Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
JOE PAIR vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-002948 (1983)
Division of Administrative Hearings, Florida Number: 83-002948 Latest Update: Jun. 29, 1984

The Issue This case arises out of the denial by the Department of Environmental Regulation of an application by the Petitioner to construct a 24-slip marina on Bayou Chico in Pensacola, Florida. At the formal hearing, Petitioner testified on his on behalf and offered and had admitted into evidence one exhibit. The Respondent called as its only witness, Jeremy Craft, and offered and had admitted into evidence four exhibits. Counsel for the Respondent submitted proposed findings of fact and conclusions of law for consideration by the Hearing Officer. To the extent that those proposed findings and conclusions are inconsistent with this order, they were rejected as not being supported by the evidence or as unnecessary to a resolution of this cause.

Findings Of Fact On March 18, 1982, Petitioner applied for a permit to dredge approximately 78,480 cubic yards from Bayou Chico and an unnamed embayment adjacent to the Bayou. The proposed project site is located in Pensacola, Florida, Bayou Chico in Section 59, Township 2 South, Range 30 West. Specifically, the project site is located on the south side of Bayou Chico just north of the Barrancas Avenue Bridge. On April 15, 1982, the Respondent, Department of Environmental Regulation, sent a completeness summary to the Petitioner requesting additional information before the application or permit could be processed. Over a period of approximately a year and a half, Department of Environmental Regulation conferred with Petitioner concerning the proposed project and a number of different plans were discussed. In July of 1983, Petitioner submitted the July 11, 1983 plan, with modifications, and withdrew all prior plans. It is this plan which is the subject of this hearing. A field appraisal of the proposed site was made by Department of Environmental Regulation on December 25, 1982. On August 31, 1983, Department of Environmental Regulation issued an Intent to Deny the Petitioner's permit application. The Intent to Deny encompassed all plans and revisions submitted by the Petitioner, Department of Environmental Regulation based its denial on Petitioner's failure to give reasonable assurances that water quality standards would not be violated by his project. The Department's denial also asserted that the project would also result in matters adverse to the public interest. The final proposal submitted by the Petitioner sought a permit to dredge a strip 100 feet wide by 450 feet long to a depth of 6 feet. This strip is adjacent to a spit or strip of land which separates Chico Bayou from the emboyment. This plan was subsequently modified to include dredging an additional 100 to 150 feet along the full length of the strip. This additional dredging would take the dredged area out to the deep water of Chico Bayou and was intended to eliminate a channeling effect. The purpose of the dredging is to enable the Petitioner to construct a marina or docking facility along the split. The marina would include 24 slips. The proposed dredge area gradually slopes from the shoreline to five and six foot depths 200 to 250 feet from the spit. The water in the embayment is highly polluted and at one time was used as a holding pond for mahogany logs because the wood-boring worms could not survive in the water. Bayou Chico is also very polluted and fails to meet the water quality standards found in Rule 17-3.121, Florida Administrative Code, for the parameters lead, cadmium, copper, and aluminum among others. The bayou has for many years been used for boat and barge traffic. Jeremy Craft testified on behalf of DER and his opinions as to the impact of the project on water quality and marine life were uncontroverted. In Mr. Craft's opinion, the dredging proposed by the Petitioner would result in further degradation of the water quality in Bayou Chico by eliminating important shallow areas and underwater grasses. The deepening of the dredged area would limit the amount of oxygen available to the water in the bayou thereby harming the aquatic life by freeing many of the heavy metals which are presently bound in the sediments in the bayou. The shallow areas are the most important areas in cleansing the water. With increased oxidation, the biota survive better and the water is better cleansed. Freeing the heavy metals would allow their introduction into the food chain and accumulation in living organisms. The Petitioner has not informed DER of his specific dock specifications, stormwater plans, upland development plans, or dredge disposal plans. The type of dock will determine the type of boating traffic and this will indicate the amount and content of stormwater discharge. Because of the contaminated nature of the spoil, the Petitioner must provide reasonable assurances that the spoil and spoil water will be properly retained. Petitioner testified on his own behalf but did not present any evidence relating to the impact the proposed prod act would have on water quality.

Recommendation Based upon the foregoing findings of fact and conclusions of law it is RECOMMENDED That the Department of Environmental Regulation enter a final order denying the Petitioner's application for a permit as set forth in the Intent to Deny previously issued by the Department. DONE AND ORDERED this 24th day of May 1984, in Tallahassee, Florida. MARVIN E. CHAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 FILED with the Clerk of the Division of Administrative Hearings this 24th day of May 1984. COPIES FURNISHED: David K. Thulman, Esquire Assistant General Counsel 2600 Blair Stone Road Tallahassee, Florida 32301 (904)488-9675 Joe Pair 1200 Mahogany Mill Road Pensacola, Florida 32907 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (2) 403.087403.088
# 2
GREENSPACE PRESERVATION ASSOCIATION, INC.; FRANK WARD; SAL LOCASCIO; FREDERICK P. PETERKIN; AND HAROLD M. STAHMER vs ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND CITY OF GAINESVILLE, 97-002845 (1997)
Division of Administrative Hearings, Florida Filed:Gainesville, Florida Jun. 13, 1997 Number: 97-002845 Latest Update: Jul. 12, 2004

The Issue The issue is whether the City's applications for an individual stormwater permit and a noticed general environmental resource permit for Phase 1A of the proposed Hogtown Creek Greenway should be approved.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In these two cases, Respondent, City of Gainesville (City), seeks the issuance of a stormwater system management permit (stormwater permit) to construct a 2,000-foot long asphaltic trail/boardwalk, a parking facility and associated improvements for Phase 1A of the Hogtown Creek Greenway project in the north central portion of the City. That matter is docketed as Case No. 97-2845. The City also seeks the issuance of a noticed general environmental resource permit (NGP) to construct 481 square feet of piling supported structures over wetlands or surface waters for the same project. That matter has been assigned Case No. 97-2846. Respondent, St. Johns River Water Management District (District), is the regulatory agency charged with the responsibility of reviewing and approving the requested permits. Petitioner, Greenspace Preservation Association, Inc., is a not-for-profit Florida corporation primarily composed of persons who own real property adjacent to the route proposed by the City, as well as local environmental interests. Petitioners, Frank Ward, Sal Locascio, Frederick P. Peterkin, and Harold M. Stahmer, are individuals who own real property adjacent to the route proposed by the City for the Greenway. The parties have stipulated that Petitioners are substantially affected by the District's proposed action and thus have standing to initiate these cases. On March 28, 1997, the City filed applications for a stormwater permit and a NPG for Phase IA of the Hogtown Creek Greenway project. After conducting a review of the applications, including an on-site visit to the area, in May 1997, the District proposed to issue the requested permits. On June 9, 1997, Petitioners timely filed a Petition for Initiation of Formal Proceedings as to both intended actions. As amended and then refined by stipulation, Petitioners generally allege that, as to the stormwater permit, the City has failed to provide reasonable assurance that the project meets the permitting requirements of the District; the City has failed to provide reasonable assurance that the stormwater system will not cause violations of state water quality standards; the City has failed to provide reasonable asurance that the project satisfies the District's minimum required design features; and the City has failed to provide reasonable assurance that the stormwater system is capable of being effectively operated and maintained by the City. As to the NPG, Petitioners generally allege that the piling supported structure is not less than 1,000 square feet; the jurisdictional wetlands are greater than the area shown on the plans submitted by the City; the City has failed to provide reasonable assurance that the system will not significantly impede navigation; the City has failed to provide reasonable assurance that the system does not violate state water quality standards; the City has failed to provide reasonable assurance that the system does not impede the conveyance of a watercourse in a manner that would affect off-site flooding; the City has failed to provide reasonable assurance that the system will not cause drainage of wetlands; and the City failed to provide reasonable assurance that the system does not adversely impact aquatic or wetland dependent listed species. Respondents deny each of the allegations and aver that all requirements for issuance of the permits have been met. In addition, the City has requested attorney's fees and costs under Section 120.595(1)(b), Florida Statutes (Supp. 1996), on the theory that these actions were filed for an improper purpose. A General Description of the Project The Hogtown Creek Greenway is a long-term project that will eventually run from Northwest 39th Street southward some seven miles to the Kanapaha Lake/Haile Sink in southwest Gainesville. These cases involve only Phase 1A of that project, which extends approximately one-half mile. This phase consists of the construction of a 2,000-foot long asphaltic concrete trail/boardwalk, a timber bridge and boardwalk, a parking facility, and associated improvements. The trail will extend from the Loblolly Environmental Facility located at Northwest 34th Street and Northwest 5th Avenue, to the intersection of Northwest 8th Avenue and Northwest 31st Drive. The trail will have a typical width of ten feet. For the majority of its length, the trail will be constructed of asphaltic concrete overlying a limerock base, and it will generally lie at the existing grade and slope away from the creek. Besides the trail, additional work involves the repaving of Northwest 5th Avenue with the addition of a curb and gutter, the construction of an entrance driveway, paved and grassed parking areas, and sidewalks at the Loblolly Environmental Facility, and the widening and addition of a new turn lane and pedestrian crosswalk at the intersection of Northwest 8th Avenue and Northwest 31st Drive. The Stormwater Permit Generally The entire Phase IA project area lies within the Hogtown Creek 10-year floodplain. It also lies within the Hogtown Creek Hydrologic Basin, which basin includes approximately 21 square miles. The project area for the proposed stormwater permit is 4.42 acres. Water quality criteria Phase IA of the Greenway will not result in discharges into surface groundwater that cause or contribute to violations of state water quality standards. When a project meets the applicable design criteria under the District's stormwater rule, there is a presumption that the project will not cause a violation of state water quality standards. There are two dry retention basins associated with the project. Basin 1 is located at the cul-de-sac of Northwest 5th Avenue and will capture and retain the stormwater runoff from the new and reconstructed impervious areas at the Loblolly Facility. Basin 2 is located at the parking area and will capture and retain stormwater runoff at the existing building and proposed grass parking area. Under the stormwater rule, the presumptive criteria for retention basins require that the run-off percolate out of the basin bottom within 72 hours. The calculations performed by the City's engineer show that the two retention basins will recover within that timeframe. In making these calculations, the engineer used the appropriate percolation rate of ten inches per hour. Even using the worst case scenario with a safety factor of twenty and a percolation rate of one-half inch per hour, the two retention basins will still recover within 72 hours. The presumptive criteria for retention basins require that the basin store a volume equal to one inch of run-off over the drainage area or 1.25 inches of run-off over the impervious area plus one-half inch of run-off over the drainage area. The calculations performed by the City's engineer show that the two retention basins meet the District's volume requirements for retention systems. An applicant is not required to utilize the presumptive design criteria, but instead may use an alternative design if the applicant can show, based on calculations, tests, or other information, that the alternative design will not cause a violation of state water quality standards. As a general rule, the District applies its stormwater rule so that water quality treatment is not required for projects or portions of projects that do not increase pollutant loadings. This includes linear bicycle/pedestrian trails. The City's proposed trail will not be a source of pollutants. The City will install signs at both entrances to the trail to keep out motorized vehicles. Except for emergency and maintenance vehicles, motorized vehicles will not be permitted on the trail. The infrequent use by emergency or maintenance vehicles will not be sufficient to create water quality concerns. The construction of a treatment system to treat the stormwater from the trail would provide little benefit and would only serve to unnecessarily impact natural areas. Although treatment of the stormwater run-off from the trail portion of the project is not required under District rules, the run-off will receive treatment in the vegetated upland buffer adjacent to the trail. The District's proposed other condition number 3 will require the City to plant vegetation in unvegetated and disturbed areas in the buffer. This will reduce the likelihood of erosion or sedimentation problems in the area of the trail. Although disputed at hearing, it is found that the City's engineer used the appropriate Manning coefficient in the calculations regarding the buffer. Even without a vegetated buffer, run-off coming from the bicycle trail will not violate state water quality standards. The City will install appropriate erosion and sediment controls. These include siltation barriers along the entire length of both sides of the proposed trail prior to commencing construction. Such barriers will not allow silt or other material to flow through, over, or under them. The City will also place hay bales and any other silt fencing necessary to solve any erosion problem that may occur during construction. In addition, the permit will require an inspection and any necessary repairs to the siltation barriers at the end of each day of construction. Saturation of the limerock bed under the paved portion of the trail is not expected to cause a problem because heavy vehicles will not regularly use the trail. The trail portion of the project can be adequately maintained to avoid deterioration. Sensitive Karst Areas Basin criteria The two proposed dry retention basins for Phase 1A are located within the District's Sensitive Karst Areas Basin. They include all of the minimum design features required by the District to assure adequate treatment of the stormwater before it enters the Floridan aquifer and to preclude the formation of solution pipe sinkholes in the stormwater system. There will be a minimum of three feet of unconsolidated soil material between the surface of the limestone bedrock and the bottom and sides of the two retention basins. The appropriate mechanism for determining the depth of limestone is to do soil borings. The soil borings performed by the City show that there is at least three feet of unconsolidated material between the bottom of the basins and any limerock where the borings were taken. In other words, limestone would not be expected to be within three feet of the bottom of either basin. Based on the soil boring results, the seasonal high water table is at least six feet below ground level. The depth of the two retention basins will be less than ten feet. Indeed, the depth of the basins will be as shallow as possible and will have a horizontal bottom with no deep spots. To make the retention basins any larger would require clearing more land. A large shallow basin with a horizontal bottom results in a lower hydraulic head and therefore is less potential for a sinkhole to form. Before entering the basins, stormwater will sheet flow across pavement and into a grass swale, thereby providing some dispersion of the volume. Finally, the two retention basin side slopes will be vegetated. Special condition number 7 provides that if limestone is encountered during excavation of a basin, the City must over- excavate the basin and backfill with three feet of unconsolidated material below the bottom of the basin. Drainage and flood protection Contrary to Petitioners' assertions, the project will not adversely affect drainage or flood protection on surrounding properties. The trail will be constructed generally at existing grade. Because the trail will be constructed at existing grade, the net volume of fill necessary for Phase 1A is approximately zero. Therefore, there will not be a measurable increase in the amount of runoff leaving the site after construction, and the trail will not result in an increase in off-site discharges. District rules require that the proposed post- development peak rate of discharge from a site not exceed the pre-development peak rate of discharge for the mean annual storm only for projects that exceed fifty percent impervious surface. The proposed project has less than fifty percent impervious surface. Even though it is not required, the City has demonstrated that the post-development rate of discharge will not exceed the pre-development peak rate of discharge. Both basins will retain the entire mean annual storm so that the post-development rate of discharge is zero. Even during a 100-year storm event, the retention basins willl not discharge. Therefore, there will not be any increase in floodplain elevations during the 10, 25, or 100-year storm events from the proposed project. Operation and maintenance entity requirements The applicable requirements of Chapter 40C-42, Florida Administrative Code, regarding operation and maintenance, have been met by the applicant. The City proposes itself as the permanent operation and maintenance entity for the project. This is permissible under District regulations. The duration for the operation and maintenance phase of the permit is perpetual. The City has adequate resources and staff to maintain the phase 1A portion of the project. The public works department will maintain the stormwater management system out of the City's utility fund. The City provides periodic inspections of all of its stormwater systems. These inspections are paid for out of the collected stormwater fees. The City will also conduct periodic inspections of the project area, and the two retention basins will be easily accessed by maintenance vehicles. The City will be required to submit an as-built certification, signed and sealed by a professional engineer, once the project is constructed. Monthly inspections of the system must be conducted looking for any sinkholes or solution cavities that may be forming in the basins. If any are observed, the City is required to notify the District and repair the cavity or sinkhole. Once the system is constructed, the City will be required to submit an inspection report biannually notifying the District that the system is operating and functioning in accordance with the permitted design. If the system is not functioning properly, the applicant must remediate the system. The City will be required to maintain the two retention basins by mowing the side slopes, repairing any erosion on the side slopes, and removing sediment that accumulates in the basins. Mowing will be done at least six times per year. The City will stabilize the slopes and bottom areas of the basins to prevent erosion. The City has a regular maintenance schedule for stormwater facilities. The project will be included within the City's regular maintenance program. The City has budgeted approximately $80,000.00 for maintenance of the trail and vegetated buffer. Also, it has added new positions in its budget that will be used to maintain and manage the Greenway system. Finally, City staff will conduct daily inspections of the Phase 1A trail looking for problems with the vegetated buffer, erosion problems along the trail, and sediment and debris in the retention basin. If the inspections reveal any problems, the staff will take immediate action to correct them. The Noticed General Environmental Resource Permit Generally By this application, the City seeks to construct 481 square feet of piling supported structures over wetlands or surface waters. The proposed structures include a 265 square foot timber bridge over an un-vegetated flow channel, which connects a borrow area to Possum Creek, and a 216 square foot boardwalk over two small wetland areas located south of the flow channel. None of the pilings for the bridge or boardwalk will be in wetlands, and no construction will take place in Hogtown or Possum Creeks. The paved portion of the trail will not go through wetlands, and there will be no dredging or filling in wetlands. The receiving waters for the project are Hogtown and Possum Creeks. Both are Class III waters. Hogtown Creek originates in north central Gainesville and flows southwest to Kanapaha Lake/Haile Sink in southwest Gainesville. Possum Creek originates in northwest Gainesville and flows southeast to its confluence with Hogtown Creek south of the proposed bridge structure. Wetlands The total area of the proposed bridge and boardwalk over surface water or wetlands is approximately 481 square feet. The wetland delineation shown on the City's Exhibit 5A includes all of the areas in the project area considered to be wetlands under the state wetland delineation methodology. The United State Army Corps of Engineers' wetland line includes more wetlands than the District wetland line. The former wetland line was used to determine the area of boardwalk and bridge over wetlands. Even using this line, however, the total area of boardwalk over surface waters or wetlands is approximately 481 square feet and is therefore less than 1,000 square feet. Navigation The proposed system does not significantly impede navigation. Further, the structures will span a wetland area and an un-vegetated flow channel, both of which are non-navigable. In fact, the flow channel generally exhibits little or no flow except after periods of rainfall. Water quality The construction material that will be used for the bridge and boardwalk will not generate any pollutants. Morever, chemical cleaners will not be used on those structures. Silt fences will be used and vegetation will be planted in the vicinity of the bridge and boardwalk to prevent erosion and sedimentation problems. The amount of erosion from drip that comes off the boardwalk will be minimal. Therefore, the bridge and boardwalk will not cause a violation of state water quality standards. Off-site flooding The project will not impede conveyance of any stream, river, or other water course which would increase off-site flooding. The structures will completely span the wetland areas and flow channel, and no part of the structures, including the pilings, will lie within any water or wetland areas including the flow channel. There will be a span of 2.5 to 3 feet from the horizontal members of the bridge and boardwalk down to the ground surface which will allow water to pass through unobstructed. Further, there will not be any cross ties or horizontal obstructions on the lower portions of the boardwalk or bridge pilings. Further, due to the spacing of the pilings, the boardwalk and bridge will not trap sufficient sediment such as leaves to impede the conveyance of the flow channel. Therefore, conveyance through the flow channel will not be affected by the structures. Because the boardwalk and bridge are not over Hogtown or Possum Creeks, they will not cause any obstruction to the conveyance of the creeks. Aquatic and wetland dependent listed species The project will not adversely affect any aquatic or wetland dependent listed species. These species are defined by District rule as aquatic or wetland dependent species listed in Chapter 39-27, Florida Administrative Code, or 50 Code of Federal Regulations, Part 17. No such species are known to exist in the project area, and none are expected to exist in the location and habitat type of the project area. Therefore, contrary to Petitioners' assertions, there are no listed salamander, frog, turtle, or lizard species known to occur within the Hogtown Creek basin. Although it is possible that the box turtle may be found in the project area, it is not an aquatic or wetland dependent listed species. One baby American alligator (between two and three feet in length) was observed in the borrow pit area of the project on September 11, 1997. Except for this sighting, no other listed animal species have been observed in the project area. As to the alligator, the only area in which it could nest would be in the existing excavated borrow pit, and none of the proposed construction will take place in that area. More than likely, the alligator had walked into the area from Clear Lake, Kanapaha Prairie, or Lake Alice. The proposed structures will not affect the movement of the alligator nor its feeding habits. Drainage of wetlands Because the boardwalk and bridge are elevated structures over waters and wetlands, and the City has not proposed to construct ditches or other drainage systems, the proposed system will not cause drainage of the wetlands. Coral/macro-marine algae/grassbeds The proposed system is not located in, on, or over coral communities, macro/marine algae, or a submerged grassbed community. D. Were the Petitions Filed for an Improper Purpose? Prior to the filing of their petitions, Petitioners did not consult with experts, and they prepared no scientific investigations. Their experts were not retained until just prior to hearing. Petitioners are citizens who have genuine concerns with the project. They are mainly longtime residents of the area who fear that the Greenway will not be properly maintained by the City; it will increase flooding in the area; it will cause water quality violations; and it will attract thousands of persons who will have unimpeded access to the back yards of nearby residents. Although these concerns were either not substantiated at hearing or are irrelevant to District permitting criteria, they were nonetheless filed in good faith and not for an improper purpose.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order approving the applications of the City of Gainesville and issuing the requested permits. DONE AND ENTERED this 19th day of December, 1997, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 19th day of December, 1997. COPIES FURNISHED: Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, Florida 32178-1429 Samuel A. Mutch, Esquire 2790 Northwest 43rd Street Suite 100, Meridien Centre Gainesville, Florida 32606 Jennifer B. Springfield, Esquire Mary Jane Angelo, Esquire Post Office Box 1429 Palatka, Florida 32178-1429 Richard R. Whiddon, Jr., Esquire Post Office Box 1110 Gainesville, Florida 32602-1110

Florida Laws (3) 120.57120.59517.12 Florida Administrative Code (6) 40C-4.02140C-400.47540C-41.06340C-42.02340C-42.02740C-42.029
# 4
EUGENE R. SMITH (BCR DEVELOPMENT) vs CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 93-005692 (1993)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Oct. 04, 1993 Number: 93-005692 Latest Update: Dec. 20, 1993

Findings Of Fact The Petitioner has an option to purchase property located at 301-307 Island Way Boulevard, Island Estate, Clearwater, Florida, on which he proposes to construct ten townhouses. Initially Petitioner asked for two variances. The first variance was for 25.12 feet to allow construction on a lot only 124.88 feet wide. This variance was granted for this nonconforming lot. The second variance, for 13.24 feet to allow construction of the ten townhouse complex 12 feet from the side property line, was denied by the Clearwater Code Adjustment Board. The Board concluded the variance requested did not meet the requirements of Section 45.24 of the Clearwater Land Development Code. Petitioner presented evidence that if the lot had been 150 feet wide they would have had 90 feet to build on without requesting any variance. However, since the lot was nonconforming, in order to have 89 feet on which to place the building, the requested variance would be necessary. Petitioner also presented evidence that the construction of ten townhouses on this lot is necessary for the project to be on a solid economic basis. Subsequent to the denial of this variance by the Development Code Adjustment Board, Petitioner submitted plans, which have been approved by the City of Clearwater, to erect nine townhouses on this property without any variance needed. However, these townhouses would be smaller than would be the ten townhouses initially proposed and would provide a lesser return on the capital invested.

Florida Laws (1) 120.68
# 5
VALENTINOS KOUMOULIDIS vs CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 95-001359 (1995)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Mar. 20, 1995 Number: 95-001359 Latest Update: Jun. 23, 1995

The Issue The issue in this case is whether to grant the appeal of Valentinos Koumoulidis from the Planning and Zoning Board's denial of his application for variances from the requirement of a minimum lot width of 150 feet at the setback line and from the requirement of a minimum of 20 percent clear space.

Findings Of Fact When the Appellant, Valentinos Koumoulidis, bought the subject property, the building was being used as a six-unit motel--three units on each of two floors. There were approximately 1600 square feet of space on each of the two floors. The property fronts at 606 Bayway Boulevard; the back of the property is waterfront. In 1991, the Appellant applied for and was granted a parking variance and variances to enable him to convert the first floor to retail use and convert the second floor to a residence. Apparently construction was delayed, and in October, 1992, the Appellant reapplied for the variances to enable him to convert the first floor to retail use and convert the second floor to a residence, while withdrawing the application for a parking variance. (He had decided to convert from straight- in/back-out parking to an off-street parking lot.) In 1994, the Appellant again applied for variances, this time to allow him to add approximately 300 square feet of commercial space to the back of the first floor and approximately 900 square feet of residential space to the back of the second floor. The Board denied those variance requests in October, 1994. Rather than appeal, the Appellant decide not to pursue the addition of commercial space to the back of the first floor and, on December 22, 1994, instead applied for variances to allow him just to add approximately 900 square feet of residential space to the back of the second floor. (Of the 900 square feet, approximately 550 would be enclosed, and approximately 350 would be open deck.) The evidence (primarily through the testimony of Noel Woods, one of the Appellant's neighbors) was that the residential property in the immediate vicinity is comparable, in terms of square footage of living space per dwelling unit, to the Appellant's current second floor--i.e., approximately 1600 to 1700 square feet. There was some evidence that residential properties across the intracoastal waterway from the Appellant's property are valued as high as a million dollars. But the evidence (again, the testimony of Noel Woods) also was that condominium units in the immediate vicinity are valued at approximately $175,000. There was no evidence that the use the Appellant is making of his property (retail on the first floor and residential on the second floor) is not a reasonable use.

Florida Laws (1) 120.68
# 6
DEPARTMENT OF ENVIRONMENTAL REGULATION vs. JACK E. MOORE, 83-001487 (1983)
Division of Administrative Hearings, Florida Number: 83-001487 Latest Update: Nov. 01, 1991

Findings Of Fact Jack E. Moore is the owner of real property in Fort Myers Beach known as Lot 9 of Indian Bayou, a subdivision in Section 33, Township 46 South, Range 24 East, Lee County, Florida. Moore's property is bordered on the north by the waters of Indian Bayou and Estero Bay. The northern portions of Moore's property are vegetated by juvenile and mature red and black mangroves. Red and black mangrove are the dominant species of vegetation on the northernmost portions of the property, waterward of the fill pad on which Moore's house is built. Sometimes during July, 1982, Moore used a shovel to excavate a channel from the open waters of Estero Bay to a dock existing at the edge of the fill pad. Approximately 48 cubic yards of excavated material was piled up along the banks of the channel. The channel measured approximately 1.5 feet deep (at low tide) by 9 feet wide by 70 feet long. The channel was dug so that Moore could got his boat in and out from the dock at medium tide. The passage to the deck was already possible at high tide, as Moore had a shallow draft pontoon boat. In July, 1981, Moore constructed a rip-rap revetment with backfill the northern side of his house fill pad. The back fill area contains approximately 160 cubic yards of fill, and is approximately 10 feet wide by 110 feet long. Red mangrove and black mangrove are and were the dominant vegetational species in the area where the channel was dug, where the excavated material was placed, and where the revetment and fill was constructed. The area of dominant mangrove vegetation extends from the work areas to the open waters of Estero Bay. Moore did not apply for or receive a permit from DER prior to undertaking the work referenced above. Upon discovery of the work in September, 1982, DER notified Moore that a permit was needed for the excavation and filling he conducted. In October, 1982, Moore agreed to fill in the channel and remove all unauthorized fill by January 19, 1983. Inspection by DER on January 26, 1983, showed that restoration had not been started, and in fact more work had been done on the channel. DER issued a Notice of Violation and Orders for Corrective Action (NOV) to Respondent on March 29, 1003, alleging violations of Chapter 403, Florida Statute's, and DER rules and requiring restoration of the areas dredged and filled. Upon service of the Notice of Violation by the Sheriff, Respondent petitioned for this hearing. DER incurred costs of 5101.88 in investigating the violations alleged in the NOV. As of the date of the hearing, restoration work still had not been performed. Although the spoil piles alongside the channel are now diminished, the channel itself was deep as it previously had been and the rip-rap revetment and backfill had not been removed.

Florida Laws (5) 120.57403.031403.087403.141403.161
# 7
FREDERICK B. SPIEGEL vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000233 (1978)
Division of Administrative Hearings, Florida Number: 78-000233 Latest Update: Apr. 06, 1979

Findings Of Fact Collier Development Corporation, Naples, Florida, owns a triangular tract of land consisting of approximately 16 acres in Naples, Florida. In 1958, the Trustees of the Internal Improvement Fund conveyed by quitclaim deed to Collier Development Corporation all its interests in the property. A 1958 affidavit of Collier's surveyor who prepared the legal description of the land was filed in the Collier County public records and states that the land conveyed by the quitclaim deed was "high land" erroneously shown as bay bottom land according to the original government survey, and that the deed was executed in exchange for the conveyance of certain parcels of bay bottom land in Naples Bay to the Trustees. (Exhibits 1-2) In 1976, Petitioner executed an option agreement with Collier Development Corporation to purchase the land in question, contingent upon certain conditions including a requirement to obtain any required fill permits. On December 27, 1976, Petitioner assigned the option agreement to Michael S. Spiegel and himself as joint tenants. On March 14, 1977, a "short form" application was filed by Petitioner, as authorized by Collier Development Corporation, with Respondent to fill the land above the mean high water line to building grade for future residential, multi-family, or commercial uses. The application reflected that 400 cubic yards of rock riprap would be placed at least five feet upland of the designated mean high water line along the boundary of the property that faced the Gordon River and Rock Creek. The riprap revetment is designed to provide a method of containing upland fill material. The application contemplates that a fabric-like material "Mirafi" will be placed on the ground and wrapped over the riprap barrier. The application further provides that approximately 90,000 pounds of fill material will be trucked into the site and placed behind the riprap material to fill the land to a minimum elevation of four feet. It is also proposed to slope the fill material behind the riprap and plant grass seed thereon. In October, 1977, Petitioner filed a "long form" application which merely amplified the original application. The mean high water line was established by a survey performed under standard procedures and which utilized the existing bulkhead line as a point of reference. The survey was conducted in 1977 and 1978, and the procedures used were approved by and the survey filed in the Department of Natural Resources on June 26, 1978. (Testimony of Park, Lawson, Exhibits 4, 6, 8, 11) By letter dated January 26, 1978, Respondent provided notice of its intent to deny the permit application pursuant to Chapters 253 and 403, Florida Statutes, and Public Law 92-500. The reasons stated for the proposed denial generally were that filling the land would destroy mangrove vegetation which provides a major input of organic material to estuarine tropic webs, and filters and assimilates pollutants from upland runoff. It was stated that the proposed project would eliminate approximately 15 acres of submerged lands and transition zones, as defined in Chapter 17-4, Florida Administrative Code, which would reduce the quality and quantity of the state's marine resources adjacent to Class II waters and "tend to cause degradation of water quality conditions." Thereafter, on January 25, 1978, Petitioner submitted a petition for hearing wherein the jurisdiction of the Respondent in the matter and its grounds for the proposed denial were challenged. (Exhibit 5) The land in question is located south and adjacent to the confluence of the Gordon River and Rock Creek along the north side of U.S. Highway 41. The Gordon River and Rock Creek are tributaries of Naples Bay and all are Class II waters. The area is vegetated by red mangroves with a lesser number of white and black mangroves. A pond of about one-half acre surrounded by red mangroves is located in the southern section of the tract which occasionally overflows into a ditch running parallel to U.S. 41 located within the highway right-of- way. There is a berm alongside the ditch designed to prevent highway runoff from flowing onto Petitioner's land. During high tides, most of the land is inundated to varied depths ranging from two to eight inches. Certain marine vegetational species are present on portions of the land, such as sea grape, sea purslane, sea daisy, and button wood. Certain marine animal life is present in the mangrove area, including coffee bean snails, ribbed mussels, marsh clams, mangrove crabs, fiddler crabs, and mosquito fish. Other marine species, such as common oysters, scorched mussels, and barnacles inhabit the Rock Creek shore line. There is sparse bird population on Petitioner's land that may in part be due to the proximity of Naples Airport. (Testimony of Lawson, Park, Carroll, Fields, M. Spiegel, Exhibits 3, 7, 10) The quality of water in the Gordon River and Rock Creek is adversely effected to some degree by receipt of sewage plant effluent, discharge from nearby canals and runoff from residential and commercial areas. As a result of high bacterial count in these waters, shell fishing and swimming is not permitted. The mangrove forest on Petitioner's property is in a stressed condition as evidenced by the thinness of the canopy. It is probable that this condition was caused primarily by the introduction of fresh water from canals into the surrounding waters. (Testimony of Carroll, Fields, Erwin, Yokel) Mangrove wetlands are an important component of the estuarine ecosystem which provide nutrient stabilization and transformation in the supply of an organic base to the estuarine food chain, filtration of upland runoff, and storage of storm waters. They are a nursery for fish and invertebrate species, and a fish and wildlife habitat. The mangrove system on Petitioner's property is productive and contributing to the needs of marine life in the Naples Bay area. In this respect, most of the detritus produced by the mangrove system occurs below the mean high water line. However, the tidal flow during storm conditions at certain times of the year can release accumulated organic matter from the higher areas. This generally occurs in late summer and early fall when feeding demands of organisms are high. (Testimony of Erwin, Yokel) Although no system for containing surface water runoff was set forth in Petitioner's permit application, it is planned that such runoff will be retained on the site by a site drainage plan that would be accomplished by grading and the use of the existing pond or other means of retention, in addition to the natural percolation into the sandy fill material. (Testimony of Park) The application did not specify the precise distance from the mean high water line at which fill would be placed, but Petitioner clarified this point at the hearing. Fill material will not be placed closer than 100 feet upland of the mean high water line. The mangrove area left intact below that point will enable the ecological system to survive. However, due to the fact that the Naples Bay area does not produce sufficient organic matter to fully support animal life in the area, the loss of a substantial portion of mangroves will impact on the detrital food chain to some extent. (Testimony of Carroll, Yokel)

Recommendation That Respondent issue the requested permit to Petitioner, subject to the modification thereto made at the hearing with regard to the 100' setback as set forth in paragraph 8 of the foregoing Findings of Fact. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1979. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1979. COPIES FURNISHED: H. Ray Allen, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Howard Horowitz, Esquire 3550 Biscayne Boulevard Suite 402 Miami, Florida 33137 William Blackwell, Esquire 3003 North Miami Trail Naples, Florida

# 8
LOIS SIMPSON vs. JOHN H. VOORHEES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 86-000599 (1986)
Division of Administrative Hearings, Florida Number: 86-000599 Latest Update: Feb. 17, 1987

Findings Of Fact The Department of Environmental Regulation (hereinafter "DER") issued a letter of "intent to issue" a permit based upon an application submitted by Respondent John H. Voorhees for a weedgate and associated fences to be placed at the mouth of the Hollerich Subdivision canal in Big Pine Key, Monroe County, Florida. The majority of owners of lots in the Hollerich Subdivision are in favor of the gate. The Hollerich Subdivision canal is approximately 1,200 feet long. it is an east-west dead-end canal with its mouth facing east. Floating seaweeds, grasses and detritus (a/k/a wrack are blown into the canal by the prevailing east and southeast winds. Although some surface wrack may blow back out of the canal with the occasional west wind, the sunken weeds will not. The accumulation of windblown wrack results in a stench caused by hydrogen sulfide gas from rotting weeds. The odor causes nausea, sore throats, and sneezing. Water quality tests of dissolved oxygen (DO) taken both in April 1985 and in November 1986 show the water in the canal to be below state standards. The low DO levels found in the canal are primarily due to the rotting weeds although the nutrients leaching from the surrounding yards also contribute to those low levels. The area outside the canal is better able to diffuse and absorb the wrack problem than the area inside the carnal. Accumulations of wrack outside the canal are more temporary and therefore produce less navigational difficulty and less deterioration of water quality. The navigational problems caused by weeds choking the canal range from difficulty in steering to poor visibility. The decaying wrack also causes growth on boat bottoms, can damage boat cooling systems, and turns the water in the canal red. The amount of wrack entering the canal and accumulating there has been increasing over the last five years. The proposed structure will stop wrack from entering the canal and will function as a weedgate. The design of the gate will not cause any navigational hazards, although the weedgate should have navigational aids to assure safety. Although the weedgate will not improve water quality in the canal so as to meet state standards, it will result in an improvement. DER has no jurisdiction to resolve property disputes. The proposed weedgate is to be placed in front of the canal with no on-land attachments, and Respondent Voorhees has given reasonable assurances that the proposed gate is not on privately owned property. The proposed structure will be placed in Class III Outstanding Florida Waters. DER has balanced the positive public interest effects that will accrue to the owners of property along the canal against the' negative public interest effects that may accrue to owners of property at the mouth of the canal. Respondent Voorhees has given reasonable assurances that the project will be clearly in the public interest. Respondent Voorhees has given reasonable assurances that the proposed project will meet all applicable DER rules and standards.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that a Final Order be entered (1), granting Respondent Voorhees' permit application and (2), authorizing the issuance of a permit subject to all permit conditions contained in the Department's letter of Intent to Issue the permit and also including the condition that no trespassing occur on the property at the mouth of the canal attendant to either the construction or the maintenance of the weedgate and associated fences. DONE and RECOMMENDED this 17th day of February, 1987, at Tallahassee, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of February, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 86-0599, 86-0600, 86-0601, 86-0954, and 86-0955 l. Respondent Department of Environmental Regulation's proposed findings of fact numbered 1-5, 9, 10, 12-15, 17-20, the first and last sentences of 21, 23, 28, and 29 have been adopted in this Recommended Order either verbatim or in substance. The remainder of the Department's proposed findings have been rejected as follows: 6-8, 11 and 16, as being unnecessary for determination herein; the remainder of 21 and 22 as being immaterial to the issues herein; and 24-27 as being subordinate. 2. Respondent Voorhees' proposed findings of fact numbered l, 3, 8, and 13 have been adopted in this Recommended Order. The remainder of Voorhees' proposed findings of fact have been rejected as follows: 2 and 16 as being subordinate; 9 and 10 as being unnecessary; and 11, 12, 14 and 15 as not being supported by the evidence in this cause. COPIES FURNISHED: Douglas H. MacLaughlin, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 John H. Voorhees Route 1, Box 612 F Big Pine Key, Florida 33043 H. Ray Allen, Esquire 618 Whitehead Street Key West, Florida 33040 Dale Twachtmann Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 9
THE SOUTHLAND CORPORATION vs. CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 87-003822 (1987)
Division of Administrative Hearings, Florida Number: 87-003822 Latest Update: Nov. 17, 1987

Findings Of Fact On or about July 9, 1987 an application for conditional use approval to allow off-premises sale of beer and wine (2APS) was filed on behalf of Petitioner for property located at 2030 Gulf to Bay Boulevard in Clearwater, Florida. The property is zoned general commercial (CG). A public hearing before the Planning and Zoning Board was held on August 4, 1987. At that hearing, the Petitioner's representative was not allowed to give rebuttal testimony, although the Board's by-laws do allow the applicant to rebut testimony in opposition to the application, and rebuttal is, in fact, usually allowed. The Petitioner's representative did not specifically request an opportunity to rebut the opponent's testimony, but assumed he would be given an opportunity to speak before the Board voted. The Planning and Zoning Board voted 3-2 to deny conditional use approval for this application. A timely appeal was taken by Petitioner on August 18, 1987. With this application, Petitioner seeks approval to sell beer and wine at a 7-11 convenience store. By subsequent application and approval of the Planning and Zoning Board on September 1, 1987 Petitioner has been granted a conditional use for 1APS, package sale of beer only. However, this 1APS application and approval is not at issue in this case. The parties stipulated that the property in question is within five hundred feet of a church and several residences.

Florida Laws (1) 120.65
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer