Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made: In January of 1994, FDOT issued an Invitation to Bid ("ITB") for contracts FE2494Z1 and FE2494Z2 to provide storm shutters for the FDOT facilities in Zones 1 and 2 of the Florida Turnpike. The ITB was entitled "Storm Shutters, Removable, Manufacture, Furnish and Install." Prospective bidders for the contracts were provided with a packet which included General Conditions, Special Conditions, Specifications and General Special Provisions. The General Conditions set forth the procedures for submitting and opening the bids. The Specifications called for custom-sized removable storm shutters and detailed the materials and installation procedures that were required. The bid package contained the following pertinent language in the Special Conditions, Section 1.0, entitled "Description", and in the Specifications, Section 1.0, entitled "Scope of Work": Work under this contract consists of providing all labor, materials, equipment, tools and incidentals necessary to manufacture, furnish and install galvanized steel storm panels and accessories for all of Zone 1 & Zone 2 buildings and locations as identified in the building listing listings document, see Exhibit "A" Zone 1 & Exhibit "A" Zone 2. The bid package contained the following pertinent language in Special Conditions Section 8.1, entitled "Required Documents": Bidders are required to complete and return the State of Florida "Invitation to Bid" form as well as the bid sheet(s). These forms must be signed by a representative who is authorized to contractually bind the bidder. All bid sheets and the "Invitation to Bid" form must be executed and submitted in a sealed envelope. At a mandatory pre-bid conference on February 17, 1994, the Department's representatives were available to answer questions regarding the bid package. During the pre-bid conference, John Vecchio of the Department orally advised the prospective bidders that they should return the whole bid package, including the specifications, when they submitted their bid. No written amendment to this effect was issued. The bids were opened on March 3, 1994 in Fort Lauderdale. Bids were received for each contract from at least three bidders, including Accurate and Hurst. The apparent low bidder for both contracts was Broward Hurricane Panel Co. ("Broward"). Prior to the bids being posted on March 28, 1994, Broward's bid was determined to be nonresponsive and Broward was therefore disqualified. After Broward was disqualified, Accurate was the apparent low qualified bidder for Zone 2 and Hurst was the apparent low qualified bidder for Zone 1. Hurst's bid for the contract for Zone 2 was $85,000. Its bid for the Contract for Zone 1 was $36,000. Accurate's bids for the contracts were $84,854.82 and $36,287.16, respectively. Hurst was awarded the contract for Zone 1 and that decision has not been challenged. At the same time the Department announced the award of the Contract for Zone 1 to Hurst, the Department announced its intent to award the contract for Zone 2 to Accurate. Hurst timely filed a notice of protest and a formal written protest of the proposed award of the contract for Zone 2 to Accurate. Initially, FDOT raised as a defense that Hurst had not posted a protest bond as required by Section 287.042(2)(c), Florida Statutes. At the hearing in this matter, FDOT conceded that Hurst had subsequently posted a protest bond which had been accepted by FDOT. Hurst contends that Accurate's bid should have been deemed nonresponsive because Accurate does not have the ability to "manufacture" the specified product in its own facility. The 2 inch corrugated shutter required by the ITB has to be shaped on a special type of machine that rolls, presses and forms the metal. Hurst owns and maintains at its Opa-Locka facility a rolling mill capable of forming the panels to the bid specifications. Accurate is in the business of supplying the types of products sought by the ITB in this case. However, Accurate does not own the kind of machine necessary to shape the metal. The evidence established that for many years, Accurate has had a continuing business relationship with a local subcontractor, Shutter Express, that rolls, presses and forms raw material supplied by Accurate in accordance with Accurate's specifications. Shutter Express has the capability of fabricating shutters with a 2 inch corrugation in accordance with the ITB. Accurate is equipped to attach the headers and sills, drill the necessary holes, complete the assembly and install the final product. The ITB in this case did not preclude subcontracting any or all of the work specified. While the description of the work in the ITB includes the term "manufacture", this reference should not be read to mean that only those companies that were able to fabricate the entire product at their own facility could properly respond to the ITB. There is no logical justification for such a narrow interpretation. Only a few companies have the ability to completely fabricate the shutters on their own property. At the prebid conference, there was discussion amongst the prospective bidders about subcontracting the fabrication work and the FDOT representatives did not raise any objections to such an arrangement. It was widely understood by the parties present at the pre-bid conference that the Department was not interpreting the ITB in the restrictive manner now urged by Hurst. Such a reading of the ITB would have precluded from the bidding process a number of companies such as Accurate that routinely supply and install shutters. Hurst also contends that the bid proposal submitted by Accurate should be deemed nonresponsive because Accurate failed to include the entire ITB with its proposal in accordance with the oral instructions at the pre-bid conference. Hurst's proposals included the entire ITB. As discussed below, Accurate's proposal did not include the entire ITB. FDOT determined that all essential pages were included in Accurate's response and the evidence did not establish that this conclusion was arbitrary, capricious or fraudulent. Paragraph 6 of the General Conditions of the ITB provided: ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and affect and are inapplicable to the bid. As noted above, at the prebid conference held on February 17, 1994, an FDOT employee told all prospective bidders to return the entire bid package when making their submittals. This request that the entire bid package be returned was simply meant as a protection for the bidder to ensure that all the necessary documents referenced in Section 8.1 of the Specifications were submitted. Other than those documents referenced in Section 8.1 of the Specifications, FDOT had no interest in having the remaining portion of the ITB submitted with a proposal. Accurate's submittal contained every document required by Section 8.1 of the Specifications. Accurate's proposal did not contain pages 3 through 12, 14, 15 and 17 through 20 of the ITB, but did include pages 1 and 2, 13, 16, 21 and 22 along with a signed Form PUR 7068 and a signed acknowledgment of Addendum In other words, the submittal contained a signed and completed Bidder Acknowledgment, completed Bid Price Forms for Zones 1 and 2, a signed copy of Addendum #1, a completed copy of the Ordering Instructions, and a signed, but not notarized, statement regarding public entity crimes. 1/ In addition to the "REQUIRED DOCUMENTS," set forth in Section 8.1 of the Specifications and quoted in Findings of Fact 6 above, the ITB included Section 8.2, "PUBLIC ENTITY CRIMES STATEMENT" which provides: Any person submitting a bid or proposal in response to this invitation should execute the enclosed form PUR 7068, SWORN STATEMENT UNDER SECTION 287.133(A), FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES, including proper check(s) provided, and submit it with the bid/proposal or within 72 hours of the bid opening. Page 7 of the ITB provided in pertinent part: 10.0 BID PREFERENCE IDENTICAL TIE BIDS - Preference shall be given to businesses with drug-free workplace programs. Whenever two or more bids which are equal with respect to price, quality and service are received by the State or by any political subdivision for the procurement of commodities or contractual services, a bid received from a business that certifies that it had implemented a drug-free workplace program shall be given preference in the award process. . . . Accurate's proposal did not include a certification that it was a drug-free workplace in accordance with this provision. However, such a certification is only used by the Department as a tie-breaker. In other words, in the event of identical bids, any firm with a drug-free workplace would get preference. Since there were no tied bids in this case, certification was totally irrelevant. When the bids were opened, Mary Bailey, the contracts administrator for the Department, noticed that Accurate's submittal was thinner than the others and asked Accurate's representative, Richard Johnson, about the remaining pages. Mr. Johnson replied that the other pages were in his truck and offered to retrieve them. Ms. Bailey told him there was no need to do so. Section 10 of the General Conditions in the bid package provides as follows: As the best interest of the State may require, the right is reserved...to reject any and all bids or waive any minor irregularity or technicality in bids received... It does not appear that Accurate has obtained any competitive advantage as a result of its failure to include the entire ITB with its bid proposals. Even if the oral instructions at the pre-bid conference are deemed to have modified the ITB so that the entire bid package should have been submitted, Accurate's failure to include the entire ITB with its response should be considered a minor technicality, pursuant to Section 10 of the General Conditions cited above, that can and should be waived in evaluating the responsiveness of the bid. Similarly, the failure to have the Form PUR 7068 notarized may have rendered Accurate's bid proposals incomplete, but not necessarily nonresponsive. This oversight can be easily corrected without giving Accurate a competitive advantage.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding the bid submitted by Accurate to be responsive and dismissing the challenge filed by Hurst. DONE and ENTERED this 24th day of June 1994, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June 1994.
The Issue The issue in this case is whether the bid of Corporate Interiors, Inc. (Petitioner) is the lowest responsive bid which was received by the Pinellas County School Board (Petitioner) for stacking polypropylene and upholstered chairs for the New District Administration Building.
Findings Of Fact On or about February 27, 1990, the Respondent sought competitive bids for stacking polypropylene and upholstered chairs for the New District Administration Building. In response thereto, Respondent timely received four bids, two of which were determined to be responsive. The bid opening occurred on April 17, 1990, and Petitioner was determined to have submitted the lowest bid. However, the Petitioner's bid did not include an amount for sales tax, and on that basis alone, the Respondent indicated its intent to award this contract to another responsible bidders. There is no dispute that the Respondent does not pay sales tax on transactions involving the acquisition of furnishings for the Pinellas County School System. Nevertheless, Section 9.2.2 of the bid specifications erroneously stated that this contract would not be exempt from sales tax. The Respondent admitted at hearing that under Section 5.3.1 of its bid instructions, it should hake waived the Petitioner's failure to include sales tax in the bib amount since this is inapplicable to this acquisition. The Respondent, in effect, concedes error in its previous notice of intent to award this contract to another bidder, and does not contest the Petitioner's claim that it submitted the lowest responsive bid for stacking chairs.
Recommendation Based on the foregoing, it is recommended that the Respondent enter a Final Order awarding the contract for stacking chairs for the New District Administration Building to Petitioner. DONE AND ENTERED this 8th day of June, 1990, in Tallahassee, Leon County, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of June, 1990. APPENDIX DOAH CASE NO. 90-2982 BID Petitioner filed a letter, but no proposed findings of fact upon which a ruling could be made. Rulings on Respondent's Proposed Findings of Fact: Adopted in Finding 1. Adopted in Finding 3. Adopted in Finding 1. 4-6. Adopted in part in Finding 2, but otherwise Rejected as unnecessary. Adopted in Finding 3. Adopted in part in Finding 2, but otherwise Rejected as unnecessary. COPIES FURNISHED: Allen D. Zimmerman, President Corporate Interiors, Inc. 1090 Kapp Drive Clearwater, FL 34625 Bruce P. Taylor, Esquire P. O. Box 4688 Clearwater, FL 34618-4688 Dr. Scott N. Rose Superintendent P. O. Box 4688 Clearwater, FL 34618
Findings Of Fact On or about December 29, 1981, the College solicited sealed bids for construction of alterations and additions to the Technical and Gymnasium Buildings located on its campus in Madison, Florida. In response, seven general contractors submitted bids. (P-1, P-2, P-3.) Bids were publicly opened on February 9, 1982. Griffin Construction, with a bid of $536,575, was the apparent low bidder; the second lowest bidder was Long Contractors, with a bid of $539,512. (Testimony of Griffin, Sims, Rutherford; P-3, P-4, P-5.) After the low bid was identified, Tom McClanahan, representing Long Contractors, asked that the subcontractor list accompanying the low bid be opened. Griffin Construction's subcontractor list was then opened. McClanahan asked if the license and charter numbers of the subcontractors were listed. 2/ Upon learning that these numbers were not included on Griffin Construction's subcontractor list, McClanahan protested. (Testimony of Sims, Rutherford, Griffin.) At its February 15, 1982, meeting, the College District Board of Trustees ("Board") rejected the low bid of Griffin Construction on the sole ground that the omission of subcontractor license and charter numbers constituted a failure to comply with the conditions of the bid documents. 3/ The Board then voted to award the contract to Long Contractors, the second lowest bidder, on the ground that it was the lowest bid conforming to the bid documents. In so doing, the Board followed the College president's recommendation--a recommendation based on his belief that the non-complying bid must be rejected, that it did not involve a matter of Board discretion. (Testimony of Sims, Rutherford, Griffin; Stipulation of Parties; P-41.) The bid specifications contain instructions to bidders requiring "each Bidder . . . [to] submit with his proposal a list of the subcontractors who will perform the work . . . as indicated by the `List of Subcontractors' form." (P-1, P-2.) The instructions further provide: The applicable subcontractor license registration or certification number must be noted on the bid opposite his name, and in the event that the subcontractor is a corporation, his State Corporate Charter number shall also be noted. If the subcontractor is an out of state firm, their Charter number with the Secretary of State to do business in the State of Florida should also be noted. The "Listing of Subcontractors" form provided with the specifications contains column headings for the names and addresses of the subcontractors but does not contain a separate heading for the requested license or corporate charter numbers. 4/ The form states that the subcontractor list "is an integral part of the bid." (P-1, P-2.) The bid instructions further require bidders to evaluate and determine the qualifications of their listed subcontractors. The bidder shall have determined to his own complete satisfaction that a listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this agreement and is qualified both technically and financially to perform that pertinent phase of the work for which he is listed. (P-1, P-2.) The bid documents expressly reserve to the College the right "to reject any or all bids, and to waive informalities." (P-1 P-2.) No bidder correctly listed the required license and corporate charter numbers on its "Listing of Subcontractors" form. Griffin Construction. Griffin failed to include any license or corporate charter numbers. However, by subsequent letters dated February 9 and February 18, 1982, and at hearing, it supplied the required subcontractor license and charter numbers. Long Contractors. Long listed for its roofing subcontractor a sheet metal registration number, not the required roofing license number. [A sheet metal registration does not qualify a contractor for roofing work. See, 489.105, 489.113, Fla. Stat. (1981).] For its electrical subcontractor, Long omitted the prefix, "ER" from the listed number. For its plumbing subcontractor, Long listed a mechanical registration number instead of the required plumbing certification or registration number. [A mechanical registration does not qualify a contractor to perform plumbing work. See, 489.105, 489.113, supra.] Of the four areas requiring state licenses--roofing, heating and air conditioning, electrical, and plumbing--Long listed correctly only the registration number for its heating and air conditioning subcontractor. Long incorrectly listed No. FO6962 as the corporate number of Gandy Enterprises, its painting subcontractor. This is the number of a related corporation, Industrial Coatings, Inc. Remaining Bidders. Of the five other general contractors submitting bids, two-- Richard Walker Construction Company and GRC Contracting, Inc.--omitted all subcontractor license and charter numbers. The other three bidders failed to completely list all the required numbers. (Testimony of Rutherford; P-11, P-12, P-13, P-14, P-15, P-16, P-17, P-34, P-37, R-1, R-5.) The project architect testified that the submittal of incorrect or incomplete subcontractor license and charter numbers was a deficiency which a bidder should be allowed to cure after bid opening. But the failure to submit any required "number" was a deficiency which, in his opinion, could not be similarly corrected. He failed, however, to supply a reasonable basis for drawing such a distinction. Therefore, his opinion on this question is given little weight. 5/ (Testimony of Rutherford.) Subcontractor license and charter numbers are readily obtainable and can be verified by contacting the pertinent state agency--the Florida Department of Professional Regulation, Construction Industry Licensing Board, or the Florida Department of State. (Testimony of Griffin, Rutherford; P-32, P-33, P- 34, P-35, P-36, P-37.) The project architect, William Rutherford, routinely requires the listing of subcontractor license and charter numbers on bids for public construction projects. The main purpose it serves is that it would enable him to identify the listed contractor, since sometimes subcontractors have similar business names. Although if he was uncertain about the qualifications of a subcontractor, he would ordinarily question the general contractor. (Testimony of Rutherford.) Although Mr. Rutherford has customarily required the listing of subcontractor "numbers" on public projects, he has never made any use of those numbers in the past. (Testimony of Rutherford.) The general contractor who is awarded the contract is responsible to Mr. Rutherford and the College for construction of the project in accordance with the bid specifications. If, after bid opening, a listed subcontractor is unable to perform, Mr. Rutherford would ordinarily arrange for substitution of a new subcontractor acceptable to the general contractor and owner. (Testimony of Rutherford.) Griffin Construction's failure to list the license and charter numbers of its listed subcontractors, and its subsequent curing of that failure, did not affect the amount of its bid 6/ by giving it an advantage or benefit not enjoyed by other bidders. The bid omission did not allow Griffin Construction the opportunity to change any material element of its bid after bid opening. The inclusion or exclusion of subcontractor "numbers" at bid opening does not affect the ability of a contractors to obtain the required bond, the quality of bidding general contractors, the quality of listed subcontractors, the quality of work performed, or any material feature of the competitive bidding process. (Testimony of Griffin, Rutherford.)
Recommendation Based on the foregoing, it is RECOMMENDED: That the construction contract in question be awarded to Vick Griffin Construction Company, the lowest responsible bidder. DONE AND RECOMMENDED this 29th day of April, 1982, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1982.
Findings Of Fact On February 28, 1990, Respondent issued an invitation to bid (ITB) on a construction project referred to as Florida Atlantic University Modulars. The ITB required a base bid and bids on five alternates to the base project. Each bidder was instructed that it must bid on the base project and on each alternate for its bid proposal to be considered responsive. On March 19, 1990, Addendum 1 to the ITB was issued to all prospective bidders. This was an informational addendum and advised the date, time, and location of the posting of the award recommendation. Addendum 1 was not required to be returned by the bidder as a part of the response to the ITB. On March 21, 1990, Addendum 2 to the ITB was issued to all prospective bidders. This was also an informational addendum and advised as to a non- mandatory, pre-bid conference to be held March 27, 1990. Addendum 2 was not required to be returned by the bidder as a part of the response to the ITB. On March 30, 1990, Addendum 3 to the ITB was issued to all prospective bidders. This addendum advised that the date and time for the bid opening had been changed to April 9, 1990, at 2:00 p.m. Addendum 3 also contained modifications, explanations and corrections to the original drawings and specifications which impacted the cost and scope of the project. Immediately above the signature line on the cover page of Addendum 3 was the following: This document must be returned in it's [sic] entirety with the bid. Please sign below to verify that you have read and understand all the changes. Item 2 on page ADD-1 of Addendum 3 required each bidder to submit its per unit price structure with its response to the ITB and provided, in pertinent part, as follows: ... The unit price shall not be included in Base Bid. Submit a separate sheet with bid package. The following instructions are given in Paragraph 1(c) of the Instructions to Bidder: NO ERASURES ARE PERMITTED. If a correction is necessary, draw a single line through the entered figure and enter the corrected figure above it. Corrections must be initialed by the person signing the bid. Any illegible entries, pencil bids or corrections not initialed will not be tabulated. The instructions are repeated in Paragraph 1 of the General Conditions of the ITB: EXECUTION OF BID: ... No erasures are permitted. If a correction is necessary, draw a single line through the entered figure and enter the corrected figure above it. Corrections must be initialed by the person signing the bid. Any illegible entries, pencil bids, or corrections not initialed will not be tabulated. The following is contained as part of the Instructions to Bidder: Failure to complete, sign, seal and return the required documents will result in rejection of your bid. Any questions should be directed to Susan Kuzenka, (305) 761-7460, Purchasing Department, Broward Community College. (Emphasis in the original.) Paragraph 8 of the General Conditions portion of the bid package provided, in pertinent part, as follows: 8. AWARDS. As the best interest of Broward Community College may require, the right is reserved to reject any and all bids and to waive any irregularity in bids received ... On April 9, 1990, Petitioner submitted a bid to Respondent in response to the ITB. Petitioner had received the complete bid package, including all instructions and addenda to the bid package. At the pre-bid conference held March 27, 1990, an employee of Respondent emphasized to the attendees that it was necessary for the bidders to return Addendum 3 in its entirety. Petitioner did not attend the non-mandatory, pre-bid conference. The base bid submitted by Petitioner was $1,085,790.00. The base bid of Double E Construction Co., the next low bidder and the bidder to whom Respondent intends to award the contract, was $1,113,300.00. Petitioner's bid for each of the alternates was lower than that of Double E Construction Co. Petitioner failed to return the entire Addendum 3 as instructed. On page four of the bid package Petitioner acknowledged that it had received Addendum 3, and it signed and returned the cover sheet to Addendum 3 under the language quoted in the foregoing Paragraph 4. Respondent considered this an important requirement because it wanted to prevent a bidder from later claiming that it had not received Addendum 3 or that it had received information different than that contained in Addendum 3. Petitioner made a correction to its bid for Alternate Number 3 found on page 5 of 13 of Petitioner's bid. Petitioner's bid for this alternate was $88,000. In the space for the written amount of the bid, Petitioner's president inserted by hand the words "Eighty-eight Thousand". In the space for the numerical insertion of the bid he initially wrote the sum $125,000 (which was the amount of Petitioner's bid for Alternate 4). He struck through the figure $125,000 and wrote above the stricken figure the figure $88,000. He did not initial his change. Respondent has never accepted changes to price quotations which were not initialed because it is concerned that uninitialed corrections on bids may result in challenges to the integrity of the bid process and may expose its staff to charges of collusion from a disgruntled bidder. Pioneer did not include a unit price structure in its bid as required by Addendum 3. The unit price structure is an informational item that is not separately considered by Respondent to determine the lowest bidder on this project. On April 6, 1990, Petitioner's estimator on this bid telephoned Susan Kuzenka regarding the unit price structure sheet to inquire as to the format that should be followed in submitting the unit price structure. Ms. Kuzenka is named in the Instructions to Bidder as the person in Respondent's purchasing department to whom questions about the bid process should be directed. Petitioner's estimator was told that the unit prices would be required to be submitted by the successful bidder at the pre-construction meeting after the bids were opened, but that the unit price structure need not be submitted with the bid. Petitioner's president verified this information on April 9, 1990, prior to the bid opening, during a telephone conference with the project engineer employed by Respondent for this project. In reliance on the information that was supplied by Respondent's agents, Petitioner did not submit its unit price structure sheet with its bid. Following its examination of all bids, the bid of Petitioner was disqualified on three grounds. The first reason cited by Respondent was that Petitioner failed to return the entire Addendum (3) as required. The second reason was that Petitioner did not initial a correction to a quoted price figure. The third reason was that Petitioner did not include the unit price structure as required in Addendum (3). Petitioner thereafter timely protested its disqualification and the intended award of the contract to Double E Construction Co. Petitioner contends that the reasons cited by Respondent for its disqualification are minor irregularities that should be waived by Respondent. Additionally, Petitioner contends that the third reason should not disqualify it because Petitioner acted in reliance upon the instructions of Respondent's agents in not submitting the unit price structure along with its bid package. This proceeding followed.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Broward Community College, enter a final order which denies the bid protest of Petitioner, Pioneer Contracting, Inc. DONE AND ENTERED this 29th day of June, 1990, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1990. APPENDIX TO THE RECOMMENDED ORDER The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioners. The proposed findings of fact in paragraphs 1, 2. 6 and 7 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 3 are rejected as being subordinate to the findings made in paragraph 10. The proposed findings of fact in paragraph 4 are adopted in part by the Recommended Order. The proposed findings in the last sentence of paragraph 4 are rejected as being unnecessary to the conclusions reached because of the clear instructions contained in Addendum 3. The proposed findings of fact in paragraph 5 are adopted in part by the Recommended Order. The proposed findings in the last two sentences of paragraph 5 are supported by the evidence, but are not adopted as findings of fact because they are unnecessary to the conclusions reached. All proposed findings of fact submitted on behalf of the Respondent are adopted in material part. Copies furnished: Eric L. Dauber, Esquire Beyer & Dauber Suite 5300 2101 W. Commercial Boulevard Ft. Lauderdale, Florida 33309 James D. Camp III, Counsel Broward Community College Fort Lauderdale Center 225 East Las Olas Blvd. Fort Lauderdale, Florida 33301 Janet Rickenbacker Director of Purchasing Broward Community College Fort Lauderdale Center 225 East Las Olas Blvd. Fort Lauderdale, Florida 33301
The Issue Whether the Petitioner was the lowest responsive bidder in Bid No. 88-030, and therefore entitled to the contract award.
Findings Of Fact The invitation to bid in Bid No. 88-030 contains specifications for two separate pieces of equipment which are to be used in the Respondent's print shop. These two items are: a) an offset duplicator with a "swing away," second color printing unit, and b) a camera/platemaker capable of processing silver masters. The Petitioner timely submitted bids on both items. On June 14, 1988, when the bids were opened, the Petitioner was the low bidder upon the equipment. The Petitioner's bids were disqualified by the Respondent, because the equipment offered did not meet the minimum specifications set forth in the bidding documents. A comparison of the minimum specifications for the duplicator and the manufacturer's specifications for the A.B. Dick #9850 duplicator that was bid by the Petitioner reveals the following differences: The specifications require the bidder to provide the Respondent with a duplicator that contains a 1 horsepower, D.C., drive motor. The A. B. Dick #9850 duplicator contains a 3/4 horsepower, A.C., drive motor. A 1/2 horsepower pump motor is required by the specifications. The literature attached to the Petitioner's bid does not reveal whether the A.B. Dick #9850 duplicator contains a pump motor. During the administrative hearing, Charles K. Hill testified that the A. B. Dick #9850 duplicator does have a pump motor. However, the size of the pump motor was not given. The specifications require a conveyor board with a jogging registration system. The A.B. Dick #9850 duplicator does not contain that type of paper feed system. Instead, the Petitioner's duplicator has a direct feed with a registration board. The paper travels only one-half of an inch in the duplicator so a conveyor board and joggers are not needed. Grippers accurately control the paper during the short travel distance. The Respondent specifically chose to require a conveyor board with a jogging registration system on a duplicator because the Respondent wants to have all of the controlling mechanisms it is possible to obtain on a duplicator within a certain price range. The conveyor board with a jogging registration system is a feature that is provided on duplicators in addition to a gripper margin adjustment and feeder bar system. The failure to provide this additional system is an omission as opposed to an alternate provision of a comparable system. The Petitioner submitted a bid upon a duplicator that did not conform in all material respects to the minimum bid specifications. The Petitioner' substituted a less expensive product with fewer features that ran on a different electrical current than the product sought in the invitation to bid. The comparison of the minimum specifications for the camera/platemaker and the A.B. Dick #148 camera manufacturer's specifications reveals the following differences: The specifications state that a reduction range of 60 percent and a magnification range of 125 percent are required. The A. B. Dick #148 camera has a reduction range of 64 percent and a magnification range of 105 percent. The specifications require a copy size of 20 1/2" x 33". The A. B. Dick #148 camera has a copy size of 23 1/2" x 26". The Petitioner submitted a bid upon a camera that did not conform in all material respects to the minimum bid specifications. The Respondent seeks a camera with a greater, and consequently more expensive, resizing range than the one bid upon by the Petitioner. The invitation to bid was liberal enough in its minimum bid specifications to allow competitive responsive bidding on comparable products from various vendors for the equipment and features sought by the Respondent. The bid posted by the Respondent from Standard Graphics, Inc., the apparent responsive low bidder, conforms in all material respects to the invitation to bid.
Findings Of Fact On August 31, 1994, the Respondent received and opened bids for its Project No. HSMV 92044000, Repairs, Art Sutton Drivers' License Office, Miami, Florida (the Project). The bid specification documents (the Specifications) for the Project included requirements for a Base Bid and for specific alternate proposals with respect to three defined items of alternate work. Section 01100 of the Specifications stated that "[a]ll Alternates described in this Section are required to be reflected on the Bid Form as submitted by the bidder." Part 2 of that section provided: ALTERNATE NO. 1 A. Provide a deductive price to the base bid for the removal of existing window units and the installation of new units as indicated in plans and specification Section 08520. ALTERNATE NO. 2 A. Provide a deductive price to the base bid for the provision of communications conductors see specification Section 16400. ALTERNATE No. 3 A. Provide a deductive price to the base bid for the installation of all landscape materials as indicated on plans and as per specification Section 02960. Also included in the Specifications as Exhibit 4 was a Proposal Form. The Specifications required each bidder to submit this form in triplicate on the bidder's letterhead. With respect to alternates, the Proposal Form required: With the foregoing as a Base Bid, the following costs of alternate proposals are submitted in accordance with the drawings and specifications. Alternate No. 1 Add or Deduct $ Alternate No. 2 Add or Deduct $ Alternate No. 3 Add or Deduct $ The Respondent's architect received four bids on August 31, 1994. As recorded on the Bid Tabulation and Notice of Award Recommendation, three bidders provided specific prices for the three alternates, as well as a Base Bid. The Bid Tabulation shows that two bidders provided specific prices for the three alternates and included the alternate prices in their Base Bids. The Petitioner provided specific prices for the three alternates, but excluded the alternate prices from its Base Bid. The fourth bidder provided a specific price for only one alternate and excluded that alternate price from its Base Bid. (The fourth bidder was disqualified as non-responsive for failing to submit prices on all three alternates.) In pertinent part, the Petitioner's proposal read: With the foregoing as a Base Bid, the following costs of alternate proposals are submitted in accordance with the drawings and specifications: Alternate No. 1 Add or Deduct . . . $4,400.00 Alternate No. 2 Add or Deduct . . . $1,158.00 Alternate No. 3 Add or Deduct . . . $2,084.00 These Alternates were in addition to the Petitioner's Base bid of $204,322.00. The proposal form submitted by the Petitioner comports with Exhibit 4 to the Specifications, which was the mandatory Proposal Form. On August 31, 1994, William Phillip Austin, Peitioner's President, wrote the architect: Per our telephone conversation this date regard- ing the confusion relating to the Add/Deduct for Alternates 1, 2 and 3 for the above project, please be advised that our base bid did not include the work described in the Alternates. As stated if you want work described in Alternates 1, 2 and 3, you must add the cost to our base bid. The base bid including Alternates 1, 2 and 3 would, therefore, be $211,964.00. If we can provide additional information, please do not hesitate to contact us. The Respondent's architect completed and submitted the bid Tabulation and Notice of Award Recommendation to the Respondent in early September. The document clearly discloses the amounts of each bidder's Base Bid and Alternate proposals. Using plus (+) and minus (-) signs, the Bid Tabulation further shows each bidder's method of calculation. The record is devoid of evidence that the Respondent had any problem in evaluating the bids and identifying the lowest bidder. The Petitioner was the lowest bidder on any combination of base bid plus or minus any or all alternates. Subsequently the Petitioner received a NOTICE OF AWARD RECOMMENDATION dated October 4, 1994. The Notice informed the Petitioner that the Respondent "has recommended that the contract be awarded to your firm in the total amount of $211,964.00, accepting the Base Bid and Alternates #1, #2 & #3. The Administrator of Contracts Design and Permitting, Division of Building Construction, Department of Management Services, State of Florida will consider this recommendation." Larry R. Coleman, Construction Projects Administrator, signed the letter. The Petitioner acknowledged receipt. A representative of the second lowest bidder, Kalex Construction, then contacted the Respondent, complaining of the Award Recommendation. The grounds for the Kalex complaint are not in the record. However, on October 14, 1994, H. R. Hough, the Respondent's Contracts Administrator, sent the Petitioner a letter "to notify you of the State's decision to reject all bids on the above referenced project due to ambiguities in the specifications." Mr. Hough's reasons for the rejection are "other than those stated by the protestor," Kalex. The Respondent's Rule 60D-5.007, Florida Administrative Code, states: Determination of Successful Bidder. All projects except where competitive bidding is waived under the provisions of Rule 60D-5.008 will be publicly bid in accordance with the provisions in the project specifications bidding documents. Award of contract will be made to the responsive bidder, determined to be qualified in accordance with the provisions herein and meeting the requirements of the bidding documents, that submits the lowest valid bid for the work. The lowest bid will be determined as follows: The lowest bid will be the bid from the responsive bidder that has submitted the lowest price for the base bid or the base bid plus the additive alternates or less the deductive alternates chosen by the Agency to be included in or excluded from the proposed contract, taken in numerical order listed in the bid documents. The order of the alternates may be selected by the Agency in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. Under the above-quoted rule, the Respondent compares bids beginning with the lowest "base bid." The Respondent is of the view that for this comparison to be fair and equal, all bidders must include the same scope of work in the "base bid." The Respondent does not interpret the above-quoted rule to allow deductive alternates from some bidders and additive alternates from others. (For reasons discussed in the Conclusions of Law which follow, the Respondent's interpretation and application of the above-quoted rule is erroneous.) The Specifications contain some ambiguous and inconsistent language regarding whether alternates should be treated as additive or deductive. The ambiguous and inconsistent language did not provide any bidder with an advantage or a disadvantage, nor did it otherwise affect the fairness of the bidding process.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Management Services issue a Final Order in this case awarding a contract for the subject project to the Petitioner. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 16th day of December 1994. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of December 1994. APPENDIX The following are my specific rulings on all proposed findings of fact submitted by all parties. Proposed findings submitted by Petitioner Paragraph 1: This is primarily a statement of position and is addressed in the Preliminary Statement. Paragraphs 2 through 10: Accepted in substance with a few unnecessary details omitted. Proposed findings submitted by Respondent Paragraphs 1 through 6: Accepted in substance. Paragraph 7: First sentence accepted in substance. Second sentence rejected as constituting a conclusion which is not warranted by the evidence. Third sentence is accepted as an accurate statement of how Respondent has been interpreting the subject rule, but is not accepted as constituting a correct interpretation of the rule. Paragraph 8: Rejected as misleading and confusing because the "scope of work" to be performed under the contract can only be determined after the Respondent decides which alternates to include and which to exclude. Paragraph 9: The first two sentences are accepted in substance. The last sentence is rejected as constituting a conclusion which is not warranted by the evidence. COPIES FURNISHED: Timothy J. Armstrong, Esquire Armstrong & Mejer Suite 1111 Douglas Centre 2600 Douglas Road Coral Gables, Florida 33134 Stephen S. Mathues, Esquire Department of General Services Knight Building, Suite 312 Koger Executive Center 2737 Centerview Drive Tallahassee, Florida 32399-0950 Paul A. Rowell, General Counsel Department of General Services Knight Building, Suite 312 Koger Executive Center 2737 Centerview Drive Tallahassee, Florida 32399-0950 William H. Lindner, Secretary Department of General Services Knight Building, Suite 307 Koger Executive Center 2737 Centerview Drive Tallahassee, Florida 32399-0950
The Issue The two major issues in this case are as follows: Was the failure of Datamaxx to submit resumes of training and maintenance personnel as required by Performance Mandatory No. 10 of the Invitation to Bid a material deviation from the Invitation to Bid such as to render Datamaxx a nonresponsive bidder? If Datamaxx was a nonresponsive bidder, must the contract be awarded to Burroughs, or must DHRS, pursuant to Section 13A-1.002(3), Florida Administrative Code, have the contract rebid, or seek single source procurement or negotiation approval from the Division of Purchasing?
Findings Of Fact Based on the admissions of the parties, on the testimony of the witnesses at the hearing, and on the exhibits received in evidence, I make the following findings of fact: For at least the past 10 years, the DHRS Data Communications Network has been maintained by Burroughs on a sole source basis. At the end of the previous Burroughs Terminal Maintenance contract with Burroughs, the Department of General Services (DOS) asked DHRS to bid the contract in lieu of sole source procurement, it being the belief of DOS that there was competition in this area. On or about September 19, 1986, DHRS published an Invitation to Bid which advised prospective bidders that sealed bids would be opened on October 20, 1986, for a contract, known as "Burroughs Terminal Maintenance" [Bid No. 86 ATM] regarding maintenance of the terminals of the DHRS Data Communications Network. The Special Conditions of the Invitation to Bid contained, among others, the following provisions: The State has established certain require- ments with respect to bids to be submitted by bidders. The use of "shall," "must" or "will" (except to indicate simple futurity) in this Invitation to Bid indicates a requirement or condition from which a material deviation may not be waived by the State. A deviation is material if, in the State's sole discretion, the deficient response is not in substantial accord with this Invitation to Bid requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the State. Material deviations cannot be waived. (at p. 1) No negotiations, decision, or actions shall be initiated or executed by the bidder as a result of any discussions with any State employee. Only those communications which are in writing from the Department's Purchasing office may be considered as a duly authorized expression on behalf of the State. Also, only communications from bidders which are signed and in writing will be recognized by the State as duly authorized expressions on behalf of the bidder. (at p. 2) All personnel performing maintenance must be trained to service the equipment covered by this contract. Training shall be completed before the individual is assigned to service the equipment covered by this contract. Training shall be provided to whatever level is necessary to ensure the individual has the required qualifications to perform satisfactory maintenance service on Burroughs equipment listed in Attachment A of this Invitation to Bid. Bidder shall submit with their bid a summary of their Burroughs training program and resumes of personnel who will be performing this training and the resumes of personnel who will be per- forming the maintenance. (at p. 8) Bidder shall certify to the State, at the time the bid is submitted, that bidder has existing established service centers staffed with personnel trained to service the equipment covered by this contract . . . In lieu of this requirement, if bidder does not have existing established service centers, liaison office, and trained personnel, and bidder submits a plan for compliance, the required certification must be given the State no later than two (2) weeks prior to the anticipated starting date of the contract as indicated in the paragraph of this document entitled Calendar of Events. Failure to comply with this requirement shall result in rejection of the bid and award of the bid to the next lowest responsive bidder. The Invitation to Bid was drafted by the Department of Health and Rehabilitative Services. The only bidders on the contract (other than no- bids) were Burroughs and Datamaxx. DHRS found Burroughs and Datamaxx both to be responsive bidders and posted their bids making them public in the recognized manner of publicizing the bidder to be awarded a bid. Both bids were found to be responsive by DHRS at the time they were made public. The Datamaxx bid was the lowest bid and the Burroughs bid was the next to lowest bid. DHRS staff recommended the contract be awarded to Datamaxx. The Datamaxx bid was approximately $784,000 less than the Burroughs bid. In its bid Datamaxx indicated that it understood and agreed to all provisions of the Invitation to Bid, specifically including those dealing with Mandatory Requirements, Verbal Instruction Procedure, Rejection of Bids, Bid Evaluation, Performance Mandatories, and Certification. Datamaxx submitted the Certification required under the terms of the Invitation to Bid and did not submit a plan for compliance with its bid. Datamaxx never requested in writing that the requirement for resumes be waived, and DHRS never advised Datamaxx in writing that it did not have to submit the resumes. Datamaxx did not submit with its bid the resumes of training and maintenance personnel required under Performance Mandatory 10 of the Invitation to Bid. Performance Mandatory No. 10 required the submission of resumes with the bid, and did not concern an event that would take place after the bid had been let. DHRS considered the requirement for resumes to be a mandatory requirement. The qualifications of the persons who would be performing the maintenance under the contract would have a potentially significant effect on the quality of the maintenance provided. Nothing could be more material to the contract than the ability of the personnel to perform that contract. The difference in the dollar amount of the bids of Burroughs and Datamaxx influenced the decision of DHRS in finding Datamaxx to be a responsive bidder. This was a major reason Datamaxx was found to be a responsive bidder. In evaluating the Datamaxx bid, DHRS went outside the material provided in the Datamaxx bid. Subsequent to the posting of bids, DHRS met with Datamaxx and advised Datamaxx that its initial submission was deficient for not including resumes with the bid, that DHRS had waived the resumes, but that in order for DHRS to continue its recommendation that the bid be awarded to Datamaxx, DHRS had to have the resumes prior to the awarding of the bid. DHRS considered it an error and a deficiency in the bid that the resumes were not furnished. Datamaxx, on November 6, 1986, advised DHRS in a letter to Charles Ray that it would submit a plan which would address, among other things, service personnel resumes by November 17, 1986. DHRS could not have considered Datamaxx's letter of November 6, 1986, in evaluating whether Datamaxx was a responsive bidder, because that letter was not received until after DHRS had already found Datamaxx to be a responsive bidder and recommended that the contract be awarded to Datamaxx. Had Datamaxx not submitted the resumes prior to November 17, 1986, DHRS staff would have recommended that the award of the contract be withdrawn. The performance the State would receive under the contract would directly depend on the qualifications of the persons performing the service and the maintenance, and the resumes would be the only source of information regarding the qualifications of the personnel.
Recommendation For all of the foregoing reasons, it is recommended that a final order be entered to the following effect: Concluding that the bid submitted by Datamaxx USA Corporation on Bid No. 86 ATM should be rejected on the grounds that it is not responsive, Concluding that the bid submitted by Burroughs Corporation should be rejected on the basis of Rule 13A-1.002(3), Florida Administrative Code, and, Providing for the agency to issue a second invitation to bid/request for proposals or take other action provided by Rule 13A-1.002(3), Florida Administrative Code. DONE AND ENTERED this 25th day of June 1987, at Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 25th day of June 1987. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 86-4460B1D The following are my specific rulings on each of the proposed findings of fact submitted by both parties: Findings proposed by Petitioner Paragraphs 1 through 19 are accepted with a few minor editorial modifications. The first two lines of paragraph 20 are rejected as redundant. The remainder of paragraph 20 is accepted. Findings proposed by Respondent Paragraphs 1 and 2 are accepted in substance. Paragraph 3 is rejected as constituting unnecessary details. Paragraphs 4 through 7 are accepted. Paragraphs 8, 9, and 10 are rejected as irrelevant. Paragraph 11 is rejected in part as irrelevant and in part as contrary to the greater weight of the evidence. Paragraph 12 is accepted. Paragraph 13 is rejected as constituting irrelevant and unnecessary details. COPIES FURNISHED: Robert L. Powell Assistant General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Room 407 Tallahassee, Florida 32399-0700 Edgar Lee Elzie, Jr., Esquire MacFarlane, Ferguson, Allison & Kelly 804 First Florida Bank Building Tallahassee, Florida 32301 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
Findings Of Fact Respondent issued an invitation to bid on March 13, 1992. Bid number SB 92-244I involved the disassembly and removal of an existing walk-in freezer and the furnishing and installation of a new walk-in freezer at Coral Sunset Elementary School. The invitations to bid provided in paragraph Y of the Special Conditions: Failure to file a specification protest within the time prescribed in Florida Statutes 120.53 3.(b) shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. (sic) Bid specifications were included in the invitations to bid issued on March 13, 1992. Twenty-three bids were solicited. There were five responses. One of the responses was submitted by Choice Restaurant Equipment, Inc. ("Choice"). Choice is a vendor for equipment manufactured by Petitioner, Nor-Lake, Inc. ("Nor-Lake"). Nor-Lake is an out-of-state corporation with manufacturer's representatives in numerous states including Florida. 4, Petitioner, CHD Marketing Group ("CHD"), is the manufacturer's representative for Nor-Lake in Florida. CHD represents no other manufacturer of the product included in the bid response. Choice is a sales agent for CHD and other manufacturer's representatives in Florida. Choice sells the products of a variety of manufacturers but is the exclusive sales agent for CHD pursuant to a verbal agency agreement. Choice timely submitted a bid for bid number SB 92-244I on April 8, 1992, prior to the bid deadline of 2:00 p.m. on the same day. The successful bidder submitted its bid by Federal Express at 4:51 p.m on April 8, 1992. Respondent's Department of Purchasing and Stores (the "Department") had stated on March 13, 1992, when the invitations to bid were issued, that bid responses must be received by the Department no later than 2:00 p.m. on April 8, 1992, at the Department's address at 3980 RCA Boulevard/Suite 8044, Palm Beach Gardens, Florida, 33410-4276. Prior to April 8, 1992, the Department relocated to a new facility at 3326 Forest Hill Boulevard, West Palm Beach, Florida. The new address was posted at the old location and Department representatives were present at the old address to accept walk-in bids. Federal Express first attempted to deliver the successful bid at the Department's old address at 10:30 a.m. on April 8, 1992. Federal Express delivered the successful bid to the Department's new address at 4:51 p.m. At 2:00 p.m. on the same day, The Department announced that all bids were in and opened the bids that had been delivered. The successful bid and one other bid were delivered on April 8, 1992, after the public opening conducted at 2:00 p.m. on the same day. Bids were tabulated on April 9, 1992. Bid tabulations were posted on April 13, 1992, and the successful bid was announced. The successful bid was for $8,174.00. Three bids were lower than the successful bid. Choice's bid was for $7,742.56. The other two lower bids were for $8,020.00 and $6,620.00. All three lower bids were rejected as non- responsive. Choice's bid was rejected because it did not meet bid specifications for 22 gauge steel, thermostatically controlled door heaters, and reinforced steel door panels. CHD filed a Notice of Protest on April 14, 1992, and a Formal Written Protest on April 24, 1992. CHD's protest alleges that: Choice's bid was lower than that of the successful bidder; the successful bid was not timely made; the bids were not opened publicly in violation of bidding procedure requirements; and the bid specifications were arbitrary and capricious, favored one bidder, and that Choice's bid was responsive. Neither a notice of protest nor a formal written protest was submitted by Choice or Nor-Lake. Neither Choice nor Nor-Lake attended the informal protest conference conducted on April 30, 1992. On May 7, 1992, Respondent's Office of General Counsel issued its written notice of proposed agency action. The written notice recommended that the bid be awarded to the successful bidder and that CHD's protest be dismissed for lack of standing. CHD requested a formal hearing on May 14, 1992, and the matter was referred to the Division of Administrative Hearings for assignment of a hearing officer on May 15, 1992. The bid submitted by Choice was prepared by CHD but signed by the president of Choice. Neither Nor-Lake nor CHD signed a bid or were otherwise bidders of record for bid number SB 92-244I. Neither Choice, CHD, nor Nor-Lake, filed a notice of protest concerning the bid specifications within 72 hours after Choice received the notice of the project plans and specifications on March 13, 1992. The sole basis upon which CHD claims it is substantially affected is the adverse economic impact caused to it by the proposed agency action. The proposed agency action will result in lost sales from this and future transactions. CHD will lose commissions from this and future transactions. The dealer relationship between CHD and Choice will be damaged because Choice will not want to sell a freezer that is not acceptable to Respondent. The marketing strategy developed between CHD and Nor-Lake will be damaged because it is conditioned upon the award of public contracts.
The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.
Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.
Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.
The Issue Whether Respondent has reason to reject the bids submitted by Petitioner to provide landscape maintenance services at two schools (item number 3 and item number 43 of the Invitation To Bid numbered SB 96C-56Z) based on Petitioner's performance of similar contracts in prior years.
Findings Of Fact On June 15, 1995, Respondent issued its Invitation To Bid number SB 96C-56Z (ITB) for landscape maintenance services to be rendered at various schools in the Palm Beach County district school system. Item 3 of the ITB was for landscape maintenance services at Bears Lake Middle School and item number 43 was for landscape maintenance services at Santaluces High School. The contracts for the various schools are awarded for a term of one year through the bid process, with the contract for the subject ITB to be for a term beginning July 21, 1995, and ending July 20, 1996. Similar ITBs for similar services have been issued by Respondent for each prior year that is pertinent to this proceeding. After the bids were opened, it appeared that Petitioner was the low bidder for items 3 and 43. Respondent rejected the bids of Petitioner for these two items and asserted, based on Petitioner's prior performance of similar contracts, that it would not be in the best interest of the School District to award items 3 and 43 to Petitioner. Petitioner thereafter timely protested the bid process for items 3 and 43, the matter was referred to the Division of Administrative Hearings, and this proceeding followed. The award of contracts by the Respondent for items 3 and 43 has been halted pending resolution of this proceeding. Petitioner has been in the landscape business for approximately ten years. For a number of years, Petitioner has been awarded contracts following an invitation to bid similar to the one at issue in this proceeding. The number of schools awarded to Petitioner has varied from "a few" to 22 in one year. Petitioner was awarded contracts for several schools for the 1994 contract term that the instant bid process is to replace. Petitioner was unable to perform the work at all the schools that it was awarded and surrendered its rights to some of those schools. Petitioner retained its contract for several other schools. The work Petitioner performed on the schools it retained was not acceptable to the Respondent. The record is replete with notices to the Petitioner stating its work was not acceptable and describing the noted deficiencies. Several of these letters threaten to terminate contracts that had been awarded to the Petitioner. Petitioner asserts that its problems with the Respondent are the product of unreasonable inspections of its work by Joe Lawson and Tom Williams, who were hired after Petitioner started working on schools. Petitioner has filed complaints against with the Respondent against Mr. Lawson and Mr. Williams on two separate occasions which purport to document the Petitioner's mistreatment by these two employees. Petitioner's assertions pertaining to these two inspectors are not based on persuasive, competent evidence and are, consequently, rejected. Petitioner also argues that it has received no more notices of complaints than other providers when the number of schools are considered. This is contrary to the more believable testimony, which established that Petitioner received more complaints. Lee Ziomek is a buyer employed by Respondent who has extensive experience in public procurement. Steve Zwirz is a landscape site technician whose duties include technical writing, supervising contracts, and supervising personnel. Joe Lawson is Mr. Zwirz's supervisor. Following the opening of bids, Mr. Ziomek, Mr. Zwirz, and Mr. Lawson met to review Petitioner's past performance. As a result of this meeting, it was decided to recommend that Petitioner had not performed its past contracts in an acceptable manner and that it was not in the best interest of the School District to award these two contracts to the Petitioner. The numerous notices of deficiencies that had been documented by Respondent provided a reasonable basis to conclude that awarding these bids to the Petitioner was not in the best interests of the School District. The first page of the ITB form used by Respondent contains the following: AWARDS: In the best interest of the School Board, the Board reserves the right to reject any and all bids . . .
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a final order that sustains the rejection of Petitioner's bids as to items 3 and 43 of ITB SB 96C-56Z and dismisses Petitioner's bid protest. Respondent's evaluation committee should resume the award process for items 3 and 43 of ITB SB 96C-56Z. DONE AND ENTERED this 23rd day of October, 1995, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 1995. COPIES FURNISHED: J. Steven Reynolds, Esquire 2628 Forest Hill Boulevard West Palm Beach, Florida 33406 Robert A. Rosillo, Esquire Palm Beach County School Board 3318 Forest Hill Boulevard West Palm Beach, Florida 33406-5813 Dr. C. Monica Uhlhorn, Superintendent Palm Beach County School District 3318 Forest Hill Boulevard West Palm Beach, Florida 33406-5813 Cynthia S. Prettyman, General Counsel Palm Beach County School District 3318 Forest Hill Boulevard West Palm Beach, Florida 33406-5813