Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs RALPH N. BATTAGLIA, INTERCONTINENTAL CONSTRUCTION CORPORATION, INC., 07-000052PL (2007)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Jan. 04, 2007 Number: 07-000052PL Latest Update: May 08, 2007

The Issue Whether Respondent committed the violations alleged in the Amended Administrative Complaint issued against him and, if so, what disciplinary action should be taken.

Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made to supplement and clarify the facts to which the parties stipulated at the outset of the final hearing (Parties' Stipulations)2: The contract referenced in the Parties' Stipulations (Building Contract) was signed by Mr. Stasinos (on behalf of ICC) and Mr. Skiera (on behalf of himself and his wife) on June 29, 2000. The home that ICC agreed to build for the Skieras (Skiera Residence) was described in the Building Contract as a "[c]ustom two-story residence with detached garage and riding cor[r]al for a total of 5,370 square feet." It was to be constructed on a tract of land owned by the Skieras in Boynton, Beach, Florida. The Building Contract provided for the following allowances: $20,000.00 for "electrical"; $17,000.00 for "plumbing"; $15,000 for "HVAC"; a "door hardware allowance" of "$50.00 per [interior] door"; $6,000.00 for a "stacked stone veneer" exterior; an "entry door hardware allowance" of "$100.00 per door"; $15,000.00 for "kitchen cabinetry and vanity"; $8,000.00 for "counter tops and vanity tops"; $9,000.00 for "landscaping," including "trees, shrubs, sod, automatic time clock, [and an] operated irrigation system with rain sensor"; and $7,000 for "driveways, walkways, [and] flatwork." There was no written statement in the Building Contract explaining a consumer's rights under the Construction Industries Recovery Fund, as then required by Section 489.1425, Florida Statutes. The Building Contract contained a "[p]ayment [d]raw [s]chedule," which provided as follows: Upon execution of contract: 10%- $36,608.00 Thereafter, progress payments based on schedule of values. This "schedule of values" (referred to in the "[p]ayment [d]raw [s]chedule") contained the following "scheduled values" (excluding change orders): 1. Permits $21,600.00 2. Clearing/Grading/Fill $10,800.00 3. Foot'gs. Undgr Plumb, Soil Treatmt $23,000.00 4. Foundation/Slab poured $32,760.00 5. Exterior Walls/Tie Beam $26,600.00 6. Roof Trusses $26,600.00 7. Roof Sheathing/Felt $19,400.00 8. Interior Framing Complete $14,000.00 9. Windows/Exterior Door Frames Set $14,400.00 10. 2nd Plumbing/Tub Set $7,200.00 11. Wiring Rough-In $14,400.00 12. HVAC Ducts Installed $7,200.00 13. Roof Shingles/Tiles Installed $14,400.00 14. Insulation (wall & ceiling) $4,200.00 15. Exterior Trim/Soffits $11,800.00 16. Drywall Hung $14,400.00 17. Drywall Finish $10,800.00 18. Interior Trim/Interior Doors Installed $13,400.00 19. Interior Paint $8,800.00 20. Siding/Stucco $14,400.00 21. Exterior Paint Complete $8,800.00 22. Exterior Doors & Garage Door Install $6,200.00 23. Cabinets/Countertops Installed $10,000.00 24. Plumbing Finish $3,600.00 25. Electrical Finish $5,600.00 26. HVAC-Compressor/A.H. Installed $10,920.00 27. Driveway/Walks Installed $3,600.00 28. Landscaping/Irrigation $7,200.00 There were six separate change orders. They were dated August 20, 2000 (Change Order No. 001), August 29, 2000 (Change Order No. 002), September 26, 2000 (Change Order No. 003), October 15, 2000 (Change Order No. 004), October 15, 2000 (Change Order No. 005), and November 10, 2000 (Change Order No. 006). As of December 21, 2000, ICC had been paid in full for all six change orders, as well as for items 1 through 8 on the "schedule of values." As of February 27, 2001, ICC had received additional monies from the Skieras: payment in full for items 9 through 12 and 15 on the "schedule of values" and partial (50 percent) payment for items 13 and 20 on the "schedule of values." As of April 10, 2001, ICC had been paid a total of $287,966.20 (all from the proceeds of a mortgage loan the Skieras had obtained from Admiralty Bank) for work done on the Skiera Residence. On May 1, 2001, the Skieras paid ICC an additional $16,800.00 for drywall work, bringing the total amount of payments that ICC had received from (or on behalf of) the Skieras, as of that date, to $304,766.20. The Skieras made no further payments to ICC. The "eight valid claims of lien" referenced in the Parties' Stipulations were filed by eight different subcontractors, all of whom had been hired by ICC to work on the Skiera Residence: Boca Concrete Pumping, Inc.; Gulf Stream Lumber Company; L & W Supply Corp., d/b/a Seacoast Supply; Waste Management of Palm Beach; B.T. Glass & Mirror, Inc.; Boca Raton Decorating Center Company; American Stairs; and Broten Garage Door Sales Inc.3 Boca Concrete Pumping was the "very first" subcontractor to work on the construction of the Skiera Residence. It did the "slab work, the foundation" (referenced in item 4 of "schedule of values"). Its lien was recorded on December 6, 2000. The lien was in the amount of $1,001.25, and it indicated, on its face, that it was for unpaid "concrete pumping" that had been furnished between September 8, 2000, and September 22, 2000. A satisfaction of this lien, dated March 8, 2001, was filed March 24, 2001. Gulf Stream Lumber's original lien was recorded February 15, 2001. It was in the amount of $67,872.59, and it indicated, on its face, that it was for unpaid "building material" that had been furnished between August 15, 2000, and January 24, 2001. An amended claim of lien was recorded May 3, 2001, in the amount of $36,530.59 for unpaid "building material" that, according to the lien, had been furnished between August 25, 2000, and March 27, 2001. A satisfaction of the original lien and amended claim of lien, dated November 30, 2001, was filed December 5, 2001. The liens were satisfied, pursuant to the terms of a Settlement Stipulation, upon the Skieras' payment of $39,579.28 to Gulf Stream Lumber. L & W Supply's lien was recorded April 30, 2001. It was in the amount of $4,536.98, and it indicated, on its face, that it was for unpaid "building materials [and] related items" that had been furnished between December 16, 2000, and January 30, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. The lien was satisfied by the payment of $10.00 "and other good and valuable consideration" (which was the payment of an additional $2,850.00 by check dated October 11, 2001). Waste Management of Palm Beach's lien was recorded May 31, 2001. It was in the amount of $1,665.89, and it indicated, on its face, that it was for unpaid "[w]aste [r]emoval [s]ervices" that had been furnished between August 30, 2000, and April 5, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. B.T. Glass & Mirror's lien was recorded June 29, 2001. It was in the amount of $3,560.00, and it indicated, on its face, that it was for an unpaid "glass/mirror package" that had been furnished between May 3, 2001, and May 31, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. The lien was satisfied by the payment of $1,600.00 (by check dated November 10, 2001), plus an agreement to provide "$2,000.00 in gazebo or arbor products from the Hitching Post," the Skieras' family business. Boca Raton Decorating Center's lien was recorded May 19, 2001. It was in the amount of $1,218.79, and it indicated, on its face, that it was for unpaid "paint, sealers [and] sundries" that had been furnished between May 1, 2001, to May 2, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. American Stairs' lien was recorded August 16, 2001. It was in the amount of $4,188.00, and it indicated, on its face, that it was for unpaid "[s]tairs and [r]ailings" that had been furnished between June 8, 2001, and June 15, 2001. A satisfaction of this lien was executed on October 15, 2001. Broten Garage Door Sales' lien was recorded September 5, 2001. It was in the amount of $3,214.00, and it indicated, on its face, that it was for the unpaid "sale and installation of garage doors and openers," which took place between June 25, 2001, and July 17, 2001. A satisfaction of this lien, dated January 31, 2002, was filed on February 5, 2002. At a meeting "in the early part of August [2001]" attended by Respondent, Mr. Stasinos, the Skieras, and the president of the bank from which the Skieras had borrowed the money to pay for the construction of their residence, Respondent announced that, on behalf of ICC, "he was filing [for] bankruptcy."4 ICC stopped working on the Skiera Residence after this meeting. At the time, the Skiera Residence was approximately 70 to 80 percent completed (and the Skieras had paid ICC a total of $304,766.20, or approximately 80 percent of the total contract price (including change orders) of $378,286.205). In addition to paying $57,316.62 to satisfy the "eight valid claims of lien" referenced in the Parties' Stipulations, the Skieras paid approximately an additional $57,000.00 to other subcontractors who provided goods and/or services "needed to complete the house." The $10,000.00 check referred to in the Parties' Stipulation 14 (that the Skieras received from Andover Construction, Inc.) did not "represent any kind of final settlement" between the Skieras and ICC. The October 4, 2001, Certificate of Occupancy for the Skiera Residence referred to in the Parties' Stipulations indicated, on its face, that ICC was the contractor, notwithstanding that ICC had abandoned the project "in the early part of August [2001]." Respondent has been a Florida-licensed general contractor since July 29, 1987. In his capacity as ICC's licensed qualifier, he has previously (by Final Order filed in DBPR Case Nos. 2001-03283 and 2001-03284 on December 23, 2003) been found guilty of, and disciplined for, violating (in connection with two residential construction projects undertaken by ICC for A. Richard Nernberg) the same subsections of Section 489.129(1), Florida Statutes (Subsections (1)(g), (i), and (m)) that he is accused of violating in the instant case. In these prior disciplinary proceedings, Respondent's license was suspended for two years, and he was fined $6,000.00 and required to pay $958.30 in investigative costs. Administrative complaints were also filed against Respondent in DBPR Case Nos. 94-15958 and 97-17352. Both of these cases were resolved by settlement stipulations in which Respondent "neither admit[ted] [nor] denie[d] the allegations of fact contained in the [a]dministrative [c]omplaint[s]."

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board issue a Final Order: finding Respondent guilty of violating Section 489.1425(1), Florida Statutes, as alleged in Count I of the Amended Administrative Complaint, and fining him $1,000.00 for this violation; (2) finding Respondent guilty of the violation of Section 489.129(1)(g)1., Florida Statutes, relating to Boca Concrete Pumping's December 6, 2000, $1,001.25 lien, alleged in Count II of the Amended Administrative Complaint, and taking the following disciplinary action against him for this violation: suspending his license for four years (with such suspension to run consecutively with his current suspension); (b) fining him $5,000.00; (c) requiring him to pay restitution in the amount of $1,001.25 to the Skieras; and (c) ordering him to reimburse the Department for all reasonable investigative and prosecutorial costs (excluding costs related to attorney time) incurred by the Department; and (3) dismissing all other charges in the Amended Administrative Complaint. DONE AND ENTERED this 8th day of May, 2007, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 2007.

Florida Laws (16) 1.01120.569120.5717.001206.20218.79455.2273458.331489.115489.119489.1195489.129489.140489.1425627.8405810.02
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs THOMAS J. FREESE, 90-001682 (1990)
Division of Administrative Hearings, Florida Filed:Fort Pierce, Florida Mar. 16, 1990 Number: 90-001682 Latest Update: Jul. 27, 1990

The Issue The issue for determination at the formal hearing was whether Respondent allowed an uncertified and unregistered person to engage in prohibited contracting in violation of Subsections 489.129(1)(e), (f), and (m), Florida Statutes. 1/

Findings Of Fact Petitioner is the state agency charged, in conjunction with the Construction Industry Licensing Board, with the responsibility for prosecuting the Administrative Complaint in this proceeding pursuant to chapters 455 and 489, and the rules promulgated thereunder. In September, 1980, license number CG C015802 was issued to Respondent, Thomas J. Freese, as the qualifying agent for Tracy Industries, 728 St. Lucie Crest, Stuart, Florida 33494 ("Tracy"). Respondent was the licensed qualifying agent for Tracy Industries at all times material to this proceeding. At no time material to this proceeding was Robert Sherno licensed by Petitioner as a contractor. On or about May 30, 1988, Mr. Sherno contracted with William F. Meinking to construct a home for Mr. Meinking. The contract price was not to exceed $64,000.00. A building permit was issued for the construction of Mr. Meinking's home on June 8, 1988. The permit was obtained by Mr. Sherno as agent for Respondent. A notice of commencement was filed by Mr. Meinking on June 20, 1988, listing Respondent as the contractor, and listing Mr. Sherno as the person designated by the owner for service of notice and other documents. Respondent authorized Mr. Sherno to obtain the building permit by letter to the local building department dated June 21, 1988 ("authorization letter"). The authorization letter was requested by Robert Nelson who was Tracy's president. Mr. Nelson was personally acquainted with Mr. Sherno and dealt directly but separately with Mr. Sherno and Respondent. Mr. Sherno paid $200.00 to Mr. Nelson at the time of the authorization letter. Mr. Nelson told Respondent that the permit was for the construction of Mr. Meinking's home. Respondent initially questioned the need for a contractor to pull the permit when the owner could build his own house under an owner's permit. Respondent was told that Mr. Meinking and Mr. Sherno were going to develop a number of homes in the area Not only would the number of homes not qualify for an owner's permit, but it was anticipated by Mr. Nelson that the development plan proposed by Mr. Sherno and Mr. Meinking had excellent profit potential for all concerned. Based on that information from Mr. Nelson, Respondent signed the authorization letter. Respondent knew Mr. Sherno and knew that Mr. Sherno was not a licensed contractor. Neither Respondent nor any qualified person supervised the construction of Mr. Meinking's home. One person employed by Tracy in an administrative or clerical capacity visited the construction site occasionally. Respondent inquired of Mr. Nelson from time to time at the offices of Tracy as to the status of construction. Respondent drove by the construction site from time to time, but did not personally supervise construction in any capacity. Respondent did not inspect the progress of construction, provide insurance, discuss the progress of construction with Mr. Meinking, Mr. Sherno, or anyone at Tracy. Respondent assumed that construction was proceeding according to schedule and in a satisfactory manner as long as there were no complaints. Mr. Meinking paid Mr. Sherno the entire $64,000.00 pursuant to the terms of the contract. During the latter stages of construction in the first or second week of November, Mr. Meinking began receiving calls from subcontractors stating that they had not been paid. Mr. Meinking terminated his contractual relationship with Mr. Sherno on or about November 17, 1988. Mr. Meinking paid approximately $16,500.00 to eight subcontractors and an additional $10,000.00 to $12,000.00 to finish construction of his home.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent be found guilty of violating Subsections 489.129(1)(e), (f), and (m), Florida Statutes. It is further recommended that Respondent be fined $2,000.00 which represents the aggregate amount of the minimum fine for each violation. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 27th day of August, 1990. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of August, 1990.

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KONRAD V. ISING, 83-002892 (1983)
Division of Administrative Hearings, Florida Number: 83-002892 Latest Update: Mar. 19, 1984

The Issue The issue for determination at the final hearing was whether the contracting license of the Respondent Konrad v. Ising should be suspended, revoked, or otherwise disciplined by the Petitioner Department of Professional Regulation, for alleged violations of Chapter 489, Florida Statutes. At the final hearing Petitioner's Exhibits 1 and 2(a)-(g) were offered and admitted into evidence. The Respondent testified on his own behalf.

Findings Of Fact The Respondent Konrad V. Ising is licensed to practice contracting in Florida, and is a licensed certified general contractor holding license number CG C009669, a license current and active from 1982 through the present. The Respondent qualified Master Craft Constructors using license number CG C009669. During 1982, the Respondent entered into an association with Carlton Mosher whereby the Respondent would use his contractor's license to obtain building permits for construction projects which Mosher had contracted. The Respondent hoped his association with Mosher would lead to a partnership and assist him in obtaining practical experience in the construction field. During his association with the Respondent, Mosher was not a licensed contractor. In December 1982, Mosher, doing business as Re-Builders, contracted with Russell Hirstins to construct a room addition on his home at 4034 27th Avenue, St. Petersburg, Florida. On December 3, 1982, an application for a building permit for the job was submitted to the City of St. Petersburg and permit number 88638 was issued. The permit was obtained using the Respondent's license number and Respondent is listed as the job contractor. However, the Respondent performed no work on the Hirstins job, maintained no control over Mosher's work, failed to adequately supervise the project, and failed to qualify Re-Builders with the Construction Industry Licensing Board. Since becoming licensed in 1975, the Respondent has not been involved in any other disciplinary proceedings. At the final hearing, the Respondent candidly acknowledged that his association with Mosher was a regrettable mistake. The project was completed by Mosher to the apparent satisfaction to the Hirstins.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That a Final Order be entered by the Construction Industry Licensing Board finding the Respondent Konrad V. Ising guilty of violating Section 489.129(1)(g) and (j), Florida Statutes, and imposing a $250 administrative fine. DONE AND ORDERED this 30th day of January 1984, in Tallahassee. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January 1984. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Konrad V. Ising Post Office Box 1023 Maitland, Florida 323751 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32302

Florida Laws (3) 120.57489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DOANLD F. ROYAL, 88-003298 (1988)
Division of Administrative Hearings, Florida Number: 88-003298 Latest Update: Dec. 20, 1988

Findings Of Fact At all times material to this proceeding, the Respondent, Donald F. Royal, was licensed as a registered roofing contractor in the State of Florida, holding license number RC 0031831. During the times of the alleged violations, the Respondent was the sole qualifying agent for J & J Construction Company (the company.) The principals of the company were the Respondent and a man named James Jimenez. Both men sold jobs for the company and were responsible for overseeing some of the work of the company. The Respondent pulled permits for, and was primarily responsible for, the roofing work contracted by the company. But sometimes, when the company had more than one job going at the same time, the Respondent would be primarily responsible for overseeing one, and Jimenez would be primarily responsible for overseeing the other. The Respondent thought that Jimenez held a license of some kind that enabled him to do some kinds of minor renovation construction. The Respondent restricted his work to roofing and did not mind Jimenez doing some renovation work on the side, separate from the business of the company. But the Respondent understood that Jimenez' "side deals" would be done separately under Jimenez' own license and would not be part of the business of the company. On or about August 14, 1986, Jimenez entered into a contract on behalf of the company to build an addition, remodel and reroof the existing structure and roof the addition of the residence of Ernest and Mercedes Riccio located at 3117 West Henry Avenue, Tampa, Florida. The contract price was $18,999. Jimenez telephoned the Respondent about the job but only told him about the part of the contract that called for the existing roof to be torn off and reroofed. He told the Respondent that the contract price for the job was $3,800. The Respondent pulled a permit for what he thought was the job and started and finished what he thought was the work to be done. The Respondent personally was compensated approximately $700-$800 for his part in the reroofing job. When the Respondent was finished, Jimenez continued with the rest of the contract, which was to include roofing the addition, without telling the Respondent about it. Jimenez did not get very far before a Tampa building inspector happened past and, seeing unfamiliar work in process, inspected the job site. He discovered that the building permit displayed at the site had been altered to expand the work purportedly permitted to include building, in addition to the roofing work for which the Respondent had obtained a permit. Someone other than the Respondent (probably Jimenez although he denied it) altered the permit. The Respondent knew nothing about the contract (other than the reroofing that he did), the alteration of the permit, or the work Jimenez was doing after he left the site. When he discovered the permit violations, the building inspector "red- tagged" the entire job, and work stopped. That was only the beginning of the Riccios' problems. Further investigation revealed that the job would require not only a valid permit but also zoning variances and utility easements. Although the contract had called for the company to obtain all necessary permits, Jimenez and the Riccios agreed that the Riccios would apply for whatever else was necessary in their own names and that Jimenez would assist them. By the time work stopped, the Riccios already had paid the company $12,666 of the total contract price. Nonetheless, when Jimenez' minimal assistance did not resolve the Riccios' problems quickly, Jimenez decided that he already had put too much into the job, and he began to lose interest and make himself scarce. The Riccios finally got their necessary permits on January 26, 1987. They then approached Jimenez about the work to be done under the contract (and the matter of the remaining $6,333 draw). The Riccios and Jimenez agreed that the Riccios would provide the materials and supplies necessary to complete the work and the company would provide the labor. Despite these alternate arrangements, the company did not promptly finish the job. Eventually, the Riccios gave up on Jimenez and in April or May, 1987, began to deal directly with the company's former job superintendent, a man named Ray. To improve their chances of getting the job done (and reduce some of their extra expenses), the Riccios agreed to allow Ray to live in the house free of charge while they were doing the work. The job still did not get finished. Eventually, Mrs. Riccio and some of her relatives finished the job themselves. Even so, the Riccios wound up spending about $20,000, in addition to the $12,666 they had paid the company, to complete the job which the company had contracted to do for $18,999, total. The Respondent was not aware of any of Jimenez' dealings with the Riccios after the Respondent completed his reroofing work. The Respondent assumed that Jimenez had called for a final inspection and that the job had been completed satisfactorily. But in approximately February or March, 1987, the Respondent was contacted by a DPR investigator in connection with the Riccios' complaint against the company. He learned at about that time about Jimenez' other dealings with the Riccios. He also learned that the roof over the addition that had been built had failed inspection. The Respondent eventually corrected the deficiencies, and the roof passed final inspection on August 19, 1987. The Respondent attempts to excuse himself of any wrongdoing, saying that he had a right to delegate the supervision of jobs such as the Riccio job to Jimenez and that he himself was victimized by Jimenez, along with the Riccios. Respondent nonetheless negotiated with Jimenez through the end of the year 1987 in an attempt to come to an agreement to continue to do business together, but the negotiations finally failed. The Respondent was disciplined by the Construction Industry Licensing Board on January 7, 1988, for offenses which occurred during the same time frame in which the Riccio job took place.

Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that Construction Industry Licensing Board enter a final order finding the Respondent, Donald F. Royal, guilty of violating Section 489.129(1)(j) and (m), Florida Statutes (1987), and imposing on him an administrative fine in the amount of $1,000. RECOMMENDED this 20th day of December, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of December, 1988. COPIES FURNISHED: Mr. Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Elizabeth R. Alsobrook, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Donald F. Royal, pro se 8509 North 16 Street Tampa, Florida 33604 Bruce D. Lamb General Counsel Dept. of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (3) 489.105489.119489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs PHILIP A. DIORIO, 96-004296 (1996)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Sep. 11, 1996 Number: 96-004296 Latest Update: May 05, 1997

The Issue Whether Respondent committed the violations alleged in the Administrative Complaint? If so, what punitive action should be taken against him?

Findings Of Fact Based upon the evidence adduced at hearing, and the record as a whole, the following Findings of Fact are made: Respondent is a building contractor. He obtained his license (License Number CB C028158) to engage in the contracting business in the State of Florida in 1984. Respondent's license expired on August 31, 1996, without Respondent having made any effort to renew it. On September 1, 1996, the Department placed Respondent's license on "a delinquent status for non-renewal." 5/ It considers the license to be invalid for the 1996-98 licensing period. At all times material to the instant case, Respondent was the primary qualifying agent for Loma Linda Homes Corporation (Loma Linda). In late 1993 or early 1994, Loma Linda entered into a written contract (Contract) with Carmen Bennett and her daughter-in-law, Virginia Bennett, in which it agreed to construct a residence for the Bennetts at 5403 Loma Vista Loop in the Loma Vista subdivision in Davenport, Florida. The Contract had a "[t]ime is of the essence" provision. 6/ The Contract further provided that is was "conditioned upon Purchaser[s, the Bennetts] obtaining a mortgage loan commitment within sixty days from the date of this contract for a term not to exceed thirty (30) years at the prevailing market interest rate at time of closing." The Bennetts timely obtained such a commitment. Prior to the execution of the Contract, Loma Linda had received a $1,000.00 deposit from the Bennetts. At or around the time the Contract was executed, the Bennetts provided Loma Linda with an additional deposit in the amount of $9,813.00. The Contract provided that "[i]f Seller [Loma Linda] fails, neglects, or refuses to perform this Contract, the Purchasers [the Bennetts] shall receive the return of all sums paid to the Seller." Loma Linda failed to meet its obligations under the Contract. Construction of the residence that Loma Linda agreed to build for the Bennetts never commenced. All that Loma Linda did in furtherance of its contractual obligations was to clear the lot on which the home was to be built. The Bennetts have not received back any of the $10,813.00 in deposit monies that they paid Loma Linda.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board enter a final order: (1) finding Respondent guilty of the violations alleged in Counts I, III and V of the Administrative Complaint; (2) penalizing Respondent for having committed these violations by imposing on him a fine in the amount of $1,000.00 and requiring him to pay $10,813.00 in restitution to the Bennetts and to reimburse the Department for all reasonable costs, excluding attorney's fees, associated with the Department's investigation and prosecution of the charges set forth in Counts I, III and V of the Administrative Complaint; 10/ and (3) dismissing Counts II and IV of the Administrative Complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 9th day of January, 1997. STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 1997.

Florida Laws (8) 120.569120.57489.105489.115489.116489.119489.1195489.129 Florida Administrative Code (5) 61G4-12.01861G4-17.00161G4-17.00261G4-17.00361G4-17.005
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE PLOMARITIS, 88-005200 (1988)
Division of Administrative Hearings, Florida Number: 88-005200 Latest Update: Mar. 21, 1989

The Issue The issue presented for decision herein is whether or not Respondent has been disciplined by a local government, the City of Tampa, in violation of Subsection 489.129(1)(i), Florida Statutes.

Findings Of Fact Based upon my observation of the witness and his demeanor while testifying, documentary evidence presented and the entire record compiled herein, the following relevant facts are found: During times material hereto, Respondent was a licensed contractor in Florida, having been issued license number CG C006397. Petitioner is the State agency charged with regulating the construction industry in Florida. On May 5, 1987, Respondent was disciplined by the Unified Construction Trades Board of the City of Tampa, and thereafter, on August 13, 1987, Respondent's license was revoked based on the determination that Respondent was guilty of violating City of Tampa codes. (Petitioner's Composite Exhibit 2.). Respondent's disciplinary action by the City of Tampa was reviewed by Petitioner and based on the May 5, 1987 suspension of Respondent's license, Petitioner found probable cause against Respondent on June 11, 1987. As stated, Respondent failed to appear to contest or otherwise refute the fact that the Unified Construction Trades Board of Tampa took disciplinary action against his license.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner's certified general contractor's license number CG C006397 be suspended for a period of one (1) year from the entry of the Board's final order. DONE and ENTERED this 31st day of March, 1989, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of March, 1989.

Florida Laws (2) 120.57489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HOWARD G. RIENECKER, 82-002261 (1982)
Division of Administrative Hearings, Florida Number: 82-002261 Latest Update: Jan. 31, 1984

The Issue Whether respondent's license as a certified general contractor should he disciplined on charges of abandonment, diversion, violation of applicable building codes, improper qualification of companies under whose name he was conducting business, and continued misconduct in the practice of contracting, in violation of Chapter 489, Part I, Florida Statutes.

Findings Of Fact At all times relevant to the charges, respondent was a certified general contractor holding license no. CG C015937. He now resides at 1210 Old Boynton Road, Apartment 113, Boynton Beach, Florida. (Testimony of respondent; P-1) I. Count I: Abandonment of a Construction Project On or about October 30, 1980, respondent, d/b/a P & R Construction, a subsidiary of New Visions, Inc., entered into a contract with Mr. and Mrs. A. J. Ervin to construct a bathroom addition to their residence located at 1119 Lake Terrace, No. 101, Boynton Beach, Florida, for the sum of $4,500. (Testimony of respondent) Respondent was the contractor of record for this project. He pulled the required building permit, hired the subcontractors, and supervised the project. Robert Popiel, owner of New Vision, Inc., kept the company's books, paid bills, and handled sales. (Testimony of respondent; P-9) In June of 1981, respondent abandoned the construction project, leaving it uncompleted. Neither the bathroom door nor the shower door had been installed; exterior stucco beneath the bathroom window (which had been removed to repair a leak) had not been replaced; and the bathroom floor was unfinished. Final inspections had not been made and a certificate of occupancy had not been obtained. During the next four or five months, Mr. Ervin tried, unsuccessfully, to locate respondent and persuade him to return and complete the project. Eventually, Mr. Ervin hired another contractor and paid him $500 to complete the unfinished work. (Testimony of Ervin, respondent) When respondent abandoned the project, the plumbing (Archie's Plumbing), roofing (Modern Roofing), and electrical (Jerry's Electric) subcontractors, who had performed work and furnished materials for the project, were left unpaid. The improvements were thus subject to the placement of contractors' liens. The subcontractors were owed a total of $2,107.21, although they eventually settled with the owner for a total payment of $1,100. (Testimony of Ervin, Yedvarb, Grummer) Moreover, when respondent abandoned the project, there were leaks in the roof, where the bathroom joined the existing structure, and leaks below the bathroom window. (Testimony of Ervin) During this time, respondent was undergoing a divorce and moving from one motel to another. Mr. Ervin tried repeatedly to contact him, but respondent neither returned his phone calls nor answered his messages. Despite the best efforts of Mr. Ervin, respondent was nowhere to be found. II. Count II: Diversion of Monies Respondent did not receive a fixed salary from New Visions, Inc. Periodically, he would be paid by simply withdrawing funds from the company. During the time in question, New Vision, Inc., had four construction projects underway and respondent withdrew approximately $500. (Testimony of respondent, Popiel) The various New Vision, Inc., projects, including the Ervin project, were apparently underbid. Subcontractors were paid by Mr. Popiel out of incoming funds. But both he and respondent realized that the incoming money under the various contracts would be insufficient to pay all subcontractors for work performed. (Testimony of respondent, Popiel) Respondent was aware that the Ervin project was "running close" and that it "was probably running over" the contract price. (TR-53) It has not been shown that respondent diverted funds received for the completion of the Ervin project and that, as a result of such diversion, he was unable to complete the work. The subcontractors were not paid because the Ervin project incurred costs which exceeded the contract price. And, since New Vision, Inc., was experiencing similar difficulties elsewhere, it had insufficient funds to cover the excess costs of the Ervin project. (Testimony of respondent, Popiel; P-9, p. 32) III. Count III: Deliberate Violation of Building Code The Department alleges that respondent violated the applicable building code (Section 105.1, City of Boynton Beach Code of Ordinances) by covering the roof before the proper city inspection had been made. Pursuant to this code, it was respondent's duty to order the flat roof sheathing inspection; but it was the roofing contractor's responsibility to obtain the "tin tag" inspection before covering the roof. This is an inspection which is required to ensure that the base sheet or black felt is properly installed. Even though it was the roofing contractor's duty to call for such an inspection, the general contractor remained responsible for the entire project. (Testimony of Howell, respondent) In this case, respondent called for the sheathing inspection but the roofing contractor laid the felt and covered the roof without first calling for the requisite tin tag inspection. The building code violation was thus primarily the fault of the roofing contractor and only secondarily, or derivatively, the fault of the respondent. No evidence was presented to show that respondent approved, or knew, in advance, of the roofing contractor's failure to call for the tin tag inspection. Respondent's failure to ensure that the roofing contractor called for the required inspection cannot, without more, support a conclusion that respondent knowingly and deliberately violated an applicable building code. (Testimony of Howell, respondent) IV. Count IV: Acting in a Capacity of a Contractor Under a Name Other Than as Certified Respondent, d/b/a P & R Construction, a subsidiary of New Vision, Inc., contracted for and constructed a bathroom addition to the Ervin residence. However, neither company was qualified with the Construction Industry Licensing Board. V. Count V: Misconduct in the Practice of Contracting In this count, the Department alleges that, by virtue of the misconduct alleged in Counts I through IV, respondent is guilty of "misconduct in the practice of contracting." No additional acts of respondent were complained of or alleged. It follows that respondent can be found guilty of this charge only to the extent he is found guilty of the charges contained in Counts I through IV. VI. Mitigation There is no evidence that respondent has ever before been the subject of a disciplinary proceeding brought by the Construction Industry Licensing Board. He has worked in construction most of his life and this is the only business he knows. It is his livelihood, and, in his words, the only way "I can make a decent living." (TR-134) He is 59 years old. His goals are modest and tempered by experience: I'm just a small, small operator, and I work to make a living. I'm not going to get rich. I'm too old to get rich. Those things, thirty years ago I had that in mind. TR-134. He now realizes, better than before, the value of his contractor's license. His misconduct in connection with the Ervin project occurred when he was in the midst of a divorce and a personal ordeal. In his own words: And I bounced from place to place. I bounced off the bottom. I was living down at a flea bitten motel here. The roaches were so thick that I never thought I'd survive it. So now I guess--now I got married last September and I guess I'm getting to appreciate things which I took for granted before. I'm just getting so I appreciate them now and what-- you know, what I got and what I can do. TR-136 He admits that he did not fulfill his responsibilities from the Ervin project and understands better the hardships which his conduct imposed on Mr. Ervin.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Construction Industry Licensing Board impose a $1,000 fine against respondent for violating Section 489.129(1)(g), (k) , and (m), Florida Statutes. DONE and ENTERED this 7th day of November, 1983, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of November, 1983.

Florida Laws (2) 120.57489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOSEPH LAWTON, 89-000742 (1989)
Division of Administrative Hearings, Florida Number: 89-000742 Latest Update: May 19, 1989

Findings Of Fact At all times material to this case, the Respondent, Joseph Lawton, was licensed as a registered roofing contractor in the State of Florida, holding license number RC 0052537. At all times material to this case, the Respondent was the qualifying agent for All Florida Systems located in Fort Lauderdale, Florida. The Notice of Hearing was mailed to Respondent at his last known address. Ronald Klein lives at 8245 Northwest Ninety-fifth Avenue, Tamarac, Florida. A portion of the roof on Mr. Klein's residence is flat and a portion is pitched. In the middle of August, 1987, Respondent met with Mr. Klein at the Klein residence to discuss Mr. Klein's roofing needs. Respondent told Mr. Klein during their meeting that the flat portion of his roof needed to be re-roofed and quoted a price for the work that Mr. Klein found acceptable. This was the only meeting between Mr. Klein and Respondent and was the only time Mr. Klein has seen Respondent. There was no written contract between Respondent and Mr. Klein because Respondent did not mail to Mr. Klein a written contract as he had agreed to do. On Sunday, August 30, 1987, Earl Batten, one of All Florida System's workers, re-roofed the flat portion of Mr. Klein's roof. Mr. Klein paid Mr. Batten $1,575.00 for the work pursuant to the verbal agreement between Respondent and Mr. Klein. Mr. Klein made his check payable to Earl Batten because Respondent had told Mr. Klein to pay his worker when the work was completed. Mr. Klein noted on the check that the check was in payment of work done by All Florida Systems. Respondent did not obtain the permits required by local law for the work done on the Klein residence. Because there was no agreement to the contrary, it would have been Respondent's responsibility to obtain the permits required by local law. Respondent did not obtain the inspections required by local law for the work done on the Klein residence. Because there was no agreement to the contrary, it would have been Respondent's responsibility to obtain the inspections required by local law. Mr. Klein's roof began leaking after Mr. Batten completed his work on August 30, 1987. In response to three weeks of repeated telephone calls from Mr. Klein, Respondent sent one of his supervisors to inspect Mr. Klein's roof. The supervisor told Mr. Klein that the work had to be redone because the work on the flat roof had not been properly tied into the remainder of the roofing system. Mr. Klein was further advised by the supervisor that Respondent would be in contact with Mr. Klein. After Respondent failed to respond further, Mr. Klein hired a second roofing contractor who corrected the deficient work in October of 1987 at a price of $1,377.00. Between the time Mr. Batten worked on his roof and the time the second contractor corrected the deficiencies, Mr. Klein sustained damages to his residence which required expenditures of over $1,500.00 to repair. Respondent was previously disciplined by the Construction Industry Licensing Board in Case No. 90265.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered finding Respondent guilty of having violated Sections 489.129(1)(d) and (m), Florida Statutes, and which imposes an administrative fine against Respondent in the amount of $5,000.00 and places Respondent on probation for a period of one year. DONE and ENTERED this 19th day of May, 1989, in Tallahassee, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of May, 1989. APPENDIX The findings of fact contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 18, 19, 20, 22 are adopted in substance; insofar as material. The findings of fact contained in paragraphs 16, 17, 21 of Petitioner's proposed findings of fact are subordinate. COPIES FURNISHED: Elizabeth R. Alsobrook, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Joseph Lawton 1000 South Ocean Boulevard Apartment 6C Pompano Beach, Florida 33062 Kenneth E. Easley, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (5) 120.57489.105489.119489.128489.129
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer