Findings Of Fact Respondent has been a registered roofing contractor at all times material hereto. His license number is RC-0035594. On or about April 26, 1985 Respondent, doing business as Pinellas Roofing Service, contracted with Bausch and Lomb to reroof their plant in Manatee County, at a contract price of $31,150. Respondent admits that at no time material hereto was he licensed to engage in contracting in Manatee County. Pinellas Roofing thereafter began, and partially performed, this job for which it was paid a total of $28,035. Petitioner alleges, and Respondent denies, that Respondent diverted funds received from this job for other purposes, and was thereafter unable to fulfill the terms of the contract with Bausch and Lomb. Petitioner did not present competent substantial evidence in support of this charge. Respondent never completed this job and took no steps to inform Bausch and Lomb that he would not complete the contract or make other arrangements for its completion. He left several thousand dollars worth of material on the roof, exposed, when he walked off this job, and this resulted in these materials being substantially destroyed. During the job, he did not take precautions to assure that the roof did not leak during heavy rainstorms. In fact, on at least three occasions, leaks caused damage to the interior of the plant and Respondent could not be reached. Therefore, Bausch and Lomb had to have another roofing contractor make emergency repairs on June 25, July 15 and September 3, 1985, at a total additional cost of $4,150. Since Respondent did not complete the contract, and left the roof unfinished, Bausch and Lomb contracted on September 17, 1985 with Bernard J. Lozon, Inc., to complete the job, and make certain additional repairs, at a cost of $24,000. In the opinion of Bernard J. Lozon, who was accepted as an expert in roofing contracting, the actual work that was done by Pinellas Roofing was satisfactory. However, Respondent's actions in walking off the job and leaving the roof unattended without completing the job is an unacceptable practice in roofing contracting, and constitutes incompetence and misconduct. Respondent failed to properly supervise this job. He relied upon his son to hire the necessary crews, pay them, handle financial aspects of the job, and assure its completion. His testimony indicates he fails to understand his own responsibility for supervising and completing the work for which he contracted, and which was performed under his license. At no time material hereto did Respondent qualify Pinellas Roofing Service with Petitioner. Respondent failed to apply for and obtain a Manatee County building permit for the roofing job in question, and also failed to request the county building department to perform inspections of the work performed. The Board of County Commissioners of Manatee County has adopted and follows the 1979 edition of the Standard for Installation of Roof Coverings, Southern Building Code, as amended in 1981. This Code requires all contractors performing work in Manatee County to be registered in Manatee County, and to obtain permits for all roof replacements and repairs in excess of $200, as well as obtain inspections of all such work to insure compliance with the Code. Respondent failed to comply with these requirements of the local building code. When Respondent submitted his proposal on April 16, 1985 for the Bausch and Lomb job, he specifically acknowledged, in writing, that "all work (is) to be done according to owner specifications sheet." (Emphasis supplied). At hearing, Respondent contended that when he submitted his proposal he never saw the project specification sheet which was thereafter attached to his contract with Bausch and Lomb and made a part thereof. Rather, he testified that his proposal referred to certain specifications that appeared on project drawings which he reviewed prior to submitting his proposal. After considering the demeanor of the witnesses and all of the evidence presented, and particularly the fact that Respondent referred to the "specifications sheet" and not "drawings" in his proposal, it is specifically found that Respondent had knowledge of, and did in fact submit his proposal based upon the "specifications sheet" which ultimately became a part of his contract. As such, he was bound thereby in the performance of work under this contract. In pertinent part, the "specifications sheet" requires that the contractor obtain all necessary permits from Manatee County, that notice be given to the owner in advance of work that will produce excessive amounts of dust or tar fumes so proper precautions could be taken, that roofing materials be stored in a manner that protects them from damage or adverse weather conditions during construction, and that the contractor provide a two year written guarantee at the conclusion of the job. Respondent failed to comply with these requirements of the specifications.
Recommendation Based upon the foregoing, it is recommended that Petitioner enter a Final Order suspending Respondent's registration for a period of ninety (90) days and imposing an administrative fine in the amount of $1,500. DONE AND ENTERED this 22nd day of April, 1987 in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-3698 Rulings on Petitioner's Proposed Findings of Fact: Adopted in Finding of Fact 1. Adopted in Finding of Fact 8. 3,4 Adopted in Finding of Fact 2. 5,6 Adopted in Finding of Fact 3, but otherwise rejected as irrelevant and unnecessary. 7,8 Adopted in Finding of Fact 9. Adopted in Finding of Fact 6. Adopted in Findings of Fact 5, 6. Rulings on Respondent's Proposed Findings of Fact: Adopted in part in Findings of Fact 3, 5. Rejected as not based upon competent substantial evidence. Adopted in part in Finding of Fact 3. Adopted in part in Findings of Fact 2, 3. 5-7 Addressed in Findings of Fact 2, 3 and 5. 8,9 Rejected as irrelevant and unnecessary. 10. Adopted in part in Finding of Fact 5. 11,12 Adopted in part in Finding of Fact 6. Rejected as not based upon competent substantial evidence. Adopted in Findings of Fact 5, 6. Adopted in Finding of Fact 6. COPIES FURNISHED: W. Douglas Beason, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Michael Schlesinger, Esquire 655 Ulmerton Road Building 11-A Large, Fl 33541 Fred Seely Construction Industry Licensing Board Post Office Box 2 Jacksonville, Fl 32201 Van Poole Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Joseph A. Sole, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750
The Issue Does the unsatisfied civil judgment in ABC v Millman et al, Case Number 50 2008 CA 006245 XXXX MB relate to practice of Respondent’s profession, thus establishing that Respondent, Harris M. Millman, violated section 489.129(1), Florida Statutes,(2009)? If he committed the violation, what penalty should be imposed?
Findings Of Fact The Construction Industry Licensing Board has certified Millman as a General Contractor and a Roofing Contractor under the authority of Chapter 489, Florida Statutes. In 2009 and 2010, he held license numbers CGC l1522 (General) and CCC 1327057 (Roofing). Millman’s licenses are presently inactive. Millman has actively practiced the licensed professions of general contractor and roofing contractor in Florida since 1977. The Department and its predecessor agencies have never taken any disciplinary action against him. At all times material to this proceeding, Affiliated was a Construction Qualified Business in the State of Florida, certified under Chapter 489, Florida Statutes, holding license number QB45287. Millman was the Primary Qualifying Agent for Affiliated under Chapter 489, Florida Statutes, at all times material to this proceeding. On December 26, 2005, Millman signed a credit application with American Builders and Contractors Supply Company, Inc., d/b/a ABC Supply Co. Inc. (ABC), on behalf of Affiliated. Millman listed his Certified General Contractor’s License (CGC 011522) on the credit application and personal guarantee Although Millman provided his General Contractor’s license number on the application, ABC did not require a license number. The application indicates that the account is related to “low and steep slope roofing.” The account was for the purchase of roofing materials and supplies. On December 29, 2005, Millman signed a personal guarantee of the Affiliated account with ABC. Millman’s personal guarantee made him personally liable for Affiliated’s obligation to pay ABC. ABC granted the application and opened a line of credit for Millman and Affiliated. Millman and Affiliated used the account to purchase roofing supplies on credit. They purchased and paid for over $800,000 worth of supplies from 2006 into 2009. This is separate from the goods and materials that were the subject of the lawsuit described below. Most of the materials and supplies that Affiliated purchased on the ABC account were for specific roofing projects. But some, as Millman acknowledged in his testimony, were to maintain roofing materials in the Affiliated warehouse. He used these on small jobs and to supplement materials purchased for larger, specific jobs. All the goods and materials purchased related to Millman’s practice of the roofing contracting profession. In 2007 Millman and Affiliated started having financial difficulties. Millman’s business began failing. The failure of a lender that took over a construction project it was financing resulted in the lender not paying Millman for approximately $500,000 worth of his company’s work. This contributed to Millman’s business failure. In addition to Millman’s problems paying ABC, his landlord was evicting him. Millman worked hard during these difficulties to meet his obligations to ABC. He liquidated his Individual Retirement Account and his life savings to make sure he paid for all charges for supplies used for specified customers. He did this to protect customers from the risk of liens being placed on their properties. Millman advised ABC that he was being evicted from his warehouse. He told ABC that the warehouse contained materials obtained with his line of credit that had not been paid for. Millman did not have the ability to return the materials to ABC. As eviction neared, he urged ABC to retrieve the materials before eviction. ABC did not act to retrieve the materials. The landlord evicted Millman. What happened to the materials is not known. On March 4, 2008, ABC sued Millman and Affiliated in the Circuit Court of the Fifteenth Judicial Circuit in and for Palm Beach County, Florida. ABC sought payment for goods and materials purchased on the account and delivered to Millman and Affiliated between January 31, 2007, and January 31, 2008. The court assigned the action Case Number 50 2008 CA 006245 XXXX MB. The goods and materials for which ABC sought payment were roofing goods and materials. They included roofing felt, roofing cement, shingles, plywood, lumber, roofing nails, lead sheets, insulation, roof tile cement, lead boots for pipes, roofing paint, asphalt, and galvanized roof edging. Much, although not all, of the material was delivered to roof tops. Many invoices for the material describe the roof for which the material is intended by height and pitch. The goods and materials related to Millman’s profession of roofing contractor. On June 17, 2008, barely three months after ABC filed suit, Millman entered into a Stipulation for Payment with Judgment upon Default with ABC. Millman agreed in the Stipulation for Payment with Judgment upon Default, that both he as an individual and Affiliated are indebted to ABC in the amount of $45,617.02. This amount included interest, attorney’s fees, and costs. The stipulation included a schedule of eight payments starting with a payment of $2,500.00 on May 30, 2008, and ending with a payment of $22,720.02 on December 30, 2008. Millman made payments from January 1, 2007, forward, even during and after the collection litigation. Millman made over $16,000.00 of those payments. But he did not make all of them. As Millman made payments, he took care to designate payments for supplies allocated to a specific customer and job. He did this to protect his customers from liens and to make sure that documents he signed attesting that supplies for specific jobs had been paid for were honest and correct. On August 3, 2009, the court rendered a Final Judgment After Stipulation in ABC’s collection action. The court adjudged that ABC recover $29,617.02 together with interest at the rate of 11 percent per annum accruing from May 31, 2008, from Affiliated and Millman, jointly and severally. The judgment is for debt incurred relating to Millman’s practice of his licensed profession of roofing contracting. It is not related to Millman’s licensed profession of general contracting. ABC continued to actively pursue collecting the judgment. It garnished Millman’s bank account with Bank Atlantic and obtained $662.61. Millman and Affiliated have not fully satisfied the judgment within a reasonable period of time. The Department incurred $216.00 in costs for the investigation and this action.
Recommendation Based on the foregoing Findings of Fact and Conclusion of Law, it is recommended that the Department of Business and Professional Regulation, Construction Industry Licensing Board, enter a final order finding that Respondent, Harris M. Millman, violated Section 489.129(1)(q), Florida Statutes, and imposing the following penalties: Payment of an administrative fine of $500.00 within 180 days of entry of the final order. Payment of costs of investigation and prosecution in the amount of $216.00 within 180 days of entry of the final order. DONE AND ENTERED this 27th day of August, 2010, in Tallahassee, Leon County, Florida. S JOHN D. C. NEWTON, II Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of August, 2010.
Findings Of Fact At all times material, the respondent, Howard E. Montgomery, was a licensed contractor having been issued license number CG C010122 by the State of Florida. At all times material, the respondent, Terry L. Montgomery, Howard's son, was a licensed contractor having been issued licenses numbered CB C012474 and CP C039916 by the State of Florida. On or about December 29, 1983, Mr. and Mrs. Chamberlain entered into a construction contract with Terry L. Montgomery, for Terry Montgomery Building Contractors, to build the Chamberlains a house at 6702 - 113th Avenue in Temple Terrace. The cost of construction under the contract was $62,900. At all times during the negotiation of that contract and at the time of the signing of that contract, Terry L. Montgomery represented that he had a license to build homes in the State of Florida. The contract itself states that Terry L. Mongomery is a building contractor and State-certified. In fact, at the time he negotiated and signed the Chamberlain contract, and through October, 1985, Terry Montgomery's license was inactive, not having been renewed as required. When it came time to pull a building permit on the Chamberlain job, Terry asked his father, Howard, to use the latter's license to pull the permit since Terry's license had not been renewed and was inactive. The older Montgomery agreed. On or about February 23, 1984, Howard authorized Terry to pull permits from the City of Temple Terrace in his name, and Terry pulled a permit for the Chamberlain job at 6702 - 113th Street, Temple Terrace, in Howard's name and listing Howard as the contractor. Construction proceeded without any supervision being exercised by Howard until problems developed during construction, including problems with the roof. During preparation for installation of the roof trusses, Terry did not assure that the trusses were marked so that the left side of the trusses, as manufactured, consistently was the left side of the trusses, as installed, as a contractor responsible for construction of a roof using pre-manufactured trusses should do. The trusses were supposed to be symmetrical. But, as commonly occurs during manufacture, although within manufacturing tolerances (and therefore not interfering with installation of the ridge cap), the trusses were not exactly symmetrical. Because Terry did not mark the trusses and some were installed "backwards" there roof exhibited a "rolling" or "wave" effect. Because the roof design called for a large expanse of unbroken roof surface, especially on the front half of the house, the "rolling" or "wave" effect was magnified and unacceptable. In addition, the construction drawings Terry Montgomery followed did not clearly show a support beam across the entrance area in the front of the house, as it should have to be structurally sound. The contractor had a responsibility to know that the construction, without a support beam in that location, would be insufficient and to so advise the Chamberlains. Instead, Terry ordered excessively cantilevered trusses to be manufactured for that portion of the roof and installed the trusses without a support beam. The construction was inadequate, and the roof eave sagged in that location. In addition, some of the wood decking supporting the roofing material was nailed one to another without underlying support from a truss or structure connected to a truss. In these relatively isolated locations, the wood decking sagged. In isolated places on the roof, some of the roof shingles were nailed in only three places, instead of the manufacturer's specified four, and some were nailed incorrectly or in incorrect places on the shingle, according to the manufacturer's specifications. As a result, some of the shingles began to curl and fray within months of delivery of the home to the Chamberlains. Flashing, particularly ion the area of the chimney, was not installed correctly, resulting in leaks that had to be fixed. In June and July, 1984, Howard Montgomery became involved in troubleshooting construction problems, including problems with the roof. He met with the Chamberlains, observed construction, investigated complaints on the Chamberlains' "punch-lists," including roof leaks, and assured the Chamberlains that Terry would correct the noted deficiencies to the Chamberlains' satisfaction. The construction contract provided that all work on the Chamberlains' house would be completed in a professional manner. The contract also provides for an all-inclusive one-year warranty. The closing took place on October 18, 1984. At the closing, Terry Montgomery agreed that he would honor his one-year warranty and after closing provide the Chamberlains with a chimney cap. The problems that developed with the roof during construction continued during the warranty period. The shingles began to curl and fray within six months after occupancy, the "rolling" or "wave" effect to the roof remained, and there were leaks around the chimney area and the clere story area. Beginning in November, 1984, right after they had moved in and right after the first rain, Mrs. Chamberlain tried to call Howard Montgomery at his home and former place of employment and attempted to call Terry Montgomery by leaving messages on his machine. Terry Montgomery went to the Chamberlain residence sometime in November, 1984, right after they moved into the house because, after the first rain, the leaks were obvious. When Terry Montgomery went to the residence in November, 1984, he looked at the leaks and said that he did not have the tools with him that day to fix them and that he would come back. When Terry Montgomery did not return, Mrs. Chamberlain continued to call him, and he finally returned in February, 1985, and did some caulking. In response to a May 22, 1986, letter from the Chamberlains, Terry Montgomery returned to the house sometime in August, 1986, with a hammer and caulking gun. On several occasions, Terry Montgomery indicated that he would have some professionals look at the roof, but he never did. During the conversations between Mrs. Chamberlain and Terry Montgomery, Terry Montgomery took the position that he was there just to fix the leaks, that the appearance of the roof did not have anything to do with the leaks, that the "rolling" of the roof and the shingles lifting had nothing to do with the leaks, that the truss problem did not have anything to do with the leaks, and that he was not going to fix those items. He was relying on his version of the settlement, at closing, of the dispute between him and the Chamberlains concerning the $2,500 the Chamberlains had withheld from the contract price. This dispute eventually was submitted to the state circuit court for resolution, resulting in a judgment which is now on appeal. Howard Montgomery took the position that he was not responsible for his son's work, despite having loaned his license to his son, but that he gratuitously offered to help resolve problems Terry was having during construction. He, too, was of the view that the parties had resolved their disputes at closing and that, after closing, he had no further responsibility and Terry's responsibility was to fix leaks and put on a chimney cap. In August or September, 1986, the Chamberlains attempted to get bids to repair the roof. They contacted at least four roofing contractors for bids. The roofing contractors that responded indicated that it would cost a substantial sum to correct the problems and that, even if the problems were corrected, they could not give the Chamberlains a warranty for the work. As a result of the leaks in the roof, there was damage to drywall and staining around the chimney, in the foyer area and underneath the clere story windows. Because of a defect in the construction of the roof, the wall in the interior of the house under the clere story window bows out about three degrees.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Construction Industry Licensing Board enter a final order: in Case No. 87-2662, holding Howard E. Montgomery guilty violating Section 489.129(1)(m), Florida Statutes (1987), and imposing a $1,000 fine; and in Case No. 87-2991, holding Terry L. Montgomery guilty of violating Section 489.129(1)(j) and (m), Florida Statutes (1987), reprimanding him for the violations, and imposing on him a $2,500 fine. RECOMMENDED this 7th day of September, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of September, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 87-2662, 87-2991 To comply with Section 120.59(2), Florida Statutes (1987), the following explicit rulings are made on the petitioner's proposed findings of fact (the respondents not having filed any): 1.-2. Accepted and incorporated. 3.-7. Accepted and, to the extent necessary, incorporated. 8. Accepted but outside the administrative complaints and unnecessary. 9.-11. Accepted and incorporated. 12. Unnecessary. 13.-16. Accepted and incorporated. 17. Accepted but unnecessary. 18.-19. Accepted and, to the extent necessary, incorporated. Accepted and incorporated. Rejected in part. It was not proven that either of the Montgomerys cut the trusses and left them cut. Others who later worked on the roof may have done it. Otherwise, accepted and incorporated. Rejected in part. It was proven that Terry was contacted within the warranty period but not that Howard was. Accepted and incorporated. 24.-25. Rejected in part. It was not proven that she called Howard. Accepted and incorporated as to Terry. 26.-29. Accepted and incorporated. 30.-32. Accepted. As to Howard, unnecessary. As to Terry, incorporated to the extent necessary. 33.-34. Accepted and incorporated. 35.-36. Rejected in part. Terry fixed the leaks temporarily. In time, leaks started again. Leaks resumed in September, 1986, during Hurricane Elena. Otherwise, accepted but unnecessary. 37.-41. Accepted and incorporated. 42.-43. Accepted and incorporated to the extent necessary. Accepted but subordinate to facts found. Rejected in part. The specifics of Howard's promise are reflected in the Findings of Fact. Otherwise, accepted and, to the extent necessary, incorporated. Accepted and, to the extent necessary, incorporated. Unnecessary. (It was not proven that Terry did not install a chimney cap, just that the Chamberlains had a new one put on.) Accepted but irrelevant (since it included the chimney cap and perhaps other work not directly related to Terry's work) and unnecessary. Subordinate to facts found. Subordinate and unnecessary. 51.-53. Subordinate to facts found. Irrelevant and unnecessary. Subordinate and unnecessary. Subordinate to facts found. Rejected as not proven. All spacings were 24" except one 29 1/2" and one 26 1/2". The evidence was that the Southern Building Code maximum separation is 32". 58.-59. Subordinate to facts found Accepted but unnecessary. Rejected. Accepted and incorporated. 63.-64. Subordinate and unnecessary. 65. Rejected as to Howard. As to Terry, accepted and incorporated. 66.-68. Accepted and incorporated. Subordinate to facts found. Cumulative. 71.-72. Accepted and incorporated. COPIES FURNISHED: Jack Larkin, Esquire 806 East Jackson Street Tampa, Florida 33602 Howard E. Montgomery Post Office Box 5334 Tampa, Florida 33675 Terry E. Montgomery Post Office Box 681 Brandon, Florida 33511 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
Findings Of Fact At all times relevant hereto, respondent, James S. Stroz, held registered roofing contractor license number RC 0034849 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. He was first licensed in November, 1979, and at that time qualified under the name of Stroz Roofing. A change in status application was later filed to qualify Stroz Roofing, Inc., 13696 Exotica Lane, West Palm Beach, Florida. Although licensed as a roofing contractor, respondent's firm only performs work on wood shakes or shingles. He does not do hot roofs or flat roofs, which is another speciality in the roofing business. While working for a roofing firm in1979, Stroz became acquainted with Lacy Davis, an unlicensed individual who specialized in flat roof work. When Stroz started his own roofing company in 1983, he began contracting out the flat roof work to other licensed roofing contractors. Lacy Davis learned of this and approached Stroz offering his services on the flat roof work. Stroz knew Davis was unlicensed and would not initially hire him, but Davis gave him a business card of Henry Haywood, a licensed roofing contractor in Palm Beach County and explained he and Haywood were partners and that the work and permitting would be done under Haywood's license. In actuality, Haywood had not authorized Davis to use his business cards, or topull permits under his name. Indeed, Haywood had no knowledge of Davis' activities. Without verifying the truth of Davis' representations, and accepting them instead at face value, Stroz agreed to hire Davis to perform his flat roof work. Between January 20, 1983 and September 30, 1984, Stroz performed some twenty-one jobs using Davis for the flat roof work. At all times, Stroz was under the impression that the work was being done under Haywood's license and that his activities were lawful. Stroz made all checks for the work payable to Lacy Davis or Lacy Davis Roofing. He did this because Davis told him he frequently had difficulty reaching Haywood to cash the checks, and because the business bank account was in Davis' own name. A few of the checks carried a notation at the bottom that payment was for work by Haywood Roofing, but most made no reference to Haywood. Stroz pulled all permits on their jobs reflecting that Haywood Roofing was the licensed contractor. Of the twenty invoices given by Davis to Stroz for the twenty-one jobs, only four were on invoices printed with Haywood's name. The remainder had various other names including "Lacy Davis Roofing," "Lacy Davis" and "Lacy Davis and Benny Guy Roofing Contractors." None of these were licensed as roofing contractors by petitioner. In June, 1984, a member of Davis' crew was injured and it was discovered Davis had no insurance. Stroz's insurance paid the claim, but an investigation ultimately determined that Davis was unlicensed and had no authority to act on Haywood's behalf. This led to the issuance of the administrative complaint herein. Respondent has fully cooperated with petitioner, and in fact voluntarily disclosed one job with Davis that petitioner's investigation had failed to uncover. He admits he was negligent in not checking out the representations of Davis, but he never intended to violate the law. No consumer was harmed in any way by Davis' work, and there are no complaints concerning the quality of the jobs in question.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as charged in the administrative complaint, and that he be fined $500 to be paid within thirty days from date of the final order rendered in this proceeding. DONE and ORDERED this 2nd day of July, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of July, 1985.
The Issue Whether Respondent committed the offenses set forth in the administrative complaint and, if so, the penalty which should be imposed.
Findings Of Fact At all times material to this case, the Respondent, Harry Bradshaw, was licensed as a registered roofing contractor in the State of Florida, holding license number RC 0033812. On August 26, 1986, Respondent's license as a registered roofing contractor was suspended by Petitioner. Respondent's license remained suspended at all times material to this case. On December 16, 1987, Respondent contracted with the Moose Lodge located in Hialeah, Florida, to reroof the Moose Lodge building. The proposal submitted by Respondent contained representations that Respondent was licensed as a registered roofing contractor and that he was insured. Respondent knew that his license as a registered roofing contractor was under suspension. Respondent had no insurance. The contract between Respondent and the Moose Lodge provided that Respondent would perform the work and supply the materials for the sum of $6,200.00. The sum of $3,200.00 was paid to Respondent in advance of his beginning the job. Respondent used the sums advanced to purchase materials and supplies. The remaining $3,000.00 was to have been paid upon Respondent's completion of the job. During the negotiations that resulted in the contract between Respondent and the Moose Lodge, Respondent represented that the job should be completed in time for the functions scheduled for New Year's Eve. While Respondent had purchased the materials needed for the job and had done a substantial amount of work on a portion of the roof, he was unable to complete the work by the New Year. Respondent was ordered to stop work on the job on January 26, 1988. Respondent did not abandon the job. Although he was slow in performing the work, a part of Respondent's delay in performance was caused by rain. There was no evidence as to what would have been a reasonable period of time for Respondent to have completed the job. On January 26, 1988, the administrator for the Moose Lodge complained to the Building Inspection Department for the City of Hialeah, Florida, because the administrator was not pleased with the progress that Respondent was making toward completion of the job. The administrator was told by a representative of the Building Inspection Department on January 26, 1988, that Respondent had no license and that the required permit had not been pulled. The administrator was told to prohibit Respondent from working on the roof. Immediately thereafter, the administrator instructed Respondent to do no further work on the roof. The members of the Noose Lodge completed the job started by Respondent for less than $3,000.00, the balance of the amount that would have been owed Respondent if he had finished the job. Respondent knew that a permit was required for this work. Respondent also knew that only a licensed roofing contractor could pull the required permit. Respondent proceeded with the job when he was unable to persuade a licensed roofing contractor to pull the permit for him. Petitioner filed an administrative complaint against Respondent alleging that at the time he contracted with the Moose Lodge, Respondent's license was suspended, thus violating the provisions of Section 489.129(1)(j), Florida Statutes, and the provisions of Section 489.127(1)(e), Florida Statutes. The administrative complaint also alleged that Respondent failed to perform in a reasonably timely manner and/or abandoned the job in violation of Section 489.129(1)(m), Florida Statutes, and Section 489.129(1)(k), Florida Statutes. Respondent denied the allegations of the administrative complaint and timely requested a formal hearing. This proceeding followed. Respondent was previously disciplined by the Construction Industry Licensing Board, and his license remained under suspension at the time of the final hearing.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered finding Respondent guilty of having violated Section 489.127(1)(e), Florida Statutes, and Section 489.129(1)(j), Florida Statutes. It is further recommended that the final order revoke Harry Bradshaw's license in the State of Florida as a registered roofing contractor. DONE and ENTERED this 31st day of October, 1989, in Tallahassee, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 1989. COPIES FURNISHED: Harry Bradshaw 5590 East Seventh Avenue Hialeah, Florida 33013 David M. Gaspari, Esquire Adams, Coogler, Watson & Merkel, P.A Suite 1600 NCNB Tower 1555 Palm Beach Lakes Boulevard West Palm Beach, Florida 33402-2069 Kenneth E. Easley, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201
Findings Of Fact At all times relevant, the Respondent was licensed by the Construction Industry Licensing Board as follows: License No(s): RC 0021957 Licensed as: Registered roofing contractor Address of record is in: New Port Richey, Florida A certain contracting job was undertaken as follows: Customer: Stella Domas Approximate contract date: 6-85 Approximate price: $600 Job location: New Port Richey, Florida Job generally consisted of: Repair roof of Customer's house Said job was undertaken by the contracting business Respondent was associated with and responsible for in his capacity as a licensee. Respondent proceeded without a timely permit having been issued, violating local law, either deliberately or through improper supervision, in violation of 489.129(1)(d), (m), (j) 489.119; and 489.105(4), Florida Statutes. Respondent proceeded without timely obtaining all required inspections, violating local law, either deliberately or through improper supervision, in violation of 489.129(1)(d), (m), (j); 489.119; 489.105(4), Florida Statutes. Respondent gave a guarantee on said job to the Customer, and thereafter failed to reasonably honor said guarantee, in violation of 489.129(1)(m), (j); 489.119; 489.105(4), Florida Statutes. Respondent performed said work in a substantially deficient manner, therefore, violating 489.129(1)(m). Respondent previously has been disciplined by the State Construction Board. STIPULATED DISPOSITION Based on the Stipulated Findings Of Fact and Conclusions Of Law, the parties agree to the following disposition of the Amended Administrative Complaint: The Respondent shall pay a $1500 fine, payable within 60 days from entry of a final order approving this stipulated disposition; and The Respondent's registered roofing contractor license number RC 0021957 shall be suspended for 60 days, beginning 60 days from the entry of a final order approving this stipulated disposition.
Recommendation It is recommended that the Construction Industry Licensing Board enter a final order approving and incorporating the settlement stipulation between the parties. RECOMMENDED 28th day of July, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of July, 1988. COPIES FURNISHED: Jack M. Larkin, Esquire 806 Jackson Street Tampa, Florida 33602 Lee Ellen Acevedo, Esquire 7716 Massachusetts Avenue New Port Richey, Florida 34653 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
The Issue Whether Respondent committed the offenses set forth in Count I of the Administrative Complaint and, if so, the penalties which should be imposed.
Findings Of Fact At all times pertinent to these proceedings, Respondent was licensed by Petitioner as a certified general contractor in the State of Florida and held license number CG- C016730. At all times pertinent to these proceedings, Respondent was the qualifying agent for Bilo Homes, Inc. (Bilo), a corporation engaged in Florida in the business of general contracting with its principal place of business in Miami, Florida. At all times pertinent to these proceedings, Mr. and Mrs. Donald Huston resided at 29843 S.W. 149th court, Leisure City, Florida. On February 24, 1988, the Hustons contracted with Bilo to build an addition to their house for the sum of $20,000 pursuant to plans and specifications that had been prepared by an architect. The Hustons' existing house was valued between $30,000-$40,000. The contract called for a one-story room addition to be built on a concrete slab with stucco exterior and sheet rock interior. The addition was to have a sliding glass door and was to be connected to the existing structure by a tie beam. The roof of the existing house was to be reshingled to match the shingles on the addition. The project also involved electrical work and plumbing work. The contract was signed on Wednesday, February 24, 1988, and work began on Friday, February 26, 1988. The contract did not specify a time for the completion of the project. The following draw schedule was agreed to by the Hustons and Bilo: 20% of the contract price upon the acceptance of the contract by the Hustons; 10% of the contract price upon the pouring of the concrete slab; 10% of the contract price upon ice completion of the tie beam: 20% of the contract price upon the drying in of the roof; 10% of the contract price upon the completion of the rough mechanical work; 10% of the contract price upon ice completion of the shingling of the roof; 10% of the contract price upon the installation of the plumbing fixtures;; 10% of the contract price (the balance) upon completion of the job. The Hustons made payments to Bilo in the total amount of $14,000.00. These payments were broken down as follows: $4,000.00 paid on February 24, 1988, upon acceptance of the contract; $2,000.00 paid on March 22, 1988, upon the pouring of the concrete slab; $2,000.00 paid on April 5, 1988, upon the completion of the tie beam; $4,000.00 paid on April 18, 1988, upon the drying in of the roof; and $2,000.00 paid on June 25, 1988, upon the completion of the shingling of the roof. Before June 25, 1988, Respondent had asked the Hustons for the draw due upon completion of the rough mechanical work in addition to the draw due upon completion of the shingling. The Hustons refused to pay both draws because they were dissatisfied with the quality of Bilo's work. The Hustons engaged the services of a lawyer and, on June 29, 1988, presented Respondent with a list of items they wanted corrected before paying the draw for the rough mechanical work. Respondent and the Hustons disagreed as to when the items on the list should be corrected. Respondent contended that the items could have been corrected as part of the punch list prior to the final payment. The Hustons contended that the items should be corrected before Respondent received any further draws. This dispute is resolved by finding that while several of the items on the list could have been corrected as part of the final punch list, there were items on the list that should have been corrected by Respondent before he proceeded. Considering the very poor quality of work that went into this job, the Hustons were justified in their demand that Respondent make these corrections before receiving an additional draw. Respondent contends that the Hustons did not pay the draw for the rough mechanical work because they ran out of money. This contention is rejected as being contrary to the greater weight of the evidence. After the Hustons presented Respondent with the list and refused to pay the draw for the rough mechanical work, Bilo stopped work on the project. Bilo performed no work on the project after June 29, 1988. Prior to the work stoppage, Respondent hired K & H Plumbing as the subcontractors to the plumbing work on the Huston job. K & H Plumbing's work failed to pass a Metro Dade County tub and water pipe inspection because the work did not meet the South Florida Building Code. K & H never completed its work on the Huston addition and no final inspection of its work was approved. K & H Plumbing filed suit against the Hustons for the unpaid portion of their contract with Bilo. In addition, K & H Plumbing failed to properly replace wood decking which it had pulled up during the course of its work on the Huston job. Respondent had received funds which1 should have been used to pay K & H. Prior to the work stoppage, Respondent hired Tom Mentelos to perform the electrical subcontracting work on the Huston addition. The work performed, by Mentelos was substandard. His work failed to pass inspection by the Metro Dade County Building and Zoning Department on six different occasions. In addition to this substandard work, one of Mentelos' employees cracked the Huston's kitchen ceiling while working in the attic over the existing portion of the house. This crack was never corrected by Mentelos or by Bilo. Mentelos never completed his work on the Huston addition, although he was never fired by the Hustons. Mentelos filed a claim of lien against the Hustons in he amount of $2,000.00. The first claim of lien was released and Mentelos filed a second claim of lien against the Hustons in the amount of $2,623.00. Respondent had received funds which should have been used to pay Mentelos. Respondent obtained the roofing permit to build the new roof on the Huston addition and to reroof the existing roof. The roofing work involved a process commonly referred to as "hot mopping", a process which requires the services of a licensed roofing contractor. Respondent exceeded the scope of his licensure by engaging in hot mopping. Bilo's employees punched two unnecessary vent pipes through the roof and placed a flat piece of PVC material around the vent holes to keep the, roof from leaking. This is an improper and unacceptable construction practice. Bilo's employees damaged the existing screen porch while working on the roof. The metal flashing which connected the existing roof to the aluminum screen porch was taken off but was never replaced. As a result, the screen porch leaked, a problem that had not been corrected as of the time of the final hearing. While Bilo's employees were working on the roof of the existing structure, a rainstorm occurred which resulted in water stains to the ceiling of the Hustons' main structure. The workmen were not supervised by Respondent and were unprepared for the rain. Other than the water stains, no damage was done to the ceiling. To repair the ceiling stains would require a chemical coating, followed by repainting of the ceiling. The cost of the repair would be approximately $75.00. Bilo engaged in poor construction practice in constructing the exterior wall by facing the poorer grade side of the exterior plywood toward the outside as opposed to inside. The better construction practice is to place the poorer grade side toward the inside where it will not be exposed to view. There is a gap in the area where the metal flashing comes down the exterior side of the end gable and meets the top of the roof. In the work performed by Bilo, the piece of sheathing was above the bottom of the sill plate which caused a gap from one inch to five inches over a distance between eight and ten feet. This gap is a source of potential leaks. Bilo attempted to cover the v-notch in the area of the gag with tar pitch in an attempt to correct this deficiency. Both the gap and the attempted repair are unacceptable construction practices. Bilo had not cut vents in the soffits at the time it stopped work on the project. Without vent holes in the soffits, the job would have not passed inspection. Bilo could have, at little expense, cut the soffit vents at a later point in the job. The end member of the frame for the partition wall between the laundry room and the masonry wall is not pressure- treated wood. The South Florida Building Code requires that the wood used for the end member of such construction be pressure treated or that there be a barrier between the end member and the adjoining wall. Here, Bilo failed to exercise either acceptable option, and, consequently performed work that failed to comport with acceptable construction practices and did not meet code. The manner in which Bilo supported the timber girder that supports the roof trusses fails to meet code because the tie beam, into which this girder is pocketed for support, is improperly supported. A hole was knocked in the cement block wall that supported the tie beam when a plumbing vent was redirected. As a result of this hole, the tie beam rests on only approximately two inches of concrete, which is inadequate to support the tie beam and the timber girder. This work fails to comport with acceptable construction practices. Bilo failed to brace the roof trusses as required by the plans and specifications of the architect. This is an unacceptable construction practiced. Bilo cut into the roof truss without authority from the truss manufacturer or from a qualified engineer. Cutting into a truss can impair its structural integrity and is a violation of code. Respondent maintained at hearing that he would have been able to get approval from the truss manufacturer for the modification of the truss caused by the cut. Respondent did not have such approval as of the time of the final hearing, and there was no evidence, other than his unilateral expectation, to support this contention. The facia board on the eaves did not join properly because Bilo's workmen did not take the time to properly cut the boards with the aid of a square. Although this is a matter that could be corrected for approximately $25.00, this work, along with the other deficiencies detailed herein, demonstrates the substandard work that went into this project and establishes that Bilo failed to provide its workmen adequate supervision or adequate training. At hearing, there was a dispute as to how much time Respondent personally spent at the Huston job site. This conflict is resolved by finding that Respondent was personally on the job site for at least 30 minutes on days when work was progressing. When major items were being performed on the job, he spent more time on the job site. When minor work was being done, Respondent did not go to the job site on a daily basis. Regardless of the number of minutes or hours that Respondent spent on the job site, the conclusion is inescapable that Respondent failed to properly supervise his workmen in light of the low level of skill the workmen exhibited throughout the job. Respondent had the responsibility as the general contractor to properly supervise his workmen and his subcontractors. He failed to perform that responsibility. As of the final hearing, the Huston addition remained uncompleted. At the time of the work stoppage, it would have cost the Hustons more than $6,600 to complete the job, the difference between the contract price and the amount that the Hustons had paid Respondent. The evidence was clear that the Hustons had incurred damages as a result of their dealings with Respondent. The amount of those damages were not established with any degree of certainty. On or about July 15, 1988, Respondent filed a claim of lien against the Hustons' property claiming that Bilo was owed $8,350 for the work that had been done. Respondent has been a certified general contractor for fifteen years and has been certified as a general contractor in the State of Florida since 1980. Respondent's licensure had not been disciplined prior to the filing of the Administrative Complaint in this proceeding.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered finding Respondent guilty of having violated the provisions of Section 489.129(1)(h), (j), and (m), Florida Statutes, which imposes administrative fines in the amount of total amount of $5,000 for such violations, and which suspends his licensure as a general contractor for a period of six months. DONE AND ENTERED this 20th day of June, 1990, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of June, 1990. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 89-0765 The following rulings are made on the proposed findings of fact submitted by Petitioner: The proposed findings in Section VI (A) are adopted in material part except to the extent that the proposed findings are subordinate to the findings made. (Section VI (A) pertains to facts established through Respondent's failure to respond to Request for Admissions.) The proposed findings in paragraphs 1 2, 3, 4, 14, 15, 16, 17, 18, 21, 22, 23, and 24 are adopted in material part. The proposed findings in paragraphs 5 - 10 are adopted in material part except to the extent that the proposed findings are subordinate to the findings made or are unnecessary to the conclusions reached. The proposed findings of paragraphs 11, 19, and 25 are adopted in material part except to the extent that the proposed findings are unnecessary to the conclusions reached. The proposed findings of paragraph 12, 26, and 27 are rejected to the extent that the proposed findings are conclusions of law. The proposed findings of fact in paragraphs 13 and 20 are rejected as being subordinate to the findings made or as being unnecessary to the conclusions reached. The following rulings are made on the proposed findings of fact submitted by Respondent: The proposed findings of fact in paragraphs 1, 2, 3, 4, 6, 7, 8, 13, 16, 18, 19, 27, and 30 are adopted in material part. The proposed findings of fact in paragraphs 5, 17, 20, 21, 22, 23, 25, 26, 28, 29, 30, and 32, are rejected as being unnecessary to the conclusions reached. The proposed findings of fact in paragraphs 9 and 11 are rejected as being subordinate to the findings made. The proposed findings of fact in paragraph 10 are adopted in part and are rejected in part as being contrary to the findings made. The proposed findings of fact in paragraphs 12, 14, 33, 35, and 37 are rejected as being contrary to the greater weight of the evidence. The proposed findings of fact in paragraph 15 are adopted in part and are rejected in part as being unsubstantiated by the evidence. The proposed findings of fact in paragraph 24 are adopted in part and are rejected in part as being unnecessary to the conclusions reached. The proposed findings of fact in paragraph 34 are rejected as being the recitation of testimony. COPIES FURNISHED: regory A. Victor, Esquire 3225 Aviation Avenue Suite 400 Miami, Florida 33133 Robert S. Cohen, Esquire Post Office Box 10095 Tallahassee, Florida 32302 Fred Seely, Executive Director Construction Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Kenneth E. Easley, Esquire Department of Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, Florida 32399-0792
The Issue The issue for determination is whether Respondent committed the offenses set forth in the Administrative Complaints and, if so, what penalty should be imposed.
Findings Of Fact It is undisputed that at all times material hereto, Respondent was licensed by the State of Florida as a Certified General Contractor, having been issued license number CG C58099. Respondent passed the licensing examination in August 1995. Case No. 99-0261 Respondent is not a licensed roofing contractor. Respondent's Certified General Contractor's license did not and does not permit him to obtain roofing permits to perform any type of work on roofs. Respondent's Certified General Contractor's license number was not low enough for him to be grandfathered in by the State to allow him to lawfully perform roofing work with his Certified General Contractor's license. On or about February 23, 1998, Delfina Valdes contracted with Johnny Hatcher, d/b/a Hatcher's Roofing, to repair the roof on her residence located at 18101 Northwest 32 Avenue, Miami, Florida. They contracted for Hatcher to remove Valdes' old roof and install a new roof at a cost of $4,000. Valdes paid Hatcher $2,000 as a down payment toward the cost of the roof's repair. At no time material hereto was Hatcher a licensed roofing contractor. Furthermore, at no time material hereto was Hatcher's Roofing qualified by the State of Florida to perform contracting. Hatcher removed the roof from Valdes' residence. After removing the roof, he did not perform any more work. Respondent met with Valdes and represented to her that Hatcher was working for him. Respondent further represented that he would obtain the permit for the roofing work. Respondent paid Cayetano Alfonso to obtain a roofing permit for the work on Valdes' roof. On or about March 26, 1998, Alfonso made application to Metropolitan Dade County, Department of Planning, Development and Regulation for the roofing permit, which was subsequently issued. Alfonso was a Certified General Contractor who was licensed to perform roofing work. Alfonso's Certified General Contractor's license number was low enough for him to be grandfathered in by the State to allow him to lawfully perform roofing work with his Certified General Contractor's license. Alfonso was not the qualifier for Hatcher's Roofing nor was he Respondent's qualifier. Alfonso did not enter into the contract with Valdes for repairing her roof. Alfonso was not a party to the contract for repairing Valdes' roof. An inference is drawn and a finding of fact is made that Hatcher was not acting on behalf of Alfonso when he entered into the contract with Valdes. An inference is drawn and a finding of fact is made that Respondent was not acting on behalf of Alfonso when he represented to Valdes that he would obtain the permit for the roofing work. When Respondent discovered that Hatcher had received a $2,000 deposit from Valdes, he requested Alfonso to cancel the permit. On or about April 20, 1998, Alfonso cancelled the roofing permit. On or about June 5, 1998, Valdes cancelled the contract between her and Hatcher Roofing. Valdes received a refund of the $2,000 from Hatcher, through a third party, that she had paid him. Case No. 98-4859 On or about April 9, 1995, Respondent entered into a contract with Susan Casper to construct an addition to her residence located at 17350 Northeast 12th Court, North Miami Beach, Florida, at a cost of $38,135. Casper paid Respondent $36,285.00 toward the cost of the addition. Respondent was not licensed at the time that he entered into the contract. On or about March 20, 1996, Respondent obtained a permit from the Metropolitan Dade County, Department of Planning, Development and Regulation for the work on the addition. Several delays were encountered during the performance of the work. Some of the delays resulted from changes by Casper, which changes required approval by Metropolitan Dade County, Department of Planning, Development and Regulation; however, most of the delays were Respondent's own doing. In October 1996, Casper paid $2,588 to Best Truss Company for a claim of lien filed on her residence, associated with the work being performed on her residence. Respondent worked sporadically on Casper's addition through April 1997. He would inform her at times that he was returning but failed to return. At one point, Casper's children constructed a sign in their own handwriting, instructing Respondent to keep out and indicating that there was no trespassing by him. The sign was posted on the door of Casper's residence. Casper informed Respondent that her children constructed the sign. It was obvious that the keep out, no trespassing sign was constructed by children. Respondent's assertion that he was kept away from Casper's residence by the children's sign is not credible. Even after the children's sign was posted on the front door of Casper's residence, Respondent agreed with Casper to resume work, and he did so. However, his work was sporadic. In or around June 1997, Casper sought assistance from the Metropolitan Dade County, Department of Planning, Development and Regulation to get Respondent to complete the work. In July 1997, Respondent obtained a window permit for the work on Casper's residence. After July 1997, Respondent ceased working on Casper's residence. He did not provide Casper with any notice that he was ceasing work. Respondent had no valid reason for ceasing the work. In September 1997, Casper transferred the permit for the work on her residence from Respondent's name to her name. Respondent failed to perform all the work under the contract. Some of the work performed by Respondent or caused to be performed by Respondent contained code violations and needed correcting. Certain work performed by Respondent or caused to be performed by Respondent needed correcting. Wood doors, glass block, electrical work, and a sprinkler were in need of correction. Casper bore the expense of the corrections. The corrective work was completed at a cost of $1,675.00. The value of the work performed by Respondent on Casper's residence was $18,272, minus the cost of the corrective work of $1,675, which equals a total value of the work at $16,597. This cost value includes overhead and profit. Even though the value of the work by Respondent was $16,597, Casper paid Respondent $36,285, a difference of $19,688. Casper hired a new contractor on or about September 17, 1997, to complete the construction on her residence at a cost of $16,350. As to Case No. 98-4859, as of January 26, 1999, Petitioner incurred a cost of $1,108.76 for the investigation and prosecution of Respondent. Petitioner previously disciplined Respondent for violating Chapter 489, Florida Statutes (1995), including violating Subsection 489.127(1)(k), Florida Statutes (1995), abandonment of a construction project.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order and therein: As to Case No. 99-0261, finding that Respondent violated Subsection 489.129(1)(e), Florida Statutes (1997). As to Case No. 98-4859, finding that Respondent violated Subsection 489.129(1)(k), Florida Statutes (1997), in Count I; and dismissing Count II. Revoking Respondent's license. Ordering Respondent to pay restitution to Susan Casper in the amount of $19,688.00. DONE AND ENTERED this 31st day of October, 2000, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 2000. COPIES FURNISHED: Diane Snell Perera, Esquire Department of Business and Professional Regulation 401 Northwest 2nd Avenue, Suite N607 Miami, Florida 33128 Richard F. Hayes, Esquire 10300 Sunset Drive, No. 499 Miami, Florida 33173 Rodney L. Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792