Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 1
LEE A. EVERHART AND COMPANY, INC. vs. DEPARTMENT OF CORRECTIONS, 83-001761 (1983)
Division of Administrative Hearings, Florida Number: 83-001761 Latest Update: May 02, 1990

Findings Of Fact On or about February 9, 1983, the State of Florida, Department of General Services, Division of Construction and Property Management, Bureau of Property Management ("DGS"), received a certification of need from the Department of Corrections ("DOC") requesting authority for DOC to advertise for competitive bids from private persons interested in providing leased office space needed to house DOC's Bureau of Industries. The Bureau of Industries was then located in leased space with leases which were scheduled to expire June 30, 1983. The Bureau of Industries has been located in DOC's central office area since its creation in 1957. The DOC central office includes the Secretary and Deputy Secretary; the Assistant Secretaries for Operations, Programs, Management, and Budget. All these officials, together with subsidiary bureaus, staff, and other subordinates are located in two adjacent buildings of the Winewood Office Complex on Blair Stone Road in Tallahassee. The prison industry program is under the supervision of the industries administrator who reports directly to the Assistant Secretary for Operations. DOC sought approval from DGS to enter into a lease for privately owned office space because of its perceived need to locate within walking distance of its central office. Programs administered by the Bureau of Industries work closely with other DOC personnel and functions located in the central office in the Winewood Office Complex. Moving any distance from the central office would create problems for the DOC mailing system and would require extra time spent traveling to and from the central office. Personnel in the Bureau of Industries utilize central office files, and confer often with staff located in the central office. Locating outside the general area of the central office would require additional expenses with regard to availability of vehicles, pick up of mail and supplies, and duplication of support services. Accordingly, DGS and DOC determined, and the record in this cause establishes, that it would not be in the state's best interest to require DOC to locate its Bureau of Industries program either in state-owned buildings in the Capitol Center, or in any area beyond walking distance of the central office location. On March 21 and 31, 1983, respectively, DOC published an advertisement in the Tallahassee Democrat inviting all interested persons to submit sealed bids at or before 2:00 p.m. on April 19, 1983, in accordance with the Invitation to Bid and Specifications prepared by DOC for the office space needed to house the Bureau of Industries. A portion of the bid specifications required that office space to be leased be located within a circle drawn on a city map of the City of Tallahassee, Florida, which could roughly be described as the southeastern portion of the city, in the vicinity of the Winewood Office Complex. There were four possible bidders in the area within the circle on the map attached to the bid specifications. Of these four possible bidders, two within the area actually submitted bids--Blairstone Center Partners and Washington Square, Ltd. One of the general provisions of the bid specifications provided as follows: The Department of Corrections reserves the right to reject any and all bids, waive any minor informality or technicality in bids received and to accept that bid deemed to be the lowest and best. . . At or before 11:00 a.m. on April 19, 1983, DOC received sealed bids from Petitioner and Intervenors in response to the aforesaid advertisement, and at 11:00 a.m. on April 19, 1983, DOC opened, tabulated, and published each of the bids. The bid submitted by Petitioner was not responsive to the requirements of the Invitation to Bid and Specifications because the property offered by Petitioner in its response was outside the area indicated on the map annexed to the Invitation to Bid. The bid submitted by Intervenor, Blairstone Center Partners, failed to offer the full services specified in paragraph six of DOC's Bid Submittal Form; failed to offer the exclusive parking specified in the paragraph seven of the Bid Submittal Form; failed to supply the photographs specified in paragraph ten of Respondent's Bid Submittal Form; and failed to supply the information specified in paragraphs one through eight of the Bid Submittal Form. Accordingly, the record in this cause fully establishes that the bids submitted by Petitioner and by Intervenors Blairstone Center Partners, failed to comply with the requirements of the Invitation to Bid and Bid Submittal Form, and that the deficiencies in the bids of Petitioner and Intervenor, Blairstone Center Partners, were so material as to require their rejection. The Invitation to Bid and Bid Submittal Form required that bidders offer for lease 2,683 square feet, plus or minus three percent. The bid submitted by Intervenor, Washington Square, Ltd., offered 2,797 square feet, which is approximately 34 square feet more than allowed in the Invitation to Bid. After this fact was discovered upon opening the bid, DOC personnel contacted a representative of Washington Square, Ltd., and advised the net square footage offered in the bid submitted by Washington Square, Ltd., exceeded the net square footage of space that DOC was authorized to lease and pay for under the Invitation to Bid. Washington Square, Ltd., subsequently agreed to modify its proposal by relieving DOC from any obligation to pay for the extra 34 square feet, and reducing the annual rental for the first year from $26,012.10 to $25,695.90, and for the second year from $27,576.60 to $27,243.18. The record in this cause does not establish any misconduct or collusion between Washington Square, Ltd., and DOC personnel obtaining this modification, nor does the record in this cause establish that any actual or prospective bidders suffered any competitive disadvantage as a result of this modification. The effect of Washington Square, Ltd.'s modification of its proposal rendered that proposal the only bid which was responsive to the Invitation to Bid. On August 18, 1983, Washington Square, Ltd., executed a deed to the property which was the subject matter of its bid to Ben Grace. Washington Square also executed an assignment of the proposed bid award to Grace.

Florida Laws (3) 120.57243.18255.25
# 2
EDWARD D. MATTHEWS AND ROBERT C. WALKER vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 89-002529BID (1989)
Division of Administrative Hearings, Florida Number: 89-002529BID Latest Update: Jul. 21, 1989

Findings Of Fact Sometime before January, 1989, The Department of Health and Rehabilitative Services (HRS) requested and received approval from the Department of General Services (DGS) for additional office space to provide for social services in Haines City, Florida. HRS was authorized to procure, through competitive bidding, a lease of 9041 square feet of existing office space, plus or minus 3%. Public notice that HRS was seeking competitive bids was given by advertisement in four central Florida newspapers. HRS had prepared a document entitled Invitation to Bid for Existing Facilities (ITB), which set forth in detail all of HRS' requirements. The purpose of the ITB was to inform all potential bidders of the minimum requirements for submitting a responsive bid, and the specific criteria by which the bids would be evaluated. The evaluation factors and their relative weights were stated in the ITB: Evaluation Criteria The successful bid will be that one determined to be the lowest and best. All bids will be evaluated on the award factors enumerated below: Associated Fiscal Costs Rental rates for basic term of lease. Evaluated using present value methodology by application of the present value discount rate of % (Weighting: 30) Rental rates for optional renewal of terms of lease. Rates proposed are within projected budgeting restraints of the department. (Weighting: 5) Associated moving costs i.e. furniture, equipment, telephone systems, etc. (Weighting: 0) Location Proximity of offered space in central or preferred area of map boundaries. (Weighting: 10) Frequency and availability of satisfactory public transportation within proximity of the offered space. (Weighting: 5) The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of the departmental operations planned for the requested space. (Weighting: 20) Facility Susceptibility of the design of the space offered to efficient layout and good utilization. (Weighting: 20) Provision of the aggregate square footage in a single building. Proposals will be considered, but fewer points given, which offer the aggregate square footage in not more than two locations provided the facilities are immediately adjacent to or within 15 yards of each other. (Weighting: 10) TOTAL POSSIBLE 100% The bid package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: rental rates environmental factors efficient space layout The above areas were important to HRS since the agency would render indigent services to several hundred people every month. The majority of Respondent's clients are served within a 10 day period each month. A great deal of pressure is placed on the surrounding area due to the influx of people. Because of servicing so many people, factors two and three received a great deal of weight under HRS's consideration of the property it desired to lease and occupy. All of the above areas were covered by Respondent's weighted bid evaluation criteria. Sealed bids were submitted by Intervenor, Unirealty Services, Inc. (bid A), and Petitioners, Messrs. Matthews and Walker (bid B). The bids were opened February 20, 1989, and Mr. Michael T. Akridge, former Facilities Services Manager, District VI HRS, determined both bids were responsive. At the time the Intervenors submitted their bid, they included documentation which showed that they had an option contract to purchase the subject facility, and an authorization from the optionees (two principals of Intervenors) for Unirealty to act as their agent. Both Petitioner's and Intervenor's property were within the mandatory geographical area designated in the bid package. Both bids were responsive under the minimum bid specifications and bidder qualifications. The District Administrator appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to him the committee's choice of lowest and best bid. The purpose in establishing the bid evaluation committee was to secure input from a cross section of people who had a variety of backgrounds and knowledge that would be material in evaluating the office space, in light of the uses for which it was intended and the relative public worth of the work space. Six individuals who were familiar with the type of work to be done in the proposed space, as well as persons familiar with the bid process were appointed to the Committee. The bid evaluation committee determined that the bid of Unirealty was the "lowest and best." The bid evaluation committee consisted of six representatives of the Department who visited each bidders' site and questioned the bidders' representatives. Each of the committee members worked with or supervised HRS programs that were to be located in the leased space. The solicitation for bids provided each bidder, among other things, with the bid evaluation criteria, a 100 point scale, which the committee used to evaluate the bids. Each committee member's evaluation scores were averaged and totaled to score Petitioners at 90.8, and Unirealty at 83.9. Each committee member gave a higher score to Unirealty. The three major bid evaluation criteria were FISCAL COSTS, LOCATION and FACILITY. Under the FISCAL COST criterion were three sub-categories: Rental Rates, Renewal Rates, and Moving Costs. For Rental Rates, Petitioners received 30 points out of 30 possible, and Unirealty got 23.1. For Renewal Rates, Petitioners got 5 out of 5 possible points, and Unirealty received 3.7 points. No points were awarded for Moving Costs. The evaluation committee did not assess points for Rental or Renewal Rates. These were scored by Michael T. Akridge, bid manager, based on a present value analysis of bidders' proposed rates. Mr. Akridge did not give the Committee the points for Rental and Renewal Rates until after they had completed their evaluations of the LOCATION and FACILITY criteria. The LOCATION criterion also had three sub-categories: Central Area-- 10 points--with both bidders receiving 9.3; Public Transportation--5 points-- which both bidders received; and, Environmental Factors--20 points--out of which Petitioners received 12.8 points and Unirealty 20 points. The Environmental Factors sub-category included building physical characteristics and surrounding area and their effect on the efficient and economical conduct of Department operations. Unirealty received a higher score than Petitioner because the committee believed its building had a better appearance, and was in better shape. The area surrounding the building was more open, while Petitioners' building was in a less desirable neighborhood with a bar or liquor store and bus station nearby which could create problems for clients because of transients. It had far more window space which creates a better work environment, and allows staff to be watchful of clients and their children outside, and the windows would be tinted. The windows at Petitioner's site were limited and no more could be added. Unirealty had more adjacent parking spaces, with handicapped parking closer to the building, and part of it was fenced which provided added protection to clients and staff. Petitioners' site had adjacent businesses whose patrons were using some of the parking spaces which the committee felt could create a problem. The Unirealty building could have an outside food stamp issuance facility which would be far more accessible to clients and to make the lobbies less crowded. It had an existing alarm system. It did not have side streets adjacent to the building, thus there would be less traffic congestion and therefore safer for clients; and, it had outside gathering areas where clients could go to smoke. Of the three sub-categories under FACILITY, Petitioners received 11.8 points out of 20 for Layout/Utilization and Unirealty received 19.7 points; for Single Building, both bidders received 10 points out of 10 possible. For the Layout/Utilization sub-category Unirealty received more points because its building configuration was more flexible and conducive to design of interior space, with less maze effect. The members of the committee each testified that it was important that the Unirealty building had no support poles to get in the way as they did in Petitioners' building. The support poles in Petitioner's building created a safety problem for clients and inhibited the location of desks and corridors. At Unirealty's site each worker could have a window, and mechanical and service areas could be put in the center of the building, with a playroom for clients' children. It provided a better restroom location near the front of Petitioner's building and lobby areas, and clients would not have to wander through work areas to get to the restrooms. Unirealty's building provided better control of clients' movements and thus better security. Members of the committee also upgraded the Unirealty building because its pitched roof was less likely to leak and its air conditioning was zoned thus providing better air quality and temperature control. At Unirealty there was better ingress and egress, and entry ways could be added. This could not be done at Petitioners' site. The Unirealty building could have different entrances for each HRS program, with separate lobbies for each program with less client congestion and better control. During the Committee members inspection of the sites they were told of an existing security alarm system already in place at the Unirealty site and were told that system would remain in place. When asked, the Petitioner's representative was unsure if his client would install a similar system at their site. A security system for the entire building was not included in the bid specifications, and it was improper for the committee to give Unirealty extra points for this unsolicited item. The proposed lease agreement calls for 9041 square feet of office space and a minimum of 66 parking spaces. Unirealty offered 72 parking spaces and Petitioner offered 75. The committee awarded more evaluation points to the Unirealty site based on future expansion capability of the building and the existing additional on-site parking spaces which were visible at the site at the time of inspection. The committee erroneously believed that the extra square footage of building space and extra parking spaces would necessarily be available to HRS if and when it might expand its offices. Future expansion was not in the bid specifications and it was clearly erroneous for them to have included this factor in their bid evaluation. The evaluation committee included the improper bid considerations in their evaluation of the Unirealty property. The two improper factors cannot be considered here. The unanimous recommendation of the evaluation committee was clearly to award the lease to the Intervenor. The evaluation committee based its decision on the scores attributed to each property on the Bid Synopsis sheet by the individual committee members. The committee utilized all the weighted bid criteria. However, two factors were of primary importance. One was its determination that the property offered by the Petitioners presented greater problems for design and flexibility due to the rectangular configuration of the building. The other consideration was that the physical characteristics of the Unirealty site and the surrounding area were considered far superior to the Petitioner's site. A close review of each evaluation sheet and the testimony of each committee member at the hearing shows that the improper factors were not so heavily weighted as to invalidate the committee recommendation. The reasons given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the Bid synopsis score sheets. The scoring was done by each member after inspection of the two buildings and without influence from the other committee members. In essence, the committee felt that Intervenor's property was the better property for the money. Importantly, every committee member came to the conclusion that Intervenor's property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a piece of property. On these facts, the individual scoring methods used by individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. Over an eight year period the Petitioner's rental cost was significantly lower than the Intervenor's. However, it is clear the legitimate considerations of the committee were crucial enough to override awarding the lease to the lowest bidder. The conclusion that the above factors can and do outweigh price and cost considerations in these facts is not an arbitrary and capricious decision, even though others may disagree with that decision. After the committee recommendation was scored and tabulated, Mr. Akridge requested the committee chair, Ms. Gail Newell, to prepare a draft letter of the proposed bid award. This was done in collaboration with the other committee members. Mr. Michael T. Akridge then prepared the bid award letter for the signature of the Administrative Services Director based on the draft letter. In it the two improper considerations were mentioned. The authority to award the lease to Unirealty was approved on March 8, 1989, by King W. Davis, Director of General Services for HRS based on the bid award letter, dated February 26, 1989.

Recommendation Based on the foregoing, the Hearing Officer recommends that the Secretary of the Department of Health and Rehabilitative Services enter a final order awarding lease number 590:2057 to Unirealty Services, Inc., as the lowest and best bidder. DONE and ENTERED this 21st day of July, 1989, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of July, 1989. APPENDIX Petitioner's Proposed Findings of Fact: The facts contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 12, 15, 23, 26, 27, 28, 30, 34, 38, 39 (in part), 40, 41, 42, 45, 46, 47, 48, 49, 50, 51, 53, 64, 65, 67, 69, 70, 71, 76, 77, 81, 83 (in part) are adopted in substance in so far as material. Paragraphs 14, 16, 17, 18, 21, 22, 24, 25, 29, 33, 36, 37, 73, 74, 80 are rejected as conclusions of law. Paragraphs 13, 19, 20, 44, 54, 59, 60, 61, 63, 68, 72, 75, 778, 82, are rejected as not supported by the evidence. Paragraphs 31, 32, 35, 43, 52, 55, 56, 57, 58, 62, 66 are rejected assubordinate or immaterial. Respondent's Proposed Findings of Fact: The facts contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17 are adopted in substance in so far as they are material. Intervenor's Proposed Findings of Fact: The facts contained in paragraphs 1-17 are adopted in substance in so far as they are material. COPIES FURNISHED: Edward D. Matthews, Jr. 2405 Hideaway Court Tallahassee, Florida 32303 Gregory L. Coler Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Jack Emory Farley, Esquire HRS District VI Legal Counsel 4000 West Buffalo Avenue, Room 500 Tampa, Florida 33614 Neal A. Sivyer, Esquire Paul J. Ullom, Esquire Shackleford, Farrior, Stallings and Evans, P. A. 501 East Kennedy Boulevard Suite 1400 Tampa, Florida 33601 Sam Power, Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Suite 407 Tallahassee, FL 32399-0700 John Miller, Esquire Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Suite 407 Tallahassee, FL 32399-0700

Florida Laws (4) 120.53120.57255.249255.25
# 3
PRO TECH DATA vs. OFFICE SYSTEMS CONSULTANTS, 85-001847BID (1985)
Division of Administrative Hearings, Florida Number: 85-001847BID Latest Update: Aug. 16, 1985

Findings Of Fact On April 1, 1985, Respondent, Florida Department of Law Enforcement (FDLE), gave notice to thirty vendors that it would receive competitive sealed bids on Bid Number 84-67 for the following commodities: eight computer binder cabinets 36x18 5/8x71 Putty/Black, three hundred single point binder hooks, six hundred 10" steel reinforced binder posts. The bids were to be filed in Tallahassee, Florida, no later than 11:00 a.m., April 16, 1985. The Invitation to Bid included General Conditions, Special Conditions and technical specifications describing the dimensions and capacities of the desired equipment. Of special significance was the technical specification that the single point binder hooks be "[c]apable of supporting up to 6 inches of llx14 7/8 20 lb. computer paper." Paragraph 6 of the General Conditions provides as follows: 6. MANUFACTURERS' NAMES AND APPROVED EQUIVALENTS: Any manufacturers' names, trade names, brand names, information and/or catalog numbers listed in a specification are for information and not intended to limit competition. The bidder may offer any brand for which he is an authorized representative, which meets or exceeds the specification for any items(s) [sic]. If bids are based on equivalent products, indicate on the bid form the manufacturer's name and number. Bidder shall submit with his bid, cuts, sketches and descriptive literature and or complete specifications. Reference to literature submitted with a previous bid will not satisfy this provision. The bidder shall also explain in detail the reason(s) why the proposed equivalent will meet the specifications and not be considered an exception thereto. The State of Florida reserves the right to determine acceptance of items(s) [sic] as an approved equivalent. Bids which do not comply with these requirements are subject to rejection. Bids lacking any written indication of intent to bid an alternate brand will be received and considered in complete compliance with the specifications as listed on the bid form. The purchaser is to be notified of any proposed changes in (a) materials used, (b) manufacturing process, or (c) construction. However, changes shall not be binding upon the State unless evidenced by a Change Notice issued and signed by the purchaser. (Emphasis added.) Paragraph 7 of the General Conditions imposed the following duty upon all bidders: 7. INTERPRETATIONS: Any questions concerning conditions and specifications shall be directed in writing to this office for receipt no later than ten (10) days prior to the bid opening. Inquiries must reference the date of bid opening. No interpretation shall be considered binding unless provided in writing by the State of Florida in response to requests in full compliance with this provision. Of the thirty vendors given an opportunity to submit bids, only two did so. They were Petitioner, Pro Tech Data (PTD or Petitioner), and Office Systems Consultants (OSC). Their bids were in the amounts of $4,645 and $5,244, respectively. After reviewing the bids, and consulting with both bidders, the director of the agency's Division of Criminal Justice Information Systems, Mark Scharein, determined that Petitioner's bid was nonresponsive for not meeting specifications and was accordingly rejected. The bid was then awarded to OSC, the second lowest bidder, on May 3, 1985. That precipitated the instant proceeding. In its bid response, PTD listed "Dennison Monarch #7830" as manufacturer and model number for the single point binder hooks. Petitioner also submitted a Dennison Monarch catalogue with its bid response. When FDLE examined the catalogue to ascertain the specifications of the hooks, it found no model number 7830. Indeed, the closest item matching this number was model number 7830-22 which referred to shelf supports, an item not solicited in the bid proposal. After consulting with PTD, it was determined that the use of model number 7830 was in error, and that Petitioner had intended to use model number 7802-30. Its request to amend the bid response was denied. Even if the bid proposal had contained the correct model number, the binder hooks in model number 7802-30 did not meet specifications. The product description of that model carries the following limitation: "Can accommodate a few sheets of paper or a stack of data 4" thick." In addition, at hearing PTD's representative conceded that the manufacturer did not recommend hanging six inches of paper from that model binder hook. This was inconsistent with FDLE's specific requirement that such hooks be "[c]apable of supporting up to 6 inches of . . . computer paper." OCS submitted product designations which conformed in all material respects to the specifications and conditions required by the bid proposal. Although PTD suggests that OCS's binder hooks do not support six inches of computer paper, .OCS's bid response reflects that they do, and there was no evidence to contradict this representation.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Bid No. 84-67 be awarded to Office Systems Consultants, and that Petitioner's bid protest be DENIED. DONE and ORDERED this 16th day of August, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this l6th day of August, 1985.

Florida Laws (2) 120.53120.57
# 4
G. H. JOHNSON CONSTRUCTION COMPANY vs PINELLAS COUNTY SCHOOL BOARD, 96-001942BID (1996)
Division of Administrative Hearings, Florida Filed:Largo, Florida Apr. 24, 1996 Number: 96-001942BID Latest Update: Aug. 15, 1996

Findings Of Fact During the month of March 1996, the Pinellas County School Board, pursuant to an advertised invitation for bids, (IFB), solicited bids for the construction of a new facility for John H. Sexton Elementary School (Sexton school). Each party submitting a bid was required to do so on a bid proposal form which was contained in the bid documents prepared by the project architect, Mr. Hoffman, and furnished to each prospective bidder who requested the bid package. One section of the bid proposal form related to "dewatering" potentially required at the construction site, and consistent with that potential two sentences were contained on the bid proposal form relating to dewatering of footings and of utilities, both of which provided for election by checking of an affirmative or a negative, and both of which had been pre-checked in the affirmative by the Board. It was the position of the Board that the pre- checked sentences as to dewatering on the bid proposal form constituted an acknowledgment by each bidder that that bidder's submittal included dewatering in the base bid. In addition to the check, the dewatering section also included blanks for the insertion by the bidder of figures representing lineal feet of header pipe and unit price per foot which figure would constitute a credit given by the bidder to the Board against the total bid price if dewatering were found not to be necessary, both as to footings and to utilities. Even further, the form also contained blanks to be filled in by the bidder for unit prices to be charged the Board in the event additional dewatering was required by virtue of the Board's later inclusion in the project of additional footings or utilities. Prior to the time for bid submittal, the Board conducted a meeting of all prospective bidders at which the project was explained and bidders given an opportunity to ask questions raised by the bid package. Johnson did not ask any questions regarding dewatering or that portion of the package relating thereto. Numerous bids were submitted in response to the proposal, including those from Johnson and Ellis. By stipulation at the hearing, the parties agreed that in all ways other than in that section of the bid proposal form for this project relating to dewatering, Johnson was and is a responsive and responsible bidder, as is Ellis. The bid proposals were opened by the Board at 2:00 PM on April 11, 1996 and the base bid prices on each proposal were read aloud to all in attendance by a Board representative. The project architect was present at the opening and tabulated and reviewed the bid proposals as opened. Johnson submitted the lowest base bid with a price of $7,965,000. The next lowest bid was that of Ellis, whose base bid price was $7,945,200. At the time of opening, no Board representative indicated anything was wrong with Johnson's bid Mr. Hoffman, the project architect, immediately noticed that Johnson had altered the Board's pre-checked bid proposal form by striking out the pre- checked "is" space regarding inclusion of dewatering in the base price of the two dewaterings, and making an X in each of the "is not" spaces. Mr. Hoffman considered that alteration by Johnson as a material alteration of the Board's solicitation which rendered Johnson's bid non-responsive. It must be noted that each change bears the initials, R. Y. Reza Yazdani is Johnson's president who initialed the changes and signed the bid proposal form for the company. In addition, Johnson also inserted a "0" in those spaces which dealt with amount of credit and cost of additional dewatering in the event additional work is required by the Board. In that regard, Hoffman opined that had Johnson not changed the check marks, but inserted the "0" figures as it did, the bid would have been responsive and Johnson would still have been lowest responsive bidder. The reason for this is that the bid form specifically notes that "the unit costs described in A & B above shall in no manner influence the School Board's selection of a firm to whom to award the Contract." The Board now recognizes that there is no part "B", as referenced in the proposal form. Since the "0's" would not influence the selection, use of an unmodified Board form, along with the lowest submitted base price would, in Hoffman's opinion, probably have meant that Johnson would have been awarded the contract. Johnson's representative, Mr. Mohme, who drafted the company proposal, specifically indicated he did not believe dewatering was a potential in this project. He recognized that such dewatering as was necessary was required by other provisions in the project specifications and he could not figure any way to recognize this and yet accurately reflect his belief that dewatering would not be necessary, other than to strike the pre-checked block and insert the check in the alternative block. He felt that by doing so, he was more accurately reflecting Johnson's bid. This reasoning is rather obscure. By letter dated April 12, 1996, written to the Board after the bids were opened, Mr. Mohme reiterated Johnson's position that dewatering is not necessary on this project, but further stated that if dewatering were to be necessary, Johnson would do so solely at its own risk and without any risk of additional cost to the Board. Bids may be clarified by a bidder, but such clarification must take place before the bids are opened. Bids may not be modified after bid opening. Before that letter was written, however, when the bids were opened and Mr. Hoffman observed what he considered was Johnson's alteration of the bid form, Hoffman consulted with a representative of the Board's purchasing department, Ms. Maas, who also reviewed Johnson's bid. Ms. Mass was of the opinion that Johnson may have attempted to qualify its bid, and she and Mr. Hoffman thereafter met with Mr. Rivas, the Board's director of facilities design and construction, to explain the problem. Mr. Rivas took the problem to two other Board personnel to see if there were some way Johnson's bid could be deemed responsive so that the Board could benefit by Johnson's low bid price. Within the context of those aforementioned discussions, Hoffman took the position that the alteration might leave the Board open to a possible change order and additional liability if dewatering were to be required and the Board had accepted Johnson's bid indicating that process was not included in the base price. Mr. Rivas, after consulting with the Board's attorney, also concluded that Johnson's alteration expressly excluded dewatering as an included factor and its exclusion constituted a serious and material deviation from the Board's solicitation. It was deemed material in that the deviation apparently gave Johnson a competitive advantage over other bidders who did not amend the form. This appears to be a valid conclusion and is adopted herein. The decision to recommend rejection of Johnson's bid and acceptance of Ellis's as the lowest responsive bid was ultimately reached by the Board's administrative staff. The Ellis bid was responsive to the solicitation whereas the determination was made that Johnson's was not responsive because of the alteration. It was not the actual act of alteration that caused that determination but rather the potential effect of the alteration. This was consistent with long standing Board policy not to accept a bid which does not conform to a bid solicitation and not to accept bids from bidders who alter the Board's bid proposal form or otherwise attempt to qualify their bids. It is the opinion of the Board personnel that such consistency in bidding procedure has resulted over time in more qualified bidders submitting bids for Board work which, in turn, has resulted in more competitive prices for the work let for bid. This is a reasonable policy. Mr. Gottschalk, Johnson's expert architect, who has designed schools for the Board, offered an alternative disposition to this dilemma. While admitting that Johnson's shifting of the risk of loss as a result of possible dewatering was a material matter, he suggested the Board could have disregarded the dewatering clause on every submittal and thereafter awarded the contract to Johnson, the lowest bidder, whose bid was responsive to the solicitation except for the dewatering provision. Recognizing this solution would have placed each bidder on an equal footing and allowed award to the lowest bidder at a substantial savings to the Board, he nonetheless also understood the decision made by Mr. Hoffman and the Board staff here and could not fault it. He agreed that reasonable men could differ on the issue of responsiveness here and how to deal with it. It is so found. After a review of the evidence submitted, including the testimony indicating the remoteness of the likelihood that extensive dewatering would be required, there appears to be no evidence that the Board, or its staff, acted dishonestly, fraudulently, illegally or arbitrarily in rejecting Johnson's bid on this project and recommending award to Ellis.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County School Board enter a final order denying and dismissing G. H. Johnson Construction Company's protest and awarding a contract for the construction of Sexton Elementary School to Ellis Construction Company, Inc. DONE and ENTERED this 8th day of May, 1996, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 96-1942BID To comply with the requirements of Section 120.59(2), Florida Statutes (1993), the following rulings are made on the parties' proposed findings of fact: Johnson's Proposed Findings of Fact. 1.-5. Accepted and incorporated herein. Accepted. Accepted but not a proper Finding of Fact. More a restatement of and comment on testimony. Rejected. Accepted but not a proper Findings of Fact. More a restatement of and comment on testimony. &11. Accepted. Accepted and incorporated herein. First sentence accepted as a literal statement of what appears in the specifications. Second and third sentences accepted but not probative of any material issue of fact. Accepted and incorporated herein. First sentence accepted. Balance not Finding of fact but argument. Ellis' Proposed Findings of Fact. 1.&2. Accepted and incorporated herein. 3.-6. Accepted. 7.-10. Accepted and incorporated herein. 11.-15. Accepted and incorporated herein. 16. Accepted but word "certain" is changed to read "likely." 17.-21. Accepted and incorporated herein. 22. Accepted and incorporated herein. 23.&24. Accepted. 25.&26. Accepted and incorporated herein. 27.-29. Accepted. Accepted and incorporated herein. Not relevant to any material issue of fact. COPIES FURNISHED: Jawdet I. Rubaii, Esquire Clearwater Executive Suites, No. 213 1345 South Missouri Avenue Clearwater, Florida 34616 John W. Bowen, Esquire Pinellas County School Board 301 4th Street S.W. Largo, Florida 34649-2942 E. A. Mills, Jr. Esquire Dale W. Vash, Esquire Fowler, White, Gillen, Boggs, Villareal and Banker, P.A. 501 East Kennedy Boulevard Post Office Box 1438 Tampa, Florida 33601 Pinellas County School Board 301 4th Avenue, S.W. Largo, Florida 34649-2942

Florida Laws (1) 120.57
# 5
INDUSTRIAL ENTERPRISES SANDBLAST AND PAINTING, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003592BID (1985)
Division of Administrative Hearings, Florida Number: 85-003592BID Latest Update: Dec. 11, 1985

Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547

Florida Laws (2) 120.57337.11
# 6
SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 7
ALL AMERICAN COMPANIES vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-002776BID (2002)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 12, 2002 Number: 02-002776BID Latest Update: Oct. 25, 2002

The Issue At issue in this proceeding is whether the Department of Environmental Protection's decision to reject all bids submitted for the project entitled BDRS 52-01/02 was illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact Parties Petitioner, All America Homes of Gainesville, Inc. (All America), is a corporation doing business in the State of Florida. All America submitted a timely written bid in response to the Department's ITB and filed timely protests to the Department's actions. The Respondent, the Department of Environmental Protection, is an agency of the State of Florida which manages and operates state parks under its jurisdiction, and solicits construction projects in state parks, pursuant to Chapter 258, Part I, Florida Statutes, through its Division of Recreation and Parks, Bureau of Design and Recreation Services. The ITB In November, 2001, the Department issued an ITB on a construction project entitled Hillsborough River State Park Concession Building, project number BDRS 52-01/02. The ITB included the Bid Specifications for the project. Bids were required to be submitted no later than 3:30 p.m. on Tuesday, December 18, 2001, at the Bureau's Tallahassee, Florida, office. The written Specifications define several terms, including, but not limited, to the following: ADDENDUM: A written explanation, interpretation, change, correction, addition, deletion, or modification, affecting the contract documents, including drawings and specifications issued by the OWNER [Department] and distributed to the prospective Bidders prior to the bid opening. ALTERNATE BID: Separate optional bid item for more or less project requirement used for tailoring project to available funding. Also may consist of alternate construction techniques. BASE BID: Formal bid exclusive of any alternate bids. BID FORM: The official form on which the OWNER requires formal bids to be prepared and submitted. ORAL STATEMENTS: Verbal instruction. NOTE: No oral statement of any person, whomever shall in any manner or degree modify or otherwise affect the provisions of the contract documents.[1] SEALED BID: The formal written offer of the Bidder for the proposed work when submitted on the prescribed bid form, properly signed and guaranteed. The Bid Specifications also contained the following relevant sections: Alternatives If the OWNER wishes to learn the relative or additional construction cost of an alternative method of construction, an alternative use of type of material or an increase or decrease in scope of the project, these items will be defined as alternates and will be specifically indicated and referenced to the drawings and specifications. Alternates will be listed in the bid form in such a manner that the Bidder shall be able to clearly indicate what sums he will add to (or deduct from) his Base Bid. The OWNER will judge for himself that such alternates are of comparable character and quality to the specified items. The Order of the alternate may be selected by the Department in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. ADDENDA If the Consultant[2] finds it would be expedient to supplement, modify or interpret any portion of the bidding documents during the bidding period, such procedure will be accomplished by the issuance of written Addenda to the bidding documents which will be delivered or mailed by the OWNER'S Contracts section to all bidders who have requested bidding documents. Interpretation No interpretation of the meaning of the drawings, specifications or other bidding documents and no correction of any apparent ambiguity, inconsistency or error therein will be made to any Bidder orally. Every request for such interpretation or correction should be in writing, addressed to the Consultant. All such interpretations and supplemental instructions will be in the form of written Addenda to the bidding documents. Only the interpretation or correction so given by the Consultant in writing and approved by the OWNER shall be binding, and prospective Bidders are advised that no other source is authorized to give information concerning, or to explain or interpret, the bidding documents. B-16 Bid Modification Bid modification will be accepted from Bidders, if addressed as indicated in Advertisement for Bids and if received prior to the opening of bids. No bid modification will be accepted after the close of bidding has been announced. Modifications will only be accepted if addressed in written or printed form submitted with the bid in sealed envelopes. Telegrams, facsimiles, separate sealed envelopes, written on printed modifications on the outside of the sealed envelopes will not be accepted. All bid modifications must be signed by an authorized representative of the Bidder. Modification will be read by the OWNER at the opening of formal bids. B-21 Rejection of Bids The OWNER reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the bid of a bidder who the OWNER determines is not in a position to perform the work. B-23 Award of Bid . . .The qualified Bidder submitting the lowest bid will be that Bidder who has submitted the lowest base bid plus any selected alternates. . . . The OWNER reserves the right to waive any minor irregularities in bids received when such waiver is in the interest of the OWNER. The Award of Bid will be issued by the OWNER only with responsible Bidders, found to meet all requirements for Award of Bid, qualified by experience and in a financial position to do the work specified. Each bidder shall, if so requested by the OWNER, present additional evidence of his experience, qualifications and ability to carry out the terms of the Agreement. (Emphasis in original, except for Section B-10.) The Bid Form is included with the Specifications and provides in part: Base Bid: Furnish labor, equipment, Lump Sum $ supervision and material to construct a new concession building of 2940 square feet located at the Hillsborough River State Park along with the alteration of the existing concession building according to plans and specifications. Alternate #1: Furnish labor, equipment, Add Amt.$__ supervision and material to renovate the existing concession building according to plans and specifications. There is a separate section for "Allowances," i.e., Section 01210, for the Hillsborough State Park. This section provides in part: SECTION 01210 – ALLOWANCES * * * 1.2 SUMMARY This Section includes administrative and procedural requirements governing allowances. Certain materials and equipment are specified in the Contract Documents and are defined by this [sic] specifications as material and labor to be provided against a pre-determined allowance. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. * * * 3.3 SCHEDULE OF ALLOWANCES A. Allowance #1: Include in the base bid an allowance for the purchase and installation of. . . kitchen equipment. . . . The total dollar amount of the allowance to be included shall be $12,000.00. There is also a separate section for "Alternates," i.e., section 01230, for Hillsborough River State Park, which provides in part: SECTION 01230 – ALTERNATES * * * 1.3 DEFINITIONS Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if OWNER decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. . . . . 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Renovate the existing concession building in its entirety as shown in the drawings and specified herein. (emphasis added.) At this stage of the bidding documents, the contractor/bidder is requested to provide a Base Bid/Lump Sum on the Bid Form to "[f]urnish labor, equipment,. . .to construct a new concession building," and to provide an additional and separate amount for Alternate No. 1 to "[f]urnish labor, equipment, . . . to renovate the existing concession building." On December 13, 2001, the Bureau issued "Addendum No. One (1)" (written by the architect) to the ITB on the "Hillsborough River State Park – Concession Building." The Addendum contained the following relevant sections: Specification Section 01210: Allowances Add the following new paragraph 3.3.B: ”Allowance #2: Include in the base bid an allowance for the renovations of the existing concession building; renovations shall be defined by the Owner. The total dollar amount of the allowance to be included shall be $25,000." Specification Section 01230: Alternates Modify paragraph 3.1.A. as follows: "Alternate No. 1: Renovate the existing concession building as defined by the Owner, and as provided for under Section 01210, Allowances." (emphasis added.) Each contractor was required to sign the Addendum and attach it to the bid. By definition, and pertinent here, an addendum is an additional written instruction to a contractor during the bidding process. Based on the weight of the evidence, the purpose of this Addendum was to require the contractor to include a $25,000.00 Allowance (for Allowance # 2) in the Base Bid, for the work which might be performed if the Department requested the work to be performed for Alternate No. 1, i.e., for the renovation of the existing concession building.3 (The Department's architect decided it would cost approximately $25,000.00 to renovate the existing concession building, hence Allowance # 2.) In other words, the Addendum does not have a specific dollar amount to be included for Alternate No. 1. Rather, the $25,000.00 is an Allowance for the work described as Alternate No. 1, but the amount is to be included in the Base Bid and not as a separate line item, dollar amount. But, importantly, the Addendum did not delete the potential work to be performed as described in Alternate No. 1, although Mr. Bowman and others believed that the Addendum deleted Alternate No. 1. It deleted the necessity to place a specific dollar amount on the Bid Form for Alternate No. 1. (Mr. Bowman is a registered Professional Engineer and a licensed contractor. He has worked for the Department for 15 years and has served as Bureau Chief for two years. He supervises the contract section and the design section, which was responsible for preparing the technical plans and specifications and bidding out the job.) Mr. Bowman offered the following explanation why he believed the Addendum was confusing: Okay. I think the confusion that was created, you know, I think the addendum in itself, you know, said add $25,000 to the base bid, but then on the bid form, it still had the space down there for alternate number one, which alternate number one, which alternate number one had become $25,000 that was to be allowed for the concession building, and I think that's where the confusion came in because I think they were still confused, that they weren't really sure that they should not put that 25 down there but they knew they had been told in the addendum to do it and I think that's the reason for the notes and we got to the correspondence on the bid form, was they wanted to make sure that that's what we were wanting to do. And I think that's where the confusion came in. Like I said, it's always, if you could go back and do it again, it would be much wiser just to issue a whole new bid form and then we wouldn't be here today. But, we didn't do that. Okay. So, that's why we are here. The language in this Addendum, when read with the original Bid Specifications, apparently caused confusion with some of the bidders on the project. Several bidders called Marvin Allen (an architect and project manager for the Department's Bureau of Design and Recreation Services) prior to the submission of the bids, to clarify how the $25,000.00 Allowance should be shown on the Bid Form. (Mr. Allen did not author any of the specifications, including the Addendum.) He was listed as a contact person. He did not contact any bidders. But, Mr. Allen recalled telling each bidder who asked that the Allowance of $25,000.00 should be included in the Base Bid. But, he does not recall the names or numbers of the bidders who called, "possibly" three, four or five. Mr. Allen believed the Addendum was clear. According to Mr. Allen, the bidders who called him found the Addendum confusing. The oral responses to the bidders can be construed as interpretations of the Addendum. However, pursuant to Section B- 10 of the Specifications, any such interpretations were required to "be in the form of written Addenda to the bidding documents." Also, any such questions should have been in writing. If Section B-10 were complied with, all bidders would have been potentially on the same footing, or, at the very least, would have had access to a written clarifying document. Opening of the Bids On December 18, 2001, the bids were opened by Mike Renard, Contracts Manager with the Bureau of Design and Recreation Services, and Susan Maynard, Administrative Assistant. Mr. Dwight Fitzpatrick, a representative of All America, also attended the bid opening. The Bid Form submitted by Nelco showed a Base Bid of $355,478.00 (Lump Sum $355,478.00), and also showed an amount of $25,000.00 on the Alternate # 1 line (Add Amt. $25,000.00). See Finding of Fact 6. (It was clear to Mr. Renard that the $25,000.00 should have been included on Nelco's Base Bid. But Mr. Renard believed that Nelco submitted a responsive bid because the Department only accepted the Base Bid. Mr. Bowman agreed.) Nelco was the only one of five bidders to have a dollar amount in the Alternate #1 line under "Add Amt. $ ." All America submitted the second lowest Base Bid of $362,000.00. There was also a hand-written note on the All- America Bid Form that stated: "Addenda # 1 instruction to place $25,000 allowance in both Base Bid and as alternate # 1." Another hand written note was located below the "Add Amt. $-0-" line: "amount added in Base Bid with $25,000 allowance per Marvin Allen." The Department considered All America's bid responsive. It is a fair inference that three out of five of the other Bid Forms contained language indicating that the bidders were relying on Addendum No. One by placing the $25,000.00 Allowance in the Base Bid.4 It is uncertain whether they did so in light of the instructions of Mr. Allen concerning how to complete the Bids Forms. However, given the nature of the calls to Mr. Allen, there is a reasonable inference that there was some confusion among some of the bidders. The Department determined that Nelco submitted the lowest Base Bid, but the Department's staff had a question as to whether Nelco had included the $25,000.00 in its Base Bid. After conferring with his superiors, Mr. Renard was instructed to call Nelco to make certain that its Base Bid included the Allowance amount ($25,000.00). Mr. Renard spoke with Steve Cleveland, Nelco's Project Manager, "to verify the fact that [Nelco] had the allowance in their base bid." Mr. Cleveland orally confirmed that Nelco's Base Bid included the $25,000.00 Allowance. Mr. Renard asked Mr. Cleveland to send him a letter verifying this statement. Mr. Renard viewed this inquiry as a request for clarification or verification, not an opportunity for Nelco to modify its bid. Mr. Bowman agreed. (Mr. Renard did not believe Addendum No. 1 was confusing.) In a letter dated December 20, 2001, Mr. Cleveland confirmed that Nelco’s Base Bid of $355,478.00 included the Allowance amount and that Nelco could still perform the contract if the $25,000 Allowance was removed from its Base Bid pursuant to the ITB, i.e., that Nelco would perform the contract for $355,478.00 less $25,000.00, or $330,478.00, if the Department did not accept Alternate # 1 and the Allowance. (An alternate does not have to be accepted by the Department.) According to Mr. Renard, Mr. Cleveland never mentioned modifying, changing, or altering Nelco's bid. The Department only accepted the Base Bid for each bid. Mr. Renard did not consider it unusual to call a bidder or contractor to verify information to determine whether they can or cannot perform the work at the stipulated price. He considered it common to make this inquiry. Also, it was common in Mr. Bowman's experience to call a bidder to get clarification. Mr. Renard was not aware of any statute or rule which authorizes the Department to request clarification from a bidder after the bids are opened. Mr. Renard was more familiar with the bid forms than Mr. Allen. After receiving Mr. Cleveland's letter, the Department determined that Nelco submitted the lowest Base Bid and that the $25,000.00 amount that Nelco wrote on the Bid Form Alternate # 1 line, was a minor irregularity in the bid which the Department, as the Owner, could waive pursuant to the ITB. On December 20, 2001, the Department posted the Tabulation of Bids showing the anticipated award of the contract to Nelco. At the hearing, an unsigned letter on Department letterhead was introduced, which was addressed to Nelco and stated that Nelco submitted the apparent low bid. However, Mr. Renard testified that these letters are prepared routinely, but not mailed out without his signature. Mr. Renard did not recall signing the letter or ever sending out such a letter to Nelco. On December 21, 2001, the Department received a Notice of Intent to Protest letter from Allen E. Stine, the President of All America. In his letter, Mr. Stine stated that Nelco’s bid should have been rejected for failure to follow the specified format as per Addendum No. 1, or adjusted to have the $25,000.00 amount added to their Base Bid. Bid Protests All America filed a written formal bid protest on January 4, 2001. On January 9, 2001, Cindy Otero of All America, notified Mr. Renard by letter, and stated that Mr. Stine was available for a hearing regarding the bid protest. On January 28, 2002, Mr. Renard returned All America's check for the bond, stating that it was unnecessary. Mr. Stine recounted a number of unanswered telephone calls after the first protest was filed. During one conversation, Mr. Renard recalled Mr. Stine saying to him, "You can't do this, you can't do this." After receiving the first formal protest, the Department staff consulted with legal staff and reviewed the documents and bid procedures. Based on the number of questions received concerning the Addendum and the hand-written notes on several of the bid forms, Mr. Bowman, Bureau Chief, determined that the bid documents were confusing and ambiguous. (Mr. Bowman stated that this was their first bid protest in his 15 years with the Department.) Therefore, Mr. Bowman decided that it would in the best interest of the State of Florida to reject all of the bids pursuant to the Bid Specifications. Mr. Bowman felt that the ITB should be re-written in order to make it clearer and allowing all of the bidders to re-bid the project without any confusion or ambiguity. Mr. Stine stated that his "senior estimator" told him that the bid language "could be confusing." He and his "senior estimator" had a discussion about whether the Allowance should have been placed in the Base Bid or not. At the time of submission of All America's bid, Mr. Stine was clear that the Allowance should be placed in the Base Bid, especially after calling Mr. Allen. But, his senior estimator was not so clear. In order to appease him, Mr. Stine placed the hand-written note on All America’s proposal. Mr. Stine essentially, "cleaned" up his proposal. At the hearing, Mr. Bowman testified Rule 60D-5.0071, Florida Administrative Code, see Conclusion of Law 59, does not list "confusing or ambiguous bid specifications" as one of the circumstances allowing for the rejection of all bids. However, Mr. Bowman later stated during the hearing that he believed the circumstances listed in Rule 60D-5.0071 were not the only circumstances authorizing the Department to reject all bids. Mr. Bowman testified that he believed that general confusion among the bidders caused by the ambiguous ITB constituted sufficient grounds for rejecting all bids. Mr. Bowman was advised by legal counsel that rejecting all of the bids would probably result in another bid protest by Nelco, All America, or both. Thus, the Department decided to delay addressing All American’s first protest until after posting the rejection of all bids and receiving the subsequent protests, so that all of the protests could be resolved at once in an efficient and economical manner. Notwithstanding the Department's justifications for rejecting all bids and not proceeding on All America's initial protest, the record is unclear why the Department waited several months to reject all bids. On May 13, 2002, the Department posted the rejection of all bids. On May 16, 2002, the Department received a formal written protest of the rejection of all bids filed by All America. On May 17, 2002, Jerome I. Johnson, attorney for the Department, contacted Mr. Robert A. Lash, All America's counsel at the time, concerning the resolution of All America’s formal protest. (Before the final hearing, Mr. Lash, with All America's consent, withdrew as counsel for All America.) The parties agreed to suspend formal bid protest procedures until a meeting could be held between the parties in an attempt to resolve the protests. Mr. Johnson sent a letter dated May 21, 2002, to Mr. Lash confirming this conversation. On June 26, 2002, a meeting was held among the Department staff, legal staff, and Mr. Lash and Mr. Stine, representing All America. The parties were unable to resolve the protests. At the conclusion of the meeting, the parties agreed that formal protest procedures would not be implemented until Mr. Stine could confer further with his counsel. In a letter dated July 5, 2002, Mr. Lash stated that his client wished to proceed with formal protest procedures and requested an administrative hearing on the protests. Are the Specifications and Bid Documents Ambiguous and Was There Confusion? The parties stipulated that "[t]he Addendum language was confusing," notwithstanding the testimony of several witnesses that they were not confused. The Department's determination that the bid Specifications, including the Addendum, and the Bid Form, which remained unchanged after the Addendum was issued, were confusing and ambiguous, is supported by the weight of the evidence. This is particularly true regarding the Bid Form. The Addendum required the bidder to include an Allowance of $25,000.00 in the Base Bid for work described as Alternate # 1. But the Bid Form was unchanged to reflect the Addendum changes. The Bid Form retained a line for the bidder to submit an additional amount for Alternate # 1. Further, it appears that several bidders were confused, including, Mr. Stine, who spoke with Mr. Allen and requested and received clarification. Further, it is unclear whether all of the bidders, including Nelco, were aware of the oral interpretations or clarifications of the Addendum rendered to some of the bidders. Rejection of All Bids Based upon the foregoing, given the standard of review in this proceeding discussed in the Conclusions of Law, the weight of the evidence indicates that the Department's action, in rejecting all bids, was not illegal, arbitrary, dishonest, or fraudulent. The Department's staff was well-intended and made some mistakes along the way, e.g., by not changing the Bid Form, which they readily admit. But there was a rationale for rejecting all bids under the circumstances.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department issue a final order dismissing All America’s Petition to Prevent Rejection of Bids and Award Contract to Petitioner and denying All America's request for attorney’s fees and costs. DONE AND ENTERED this 24th day of September 2002, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September 2002.

Florida Laws (3) 120.569120.57120.595
# 8
DAVID NIXON, INC. vs DEPARTMENT OF CORRECTIONS, 90-006278BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 05, 1990 Number: 90-006278BID Latest Update: Jan. 15, 1991

The Issue The Department of Corrections sought bids for construction of a health services building for a correctional facility. A discrepancy existed between the written specifications and the architectural drawings for the project. An addendum was issued to clarify the matter. The low bidder (Intervenor) did not acknowledge receipt of the addendum until several hours after the opening of bids. The Department accepted the Intervenor's bid. The Petitioner timely protested the action. The issue in this case is whether, in accepting the Intervenor's bid, the Department acted contrary to the requirements of law.

Findings Of Fact On July 31, 1990, the Department of Corrections (hereinafter "Department") issued an Invitation To Bid ("ITB") for PR-35-JRA, Project #90015, consisting of the construction of a Health Classification Building at the Columbia County Correctional Institution. In relevant part, the ITB requested price proposals for said construction, provided that the bid would be awarded to the responsive bidder submitting the lowest cost proposal, provided that "in the interest" of the Department, "any informality" in bids could be waived, and provided space on the bid form for acknowledgment of receipt of all addenda to the ITB. Bids were to be filed no later than 2:00 p.m. on September 11, 1990, the time scheduled for bid opening. Documents issued with the ITB included architectural drawings and written specifications for the building. The architectural firm of Jim Roberson and Associates, (hereinafter "JRA") had been employed by the Department to prepare the drawings and specifications. JRA was responsible for preparation and distribution of related addenda. Further, a JRA representative presided over the opening of bids on behalf of the Department. Following release of the ITB and supporting documents, JRA became aware of a conflict between sink faucets required by the drawings and those required by the written specifications. The specifications provided that sink faucets operated by hand levers or foot pedals were to be installed in the facility. The architectural drawings JRA indicated that sink faucets were to operate by means of "electric-eye" activators, rather than by hand levers or foot pedals. On September 10, 1990, JRA issued an addendum (identified as Addendum #2) 1/ to clarify that "electric-eye" type operators were to be included in the bids. The addendum was sent by telephone facsimile machine to all anticipated bidders. In part the addendum provides as follows: "This Addendum forms a part of the Contract Documents and modifies the original Specifications and Drawings, dated 31 July 1990, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to Disqualification." On September 11, 1990, the eight bids submitted in response to the ITB were opened by the JRA representative. The Intervenor, Custom Construction (hereinafter "Custom"), submitted the lowest bid at $898,898. The Petitioner, David Nixon (hereinafter "Nixon"), submitted the next lowest bid at $900,000. The bid form provided by the Department as part of the ITB materials to prospective bidders provided space for acknowledgment of addenda to the ITB documents. Upon opening the bid submitted by Custom, the JRA representative officiating at the opening noted that the Custom bid failed to acknowledge Addendum #2 in the appropriate space on the bid form. 2/ Robert L. Harris, president of Custom Construction, attended the bid opening. When the JRA representative noted the lack of acknowledgment of Addendum #2, Mr. Harris stated that he was unaware of the addendum. At hearing, Mr. Harris testified that his secretary told him that Addendum #2 was not received by his office. The JRA representative testified that his review of JRA's FAX transmission records indicated that the FAXed Addendum #2 was received by all bidders. The greater weight of the evidence establishes that Addendum #2 was transmitted to and received by, all bidders. Upon leaving the bid opening, Mr. Harris immediately contacted his plumbing subcontractor, Jerry Stratyon, and discussed the situation. Approximately two hours after the bid opening, and after talking with Mr. Stratton, Mr. Harris notified JRA, in a letter transmitted by FAX machine to JRA, that his bid price did include plumbing fixtures required by Addendum #2. Mr. Harris concluded the letter, "[w]hen can we start work. I know you don't want the alternate." On October 8, 1990, JRA recommended to the Department, that the Custom bid be accepted. The letter of recommendation, in part, provides: The apparent low bidder however, did not verify receipt of Addendum No. 2 on the Bid Proposal. Our office did receive a, facsimile after the bid verifying Addendum NO. 2 receipt from the Contractor's Office." However, the actual letter from Custom to JRA states, not that Addendum #2 was received, but that it was included in the price bid by Custom's plumbing subcontractor. Both Nixon and Custom obtained plumbing bids from the same subcontractor, Jerry Stratton. The cost increase attendant to the requirements of Addendum #2 is approximately $2,400 over the plumbing fixtures indicated in the written project specifications. Mr. Stratton was aware of Addendum #2 and testified that the requirements of Addendum #2 were reflected in his price quotes to both bidders. Mr. Stratton provided the same price bid to Nixon and Custom. Mr. Stratton also provided bids to Nixon and Custom for HVAC work. Mr. Stratton was accepted as Custom's HVAC subcontractor. Nixon's bid indicates that another HVAC subcontractor will perform the cork should Nixon receive the contract. The ITB provided that bid modification or withdrawal was permitted on written or telegraphic request received from a bidder prior to the time fixed for opening. Mr. Harris did not attempt to either withdraw or modify Custom's bid prior to bid opening. No bid modification was permitted subsequent to the bid opening. The Department's policy is to waive minor irregularities when to do so would be in the best interests of the State and would not be unfair to other bidders. The evidence does not establish that Custom Construction's failure to acknowledge the addendum was purposefully designed to permit withdrawal of their bid subsequent to the public bid opening. The omission of acknowledgment of Addendum #2 provided Custom an opportunity to withdraw the bid that was not available to other bidders. Custom could have informed the Department that the bid price did not include the requirements of Addendum #2, and the bid could have been withdrawn. Custom was therefore provided with a substantial advantage or benefit not enjoyed by the other bidders. The other bidders, all of whom acknowledged receipt of Addendum #2, had no opportunity to, and would not have been permitted to, withdraw their aids. The fact that Custom did not withdraw the bid is irrelevant.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a Final Order rejecting the bid submitted by Intervenor as nonresponsive and awarding the contract to the Petitioner. DONE and RECOMMENDED this 15th day of January, 1991, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 1991.

Florida Laws (4) 120.53120.57120.68255.29
# 9
ALL AMERICAN COMPANIES vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-002777BID (2002)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 12, 2002 Number: 02-002777BID Latest Update: Oct. 25, 2002

The Issue At issue in this proceeding is whether the Department of Environmental Protection's decision to reject all bids submitted for the project entitled BDRS 52-01/02 was illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact Parties Petitioner, All America Homes of Gainesville, Inc. (All America), is a corporation doing business in the State of Florida. All America submitted a timely written bid in response to the Department's ITB and filed timely protests to the Department's actions. The Respondent, the Department of Environmental Protection, is an agency of the State of Florida which manages and operates state parks under its jurisdiction, and solicits construction projects in state parks, pursuant to Chapter 258, Part I, Florida Statutes, through its Division of Recreation and Parks, Bureau of Design and Recreation Services. The ITB In November, 2001, the Department issued an ITB on a construction project entitled Hillsborough River State Park Concession Building, project number BDRS 52-01/02. The ITB included the Bid Specifications for the project. Bids were required to be submitted no later than 3:30 p.m. on Tuesday, December 18, 2001, at the Bureau's Tallahassee, Florida, office. The written Specifications define several terms, including, but not limited, to the following: ADDENDUM: A written explanation, interpretation, change, correction, addition, deletion, or modification, affecting the contract documents, including drawings and specifications issued by the OWNER [Department] and distributed to the prospective Bidders prior to the bid opening. ALTERNATE BID: Separate optional bid item for more or less project requirement used for tailoring project to available funding. Also may consist of alternate construction techniques. BASE BID: Formal bid exclusive of any alternate bids. BID FORM: The official form on which the OWNER requires formal bids to be prepared and submitted. ORAL STATEMENTS: Verbal instruction. NOTE: No oral statement of any person, whomever shall in any manner or degree modify or otherwise affect the provisions of the contract documents.[1] SEALED BID: The formal written offer of the Bidder for the proposed work when submitted on the prescribed bid form, properly signed and guaranteed. The Bid Specifications also contained the following relevant sections: Alternatives If the OWNER wishes to learn the relative or additional construction cost of an alternative method of construction, an alternative use of type of material or an increase or decrease in scope of the project, these items will be defined as alternates and will be specifically indicated and referenced to the drawings and specifications. Alternates will be listed in the bid form in such a manner that the Bidder shall be able to clearly indicate what sums he will add to (or deduct from) his Base Bid. The OWNER will judge for himself that such alternates are of comparable character and quality to the specified items. The Order of the alternate may be selected by the Department in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. ADDENDA If the Consultant[2] finds it would be expedient to supplement, modify or interpret any portion of the bidding documents during the bidding period, such procedure will be accomplished by the issuance of written Addenda to the bidding documents which will be delivered or mailed by the OWNER'S Contracts section to all bidders who have requested bidding documents. Interpretation No interpretation of the meaning of the drawings, specifications or other bidding documents and no correction of any apparent ambiguity, inconsistency or error therein will be made to any Bidder orally. Every request for such interpretation or correction should be in writing, addressed to the Consultant. All such interpretations and supplemental instructions will be in the form of written Addenda to the bidding documents. Only the interpretation or correction so given by the Consultant in writing and approved by the OWNER shall be binding, and prospective Bidders are advised that no other source is authorized to give information concerning, or to explain or interpret, the bidding documents. B-16 Bid Modification Bid modification will be accepted from Bidders, if addressed as indicated in Advertisement for Bids and if received prior to the opening of bids. No bid modification will be accepted after the close of bidding has been announced. Modifications will only be accepted if addressed in written or printed form submitted with the bid in sealed envelopes. Telegrams, facsimiles, separate sealed envelopes, written on printed modifications on the outside of the sealed envelopes will not be accepted. All bid modifications must be signed by an authorized representative of the Bidder. Modification will be read by the OWNER at the opening of formal bids. B-21 Rejection of Bids The OWNER reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the bid of a bidder who the OWNER determines is not in a position to perform the work. B-23 Award of Bid . . .The qualified Bidder submitting the lowest bid will be that Bidder who has submitted the lowest base bid plus any selected alternates. . . . The OWNER reserves the right to waive any minor irregularities in bids received when such waiver is in the interest of the OWNER. The Award of Bid will be issued by the OWNER only with responsible Bidders, found to meet all requirements for Award of Bid, qualified by experience and in a financial position to do the work specified. Each bidder shall, if so requested by the OWNER, present additional evidence of his experience, qualifications and ability to carry out the terms of the Agreement. (Emphasis in original, except for Section B-10.) The Bid Form is included with the Specifications and provides in part: Base Bid: Furnish labor, equipment, Lump Sum $ supervision and material to construct a new concession building of 2940 square feet located at the Hillsborough River State Park along with the alteration of the existing concession building according to plans and specifications. Alternate #1: Furnish labor, equipment, Add Amt.$__ supervision and material to renovate the existing concession building according to plans and specifications. There is a separate section for "Allowances," i.e., Section 01210, for the Hillsborough State Park. This section provides in part: SECTION 01210 – ALLOWANCES * * * 1.2 SUMMARY This Section includes administrative and procedural requirements governing allowances. Certain materials and equipment are specified in the Contract Documents and are defined by this [sic] specifications as material and labor to be provided against a pre-determined allowance. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. * * * 3.3 SCHEDULE OF ALLOWANCES A. Allowance #1: Include in the base bid an allowance for the purchase and installation of. . . kitchen equipment. . . . The total dollar amount of the allowance to be included shall be $12,000.00. There is also a separate section for "Alternates," i.e., section 01230, for Hillsborough River State Park, which provides in part: SECTION 01230 – ALTERNATES * * * 1.3 DEFINITIONS Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if OWNER decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. . . . . 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Renovate the existing concession building in its entirety as shown in the drawings and specified herein. (emphasis added.) At this stage of the bidding documents, the contractor/bidder is requested to provide a Base Bid/Lump Sum on the Bid Form to "[f]urnish labor, equipment,. . .to construct a new concession building," and to provide an additional and separate amount for Alternate No. 1 to "[f]urnish labor, equipment, . . . to renovate the existing concession building." On December 13, 2001, the Bureau issued "Addendum No. One (1)" (written by the architect) to the ITB on the "Hillsborough River State Park – Concession Building." The Addendum contained the following relevant sections: Specification Section 01210: Allowances Add the following new paragraph 3.3.B: ”Allowance #2: Include in the base bid an allowance for the renovations of the existing concession building; renovations shall be defined by the Owner. The total dollar amount of the allowance to be included shall be $25,000." Specification Section 01230: Alternates Modify paragraph 3.1.A. as follows: "Alternate No. 1: Renovate the existing concession building as defined by the Owner, and as provided for under Section 01210, Allowances." (emphasis added.) Each contractor was required to sign the Addendum and attach it to the bid. By definition, and pertinent here, an addendum is an additional written instruction to a contractor during the bidding process. Based on the weight of the evidence, the purpose of this Addendum was to require the contractor to include a $25,000.00 Allowance (for Allowance # 2) in the Base Bid, for the work which might be performed if the Department requested the work to be performed for Alternate No. 1, i.e., for the renovation of the existing concession building.3 (The Department's architect decided it would cost approximately $25,000.00 to renovate the existing concession building, hence Allowance # 2.) In other words, the Addendum does not have a specific dollar amount to be included for Alternate No. 1. Rather, the $25,000.00 is an Allowance for the work described as Alternate No. 1, but the amount is to be included in the Base Bid and not as a separate line item, dollar amount. But, importantly, the Addendum did not delete the potential work to be performed as described in Alternate No. 1, although Mr. Bowman and others believed that the Addendum deleted Alternate No. 1. It deleted the necessity to place a specific dollar amount on the Bid Form for Alternate No. 1. (Mr. Bowman is a registered Professional Engineer and a licensed contractor. He has worked for the Department for 15 years and has served as Bureau Chief for two years. He supervises the contract section and the design section, which was responsible for preparing the technical plans and specifications and bidding out the job.) Mr. Bowman offered the following explanation why he believed the Addendum was confusing: Okay. I think the confusion that was created, you know, I think the addendum in itself, you know, said add $25,000 to the base bid, but then on the bid form, it still had the space down there for alternate number one, which alternate number one, which alternate number one had become $25,000 that was to be allowed for the concession building, and I think that's where the confusion came in because I think they were still confused, that they weren't really sure that they should not put that 25 down there but they knew they had been told in the addendum to do it and I think that's the reason for the notes and we got to the correspondence on the bid form, was they wanted to make sure that that's what we were wanting to do. And I think that's where the confusion came in. Like I said, it's always, if you could go back and do it again, it would be much wiser just to issue a whole new bid form and then we wouldn't be here today. But, we didn't do that. Okay. So, that's why we are here. The language in this Addendum, when read with the original Bid Specifications, apparently caused confusion with some of the bidders on the project. Several bidders called Marvin Allen (an architect and project manager for the Department's Bureau of Design and Recreation Services) prior to the submission of the bids, to clarify how the $25,000.00 Allowance should be shown on the Bid Form. (Mr. Allen did not author any of the specifications, including the Addendum.) He was listed as a contact person. He did not contact any bidders. But, Mr. Allen recalled telling each bidder who asked that the Allowance of $25,000.00 should be included in the Base Bid. But, he does not recall the names or numbers of the bidders who called, "possibly" three, four or five. Mr. Allen believed the Addendum was clear. According to Mr. Allen, the bidders who called him found the Addendum confusing. The oral responses to the bidders can be construed as interpretations of the Addendum. However, pursuant to Section B- 10 of the Specifications, any such interpretations were required to "be in the form of written Addenda to the bidding documents." Also, any such questions should have been in writing. If Section B-10 were complied with, all bidders would have been potentially on the same footing, or, at the very least, would have had access to a written clarifying document. Opening of the Bids On December 18, 2001, the bids were opened by Mike Renard, Contracts Manager with the Bureau of Design and Recreation Services, and Susan Maynard, Administrative Assistant. Mr. Dwight Fitzpatrick, a representative of All America, also attended the bid opening. The Bid Form submitted by Nelco showed a Base Bid of $355,478.00 (Lump Sum $355,478.00), and also showed an amount of $25,000.00 on the Alternate # 1 line (Add Amt. $25,000.00). See Finding of Fact 6. (It was clear to Mr. Renard that the $25,000.00 should have been included on Nelco's Base Bid. But Mr. Renard believed that Nelco submitted a responsive bid because the Department only accepted the Base Bid. Mr. Bowman agreed.) Nelco was the only one of five bidders to have a dollar amount in the Alternate #1 line under "Add Amt. $ ." All America submitted the second lowest Base Bid of $362,000.00. There was also a hand-written note on the All- America Bid Form that stated: "Addenda # 1 instruction to place $25,000 allowance in both Base Bid and as alternate # 1." Another hand written note was located below the "Add Amt. $-0-" line: "amount added in Base Bid with $25,000 allowance per Marvin Allen." The Department considered All America's bid responsive. It is a fair inference that three out of five of the other Bid Forms contained language indicating that the bidders were relying on Addendum No. One by placing the $25,000.00 Allowance in the Base Bid.4 It is uncertain whether they did so in light of the instructions of Mr. Allen concerning how to complete the Bids Forms. However, given the nature of the calls to Mr. Allen, there is a reasonable inference that there was some confusion among some of the bidders. The Department determined that Nelco submitted the lowest Base Bid, but the Department's staff had a question as to whether Nelco had included the $25,000.00 in its Base Bid. After conferring with his superiors, Mr. Renard was instructed to call Nelco to make certain that its Base Bid included the Allowance amount ($25,000.00). Mr. Renard spoke with Steve Cleveland, Nelco's Project Manager, "to verify the fact that [Nelco] had the allowance in their base bid." Mr. Cleveland orally confirmed that Nelco's Base Bid included the $25,000.00 Allowance. Mr. Renard asked Mr. Cleveland to send him a letter verifying this statement. Mr. Renard viewed this inquiry as a request for clarification or verification, not an opportunity for Nelco to modify its bid. Mr. Bowman agreed. (Mr. Renard did not believe Addendum No. 1 was confusing.) In a letter dated December 20, 2001, Mr. Cleveland confirmed that Nelco’s Base Bid of $355,478.00 included the Allowance amount and that Nelco could still perform the contract if the $25,000 Allowance was removed from its Base Bid pursuant to the ITB, i.e., that Nelco would perform the contract for $355,478.00 less $25,000.00, or $330,478.00, if the Department did not accept Alternate # 1 and the Allowance. (An alternate does not have to be accepted by the Department.) According to Mr. Renard, Mr. Cleveland never mentioned modifying, changing, or altering Nelco's bid. The Department only accepted the Base Bid for each bid. Mr. Renard did not consider it unusual to call a bidder or contractor to verify information to determine whether they can or cannot perform the work at the stipulated price. He considered it common to make this inquiry. Also, it was common in Mr. Bowman's experience to call a bidder to get clarification. Mr. Renard was not aware of any statute or rule which authorizes the Department to request clarification from a bidder after the bids are opened. Mr. Renard was more familiar with the bid forms than Mr. Allen. After receiving Mr. Cleveland's letter, the Department determined that Nelco submitted the lowest Base Bid and that the $25,000.00 amount that Nelco wrote on the Bid Form Alternate # 1 line, was a minor irregularity in the bid which the Department, as the Owner, could waive pursuant to the ITB. On December 20, 2001, the Department posted the Tabulation of Bids showing the anticipated award of the contract to Nelco. At the hearing, an unsigned letter on Department letterhead was introduced, which was addressed to Nelco and stated that Nelco submitted the apparent low bid. However, Mr. Renard testified that these letters are prepared routinely, but not mailed out without his signature. Mr. Renard did not recall signing the letter or ever sending out such a letter to Nelco. On December 21, 2001, the Department received a Notice of Intent to Protest letter from Allen E. Stine, the President of All America. In his letter, Mr. Stine stated that Nelco’s bid should have been rejected for failure to follow the specified format as per Addendum No. 1, or adjusted to have the $25,000.00 amount added to their Base Bid. Bid Protests All America filed a written formal bid protest on January 4, 2001. On January 9, 2001, Cindy Otero of All America, notified Mr. Renard by letter, and stated that Mr. Stine was available for a hearing regarding the bid protest. On January 28, 2002, Mr. Renard returned All America's check for the bond, stating that it was unnecessary. Mr. Stine recounted a number of unanswered telephone calls after the first protest was filed. During one conversation, Mr. Renard recalled Mr. Stine saying to him, "You can't do this, you can't do this." After receiving the first formal protest, the Department staff consulted with legal staff and reviewed the documents and bid procedures. Based on the number of questions received concerning the Addendum and the hand-written notes on several of the bid forms, Mr. Bowman, Bureau Chief, determined that the bid documents were confusing and ambiguous. (Mr. Bowman stated that this was their first bid protest in his 15 years with the Department.) Therefore, Mr. Bowman decided that it would in the best interest of the State of Florida to reject all of the bids pursuant to the Bid Specifications. Mr. Bowman felt that the ITB should be re-written in order to make it clearer and allowing all of the bidders to re-bid the project without any confusion or ambiguity. Mr. Stine stated that his "senior estimator" told him that the bid language "could be confusing." He and his "senior estimator" had a discussion about whether the Allowance should have been placed in the Base Bid or not. At the time of submission of All America's bid, Mr. Stine was clear that the Allowance should be placed in the Base Bid, especially after calling Mr. Allen. But, his senior estimator was not so clear. In order to appease him, Mr. Stine placed the hand-written note on All America’s proposal. Mr. Stine essentially, "cleaned" up his proposal. At the hearing, Mr. Bowman testified Rule 60D-5.0071, Florida Administrative Code, see Conclusion of Law 59, does not list "confusing or ambiguous bid specifications" as one of the circumstances allowing for the rejection of all bids. However, Mr. Bowman later stated during the hearing that he believed the circumstances listed in Rule 60D-5.0071 were not the only circumstances authorizing the Department to reject all bids. Mr. Bowman testified that he believed that general confusion among the bidders caused by the ambiguous ITB constituted sufficient grounds for rejecting all bids. Mr. Bowman was advised by legal counsel that rejecting all of the bids would probably result in another bid protest by Nelco, All America, or both. Thus, the Department decided to delay addressing All American’s first protest until after posting the rejection of all bids and receiving the subsequent protests, so that all of the protests could be resolved at once in an efficient and economical manner. Notwithstanding the Department's justifications for rejecting all bids and not proceeding on All America's initial protest, the record is unclear why the Department waited several months to reject all bids. On May 13, 2002, the Department posted the rejection of all bids. On May 16, 2002, the Department received a formal written protest of the rejection of all bids filed by All America. On May 17, 2002, Jerome I. Johnson, attorney for the Department, contacted Mr. Robert A. Lash, All America's counsel at the time, concerning the resolution of All America’s formal protest. (Before the final hearing, Mr. Lash, with All America's consent, withdrew as counsel for All America.) The parties agreed to suspend formal bid protest procedures until a meeting could be held between the parties in an attempt to resolve the protests. Mr. Johnson sent a letter dated May 21, 2002, to Mr. Lash confirming this conversation. On June 26, 2002, a meeting was held among the Department staff, legal staff, and Mr. Lash and Mr. Stine, representing All America. The parties were unable to resolve the protests. At the conclusion of the meeting, the parties agreed that formal protest procedures would not be implemented until Mr. Stine could confer further with his counsel. In a letter dated July 5, 2002, Mr. Lash stated that his client wished to proceed with formal protest procedures and requested an administrative hearing on the protests. Are the Specifications and Bid Documents Ambiguous and Was There Confusion? The parties stipulated that "[t]he Addendum language was confusing," notwithstanding the testimony of several witnesses that they were not confused. The Department's determination that the bid Specifications, including the Addendum, and the Bid Form, which remained unchanged after the Addendum was issued, were confusing and ambiguous, is supported by the weight of the evidence. This is particularly true regarding the Bid Form. The Addendum required the bidder to include an Allowance of $25,000.00 in the Base Bid for work described as Alternate # 1. But the Bid Form was unchanged to reflect the Addendum changes. The Bid Form retained a line for the bidder to submit an additional amount for Alternate # 1. Further, it appears that several bidders were confused, including, Mr. Stine, who spoke with Mr. Allen and requested and received clarification. Further, it is unclear whether all of the bidders, including Nelco, were aware of the oral interpretations or clarifications of the Addendum rendered to some of the bidders. Rejection of All Bids Based upon the foregoing, given the standard of review in this proceeding discussed in the Conclusions of Law, the weight of the evidence indicates that the Department's action, in rejecting all bids, was not illegal, arbitrary, dishonest, or fraudulent. The Department's staff was well-intended and made some mistakes along the way, e.g., by not changing the Bid Form, which they readily admit. But there was a rationale for rejecting all bids under the circumstances.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department issue a final order dismissing All America’s Petition to Prevent Rejection of Bids and Award Contract to Petitioner and denying All America's request for attorney’s fees and costs. DONE AND ENTERED this 24th day of September 2002, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September 2002.

Florida Laws (3) 120.569120.57120.595
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer