The Issue Whether Petitioner’s application for a variance to permit an onsite treatment and disposal system should be approved.
Findings Of Fact The lot of land for which the Bank seeks a variance for an onsite sewage treatment and disposal system is located at 341 Compass Lake Drive in Jackson County, Florida. The lot is approximately 40 feet wide and 300 feet deep, with approximately 40 feet of frontage on Compass Lake. Prior to its severance in 2010, the lot was part of a larger parcel of land with an address of 343 Compass Drive in Jackson County. The larger parcel was owned by Charles Paulk and had substantial improvements consisting of a house, boathouse, and dock. In 2004, Mr. Paulk borrowed money from the Bank and gave the Bank a mortgage lien on the entire larger parcel to secure the loan. At some point, a survey was prepared which subdivided the larger parcel into two lots -- the first containing the substantial improvements, and the other consisting of the approximately 40-foot by 300-foot lot at issue, which is .28 acres in size, with no improvements. There is no indication that the survey was ever recorded in the public records. Later, in 2010, Mr. Paulk decided to sell the lot with the substantial improvements for $330,000. Because the Bank had a lien on the entire larger parcel, Mr. Paulk requested that the Bank release its lien on the lot with the substantial improvements. The Bank agreed to release its lien on the lot with substantial improvements and, after receiving what the Bank felt was a “sufficient pay-down” on the loan, shifted its lien to the smaller, unimproved lot that is at issue in this case. The sale and release of lien transaction “substantially reduced the loan versus the collateral value” that the Bank previously had. According to the Bank’s Senior Vice President, James Goodson, after the sale transaction, there was “not a lot of money left on the loan ” Mr. Goodson testified that, at the time that the Bank agreed to release its lien on the substantially improved lot and shift its lien to the remaining unimproved lot, it was unaware that a variance would be required for an onsite sewage treatment and disposal system (septic tank) on the unimproved lot. The facts as outlined above, however, demonstrate that the Bank was an active participant and beneficiary of the transaction that ultimately resulted in the creation of the two lots, one of which was the approximately 40-foot by 300-foot unimproved lot at issue in this case. In 2012, Mr. Paulk experienced financial problems and was having difficulty paying back the loan to the Bank secured by the unimproved lot. Because it was easier than foreclosure, the Bank agreed to take a deed to the unimproved lot in lieu of foreclosure.1/ At the time of the Bank’s release of lien in 2010, as well as at the time of the deed in lieu of foreclosure, the 40- foot by 300-foot lot size of the unimproved lot was too small to meet the statutory requirements for a septic permit. Mr. Goodson testified that, at the time that the Bank accepted the deed in lieu of foreclosure, the Bank was aware that the lot was too small and would need a variance for a septic tank. He did not explain, however, why the Bank had earlier been unaware of the need for a variance when it agreed to release its lien on the substantially improved lot in 2010. After the Bank acquired title to the unimproved lot, a third party offered to purchase it on the condition that the Bank could obtain a permit. The Bank went to Jackson County to request a permit, knowing that its request would be denied because the lot size was insufficient for a septic tank without a variance. Nevertheless, the Bank believed that it would qualify for a variance on hardship grounds because it did not “intentionally” create the hardship. The Bank commenced the permitting process by submitting an application with the Jackson County Health Department on October 4, 2012. The County denied the application on the grounds that the lot was deficient in width and total area. Next, the Bank submitted a request to the Department for a variance. The request was considered by the Department’s Variance Review and Advisory Committee (Committee) on December 6, 2012. The Committee has only recommending authority to the State Health Officer. In a four to three vote, the Committee recommended approval of a variance. The members voting against a recommendation for approval were representatives of the State Health Office, the Department of Environmental Protection, and the County Health Department. Eight objections from adjacent property owners were provided to the Committee’s review and consideration. After considering the facts, including the decision of the County Health Department, objections filed by adjacent property owners, actions taken by the Bank, and the recommendations of all the members of the Committee, Gerald Briggs, Bureau Chief for Onsite Sewage Programs for the Department of Health, made the Department’s preliminary decision that the Bank’s variance request should be denied, concluding, among other things, that “[a]ny perceived hardship that [the Bank] might experience as a result of the obligation to meet established standards comes about as a direct result of your own proposed action.” Likewise, considering the facts and evidence as presented in this case, the undersigned finds, as a matter of fact, that the Bank intentionally participated in and benefitted from the transaction that resulted in the hardship posed by the small lot size that it now owns and for which it seeks a variance.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health enter a Final Order denying SunSouth Bank’s application for a variance. DONE AND ENTERED this 21st day of March, 2014, in Tallahassee, Leon County, Florida. S JAMES H. PETERSON, III Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of March, 2014.
Findings Of Fact Respondent is the owner and developer of the Plaza Venetia Marina, located in Biscayne Bay in Dade County, Florida, immediately north of the Venetian Causeway. The marina is constructed on submerged lands leased from the Board of Trustees of the Internal Improvement Trust Fund. On May 4, 1976, DER issued Permit No. 13-30-0364-6E to Respondent. That permit authorized the construction of two concrete marina docks, one "T" shaped and 255 feet long, and the other "J" shaped and 500 feet long. The project site is north of the Venetian Causeway on the western edge of Biscayne Bay, Section 31, Township 53 North, Range 42 East, Dade County, Florida. On August 18, 1977, DER issued Permit No. 13-30-3984 to Respondent. That permit authorized the construction of a 700 foot long "J" shaped pier with 24 finger piers and associated mooring pilings, and the construction of a 280 foot long "T" shaped pier. This permit authorized construction to be undertaken directly north of the docks authorized by Permit No. 13-30-0364-6E described above. On August 18, 1977, Respondent applied to DER's West Palm Beach office for a permit to construct the center pier of the Plaza Venetia Marina. On October 27, 1977, DER issued Permit No. 13-30-0740-6E to Respondent. This permit, which is the only one of the three permits at issue herein, authorized construction of a boat tie-up and fueling facility for a public marina. This facility represented a final phase of a master plan which includes the two other marinas with tie-up accommodations authorized by Permit Nos. 13-30-0364-6E and 13-30-3984. The drawings which accompanied the permit application carried the designation "FUEL" on the large platform at the end of the center pier of the marina. The cover letter from Respondent's authorized agent explained that " . . . the fueling area has been made sufficiently large so as to isolate the fuel pumps." No specific mention was made in the application or supporting materials of any building to be constructed on the central pier, and none of the permit drawings initially filed with DER depict any such building. DER employees who processed the permit, however, knew at some time during the processing of the permit application that some sort of structure would likely be constructed on the platform at the end of the center pier, although the plans did not disclose such a building, and the agency made no inquiries about, nor requested any additional information from Respondent concerning the type of structure contemplated. At the time of the issuance of Permit No. 13-30-0740-6E Respondent did not know the exact nature, size, or height of any structure that it might wish to build on the central platform. At the time, Respondent had only a conceptual idea of a structure that might accommodate the uses it contemplated for the platform. The words "fueling station" appear on the platform at the end of the center pier in one of the drawings attached to Permit No. 13-30-0740-6E. That drawing was not initially filed with the original permit application, but was provided during the permitting process by Respondent prior to issuance of the permit. Permit No. 13-30-0740-6E was issued to Respondent on October 27, 1977, pursuant to the authority granted DER under Chapters 253 and 403, Florida Statutes. Nowhere in the permit is there any reference to Section 258.165, Florida Statutes. The permit, by its expressed terms, authorized the following: To construct a boat tie-up and fueling facilities [sic] for a public marina. The facility will extend approximately 390 feet into Biscayne Bay from the bulkhead line. The dock will provide tie-up spaces for 20 boats and six fuel slips, and will contain floating oil collars in case of oil or gasoline spillage. This facility represents the final phase of a master plan which includes two other marinas with tie-up facilities . . . On January 11, 1979, some approximately fourteen months after issuance of the permit for the center pier, Respondent sent a letter to DER's West Palm Beach office which read as follows: Enclosed please find a copy of a letter as sent to the Army Corps, re: the service facility you and I discussed for the already approved fuel dock (State No. 13-30-0740-6E) for the Plaza Venetia Marina. I also enclose copy of the plans. Please review as quickly as possible since we intend to start construction on the marina within 30 to 45 days. (Emphasis added.) Enclosed with the January 11, 1979, letter to DER was a copy of a January 11, 1979, letter to the Army Corps of Engineers which read as follows: Recently I reviewed with [a Corps representative] the placement of a small service accommodation facility on the already approved fuel dock for the Plaza Venetia Marina . . . I left a set of plans with [the Corps] at the Corps office in Miami Beach. The facility is in close keeping with the permitted use of the marina. It will occupy less than half the already approved area of the fueling facility. It will be constructed on an already permitted facility. Included are a small bait and tackle shop; convenience store; captains' office; observation area and required bathrooms. The discharge from the bathrooms will flow directly into the main County sewer disposal system and will utilize a sewer pump-out facility located on the fuel dock. * * * After carefully reviewing my existing permit, the limited nature of the facility described, and its sole purpose of servicing the already permitted marina, please advise me if any modifications are required. I look forward to hearing from you as quickly as possible on this matter since construction of the marina is projected to begin within the next 30 to 45 days. A copy of the floor plan of the proposed building was attached to the January 11, 1979, letter received by DER. This floor plan indicates areas to be included in the building for bait and tackle facilities, a food store, storage areas, restroom facilities, and a marina office. Also shown on the floor plan is a storage area for electric carts to be used in servicing vessels utilizing the marina facility. The record in this cause establishes that Respondent never intended its January 11, 1979, letter to DER to be a request for a permit modification or an application for a new permit. Instead, the letter was intended only as a request for DER review of and comments on the proposed structure to be built at the end of the central pier. DER representatives in its West Palm Beach office forwarded the letter to the Tallahassee office of DER. DER never responded either orally or in writing to Respondent's communication of January 11, 1979, enclosing the building plan. On June 19, 1979, DER had opened its file No. 13-9916 in its standard form dredge and fill permitting section in Tallahassee in response to a letter received from Respondent requesting the addition of some dolphin pilings along the bulkhead at the Plaza Venetia Marina. The request from Respondent was treated as standard form application because the scope of the entire marina project exceeded short-form criteria. After receiving this request from Respondent, DER sent a completeness summary to Respondent within 30 days of receipt of the application requesting that Respondent provide approval from the Department of Natural Resources for the use of sovereignty submerged lands. Through various correspondence, this application was expanded to include several additional modifications to the overall marina, including reconfiguration of the fuel dock, addition of finger piers, reconfiguration of the "T" docks, and addition of a 12-foot boardwalk. Finally, the application was modified so that it constituted an application to consolidate the three existing permits. On January 29, 1980, Respondent submitted the last item of information required by the completeness summary except for DNR approval for use of sovereignty submerged lands. The aforementioned letter of January 11, 1979, from Respondent, which included the building floor plan, was apparently placed in DER file No. 13-9916 relating to Respondent's requested permit modification. Although the floor plan is contained in this file, the record in this cause clearly establishes that neither Respondent nor DER treated either the January 11, 1979, letter or the enclosed plan as a request for modification of Permit No. 13-30-0740-6E. DER file No. 13-9916 sat dormant for almost three years awaiting DNR consent for the use of state-owned lands. By letter dated July 10, 1981, DER requested Respondent to indicate whether it wished to pursue the permit modification application further since it had been 1,085 days since DER had notified Respondent of the necessity to furnish notification from DNR concerning further use of state sovereignty submerged lands. By letter dated July 15, 1981, Respondent withdrew its permit modification application. On April 20, 1979, the City of Miami issued a valid building permit for the marina fueling station. Respondent notified DER in July, 1979, that it was beginning construction of the marina. Construction of the central pier began on July 16, 1979, and ended on June 11, 1980. Construction of the fueling platform began on February 28, 1981, with erection of the fueling station walls beginning sometime after April 1, 1981. Subsequent to the commencement of construction DER representatives inspected the building site on several occasions. Respondent was not made aware in advance of when these inspections would occur since they were scheduled at the sole discretion of DER. DER first learned of the actual construction of the marina fueling station after receipt of a citizen complaint on December 1, 1981. Upon inspection of the site by DER personnel on December 2, 1981, it was discovered that the building on the fuel dock was partially complete with finish work and the placement of some interior and exterior walls remaining to be accomplished. DER served a warning notice on Respondent on December 7, 1981, advising Respondent of an alleged violation of its existing permit. A second warning letter was sent to Respondent on January 26, 1982, followed by the issuance of the Notice of Violation by DER. DER incurred costs and expenses of $405.40 in investigating the alleged violation. The structures authorized by Permit Nos. 13-30-0364-6E, 13-30-3984, and 13-30-0740-6E ("the structures") have been constructed by Respondent. The structures are located within the Biscayne Bay Aquatic Preserve ("the Preserve") established by Section 258.165, Florida Statutes. Biscayne Bay at the site of the structures is a navigable water of the State of Florida. A building with a floor area of approximately 3,800 square feet and a roof area of 5,292 square feet has been constructed at a cost of approximately $500,000 on the platform at the end of the center pier of the marina. The net area of the platform contains about 9,640 square feet. It has been stipulated by the parties that construction of the building on the center pier will not result in significant adverse water quality or biological impacts which were not contemplated when the above-referenced permits were issued for the marina. The building as presently constructed has provisions for the following uses: a waiting area for water-borne transportation, a bait and tackle shop and marine supply store, an electric cart parking and recharging station, and an attendant's room with cash register and equipment for the fuel pumps. All of these uses are customarily associated with the operation of marina facilities. The building as constructed differs in several minor respects from the one shown on the plans submitted to DER in the January 11, 1979, letter from Respondent. What had been shown on those plans as outdoor seating has been enclosed, walls and proposed uses have been relocated within the building, and the entire building has been moved back on the fuel dock. It is concluded, however, that these changes are of such a minor nature as to not constitute a material departure from the plans furnished to DER in January of 1979. As-built plans for the building have never been provided by Respondent to DER. At the time of Respondent's application for the permit for the center pier, DER rules required that a permit applicant provide cross-sectional drawings of proposed structures to be built in conjunction with docking facilities such as those proposed by Respondent. Drawings attached to the permit application show two cross sections through the center pier, but neither of these cross sections depict a building to be constructed on the pier. Respondent did not submit cross-sectional drawings for the building at the time of its application, and none had been submitted to DER as of the date of final hearing in this cause. However, DER at no time requested such cross-sectional drawings, despite the fact that those agency representatives processing Respondent's permit application assumed from the outset that some structure would and could be built by Respondent on the platform attached to the central dock under the terms of the October 27, 1977, permit. The estimated cost for removal of the building at the end of the central pier is $150,000-$200,000.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a Final Order be entered by the State of Florida, Department of Environmental Regulation, dismissing the Notice of Violation. DONE AND ENTERED this 3rd day of June, 1983, at Tallahassee, Florida. WILLIAM E. WILLIAMS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of June, 1983. COPIES FURNISHED: Paul R. Ezatoff, Jr., Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Clifford A. Shulman, Esquire and Thomas K. Equels, Esquire Brickell Concours 1401 Brickell Avenue, PH-1 Miami, Florida 33131 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Lee Rohe, Esquire Assistant Department Attorney Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, Florida 32303 Elton Gissendanner, Director Department of Natural Resources Executive Suite 3900 Commonwealth Boulevard Tallahassee, Florida 32303 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION, Petitioner, v. CASE NO. 82-1640 FLORIDA EAST COAST PROPERTIES, INC., Respondent. /
The Issue The appellant contends that the Planning Commission "did not base its decision on specific standards or criteria [set forth in the zoning regulation] as required. Nor was there any competent substantial evidence presented that would support the Planning Commission's findings."
Findings Of Fact Based upon the evidence of record submitted with this appeal, the findings of fact of the Planning Commission are rejected and the following substituted: The proposed use constitutes a marina pursuant to section 9.5-4(M-5) of the Monroe County Code, Land Development Regulations, and it must, therefore, be reviewed as a major conditional use. The proposed development complies with all applicable Monroe County land development regulations. The proposed development is limited to two fueling docks, one 9' x 16'4" and the other 13' x 12'8", and one fueling pump. The proposed development does not include provisions for boat storage, boat ramps, or liveaboard docking. The proposed development is not expected to generate additional vehicular traffic nor, as a result, demand additional on-site vehicular parking due to its exclusively water-oriented nature. The proposed development does not include provisions for additional outdoor lighting. The proposed development includes provisions for a five-year water quality monitoring program which contains adequate recommendations for spill containment, including provision of a containment kit and use of absorbent carpeting on the dock surface, as well as corrective measures to be undertaken by the applicant in the event of water quality deterioration. Coordination with the United States Environmental Protection Agency is necessary to insure that the proposed water quality monitoring program follows the guidelines of this agency. The proposed development is located in the vicinity of a designated critical habitat of the American crocodile, and the presence of the West Indian manatee in the area is documented. The Florida Game and Fresh Water Fish Commission and the United States Fish and Wildlife Service have offered recommendations to mitigate the secondary impacts of the proposed development on these species of endangered wildlife, including the installation of an educational display and restrictions on the provision of additional marina facilities. Additional conditions and restrictions are appropriate and may be imposed pursuant to sections 9.5-61 and 9.5-63 of the Monroe County Code, Land Development Regulations. Limitations are particularly necessary to minimize the impacts of the proposed development upon neighboring residential uses and the canal, in consideration of the water-oriented nature of the use.
Findings Of Fact Application No. 76-00493 is for an existing consumptive use permit for five wells located in the Peace River Basin, Polk County on 608.6 acres. The permit seeks a total average annual withdrawal of 7.2 million gallons per day and a maximum daily withdrawal of 14.97 million gallons per day. Ninety-five percent of the water withdrawal will be used for industrial purposes and five percent will be used for irrigation. The Southwest Florida Water Management District's staff recommends issuance of the permit with the following conditions: That the applicant shall install totalizing flow meters of the propeller-driven type on all withdrawal points covered by the application except that well located at Latitude 28 degrees 03' 13", Longitude 81 degrees 47' 54". That the applicant shall record the pumpage from the above meters on a weekly basis and submit a record of that pumpage quarterly to the district beginning January 15, 1977. That the permit shall expire on December 31, 1980
Recommendation It is hereby RECOMMENDED that a consumptive use permit be granted in the amounts applied for in Application No. 76-00493 subject to the conditions set forth in paragraph 2 above. ENTERED this 13th day of October, 1976, in Tallahassee, Florida. CHRIS H. BENTLEY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Coca Cola Company Post Office Box 247 Auburndale, Florida 33823
The Issue Whether Bay North Corporation should be issued a permit to construct a domestic wastewater treatment and disposal system at Camp Weed, Franklin County, Florida, pursuant to Chapter 403, Florida Statutes.
Findings Of Fact On February 27, 1978, Lomax Smith, a builder and developer in Tallahassee, Florida, entered into an agreement with the Protestant Episcopal Church in the Diocese of Florida to purchase some 42 acres of real property and the improvements thereon known as "Camp Weed" which is located in Franklin County, Florida. The purchase price of the property was $725,000, with an earnest money deposit of $20,000, and closing of the transaction to be on or before July 1, 1978. At the time of purchase, eight dormitory and several accessory buildings were located on the property which utilized septic tanks for sewage disposal. An existing deep well is in the northwest portion of the property for a water supply. Smith proposed to develop the property by the sale of lots, remodel some of the existing buildings, and construct new housing units. He employed the engineering firm of Broward Davis and Associates, Inc., Tallahassee, Florida, to prepare the necessary design plans and a state environmental permit application for a proposed domestic wastewater treatment plant to be located on the site. (Testimony of L. Smith, N. Smith, Exhibits 12, 13) On September 6, 1978, Smith filed an application with Respondent Department of Environmental Regulation (DER) for a permit to construct the sewage treatment plant (STP) at Camp Weed. He signed the application as owner of the property although he had not closed the purchase transaction nor acquired legal title at that time. The application and supporting plans were reviewed in the Northwest District Office of the Department of Environmental Regulation after site investigation, and it was determined that construction of the facility would be in accordance with applicable laws and regulations. A construction permit was issued to Smith for the STP on October 10, 1978, subject to certain specified conditions attached to the permit. Notification of the permit issuance was not preceded by a notice of intent to grant the permit, nor were any third parties advised of its issuance. Petitioners St. Teresa Dock Association, Inc. (then St. Teresa Dock Association) and H.S. Oven first learned of the permit issuance when their counsel was informed by Smith's counsel on November 3, 1978, that the permit had been issued. Petitioners thereafter on November 17 filed a petition for hearing with DER. (Testimony of L. Smith, Huff, Exhibits 1, 4-5, 8) Camp Weed is bounded on the north by U.S. Highway 98 and on the south by the Gulf of Mexico. The planned site for the STP is in the northeast corner of the tract which is some twelve feet above mean sea level and approximately 950 feet from the shoreline. The elevation of the property on the northwestern side is about 24 feet and is five feet in the middle. The land slopes generally toward the middle area and drains in a southerly direction to the gulf. The subdivision of St. Teresa where Petitioners' members own summer homes is located immediately west of Camp Weed. The members of the St. Teresa Dock Association, Inc., and Petitioner Hamilton S. Oven use the beach and gulf waters for boating, fishing, and other recreational purposes. About a dozen shallow wells in the St. Teresa subdivision provide drinking water for the residents. They are located over 1700 feet southwest from the site of the proposed STP. There are two ponds north of the St. Teresa area adjacent to U.S. Highway 98. An artesian well is located in the gulf about 25 feet south of the Camp Weed property. (Testimony of Huff, N. Smith, Oven, Sensabaugh, Exhibits 2,7, 9-11, 22, 24) The proposed plant is designed to provide sewage treatment for 132 housing units containing an estimated population of 3 persons per unit. A gravity flow collection system to a pumping station will produce a peak influent rate of 29,700 gallons per day with an estimated biological oxygen demand (BOD) loading of 49.6 pounds per day. A basket strainer on the influent line will remove trash. Plant operation will involve the use of aeration tanks, clarifier, chlorination, sand filter and clear well for discharge to a percolation pond. A polishing pond was originally planned, but was deleted at the suggestion of the DER because it performs the same function as the proposed sand filter. Two percolation ponds for alternate use will be construed so that the pond bottom is twelve feet above sea level. A soil test revealed that a sand layer extends under the shallow surface top soil to a depth of approximately 10 feet before reaching the shallow ground water table and that the effluent will percolate through the sand at the rate of one inch per minute. A five foot soil boring by DER failed to encounter ground water at that level and show that rate of percolation through the sand would be acceptable. The ground water table is subject to an unknown variance indepth during the wet and dry seasons of the year depending on the amount of rainfall. Although tide fluctuations may also have some effect on depth of the ground water table, the tide most likely will be of minimum influence due to the distance of the plant site from the gulf. Percolation of at least three feet through sand before reaching ground water is sufficient to meet DER policy requirements. (Testimony of Huff, N. Smith, Bishop, Exhibits 1, 3, 16-17). Based on the design of the STP, it is predicted by applicant's design engineer that there will be at least 90 percent removal of pollutants after chlorination and prior to passage of the effluent through the sand filter. The engineer predicts that after such filtration, there will be approximately 95 percent removal prior to percolation and that the effluent will then be pure enough to use as drinking water. Further purification will take place during the percolation process. The DER District Supervisor of Domestic Wastewater Permitting, who also is a professional engineer, substantially agrees with those predictions. Actual results of the treatment process can be determined, however, only after tests from monitoring wells are made during actual trial operations of the plant. It is further agreed by those experts that the average chlorine residual content in the effluent will be 0.5 parts per million. The DER supervisor therefore is of the opinion that, if the STP is properly operated, the processed effluent will not degrade ground waters, not adversely affect the wells in the St. Teresa Community or the waters of the gulf. After percolation, there is further dilution and ultimately the ground water which reaches the gulf in eight to ten days will be in a purer form than prior to introduction of the effluent. Although a twenty-year storm criterion was applied in the design of the percolation ponds, a catastrophic storm such as a hurricane was not taken into consideration since it would not be economically feasible to design for such an effect and, in any event, super dilution caused by such a storm would negate the possibility of water quality degradation. (Testimony of Huff, N. Smith, Exhibit 1) The buildup of sludge in the plant's holding tank will require removal about once a year when the plant is in full operation. The applicant will employ a certified individual to operate the plant and to remove sludge periodically to an appropriate place for disposal in an authorized manner. DER regards sludge disposal to be a matter for determination at the time application is made for an operating permit. (Testimony of Huff, L. Smith, McNeill, N. Smith, Exhibit 1) The applicant estimates that the construction of the plant and collection system will cost approximately $1,000 per housing unit for a total of $132,000. It is planned to recover this cost on the sale of lots. A condition of such purchases will be that the sewage system and treatment plant will be operated by a home owners association which is to be activated in the near future. Maintenance cost of the sewage plant will be shared by the individual members. Approximately twenty or twenty-five members are required for economical operation of the plant. (Testimony of N. Smith, L. Smith) The county zoning classification for the Camp Weed area is currently the subject of litigation by the applicant in the Franklin County Circuit Court and the result of that litigation as to permitted density of housing will determine the amount of units to be constructed by the applicant. In any event, if the applicant does not secure a county building permit, any DER construction permit would expire at the termination of the time granted therefor. (Testimony of L. Smith, Huff, Exhibit 24) At the time Intervenor Lomax Smith signed the permit application, Bay North Corporation had not been formed. It was incorporated in November, 1978, in order that Smith could obtain financing to complete the property purchase. The transaction was closed November 6, 1978, and a warranty deed to the property was issued to Bay North Corporation by the Episcopal Church in the Diocese of Florida, Inc. The deed was recorded in the public records of Franklin County on November 7, 1978. Lomax Smith is the president and principal stockholder of Bay North Corporation. Promissory notes secured by mortgages to the Southern Bank of Tallahassee and the Episcopal Diocese of Florida in the amounts of $350,000 and $362,500 respectively, were executed by Bay North Corporation on the same date. Pursuant to a request to DER from Lomax Smith on May 15, 1979, the Northwest District DER Office, on June 29, 1979, purported to transfer the permit to Bay North Corporation and extend the expiration date to September 30, 1980. (Testimony of L. Smith, Huff, Exhibits 6, 14-15, 21) The construction permit issued in October, 1978, was subject to standard and special conditions, including the requirement that the permit holder comply with county and municipal regulations prior to construction. They provided that monthly reports be furnished to the DER prior to issuance of an operation permit setting forth wastewater characteristics during a trial period of plant operation. They also required that the facility meet the treatment requirements contained in Chapter 17-3, F.A.C., including a 90 percent reduction in BOD and suspended solids based on concentration of the influent entering the plant. The conditions further provide that at the time of application for an operation permit, it must be shown that a certified operator under Chapter 17- 16, F.A.C., is retained, together with a copy of any contract for contract operation of the facility. Additionally, the conditions require that two monitoring wells be established upstream and downstream of the ponds and that quarterly ground water samples be analyzed and reported to DER. A further condition provides that a three-foot buffer zone must be maintained between the bottom of the percolation ponds and the maximum elevation of the ground water. (Exhibit 8)
Recommendation That the Department of Environmental Regulation issue the requested permit to Bay North Corporation, subject to the conditions attached to the permit issued on October 10, 1978. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 21st day of November, 1979. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: George E. Lewis, II, Esq. 316 East Park Avenue Tallahassee, FL 32303 William L. Hyde, Esq. Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Ben H. Wilkinson, Esq. Pennington, Wilkinson, Gary and Dunlap Post Office Box 3875 Tallahassee, FL 32303 Alfred O. Shuler, Esq. Post Office Box 850 Apalachicola, FL 32320
Findings Of Fact Petitioner Richard L. Buchanan owns a lot in Franklin County, which lies on the north shore of Apalachicola Bay. Shellfish harvesting is prohibited in the water adjacent to his parcel despite, or perhaps because of, oyster houses having operated in the vicinity for many years. Mr. Buchanan is not an oysterman himself, but he does fish commercially, when he is able. He owns two licensed fishing boats. He goes floundering and also fishes with gill nets. Since he acquired the property 10 or 12 years ago, Mr. Buchanan regularly loaded nets from shore and unloaded fish and nets on shore, until the prop-dredging took place, even though a dock extends out into the Bay from his property. The outboard motor is hard to handle from the dock and it is virtually impossible to load the nets from the dock without fouling them. Until the prop-dredging he could bring his boats all the way in and lay their bows on the shore along the stretch of clean sand 35 to 50 feet wide at the western end of his 145 feet of Bay frontage. There was a sheer drop to a depth, at high water, of about 3.5 feet. The Sadler boy drowned there. Before the prop-dredging disturbed it, the configuration of the bottom that allowed small boats to come all the way into shore at that point had obtained for decades. Leo Nixon Harwell, son of the former owner of petitioner's property, remembered running the Harwells' oyster boat, which drew three feet, right up on the beach. Mr. Harwell, who looked to be in his 50's, testified that there had been deep water next to the shore ever since he was "no yearly boy." The further from shore the deeper it got till you reached Two Mile Channel. Between the sandy beach and the channel there was no vegetation to speak of although there was a marshy swash to the east of the sandy beach. In 1979, when Arman Earl Cloud had to haul his bay shrimper for repairs, he floated it to the beach in back of Mr. Buchanan's house and pulled it up on the beach, using rollers. The bow floated to the water's edge. The boat had a length overall of 25 to 28 feet, a beam of nine feet and drew three to three and a half feet of water. An oyster house sits on the next parcel west of the Buchanan property. The oyster house belongs to a man named Page, and a dock 100 feet long juts out toward Two Mile Channel from the oyster house. It used to be impossible to get an oyster boat in any closer to shore. When John Paul Whitehead was oystering some years back, they used to have to anchor out and transfer the oysters to a skiff to get them to the Page oysterhouse. In fact, when Diane Collins rented the oysterhouse (from Bobby Youngblood) in 1974 or 1975 it was impossible to bring even a flat-bottomed boat in as far as the waterward end of the dock. "On dead low tide all you seen was sand on either side of the dock." According to unrebutted testimony, the Pages changed all this by prop- dredging. (Mr. Page failed to honor the subpoena requiring his attendance at the final hearing.) Prop-dredging involves fixing the bow of a boat by grounding or otherwise, and turning the propeller at speeds high enough to move soils on the bottom. Bay this technique, the Pages dredged great quantities of sand on either side of their dock. Most of the sand stayed suspended in the water only long enough to settle in front of their neighbors' property. This illegal activity was brought to the attention of the marine patrol at the time, whose warning to the Pages to desist went unheeded, and at least one employee of respondent Department of Environmental Regulation was also apprised. The prop- dredging continued for some time, usually at night, and the eventual result was "a muck hill" in front of the Miracle Seafood property abutting the Pages to the west, and a sandbar in front of Mr. Buchanan's property that completely blocks access to his sandy beach. The Pages, with 55 front feet on the Bay, can now accommodate quite a fleet at their dock. One day six to eight boats were docked there. The sandbar in front of Mr. Buchanan's property attributable to the Pages' unpermitted and illegal prop-dredging has by now been there long enough that smooth cord grass (Spartina altiflora), saw grass and maiden cane have taken root. The dredging proposed by petitioner to restore access to his shoreline would disturb some 400 square feet, on which only Spartina altiflora is growing. On about a quarter of the proposed site, there is no vegetation. The Spartina altif lora helps stabilize the shoreline, serves to filter pollutants running off into the Bay and provides a habitat and food for insects, worms, oysters, shrimp and fishes. Dredging would resuspend any heavy metals in the soil, and increase the turbidity of the water, in the immediate vicinity. There is a boat ramp 500 feet from petitioner's property. DER would issue a permit for a marine railway at the site where petitioner hopes to dredge. Apalachicola Bay is classified as Class II waters, and as outstanding Florida waters, being part of an aquatic preserve. There is a clear public interest in permitting a private citizen, who is willing to restore, at his own expense, a part of the coastline disturbed by illegal activity which he responded to the authorities at the time, to the status quo which existed for as long as anybody can remember, before the illegal activity disturbed it. In an undated letter to Mr. Buchanan, James W. MacFarland, Director, Division of State Lands, Department of Natural Resources, advised that Upon the assurance that the environmental effects are acceptable and with the understanding that DER intends to issue the permit, we will request the dredge material severance fees and issue our authorization pursuant to Section 253.77, Florida Statutes, upon the permit receipt. The credible testimony of DER staff was to the effect not that the loss of some 300 square feet of Spartina altif lora would have unacceptable environmental effects, but that the cumulative effect of projects entailing destruction of such grasses would have unacceptable environmental consequences. Respondent's proposed findings of fact, conclusions of law and proposed recommended order have largely been adopted, in substance. To the extent any proposed finding of fact has been rejected, it has been deemed immaterial or unsupported by the weight of the evidence.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner grant respondent's application for a dredging permit on such reasonable conditions, including turbidity curtains, as are necessary adequately to protect the project vicinity. DONE and ENTERED this 8th day of August, 1983, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of August, 1983. COPIES FURNISHED: E. Gary Early, Esquire Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Richard L. Buchanan P. O. Box 33 Apalachicola, Florida 32320 Victoria Tschinkel, Secretary Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue Whether the Department of Environmental Protection (DEP) has issued an agency statement defined as a rule which has not been adopted by rulemaking as required by Section 120.54(1)(a), Florida Statutes. (All statutory citations are to the 2000 codification of the Florida Statutes. All rule citations are to the current Florida Administrative Code.)
Findings Of Fact On April 20, 2001, DEP's Southwest District office issued an Intent to Issue with respect to Tampa Bay Desal's application for a NPDES permit for the construction and operation of a proposed desalination facility (DEP File No. FL0186813-001-IW1S). DEP's Intent to Issue for the Tampa Bay Desal NPDES permit provided in part: A person whose substantial interests are affected by the Department's proposed permitting decision may petition for an administrative proceeding (hearing) under sections 120.569 and 120.57 of the Florida Statutes. The Intent to Issue for the NPDES permit also specified the type of information that must be included in a petition filed under Sections 120.569 and 120.57. SOBAC timely challenged DEP's proposed agency action concerning the Tampa Bay Desal permit application. The challenge is currently pending as DOAH Case No. 01-1949. The Intent to Issue the Tampa Bay Desal permit also included the statement: "Mediation under section 120.573 of the Florida Statutes is not available for this proceeding." On June 7, 2001, SOBAC filed a Petition to Invalidate Agency Statement under Section 120.56(4). SOBAC alleged that the statement regarding mediation met the definitions of a rule but was not adopted by rulemaking as required by Section 120.54(1)(a). By correspondence dated June 13, 2001, DEP notified counsel for SOBAC of DEP's willingness to participate in mediation in an effort to resolve the issues underlying the administrative challenge. However, DEP's offer to participate in mediation was predicated, at least in part, on the following conditions: the parties would agree on the selection of the mediator; any discussions and documents introduced in the mediation would remain confidential; and notwithstanding the mediation, discovery in the administrative proceeding would continue, and the parties would be prepared to proceed to the final hearing as scheduled. On or about June 14, 2001, Tampa Bay Desal agreed, at least in principle, to participate in mediation with SOBAC under those conditions. There was no evidence that either DEP or Tampa Bay Desal ever agreed to toll the administrative proceeding (DOAH Case No. 01-1949) pending mediation. On or about June 15, 2001, counsel for SOBAC contacted DEP and accepted DEP's offer to participate in a mediation conference. On or about July 23, 2001, the Department, SOBAC and Tampa Bay Desal participated in a mediation conference in an effort to resolve the issues underlying SOBAC's challenge to Tampa Bay Desal's permit application. Mediation efforts failed. According to the evidence, SOBAC is an organization with an interest in various environmental permitting activities in and around Tampa Bay. SOBAC monitors local newspapers for DEP notices of intent to issue permits. Besides the Tampa Bay Desal permit, SOBAC has become aware of three other DEP notices of intent of interest to SOBAC. One was a notice of intent to issue a permit to Tampa Electric Company (TECO) for NPDES permit modifications relating to and for purposes of accommodating the Tampa Bay Desal project. This notice of intent also contained the statement: "Mediation under Section 120.573, Florida Statutes, is not available for this proceeding." SOBAC nonetheless requested mediation under Section 120.573. When the time to challenge the notice of intent was about to expire, SOBAC also filed an administrative challenge under Sections 120.569 and 120.57. The TECO challenge also was referred to DOAH, where it was given Case No. 01-2720 and consolidated with Case No. 01-1949. TECO never agreed to mediation, and DEP never responded to SOBAC's request for mediation. Another case involved a TECO air pollution permit unrelated to the desalination project. The notice of intent to issue stated: "Mediation is not available for this proceeding." The evidence did not indicate that SOBAC took any action with respect to this notice of intent to issue. The third case involved IMC Phosphates Company and a permit to operate a barge loading facility handling phosphate materials. The notice of intent to issue stated: "Mediation under Section 120.573, F.S. is not available in this proceeding." SOBAC filed an administrative challenge to this permit under Sections 120.569 and 120.57. IMC never agreed to mediation. The evidence was not clear whether SOBAC received a response to its request for mediation. After initiating the instant proceeding, SOBAC researched the Florida Administrative Weekly (FAW) from September 1999 through the date of final hearing and found 30 notices of intent, all of which stated essentially that mediation was not available for (or in) the proceeding, and one notice of intent. No further explanation was given. Of the 30, 24 were electric power plant siting cases, 4 were water quality exemptions, one involved a state revolving loan fund, and one was a joint coastal permit case with consent to use sovereign lands and requested variances. SOBAC presented no evidence as to DEP intents to issue not published in FAW. However, DEP entered into the record evidence of one other DEP notice, apparently not published in FAW, of intent to issue a coastal construction control line permit stating that mediation under Section 120.573 was available and describing procedures to be followed for mediation. SOBAC presented no other evidence to explain why mediation was not offered in the examples given or why it was offered on the one occasion. There also was no evidence as to whether any of the statements regarding availability of mediation reflected by the evidence were intended to mean that mediation was available in one type of case but not in another. Such an intent would have to be inferred. But the evidence was not sufficient to infer such an intent. SOBAC complains that the statements in DEP's notices of intent as to availability of mediation under Section 120.573 force SOBAC to either waive rights or timely initiate administrative challenges under Sections 120.569 and 120.57 and incur litigation costs which might be unnecessary if mediation were initiated. But there was no evidence of any case in which the parties agreed to mediation under Section 120.573. (The failed attempt at mediation in DOAH Case No. 01-1949 was not conducted under Section 120.573.) Second, even if the parties agreed to mediation under Section 120.573, the evidence did not prove the likelihood that mediation would be successful; if not, and if administrative litigation resumed, mediation would have added to the cost of litigation.
The Issue Should Respondent be fined $500.00 for initiating repairs to an on-site sewage treatment and disposal system before obtaining a permit?
Findings Of Fact Respondent is engaged in the septic tank contracting business as a contractor licensed under Chapter 489, Part III, Florida Statutes. He does business as "Alpha." In association with his business Respondent provided services to residents at 224 North Orange Avenue, Orange City, Florida. This was related to a failed on-site sewage treatment and disposal system at that residence. To assist in providing repair service to the residence in Orange City, Florida, Respondent engaged Andy Trapp. Mr. Trapp's business is to assist septic tank contractors in obtaining necessary permits to perform septic tank contracting services. Mr. Trapp's occupation includes field work involving soil testing, measurements, and completion of necessary paperwork to assist the septic tank contractor in obtaining necessary permits. As permitting agency, usually Petitioner would accept applications submitted by Mr. Trapp in relation to the application for a permit to repair on-site sewage treatment and disposal systems, in that Mr. Trapp is recognized by Petitioner as being sufficiently qualified to submit information in support of an application for permit. On March 27, 1998, Mr. Trapp submitted an application for a permit to repair the on-site sewage treatment and disposal system at the Orange City, Florida, address, to include supporting information concerning the results of soil testing. That application was accompanied by the necessary fee to obtain a permit. The application was delivered to Petitioner's Daytona Beach, Florida, office as a matter of convenience to Mr. Trapp. Mr. Trapp realized that the actual processing of the permit application would be conducted by Petitioner's Deland, Florida, office. In that connection, Mr. Trapp realized that the application that he had submitted to the Daytona Beach office would be forwarded by interoffice transmittal to the Deland office, which would cause a delay in the processing of the application. In his experience Mr. Trapp has filed applications with the Daytona Beach office to be subsequently transmitted to the New Smyrna Beach office of the Petitioner, which ordinarily can be done late on the same day that the application was presented or by the next day. James McRae is an environmental supervisor for the Volusia Health Department, Environmental Health Office in Deland, Florida. It is his office that had ultimate responsibility for considering, and if appropriate, issuing a permit allowing Respondent to conduct necessary repairs of the failed on-site sewage treatment and disposal system at the Orange City, Florida address. Mr. McRae confirmed that the permit application, as submitted by Mr. Trapp for the repairs, had been received by the Deland office on March 30, 1998. In addition, the accompanying $57.00 fee had been transferred from the Daytona Beach office to the Deland office, as was customary, the custom being that the funds in support of an application would ultimately be received in the office from which the application would be processed and a permit number assigned, as applicable. Upon receipt of the application in the Deland office, a receipt was generated. Information concerning the permit application was placed in the computer. Assessment of the application was assigned to William Vander Lugt, Environmental Specialists II, who is part of the field staff for the Petitioner's Deland office. Beyond Mr. Vander Lugt's assignment to consider the application for the permit for the Orange City, Florida project, it was expected that he would do any necessary field work involving an inspection and any necessary soil analysis. If satisfied that the site was appropriate to effect repairs to the failed on-site sewage treatment and disposal system, Mr. Vander Lugt would issue a permit subject to approval by Mr. McRae. Mr. McRae identified that the usual turn around time for issuing permits is two to three days, assuming that the permit was applied for at Petitioner's office which would be responsible for assessing the application. In this instance the permit had been applied for at another office which delayed consideration of the permit application by the Deland office. The permit was approved on April 2, 1998, within three days of its receipt by the Deland office. Before the permit was issued, Respondent, through his employees, had commenced the repairs at the Orange City, Florida, address. The commencement of repairs was verified by an on-site inspection performed by Mr. Vander Lugt, on March 31, 1998. Although the supporting information presented by Mr. Trapp was in order and the fee had been paid, and there was no indication that any other problems existed which would prohibit the repairs from being conducted, Respondent was premature in commencing the work before the permit issued, and was unjustified in that choice.
Recommendation Upon consideration of the facts found and conclusions of law reached, it is RECOMMENDED: That a final order be issued which imposes a $500.00 fine against Respondent for initiating a repair of an on-site sewage treatment and disposal system without first obtaining a permit to do the work. DONE AND ENTERED this 24th day of September, 1998, in Tallahassee, Leon County, Florida. CHARLES C. ADAMS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 24th day of September, 1998. COPIES FURNISHED: Charlene Petersen, Esquire Department of Health 420 Fentress Boulevard Daytona Beach, Florida 32114 Michael J. Jedware Post Office Box 390073 Deltona, Florida 32739-0073 Angela T. Hall, Agency Clerk Department of Health 2020 Capital Circle, Southeast Bin A02 Tallahassee, Florida 32399-1703
The Issue The issues are whether respondents’ motions to dismiss the amended petitions should be granted on the ground they were not timely filed, or whether the time limitation for filing a request for hearing was equitably tolled.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background Petitioners, Judge Ray and Gerra Gatlin (petitioners or Gatlins), own a parcel of real property in the central portion of Baker County, Florida, generally located to the north of U. S. Highway 90 between Glen St. Mary and Macclenny, Florida. Respondent, St. Johns River Water Management District (District), is the state agency charged with the responsibility of issuing Water Resource Management (WRM) and Management and Storage of Surface Water (MSSW) permits within its boundaries. Respondent, Department of Transportation (DOT), is a state agency charged with the responsibility of maintaining the state highway system. On April 27, 1993, DOT filed two applications with the District seeking MSSW and WRM permits for a road widening and bridge replacement project on State Road 10, also known as U. S. Highway 90, in Baker County. After notices of receipt of application and intent to grant the applications were published in a local newspaper on June 3 and July 22, 1993, respectively, and no requests for a hearing were received, the District issued the two permits on August 10, 1993. On December 20, 1996, or 1,216 days after the permits had been issued, petitioners filed their petitions for administrative hearing to contest the issuance of the permits. The petition challenging the MSSW permit has been assigned Case No. 97-0803 while the challenge to the issuance of a WRM permit has been assigned Case No. 97-0804. As amended on February 10, 1997, the petitions generally allege that the Gatlins were not given actual notice of the WRM application as required by a District rule, DOT supplied inaccurate or false information in the applications as to the ownership of the property on which a portion of the work was to be performed, and the District's notice was confusing and misleading. Because of this, they contend the time limitation for challenging the permits was equitably tolled. Motions to dismiss the amended petitions on the ground they are untimely have been filed by the District and DOT, and they are the subject of these proceedings. Events Prior to Issuance of the Permits As early as 1990 or 1991, the DOT began planning for certain improvements to State Road 10 from County Road 125 in Glen St. Mary, Florida, east to State Road 121 in Macclenny, Florida. The work involved the widening of the road from two to four lanes and replacing an existing bridge. Excluding the work within the two municipalities, the total length of the project was less than two miles. On April 23, 1991, the DOT sent all property owners along U. S. Highway 90 a letter advising that a public meeting would be held on May 16, 1991, to discuss the proposed improvements. Although DOT records indicate that petitioners were on the mailing list, petitioners deny that they ever received a letter. In addition to a personal letter to each owner, notice of the meeting was published in a local newspaper. Another meeting with owners of property adjacent to S. Highway 90 was held on August 13, 1992, concerning the proposed project. Although a letter was sent to all property owners on July 21, 1992, advising that such a meeting would be held, petitioners deny that they ever received one. A notice of the meeting was also published in a local newspaper. The MSSW permit On April 23, 1993, DOT filed with the District an application, with various attachments, seeking the issuance of a MSSW permit. If approved, the permit would authorize DOT to construct surface water works, including the treatment of stormwater runoff by wet detention ponds, on an approximately eleven acre site. The application described the project as follows: The proposed facility typical section will be a four-lane roadway with a center turn lane through Glen St. Mary and unincorporated Baker Co. [T]hrough Macclenny, the typical section will be a two-lane roadway with a center turn lane. It further described the location of the project as follows: The segment of SR 10 (US 90) presented in this application begins approximately 500 feet west of the intersection of SR 10 and CR 125 and runs east to the intersection of SR 10 and SR 121. The project is located in Section 36, Township 2 south, and Range 21 east and Sections 31 and 32, Township 2 south, and Range 22 east in Baker County. In answer to a question regarding who owned the works to be constructed, DOT identified itself as the owner. The application did not require, however, that an applicant certify that it was the present owner of the property on which the proposed works were to be constructed. In fact, DOT followed its standard practice of not filling in the areas on the application form that asked for "Project Acreage" and "Total Acreage Owned" because it did not know exactly how much property it would need to acquire through exercise of its power of eminent domain until the District had approved the design of the proposed surface water works. It was clear, however, that DOT had the ability and intention to acquire whatever property was needed through eminent domain proceedings. Attached to the application were certain sketches. They did not depict the storm detention pond which was to be built on the Gatlins' property. Under an applicable District rule and statute, the District was required to give actual notice of the application only to persons who had previously filed a written request for such notice. Because petitioners had not made such a request, they were not given actual notice. In the absence of a written request, the statute allows constructive notice of the agency’s intended action to be provided by publication in a newspaper of general circulation in the county in which the work is to be performed. The specific requirements for this notice are found in Rule 40C-1.511(5), Florida Administrative Code. They include "a brief description of the proposed activity and its location," "location of the application," "statement of the District's intended action," "scheduled date of Board action," and "notification of administrative hearing opportunity." On July 22, 1993, the District published notice of its intended agency action in The Baker County Press, a weekly newspaper of general circulation published in Macclenny, Florida. The notice read, in pertinent part, as follows: The District gives notice of its intent to issue a permit to the following applicant on August 10, 1993: FLORIDA DEPARTMENT OF TRANSPORTATION, P. O. Box 1089, Lake City, Fla., 32056, application #4-003-0010AG. The project is located in Baker County, Sections 31, 32 & 36, Township 02 South, Ranges 21 & 22 East. The application is for the CONSTRUCTION OF A SURFACE WATER MANAGEMENT SYSTEM ASSOCIATED WITH THE WIDENING OF SR 10 (U.S. 90) FROM CR 125 TO SR 121. The receiving waterbody is the St. Mary's River. The file containing the above-listed application is available for inspection Monday through Friday except for legal holidays, 8:00 am to 5:00 pm at the St. Johns River Water Management District headquarters or the appropriate field office. The District will take action on the permit application listed above unless a petition for an administrative hearing is filed pursuant to the provisions of section 120.57, F.S., and section 40C-1.511. A person whose substantial interests are affected by the District’s proposed permitting decision identified above may petition for an administrative hearing in accordance with section 120.57, F.S. Petitions must comply with the requirements of Florida Administrative Code Rules 40C-1.111 and 40C- 1.521 and be filed with (and received by) the District Clerk, P.O. Box 1429, Palatka, Florida 32178-1429. Petitions must be filed within fourteen (14) days of publication of this notice or within fourteen(14) days of actual receipt of this intent, whichever occurs first. Failure to file a petition within this time period shall constitute a waiver of any right such person may have to request an administrative determination (hearing) under Section 120.57, F.S., concerning the subject permit application. Petitions which are not filed in accordance with the above provisions are subject to dismissal. Thus, the notice provided a brief description of the project and its location, the location of the application, the District's intended action, the scheduled date of Board action, and notification as to the right of a hearing. Although petitioners acknowledge that they never read the notice, they contend that, even if they had read it, the notice was nonetheless misleading and confusing in several respects. First, they point out that the legal notice identified the receiving waterbody as the St. Mary's River. The application, however, identified the receiving water as the South Prong St. Mary's River whereas the technical report of the District staff identified the receiving water as the Little St. Mary's River. The South Prong St. Mary's River and the Little St. Mary's River are the same river, and it eventually flows into the St. Mary's River approximately six miles north of petitioners' property. Therefore, the notice is technically correct since the larger St. Mary's River is the ultimate receiving water for the smaller tributary. Even if the notice was in error in this respect, however, for the reasons cited below, the error was immaterial and would not mislead or confuse readers. The notice provides further clarification on the project's location by stating that the project encompasses the "construction of a surface water management system associated with the widening of SR 10 (U.S. 90) from CR 125 to SR 121." This clearly alerts the reader that the project is on or near U. S. Highway 90 between Glen St. Mary and Macclenny, a short stretch of road less than two miles in length. Given this description, a reasonable person would not assume that the work would take place on the St. Mary's River, six miles to the north, as petitioners suggest. Petitioners also point out that the notice identified the location of the project as "Sections 31, 32 & 36, Township 02 South, Ranges 21 & 22 East," an area petitioners say encompasses some 1,900 acres of land. Because the MSSW project will actually involve only 11 acres of land, they contend the notice is misleading. Although the notice identifies three sections, and each section is one square mile, the notice alerts the reader that the project will be confined to the "widening of S. R. 10 (U. S. 90)" between Glen St. Mary and Macclenny, a relatively short stretch of roadway. Finally, the notice provided that a copy of the application was on file at the "appropriate field office" of the District should any member of the public desire more detailed information. Petitioners' property lies within Sections 31 and 36 and would therefore be affected by the application. Although they reside in Baker County, petitioners did not subscribe to The Baker County Press, and therefore they did not read the legal advertisement. Accordingly, a request for a hearing was not filed by petitioners by the August 10 deadline. When no requests for a hearing were filed within the fourteen day time limitation, the District took final agency action on August 10, 1993, and issued MSSW permit number 4-003-0010G. The WRM permit On April 27, 1993, DOT filed with the District an application, with attachments, seeking the issuance of a WRM permit. If approved, the permit would authorize the excavation and filling (dredging and filling) associated with the bridge replacement over the Little St. Mary's River, also known as the South Prong St. Mary's River, midway between Glen St. Mary and Macclenny on U. S. Highway 90. The dredge and fill project encompasses approximately one-half acre of land. The WRM application contained the same description and location of the project as did the MSSW permit application. Question 14 on the application form required an applicant to certify as to ownership of the property. The applicant could either indicate that it was the record owner of the property on which the proposed project was to be undertaken, or it could indicate that it was not the record owner, but it intended to have the requisite ownership before undertaking the proposed work. DOT checked off the box which indicated that it was the record owner. At hearing, a DOT representative agreed that this was an incorrect response since around 8,953 square feet of the land on which the dredging and filling would take place was then owned by petitioners. In hindsight, the DOT witness says he probably should have checked off both boxes since DOT owned most of the property and would acquire the remaining part through eminent domain proceedings before the project began. Acquisition of the land was clearly within DOT's power and authority. There is no evidence that DOT provided the information with the intent of misleading the District, or that the ownership information affected the District's decision. In 1988, the Department of Environmental Regulation (DER), now known as the Department of Environmental Protection, delegated its dredge and fill permitting authority to water management districts. In carrying out that delegation of authority, the districts were required to follow all applicable DER rules. One such rule, Rule 62-312.060(12), Florida Administrative Code, required that the District forward a copy of the application to and request comments from the adjacent waterfront property owners unless the number of owners was so extensive that personal notice was impractical. Petitioners own adjacent waterfront property, and it was not shown that the number of waterfront owners was so extensive that personal notice was impractical. To implement the above rule, question 5 on the application form required the applicant to identify all adjacent waterfront owners. DOT answered "See Attachment." At hearing, the individual who prepared the application "believed" that a list was attached to the application when it was filed with the District, but he could not locate a copy of the list in his file. The application was the first dredge and fill permit application for Baker County processed by the District. When the application was received by the District, a clerical employee reviewed the application to determine if it was complete. If an item was missing, the clerk was instructed to note the missing item on an "initial checkoff sheet." In this case, a "very, very cursory look" was made, and no box on the checkoff sheet was marked. This would indicate that the list was attached to the application. After this review was made, the application was sent to the technical staff for review. Whether the attachment was ever received by the District, and then lost or misplaced, is conjecture. In any event, a District witness acknowledged that there may have been a "mix-up" during the initial review. Because the District had no attached list, it gave no actual notice to adjacent owners, including petitioners, prior to publication of the notice. Therefore, the rule requiring actual notice on this type of application was not satisfied. Except for this instance, the District is unaware of any other occasion when a list of adjacent waterfront property owners, through inadvertence, was lost or not provided. On July 22, 1993, the District published notice of its intent to issue a permit in The Baker County Press. The notice read, in pertinent part, as follows: The District gives notice of the Intent to Issue a permit to the following applicant on August 10, 1993: FLORIDA DEPARTMENT OF TRANSPORTATION, P. O. Box 1089, Lake City, Fla., 32056, application #4-003-0010AG. The project is located in Baker County, Sections 31, 32 & 36, Township 02 South, Ranges 21 & 22 East. The application is for EXCAVATION AND FILLING ASSOCIATED WITH THE WIDENING OF SR 10 (U.S. 90) FROM CR 125 TO SR 121. The receiving waterbody is the St. Mary's River. The file pertaining to the above-listed application is available for inspection Monday through Friday except for legal holidays, 8:00 am to 5:00 pm at the St. Johns River Water Management District headquarters or the appropriate field office. The District will take action on the permit application listed above unless a petition for an administrative proceeding (hearing) is filed pursuant to the provisions of section 120.57, F.S., and section 40C-1.511, F.A.C. A person whose substantial interests are affected by the District’s proposed permitting decision identified above may petition for an administrative hearing in accordance with the requirements of Florida Administrative Code Rules 40C-1.111 and 40C-1.521 and be filed with (received by) the District Clerk, P.O. Box 1429, Palatka, Florida 32178-1429. Petitions for administrative hearing on the above application must be filed within fourteen (14) days of publication of this notice or within fourteen (14) days of actual receipt of this intent, whichever first occurs. Failure to file a petition within this time period shall constitute a waiver of any right such person may have to request an administrative determination (hearing) under section 120.57, F.S., concerning the subject permit application. Petitions which are not filed in accordance with the above provisions are subject to dismissal. Thus, the notice provided a brief description of the project and its location, the location of the application, the District's intended action, the scheduled date of Board action, and notification of hearing opportunity. Even though they did not read the notice, petitioners contend that it was "confusing and misleading to any readers." First, they point out that the legal notice identifies the receiving water as the St. Mary's River. Both the application and technical report of the District staff, however, identified the receiving water as the South Prong St. Mary's River. The South Prong St. Mary's River flows north and south and crosses under U. S. Highway 90 at the bridge replacement site. It eventually flows into the St. Mary's River, which is approximately six miles further north and forms the boundary between Florida and Georgia in that area. Therefore, the notice was technically correct since the St. Mary's River is the ultimate receiving water from the smaller tributary. Even if the notice erred in this respect, the error was immaterial and would not mislead the reader. This is because the cited sections, township, ranges and road being improved are all at least five miles south of the St. Mary's River, and thus the notice could not lull readers into believing that the project would actually be closer to that river, some six miles to the north. Petitioners also point out that, even though the dredge and fill project encompasses only one-half acre, the notice identifies the project as being located in Sections 31, 32, and 36, Township 2 South, Ranges 21 and 22 East, a tract of some 1,900 acres. These sections, township and ranges are the same ones included in the legal description of the then existing right-of-way for U. S. Highway 90 owned by DOT and which was attached to the application. While it is true that each section is one square mile, the actual work site within the sections was narrowed considerably by advice that the work would be "associated with the widening of SR 10" between Glen St. Mary and Macclenny. Given this information, a prudent person owning land on U. S. Highway 90 between the two municipalities would be alerted that the project might well impact his property. Finally, the notice provided that a copy of the application was on file for review if any member of the public desired more specific information. As a corollary to the above argument, petitioners contend that the notice implies that dredge and fill work will only be performed on DOT's existing right-of-way since the sections, township and ranges track the legal description of DOT's right-of-way along U. S. Highway 90. Again, however, only a "brief description" of the project's location is required, and the above description in the notice satisfies this requirement. Although petitioners reside in Baker County, they did not subscribe to the local newspaper, and therefore they did not read the legal advertisement. Accordingly, they did not file a request for a hearing. When no requests for a hearing were received within fourteen days after publication of the notice, on August 10, 1993, the District issued WRM permit number 12-003-0001G. C. Events After Issuance of the Permits On September 22, 1994, DOT sent to petitioners, by certified mail, a Letter of Notification regarding DOT's intention to acquire the interest in eight parcels of the Gatlins' property for the road improvement project. The letter was received by Gerra Gatlin on September 23, 1994. While the letter did not specifically state that a detention pond and bridge replacement project would be built on the Gatlins' property, it explained that DOT was currently planning the construction of a "highway facility" on State Road 10 and that its records indicated that petitioners owned property within the area which was needed for right-of-way on this project. The letter went on to describe the project in general terms, and it referenced parcel 140 which was owned by the Gatlins. On a separate parcel information sheet attached to the letter, parcel 140 was divided into three parcels: 140A, 140B, and 140C. The sheet noted that parts B and C were designated as "water storage" areas. Parcel 140B is 10.727 acres in size and will hold the stormwater detention pond currently being constructed by DOT. A portion of the dredge and filling related to the bridge replacement project will occur on parcel 140C. Ray Gatlin acknowledged that he became aware of a "pond" when he initially reviewed the packet, but he was not sure in which part of parcel 140 the pond would be located since the "printing was off" on the drawings, and he could not find parcel 140C. Therefore, he immediately hired a Jacksonville attorney, Robert S. Yerkes, to represent him and his wife in the condemnation matter. On October 31, 1994, Yerkes sent a letter to DOT requesting a copy of "the current right way map and construction plans, as well as the present schedule for aquisition and construction." On November 17, 1994, DOT sent Yerkes the right-of-way maps but noted that "[c]onstruction plans are still not available." Whether Yerkes requested the construction plans after that date is not of record. On May 22, 1995, a DOT right-of-way specialist met with Yerkes and Ray Gatlin regarding the acquisition of the Gatlins’ property. On July 19, 1995, DOT initiated an action in eminent domain against petitioners, and several other landowners, by filing a petition in the Circuit Court of Baker County. Among other things, the petition sought to condemn parcels 140A, 140B, and 140C owned by petitioners. An Order of Taking was entered by the court on September 6, 1995, which conveyed fee simple title of parcel 140, and its parts, to DOT. When Yerkes "didn’t get the job done," the Gatlins hired new counsel, who made an appearance on July 31, 1996. Just prior to the appearance of new counsel, and because of "a problem with the assessment," the Gatlins hired an environmental consultant, Peter M. Wallace, to verify whether DOT had correctly told them that no jurisdictional wetlands existed within the parcel being condemned. At this time, the Gatlins were in a dispute with DOT over the value of their property. After determining that wetlands existed on the parcel, Wallace made inquiry in late July 1996 with a District employee, Christine Wentzel, to ascertain if any permits had been issued to DOT for a project on U. S. Highway 90 between Glen St. Mary and Macclenny. Wentzel was unaware of any permits being issued, but she referred Wallace to Helen Cortopassi, who would have reviewed the applications three years earlier. Cortopassi told Wallace that no permits relating to this project had been issued. Because Wallace believed that the storm detention pond would impact wetlands, and therefore required a review by DER or the United States Army Corps of Engineers, he made similar inquiries with those two agencies regarding the issuance of permits. He was assured that those two agencies had not issued permits. In late September 1996, Cortopassi telephoned Wallace and advised him that a further review of her files revealed that two permits had been issued for the project. Because Wallace had inquired about permits for a project on U. S. Highway 90, and Cortopassi had created a file for the project under State Road 10 (rather than U. S. Highway 90), she had failed to discover them when Wallace first made his inquiry two months earlier. On October 15, 1996, Wallace went to the DOT office and reviewed its files pertaining to the project. He found copies of the issued permits and a set of construction plans which revealed a pond. A public records request filed by the Gatlins' counsel with DOT in September 1996 was later granted, and copies of the applications were eventually obtained from DOT on December 9, 1996, or almost three months after the request was made. Within fourteen days thereafter, or on December 20, 1996, the Gatlins filed their initial requests for a hearing. DOT did not begin work on the project until March 1997, or some three months after the requests for hearing were filed. Photographs received into evidence show that, in April 1997, some excavation work was being done around the bridge site. Work has continued during the pendency of this proceeding. At least a small portion of the storm detention pond will be built in wetlands. The District made no review of the wetlands impact associated with the pond. Had this been done, a disclosure of the pond in the dredge and fill permit application would have been required. Petitioners contend that, if actual notice of the WRM had been given, as required by rule, and a wetlands impact performed, in this way they would have had actual notice of the MSSW application by simply reviewing the WRM application. The District contends, however, that the content and manner of notice would not have changed.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order granting the motions to dismiss and dismissing the amended petitions for hearing in Case Nos. 97-0803 and 97-0804 with prejudice. DONE AND ENTERED this 14th day of July, 1997, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675, SUNCOM 278-9675 Fax Filing (904) 921-6847 \ COPIES FURNISHED: Filed with the Clerk of the Division of Administrative Hearings this 14th day of July, 1997. Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1489 Palatka, Florida 32178-1489 J. Victor Barrios, Esquire 1026 East Park Avenue Tallahassee, Florida 32301-1673 Susan K. S. Scarcelli, Esquire Post Office Box 3399 Tampa, Florida 33601-3399 Nancy B. Barnard, Esquire Post Office Box 1429 Palatka, Florida 32178-1429 Francine M. Ffolkes, Esquire Mary S. Miller, Esquire Haydon Burns Building, Mail Station 58 Tallahassee, Florida 32399-0458
The Issue The issue for consideration in this case is whether the Respondent, Hi Hat Cattle and Grove, should be issued water use permit 204387.03, to withdraw groundwater from the wells on its property, and if so, in what amount and under what conditions.
Findings Of Fact At all times pertinent to the issues herein, the Respondent, District, was the state agency responsible for the permitting of consumptive water use within its area of geographical jurisdiction. The Respondent, Hi Hat, is a family owned farming and ranching operation in eastern Sarasota County with water wells on its property. The Intervenor, City of Sarasota, is a municipality in Sarasota County which operates wells in the general area of those operated by Hi Hat, and which has an agreement with Hi Hat for the latter's use of treated wastewater pumped from the city's treatment plant to Hi Hat Ranch. The Petitioner, Wyatt S. Bishop, Jr., is a property owner and resident of Sarasota County whose property is located near the Hi Hat Ranch, and whose potable water is drawn from a well on his property which utilizes both the surficial and intermediate aquifers which are penetrated by the wells on Hi Hat Ranch. Hi Hat Ranch consists of 11,000 acres owned by Hi Hat Cattle and Grove, the family owned business which operates it, and an additional 3,227 acres leased from the City of Sarasota. Agricultural operations, including citrus farming, truck farming, sod farming, and grazing have been conducted on the ranch since the mid 1940's. In February, 1990, Hi Hat applied to the District for a permit to withdraw and use water from some 14 wells located on its property. It requested an annual average of 6,267,000 gallons per day, (gpd), and a peak monthly rate of 32, 668,000 gpd. Upon receipt by the District, the application was assigned a number, (204387.03), and was submitted for evaluation by the District staff for conformity with applicable District rules and policies. When the staff evaluation was completed, the District issued a staff report and proposed staff agency action in which it indicated its intention to issue a permit authorizing water to be drawn from the wells at a rate of 6,570,000 gpd, average annual, a peak monthly rate of 14,300,000 gpd, and a maximum daily rate of 5,210,000 gpd. In conducting its evaluation, the District staff relied upon the District's Basis of Review For Water Use Permit Applications which contains within it the provision for use of a "water use model" in assessing the need and appropriateness of water withdrawal amounts. This model, known as the Blaney- Criddle Model considers numerous factors in the evaluation, including rainfall, soil characteristics, irrigation methods used, and proposed crop types, all in an effort to determine a reasonable estimate of the applicant's supplemental water needs. Hi Hat's application was evaluated primarily by Marie Jackson, a Hydrologist III employed by the District, and an expert in hydrology, who has, over the years, reviewed between 350 and 400 permit applications, of which approximately 90 percent have been for agriculture. She is, therefore, quite familiar with the specifics of agricultural water use needs. Her evaluation of Hi Hat's application was done in the same manner as the others she has done and utilized the same tests, measurements and factors for consideration in arriving at her conclusion. In its application, a renewal with modification sought to increase average annual quantities due to a change in crop plans, Hi Hat indicated that its criteria for water use was based on certain agricultural uses and application rates. These included: low volume under tree spray irrigation of 778 acres of citrus at an application rate of 17.2 inches/year plus one inch/year for frost and freeze protection. open ditch irrigation of 135 acres of sod at an application rate of 30 inches/year. open ditch irrigation of 1,367 acres of improved pasture at an average application rate of 26.6 inches/year. overhead spray irrigation of 1,200 acres of improved pasture at an application rate of 20.3 inches/year. open ditch irrigation of 110 acres of spring peppers at an application rate of 30.0 inches/crop, and open ditch irrigation of 110 acres of fall peppers at an application rate of 45.2 inches/crop. Applicant also stipulated that the peak monthly quantities that it requested would be utilized for pasture, sod and citrus irrigation during the month of May. The proposed maximum quantities were for frost and freeze protection of citrus only. In January, 1989, Hi Hat entered into a contract with the City of Sarasota under which the City was obligated to deliver reclaimed water from its wastewater treatment plant to a "header" located on the ranch which thereafter distributes the water through pipes to "turnouts" located at various high points on the property. From these, the water is then discharged into a system of ridges and furrows for distribution of the water across the needed area. The reclaimed water is used to irrigate approximately 5,403 acres of ranchland. The Contract provides for minimum and maximum amounts of water to be delivered as well as for water quality standards which must be met. In periods of adequate rainfall, when irrigation is not required, any treated wastewater which is not needed is stored in a 185 million gallon holding pond on City property located adjacent to the ranch. When needed, water can be fed into the wastewater distribution system described above from the holding pond. This reclaimed water, whether from the pond or direct from the header, can also be utilized to irrigate citrus crops, but this requires a filter system which has not yet been able to operate properly. Therefore, no reclaimed water has yet to be utilized for citrus irrigation on the ranch. At an average annual flow of 6.2 million gallons per day, the pond has the capacity to hold enough treated water for almost 30 days. Not all wells on Hi Hat Ranch are active wells. Several of the wells are classified as standby wells which are intended to be used only to back up the reclaimed water delivery system and are located, normally, beside the "turnouts." In the event the reclaimed water is not available from the city, the standby wells can be utilized to provide water to the ridge and furrow system used to irrigate pasture land. The standby wells are numbers 1, 6, 7, 11, 13, 14, and 15. Well number 5, also identified as a standby well in the staff report and in the draft permit was mistakenly so identified. The draft permit contains several special conditions which impact on the drawing of water under the terms of the permit. Significant among these is Special Condition 33 which prohibits the withdrawal of water from any of the standby wells unless the reclaimed water supply from the city is interrupted. Special Condition 27 requires the installation of a flow meter on any standby well that becomes active as a result of permanent discontinuance of the reclaimed water supply. With regard to flow meters, Special Condition 22 requires flow meters on all of Hi Hat's wells. Ms. Jackson, however, indicated this was in error and has recommended that the standby wells be deleted from that Special Condition. When that is done, only those wells actively producing water on a regular basis would require the installation of flow meters. In its analysis of the application for permit, the District staff considered several factors pertinent to the impact the well would have on the water supply in the area and its effect on other users. These factors include hydrologic impacts, well condition, the history of water use at the ranch, the reliability of the reclaimed water system and its ability to provide a uniform source, and the city's water reuse policy. Addressing each individually, and starting with the hydrologic impact of the withdrawal of the requested amounts, the District considered the nature of the existing wells and how they are constructed and maintained. The District assumed, because the data regarding the construction of the existing wells was incomplete and insufficient to properly disclose the status of casing on each well, that they were shallow cased. As a result, the calculations incorporating this assumption indicate a situation that would occur in its most aggravated form. The parties agreed that Hi Hat's wells are shallow cased and probably go no deeper than 90 feet. To determine, as much as possible, the projected drawdowns in the surficial and intermediate aquifers that might be expected if Hi Hat withdrew the amounts of water proposed, the District utilized the "MODFLOW" computer model which factors in simultaneous peak withdrawals from all 14 of the wells along with a 90 day no rainfall drought condition. This, too, contributes to a worst case scenario, and the resultant figures are considered to be conservative estimates of the hydrologic impact of the water withdrawal. Notwithstanding, the application of this computer model resulted in the indication that, as to the surficial aquifer, the drawdown at Mr. Bishop's property located approximately one half mile from the ranch border, would be no more than .055 feet. Since normal fluctuations in the surficial aquifer during the course of the year can be as much as 6 feet, the projected drawdown as a result of Hi Hat's withdrawals was considered insignificant. Applying the same assumptions and utilizing the same computer model as it relates to the intermediate aquifer resulted in an indication of a drawdown of no more than 2.3 feet at Mr. Bishop's property. Since annual fluctuation in the intermediate aquifer can range from 15 to 20 feet normally, the District considers that any reduction of less than five feet in the intermediate aquifer is insignificant. The permit held by Hi hat currently allows for the withdrawal of more water than would be withdrawn under the proposed permit as conditioned and is consistent with the proposed reduction in allowable withdrawals. Considering that factor, as well as the prohibition against withdrawals from standby wells as long as reclaimed water is available, the actual impact of the water withdrawals consistent with the proposed permit would be substantially less than the computed prediction which includes production from all wells. Drawdown contours are defined across the entire effected area. One of the levels is a 4 foot contour, and when a computer simulation indicates that the 4 foot contour includes a withdrawal previously or otherwise permitted, the District will generally conduct a cumulative impact analysis. In this case, however, since there was only one golf course well within the area circumscribed by the 4 foot contour line, and since this withdrawal was too small to have effected an evaluation, it was not done. The condition of the wells on the Hi Hat Ranch has some bearing on whether or not the application for additional withdrawal of water should be granted. These wells are almost 30 years old, having been drilled in the 1960's. As a result, there is little information available regarding their construction detail. This is not necessarily unusual for agricultural wells, and there is evidence that there are many similar wells in use within the District. The reason for this is that at the time the wells were drilled, information regarding their depth, casing and other matters were not required to be kept or reported. However, there is no indication the wells are in any way violative of well construction criteria and their use has been authorized continuously since 1977. When he prepared Hi Hat's application, Mr. Turner included much the same information regarding the wells as pertains as to depth and diameter which he had previously submitted in earlier applications and which had been accepted. In each case, casing depths had been reported as unknown. Notwithstanding the information contained in some old well logs relative to only a few of Hi Hat's wells, this information is in no way definitive and it is difficult to describe anything specific with the majority of these wells. Nonetheless, as already found, it is stipulated that most are approximately 90 feet deep. It is reasonable to assume that the existing wells, however, are cased only to a shallow depth, and that in many cases, the existing casings have corroded away, either totally or in part. This can cause an intermixing of water from the separate aquifers, but whether this is in fact happening depends upon factors specific to that particular well. Petitioner did not present any evidence to show that as a result of the condition of Hi Hat's wells, any degradation is occurring in the more potable, surficial aquifer as a result of intermixing with water from the intermediate aquifer on or around the Hi Hat Ranch. In Ms. Jackson's opinion, and there appears to be no evidence to contradict it, the amount of drawdown which would occur as a result of maximum pumping at Hi Hat Ranch would not be sufficient to cause poorer quality water from the Floridan aquifer to percolate upward (upcone) into the better quality water of the two upper aquifers even during drought conditions. By the same token, there is no evidence that drawdown would encourage or permit salt water intrusion. Petitioner attempted to show by the records kept on the various Hi Hat wells that many of them have been abandoned and are no longer operative and should not be allowed to fall within the parameters of this permit. He testified clearly that over the years, the level of water in his potable water well has lowered and presumed that this was the result of increased water usage by other entities which draw from the aquifer into which his well is sunk. Water level, however, depends upon numerous factors, of which usage is only one. Others include recharging of the aquifer and the amount of rainfall and other recharge sources not only in the immediate area but across the large area which feeds the aquifer. Mr. Bishop did not present any evidence showing a causal connection between the lowering of the water in his well, or the degradation in water quality he claims to have experienced, and either the drawdown caused by Hi Hat's operation or by aquifer intermixing. He indicated, and it is not disputed, that within the past year, he has had to take measures to improve the water quality in his potable well, but, again, he has not presented any evidence to show this was caused by Hi Hat's ground water withdrawals. In its long range planning, the District intends to implement a program to rehabilitate old wells, and when that program is implemented, almost every agricultural well within the District may require recasing or redrilling. This program will not be implemented for several years, however. In an effort, however, to insure that all reasonable precautions are taken to see that approval of any petition for withdrawal does not have an unacceptable adverse impact on the water needs of the surrounding community, in its analysis of this application, and in all cases, the District makes certain assumptions when adequate empirical data is not available. In this case, pertaining to the unavailability of information regarding Hi Hat's wells, the District assumed that all wells were shallow cased, and this placed the application in the worst possible light. Shallow cased wells allow more upconing and aquifer intermixing. Nonetheless, the amount of water permitted to Hi Hat, even if not used, could impact on Mr. Bishop and other adjoining owner's use of additional water as a result of a possible change to their permitted quantities. However, to compensate for this, the District has also included a special condition, (#26), which requires Hi Hat to log all 14 of its wells within the term of the permit, (7 years), which will require at least 2 wells be done each year. The cost of that action will be between $800 and $2500 per well. Another condition, (#31), requires Hi Hat to look into any complaint from adjacent property owners regarding adverse impacts due to water withdrawal, to report the results of its inquiry to the District, and to mitigate, as much as possible, all adverse impacts due to its withdrawal. Mr. Bishop claimed, and introduced evidence purporting to demonstrate, that many of the wells on the Hi Hat Ranch, which are covered by the permit applied for here, are no longer in use and have been abandoned. In response, Mr. Turner, who has been actively engaged in the ranch's operations for at least the past four years, indicates from his personal knowledge, that all 14 wells included in the permit applied for have been operated within the past two years, and all are capable of producing water. It is so found. Not all wells, however, have been operated at all times. Crop rotation and a varying need for groundwater has resulted in some wells not being used at some times. This is, of course, commonplace in agriculture and to be expected as a result of crop planning programs. Admittedly, an accurate figure for the amount of water which has been withdrawn from the 14 wells cannot be established because these wells do not have, and were not required to have, flow meters. Two of the wells were fitted with hour meters in January, 1989, but because the capacity of the pumps on those wells is variable, a precise estimate of volume pumped cannot be determined. The meters measured only the number of hours the pumps were in operation and not the amount of water passed through the pumps. Evidence was presented, however, to show that wells have been utilized at the ranch since the 1960's, and in 1977, some 14 years ago, following District implementation of a consumptive water use permit program, the ranch first applied for water withdrawal permits. These permits have been renewed as required and all water usage since the implementation of the program has been permitted. Turning to the reclaimed water supply, the delivery system, incorporating a program to pump reclaimed water from the treatment plant all the way back out to the ranch site, is subject to material failure and operator error, and either one can occur at any number of places along the system route. Each could result in interruption of the delivery of the reclaimed water to the ranch. The system is far more complex than would be the use of on-site wells for delivery of ground water. One two week shutdown in the system was occasioned by a major pipe failure as a result of pressure building up in the pipes. Were it not for the fact that a contractor was already at the ranch with replacement parts on hand to effect expeditious repair of the system, the shutdown could have lasted considerably longer than it did. This is not the only interruption, however. Several main line leaks and valve problems have caused the system to be shut down on several occasions for short periods of time. The filter system required for the water destined for the citrus area is problematical, and so far this area of the ranch has not received any reclaimed water in the 10 months the system has been in operation. Mr. Bishop argues that the wet weather holding pond is a solution to the reliability problems with the pipe line, but the pond has had problems of its own. Sand in the water, which comes from the holding pond, has been the primary difficulty in the filter system for the citrus area, and algae growth in that pond has the potential to create other filter problems. Delivery of the water from the pond is not accomplished by a gravity system, but instead, requires the use of pumps powered by an electric motor. In the event of a power failure, this source would be unavailable. Discounting all of the above, however, and assuming, arguendo, that all systems were in top operating condition, the fact remains that the delivery system from the pond to the distribution system is not adequate to supply the amount of water that would be necessary to have an effective freeze protection program. In any case, the reclaimed water supply is not the panacea for all water shortage problems experienced at Hi Hat Ranch. In the first place, the quality of the reclaimed water is generally lower than that of the groundwater which would come from wells on the ranch. Also, the City's treatment process does not remove from the water all the pollutants that are of concern to the farm operators. For one thing, total dissolved solids in the reclaimed water are considerably higher than in the ground water, and high dissolved solid levels can be harmful to citrus crops. In fact, the Institute of Food and Agricultural Sciences recommends that citrus irrigation water not exceed total dissolved solid ranges of from 1000 to 1500 milligrams per liter, (mpl). Testing done on the reclaimed water delivered to Hi Hat Ranch showed it averaged between 1200 and 1500 mpl. Though within recommended parameters, it was toward the high end. Further, reclaimed water is not totally interchangeable with ground water for all agricultural purposes. It cannot, by law, be applied to certain types of ground crops such as melons, nor can it be used for overhead citrus irrigation. There is also a restriction on the use of reclaimed water for pastures on which dairy cattle will be grazed. This all results in a restriction on the options available to the farmer who chooses to use reclaimed water in his irrigation plan. As a result, many farmers try not to use reclaimed water if they have access to adequate amounts of groundwater from on- site wells. Notwithstanding all the above, the parties agree that the use of reclaimed water for irrigation purposed is in the public interest. The District encourages it but nonetheless concedes that even with the availability of reclaimed water, a farmer should have access to wells on his property, in a standby capacity, as an alternative source of water to support his farming activities. Not only that, the agreement between the City and Hi Hat provides for Hi Hat to maintain its water use permit even while receiving reclaimed water from the City. Hi Hat is not the only farm operation with whom the City has negotiated in a effort to expand its wastewater distribution program. It has found in those negotiations, that most farm producers are not willing to rely totally on reclaimed water for all their irrigation needs, and it has concluded that were it mandatory that a farmer give up his on-site ground water withdrawals in order to utilize reclaimed water for a part of his needs, most would be reluctant to use it at all. This would seriously interfere with the City's ability to dispose of its surplus reclaimed water consistent with its policy. Even though Hi Hat's property lies within the Eastern Tampa Bay Water Use Cautionary Area, the rule pertaining thereto is inapplicable to Hi Hat because Hi Hat filed its application for permit, which was deemed complete, prior to the adoption of the rule. Nonetheless, water use officials agree that the proposed permit is consistent with the rule emphasis on the use and reuse of reclaimed water, and the District does not object to backup wells being permitted as supportive of the District's desire to keep ground water within the ground.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that Hi Hat Cattle and Grove be issued water use permit No. 204387.03, within the limits of the authorized quantities as indicated in the intent to issue, subject to conditions contained therein; except that the permit be amended to show well No. 5 as a non-standby well, and to delete standby wells from the terms and requirements of Special Condition 22. RECOMMENDED this 17th day of May, 1991, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of May, 1991. APPENDIX TO RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: Accepted Accepted and incorporated herein. Accepted and incorporated herein. - 6. Accepted and incorporated herein. 7. - 11. Accepted. - 15. Accepted and incorporated herein. Accepted. Accepted. & 19. Accepted and incorporated herein. - 22. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 28. Accepted and incorporated herein. Accepted and incorporated herein. Rejected. She testified that Condition 28 of the permit provides this. Accepted. Accepted. Accepted and incorporated herein. Accepted. & 36. Accepted. Rejected as not supported by the evidence except that the method permitted was the method being used. - 40. Accepted. Ms. Jackson indicated she "assumed" some wells were drilled into the Florida aquifer. Rejected. Accepted as qualified by the comment, "depending on the respective potentiometric heads." - 47. Accepted. Accepted but incomplete. This is because they did not feel it was necessary under the circumstances. - 51. Accepted. Accepted. Accepted. Accepted. Accepted. Accepted and incorporated herein. Accepted. Redundant. - 61. Accepted. - 66. Accepted and incorporated herein. Accepted. More a restatement of testimony than a Finding of Fact Accepted and incorporated herein. & 71. Accepted and incorporated herein. - 74. Accepted. Accepted. First sentence accepted. Second portion rejected since cited case involves active wells versus standby, as here. The comparison made is accepted. The conclusion drawn as to validity is rejected. & 79. Accepted. FOR THE RESPONDENTS AND INTERVENOR: & 2. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. & 6. Accepted and incorporated herein. 7. - 10. Accepted and incorporated herein. 11. - 13. Accepted and incorporated herein. - 17. Accepted and incorporated herein. Accepted. Accepted. Accepted and incorporated herein. Accepted and incorporated herein. & 23. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Not a Finding of Fact but a comment on the evidence. 27. Accepted. 28. & 29. Accepted and incorporated herein. 30. - 33. Accepted and incorporated herein. 34. - 37. Accepted and incorporated herein. 38. Accepted. 39. Accepted. 40. - 42. Accepted and incorporated herein. Accepted and incorporated herein, & 45. Accepted. 46. & 47. Accepted and incorporated herein. COPIES FURNISHED: Wyatt S. Bishop 5153 Tucumcari Trail Sarasota, Florida 34241 Bram D.E. Canter, Esquire Haben, Culpepper, Dunbar & French, P.A. 306 N. Monroe Street Tallahassee, Florida 32301 Edward B. Helvenston, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Barbara B. Levin, Esquire de la Parte & Gilbert 705 East Kennedy Blvd. Tampa, Florida 33602 Peter G. Hubbell Executive Director SWFWMD 2379 Broad Street Brooksville, Florida 34609-6899