Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GRACIELA ZARA, 84-002421 (1984)
Division of Administrative Hearings, Florida Number: 84-002421 Latest Update: Dec. 04, 1990

Findings Of Fact At all times pertinent to the issues herein, Graciela Zara was a registered roofing contractor in the State of Florida having license number RC 0035417. Respondent qualified Rolando Lopez Roofing Corp. at all times material to the complaint. Roofing work was done on the building located at 8413 8415 Hardin Avenue; however, the roofing work was not done by Rolando Lopez Roofing, but rather by Chungo, an employee of M. G. Construction Company, the owner of the building. Certain materials for the roofing work were delivered to 8413-8415 Harding Avenue by Tops All Roofing & Building Products, Inc., and those materials were ordered by Rolando Lopez and/or Renee Garcia. Rolando Lopez Roofing performed roofing work at the the bank at Las Americas Shopping Plaza, 8500 N.W. 85th Street; however, there was no evidence presented that Rolando Lopez Roofing failed to obtain a permit for the work it performed. Tropical Roofing entered into a contract for roofing work at the home of Mr. Sosa, 3001 S.W. 96th Avenue, Miami, Florida. 2/ The work was subcontracted to and done by Rolando Lopez Roofing. Although a permit for the work was required, respondent failed to obtain a permit. The respondent was responsible for obtaining the permit because the contractor that performs the work is responsible for obtaining the permit. Leon Gomez entered into a contract with Rene Garcia for roofing work at 309 Pinecrest Drive. Rene Garcia performed the roofing work on the house and was paid for the work by Mr. Gomez. However, the permit for the roofing work was obtained by the respondent. Roofing work was performed at the home of Felipe Acosta, 401 Flagami Boulevard, Miami, Florida. The permit for the roofing work was obtained by respondent. The contract for the work was with Rolando Lopez Roofing. The roofing work was performed by Rene Garcia and other workers that Mr. Acosta did not know. Mr. Acosta does not know Rulando Lopez. The contract negotiations and the payment for the job were handled by Mr. Acosta's brother. Mr. Acosta did not know whether Rene Garcia or Rolando Lopez received payment for she roofing work, but he knows his brother paid one of them. The roofing work was performed pursuant to the contract with Rolando Lopez Roofing. On June 1, 1983, Rolando Lopez Roofing Corp. issued a check for $11,667.86 to Tops All Roofing & Building Products. The check was returned by the bank stamped "Account Closed." On September 16, 1983, Rolando Lopez was adjudicated guilty of issuing a worthless check in violation of Section 832.05. Mr. Lopez paid $5,000 in restitution to Tops All Roofing & Building Products, but he was unable to pay the remaining amount because he has been unable to get any work. There was no evidence that Rolando Lopez Roofing Corp. failed to pay creditors for materials furnished. Although Rolando Lopez failed to make full restitution to Tops All Roofing and Building Products for the $11,667.86 check that was returned, there was no evidence that the check was for building supplies furnished to Rolando Lopez Roofing. Rolando Lopez testified that the check was written for the benefit of his nephew, Rene Garcia, to be used as collateral. Further, there was no evidence that Tops All Roofing & Building Products had furnished any building materials to Rolando Lopez Roofing prior to June 1, 1983, the date of the check. There was no evidence presented that Rene Garcia was not licensed by the State of Florida as a registered or certified roofing contractor

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Respondent be placed on probation for a period of six months. DONE and ORDERED this 2nd day of January, 1985, in Tallahassee, Leon County, Florida. DIANE GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of January, 1985.

Florida Laws (4) 120.57489.119489.129832.05
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN W. THORN, 84-000154 (1984)
Division of Administrative Hearings, Florida Number: 84-000154 Latest Update: Aug. 22, 1984

Findings Of Fact The Respondent is a registered roofing contractor, having been issued license number RC 0020923. On may 27, 1982, the Respondent, doing business as T & T Roofing Company, contracted with Jessie Reid, 1021 Abeline Drive, Deltona, Florida, to replace an existing shingle roof for a total contract price of $2,406.20. At all times material hereto, the Respondent was registered with the Construction Industry Licensing Board as qualifying agency for A. L. Roofing Specialists. At no time has the Respondent qualified T & T Roofing Company. On August 26, 1982, when the Respondent completed work on Jessie Reid's roof, he was paid $2,406.20 which was the entire contract price for this job. The Respondent was to return to the job site to inspect the roof and correct minor remaining problems. However, when the Respondent would not return to the job, even after repeated calls, it was determined that there is a difference in shingle thickness at points on the roof, and the rain runs down over the gutters instead of into them. Further, the hip and ridge caps are of a different material than the major portion of the shingled roof; there are exposed nails; and the gutters are filled with roofing debris. The Respondent has not been responsive to communications and he has refused to make the necessary corrections to Jessie Reid's roof. The Respondent never obtained a permit for the reroofing work done for Jessie Reid at 1021 Abeline Drive, in Deltona. A permit is required to do reroofing work in Deltona, which is within the jurisdiction of Volusia County.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Registered Roofing Contractor's license number RC 0020923 held by the Respondent, John W. Thorn, be revoked. DONE AND ENTERED this 30th day of May 1984 in Tallahassee, Florida. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of May 1984. COPIES FURNISHED: Edward C. Hill, Jr., Esquire 130 North Monroe Street Tallahassee, Florida 32301 Mr. John W. Thorn Post Office Box 1897 Deland, Florida 32720

Florida Laws (5) 120.57455.227489.105489.119489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. LARRY DAVID COMES, 87-001719 (1987)
Division of Administrative Hearings, Florida Number: 87-001719 Latest Update: May 13, 1988

Findings Of Fact At all times material to these proceedings, the Respondent LARRY DAVID COMES, was licensed by the State of Florida as a registered specialty contractor and held license number RX00400762. Mr. Comes is the qualifying agent for D & L Enterprises. At all times material to these proceedings, the Respondent CHARLES J. GOREE was licensed by the State of Florida as a certified general contractor and held license number CG C007621. Mr. Goree is the qualifying agent for CJC Incorporated. In the beginning of the year 1985, the Island Village Association decided to reroof all six buildings located in the condominium project. At the time of the decision, all of the roofs were leaking. The existing roofs had been repaired and patched numerous times since the condominiums were built in 1973. On February 27, 1985, the Respondents COMES and GOREE submitted a joint proposal to the association to remove the existing built-up roof, apply a Neoprene/Hypalon roof, and remove and reshingle the mansard roof for $19,865.00. On April 15, 1985, a written contract was entered into between Island Village Condominium Association and David L. Comes, d/b/a D & L Enterprises, as contractor for the reroofing of Building "C." The Contract required the contractor to furnish all materials and labor to remove the existing built-up roof. Rotten wood on the deck was to be replaced on a time and materials basis. Damaged scuppers were to be replaced and other scuppers were to be cleaned out by the contractor. The Neoprene/Hypalon system would then be applied to the flat roof and the parapet walls. The mansard roof was to be removed and reshingled. Although Charles J. Goree, d/b/a CJC Incorporated, was not named in the contract, the omission was an oversight. At all times during the course of the reroofing project, the Respondent GOREE was responsible for the removal of the existing built-up roof and the application of new shingles to the mansard roof. The Respondent COMES was responsible for the application of the Neoprene/Hypalon roofing system. The reroofing project was a joint undertaking in which Respondents GOREE and COMES exercised equal authority, joint control, or right of control. The Respondents had a community of interest in the performance of the contract with the association. Respondents GOREE and COMES were familiar with what was required of each of them under the verbal joint venture agreement as they had conducted business in the same manner over an extended period of time on several projects. On May 10, 1985, Respondent GOREE applied for and received a building permit for the reroofing of Building "C" at Island Condominiums. During the removal of the built-up roof, GOREE observed "an absolute mess and disaster." The roof had been patched in various ways on numerous occasions. GOREE observed a few "T nails" in a piece of metal stripping picked up with shovels on the roof. The "T nails" discovered were the type which are shot into materials from a nail gun. (See GOREE Exhibit #2) They are not used to secure plywood on a deck because of their short length. Another "T nail," such as GOREE's Exhibit 2, was found by GOREE lying on the area of the roof by the air conditioners. This area of the existing roof was not removed or disturbed during the reroofing process. In the application of his common sense and knowledge of good construction practices and in light of the material in which the "T nails' were located, Respondent GOREE was not put on notice that these "T nails" may have been used to fasten the plywood decking. The type of "T nail" which was used upon plywood roof decking a few years ago in Florida was longer, thicker, and shaped like an elongated wedge. (See GOREE Exhibit 4) None of the "T nails" formerly used for plywood decking were observed by GOREE on the roof. Once the built-up roof was removed, Respondent COMES acted within the terms of the joint venture agreement by applying the Neoprene/Hypalon roofing system in full compliance with the specifications as set forth in the contract with Island Village Condominium Association. During the application of the system, COMES and his crew did not observe any conditions on the plywood decking which would alert them to the possibility of any future problems with the system. On May 17, 1985, Mr. Jim Peaks, an Inspector for Brevard County, completed a "dry in" inspection of the roof on Building "C" which had been requested by Respondent GOREE. Mr. Peaks placed a stop order on the project because the Neoprene/Hypalon roofing system was not an approved product under the Southern Building Code which he believed was in effect in Brevard County on May 14, 1985. In actuality, the 1982 Standard Building Code was in effect at the time. Upon receipt of the stop order, Respondents COMES and GOREE went to the building department and met with Murray Schmidt, Mr. Peaks' supervisor. Mr. Schmidt had the authority to override Mr. Peaks' stop order. Mr. Schmidt, who was new to the county and his position, discussed the stop order with the Inspector. Mr. Peaks refused to remove his stop order because of the lack of code compliance. Mr. Schmidt verbally allowed the Respondents GORE and COMES to continue to work on the roof. Mr. Peaks was told to investigate the roofing system with the Southern Building Code Conference in Birmingham, Alabama. The Respondents were not notified again as to the status of the stop order, one way or the other. Because the Respondents had been told to continue the work on the roof by Mr. Schmidt, who had the authority to override stop orders, the Respondents reasonably assumed that a stop order was no longer in effect. In fact, the permit had the notation "See Murray" on it after the stop order notation. Upon completion of the project, Respondent COMES contacted the building department and requested a final inspection. In the usual course of dealing between contractors and the building department in Brevard County, a contractor is notified only if there is a problem with the project which needs correction before final approval. Neither COMES or GOREE received notification of a problem. Another recognized, usual course of dealing between a contractor and the building department is that the department notifies an owner or the contractor if a six month permit has expired and a final inspection has not been completed. GOREE was not notified of any permit expiration in this case. Again, the Respondents were given the impression by the inactivity in the building department that business was being conducted in the usual manner. The Respondents believed, based upon past and ongoing dealings with the department, that all of their obligations had been met on the reroofing project. On May 28, 1985, the final payment was received from Island Village Condominium Association and a limited warranty was issued in both Respondents' company names, pursuant to the contract with the association. Shortly after completing the job on Building "C," Respondent COMES was called to repair leaks in the new roof. COMES responded promptly and courteously, and placed the blame for the leakage on various factors such as: (1) The short "T" fasteners had begun popping through the Neoprene/Hypalon and destroyed its ability to prevent water penetration. (2) The roof had an inadequate drain system. (3) The plywood deck was bowed in a concave fashion due to the years of improper weight and excess water on the roof. During a meeting with the board of directors of the association requested by COMES, COMES offered to put on a new roof if the board would install sump pumps to remove standing water. The board rejected COMES offer and authorized the condominium property manager to seek other solutions. The Respondents were not contacted by the board again concerning alternative solutions to the problem. In June of 1986, Mr. Rex Lahr, the condominium property manager, began a review of the roof situation. After consulting with Mr. Tom Butler of the county building department, Mr. Lahr decided that an architect needed to be retained by the association to determine whether a structural deficiency or the new roofing system caused the leaks in the roof. An architect was not hired by the association. A traditional, built- up roof was applied over the Neoprene/Hypalon roofing system. In the application of the new roof, the drainage system was redone and the flat roof was given pitch, thereby redesigning the roof as well. Mr. Robert B. Hilson, who was tendered as an expert witness in the case, opined that the Respondents COMES and GOREE failed to properly determine whether the roof deck was in a condition to accept the Neoprene/Hypalon system. Mr. Robert H. Adams, who was tendered as an expert witness in the case, opined that the leaks which developed soon after the application of the Neoprene/Hypalon system indicated that the deck was not in a condition to accept the system. Although there is some basis in fact for the opinions rendered by the two experts, their opinions must be rejected for the following reasons: (1) The experts did not personally observe the building, nor was a determination made which would exclude the possibility that the roofing system failed as a result of structural or design defects. (2) There is ample evidence in the case to support a finding that the leaks were caused by structural or design defects, as well as latent defects not readily observable to the Respondents at the time the roofing system was applied, and outside the terms of the reroofing contract. Some examples of evidence which support a finding that the leaks were caused by structural or design defects are: (1) Mrs. Delores Hammels' testimony that all six buildings had to be reroofed as they all leaked periodically throughout their 12 years of existence; (2) the redesign of the drainage system and the placement of a pitch on the roof by Mr. Roush; (3) the testimony and sketch submitted by Respondent GOREE (GOREE Exhibit #5) which shows that an identical building with a pitch on the roof allows the drainage system, including the internal hidden piping system, to work correctly. The effective redesign of the roof by Mr. Roush confirms this theory as much as, or more than, Mr. Robert H. Adams' theory that the deck was not in a condition to accept the Neoprene/Hypalon system.

Florida Laws (4) 120.57489.105489.119489.129
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs CHRIS RAMEIZL, D/B/A C. J. HOME IMPROVEMENT, 98-001283 (1998)
Division of Administrative Hearings, Florida Filed:Miami, Florida Mar. 16, 1998 Number: 98-001283 Latest Update: Feb. 05, 1999

The Issue Whether Respondent committed the offenses alleged in the Administrative Complaint and the penalties, if any, that should be imposed.

Findings Of Fact At the times pertinent to this proceeding, Respondent was not registered, certified, or otherwise licensed to engage in contracting in the State of Florida. At the times pertinent to this proceeding, Respondent conducted business through an entity known as C. J. Home Improvement Corporation, which was also not registered, certified, or otherwise licensed to engage in contracting in the State of Florida. In 1995, Joseph Pallant was one of the owners and the manager of a commercial building located at 3700 Biscayne Boulevard, Miami, Florida. In January 1995, Mr. Pallant entered into an agreement to lease the building for a term of ten years to a non-profit organization named PWAC, an acronym for People With Aids Coalition. PWAC had an office in the adjacent block and wanted to operate a thrift shop at the subject premises. The roof on the subject building leaked. The parties agreed that Mr. Pallant would pay to replace the roof and that PWAC would thereafter be responsible for maintenance. The officers of PWAC informed Mr. Pallant that they wanted Respondent to do the roofing work. There was a conflict in the evidence as to whether Mr. Pallant knew that Respondent was unlicensed. It is clear that Mr. Pallant and Respondent knew one another prior to January 1995. Based on Mr. Pallant's testimony, which the undersigned finds credible, it is found that Mr. Pallant knew that Respondent was in the building repair business, but that he did not know Respondent was unlicensed. Respondent's assumption that Mr. Pallant knew he was unlicensed is not as credible as Mr. Pallant's direct, unequivocal testimony that he had no such knowledge. After having several conversations with Mr. Pallant by telephone and at the building, Respondent prepared a written proposal on his business form to do the work necessary to replace the roof. The proposal was submitted to PWAC. The proposal described in detail the work that would be done and the materials that would be furnished, the time frame for the work, and the price. The price was set at $6,183.00 plus $400.00 if certain additional work would have to be done on certain drains. PWAC was provided a copy of the proposal that was dated February 25, 1995. Respondent signed this proposal and affixed the corporate seal of his business entity. Under Respondent's signature was the phrase "personally individually guaranteed." At all times pertinent to this proceeding, Respondent knew that Mr. Pallant was one of the owners of the building and that he would be paying for the roofing work. On February 27, 1995, Respondent and Mr. Pallant met. Respondent gave Mr. Pallant an unsigned copy of the written proposal (dated February 27, 1995, but otherwise identical to the form given PWAC, but dated February 25, 1995). After they discussed the work, Mr. Pallant accepted the proposal and gave Respondent a check made payable to C. J. Home Improvement in the amount of $3,100.00. Respondent accepted this check and deposited the proceeds of the check in his company's bank account. Without the prior knowledge or consent of Mr. Pallant, Respondent attempted to subcontract the roofing job to a licensed roofer named Don Palmier.1 No work was started on the job. In March 1995, Mr. Pallant met with representatives of PWAC and Respondent to discuss the lack of progress. As a result of that meeting, Mr. Palmier refused to proceed with the roofing job2 and Mr. Pallant learned that Respondent was unlicensed and could not do the work. During the course of the meeting PWAC cancelled its lease. Mr. Pallant subsequently filed suit against C. J. Home Improvement for the return of the $3,100.00. Despite obtaining a final judgment for that sum plus costs and fees, the Respondent has not satisfied any portion of the judgment. As of April 23, 1998, the Petitioner's costs of investigation and prosecution in this case, excluding costs associated with an attorney's time, totaled $269.62.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a final order that adopts the findings of fact and conclusions of law contained herein; finds Respondent guilty of violating the provisions of Section 489.127(1)(f), Florida Statutes, as alleged in Count I of the Administrative Complaint; dismisses Count II of the Administrative Complaint; imposed an administrative fine against the Respondent in the amount of $2,500.00; and assesses costs against Respondent in the amount of $269.62. DONE AND ENTERED this 10th day of September, 1998, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of September, 1998

Florida Laws (8) 120.5720.165455.227455.228489.105489.126489.127812.014
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs DARRYL S. SAIBIC, 95-001079 (1995)
Division of Administrative Hearings, Florida Filed:Miami, Florida Mar. 06, 1995 Number: 95-001079 Latest Update: Mar. 25, 1996

Findings Of Fact Jurisdiction findings Petitioner is the state agency charged with regulating licenses for roofing contractors in the State of Florida. At all times material to the allegations of these cases, Respondent held two licenses; he was a certified roofing contractor, license no. CC CO55580, and a registered roofing contractor, license no. RC 0060386. Respondent filed an application to qualify the company, D.S.S. & Sons, Inc., as a licensed roofing contractor; however, he failed to complete all documents necessary for licensure, and his application was closed for lack of response effective August 3, 1993. Respondent's address of record with the Department is 821 SW Dwyer Street, Port St. Lucie, Florida 34983. D.S.S. & Sons, Inc. is not now, nor has it ever been, licensed to perform roofing construction by the State of Florida. Facts common to all consumers On or about August 24, 1992, Hurricane Andrew struck Dade County, Florida, resulting in damage to hundreds of roofs. Roof repair or total replacement following the storm was not uncommon. Due to the large amount of damage, and the demand for roofing materials created by the volume of work to be performed, some contractors had difficulty obtaining roofing supplies. Additionally, some contractors had difficulty hiring qualified labor to perform the extensive roofing that was in great demand. The problems with obtaining materials and labor, however, were short term in that most roofing contractors made arrangements to bring in supplies and staff from other areas. In fact, by the time the work was to be performed in connection with these cases, the problems which had plagued the Dade County contractors were subsiding. Additionally, at all times material to these cases, the weather would not have been a factor to justify the delays complained of by these consumers. Rainy weather did not cause any prolonged work delays after the storm. Findings as to Helmly Charles Helmly resides at 11985 SW 98th Lane, Miami, Florida. His home was damaged by Hurricane Andrew and required roof replacement. Mr. Helmly contracted with Respondent to re-roof his home for the sum of $17,940.00. The contract was signed by Respondent's salesman, Felix Fowler, and identified D.S.S. & Sons, Inc. doing business as Darryl Saibic, Roofing Contractor as the licensed entity. Mr. Helmly paid an initial deposit of $5,382.00 in order for the Respondent to begin work on the project. The next payment, an additional $5,382.00, was to be due at the "dry in" stage of the job, with the final payment (the balance) due on completion. One of the contract provisions Mr. Helmly insisted upon was a completion deadline to be stated in the contract. He was expecting visitors and he was anxious to have the home re-roofed before their arrival. He insisted that a guaranteed completion date of March 7, 1993 be noted on the face of the contract. Mr. Helmly complied with all requirements of the payment schedule outlined by the contract. In fact, he remitted $10,764.00 even though the roof had not been at the "dry in" stage. Between January and February, 1993, the Respondent removed the old roof, installed a base sheet, and nailed a single ply roof membrane to the roof. After February, 1993, the Respondent failed to timely complete the Helmly roof. The value of the work performed by Respondent on the Helmly roof was no more than $3,588.00. The Respondent did not respond to numerous telephone calls and letters from Helmly, and threatened to place a lien on the Helmly property when Mr. Helmly attempted to cancel the contract in May, 1993. Mr. Helmly went to the Dade County Building Department and complained about roof leaks in June, 1993 (Respondent had still not done any further work). On or about June 4, 1993, Respondent sent a crew to the Helmly property to repair the roof. The repairs caused the roof to leak more. Respondent did not refund Mr. Helmly's money, did not complete the roof, and showed a gross indifference to the plight which resulted when he failed to timely complete the project. In July, 1993, desperate to have his roof completed, Mr. Helmly offered to purchase the tiles himself if Respondent would have a crew come install the new roof. Respondent agreed to have a crew install the tile within ten days of its arrival. On September 17, 1993, Mr. Helmly took delivery of the new tile, paid for it in full (a cost of $4,803.00) and notified the Respondent so that the installation could begin. Respondent never returned to complete the re-roofing. He failed to honor his verbal agreement to install the tiles. By letter dated October 1, 1993, Respondent offered to reimburse Helmly for the overage if he would hire another contractor to complete the job. On October 19, 1993, Mr. Helmly hired a new contractor who completed the installation of the new roof in early November, 1993. Approximately eight months after the deadline on Respondent's contract, Mr. Helmly had his new roof. Extra expenses totalling $2,936.21 were paid by Mr. Helmly as a result of the Respondent's abandonment of this job. Findings as to Gurdian On January 14, 1993, the Gurdians contracted with Respondent through his agent, Ed Comstock, to repair the roof on their home located at 13301 SW 110 Terrace, Miami, Florida. The contract was executed as D.S.S. and Sons, Inc. d/b/a Darryl S. Saibic, Roofing Contractor and called for a total payment of $7,725.00 for the work to be done. The Gurdians made a deposit of $2,300.00 on January 14, 1993 by check made payable to D.S.S. and Sons, Inc. and received a partial release of lien. On February 8, 1993, the Respondent pulled a permit for the Gurdian home but never called for inspections on this project. In February, 1993, all the tiles were removed from the roof and roofing paper was installed. On March 1, 1993, the Gurdians made a second payment of $2,300.00 by check made payable to D.S.S. and Sons, Inc. and received another partial release of lien. The Respondent did not timely complete the Gurdian roof. From June through November, 1993, Respondent sent the Gurdians unsigned notices claiming he would return to their job but did not do so. Numerous excuses were offered as to why the project was not completed; however, none of these had merit. The Gurdians waited until April, 1994 hoping the Respondent would return and complete the work. They drove to Respondent's office and left a message seeking assistance. Finally, Respondent recommended a company called CTI to complete the roof work for the Gurdians. When contacted, CTI told the Gurdians it would cost $7,600.00 to complete their job for which they, not Respondent, would be responsible. The Gurdians then attempted to notify the Respondent at his address of record by certified mail of their continuing problems but the letter was returned to them unopened. In June, 1994, the Gurdians hired another company to finish their roof which was finally complete and passed inspections on July 26, 1994. The Gurdians were required to pay a total of $13,475.00 to have their roof replaced because the Respondent failed to perform under the original contract. Due to the Respondent's abandonment and indifference in connection with this project, the Gurdians were damaged in an amount not less than $4,200.00. The value of the work performed by Respondent on the Gurdians' roof did not exceed $1,545.00. Respondent has not refunded any of the funds paid by the Gurdians. Findings of fact as to Vila Marta Vila resides at 11116 SW 133 Place, Miami, Florida 33186. Like the others discussed above, the Vila home was damaged and required a new roof. On January 13, 1993, Vila signed a contract with Ed Comstock acting on behalf of D.S.S. and Sons, Inc., doing business as Darryl S. Saibic, Roofing Contractor, to have her roof repaired for a total contract price of $7,200.00. A down payment of $2,160.00 made payable to the company was made at that time. On February 8, 1993, Respondent pulled a permit to re-roof the Vila home. On February 15, 1993, Vila paid an additional $2,160.00 to Respondent. At that time Respondent removed the tiles from the Vila roof and installed one layer of roofing paper over the roof decking. Despite representations from Respondent that new tiles would be delivered in approximately three to four weeks, the Respondent did not install a new roof on the Vila home. In February and March, 1993, the roof was patched three times to stop leaks but no substantive work was performed to install new tiles. Respondent did not return to the Vila home despite numerous requests from the homeowner for the work to be completed. In June, 1993, Respondent represented that the Vila job might be completed if the tiles were sent out COD. When Vila attempted to verify that information, she was told she had paid enough to not have that concern. However, no tiles were ever delivered to her home. In August, 1993, Vila, after Respondent failed to return telephone calls, wrote to Respondent and demanded a refund. She has not received one. Vila ended up paying $7,754.00 to another contractor to have her roof replaced. The value of the work performed by Respondent on the Vila project did not exceed $1,440.00 yet he has failed or otherwise refused to refund the difference between that amount and what she paid. Vila has suffered monetary damages in an amount not less than $4,800.00 as a result of Respondent's abandonment of this project. Findings of fact as to Bermudez Mr. and Mrs. Bermudez reside at 8335 SW 147th Place, Miami, Florida. On November 30, 1992, they signed a contract with Respondent in the amount of $6,400.00 to correct extensive leakage on both floors of the Bermudez home. Mrs. Bermudez gave a deposit in the amount of $1,860.00 and was told that the repairs would begin in two weeks and be completed in approximately five weeks. In December 1992, and January, 1993, the Respondent performed some minor patching but no significant work was undertaken to repair the Bermudez home. In January, 1993, Respondent pulled a permit to replace the Bermudez roof. Within a week of the permit, Respondent sent an unsigned form letter to the Bermudez advising them that there would be delays. In February and March, 1993, the Respondent's crew stripped the old tile off the Bermudez home and installed batten and roofing paper over the decking. Mrs. Bermudez made deposits totalling $3,720.00 to Respondent in connection with this contract. Despite numerous requests from Mrs. Bermudez, Respondent did not complete the roof. In July, 1993, Respondent sent a crew to the Bermudez home in connection with a leak but the repair did not resolve the problems and did not substantively finish the roof. As with the other cases, between July and November, 1993, Respondent sent numerous unsigned form letters to Mrs. Bermudez offering false or ridiculous excuses for why the project had not been completed. In January, 1994, Mrs. Bermudez filed a formal complaint against Respondent but he never completed the job nor refunded the deposits. Between March and July, 1994, Respondent represented he would complete the Bermudez job but did not do so. The Bermudez roof was not completed until December 13, 1994. As a result of Respondent's incompetence, inability, or refusal to complete the Bermudez roof, the family lived with a leaking roof for approximately two years and incurred unnecessary expenses. Respondent showed a gross indifference to the plight of the Bermudez family. Respondent could not have timely completed the projects described above during the period July, 1993 to July, 1994, as his workers compensation had expired. The numerous promises to perform the contracts as originally agreed were meaningless.

Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order revoking Respondent's licenses, requiring Respondent to make full restitution to the consumers in these cases before being entitled to seek new licensure, imposing an administrative fine in the amount of $10,000, and assessing costs of investigation and prosecution of these cases as set forth in the affidavits filed in this cause. DONE AND RECOMMENDED this 25th day of October, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of October, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 95-1079, 95-1080, 95-1081, 95-1082 Rulings on the proposed findings of fact submitted by the Petitioner: 1. Paragraphs 1 through 155 are accepted. Rulings on the proposed findings of fact submitted by the Respondent: 1. None submitted. COPIES FURNISHED: Elizabeth Masters Senior Attorney Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 230 Jacksonville, Florida 32211 Darryl Saibic 821 S.W. Dwyer Road Port St. Lucie, Florida 34983 Richard Hickok Executive Director Department of Business and Professional Regulation Construction Industry Licensing 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 489.1195489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID MORTON, 82-002861 (1982)
Division of Administrative Hearings, Florida Number: 82-002861 Latest Update: Dec. 04, 1990

The Issue By Administrative Complaint filed on March 24, 1982, the Petitioner, Department of Professional Regulation, charged the Respondent, David Morton, with specific violations of Florida Statutes and Section 81-64 of the City of Hollywood Ordinances. The charged violations generally involve the alleged failure of Mr. Morton to obtain building permits prior to performing roofing repairs and failure to honor and make good certain guarantees that he gave on two roof repair jobs. Petitioner presented the testimony of Carol Glovan, of the City of Hollywood Building Department; Maurice Segall, complainant; and Hershal K. Deuchare, complainant. Petitioner's Exhibits 1 through 7 were received into evidence. Respondent failed to appear and, therefore, presented no witnesses or documentary evidence on his behalf. The counsel for the Petitioner submitted proposed findings of fact and conclusions of law for consideration by the Hearing Officer. To the extent that those proposed findings of fact and conclusions of law are not adopted in this order, they were considered and determined to be irrelevant to the issues in this cause or not supported by the evidence.

Findings Of Fact Respondent is a registered roofing contractor having been issued License No. RC0030473. David Norton was first licensed as a registered roofing contractor in July, 1977. License No. RC0030473 was issued to David Morton qualifying David Morton Roofing, 6422 Southwest 24th Street, Miramar, Florida 33023. Since qualifying David Morton Roofing, the Respondent has changed business addresses but has not qualified any other business name for the purpose of performing work under his license. On May 8, 1980, the Respondent contracted with H. Deuchare to perform repairs on the roof of the Deuchares' home located at 5521 Buchannon Street, Hollywood, Florida. The contract price was $500. The written contract dated May 9, 1980, and attached as a part of Petitioner's Composite Exhibit No. 3, reflects that the name in which the Respondent was doing business at that time was "David M. Roofing." The contract also provided for a one-year guarantee against faulty material and workmanship. Respondent performed the roof repairs on the Deuchare home but failed to obtain a permit for the work as required by Section 81-64, City of Hollywood Ordinances. After completion of the work, the roof continued to leak, and after two calls from Mr. Deuchare, the Respondent came out and attempted to repair the work. Following this repair effort, the roof leaked worse than before. After continuing calls, the Respondent finally got the leak fixed. However, during the course of making the final repair, the Respondent removed tiles from the roof and broke certain of the tiles. Following completion of the repair, Respondent did not put the tiles back in place and refused to come back and replace the broken tiles. The Respondent made a total of three repair visits to the Deuchare home and on the occasion of each call, was very cordial. On April 22, 1981, Respondent contracted with Maurice Segall to perform roof repairs on the Segalls' home located at 4400 Lincoln Street, Hollywood, Florida. The contract price was $1,075.00. The contract which is attached to Petitioner's Composite Exhibit 4 is dated April 22, 1981, and reflects that the Respondent was doing business in the name of David M. Roofing. The contract also provided for a guarantee for seven years against faulty material and workmanship. The Respondent performed the work on the roof but failed to obtain a building permit prior to beginning the work as required by Section 81-64, City of Hollywood Ordinances. A building permit was later obtained after the repairs were completed. After the Respondent performed the work, the roof continued to leak, and after many calls, Respondent sent someone out to make additional repairs. After Mr. Segall initiated an action with the county licensing board, Mr. Morton did come out and do the roof over again and performed the work in a proper manner. Mr. Morton did obtain a proper hermit prior to performing the work the second time. No charge was made to Mr. Segall for the work performed in redoing the job. Following this work, the roof did not leak.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED: That the Construction Industry Licensing Board enter a Final Order finding Mr. David Morton to have violated Florida Statutes 489.129(1)(d) and Florida Statutes 489.119. It is further recommended that the Board impose an administrative fine upon the Respondent of $250 and that the Respondent be placed on probation for a period of six months. RECOMMENDED this 11th day of April, 1983, in Tallahassee, Florida. MARVIN E. CHAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of April, 1983. COPIES FURNISHED: Michael J. Cohen, Esquire Suite 101, Kristin Building 2715 East Oakland Park Boulevard Ft. Lauderdale, Florida 33306 Mr. David Morton 6432 S.W. 24th Street Miramar, Florida 33023 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (3) 455.227489.119489.129
# 6
PINELLAS COUNTY CONSTRUCTION LICENSING BOARD vs RICHARD STRATTON, 17-004640 (2017)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Aug. 15, 2017 Number: 17-004640 Latest Update: Oct. 06, 2024
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JERRY E. SMITH, 82-001693 (1982)
Division of Administrative Hearings, Florida Number: 82-001693 Latest Update: Apr. 27, 1983

The Issue Whether Respondent's registered roofing contractor's license should he revoked, suspended or otherwise disciplined based on charges that he violated Ch. 455, Florida Statutes (1979), by (1) abandoning a construction project; making a misleading, deceptive or untrue representation in the practice of his profession; (3) violating local building codes in two instances; and (4) engaging in the business of contracting in a county or municipality without first complying with local licensing requirements.

Findings Of Fact At all times material hereto, respondent held registered roofing contractor's license, number RC 0033215, issued by the State of Florida. The license has been in a delinquent status since July 1, 1981. (Petitioner's Exhibit 1). Between October 1, 1979, and September 30, 1980, respondent held an occupational license issued by the County of Indian River, Florida, which enabled him to engage in the business of roofing contracting in that county. However, this occupational license expired on September 30, 1980. (Petitioner's Composite Exhibit 9). In February, 1981, respondent entered into a verbal agreement with Ezra Grant to repair, for compensation, all leaks in the front and rear sections of the roof on Grant's home, which was located in Sebastian, Florida. (Testimony of Grant). When respondent and Grant entered into this verbal agreement, respondent gave Grant one of his calling cards. On the face of the calling card, in the lower right corner, was written "licensed and insured." (Petitioner's Exhibit 4; Testimony of Grant). At all time material hereto, respondent was not licensed to engage in the business of roofing contracting in the City of Sebastian, Florida. (Petitioner's Exhibit 5). Pursuant to the agreement, respondent performed roof repairs on Grant's home. (Testimony of Grant). Respondent failed to obtain a permit to perform such roof repairs in violation of Section 105.1, Standard Building Code, as adopted by the City of Sebastian, Florida in Section 7-16, Article II, Sebastian Code of Ordinances. (Petitioner's Exhibits 6 and 8a and b). On February 19, 1981, respondent submitted a bill in the amount of $800.00 to Grant for the roof repairs. The bill described the work performed and stated that the "work is guaranteed for 1 year." (Petitioner's Exhibit 2; Testimony of Grant). On February 20, 1981, Grant paid respondent, in full, for the described roof repairs. (Petitioner's Exhibit 3). Approximately two weeks after respondent performed the roof repairs, the roof over the rear portion of Grant's home began to leak, again, in the area where it was repaired. (Testimony of Grant). Respondent returned to Grant's home, on two occasions1 after the discovery of continuing leakage in the roof over the rear portion of Grant's home. However, respondent did not perform roof repairs on either occasion. On the first occasion, he merely removed equipment which he had left at Grant's home. (Testimony of Grant). After Grant complained to petitioner Department of Professional Regulation, respondent returned a second time. He inspected the rear portion of Grant's roof, removed two layers of slate from the roof, and tested it by pouring water over it. Although this test revealed that Grant's roof still leaked, Grant made no effort to repair the leakage. (Testimony of Grant). Arthur Mayer, then the Building Official for the City of Sebastian, observed respondent removing the slate from the roof. He instructed respondent that, upon finishing the work, he should go to the Sebastian City Hall and apply for a roofer's license and a permit for the roof repairs already performed on Grant's home. Respondent promised to comply. (Testimony of Mayer). But, despite his promise, he failed to apply for and obtain a license to engage in the business of roofing contracting in the City of Sebastian, Florida. He also failed to apply for and obtain a roof permit, and pay the proper late fees, as required by Section 107.2, Standard Building Code, as adopted by the City of Sebastian, Florida, in Section 7-16, Article II, Sebastian Code of Ordinances. (Testimony of Mayer; Petitioner's Exhibits 6, 8a and c). Grant, eventually, had his roof repaired by another contractor at a cost of $150.00. (Testimony of Grant).

Recommendation Based on the foregoing, it is RECOMMENDED: That respondent's registered roofing contractor's license be revoked. DONE AND ORDERED this 28th day of February, 1983, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of February, 1983. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Jerry E. Smith Route 1, Box 111B Fellsmere, Florida 32948 James Linnan, Executive Director Construction Industry Licensing Board P. O. Box 2 Jacksonville, Florida 32202

Florida Laws (4) 120.57455.227489.117489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THOMAS G. WALKER, D/B/A INSULSHIELD ROOFING, 78-002448 (1978)
Division of Administrative Hearings, Florida Number: 78-002448 Latest Update: May 15, 1979

Findings Of Fact Based on my observation of the witnesses and their demeanor while testifying, the documentary evidence and the positions of the parties, I hereby make the following: Thomas G. Walker (herein sometimes called "Licensee" or "Respondent") is a registered residential contractor and is issued license number RR 0009839. Thomas G. Walker was initially licensed by the Board in July of 1969 as an individual and during January, 1975, he changed his registration status as an individual to qualify Insulshield Roofing as the business entity through which he would conduct his business (Petitioner's Exhibit No. 1). An examination of the official records pertaining to the Licensee reveals that he does not now nor has he ever held a roofing license in the State of Florida. On February 16, 1979, the Licensee was apprehended contracting roofing without a State roofing contractor's license by the Board's representative and was issued a Notice of Violation (Petitioner's Exhibit No. 3). On July 26, 1977, the Licensee entered into an agreement with Jan Soderstrom, 501 Orlando Avenue, Indialantic, Florida, to remove the tile from the Florida Room of her residence and hot mop the herein-described roofing area, to replace tile as needed, to clean and coat the entire roof, and to install a cap over Ms. Soderstrom's chimney. He guaranteed the work for a period of five (5) years and charged a contracted price of $800.00. The Licensee was paid the contracted price of $800.00 by check dated August 4, 1977 (Petitioner's Exhibit No. 5). During early February, 1978, Ms. Soderstrom detected a leak in her roof and summoned the Licensee back to her residence to repair same. During February, 1978, Respondent returned to Ms. Soderstrom's residence to repair the leak in her roof. Upon his return, he removed several roof tiles and since February, 1978, to the present, he has not returned to this project. Clyde Pirtle, a field investigator for the Board, investigated the Licensee based on complaints that he received from Ms. Soderstrom and from a Mr. Capitz. On or about February 16, 1977, Mr. Pirtle discussed a Notice of Violation with the Licensee and explained to him the necessity to register as a Roofing Contractor, if he was in the business of acting as a Roofing Contractor. Mr. Charles D. Franklin, a building official of Indian Harbor Beach, Florida, is the custodian of the records in Indian Harbor, Florida. Based on an examination of the records by Mr. Franklin, the Respondent/Licensee is not registered as a Roofing Contractor locally.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby, RECOMMENDED: That the registered residential contractor's license, number 0009839, of the Licensee, Thomas G. Walker, d/b/a Insulshield Roofing, be suspended for a period of one (1) year. RECOMMENDED this 4th day of April, 1979, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 Thomas G. Walker d/b/a Insulshield Roofing 170 5th Street South Melbourne Beach, Florida 32951 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer