Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 1
THE HARTER GROUP vs PINELLAS COUNTY SCHOOL BOARD, 90-003261BID (1990)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida May 25, 1990 Number: 90-003261BID Latest Update: Jul. 17, 1990

Findings Of Fact In order to meet its need for new equipment in the new district administration building, the School Board advertised for competitive bid proposals for clerical, professional task, guest and conference chairs (task seating). Five bids were timely received by the School Board, two of which were determined to be responsive. The bid opening occurred on April 17 1990, and the Knoll Source was determined to be the lowest responsive bidder. In spite of this determination, the bid was rejected by the Director of Purchasing or the appointed designee because sales tax was not included in the bid. The Notice of Award was issued to Haworth, who submitted its bid showing the price it was willing to accept for the sale of the task seating, with and without sales tax. The initial decision to reject the Knoll Source bid, which was $10,393.72 less than Haworth in Sequence I; $12,231.94 less in Sequence II; and $994.17 less in Sequence III, was based upon Section 9.2.2.a in the "Instructions to Interior Bidders". This section of the bid documents provided that the contract for purchase of the task seating would not be exempt from sales tax. This bid specification is incorrect because the School Board does not pay sales tax on acquisitions of furnishings for the Pinellas County School System. Knoll Source was aware of the School Board's sales tax exemption prior to its bid submission. As Section 9.2.2.a of the instructions was inappropriate, the vendor relied on Section 9.2.2.c, and excluded sales tax from the bid because the cost of such tax was not applicable. Section 9.2.2.c instructed bidders to exclude inapplicable taxes from their bids. Pursuant to Section 5.3.1 of the bid instructions, the School Board has the right to waive any irregularity in any bid received and to accept the bid which, in the Board's judgment, is in its own best interest. The Knoll Source and Haworth bids can be comparatively reviewed, and Knoll Source is the lowest responsive bidder if the failure to include sales tax in the bid amount is waived by the School Board. It is in the Board's best interest to waive Knoll Source's failure to include a sales tax in the bid because sales tax does not apply to this purchase.

Florida Laws (2) 120.53120.57
# 2
SAXON BUSINESS PRODUCTS, INC. vs. DEPARTMENT OF GENERAL SERVICES, 81-002230 (1981)
Division of Administrative Hearings, Florida Number: 81-002230 Latest Update: Jun. 01, 1990

The Issue Whether Saxon Business Products, Inc.'s ("Saxon") response to the Department of General Services' invitation to bid for walk-up convenience copiers should be disqualified on grounds that: Saxon's omission of a supply price list was a material deviation from the bid specifications and conditions; and Saxon's walk-up convenience copier, model "Saxon 300," failed to prove two-sided copy capability.

Findings Of Fact I. Invitation to Bid On June 10, 1981, DGS issued invitation to Bid No. 544-600-38-B ("ITB") entitled, "Walk-Up Convenience Copiers; Bond Paper and Magazine Finish Bond Paper." The ITB proposes an annual contract under which state agencies and institutions can purchase copying machines. It contains general and special conditions and specifications, and warns vendors that bids that do not comply with such conditions "are subject to rejection." (Testimony of Celnik) The ITB specifications divide copiers into two groups: Group I, plain bond copiers, Group II, magazine finish copiers. The copiers are further categorized by type: Type I indicates minimum features; Type II indicates two- sided copying capability; Type III indicates one reduction capability; and Type IV indicates two or more reduction capabilities. These types are further separated into 12 classes on the basis of speed and volume (P-1.) The ITB special conditions instruct bidders to submit bid sheets 2/ breaking down all copying costs to a per-copy basis. Bids are to be evaluated and contracts awarded to bidders submitting the, lowest cost per copy in each category of copier. Cost per copy is calculated by using a specific cost formula. (P-1.) The ITB cost formula contains three components: machine cost, labor cost, and supply cost. DGS proposes to disqualify Saxon's bid in several categories of copiers for failure to supply a supply price list required by the supply cost component. This component provides, in relevant part: C) SUPPLY COST - The bidder shall compute supply costs on the Manufacturer's Brand. If there is an existing state con- tract for supplies for the manufacturer's brand equipment, the state contract price may be substituted. Supply costs will be rounded to six (6) decimal points. All other costs will also be rounded off to six (6) decimal points. The volume price used by the vendor to compute supply cost shall be based on the monthly median vol- ume of the type and class being bid. Supply cost submitted shall be firm for the contract period, except for paper, and all supply costs shall be current market price, verifiable. Vendor must submit supply price lists with his bid to substantiate that correct price vol- umes were used, unless state contract prices were used. A contract award may include supplies if deemed in the best interest of the State. By electing to substitute state contract supplies, the vendor is certifying that his equipment, using said supplies, will meet all per- formance requirements of this bid and of the equipment manufacturer. NOTE - All cost formulas will be verified by the Division of Purchasing and errors in extension will be corrected. In the event incorrect supply cost volumes are used by a bidder, the Division of Purchas- ing will adjust these costs to the median volume range. (e.s.)(P-1.) The purpose of the supply price list requirement, included in DGS's 1980 and 1981 ITB for convenience copiers, is to enable DGS to verify the supply cost figures shown on a vendor's bid sheets; in this way, DGS can insure that all vendors are using correct quantity pricing on their bid sheets. 3/ (In the past, some bidders had used lower supply prices, which were tied to high volume purchases; but those volumes frequently exceeded the state's needs and the median volumes specified by the ITB for each category of copier.) The verification procedure followed by DGS in both 1980 and 1981 involves checking the vendor's bid sheets against the prices shown on the supply price list. 4/ If DGS finds an inconsistency between the two, it "corrects" the bid sheet supply cost upward or downward to reflect the price shown on the supply price list. 5/ Such a bid sheet correction would also change the total median cost per copy, the factor used to evaluate competing bids. DGS also checks the supply list to determine whether it contains current market prices. (Testimony of Hittinger, Eberhard.) If a vendor fails to submit a supply price list, DGS cannot verify that the supply prices used on the bid sheet (to compute total median cost per copy) accurately reflect the median volumes specified in the ITB. Neither can DGS determine whether the supply prices used on the bid sheet are set prices, which do not vary with volume, or volume prices, which do; the bid sheets, on their face, do not reveal which type of pricing is being used. (Testimony of Eberhard; P-1.) After sealed bids are publicly opened, DGS has an established practice of not allowing any bidder to submit additional material which could alter price or other information previously submitted on bid sheets. DGS does, however, accept late information if it can be corroborated by an independent source. For example, a bidder might -- after bid opening -- supply its corporate charter number, which can be easily verified by contacting the Department of State. (Testimony of Hittinger, Eberhard.) The ITB special conditions also require DGS to test and approve copiers prior to bid opening. Copiers which are not tested and accepted by DGS are ineligible for a contract award: EQUIPMENT APPROVAL - Each item of equipment bid shall have been tested by the Division of Purchasing prior to the bid opening time and date for performance and reliability under normal working con- ditions. Any bidder whose equipment has not been tested shall provide a model of the equipment on which he intends to bid to a specified testing station, complete with all supplies, at no expense to the State. Testing will extend for a period of twenty (20) working days. In the event evaluation and acceptance of untested ma- chines has not been accomplished prior to the bid opening date and time, such machine shall not be eligible for an award. (P-1.) II. Bid Opening: Saxon's Failure to Submit Supply Price List Prior to the 1981 bid opening, Saxon failed to submit a supply price list in connection with its bid. This was apparently an oversight on its part; a year earlier, it had furnished a supply price list in response to a similar ITB for convenience copiers. Because of Saxon's omission, DGS was unable to verify the supply prices used by Saxon on its bid sheets or determine whether Saxon was utilizing set or volume prices. (Testimony of Eberhard, Celnik, Hittinger.) After bid opening, Saxon notified DGS that the supply prices shown on its bid sheets were set supply prices -- unit prices which do not vary with volume -- and confirmed that they are the supply prices which it now offers to the state. (Testimony of Celnik.) In its evaluation of the bids, DGS applied the requirement of a supply price list equally to all bidders. All bidders who omitted a supply price list were informed that they were disqualified. Saxon's bid was disqualified in five copier categories: Group I, Type I, Class I; Group I, Type I, Class II; Group I, Type I, Class IV; Group I, Type II, Class I; and Group I, Type II, Class II. At least 11 vendors, however, did submit supply price lists with their bid sheets; approximately one-third were set price lists, the remaining were volume price lists. (Testimony of Eberhard; P-3.) If a vendor could submit a supply price list after the bid opening, it could effectively decrease or increase its bid. (This is so because, in case of a conflict between the bid sheet supply price and the supply price list, the price list value will prevail. A change in the bid sheet supply price will change the cost per copy figure the determining factor in awarding contracts.) A vendor submitting a late supply price list would have an unfair advantage since it could change its bid after bid opening while its competitors could not. The competitive nature of the bidding process would be impaired. (Testimony of Hittinger, Eberhard.) Furthermore, if late submittal of a supply price list was allowed, a bidder could disqualify itself by refusing to provide it; the bidder would then have the advantage of revisiting its bid and -- if it chose -- withdrawing it after bid opening. The opportunity to withdraw a bid -- after bid opening -- would be an advantage not enjoyed by those who timely submitted supply price lists with their bids. (Testimony of Hittinger, Eberhard.) In some copier categories, the vendors who omitted supply price lists were the low bidders. If DGS disqualifies them for their omission, it must award the contract to the next highest bidder. The difference between those low bids and the next higher bid is substantial -- in some cases exceeding 23 percent. 6/ (Testimony of Celnik, Eberhard, Nee, Reinhart.) III. Failure of "Saxon 300" to Demonstrate Two-Sided Copying Capability In accordance with the ITB, Saxon submitted its "Saxon 300" copier to DGS for evaluation and testing. Prior to bid opening, DGS conducted a 20-day test of the machine. The "Saxon 300" machine which DGS tested lacked two-sided copying capability. It could reproduce clearly on one side, but not on the other. The "Saxon 300" sales literature and instruction manual submitted with the machine did not represent that the machine had two-sided copying capability. (Testimony of Nee; 1-5, 1-6, 1-7, R-2.) The "Saxon 300" may have two-sided copying capability, but only after special modifications are made to the copier. These modifications include removal of a roller device, replacement of the heating element, and replacement of the blower system. Saxon did not indicate at the time of testing, or in its bid, that the "Saxon 300" required such modification for two-sided copying capability. Neither did it indicate what, if any, additional costs would be charged for such modifications. (Testimony of Nee, Wallace; R-3.) After DGS tested the "Saxon 300," it sent Saxon a form letter indicating that the copier met minimum operating requirements. The letter did not inform Saxon that the machine lacked two-sided copying capability because DGS did not consider the lack of such capability a major malfunction in the equipment. (Testimony of Nee.) If a machine malfunctions, DGS has -- in the past -- allowed vendors to correct the deficiency or substitute another machine. (Testimony of Nee.) The Group I, Type II, Class I category of copiers, requires two-sided copying capability. Saxon bid its "Saxon 300" as a copier which meets this requirement. (Testimony of Celnik, Nee; P-1.)

Recommendation Based on the foregoing, it is RECOMMENDED: That Saxon's bids in Group I, Type I, Class I; Group I, Type I, Class II; Group I, Type I, Class IV; Group I, Type II, Class I; and Group I, Type II, Class II be disqualified; and That Saxon's bid in Group I, Type II, Class I be disqualified. DONE AND RECOMMENDED this 26th day of February, 1982, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of February, 1982.

Florida Laws (3) 1.02120.57287.042
# 3
MARVIN`S GARDEN AND LANDSCAPE SOUTHEAST SERVICE, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003337BID (1985)
Division of Administrative Hearings, Florida Number: 85-003337BID Latest Update: Dec. 02, 1985

Findings Of Fact Both DOT and Weekley submitted proposed Recommended Orders. Their proposed findings of fact have generally been adopted here but are addressed in detail in Appendix A, attached and incorporated in this Recommended Order. On or before July 31, 1985, DOT received sealed bids from three bidders for State Project Nos. 86070-3492 and 93220-3403, involving landscaping of interchanges in Broward and Palm Beach counties. Marvin's Garden was the apparent low bidder, with a total of $389,112.19 shown on the face sheet of the bid blank form. Weekley was the next lowest bidder with a total of $419,899.56, and P. J. Constructors, Inc., was the highest bidder with a total of $458,805.90. After review of the bid documents for compliance with DOT bid procedures, a discrepancy was found in the Marvin's Garden bid and DOT notified the parties by letter dated August 20, 1985, that Weekley was the apparent low bidder on the project. The discrepancy was found on page 001 of the bid blank form submitted by Marvin's Garden. For item 570-11, "Water for Plant Establishment," under the column, unit price written in words, Marvin's Garden showed "fourteen thousand two hundred eighty two dollars and sixty six cents." The column, unit price in figures, showed "14,282.66," and the final column, headed "amounts" showed "14,282.16." The bid item was supposed to show the unit price for a thousand gallons of water (which price was to be written in both words and figures) and a total, or extension price for 3,743.125 thousand gallons of water. When the unit price on Marvin's Garden's bid was multiplied by 3,743.125 (number of units), the resulting total price for that bid item was $53,461,781.71. This figure was entered on the form in red ink and was initialled by Raymond Patrick Haverty, the DOT reviewer. Marvin's Garden's total bid for the project was then adjusted to $53,836,611.04, a figure far in excess of either Weekley's or P. J. Constructors' bids. Marvin Gross is the individual responsible for preparing and submitting bids for his corporation. He has been doing bid work for DOT for approximately 20 years and is thoroughly familiar with the bid procedures, forms and standard specifications. He attributes the irregularity on his submission to his "tunnel vision." Unit prices are significant because the quantity designated by DOT is merely an approximate, best guess by the Department engineers. For item 570-II, unpredictable weather conditions will ultimately dictate exactly how much water will be necessary to successfully complete the landscape project. That exact quantity times the unit price will be the basis of payment to the contractor. DOT found no violations of bid requirements in the bids of Weekley and P. J. Constructors, Inc., and none have been raised in this proceeding.

Recommendation For the foregoing reasons, a final order should be issued declaring Weekley the lowest responsible bidder on project Nos. 86070-3492 and 93220-3403, and the contract awarded accordingly. DONE and ORDERED this 2nd day of December 1985, in Tallahassee, Florida. Hearings Hearings MARY CLARK, Hearing Officer Division of Administrative The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative this 2nd day of December 1985. APPENDIX In accordance with Section 120.59(2) Florida Statutes, the following are recommended rulings on proposed findings of fact submitted by Respondent and Intervenor in this case. Respondent's Paragraph: Corresponding R. O. Paragraph or basis for rejection: The corporate status and the addresses of the bidders are not material. See Paragraph 1, R.O. See Paragraph 2, R.O. and Conclusion of law 2, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.O. See Paragraph 6, R.O. See Paragraph 2, R.O. Intervenor's Paragraph: Corresponding R.O. Paragraph or basis for rejection: See Paragraphs 1 and 2, R.O. Facts which relate to the composition of bid packages are not material. See Paragraph 3, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.0. See Conclusion of law 5, R.O., relating to the specifications of the department. The remainder of the paragraph proposed is immaterial. See Paragraph 5, R.O. COPIES FURNISHED: Thomas E. Drawdy, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301 A. J. Spalla, Esquire General Counsel 562 Haydon Burns Bldg. 605 Suwannee Street Tallahassee, Florida 32301 Mr. Marvin Gross, President Marvin's Garden and Landscape Services, Inc. 37 North McIntosh Sarasota, Florida 33582 Mel L. Wilson, Esquire Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32301 Harry R. Detwiler, Jr., Esquire HOLLAND & KNIGHT Post Office Drawer 810 Tallahassee, Florida 32302

Florida Laws (3) 112.19120.53120.57
# 4
SHAFER AND MILLER, INC. vs. DEPARTMENT OF GENERAL SERVICES, 76-001375 (1976)
Division of Administrative Hearings, Florida Number: 76-001375 Latest Update: Oct. 05, 1977

The Issue Whether Petitioner should be granted an equitable adjustment to increase the contract price in the amount of $337,714 for a mistake in bid on project No. BR-7702/8701, Library/Auditorium, Florida International University.

Findings Of Fact In April 1974, Respondent advertised for bids for the construction of a library-auditorium building at Florida International University, Miami, Florida, State Project No. B.R. 7702/8701. Respondent's representative for this project was the architectural firm of Ferendino/Grafton/Spillis/Candela, Coral Gables, Florida. The advertisement for bids specified that sealed bids would be received until 2:00 p.m. on May 16, 1974, at which time they would be publicly opened and read aloud. In fact, the advertised time period was extended until the same hour on May 23, 1974. The advertisement provided that bids must be submitted on the proposal form furnished by the architect/engineer and be accompanied by a bid bond or an equivalent cash amount in a sum not less than five per cent of the amount of the base bid as a guarantee that the bidder would enter into an agreement with the owner if this bid was accepted. It further provided that the bid would remain in force for thirty (30) days after the time of opening. The advertisement also contained the following statement: "The Department of General Services reserves the right to reject any and all bids and to waive informalities in any bid whenever such rejection or waiver is in the interest of the State of Florida." (Exhibit 1a, testimony of Williams) In preparing its bid on the project, Petitioner utilized two company forms. One included columns for the various portions of the work with blocks opposite each portion for the insertion of the names of subcontractors and the amounts of their bids. The other form was a recapitulation of the low subcontractors' bid by the various segments of the contract, and the form also included spaces and amounts for the work to be accomplished by the contractor itself. The normal procedure followed by Petitioner in this and prior projects was to enter subcontractors' bids on the subcontractor's bid tabulation form when received over the telephone and, when all such bids had been received shortly before the deadline for submission of bids by the prime contractors on the project, to enter each low subcontractor bid on the recapitulation form. This would then be totaled to arrive at Petitioner's bid to be submitted to Respondent. (Testimony of Kearns). The subcontractor tabulation form for the instant project listed an item for "PRECAST STRUCTURAL." Opposite this entry in blocks on the form had been printed the names of subcontractors from whom Petitioner expected to receive bids, including Pre-Stressed Systems, Inc. (P.S.I.), Meekins, Stresscon, and Houdaille. However, since there were two different pre-case structural items called for under the specification, i.e., joists under section 3-B and pre-case panels under section 3-C, the words and figures "3B Joists" and "3C panels" were penciled in above and below the printed words "PRE-CAST STRUCTURAL" to show the need for entering bid figures for both items. However, there was no separation of these items in the various blocks for subcontractor's bids. (Exhibits 1b, 1c, Testimony of Kearns) Usually bids of major subcontractors were not received until the morning of the final day for submission of the total bids, and many were not received until immediately prior to the time the bid must be tallied and submitted. On the morning of May 23, 1974, the day for bid opening, Petitioner's employee, Edward A. Kearns, Jr., an estimator, was responsible for preparing Petitioner's bid. The only bid Petitioner had received for precast joists was that submitted by P.S.I. in the base amount of $460,000. This sum was entered on the bid tabulation from in pencil under the printed name P.S.I. Bids for the pre-cast panels were received from two of the subcontractors whose names were printed on the form an the amounts were entered in pencil as follows: "Meekins - 399,800, Stresscon - 400,00." No bid was entered for Houdaille. About 11:00 a.m., a telephonic bid on the panels was received from Cast-Crete Corporation of Kissimmee. This bid was considerably lower than that of Meekins and, because Petitioner had not heard of or dealt with Cast-Crete in the past, it asked all three bidders on the panels to verify the requirements and prices. While awaiting the return of this information, the Cast-Crete bid was not entered on the bid tabulation form. Thereafter, Cast-Crete informed Petitioner that it was raising its bid somewhat and this information was placed on a separate subcontractor bid form for cast-Crete, but not entered on the tabulation form containing all bids. The final Cast-Crete bid was in the amount of $337,714. By this time, Petitioner's office was quite hectic in that other bids were coming in at a fast pace and the phone was ringing continuously. Many bidders sought clarification on items or had to give their bids to Kearns which was time-consuming. As the time for submission by Petitioner to Respondent drew near, Kearns took the low subcontractor bids from the bid tabulation form and transferred them for each category of work to the recapitulation form. On this form, there was a single line for "Precast structural" and, on that line, Kearns entered the bid that had been received from P.S.I. for precast joists, but forgot to include any bid for the precast panes. Since no breakdown for joists and panels was shown on the recapitulation form, he assumed that bids for all portions of the work hand been included. All items on the recapitulation form were added and Petitioner arrived at a total base bid of $3,999,259, which did not include the bid for precast panels in the amount of $337,714. (Testimony of Shafer, Sr., Kearns, Exhibits 1b, 1c, 1f) Petitioner's employee, Ron Shafer, Jr., previously had been sent to the place of bid opening at Florida International University with the formal bid letter with the amounts left blank. Shortly before 2:00 p.m., Petitioner provided him by telephone with the amounts to place on the be bid form and submit to the Respondent's representative. He submitted the formal bid just prior to the deadline. The bids were thereafter opened and, although Ron Shafer, Jr., noted that Petitioner's bid was some $400,000 lower than the next lowest bidder, he was unaware of the circumstances of the mistake and returned to the office. The representative of Respondent had opened the bids and an officer of the architectural firm, Freeman J. Williams, was also present. Nothing was said at the time concerning the large disparity between Petitioner's bid and the other bids, and Williams saw no need to ask Petitioner to verify its bid at that time. (Testimony of Shafer, Jr., Williams, Exhibits 1d, 1v) Meanwhile, after Kearns had tallied the final bid figures and they had been called in to the employee at Florida International University, Petitioner's personnel sat around the office and discussed the job for several minutes. They then started to gather up all the sub-bids to put in a folder when they discovered a "subcontractor's bid form" for Cast-Crete Corporation and realized that it had not been included on the tabulation sheet or on the final recap sheet. Immediate attempts were made to telephone the architect about the mistake. When Williams was reached at his office some thirty minutes after he had left Florida International University, Petitioner requested that its bid be withdrawn after explaining the circumstances. Williams suggested that Petitioner immediately send a telegram to Respondent explaining this situation. Petitioner did so in the following language: "In reviewing our bid, we discovered we had omitted the cost of precast panels manufacturers bid from our tabulation sheet, in the amount of $282,714. We, therefor, regretfully must with- draw our bid on the FIU library and auditorium building. We could, however, accept award of contract if this amount could be added to either of our base bids. Please advise. SHAFER AND MILLER, INC. R C Shafer" In the telegram, an additional mistake was made by using the figure of $282,714 which did not include the erection of the panels in the amount of $55,000 that had been the subject of a separate bid by Cast-Crete. After receipt of the telegram, Respondent's representatives requested that Petitioner come to Tallahassee with their pertinent documents relating to the bid to discuss the matter. They did so and thereafter heard nothing further until June 5, 1974, at which time a letter was received from the Department of General Services, dated May 31, 1974, advising that, subject to final approval by the Governor and the Cabinet, it was propose to recommend acceptance of Petitioner's low bid and award the contract to it in the amount of $4,122,000 for Base Bid 1 and Priority 1 Alternate A, Priority 2, Alternate C, and Priority 3, Alternate D. The meeting of the Cabinet at which the award was to be recommended was stated in the letter to be held on June 4, 1975. Since Petitioner did not receive the letter until June 5, it had no opportunity to be present at the time matter was considered. By separate letter of May 31, 1974, the Department of General Services enclosed four copies of a standard form of agreement and performance and payment bond to be executed and returned. (Testimony of Williams, Shafer, Sr., Kearns, Exhibits 1e, 1g, 1h) Petitioner contacted legal counsel, James E. Glass, on June 5. He checked into the matter and found that the contract had already been awarded on June 4 by the Cabinet. He then telephoned Arnold Greenfield, General Counsel for the Department of General Services, and asked if the state could rebid the job at which time Petitioner would submit its original intended bid. Greenfield stated that the project was critical from a budget standpoint and that the state would not rebid it, and insisted that the Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner could seek injunctive relief in the matter, and the latter then stated that if Petitioner would proceed with the contract, Respondent would acknowledge its right to claim a modification of the contract. This conversation was confirmed in a letter from Greenfield to Glass, dated June 7, 1974, wherein it was stated "We further understand that your client may wish to seek a modification of such contract, after execution." Glass, in a return letter dated June 12, returned the executed contracts and bonds, stating that Petitioner was doing so in order to act "equitably and in good faith", and was fully reserving its rights to contest the erroneous bid by judicial action for equitable relief. Thereafter, Petitioner received notice to proceed with the work and in due course satisfactorily completed the contract within the required period. This was evidenced by a certificate of acceptance of the building by the using agency, which was approved by Respondent on December 4, 1975. (Testimony of Glass, Exhibit 1e, 1g, 1h, 1i, 1j, 11, 1m, 1s) In December, 1974, Petitioner had submitted its claim for an equitable adjustment in the amount of $337,714 which was the amount of the omitted Cast- Crete bid. During the ensuing year Petitioner submitted audits of its expenses on the job to Respondent and in January, 1976, further audit information was provided at the request of Respondent. On May 6, 1976, Respondent informed Petitioner that it would not approve any increase in the contract amount. Thereafter, on June 11, Petitioner filed its petition herein seeking an equitable adjustment in the amount of $337,714. The petition was referred to the Division of Administrative Hearings by the Respondent on August 2, 1976, and the undersigned Hearing Officer was assigned to conduct the hearing therein. (Exhibit 1r, 2, 4, 5, 6) By a Motion to Abate, dated August 23, 1976, Respondent requested that the matter be held in abeyance pending the submission of the petition to the project architect and his rendering of a determination indicating whether the relief should be granted or denied, as a "condition precedent to the contractor obtaining consideration of said petition in any proceeding authorized by Chapter 120, Florida Statutes." Respondent stated in its motion that the contract clearly provided that nay and all claims or disputes should be first submitted to the architect for determination, and that thereafter, either party could obtain administrative review of the determination by filing a written appeal to the Department of General Services within thirty days. The motion further stated that since this prerequisite had not been accomplished, there was no basis for an administrative appeal at that time. On the same date, Respondent advised the architect of the situation and requested expeditious consideration of the matter. On August 27, the architect issued its determination stating "From our personal knowledge of the events during the bid opening process, and the subsequent events that led to the awarding of the bid, we concur in the contractor's request." In November 1976, Respondent's general counsel advised the Hearing Officer that settlement efforts were in progress but requested that the matter be scheduled for hearing nevertheless. Notice of hearing was issued on December 15, 1976, and the case was heard on January 27, 1977. (Exhibits 1t, 1u, Pleadings) Petitioner's intended total bid, including alternates, amounted to $4,459,714. A change order of $194 was issued during the course of the work, amounting to a total of $4,459,908. Petitioner's direct costs on the project were $4,094,890. Overhead was computed at 2.85 per cent of direct costs in the amount of $116,705, for a total cost of $4,211,595. Overhead was computed based on the ratio of total general and administrative expense to total direct costs incurred on all of Petitioner's jobs in process for the year ending May 31, 1975. However, the audit reports included payment in the amount of $335,634 to Cast-Crete Corporation. The actual amount paid to that firm was $325,234 - difference of $10,400, making Petitioner's actual costs $4,201,195. During the course of the contract, Respondent paid Petitioner $4,122,194, resulting in a net loss to Petitioner of $79,001. An anticipated profit for performance of the contract was computed on the basis of the average profit on other jobs of 4.4 per cent, amounting to the sum of $180,377. The latter two sums total $259,378, and it is found that figure is the reasonable amount of Petitioner's claim. (Exhibits 2-5)

Recommendation That Petitioner's claim for equitable adjustment under Project No. BR- 7702/8701 be granted and that a change order be issued increasing the contract price by $259,378.00. DONE and ENTERED this 21st day of March, 1977, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida 32304 (904) 388-9675 COPIES FURNISHED: Donna H. Stinson and Daniel S. Dearing, Esquires Post Office Box 1118 Tallahassee, Florida 32302 James E. Glass, Esquire 2600 First Federal Building 1 Southeast 3rd Avenue Miami, Florida 33131 John A. Barley, Esquire General Counsel Department of General Services Room 110 Larson Building Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 5
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 6
MARPAN SUPPLY COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 96-002777BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jun. 11, 1996 Number: 96-002777BID Latest Update: Nov. 26, 1996

The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.

Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.

Florida Laws (6) 112.061120.57215.422287.001287.012287.057 Florida Administrative Code (1) 60A-1.001
# 7
MID-STATE PAVING CO., INC. vs DEPARTMENT OF TRANSPORTATION, 08-004272BID (2008)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Aug. 28, 2008 Number: 08-004272BID Latest Update: Jan. 29, 2009

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules or policies, or the bid specifications in its proposed decision to award Contract No. T1285 to Intervenor Kamminga & Roodvoets, Inc. ("K & R").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of the proceeding, the following findings of fact are made: On May 14, 2008, the Department released its bid solicitation for Contract T1285. The proposed contract was for the construction of a one-way pair through Lake Alfred, including new construction, reconstruction, milling and resurfacing, widening, drainage improvements, lighting, signalization, signing and pavement marking and landscaping on State Road 600 (U.S. 17/92). Polk County, the location of the project, lies in the Department's District 1. Qualified contractors, including Mid-State and K & R, received an electronic disk containing the solicitation, bid blank, plans and specifications for Contract T1285. The letting date for this project was June 18, 2008. Bids were to be submitted on or before that date via Bid Express, the electronic bidding system used by the Department. No party submitted a protest of the terms, conditions, and specifications contained in the solicitation pursuant to Subsection 120.57(3)(b), Florida Statutes. The work to be performed on Contract T1285 included the installation of limerock road base to be paid for in accordance with line item 0175, Optional Base Group 09 ("Base Group 09"). The bid documents included a set of "Supplemental Specifications." Section 6 of the Supplemental Specification was titled "Control of Materials." Subsection 6-3.3, titled "Construction Aggregates," provided as follows: "Aggregates used on Department projects must be in accordance with Florida Administrative Code Rule 14-103."2 Under the heading "Developmental Specifications" is a February 15, 2008, revision to the Construction Aggregates subsection that provides: Subarticle 6-3.3 (Page 54) is expanded by the following: 6-3.3.1 Department Directed Source for Aggregates: For this Contract, obtain aggregates for use in limerock base from the following vendor: Vulcan Construction Materials LP. Upon award of the Contract, provide the vendor and the Department a schedule of project aggregate needs. Once a schedule has been provided to both the Department and vendor, the Engineer will issue written authorization, with a copy to the vendor, for the purchase of aggregates from the vendor. This authorization is required before aggregates will be released by the vendor. Pick up the required aggregate such that the project schedule will be maintained. Payment to the vendor by the Contractor will be due upon receipt of the materials pursuant to the Department's Vendor Contract No. BDH50. This rate is the unit price agreed upon by the Department and the vendor and will be made available to bid proposal holders at the time of bid at http://www.dot.state.fl.us/construction/aggregate /aggregate.htm. The Department will make payment to the Contractor for the aggregates on progress estimates as a part of the bid unit price for the appropriate pay items. The rate is subject to change and adjustments for such changes will be made to the bid unit price of the appropriate pay items. Disputes with the vendor concerning aggregate supply will not be cause for Contract time adjustments, time suspensions or monetary adjustments to the Contract amount. The Contractor will be solely responsible for providing the necessary advance notice to the vendor and other coordination to obtain timely aggregate supply for the project. The import of Developmental Specification 6-3.3.1 was that all bidders would be required to obtain the limerock needed for Base Group 09 from a single vendor, Vulcan Construction Materials LP ("Vulcan"). The winning bidder would agree to pay Vulcan in accordance with a separate contract negotiated between Vulcan and the Department. The hyperlink provided in Developmental Specification 6-3.3.13 led to a document called "Aggregate Guidance" produced by the Department's State Construction Office. The front page of the Aggregate Guidance document contained "Bidder Information" consisting of a spreadsheet setting forth the Vulcan price per ton for limerock base and limestone coarse aggregate, with the price varying depending on the date and port of delivery. Between January and June 2008, the Vulcan price per ton for limerock base from both the Port of Tampa and Port Canaveral was $16.93. The Aggregate Guidance page contained additional hyperlinks with the following titles: "Aggregate Vendor Contract Usage," "Aggregate Vendor Contract," "Aggregate Vendor Projects List," "Aggregate Vendor Authorization Letter," "Aggregate Vendor Contract Frequently Asked Questions," and "Aggregate Price Adjustment Sheet." Alvin Mulford is the vice-president of Mid-State who, along with his estimator, put together his company's bid for Contract T1285. Mr. Mulford testified that his company has been bidding on Department work, and that he has never before seen a provision similar to Developmental Specification 6-3.3.1. Mr. Mulford directed his estimator to obtain clarification from the Department, to be sure that the bidders were required to purchase the limerock base from Vulcan. One reason for Mr. Mulford's concern was the "exorbitant" rate charged by Vulcan in comparison to other vendors. The restriction to a single supplier was so abnormal, and that supplier's rate was so out of line with the market, that Mr. Mulford decided to seek guidance from the Department through the question and response internet bulletin board provided by the Department for its projects. The question posed by Mid-State was as follows: Does the contractor have to use Vulcan materials for the limerock base at a rate of $16.93 per ton as stated in the Developmental Specifications 6-3.3.1? If so from which location is the material to be picked up? Is it also true that payment to the vendor (Vulcan Materials) will be due immediately upon receipt of the materials? I wanted to clarify this issue as it is unusual for the contractor to be limited to the use of only one vendor. The Department's response was as follows: The unit rate for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Pickup locations for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Payment should be issued by the Contractor to the Vendor (Vulcan Construction Materials LP) upon receipt of the materials as defined in Developmental Specification 6-3.3.1. Because the Department's response did no more than redirect him to the Department's website, Mr. Mulford decided to look at the website in more detail. He investigated the hyperlinks, including the Vulcan contract with the Department. When he clicked on the hyperlink titled "Aggregate Vendor Contract Usage," he found a document that provided as follows, in relevant part: Aggregate Vendor Contract Usage by Districts With the execution of the contract with Vulcan Construction Materials LP, contract number BDH50, Vulcan has committed to provide aggregate in the types and quantities defined in the contract (attached). The process for this contract in Districts 1, 5, and 7, is as follows: Include in the projects identified in the attached spreadsheet the appropriate special provision beginning with the July 2007 lettings. The District Specifications Engineer and District Construction Office will need to coordinate this effort. There are two special provisions for the purpose of notifying construction contract bidders of the Department's intention toward the aggregate. The first special provision is the mandatory version that will direct the bidder to obtain aggregates for the specified work from Vulcan. The second special provision provides the bidder an option to obtain its aggregates from Vulcan. * * * After these projects have been awarded, the contractor is required to notify FDOT and Vulcan a schedule of its aggregate needs for the project. After receiving this schedule, FDOT's Resident Engineer will issue written authorization to the contractor, with copy to Vulcan. This authorization is required before Vulcan will release aggregate to the contractor. Payment to Vulcan will be from the contractor. FDOT will pay cost of aggregate on progress estimates as part of the contractor's bid price for the work. The contractor is required to include in its bid price for the work the cost of the aggregate at the Vulcan rate. The Vulcan rate will be posted on the FDOT State Construction Website showing the rate. When adjustments are made to the Vulcan rate, FDOT will make adjustments in the construction contract unit price. . . . (Emphasis added.) Mr. Mulford testified that he understood the underscored language in the hyperlinked document to be a directive to the bidders and therefore a mandatory requirement of the bid specifications. He did not ask the Department for further clarification because he believed the requirement was clearly stated in the hyperlinked document. David Sadler, the director of the Department's office of construction, testified that the hyperlinked document was developed by his office to offer guidance to the districts as to the concept behind and use of the aggregate vendor contract. The document was not a part of the bid solicitation document. Mid-State's bid price was $7,429,398.44. Mid-State's price for Base Group 09 was $619,645.80, or $19.30 per square yard. This price reflected the Vulcan rate for limerock base of $16.92 plus tax and Mid-State's costs for the work associated with Base Group 09. 19. K & R's bid price was $7,370,505.24, or $58,893.20 lower than the bid price of Mid-State. K & R's price for Base Group 09 was $256,848.00, based on a stated unit price of $8.00 per square yard for limerock base. K & R's price for Base Group 09 was $362,797.80 lower than that of Mid-State, accounting for more than the differential between the overall bids of Mid-State and K & R. Marcus Tidey, Jr., K & R's vice president in charge of its Florida division, testified that K & R was well aware that the Vulcan price for limerock base was $16.93, and that K & R understands its obligation to pay that price to Vulcan should K & R be awarded Contract T1285. Mr. Tidey testified that at the time of bid submission, he cut K & R's bid price to $8.00 per square yard as a competitive strategy to win the contract. Mr. Tidey made a conscious decision that K & R would absorb the difference between $8.00 bid price and the Vulcan price of $16.93. Mr. Tidey testified that K & R needed to win this job in order not to have its crews and equipment sit idle during the economic downturn, and therefore decided to take all of its markup, roughly $250,000, out of the bid. He could have made the $250,000 cut on any item or items in the bid, but decided on Base Group 09 because the limerock base was a big item and therefore easy to cut by a large amount. Mr. Tidey also testified that the contract provides a $400,000 incentive payment for early completion of the job, meaning that K & R will be able to work "faster and smarter" and make up for the price reduction at the end of the job. Mr. Tidey testified that he obtained the Vulcan prices from the Department's website as instructed by Developmental Specification 6-3.3.1. He did not click on the hyperlinks, which appeared to reference the contract between the Department and Vulcan and therefore was of no concern to him. The Department and K & R dispute Mid-State's assertion that the underscored language of the hyperlink set forth in Finding of Fact 15 was a requirement of the bid specifications, based on Mr. Sadler's direct testimony and the underlying illogic and unfairness of requiring bidders to seek out hidden specifications. The Department and K & R concede that if the bid specifications did in fact require the bidders to include in Base Group 09 the full costs associated with obtaining the limerock base from Vulcan, then K & R's bid is nonresponsive. Developmental Specification 6-3.3.1 directed bidders to the Department's webpage for the purpose of obtaining the current Vulcan rate quote. It did not instruct the bidders to investigate the hyperlinks or to assume that the information contained therein was mandatory. Absent an instruction to bidders to review the information contained in the hyperlinks, the Department could not make such information mandatory without placing less curious bidders at a competitive disadvantage. The Department had no intent to play hide-and-seek with the bid specifications in the manner suggested by Mid-State. In addition, K & R points to three line items of the bid specifications in which the Department eliminates competition, instructing the bidders not to bid and inserting a fixed unit price and bid amount for all bidders as to those items. K & R reasonably asserts that the Department was fully capable of treating Base Group 09 in the same fashion, had it intended to require the bidders to pass through to the Department all the costs associated with obtaining the limerock base from Vulcan. However, the Department supplied the bid quantity (31,106 square yards) and left it to the bidders to determine the price per unit they would bid. K & R's bid was responsive. Nothing in the bid specifications prevented K & R from absorbing part of the cost of the Vulcan limerock base and passing the savings on to the Department, or required bidders to pass on to the Department the full costs of complying with the bid specifications regarding Base Group 09. The sole remaining issue is whether K & R's bid, though facially responsive, was materially unbalanced. The Department routinely conducts reviews of bid line items that appear "unbalanced," i.e., for which there appear to be significant differences between the price bid and the Department's cost estimate, in order to determine whether the price difference is due to a quantity error by the bidder. The Department's review confirms that the bid quantity specified on the bid blank is accurate. If a quantity error is found, the bids are recalculated using the bidders' unit prices and the correct quantities to determine whether the bid rankings would change. A bid for which there is a discrepancy between the bid and the Department's estimate is termed "mathematically unbalanced." A mathematically unbalanced bid that affects the ranking of the low bid is "materially unbalanced." A mathematically unbalanced bid is acceptable, but a materially unbalanced bid affords the bidder an unfair competitive advantage and must be rejected. The Department followed its usual procedure in analyzing the K & R bid to determine whether it was unbalanced. Philip Gregory Davis, the Department's state estimates engineer, testified that there were some unbalanced items in the K & R bid, but no quantity errors that would have changed the ranking of the bids. Richard Ryals, the project designer who conducted the unbalanced bid review, testified that the quantities were correct for Base Group 09. As noted above, K & R's low bid for Base Group 09 was an intentional strategy, not the result of a quantity error. K & R's current bonded capacity qualification with the Department is $258 million in contracts at any one time. K & R posted a bid bond, and has more than enough capacity to comfortably perform this contract. There is no economic danger to the Department in accepting K & R's low bid.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Mid-State's formal written protest and awarding Contract T1265 to K & R. DONE AND ENTERED this 9th day of January, 2009, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2009.

Florida Laws (3) 120.569120.57893.20 Florida Administrative Code (2) 14-103.00114-103.002
# 8
A2 M2 R CONSTRUCTION, INC. vs COLLIER COUNTY SCHOOL BOARD, 91-003828BID (1991)
Division of Administrative Hearings, Florida Filed:Naples, Florida Jun. 24, 1991 Number: 91-003828BID Latest Update: Aug. 05, 1991

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: On May 10, 1991, respondent, School Board of Collier County (Board), issued a written invitation to various contractors inviting them to submit proposals for certain construction work to be performed on Naples Park Elementary School in Collier County, Florida. The invitation in question is more specifically identified as Bid No. 120-5/91 Site Development/Naples Park Elementary School. The bidders were advised that their bids must be submitted no later than 2:00 p.m. on June 4, 1991. Bids were timely filed by five contracting firms, including petitioner, A2M2R Construction, Inc. (AMR), and Haas Construction, Inc. (Haas). On June 4, 1991, various school personnel, including Dallas Disney, Board architect, Vicki McKinney, Board assistant director of purchasing, and Pat Humphrey, a Board secretary, and the Board's engineering consultant, Glen Bridges, met for the purpose of opening the sealed bids. They agreed that the five bids would be opened in alphabetical order. This meant that AMR's bid was opened first while Haas' bid was opened fourth. Bridges was assigned the task of opening the bids and reading the dollar amount of each bid. In the case of AMR, it proposed a base bid in the amount of $174,815. When Bridges opened Haas' bid, he said words to the effect that he could not clearly make out the amount of the base bid. This was because the original number had been changed by Haas prior to the submission of its bid, and it could not be clearly read. Accordingly, Bridges handed the proposal to McKinney, who read the number as $146,500. She then handed the bid document to Disney who also concluded the bid was in that amount. At that point, the president of Haas, who was present at the bid opening, was asked if the amount was indeed $146,500. When he confirmed that it was, he was asked to place his initials next to the base bid number. He did so even though paragraph (6)(a) of the Bid Instructions provides that "(a)ny erasures or other corrections in the proposal must be explained or noted over the signature of bidders". According to AMR, this provision required that Haas initial the amount before it sealed and filed its bid. This interpretation of the Bid Instructions was confirmed by Board personnel. Thus, AMR contends that by Haas initialing its bid amount after the bids were opened, Haas violated the Bid Instructions and should have its bid proposal rejected. As it turned out, the bid amount submitted by Haas was the lowest dollar bid on the project, and the Board has proposed to award the contract to Haas. According to the Board's assistant superintendent for business affairs, Robert Wilson, who has supervised hundreds of bid lettings over the last several years, the circumstances in this case were "unusual" in that Haas initialed the bid amount after the bid documents were opened. However, Wilson considered this to be a minor irregularity which, by the terms of the Bid Instructions, could be waived by the Board. Further, he did not find such action to give Haas an undue advantage in the bidding process or place AMR and other bidders at a disadvantage. This was not contradicted. On the bid form used by the bidders, there is a line left blank before the space where the numerical amount of the bid is inserted. AMR contends that the purpose of this space was to be used by a bidder to spell out in words the amount of its bid, and because Haas did not spell out in words the dollar amount of its bid, the proposal should be rejected. However, there is no requirement in the Bid Instructions that the dollar amount be spelled out in words nor was there a school policy imposing such a requirement. Therefore, as to this contention, no irregularity in the bidding process occurred.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered by respondent awarding the contract in question to Haas Construction, Inc. DONE and ENTERED this 19th day of July, 1991, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of July, 1991. APPENDIX TO RECOMMENDED ORDER Respondent: 1-2. Adopted in finding of fact 3. Adopted in finding of fact 2. Adopted in finding of fact 4. 5-7. Adopted in finding of fact 3. Rejected as being unnecessary. Adopted in finding of fact 3. Adopted in finding of fact 4. Adopted in finding of fact 3. COPIES FURNISHED: Mr. James R. Powell, Jr. P. O. Box 150340 Cape Coral, FL 33915 Thomas W. Franchino, Esquire 700 Eleventh Street, South Suite 203 Naples, FL 33940-6777 Dr. Thomas L. Richey, Superintendent Collier County School Board 3710 Estey Avenue Naples, FL 33942

Florida Laws (1) 120.57
# 9
CROSS ENVIRONMENTAL SERVICES, INC. vs DEPARTMENT OF TRANSPORTATION, 20-004216BID (2020)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Sep. 18, 2020 Number: 20-004216BID Latest Update: Jan. 11, 2025

The Issue Whether the Department’s action to reject all bids submitted in response to DOT-RFP-20-5003-DAA, relating to asbestos abatement, demolition, and removal services, is illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact Stipulated Facts (verbatim) The Department is an agency of the State of Florida tasked with procuring the services for Districtwide Asbestos Abatement and Demolition and Removal Services for Right of Way property under the Department’s supervision by law. The Department published a bid solicitation for DOT-RFP-20-5003- DAA, seeking bids to provide District Five Asbestos Abatement and Demolition and Removal Services for FDOT. The RFP included specifications, qualification requirements, instructions on what would be required of responders, a bid price proposal sheet, and the award criteria. Cross Construction and Cross Environmental submitted bids in response to the RFP. Cross Construction’s and Cross Environmental’s bids were evaluated by the Department. There is no debate, challenge, or disagreement raised in the Petitions with regard to the Technical Scores submitted by the responding firms to the RFP, only disagreement on three pay items. On June 15, 2020, the Department’s Selection Committee reviewed and discussed the information presented as to the Technical and Pricing scores of the Responding firms, asked for an additional bid item analysis, and indicated that it would reconvene at a future date for a decision. On June 22, 2020, the Selection Committee reviewed, discussed, and confirmed the recommendation presented by the results of the Technical Review Committee scorings and the Project Manager’s Bid Price analysis and selected Cross Construction and Cross Environmental as Intended Awardees. The Selection committee also found that Johnson’s Excavation and Services Inc., [Johnson] and Simpson Environmental LLC [Simpson] were deemed non-responsive due to irregular, and unbalanced pay items prices. On August 24, 2020, the Department’s Selection Committee decided to cancel the Procurement with the intent to readvertise with adjustments to the Scope and Pricing Structure and decided to reject all proposals. Additional Findings of Fact The “three pay items” referenced in paragraph six of the stipulated facts are the items that ultimately caused the Department to reject all bids in the instant dispute. The three pay items are collectively referred to as mobilization pay items. The RFP directs that bids are to contain two parts. Part I is the technical proposal, and Part II is the price proposal. Section 30.3 of the RFP provides that proposers “shall complete the Bid Price Proposal Form No. 2 and submit [the form] as part of the Price Proposal Package … [and that] [t]he Procurement Office and/or the Project Manager/TRC will review and evaluate the price proposals and prepare a summary of its price evaluation.” Five bidders submitted proposals in response to the RFP. One bidder did not advance beyond the initial review phase because its technical proposal did not meet minimum bid standards. The remaining bidders were CCS, CES, Simpson, and Johnson. Price proposals submitted by each of the remaining bidders were evaluated by the Department. Section 3 of the RFP provides a general outline of the process associated with awarding the contract. The steps are: “Pre-Proposal Conference; Public Opening (Technical Proposals); Price Proposal Opening & Intended Award Meeting; and, Selection Committee Meeting Summarizing Evaluations and Determining Anticipated Award.” The agenda for the “Price Proposal Opening & Intended Award Meeting,” as established by the RFP, provides as follows: Opening remarks of approx. 2 minutes by Department Procurement Office personnel. Public input period – To allow a reasonable amount of time for public input related to the RFP solicitation. At conclusion of public period, the Technical evaluation scores will be summarized. Announce the firms that did not achieve the minimum technical score. Announce the firms that achieved the minimum technical score and their price(s) as price proposals are opened. Calculate price scores and add to technical scores to arrive at total scores. Announce Proposer with highest Total Score as Intended Award. Announce time and date the decision will be posted on the Vendor Bid System (VBS). Adjourn. Section 30.4 b. of the RFP provides that a proposer can be awarded a maximum of 30 points for its price proposal. This section also provides that “[p]rice evaluation is the process of examining a prospective price without evaluation of the separate cost elements and proposed profit of the potential provider.” On June 15, 2020, the selection review committee met publicly for the purpose of opening price proposals and announcing an intended award. Price proposals were opened, and the eligible bidders received the following price scores: CCS - 11.09; CES - 13.22; Johnson - 19.76; and Simpson - 30. In terms of total score, which combined both the technical and price scores, Simpson received a score of 113.00, which was the highest score, followed by CES (107.55), CCS (103.76), and Johnson (101.76). After opening and considering the price proposals of the respective bidders, the selection committee did not announce an intended award at the meeting on June 15, 2020, but instead requested that the project manager “do further analysis on the pay items for any potential imbalance.” The project manager, through a staff member, performed the additional analysis and determined that Johnson and Simpson submitted “irregular, unbalanced pay items” which resulted in their respective bids being deemed non- responsive and thus not eligible for award. The “irregular, unbalanced pay items” are the three mobilization pay items at issue in the instant matter, and are identified on the bid price proposal sheet as items AB200, AB201, and AB202. Simpson bid $400 for item AB200, $100 for item AB201, and $50 for item AB202. Johnson bid $250 for item AB200, $250 for item AB201, and $100 for item AB202. CCS bid $1 for item AB200, $1 for item AB201, and $1 for item AB202. CES bid $1 for item AB200, 75 cents for item AB201, and 50 cents for item AB202. The Department, in evaluating the bidders’ mobilization pay items, considered costs associated with abatement two structures, a 1,500 and 2,250 square feet structure respectively. For the 1,500-square-foot structure, CCS’ AB200 mobilization costs totaled $1,500. For the 2,250-square-foot structure, CCS’ AB201 mobilization costs totaled $2,250. For the 1,500-square-foot structure, CES’ AB200 mobilization costs totaled $1,500. For the 2,250-square-foot structure, CES’ AB201 mobilization costs totaled $1,687.50. For the 1,500-square-foot structure, Johnson’s AB200 mobilization costs totaled $375,000. For the 2,250-square-foot structure, Johnson’s AB201 mobilization costs totaled $562,500. For the 1,500-square-foot structure, Simpson’s AB200 mobilization costs totaled $600,000. For the 2,250-square-foot structure, Simpson’s AB201 mobilization costs totaled $225,000. On June 22, 2020, the selection committee reconvened and announced CCS and CES as intended awardees of the contract. The Department also announced at this meeting that Johnson and Simpson were “deemed non- responsive due to irregular, unbalanced pay item prices.” On June 24, 2020, Simpson filed a Notice of Protest wherein the company informed the Department of its intent to formally protest the intended award of contracts to CCS and CES. On or about July 6, 2020, Simpson filed with the Department its “formal written petition of protest.” Although Simpson’s formal protest is dated July 6, 2020, CCS and CES contend that Simpson’s protest was actually filed on July 7, 2020, thereby making the protest untimely by a day. The Department did not refer Simpson’s formal protest to DOAH for final hearing, but instead considered the issues presented by Simpson in its protest and then attempted to negotiate a resolution with Simpson, CCS, and CES. Those efforts were unsuccessful. The question of the timeliness of the formal bid protest filed by Simpson is not before the undersigned. Nevertheless, the undisputed facts as to Simpson’s protest, as demonstrated by the record herein, are as follows. On June 24, 2020, Simpson filed notice of its intent to protest the RFP. On June 29, 2020, CCS received notice that a bid protest was filed with respect to the RFP. On July 1, 2020, CES filed a public records request “for public records related to the bid protest made to the” RFP. On or about July 6, 2020, Simpson filed its formal written protest with respect to the RFP, and although the evidence is not clear as to the date, it is undisputed that the Department received affidavits from Simpson explaining the factual circumstances surrounding the filing of the company’s formal written protest. On July 15, 2020, the Department notified CCS and CES that “in response to the Formal Written Protest filed by Simpson Environmental Services, the Department will hold a settlement conference” on Friday, July 17, 2020. On July 21, 2020, Simpson, CES, and CCS notified the Department that they “reached an agreed upon settlement proposal.” On August 11, 2020, the Department, after considering the settlement proposal for several weeks, notified Simpson, CES, and CCS that the Department would discuss the RFP at a public meeting to be held on August 24, 2020. As previously noted, it was during the meeting on August 24, 2020, when the Department announced that all proposals received in response to RFP were rejected. CES, on or about July 1, 2020, submitted to the Department a public records request wherein the company sought a copy of documents related to Simpson’s protest. In response to the request, the Department provided CES a copy of the formal written protest filed by Simpson. It is undisputed that the initial copy provided to CES by the Department did not show either the date or time of receipt of the document filed by Simpson. At some point after the settlement conference, the Department provided to CES a date and time stamped copy of Simpson’s formal written protest. There was no evidence presented explaining the circumstances or the process which resulted in the Department providing different copies of Simpson’s formal written protest to CES, and the remaining evidence does not provide a sufficient foundation to reasonably infer that the Department acted with nefarious motives when providing different versions of the documents to CES. Simpson’s formal protest contains the following statement with respect to the price proposal that the company submitted in response to the RFP: Petitioner’s individual bid price items were based in fact, were reasonable and were in conformity with standard industry rates for similar asbestos abatement and demolition and removal projects. Petitioner’s bid price items were also patently similar to bid price items that Petitioner has previously submitted in response to past FDOT proposal requests that ultimately resulted in the corresponding contracts having been awarded to Petitioner. Indeed, Petitioner has a longstanding relationship with the FDOT as Petitioner has previously contracted with FDOT as a vendor performing asbestos abatement services on numerous projects over the course of the past eight years. Petitioner’s price items for bid proposals have remained consistent for each of its past projects with FDOT. Petitioner’s price items for the instant bid proposal did not differ or vary in any material aspect from those proposed by Petitioner for previous projects that FDOT has deemed reasonable. Michelle Sloan works for the Department as a district procurement manager, and was assigned to manage the instant RFP. Ms. Sloan testified that because Simpson protested the Department’s intended decision to award the contracts to CCS and CES, and specifically referenced in its protest “that their bid for mobilization was in conformance with industry standards, as well as previous bids submitted to the agency that were deemed responsive,” she conducted additional review of the Simpson and Johnson bids. Ms. Sloan testified that after reviewing the RFP, the price sheets related thereto, Simpson’s protest, and the additional analysis of the pay items conducted following the June 15, 2020, selection committee meeting, she concluded that material ambiguities existed in the RFP’s mobilization pay items and recommended to the district secretary that the Department “reject all [bids] and re-advertise with a revised pricing sheet and instructions.” On August 24, 2020, the selection committee, following public notice, accepted Ms. Sloan’s recommendation, rejected all proposals, and canceled the procurement with the “intent to re-advertise with adjustments to the Scope and Pricing structure.” A review of the credible evidence demonstrates a rational basis for the conclusions reached by Ms. Sloan and members of the selection committee. Exhibit C of the RFP is titled “Price Proposal/Detailed and Contractual Price Sheet.” The first page of this document provides a general description of the asbestos removal and abatement pay items. The general pay items are as follows: AB100 Fees [as] determined from the Department of Environmental Protection based upon regulated material. AB200 One-time fee necessary to mobilize for full isolation, per parcel, when abatement with isolation is required. AB300 Fees to be charged by square feet for preparation [of] structure before abatement can commence. AB400 Fees to be charged by square feet, to abate asbestos from various surfacing material such as ceiling, walls, beams, plaster, sheetrock and fireproofing using conventional containment methods. AB500 Fees to be charged either by square foot, linear foot or fittings to abate asbestos from various mechanical systems such as boilers, stacks ducts, fittings, pipes, flutes and flanges. AB600 Fees to be charged either by square foot, linear foot or fittings to abate asbestos from various mechanical systems such as boilers, stacks, ducts, pipe, fittings and jackets which involve the use of a Glove bag. AB700 Fees to be charged by square foot, to abate asbestos from various roofing materials such as cement roof shingles, flashing, rolled roof, felts, wood shingles and mobile home coating. AB800 Fees to be charged by square foot or piece to abate asbestos from various materials such as floor tile, mastic adhesive, sheet vinyl, carpet, wood sub- floor, concrete sub-floor, vibrator dampers, wallboard, metal ductwork and sinks with insulation and heat shields (light fixture). AB900 Fees to be charge[d] by landfill for asbestos disposal. The bid price proposal sheet, which is form number 2 of the RFP, provides a listing of specific pay items related to the general “AB ---” items listed in Exhibit C to the RFP. Below is an example of some of the specific pay items listed on the bid price proposal sheet: [See table on next page] Item Number Description (A) Estimat ed Quantit y Unit (B) Unit Pric e Total Bid Amount (A x B) ASBESTOS REMOVAL ABATEMENT AB200 Mobilization for structures less than 2,000 Sq. FT. 1 SQ. FT. AB201 Mobilization for structures [from] 2001 – 5000 Sq. FT. 1 SQ. FT. AB202 Mobilization for structures over 5001 Sq. FT. 1 SQ. FT. AB300 Mask and Seal 1 SQ. FT. AB401 Remove ACM plaster/lathe including all surface materials 1 SQ. FT. AB501 Remove insulation from fittings 1 LF. AB603 Remove insulation from boilers, stacks or ducts piping 1 LF. AB703 Remove roofing cement 1 SQ. FT. AB810 Remove carpet and mastic adhesive 1 SQ. FT. AB820 Remove sinks with insulation 1 SQ. FT. AB901 Non-Friable 1 SQ. FT. General pay item category AB200, as described on Exhibit C, does not reference a “unit of measurement,” but instead notes that items within this category are to be determined on a “one-time – per parcel” basis. When the AB200 general pay item category is compared to the specific pay items for this category enumerated on the bid price proposal sheet (i.e., AB200, AB201, and AB202), it is evident that the unit of measurement “square feet” is listed as the basis for calculating the bid amount for this item when no such unit of measurement is stated for this item on Exhibit C. Comparatively, general pay item categories AB300 through AB800 each expressly references a specific unit of measurement (i.e., square foot, linear foot, or by the “piece”), and these units of measurement carry over to and are consistently reflected on the bid price proposal sheet for the specific pay items enumerated therein. By inserting a unit of measurement (i.e., square feet) in the mobilization pay items listed on the bid price proposal sheet, when the general description on Exhibit C instructs that they are “one-time, per parcel” pay items, the Department created a material ambiguity in the bidding process.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby Recommended that the Department of Transportation issue a final order in Case Nos. 20-4214 and 20-4216 finding that the rejection of all proposals in response to Request for Proposal RFP-DOT-20-5003-DAA was not illegal, arbitrary, dishonest, or fraudulent, and dismissing the two petitions. DONE AND ENTERED this 14th day of December, 2020, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of December, 2020. COPIES FURNISHED: Douglas Dell Dolan, Esquire Florida Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0458 (eServed) Richard E. Shine, Esquire Florida Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399 (eServed) Brian A. Leung, Esquire Holcomb & Leung, P.A. 3203 West Cypress Street Tampa, Florida 33607 (eServed) Diane E. H. Watson, Esquire Cross Environmental Services, Inc. Post Office Box 1299 Crystal Springs, Florida 33524-1299 (eServed) Kevin J. Tibault, P.E., Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 57 Tallahassee, Florida 32399-0450 (eServed) Sean Gellis, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0450 Andrea Shulthiess, Clerk of Agency Proceedings Department of Transportation Haydon Burns Building 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0450 (eServed)

Florida Laws (2) 120.569120.57 DOAH Case (3) 12-084620-4214BID20-4216BID
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer