Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
FAIRCHILD CORPORATION vs DEPARTMENT OF TRANSPORTATION, 90-003122BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 23, 1990 Number: 90-003122BID Latest Update: Jul. 30, 1990

Findings Of Fact State Project No. 46090-3511 (the project) is for construction of the West Bay Bridge on State Road 79 in Bay County, Florida. Competitive bids on the project were solicited in February, 1990. The bid letting on the project was held in March, 1990. The Petitioner, Fairchild, the Hardaway Company and ten other contractors bid on the project. The Hardaway Company submitted the lowest bid on the project in the amount of $9,487,258.17. Fairchild submitted the next lowest bid in the amount of $9,835,279.34. Divergent Unit Prices and Imbalances. The part of the Hardaway Company's bid relating to construction of the foundation for the approaches to the bridge (the "structural bid") is obviously below reasonable cost in several respects. The contract specifications require the use of sand fill, shell fill, reinforcement grid (biaxial type 2), and Class III (seal) concrete. The Hardaway Company's unit prices for these items were, respectively, one dollar per cubic yard for the sand fill, fifty cents per cubic yard for the shell fill, twenty-five cents per square yard for the reinforcement grid, and ten cents per cubic yard for the Class III seal concrete. As a result, the Hardaway Company's bid for these items is obviously significantly below reasonable cost and approximately $95,500 below what Fairchild bid for the same portion of the contract. In contrast to the sand fill, shell fill, reinforcement grid and Class III concrete, the Hardaway Company's bid on some of the other parts of the structural bid were relatively high. The reinforcing steel for the substructure (Item 415-1-5) was bid at approximately twice reasonable cost (80 a pound versus, e.g., 42 in Fairchild's bid), resulting in $609,936.80 attributable to that part of the bid versus, e.g., $320,216.82 for Fairchild. The statistical average (the DOT's so-called "average 2") for the other serious bidders under this item also was 42 a pound. The Hardaway Company also bid obviously in excess of reasonable cost for the lump sum item of mobilization for pile installation--$600,000 versus $125,000 in Fairchild's bid and less in the bids of several of the others bidders. (The statistical average for the other serious bidders under this item was $225,000.) But the Hardaway Company bid only $60,000 for the lump sum item for removal of existing structures (versus $160,000 in Fairchild's bid) and only $30,000 for the lump sum item for removal and disposal of fender system (versus $110,000 in Fairchild's bid). The portion of the Hardaway Company's bid attributable to mobilization for the roadway work is significantly less than the Fairchild bid under this item ($200,000 versus $375,000) and partially counterbalances the excess in the part of the Hardaway bid for mobilization for the pile installation. The portion of the Hardaway Company's bid attributable to clearing and grubbing also was high, at $20,000 an acre versus a statistical average of $4,200 an acre for the other serious bidders, resulting in $216,000 for the Hardaway Company bid versus, e.g., $32,400 for the Fairchild bid and the $45,360 statistical average. DOT Review Procedures. Section 2-6 of the DOT's Standard Specifications applicable to the project provides: 2-6 Rejection of Irregular Proposals. A proposal will be subject to being considered irregular and may be rejected if it shows omissions, alterations of form, additions not called for, conditioinal or unauthorized alternate bids, or irregularities of any kind; also if the unit prices are obviously unbalanced, either in excess of or below the reasonable cost analysis values. The DOT is in the process of formulating a policy on the use of the Technical Review Committee in the bidding process. A proposed procedure has been developed, which has not yet been made final and has not yet been signed by the Secretary of the DOT, under which the Technical Review Committee would review the low bid on each contract, among other things not applicable to this case, for "any significant irregularities in unit bid prices" and for "unbalanced bidding." The DOT has not yet defined "any significant irregularities in unit bid prices" or "unbalanced bidding" for purposes of defining the event that triggers review by the Technical Review Committee. The DOT Director of the Office of Construction, Robert Buser, is of the opinion that the unit prices the Hardaway Company bid for the sand fill, the shell fill, the reinforcement grid and the Class III seal concrete are "significant irregularities in unit bid prices." On the other hand, the DOT's Preliminary Estimates Engineer, Robert Griner, who, unlike Buser, is a member of both the Technical Review Committee and its Preliminary Technical Subcommittee, and is of the opinion that the Hardaway bid for the sand fill, the shell fill, the reinforcement grid and the Class III (seal) concrete are "mathematical imbalances," not "significant irregularities in unit bid prices," which he would define as bids that omit a unit price, whose numerical values do not match words used to express the values, or that are not signed. Under Griner's approach, which was followed in this case, the Preliminary Technical Subcommittee looks at "mathematical imbalances" to see if they are "material imbalances." If the Preliminary Technical Subcommittee decides that it is not a "material imbalance," it simply reports this finding at the outset of the meeting of the Technical Review Committee, which accepts the finding and does not itself consider the matter any further. Only if the Preliminary Technical Subcommittee reports a "material imbalance" does the Technical Review Committee further consider the question. Front-end Bidding. Under the DOT contract for the project, like other items in the specifications, mobilization and land clearing and grubbing are paid in installments as the work proceeds. But, unlike the other items, all of the portion of the contract attributable to mobilization and land clearing and grubbing is paid by the time the entire project is half completed. Similarly, a contractor is paid for reinforcement steel (substructure) when it is delivered to the site. As a result, by shifting dollars in a bid to these "front-end," lump sum items, a contractor can manipulate the bid process and contract to reasonably insure himself of early payment of these inflated items regardless what may happen to the project later. In analyzing these front-end, lump sum items, Griner treated them (along with the unreasonably low bids on the sand fill, shell fill, reinforcement grids and C III seal concrete) as "mathematical imbalances." Following the guidance of a Federal Highway Administration (FHWA) memorandum, dated May 16, 1988, on the subject of "Bid Analysis and Unbalanced Bids," Griner analyzed the Hardaway bid to be sure it would not be susceptible to cost overruns (it was not) and to be sure the quantities were correctly estimated (they were). He also analyzed the additional cost to the DOT of paying the Hardaway Company early (by the half way point of the project) for the inflated front-end items to determine whether the "mathematical" imbalance was "material," i.e., whether "the mathematically imbalanced bid will result in the lowest ultimate cost to the Government." Based on a twelve percent interest rate, Griner calculated that the inflated front-end items would cost the DOT approximately an additional $98,000, 1/ still much less than the difference between the low Hardaway bid and any other bid. Based on this calculation, Griner concluded that the "mathematical imbalance" in the Hardaway bid was not a "material imbalance" and did not require the award of the bid to Fairchild or one of the other bidders. Griner overlooked and did not apply another portion of the method of analysis in the FHWA memorandum on "Bid Analysis and Unbalanced Bids" that states: There are numerous reasons why a bidder may want to unbalance his/her bid on a contract. One reason is to get more money at the beginning of the project. The bidder does this by overpricing the work done early in the project. This is called "front loading" the contract. The leading case in the "front loading" area is Matter of: Riverport Industries, 64 Comp. Gen. 441 (1985). Here the Comptroller General held that if the bid is front loaded, regardless if it is the lowest bid, it "should be viewed as materially unbalanced since acceptance of the bid would result in the same evils as an advance payment. An advance payment is prohibited by law." The "front loading" may also be materially unbalanced due to the cost of money that must be paid out early versus over the normal construction fo the project. Under the Hardaway Company bid, the pile mobilization, the land clearing and grubbing, and the reinforcement steel (substructure) parts of the bid are "front-ended." 2/ Under the method of analysis suggested by the FHWA memorandum, the Hardaway Company would be paid approximately $428,000 in "advance payments" under these two items if it is awarded the contract. Approximately $375,000 in pile mobilization, $183,600 in land clearing and grubbing, and $289,700 in the reinforcement steel were shifted to these front- end items from the unbalanced sand fill, shell fill, reinforcement grid, and Class III (seal) concrete items. These dollars The shifted dollars are estimated by taking the difference between the statistical average for these items and the Hardaway bid on them. Since roiughly half of the shifted dollars would be paid earlier than they would be paid if they were bid under the sand fill, shell fill, reinforcement grid and Class III (seal) concrete items, the amount of "advance payment," under the FHWA analysis would be approximately $428,000. Griner did not explain why he only followed part, but not all, of the method of analysis suggested by the FHWA memorandum, other than to say he overlooked it. But he also testified that it is common practice for contractors to submit mathematically unbalanced bids, and the DOT always analyzes them the way he did in this case. Indeed, in the March, 1990, bid letting, Griner found "mathematical imbalances" in 21 of the 29 low bids but no "material imbalances." The Fairchild bid also contains "mathematical imbalances." It also "front-ends" several items. The total dollar value of the "front-ending" in the Fairchild bid (including roadway mobilization) closely approximates that found in the Hardaway bid and, under the FHWA analysis, would result in approximately the same amount of advance payment. Under Section 101-2.2 of the DOT's Standard Specifications for this project, contractors are limited to a maximum of ten percent of the total contract for mobilization. The Hardaway Company's total mobilization bid is within the maximum under the specifications. Notwithstanding the imbalances in the Hardaway bid, and the so-called "advance payments" that would result from the "front-ending" in the Hardaway bid, the Hardaway bid remains the lowest and best bid on the project, and it is the best interest of the DOT and the public to award the contract to the Hardaway Company. Even if the Hardaway Company had bid the sand fill, shell fill, reinforcement grid, and Class III (seal) concrete items exactly as Fairchild did, Hardaway still would be low bidder. "Value Engineering" and Alleged Alternative or Contingent Bidding. Inferences reasonably could be drawn from the evidence that the Hardaway Company may intend to propose to the DOT that the approach to the bridge be re-engineered so as to eliminate the need for the sand fill, the shell fill, the reinforcement grid and the C III (seal) concrete. If the DOT accepts such a proposal, the contract between the DOT and the Hardaway Company would have to be modified. If the re-engineered project were to allow the Hardaway Company to do the job for less than its bid price, half (or, if the proposal is innovative or unique, up to 80%) of the savings would be paid to the Hardaway Company under what the DOT calls "value engineering." Under DOT procedures, "value engineering" proposals are not made or evaluated until after the original contract is signed with the successful bidder. It is not an alternative bid or a contingent bid.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Respondent, the Department of Transportation, enter a final order dismissing the bid protest filed by W. R. Fairchild Construction Company, Ltd., and awarding State Project No. 46090-3511 to the Hardaway Company. RECOMMENDED this 30th day of July, 1990, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of July, 1990.

Florida Laws (1) 120.57
# 1
BUCCANEER STEEL ERECTORS, INC. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 86-000495BID (1986)
Division of Administrative Hearings, Florida Number: 86-000495BID Latest Update: Apr. 01, 1986

Findings Of Fact Respondent advertised for bids for work to be performed on the Statewide Regional Juvenile Detention Center located in Pasco County identified as Project Number HRS 85-300000. In response to this advertisements Petitioner and Intervenor timely submitted bids on January 23, 1966. According to calculations performed by Respondent, Petitioner was low bidder and Intervenor was the next lowest bidder. The construction budget for this job is $1.5 million, and both bids are considered by Respondent to be within budget. Depending on the alternatives chosen within each bid, Petitioner's bid is lower than Intervenor's by between approximately $6,000 and $40,000. Section B-14 of the advertisement for bids requires each bidder to submit a list of the subcontractors who will perform work on the job for him and specifies that only one subcontractor shall be listed for each phase of the work. Section D of the advertisement for bids specifies the work areas for which a subcontractor must be listed and states that said list is an integral part of each bid submitted. The subcontracting areas include electrical plumbing, mechanical, roofing security control systems, food service equipment and fire protection. Petitioner's bid was rejected on February 4, 1986, because its bid failed to include a roofing subcontractor's name as required in the advertisement for bids. Petitioner does not dispute that its bid was incomplete when submitted since it failed to identify a roofing subcontractor. However, Petitioner contends this omission was a result of clerical error in typing the bide and that, in fact, it had selected Republic Roofing as its subcontractor. John Breen, Petitioner's project manager, testified that it was his intent to use Republic Roofing when he submitted the bide that he had a firm bid from Republic Roofing, and that when this omission was brought to his attention after bids were opened, he identified Republic Roofing in writing on January 24 and 29, 1986, to Brian Seufert an intern architect working for Respondent's project architect. Seufert confirms Breen's testimony through affidavit jointly filed by the parties. Seufert indicates that the project architect has no reason to believe that Petitioner could not perform the work required by the project. By affidavit jointly filed by the parties, Joyce Kleja secretary for Petitioners also supports Breen's testimony about her clerical error in omitting the roofing subcontractor when she typed the bid. Ray Scerbo, an estimator for Republic Roofing, disputes the testimony of Breen through jointly filed affidavit. Scerbo indicates it was not until a couple of days after the bid opening that he was told by Petitioner that Republic Roofing "had the job" if Petitioner was awarded the contract. This conflicts with the first written notice from Breen to Seufert dated January 24, 1986, as well as Seufert's affidavit that Petitioner told Seufert on January 24, 1986, that Republic Roofing had been selected. Scerbo is no longer employed by Republic Roofing. After considering all of the evidence, it is specifically found that Petitioner's omission of Republic Roofing from its list of subcontractors was through clerical error and that Petitioner had firmly decided to use Republic Roofing for subcontracting work prior to submission of its bid. The advertisement for bid required all subcontractors to be listed in any bid in order to allow Respondent to review prior performance and licensure of subcontractors, and also to prevent "bid shopping". Bid shopping is a practice which inflates a general contractor's bid and therefore the actual award by encouraging subcontractors to initially submit high bids to the general contractor and then negotiate a lower price with the general contractor who has received the award. The general contractor's bid remains inflated however and in this way the cost to the state is increased.

Recommendation Based upon the foregoing it is recommended that Respondent enter a Final Order awarding Project Number HRS 85-300000 to Intervenor. DONE and ENTERED this 1st day of April 1986, at Tallahassee Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 1st day of April 1986. APPENDIX (DOAH CASE NO. 86-0495B1D) Petitioner has submitted a memorandum and a Proposed Recommended Order, both of which appear to set forth proposed findings of fact in unnumbered paragraphs. For purposes of ruling thereon, the unnumbered paragraphs which appear to set forth proposed findings have been consecutively numbered. Memorandum: Introductory material and not a proposed finding of fact. Adopted in part in Findings of Fact 1, 2, 3, 4, but otherwise rejected as cumulative and unnecessary. Adopted in Findings of Fact 5, 7. Rejected as simply a summary of testimony and evidence and not a proposed finding of fact. Rejected as irrelevant. Adopted in part in Findings of Fact 5, 6. Adopted in part in Finding of Fact 4, but rejected in part in Finding of Fact 2 and otherwise rejected as not based on competent substantial evidence. Proposed Recommended Order: Adopted in part in Findings of Fact 1, 3, but otherwise rejected as unnecessary and irrelevant. Rejected as irrelevant. Adopted in part in Finding of Fact 2, but otherwise rejected as contrary to Finding of Fact 2. Adopted in Finding of Fact 5. Adopted in Findings of Fact 5, 7. Adopted in Finding of Fact 4. Rulings on Respondent's and Intervenor's jointly filed Proposed Findings of Fact: Adopted in Findings of Fact 1, 3. Adopted in Findings of Fact 1, 2. Adopted in Findings of Fact 4, 5. Adopted in Finding of Fact 8. , 6. Adopted in Findings of Fact 6, 7. COPIES FURNISHED: Dennis R. Long Esquire 2101 U.S. Highway 19 North Suite 201 Palm Harbor, Florida 33563 Sam Powers Esquire Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee Florida 32301 William Page; Jr., Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32301 John P. Fons Esquire Post Office Drawer 11307 Tallahassee, Florida 32302

Florida Laws (3) 120.53120.57255.0515
# 2
MARPAN SUPPLY COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 96-002777BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jun. 11, 1996 Number: 96-002777BID Latest Update: Nov. 26, 1996

The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.

Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.

Florida Laws (6) 112.061120.57215.422287.001287.012287.057 Florida Administrative Code (1) 60A-1.001
# 3
ANDERSON COLUMBIA COMPANY, INC., AND PANHANDLE LAND AND TIMBER COMPANY, INC. vs DEPARTMENT OF TRANSPORTATION, 99-000740BID (1999)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 17, 1999 Number: 99-000740BID Latest Update: Oct. 19, 1999

The Issue The issue in this case concerns whether the Florida Department of Transportation's (FDOT's or Department's) proposed action to award a contract to Couch Construction, L.P., is contrary to the agency's governing statutes, the agency's rules or policies, or the bid or proposal specifications.

Findings Of Fact The Florida Department of Transportation (Department) issued an Invitation to Bid (ITB) for road resurfacing on State Road 10/US 90 in Columbia County, Florida; Financial Project No. 208406-1-52-01 (The Project). Four companies submitted responses to the ITB. Couch was low bidder at $2,271,354.81, and Petitioner was second low at $2,278,263.07. The ITB incorporated the plans and specifications for the proposed highway resurfacing. The price proposal specifications stated in pertinent part: Item Number 2102-10. . .Approximate Quantity. . . 4,320.00 hours Item Number 2102-74-1 . Approximate Quantity . . .75,780.00 each day Item Number 2102-99 . . Approximate Quantity . . . 720.00 each day None of the bidders filed a timely objection to the price proposal specifications. Article 2-6, of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction states: A proposal will be subject to being considered irregular and may be rejected if it shows omissions, alternations of form, additions not called for, conditional or unauthorized alternate bids, or irregularities of any kind; also if the unit prices are obviously unbalanced, either in excess of or below the reasonable cost analysis values. After the bids were opened, each bid was reviewed by the Department to determine whether the bid was mathematically and/or materially unbalanced. The Department's Preliminary Estimates Engineer conducts an unbalanced review of the bids to determine if the bids are mathematically unbalanced. A bid is considered to be mathematically unbalanced if the prices quoted are significantly different from the approximate cost of the item to the contractor. It is very common for bids on construction projects to contain some item prices that are mathematically unbalanced. Bid prices that are mathematically unbalanced are considered by the Department to be non-material irregularities if they do not affect the order of the bidders. In determining whether a mathematically unbalanced price is material, the Department follows a policy set out by the Federal Highway Administration (FHWA). The Department has been following the same policy since at least 1992. The FHWA does not allow for materially unbalanced bids to be accepted by the Department on projects that are federally funded. A materially unbalanced bid is one in which there is a reasonable doubt as to whether award to the bidder submitting the mathematically unbalanced bid will result in the ultimately lowest cost to the Department. The Department has developed an Unbalanced Program Logic for its computer analysis of the bids. The program flags the items that are mathematically unbalanced. It flags the item with an "A" for those items that are above the tolerance window, "U" for under the tolerance window, and "F" as front-loaded items. The flagged items which are short-listed by the computer program are sent to the designer of record to verify the quantities and to verify whether the correct pay item was used. The designer of record verified that the quantities were correct for this Project. As part of the bid review, the Department does a statistical average or mean average for each of the bid items. A standard and a-half deviation either side of the mean is established. The bid items outside that standard and a-half deviation, positive or minus, are discarded. The remaining bid items are re-averaged and this second average is referred to as the "serious average." A front-end loaded item is an item for which work is performed early in the contract. Mobilization is considered a front-end loaded item. Couch's Mobilization item 2101-1B was flagged by the computer analysis. The Department did an analysis of the Mobilization item. The Department started with the difference between Couch's bid and the Petitioner's bid on this item, $18,0000.00. That amount was multiplied by the current interest rate, 10 per cent, and then multiplied by a factor of .5, which spread it over half the contract, times 180-day contract period divided by 365, one calendar year. The result was $434.84, which represents the potential advantage that could result from paying the $18,000.00 amount early in the contract. That amount, $434.84, did not materially unbalance Couch's bid. The three items identified by Petitioner as unbalanced (paragraph 3, above) were low and did not present any detriment to the Department. If those three items overran at the rate established, it would be an advantage to the Department. In evaluating unbalanced bids, the Department follows the guidance in a May 1988 memorandum from the FHWA, which addresses bid analysis and unbalanced bids. The memorandum provides that where unit prices for items bid are either unusually high or low in relation to the engineer's estimate of the price, the accuracy of the estimated quantities of the items are to be checked. If the quantities are reasonably accurate, the bid is to be further evaluated to determine whether the mathematical imbalance is materially unbalanced such that there is "reasonable doubt that award to the bidder submitting the mathematically unbalanced bid will result in the lowest ultimate cost to the Government." The analysis of a mathematically unbalanced bid to determine if it is materially unbalanced considers the effect of the unbalanced bid on the total contract amount; the increase, if any, in the contract cost when quantities are corrected; whether the low bidder will remain as the low bidder; and whether the unbalanced bid would have a potential detrimental effect upon the competitive process or cause contract administration problems later. In this case, the Department compared the unit prices (line item prices) by each bidder on the bid proposal sheet to the average unit price for that item. The average unit price is based upon an average of the bidders' unit prices bid for a given pay item and the Department's estimated unit price for that item. If an individual bidder's unit price is significantly greater or less than the average price, the Department's computer flags the item as mathematically unbalanced. Such a bid then receives further evaluation by the Department to ensure the accuracy of the original estimates of the quantities of those items for which an unbalanced unit price has been submitted. The Department also reviews the project plans for accuracy. The more in-depth review is performed to determine if there is a potential for a cost overrun or if there is an error in the Department's estimated quantities which would result in an increased cost to the Department for the project. In this case, Couch and Anderson submitted bid proposals for each of the individual line item prices contained on FDOT's form. Couch's unit price for the off-duty law enforcement item was $0.25/hour. The Department's average price for the off-duty law enforcement item was $25.22/hour. The Petitioner's quotation for off-duty law enforcement was $26.00/hour. The Department's computer analysis of Couch's bid flagged the off-duty law enforcement item as mathematically unbalanced. The quote by Petitioner for the off-duty law enforcement item was not unbalanced, and therefore was not flagged for further review by the Department. The same analysis was applied to the barricades and variable message sign items, with similar results. The Department also did an in-depth review of item 2101-B, Mobilization, for front-end loading. The result of that analysis was that, as a result of front-end loading, there was the probability of increased cost to the Department of $443.84. This small increase in the cost to the Department was not large enough to change the order of the bidders. Therefore, it was not a materially unbalanced item. The Department then made a more in-depth review of the three mathematically unbalanced items in Couch's bid and determined that none of those items were materially unbalanced, because none of them had the potential to increase the cost to the Department and none of them had the potential to change the order of the bids. In sum, the Couch bid was not materially unbalanced. The evidence in this case is insufficient to support a basis for rejecting the Couch bid.

Recommendation On the basis of all of the foregoing, it is RECOMMENDED that the Florida Department of Transportation issue a final order in this case dismissing the Petitioner's Formal Protest and Request for Hearing; denying all relief requested by the Petitioner; and awarding the subject contract to the Intervenor, Couch Construction, L.P. DONE AND ENTERED this 7th day of May, 1999, in Tallahassee, Leon County, Florida. MICHAEL M. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of May, 1999.

Florida Laws (3) 120.569120.57337.11
# 5
GUIDING LIGHT ENTERPRISE, INC. vs DEPARTMENT OF TRANSPORTATION, 04-002163BID (2004)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Jun. 21, 2004 Number: 04-002163BID Latest Update: Sep. 17, 2004

The Issue The issue in this case is whether the Department of Transportation's proposed award of a contract to Daniels Janitorial Service is contrary to the agency's governing statutes, the agency's rules or policies, or the specifications of the Invitation to Bid (ITB).

Findings Of Fact In April 2004, DOT issued ITB-DOT-04/05-5002-PDW (the ITB) seeking to contract for janitorial services at two state office buildings in DeLand, Florida. The ITB included a "bid blank," upon which vendors were directed to submit their cost proposals. The bid blank was titled "MONTHLY JANITORIAL SERVICES PER SCOPE OF SERVICES." The bid blank included three spaces where each bidder was to provide cost information. The three spaces were titled as follows: "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and "TOTAL YEARLY AMOUNT BOTH BUILDINGS." In response to the ITB, DOT received 18 bids. The bids were opened at 3:00 p.m. on April 29, 2004. The lowest bid was $5,185.76, submitted by Daniels Janitorial Service, including: $4,895.76 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $200.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $5,186.76 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The second lowest bid was $10,686.00, submitted by Jan-Pro Cleaning Systems, including: $9,971.00 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $715.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $10, 686.00 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The third lowest bid was $67,777.77, submitted by the Petitioner. The remainder of the bids ranged between $69,600.00 to as much as $201,464.64. At the time of the opening, Diane Warnock, a DOT District Contract Specialist and Purchasing Agent in charge of the bid opening, observed that two of the bids (the Daniels Janitorial Service and the Jan-Pro Cleaning Systems bids) appeared to be very low in relation to the other bids. Ms. Warnock believed that the two lowest bids submitted were likely set forth on a monthly basis rather than annual amount, and that the bidders had failed to extend the monthly charges to an annual cost. Ms. Warnock contacted David Callaway, a DOT Procurement Analyst with statewide contract responsibilities, to discuss her observations. Mr. Callaway advised Ms. Warnock that she could contact the two low bidders and ascertain whether the bids submitted reflected a monthly or an annual cost. Ms. Warnock separately contacted each of the individuals responsible for submitting the low bids and inquired as to whether the bids reflected a monthly cost or an annual cost. Ms. Warnock learned that each vendor had submitted a monthly bid amount. Ms. Warnock multiplied the monthly amounts submitted by the two vendors by 12 to arrive at an annual cost. On the bid tabulation form, Ms. Warnock included the bid amount submitted by each bidder. For the two bidders who submitted monthly cost information, Ms. Warnock included the monthly costs submitted and the annual cost figures she had calculated. Based on annual costs, the lowest vendor was Daniels Janitorial Service with an annual bid amount of $62,229.12. Section 13.2 of the ITB provides as follows: 13.2 RESPONSIVENESS OF BIDS Bids will not be considered if not received by the Department on or before the date and time specified as the due date for submission. All bids must be typed or printed in ink. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid in accordance with all requirements of this Invitation to Bid. Bids found to be non- responsive will not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons that include, but are not limited to, failure to utilize or complete prescribed forms, modifying the bid requirements, submitting conditional bids or incomplete bids, submitting indefinite or ambiguous bids, or executing forms or the bid sheet with improper and/or undated signatures. Section 13.4 of the ITB provides as follows: 13.4 WAIVERS The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregularities are defined as those that do not have an adverse effect on the Department's interest and does not effect the price of the bid by giving a bidder an advantage or benefit not enjoyed by other bidders.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Transportation enter a final order awarding the contract for ITB-DOT-04/05- 5002-PDW to Daniels Janitorial Service. DONE AND ENTERED this 25th day of August, 2004, in Tallahassee, Leon County, Florida. WILLIAM F. QUATTLEBAUM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of August, 2004. COPIES FURNISHED: C. Denise Johnson, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Anthony Payne 1031 Eagles Forrest Drive Apopka, Florida 32712 James C. Myers, Clerk of Agency Proceedings Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450 Pamela Leslie, General Counsel Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450

Florida Laws (1) 120.57
# 6
VICK GRIFFIN CONSTRUCTION COMPANY vs. LONG CONTRACTORS, INC., AND NORTH FLORIDA JR. COLLEGE, 82-000654 (1982)
Division of Administrative Hearings, Florida Number: 82-000654 Latest Update: Apr. 29, 1982

Findings Of Fact On or about December 29, 1981, the College solicited sealed bids for construction of alterations and additions to the Technical and Gymnasium Buildings located on its campus in Madison, Florida. In response, seven general contractors submitted bids. (P-1, P-2, P-3.) Bids were publicly opened on February 9, 1982. Griffin Construction, with a bid of $536,575, was the apparent low bidder; the second lowest bidder was Long Contractors, with a bid of $539,512. (Testimony of Griffin, Sims, Rutherford; P-3, P-4, P-5.) After the low bid was identified, Tom McClanahan, representing Long Contractors, asked that the subcontractor list accompanying the low bid be opened. Griffin Construction's subcontractor list was then opened. McClanahan asked if the license and charter numbers of the subcontractors were listed. 2/ Upon learning that these numbers were not included on Griffin Construction's subcontractor list, McClanahan protested. (Testimony of Sims, Rutherford, Griffin.) At its February 15, 1982, meeting, the College District Board of Trustees ("Board") rejected the low bid of Griffin Construction on the sole ground that the omission of subcontractor license and charter numbers constituted a failure to comply with the conditions of the bid documents. 3/ The Board then voted to award the contract to Long Contractors, the second lowest bidder, on the ground that it was the lowest bid conforming to the bid documents. In so doing, the Board followed the College president's recommendation--a recommendation based on his belief that the non-complying bid must be rejected, that it did not involve a matter of Board discretion. (Testimony of Sims, Rutherford, Griffin; Stipulation of Parties; P-41.) The bid specifications contain instructions to bidders requiring "each Bidder . . . [to] submit with his proposal a list of the subcontractors who will perform the work . . . as indicated by the `List of Subcontractors' form." (P-1, P-2.) The instructions further provide: The applicable subcontractor license registration or certification number must be noted on the bid opposite his name, and in the event that the subcontractor is a corporation, his State Corporate Charter number shall also be noted. If the subcontractor is an out of state firm, their Charter number with the Secretary of State to do business in the State of Florida should also be noted. The "Listing of Subcontractors" form provided with the specifications contains column headings for the names and addresses of the subcontractors but does not contain a separate heading for the requested license or corporate charter numbers. 4/ The form states that the subcontractor list "is an integral part of the bid." (P-1, P-2.) The bid instructions further require bidders to evaluate and determine the qualifications of their listed subcontractors. The bidder shall have determined to his own complete satisfaction that a listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this agreement and is qualified both technically and financially to perform that pertinent phase of the work for which he is listed. (P-1, P-2.) The bid documents expressly reserve to the College the right "to reject any or all bids, and to waive informalities." (P-1 P-2.) No bidder correctly listed the required license and corporate charter numbers on its "Listing of Subcontractors" form. Griffin Construction. Griffin failed to include any license or corporate charter numbers. However, by subsequent letters dated February 9 and February 18, 1982, and at hearing, it supplied the required subcontractor license and charter numbers. Long Contractors. Long listed for its roofing subcontractor a sheet metal registration number, not the required roofing license number. [A sheet metal registration does not qualify a contractor for roofing work. See, 489.105, 489.113, Fla. Stat. (1981).] For its electrical subcontractor, Long omitted the prefix, "ER" from the listed number. For its plumbing subcontractor, Long listed a mechanical registration number instead of the required plumbing certification or registration number. [A mechanical registration does not qualify a contractor to perform plumbing work. See, 489.105, 489.113, supra.] Of the four areas requiring state licenses--roofing, heating and air conditioning, electrical, and plumbing--Long listed correctly only the registration number for its heating and air conditioning subcontractor. Long incorrectly listed No. FO6962 as the corporate number of Gandy Enterprises, its painting subcontractor. This is the number of a related corporation, Industrial Coatings, Inc. Remaining Bidders. Of the five other general contractors submitting bids, two-- Richard Walker Construction Company and GRC Contracting, Inc.--omitted all subcontractor license and charter numbers. The other three bidders failed to completely list all the required numbers. (Testimony of Rutherford; P-11, P-12, P-13, P-14, P-15, P-16, P-17, P-34, P-37, R-1, R-5.) The project architect testified that the submittal of incorrect or incomplete subcontractor license and charter numbers was a deficiency which a bidder should be allowed to cure after bid opening. But the failure to submit any required "number" was a deficiency which, in his opinion, could not be similarly corrected. He failed, however, to supply a reasonable basis for drawing such a distinction. Therefore, his opinion on this question is given little weight. 5/ (Testimony of Rutherford.) Subcontractor license and charter numbers are readily obtainable and can be verified by contacting the pertinent state agency--the Florida Department of Professional Regulation, Construction Industry Licensing Board, or the Florida Department of State. (Testimony of Griffin, Rutherford; P-32, P-33, P- 34, P-35, P-36, P-37.) The project architect, William Rutherford, routinely requires the listing of subcontractor license and charter numbers on bids for public construction projects. The main purpose it serves is that it would enable him to identify the listed contractor, since sometimes subcontractors have similar business names. Although if he was uncertain about the qualifications of a subcontractor, he would ordinarily question the general contractor. (Testimony of Rutherford.) Although Mr. Rutherford has customarily required the listing of subcontractor "numbers" on public projects, he has never made any use of those numbers in the past. (Testimony of Rutherford.) The general contractor who is awarded the contract is responsible to Mr. Rutherford and the College for construction of the project in accordance with the bid specifications. If, after bid opening, a listed subcontractor is unable to perform, Mr. Rutherford would ordinarily arrange for substitution of a new subcontractor acceptable to the general contractor and owner. (Testimony of Rutherford.) Griffin Construction's failure to list the license and charter numbers of its listed subcontractors, and its subsequent curing of that failure, did not affect the amount of its bid 6/ by giving it an advantage or benefit not enjoyed by other bidders. The bid omission did not allow Griffin Construction the opportunity to change any material element of its bid after bid opening. The inclusion or exclusion of subcontractor "numbers" at bid opening does not affect the ability of a contractors to obtain the required bond, the quality of bidding general contractors, the quality of listed subcontractors, the quality of work performed, or any material feature of the competitive bidding process. (Testimony of Griffin, Rutherford.)

Recommendation Based on the foregoing, it is RECOMMENDED: That the construction contract in question be awarded to Vick Griffin Construction Company, the lowest responsible bidder. DONE AND RECOMMENDED this 29th day of April, 1982, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1982.

Florida Laws (3) 120.5720.15489.105
# 7
CON-AIR INDUSTRIES, INC. vs SEMINOLE COUNTY SCHOOL BOARD, 98-004714BID (1998)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Oct. 27, 1998 Number: 98-004714BID Latest Update: Jan. 20, 1999

The Issue Whether the School Board of Seminole County's, notice of intent to award Bid No. 102589, for air filter maintenance, service, and replacement to Filter Service and Installation Corporation was clearly erroneous, contrary to competition, arbitrary, or capricious.

Findings Of Fact The Seminole County School District is a political subdivision of the State of Florida, created by Article IX, Section 4, Florida Constitution. The powers and duties of the school board are enumerated in Chapter 230, Florida Statutes. The Superintendent of the Seminole County School District is a constitutional officer, whose office is created by Article IX, Section 5, Florida Constitution. The powers and duties of the Superintendent are enumerated in Chapter 230, Florida Statutes. The Seminole County School Board issued a call for bids for air filter maintenance service and replacement under Bid No. 102589 on September 14, 1998. Bids were submitted by Con-Air Industries, Inc., the protester, and Filter Service & Installation Corp., the apparent low bidder. The bids were opened on September 28, 1998, and were evaluated. Each bidder was determined to be a responsible bidder to the CFB. Intervenor submitted the lowest numerical bid. On October 1, 1998, Respondent's staff recommended that the CFB be awarded to Intervenor. The decision to recommend the award of the filter service Bid No. 102589 complies with the bid specifications. The instructions to bidders, as stated on the Proposal Form, direct a bidder to total lines A-C and to enter the total at line D. The instructions state that a bidder is not to include the cost as stated at lines E & F in the total. The proposal form then states that the total cost, as stated at line D shall be used to determine the apparent low bidder. The bid proposal document stated that the total of the prices stated at items A, B, and C would be used to determine the lowest numerical bid. The bid proposal document stated that the Respondent reserves the right to negotiate unit cost proposed for item E. The line D total submitted by the Petitioner is stated at $3.45. The line D total submitted by the apparent low bidder, is stated at $2.60. Intervenor submitted the lowest numerical bid. Intervenor does business under the fictitious name Filter Sales & Service. That fictitious name has been registered with the Secretary of State for the State of Florida. Filter Service & Installation Corp., and Filter Sales & Service are one and the same. The reference by Intervenor at line F to "Per Price Sheet" and the failure of Filter Service & Installation Corp. to attach a price sheet to its proposal form is not a material deviation from the requirements of the bid specifications. The total at line D is the total used to determine the lowest bidder. Filter Service & Installation Corp. is the lowest and best bid from a responsive and responsible bidder. The Petitioner followed the procedure set forth in the bid proposal document in making a determination that the Intervenor was the lowest numerical bidder. Petitioner reserved the right to reject all bids and to waive any informalities. Petitioner failed to prove that the notice of intent to award the bid to Intervenor was clearly erroneous, contrary to competition, arbitrary, or capricious.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Respondent award the contract for filter maintenance, service, and replacement under Bid No. 102589 to the Intervenor, Filter Service and Installation Corp., as recommended by its staff. DONE AND ENTERED this 11th day of December, 1998, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 1998. COPIES FURNISHED: Robert N. Hering, President Con-Air Industries, Inc. 3055 Pennington Drive Orlando, Florida 32804 Ned N. Julian, Jr., Esquire Seminole County Public Schools Legal Services Department 400 East Lake Mary Boulevard Sanford, Florida 32773-7127 Robert W. Smith, Esquire 430 North Mills Avenue, Suite 1000 Orlando, Florida 32803 Dr. Paul J. Hagerty, Superintendent Seminole County Public Schools 400 East Lake Mary Boulevard Sanford, Florida 32773-7127

Florida Laws (1) 120.57
# 8
ROBERT A. WEINBERG, TRUSTEE FOR ROBERT ALLAN WEINBERG REVOCABLE TRUST vs DEPARTMENT OF INSURANCE, 98-003593BID (1998)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 10, 1998 Number: 98-003593BID Latest Update: Nov. 24, 1998

The Issue The issue in this proceeding is whether the Respondent, the Department of Insurance, acted illegally, arbitrarily, fraudulently, or dishonestly in rejecting all bids for lease #460:0119 and not awarding subject lease to Petitioner.

Findings Of Fact The Department of Insurance established a requirement to lease 5371 square feet of office space in Daytona Beach, Florida, and a "Request for Space Need" was approved by the Department of Management Services on February 11, 1998. The Department of Insurance subsequently issued a Request for Proposal (RFP) for lease #460:0119 (Respondent's Exhibit 1). A non-mandatory pre-bid conference was held on June 1, 1998, in Daytona Beach and two prospective bidders, Petitioner and Nova Village Market partnership attended. The RFP provided that proposals which did not meet all mandatory requirements of the RFP would be rejected as non- responsive. The RFP provided for evaluation criteria are awards factors. The awards factors totaled 100 points with no minimum point total required. Ten of the points were allotted for moving costs defined as the costs of relocating communications, networks, furniture and other equipment. This factor gave the current landlord an automatic 10-point advantage since there would be no relocation costs. Moving costs provisions tend to discourage the presentation of bids because the bidders have to overcome an automatic 10-point advantage provided the current landlord. The RFP also provided that all proposals could be rejected, however, such "rejection shall not be arbitrary, but be based on strong justification." None of the conditions of the RFP were questioned or challenged by interested parties. Two responses were received by the Department of Insurance in response to the RFP and these were opened in Respondent's Tallahassee office on July 8, 1998, by Mr. Kip Wells of the Department. One was received from the current landlord, Nova Village Partnership, hereafter Nova, and the other from the Petitioner. The Nova proposal was deemed non-responsive. Neither Nova nor Petitioner contested the determination that Nova's proposal was non-responsive. Only one responsive proposal, the Petitioner's proposal, remained. On July 9, 1998, the Department representative, Mr. Kip Wells, called Petitioner to schedule an appointment for 9:00 a.m., on July 10, 1998, to visit and evaluate the proposed facility. No persons from the Department appeared at the scheduled appointment. At 10:45 a.m., on July 10, 1998, Kip Wells called Petitioner to say that since Petitioner's proposal was the only responsive proposal received, and that "all bids" were being rejected. Mr. Wells testified at hearing. His reason for rejecting the remaining bid was: When I saw that it was obvious the current landlord was not going to be very cooperative, I decided that one choice was not enough. If we were going to have to make a move, we needed more than one thing to choose from. So, I immediately - - since I had already set up with local people in Daytona to tell them that I was coming down to evaluate the bids, I sent them an E-mail and told them that I would not be meeting the following day to evaluate the bids. Mr. Wells decided to reissue the RFP without any moving costs criteria, and redistribute those 10 points among the other award factors. Petitioner filed a Notice of Intent to Protest and then a Formal Protest, both in a timely fashion. There is no state policy prohibiting the award of a lease to a sole bidder on a RFP. The "Leasing Policy" of the Department of Insurance states that "The Lease Administrator, with assistance from the Division employees, will establish bid or quote specifications. These specifications will include special needs for the Division(s) as well as the evaluation criteria upon which to evaluate the proposals." Neither the Department's Lease Policy (Petitioner Exhibit 3) nor the State's Real Property Leasing Manual (Petitioner's Exhibit 4) give the Lease Administrator the authority to reject or evaluate bid responses. Neither does he have a vote in the bid evaluation process. His responsibility is to coordinate the process. Randall Baker, Manager of Private Sector Leasing of the Bureau of Property Management of the Department of Management Services (hereinafter DMS), testified. The DMS prepares a manual as a guideline for user agencies to assist in the leasing of property. The DMS manual is not binding on agencies and DMS has no review oversight; however, their comments on agencies' leases are reviewed by the state auditing authorities and failure to follow the guidelines can result in audit criticism. Baker confirmed that the agency's written procedures as outlined in the RFP were consistent with the DMS guidelines. The DMS manual states as follows regarding the receipt of only one responsive proposal: When only one responsive proposal is received it may be considered and accepted providing the following conditions are documented: Adequate competition was solicited. The rate is within established rental rate guidelines. The proposal meets stated requirements. The proposal was processed as though other proposals were received. The Petitioner's bid was responsive to the RFP and the lease rate bid by the Petitioner was less than the average rate for state leases in the Daytona area and less than the amount budgeted by the Department for this lease. The lease rate by the Petitioner was reasonably priced and competitive. Although the agency failed to complete the process as envisioned, see paragraph 20 below, this was in no way the fault of Petitioner. The Department's leasing policy requires that the lowest and best response to an RFP be determined through cost analysis and evaluation by an evaluation committee. Mr. Wells did not forward Petitioner's bid to or discuss with the evaluation committee Petitioner's bid, but unilaterally rejected it. It was clear from Mr. Wells' testimony that this was his individual decision and was based upon his personal belief that it was the best thing to do.1 At hearing, the stated justification for rejecting "all bids" was that it gave the Department the opportunity to delete the requirement of moving costs from the awards factors; however, the evidence does not indicate that the moving cost provision result in non-competitive bids. The sole responsive bidder was within the local lease price range and within budget. Neither the Respondent nor DMS has established a policy prohibiting the acceptance of a sole responsive bid if there is competition solicited. The Department of Insurance has accepted a sole bid on at least one project in the past. There was no evidence that the RFP was not an open and fair competition. The evidence shows that it was properly advertised, that all conditions were known, and that all interested parties had an equal opportunity to participate. In sum, there was adequate competition in submitting the bids. Mr. Baker testified regarding the policy of DMS. The DMS policy is that if there is one responsive bidder, there has been competitive bidding. The RFP provides that the Respondent may reject all bids if it has strong justification. See paragraph 5 above. Mr. Baker also provided examples of "strong justification for rejecting proposals." His examples include facilities which are proposed outside the required geographic area, prices considerably in excess of state guidelines and agency budgets, specification changes due to modification of the agency's program requirements, and "intervening external forces." No evidence establishing a strong justification for rejecting the Petitioner's bid was presented. Without completing the process and evaluating the Petitioner's bid, the agency never considered whether the bid was in the state's best interest. However, this was not the fault of the Respondent, and the agency's failure to follow its procedures should not inure to its benefits. Further, Because there was no minimum score required on the evaluation criteria of the RFP, there is no need to evaluate Petitioner's proposal because it is the only responsive proposal. For all the reasons stated above, the rejection of Petitioner's bid was contrary to the terms of the RFP, contrary to state policy, and arbitrary.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is, RECOMMENDED: That a Final Order be entered which finds that: Respondent's actions in rejecting Petitioner's responsive bid were arbitrary; The Respondent did not follow the requirements set forth in the Department of Insurance Leasing Policy, nor the Department of Management Services Real Property Leasing Manual, or the Request for Proposal itself; That no adverse interest to the State or the Department would have occurred had Petitioner's responsive bid been accepted; and therefore, Petitioner's claim shall be upheld as the lowest cost and best proposal for RFP #460:0119, and that the Department of Insurance shall award Petitioner Lease #460:0119. DONE AND ENTERED this 30th day of October, 1998, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 30th day of October, 1998.

Florida Laws (3) 120.57255.249255.25
# 9
CLOSE CONSTRUCTION, INC. vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 09-004996BID (2009)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 14, 2009 Number: 09-004996BID Latest Update: Jul. 13, 2011

The Issue The issues to be resolved in this proceeding concern whether the Petitioner, Close Construction, Inc. (Petitioner), (Close) was the lowest responsive and responsible bidder in the Request For Bid (RFB) Number 6000000262, whether the subject contract should be awarded to the Petitioner, and, concomitantly, whether the Respondent agency's decision to award the contract to the Intervener, Worth Contracting, Inc. (Worth) was clearly erroneous, contrary to competition, arbitrary or capricious.

Findings Of Fact The South Florida Water Management District is a public corporation authorized under Chapter 373, Florida Statutes. It issued a request for bids for the refurbishment and automation of certain facilities in Broward County, Florida. Close is a construction company duly authorized to do business in the state of Florida. It was one of the bidders on the procurement represented by the subject request for bids and is the Petitioner in this case. This dispute had its beginnings on June 5, 2009, when the Respondent issued RFB number 6000000262. The RFB solicited construction services for the refurbishment and automation of two facilities in Broward County. The procurement would involve the installation of new direct-drive electric pumps at the Respondent's G-123 Pump Station in Broward County, along with the construction of an equipment shelter and the replacement of a retaining wall with a poured concrete retaining wall, as well as refurbishment of "pump flap gates." The RFB also requested construction services for the replacement of gates at the Respondent's S-34 water-control structure in Broward County. Both facilities would thus be automated so that they can be remotely operated from the Respondent's headquarters in West Palm Beach. After issuance of the RFB, two addenda were supplied to vendors and were posted. The first addendum was posted on or about June 19, 2009, concerning a change in specifications for flap gates and is not the subject of this dispute. Addendum No. Two was electronically posted on or about June 30, 2009. It amended the technical specifications of the RFB by deleting Section 11212 regarding measurement of payment of electric motors/belt-driven axial flow pumps. That addendum also added a new measure and payment to Subpart 1.01 of the technical specifications to provide for an owner-directed allowance of $40,000.00 to provide for the potential need for certain electrical utility work to be done by FPL in order to complete the project. Addendum No. Two added an additional term to the RFB in providing that the $40,000.00 allowance price "Shall be added to the other costs to complete the bid." The second Addendum also stated, "The allowance price shall be used at the discretion of the District and, if not used, will be deducted from the final Contract Price." That addendum also directed bidders to replace the original Bid Form 00320-2, which had been enclosed with the RFB, with a new Bid Form, 00320R1-2. The new Bid Form is identical to the original form except that the schedule of bid prices contained in paragraph four, on page 003201-2, was altered to itemize the $40,000.00 discretionary cost allowance. The original form had contained a single line for the bidder's lump sum bid price, whereas the revised form provided for a lump sum bid amount to be itemized and a base bid amount, which required the bidder to enter on the form the amount of its bid, then add the discretionary cost amount and write the sum of those two numbers on a third line. In paragraph four of the new bid form there is re- printed language concerning the use of the discretionary allowance which appeared on the face of Addendum No. Two. Other than the change to paragraph four and the alteration of the page numbers to include an "R" in the page number, the revised bid form is identical to the original bid form. The other bid documents were not altered in any manner by Addendum No. Two. The deadline for bid submissions was Thursday, July 9, 2009, at 2:30 p.m. The Petitioner timely submitted its bid to the District. In submitting its bid however, the Petitioner used the original bid form which had been enclosed with the RFB. The bid form submitted was an exact copy of the bid form furnished by the District which Close had printed from the electronic copy of the RFB received from the District. The Petitioner did not substitute the revised bid form, attached to Addendum No. Two, for the original form in submitting its bid. The Petitioner's bid was deemed non-responsive by the District and was rejected on the basis that Close had failed to submit the bid on the revised form required by Addendum No. Two. Thereafter, the District, at its August 13, 2009, meeting, approved award of the bid to Worth. The intent to award was posted electronically on or about August 14, 2009. The persuasive evidence establishes that Close received both addenda to the bid documents. It was aware of the Addendum No. Two, and it accounted for all of the changes to the technical specifications made in both addenda in the preparation of its bid. The evidence shows that Close was aware of the $40,000.00, owner-directed cost allowance and that it incorporated it in the formulation of its total bid price. Thus, Close's final bid amount was $3,751,795.00. That number included the $40,000.00 cost allowance at issue, added to the bid documents by Addendum No. Two. The internal bid work sheets, prepared by personnel of Close, identified and itemized the $40,000.00 discretionary cost allowance as a component of the final bid price. The persuasive evidence thus establishes that Close's final bid amount did include the $40,000.00 cost allowance. Moreover, the written notes of witness Christopher Rossi, the estimator for Close, show the $40,000.00 amount as an "FPL Allowance." Both Mr. Rossi and Mr. Boromei, the Vice President for Close, who prepared the bid, explained that the $40,000.00 was understood by Close to be a cost allowance, that it would only be charged to the District to the extent that it was actually used, at the District's discretion. If it were not used, it was to be deducted from the overall contract price. Addendum Two specifically provides that the discretionary cost allowance was to be used only at the discretion of the District and that the unused portion would be deducted from the contract amount. When Close submitted its bid it mistakenly submitted it on the original bid form and failed to exchange the bid forms as directed in Item Two of Addendum No. 2. In paragraph one of both bid forms, however, the bidder is required to specifically fill out, acknowledge and identify all addenda. By doing so the bidder expressly agrees to build the project in conformance with all contract documents, including all addenda, for the price quoted in the bid. Close completed this paragraph, specifically identified both Addendum One and Addendum Two, and specifically agreed to strictly conform, in performance of the work to the plans, specifications and other contract documents, including Addendum Nos. One and Two. Paragraph one was not changed by the addition of Addendum No. Two and it is identical in both the original and the revised forms at issue. Paragraph one of the original and the revised bid forms constitutes an agreement by the bidder to perform and construct a project "in strict conformity with the plans, specifications and other Contract Documents. . . ." The addenda are part of the contract documents and are expressly referenced as such in this agreement. Both bid forms, the original and the revised, include paragraph eight, which clearly states that the bidder will post a bid bond to secure and guaranty that it will enter into a contract with the District, if its bid is selected. Paragraph eight was unchanged by Addendum No. Two and its terms are identical in both Bid forms at issue, including the form that Close signed and submitted as its bid. The persuasive evidence shows that in submitting its bid, whether on either form, Close committed itself to the identical terms as set forth in the identical contract documents agreed to by Worth and the other bidders. The evidence established that Close intended to bind itself to the terms of the RFB, and all terms of Addendum No. Two, including the discretionary cost allowance term. Close considered itself bound to enter into a contract for the price of its bid if selected by the District. It likewise considered that the price of its bid, would only include the cost allowance if the discretionary allowance was implemented by the District. Upon the opening of the bids, the firm of Cone and Graham, Inc., was identified as the lowest bidder. Cone and Graham's bid was in the amount of $2,690,000.00. Close was the second lowest bidder, with a bid of $3,751,795.00. The third lowest bidder was Worth Contracting, Inc., with a bid of $3,898,410.00. Cone and Graham was allowed to provide additional information and to even meet with some District staff following the opening of its bid. The additional information it was allowed to provide concerned technical specifications of the pumps proposed in its bid. Through this verification process conducted with the Agency, Cone and Graham ultimately convinced the District to permit them to withdraw its bid without forfeiting their bid bond. This left the Petitioner, Close, the lowest bidder, at $146,615.00 less than the bid submitted by Worth, the initially-awarded bidder. Close's bid, upon review, was rejected as non- responsive due to its failure to exchange the original Bid form with the revised Bid form, as indicated above, in spite of the fact that Close had also agreed to adhere to the entirety of Addendum No. Two on the face of the Bid form. Thus the recommended award to Worth for the above-referenced additional amount of bid price was adopted by the District, engendering this protest. James Reynolds, the Contracts Specialist for the District, conceded that it was apparent on the face of Close's bid that a mistake had been made in the use of the original form, rather than the revised form. He conceded there was an inconsistency between Close's clear acknowledgement of and agreement to the terms of the contract documents, which expressly included Addendum No. Two and Close's apparent mistaken use of the original Bid form. Under the express terms of Article 19.03 of the RFB, "The Bid shall be construed as though the addendum(a) have been received and acknowledged by the bidder." Mr. Reynolds admitted, however, that he did not apply the terms of Article 19.03 of the RFB in his review of Close's bid and did not construe the bid in the manner provided in the RFB to resolve the apparent inconsistency. He reasoned that Close had used the wrong bid form and looked no further. The District's Procurement Manual provides a procedure whereby a bidder may correct inadvertent mistakes in its bid. Under the terms of Chapter 5-5 of that manual, where the District knows or has reason to conclude, after unsealing of bids, that a mistake may have been made by a bidder, the District "shall request written verification of the bid." In such a circumstance the bidder "shall be permitted the opportunity to furnish information in support of the bid verification as long as it does not affect responsiveness, i.e., the bid substantially conforms to the requirements of the RFB as it relates to pricing, surety, insurance, specifications and any other matter unequivocally stated in the RFB as determinant of responsiveness." See Joint Exhibit 7,6 pages 61 and 62, in evidence. Mr. Reynolds admitted in his testimony that he did not follow the procedure set forth in the manual for verifying a bid because, in his view, that would be allowing an impermissible supplementation of Close's bid. Ms. Lavery, in her testimony, in essence agreed. The Procurement Manual expressly required the District, upon recognizing the mistake and an inconsistency apparent on the face of Close's bid, to verify that bid and to provide Close with the opportunity to furnish information in support of bid verification. Thus, by the express terms of the manual, a bidder must be given an opportunity to clarify mistakes. The Procurement Manual expressly permits a bidder under these circumstances to correct any "inadvertent, non- judgmental mistake" in its bid. Chapter 5 of the Manual provides that "a non-judgmental mistake" is a mistake not attributable to an error in judgment, such as mistakes in personal judgment or wrongful assumptions of contract obligations. Inadvertent technical errors, such as errors of form rather than substance, are considered non-judgmental errors." See Joint Exhibit 7, page 62, in evidence. It is patently apparent that Close's use of the original bid form, inadvertently, while also unequivocally acknowledging and agreeing to the entirety of Addendum No. Two, represented a non-judgmental mistake. Both of the District witnesses, however, testified that the policy regarding mistakes was not followed and Close was not given an opportunity under the District's policy to provide additional information to support verification of the bid. Although Close failed to substitute the revised Bid form for the original Bid form, as called for by Addendum No. Two, its bid was substantively responsive to the technical specifications and requirements of the RFB, and the irregularity is technical in nature. The parties stipulated that the use of the original form, rather than the revised bid form, was the sole basis for Close being determined to be non-responsive by the Agency. In accordance with Florida Administrative Code Rule 40E-7.301, in Chapter 5 of the District's Procurement Manual, the District reserves the right to waive minor irregularities in a bid. A material irregularity is defined by the District's policy as one which is not minor in that it: (a) affects the price, quality, time or manner of performance of the service such that it would deprive the District of an assurance that the contract will be entered into, performed and guaranteed according to the specified requirements; (b) provides an advantage or benefit to a bidder which is not enjoyed by other bidders; or (c) undermines the necessary common standards of competition. See Joint Exhibit 7, page 58, in evidence. The preponderant, persuasive evidence shows that the irregularity in Close's bid did not affect the price of the bid or truly deprive the District of assurance that the contract would be entered into and performed according to all the terms of the RFB, including addenda. The evidence established that Close actually included the $40,000.00 discretionary cost allowance in its final bid price. It merely did not show it as a separate itemization, because it did not use the revised form providing that itemization line. The fact that the discretionary allowance was itemized in the revised bid form, as part of the bid amount, does not equate to an effect on the contract price as a result of Close's using the original Bid form. Close's error, by mistakenly submitting its bid on the original bid form, did not alter the price of its bid. The evidence clearly established that the bid price for Close's bid would be the same regardless of which form it used. Moreover, the preponderant, persuasive evidence establishes that the use of the original Bid form by Close did not deprive the District of assurance that the contract would be performed in accordance with the all bid documents. Close's bid, secured by its bid bond, clearly acknowledged and agreed to the express terms of Addendum No. Two in their entirety, which included the terms under which the discretionary cost allowance could be applied. Close considered itself bound to the terms of the RFB and assured the Agency that it was so bound by the written acknowledgement and agreement it submitted to the Agency as part of its bid, concerning the elements of Addendum No. Two. The evidence demonstrated that Close understood that the $40,000.00 amount was a discretionary cost allowance and that Close would not be entitled to it unless the District decided to use it. Despite the opinion of Agency witnesses to the contrary, the error in Close's bid was a technical one and non- material because it did not confer a competitive advantage upon Close. Close's use of the wrong form did not alter the price of its bid. Its mistake in the use of the original bid form could only change the relative, competitive positions of Close and Worth if the amount of the discretionary cost allowance was greater or equal to the difference between those two bids, i.e., the $146,650.00 amount by which Worth's bid exceeded the bid of Close. 1/ The bid of Worth exceeds Close's bid by an amount far greater than the amount at issue in the discretionary cost allowance identified in Addendum No. Two and expressly itemized in the revised Bid form, i.e. $40,000.00. The District contends that Close gained some competitive economic advantage over other bidders by having the means by which it could optionally withdraw its bid, based upon alleged non-responsiveness, in not substituting the revised Bid form which would contain the itemization of the $40,000.00 cost allowance. It is difficult to see how it could gain a competitive advantage versus other bidders through some perceived ability to deem itself non-responsive, at its option, and withdraw its bid, thus denying itself the contract. The competitive bidding laws are designed to prevent a firm from gaining a competitive advantage in obtaining a contract versus the efforts of other bidders, not in depriving itself of the opportunity to get the work. Moreover, concerning the argument by the District that this may confer the advantage to Close of allowing it to withdraw its bid at its option and still obtain a refund of its bid bond; even if that occurred, it would not confer a competitive advantage vis-à-vis other bidders. It would merely involve a potential pecuniary advantage to Close's interest, versus that of the Agency itself, which obviously is not a bidder. Moreover, it should again be pointed out that Cone and Graham was allowed to provide additional information concerning its bid elements, and even to meet with the District staff, following the opening of the bids. It was then allowed to withdraw its bid without forfeiting its bid bond. If the District had inquired, by way of verification of Close's bid, as to whether the discretionary cost amount was included in it's bid, that inquiry does not equate to allowing Close to unlawfully supplement its bid. Indeed, if in response to such an inquiry, Close announced that the discretionary allowance was not included in its bid, its bid at that point would be materially non-responsive to the specifications. If Close was then allowed to supplement its bid by changing its price to add the allowance, such would indeed be an unfair competitive advantage and a violation of law on the part of Close and the Agency. The evidence does not show that such happened or was proposed by any party. If a verification inquiry had been made and Close announced that, indeed, its bid price did include the subject discretionary cost allowance, without further response to the specifications being added, then no competitive advantage would be afforded Close and no legal violation would occur. In fact, however, as pointed out above, the verification request, pursuant to the District's policy manual, was never made. This was despite the fact that the District's witness, Mr. Reynolds, acknowledged that the use of the original bid form was an apparent mistake on the face of the bid, when considered in conjunction with Close's express agreement to construct the project in strict conformance with all contract documents, and particularly with regard to Addenda Numbers One and Two. The non-judgmental mistake, involving use of the original bid form in lieu of the revised bid form, could have been easily clarified by a verification inquiry. That policy was not followed, based solely on the fact that the wrong bid form was used, even though the preponderant, persuasive evidence shows that in all material and substantive respects the bid was a conforming, responsive bid and included in its price the discretionary cost allowance. The preponderance of the evidence shows that the mistaken use of the original Bid form was a non- material irregularity under the District's policies and the terms of the RFB. The District's actions in failing to uniformly apply its own bid verification policy when, in fact, it had allowed verification to one of the other bidders, and when, according to its own witness, it perceived an apparent mistake, was clearly erroneous. It is true that Close may not supplement its bid by changing material terms, but it is permitted to verify whether, in light of the mistaken use of the original Bid form, its bid price, as submitted, included the $40,000.00 discretionary allowance or not. Providing such "yes or no" type of additional information in order to clarify, and only clarify, information already submitted in the bid, in response to an inquiry by the District does not constitute "supplementation" of the bid for purposes of Section 120.57(3)(f), Florida Statutes (2008). NCS Pearson, Inc. v. Dept of Education, 2005 WL 31776, at page 18 (DOAH, Feb. 8, 2005). Even without verification of the bid, the bid on its face agrees to compliance with all terms and specifications, including Addendum No. Two. It is thus determined that there is no material irregularity. The bid submitted by Close does not afford it any competitive advantage vis-à-vis the other bidders and it is responsive.

Recommendation Having considered the foregoing Findings of Fact, conclusions of law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED that a Final Order be entered by the South Florida Water Management District, awarding the subject contract for RFB 6000000262 to the Petitioner herein, Close Construction, Inc. DONE AND ENTERED this 5th day of January, 2010, in Tallahassee, Leon County, Florida. S P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 2010.

Florida Laws (3) 1.01120.569120.57 Florida Administrative Code (1) 40E-7.301
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer