Findings Of Fact Petitioner Ferncrest Utilities, Inc. owns and operates a sewage treatment plant at 3015 Southwest 54th Avenue, Fort Lauderdale, Florida. It presently services the needs of a population of about 2500 primarily located in three trailer parks, certain warehouses, a 153 room hotel, and several other business establishments. The plant was constructed and operated by a lessee of Petitioner's owners, but, in July 1979, Petitioner became the owner and operator of the facility. At that time, it was determined necessary to secure new operators and upgrade the plant equipment and method of process in order to properly service the existing and anticipated future number of customers in the area covered by a Public Service Commission franchise. Although the plant had been operating at a permitted capacity of 0.25 million gallons per day (MGD), Petitioner planned to expand the capacity to 0.60 MGD by modifying the aeration tank, and adding tertiary sand filters and equipment for clarification. Upon assuming control of the plant, Petitioner found that the 0.25 MGD permitted capacity had been exceeded by approximately 120,000 gallons per day for a number of years. Petitioner estimates that a population of 6,000 could be served under its new proposed design capacity. (Testimony of Forman, Exhibit 1) Pursuant to Petitioner's application for a construction permit, dated May 25, 1979, to modify the existing treatment plant, Respondent issued permit No. DC06-21789 on August 6, 1979. The permit specified that it was for construction of additional tank capacity for an existing 0.25 MGD wastewater treatment plant intended to approve effluent quality, and further stated that plant design capacity would remain at that figure. A subsequent letter from Respondent's subdistrict manager to Petitioner on January 15, 1980, stated that an evaluation of the quality of the surface waters receiving the plant discharge and the effect of such increased discharge would have to be made before processing a request for an increase in permitted flow. (Exhibit 7) On February 8, 1980, Respondent issued a temporary operating permit for Petitioner to temporarily operate a 0.25 MGD contact stabilization sewage treatment plant, including additional tank capacity and tertiary filtration. Specific conditions attached to the permit stated that it was issued to give the permittee a reasonable period of time to complete construction of the modification outlined in DER Permit DC06-21789 and for subsequent assessment of the effects of discharge on receiving waters. The conditions further required that the facility continue to achieve 90 percent removal of BOD5 and total suspended solids at all times with specified average daily discharges of such substances. Another condition required that the effluent from the plant be adequately chlorinated at all times so as to yield the minimum chlorine residual of 0.5 parts per million after a minimum contact period of 15 minutes. (Exhibit 8) Thereafter, on July 21, 1980, petitioner filed the instant application for an operation permit for the facility at a design capacity of 0.60 MGD. On October 7, 1980, Petitioner filed a certificate of completion of construction. By letter of December 16, 1980, Respondent's South Florida Subdistrict Manager advised Petitioner that the application for an operating permit had been denied for the reason that monitoring of the Class III receiving waters by the Broward County Environmental Quality Control Board indicated that the dissolved oxygen concentration was frequently below the minimum of 5 milligrams per liter required by Section 17-3.161(1), Florida Administrative Code, and that Petitioner's plant contributed to the substandard conditions in those waters. Petitioner thereafter requested a Section 120.57(1), F.S., hearing. (Exhibits 1-2, 4, 8) Petitioner's plant discharges into the North New River Canal through a six inch effluent pipe. The canal extends from Lake Okeechobee to the intracoastal waterway approximately five miles in distance from the point of discharge of Petitioner's plant. Monitoring of water quality in the canal for the past several years by the Broward County Environmental Quality Control Board shows that the dissolved oxygen concentrations at various sampling stations have ranged from below one part per million to in excess of five parts per million, depending upon the season of the year. However, at no station did the dissolved oxygen concentration reach an average of five parts per million. In addition, the tests also showed that BOD5 is generally low in the canal waters. (Testimony of Mazzella, Exhibits 1, 3, 5) Petitioner's modified plant is now capable of treating 0.60 MGD and meets current basic state requirements of 90 percent (secondary) removal of BOD and total suspended solids. In fact, the plant has tertiary treatment and can consistently operate at a level of 95 percent treatment. The data submitted by the applicant as to effluent water quality characteristics showed removal of 98 percent BOD, 97 percent suspended solids, 50 percent total nitrogen, and 25 percent total phosphorus with an average chlorine residual in the effluent of 0.2 parts per million. The dissolved oxygen level in the effluent has been established at 6.5 milligrams per liter. (Testimony of Hermesmeyer, Dodd, Exhibit 1) Respondent's district personnel took one 24-hour sample of the effluent from Petitioner's plant in March 1981 and determined that a concentrate of 14.6 milligrams per liter of ammonia was being discharged to receiving waters. Respondent therefore determined that the dissolved oxygen levels of the canal would be further degraded because approximately 48 to 50 parts per million of dissolved oxygen would be necessary to offset the effects of oxygen removal resulting from the ammonia discharge. Respondent further found that, although the effluent from the plant had 6.5 milligrams per liter of dissolved oxygen, the amounts of phosphorus and nitrogen being discharged could lead to algal blooms and consequent eventual eutrophication of its waters. Respondent's reviewing personnel therefore considers that there would be negative impacts upon the receiving waters if Petitioner discharged its prior licensed capacity of 250,000 gallons per day, and that a discharge of 600,000 gallons per day would double such impacts. Respondent's personnel therefore believes that although Petitioner's facility meets the basic secondary treatment requirements of Rule 17-6.01, Florida Administrative Code, it does not meet the water quality-based effluent limitation specified in Rule 17-6.10. In order to meet such requirements, it would be necessary to redesign the plant for more efficient removal of nutrients or to redirect the discharge. (Testimony of Mazzella) Other facilities adjacent to or near the North New River Canal discharge directly or indirectly into the canal waters and contribute to an unknown degree to the poor quality of the canal waters. Additionally, agricultural use of land produces stormwater runoff containing fertilizer residue into the canal in an unknown amount. A sewage treatment plant operates at optimum level of treatment when it discharges at about 50 percent of its treatment capacity. (Testimony of Mazzella) In 1983, Broward County will require Petitioner's plant to conform to state advanced waste treatment criteria which will provide for additional removal of nitrogen and phosphorus from effluent. To meet this requirement, Petitioner, plans to investigate the possibilities of utilizing a landlocked lake on its property near the treatment plant as a seepage pond. Although Petitioner's plant is identified in area regional plans to be diverted to the Hollywood wastewater treatment plant in the future, there is presently no target date for tying in to such a regional facility. (Testimony of Hermesmeyer, Exhibit 1)
Recommendation That Respondent issue a permit to Petitioner for the operation of its sewage treatment plant, with appropriate conditions as designed to protect the receiving waters. DONE and ENTERED this 27th day of May, 1981, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 1981. COPIES FURNISHED: Alfred Clark, Esquire Deputy General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Martin S. Friedman and R.M.C. Rose, Esquires Myers, Kaplan, Levinson, Kenin and Richards 1020 East Lafayette Street Tallahassee, Florida 32301 Honorable Victoria Tschinkel Secretary, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 =================================================================
Findings Of Fact Respondent HDR has applied to DER for a permit to construct a 60,000 gallon per day extended aeration sewage treatment plant with percolation ponds. The facility would be used to provide secondary treatment of domestic waste from the HDR Mobile Home Park. The project is in Volusia County south of the City of Oak Hill and north of the Town of Edgewater. It is bounded on the east side by the Indian River and the west side by U.S. Highway One. The mobile home project site consists of approximately 156 acres, with the proposed wastewater treatment plant located in the southwest corner of the tract. HDR submitted Application No. 85433 to DER on July 2, 1984, requesting a permit to construct a 0.6 MGD extended aeration sewage treatment plant and associated percolation ponds for the mobile home project. Supplemental information was filed with DER on August 29, 1984. DER issued a notice of intent to permit the project on November 8, 1984. The plant would provide secondary treatment of effluent with a minimum of 90 percent removal of BOD's and suspended solids through aeration, settling and chlorination processes. The system is designed to collect sewage through a gravity system and lift station. The lift station dumps the sewage into the aeration chambers where forced air is mixed with the sewage, resulting in removal of organic materials and solids. The dissolved solids are then separated in the settling tank. From the settling tank, clear effluent enters the chlorine contact chamber where chlorine disinfectant is added prior to discharge into the percolation pond. The method of treatment described above and the design of the plant are standard. If the plant is operated properly, the wastewater will meet all DER criteria for secondary sewage treatment. Plant odor will be minimized by the continual feed of forced air into the system. Silencers will be installed on blowers to minimize any adverse noise effects from the blowers' operation. Aerosol drift is not a factor with the design of this plant. Security lighting will be provided, and the plant site will be surrounded by a six foot security fence. The design provides for effluent sampling access points and there will be a flow meter for measuring effluent discharge on site. A Class C operator will be required to operate the plant. Disposal of the 90 percent treated effluent will be made into two percolation ponds. The ponds will be alternately loaded, with one pond being loaded for seven days and then resting seven days. The total surface area for the two ponds is approximately 130,000 square feet. The ponds are designed with berms of three feet with an emergency overflow one foot from the top of each berm. The two ponds together are designed to handle 200,000 gallons per day which would be the ultimate build out of this project. However, the maximum capacity of the initial phase of the wastewater treatment plant would be 60,000 gallons a day. Any expansion to the sewage treatment plant would require a separate permit. The overall elevation of the area where the ponds are to be located is approximately 14 feet above sea level. Each pond is designed so that the pond bottom is two feet above the underground water table level measured at the highest point for the rainy season. In a 100 year flood, it is expected that the effluent and water can be absorbed without an overflow. The mobile home park has a storm retention system in which any theoretical overflow would be caught. The soil type at the location of the percolation ponds consists of several layers of sands. This type of soil has good permeability in that it provides a good transfer of water through the soil and is therefore suitable for siting of the percolation ponds. Pond design is conservative in that the hydraulic loading rate has a safety factor of at least 300 percent. Once the effluent has percolated into the ponds, the discharge will meet or exceed the level of quality of the G-2 ground water within the 100 foot zone of discharge. The design of the wastewater treatment plant also includes sufficient monitoring wells and provides for adequate buffer zones from residences and drainage ditches. No surface waters of the state are located within 500 feet of the sewage treatment plant or its percolation ponds. The Indian River, which is adjacent to the Hacienda Del Rio project, is approximately 2,500 feet from the sewage treatment plant. There will be no direct discharge by the sewage treatment plant into this body of water or any surface waters, nor would any indirect effect on surface waters be measurable. Shellfish harvesting is a local industry. The waters of the Indian River immediately east of the Hacienda Del Rio property are designated Class II waters suitable for shellfish harvesting. The Indian River is also part of the Canaveral National Seashore Waters, which are designated as Outstanding Florida Waters. Concern was expressed that additional growth in the area might contribute to degradation of these Class II waters. There was, however, no evidence to indicate that the construction or implementation of the wastewater treatment plant by HCD would degrade ore pollute the Indian River (which is both Class II and Outstanding Florida Water) or any other State of Florida surface waters. It should be noted that waters north and south of the property in the Indian River are closed to shellfish harvesting, apparently due to pollution. The Town of Edgewater north of the Hacienda Del Rio project has a secondary wastewater treatment plant which discharges its effluent directly into the Indian River. The City of Oak Hill to the south of the project has no wastewater treatment plant whatsoever. Individual businesses and homes utilize septic tanks, which can cause pollution to the Indian River through seepage. The HDR sewage treatment plant would thus meet higher standards than neighboring community facilities.
Recommendation From the foregoing, it is RECOMMENDED that the Department of Environmental Regulation issue a Final Order granting the application of Hacienda Del Rio. DONE and ENTERED this 31st day of May, 1985, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of May, 1985. COPIES FURNISHED: Betty J. Steffens, Esquire NABORS, GIBLIN & STEFFENS, P.A. 102 South Monroe Street Tallahassee, Florida 32302 William C. Henderson, Esquire HENDERSON & HENDERSON, P.A. Post Office Box 1840 New Smyrna Beach, Florida 32070 B. J. Owens, Esquire Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32301 Alva Stewart, Vice President South Waterfront Park Homeowners Association 150 Charles Street Edgewater, Florida 32032 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blairstone Road Tallahassee, Florida 32301
The Issue Whether Beker Phosphate Corporation should be granted a hermit to construct an industrial waste water facility pursuant to chapter 403, Florida Statutes. By application, dated April 8, 1975, Beker Phosphate Corporation (hereinafter Beker) , sought a permit to construct an industrial waste water facility in Manatee County, Florida, from the Department of Pollution Control (now and hereinafter DER) . The application was received on April 11 and, after advising Beker that the application was incomplete a meeting was held on May 9th between DER and Beker representatives with the result that Beker filed a new application dated June 11, that was received by the DER in July. Further meetings were held in the fall of 1975 and additional in formation was received as to the application. On December 16, 1975, DER secretary. Jay W. Landers, Jr., issued a Notice Of Intent To Grant A Permit With Conditions. The conditions were unspecified in the letter of intent (Exhibit 1.) Subsequently, on December 23 and December 24, 1975, Sarasota County (hereinafter Sarasota) and the Town of Longboat Key (hereinafter Longboat Key), respectively, filed petitions with the DER alleging that their substantial interests would be adversely affected by approval of the permit application and setting forth in their petitions certain disputed questions of fact for determination. After a prehearing conference, Amended Petitions were filed by those parties to clarify and expand on such questions of fact and to resolve procedural matters. Additionally, during this period, George Browning, III, of Sarasota, Florida was granted status as an intervenor.
Findings Of Fact Beker proposes to construct a phosphate rock mine and beneficiation plant on a tract of approximately 11,000 acres in a predominately agricultural and ranching area of Manatee County about 10 miles from Myakka City, Florida. The mining will be performed by two dredges. One will mine overburden and return it to the mined-out area and the other will mine phosphate rock matrix which will be pumped to the beneficiation plant. The plant will consist essentially of two circuits. The first is a washer where the matrix pumped from the dredging operation is partially cleaned of clay and fine sand, and the coarser phosphate particles "pebbles" are separated as a product. The "fines" from the washing operation consist of small phosphate rock particles, sand, and clay. This mixture will be treated in the second section of the plant by "flotation" methods to recover the small phosphate rock particles as a product. During initial operation, the sand and clay will be stored in a temporary waste material storage area, but as the mining proceeds and the dredge pits open up, the sand and clay material will be pumped back to the dredge pits so that sand, and overburden will be mixed and redeposited to reclaim the land. Approximately 8 million gallons of fresh water per day will be drawn from the Floridian aquifer to be used in the flotation circuits. From the plant the water flows in two types of streams--one containing sand suspended in water and one containing clay suspended in water. Both streams flow into a settling pond surrounded by an earthen dam where sand and clay solids settle to the bottom. The clarified water is then decanted through six spillway structures into a hydraulic recirculation ditch outside the dam and flows back to the plant for re-use. The ponds and canals that make up the hydraulic circuit are planned to have sufficient capacity to contain rainwater falling on the site and pond system during the wet season when there are heavy rainfalls (approximately from May to September). Excess water will be decanted from the hydraulic recirculation ditch through a structure into a pipe and then discharged into Wingate Creek. The settling pond will occupy approximately 225 acres and its capacity will be about 8,458 acre- feet. The pond itself can be used to act as a reservoir and water can be built up in the pond during periods of high rainfall. It will not be necessary to release the water at any particular time. It can be released at will when the effluent contains a minimum of pollutant materials (Exhibit 1). Matrix is an unconsolidated mixture of phosphate pebbles and boulders of partly phosphatized limestone, quartz and clay. The washing operation removes unwanted oversized material and fine clays. The purpose of the flotation plant is to recover fine phosphate rock that might otherwise be lost. In the flotation process, flotation reagents, including sulfuric acid, number 2 fuel oil, tall oil, sodium hydroxide, and amines are used for treatment. The wastes are then moved to the settling pond where over a period of time the "slimes", (sands and clays) will settle to the bottom forming an impervious layer which will seal the pond. The settling process removes more than 90 percent of the contaminants from the influent. The coarser clay particles settle first and many of the fine particles settle in a process called "flocculation" by which electrical forces bring the particles together. However, some of the particles will not flocculate and remain suspended in the water. These extremely small particles constitute the total suspended solids that remain in the effluent when it is discharged from the settling area. They probably will not settle out entirely during their course from Wingate Creek into the Myaaka River and eventually to the Gulf of Mexico. However, even if it were assumed that such materials would settle somewhere between the point of discharge and Charlotte Harbor, over the entire 20 year proposed life of the mine they would form a deposit much less than 1/10th of an inch. Although it is technically possible to treat water to the degree that it would result in distilled water, realistic concepts of treatment establish that an additional settling or "polishing" pond for the proposed facility might not improve the quality of the wastewater finally discharged in state waters to any appreciable degree. Alternative proposals for the reduction of pollutants by additional processing, such as the intentional growth of water hyacinths in settling areas or use of chemical coagulants would result in creating other waste materials and thus be counterproductive (Testimony of Bromwell; Exhibit 1). The applicant's discharge of wastewater to Wingate Creek will average approximately 3.19 million gallons per day. However, since discharge will be effected primarily during periods of excessive rainfall, actual discharges can reach a maximum of about ten million gallons per day during this period. The effluent contained in such discharge will meet the test of at least 90 percent removal of organic and inorganic wastes specified by Rule 17-3.04(1), Florida Administrative Code, when measured by the influent into the settling pond and the effluent leaving that area. This treatment, however, will not produce an effluent equivalent to that produced by the "highest quality municipal waste treatment." The highest degree of treatment that has been reached by municipalities is "advanced waste treatment" as defined in Rule 17-3.04(2)(b), Florida Administrative Code. The water quality characteristics of the effluent will meet the standards of Rule 17-3.05 as to concentrations of those pollutants reasonably anticipated to be fond in the wastewater based on samples taken where the waters are discharged into Wingate Creek (Testimony of Gilgallon, Davis, Edwards, Heinzman, Bromwell, Bartow, Wellford, Exhibit 1). In preparing the application, no consideration was given to the need of meeting treatment standards for highest quality municipal waste treatment or advanced waste treatment. Neither did the recommending official of the DER, Mr. Edwards, then Regional Administrator for the Southwest Region, consider this standard because he had been advised by the DER legal staff that Rule 17-3.04(2) did not apply to Wingate Creek since it was not a tributary to one of the bodies of water listed in subparagraph (c) of the rule 17-3.04(2). This determination was based upon Resolution No. 74-83, September 17, 1974, of the Florida Pollution Control Board that was issued after legal challenges had been made to an interpretation by the Department of Pollution Control legal staff that Rule 17-3.04(2) required advanced wastewater treatment for industrial waste discharges. The Board, in its resolution, determined that since evidence had not been taken concerning treatment standards for industrial waste discharges at the time of adoption of the effluent standards for sanitary waste contained in Rule 17-3.04(2), the advanced wastewater treatment standards in the aforesaid rule would not be enforced against industrial dischargers pending full hearings on a new Rule to clearly express the Board's intent in this regard (Testimony of Gilgallon, Edwards; Exhibit 1). Special conditions that the Southwest Region, Department of Environmental Regulation, recommends should be attached to any issuance of a construction permit, other than standard conditions and those relating to other types of permits, are as follow: Approval by DER prior to the construction of any above grade phosphatic clay storage facility other than the initial settling pond. Removal efficiencies for oil and grease shall be a minimum of 90 percent and shall not exceed 14 milligrams per liter measured in the discharge effluent. Discharge effluent to Wingate Creek shall meet the water quality standards of Chapter 17-3.05(2) at the point of discharge prior to mixing with the receiving stream. Further treatment of the discharge will be required in the event compliance with proviso (c) above cannot be achieved or significant degradation of the receiving stream occurs as determined by the DER. In addition to required routine monitoring, a detailed analysis of the untreated and treated wastewater to be conducted once on representative samples during (1) month of July and (2) month of February. Such analyses shall, as a minimum, include all the parameters listed in 17-3:05(2). Applicants shall conduct an investigation into total retention possibilities of the effluent including, but not limited to, the following areas: recharge wells retention and storage of excess water during the "wet" season with subsequent reuse during the "dry" season for process and/or irrigation purposes. A report of these investigations shall be submitted prior to submission of operation permit application The location of monitoring wells shall be down gradient from the settling pond. Detailed proposal, subject to the DER approval, regarding exact location and number of wells to adequately ascertain the impact of seepage to be submitted no later than 90 days prior to commencement of operation. Bond to be posted for damages that may result from a clay settling area dam failure. Oral and written communications from the public were received at the hearing and included the following: Announcement by the County Attorney, Manatee County, that the county did not plan to appeal the DER Notice of Intent to Grant the permit (Statement of E.N. Fay, Jr.). The Division of Recreation and Parks, Department of Natural Resources, fears that the construction of the phosphate mine up-stream from the Myaaka diver State Park poses a serious potential threat to its aquatic habitat due to the possibility of a dam failure. It also fears that pollutants from the project will tend to settle as the river waters flow through the two lakes in the park. It therefore, opposes the construction until assurance can be given that proper safeguards have been taken to prevent such problems (Testimony of Alverez). The Longboat Key Garden Club believes that the project would involve too much water consumption and also that phosphate mining should be halted until further government studies are made to assure that the safety and health of the populace and the environment will not be endangered through polluted runoff and phosphate spills (Testimony of Monroe). The Save Our Bays Association in Manatee County has collected petitions from citizens in Manatee County requesting a referendum on a ballot this November for or against phosphate mining. The Association believes that such a vote should be taken before final decision is made on the subject. Its spokesman fears that if the quality and quantity of the drinking water is disrupted, it will interfere with continued tourist trade (Testimony of Howard Greer). The Palma Sola Parks Association opposes the Beker Application until there is greater assurance of environmentally safe mining (Testimony of Blankenship) A former physical and health education director is concerned about the fact that there has not been sufficient data collected on the effect of radioactive materials in runoff and waste. She believes there should be more research in these areas and asked that the public be protected from such hazards (Testimony of Mary Kay Greer). The Manasota-88 project for environmental qualities of 1968 and 1988 believes that issuance of the permit should be withheld until health implications can be determined concerning potential hazards to the Myakka and Manatee Rivers' watersheds (Exhibit 7). A former member of the Manatee County Planning Commission that approved the Beker application prior to action by the County Commission of Manatee County is in favor of the proposed project because Beker's plan to impound water will augment the water facilities of the county (Testimony of Reasoner). The City of Bradenton believes that since it is being required to meet advanced water treatment standards of discharge for sanitary sewage, Beker Phosphate Corporation should be required to meet similar standards (Testimony of Mayor A.K. Leach). A member of the Myakka City Civic Association who is an adjacent land owner to Beker Phosphate Corporation feels that the project is necessary in order to produce jobs for individuals in that area of the county (Testimony of Mizell). The U.S. Fish and Wildlife Service is concerned that proposed construction of two dams by the applicant will destroy approximately (4) acres of mangrove areas, three acres of pasture land and about 185 acres of bottom land or hardwood habitat. It recommends an alternative method of backup levies constructed around the primary settling bases on the applicant's land to contain any spills and prevent destruction of the streams and associated wetlands (Testimony of Johnston) The Conservation Council of Manatee County believes that Beker's unique mining and reclamation plan will help the farming industry and also create necessary water reserviors and recreation areas, and therefore endorses its proposal to mine in Manatee County (Testimony of Kent, Exhibit 14). Petitions were submitted at the hearing from approximately 3,000 individuals living in Manatee and Sarasota Counties opposing the issuance of the permit because they believe that phosphate mining is dangerous to the quality and supply of the water and endangers the health of the people (Composite Exhibit 9, Testimony of Humphrey).
The Issue The ultimate issue is whether Celebrity Resorts, Inc., (Celebrity) is entitled to a permit to construct a wastewater treatment and reuse/disposal facility in Marion County, Florida.
Findings Of Fact Proposed Project Celebrity is seeking a DER permit to construct a 0.065 million gallon per day wastewater treatment and reuse/disposal facility to serve a proposed recreation vehicle (RV) park. The facility is to be located in northern Marion County on the southern border of Orange Lake, an Outstanding Florida Water. The RV park is to be located on 75 acres of land, and is to contain 372 RV and "park model" sites, four bath houses, a clubhouse, and an expanded boathouse. The sewage treatment plant (STP) and effluent disposal system, consisting of a spray irrigation system, are to be located on the southern end of the site, away from Orange Lake. There is a "break" in the watersheds of the Celebrity property caused by a ridge across the approximate center of the project site. The effect of this "break" is that approximately one-half of the property drains toward the lake while the approximate southerly half of the property drains into an independent depression creating a watershed separate from the lake. Some underground pipes for a sewage collection system were installed at the site without an appropriate DER permit. Celebrity stopped the installation upon notice from DER that a permit was required for such installation. The permit needed for the installation of the collection system pipes was not the permit for the sewage treatment project which is being considered in this proceeding. Celebrity was penalized for its collection system violation, which was resolved with a consent order. Sewage Treatment Plant (STP) The STP is an extended aeration plant. It is designed to meet secondary treatment standards (90% removal of BOD and suspended solids from raw sewage) and basic disinfection. This type of treatment plant is very reliable. All mechanical components have a 100% backup so if a pump or blower fails, another is available to operate. The STP is designed to be capable of treating the flow from this RV park. Additionally, the facility has a holding pond for treated sewage effluent that can store five days of flow. Furthermore, because the RV park is a transient facility, it is possible in an emergency to shut down the entire plant and have people leave. By its nature, this is much more convenient in an RV park that in a residential or commercial neighborhood. The holding pond is to be lined with a 60 millimeter high density polyethylene liner, so there should be no leakage to the ground or groundwater even if there is an accident in the STP causing release of untreated sewage into the holding pond. The STP is to be maintained five days a week and must be attended for three nonconsecutive visits a week by a Class D certified plant operator. The amount of dissolved/undissolved heavy metals in the effluent is typically not a problem in domestic sewage effluent such as from the proposed RV park. To the extent that trace amounts of metals will exist, the STP will remove some heavy metals from the effluent during the treatment process and entrain them in the sludge (which will be taken to appropriately licensed landfill). There is no possibility of effluent leaking or discharging from the plant to directly discharge to Orange Lake, even if the STP completely malfunctions. Although the proposed STP is not a highly sophisticated plant, reasonable assurances have been provided that the STP will comply with DER's requirements for secondary treatment and basic disinfection and proper operation. Effluent Disposal System (Spray Irrigation System) Phase I of the effluent disposal system (spray irrigation system) is 3.66 acres in size, with an additional 1.7 acres designated if Phase II is implemented. Approval under this permit authorizes only the 3.66 acres on Phase I. Numerous separate sprinkler heads will spray the treated effluent on the field. The heads can be separately controlled and shut down. The sprayfield is sited on the southwestern corner of the 75-acre site and is separated hydrologically from the Orange Lake drainage basin by the "break" referred to in Paragraph 4 above. Therefore, surface water drainage in the area of the sprayfield drains away from the lake and does not connect back to the lake. The permitted loading rate is 1.7 inches per week, or approximately 24,000 gallons per day at full capacity. This amount corresponds to only approximately 170% of natural rainfall, but is more evenly distributed and controlled. After uptake of nutrients by green plants and evaporation (evapo- transpiration), the average amount of treated effluent that will percolate below the "uptake zone" to the surficial aquifer (to the extent that such exists on the site) is 0.3 to 0.4 inches per week. The surficial water table in the area of the sprayfield generally flows to the north toward the lake, although the flow is not immediately direct toward the lake. The Floridan Aquifer (which is beneath the intermittent surficial water table) in the area of the sprayfield generally flows away from the lake to the south and southeast. There are four sinkholes on the 75-acre site, although none of these four sinkholes have been identified on the 3.66-acre sprayfield. The four sinkholes on the 75-acre site and the majority of sinkholes in the area are "subsidence sinkholes." These sinkholes do not result in an open void down to the limerock after the collapse forming the sinkhole, but instead continue to have unconsolidated material above the limerock, even though a depression forms on the surface. One of the sinkholes has standing water within it and could possibly represent a connection with the lake water table or the Floridan Aquifer, but that sinkhole is separated hydrologically from the sprayfield site by the "break" across the property. There will generally be a slight increase in hydrologic conductivity through a subsidence sinkhole, since the unconsolidated material on the surface remains and is loosened. In some cases there may be even less hydrologic transmissivity due to a "jamming up" of the unconsolidated material, and in some cases there may be an increase in transmissivity when the unconsolidated material falls into an even less consolidated state. A "lineament" may exist on the 75-acre site. A lineament is a fracture zone, which indicates an increase in ground water transmissivity, resulting in an increase in solution of limestone and therefore indicating a more likely location for sinkhole formation. If a sinkhole develops within the sprayfield and if the sinkhole results in an increased area of ground water transmissivity, it could be a conduit for treated effluent to reach the surficial aquifer or Floridan Aquifer. Sinkholes which may form on the site are subject to being repaired with impervious material which prevents their becoming routes of contamination to the aquifer. In addition, the loading rate of any single sinkhole that forms within the spray irrigation field is so light and so easily shut down that there is a high confidence rate that no new sinkhole will act as a conduit for even the small immediate discharge over the area of the new sink to reach the Floridan Aquifer. A spray irrigation effluent disposal system is appropriate for this area which is subject to sinkhole formation. Spray irrigation allows dispersal of the effluent over a large area as opposed to a percolation pond which concentrates in the percolation area and therefore increases the chance of sinkhole formation and the chance of larger amounts of effluent reaching the Floridan Aquifer if all the intervening safeguards should fail simultaneously. In addition, the repair of any sinkhole forming within the sprayfield is simplified by the ability to simply shut off the sprinkler head or heads affecting that sinkhole while repair is being effected. Permit conditions further limit excessive effluent application rates by limiting the amount of flow, prohibiting application during storm events, and requiring monitoring of the flow. Spray irrigation is a common method of effluent disposal which generally has fewer problems than use of percolation ponds. No evidence has been presented that discharge from the sprayfield will cause violations of groundwater quality standards or violations of surface water quality standards, including the Outstanding Florida Water requirements in Orange Lake. Reasonable assurance has been provided that the proposed effluent disposal system will not violate DER water quality standards or other applicable DER rules. Standing Petitioner Suto could be substantially affected by this proposed facility if it causes pollution to Orange Lake since she uses the lake for nature photography. Additionally, she resides to the southeast of the proposed sprayfield and has concerns over contaminated ground water reaching her property and affecting her drinking water. Petitioner Riley could be substantially affected by this proposed facility if there is pollution to the Floridan Aquifer since she lives southeast of the proposed facility and has two drinking water wells on this property. Additionally, Petitioner Riley is a user of Orange Lake and therefore could be substantially affected by the proposed facility if it impacts the lake. Petitioner Solomon could be substantially affected by the proposed project if the project impacts Orange Lake since Mr. Solomon earns his living on the lake as a commercial fisherman and bass fishing guide.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Environmental Regulation enter a Final Order granting to Celebrity Resorts, Inc., a permit to construct a wastewater treatment facility and spray irrigation disposal system subject to the conditions set forth in the Intent to Issue. RECOMMENDED this 15th day of July, 1991, in Tallahassee, Florida. DIANE K. KIESLING, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of July, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 91-2722 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Celebrity Resorts, Inc. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 4(1); 5(2); 6(4); 7(5&6); 8- 12(7-11); 13(12); 14(13); 15(14); 16(15&16); 17(17); 18(18); 19-21(20-22); and 22-27(26-31). Proposed findings of fact 1-3 are unnecessary. Proposed finding of fact 28 is subordinate to the facts actually found in this Recommended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Department of Environmental Regulation Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 4-6(1-3); 7-13(5-11); 14(12); 15-17(13-15); 18(17); 19(18); 20-26(19-25); 27-32(26-31); and 33-35(32- 34). Proposed findings of fact 1-3 are unnecessary. COPIES FURNISHED: Delcie J. Suto, Pro Se 2400 N.W. 165th Street Citra, FL 32113 Carol B. Riley, Pro Se 2250 N.W. 165th Street Citra, FL 32113 Crawford Solomon, Pro Se 1303 N.W. 186th Place Citra, FL 32113 Karen English 3680 West Highway 318 Citra, FL 32113 Marilyn Nehring P. O. Box 481 Orange Lake, FL 32112 John Monsees 2400 NW 165 Street Citra, FL 32113 William L. Townsend, Jr. Attorney at Law Post Office Box 250 Palatka, FL 32178-0250 Douglas H. MacLaughlin Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400
The Issue The issues are: (1.) Whether Respondents' request for variance from requirements of Rule Chapter 10D-6, Florida Administrative Code, should be granted. (2.) Whether Respondents are guilty of violation of certain provisions of Chapter 381 and Chapter 403, Florida Statutes, and Rule Chapter 10D-6, Rule Chapter 17-550, and Rule Chapter 17-555, Florida Administrative Code, regulating the operation of onsite sewage disposal systems.
Findings Of Fact Respondent V.M.P. Corporation (VMP) operates a lounge known as Stud's Pub in Jacksonville, Florida. Licensed for 75 seats, the lounge actually contains 50-55 seats and employs five people full time. Additionally, 10-15 independent entrepreneurs known as dancers may be present at times. The dancers are not employees of Respondents. Less than 25 people, other than patrons, are present at the facility at any time. Respondent Vincent M. Paul (Paul) owns the facility and the corporation. The lounge is on lots that were platted prior to 1972. Petitioner is the statutory entity with authority for granting variances for onsite sewage disposal systems regulated by Petitioner pursuant to provisions of Section 381.0065(8)(a), Florida Statutes (1991). The lounge is serviced by a septic tank with a drainfield which is covered by an asphalt parking lot. The portion of the parking lot over the drainfield is bounded to the west by a dirt city street, to the north by other pervious surfaces, to the east by the lounge and to the south by the remainder of the asphalt parking lot. A sign on the premises which advertises the business is protected from automobile traffic by concrete barriers. The septic tank system and drainfield were installed prior to 1972 by a previous owner. Respondent Paul retrofitted the septic tank system after 1972. Respondent Paul was responsible for paving over the drainfield after he purchased the property. Petitioner's representatives inspected the lounge, determined the drainfield to be covered by the asphalt parking lot and requested Respondents to remove the asphalt covering. Respondents requested a variance pursuant to Rule 10D Administrative Code, for the asphalt covered drainfield and other deficiencies of the onsite sewage disposal system. Petitioner's review board recommended denial of the request on the basis that the variance would not constitute a "minor deviation" from rule requirements. Although the term is not defined by Petitioner's rule, Petitioner's usage of this term was the result of the consideration by Petitioner's review board of the application for variance within the context of Section 385.0065(8)(a), Florida Statutes, which authorizes Petitioner to grant variances only where the hardship is not intentionally caused by the applicant, where no reasonable alternatives exist and where no evidence of adverse effect upon public health or ground and surface waters is demonstrated. Respondent has no record of failure of the septic tank or drainfield. Water samples from the onsite potable water well filed with Petitioner tested below detectable limits for nitrates and coliforms, the only parameters Petitioner is required to analyze. Respondents' records of water flow or usage from the well into the lounge show daily flow rates of between 320 and 580 gallons, with an average rate of between 450 and 480 gallons. Respondent Paul is responsible for the installation of an unpermitted chlorinator on the water supply system which provided actual flow information. The only onsite water well has no grout sealant. It is the only well of which the parties are aware that lies within 100 feet of the septic system. The potable water well is located approximately 42 feet from the edge of the covered drainfield. The well head does not extend above line surface and there is no concrete pad around the wellhead. The exact depth of the well is unknown, although the well is located upgradient of the drainfield and a nearby junkyard. Denial of the variance would require that Respondents uncover the drainfield since there is no practically available offsite sewage system currently available. Soil in the area of the drainfield is classified as well- draining sand. Due to the impervious surface covering the drainfield, Petitioner's representative was unable, during his inspection, to discern any symptoms of drainfield failure in the form of "blow field should be totally unobstructed to allow aerobic processes to take place in the drainfield which will permit the breakdown of contaminants. A portion of Respondents' 1200 gallon septic tank is located partially under and immediately adjacent to Respondents' facility. A dousing tank which retains liquid waste and operates as part of the septic system is also totally covered by the asphalt pavement. Although there has been no detectable failure of the system, every eight or nine months Respondents have the septic tank and dousing tank pumped out. The tanks never get full.
Recommendation Based on the foregoing, it is hereby Recommended that a final order be entered by Petitioner denying the variance requested by Respondent with exception of such minimal distance as may be required to relocate the water well as far as possible from the drainfield on the Respondent property, and, Further Recommended that such final order also assess Respondent Paul an administrative penalty of $500 for each of the four violations contained in the Administrative Complaint which were proven in this proceeding for a total of $2000, and a continuing assessment of $500 per day for each violation for a total of up to $2000 per day after first allowing Respondents a 60 day period within which to correct all four violations. DONE AND ENTERED this 3rd day of May, 1993, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of May, 1993.
Findings Of Fact The Petitioner and his father own and operate the Hiland Park Laundry, a laundromat located at 2431 Highway 231, Panama City, Florida. The Petitioner purchased the business in 1975 and has operated continuously since that time. Wastewater from the laundry, as well as a trailer on the property, passes through a "trickling filter" wastewater treatment facility consisting of primary and secondary settling tanks as well as a trickling filter, thus discharging the treated effluent into a drainage ditch adjacent to the Petitioner's property line, from which drainage ditch the effluent is discharged into Beatty Bayou, a Class III water of the State. The treatment plant and disposal system has been operating since the early 1970's, prior to the Petitioner's purchase of the laundromat and treatment and disposal facility. In 1980, the Petitioner applied for an operating permit for his wastewater treatment facility. Because the discharge from the facility violated the effluent limitations of Chapter 17-6, Florida Administrative Code, the Petitioner was only issued a Temporary Operating Permit on February 2, 1981, which was modified by virtue of the letter from DER on June 8, 1981. The pertinent conditions in the TOP provided that the discharge from the Petitioner's wastewater treatment system must meet the requirements of Chapter 17-6, Florida Administrative Code, as to the quality of its effluent prior to its expiration. Failure to meet that condition would result in a denial of a Permanent Operating Permit and the denial of any further TOP. The pertinent effluent limitation which the TOP (and rules) required the facility to meet was 90 percent removal of biochemical oxygen demand and suspended solids. Since the issuance of the TOP, the discharge from the plant has seldom met those standards. Upon applying for the TOP, which is the subject of this proceeding, the Petitioner failed to present any concrete plans for improving the quality of the effluent from his plant. He merely stated his acknowledgment that, although the system does not comply with current DER requirements, that it will be dismantled upon the Bay County Regional Sewage Treatment and Disposal System becoming available at his location. It is not established, however, that there are any current plans to extend public sewer service to the vicinity of the Petitioner's property at the present time. (DER Exhibit 9) Upon the issuance of the Notice of Intent to Deny the request for the TOP, the Petitioner requested a formal proceeding and the cause was set for hearing before the undersigned on September 24, 1982. At the time of the hearing, the parties agreed on the record to a continuance on the basis that the Petitioner would submit within 60 days a plan certified by an appropriate engineer for a design to bring the discharge effluent into compliance with the effluent parameters of Chapter 17-6, Florida Administrative Code. It was suggested at that time to the Petitioner that his plant and system might comply with the permit exemption contained in Rule 17-4.60, Florida Administrative Code, which provides that such plants are exempt from permitting requirements if they incorporate a trickling filter, a sand filter, as well as a drain field. The Petitioner elected to avoid purchasing a sand filter unit inasmuch as a civil engineer he consulted informed him that the purchase and installation price for such a unit would be approximately $17,000.00, with the attendant drain field estimated to cost an additional $13,000.00. It was established contrarily however that because of the actual peak and average flows of the plant which equate to a daily hydraulic loading on the proposed sand filter of 7,000 gallons per day and 6,000 gallons per day, respectively, that a much smaller sand filter would be required, at a much reduced price. Thus, it was established that a figure of $9,000.00 to $10,000.00 would be the appropriate cost of installing the sand filter which would exempt the facility from the permitting requirements. The concrete slab proposed to be used by the Petitioner's engineer at a cost of in excess of $4,000.00 would not be necessary with a properly designed sand filter with underdrains and grated gravel courses. Based upon his own engineer's estimate of approximately $30,000.00 for the required upgrading, the Petitioner informed the Department that he was not able to underwrite such a high expense and would prefer to find some other solution to the problem. As of the date of the hearing, the Petitioner still was desirous of the Department conferring with him to find a less expensive solution to the problem, but failed to adduce any evidence to establish that such a less expensive solution (less than the solution proposed by the Department) existed. During the period the case was held in abeyance for 60 days after the scheduling of the first hearing in September, 1982, during which time the parties had agreed to seek a solution to the problem involving denial of the permit application, and thereafter until the subject hearing, the Petitioner made no substantial efforts to confer with the personnel of DER and attempt to arrive at a feasible solution to the treatment and disposal problem upon which the denial of the permit application was based. Carol Daugherty is a chemist whose firm supplies the Department with the Petitioner's monthly operating reports, and obtains samples of effluent upon which those reports are based. She performs the testing on the samples from the plant's effluent discharge and engages somewhat in operation of the plant. The Petitioner's discharge has consistently failed to comply with the BOD and total suspended solids effluent limitations listed in Rule 17-6.060, Florida Administrative Code, providing for 90 percent removal of those effluent constituents. William Young, accepted expert witness in the field of biology and water quality assessment, visited the site in February, 1982, and in April, 1983, taking water quality samples from a drainage ditch both upstream and downstream of the Petitioner's discharge point. Chemical analysis of the samples reveal that the Class III parameter for bacteriological quality (coliform bacteria) was violated downstream of the discharge point. An imbalance existed in the bayou in natural populations of aquatic flora and fauna establishing there to be violation of permissible nutrient levels in terms of the excessive deposition of nutrients from the Petitioner's plant into the drainage ditch and thence into the bayou. Mr. Pressley's facility is not the only source of discharge into the drainage ditch which discharges into the bayou, but is the primary source of discharge. Rick Bradburn also was accepted as a expert witness in the field of biology and water quality assessment. He has visited the Petitioner's facility on a number of occasions and periodically has reviewed the monthly operational reports supplied by the Petitioner. The Petitioner's effluent, on a regular basis, is characterized by excessive biochemical oxygen demand, excessive total suspended solids and excessive fecal coliform bacteria counts vis-a-vis the standards and the rules cited hereinbelow. The discharge from the Petitioner's facility thus seldom exceeds 85 percent removal of biochemical oxygen demand and suspended solids (over the past 23 months) and is characterized by excessive nutrient deposition in the Class III waters of the State. The Petitioner has known, or should have known, since shortly after February 2, 1981, when the original TOP was issued with the subject condition regarding required upgrading of the plant and disposal system, that additional upgrading would be required in order to render the effluent produced by plant less degradory. Since that time he knew, or should have known, that the failure to take steps to achieve such upgrading of the treatment and effluent disposal system would jeopardize his continued operation of his business. The Petitioner has made little effort to arrive at and submit plans to achieve a more qualitative level of effluent treatment and as of the time of the hearing had not yet submitted a reasonable compliance schedule nor any sort of commitment to construct needed additional treatment facilities, even though the parties do not dispute that the effluent produced by the plant does not meet the required standard of 90 percent removal of biochemical oxygen demand and suspended solids.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED that the application of Freddie Pressley for a Temporary Operating Permit allowing continued operation of a wastewater treatment and disposal facility in Bay County, Florida, be and the same is hereby DENIED. DONE and ENTERED this 23rd day of August, 1983, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 23rd day of August, 1983. COPIES FURNISHED: Freddie Pressley c/o Highland Park Laundry 2431 Highway 231 Panama City, Florida 32405 Dennis R. Erdley, Esquire Department of Environmental Regulation Twin Towers Office Bldg. 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Bldg. 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact The Petitioner, Phillip G. Panos, recently moved from Michigan to Florida and is now a Florida resident. On December 9, 1989, prior to moving to Florida, he applied to the Respondent, Department of Environmental Regulation for certification as a Class C domestic waste water treatment plant operator. The Respondent is an agency of the State of Florida charged, among other duties, with regulating the certification, the practice standards and the educational standards of Class C domestic waste water treatment plant operators. The Respondent agency reviewed the Petitioner's application and denied it for failure to demonstrate the requisite three years of experience required by the rule cited below. From April, 1974 to June, 1990 the Petitioner was employed at the Chapaton Pumping Station in St. Clair Shores, Macomb, Michigan. The Chapaton Pumping Station duties involved the Petitioner monitoring the distribution of sewage flows, collecting sludge samples, chlorinating the effluent and pumping it into Lake St. Clair. When the Petitioner left the Chapaton Pumping Station, in June of 1990, he held the position of Senior Station Operator II. The Chapaton Pumping Station receives a combination of storm water flow and sanitary sewage flows. It is a pumping and storm water retention facility for combined sewage. The facility provides primary treatment and disinfection for this combined sewage effluent. The effluent is chlorinated and then pumped to nearby Lake St. Clair while the solids that have settled out of the effluent are retained, collected and sent to the Detroit waste water treatment facility for advanced waste treatment. Chapaton is classified by the state of Michigan's Department of Natural Resources as an "industrial/commercial facility". The industrial classification was originated by the U.S. Environmental Protection Agency (EPA) and has been adopted as a designation or classification by both Michigan and Florida. The Petitioner holds an industrial/commercial waste water treatment certification from the state of Michigan in the category of "plain clarification and disinfection." The Petitioner's experience in Michigan is in the area of industrial waste water treatment and does not constitute actual experience in on-site operational control of a domestic waste water treatment plant (that is a sewage treatment plant). The Petitioner's experience in Michigan does not qualify as industrial waste water treatment plant experience, that could be used to meet the actual experience requirement, because the Chapaton plant performs only primary treatment and disinfection. Secondary or advanced waste treatment is performed at the Detroit waste water treatment plant, with which the Petitioner has no experience. In a typical domestic waste water treatment plant in Florida, "primary treatment" involves primary clarification or settling. Primary clarification occurs in a circular or rectangular tank where soluble solids settle out to the bottom of the tank and floating solids are removed by a skimming device. The soluble solids are called sludge. Primary clarification can remove 40% of BOD and suspended solids. It is not a form of advanced treatment or even secondary treatment. At the Chapaton plant, during primary treatment, a minimum of 70% BOD and suspended solids are removed. The sludge is not treated at the Chapaton plant but is pumped to the Detroit waste water treatment plant. Thus Chapaton could not be classified as a domestic waste water treatment plant by Florida standards, since it only provides primary clarification and no secondary or advanced waste water treatment. Secondary treatment consists of two types. Activated sludge or trickling filter treatment. Both types deal with oxygen being introduced to the sludge to achieve stabilization and more settling out of the sludge elements. Since June 18, 1990 the Petitioner has been employed as a waste water treatment plant operator I in a training program at the George L. Lohmeyer Waste water Treatment Plant in Ft. Lauderdale, Florida. In that training program the Petitioner is being trained in all phases of operation of the Lohmeyer plant. It is a 34-million-gallon-per-day (MGD) activated sludge treatment plant. In his duties, the Petitioner monitors the plant treatment processes, takes samples and submits them to the city's laboratory. The Petitioner is capable of testing the samples himself for dissolved oxygen, chlorine and ph. Reports are signed by the regional chief or the regional facilities manager. The Petitioner's present position qualifies as actual, appropriate experience in the operational control of a waste water treatment plant. The Petitioner has accumulated approximately 3-1/2 months of the 12 months of actual experience required for certification as a Class C waste water treatment plant operator, through the exercise of his duties at the Lohmeyer plant. The Petitioner must accumulate 12 months or 2,080 hours of actual experience before he can qualify for the Class C certification. The Petitioner is a high school graduate and has successfully completed Volumes I and II of the California State University correspondence course in waste water treatment, which is included on the Respondent agency's list of approved courses. Petitioner's 3-1/2 months of actual appropriate experience in Ft. Lauderdale, plus his educational background, including the courses taken in California, yield a total of 36 months or 3 years of constructive experience. Petitioner does not yet have the 12 months of actual experience required by the rules but rather, is approximately 8-1/2 months short of the actual experience requirement. Thus, the Petitioner fails to meet the experience requirement necessary for certification as a Class C domestic waste water treatment plant operator at this time, although in approximately 8-1/2 months, he should be able to meet that requirement.
Recommendation Having considered the foregoing findings of fact, conclusions of law, the evidence of record and the candor and demeanor of the witnesses, it is therefore RECOMMENDED: That a Final Order be entered by the Department of Environmental Regulation denying Petitioner's application for certification as a Class C domestic waste water treatment plant operator without prejudice to reapplication at such time as his one year of actual experience at such a treatment facility is completed. DONE and ENTERED this 11 of December, 1990, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11 day of December, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 90-479 (The Petitioner filed no proposed findings of fact.) RESPONDENT'S PROPOSED FINDINGS OF FACT 1. - 21. are accepted. COPIES FURNISHED TO: Dale H. Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esq. General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Phillip G. Panos 2315 N.W. 115 Drive Coral Springs, FL 33065 Francine M. Ffolkes, Esq. Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400
Findings Of Fact During 1990, Respondent/Applicant, City of Lynn Haven, filed several applications with the Respondent, Department of Environmental Regulation, seeking the issuance of several permits to build a wastewater collection system and a two million gallon per day advanced wastewater treatment (AWT) plant. The proposed facility is intended to replace the wastewater treatment facility currently being used by the City of Lynn Haven. After a review of the applications the Department proposed several Intents to Issue covering the different aspects of the proposed projects. The Intents to Issue included: A) a variance and dredge and fill permit, pursuant to Sections 403.201, 403.918, 403.919, Florida Statutes, and Rule 17-312, Florida Administrative Code, authorizing a subaqueous crossing of North Bay (Class II waters) and installation of a force main (permit #031716641), B) a collection system permit, pursuant to Chapter 403, Florida Statutes, and Rules 17-4, 17-600 and 17-604, Florida Administrative Code, for the installation of approximately 11 miles of pipe from North Bay to the proposed treatment plant, C) a dredge and fill permit #031785181, pursuant to Sections 403.918, 403.919, Florida Statutes, and Rules 17-4, 17-312, Florida Administrative Code, authorizing 10 incidental wetland crossings associated with the collection system, and, D) a construction permit #DC03-178814, pursuant to Chapter 403, Florida Statutes, and Rules 17-4, 17-302, 17-600 and 17-611, Florida Administrative Code, authorizing the construction of a 2.0 mgd wastewater treatment plant. Sand Hill Community Improvement Association challenged the Department's Intents to Issue. The Sand Hill Community Improvement Association (Sand Hill) is an association composed of 74 formal members plus numerous supporters. Both members and supporters are residents who live near the site of the proposed Lynn Haven sewage treatment plant. They are sufficiently close to the plant site that construction of the proposed project could impact their property. The members are very concerned about any threat of pollution to the aquifer from the proposed plant since all of the members are dependent on private wells for their drinking water. Additionally, members of the association use the proposed site, as well as the associated wetlands, Burnt Mill Creek and the nearby lakes, for a variety of recreational purposes, including hunting, fishing, hiking, bird-watching, boating and swimming. Given these facts, the Association has standing to challenge the Department's Intents to Issue involved in this case. The City of Lynn Haven is located on a peninsular section of the south shore of North Bay and, except for its connection to the land, is surrounded by environmentally sensitive Class II or Class I waters. Lynn Haven's existing wastewater treatment plant was poorly designed, has not worked properly, and is old and outdated. The plant is permitted to treat up to 950,000 gallons per day. However, the existing plant is currently exceeding its originally permitted treatment limits and is treating in excess of 1,200,000 gallons per day. The sewage only receives secondary treatment, Secondary treatment is the minimum state standard for wastewater treatment. The secondarily treated wastewater is pumped several miles to a spray irrigation site located in the eastern portion of the City. The sprayfield site has never worked properly due to a high groundwater table and a confining layer of soil, both of which prevent the effluent from percolating into the ground. Because the sewage effluent cannot percolate into the ground, the existing operation frequently results in direct runoff into a ditch which empties into North Bay, a Class II waterbody. Such discharge of wastewater effluent into Class II waters is prohibited by Department regulations. 1/ At this time, the existing wastewater treatment facility is in violation of both DER and EPA standards and is under enforcement action by both agencies. The existing facility is currently operating without a permit and the Department has advised Lynn Haven that the existing facility as it now operates can not be permitted. In fact, all the parties agree that the City is in serious need of a wastewater treatment facility which works and does not pollute the environment. However, the parties disagree over the method by which proper wastewater treatment could be accomplished by Lynn Haven. Since 1972, the City, through various consultants and with the aid of DER, has reviewed approximately 40 alternatives for wastewater disposal. After this review, the City of Lynn Haven selected the alternative which is the subject of this administrative hearing. The alternative selected by the City of Lynn Haven consists of the construction of a proposed advanced wastewater treatment (AWT) plant and distribution system. The new plant will be on a 640 acre parcel of property located approximately 12 miles north of Lynn Haven. The location of the new plant will necessitate the rerouting of the wastewater from the old plant to the new plant by construction of a new transmission line approximately 12 miles north of the City across North Bay and parallel along State Road 77. 2/ The treatment process proposed for use in the new AWT plant is known as the AO2 process. The process is patented. The AO2 treatment process primarily consists of biological treatment with settling and filtration. The treatment process also includes a chemical backup treatment to further reduce phosphorus if necessary. The evidence demonstrated that this type of facility has been permitted by the Department in at least five other wastewater facilities throughout the state. The treatment facility will have a two million gallon per day, lined holding pond on site for the purposes of holding improperly treated wastewater for recirculation through the proposed facility. Any excess sludge generated by this treatment process would be routed to lined, vacuum-assisted, sludge drying beds. The sludge would then be transported offsite to a permitted landfill for disposal. The evidence demonstrated that this treatment process would not produce any objectionable odors. Once the wastewater is treated, it will be disinfected by chlorination to eliminate pathogens. The chlorination process is expected to meet state standards. After chlorination, a dechlorination process would occur to remove any chlorine residuals which would have a harmful affect on the environment. The treated wastewater would then be re-aerated and discharged through the distribution system indirectly into a wetland located on the 640 acre parcel of property. The quality of the treated wastewater is expected to meet the advanced wastewater treatment (AWT) standards. These standards are five milligrams per liter total suspended solids (T.S.S.), five milligrams per liter BOD, three milligrams per liter nitrogen (N), one milligram per liter phophorus (P). Ph will be in the range of six to eight units on an average annual basis and can be adjusted up or down if necessary to meet the ph levels of the ecology into which the wastewater ultimately flows. This effluent quality is approximately five times cleaner than secondarily treated effluent. Additionally, as a condition of the draft permit, the proposed facility would be operated by a state-licensed operator and would be routinely monitored to insure that the treated wastewater effluent meets advanced wastewater treatment standards. Given these facts, the evidence demonstrated that the applicant has supplied reasonable assurances that the plant will perform as represented and that the effluent will meet the state standards for advanced wastewater treatment. As indicated earlier, the site for the proposed AWT plant contains approximately 640 acres and is located approximately 12 miles north of Lynn Haven in an area known locally as the Sand Hills. The City specifically purchased this parcel of property for the construction of the proposed wastewater treatment plant. The plant itself would be located in the northeast corner of the property. The 640 acre site was previously used for silviculture. The entire area is currently planted in pines except for a low area that is dominated by a pristine, woody wetland system of titi. The titi wetland is approximately 212 acres in size and generally runs through the center of the property from the northeast to the southwest. The wetland is low in acidity, with an estimated ph between 4 and 5. The site consists of hilly, mineralized soils. The soils within the forested wetland are organic in nature. Based on the evidence at the hearing, there does not appear to be any significant confining layers of soil which would prevent the treated wastewater from percolating in the soils and draining towards the wetland and ultimately into Burnt Mill Creek, a Class III waterbody. Once the effluent leaves the plant, it would go through a distribution system. The proposed distribution system will consist of six, 500 foot long, 12 inch diameter perforated pipes. Each 500 foot section of pipe has 100 one and one-half inch orifices which will discharge the treated effluent onto an eight foot wide concrete pad. This concrete pad will dissipate the effluent's energy, prevent erosion at the orifice site and insure that the effluent sheetflows onto and eventually into the sandy soils of the plant site and ultimately into the receiving wetland. The distribution pipes are located around the east, north and western portions of the receiving wetland and are variously set back from the receiving wetland approximately 80 to 200 feet. The distribution system is designed with valves to allow for routing of flow to different branches of the system if it is determined through long term monitoring that there is a need to allow for any of the receiving wetland to dry out. None of the distribution branches are located in any jurisdictional wetlands of the State of Florida. The receiving wetland will receive a hydraulic loading rate of approximately 1.8 inches per week once the new advanced wastewater treatment plant is operating at capacity. Both the surface waters and groundwaters on the 640 acre parcel flow from northeast to southwest across the property. The evidence clearly demonstrated that any treated wastewater discharged on the site would move down hill by surface or groundwater flows towards the wetlands in the central portion of the property and eventually discharge into Burnt Mill Creek located at the southwest corner of the parcel. The evidence demonstrated that it would be highly unlikely for the surface or groundwater to move in any other direction and would be unlikely for the surface or groundwater to move towards any residents located to the north or east of this parcel. Evidence of the topography and its relatively sharp gradient clearly demonstrated that the treated wastewater discharged in the northeast corner of this site would not result in any significant still water ponding and would exit the site at the southwest corner of the property in approximately 14 hours. The evidence did demonstrate that, depending on the wetness of the weather, there may likely be certain times of the year when a flowing type of ponding would occur. However, this wet weather ponding was not shown to be of a duration which would impact to a significant degree on the flora and fauna of the area or increase the number of disease bearing mosquitoes in the area. As indicated earlier the treated effluent from the proposed AWT plant will flow into Burnt Mill Creek. Burnt Mill Creek will ultimately carry the treated wastewater approximately 11 miles down stream to North Bay. The City can directly discharge up to two million gallons per day of AWT water into Burnt Mill Creek without violating state water quality standards. Therefore, the volume of wastewater discharged into Burnt Mill Creek should not have significant impacts on surface and ground water quality. Moreover, Chapter 17-611, Florida Administrative Code, authorizes the discharge of up to 2 inches per week to receiving wetlands provided wastewater is treated to AWT standards. The evidence demonstrated that this rule was developed as an experimental effort to determine if wetlands could be appropriate areas for wastewater effluent to be either discharged or treated. These state limits were intended to be very conservative limits and were designed to insure that the impacts to receiving wetlands would be minimal. The evidence and testimony demonstrated that the receiving wetland system involved in this case should not be adversely impacted beyond those limits set forth in Section 17-611.500, Florida Administrative Code, for flora, fauna, macroinvertebrates, fish or vegetation and will meet all standards set forth in Chapter 17-611, Florida Administrative Code. However, it should be noted that the wetland/wastewater program is highly experimental and very little is known about the actual impacts of wetland/wastewater systems since facilities similar to the one proposed by Lynn Haven have not yet been placed in service. The evidence did show that there would be some long term impacts to flora and fauna in the wetland area primarily due to ponding, changed ph and the introduction of nutrients and pollution in the form of the effluent. However, the regulation does allow for some change within a receiving wetland and the evidence did not demonstrate that these changes would be significant or detrimental. Petitioners' own witness concluded that other deep wetland treatment systems are doing a very good job in meeting state water quality standards. Although Petitioners' expert noted potentially adverse impacts to flora and fauna from other wastewater treatment systems, these other systems were slow moving, impoundment-type systems that are not similar to the wastewater/wetlands system proposed by the City of Lynn Haven. The Lynn Haven system is designed for percolation and sheetflow, not ponding. Though there should be some expected changes, no evidence was provided that the receiving wetlands for the Lynn Haven facility would be affected to the extent there would be violations of any standard as set forth in Chapter 17-611, Florida Administrative Code. In essence, the legislature has determined that such experimentation with wetland areas is appropriate, albeit, even with the conservative limits of DER's rule, may prove to be a mistake. This facility is designed to fit within that rule and in fact is probably the best technology available for use in a wetland/wastewater situation. Finally, in order to avoid any potential impacts on the area which may over time become significant an approved monitoring program for surface water quality and affects on flora and fauna, as well as a groundwater monitoring program are required as conditions of the permit. The groundwater monitoring program has been designed to monitor any potential long term impacts to groundwater. With these protections there should not be any significant adverse impacts to surface or groundwater quality and the applicant is entitled to a construction permit for the AWT plant and distribution system. Lynn Haven's sewage would reach the proposed AWT plant through a transmission line. The transmission line would run from Lynn Haven's existing wastewater treatment plant across North Bay and through the unincorporated area of South Port. The Southport area is not sewered and utilizes individual septic tanks for its sewage. The transmission line would be constructed entirely in state road right-of-way. The line would terminate at the 640 acre site described above. A new, variable speed pumping station would be constructed adjacent to the old wastewater treatment plant. From this pump station, a 24 inch line would be constructed on City right-of-way up to the south shore of North Bay. At this point, the transmission line would be reduced in size to 20 inches and would be embedded approximately three feet below the Bay bottom. An additional variable speed pumping station would be located approximately half way along the 12 mile route of the transmission line to insure adequate pressure to pump wastewater to the new wastewater treatment plant. The pumps are to be employed to insure that the wastewater is continuously pumped uphill to the new site so that waste does not set, become septic, and create odor problems. The pumps are equipped to provide for chemical control of odor if necessary. Also, as a condition of the permit, the pumping stations are required to have backup power supplies should power be lost to the stations. The pumping stations and backup power supplies are to be tested monthly and the pumps are required to be continuously monitored by radio telemetry to insure they are operating properly. Additionally, the City of Lynn Haven will be required, as a condition of the permit, to visually inspect the entire length of the wastewater transmission line three times per day. The portion of the transmission line which would cross North Bay is approximately 3000 feet in length and would be constructed of high density polyethylene pipe (HDPE) with a wall thickness of one and one-half inches. HDPE pipe is used to transport materials such as hazardous wastes where leakage is not permissible. This type of pipe is virtually inert in that it is highly resistant to corrosion and other chemical reactions. It is also impact resistant and has a very high tensile strength. The pipe comes in 40 foot segments and is heat welded (fused) together. This type of joint significantly reduces the chance of any leakage. In fact, leakage around pipe joints is more likely to occur with other types of pipe and pipe connections. HDPE pipe is currently carrying wastewater across Watson Bayou in Bay County, Florida. 3/ There have been no reported problems with leaks or breaks occurring in the pipe crossing Watson Bayou. Given these facts, the probability of the proposed HDPE pipe leaking or breaking is extremely low, albeit not impossible, and such pipe appears to be the best material available for constructing a wastewater treatment transmission line across protected waters of the State. As a condition of the construction permit, the portion of the transmission line crossing North Bay will be required to have isolation valves at each end so that the pipe may be completely isolated in the event that it needs repair. The underwater portion of the line would be visually inspected by a diver twice per year and the line would be pressure tested before being placed into service. Additionally, pressure tests would be performed once a year. The construction permit also requires Lynn Haven to periodically inject dye into the proposed transmission line to check for any small leaks that may not otherwise be detected. Finally, the HDPE pipe would also be equipped so that television cameras could be inserted into the pipe to routinely inspect the interior of the pipe. In the event the HDPE portion of the transmission line would need to be repaired, the line could be immediately, temporarily repaired by a dresser coupling. A permanent repair could then be made in less than 24 hours once the material and equipment were staged at the site. The City intends to locally stockpile all necessary parts and equipment to effect any required repair to prevent any delay beyond four days. Permanent repairs would be accomplished by floating the line to the surface. The area needing repair would be cut out and a new section would be put in place by heat fusion. The line would then be pressure tested to insure the absence of leaks and placed back into service. During this process, the line would be taken out of service by the isolation valves and flow would be diverted to the eight million gallon holding ponds at the City of Lynn Haven's existing facility. These holding ponds can hold four days worth of wastewater from the City of Lynn Haven. Lynn Haven is required, as a condition of the construction permit, to have this reserve capacity as well as have a contractor on standby to make any repairs in the event such repairs are necessary. All of the technical specifications for the transmission system and the operating conditions imposed on it are designed to insure that the system does not fail or develop any leaks which could impact receiving waters, including North Bay. Given the permit conditions, the required inspections for leaks, the sound engineering design and quick repair methods proposed, the evidence demonstrated that the probability of any leak occurring in the portion of the transmission line crossing North Bay is extremely low and that if such a leak does occur any potential harm to the environment will likely be limited and quickly eliminated. The evidence demonstrated that the design of the transmission line and permit conditions provide reasonable assurances that the transmission line will meet or exceed the Department standards set forth in Chapter 17-604, Florida Administrative Code. Therefore, the applicant has provided reasonable assurances that the transmission line/collection system will not violate Department standards or rules and the applicant is entitled to a permit (permit #CS03-178910) for the proposed collection system. In addition to requiring a construction permit/collection system permit for the wastewater transmission line, the line will also require dredge and fill permits and a variance for crossing waters of the state. There are ten incidental crossings of state waters and one major crossing o f North Bay. Of the ten incidental crossings, two are over small creeks (Scurlock and Little Burnt Mill) These two incidental creek crossings will be accomplished by placing the transmission line (ductile iron pipe) on top of pilings placed in the water. Best management practices such as turbidity curtains and other erosion control practices are proposed and required by the permit to minimize construction impacts on water quality. The only impacts to wetland resources would be from the placement of the pilings. The evidence demonstrated that any impact would be minimal and not significant. The evidence did not demonstrate that the aerial crossings would have any long term water quality or environmental impacts. The remaining eight incidental crossings of waters of the state consist of small, seasonally wet ditches which would be traversed by trenching and burying the transmission line. Again, turbidity controls such as curtains and hay bales would be employed to protect water quality. The evidence did not demonstrate that any significant long term or short term impacts to resources of the state would occur. The evidence did demonstrate that the applicant has provided reasonable assurances that water quality standards would not be violated in regards to these 10 incidental water crossings. Likewise, the evidence demonstrated that the construction of these 10 incidental water crossings would not be contrary to the public interest. Therefore, the applicant is entitled to issuance of a dredge and fill permit (permit #031785181) for these 10 water crossing. However, a much harder question arises in relation to the dredge and fill permit and the variance required for the 3,000 foot segment of the wastewater transmission line which crosses North Bay. Pursuant to Rule 17- 312.080(7), Florida Administrative Code, permits for dredging and filling activity directly in Class II waters which are approved for shellfish harvesting by the Department of Natural Resources (DNR) shall not be issued. The reason for the rule is that any pollution caused by dredging and filling and, as in this case, the permanent placement of a sewage pipe in food producing waters could potentially have catastrophic effects on more than just the environment but on local employment in the shellfish industry and the quality of food available to the State. Put simply, the Department has determined by enacting its Rule that the public interest in food producing waters far outweighs any other consideration or criteria under Sections 403.918 and 403.919, Florida Statutes, in determining whether dredging and filling should take place in Class II, shellfish waters. In other words, it is not in the best interest of the public to allow dredging and filling so that a pipe carrying raw sewage can be placed in shellfishing waters. However, irrespective of this determination, the Department believes that, pursuant to Section 403.201(1)(c), Florida Statutes, it may grant a variance from its rules to relieve a hardship. As indicated earlier, North Bay is a Class II waterbody, conditionally approved for shellfishing. North Bay, therefore, falls within the Rule's prohibition against dredging and filling in Class II waters and the City is required to demonstrate the presence of a hardship in order to vary the Rule prohibition and obtain a dredge and fill permit for the North Bay crossing. On issues involving variances, the Department employs a two step analysis. The first part of the analysis is whether a hardship is present and the second is whether, if the variance were granted, would it result in permanent closure of Class II shellfish waters. The Department correctly recognizes that the question of whether a hardship exists is a question of fact and is determined on a case-by-case basis. Surprisingly, in a kind of "what we don't know can't hurt" posture the Department reviews a request for a variance standing alone based on the application as it is presented and does not require analyses of other possible alternatives to the granting of a variance. However, the existence of any alternatives, costs of any alternatives, timeliness of any alternatives, problems with any alternatives, whether an alternative represents a short term or long term solution to a given problem and the implementability of any of the alternatives are all factors utilized by the Department in determining whether or not to grant a variance. The Department's policy of non- review makes no sense, either factually or statutorily, when the Department is faced with varying a prohibition it created in its own rules. Similarly, the Department's policy of not requiring other alternatives to be examined before granting a variance goes against the fact that an applicant has the burden to establish entitlement to a permit and, in the case of a hardship variance, that a hardship exists because reasonable alternatives to granting a variance are not available. 4/ Likewise, the second part of the Department's hardship analysis relating to the permanent closure of shellfishing waters makes no sense given the fact that a non-permanent closure of shellfishing waters may have the same or just as serious effect on employment in the shellfishing industry, the loss of income due to an inability to earn a living in that industry and health risks posed by contaminated seafood. Temporary loss of income or a livelihood can, for all practical purposes, have consequences to the persons directly affected by a temporary closure of shellfishing waters similar in nature those caused by the permanent closure of shellfishing waters. The same can be said for health risks posed by a contaminated food supply. Rule 17-312.080(7), Florida Administrative Code, does not contain any exceptions for the temporary closure of shellfish waters. Nor is the rule limited to instances of permanent closure. Permanent closure is simpy not required in order to support a hardship under Section 403.201, Florida Statutes. Moreover, neither step in the Department's two-step analysis is included in any Rule promulgated by the Department. 5/ Without such a Rule, it is incumbent upon the Department or the applicant to demonstrate the underpinnings for this non-rule policy. No such evidence was presented at the hearing. In fact, the evidence presented at the hearing affirmatively demonstrated that the Department's non-rule policy violated both its own rules and the statute under which it is trying to proceed. As indicated, the issue of hardship is a question of fact and involves a weighing of all the facts and cicumstances involved in this project. In this case, there are shellfishing areas located close to the proposed location of the transmission line. North Bay is sometimes closed to shellfish harvesting by the Department of Natural Resources. These closures generally occur during wet weather conditions and are due to stormwater runoff and the failure of septic tanks in Southport. 6/ Additionally the current Lynn Haven system also contributes to the closure of North Bay. No competent, substantial evidence was provided that issuance of the permit and variance would result in the permanent closure of shellfish waters. The location of the proposed transmission line would be several hundred feet west of the Bailey Bridge embedded in the Bay floor. 7/ The proposed alignment of the transmission line through North Bay is in an area which is relatively biologically unproductive. The proposed placement of the transmission line avoids the few grassbeds that exist in the nearshore shallow areas except for approximately 200 square feet of grass. During construction of the line, these grasses would be removed immediately before the line is placed in a trench and then would be promptly replanted in the same area. The evidence demonstrated that the affected areas of grass should be able to reestablish itself. The evidence further demonstrated that there would not be any long term adverse impacts to these aquatic resources and there should not be any significant long term impacts on the balance of any aquatic life which may exist on the bay bottom. Water quality during construction will be protected by use of turbidity controls to control sediments. Therefore, any short term impacts on aquatic resources are likely to be insignificant. Concerns about long term adverse impacts to Class II waters are greatly reduced by the type of pipe and conditions in the permit which require that the transmission line be routinely inspected and tested to insure that there is no leakage and that in the unlikely event the line should need to be repaired, the line could be easily isolated and quickly repaired. The evidence showed that, to completely avoid Class II waters, the line could be moved several miles to the west or east of the line's proposed location or be placed over or under the Bay. If the line was moved west to the extent that it was in Class III waters, it would be over 40 miles long and would more than double the cost of the project. If the line was moved several miles to the east, it would go through the Deer Point Lake Watershed. The watershed is a Class I water supply for Bay County. Clearly, moving the line either west or east is not practical nor realistically feasible. Tunneling under North Bay would be very risky and is not technically feasible. The length of the tunnel would require steel pipe to be used. If tunneling could be done at all steel pipe would not provide the level of protection afforded by the HDPE pipe proposed by Lynn Haven. Placing the transmission line on pilings for an aerial route over North Bay is uneconomical and would create a potential hazard to navigation. Moreover, an aerial crossing would not solve any pollution problems should the transmission line leak or break and would also still involve a variance request since it would be necessary to dredge and fill in Class II waters for the placement of pilings or supports. Put simply, the evidence, showed that there was no realistic way to avoid Class II waters in North Bay given the location of the proposed wastewater treatment facility. A location which the City knew would require a hardship variance from the rule prohibition of dredging and filling in Class II, shellfishing waters. A hardship which the City created by site selection and which it hoped to overcome by strenuous permit conditions and futuristic speculative benefits to unsewered areas of the County. The existing treatment facility is operating in violation of both EPA and DER requirements, has been issued a notice of violation, is nonpermitted and is destined to be operating under a consent order. The system is hydraulically overloaded, handling approximately 1.2 million gallons per day while its rated capacity is 950,000 gallons per day. Refurbishing Lynn Haven's existing wastewater treatment facility would not be viable since the plant has outlived its useful life, is of a very poor design and probably could not be made to function within Departmental standards and water quality standards. The existing sprayfield does not function and results in overland flow of effluent which discharges to Class II waters. The high water table and presence of a semiconfining layer on the Lynn Haven peninsula virtually guarantee such discharges. Further, the plant only provides secondary treatment. Put simply, Lynn Haven needs another method of handling its sewage. The only remaining alternative to a Bay crossing is to tie into the existing Bay County system and any AWT wastewater treatment plant Bay County may build in the future. 8/ The existing Bay County system provides at most only secondary treatment. The Cherry Street facility, which is part of that system, functions essentially as a lift station rather than a treatment facility. The Military Point Lagoon portion of the system is nonpermitted and is operating under a consent order and has been the subject of enforcement action. The Department has an extensive agreement with Bay County requiring a significant and long term series of actions to deal with their wastewater treatment system. The modifications or improvements to the Bay County system to provide advanced treatment are not imminent and the final system conditions cannot now be determined as they will depend in large measure upon data and analysis remaining to be collected. Currently, the existing Bay County system processes a significant amount of industrial discharge and has a problem with phenols most likely due to industrial waste from two discreet industrial facilities in the County. 9/ However, all of Bay County's wastewater system problems are reasonably solvable and will be corrected in the near future, if they have not already been corrected. Additionally, the amount of sewage Lynn Haven would be sending into the current Bay County system probably would not significantly impact that system and its problems or the County's ability to solve those problems. The County is willing to accept Lynn Haven's sewage into its system and future AWT system. The connection into Bay County's system is a viable alternative currently in existence. Moreover, as indicated, Bay County has a long range plan to build an advanced wastewater treatment plant. As yet the plan remains "just a twinkle in the County's eye" and has not progressed to the design stage. However, this plan, of necessity, will eventually become reality in the next 5 to 10 years. The estimated cost to a Lynn Haven user for the Bay County conceptual system will be $25.00 per month in lieu of $15.00 for the proposed Lynn Haven system. These estimates are at best speculative. However, this cost estimate is not excessive given the fact that a Lynn Haven user lives in an environmentally sensitive area and a Bay County hook-up would eliminate the need to run a sewer pipe through food producing, Class II waters. 10/ Based on these facts, the evidence demonstrated that it was feasible for Lynn Haven to hook into Bay County's wastewater system without creating any more environmental impacts than that system is already experiencing and must solve and which, to a significant degree, have already been solved by Bay County. Given the existence of this alternative to crossing food producing waters and the fact that any future benefits are just as likely to be provided just as quickly by the County through AWT facilities, the applicant has failed to demonstrate the necessity for crossing North Bay and failed to demonstrate entitlement to a hardship variance for that crossing. Therefore, the applicant is not entitled to either a dredge and fill permit or variance for the proposed North Bay crossing.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is, recommended that the Florida Department of Environmental Regulation enter a final order issuing permit applications CS03178910, DC03178814, and 031785181, and denying the variance and permit number 031716641. RECOMMENDED this 27th day of November, 1991, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of November, 1991.
The Issue Whether the Petitioner's request for variance should be granted.
Findings Of Fact Petitioner owns a parcel of land in Palm Beach, County on which is housed Petitioner's paving and landscapping business and which is zoned for industrial use. Petitioner intends to install a manufactured building for use as an office. To provide sewage treatment for the bathroom of the office, Petitioner had a septic tank designed and applied for a septic tank permit which was denied as was its variance request. As a result of a complaint, Petitioner was inspected in August, 1988, by the Palm Beach County Department of Environmental Resources Management and by the Florida Department of Environmental Regulation. Both inspections yielded citiations for soil contamination by oil and other hazardous waste. Petitioner represented that most of the infractions had been rectified by the date of the hearing in this matter and pledged full cooperation with the County and State rules. To oversee the operation of the business and assure that no further problems arose, Petitioner decided to establish its office on site. The closest sewage treatment plant is at full capacity and does not intend to provide service to the parcel in the near future. The adjoining properties are serviced by septic tanks. As such, the proof did not demonstrate that alternative methods of waste disposal were available to the site However, as part of its business operation, Petitioner does minor repair of its equipment on site and may include oil changes and other such services. Although Petitioner does not intend to pollute the groundwater and intends to use the proposed septic tank for office use only, the proof demonstrated that waste disposal into a septic tank from the maintenance and repair of its equipment could result in the disposition of prohibited hazardous waste into the groundwater. Further, the proof failed to demonstrate that the septic tank would be protected from use by those who handled the hazardous waste. Although the hardship, if any, caused by the denial of the variance was not caused by Petitioner and the proof failed to demonstrate reasonable alternatives of waste disposal, the potential for an adverse affect of the operation to the groundwater is great. Additionally, the proof failed to establish the ameliorating conditions of soil, water table or setback conditions or whether the property was platted prior to 1972. Accordingly, the denial of the variance was proper.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered denying the variance. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 6th day of July 1989. JANE C. HAYMAN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of July 1989. COPIES FURNISHED: Hattie Parker 160 Toneypenna Drive Jupiter, Florida 33468 Peggy G. Miller, Esquire Department of Health and Rehabilitative Services 111 Georgia Avenue Third Floor West Palm Beach, Florida 33401 Sam Power, Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Miller General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
Findings Of Fact Petitioner owns an undeveloped parcel of land in Palm Beach, County which is zoned industrial and on which he intends to construct a storage building to house and repair farm equipment. To provide sewage treatment at the site, Petitioner had designed an on site sewage disposal system and applied for a septic tank permit which was denied as was his variance request. The closest public sewage treatment plant to the property is over five miles from the site, and the closest private treatment is approximately three miles from the subject site. Petitioner has no easement to either site if capacity were available and if he chose to connect. However, the proof did not show capacity at either site. Although Petitioner does not intend to pollute the groundwater, the proof demonstrated that waste disposal into a septic tank from the maintenance and repair of farm equipment could result in the disposition of prohibited hazardous waste into the groundwater. Alternative methods of waste disposal are available which would properly dispose of the waste and, yet, protect the groundwater from contamination by hazardous waste. Such systems include certain aerobic treatment units and package plants. The monetary costs of these systems is greater than the septic tank proposal; however, the proof did not demonstrate that the cost was prohibitive or a hardship. Although the hardship, if any, caused by the denial of the variance was not caused by Petitioner, the proof failed to demonstrate lack of reasonable alternatives of waste disposal and the absence of adverse effect of the operation to the groundwater. Additionally, the proof failed to establish the ameliorating conditions of soil, water table or setback conditions although a survey of the property dated September 3, 1985, indicates that the subject parcel was not platted. Accordingly, the denial of the variance was proper.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered denying the variance. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 6th day of July 1989. JANE C. HAYMAN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of July 1989. COPIES FURNISHED: Lee B. Sayler, Esquire 50 South U.S. Highway One Suite 303 Jupiter, Florida 33477 Peggy G. Miller, Esquire Department of Health and Rehabilitative Services 111 Georgia Avenue Third Floor West Palm Beach, Florida 33401 Sam Power, Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Miller General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700