The Issue The issue in this case is whether the bid of Kimball International Marketing, Inc., and Corporate Interiors, Inc., (Petitioners) is the lowest responsible bid which was received by the Pinellas County School Board (Respondent) for systems furniture (partitions) for the New District Administration Building, or in the alternative, whether all bids should be rejected as urged by The Harter Group (Intervenor).
Findings Of Fact On or about February 27, 1990, the Respondent sought competitive bids for systems furniture (partitions) for the New District Administration Building. In response thereto, Respondent timely received three bids, including those of the Petitioners and Intervenor, and one no bid. The bid opening occurred on April 17, 1990, and neither Petitioners nor Intervenor were determined to be the lowest responsible bidder. However, the Petitioners' bid was lower than that of the bidder to whom the Respondent proposes to award this contract. Petitioners' bid was $932,502.39, Intervenor's bid was highest at $1,101,509.90, and the bid of lowest responsible bidder, Haworth, Inc., was $1,072,286.50. The first reason given by Respondent for its determination that Petitioners' bid was not responsive to the bid specifications is that it did not include an amount for sales tax. Intervenor also did not include sales tax in its bid, but Haworth, Inc., which was determined by Respondent to be the lowest responsible bidder, did include sales tax. However, there was no dispute at hearing that the Respondent does not pay sales tax on transactions involving the acquisition of furnishings for the Pinellas County School System, and that Section 9.2.2 of the bid specifications erroneously stated that this contract would not be exempt from sales tax. The second reason given by Respondent for rejecting Petitioners' bid was that it omitted a required page from the approved form which was to be used to list those items in the bid proposal that were not in strict compliance with the Respondent's specifications. Petitioners admit that the required page numbered 00310-7 was not included in their bid, but maintain that it was not necessary to include this exact page since all items in their bid do meet specifications, and since a statement to this effect was included elsewhere in the bid. The lowest responsible bidder, as determined by the Respondent, did include this required page with a statement thereon that "all items comply". Intervenor also included this page listing 11 items in its bid which differed from the specifications. The purpose of this required page is to allow the Respondent to have a uniform, clearly identifiable place in each bid proposal where it can look to determine if the items in that bid meet specifications, without having to check every page of each bid. The third reason given by Respondent for rejecting Petitioners' bid was that it included numerous pages of unit costs which were not called for in the specifications, without any explanation as to their meaning or the purpose for which they were included in the bid. Section 4.1.1 of the bid specifications, found at page 00100-11, makes it clear that no bid form other than that which is set forth in the specifications will be accepted, and specifically states that bidders are not even to retype the form on their letterhead, but are to simply fill-in a copy made from the form in the specifications. The Petitioners admit that their bid includes additional, unexplained information that was not called for in the specifications. A final reason given by Respondent at hearing for rejecting Petitioners' bid was that it was accompanied by a bid bond, required by Section 4.2.4 of the specifications, in the name of Kimball International Marketing, Inc., while the public entity crime affidavit, required by Section 2.1.5, was subscribed to by Corporate Interiors, Inc. Petitioners' bid did not include a resolution or other evidence of authority that Corporate Interiors, Inc., had authority to submit a public entity crime affidavit on behalf of Kimball International Marketing, Inc., or that the affidavit submitted was valid as to Kimball. Thus, while Petitioners maintain that their bid was jointly filed on behalf of the manufacturer, Kimball, and the vendor, Corporate Interiors, their bid includes a bond from the manufacturer only, and a crime affidavit from the vendor only. Section 1.8 of the specifications, found at page 00100-2, specifies that the bidder is the person or entity that submits a bid. Petitioners urge that theirs is a joint bid, but they have failed to submit a joint bond or affidavit. Section 5.2.1 of the specifications allows the Respondent to reject any bid which fails to include a required security, or other required data. The bid which was determined by the Respondent to be the lowest responsible bid contains no technical flaws, errors or omissions, and the proposal meets all specifications for this project. The Respondent properly posted notice of its intent to award this contract to Haworth, Inc., the lowest responsible bidder. Under Section 5.3.1 of its bid instructions, the Respondent has the right to waive "any informality or irregularity in any Bid or Bids received and to accept the Bid or Bids which, in (its) judgment, is in (its) own best interest." Respondent chose not to waive any of the irregularities in the Petitioners' bid. This decision was made, in part, because of Respondent's previous experience with Petitioners in their installation of similar systems for Respondent at the Walter Pownall Service Centers in which there had been problems involving service during installation, coordination of the installation work, and verification that invoices received from Corporate Interiors did not exceed the bid base price, and that all items being paid had actually been received.
Recommendation Based on the foregoing, it is recommended that the Respondent enter a Final Order dismissing Petitioners' and Intervenor's protests of its intent to award a contract for systems furniture (partitions) for the New District Administration Building to Haworth, Inc., as the lowest responsible bidder. DONE AND ENTERED this 6th day of July, 1990, in Tallahassee, Leon County, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of July, 1990. APPENDIX TO RECOMMENDED ORDER, CASE NO. 90-2863BID Petitioner and Intervenor filed letters, but no proposed findings of fact upon which rulings could be made. Rulings on Respondent's Proposed Findings of Fact: Adopted in Finding 1. Adopted in Finding 3. 3. Adopted in Findings 4-6. 4. Adopted in Finding 6. 5. Adopted in Findings 4-6. 6. Adopted in Finding 6. 7. Adopted in Findings 6, 8. 8. Adopted in Finding 1. 9. Adopted in Findings 2, 3. 10-12. Adopted in Finding 6. 13. Adopted in Finding 4. 14. Adopted in Finding 3. 15. Adopted in Finding 5. 16-17. Adopted in Finding 7. 18. Adopted in Finding 1. 19. Adopted in Finding 8. COPIES FURNISHED: Allen D. Zimmerman, President Corporate Interiors, Inc. 1090 Kapp Drive Clearwater, FL 34625 Bruce P. Taylor, Esquire P. O. Box 4688 Clearwater, FL 34618-4688 Sue Olinger 1284 West Fairbanks Avenue Winter Park, FL 32789 Dr. Scott N. Rose Superintendent P. O. Box 4688 Clearwater, FL 34618
The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.
Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.
Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.
The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.
Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.
Findings Of Fact Upon consideration of the oral and documentary evidence addressed at the hearing, the following relevant findings of fact are made: The request for sealed bids for the construction of the Project was advertised on October 9, 16 and 23, 1991. There were six addenda to the original bid documents which added, deleted or modified provisions of the original bidding requirements, contract requirements, administrative requirements and technical specifications. The original bid documents plus the six addenda will be referred to herein as the "bid documents". The bid documents required that all bids be in full accord with the contract documents. Sealed bids for the Project were opened on October 30, 1991. Wright submitted the lowest lump sum bid for the Project, with Sovran submitting the second lowest lump sum bid and Kellogg submitting the third lowest lump sum bid. At the time of the bid opening, the bid documents listed only four casework manufacturers that were approved to furnish casework for the Project. Empire Custom Cabinets, Inc. (Empire) was not listed as one of the four approved casework manufacturers in the bid documents. The bid documents did not require the bidder to list the casework manufacturer it intended to obtain the casework from, but only that the bidder name the casework subcontractor. The only work item in the bid documents which requires identifying the name of the manufacturer on the subcontractor's list is the metal roof system. Because Empire's bid on the casework was extremely low compared to other bids received by Wright on the casework, Wright called Empire prior to submitting its bid to confirm that Empire's bid was submitted per plans and specifications. Although Wright did not specifically inquire of Empire at this time as to which manufacturer Empire was obtaining the casework from for the Project, Empire did advise Wright that Empire's bid on the casework was according to plans and specifications. Additionally, Empire did not divulge or advise Wright at this time that the bid was based on Empire manufacturing the casework for the Project. Based on this representation from Empire, Wright listed Empire as its casework subcontractor, and calculated its lump sum bid for the Project using Empire's bid. Although Wright listed Empire as its casework subcontractor in its bid, this did not create an irregularity in Wright's bid since Wright's bid was per plans and specification without exception or exclusion. This would require Wright to furnish casework for the Project manufactured by one of the four approved casework manufacturers listed in the bid documents regardless of which subcontractor Wright listed as the subcontractor for casework. By letter dated November 1, 1991, the Board's architect for the Project requested Wright to have Empire submit written certification by one of the four approved casework manufacturers that its casework was being furnished to Empire for the project. By letter dated November 4, 1991, Empire advised Wright that Empire's bid on the casework for the Project was based on casework to be manufactured by Empire. On the same day, Wright furnished the architect for the Project a copy of Empire's letter of November 4, 1991. In response to a request by the Board, Wright, by letter dated November 7, 1991, advised the Board that Wright would furnish casework manufactured by one of the four approved manufacturers listed in the bid documents for the Project. By letter dated December 3, 1991, Empire advised Wright that Empire would need to withdraw its bid if Empire was required to use casework manufactured by one of the four approved casework manufacturers listed in the bid documents. On that same day, Wright furnished the Board a copy of Empire's letter and requested that the Board allow Wright to remove and replace Empire with Steven Ward and Associates, Inc. (Ward), as the casework subcontractor since Ward would be able to furnish and install casework manufactured by LSI Corporation of America, Inc., one of the four approved casework manufacturers. No Action has been taken on that request. The bid documents provide for a subcontractor to be removed and replaced from the list of subcontractors after the bid is opened if there is a showing of good cause and written approval by the Board and the Project architect is obtained. Although Empire's bid on the casework for the Project submitted to Wright was based on Empire manufacturing the casework, there is competent substantial evidence in the record to establish facts to show that at the time Wright submitted its bid on the Project it had reasonable grounds to believe that Empire's bid on the casework was based on Empire furnishing and installing casework manufactured by one of the four approved casework manufacturers. After determining that Empire could not perform under its bid, Wright obtained a bid from Ward for furnishing and installing the casework for the Project which was less than Ward's original bid submitted to Wright before the bid opening. However, this bid was substantially more than Empire's bid, and if Wright is allowed to substitute Ward for Empire, Wright will have to absorb the additional costs since the bids were lump sum bids. Wright is neither attempting to furnish casework from a manufacturer that is not approved, nor is Wright requesting an increase in the lump sum bid price. The advertisement for Sealed Bids for the Project required that all bidders be prequalified by the Board prior to the bid date. Sovran and one other bidder were not prequalified by the Board prior to the bid date in accordance with Advertisement for Sealed Bids for the Project. Sovran received the bid documents for the Project approximately one month before the bid date but did not file a Notice of Protest of the prequalification requirement contained in the Advertisement for Sealed Bids for the Project. Sovran holds a certificate as a general contractor licensed in the State of Florida in accordance with Chapter 489, Florida Statutes. As a certified general contractor Sovran, pursuant to Section 489.125, Florida Statutes, was authorized to bid on the Project notwithstanding the Board's prequalification requirement. This was explained by the Board's representative at the bid opening. The bid documents required that a subcontractor list be submitted by all bidders, and when submitted with the bid becomes an integral part of the bid. The purpose of the subcontractor list was to prevent bid shopping, and to allow the Board an opportunity to review the subcontractors to determine if any subcontractor on the list had performed unsatisfactorily on previous Board projects. Neither the statutes relating to competitive bidding nor the bid documents prohibit the listing of the general contractor together with a subcontractor on a subcontractor list. The subcontractor list submitted by Sovran indicated "Sovran Constr/Naples" as the name of the subcontractor for the masonry work and "Sovran/Naples" as the name of the subcontractor for the poured-in-place concrete work. "Naples" is Naples Concrete and Masonry Work, Inc. The bid received by Sovran from Naples was for both labor and materials for the poured-in-place concrete and masonry work. Sovran neither requested nor did Naples furnish Sovran a bid to provide labor only for the poured-in-place concrete and masonry work. There was no agreement between Sovran and Naples whereby Sovran would supply the materials and Naples would furnish the labor for the poured-in-place concrete and masonry work. Sovran did request and receive bids from other companies for furnishing materials only for the poured-in-place concrete and masonry work. Sovran listed itself, the general contractor, along with Naples on the subcontractor list for the purpose of supplying the materials for the poured-in- place concrete and masonry work. Sovran's main reason for supplying the materials was that Naples was not bondable. Without a payment bond from Naples, Sovran would be without protection and could be forced into paying double for the materials in the event Naples failed to pay the material suppliers. Although the Superintendent of the Lee County Schools has recommended to the Board that the Board accept Wright's bid for the Project, the Board has not voted on that recommendation. The fact that Wright used Empire's bid to calculate its lump sum bid in no way excuses Wright for the requirement set out in the bid documents that casework used for the Project (when the time comes) be manufactured by one of the four approved casework manufacturers. Wright gains no economic advantage in this regard since the lump sum bid price remains the same. The advertisement for Sealed Bids on the Project provides that the Board reserves the right to waive any and all irregularities of any bid received.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Board enter a Final Order dismissing the instant bid protest and awarding to Wright the contract for the construction of Elementary School "C", Job No. 91063. DONE and ORDERED this 13th day of February, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13 day of February, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 91-7597B1D The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 3(1,2 and 3 , respectively); 4 - 5(6); 6(4); 7 - 9(5); 12(10); 13(11); 15 - 16(12); 17(13); 18 - 19(16); 20(29); 21(18); 23(19); 24 - 25(20); 26(22); 27(23); 28(22); 29 - 30(29); 32 - 33(25); and 34(26). Proposed finding of fact 10 is rejected as not being supported by competent substantial evidence in the record in that Wright's bid was as per plans and specifications without exceptions or exclusions which included the use of casework manufactured by one of the approved casework manufacturers. Proposed finding of fact 11 is rejected as not being supported by competent, substantial evidence in the record in that the Board knew of Empire's bid being based on nonconforming materials prior to issuing its Notice of Intent. However, the only information the Board had in reference to Wright's bid before issuing its Notice of Intent was that Wright had bid as per plans and specifications and would be installing casework manufactured by one of the approved manufacturers. The only question was whether Empire could furnish casework manufactured by one of the approved manufacturers. Proposed finding of fact 14 is neither material nor relevant. How the Board's architect interpreted Wright's bid is neither material nor relevant to this proceeding. Proposed finding of fact 22 is unnecessary to the conclusion reached in the Recommended Order. Proposed finding of fact 31 is more in the way of an argument than a finding of fact. Proposed findings of fact 35 and 36 are covered in the Preliminary Statement. The timeliness of Kellogg's protest is not an issue and therefore, a finding that it was timely is unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent While not specifically adopting proposed finding of fact 1, where material or relevant or necessary to this proceeding, and supported by competent, substantial evidence in the record the stipulated facts have been adopted. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2(4,5); 3(9); 4 - 5(7); 7 - 8(8); 10(16); 11(14); 12(31); 13(21); and 15(23). Proposed finding of fact 6 is more in the way of an argument than a finding of fact. Proposed finding of fact 9 and 14 are neither material nor relevant. Rulings on Proposed Findings of Fact Submitted by the Intervenor See ruling on Respondent's proposed finding of fact Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2 - 3(21); 4(24); 5 - 6(21); 13(23); 14(24,28); 15(22); 16 - 17(23,24); and 18(28). Proposed findings of fact 7 through 12 are neither material nor relevant to this proceeding. COPIES FURNISHED: David E. Gurley, Esquire Norton, Gurley & Darnell, P.A. 1819 Main Street, Suite 610 Sarasota, FL 34236 Marianne Kantor, Esquire The School Board of Lee County 2055 Central Avenue Fort Myers, FL 33901 James M. Talley, Esquire Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, P.A. Post Office Box 712 Orlando, FL 32802 Karl Engel Superintendent Lee County School Board 2055 Central Avenue Ft. Myers, FL 33901 Honorable Betty Castor Commissioner of Education The Capitol Tallahassee, FL 32399-0400
The Issue Whether Respondent properly rejected Petitioner's bid on the grounds that the bid did not meet a fatal item requirement.
Findings Of Fact On April 24, 1992, Respondent published a Request for Proposals (RFP) for the provision of housekeeping services to South Florida State Hospital. Attached to the RFP as Appendix I was a blank copy of Respondent's "Standard Contract" which is also referred to as its "core model contract". Paragraph 1.a. of Section D of the RFP contains the following instructions to bidders: BIDDER RESPONSE a. State of Florida Request for Proposal Contractual Services Acknowledgment Form, Pur 7033 The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, Appendix II must be signed and returned ... with the proposal or submitted by itself if you choose not to submit a proposal and wish to remain on the department's active vendor list. Paragraph 1.g. of Section D of the RFP, contains the following instructions to bidders: Required Bidders Certification Contract Terms and Conditions The proposal must include a signed statement in response to the RFP indicating acceptance of the terms and conditions of provisions of service as specified in the RFP and contained in the core model contract. Bidders were provided a copy of the RFP rating sheet which contained the following under the heading of Fatal Items: The following criteria must be met in order for the proposal to be considered for evaluation, failure to receive a "Yes" response for any time [item] will result in automatic rejection of the proposal. * * * Does the proposal include a statement agreeing to terms and conditions set forth in the core model contract and the RFP? Petitioner was represented at a "Bidders' Conference" held May 15, 1992, at which the fatal items were discussed. Bidders were advised that it would be necessary for the responses to contain a statement agreeing to the terms and conditions set forth in the core model contract. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, contains the following certification: I certify that this proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same contractual services, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. In submitting a proposal to an agency for the State of Florida, the proposer offers and agrees that if the proposal is accepted, the proposer will convey, sell, assign or transfer to the State of Florida all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti-trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the State of Florida. At the State's discretion, such assignment shall be made and become effective at the time the purchasing agency tenders final payment to the proposer. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was signed by Richard A. Cosby on behalf of Petitioner and submitted as part of Petitioner's response to the RFP. Upon receipt of all responses, Respondent convened an evaluation committee to evaluate the responses. The evaluation committee determined that the response submitted by Petitioner did not contain the required statement agreeing to the terms and conditions set forth in the core model contract and the RFP. Consequently, the evaluation committee rejected Petitioner's proposal from further consideration. Petitioner does not challenge the specifications of the RFP, but, instead, asserts that Mr. Cosby's execution of the State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was sufficient to meet the requirement the evaluation committee found lacking. The language of the Contractual Services Acknowledgment Form, PUR 7033, that most closely approximates the certification that the bidder accepts the terms and conditions set forth in the core model contract and of the RFP is as follows: I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. The proposal submitted by Petitioner did not contain any other statement which could be construed as accepting the terms and conditions set forth in the core model contract and the RFP. The broad language of the Contractual Services Acknowledgment Form, PUR 7033, upon which Petitioner relies does not state that the bidder accepts the terms and conditions set forth in the core model contract and the RFP. The evaluation committee properly determined that Petitioner's response failed to meet this fatal item. In this proceeding, there was evidence that the Respondent routinely inserts in its Request for Proposals the fatal item requirement that the bidders agree in writing to accept the terms and conditions set forth in the core model contract and the RFP, and that Respondent has never waived that fatal item requirement. There was no evidence that Respondent was using this fatal item requirement to discriminate against or in favor of any bidder.
Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of August, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1992. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 92-4311BID The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioner. 1. The proposed findings of fact submitted by Petitioner are accepted in material part by the Recommended Order. Petitioner's conclusions based on those facts are rejected for the reasons discussed in the Recommended Order. The following rulings are made on the proposed findings of fact submitted on behalf of the Respondent. 1. The proposed findings of fact submitted by Respondent are adopted in material part by the Recommended Order. COPIES FURNISHED: Richard A. Cosby, Vice President National Cleaning of Florida, Inc. 1101 Holland Drive, #32 Boca Raton, Florida 33487 Colleen A. Donahue, Esquire District 10 Legal Office Room 513 201 West Broward Boulevard Fort Lauderdale, Florida 33301-1885 Sam Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Slye, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
The Issue Whether the Barton-Malow Southern, Inc., deviated from the bid requirements, and if so, whether such deviation consists of a minor deviation which may be waived by the respondent, or whether Ron A. Royal, Inc., should be awarded the elementary school "C" project as the lowest responsive bidder.
Findings Of Fact On April 20, April 27, and May 4, 1986, the Board advertised its Notice of Call for Sealed Bids, soliciting bids for the construction of Elementary School "C". The notice advised that the contract to be awarded would require approval of subcontractors by the Board and stated that the Board "reserves the right to reject any and all bids received and to waive any and all informalities in regard thereto." A pre-bid conference was held on May 15, 1986, at which time the potential bidders were advised that page 14 of the bid documents entitled "List of Subcontractors" would be deleted and addendum #1 would include a more specific list of subcontractors to be completed by the bidder. The original list of subcontractors stated: The undersigned, hereinafter called "Bidder", list below the names of all the subcontractors who will perform under the Bidder. Any work item (Trade) not included will be assumed by the owner as being performed by the Bidder's own forces." A space was provided for the bidder to state the work item and the name of the subcontractor who would perform the work. Addendum #1 instructed the bidders to delete the original page C.14 and insert the enclosed sheet C.14 (addendum #1) "List of Subcontractors" for submission with the sealed bids. The substituted list of subcontractors provided as follows: The undersigned, hereinafter called "Bidder", lists below the names of the subcontractors who will perform under the Bidder. In the event the general contractor will perform one of the phases listed with his own personnel, he shall state by "general contractor". The form listed 20 specific areas of work, such as site work, iron and steel work, roof decks, and electrical, and provided a space for the bidder to fill in the firm name and address of the subcontractor for each specific area. Bids were submitted to the Board by nine (9) general contractors. The lowest bid by $310,000, was submitted by Barton-Malow; the second lowest bid was submitted by Royal. On the list of contractors submitted with Barton Malow's bid, Barton- Malow listed "G.C". (General Contractor) for the work areas described as site work, concrete work, masonry work iron and steel work, and lathing and plastering. Barton-Malow listed a subcontractor and "G.C." for phases described as hard tile and electrical. For the work areas described as "roof decks" and "roofing and sheet metal" three (3) subcontractors were listed for each of the areas. The list submitted by Royal with its bid provided that the concrete work would be performed by the general contractor and listed a single subcontractor for each of the other 19 areas of work specified. Barton-Malow was the only bidder who listed multiple subcontractors for a specified work area. In the blanks provided for the subcontractors' addresses, Royal listed the city where each subcontractor was located; Barton-Malow did not provide any addresses bout stated at the top of the column "will be advised upon request." None of the bidders provided street addresses for the subcontractors, however, only one bidder other than Barton Malow failed to provide the city in which the subcontractor was located. Immediately after the bids were opened and read, 1/ the meeting was adjourned and Mr. Derryberry, Mr. Collins, and two other people reviewed the bids. Mr. Derryberry concluded that the Barton-Malow bid was not in compliance with the bid requirements due to the manner in which Barton-Malow had filled out the subcontractor list. Mr. Derryberry therefore recommended to the Board that the Barton-Malow bid be rejected because of the perceived irregularities and the bid of Royal be accepted. The recommendation of the architect was adopted as the recommendation of the school administration and presented to the Board at a public meeting on June 3, 1986. The Board received the report of the architect and the administration, heard from the attorneys and representatives of Barton- Malow and Royal, and then voted to waive any irregularities and accept the Barton-Malow bid. The original page C.14 was approved by the Board in about 1980 and used since that time. However, there had been some difficulty with that form on two different jobs within the last six months, and therefore it was decided to clarify the purpose of the form by specifically listing all the major subcontracting areas. The intent was to require all bidders to list the primary subcontractor in each of the major work areas, and thus prevent bid shopping after the bids were opened. The architect, Mr. Derryberry, prepared and included the amended form C.14 as part of Addendum #1 to the bid documents. Although the Board never formally approved the amended form, Mr. Derryberry had the authority to clarify any of the bid documents by addendum. Page C.14 (Addendum #1) lists 20 major subcontracting areas; however, in almost all of the areas it would be possible for more than one subcontractor to perform the designated work, and in several areas it would be unlikely that one subcontractor would perform all the required work. For example, site work includes paving, earth moving, culvert work, fencing, and irrigation, and one subcontractor would not normally do the work in all those areas. The amended page C.14 does not state that only one subcontractor should be listed for each specified work area. The bidders were not advised at the pre-bid conferences or subsequent thereto, that only one subcontractor should be listed in each category. The only information the bidders received regarding the list of subcontractors was the information contained on the revised page C.14. In other words, the bidders were simply directed to list "the names of the subcontractors who will perform under the Bidder", and to list general contractor when "the general contractor will perform one of the phases listed with his own personnel." In the subcontractor list submitted with their bid, Barton-Malow listed "Batten Electric Co./G.C." for the subcontract "Electrical", and listed "Bauer & Assoc./G.C." for the "Hard Tile" subcontract. The listing of a subcontractor and the general contractor in these areas is not a deviation from the bid requirements. There is no indication on the list submitted by Barton- Malow that the listing of a subcontractor and the general contractor in the hard tile and electrical categories meant anything other than both the subcontractor and the general contractor would perform the work required in those areas, and there was no evidence presented at the hearing that would require a different conclusion. 2/ Categories 5 and 6 on the subcontractor list are "roof decks" and "roofing and sheet metal." Although listed as two separate categories, the same subcontractor would have to perform both due to the bid requirements. Further only one subcontractor can perform the roofing work; it is not an area that is divisible into subcategories that can be performed by different subcontractors. For categories 5 and 6, Barton-Malow listed "H. H. Robertson/Architectural Exteriors/Commercial Roof Decks." As admitted by Barton-Malow, that all three subcontractors "will perform" the subcontract is an impossibility. 3/ From the list submitted by Barton-Malow it cannot be determined who will perform and be responsible for the roofing work. When asked at the hearing who was going to perform the roofing work for Barton Malow, the vice-president of operations for Barton-Malow responded, "One of those three would have done it." He indicated that a submission would have been made to the Board designating the subcontractor. By listing three subcontractors for the two roofing categories, Barton-Malow deviated from the bid requirements. The subcontractor list contained one basic requirement, that the subcontractors listed "will perform." By listing three subcontractors for the roofing, when only one subcontractor could performs Barton-Malow would be able to bid shop for subcontractors after the bid submission. This would give Barton Malow a definite advantage over the other bidders who complied with the bid requirements and listed only the one contractor who would perform the work. The other bidders would be bound to use the subcontractor listed and therefore, would be unable to negotiate for a better price after obtaining the contract. However, by listing multiple subcontractors, Barton-Malow would be able to negotiate for a better price because it had not committed itself to any one subcontractor. In five categories, site work, concrete work, masonry work, iron and steel work, and lathing and plastering, Barton Malow listed general contractor. About an hour after bid opening, Mr. Derryberry called Mr. Polso, the Vice- President of Operations for Barton-Malow, to inquire about the bid because it was so much lower than the other bids. Mr. Polso assured Mr. Derryberry that there had been no mistake in the amount bid. Mr. Derryberry then asked about the listing of general contractor for the iron and steel work because he had never known of a general contractor doing that type of work. Mr. Polso stated that he had not had time to determine the low bidder in that category and was still getting prices. He also said that Barton-Malow would not be doing the lathing and plastering. However, when Mr. Derryberry advised that he was recommending that the bid be disqualified due to the incompleteness of the subcontractors form and asked whether Barton-Malow wished to withdraw its bid, Mr. Polso stated that Barton-Malow had no intention of withdrawing its bid. Subsequently, Mr. Polso met with Mr. Derryberry and Mr. Collins at the school offices and advised them that Barton-Malow had every intention of performing the work where general contractor had been listed. Barton-Malow is a wholly owned subsidiary of Barton Malow Company and has the resources of Barton-Malow Company available when necessary. In 1985, Barton-Malow did between 60 and 70 million dollars of construction work; Barton- Malow Company had a dollar volume of 600 million dollars. Barton-Malow has the capacity to perform work in the areas where it listed general contractor. Barton-Malow prepares its bid by estimating the value of the total project and the value of the majority of the specific trades involved. If Barton-Malow does not receive a bid from a subcontractor that it feels is competitive in a particular trade area, it performs that work itself. The C.14 (Addendum #1) form permitted a bidder to list "general contractor" in any or all subcontract areas in which it would perform the work with its own personnel. Once the bids are opened, the bidder cannot unilaterally substitute a subcontractor for the general contractor. The general contractor would be required to do the work unless it received authorization to substitute a subcontractor based upon a showing of good cause. The evidence does not support a finding that Barton-Malow was incapable of performing the work in the areas in which it listed "general contractor." Therefore Barton- Malow did not deviate from the bid requirements by listing "general contractor" in five of the twenty specified areas. Although Baron-Malow deviated from the bid requirements by failing to list any addresses on its subcontractor list, this was a minor irregularity which did not give Barton-Malow any competitive advantage over the other bidders. In Division C, Article 5, Section 5.3.1., the bid documents provide: It is the intent of the owner to award a Contract to the lowest responsible Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents....The Owner shall have the right to waive any informality or irregularity in any Bid or Bids received and accept the Bid or Bids which in his judgment, is in his own best interests.
The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.
Findings Of Fact On or about February 9, 1983, the State of Florida, Department of General Services, Division of Construction and Property Management, Bureau of Property Management ("DGS"), received a certification of need from the Department of Corrections ("DOC") requesting authority for DOC to advertise for competitive bids from private persons interested in providing leased office space needed to house DOC's Bureau of Industries. The Bureau of Industries was then located in leased space with leases which were scheduled to expire June 30, 1983. The Bureau of Industries has been located in DOC's central office area since its creation in 1957. The DOC central office includes the Secretary and Deputy Secretary; the Assistant Secretaries for Operations, Programs, Management, and Budget. All these officials, together with subsidiary bureaus, staff, and other subordinates are located in two adjacent buildings of the Winewood Office Complex on Blair Stone Road in Tallahassee. The prison industry program is under the supervision of the industries administrator who reports directly to the Assistant Secretary for Operations. DOC sought approval from DGS to enter into a lease for privately owned office space because of its perceived need to locate within walking distance of its central office. Programs administered by the Bureau of Industries work closely with other DOC personnel and functions located in the central office in the Winewood Office Complex. Moving any distance from the central office would create problems for the DOC mailing system and would require extra time spent traveling to and from the central office. Personnel in the Bureau of Industries utilize central office files, and confer often with staff located in the central office. Locating outside the general area of the central office would require additional expenses with regard to availability of vehicles, pick up of mail and supplies, and duplication of support services. Accordingly, DGS and DOC determined, and the record in this cause establishes, that it would not be in the state's best interest to require DOC to locate its Bureau of Industries program either in state-owned buildings in the Capitol Center, or in any area beyond walking distance of the central office location. On March 21 and 31, 1983, respectively, DOC published an advertisement in the Tallahassee Democrat inviting all interested persons to submit sealed bids at or before 2:00 p.m. on April 19, 1983, in accordance with the Invitation to Bid and Specifications prepared by DOC for the office space needed to house the Bureau of Industries. A portion of the bid specifications required that office space to be leased be located within a circle drawn on a city map of the City of Tallahassee, Florida, which could roughly be described as the southeastern portion of the city, in the vicinity of the Winewood Office Complex. There were four possible bidders in the area within the circle on the map attached to the bid specifications. Of these four possible bidders, two within the area actually submitted bids--Blairstone Center Partners and Washington Square, Ltd. One of the general provisions of the bid specifications provided as follows: The Department of Corrections reserves the right to reject any and all bids, waive any minor informality or technicality in bids received and to accept that bid deemed to be the lowest and best. . . At or before 11:00 a.m. on April 19, 1983, DOC received sealed bids from Petitioner and Intervenors in response to the aforesaid advertisement, and at 11:00 a.m. on April 19, 1983, DOC opened, tabulated, and published each of the bids. The bid submitted by Petitioner was not responsive to the requirements of the Invitation to Bid and Specifications because the property offered by Petitioner in its response was outside the area indicated on the map annexed to the Invitation to Bid. The bid submitted by Intervenor, Blairstone Center Partners, failed to offer the full services specified in paragraph six of DOC's Bid Submittal Form; failed to offer the exclusive parking specified in the paragraph seven of the Bid Submittal Form; failed to supply the photographs specified in paragraph ten of Respondent's Bid Submittal Form; and failed to supply the information specified in paragraphs one through eight of the Bid Submittal Form. Accordingly, the record in this cause fully establishes that the bids submitted by Petitioner and by Intervenors Blairstone Center Partners, failed to comply with the requirements of the Invitation to Bid and Bid Submittal Form, and that the deficiencies in the bids of Petitioner and Intervenor, Blairstone Center Partners, were so material as to require their rejection. The Invitation to Bid and Bid Submittal Form required that bidders offer for lease 2,683 square feet, plus or minus three percent. The bid submitted by Intervenor, Washington Square, Ltd., offered 2,797 square feet, which is approximately 34 square feet more than allowed in the Invitation to Bid. After this fact was discovered upon opening the bid, DOC personnel contacted a representative of Washington Square, Ltd., and advised the net square footage offered in the bid submitted by Washington Square, Ltd., exceeded the net square footage of space that DOC was authorized to lease and pay for under the Invitation to Bid. Washington Square, Ltd., subsequently agreed to modify its proposal by relieving DOC from any obligation to pay for the extra 34 square feet, and reducing the annual rental for the first year from $26,012.10 to $25,695.90, and for the second year from $27,576.60 to $27,243.18. The record in this cause does not establish any misconduct or collusion between Washington Square, Ltd., and DOC personnel obtaining this modification, nor does the record in this cause establish that any actual or prospective bidders suffered any competitive disadvantage as a result of this modification. The effect of Washington Square, Ltd.'s modification of its proposal rendered that proposal the only bid which was responsive to the Invitation to Bid. On August 18, 1983, Washington Square, Ltd., executed a deed to the property which was the subject matter of its bid to Ben Grace. Washington Square also executed an assignment of the proposed bid award to Grace.
The Issue The issue in this case is whether the bid specifications, together with other applicable authority, require that a bid, in order to be responsive, contain any written list of subcontractors.
Findings Of Fact On September 26, 1989, Respondent issued a document entitled, Specifications for Replacement of Air Conditioning, West Orange High School, Winter Garden, Florida, Engineers Project No. 89-016. As amended by three addenda, the above-described specifications shall be referred to as the "ITB." Respondent duly advertised for bids ore September 26, October 3, and October 10, 1989. The advertisement did not state that Respondent reserved the right to waive minor irregularities. In response to the ITB, Florida Mechanical, Inc. ("FMI") and B & I Contractors, Inc. ("B & I") timely submitted bids. For the base work and alternate 1, which Respondent ultimately decided to select, FMI bid $1,439,000, B & I bid $1,438,000, and a third bidder, S. I. Goldman, Company bid $1,621,000. These bids are recorded on a Bid Tabulation Sheet prepared by the engineer retained by Respondent for the project. The Bid Tabulation Sheet contains eight columns. Four columns record bid amounts for the base work and various alternates. The remaining columns are entitled, "Bidder," "Bid Bond," "Addenda," and "Subs." Each of the three bidders were named in one of the rows beneath the "Bidder," column. Each bidder had one "X" in its "Bid Bond" column and three "X"s in its "Addenda" column. However, only FMI and S. I. Goldman Company had "X"'s in their "Subs" columns. By resolution adopted on November 29, 1989, Respondent directed that all bids were rejected and that the Superintendent would correct any ambiguities and uncertainties in the ITB and solicit new bids. The resolution noted that Respondents staff had recommended that, if any bid were accepted, it should be that of B & I. However, [FMI] submitted with its bid a list of Major Sub-contractors of the form displayed in the [ITB], and B & I did not submit wish its aid a list of Major Sub-contractors[.] The resolution concluded that Respondent based on advice of staff and counsel, found that the [ITB is) ambiguous and/or uncertain as to whether or not a bidder must submit along with his bid a list of Major Sub-contractors, (b) that because of such ambiguity and/or uncertainty, it would be unfair and/or improper for [Respondent] to accept either of the bids received by it, and (c) that as a result thereof [Respondent] should reject all bids received by it for ,the Project and should solicit new bids for the Project as soon as is reasonably feasible after correction by [Respondents] staff of any ambiguity and uncertainty as aforesaid in the [ITB]. FMI and B & I each timely filed a notice of intent to protest and formal written protest of Respondent's decision to reject each company's respective bid. S. I. Goldman did not protest the decision and is not a party to the subject case. At a meeting on December 12, 1989, Respondent elected to refer the bid protests to the Division of Administrative Hearings for a formal hearing., At the beginning of the hearing, the parties filed a written stipulation, which stated that the only issue for determination was which Petitioner should be awarded the contract and not whether Respondent should seek further bids or award the contract to another bidder. The stipulation also stated that the Petitioners and Respondent agreed to abide by the recommendation of the hearing officer. At the hearing, the parties further stipulated that the sole issue for determination is whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. In addition, the parties stipulated that both Petitioners had standing and the protests were timely and sufficient. The ITB requires that each bidder familiarize itself with all federal, state, and "Local Laws, ordinances, rules, and regulations that in any manner affect the work." Under the section entitled, "Preparation and Submission of Bids," the ITB states: "Each bidder shall use the Bid Form that is inserted herein, and may copy or reproduce the form on this own letterhead." Among other requirements, the ITB requires two bonds. The first is a "bid guarantee" of at, least five percent of the amount of the bid. The form of this guarantee may be cash or a Bid Bond." The other bond described in the ITB a 100% public construction bond. The surety on this bond must have been admitted to do business in Florida, must have been in business and have a record of successful continuous operation for at least five years, and must have at least a Bests Financial Rating of "Class VI" and a Bests Policyholder Ration of "A." The Bid Form contained in the ITB is two pages. Among other things, the Bid Form requires that the bidder receiving written notice of acceptance of its bid must provide the prescribed payment and performance bond and execute the contract within ten days after notification. The next document in the ITB is a single page entitled, "Form of Bid Bond." The provisions on this page identify the A.I.A. document to use and state that the Bid Bond "shall be submitted with the Bid Proposal Form." The next document in the ITB is a single page entitled, "List of Major Subcontractors." The List of Major Subcontractors states: Bidders shall list all major subcontractors that will be used if a contract is awarded. Additionally, bidders shall identify in the appropriate box whether or not that trade specialty is minority owned. Another paragraph defines minority ownership. The remainder of the form consists of ten rows for the "bidder" and nine major subcontractors, such as concrete, electrical, HVAC, and controls, and blanks where the bidder can indicate which of these entities are minority owned. The next document in the ITB is the Owner-Contractor Agreement, which is followed by tie Form of Construction Bond, General Conditions, and Supplementary General Conditions. Section 7.11 of the Supplementary General Conditions establishes certain requirements to be performed after the submission of bids. This section provides: Pre-Award Submittals: Before the Contract is awarded the apparent low bidder shall provide the following information to the owner. A copy of the Contractors current State of Florida General Contractor's or Mechanical Contractors License. Pre-Construction Meeting. After the Notice to Proceed and within eight (8) business days of the Owner [sic], the Contractor shall meet with the Owner, Engineer and Subcontractors that the Owner may designate... The Contractor shall provide the following to the Owner. * * * 2. A written list of all Subcontractors, material men and suppliers with such information as requested by the Owner or Engineer. * * * The remaining documents in the ITB are the technical specifications for the job. The three addenda supply additional technical information not relevant to this case. Respondent has promulgated rules with respect to the bidding process ("Rules"). The ITB does not refer to the Rules, which define and use many terms that are found in the ITB. For instance, Rule 1.1.25 defines the phrases, "Performance and Payment Bond," which is the same phrase used in the Bid Form in the ITB. The Rules define several other capitalized terms that are also used in the ITB, such as Bid Bond, Bid Guarantee, Bidder, and Contractor. Rule 4.1 similarly states that the bidder is familiar with federal, state, and "Local Laws, Ordinances, Rules and Regulations that in any manner affect the Work." Rule 6.1 describes the process by which a bidder is to prepare and submit bids and the Bid Guarantee in language similar to that contained in the ITB. Rule 6.2 discusses the listing of subcontractors. Rules 6.2.1 and 6.2.2 state: General Contractor shall include as an integral part of his bid a List of Subcontractors he proposes to use. The Bidder shall enclose this list in a 4" x 9" envelope, sealed and marked "List of Subcontractors" and identified ... The Bidder shall enclose said envelope with his bid proposal in the mailing envelope. The List of Subcontractors enclosed with tee Proposal of each Bidder will be examined by the ... Engineer before the Proposal is opened and read. In the event that the form is not properly executed and signed, the Proposal of that Bidder will be returned to him unopened... Rule 6.3 requires a Statement of Surety as another "integral part" of each bid. Rule 6.3.3 states: The Statement of Surety will be opened examined by the ... Engineer prior to the opening of the Proposal.... Although similar to Rule 6.2, Rule 6.3 lacks the warming that if the Statement of Surety is not "properly executed and signed, the Proposal of that Bidder will be returned to him unopened." Rule 19.1 sets forth the requirements, for the surety. These requirements are different than those set forth in the ITB. Rules 19.1.1 and 19.1.2 require, as does the ITB, that the surety be admitted to do business in the State of Florida and shall have been in business and have a record of successful continuous operations for at least five years. However, Rule 19.1.1 requires that the surety be represented by a reputable and responsible surety bond agency licensed to do, business in the State of Florida and have a local representative in the Orlando area. Rule 19.1.3 requires minimum Bests ratings of "A" in "management," and, as to "strength and surplus," "AAA+" in financial rating and $12,500,000 minimum surplus. Rule 19.1.3.3 also requires that the surety be listed on the U.S. Treasury Departments Circular 570. The bids of FMI and S. I. Goldman Company contained a completed List of Major Subcontractors. The bid of B & I did not. No bidder included a Statement of Surety with its bid.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the School Board of Orange County enter a Final Order awarding the subject contract to Florida Mechanical, Inc. ENTERED this 15th day of February, 1990, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1990. APPENDIX Treatment Accorded Proposed Findings of FMI All of FMI's proposed findings have been adopted or adopted in substance. Treatment Accorded Proposed Findings of B & I 1-4: adopted or adopted in substance. 5: adopted, except that the staff recommended that, if the bid was to be awarded, that it be awarded to B & I. 6: adopted in substance. 7: rejected as conclusion of law and, to the extent fact, subordinate. 8-12: rejected as subordinate. 13-16: adopted or adopted in substance. 17: rejected as subordinate. 18: rejected as unsupported by the greater height of the evidence. 19-21: rejected as subordinate. 22: rejected as beyond the scope of the issues and irrelevant in view of the stipulation. In the stipulation, the parties agreed that the issue to be addressed would not be whether the intended agency action of Respondent was lawful (i.e., not arbitrary, fraudulent, dishonest, or otherwise improper), but rather whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. COPIES FURNISHED: James L. Schott, Superintendent The School Board of Orange County, Florida P.O. Box 271 Orlando, FL 32802 Charles Robinson Fawsett, P. A. Shutts & Bowen 20 North Orange Avenue Suite 1000 Orlando, FL 32801 James F. Butler, III Smith, Currie & Hancock 2600 Peachtree Center Harris Tower 233 Peachtree Street, N.E. Atlanta, GA 30043-6601 William M. Rowland, Jr., Esq. Rowland, Thomas & Jacobs, P.A. 1786 North Mills Avenue P.O. Box 305 Orlando, FL 32803
The Issue Petitioner and Lyell Hintz protest the Department's intent to award the bid for Lease No. 550-0209 to Southeastern Investment Properties, Inc. Issues derived from the pleadings, the joint prehearing stipulation and the evidence and argument at hearing are: Whether Petitioner has standing to protest the bid award; Whether Petitioner and Lyell Hintz have waived the right to contest evaluation criteria; If not, whether those criteria are valid; Whether the Respondent has properly applied the criteria to the bid proposals; Whether Southeastern's bid was nonresponsive; Whether Southeastern changed its bid after opening; Whether Petitioner's bid was defective for failure to include a waiver of existing lease; Whether the bid should be awarded to Lyell Hintz or Petitioner; and Whether all bids should be rejected and the lease re-bid.
Findings Of Fact The Bid Solicitation On or about January 31, 1991, the Florida Department of Transportation (DOT) advertised its request for proposals (RFP) for a full service lease for its District Five, Operations and Planning Office, Public Transportation Office and Construction Office. The RFP is identified as lease #550:0209. Specifications include net square footage of 13,640 + 3% (13,231 - 14,049), divided into 90% office and 10% storage space, to be available by July 1, 1991, or within 30 days of notice of bid award, whichever occurs last. The space is to be available in a northern section of Orange County designated on a map attached to the RFP, in the Winter Park/Maitland/Orlando area surrounding the intersection of Lee Road and I-4. The following evaluation criteria (award factors) are included in the RFP: The successful bid will be that one determined to be the lowest and best. All bids will be evaluated based on the award factors enumerated below: Rental, using total present value methodology for basic term of lease... (weighting: 15) Conformance of and susceptibility of the design of the space offered to efficient layout and good utilization and to the specific requirements contained in the Invitation to Bid (not to exceed a weight of 10 award factors). (weighting: 10) Provision of the aggregate square footage on a single floor. Proposals will be considered, but fewer points given, which offer the aggregate square footage in not more than two floors. (weighting: 25) The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of Departmental operation planned for the requested space. (not to exceed a weight of 10 award factors) (weighting: 10) Offers providing 100 s.f. of street-level secured storage. (weighting: 10) * * * [deleted criteria given 0 weight and not relevant] Option period rental rate proposed is within projected budgetary restraints of the department. (weighting: 15) Accessibility to an I-4 Interchange. (weighting: 15) total award factors = 100 (Joint Exhibit #1, p. 7 of 10) Paragraph D.1., General Provisions, includes a notice that failure to file a protest within the time prescribed in Section 120.53(5), F.S., constitutes a waiver of proceedings under Chapter 120, F.S. The notice references an attachment which includes the text of Chapter 90-224, Laws of Florida, requiring posting of a bond at the time of formal written protest. Paragraph D.6.A., General Provisions states: Each proposal shall be signed by the owner(s), corporate officers, or legal representatives(s). The corporate, trade, or partnership title must be either stamped or typewritten beside the actual signature(s). If the Bid Submittal is signed by an Agent, written evidence from the owner of record of his/her authority must accompany the proposal. If the agent is to execute the lease, the authority must be supported by a properly executed Power of Attorney. If the Bid Submittal is offered by anyone other than the owner or owner's agent, proof of the bidder's authority to offer the facility, i.e., copy of bidder's Option to Purchase, must accompany the proposal. This option must be valid through the validity date established for bids. If a corporation foreign to the State of Florida is the owner of record, written evidence of authority to conduct business in Florida must accompany the Bid Submittal. If there is an existing lease extending beyond the required availability date for all or any portion of the premises being offered to the agency a release of the applicable lease must accompany the Bid Submittal. (Joint Exhibit #1, p. 8 of 10) Paragraph D.8., General Provisions, provides the Department reserves the right to reject any and all bid proposals, waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the state, and if necessary, to reinstate procedures for soliciting competitive proposals. Paragraphs D.12 and 13, General Provisions, establish a March 4, 1991 bid opening and a February 11, 1991 preproposal conference, respectively. On the RFP/Bid Proposal Submittal form, below the bidder's signature space, there is a list of required attachments and notice that failure to include such, if applicable, "...shall render the proposal nonresponsive and such proposal shall be rejected". (Joint Exhibit #1, p. 10 of 10) The relevant attachments include a map with location of the facility, photograph, floor plan, authorization as agent for bidder, and release of existing leases. The RFP/Bid Proposal Submittal Form was furnished to the DOT by the Department of General Services (DGS). As permitted, DOT made some modifications to the criteria to meet the specific needs of the agency. No protests of the bid solicitation were filed by any party. The Bid Responses Four proposals were timely received at the bid opening deadline, March 4, 1991: Clayton's Realty (Petitioner) submitted two proposals, Lyell Hintz submitted one proposal, and Southeastern Investment Properties, Inc., submitted one proposal. Clayton's bid for its building at 611 Wymore Road, Winter Park ("Clayton Bldg.") offers 13,984 square feet for $1,136,200.00 for the five-year rental period and $1,398,400.00 for the option years. Some of DOT's offices are already in this building. Clayton's bid for its building at 5600 Diplomat Circle, Orlando, ("Promenade Building") offers 14,049 square feet at $965,868.75 for the 5-year rental term, and $1,229,287.50 for the option period. Both of Clayton's buildings offer space on two floors. Lyell Hintz offers 14,049 square feet at 1241 S. Orlando Avenue, Maitland. The five year rental cost is $895,623.75, and the option period rental is $1,123,920.00. All of the space is offered on a single first floor. Southeastern Investment Properties, Inc., offers 14,049 square feet in the Adlee Building at 5151 Adamson Street, Orlando, for $1,009,139.67 for the 5- year rental term and $1,288,012.32 for the option period. Southeastern contends that it is offering 100 square feet of storage space on the first floor and the remainder of space on the second floor. Committee Analysis of the Bids An evaluation committee comprised of four DOT employees met on March 6, and March 12, 1991, to evaluate the bids. Their evaluation included a visit to each site with pre-established questions. The four employees were Nancy Houston, District Five District Director for Planning and Public Transportation; Donna Sovern, Ms. Houston's Administrative Assistant; Jim Hamelin, Resident Engineer in charge of construction in District Five; and Steven J. Nunnery, Office Manager for District Five Construction. The committee had prior experience in the leasing process on only one occasion. In November 1990, this same lease #550:0209 was bid. Lyell Hintz and Southeastern were the bidders. All bids were rejected after it was discovered that Southeastern's bids included typewritten language added by the bidder and in conflict with standard requirements. No protest was filed from that agency decision. In the November bid the committee simply utilized the criteria provided in the DGS packet. Later the Committee learned that criteria could be modified by the individual agency. With this understanding, the Committee changed the criteria for the March 1991 bids to provide that space be offered on no more than two floors, rather than two buildings; that points would be awarded for offers of 100 square feet of street level storage space, rather than all space on the street level; and that accessibility to an I-4 Interchange would be an additional evaluation factor. The committee felt these criteria appropriately addressed agency need to collocate programs and share facilities, to have ground floor storage for heavy samples and equipment, and to provide easy access by field staff and others using I-4 regularly. The committee devised a methodology for awarding points to each bidder in each category described in paragraph 3, above. The methodology is stated in the minutes of the evaluation committee meeting dated March 6, 1991. For item no. 1, the committee awarded 15 points (the highest) to the lowest bid. The percentage of difference between each bid and the lowest bid was multiplied by 15 to determine the point value. Hintz received 15 points; Clayton (Promenade Building) received 14 points; Southeastern received 13 points; and Clayton (Clayton Building) received 12 points. For item no 2, the committee stated it would take into account the design and other factors in the description of this item, including the parking requirement addressed in the invitation to bid. Southeastern received the maximum, 10 points; Hintz received 8 points; and the two Clayton buildings received 6 points each. As part of the November bid process, when the agency initially intended to make the award to Southeastern, Nancy Houston's husband, an architect in private practice, prepared without charge a layout of Southeastern's building to see if Southeastern could meet DOT's needs. At Clayton's and Southeastern's requests, that layout was provided to the bidders, except for Hintz. Since Hintz' building is basically a shell, and he assured DOT he would make the renovations they needed, Ms. Houston did not feel that he needed the floor plan. After the bids were rejected in November, the layout became a public record, available to anyone upon request. However, Ms. Houston opined at hearing that they could not get a good layout that would work for the Hintz building. This contradicts Mr. Hintz' testimony that the suggested floor plan attached to the RFP could easily fit in his building. The floor plan attached to the RFP is not the same floor plan prepared by Ms. Houston's husband for the Southeastern building and the fact that Hintz' building is a shell capable of a vast variety of layouts impeaches Ms. Houston's opinion. Item no. 3 requests aggregate square footage on a single floor, with fewer points for space on two floors. The committee methodology was to give 25 points for space on one floor and "reduction given accordingly" for two floors. (Joint Exhibit #6, attachment A, page 1) Hintz and Southeastern were each granted 25 (maximum) points. Although various committee members testified that two floors should have warranted 1/2 the points, or 13, Clayton's buildings were awarded 16 points each. Southeastern is not proposing to provide all space on one floor, as it is offering storage on the first floor and office space on the second floor. The committee considered this worthy of full points, as all of the office space is on one floor. Item no. 4 is related to environmental factors such as aesthetics of the building and surrounding areas. The committee methodology states that aesthetics of the building and area would be considered along with "...the economical factor relating to the conduct of our everyday activities from and in each space proposed." (Joint Exhibit #6, Attachment A) Southeastern was awarded 10 points (maximum); Clayton's Clayton Building and Promenade Building were awarded 6 and 8 points respectively; and Hintz was awarded 3 points. Item no. 5 relates to provision of 100 square feet of storage on the street level. The committee methodology provides that full ten points will be awarded if this is met; if not, the score would be "adjusted accordingly". Each bid was awarded the full 10 points. The committee members learned that Southeastern was willing to provide street level storage when they made their site visit and inquired. The space was not described in Southeastern's written proposal. Item no. 11 relates to rental cost for the option period. The methodology adopted by the committee for this item is the same as for item no. Hintz, the lowest bidder for the option term, received 15 points; Clayton's Promenade Building received 14 points; Southeastern received 13 points; and the Clayton Building received 12 points. Item no. 12, accessibility to an I-4 Interchange, is worth 15 points maximum. For its methodology the committee devised a formula of granting the closest building a full 15 points. The I-4/Lee Road interchange was selected as the reference hub. The Clayton Building, .2 miles from the interchange, was given 15 points. Southeastern's building .6 miles away, three times as far, was given 1/3 value, 5 points; the Promenade Building, .4 miles away, or twice as far, was given 1/2 full value, or 7.5, rounded to 8 points; and Hintz' building, 2 miles away, or 10 times as far, was given 1.5 points, rounded to 2. The total values thus awarded by the committee were: 86 points to Southeastern; 78 points to Hintz; 77 points to Clayton (Clayton Bldg.); and 76 points to Clayton (Promenade Bldg.). The committee, after meeting on March 6th and making its awards, decided to meet again on March 12th, after obtaining more information on phone service, zoning regulations, crime, and bidder's previous experience in renovations. Although some additional information was obtained and the committee did meet again, it determined that the additional information (not clearly related to any of the seven criteria above) did not warrant changing any of the scores. The committee recommended award of the lease to Southeastern. Southeastern's Bid Allegedly Defective Southeastern's bid is signed by Gilmore E. Daniel, Vice President of Southeastern Investment Properties, Inc., as agent for the owner, Cynwyd Investments, a partnership which operates under about 150 different partnerships. The building in issue is owned by an entity designated "Adlee Building, Cynwyd Investments General Partnership". Attached to Southeastern's bid is a letter on Cynwyd Investments letterhead, dated February 7, 1991, addressed to Mr. Gil Daniel, re: Adlee Building, 5151 Adamson Street, Orlando, Florida, stating: As leasing and managing agent for the above captioned property, you are hereby authorized to negotiate on our behalf with the State of Florida in order to procure the Department of Transportation as a tenant in our building. (Joint Exhibit #5) The letter is signed by Stephen Cravitz, CSM. Although the language of the letter is inartful (the agent was not "negotiating" a lease), the intent is plain on its face that the agent procure a lease. This is sufficient to convey authority for Gil Daniel to act on behalf of the owner. The requirement of the RFP, paragraph 6.A. is met. (see paragraph 5, above) There are several tenants currently occupying space proposed to be leased to DOT under lease no. 550:0209. There are three "agreements" attached to Southeastern's bid proposal for three tenants. Each agreement provides the tenant will move by April 15, 1991 "...contingent upon the landlord being the successful bidder for the State of Florida Department of Transportation lease no. 550:0209, and having an executed lease with the State." (Joint Exhibit #5) The tenants have not moved, but neither has the contingency been satisfied; and when or if it is, the tenants will move. These agreements are sufficient "release" to meet the requirements of RFP paragraph 6.A. The remaining tenant does not have a lease. Clayton's Bid Allegedly Defective Clayton's bids did not include any releases from tenants. There is a tenant currently in part of the space offered in the Clayton Building. There is also a lease agreement dated August 28, 1989, between the Claytons and Canam Steel Corporation describing a lease term of three years and termination date of September 14, 1992. Edward Fielding, Jr. is Director of Operations in the Leasing Department for Charles and Malcolm Clayton. He is well aware of the requirements for state leasing as he and the Claytons have been involved for several years in leasing space to state agencies. Canam Steel Corporation provided a letter in April 26, 1990, stating that it is closing its Orlando operation and requesting that its lease be terminated. It still occupies the space, but Edward Fielding is assured that it wishes to leave, and will do so immediately upon approval by Clayton. The lease and release was not included with the bid packet, as Fielding properly determined that it was no longer binding on the landlord. The Clayton Building bid does not violate the requirement of RFP, Paragraph 6.A. F. Alleged Bias of the Committee in Favor of Southeastern and Improper Award of Points Hintz and Clayton contend that the bid process was thoroughly tainted with a bias in favor of an award to Southeastern. Clayton did not respond to the November bid; Hintz did, and did not protest the earlier process, although he apparently brought to DOT's attention the language added to Southeastern's bid response that led to the rejection of all bids and reinitiation of the process. The committee changed its evaluation criteria when it learned that DGS's form criteria are not binding on the agency. The committee's alterations and addition of the I-4 accessibility requirement were intended to better meet the specific needs of the programs that would be using the space. The changes did not specifically benefit Southeastern; it was neither the closest nor next closest building to the I-4 interchange. For those criteria which could be objectively quantified, such as rental rate and proximity to I-4, the committee attempted in good faith to devise formulae. That the point spread for the I-4 criteria was substantially wider than for rental rates does not invalidate those formulae. For those criteria requiring a subjective analysis, the conformance/design and environmental factors, Petitioner and Hintz failed to prove the committee's point awards were patently wrong or fraudulent. One committee member, James Hamelin, admitted that Clayton should have received 13, rather than 16 points for providing space on more than one floor, but that error, if it indeed was an error, inured to the benefit of Petitioner and made no impact on Hintz, the next highest scorer. None of the floor plans presented by the bidders with their proposals are attached to the exhibits received in evidence, and those floor plans are not part of the record in this proceeding. One committee member, Donna Sovern, admitted that all of the square footage proposed by Southeastern was initially on the second floor. When the site visit was made and the committee discussed the space, Southeastern offered 100 square feet of storage on the first floor. (Transcript, pp 200-201) Because of this, Southeastern was awarded the full 10 points for Item No. 5, requiring 100 square feet of street-level secured storage. Allowing Southeastern to change its bid thus provided an advantage of 10 additional points. Assuming that the change was appropriate, Southeastern should not have also received the full 25 points for Item No. 3, provision of aggregate square footage on a single floor, since the remainder of its space is on the second floor. The award of points in these two items by the committee is inconsistent and erroneous. Page 4 of 10 of the RFP describes the space to be included in the 13,640 square feet to be leased. The description includes storage areas. (Joint Exhibit #1) The bidders were on notice that "aggregate" square footage includes storage space. The total number of points awarded to Southeastern must be reduced by either 10 (the after-the-fact storage space on the first floor) or 9 (the difference between the full 25 points and 16, the points awarded to Clayton for space on two floors). This results in a total of either 76 or 77 points for Southeastern. In either case, Hintz becomes the highest scorer, and Clayton and Southeastern are tied.
Recommendation Based on the foregoing, it is hereby, RECOMMENDED: That the agency enter its Final Order awarding lease no. 550:0209 to Lyell Hintz. DONE AND RECOMMENDED this 12th day of June, 1991, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of June, 1991. APPENDIX TO RECOMMENDED ORDER The following constitute specific rulings on the findings of fact proposed by the parties: Petitioner's Proposed Findings Adopted in paragraphs 1 and 7. - 5. Adopted in paragraph 11. Adopted in paragraph 20. Adopted in paragraph 31. Adopted in summary in paragraph 18. Rejected as immaterial. and 11. Adopted in part in paragraph 5, otherwise rejected as immaterial. Southeastern's name is typewritten. Rejected as immaterial. Adopted in part in paragraph 31, otherwise rejected as immaterial. and 15. Adopted in part in paragraph 33, otherwise rejected as immaterial. Adopted in paragraphs 17 and 18. Rejected as immaterial and irrelevant. Adopted in paragraph 19. Rejected as immaterial. Adopted in part in paragraphs 20 and 27, otherwise rejected as unnecessary. Rejected as unnecessary. Adopted in substance in paragraphs 21, 26 and 27. Rejected as unnecessary. Adopted in paragraph 37. Adopted in part in paragraph 29, otherwise rejected as irrelevant as points were not awarded or subtracted for the additional factors. Rejected as irrelevant. Lyell Hintz' Proposed Findings Adopted in paragraphs 1 and 2. Adopted in paragraph 11. Adopted in paragraphs 13, 15, 16 and 21. Adopted in paragraph 3. Adopted in paragraphs 17 and 18. Adopted in paragraph 5. Adopted in paragraph 8. Rejected as unnecessary. Adopted in paragraphs 31 and 32. - 11. Rejected as immaterial and contrary to the weight of evidence. The letter attached to the bid was sufficient authority. 12. Rejected as contrary to the weight of evidence. 13. and 14. 15. Adopted Adopted in in paragraph 25. paragraphs 3 and 25. 16. Adopted in paragraph 38. 17. - 21. Adopted in paragraphs 3 and 22. 22. Rejected as argument rather than finding of fact. 23. Rejected as immaterial and unsupported by the evidence. 24. Adopted in paragraph 3. 25. - 34. Adopted in summary in paragraphs 23, 14 and 16. 35. and 36. Adopted in paragraph 38. Adopted in paragraphs 3 and 24. - 50. Rejected as immaterial. According to the evidence these factors did not change the committee's evaluation. 51. - 53. Rejected as immaterial and, as to the DGS requirement, unsupported by the record. Respondent and Southeastern's Proposed Findings Adopted in paragraph 1. Adopted in paragraph 9. Adopted in paragraph 11. Adopted in paragraph 10. Adopted in paragraph 17. Adopted in paragraphs 18 and 19. Adopted in paragraph 3. Adopted in part in paragraph 3, otherwise unnecessary. Adopted in paragraph 23. Rejected as unnecessary. Adopted in paragraph 25. Adopted in paragraph 19. Adopted in paragraph 27. Adopted in paragraph 3. Adopted in paragraph 28. Adopted in paragraph 24. Rejected as contrary to the evidence, specifically the RFP which unambiguously included all storage and office space in the "aggregate." - 19. Rejected as irrelevant or unsupported by the record. Adopted in paragraph 31. Adopted in paragraph 33. Adopted in part in paragraph 34, but the letter requesting its lease be terminated is sufficient release. Adopted in part in paragraph 12. Rejected as unnecessary. COPIES FURNISHED: Marvin L. Beaman, Jr., Esquire 605 North Wymore Road Winter Park, FL 32789 Wings L. Benton, Esquire P. O. Box 5676 Tallahassee, FL 32314-5676 Susan P. Stephens, Esquire Dept. of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 Kenneth M. Meer, Esquire 423 Country Club Drive Winter Park, FL 32789 Ben G. Watts, Secretary Attn: Eleanor F. Turner, M.S. #58 Dept. of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458 Thornton J. Williams, General Counsel Dept. of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458