CONSTRUCTION INDUSTRY LICENSING BOARD vs. STUART L. REISE, 87-003955 (1987)
Division of Administrative Hearings, Florida Number: 87-003955 Latest Update: Sep. 19, 1988

The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.

Florida Laws (4) 120.57489.105489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD W. ANDREWS, 87-004395 (1987)
Division of Administrative Hearings, Florida Number: 87-004395 Latest Update: Feb. 29, 1988

Findings Of Fact At all times material hereto, Respondent has been a certified pool contractor in the state of Florida, having been issued License No. CP C029646. At all tines material hereto, Respondent has been the qualifying agent for Pools by Andrews, Inc., and the owner of that company. On August 21, 1986, George Silvers, a building inspector for the Village of Tequesta, saw people working at a pool site with no identification on the truck parked nearby. When he stopped, he discovered a crew installing- plumbing pipes for a swimming pool. When he asked for identification, Roland R. Androy identified himself as an employee of Pools by Andrews, Inc. Although "piping a pool" does not itself require specialized licensure, Silvers asked Androy if he were a licensed contractor, and Androy said that he was not. By way of further identification, Androy produced a personal card which read "Andy's Elite Pools." Silvers "red flagged" the job stopping construction and filed a complaint with the Department of Professional Regulation. Androy was an employee of Pools by Andrews, Inc., for approximately one year in 1974. He returned to Florida and again became an employee of Pools by Andrews, Inc. in February, 1985. During the remainder of that calendar year Androy drew a regular weekly salary from that company, received holiday pay, and drove a company vehicle. Taxes were deducted from his salary check, and the company provided him with health insurance. Androy was a fast worker and frequently finished piping pools early in the day at which time he was given odd jobs to perform for the company such as building shelves in the warehouse. Androy decided that he could make the same amount of money and substantially shorten his work day if he were paid on a piecework basis rather than for an eight hour work day. That way he would also be able to 'moonlight' by using his free time performing maintenance and repair work for swimming pool owners. Respondent agreed to pay Androy on the basis of piecework rather than a 40-hour work week. Since January 1, 1986, Androy appears at Pools by Andrews, Inc., at 6:00 a.m. six days a week at which time he is given a list of pools to plumb that day. All materials and equipment necessary to perform the work are supplied by the Respondent. When Androy finishes, he goes home. Every Friday he gives Respondent a list of pools that he piped that week, and Respondent pays Androy by check. Because Androy wanted to be free to leave when he finishes that day's work, he no longer drives a company truck but rather drives his own truck so he does not have to return the truck before he can go home. Under the new salary arrangement, he is paid by the job and no longer receives a regular weekly salary or holiday pay or health insurance. Further, Respondent has ceased deducting withholding tax and social security taxes from Androy's paycheck. The card which Androy gave to Inspector Silver is a card that he used prior to moving to Florida. He had new cards printed with his Florida address and telephone number. He uses them when persons ask how they can get in touch with him. Respondent had no knowledge of Androy having or using such a card. As a certified pool contractor, Respondent is aware of the requirements for licensure, that is, installation of a swimming pool must be done by a licensed contractor. However, there is no requirement for licensure for that portion of the installation known as piping a pool. Rather, that work can be performed by anyone under the supervision of a licensed contractor. Further, no separate permit is required for that "plumbing" portion of pool installation. All permits for the job in question were obtained by Pools by Andrews, Inc., pursuant to Respondent's state licensure. No other permits were necessary for the job, including the work done for Respondent by Androy. Respondent (like Androy) believes that Androy is an employee of his and not an independent contractor or a subcontractor. There is no intent on Respondent's part to evade he state licensure requirements. Respondent has had no other disciplinary actions filed against him.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that a Final Order be entered finding Respondent not guilty and dismissing the Administrative Complaint filed against him in this cause. DONE and RECOMMENDED this 29th day of February, 1988, at Tallahassee, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-4395 Petitioner's proposed findings of fact numbered 1, 2, and 4-6 have been adopted either verbatim or in substance in this Recommended Order. Petitioner's proposed finding of tact numbered 2 has been rejected as not being supported by any evidence in this cause. Petitioner's proposed finding of fact numbered 7 has been rejected as being contrary to the evidence in this cause. Respondent's proposed findings of fact numbered 1, 2, 6, 8, 9, and 12 have been adopted either verbatim or in substance in this Recommended Order. Respondent's proposed findings of fact numbered 3, 7, and 10 have been rejected as being irrelevant to the issues under consideration herein. Respondent's proposed findings of fact numbered 4, 5, and 11 have been rejected as not constituting findings of fact but rather as constituting argument of counsel or conclusions of law. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Edward W. Andrews 8300 Resource Drive Riviera Beach, Florida 33404 William O'Neil, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. FREDERICK G. GERVIA, 83-000037 (1983)
Division of Administrative Hearings, Florida Number: 83-000037 Latest Update: Jun. 01, 1984

The Issue This case concerns the issue of whether the Respondent's license as a certified general contractor should be suspended, revoked, or otherwise disciplined for multiple violations of Chapter 489 of the Florida Statutes. Specifically, the Respondent is charged with having been found guilty of a crime which relates directly to the practice of contracting in violation of 489.129(1)(b)(1979); willfully or deliberately disregarding and violating the applicable building code in violation of Florida Statute 489.129(1)(d)(1979); aiding and abetting an unlicensed person in his evasion of the Contracting Practice Act in violation of 489.129 (1)(e)(1979); knowingly combining or conspiring with an unlicensed person by allowing Respondent's license to be used by said unlicensed person with the intent to evade the provisions of the Contracting Practice Act in violation of Florida Statute 489.129 (1)(f)(1979); and, violating Florida Statute 489.129(1)(j)(1979) by failing to renew his license every two years and by failing to supervise a construction project. At the formal hearing, the Petitioner called as witnesses the Respondent, Frederick G. Gervia, Leroy S. Duncan, John Knezevich, and Evodio Llevado. Respondent testified on his own behalf and also called as a witness Mr. L. Perry Curtis. Petitioner offered and had admitted without objection eight exhibits. The Respondent offered no exhibits into evidence.

Findings Of Fact The Respondent is a certified general contractor holding License No. CG C003114. Respondent is also a registered general contractor having been issued License No. RG 0009802. Respondent's license CGC003114 was delinquent as of December 7, 1981, and had not been renewed for the 1981-83 licensing period. On October 11, 1981, Fiberglass Pools of South Florida, Inc. entered into a contract with Mr. Leroy Duncan to construct a fiberglass pool at Mr. Duncan's residence located at 1385 N.W. 192nd Terrace, Miami, Florida. On November 10, 1981, Respondent applied for a building permit (see Petitioner's Exhibit 2) for the pool construction at Mr. Duncan's home. The Respondent signed the application in the block designated "Signature of Qualifier or Owner-Builder". The application named Gervia Construction Company, address 2810 S.W. 78th Court as the building contractor. Gervia Construction Company was neither the general contractor nor a subcontractor in connection with the construction of the Duncan pool. At the time that he applied for the building permit, Respondent was qualifying agent for Gervia Construction Company, 2810 S.W. 78th Court, Miami, Florida 33155. The Respondent has made no request to qualify under either of his licenses as the qualifying agent for Fiberglass Pools of South Florida, Inc. Neither Fiberglass Pools of South Florida, Inc. or its principals were licensed. Prior to and during construction, Mr. Leroy Duncan had no dealings at all with the Respondent or Gervia Construction Company. Mr. Duncan's dealings were primarily with Douglas Lake of Fiberglass Pools of South Florida, Inc. Mr. Duncan observed a substantial portion of the construction, but was not present during the form work for the deck. At no time did Mr. Duncan observe the Respondent working on the construction of the pool at his home. The only work performed by Mr. Gervia on the Duncan pool contract was to check the plumbing prior to the county inspection. The pool was actually installed by two principals of Fiberglass Pools of South Florida, Inc. and two helpers. These persons were neither supervised nor controlled by the Respondent during construction. During the time period October 11, 1980, through initial construction of the Duncan pool, the Respondent was employed by Fiberglass Pools of South Florida, Inc. at a salary of $350 per week. One of his duties was to pull permits. Although the Respondent was also hired to supervise all field construction, at the time the Duncan pool was contracted for and constructed, his supervisory status had been eliminated. The Respondent performed no supervisory duties in connection with the Duncan pool construction. All payments from Mr. Duncan, including two checks totaling $950 and a cash payment of $6,230 were made to Fiberglass Pools of South Florida, Inc. No payments were made to the Respondent or Gervia Construction Company. Mr. Gervia did not hire or fire any of the persons who worked on the Duncan pool and kept no records relating to payments received or monies spent on the job at the Duncan residence. Subsequent to the pool being completed, substantial problems and flaws in the Duncan pool developed. The following problems were present in the pool: (See Petitioner's Exhibit 5.) Seven patches on South wall, below water line, are rough, discolored and flaking. The largest two are approximately 12" in diameter and 12" x 4". There is a very small depression in the shallow end seat. The pool flange at the ladder is full of depres- sions, making the edge very rough. Flange cracks at three corners are excessive and need repair. The Southwest corner has a vertical crack down the wall about 1'. See exhibits II, III, IV, and V. The pool wall thickness at corners was 3/8" but north, south and west wall were 7/32" to 1/4" thick. Several dark circles about 2" in diameter are located around perimeter flange and show where holes were drilled and patched poorly. . . Four hydrostatic valves seem high to effectively counteract buoyancy, but approved plan approves 1' above floor at deep end plus one valve in main drain [could not check with pool full]. See notes 9, 10 & 11 - William Meyers plan. 13' x 30' x 72" pool actually measures 12'-11" x 29'-8" x 71 1/8" deep. Vertical floor variations in shallow end are about 1 3/4". Seems depressions occur between ribs. A small bow occurs at Northwest corner near surface of water. Area covers about 18" square. Some concrete voids occur beneath pool lip. Pursuant to an agreement with Mr. Duncan, the Respondent and Fiberglass Pools of South Florida, Inc. have repaired those items listed in paragraph 9 in an excellent manner and to the full satisfaction of the owner, Leroy Duncan. On November 17, 1982, the Respondent was convicted in the County Court of Dade County, Florida, of unlawfully aiding and abetting an unlicensed contractor in violation of Section 10-22(h) of the Metropolitan Dade County Code. Adjudication of guilt was withheld and Respondent was required to pay a $500 fine. The Respondent has been a licensed certified general contractor in the State of Florida since November, 1971, and has had no other charges or actions against his license. There have also been no other complaints filed with the Petitioner regarding the Respondent.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Respondent be found guilty of those specific violations as set forth in the Conclusions of Law above and that his license as a certified general contractor be suspended for a period of six months and that the Respondent be required to pay an administrative fine of $250.00. DONE and ENTERED this 20th day of July, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of July, 1983. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Frederick G. Gervia 2810 Southwest 78th Court Miami, Florida 33155 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (3) 489.115489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THOMAS CHARLES HITCHENS, 84-003766 (1984)
Division of Administrative Hearings, Florida Number: 84-003766 Latest Update: Jul. 10, 1985

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following facts were found: At all times material to these proceedings Respondent was licensed by the State of Florida as a certified pool contractor, licensed No. CP C025535 and registered pool contractor, License No. RP 0041301. On June 7, 1983, Respondent entered into a Contract (Contract) with Edward and Maureen Kerstein (Kersteins) of 283 Islander Lane, Hudson, Florida, under which a pool was to be constructed on the Kersteins' property for a contract price of $7,777.00. The Contract was later amended by a letter, signed by Respondent and dated July 15, 1983, providing a penalty of $50.00 per day to be deducted from the balance due on the contract price if Respondent failed to complete the pool by July 23, 1983. Respondent obtained building permit No. 34342 on June 15, 1983, in the name of Crystal Clear Pool for the construction of the Kersteins' pool from the Pasco County Building Division. The pool steel inspection was called for and approved on July 8, 1983 and the pool bonding inspection was called for and approved on July 18, 1983. No other inspections were called for by the Respondent and the Respondent did not request an extension of time on the building permit. Therefore, on January 18, 1984, as required by the Standard Building Code of Pasco County, the permit lapsed and was invalid. However for reasons that are not clear in the record Vern Rossky, Building Inspector, Pasco County Building Division, made a final inspection of the Kersteins' pool (Permit No. 34342) on June 28, 1984 and approved the pool. Ordinarily the contractor would call for the final inspection or if the permit had lapsed or was invalid then the Pasco County Building Division would contact the contractor in order to finalize the permit. However, the record is clear that Respondent's intent was to leave the permit open due to the problems with completing the pool and satisfying the Kersteins. Although problems with the pool still existed, the pool was substantially completed in August, 1983 and the Kersteins used the pool in late summer 1983 (August) and the summer of 1984. The pool was operational in August of 1983. The respondent has received $7,055.05 for his work on the construction of the pool under the Contract with the Kersteins. While the Contract did not specify which side yard Respondent was to have access through for construction of the pool, the testimony of both the Respondent and the Kersteins was that it was the west side yard. However, the record reflects that the Kersteins gave either an expressed or implied approval for the use of the east side yard. All of the shrubbery, with the exception of the shrubbery that was part of the Contract, has been properly replaced and the clothesline has been replaced. The evidence was insufficient to show that the cracks which occurred in the house some 3-6 months after the pool construction was caused by the equipment being brought in on the east side of the house. Although Edward Kerstein's testimony was that an expert had not looked at the damage caused by the alleged water seepage around the electrical conduit pipe installed by the Respondent, his testimony that he had identified the Respondent's failure to caulk around the conduit pipe as the reason for the water seepage which resulted in damage to the carpet and speakers went unrebutted and was credible. However, Respondent was not made aware of this problem until the summer of 1984, almost a year later. The record is clear on the following: (a) that the tile placed around the top edge of the pool by Respondent was defective; (b) that there were several acceptable methods of replacing the defective tile; (c) that there were differences of opinion as to which method should be used in this situation; (d) that the reglazing over the existing tile was not an acceptable method; (e) that the pool would have to be drained to replace the defective tile; (f) that the Kersteins did not want to tile over the existing defective tile; (g) that the Respondent and Drew Tile Supply Company (Drew), the supplier of the defective tile, agreed on the method of cutting the tile away from the bull nose cap and replacing just the tile and based on this agreement; Drew delivered a check to Respondent in the sum of $823.75 ($700 for labor and $123.75 for tile) made payable to Crystal Clear Pools and Phil Klein, the subcontractor who had installed the defective tile; (h) that the Respondent, as President of Crystal Clear Pools assigned Crystal Clear Pools' interest in the check to Phil Klein provided the work on the defective tile in the Kersteins' pool commenced no later than February 1, 1984; (i) that Phil Klein endorsed and cashed the check with the knowledge of the assignment; and Phil Klein's testimony that even though the assignment was on the check at the time he endorsed and cashed the check the Respondent told him that the money was a partial payment of another job is just not credible; (j) the more credible evidence is that Respondent assigned the check to Phil Klein for labor and tile to replace the defective tile on the Kersteins' pool and there was no intent by Respondent to divert these funds to another job; (k) that the Kersteins' had not agreed to the method of replacing the defective tile which was part of the agreement between the Respondent and Drew; (1) that Drew had agreed that if the method selected was not satisfactory, then Drew would make it right; (m) that the problem with the drain in the pool, the filtering system, the telescoping rod, the damage to the air conditioning controls on the house, the failure to put tile chips on pool steps and the damage to the underground wire, were legitimate problems and it was Respondent's intent to correct all by the time the pool was drained to replace the defective tile; (n) that the Kersteins understood this when they agreed to allow Respondent to wait until the winter of 1984 to correct these problems because they were already using the pool in the latter part of the summer of 1983 and did not want to drain it at that time; (o) that none of these problems had been corrected due to the failure of both the Respondent and Drew to reach an agreement with the Kersteins on how both the defective tile problem and the other problems were to be resolved and; (p) that there had been continuous negotiations between either the Respondent and the Kersteins or Drew and the Kersteins concerning the settlement of this problem.

Recommendation Based upon the findings of fact and conclusions of law cited herein it is RECOMMENDED that the Board enter a final order finding the respondent not guilty of the violations charged in Count I, Count II, and Count III of the Administrative Complaint and that Counts I, Count II and Count III of the Administrative Complaint be DISMISSED. Respectfully submitted and entered this 10th day of July, 1985 in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of July, 1985. COPIES FURNISHED: Douglas A. Shropshire, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Gerald A. Figurski Post Office Box 786 New Port Richey, Florida 33552 Mr. James Linnan Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (3) 120.57455.227489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs MERWIN C. CARTER, 91-005266 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Aug. 21, 1991 Number: 91-005266 Latest Update: Apr. 16, 1992

Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825

Florida Laws (5) 120.5717.00140.34474.214489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RONALD B. HAENDIGES, 82-002873 (1982)
Division of Administrative Hearings, Florida Number: 82-002873 Latest Update: Dec. 04, 1990

Findings Of Fact Ronald B. Haendiges is a registered general contractor in the State of Florida holding license number RG 0039437. The Respondent was so licensed at all times material to the Administrative Complaint and at the time the Administrative Complaint issued. On May 29, 1981, the Respondent contracted with Mary Raney to put into operation a pool located at 479 East Main Street, Longwood, Florida, for a contract price of $4,025. Said pool had been partially floated out of the ground. The contract between Raney and the Respondent specifically provided that the Respondent would perform the following: Knock off existing tile; Reform beam; Reset new level of skimmer; Pressure-test existing plumbing and repair as needed (but not to exceed $300 of extra cost); Reform new deck area (450 square feet) Fill as needed; Place wire mesh in new deck area and pour new deck; Retile waterline, 6 by 6 bullnose; Re-(illegible) cracked area on bottom of pool; Recement pool with Pool-tight; Put cool deck topping on new deck area; Reform and pour new steps and tile step edge with matching tile; Replace pump and motor with new comparable. The Respondent commenced work in workmanlike fashion on or about May 29, 1981. As work progressed on the pool, he received various payments from Raney in accordance with their contract. The Respondent received a total of $2,750 of the $4,025 contract price. On or about July 13, 1981, the Respondent, nearing completion of his work, filled the swimming pool with water. At that time, additional cracks and leaks developed in the sides and bottom of the Raney pool. when these cracks developed, Raney refused to pay any of the balance of the contract price, or a total of $1,275. At that time, all work covered under the contract was completed, to include reinforcing the cracked areas with steel, except that the pool deck had not been poured. A square hole at one end of the pool and a larger area at the shallow end had not been finished. The cracks in the pool were created when the pool was filled with water because a void had been created beaten the bottom of the pool and the foundation of the pool when the pool floated up out of the ground. when the weight of the water was placed in the pool, it broke out the bottom of the pool. The problem with this void was not anticipated by Raney, the pool's owner, or the Respondent. Harvey's Bobcat Service provided fill dirt and labor to the Respondent for repairs on the pool, which were not paid for, and a lien of $382 was filed against the Raney property. Dove Henson performed marcite work and pool decking on the Raney pool for the Respondent. The Respondent was to pay Henson $400 for the work performed and, as of the date of the hearing, had not done so. The Respondent purchased Pool-tight on two occasions from Contractor's Supply of Orlando, Florida. On July 8, 1981, the Respondent purchased $275.60 worth of Pool-tight. On July 11, 1981, the Respondent purchased another $78 worth of Pool-tight from Contractor's Supply. On July 10, 1981, the Respondent paid $275.60 on this bill. This left a remaining balance of $78 due Contractor's Supply, which was not paid. Raney subsequently contracted with another contractor to repair the pool's bottom. This contract between Mary Raney and Reid Baker provided that Baker would perform the following work for a contract price of $2,780: Remove cracked bottom; Install or replace dead line and rock bottom and steel; Re-Gunite bottom and walls where necessary; Check all piping and repair; Marcite entire pool; Furnish and install grab rails; Recoat cool deck where necessary for a first-class job; Reinstall owner's filter, pump, valve, etc.; Clean up pool debris. The contract between Raney and the Respondent did not call for the replacement of the bottom of the pool, and the replacement of the bottom of the pool was not anticipated in said contract. The standard building code of the City of Longwood requires that a contractor obtain a building permit prior to construction or repair of a pool.

Recommendation Having found the Respondent, Ronald B. Haendiges, not guilty of violating Section 489.129(1)(h), Florida Statutes, the Hearing Officer recommends that this charge be dismissed. Having found the Respondent guilty of violating Section 489.129(1)(d), Florida Statutes, by failing to obtain a permit as required by the local building codes, the Hearing Officer recommends that the Respondent receive a letter of reprimand. DONE and RECOMMENDED this 15th day of April, 1983, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of April, 1983. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Ronald B. Haendiges Post Office Box 388 Winter Park, Florida 32790 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 J. K. Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (2) 120.57489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MILLARD P. HILL, JR., 76-001011 (1976)
Division of Administrative Hearings, Florida Number: 76-001011 Latest Update: Dec. 04, 1990

Findings Of Fact The parties stipulated that Petitioner's Exhibit number 1, which is the Florida Construction Industry Licensing Board official records as they relate to Millard P. Hill, Jr., should be received into evidence. The parties noted further that there is little dispute as to facts, however, the Respondent contends that there is no diversion of funds based on the facts of this case. On June 10, Respondent advised Petitioner that he wished to qualify Master Pools, a corporation which he had applied to Petitioner to qualify as the name under which his pool contracting would be done to reflect the name H. B. Patten, Inc. as the name under which said contracting would be done. Petitioner changed its records to show this change. On July 12, Respondent entered into a contract with Manuel and Anna Bueno for a pool to be built at 6960 Northwest 4th Place, Margate, Florida, for a sum of $5,665. See Petitioner's Exhibit number 2 received into evidence and made a part hereof by reference. Anna Bueno testified that a hole was dug and tar paper and steel bars were erected in the hole and the work was abandoned thereafter. Prior to abandonment, the Bueno's paid approximately $4,100 to Patten Pools. To complete the construction, the Bueno's used Hallmark Pools to finish the pool which required an additional sum of approximately $5,000. As can be seen, this is approximately $3,300 over and above the contract price. The evidence also reveals that Patten Pools, Inc., through Millard P. Hill, applied for and obtained a permit for the construction of the pool for the Bueno's on August 5. See Petitioner's Exhibit number 3, received into evidence and made a part hereof by reference. On April 24, Mr. and Mrs. Edward Eskie entered a contract with Respondent for the erection of a swimming pool on their property located at 1525 Southeast 14th Court, Deerfield Beach, Florida for $6,786.00. See Petitioner's Exhibit number 4 received in evidence and made a part hereof by reference. Mr. Eskie testified that the excavation for the pool began on May 20, and on June 2 gunite services were complete. On July 9, he received a letter from Crockett- Bradley, Inc. a gunite subcontractor, indicating that it was filing a lien for $1,312 against the Eskie's property for services performed. The building permit for the Eskie project was obtained by Respondent on June 10. See Petitioner's Exhibit number 7 incorporated herein by reference. Edward Eskie paid Respondent approximately $4,778 and $1,312 was paid to Crockett-Bradley, Inc. to satisfy the lien which was placed against their property. The Eskie's completed their pool by payment of an amount in excess of $4,000 to another pool contracting firm. Prior to completing the pool and after the Respondent abandoned the project, Edward Eskie made numerous attempts to contract Respondent by phone to no avail. On June 27, Respondent entered a contract with Orlando Gonzalez for a pool to be built at his residence located at 353 Northwest 22nd Street, Boca Raton, Florida for $9,000.00. See Petitioner's Exhibit number 8 which was received and made a part hereof by reference. Orlando Gonzalez paid Respondent $3,600 through his bank toward the contract price. For that payment, Respondent dug a hole and the project was abandoned. After work was abandoned, Gonzalez made repeated attempts to contact Respondent to no avail. To complete the project, he paid another contractor approximately $6,000. On April 18, Respondent entered into a contract with Howard and Sheila Siclari for a pool to be built at their home located at 7812 Northwest 67th Avenue, Tamarac, Florida, for the sum of $4,280. To commence the construction, Respondent obtained a building permit on June 18, 1975. See Petitioner's Exhibits number 9 and number 10 received in evidence and made a part hereof by reference. The Siclari's paid Respondent $3,456.75. Thereafter they completed the work which cost them an additional $2,500 and they did most of the work themselves. James T. Anglen, a pool salesman for Patten Pools testified that he was initially employed by Master Pools until June, 1975. A reference to Petitioner's Exhibit number 1 indicates that Master Pools registered as Brian Sales Corporation as the first entity that Respondent registered with Petitioner on January 1, 1974. He was a superintendent of Patten Pools in June, 1975 when he commenced employment with Patten. He acknowledged that he received money from the Bueno's which was transmitted to Patten Pools. He also acknowledged that the Bueno's were probably hurt most of all the complaining parties in this case. Respondent discovered that its cash flow was short approximately $40,000 to $50,000 and that that amount in checks were floating with insufficient funds to cover them. He commenced efforts to try to straighten out the firms cash flow and that for a while the bank worked along with him. Anglen also acknowledged the abandonment of the Gonzalez project. He further acknowledged that monies received from projects were used to cover deficiencies on other projects to continue Respondent's operations.

# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILBUR A. SELLARS, 83-001510 (1983)
Division of Administrative Hearings, Florida Number: 83-001510 Latest Update: Mar. 19, 1984

Findings Of Fact The Respondent Wilbur A. Sellars is licensed as a residential pool contractor by the Construction Industry Licensing Board through license number RP 0045541. Mr. Sellars was first licensed in 1975. At all times material to this case Respondent has owned and operated in Tallahassee, Florida, a pool contracting company called Pro Pools Service and Supply or Pro Pools, Inc. Cabana Construction In November 1977 Respondent entered into a contract with Dr. Frank S. Bilek to construct for him a 20' by 40' vinyl lined pool and a 20' by 40' cabana building. The contract price for the pool was $11,166.10. The price for the cabana was $14,517.30. The pool and building were constructed as provided in the contract. The cabana sits on an 800 square foot slab with footings and consists of three separate rooms. One room is a small bathroom containing a lavatory, water closet, and shower. Another room is fully enclosed by finished walls and sliding glass doors. The third room is open on two sides, one of which faces the swimming pool. The walls are typical stud construction with plywood siding on the exterior and half-inch drywall on the interior. The roof is supported by 2/12 2x4 prefabricated trusses with shingles on top. The ceiling inside the cabana is the same as would be found in a residential home and the floor is a cement slab covered by carpet. There is one overhead ceiling fan in the open room and another in the fully enclosed room. For all practical purposes the construction techniques and materials used in the cabana are the same as would be used in a residential dwelling, although they may not meet the code standards which would be applicable to a dwelling in the Killearn residential area where Dr. Bilek's home is located in Tallahassee, Florida. The cabana is equipped with plumbing for the bathroom and also for a wet bar in the kitchen area of the cabana. No pool accessories were located in the cabana at the time Petitioner's witness inspected the facility, however as with any other structure of its size, pool equipment such as vacuuming hoses, wands, etc., could be placed inside it. The original design for the cabana included large solar panels located on the roof. The purpose of these panels was to provide heating for the swimming pool water. After the panels were installed they malfunctioned and have since been removed from the cabana roof. Typically in home swimming pool installations such panels are placed on house roofs or are independently supported by a special structure located near the swimming pool. The swimming pool water recirculation pump and filter for Dr. Bilek's pool were not located inside the cabana in issue, but were located nearby out in the open. The cabana was not designed for the purpose of housing this equipment. It appears from the furnishings found in the cabana, its orientation with respect to the pool, and from its equipment that the cabana along with the pool coordinate to create a unified entertainment complex. Neither is essential to the other, however. The cabana could host a cocktail party without there being a drop of water in the pool and the pool can function perfectly without the cabana. Criminal Convictions On May 18, 1979 Respondent sent a work crew to Cairo, Georgia, for the construction of a residential swimming pool for Mr. and Mrs. Vanlandingham. The crew was using a dump truck to haul excavated dirt from the pool site to a dumping site several miles from the Vanlandinghams' residence. An inexperienced driver was operating the truck. Upon arrival at the dumping site he engaged the bed lift to dump the dirt but forgot to release the safety chains. As a result the chassis of the truck broke. Members of the crew called Mr. Sellars to give him the bad news. He instructed them to burn the truck, which they did. Respondent then submitted an insurance claim for the loss of his truck due to an accidental fire. As a result of this false claim he was convicted of insurance fraud as defined in Section 817.234(1)(a), Florida Statutes. He entered a guilty plea and judgment was entered on June 7, 1982. On the same date Respondent also pled guilty and was convicted on another count of insurance fraud arising from his filing a false claim for the alleged theft of three mobile radios from trucks operated and owned by Pro Pools Service and Supply. The radios had in fact not been stolen. Since his conviction Mr. Sellars has obtained insurance coverage for the business of Pro Pools including automobile liability, physical damage, general property and general liability insurance.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Construction Industry Licensing Board enter a Final Order finding the Respondent Wilbur A. Sellars guilty of Counts One, Two, Three and Four in the Amended Administrative Complaint and impose discipline in the form of an administrative fine of $200 and suspending Respondent's license as a residential pool contractor for a period of three months. DONE and RECOMMENDED this 23rd day of December, 1983, in Tallahassee, Florida. MICHAEL P. DODSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of December, 1983.

USC (1) 18 U.S.C 1464 Florida Laws (7) 120.57455.225489.101489.127489.129817.23495.111
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WESLEY ASH, 86-002642 (1986)
Division of Administrative Hearings, Florida Number: 86-002642 Latest Update: Dec. 09, 1986

Findings Of Fact Respondent, Wesley Ash, currently holds license number CP C015871 issued by the Construction Industry Licensing Board to authorize Ash to engage in the pool contracting business. Dodd Complaint (Count I). Respondent, Wesley Ash, doing business as Wada Pools, Inc., contracted with Jerry Dodd on or about June 17, 1981, to build a pneumatic concrete pool with skimmer and recirculation system. The contract did not include installation of the concrete deck around the pool. Dodd decided to contract with another independent contractor to install the deck at a lower price than Ash wanted for the job. Ash completed his work by approximately August 1981. He installed the concrete pool shell, finished the inside surface and installed tile along the water line. He then attached the skimmer assembly, plumbing it so that it was level and attaching it to the concrete pool shell by means of the skimmer's PVC plumbing piping. After Ash finished his work, Dodd's other contractor came behind Ash. He used some of the dirt Ash had excavated from the pool site to raise the ground surrounding the pool by approximately six inches above grade. He then poured the concrete deck but failed to encase the skimmer assembly with the deck concrete in the process of pouring the concrete deck. It was not Ash's practice to make any special arrangements to stabilize the skimmer assembly when he installed both pool and concrete deck. He relies on the skimmer assembly plumbing to stabilize the skimmer assembly until the concrete deck is poured. In pouring the concrete deck, Ash encases the skimmer assembly with the deck concrete to stabilize the skimmer assembly and prevent leakage. In the case of the Poland pool (paragraphs 17 and 22, below), Ash used this method to install both the pool and the concrete deck, and Poland has had no complaint of leakage at the skimmer (nor was there any evidence of leakage at the skimmer). In the case of the Priests' pool (paragraphs 11 through 13, below), Ash followed the same procedures as he did with the Dodd pool, and another contractor poured the concrete deck. As with the Poland pool, there have been no complaints (nor was there any evidence) of leakage at the skimmer. Within approximately one and one-half years after installation of the Dodd pool, Dodd began to notice what he thinks is a leak in his pool. The water level in the Dodd pool drops approximately one-quarter inch per day. But the Department's own expert witness conceded that water loss of between one-eight and one-quarter inch can be explained by evaporation. It was not proved that the Dodd pool is leaking at all. If there is a leak causing a small increment of water loss above loss through normal evaporation, the leak would have to be very small and would be very difficult to detect. Ash and others have tried but have been unable to find a leak at the skimmer of Dodd pool. In approximately summer 1985, Dodd himself dug a hole under the concrete deck to expose the bottom of the skimmer assembly. The excavation revealed an unusual amount of moisture that might be the result of a leak at the skimmer. It also revealed that the contractor who poured the Dodd concrete deck did not encase the skimmer assembly as Ash had thought he would. The Department's expert - a professional engineer with a B.S. degree in civil engineering, an M.S. degree in structural engineering and a Ph.D. degree in environmental engineering - gave his opinion that a residential pool skimmer assembly should be either (1) encased with the concrete of the pool shell or (2) encased with deck concrete which is structurally tied to the concrete pool shell. He opined that the latter method would require either a very rough surface on the pool shell concrete or steel extending from the pool shell in order for the structural tie to be accomplished. But he also conceded that it is possible for deck concrete encasing a skimmer assembly to be sufficient to stabilize the skimmer assembly even without taking any extra measures to accomplish a structural tie. There was no evidence that any building code would require a pool contractor to take these measures to accomplish a structural tie between the pool shell and skimmer assembly. Nor was there any evidence that a reasonably prudent pool contractor (as opposed to a professional engineer) would be expected to take these measures. Based on this evidence, together with all the other evidence taken as a whole, the Department did not prove that Ash was either incompetent or grossly negligent in not taking any extra measurers to accomplish a structural tie between the concrete pool shell and the skimmer assembly. Based on the evidence in this case, the contractor Dodd hired to pour the concrete deck was either incompetent or grossly negligent (assuming he was even a licensed pool contractor a fact not shown by the evidence.) He did not encase the skimmer assembly with the deck concrete, allowing it to "float" unprotected in the fill under the concrete deck. Settling of the fill could have caused the deck to settle and crack, moving the skimmer assembly and causing a small leak. Ash may have been able to prevent this by warning the contractor to be sure to encase the skimmer assembly with deck concrete when he poured the concrete deck. But there was no evidence that Ash had a duty to advise the other independent contractor Dodd hired or was responsible for the other contractor's incompetence or gross negligence. Ash's failure to advise the other contractor was not incompetence or gross negligence on Ash's part. Dodd has no other complaints about the pool Ash built for him. Priests' Complaint (Count II). On or about October 11, 1984, Ash contracted with Joseph and Rita Priest to build them a pneumatic concrete pool. The Contract included a warranty that the labor, materials and workmanship would be free of defects for one year and that the shell would be structural sound and capable of holding the water for ten years. Like Dodd, the Priests contracted with another independent contractor to install the concrete deck around the pool. Ash was responsible only for placement of decorative "river rock" on top of the deck. Ash finished his work in February 1985. Like Dodd, the Priests complained of water loss from the pool although the Priests noticed the water loss sooner than Dodd (approximately March, 1985). The water level was dropping approximately one-quarter inch per day more than it was dropping in a bucket used as a control. In response to the complaint, Ash sent his employees to the Priests' pool on several occasions. They found no leak at the skimmer. To determine whether the pool's "caretaker system" 1/ was leaking, Ash's employees plugged all but one pair of the caretaker heads. After waiting a period of days, they would try to see whether the rate of water loss changed. They tested all four pairs of caretaker heads on the bottom of the pool and the pair in the spa attached to the pool. No leaks could be found. They did not replace the last two (in the spa), and Mr. Priest had to replace them. As with the Dodd pool, the Department did not prove that the Priests' pool is leaking at all. The Priests continue to complain of water loss of approximately one-quarter inch per day, within the range of water loss from normal evaporation. As with the Dodd pool, a leak responsible for a small increment of water loss above water loss from normal evaporation would be very small and difficult to find, especially if the leak were in the caretaker heads or pipes under the pool leading to the heads. Now the Priests suspect a water leak at the filter. But the Department's expert witness could not find a leak there large enough to account for much water loss. The minor leak at the filter is a normal maintenance item for a pool as old as the Priests' pool. There was no evidence how long it has existed, and there was no evidence that the Priests ever told Ash there was a leak at the filter. The Priests now also complain that one of the caretaker heads does not re-seat properly. But this has nothing to do with the leakage complaint to which Ash is charged with not reasonably responding. Taken as a whole, the evidence did not prove that Ash committed misconduct or deceit by failing to make reasonable response to warranty service requests within a reasonable time, as charged. Nor does the evidence prove misleading or untrue representations, gross negligence, incompetence or fraud in connection with the Priests' pool, as charged. Poland Complaint (Count III). On or about December 9, 1981, Ash entered into a contract with James Poland to build Poland a pneumatic concrete pool and concrete deck. Poland contracted with another independent contractor to build a screen enclosure around the pool. Before construction began, one of Ash's employees asked Poland to sign an addendum to the contract for an additional $235 to pay for foundation footers required to comply with Lee County building code provisions for the screen enclosures. Before Ash signed the initial Poland contract on December 9, 1981, he was unaware of the Lee County Aluminum Code, adopted March 18, 1981. The code requires eight inch foundation footers for "aluminum additions." Another part of the code addresses "screen enclosures with screen roofs known to the industry as birdcage swimming pool enclosures." The language of the code is not explicit that screen swimming pool enclosures are required to meet the foundation requirements for "aluminum additions," and at first Lee County did not interpret the code that way. With a change of personnel in code enforcement, Lee County began to interpret the code that way, and screen swimming pool enclosures Ash had under construction began to fail building inspection for inadequate foundation footers. Ash inquired why and was told about the aluminum code and how it was being interpreted. Ash argued that the interpretation was erroneous but, failing to dissuade enforcement personnel, began to comply. As part of his compliance efforts, Ash had his employees try to secure the contract addendum from Poland. Poland refused to sign the contract addendum, insisting on an opportunity to verify that the additional foundation footers were indeed new building code requirements. There still is a dispute between the parties whether Poland ever agreed to pay the additional $235 after he verified that the footers were being required. (He never signed the contract addendum.) But, in any event, the evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct in connection with the additional $235 charge. 2/ There was some evidence that Ash did not in fact comply with the Lee County Aluminum Code, as he was told it was being interpreted, in his construction of the Poland pool deck. In two places the foundation footers were 6 and 7 inches - deeper than the four-inch normal thickness of a concrete pool deck but short of the eight-inch requirement. But Ash was not charged with failure to comply with the foundation footer requirement. He had no legally sufficient notice that he should be prepared to defend against that charge and was not prepared to defend against that charge. Therefore, no finding is made whether Ash complied with the Lee County Aluminum Code. Ash performed the Poland contract between approximately January 27 and February 26, 1982. In September, 1985, Poland began to notice that some of the tile Ash installed at the waterline around the perimeter of the pool was coming loose. As explained by the Department's expert witness, the concrete deck settled in places, cracking slightly and rotating over the fulcrum created by the wall of the concrete shell of the pool. The rotating action pulled up on the tile attached to the inside of the pool wall in places, loosening the tile. In all, less than 10 percent of the 77 foot perimeter of the Poland pool experienced problems with loose tile. The loose tile easily can be removed and replaced. The minor deck cracking and loose tile problems at the Poland pool are within the normal range for a competently constructed pool under normal conditions of ground settlement. The evidence did not prove that Ash improperly installed the pool deck or that he was incompetent or grossly negligent in the construction of the Poland pool and deck. Besides the loose tile and minor cracks in the concrete deck, the Poland pool had no apparent defects. There also was evidence that the Poland pool was finished with a coating of marcite on the inside surface of the pool shell which was mottled gray in color instead of white. Poland complained persistently about the marcite3 and insisted that Ash make it white. But the discolored marcite was a factory defect of which Ash had been unable to know before he used it. There is no way to make mottled gray marcite white. Ash tried to explain this to Poland but the customer would not be satisfied. Taken as a whole, the marcite evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct. Nor does the evidence prove any of those violations for failure to cure the marcite problem under warranty. First, as already stated, there was no cure. Second, Ash and Poland also had a running dispute whether Poland had paid the full contract price, including the additional $235 for foundation footers, so as to entitle him to any warranty repairs. In light of this genuine dispute, failure to do warranty work, if otherwise a reasonable request, still could not be found to be misconduct, fraud or deceit.

Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing the Amended Administrative Complaint that has been filed against Respondent, Wesley Ash, in these cases. DONE AND ORDERED this 9th day of December 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of December, 1986.

Florida Laws (3) 455.227489.105489.129