of excessive and unnecessary noise. . . . . Section 403.201, Florida Statutes, sets out a separate procedure to apply to DEP for a variance from DEP's rules and regulations, including water quality standards, "for any one of the following reasons": There is no practicable means known or available for the adequate control of the pollution involved. Compliance with the particular requirement or requirements from which a variance is sought will necessitate the taking of measures which, because of their extent or cost, must be spread over a considerable period of time. A variance granted for this reason shall prescribe a timetable for the taking of the measures required. To relieve or prevent hardship of a kind other than those provided for in paragraphs (a) and (b). Variances and renewals thereof granted under authority of this paragraph shall each be limited to a period of 24 months, except that variances granted pursuant to part II may extend for the life of the permit or certification. There was no evidence that the revised TMDLs for TP and TN allowed for the marine portion of the LSJR will lead to algal growth and algal blooms, reduced DO, fish kills, or adverse impacts to recreation on the river. To the contrary, the Type II DO SSAC for the marine portion of the LSJR has not been challenged and conclusively establishes that it will "maintain and protect human health, existing uses, and the level of water quality necessary to protect human health and existing and designated beneficial uses" and will "protect the aquatic life designated use of the water body." Fla. Admin. Code R. 62- 302.800(2)(c). See also Affidavit of Douglas J. Durbin, Ph.D., filed June 25, 2010.
Findings Of Fact The Applicant, John E. Bravo, applied for a dredge and fill permit to construct a dockage facility. The proposed facility will consist of a 910 foot pier with a "T"-shaped platform structure extending perpendicular in two directions from the seaward end of the pier, all of which is designed to accommodate 56 boat slips, restricted to the use of pleasure boats only. The proposed project site is located on the southeast side of "Long Point" and would extend into the waters of East Bay, which is a tidally influenced water body in Bay County, Florida. The project site lies in Class II waters of the State. The waters involved are not approved for shellfish harvesting, however, but rather are under a shellfish harvesting prohibition imposed by the Department of Natural Resources. The portion of East Bay involved also lies within the Intracoastal Waterway. The waterway is approximately 6,000 feet wide at the site of the proposed docking facility. The water along the shoreline of the area is shallow for a considerable distance waterward. The bay bottom is characterized by profuse seagrass for approximately 500 feet waterward of mean high water. Beyond that point, the seagrass (Cuban Shoal Grass) dissipates and disappears. The first 400 feet waterward of the mean high water line at the location of the proposed dock, is shallow and not truly navigable. The water then deepens to approximately five feet at mean low water some 525 feet from the shore. This distance from the shore marks the beginning of the area where no significant amount of seagrass exists and where the boat docking slips and mooring pilings would be installed in a waterward direction down the remaining length of the proposed dock. The water depth continues to increase to approximately 20 feet at the proposed location of the end of the dock. The dock would be constructed of pilings driven into the bay bottom supporting the decking of the walkway portion and "T" portion of the dock. The "T" would be installed on the seaward end of the dock, perpendicular to the walkway portion of the dock with most of the boat slips installed and operated at that point. The length of the docking facility is dictated by the fact that the Applicant seeks to locate the boat slips in a manner so that all boats will be moored and operated well beyond existing seagrasses. In fact, the length of the dock is more than absolutely necessary to accomplish this purpose since water depth and avoidance of seagrasses could accomplished with the dock ending approximately 700 feet from the mean high water line. In an abundance of caution, however, in order to avoid the possibility of propeller dredging and prop wash damaging the bottom substrates and grasses, and since the Intracoastal Waterway is over a mile wide here, the Applicant elected to design the dock in the length and configuration proposed. Such will cause no unreasonable impediment to navigation. In this connection, the Applicant has agreed to post Coast Guard- approved safety lights on the dock which will warn boats of its presence in hours of darkness. Further, the dock does not extend far enough into the 6,000 foot wide Intracoastal Waterway to pose a hazard to barge and other boating traffic in the Waterway. Some of the Petitioner's witnesses revealed that shrimp boats pull their nets during shrimping operations closer than 900 feet to the shore line and in the vicinity of the grass beds. While the presence of the dock may alter the trawling pattern of shrimp boats and the operations of other commercial fishermen, as well as water skiing and boating by members of the public, this may in fact have a beneficial effect by promoting the public interest in preserving marine habitat and the conservation of marine resources by preventing some damage to the grass beds. Such marine grass beds are valuable nursery areas for fishes and other marine animals, the effects upon which must be considered in weighing the various statutory indicia of the public interest which must be satisfied before granting a dredge and fill permit. Further, because the dockage facility at issue would be an isolated one with no significant similar docks in the immediate vicinity, the likelihood that it would pose a navigational hazard to water skiiers, fishermen, shrimpers, and other commercial and recreational interests is rather insignificant. Water Quality The water quality issues posed by a project such as this typically involve the water quality parameters of dissolved oxygen, nutrients, bacteriological quality, turbidity, oils, greases, fuel, paint or varnish, solvents and heavy metals, as contemplated by the below-cited rules concerning general surface water quality criteria and the specific rules related to Class II surface waters. The project site is located in Class II surface waters of the State. Those Class II waters are classified by the Department of Natural Resources as "not approved" for shellfish harvesting. The zone of the Class II waters of East Bay in which shellfish harvesting is not approved extends some two miles eastward of the project site. Marinas and dockage facilities such as this one, which will accommodate fairly large boats in significant numbers, typically pose potential pollution problems involving deposition of nutrients in State waters in the form of fish carcasses and offal, garbage and human wastes. Additionally, boats can pose pollution hazards because of attendant dumping of grease, oil and fuel residues in marina waters as well as the deposition of trash in various forms such as paper and plastic items as a result of human use of the boats and the marina facility itself. Perhaps the most severe potential problem is the deposition of human fecal matter into the water as a result of the flushing of marine heads on the larger boats, which the dockage facility will accommodate in the slips as designed. The fecal coliform bacteria which emanate from the deposition of human wastes into the waters around such a dockage facility can be concentrated in oysters and other shellfish to such an extent as to cause severe illness, permanent disability or even death in humans. Consequently, in order to avoid this problem in a magnitude which would violate the water quality parameter in the rule cited below for bacteriological quality, substantial measures must be taken with a project such as this to avoid the deposition of human wastes from the dockage facility itself and from the boats using the slips. In furtherance of this end, the Applicant proposes to allow no live- aboard vessels to be occupied over night while moored at the docking facilities. Live-aboard vessels are deemed to be those with sleeping accommodations and marine heads. The Applicant also proposes to employ a full-time dock master seven days a week, eight hours a day to ensure that all dockage users are familiar with dockage rules, and who would enforce them, especially that prohibiting any discharges from vessels using or docking at the marina. The rules would be incorporated in the dockage lease agreements. The dock master would be responsible for the clean up and correction of all unauthorized discharges. In view of the potential for sewage discharges from marine heads, even with sewage pump-out facilities and the other restrictions on the use of live-aboard type boats, the additional protective measure of requiring a sewage pump-out line and pump-out equipment, including a storage tank and a means to direct sewage pumped from boats into the upland sanitary sewer system, should be imposed as an additional condition. Additionally, the restriction against over night stays aboard boats, the discharge of marine heads into the marina waters and the requirement for use of the sewage pump-out system should be publicized on large, easily legible signs at various points on the pier so that all boat slip renters or users can be on notice of the restrictions and the dock master's and the Department's enforcement of them. Additional potential sources of nutrient and bacteriological degradation of the dissolved oxygen content and bacteriological integrity of the surface waters involved can be posed by the deposition of fish carcasses and parts, as well as food wastes and other garbage in the marina waters. In order to prevent this, the Applicant has proposed to provide fish cleaning stations located on the upland and to require all fish carcasses and other related wastes to be placed in upland containers and not disposed of in the Class II waters at the dock site. Additionally, waste containers will be located along the length and perimeter of the dock facility for garbage, with regular emptying of the containers enforced by the dock master to prevent spillage. In connection with the upland fish cleaning sites to be installed, the drainage waters or waste water from fish cleaning stations should be directed into an upland disposal system so that it may be ensured that the water does not get back into the Class II waters of the bay. In addition to the above measures, pump-out facilities and equipment will be provided by the Applicant for used engine oil removed from boats and oil and water from boat bilges. These wastes, under agreed-upon conditions, would be transported by pipeline to the upland to a storage tank pending proper disposal. Trash, garbage and other refuse will be deposited in dumpsters for removal by municipal garbage disposal services. No fueling facilities or fueling of boats will be allowed. Additionally, oil spill clean up materials will be maintained on the marina site in sufficient quantities to allow clean up of the maximum spill expected from the largest boat typically using the marina pursuant to the leases for the boat slips. In order to further lessen the possibility of spills of oils, greases and fuels, the permit should be conditioned (as should the leases) upon no boat maintenance being performed at the marina site other than minor engine adjustments. In this context, an additional enforcement measure will be in the boat slip rental agreements themselves. The agreements will contain restrictive provisions requiring lessees to properly handle and dispose of fish carcasses and wastes, used engine oil, bilge water and requiring them to comply with sewage pump-out and refuse disposal conditions enumerated above. Upon completion of the facility, the dock master will manage and accomplish maintenance of the various items of equipment, such as the pump-out facility, on an eight hour a day, seven day per week basis and will enforce the restrictive provisions incorporating the above conditions in the boat slip rental agreements. Those restrictive provisions should include putting the lessees on notice that violation of any of the conditions enumerated above and in the boat slip leases will result in a breach of the lease and removal of their vessel from the marina and reporting of the violation to regulatory authorities. The various expert witnesses agreed that the proposed permit conditions enumerated above, if enforced, would adequately protect water quality as to the above parameters at issue. The Class II water quality standards will not be violated by the installation and operation of the project as proposed, provided the above conditions are strictly enforced and adhered to. Mr. Jack Taylor, the expert witness for the Petitioner, agreed that the above measures would reasonably ensure that the marina will not cause pollution and contravention of Class II water quality standards, but feared that enforcement problems would prevent such conditions from prevailing. In view of the measures enumerated above which will be undertaken by the Applicant to ensure that water quality standards are adhered to, including the liberal use of warning signs for marina customers and slip lessees, the use of a full-time dock master to enforce the conditions and including the enforcement measure of putting the conditions as restrictions in the slip rental leases, it has been shown that the enforcement will be reasonably adequate. An additional and important enforcement measure can be incorporated into this project, however, by requiring the Applicant to submit an operation and maintenance plan for the marina and requiring a monitoring program under the auspices of the Department for at least a year of operation in order to ensure that the project operates as it is proposed under the above-delineated conditions. The Department has continuing enforcement power and the monitoring program would, with regular monthly inspections, allow early detection and correction of any water quality violations, to and including the voiding of the permit and the closing of the marina operation should violations prove severe and uncorrectable. 1/ Such a monitoring program and marina operation and maintenance plan should be required as a condition to granting of the permit. 2/ Finally, it should be pointed out that the area of East Bay where the project would be built is Class II shellfish prohibited waters. The proposed project itself will not likely adversely affect shell fishing to the extent of closing additional waters if the above water quality safeguards are imposed as conditions on the permit and on the marina operation. This is especially true because the boundary line of the shellfish approved water to the east is at least two miles away, which distance incorporates a substantial mixing zone in the open waters of East Bay to sufficiently dilute pollutants which might emanate from the marina or other sources to levels such that the shellfish waters presently open will not be subject to any further closures by the Department of Natural Resources, as a result of this installation. The primary reason the shellfish waters in the immediate vicinity of the proposed project are closed to harvesting is the presence of the Military Point Sewage Treatment Plant which discharges its effluent into the waters of East Bay, such that the DNR's dye flow studies reveal that a 5.1 square mile buffer zone around that plant is necessary for closure to shellfish harvesting to ensure that the public health is not adversely affected by consumption of shellfish from the waters in that buffer area. That buffer area includes the proposed marina site. Additional significant pollution sources include fecal coliform bacteria, oils and greases and other contaminants associated with rainfall events and resultant urban runoff from the City of Parker and surrounding areas, including septic tank leachate and petroleum residues. These influences also currently add to the reasons why shellfish harvesting is precluded in the area of the proposed facility. It was not demonstrated that the addition of the marina and the boats operating under the above strict conditions will result in any additional closures to shellfish harvesting in surrounding, presently approved areas as a result of any water quality degradation posed by the subject project. Public Interest The public interest criteria-enumerated at Section 403.918(2)(a), Florida Statutes, which are actually at issue in this proceeding concern: (1) whether the project will adversely affect the public health, safety, welfare or property of others, (2) whether it will adversely affect conservation of fish and wildlife, including their habitats, (3) whether the project will adversely affect navigation, water flow or cause harmful erosion or shoaling, (4) whether it will adversely affect fishing or recreational values or marine productivity in its vicinity, and (5) whether the current condition and relative value of the functions of the natural area involved at the project site will be adversely affected by the proposed activity. There is no issue or dispute raised concerning the permanence of the project for purposes of criteria number 5 under this subsection, nor as to number 6, concerning historical and archaeological resources. Concerning criteria numbered 1-4 and 7, of this subsection, it has been demonstrated that the project will not likely affect the public health, safety, welfare or the property of others if constructed and operated according to the conditions delineated herein. Some members of the public testifying on behalf of the Petitioner objected to the interference they feared the dock would cause with their jogging along the shoreline and feared an impediment to their use of the area for water skiing. This is the only dock in this vicinity, however, and such interference is minor. It will be well lit in order to avoid impeding navigation or posing a danger to the public health or safety during hours of darkness in terms of the public's ability to safely operate boats in the area. There is some potential for the project adversely affecting conservation of fish and wildlife or their habitats in that, if boats are permitted to operate in the vicinity of the dock and use the dock for mooring, loading and unloading purposes, and the like, closer than 500 feet off shore, harmful propeller washing or dredging of the bottom sediments and seagrasses growing therein will result. If such erosion of the bottom and seagrass growth begins occurring, it will adversely affect and gradually destroy the area as a habitat for fish and other marine life, which is of particular importance since such Cuban Shoal Grass stands are quite beneficial as nursery areas for fish and other organisms. Thus, if boating activity were allowed unimpeded around the dock, including in the near shore area within 500 feet from the mean high water line, the resultant erosion and propeller damage to the seagrass beds in the bottom would indicate that, as to criteria 2 and 3 of the above subsection, that the project would not be in the public interest and would be contrary to the public interest. This same consideration is true with regard to the fourth criteria concerning whether the project adversely affects fishing and recreational values or marine productivity for similar reasons. If marine habitat is disrupted or destroyed in whole or in part in the vicinity of the dock due to erosion and other damage caused by boat and propeller contacts with the bottom or prop wash near the bottom, then as to this criteria, concerning marine productivity and recreational value, the project will be contrary to the public interest also. To the extent that nursery areas for fish and other valuable marine organisms are destroyed, the recreational value in terms of quality of fishing will certainly be diminished. The "current condition and relative value of functions" being performed by the area of marine habitat affected by this project must also be considered. In a like vein, this particular area constituting dense growths of seagrasses has a relatively high functional value as a marine habitat and, particularly, a nursery for marine animals. This current condition and value of the area should be accorded a fairly high status in weighing and balancing the various considerations used in determining whether the project is or is not contrary to the public interest. If the boats which are to use the marina upon its construction and operation are permitted inside the grass bed area, roughly within 500 feet of the shore, then clearly the considerations mentioned above will be the subject of adverse effects caused by the boats' operation which in turn is a direct result of the installation of this marina, the dock and the slips. In view of the reasonable likelihood of the project causing some of the adverse effects mentioned above, resulting from contact by boat propellers and boat hulls with the grass beds or erosive prop wash caused by operation of boats in water so shallow that the propellers are too near the bottom, the Applicant has agreed to a condition which will effectively remove boats from the seagrass bed area, provided it is strictly enforced. That condition would provide that boats and the slips in which they would be moored cannot be landward of 600 feet off shore of the mean high water line along the sides of the seaward extending dock. All boat slips are to be located seaward of that point. The Petitioners, however, raised a valid point that, the dock being so long, the natural tendency of boat operators would be to moor their boats along the sides of the dock as close into shore as boat operation is possible in order to more easily load and unload their boats. In order to prevent this problem from occurring, therefore, an additional condition should be imposed on the permit which would provide that the sides of the dock be enclosed by a fence out to the 600 foot mark and of such a configuration and type as to prevent boat operators from mooring boats to the sides of the dock and gaining ingress or egress from their boats on the dock shoreward of the 600 foot point mentioned above. In other words, if it is made impossible to enter or leave a boat from the dock in the area of the seagrass beds, this would substantially reduce the likelihood that the seagrass beds would be damaged by boats using the dock. Additionally, prominent signs should be posted on or in the vicinity of the dock announcing the necessity to avoid operating boats landward of the point mentioned above and the necessity of avoiding contacting the seagrass beds with boats or boat propellors. If this condition is adhered to and strictly enforced, as even Petitioner's expert witness concedes, it will prevent the chief source of adverse effects upon the public interest. An additional consideration in determining whether or not this project is contrary to the public interest concerns its effect upon navigation. This has already been discussed in the above Findings of Fact. Since this would be the only dock in the immediate area, it is found that the presence of the dock, even though it extends a significant distance seaward of the shore line, will still not pose a significant impediment to navigation. Additionally, as has been pointed out above, the public interest might be served in a positive way by the installation of the dock to the extent that it might prevent shrimp boats and other fishing boats pulling nets from using the shallow seagrass area which will help prevent uprooting and other damage to the grass beds caused by the nets and associated fishing gear. Finally, it should be pointed out that to a certain extent the project will positively serve recreational values and the public welfare, in the context of balancing the various public interest considerations, because at least half the boat slips will be reserved for public use and because the addition of such a marina or docking facility will enhance the public's ability to obtain recreational value from the State waters involved in East Bay by improving marine access to those waters for fishing, boating, skiing and other purposes. In short, reasonable assurances have been provided that the project is not contrary to the public interest.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that the application of John E. Bravo for the dredge and fill permit at issue be GRANTED, provided that the terms and conditions enumerated in the above Findings of Fact are incorporated in the permit as mandatory conditions. DONE and ORDERED this 29th day of July, 1987, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of July, 1987.
Findings Of Fact In September, 1985, Armand J. Houle purchased an 80 acre tract located eight miles east of the Naples toll booth on State Road 84 and approximately two miles north of Alligator Alley. The purpose of buying the property was to mine the limestone rock thereon, through a borrow pit, for the purpose of selling it as road base to the State of Florida Department of Transportation for use in the construction of 1-75 (Alligator Alley extending from Naples to the Florida east coast). While no contract has existed or currently exists, correspondence between the Department of Transportation and counsel for the Petitioner indicates that approximately 800,000 cubic yards of fill will be required in the immediate area and that Petitioner's proposed borrow pit would be the ideal source of this rock. Prior to making the purchase, Mr. Houle's associate, Raymond Chester, contacted both the Department of Transportation concerning the potential use of the rock and representatives of the Department of Environmental Regulation. The response he received from these agencies led him to, believe that a borrow pit might well be permitted and the effort should be pursued. After Mr. Chester and Mr. Houle became partners in the property, they contacted county officials and received zoning and other local permits for the facility. It was only after this, when DER was approached again that the applicants were advised a permit would not be issued. Mr. Houle agrees that, if the permits as requested were granted, he would accept a prohibition against further development of the property after removal of the rock and fill, would allow access to the restored lakes to the public for fishing and recreation; would agree to an appropriate restoration plan for the site; and would ensure compliance with the restoration plan stipulated by the Department. After the property was purchased in late 1985, Mr. Houle approached Daniel W. Brundage, the vice-president of an engineering firm in Naples, with a view toward developing the property in question as a borrow pit. Plans were developed for application for permits with the County and Mr. Brundage, consistent therewith, visited the site on several occasions. He found some vegetation off from the site which could be related to wetlands and contacted a representative of DER with whom he went to the site to look it over. This agency representative, Mr. Beever, concluded that the property was a jurisdictional wetland. Mr. Brundage nonetheless felt confident enough to begin work with the County to secure a permit to convert this land, classified as agricultural, to mining property. Consistent with his efforts, the request for conversion went through a four step process on the way to the County Commission which included approval by (1) the Water Management Advisory Board, (2) the Environmental Advisory Council which recommended same changes accepted by the Petitioner, (3) the Subdivision Review Committee, and (4) the Coastal Area Planning Council. All four subagencies recommended approval and thereafter the County granted its permit for work to begin. Assuming all permits are issued, the property will be developed in two stages. In stage one the site will be cleared of vegetation, and the top soil on Phase I, the western 40 acre parcel, removed and used to construct a berm around the entire perimeter of the site as well as between the two 40 acre parcels. The berm will be entirely within property boundaries and used to isolate any water removed from the active phase within the site so that it does not flow onto adjoining property. The eastern 40 acre tract, (Stage II) will be used for water storage during the excavation of Stage 1. It is anticipated that no water will leave the site during construction of either stage with the exception of extraordinary waterfall during rainfall or hurricane. Before any water is discharged, it will go into a storage configuration so that any sediment therein would settle to the bottom before discharge. The discharged water will be filtered through hay bales or filter screens to avoid any turbidity in the surrounding water. The design of this holding capacity in the filter system is sufficient to accommodate the water of a 25 year storm. As Stage I is completed, Stage II will be opened, and the ground water from Stage II pumped back to Stage I for storage. A similar storage and filtration system will be utilized around Stage I. Primary access to the property will be along the western boundary of 8 Mile Canal, but if this is not allowed, Petitioner proposes to build a single span bridge across the 8 Mile Canal at 40th Street to allow access to the property. After the lime rock has been excavated, the berm will be removed and the side of the property graded to form the banks of a 56 acre lake for recreational purposes. The edge of the lake will be a meandering slope at a ratio of 10:1 which will be assured by survey to be in compliance with the County plan. The lake, which will have a maximum depth of 20 feet, will be excavated at a depth ratio of 2:1 from the edge of the slope to the bottom of the lake. During excavation and prior to restoration, heavy equipment will be used for the removal of the rock such as drag lines, back hoes, motor graders, and bulldozers and an area within the boundaries of the site will be isolated and set up for fueling and maintenance. It will be floored with a membrane to prohibit oil and fuel from getting into the ground as a result of accidental spills. Storage tanks for fuel and oil will be above ground and available for immediate inspection. Waste facilities will be in the form of porta-potties and any water falling in this maintenance area will be drained to a low sump within the membraned area for storage until evaporation or safe removal. In the event of a heavy rainfall, water can be stored and anti-sedimented and cleaned and, if necessary, operations can be temporarily stopped. Mr. Brundage indicates that he has never seen any standing water on the site during his five visits nor has any standing water ever been reported to him. He is aware of no historical or archaeological sites on the property, and at no point would rock be mined within 50 feet of the property line. Dr. Durbin Tabb, a botanist, was retained by the Petitioner to prepare a plan for restoration of the site after mining operations were complete. In preparing his plan, he visited the site on several occasions finding varying plant life, much of which was grasses and rushes. In the north was a pine lowland where he saw palmettos scattered in the grassland as well as a few dwarf cypress trees. He also observed a small cluster of cabbage palms in the southern portion of the eastern tract and noted that the currently existing berm along the eastern boundary of the eastern tract is currently being invaded by exotic plant life including the Brazilian pepper. Dr. Tabb found little evidence of recent surface water accumulation; mollusk residue showed no evidence of recent viability; and he found no crawfish burrows which, if present, would show a water table near the surface. Other visitors to the site, however, did find crawfish burrows. The marsh soil shows that, at some time in the past, it was wet enough to support a soil-forming community. This is no longer' the case according to, Dr. Tabb. The process was stopped by the formulation of the Golden Gate Canal System in the 1960's. The existing marsh does, however', hold sufficient water to support the growth of muhli grass. Dr. Tabb's restoration plan is his best estimate of how the property can be restored to its previous condition by replanting native species found in the area. The program will include littoral zone vegetation to provide shelter and a feeding zone along the water's edge which does not now exist. The plan calls for the saying of the marsh soil. Since neither DER nor the client responded to his plan, when submitted, with any suggestions or corrections, he assumed it was approved. Dr. Tabb, who is also an expert in estuarian biology and zoology, concluded that the area on which this site is located is a very poor habitat for deer and panther. The red cockaded woodpecker has no trees on the property which it specifically desires and the property is a poor or nonexistent habitat for the indigo snake and the Everglades snake. It might, however, constitute a habitat for the Cape Sable seaside sparrow, but this bird has never been seen in this inland area. Panthers cross the area as do bears, but the presence of the excavated lake would be no more hindrance to them in their crossing than would the presence of Alligator Alley and the proposed 1-75. The area with sawgrass and muhli grass, which is dominant throughout the Golden Gate area, is called a "dry prairie" as opposed to a "wet prairie." While some of the same plants exist, it is somewhat different in that there are no viable wetlands wildlife organisms currently existing on the property. In Dr. Tabb's opinion, the property has lost its wetlands characteristics and only the marsh soil's water retention permits the life of the grasses currently existing. Wading birds would use the site later but do not currently utilize the area where excavation would take place. In Dr. Tabb's restoration plan, the slope to the lake would be replanted with saw and muhli grasses down to the litoral zone. From there on to the water, a palette of normal wet grasses would be planted to serve as feeding sites and roasting sites for the birds. In addition, an island planted with willows would be constructed off shore in the lake. Deer currently visit the area. They are not currently supported on the land though Mr. Barnett, of the Game and Fresh Water Fish Commission, indicated that they come out of the pine flats at night to feed on the grasses on the prairie. These deer form a large portion of the food chain for the panther, and Dr. Tabb does not consider it conceivable that the project, replanted and restored, would in any way adversely impact the Florida panther or the birds in issue here. In Dr. Tabb's opinion, it is questionable whether the site comes under the jurisdiction of DER based on the grasses present because he cannot find the water connection to confer jurisdiction. Dr. Tabb has not seen standing water on the site as he has seen on two other sites within the area where DER has granted permits for rock pits. On a site like this, the vegetation changes with the seasons. This site is not now connected to the canal along Alligator Alley by vegetation. There may have been a vegetation connection in the past, but as one goes up toward the site from the canal, the grass changes gradually from low pineland grasses found on higher ground to the lower sawgrasses found on the site in question. In Dr. Tabb's opinion, if Mr. Houle's property is to be considered a wetland, it is a transitional wetland. Turning to the issue of loss of habitat, if one assumes that portion of the property that will be converted to a lake will be denied to the panther, this is not the case for the deer which, in this area, is considered to be aquatic. Any denial of the lake area would constitute a very small negative impact compared to what is going on in other areas of Collier County. Admitting that there is a requirement to consider the cumulative impact of a project, in Dr. Tabb's opinion, this project would constitute a "may impact" situation. There is no definitive evidence as to what would happen, and he would be more concerned if the area were now a good panther habitat. It is not, however, and in fact it is no more than a habitat for the grasses which grow there. As to the wetlands issue, the only sign of exotic plant invasion is in the disturbed area around the canal which was installed approximately 18 years ago. The absence of these exotic species is, in Dr. Tabb's opinion, a clear indication that there is no flowing or standing water since the site is too dry for the germination of the seeds. There will be some removal of the biomass by the excavation of the lake. This biomass, consisting of grass primarily, is consumed by fire every year or so and insects eat it as well. Admittedly, some of the biomass is being eaten by animals of some nature and that which is converted to a lake will be removed. There is a trade-off, however. Dr. Martin Roessler, a marine biologist, prepared a report, on the water quality of the adjacent 8 Mile Canal, and other water bodies in the area. In preparation of his report, he took water samples in the areas in question, read literature on the water quality in the area, and looked at water quality data provided by U.S. government agencies and private companies. On the several visits he made to the site, he has not seen any surface water. The first time he could get water only in the adjacent canal, and he also got some water from the land borings done by Dr. Missimer on the site. Dr. Roessler is familiar with State standards for water quality and, in his opinion, the turbidity standards would not be disturbed because there was no water on the ground to be sheet flow. All water was at least three feet underground and, in addition, Petitioner has agreed to properly sod or otherwise treat the berms he will build to prevent erosion and any resultant turbidity either off-site or in the 8 Mile Canal. Dr. Roessler also does not believe the project would violate the oil and grease standards. There is nothing inherent in the mining process to bring into play oils and greases except for the possible problem in refueling and maintenance operations. In that regard, Petitioner has shown how he will provide against that by placing a membrane to prevent any oil, grease or other contaminant from getting into the ground. This area does not contain the organic mulch which produces natural oils and greases. The water near the surface of the lake will contain sufficient dissolved oxygen to meet State standards without problem. In the summer months when the dissolved oxygen count is low, generally, the lake bottom water may not meet State standards, but that happens quite frequently, naturally, across the entire area. Dr. Roessler believes that the dissolved oxygen requirements of 2.5 at the surface and .5 at the bottom will most likely be met in the lake created by this project. Concerning the biochemical oxygen demand (BOD), he concludes the operation in the quarry will not artificially decrease the available oxygen below the required amount. The BOD demand in this area would not be threatened by the lake. As to the iron standard and other toxic substances, Dr. Roessler does not believe that the project will create a violation of the standard nor will any runoff increase dissolved iron in adjacent waters. Hydrogen sulfide and pharasulfide standards will similarly not be violated. Sulfides are found only in trace amounts, if at all, in natural waters. In deep limestone lakes the chemical structure is not conducive to the formation of the acidic compounds. In short, Dr. Roessler believes the water in the mine would be very similar to that found in other rock quarries in the area. These lakes are a dominant portion of the recreational fresh water fishing availability. This instant lake also will, in time, upon development of the food chain for the fish, become an equivalent fishing habitat. Dr. Roessler concurs with Dr. Tabb regarding the flora on the site, which he observed himself. This site is 15 to 18 miles from marine or estuarian waters and to reach them one would have to go down a series of canals and past a saline dam to the coast. Any runoff from the site in question would have, if any, a minuscule effect on marine waters. This site was originally a wet prairie which was drained by the Golden Gate Canal System. As such it is a relatively poor habitat for life forms generally found in cypress wetlands. Creation of this lake will, in the opinion of Dr. Roessler, enhance the game, fish, and recreational activity of the area. It would be a benefit to the animal population to have a water source for drinking during drought. There would be no adverse effect on public health, safety or welfare. Turning to the major issue of water, Dr. Thomas Missimer, a hydrogeologist specializing in ground water, visited the site, examining the canal on the east side, and the soils and rocks exposed. He took soil borings and examined the site hydrology to see what fluctuations occurred in the water levels due to rainfall. Mr. Missimer, took numerous readings from September 18 through November 5, 1987 during a period of wet weather including a tropical storm. He carefully compared the site geology to other sites he had studied and compared the flow of water through the soil. He compiled existing information on chemistry in the streams in the area to see what the natural conditions were. He looked at other man-made lakes in the area which were previously borrow pits. As a result of his studies, he concluded that the groundwater level throughout the entire period never got higher than three feet below the land's surface and often was five feet below. During the previous July through September, 34 inches of rain fell in the area which was, in his opinion, average to above average. There is some evidence, however, to indicate that rainfall in the area was approximately 33 percent below average during the period. Nonetheless, Mr. Missimer took a measurement the day after a tropical storm had deposited three inches of water on the land. The water level at that time was still three feet below land level, and there was no standing water. Both the three foot and the five foot level are well below the top of the berm sloped at 10:1 as is proposed in the restoration plan submitted by Dr. Tabb. This site has, from a hydrological standpoint, been greatly affected by the installation, of the 8 Mile Canal and the canal system to the north. As, a result of this activity, standing water has not existed for many, years since the dredging of those canals. If de-watering is a necessary portion of the mining plan, any waters removed thereby would be retained in the impoundment area described by Mr. Brundage and switched back and forth. As proposed, the plan can completely avoid any impact to off-site property by water runoff. Construction of the pit and the lowering of the water level thereby will not have a major impact on the groundwater in the surrounding areas. Any effect would taper off as the distance increased from the site and would be of little significance. This proposal would also have little, if any, impact on groundwater quality. In Mr. Missimer's opinion, water quality is currently good and will stay good. This type of rock mine is very common in the area incident to construction. Some have been used as a source of potable water by The City of Naples; by Deltona Utility Company for Marco Island; and the south area of the County. These resources are still being used. There is little difference between those currently being used as potable water sources and the proposed lake here. Mr. Missimer also indicates the project will have little impact on the sheet flow of water. Sheet flow no longer exists here because of the canals and roads already existing. If there were a sheet flow created by a very heavy rain, this pit would have no impact on it. The water level in the lake will be approximately the same as exists in the ground currently and in the 8 Mile Canal. There should be no shoaling in the canal due to the project, and the presently existing spoil bank on the west side of the canal already prevents flow into the, canal from this land. If this pit is properly constituted and maintained, and if proper mining procedures are followed there should be no effect on the 8 Mile Canal to the east or the Alligator Alley Canal to the south. There is no surface water connection currently existing between this site and either canal. As to the issue of dissolved oxygen, the currently existing groundwater on the site and in the surrounding area has little or no dissolved oxygen in it. Water coming into the lake will be groundwater low in dissolved oxygen, which is identical to the water which currently goes into the canal system. The canal gets very little oxygen from the wind because it is so narrow. The lakes to be constructed, on the other hand, will get a large amount of oxygen from the 56 acres of water exposed to the open air. Consequently, construction of the lakes would increase the dissolved oxygen content of the water in the area, at least in the lakes, down to a level of several feet. This is a positive factor. Mr. Missimer recognizes, however, that during the dry seasons, when the lake is fed solely by groundwater generally low in dissolved oxygen, the lake water which has been converted to surface water may fail to meet the Department's surface water standards for dissolved oxygen. Warmer weather generally results in lower dissolved oxygen readings and, admittedly, Respondent's readings were taken in December when the dissolved oxygen levels are higher. As a result, the comparative samples which were taken in December are not necessarily indicative of what will be the situation in the lake, year- round. Respondent's witnesses present a more dismal picture of the effect of Petitioner's proposed project. Mr. Bickner, an Environmental Supervisor with DER's Bureau of Permits and himself an expert in water quality, zoology, and ecosystem biology, first became involved with this project while the permit request was being processed in late 1986. This application was a standard form project because of the quantity of material to be excavated. As a part of his processing, Mr. Bickner requested evaluations of the project from other agencies and divisions within DER and, on the basis of his personal evaluation and the recommendations he received, concluded that the application was not permittable. He recommended it be denied. Mr. Bickner considered Petitioner's application under the provisions of Chapter 403.918, Florida Statutes, which requires a two step evaluation. In the first step, the project must be determined to meet water quality standards. If it does, as a second stage, the project must be determined not to be contrary to the public interest. The major water quality standard in issue here was that of dissolved oxygen along with that concerning BOD and other deleterious substances. The water body involved was classified as a Class III Water under the provisions of Rule 17-3.121, Florida Administrative Code, since it was designed to be a recreational, fish and wildlife habitat. The standards contained in the statute and the rule relate to surface water as opposed to groundwater and, as to the public interest question, Chapter 403 provides a list of seven factors which must be evaluated. In this determination the agency has wide latitude and no one factor is controlling. In evaluation, agency personnel try to look at the project overall. Specifically, the project cannot cause or contribute to an existing water quality violation. In evaluation, agency personnel do not look at the project by itself. They must keep in mind that other projects exist or are proposed for the area. This is known as the cumulative impact of the project which is provided for in Section 403.919, Florida Statutes. As to the variance requested, this is also provided for by statute. The criteria require that the petition be based on some specific ground. In the instant case, the ground utilized by Petitioner was that there was no alternative to the dissolved oxygen level proposed. Granting of a variance is totally within the discretion of the Department even if Petitioner can show grounds therefor. Mr. Bickner was at the site only once. He approached from the south. At the low end of the approach was a mixture of wetlands and upland vegetation, but as he got toward the site the upland species dropped off and only the wetland species only remained. These were primarily sawgrass, cattails, and the like. He was satisfied that there was no obvious break in jurisdiction, and the testimony of Mr. Beever confirmed that jurisdiction over the site was gained through the wetlands character of the property from the site down to the Alligator Alley Canal, which is considered a water of the state. The site consists primarily of sawgrass and muhli grass with minor amounts of other grasses. The site seems to rise toward the 8 Mile Canal where there is an invasion of Brazilian peppers and other exotic species. Mr. Bickner was looking for upland species and found only one specimen of one species, a few of another, and no invasion of slash pine on the site at all. As a result, he concluded that the site was not an upland site. There was no standing water on the site at the time Mr. Bickner visited it, but the soil was wet to the surface. In addition, there was a large number of recently dead shells in low spots which had held water. There were some tracks of a large animal and a large number of smaller animal tracks and scats (scats are animal droppings). He also saw some birds which were too far away to identify and observed what he thought were crayfish tunnels near the cypress trees. Mr. Bickner found evidence of dried periphyton widely scattered over the site. Periphyton, an algae which attaches itself to other plants and which in times of inundation, forms sheets across the water connecting one plant to another, is a sign of previous inundation. The other plants on the site were not showing water deprivation stress, and there was no evidence of upland species invasion. All of this leads Mr. Bickner to conclude that the area has plenty of water and this opinion was enhanced by the lushness of the plants' growth. This, along with the high diversity of plant life, indicated to him a healthy ecosystem. To Mr. Bikner, the fact that the area was not currently inundated is not significant. In this particular area there are wet and dry seasons and, even in the dry season such as existed at the time of his visit, the soil was wet. The signs he saw indicated to him there has to be standing water on the site at some time. His visit was in January, which is well within the dry season. As to water quality, Mr. Bickner does not believe that the water quality standards will not be violated. In fact, by the nature of the project, Petitioner has, in Mr. Bickner's opinion, assured that it will be violated. A 20 foot deep pit must, in his opinion, result in low levels of dissolved oxygen below standards. Any water below seven foot in depth has little dissolved oxygen. Most dissolved oxygen is in the surface water, and there is little exchange between deep and surface waters. As a result, he concludes that the groundwater has low dissolved oxygen, a fact confirmed by Mr. Missimer. Dissolved oxygen is the only source of oxygen for fish and aquatic animals. Without dissolved oxygen, the fish die. There are currently no fish on the property. Mr. Bickner was also concerned with the biochemical oxygen demand which would further reduce the oxygen levels in the water. He was further concerned with the hydrogen sulfide levels coming from deterioration of plant material in the bottom of the pit, and iron which he found to be already in the groundwater. Mr. Bickner contends that during construction of the pit petro- chemicals will be introduced into the water, and that during the construction period the on-site water will have increased turbidity which will most likely be transmitted off-site as the pit is de-watered. There are management procedures which can reduce the risk, but none can avoid it entirely. Mr. Bickner is satisfied that the water quality standards will not be met. It is so found. Mr. Bickner also evaluated the property from the public interest standpoint, and in that regard he is satisfied there is a substantial potential for damage to adjacent properties by de-watering. Based on his experience and observation of other projects, he is satisfied there is no way to keep people employed on the site from using adjacent property for parking and vehicle maintenance. The witness believes that the 56 acres of habitat removed by the lake, and the remaining acres, which will be replanted, will be permanently impacted. While he admits that the property as it currently exists, may not be a prime habitat for the panther, there is some evidence which indicates panthers do cross it. He is concerned that the applicants submission here does not sufficiently answer all the questions as to impact on the public interest. The mechanics of the maintenance yard, soil storage and other potential areas of trauma are not explained satisfactorily, and Mr. Bickner does not see how all that is proposed can fit on the site. As a result, in his opinion, there must be some off-site impact. As to cumulative impact, since the valuable rock does not lie only under Petitioner's property, owners of the surrounding property may want to mine their properties as Petitioner proposes to do. If that happens, Mr. Bickner cannot explain how the Department can deny these subsequent applications. If the current application is permitted, taken together with the others, there would be a serious effect on the panther population. This opinion is not supported by evidence, however. If the public interest test is the only basis for disqualification of the project, (here the water quality test is also not met) a permit can still be granted if the applicant agrees to take appropriate mitigation steps at the site. Mr. Bickner is of the opinion that the applicant's mitigation plan to create the 100 foot wide shelf around the lake is not the same type of system which currently exists, will not fulfill the same function as the present property, and is not sufficiently large to replace what is being lost. One basis for granting the variance suggested by the Petitioner was the public interest, (the material was to be used for a public road), and the other was that there was no alternative way to get the material. While it is possible the rock would be used for public road, Mr. Bickner was concerned no assurances were given by the Petitioner that it would be. No contract has been signed yet, and Mr. Bickner is not satisfied that the letter from the Department of Transportation, indicating the rock there would suit its purpose, is sufficient indication that a contract would be signed. There is a possibility of making the pit shallower, which would permit the dissolved oxygen content of the lake water to meet state standards, but even if that problem were solved, Mr. Bickner is not satisfied that Petitioner has met the public interest test. Respondent has granted three permits and a variance to the Department of Transportation to build a portion of I-75 across Alligator Alley in Collier County. These permits are for the dredging of canals parallel to the roadway and to develop a borrow lake of 73.1 acres to be excavated to a depth of from 6 to 9.7 feet. The variance in question applies to all three projects and relates to the dissolved oxygen level. The DOT variance was applied for on the basis that no practical means for avoidance of the pollution existed. The Department of Transportation did not request a variance for BOD or for toxic and deleterious substances or iron. Mr. Bickner, admitted that these permitted projects would possibly have the same problem of oils and greases as he foresees with Petitioner's project. Nonetheless, he concludes that Petitioner's project should not be permitted, even though the Alligator Alley canals are already below standards, because to do so would contribute to a currently existing violation. Mr. James Beever, an Environmental Specialist with the Department of, Environmental Regulation, visited the site on several occasions, both on the ground and from the air. He observed much of the same flora and fauna observed by the other visitors who testified in this case and took color photographs of the area which portray the character of the property. All of the plants he discovered on the site are on the DER jurisdictional list and, on at least one occasion, from the air, he saw standing water on the site. In his opinion, the property is a fresh water wet prairie system which is admittedly drier than it should be. The plants he saw on the site indicate the jurisdiction of DER if there is a connection to other waters of the state, and in Mr. Beever's opinion, there is connection through the flow of sheet water south from the site to the I-75 (Alligator Alley) canal; then, east to the 8 Mile Canal; then south to the Fuqua Union Canal which empties southwest to the Gulf of Mexico. In his opinion, therefore, this is definitely jurisdictional land, and it is so found. The site supports an underground system of roots as well as the upper portion of the, plants existing thereon. He observed periphyton and many other animal tracks and scats. He also saw signs of regular inundation such as numerous snail shells, and he is satisfied there is no indication of a change in the area from the wetlands to an upland area. Admittedly, the area has been dry for a while. Even after Hurricane Floyd in 1987, there was no standing water. The site is, in his opinion, definitely productive, however. The vegetation existing thereon stabilizes the soil and provides food for snails, insects and crayfish which are on the bottom of the foodchain for other life forms on the property. The grasses provide a habitat for animals such as cotton rats, roosts for birds, pollen for insects, all which, themselves, become food for the larger animals. This wetland is a part of a large wetland prairie system and part of the Fuqua Union drainage basin, and acts as a filter for the water system for the area. According to Mr. Beever, most borrow pits like this are located on uplands which then provide rain water lakes. The instant pit, however, is in a wetlands area and if built, he believes, will engender violations during the mining operation. Groundwater coming in will contain iron and hydrogen sulfide which will combine with the dissolved oxygen in the water and further deplete the already low oxygen levels. All of this will constitute a violation of the rules regarding waters of the state since the waters within the pit would fall within that category. Mr. Beever is also concerned with the `bridge over the 8 Mile Canal and the turbidity connected with its construction and removal. In substance, Mr. Beever is convinced that construction of the project will create violations of the water quality standards for the area. As to the public interest, the wetlands character of the site will be completely lost. The vegetation will be removed, and the animals utilizing it will either leave or be destroyed. After, construction, some natural healing will occur, but a long-term maintenance program will be required to provide even different functions for the land than those which currently exist. In that regard, Mr. Beever is convinced that the applicant's proposed restoration plan is not acceptable. It will not replace the lost functions of the site; it will replace the species removed with a different ecosystem; it will provide a habitat for different species of animals and birds; it will adversely affect the shoaling and erosion in the lake itself (this is found to be without merit); it will have some adverse effect on the property of others; and will have an adverse cumulative impact on the area. The habitat will not be used any more by endangered species such as the wood stork and the panther. Even assuming, arguendo, the plans were suitable, in Mr. Beever's opinion, the project would not work here because of the lack of information on what the actual water level of the lake will be. The plant species proposed may not remain because of possible changes in water level in the lake. In addition, the marl berms will dry out over the three years of their life while the pit is being worked, and form a location for a lot of invasive upland plants. Much of Mr. Beever's concern is shared by Mr. Barnett, of the Game and Fresh Water Fish Commission, who indicated that birds now frequently use the area for nesting and feeding because of its wetlands character. Endangered species such as the Florida panther cross it from time to time as does the Florida black bear. Human encroachment reduces the panther's territory and reduces the area for forage of deer, which are the principal food of the panther. The bigger issue, however, is the cumulative impact. The 80 acres is not so important by itself, but to permit its removal would set a precedent for future encroachment by others. Mr. Barnett's experience is that restoration plans are quite often not successful. Even the successful ones, however, replace the removed system with a different system, and the species which now use the property would find it much less desirable as changed. Specifically, the bear, the deer, and the panther would find it unusable as proposed. At the present time, the deer spend their days in the pines forest to the north of the property, coming out onto the area, in question only at night to feed. It is during the night that the panther stalks. As presently constituted, this property is of no benefit to the wood stork or the red cockaded woodpecker. The Cape Sable sparrow could use it but does not. The development of Golden Gate Estates to the north and east and south of the property has a two pronged effect on the area in question. The southern portion of Golden Gate Estates has been abandoned, but the central and northern portions will be developed. On the one hand, it is likely that the increased population to the north and east will make the Petitioner's property less desirable and make access to it more difficult for the wildlife currently utilizing it. On the other hand, removal of the northern and central portions of Golden Gate from usable area for the panther and other species make it more important that Petitioner's area, which Barnett claims is not likely to be developed, remain as an animal habitat to offset the encroachment of the development area. There is no evidence to support this prediction of non- development, however. History tends to indicate otherwise.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore, RECOMMENDED that Petitioner be issued a dredge and fill permit as requested and a variance to the state water quality standards as identified in the request. RECOMMENDED this 29th day of April, 1988, in Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-1469 AND 87-4404 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. By the Petitioner 1 - 2. Accepted. 3 - 6. Accepted and incorporated herein. 7. Accepted. 8. Accepted. 9 - 14. Accepted and incorporated herein. 15. Accepted. 16 - 17. Accepted and incorporated herein. 18 - 19. Accepted and incorporated herein. 20. Accepted. 21 - 23. Accepted and incorporated herein. 24. Not a Finding of Fact. 25 - 26. Accepted and incorporated herein. 27 - 28. Accepted and incorporated herein, except for finding it is likely that more wildlife will use the site after construction. Rejected as speculation. 29 - 30. Accepted and incorporated herein. 31 - 33. Accepted and incorporated herein. 34. Accepted and incorporated herein. 35. Accepted and incorporated herein. 36 - 38. Accepted and incorporated herein. 39. Accepted and incorporated herein. 40. Accepted and incorporated herein. 41. Accepted and incorporated herein. 42. Accepted. 43 - 44. Rejected as contra to the evidence. Accepted. Accepted and incorporated herein. For the Respondent 1 - 3. Accepted and incorporated herein. 4 - 8. Accepted and incorporated herein. 9. Accepted and incorporated herein. 10 - 17. Accepted and incorporated herein. 18 - 20. Accepted and incorporated herein. 21. Accepted and incorporated-herein. 22 - 25. Accepted and incorporated herein. 26 - 33. Accepted and incorporated herein. 34 - 35. Accepted and incorporated herein. 36. Rejected as contra to evidence presented. 37 - 40. Accepted and incorporated herein. 41. Accepted and incorporated herein. 42 - 43. Rejected. 44. Accepted and incorporated herein. 45 - 47. Accepted and incorporated herein. 48 - 60. Accepted and incorporated herein. Rejected. Accepted in part - (temporary). Accepted. Accepted and incorporated herein. Accepted and incorporated herein. Unproven. Accepted. Accepted and incorporated herein. Accepted. Accepted. Accepted. Accepted. Accepted and incorporated herein. Accepted. COPIES FURNISHED: Robert Routa, Esquire ROBERTS, EGAN & ROUTA, P.A. 217 South Adams Street Post Office Box 1386 Tallahassee, Florida 32302 Richard Grosso, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Dale Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400
The Issue At issue in this proceeding is whether certain development orders issued by Monroe County to Homeowners, Ocean Reef Club and Key Largo Foundation (Applicants) for a project that would ultimately result in the construction of a flushing canal in the Ocean Reef Club development on north Key Largo are consistent with the Monroe County comprehensive plan and land development regulations.
Findings Of Fact The parties Petitioner, Department of Community Affairs (Department), is the state land planning agency charged with the responsibility of administering and enforcing the provisions of Chapter 380, Florida Statutes, and all rules promulgated thereunder. Section 380.031(18) and 380.032(1), Florida Statues. Respondent, Monroe County, is a local government within the Florida Keys area of Critical State Concern designated by Section 380.0552, Florida Statutes, and is responsible for the implementation of, and the issuance of development orders that are consistent with, the Monroe County comprehensive plan and land development regulations, as approved and adopted in Chapters 9J-14 and 28-20, Florida Administrative Code. Respondents, Homeowners, Ocean Reef Club and Key Largo Foundation (Applicants), are the owners of real property in the Ocean Reef and Harbour Course subdivisions, Key Largo, Monroe County, Florida; properties that are located within that part of Monroe County designated as an area of Critical State Concern. The Applicants have sought the development orders (permits) at issue in this proceeding incident to their 8-year quest to achieve regulatory approval to initiate a project that would restore the water quality of Dispatch Creek to Class III water standards. Background The site of the proposed project, the present terminus of Dispatch Creek, is located within the Ocean Reef Club development on north Key Largo. That development is bordered on the east by the Atlantic Ocean and John Pennekamp Coral Reef State Park, on the north by Biscayne National Park, and on the west by the Biscayne Bay/Card Sound Aquatic Preserve. Currently, the development at the Ocean Reef Club includes a number of canals and boat basins, an airstrip; three 18-hole golf courses, a 174-slip marina capable of docking vessels in excess of 100 feet, and extensive residential and-commercial uses. In the mid-1970's, Dispatch Creek was a natural, albeit shallow, waterbody that was able to maintain, through natural tidal actions, water quality standards. However, in 1977 Ocean Reef Club, under permits issued by the Department of Environmental Regulation (DER) in the mid-1970's excavated the creek to new depths to create a navigable channel and extended its length beyond its natural contours. When completed, the creek was converted from a natural waterbody, that could maintain water quality standards through natural tidal action, into a dead-end system, that could not maintain such standards through natural processes along the course of its extended terminus. 1/ Over time, the water quality of Dispatch Creek from its approximate midpoint to its dead-end terminus has steadily declined. The cause of this decline is reasonably attributable to the biochemical oxygen demand placed on the creek by the continuous input of detritus from mangroves, which boarder the creek on the east and to a lesser extent on the west, and the length of the channel, coupled with the dead-end basin surrounding an island, which has assured the continued decline of water quality due to poor water circulation. As a consequence, the creek, as a habitat, has been altered from an oxygen rich system supportive of aerobic life to an oxygen poor system supportive of anaerobic life. This has evidenced itself through algae blooms, the intermittent emission of hydrogen sulfide gas, and a change in water clarity to that of a "coffee au lait" color. Currently, a significant portion of Dispatch Creek is devoid of aerobic life, and unless its condition is reversed it could not support aerobic marine organisms in the future. /2 Today, conditions in portions of Dispatch Creek fail to meet DER standards. DER regulations establish the dissolved oxygen (DO) standard to be not less than five milligrams per liter in a 24-hour period, and never less that four milligrams per liter. The DO Standard is currently violated in Dispatch Creek beginning at the mid point of the creek to its terminus. At its terminus, DO levels are chronically below one milligram per liter. Additionally, DER nutrient standards prohibit the alteration of nutrient concentrations of a body of water so as to cause an imbalance in natural populations of aquatic flora or fauna. Here, the high nutrient levels of Dispatch Creek resulting from the mangrove detritus and lack of circulation has, as heretofore noted, caused the natural aquatic flora and fauna to be replaced by anaerobic life. As a consequence of the changes in water quality that had occurred in Dispatch Creeks the Applicants have, over the course of the past eight years, sought approval from various regulatory authorities, including DER and Monroe County, of a plan to improve the water quality in Dispatch Creek. Such approval has been garnered from DER, and Monroe County's approval is at issue in this proceeding. The DER permit On February 7, 1986, the Applicants received approval from DER for a permit to construct a flushing canal from the terminus of Dispatch Creek to the Atlantic Ocean. That permit authorized the Applicants: To construct a "flushing canal" between the dead end of Dispatch Creek Waterway and the Atlantic Ocean by: excavating approximately 13,000 cubic yards to create a canal approximately 3000 ft. long by 20 ft. wide with a bottom elevation of 6 ft. Mean Low Water; placing three 6 ft. by 6 ft. by 380 ft. box culverts in the canal alignment at the basin end; placing tidal actuated flap gates on the basin end of the culverts in a manner which will allow the basin to intake water from the flushing canal on incoming tides while preventing discharge into the flushing canal on outgoing tides; placing 5 pilings across the canal at it's juncture with the Atlantic Ocean to prevent navigation in the canal; and creating a 12,900 sq. ft. mangrove mitigation area by excavating approximately 1,450 cu. yds. from a spoil area to create an area with an elevation of +1.4 Ft. NGVD which will be planted with red mangroves. DER was, in evaluating the application pending before it, charged with the duty to apply, enter alia, the criteria of the 1984 Warren Henderson Wetlands Act, Section 403.918(2), Florida Statutes, as well as Chapters 17-3 and 17-4, Florida Administrative Code. Based on DER's decision to issue its permit, it is reasonable to conclude that DER, within its permitting jurisdiction, concluded that construction of the proposed circulation channel would not lower ambient water quality, and would not significantly degrade Outstanding Florida Waters (OFW), including those of John Pennekamp Coral Reef State Park. As heretofore noted, the Department does not contend that the subject project will violate any specific criteria within DER's Chapter 403, Florida Statutes, permitting jurisdiction. The Monroe County permits On July 19, 1989, Monroe County issued to the Applicants the building permit, excavation permit, and land clearing permit (development orders), each numbered 8930001680, at issue in these proceedings. As permitted, the project proposed by the Applicants is designed to improve the water quality of Dispatch Creek, particularly in the vicinity of its dead-end terminus, and consists of two phases. Phase I contemplates the installation and operation of an aeration system for at least one year, which will extend from the dead-end terminus of Dispatch Creek toward its midpoint, as well as a water quality monitoring program, until such time as the water quality of the entire creek comports with that of adjacent Class III waters. Should the Applicants be successful in Phase I, they would then be authorized to proceed with Phase II, which would allow the construction of the flushing canal contemplated by the DER permit. As approved by Monroe County, Phase I would consist of the installation of an aeration system around the island, located at the terminus of Dispatch Creek, and in the canal, as well as the suction dredging of loose sediments in the upper reaches of Dispatch Creek. The system would consist of fifteen microporus diffuser/aerators producing approximately 5 CFM per unit, and would be anchored near the bottom to maximize the introduction of dissolved oxygen into the anaerobic water and to optimize water movement. Operation of such system, coupled with the introduction of aerobic bacteria, will shortly reduce the concentration of hydrogen sulfide dissolved in the water, reduce the concentration of ionized sulfides in solution, retard the growth and propagation of anaerobics in the benthic layer, and activate the growth and propagation of aerobics in all strata. As a consequence, over time, water clarity will improve, which will allow the penetration of sunlight into the benthos. This illumination will spawn the growth of photosynthetic bacteria, as well as phytoplankton, which will aid in the continued aerobic cleansing of the water and bottom sediments. In all, installation and operation of the aeration system, which has proven successful at other locations, should, over time, restore the waters of Dispatch Creek to Class III standards, without any adverse impacts to adjacent waters or the park. While operation of the aeration system will, over time, restore the waters of Dispatch Creek to Class III standards, the perpetual maintenance of such system would be energy intensive and expensive. for this reason, the Applicants have proposed the Phase II canal, which would maintain, through natural tidal processes, water quality standards within the creek. The canal permitted by Monroe County under Phase II is consistent in all respects with the DER permit except the Monroe County permits require that the canal be sited 20 feet landward of the alignment permitted-by DER into previously scarified uplands. So aligned, the canal would begin at the landward terminus of Dispatch Creeks run easterly within the rear lot lines of at least 15 lots within Harbour Course South subdivision, a platted subdivision, pass through a fringe of red and black mangroves fronting the ocean, and terminate approximately 100 feet seaward of the mean high water line (MHWL) within the boundaries of John Pennekamp State Park. At the point where the canal would join with Dispatch Creek, three 6 foot by 6 foot by 380 foot box culverts would!! be installed with one-way tidal activated flap gates, which would permit waters from the Atlantic to enter Dispatch Creek on a rising tide, but would preclude an exchange of waters from Dispatch Creek on a falling tide. Through such design, sufficient mix and force will be exerted within the waters of Dispatch Creek to maintain Class III water quality standards by natural circulation, and to return the habitat offered by the creek to an oxygen rich system capable of supporting aerobic life. While construction of the canal would be beneficial, by restoring the waters: of Dispatch Creek to Class III standards, it is not without cost to the environment. As aligned, the canal, although predominately within previously cleared or scarified uplands, will require excavation through several types of habitat that are either undisturbed or reestablished, including undisturbed buttonwood association, salt marsh, hardwood hammock, transitional habitat, mangroves and submerged lands, and will require the removal of approximately one-tenth of an acre of red and black mangroves, a species of special concern, as well as a number of mahogany trees, twisted air plants, prickly pear cactus and barpar cactus, which are threatened species. Its construction would likewise sever the uplands from the adjacent transitional and wetland areas that traditionally buffer, insulate and protect nearshore waters from runoff from upland areas. Construction of the canal should not, however, adversely impact any threatened or endangered animal species since the proposed alignment is currently a poor habitat for threatened or endangered species, such as the Key Largo woodrat, that may reside in the area, and there is currently no threatened or endangered animal species inhabiting the site. This is not, however, to suggest that the site would not support such species in the future, provided that existing habitat is permitted to continue its progress towards reestablishment. To mitigate the loss of habitat types, the Monroe County permit provides: The agreed mitigation for the loss of all rare and/or endangered habitat types located within the area impacted by the dredging shall be carried out prior to initiation of the dredge project. This shall be based on existing vegetation surveys and an assessment of species currently located within the confines of the project area. Prior to initiation of any dredge activity, a formal inventory of the project site shall be made and a one-to-one replacement program (baked on species rarity or level of endangerment) shall be established and agreed upon. Such an agreement will include defining an appropriate site and the number and type of trees, as well as a maintenance plan for the agreed upon area. Additionally, the DER permit addresses the loss of mangroves, by requiring the establishment of a 12,900 square foot mangrove mitigation area. Under the facts of this case, the mitigation proposed would, assuming the propriety of such development under the Monroe County comprehensive plan and land development regulations, address the loss of habitat types occasioned by development of the proposed canal. To assure that water quality within Dispatch Creek comports with Class III standards before the canal is dug, and that the creek maintains such standards following construction, the Monroe County permits establish a water quality monitoring program. During the first year, samples will be taken and tests performed on a weekly basis for pH, DO, turbidity, Secchi Disc, temperature, and sulfite; on a biweekly basis for total bacterial count and composition; on a monthly basis for total nitrogen and phosphate; on a quarterly basis for: macro-invertebrates and macrophytes; and on a semiannual basis for heavy metals and pesticides. During the second yearn biweekly testing will be done for DO, temperature, hydrogen sulfide, turbidity and Secchi Disc; quarterly testing for total nitrogen and phosphate, macro- invertebrates, and macrophytes; and, annual testing for heavy metals and pesticides. After the second year, monthly tests will be done for DO, temperature, hydrogen sulfide, turbidity, and Secci Disc; quarterly tests for total nitrogen and phosphate, as well as macro- invertebrates; and annual tests for heavy metals and pesticides. Should the water quality of the creek fail to maintain Class III standards following construction of the canal, the Monroe County permit contains the following special condition: The water quality monitoring program shall be maintained to assess the quality of water in Dispatch Creek subsequent to the dredge project completion. If at any time the water quality fails to meet the standards established by this permit, the one way flushing valve shall be closed by the applicant, and in applicant's failure to do so, by the County. The applicant assumes all costs of closing said valve, whether closed by applicant or the County. Aeration, aid/or other means at the discretion of the applicant, shall be utilized to reestablish quality. The valve shall not be reopened until the water quality standard is met. The purpose of the foregoing condition, as well as the requirement that the waters of Dispatch Creek meet Class III standards before the canal can be dug, is to assure that operation of the canal will not lower ambient water quality within the Outstanding Florida Waters of John Pennekamp Coral Reef State Park, and thereby protect the park from any adverse impacts associated with the improved circulation of the creek. John Pennekamp Coral Reef State Park is a unique and world-renowned resource, attracting millions of visitors each year. At least fifty percent of the activities engaged in by visitors to the park are water-related, including fishing, observational diving and boating. Any degradation of the ambient quality of those waters would be contrary to DER's rules promulgated under Chapter 403, Florida Statutes, and could adversely impact the natural biota of the park, with a corresponding reduction in the number of visitors to the park and revenues contributed by those visitors to the local economy. Here, the proof demonstrates, consistent with DER's prior permitting, that the subject project, built as proposed, would not lower the ambient water quality of adjacent waters through the discharge of pollutants, and therefore would not adversely affect the park. If anything, the Monroe County permits, with one exception to be discussed infra, offer stronger assurances than the DER permit that adverse impacts will not occur. Notably, under such permits the Applicants must first bring the water quality of the Creek up to Class III standards before the canal can be dug. If the Applicants are ssuccessful at that phase of the project, there will not be excessive nutrient loading within the creek, and the detritus that may thereafter be removed from the creek by improved circulation would not adversely affect water quality or the park. Currently, there are no heavy metals in the sediments or water column of the creek which are at levels above those found naturally, and no pesticides or toxic organics. In sum, there is no basis to conclude, based on the record, that-there is any substance within the waters or sediments of Dispatch Creek that would, upon the waters achieving Class III standards, lower the amient quality of adjacent waters or adversely impact the park. /4 Ostensibly, as an added measure of protection to adjacent waters, the Monroe County permits contain a condition, with which the Applicants concur, that should the waters of Dispatch Creek fail to maintain Class III standards following construction of the canal, the one-way tidal actuated flap gates will be closed. That condition, a noted supra, provides: If at any time the water quality [of the creek] fails to meet the standards established by this permit, the one way flushing valve shall be closed by the applicant, and in the applicant's failure to do so, by the County. The applicant assumes all costs of closing by applicant or the County. Aeration, and/or other means at the discretion of the applicant, shall be utilized to reestablish quality. The valve shall not be reopened until the water quality standards is met. The foregoing condition presumes to address the possibility that should the proposed project fail to function as expected by the experts, as did the current Dispatch Creek fail to function as expected, that such failure will no result in an adverse impact to adjacent waters or the park. In this regard, it is worthy of note that DER's approval of the extension of Dispatch Creek to create a 7,200 foot dead-end canal in the mid-flush the pollutants from the canal into the park. The Applicants presented persuasive testimony, however, through their 1970's was, based on current knowledge, an error, and that today no dead-end system would be approved in excess of soon feet. Monroe County's condition, while preventing the discharge of degraded waters from Dispatch Creek to the park upon closure of the one way flushing valves, fails to address, however, the adverse impacts that could result from its closure. By closure of the valves, the flushing canal would be instantly converted into a 3,000-foot dead-end canal, and would suffer the same water quality problems as similar systems, with probable adverse effects to adjacent waters and the park. Accordingly, so as not to compound the existing error occasion by the extension of Dispatch Creek in the mid-1970's, prudence would dictate a proviso that, if the valves are shut, appropriate monitoring will occur within the waters of the flushing canal to detect any significant degradation of water quality, and that should such degradation pose a threat to adjacent waters or the park, that the Applicants be required, at their expense, to restore promptly the water quality within the flushing canal to Class III standards or restore the area to its present condition. Consistency of the proposed project with the Monroe County comprehensive plan and land development regulations Lack of plat approval As heretofore noted, the proposed canal would begin at the landward terminus of Dispatch Creek and run easterly within the rear lot lines of at least 15 lots in Harbour Course South subdivision, a platted subdivision, before it passed through fringing mangroves and terminated in the Atlantic Ocean. Currently, the final recorded plats of Harbour Course South subdivision do not reflect the proposed canal, as mandated by Section 177.091(15), Florida Statutes, and the Applicants have not sought to amend the plat to include the proposed canal. Pertinent to this case, the Monroe County Code (MCC), the land development regulations, /5 provides: Sec. 9.5-1. Purpose. It is the purpose of this chapter, the Land Development Regulations, to establish the standards, regulations, and procedures for review and approval of all proposed development of property in unincorporated Monroe County, and to provide a development review process what will be comprehensive, consistent and efficient in the implementation of the goals, policies and standards of the comprehensive plan . . . Sec. 9.5-2. Applicability. General Applicability: The provisions of this chapter shall apply to all land in unincorporated Monroe County. All development of whatever type and character, whether permitted as of right or as a conditional use, shall comply with the development standards and the environmental design criteria set forth in article VII hereof. No development shall be undertaken without prior approval and issuance of a development permit under the provisions of this chapter and other applicable laws and regulations. Sec. 9.5-81. Plat approval and recording required. * * * No building permit, 6/ except for single family detached dwellings and accessory uses thereto, shall be issued for the construction of any building, structure or improvement unless a final plat has been approved in accordance with the provisions of this division and recorded for the lot on which the construction is proposed. * * * (e) If a plat has been previously approved and recorded, technical or minor changes to the plat may be approved by the director of planning. All other changes shall be considered in accordance with the provisions of this Division. Sec. 9.5-94. Amendment of a recorded final plat. An amendment of a recorded final plat or portion thereof shall be accomplished in the same manner as for approval of the plat. Here, the subject permits were issued contrary to the foregoing provisions of the MCC because there was no final plat of record approving the canal as to each affected lot. While the Applicants offered proof, if credited, that the existing plat could be amended to include the canal as a "minor change" upon approval of the Director of Planning, it is noteworthy that no such approval has been obtained. More importantly, it is found that a change in the existing plat to include the canal would not constitute a "technical or minor change," and that formal amendment of the plat would be required. 7/ The provision of the MCC dealing with plat approval, provide a comprehensive scheme to assure, among other things, than the proposed plat is consistent with the purposes, goals and objectives of the comprehensive plan, the development regulations, and state laws, as well as affording an opportunity for public input. Of import here, the MCCs provide: Sec. 9.5-82. General Standards for Plat Approval. No preliminary or final plat shall be approved unless the plat is consistant with the purposes, goals and objectives of this plan, this chapter, applicable provisions of state law, the provisions governing the development of land set forth in article VII, and the procedures set forth in this article. Sec. 9.5-83. Preliminary Plat Approval. Generally. All applicants for approval of a plat involving five (5) or more lots shall submit a preliminary plat for approval in accordance with the provisions of this section. Application. An application for preliminary approval shall be submitted to the development review coordinator in accordance with the provisions of this section, accompanied by a nonrefundable fee as established from time to time by the board of county commissioners. The application shall contain the information required on a form provided by the director of planning. Staff Review. After a determination that the application for preliminary plat approval is complete under the provisions of section 9.5-44, the development review coordinator shall submit the application to the development review committee, which shall prepare a recommendation and report for the commission. Public Hearing and Action by the Planning Commission. The planning commission shall conduct a public hearing on an application for preliminary plat approval of a subdivision involving five (5) or more lots, in accordance with the requirements of sections 9.5-46 and 9.5-47. The commission shall review such applications, the recommendation of the development review committee, and the testimony at the public hearing, and shall recommend granting preliminary plat approval, granting approval subject to specified conditions, or denying the application at its next meeting following submittal of the report and recommendation of the development review committee. Effect of Approval of Preliminary Plat. Approval of a preliminary plat shall not constitute approval of a final plat or permission to proceed with development. Such approval shall constitute only authorization to proceed with the preparation of such documents as are required by the director of planning for a final plat. Sec. 9.5-84. Final Plat Approval. Generally. All applicants for approval of a plat shall submit a final plat for approval in accordance With the provisions of this section. Application. It shall be the responsibility of the developer to complete, have in final form, and submit to the development review coordinator for final processing the final plat, along with all final construction plans, required documents, exhibits, legal instruments to guarantee performance, certificates properly executed by all required agencies and parties as required in this article, and the recording fee, and any other documents or information as are required by the director of planning. After receipt of a complete application for final plat approval, as determined in accordance with section 9.5-44, development review coordinator shall submit the application and accompanying documents to the development review committee. Review and action by Development Review Committee. The development review committee shall review all applications for final plat approval. b. For a final plat for subdivision involving five (5) or more lots, if the plat conforms to the approved preliminary plate and the substantive and procedural requirements of this chapter, at its next regular meeting or as soon as practical after receipt of a complete application, the development reviews committee shall recommend to the planning commission approval of the final plat or approval with conditions. If the committee finds that the plant does not substantially conform to the approved preliminary plat or the substantive and procedural requirements of these regulations, the committee shall recommend denial, specifying the area(s) of nonconformity. Review and Action by the Planning Commission. The planning commission shall review all applications far final plat approval involving five (5) or more lots and the recommendation of the development review committee. If the commission finds that the final plat conforms to the approved preliminary plat and the substantive and procedural requirements of this chapter, the commission shall recommend to the board of county commissioners approval of the final plat, or approval with specified conditions, and shall submit a report and written findings in accordance with section 9.5-47. Public Hearing by the Board of Country Commissioners. The board off county commissioners shall conduct a public hearing on all applications for final plat approval involving five (5) or more lots in accordance with the procedures of section 9.5-46C. Action by the Board of County Commissioners. For proposed subdivisions involving five (5) or more lots the board of county commissioners shall review the application, the recommendations of the development review committee and the planning commission, and the testimony at the public hearing, and shall grant final plat approval, grant approval subject to specified conditions, or deny the application, in accordance with the provisions of section 9.5-47. Sec. 9.5-90.Maintenance of Private Improvements. If any plat of subdivision contains streets, easements, or other improvements to be retained for private use, the final plat for recordation shall indicate to the satisfaction of the director of planning and the county attorney the method or entity by which maintenance of the private improvements shall be performed. As a consequence of Monroe County's failure to comply with the provisions of its regulations which require final plat approval before a building permit may be issued, there has been no review by the Development Review Committee, no public hearing conducted by the Planning Commission, no recommendation of the Planning Commission, and no public hearing before the County Commissioners on the propriety of amending the subject plat to permit the proposed construction, or a resolution, through the plat approval process, as to whether the proposed canal is consistent with, inter alia, the purposes, goals, and objectives of the Monroe County comprehensive plan, as mandated by section 9.5-82(a), MCC. As importantly, where, as here, the proposed canal is to be retained for private use, there is no indication on the recorded plat, 4s required by MCC 9.5-90, of the method or entity by which maintenance of the canal shall be performed. Notably, the property through which the canal will be constructed is not owned by any of the Applicants but, rather, by Driscoll Properties , with whom the Applicants state they have an agreement to permit construction. 8/ Open space requirements and environmental design criteria Pertinent to this case, the MCC further provides: Sec. 9.5-3. Rules of construction. In the construction of the language of this chapter, the rules set out in this section shall be observed unless such construction would be inconsistent with the manifest intent of the board of commissioners as expressed in the Monroe County Comprehensive Plan or an element or portion thereof, adopted pursuant to chapters 163 and 380, Florida Statutes (1985). The rules of construction and definitions set out herein shall not be applied to any section of these regulations which shall contain any express provisions excluding such construction, or where the subject matter or context of such section is repugnant thereto. (a) Generally: All provisions, term , phrases and expressions contained in this chapter shall be liberally construed in order that the true intent and meaning of the board of county commissioners may be fully carried out. Terms used in this chapter, unless otherwise specially provided, shall have the meanings prescribed by the statutes of this state for the same terms. In the interpretation and application of any provision of this chapter, it shall be held to be the minimum requirement adopted for the promotion of the public health, safety, comfort, convenience and general welfare. Where any provision of this chapter imposes greater restrictions upon the subject matter than a general provision imposed by the Monroe County Code or another provision of this chapter, the provision imposing the greater restriction or regulation shall be deemed to be controlling . . (Emphasis added) Sec. 9-804 (MCLDR) Open space requirements. No land shall be developed, used or occupied such that the amount of open space on the parcel proposed for development is less than the following ratios, nor shall open space be cleared or otherwise disturbed including ground cover, understory, mid-story, and canopy vegetation. All such required areas shall be maintained in their natural condition. The amount of open space required on any parcel for development shall be determined according to each land type and no development activity within any individual land type shall exceed the open space ratio for that land type. Land Type on Existing Open Space Conditions Map Ratio Open Waters 1.00 Mangrove and Freshwater 1.00 Wetlands Salt Marsh and Buttonwood .80 Associations .85 High Hammock (High Quality) .80 High Hammock (Moderate Quality) .60 High Hammock (Low Quality) . 4 Low Hammock (High Quality) .80 Low Hammock (Moderate Quality) .60 Low Hammock (Low Quality) . 4 Palm Hammock .90 Cactus Hammock .90 Pinelands (High Quality) .80 Pinelands (Low Quality) .60 Beach Berm .90 Disturbed . 2 Disturbed with Hammock . 2 Disturbed with Salt Marsh and Buttonwood . 2 Disturbed Beach/Berm . 2 Disturbed with Exotics . 2 Disturbed with Slash Pines . 2 Offshore Islands . 9 (Emphasis added) Sec. 9.5-345. Environmental design criteria. No land, as designated on the existing conditions map and analyzed in accordance with the standards in sections 9.5-339 and 9.5-340, shall be developed, used ~re occupied except in accordance with the following criteria unless the county biologist recommends an authorized deviation from the following criteria in order to better serve the purpose and objectives of the plan and the director of planning or planning commission approves the recommendation as a minor or major conditional use. No recommendation for an authorized deviation from these environmental design criteria shall be made unless the county biologist makes written findings of fact and conclusions of biological opinion which substantiate the need and/or benefits to be derived from the authorized deviation. (m) Mangroves and Submerged Lands: Except as provided in subsection (3), only piers, docks, utility pilings and walkways shall be permitted on submerged lands and mangroves; All structures on any submerged lands and mangroves shall be designed, located and constructed such that: All structures shall be constructed on pilings or other supports; Bulkheads and seawall shall be permitted only to stabilize disturbed shorelines or to replace deteriorated existing bulkheads and seawalls; No structure shall be located on submerged land which is vegetated with sea grasses except as is necessary to reach waters at least four (4) feet below mean low level for docking facilities. (Emphasis added) From the foregoing regulations it is apparent that Monroe County has accorded mangroves the highest of protections. The regulations mandate a 100 percent open space ratio in such areas, and preclude any clearing or other disturbance of such areas. The only exception provided by the regulators, absent approval of an application for a minor or major conditional use, is for the construction of piers, docks, utility pilings and walkways, and then only when such structures are constructed on pilings or other supports to minimize their impact. Here, the proposed development, "permitted as of right" and not as a minor or major conditional use, fails to comply with the Monroe County land development regulations because it will result in the elimination of an existing mangrove community. In addition to the environmental design criteria established for mangroves by section 9.5-345, discussed supra, that section likewise establishes-specific performance standards for the development of any parcel (lot) depending on the habitat type, and where mixed habitat is encountered, requires that development occur on the least sensitive portions of the parcel. Here, while the Applicants did address the habitat types encountered along the canal alignment, the record fails to address the habitat types encountered on each of the platted lots through which the canal will run. Consequently, the Applicants failed to demonstrate that development of those lots, by construction of a canal within their rear boundary, would be consistent with the open space ratios mandated by section 9-804, MCLDR, or the environmental design criteria mandated by section 9.5-345, MCC. C. The Monroe County land development regulations further and implement the Monroe County comprehensive plan. The foregoing land development regulations were adopted by Monroe County, as well as approved by the Department and adopted by the Administrations Commission, to further and implement the standards, objectives and policies of the Monroe County comprehensive plan. That plan evidences a strong commitment to the protection, maintenance, and improvement of the Florida Keys environment. In this regard, the comprehensive plan provides: Sec. 2-104. Nearshore Waters The Florida Keys are dependent nearshore water quality for their environmental and economic integrity. The heart of the Florida Keys economy, the means by which Monroe County exists as a civil and social institution, is based on its unique, oceanic character. If nearshore water quality is not maintained, then the quality of life and the economy of Monroe County will be directly and immediately impacted. OBJECTIVES 1. To protect, maintain and, where appropriate, improve the quality of nearshore waters in Monroe County. POLICIES 1. To prohibit land uses that directly or indirectly degrade nearshore water quality. To prohibit the development of water dependent facilities, including marinas, at locations that would involve significant of the biological character of submerged lands. To limit the location of water- dependent facilities at locations that will not have a significant adverse impact on offshore resources of particular importance. For the purposes of this policy, offshore resources of particular importance shall mean hard coral bottoms, habitats of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of legs than four (4) feet, and all designated Aquatic Preserves under Ch. 258.39 et seq. the Florida Statutes. To limit the location of docking facilities to areas which have adequate circulation and tidal flushing. To protect wetland and transitional areas that serve to buffer, insulate and protect nearshore waters from run- off from upland areas. To prohibit the discharge of any pollutant directly or indirectly into nearshore waters. For the purposes of this policy, indirect discharge into nearshore waters shall include surface runoff, surface spreading or well injection of any effluent that does not meet state or federal standards for point and non-point discharges. To monitor nearshore water quality to ensure that growth and envelopment is not degrading nearshore water quality. To encourage the rehabilitation of canals and other water bodies where water quality has deteriorated. Sec. 2-105. Wetlands and Associated Systems Wetlands are an essential element of the Florida Keys and they play several vital roles. Wetlands serve as principal habitats for a wide variety of plants and animals, including juvenile forms of several commercially-exploited species of seafood. In addition, wetland plants play an important role in pollution control through nutrient uptake, and in primary production control through nutrient uptake, and in primary production for food webs. Wetland plants also serve as important natural buffers to the onslaught of storm-driven winds and water. OBJECTIVE To protect and maintain the functional integrity of wetlands and associated transitional areas within the Florida Keys. POLICIES To prohibit the destruction, disturbance or modification of any wetland or associated transition area, except where it can be demonstrated that the functional integrity of a wetland or associated transitional area will not be significantly adversely affected by such disturbance or modification. Marine Resources The great value attributed to Monroe County's marine resources is due to their crucial role in the local economy, and in providing a wide range of natural amenities and services. Health and integrity of the marine system is a fundamental prerequisite if these resources are to continue to provide social, economic, and environmental benefits that we have at times taken for granted. Mangroves, seagrasses, and coral reefs, all of which are susceptible to pollution and dredging, are extremely important in providing food and shelter for myriad forms of marine life, providing storm protection, and maintaining water quality. If uses and activities such as dredge and fill, destruction of natural vegetation, use of pesticides and fertilizers, improper sewage and solid waste disposal continue indiscriminately and uncontrolled; the ability of the marine system to function effectively will deteriorate, thereby resulting in the loss of many natural services and socioeconomic benefits to society. Therefore, it is imperative that such uses and activities be carefully regulated so as to insure conservation and protection of resources and long-term maintenance of their productivity. Marine Resources Management Policies Recognizing the crucial role that the marine environment plays in the economy, the protection, conservation, and management of marine resources will be viewed as an issue requiring the County's utmost attention. In an effort to protect and conserve marine resources, emphasis will be placed on protecting the entire marine ecosystem. To this end, maintenance of water quality; protection of marine flora and fauna, including shoreline vegetation; and preservation of coral reefs will be regarded as being absolutely essential to maintaining the integrity of the marine system. * * * Land and water activities which are incompatible with the preservation of marine resources because of their potential adverse effects will be prohibited, restricted, or carefully regulated depending upon the nature of activity and the extent of potential impact. * * * 3.2. Dredging and/or filling associated with maintenance or necessary water- dependent public projects shall be minimized and carefully managed to prevent unnecessary adverse environmental impact. The County will develop and enforce stringent development regulations to minimize water pollution from point and non-point sources in an effort to: improve and maintain quality of coastal waters. . Marine grass beds, mangrove communities, and associated shoreline vegetation will be preserved to the fullest extent possible. Removal of vegetation or modification of natural patters of tidal flow and nutrient input, cycling and export should be considered only in the case of overriding public interest. The County will encourage creation and restoration of marine grass beds, and mangrove communities in areas which could support such growth and could potentially enhance the environmental quality. As far as possible, natural patterns of gradual and dispersed runoff will be maintained. Land and water activity in the vicinity of stress areas (coral, grass bed, and inshore water quality) as identified and illustrated in the Florida Keys Coastal Zone Management Study and as may be discovered during any future study will be carefully controlled and regulated in an effort to arrest further deterioration. Research and study directed toward alleviating the stresses and restoring their condition to natural healthy state will be encouraged arid supported. Marine Resources Areas of Particular Concern Site-specific Designations Lignumvitae Key Aquatic Preserve. * * * Management Policies: B. Development activity on Upper and Lower Matecumbe Keys, including dredging and filling will be prohibited so as not to degrade the waters of the Preserve. * * * 3. John Pennekamp Coral Reef State Park and Key Largo Coral Reef Marine Sanctuary. Management Policies: * * * B. Development activity on Key Largo, including dredging and filling, urban runoff water, and the use of septic tanks will be controlled and regulated in order to minimize stresses which result in cater quality deterioration. Generic Designations All marine grass beds in waters off the Florida Keys. All patch reef coral and other reef formations found in the surrounding waters off the Keys. All shore-fringing mangrove and associated vegetation extending up to 50 feet laterally upland from the landward limit of the shoreline mangrove. Management Policies A. These biotic communities will be preserved to the fullest extent possible. Natural Vegetative Resources The diverse and often unique plant associations of the Florida Keys are a vital element of Monroe County's natural system and economic structure. The natural functions performed by these plant communities with1 regard to marine resources, unique and endangered wildlife, shoreline stabilization, filtering of urban runoff and scenic value make them vital elements in maintainance of the urban structure and attractions for the tourist base of Monroe County's economy. Natural Vegetation Management Policies In recognizing the need to preserve as much natural vegetation as possible, the County will direct its land use and development regulations; to minimize destruction of natural vegetation and modification of landscape. Guidelines and performance standards designed to protect natural vegetation from development will be developed and enforced. Clearing of native vegetation for development will be controlled. 3. Regulations controlling development in areas characterized primarily by wetland vegetative species such as mangrove and associated vegetation will emphasize preservation of natural vegetation to the maximum degree possible. 8. The existing County ordinances designed to protect and conserve natural vegetation will be strictly interpreted, rigidly enforced, and/or amended when necessary. Consistent with the Monroe County comprehensive plan, the Monroe County land development regulations further the standards, policies and objectives of the plan to protect, maintain and improve the Florida Keys environment. In this regard, the provisions of the regulations requiring final plat approval before a development order may issued provide assurance that the proposed activity will be -consistent with the comprehensive plan, the land development regulations, and applicable provisions of state law. Likewise, pertinent to this case, the provisions of section 9-864, MCLDR, regarding open space requirements, and section 9.5-345, regarding environmental design criteria, further the plan's policy to minimize the destruction of natural vegetation and modification of landscape, and to preserve to the maximum degree possible areas characterized primarily by wetland vegetation, such as mangroves and associated vegetation, and to permit such removal only in cases of overriding public interest. Here, while it cannot be concluded, as advocated by the Department, that the Monroe County comprehensive plan and land development regulations prohibit, under any circumstances, construction of the subject canal, it must be concluded, at this stage, that construction of the canal has not been demonstrated to be consistent with the plan and regulations. To be consistent, the Applicants would have to secure final plat approval for the canal, through the plat amendment process; a minor or major conditional use approval, as appropriate, as mandated by, inter alia, section 9 .5-345, MCC, for destruction of the mangrove community; and demonstrate that excavation of the canal on each of the platted lots would be consistent with the open space ratios of section 9- 804, MCLDR, and the environmental design criteria of section 9.5-34, MCC, or secure a conditional use as required by section 9.5-34-5, MCC. Amendment to the application post hearing In their proposed recommended order, submitted post hearing, the Applicants propose that the hearing officer recommend that, as a condition, the proposed canal terminate at the line of mean high water instead of extending approximately 100 feet into the boundaries of John Pennekamp State Park. The ostensible reason for the Applicants' request is their desire to eliminate the need for seeking approval from the Department of Natural Resources for intrusion into the boundaries of the park, and thereby shorten the time needed to secure all governmental approvals. While the Applicants did elicit testimony at hearing, albeit on rebuttal, that termination of the canal at the mean high water line would not significantly affect its performance as a flushing canal due to the extreme porosity of the caprock, the proof is not persuasive that the subject permits should be so limited or conditioned. Notably, the opinion that was offered in this regard was that of an expert hydrographic engineer who directed his remarks solely from a hydrographic viewpoint. The Applicants offered no testimony or other proof that would address the potential impacts, in any, that might occur to, inter alia, water quality or the biota, should the canal be terminated or closed in such a fashion. Under the circumstances, the Applicants failed to persuasively demonstrate that such amendment or condition is appropriate. This finding is not, however, preclusive of their applying for such modification to Monroe County.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Florida Land and Water Adjudicatory Commission enter a final order sustaining Monroe County's issuance of the subject permits in so far as they relate to Phase I of the proposed project, and reversing Monroe County's decision to issue the subject permits in so far as they relate to Phase II of the proposed project. It is further recommended that such final order specify those items set forth in paragraph 4, Conclusions of Law, as the changes necessary that would make the Applicants' proposal eligible to receive the requested permits for Phase II of their proposal. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 19th day of October 1990. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October 1990.
Findings Of Fact Petitioner James C. Dougherty owns property known as Buccaneer Point, which is a peninsula on the western side of Key Largo, Florida. This property is also known as Buccaneer Point Estates, and is a residential subdivision. On June 26, 1979, the Petitioner individually and as a trustee, applied to the Respondent for a permit to conduct dredging and filling activities at the aforementioned property, in particular, the project contemplated dredging access channels in Florida Bay and Buttonwood Sound and the connection of two existing inland lakes on the property site to those water bodies. After review, the Respondent denied the permit request and asserted permit jurisdiction in keeping with Chapters 253 and 403, Florida Statutes, and associated regulatory provisions found in the Florida Administrative Code. Having been denied the permit, the Petitioner requested a formal hearing to consider the matters in dispute and a hearing was conducted on the dates alluded to in this Recommended Order. The hearing was conducted in keeping with Subsection 120.57(1), Florida Statutes. The denial of the permit request was in the form of a letter of intent to deny dated May 27, 1980. See Petitioner's Exhibit No. 4, admitted into evidence. Following the receipt of the letter of intent to deny, the Petitioner commenced a series of revisions to the project leading to the present permit request which is generally described in Petitioner's Exhibit No. 6, admitted into evidence. If the project were allowed, it would call for the dredging of access channels in Florida Bay and Buttonwood Sound, those channels to be 75 feet long and -5 feet N.G.V.D., with side slopes of 1:3. Additional inland canals would be dredged to connect the access channels with the interior lakes, the north channel being 100 feet wide -6 feet N.G.V.D. and 400 feet long, and the south canal being 62 feet wide -6 feet N.G.V.D., and 225 feet long. Side slopes of the canals would be 1:3. The project also intends the connection of the two interior lakes by the excavation of a 162-foot long by 50-foot wide connection or plug at a depth of -5 feet N.G.V.D. The material from this excavation of the plug would be used as ton soil on the uplands. Finally, the permit proposes the shoaling of the North Lake on the property to -15 feet N.G.V.D. by the use of clean limerock fill. Through its opposition to the project, the Respondent has indicated concerns that bay grass beds would be damaged over the long term by boats as a result of the dredging of proposed channels and canals; a concern about increased BOD demands which would lower water quality following the long-term accumulation of organic materials in the channels. The Department also contends that construction of the south channel would destroy productive grass beds and "vegetated littoral shallows," which now serve as a nursery and feeding ground for numerous invertebrates. Respondent believes that the north channel would eliminate an area of mangrove wetlands which filters nutrients and toxic materials and serves as a nursery and feeding ground for estuarine organisms and wading birds. The Respondent also feels that the north channel would disturb a stable mangrove humus peat band, which now supports large numbers of invertebrates and which band extends along the northern shoreline of Buccaneer Point. The Department, in discussing the acceptability of the permit, has expressed concern that bottoms adjacent to the north channel would be harmed by increased erosion and sedimentation of the disturbed mangrove peat. Respondent has further stated that water in both interior lakes is now in violation of water quality standards and that water quality data shows high oxygen demands. The Respondent has put at issue the Petitioner's hydrographic report on the flow-through lake system, citing what it believes to be errors in the report. The Respondent has expressed specific concern about water quality standards as set forth in the following rules: Rule 17-3.121(5), Florida Administrative Code, Bacteriological Quality; Rule 17-3.121(7), Florida Administrative Code, Biological Integrity; Rule 17-3.061(2)(b) Florida Administrative Code, BOD; Rule 17-3.121(14), Florida Administrative Code, Dissolved Oxygen; Rule 17-3.121(20), Florida Administrative Code, Nutrients; Rule 17-3.061(2)(j) Florida Administrative Code, Oils and Greases; Rule 17- 3.061(2)(1), Florida Administrative Code, Phenolic Compounds; Rule 17-3.121(28), Florida Administrative Code, Transparency; and Rule 17-3.061(2)(a), Florida Administrative Code, Substances. The Respondent indicated that it felt the project would be adverse to the public interest because it would cause erosion, shoaling, or creation of stagnated areas of water, would interfere with the conservation of fish, marine life and wildlife or other natural resources, and would result in the destruction of oyster beds, clam beds or marine productivity, including destruction of natural marine habitats or grass flats suitable as nurseries or feeding grounds for marine life, including established marine soils which are suitable for producing plant growth of a type useful as nursery or feeding grounds for marine life. The project was also thought by the Department to be not in the public interest because it would reduce the capability of the habitat to support a well-balanced fish and wildlife population because it would impair the management or feasibility of management of fish and wildlife resources. The Petitioner has employed hydrographic engineers to conduct a study of the flushing characteristics of the system, should the access channels, canals and interior connections be allowed. It is an undertaking on the part of the Petitioner dealing with physical characteristics of the waterway and the forcing conditions in and around the site, which include tidal flow, wind-driven flow and mean sea level changes. The two State water bodies at the site, Buttonwood Sound and Florida Bay, are separated by the project site and other islands at the northern tip of the project. The effects of this separation changes the arrival time of high tide at the northern and southern extremities of the project site promoting a mean sea level surface difference between Buttonwood Sound and Florida Bay. The sea level difference or "head" assists in generating flow in the sense of moving the water from the high to the low elevation. To gain an exact measure of the hydraulic head, tidal gauges were placed at the northern entrance channel and in the southern entrance channel. The use of these gauges over a period of time allowed the determination of the spring and neap tide conditions. The "head" differences finally arrived at by calculations by the Petitioner's experts assisted in the creation of a mathematical model to determine flows in the water system. This lead to an estimate of flushing time of 2 1/2 days. See Petitioner's Exhibits 7-9,admitted into evidence. In turn, an estimation was made that approximately half of the flow which presently flows through Baker Cut, at the project site, would be diverted to the waterway system if constructed and this in conjunction with other calculations led to the conclusion that the flushing time was 3 to 4 days as opposed to the 2 1/2 days arrived at by the mathematical system. See Petitioner's Exhibit 10, admitted into evidence. The estimate of 3 to 4 days was the more current study and was premised upon conditions of an adverse south, southeast wind which would cause the water to move north, absent current conditions, as opposed to this south direction which was the normal direction of movement. The Petitioner also examined the flushing characteristics of similar projects which were not as favorable because of a lack of "head" differences which assisted in the flow of the water. Based upon the results of the studies conducted by Petitioner's experts, the flushing time of the system is found to be 3 to 4 days. While there is some correlation between a short flushing time for a water system and the water quality within that system, examination of other channel systems in the Florida Keys indicates that short flushing times do not always cause the waters to meet State water quality standards. For that reason, water quality considerations must be dealt with bearing in mind the physical characteristics of the system extant and as proposed using flushing time as a part of the equation. Those specific water quality criteria will be addressed in subsequent portions of these findings. Tests conducted by the parties dealt with the amount of dissolved oxygen in waters at the project site, and revealed dissolved oxygen levels of less than 4 parts per million, even when testing at depths less than 15 feet. This condition is one which is not unusual for natural water systems which have remarkable stability and are not the subject of flow or flushing, as example in mangrove forests. If the system were open, dissolved oxygen levels in the interior lakes would improve, though not necessarily to a level which no longer violates State water quality considerations related to dissolved oxygen levels. On the related subject of BOD or biochemical oxygen demand, that demand placed on oxygen in the water biochemicals or organic materials, the system as it exists and as proposed does not appear to cause excessive BOD, notwithstanding an 8 to 12 foot wide band of peat substrate in the area of the North Lake wall. Although the biochemical oxygen demand related to the layer of peat in the lake's system in its present state presents no difficulty, if the water system were open this peat layer would cause a significant amount of loading of biochemical oxygen demand in the lake system and eventually the surrounding water bodies. On the question of nutrients in the marine system, reflected by levels of phosphorus and nitrogen or variations impact the compensation point for the North Lake. In fact, there would be improvement in transparency or clarity for both lakes. Nonetheless, in the short run, the turbidity problems associated with the placement of clean limerock fill over the flocculent peat material would violate the transparency standard in that location. On the subject of toxic substances, meaning synthetic organics or heavy metals in sea water, tests by the Petitioner at the project site and comparison site demonstrated that those substances would not exceed the criterion related to those materials. On the subject of fecal coliform bacteria, water quality samples were taken at the project site and a comparison site. The residences now at the project site and those at a development known as Private Park use septic tanks. In view of the porous nature of the limerock foundation upon which the residences are built and in which the septic tanks are placed, the possibility exists for horizontal movement of the leachate into surrounding waters of the project site and the landlocked lakes; however, this movement is not dependent upon the opening of a flow-through system at the project site. Moreover, tests that were conducted in the comparison site and project site reveal less than one fecal coliform bacterium per 100 milliliters and if the system were open, the circulation in the lakes would lower the residence time of leachate. In describing the habitat afforded by the interior lakes as they now exist, the North Lake does not afford animals or fish the opportunity to colonize, because there are no areas where they may disappear into the lake. This limits the opportunity for habitat to those animals who have their entire life cycle in a landlocked system, and necessarily of those substances in the water, water quality standards for nutrients will not be substantially altered by the proposed project. In other words, the project will not cause an imbalance in natural aquatic flora or fauna population, by way of advent of phytoplankton bloom leading to eutrophy. The nutrient samples taken in the interior lakes demonstrate normal sea water levels and those levels outside the lake were low and the flow-through system is not expected to raise nutrient levels. Sampling for oils and greases in the comparison waterways where residential development had occurred in the lakes and ambient waters at the site, did not indicate problems with those substances in the sense of violation of State water quality standards. Sampling for phenolic compounds at the comparison sites and at the lakes and ambient waters at the project site showed less than .001 micrograms per liter in each instance of the sample. There are no sources or potential sources of phenols at the site. On the question of the State water quality dealing with transparency, that standard requires that the level of the compensation point for photosynthetic activity shall not be reduced by more than ten percent (10 percent) compared to natural background levels. The compensation point for photosynthetic activity is the level at which plant and animal respiration and photosynthetic activity are equal. In static state, the Petitioner's analysis of this criterion revealed that the North Lake compensation point would be below 15 feet and the South Lake would have no compensation point, due to its shallow nature. In the long run, the opening of the proposed connections in the planned development together with the shoaling, would not negatively excludes animals with a long larva stage. Examination of comparison sites pointed out the possibility for colonization at the project site should the waterways be opened. Specific testing that was done related to colonization by fishes, in particular sport and commercial fishes, demonstrated that those species increased in richness, density and diversity if a system was opened by channels and canals. In addition, the comparison of this project site and systems similar to that contemplated by the open waterway indicated that sea grasses would increase after a period of years if the system were open. Sampling was conducted in substrates to gain some understanding of the effect of the proposed project on the Shannon Weaver Index, i.e., whether there would be a reduction by less than 75 percent of established background levels. Although there would be no problem with the biological integrity standard related to South Lake and its waterway, the North Lake and waterway system could be expected to be in violation of that index due to the present circumstance as contrasted with that circumstance at the point when water flowed through. If the waters were opened to the project site, marine biological systems on the outside of the interior lakes would be given an opportunity to use those lakes as a nursery ground or spawning site for fishes, a refuge in cold weather conditions and a site for predators to find prey. If the lakes were opened to the outlying areas, alga, grass populations, mobile invertebra, plankton and other forms of life could utilize the interior lakes. In the area where the north canal or inland canal would be placed are found red mangroves (Rhizophora mangle) and black mangroves (Avicennia germinas) . The mangroves are frequently inundated by tidal waters and are the most mature and productive of the mangroves which are found at the property site. Some of those mangroves are located waterward of the line of mean high water and would be removed if the project is permitted. The mangroves at the project site provide filtration of sediments and nutrients contained in stormwater runoff from adjacent upland areas, as well as from tidal flows. This filtering process is an essential part of the maintenance of water quality in the adjacent open bay estuarine or marine system. Nutrients in the tidal waters, as well as runoff waters, are settled out and in the sediments retained by the mangrove roots and are transformed into vegetative leaf matter by the mangroves as they live and grow. The root systems of the mangroves and their associated vegetation provide stabilization of estuarine shoreline sediments and attenuation of storm-generated tides. These mangrove wetlands provide unique and irreplaceable habitats for a wide variety of marine as well as upland wildlife species. The mangroves also contribute leaf or detrital matter to the surrounding State waters and estuarine system in the form of decayed leaf litter. This organic component forms the basis of the marine food chain and is used directly for food by a variety of marine organisms, including small fish. Commercial and sports fish species feed directly on the mangrove detritous or on the fish or other forms of marine life that feed on that detrital matter. In removing the mangroves, the applicant causes a loss of the function which those plants provide in the way of filtration and the promotion of higher water quality and causes biological impact on marine organisms, to include sports and commercial fishes. In the area of the north access channel, there exists a band of stable mangrove peat which is 50 to 75 feet wide and one to two feet thick. Waterward of this expanse of humus is located a sandy bottom vegetated by turtle grass and other sea grasses and alga. The turtle grass in the area of the proposed north channel serves as a nursery and feeding ground for a rich and diverse aquatic community, including species of oysters, clams and other mollusks, as well as commercial and sports fish. This grass also filters and assimilates contaminants in the water column and serves to stabilize sediments to prevent turbidity. Dredging would destroy the turtle grass beds and their functions. These impacts on mangroves and sea grasses are significant matters, notwithstanding the fact that the possibility exists that mangroves would repopulate in the area of the north channel and North Lake, together with the repopulation of sea grasses in that area after a period of years. The south waterway would cause the removal of certain sea grasses, which could be expected to revegetate. Moreover, at present, the sea grasses in this area are sparse due to the shallow waters in that area, which waters are too warm for sea grasses to thrive. Construction of the access channel would result in increased erosion and sedimentation based upon boat wake wash and in turn allow for adverse impact on the biologically productive bay bottom. Water quality degradation can be anticipated because of the erosion and leaching of dissolved particulate material from the disturbed peat band at the shoreline and into shallow waters in the bay and into the North Lake. Transition from the inland channels to the bay side access channels at the north and south will be box cut at the mean high water line and in view of the fact that the inland channels are 100 feet wide and the bay side access channels are only 50 feet wide, erosion can be expected, causing turbidity.
Findings Of Fact The Petitioner, E. F. Guyton, has filed an application for a permit which would allow the dredging of a boat slip and construction of a sedimentation basin with boat storage, specifically requiring the excavation of a boat basin, access canal, and access channel on his property which is located on the west shore of Crescent Lake, in Putnam County, Florida. The permit application number is 54-6806. The Respondent, State of Florida, Department of Environmental Regulation, is an agency of the State of Florida which has the responsibility of appraising those applications such as the one submitted by the Petitioner, E. F. Guyton, and making a decision to grant or deny that permit. The authority for such action on the part of the Respondent resides in Chapters 253 and 403, Florida Statutes, and Rule 17, Florida Administrative Code. This cause comes on for consideration based upon the Respondent's letter of intent to deny the application, as dated August 22, 1978, after which the Petitioner has filed its petition challenging that intent to deny and requesting that the permit be granted. The petition in behalf of the Petitioner was received by the office of the Respondent on September 8, 1978. It was subsequently assigned to the Division of Administrative Hearings for consideration and that Notice of Assignment was dated September 28, 1978. The proposal for permit calls for excavation of a boat basin 100 feet wide and 480 feet long, leading into an access canal 25 feet wide and 500 feet long. This excavation is in the vicinity of an existing intermittent natural stream. The proposal would call for the removal of approximately 21,000 cubic yards of silt and sand, landward of mean high water. The excavation would be accomplished by use of a dragline to a depth of -2.0 feet MSL. The basin and canal slopes would be 2:1 and stabilization of slopes would be assured by riprap and grassing. A concrete spillway would be constructed at the upper end of the basin to direct the stream flow into the basin. In addition, the proposal calls for the dredging of an access channel through the shallow littoral zone of Crescent Lake to the mouth of the proposed access canal. The dredging involved with the access channel would cause the removal of 400 cubic yards of sediment from an area 250 feet long and as wide as 30 feet. The proposed depth of the channel is 2.0 feet MSL and slide slopes would be 5:1. The spoil would be pumped to a dike holding area on adjacent uplands. The Respondent's Exhibit No. 1, which is the permit application, offers a sketch of the boat basin with secondary sedimentation feature and the attendant access canal and channel. The project lies between U.S. Highway 17 and Crescent Lake, Areas to the south and west of the site are pasture and bayhead wetlands and they serve as a watershed for the aforementioned intermittent stream. Other upland areas in the vicinity are dominated by fully-drained flat woods and well-drained sand hill and messic oak terrain. The project site waterward of the mean high water is part of a shallow littoral zone of the west shore of Cresent Lake. The intermittent stream receives the runoff from the pastureland and drainage from U.S. Highway 17. There is a pronounced change in elevation during the course of the intermittent stream. The submerged littoral zone of the lake, which includes the proposed site of the access canal, falls away at a gentle slope and includes a number of supporting hardwoods, predominantly bald cypress. The area also includes submerged emergent vegetation, which is found in the shallows offshore. These shallows are exposed to favorable sunlight from the point of view of the health of this vegetation. The vegetation includes an emergent bed of oft stem bulrush (Sicrpus validus) which is in line with the proposed channel. Within the photic zone there is submerged tape grass (Valisneria americana) and naiad (Najas sp.). On the shore of Crescent Lake at the project site is found a hardwood swamp in its natural form, together with a creekbed which divides into numerous channels fanning out in the direction of the lake itself. This area of the creekbed contains bald cypress (Taxodium distichum), red maple (Acer rubrum), swamp ash (Fraxinus panciflora), black willow (Salix nigra), black gum (Nyssa biflra), water hickory (Carya aquatica), and wax myrtle (Myrica cerifera). The herbs and ferns in this area include penny wort (Hydrocotyl umbellata), arrow- arum (Peltandra virginica), leather fern (Acrostichum danaeifolium), and royal fern (Osmunda regalis). The sediments found in the creek area are sandy to silty sand. In the area where the boat basin/sedimentation facility would be located, the present intermittent stream is much more confined than in the area of the creekbed. Only in times of heavy rainfall does the water come outside the banks of the intermittent stream and inundate the surrounding territory. This portion of the stream is densely vegetated by a mixture of hydrophytes, facultative hydrophytes, an optimally situated upland species. These include sweet bay (Magnolia virginiana), black gum (Nyssa biflora), and red maple (Acer rubrum). Additionally, there are slash pine (Pinus elliotii), long leaf pine (Pinus palustris), dahoon (Ilex cassine), wax myrtle (Myrica cerifera), water oak (Quercus nigra), wild azalea (Ericaceae), and saw palmetto (Serenoa repens). The sedminets in this area range from very sandy in the slightly higher elevations adjacent to the stream bed to a heavy peat which is found predominantly in the bay tree locations. The uplands in the agricultural area are dominated by water oak, slash pine, long leaf pine, live oak and saw palmetto. A more graphic depiction of the project site and in particular as it relates to the intermittent stream, shore line upland agricultural area, and U.S. Highway 17 may be found in the Petitioner's Exhibits 1 and 2 and the Respondent's Exhibits 2 through 15, which are photographs of the project site. There are numerous varieties of fish in the area of Crescent Lake through which the access channel would be routed. These include: Seminole killifish (Fundulus seminolis), naked goby (Gobiosoma bosci), black bullhead (Ictalurus melas), brook silversides (Labidesthes sicculus), sunfish (Lepomis sp.), large-mouth bass (Micropterus salmoides) and Atlantic needlefish (Strongylura marina) . In addition, there are 35 species of invertebrates which were collected in the studies made by employees of the Respondent in their assessment of this permit application. The names of those invertebrates may be found in the Respondent's Exhibit No. 19 which was admitted into evidence in the course of the hearing. The vegetation and shallow water with a sandy bottom, together with the numbers and species of macro invertebrates, small fishes and immature game fishes point to the fact that this part of the lake serves as a valuable site for the propagation of fish, otherwise referred to as a spawning ground. The water quality in Crescent Lake at the site of the project is good, from the standpoint of gross observations. However, there have been some indications of eutrophication in Cresent Lake. A more complete understanding of the water quality may be gained from an examination of the Respondent's Exhibits 21 through 41 admitted into evidence. These exhibits are constituted of certain water quality reports rendered after extensive testing in Crescent Lake. The rainfall in the area exceeds 54 inches a year, with 50 percent of that rainfall being recorded in the wettest quarter, in which over 7 inches a month would fall. July has recorded 15 inches as a mean measurement over the last 80 years, with the month of May showing less than 2 inches, the month of September showing less than 2 inches and the month of October less than 1 inch. In considering the proposed project, a beginning point would be an examination of the ability of the primary filtration pond and secondary filtration function found in the boat basin, to adequately disperse the pollutants which will come into the system from the agricultural area and U.S. Highway 17. That treatment system is inadequate. The inadequacy exists because in periods of low rainfall the pollutants will settle to the bottom of the siltation system and will not be dispersed evenly. This cycle of low rainfall when followed by heavy rainfall, such as occurs in July, will cause the pollutants to be rapidly discharged from the system into the basin of the lake, either in a dissolved form or a free form, causing an unreasonable dilatorious effect to water quality and creating possible turbidity. The confined nature of the proposed channel which empties into the lake will promote scouring because the water is coming out in a more confined area than the natural access allows at present. In addition, the flow velocity in the secondary siltation system is not strong enough to flush out the pollutants in an efficient manner. Finally, channelization promoted by the system would remove a certain percentage of the biological treatment that occurs in the natural intermittent stream, thereby introducing a greater quantity of pollutants into the lake and reducing oxidation that this biological treatment and natural course of the intermittent stream bed now provides. The project, as contemplated, is very similar in its nature to the canal system in Dunns Creek, a body of water adjacent to Crescent Lake. A study conducted on that canal system revealed a very poor quality of dissolved oxygen, which falls below the water quality standards for Class III waters. (A copy of this report may be found as Respondent's Exhibit No. 20 admitted into evidence.) These are the same standards that would apply to Crescent Lake. In addition, there is a lack of flushing and the development of aquatic weeds deterimental to the fish and invertebrates located in the area of the Dunns Creek canals. Therefore, a similar problem could be expected in the project now under consideration. If the project were completed, the excavation of the material would cause disruption of the sediment and water quality degradation if precipitation occurred during the excavation. Efforts at turbidity control would not protect against a heavy rain and the maturely vegetated stream bed and productive littoral vegetation and substrates would be lost. The long term effects of the project would cause degradation of the water quality and a loss of fish and wildlife resources in the impact area. The filtrative assimilative capacity provided by the algae, shrubs, trees and associated substrates involved in the process of absorption and in aerobic bacterial metabolism, would be eliminated by the project and replaced by an intermittently flushed, highly nutrified shallow water lagoon and canal. Pollutants associated with boat operations would further compound the water quality problems and perpetual sediment disruption would occur because of a natural result of shallow water maintenance and use of the system. Siltation and periodic discharge of degraded basin water into the littoral zone of the lake would adversely effect the productive potential and the habitat potential offered by this area in its present form. Based upon a full assessment of the project, it is established that there would be increased and harmful erosion, shoaling of the channel and the creation of stagnant areas of water. It would also cause an interference with the conservation of fish, marine and wildlife to an extent that is contrary to the public interest. It would promote the destruction of natural marine habitats, grass flats suitable as nurseries or feeding grounds for marine life and established marine soils suitable for producing plant growth of a type useful as a nursery or feeding ground for marine life or natural shoreline processes to an extent contrary to the public interests. These failings are in direct contravention of Chapter 253, Florida Statutes. The project would be contrary to State Water Quality Standards, as developed pursuant to authority of Chapter 403, Florida Statutes. Thus, the Petitioner has failed to give reasonable assurances that the immediate and long term impacts of the project would not result in a violation of the State Water Quality Standards, as required by Rule 17-4.28(3), Florida Administrative Code.